Академический Документы
Профессиональный Документы
Культура Документы
CREAVES
Converting MNB - MINOR BRIDGE SWIVEL CLAMPS/COUPLERS
VUP- VICHLE UNDER PASS MS PIPE
SQ TO SK BC- BOX CULVERT PROPS JACK
SQ / COS ANGLE HPC- HUME PIPE CULVET CUP LOCKS
LONG SPAN BRIDGE > 120 MTR SOLDER
SK TO SQ MAJOR BRIDGE 60 TO 120 MTR PLATS
SK X COS ANGLE MINOR BRIDGE 6 TO 60 MTR JACKS
250/.89 = S2/1.580
280.89XS2/ 1.580
443.8=S2
SAY 444
SLANDERNESS RATIO
LONG COLUMN DELTA>12 ( FAIL DUE TO BUCKLING PROBLEM)
SHORT COLUMN DELTA= 3TO 12 (FAIL DUE TO CRUSHING)
PEDESTAL DELTA<3
HI = BM/RL + BS
RL= HI- IS/FS
STATION BS HI FS
STATION BS IS FS
ARITHMETIC CHECK-
SAMMASUM OF BS - SAMMASUM OF FS= LAST RL - IST RL
PROPS JACK
CUP LOCKS
U JACK BASE JACK
STANDARD
LEDGER
4.044 4.782
0.9
4.944
N CENTER OF BEAM
ULD BE IN L/4 OR ON COLUMN JUNCTION
IS RL REMARK
HI RL REMARK
CENTIGRADE
E CENTIGRADE
TYPE COLUMN FOR BIG STRUCTURE KNOW
EMENT OF ROAD-
ULDER + CARRIAGE WAY)
TECHNICAL SPECIFICATION:-
3. SIZE OF MATERIALS- MAX. SIZE OF PARTICAL FOR 3. MAX. SIZE OF AGGREGATE - 75MM
EMBANKMENT- 75MM
SUBGRADE-50MM 4. L.L. & P.I. - NOT MORE THAN 25% TO 6%
MAX. PARTICAL SIZE SHALL NOT BE MORE THAN TWO, THIRD OF 5. C.B.R. - MORE THAN 30%
THE COMPACTED LAYER OF THICKNESS (200MM, 300MM)
6. FIELD DENSITY - 98% OR 99%
4. LIQUID LIMIT & PLASTICITY INDEX-
NOT MORE THAN 40% & 18% 7. MAXI LAYER THICKNESS- 150MM, 200MM,22
L.L.- 30 TO 38%
P.I.- 10 TO 18% 8. LEVEL TOLERANCE- +10MM TO -20MM
6. C.B.R. -
MORE THAN 7 TO 12% OR 8 TO 15%
2. O.M.C.- 7.56%
2. TEMPRATURE-
3. FIELD DENSITY- 98% AT THE TIME OF MIX MATERIAL - M
GREGATE - 75MM LAYING TIME- MIN. 125 DEGREE. C
4. MAX. AGGREGATE SIZE- ROLLING TIME- MIN. 90 DEGREE. C
MORE THAN 25% TO 6% 35MM SIEVE 100% PASSING
3. LEVEL TOLERANCE- + 6 TO -6MM
5. MAX. LAYER THICKNESS - 200MM
4. FIELD DENSITY TEST- 98%
8% OR 99% 6. LEVEL TOLERANCE- +10 MM TO - 20MM ( 1 TEST PER 250 SQUARE MTR. OF
E- +10MM TO -20MM
INOUS MACADAM (B.M.) DRY LEAN CONCRETE (D.L.C.)
2. O.M.C. - 6.50%
ME OF MIX MATERIAL - MAX. 165 DEGREE CENTI. 3. FIELD DENSITY - 97% OR MORE
ME- MIN. 125 DEGREE. CENTI.
TIME- MIN. 90 DEGREE. CENTI. 4.FINISHING TIME- MAX. 90 MINUTE
WHEN CONCRETE TEMPERATURE ABOVE 25 DEGREE CENTI. OR BELO
TOLERANCE- + 6 TO -6MM
MAX. 120 MINUTE WHEN CONCRETE TEMP. BELOW 25 DEGREE CENT
DENSITY TEST- 98%
ER 250 SQUARE MTR. OF AREA) 5. D.L.C. TOLERANCE- +6 TO -10MM
1. GUID WIRE LEVEL (SENSOR WIRE)- 12. TEMP. 27 DEG. CENTI. (+2 T
MAX. TOLERANCE- +2 TO -2MM
10.16DIA, 600 LENGTH TIE BAR USED IN LONGITUDINAL CONTRACTION JOINT ALSO
ROLLING TRIAL BATCH, 1. PLAIN PASS, 2. TWO LOW, 3. THREE VIBRATION PASS
SEALENT FILLING
DONE OF CONCRETE