As per Annexure I,
As per Annexure I, Clause
2.1 WPS, PQR &WPQ Welding Parameters 100% Clause 3.1.2 of PED WPS/PQR & WPQ P A
3.1.2 of PED 2014/68/EU
2014/68/EU
Weld Map & Weld
2.2 Weld Map & Weld Plan Welding Parameters 100% As Per EN ISO 15614‐1
Plan
As Per EN ISO 15614‐1 P R
3 Raw material identification:
a) Surface 100%
1) MTC shall be as per EN 10204 Type 3.1
Plate For Shell, Channel Shell, Dishend b) Dimension 100% ASME SEC II Part A ASME SEC II Part A
3.1 MTC, CTC & IR P W 2) In absence of original MTC, Check Test to
& Tubesheet c) Chemical 100% Approved Drawing Approved Drawing
be carried out at NABL approved Lab.
d) Physical 1 Per Heat/Lot
a) Surface 100%
1) MTC shall be as per EN 10204 Type 3.1
b) Dimension 100% ASME SEC II Part A ASME SEC II Part A
3.2 Nozzle Pipe MTC, CTC & IR P W 2) In absence of original MTC, Check Test to
c) Chemical 100% Approved Drawing Approved Drawing
be carried out at NABL approved Lab.
d) Physical 1 Per Heat/Lot
a) Surface 100%
b) Dimension 100% ASME SEC II Part A ASME SEC II Part A 1) Witness at Kinam Works.
3.3 Body Flange & Nozzle Flange MTC, CTC & IR P W
c) Chemical 1 Per Heat/Lot Approved Drawing Approved Drawing 2) MTC shall be as per EN 10204 Type 3.1
d) Physical 1 Per Heat/Lot
a) Surface 10%
b) Dimension 10%
c) Chemical 1 Per Heat/Lot ASME SEC II Part A ASME SEC II Part A
3.4 Tubes MTC & IR P W 1) MTC shall be as per EN 10204 Type 3.1
d) Physical (Review of MTC) Approved Drawing Approved Drawing
10%
e) Hydrotest
(Review of MTC)
a) Surface 10%
b) Dimension 10% ASME SEC II Part A ASME SEC II Part A
3.5 Fasteners MTC & IR P RW Fastners shall be Zinc Plated
c) Chemical 1 Per Heat/Lot Approved Drawing Approved Drawing
d) Physical 1 Per Heat/Lot
a) Surface 100%
ASME SEC II Part A ASME SEC II Part A
3.6 Gasket b) Dimension 100% MFR T.C. P RW Gasket should be Asbestos Free
Approved Drawing Approved Drawing
c) Other Properties 100%
a) Surface 100%
Tie Rod, Spacer Tubes, Baffle Plates, ASME SEC II Part A ASME SEC II Part A
3.7 b) Dimension 100% CTC P R
Supports Approved Drawing Approved Drawing
c) Chemical only 1 Per Heat/Lot
Prepared By:
Prepared By:
Key Codes : ‐
Remarks:
1) All material should be free from radioactive contamination
2) C. S material should be sandblasted and primer coated before commencement of fabrication with S.S. material
3) Tubes should be procured from approved manufacturers only.
4) Contamination, dent, scratch, pitting etc should not be acceptable.
5) Pipe fittings and flanges should be procured from approved suppliers only.
6) Additional welders to be qualified before welding on job.
7) Temporary external stiffening ring should be provided to avoid distortion during fabrication and welding.
8) All welding should be ground flush from inside the shell.
9) Tube sheet holes should be cleaned prior to tube insertion.
10) Eqpt. should kept in inclined position to check leakage from tubes.
11) All nozzles flanges shell be blanked with std plastic pipe cap .
12) All loose parts should be furnished with position no., quantity, drg. no. and wrapped with transparent polythene and bubble sheets.
13) If the equipment is delivered in Wooden boxes, then it should fumigated.
Prepared By: