Академический Документы
Профессиональный Документы
Культура Документы
SUBSTRUCTURE
EARTHWORKS
Excavation
A Clear the site of vegetation / site clearing 100.0
B Excavating to reduced levels 150mm deep from natural ground level 15.0
Disposal
D Disposal of surplus excavated material off site 0.0
Filling
E Backfilling to sides of foundations walls and columns 1.7
Brickwork
Termite treatment
H Anti-termite treatment with Dusban TC on compacted
hardcore, bottoms & sides of excavations 95.3
Concrete works
I 225mm thick Strip footing 2.6
J 100mm thick ground floor concrete slab C 30, on polythene sheeting 3.2
SUBSTRUCTURE to collection
ITEM DESCRIPTION
Err:509
L 0.0
N Err:509
Err:509
O 32.3
13.5
Formwork/Shuttering
P To edges of slab (2 uses) 0.0
SUBSTRUCTURE COLLECTION
PAGE 1
PAGE2
SUBSTRUCTURE TO SUMMARY
ITEM DESCRIPTION
SUPERSTRUCTURE
Walling
A Brickwalls 150mm thick, in cement mortar (1:4)
Beams
D Reinforced in -situ concrete; Class 30 in 200mm X 400mm,
beam,
Suspended slab (First floor slab) Precast slab ; block and beam
E Block and beam deck floor
F Topping concrete to the block and beam deck (50mm - 60mm thick)
Reinforcement
G 16mm diameter to columns (4 N0)
Formwork/Shuttering
L Sawn timber to beams, columns (3 uses)
Painting
B Two coats emulsion to internal/external walls
Wall tiles
E Wall tiles in toilets; 1.5m high
Floor tiles
F Unglazed ceramic floor tiles on 25mm screed
Non-slip.
F Light switches
PLUMBING INSTALLATION
A WC Suites complete with pipework
SUMMARY
SUBSTRUCTURE
SUPERSTRUCTURE
ELECTRICAL INSTALLATION
PLUMBING INSTALLATION
UNIT ZMW RATE ZMW PRICE
m2 2 150.00
m3 25 375.00
m3 34 274.79
m3 0 0.00
m3 0.00
m3 0.00
m2 0.00
m2 0.00
m3 0.00
m3 0.00
m2 0.00
m2 0.00
799.79
0.00
Kg Err:509
Kg 0.00
Kg Err:509
Kg 0.00
Kg 0.00
m 0.00
0.00
0.00
0.00
0.00
UNIT ZMW RATE PRICE
m2 0.00
m3 0.00
m3 0.00
Item 0.00
0.00
kg 0.00
kg 0.00
Kg 0.00
Kg 0.00
kg 0.00
m2 0.00
m2 0.00
0.00
UNIT ZMW RATE PRICE
no 0.00
no 0.00
no 0.00
no 0.00
0.00
no 0.00
0.00
UNIT ZMW RATE PRICE
m2 0.00
0.00
0.00
m2 0.00
m2 0.00
0.00
item 0.00
0.00
m2 0.00
0.00
0.00
0.00
m2 0.00
0.00
0.00
UNIT ZMW RATE PRICE
item 0.00
0.00
item 0.00
0.00
no 0.00
0.00
no 0.00
0.00
no. 0.00
0.00
no 0.00
0.00
no 0.00
0.00
no 0.00
0.00
item 0.00
item 0.00
0.00
item 0.00
0.00
item 0.00
0.00
no 0.00
no 0.00
no 0.00
no 0.00
item 0.00
item 0.00
item 0.00
0.00
UNIT ZMW RATE PRICE
0.00
0.00
0.00
0.00
0.00
0.00
TOTAL = 0.00
ITEM PARTICULARS NO.
SUBSTRUCTURE
EARTHWORKS
Excavations:
A Clear the site of vegetation / site clearing
Disposal
D Disposal of surplus excavated material off site
Filling
E Backfilling to sides of foundations walls 3.00
2.00
1.00
1.00
Brickwork
G 150mm thick brickwork; for foundation walls 1.00
Termite treatment
H Anti-termite treatment with Dusban TC on compacted 3.00
hardcore, bottoms & sides of excavations 2.00
1.00
1.00
1.00
1.00
Roll
DEPTH TOTAL
LENGTH(M) WIDTH(M) / HEIGHT QTY QTY UNIT
10.00 10 100.00 m2
0.68 m3
1.02 tons
4.91 bags
13.47 m
60 0.22458 roll
Concrete works NO. L W
Insitu concrete in strip foundations
I Centreline method 2.000 6.300 0.600
2.000 3.150 0.600
STRIP FOOTING
1.55 CEMENT SAND STONE
Mix proportion : 1 2 3
Dry volume of concrete = 3.955 m3
Wet volume of concrete = 2.552 m3
LINTELS
0.225 1.701
0.225 0.851
2.552 m
3
TOTAL:
0.100 2.15
0.100 1.09
3.23 m
3
TOTAL:
0.150 0.10
0.150 0.07
0.150 0.06
0.24 m
3
ULATIONS
Item Description No. L(m) W(m)
0.4mm guage long span colour coated aluminum roofing sheet laid on
steel trusses
A in covering 2 7 3.6
12feet GI roofing sheets 1 0.68 3.6
C 50 x 75 mm purlins 14 7
1.600
6600mm 1.22
0
12 2.820
Struts or ties
Assorted Nails
TINNERY WORKS
50.40 m2
2.45 m2
20.59 No
54.00 m
98.00 m
16.50 m
30.00 m
19.80 m
33.84 m
Total: 53.64 m
140.00 m
9.90 m
40.32 m2
14 No
m2
5 No
4 No
32 No
7m
24 No
BILL OF MATERIA
ITE
M ITEM OF WORK/PARTICULARS BILLED QTY UNIT UNIT COST
NO.
1 SITE WORKS
Excavation 100.00 m3
Filling / Backfilling 0.00 m3 0.00
C. STRIP FOOTING
Cement 18.98 bags 65.00
Sand 1.98 Ton 75.00
19mm crushed stone 2.87 Ton 150.00
D. FOUNDATION WALLS
6"Burnt clay bricks 363.97 Nos. 2.70
Cement 4.91 bgs 65.00
Sand 1.02 Ton 75.00
LINTELS
Y12 RSB 42.40 m 8.00
Y8RSB 35.88 m 4.20
#16 Tie wire 2.55 kgs 2.50
Cement 1.77 bgs 65.00
Sand 0.18 Ton 75.00
19mm crushed stone 0.27 Ton 150.00
H. MASONRY WALLS
6"Burnt clay bricks 1,929.04 No. 2.70
Cement 26.05 bgs 65.00
Sand 5.43 Ton 75.00
I. FINISHING/PLASTERING (BOTH FACE)
Cement 0.00 bgs 0.00
Sand 0.00 ton 75.00
3 CARPENTRY
A. TRUSS/ROOF FRAMING
50 x 100 mm common rafters 54.00 m 19.50
50 x 75 mm purlins 98.00 m 6.00
50 x 100 mm wall plate 16.50 m 19.50
25 x 225 mm ridge board 30.00 m 15.00
50 x 100 mm struts or ties : 53.64 m 19.50
50 x 100mm King post 9.90 m 19.50
B. CEILING (OPTIONAL)
4 TINNERY WORKS
0.4mm LS color roof 20.59 No. 0.00
0.4mm LS pre fab ridges 0.00 pcs 0.00
0.4mm LS pre fab gutter 0.00 pcs 30.00
Flat bar 0.00 m 0.50
GLAZING
4mm thick clear glass sheet 0.00 0.00
4mm thick obscured glass sheet 0.00 175.00
6mm thick georguan glass sheet 0.00 425.00
Window putty 0.00 925.00
6 FORMWORKS
6mm thk. Plywd(1.2m x 2.4m ). 0.00 pcs 15.00
50mm x 50mm white timber 0.00 m 0.00
25mm x 150mm white timber 0.00 m 6.50
assorted CWN 0.00 kgs 15.00
TIMBER SCALFFORDING
50mm x 100mm x 5000mm white timber 0.00 m 19.50
50mm x 75mm x 5000mm white timber 0.00 m 6.00
Wire Nails assorted 0.00 kgs 15.00
7 ELECTRICAL
l.s
8 PLUMBING
l.s
9 PAINTING (OPTIONAL)
TOTAL MATERIAL COST
TOTAL LABOR COST
GRAND TOTAL
BILL OF MATERIALS
ADD (5%) WASTE TOTAL QTY MATLS COST LABOR COST TOTAL COST
WASTE ALLOWED RQD
WINDOWS
DOORS
LINTEL 5 Y12 2 4 8 1400 0 1400
LINTEL 6 Y8 2 10 20 460 51 90 90 50 50
18400
Rev letter
18.4 42.4
15.64 35.88
12.8
11.04
11.2
9.2
L
Brickwork
G 150mm thick brickwork; for interbal and external walls 1.00 33.00
2.00 3.30
1.00
2.85 94.05
1.65 10.89
104.94 104.94
3.62
5.43 TONS
26.05 BAGS