13 Nos well Pad Job Manpower & Staff Plan a

Sl.No. Well Pad Pipe No of No of Total Staff QC Staff


No. Size /Thk Spool Joint Inch Dia Day/Night

1 1 42278 2 4 40 2

2 3 42278 2 4 40 2

3 4 42278 2 4 40 2

4 10 42278 2 4 40 2

5 11 42278 2 4 40 2

6 12 10,12/15 2 4 44 2
2 Day & 2
night for
Paper Work
7 14 10,12/15 2 4 44 2 and tuch
with Cairn
QC.
8 16 12,14/15 2 4 52 2

9 6 42278 2 4 40 2

10 7 10/15.9 2 4 40 2

11 8 10,12/15 2 4 44 2

12 9 10",12/15 2 4 44 2

13 17 10"/15 2 4 40 2

Total 548 26

Note:- 1) Materials Co-odinater 3 day shift and 2 Night Shift.


2) Crane Co-odinator 1+1
3) Bulero Camper 05 Nos for 13 wellpad Job(2 Nos. with Co-odinator and 3 nos Welpad .
4) Contractor Shuld Must Present at Site During Job.
6) Welder Test Plan in Manjusar workshop with 6" Pipe Sch.80 Thk 10.97 (allready Discussed wit Cairn QC
7) We are Planning All Departmentle Welder for 2 days.
s well Pad Job Manpower & Staff Plan at Cairn Oil & Gas , Barmer (Total Duration 36 hours)
Safety
Electrician Planning
Manpower Day/Night Manpower Qty. Supervisor
Day/Night Day/Night Day/Night
Welder-4+Grander-3+Fab abd
fitter-2+Rigger-6+Helper-4+R 20
forman -1
1+1
Welder-4+Grander-3+Fab abd
fitter-2+Rigger-6+Helper-4+R 20
forman -1
Welder-4+Grander-3+Fab abd
fitter-2+Rigger-6+Helper-4+R 20
forman -1
1+1
Welder-4+Grander-3+Fab abd
fitter-2+Rigger-6+Helper-4+R 20
forman -1
Welder-4+Grander-3+Fab abd
fitter-2+Rigger-6+Helper-4+R 20
forman -1
1+1
Welder-4+Grander-3+Fab abd
fitter-2+Rigger-6+Helper-4+R 20
forman -1
Welder-4+Grander-3+Fab abd
fitter-2+Rigger-6+Helper-4+R 20 1+1 4+3
forman -1
1+1
Welder-4+Grander-3+Fab abd
fitter-2+Rigger-6+Helper-4+R 20
forman -1
Welder-4+Grander-3+Fab abd
fitter-2+Rigger-6+Helper-4+R 20
forman -1
1+1
Welder-4+Grander-3+Fab abd
fitter-2+Rigger-6+Helper-4+R 20
forman -1
Welder-4+Grander-3+Fab abd
fitter-2+Rigger-6+Helper-4+R 20
forman -1
1+1
Welder-4+Grander-3+Fab abd
fitter-2+Rigger-6+Helper-4+R 20
forman -1
Welder-4+Grander-3+Fab abd
fitter-2+Rigger-6+Helper-4+R 20 1+1
forman -1
260 14 2 7

ith Co-odinator and 3 nos Welpad .


e Sch.80 Thk 10.97 (allready Discussed wit Cairn QC)
tion 36 hours)

Contractor Status Remarks


Name/Team

A Next week Coform

A Next week Coform

B Next week Coform

B Next week Coform

C Next week Coform

C Next week Coform

D Next week Coform

D Next week Coform

E Next week Coform

E Next week Coform

F Next week Coform

F Next week Coform

G+ Floting Next week Coform

7
First Well pad Job Execution Plan by 23 Ton Farana then after site visit on 25/12/19 100 ton Crane required
at Carin India,Barmer.
Sl.No. Well Pad No. Pipe Size /Thk No of Spool No of Joint Total Inch Dia Approx Total Weight Remarks
1 1 10/15.9 2 4 40 7 ton Each Spool
2 3 10/15.9 2 4 40 7 ton Each Spool
3 4 10/15.9 2 4 40 7 ton Each Spool
4 10 10/15.9 2 4 40 7 ton Each Spool
5 11 10/15.9 2 4 40 7 ton Each Spool
6 12 10,12/15.9 2 4 44 7 &8 ton Each Spool
7 14 10,12/15.9 2 4 44 7 &8 ton Each Spool
8 16 12,14/15.9 2 4 52 8 &9 ton Each Spool
Total 340
First Well pad Job Execution Plan by 23 Ton Farana then after site visit on 25/12/19 100 ton Crane required
at Carin India,Barmer.
Sl.No. Well Pad No. Pipe Size /Thk No of Spool No of Joint Total Inch Dia Approx Total Weight
1 1 10/15.9 2 4 40 7 ton Each Spool
2 3 10/15.9 2 4 40 7 ton Each Spool
3 4 10/15.9 2 4 40 7 ton Each Spool
4 10 10/15.9 2 4 40 7 ton Each Spool
5 11 10/15.9 2 4 40 7 ton Each Spool
6 12 10,12/15.9 2 4 44 7 &8 ton Each Spool
7 14 10,12/15.9 2 4 44 7 &8 ton Each Spool
8 16 12,14/15.9 2 4 52 8 &9 ton Each Spool
Total 340
2/19 100 ton Crane required

Remarks