Вы находитесь на странице: 1из 8

Electric Power Systems Research 55 (2000) 49 – 56

www.elsevier.com/locate/epsr

Management of loss reduction projects for power


distribution systems
Emad S. Ibrahim 1
Faculty of Engineering, King Abdul Aziz Uni6ersity, Jeddah 21413, Saudi Arabia

Received 20 April 1999; accepted 17 August 1999

Abstract

Reducing the losses of power distribution systems (technical and non-technical losses) is an absolutely necessary objective in the
sound management of any electrical utility and a major stake for the countries concerned and the lenders. The paper describes
the context of losses in power distribution systems and deals more specifically with the corresponding diagnostics and
implementation of losses reduction plan. This paper has developed a precise and effective technique and method for the analysis
of the loss reduction problem and for the subsequent development of action plans to solve the overall problem, through a systemic
approach. © 2000 Published by Elsevier Science S.A. All rights reserved.

Keywords: Losses reduction; Technical losses; Non-technical losses; Power distribution systems; Management

1. Introduction different sub-projects of varying size and profitability


which calls upon the many and varied skills within the
The losses in power distribution systems can be company and which also deals with the relations with
classified as technical and non-technical losses. Whether the external environment. The following are the main
losses are considered ‘technical’ or ‘non-technical’, re- items, which must be conducted during the loss reduc-
ducing them is an imperative requirement for any elec- tion project:
tric company, because if they exceed certain ‘allowable’ 1. Measuring and evaluating the losses which is a
levels, they can actually endanger the company’s finan- complex problem with technical, economic and ac-
counting nature.
cial status. Of course, the losses concern the entire
2. The diagnosis which allows to determine the level
power systems, from production through transmission
and the origin of the losses.
to distribution; but the discussion is mostly oriented
3. The recommendations, which propose the actions to
toward losses in the distribution networks, where most
be undertaken inside and outside the company, to
of them occur.
reduce losses to a tolerable level.
The technical losses are related to energy distribution
4. Implementation of a tried and tested methodology
process while the non-technical losses are related to the resulting, in particular, in the drawing up of a
customer management process. schedule of actions to be carried out to conduct and
This paper develops a technique for the analysis of mark out the project.
the losses reduction problem and for the subsequent 5. Determination of the economic profitability criteria
development of action plans to solve the overall prob- for the choice of the actions to be undertaken.
lem, through a systemic approach. The losses reduction 6. A stringent management system, for the follow-up
plan is a medium-term investment project, with its of the actions undertaken and the assessment of the
results obtained in financial and institutional terms.
E-mail address: zcc3875@kaau.edu.sa (E.S. Ibrahim) 7. Implementation of a maintenance program to main-
1
On leave from Helwan University, Cairo, Egypt. tain and consolidate the results obtained.

0378-7796/00/$ - see front matter © 2000 Published by Elsevier Science S.A. All rights reserved.
PII: S 0 3 7 8 - 7 7 9 6 ( 9 9 ) 0 0 0 7 3 - 5
50 E.S. Ibrahim / Electric Power Systems Research 55 (2000) 49–56

2. Definition of losses 1. Buy the amount (A) strictly necessary to meet de-
mand (D): to achieve this, he must design and
The problem of losses may be illustrated as shown in operate the power network in a technically optimum
Fig. 1 that explains the functional process and the way to reduce the losses to a minimum natural level,
losses generated at each stage of the technical and linked to physical phenomena.
commercial management of a distribution company. 2. Maximize billed energy (F): the operator must de-
The operator of a power distribution system receives or sign and operate a customer management system
purchases the amount of energy (A) needed to meet the enabling him to assess the energy consumed by
customers’ demand (D). His task is to manage this customer and to invoice it accurately and then add
energy and see that it is conveyed to each customer. up the total amount. A customer who has been
The financial resources of the operator come from ‘forgotten’ or ‘not billed’ means the loss of mer-
the energy billed (F) to each customer (i.e. the product chandise and consequently a financial loss.
actually sold) and the effective payment of the invoices 3. Maximize paid energy (C): one therefore has to
which is the amount of energy (C) indicated in the monitor the payment of invoices, conduct actions to
invoices collected. The ideal situation would be for the compel defaulters to pay as quickly as possible,
quantities A F C to be equal. However, energy A manage accounts receivable so as to reduce unpaid
received by the distribution network is always higher energy to a minimum.
than energy F billed to customers, itself higher than
energy C which is effectively paid. The technical losses result from active and reactive
The interest of any operator is therefore to reduce energy in the networks during the distribution process.
system losses. To do so, he has three means of actions: The quantity of technical losses depends on the charac-

Fig. 1. Technical operation and commercial management.


E.S. Ibrahim / Electric Power Systems Research 55 (2000) 49–56 51

Table 1
Indicative values for percentage of lossesa

System losses Organization General action


L = TL+CL1

LB10% Excellent organization Efforts to maintain the level and vigilance


L = 10% Good Major investment required if losses are to be reduced fur-
ther. Effort to maintain the level
10%5L515% Correct. Significant commercial losses Improvement possible in the existing structure. Maintaining
the targeted reduction
15%5L520% Improvable organization. Major commercial losses Partial reorganization sometimes is necessary. Establishing
the loss reduction as a strategic project and mobilizing the
company
20%5L530% Defective substantial losses In depth reorganization. A strategic project is necessary.
Support of authorities is necessary
30%BL Exceptional situation linked to a crisis in the power sector. Reconstructing the company from the ground up, with the
Highly deficient organization authorities

a
Compared to the energy supplied to the distribution network.

teristics of existing facilities and their mode of operation. able, measured in currencies or days (months) of sales
The non-technical losses or ‘commercial’ losses result revenue. Forty-five days is an acceptable value for a great
from more or less serious dysfunctions in the process of many companies in developing countries. Finally, it
metering, reading, accounting, invoicing and collection should be noted that when CL1 losses are high, CL2
for energy consumed by customers. Their extent directly losses are as well, thus confirming the company’s serious
depends on the quality of the customer management dysfunctions.
chain. The non-technical losses may be classified into two
major groups:
1. CL1 Loss: unbilled energy corresponding to energy 4. Losses reduction gains
that has actually been consumed, but not recorded or
inaccurately recorded in the distribution company’s The high rate of technical and non-technical losses
billing system. In other words, CL1 loss is generated generates:
by dysfunctions, or even deficiencies, in the compa- 1. A reduction in revenue resulting in cash difficulties,
ny’s billing system. with all the ensuing economic consequences.
2. CL2 Loss: unpaid energy, originating from collection 2. Costly, useless or premature investments
losses induced by the absence of payment or a delay 3. Poor quality of service offered to customers.
in the payment of invoices issued. Major losses drive the authorities to subsidize the
company thus increasing the states’ financial load. Re-
ducing the losses and reaching an acceptable level will
3. Average loss levels restore the confidence of lenders and private investors to
encourage them to participate financially in the develop-
The voltage limits between transmission and distribu- ment of the power sector. The gains resulting from loss
tion after differs from country to country. In this paper reduction can be classified to: economic and financial
the voltage level, for calculation of distribution losses, is gains and institutional benefits.
up to and includes the 20 kV network voltage level.
Table 1 shows an indicative values for percentage of 4.1. Economic and financial gains
losses compared to the energy supplied to the distribution
network only and not to the energy supplied to the The economic and financial gains can be classified into
overall power system. For the losses of a distribution two kinds:
system (TL+CL1), 10% is estimated to be a technically 1. with constant consumption, the reduction of techni-
acceptable level. Some companies, in Western Europe, cal losses makes it possible to cut down generation
Japan and North America, manage to reach only 5% by and therefore save on investments and fuel (with
investing to a considerable extent in networks and the constant generation).
customer management system. For many countries in the 2. with constant generation and consumption, the re-
world, 10% in distribution system losses remains an duction of non-technical losses helps increase the
objective that is difficult to reach. Commercial losses sales revenue.
CL2, linked to the quantities of unpaid energy, are Thus, the reduction of technical losses leads to a real
usually recorded directly in the form of accounts receiv- gain in energy and reduced capital-intensive invest-
52 E.S. Ibrahim / Electric Power Systems Research 55 (2000) 49–56

ments. It therefore benefits the country’s economy. The company that succeeds in controlling its losses may be
reduction of non-technical losses not only improves the used by the Public Authorities as a model to be fol-
financial balance of the company concerned, but also lowed for the other infrastructure departments: water,
the load curve by subjecting consumption to the tariff post, telephone, etc. A successful loss reduction project
regulation. is a factor for progress in the country’s infrastructures.
Another way of stating the main benefits may be as
follows:
1. reduction of cost prices (with regard to the kWh 5. Non-technical losses
sold operating costs), improvement of accounting
results and financial stability of electrical utilities. Non-technical losses are not inevitable. They must be
2. improvement of the quality of supply and service identified and fought with eradication objective by all
offered to customers. electricity distribution companies concerned about
3. optimization of investments and improvement of the sound management. The problem caused by these non-
environment (reduction of the pollution of power technical losses is in many cases so serious that it is a
plants, more efficient use of financial resources, major, even vital, priority for the companies involved.
rational use of energy and tracking down customers’ To determine the level of non-technical losses, one
waste of energy). starts with the energy supplied to the distribution net-
4. it should also be noted that when a company has work from which are subtracted the technical losses on
stringent management, it can legitimately require the same network. Thus we reach the notion of effec-
the same stringency of its customers. tively consumed energy. Part of this consumed energy is
not invoiced. The unbilled consumed energy is the
4.2. Institutional benefits primary component of non-technical losses. When one
considers effectively invoiced energy, one notices that
Excessive losses are a synthetic indicator of more or part of the invoices are collected late compared with the
less serious dysfunctions in the Distribution Company, limit payment date fixed by the distributor. The finan-
affecting in particular organization, management and cial expenses generated by the unpaid invoice portfolio
skills. When the loss reduction project is a success and may be substantial.
losses have been brought down to a reasonable value, By definition, it is considered that the global value of
the success is therefore the proof that the actions for the non-technical losses borne by the company com-
reorganization, managerial change, training and moti- prises the cost of the unbilled consumed energy, to
vation of the personnel have been efficient, at the same which are added the financial expenses induced by the
time as the technical actions themselves. management of the customer debt and the amount of
Not only must one therefore seek to reduce the irrecoverable invoices.
losses, but also endeavor to teach the company to Table 2 shows the main causes of non-technical
continuously struggle to reduce losses. A distribution losses, which can be classified, into three major groups:

Table 2
Main causes of non-technical losses

Non-metered energy (consumption losses) Unbilled energy (invoicing errors) Unbilled energy
(collection losses)

1 — illegal connections (A) incorrect customer file (A) unpaid invoices


2 — delay in the installation of meters 1 — insufficient or erroneous contractual information 1 — non-distributed
invoices
3 — metering equipment tampered with 2 — non-conform metering coefficients 2 — customer payment
difficulties
4 — faulty meters 3 — faulty updating of the file 3 — unadapted collection
procedures
5 — estimates of effective consumption too low 4 — poor management
of unpaid invoices
6 — faulty connections (B) incorrect invoicing (B) payment management
7 — unadapted metering equipment 1 — customers not billed because of a lack of 1 — misappropriation of
knowledge and follow-up payments
8 — customers not taken into account 2 — absence of follow up of customers who benefit 2 — payment losses
from special or free tariffs
9 — meter reading errors at the reading level or 3 — absence of follow-up and reports on invoicing
erroneous index transfers incidents
4 — absence of check of rectified invoices
E.S. Ibrahim / Electric Power Systems Research 55 (2000) 49–56 53

1. Consumption losses corresponding to energy actually 1. the diagnosis of the existing situation, identification
consumed, but not recorded or inaccurately recorded of losses and their main causes.
in the distribution company’s invoicing system. 2. recommendations, with the writing of an Action Plan
2. Invoicing losses generated by dysfunctions, or even to reduce the detected losses.
gaps in the company’s invoicing system. 3. implementation of the action plan and measurement
3. Collection losses generated by non-payment or delay of the results obtained.
in the payment of the invoices issued. Even when an external consultant participates in
drawing up the project, the company management
should be closely involved in all these phases, as part of
6. Technical losses a complete learning process, because the implementation
of the Action Plan and lasting value of the results
Energy and power losses in electrical networks result depends entirely on them.
from the very transit of energy, and are therefore
intrinsic to transmission and distribution. So they are,
physically speaking, unavoidable. They can be reduced, 8. Conducting a non-technical loss reduction project
but not suppressed completely. The causes of these losses
8.1. Diagnostic phase
are:
1. contact resistors and conductors, where ‘Joule’ losses
This phase may be divided into two parts:
are found.
1. The audit of the general conditions of the customer
2. transformer plate magnetization, where ‘iron’ losses
service, which will take place at the company’s head
are found.
office.
3. auxiliary supplies needed for operating transformer
2. The analysis of the practical implementation of each
stations or network automatic systems, which are the
of the activities attached to customer management,
cause of parasitic consumption.
which will take place partly at the company’s head
4. major unbalances between phases on LV networks.
office and partly ‘in the field’, in the operational units
Losses have an effect on investments (mainly genera-
chosen by common consent.
tion) and on product quality (causing possible voltage
A typology per nature of customers, regions and
drops and cutoffs in the face of demand).
geographical areas must be studied. The results of the
As energy is measured only at the input or output of
analysis carried out by the project team are set out in a
the electric system, the only way of determining how
detailed report which clearly indicates the level, nature
much energy is lost at each voltage level is to determine
and value of the losses identified, as well as their main
physical quantities that result from measurements (of
origin. These conclusions are presented by the project
current, maximum power) taken in the network at
team to the company’s management before the following
properly chosen moments, and statistics that are charac-
phase gets under way.
teristic of customer consumption (load factors at the
various voltage levels). So, measurements campaigns are 8.2. Drawing up the action plan
indispensable for determining the:
1. local current intensities and (active and reactive) The purpose of this phase, which follows from the
power peaks. preceding one, is to determine the actions to be imple-
2. share of each voltage level in the national (and mented to reduce non-technical losses and classify them
sometimes regional) system peak. according to a short, medium and long-term plan, while
3. load factor at each voltage level. taking into account their technique-economic interest for
Mathematical laws using load factors and participa- the company.
tion factors in the system peak of each network compo- To compare the profitability and efficiency of the
nent can then be used to determine the: actions proposed, the experts use a homogeneous
1. energy losses at each voltage level (from the power method based on notions of discounted profits and
losses at the local peak). return time on investments. The proposed action plan
2. share of each voltage level in the system peak power consists of the following indications for each of the
losses (national or regional). recommended actions: urgency, expected efficiency,
global profitability, implementation time, required re-
sources (such as data processing hardware, vehicles,
metering equipment, training or hiring of personnel).
7. Implementing loss reduction projects The company thus has all the elements at its disposal to
assess and select the most efficient actions, according to
The loss reduction projects may be broken into three the company’s specific political and economic criteria
major phases: and constraints.
54 E.S. Ibrahim / Electric Power Systems Research 55 (2000) 49–56

Two examples help illustrate the type of action un- taken and (e) a strict management organization for
dertaken as part of a loss reduction action plan: following up on actions and their results.
1. if the metering of the energy supplied to customers
proves to be unreliable as shown by the diagnosis. An 9.1. Diagnostic, measurement and e6aluation phase
on-site check will have to be carried out and the
technical and administrative level of all the metering The objectives of this phase are:
equipment of major customers upgraded (MV and 1. Assess losses at each voltage level.
major LV consumers). 2. Detect abnormal points of loss.
2. if the information in the customer file is generally 3. Determine their causes.
missing or erroneous, there is good reason to perform 4. Evaluate overall technical energy losses, broken down
an on-site inventory of all electricity consumers and by voltage level.
the creation of a reliable and complete file. 5. Deduce the level of non-technical losses.
Other actions may concern management, organiza- 6. Establish the system peak power balance, broken
tion, procedures, or even the company’s legal down by voltage level.
environment. 7. Evaluate the cost of the lost kilowatt at peak, by
voltage level and as a function of the load factor.
8.3. Implementing the action plan 8. Establish the financial balance of energy transfers.
9. Deduce the cost of non-technical losses.
The objective of this phase is to implement the action The stages of diagnostic phase are:
plan with the assessment and follow-up of the results 1. Assembly of project team; surveys of available data;
obtained. During this phase, cooperation between the collection of general statistics.
company and the consultant, which must come within a 2. Methodological, development, with initiation of data
clear contractual framework, may take on extremely collection and measurement campaigns; analysis of
varied forms: training, advisory actions, management medium and low voltage networks sample selection
of the project, secondment of temporary or resident criteria; preliminary choice of geographic areas to be
experts, etc. The three main concerns in accompanying studied.
this phase are as follows: 3. Collection and data entry of general network
1. Assistance adapted to the context. characteristics.
2. A real desire for the transfer of know-how 4. Selection of samples and initiation of data collection
3. Durability of the progress recorded. Indeed the fight concerning them (MV and LV line and MV/LV
against non-technical losses is a long and exacting transformer characteristics); data collection for HV/
task. Great vigilance is constantly required and a MV substation transformers.
major amount of equipment and means must be used 5. Validation of data collected and entered; collection of
(metering equipment, invoicing data processing, cus- economic data to evaluate the cost of losses.
tomer file, and training, internal and external commu- 6. Computation of losses on medium and low voltage
nication). networks.
It is highly recommended that the project team be set 7. Validation of loss calculations.
up at the beginning of the operation, remain mobilized 8. Establishment of various balances (energy, system
for the implementation of the action plan, by carrying peak power, etc . . .).
out its role of supervising the control and training of the 9. Calculation of the cost of peak kilowatt lost.
players concerned. This project must include continuous The methodology generally applied by the project
monitoring to see that the planned schedule has been team during the diagnostic phase is based mainly on three
complied with and follow-up of the results obtained by elements:
comparing them with the objectives laid down. 1. The sampling by voltage level is based on the appli-
cation of families of works, each having a homoge-
neous behavior with respect to losses.
9. Technical loss reduction project process 2. Network computation tools.
3. The cost of the losses is computed by the marginal
Even if technical losses are more clearly definable development cost method.
than ‘non-technical’ ones, the process of reducing them
still has to become a true corporate, too. This process
involves: (a) a string determination on the part of the 9.2. De6eloping the action plan
company’s management; (b) the designation of a pro-
ject team with means and objectives; (c) implementation Depending on the scope of the mission entrusted to the
of a proven methodology; (d) determination of project group, its conclusions will be expressed in one of
profitability criteria for choosing actions to be under- the two following forms:
E.S. Ibrahim / Electric Power Systems Research 55 (2000) 49–56 55

1. It will state its advice and recommendations, includ- 7. MV or LV voltage changeover.


ing the type of operations and volume of invest- 8. LV network balancing.
ments to be made in order to reduce technical losses 9. Fallback on independent local production.
to an acceptable level. The investments will be eval- 10. Revision of planning, works dimensioning, mainte-
uated by extension of the stated volume on the nance or servicing mode standards.
samples. 11. Adaptation of tariffs to discourage consumption
2. If a more complete operation is planned, the group during peak hours.
will propose an action plan with dates and figures,
listing the operations on a schedule, in accordance 9.2.2.1. Action classification methodology. The method-
with the company’s possibilities and constraints, so ology applied should be based on a hierarchy of actions
that the company can integrate these operations in to be considered, guided by technical and economic
its projects and its budgets. The investments will be criteria. The basic ideas used are the discount rate,
evaluated by processing the whole network full losses cost, and discounted profit. Different projects can
scale. be compared using the investment return time and
In either case, the group will draw up a list of urgent profit cost ratio. The actions retained should have
measures to be taken with the immediately available either an acceptable return time or a profit cost ratio
means. greater then the discount rate.
Losses cost, which is an indispensable element in
9.2.1. First phase of action plan: plan of urgent evaluating the expected benefit of a project, can be
measures determined using the annual cost of the peak kilowatt
This includes quick actions to be taken with no lost. This method is based mainly on the computation
major investment involved. These actions, which consist of loss rates and marginal network development costs
in improving the operation of the existing system, are at each voltage level, and can also be based on an
essentially: in-house tariffs study. It evaluates the cost of the losses
1. optimization of the network operation scheme un- generated over 1 year by the loss of a kilowatt at the
der normal and backup conditions (certain com- special moment of peak consumption. This technique
puter programs can render the network’s minimum avoids having to consider each kilowatt-hour lost in its
loss configuration). tariff context.
2. optimization of HV/MV transformer use. Network electrical analysis should cover a period of
3. optimization of existing capacitors bank use. 5–10 years, because reducing electric system losses is an
4. suppression of weak points in the network, caused action to be viewed and implemented in the medium-
by high overloads (shifting of loads). term, so that the required investments can be
5. adjustment of MV voltage. amortized.
6. adjustment of LV voltage.
7. rebalancing of LV networks. 9.2.2.2. Means and tools used. To write a rational
Action Plan, relatively large network computations are
9.2.2. Second phase: action plan itself needed. The contribution of a computer system is deci-
This includes actions requiring investments that can sive here. No suitable actions can be proposed without
be implemented in the medium term, along with longer excellent technical management of the works. With the
term decisions supported by detailed technical and eco- computer facilities available today on the market, rapid
nomic planning analyses. This must contain a list and progress is possible and, above all, the necessary invest-
schedule of the necessary investments, compatible with ments can be optimized. Many electric companies have
the companies budgetary possibilities. Some of the pos- the software needed to plan their medium-and low-
sible actions are: voltage networks and to compute losses.
1. Modification of the electric network structure.
2. Installation of capacitors bank in HV/MV stations 9.2.2.3. Action plan de6elopment phase. The develop-
and in MV networks. ment phase can be broken down as follows:
3. Encouraging MV customers to correct their power 1. development and evaluation of medium-and low-
factor. voltage reinforcement projects for the whole
4. Backup of HV/MV stations and MV and LV network.
networks, with possible creation of new networks. 2. classification of projects by order of decreasing
5. Optimization of the purchase and operational profitability.
management of HV/MV and MV/LV stations and 3. evaluation of the total amount to be invested; com-
MV networks. parison with the profitability threshold set by the
6. Use of on-load regulators in HV/MV stations and financial backer; and determination of losses after
MV networks. works.
56 E.S. Ibrahim / Electric Power Systems Research 55 (2000) 49–56

4. establishment of short-term works program and the community as a whole and for the lenders.
schedule. Reaching an acceptable loss level will restore the
5. simulation of energy and peak power balances be- confidence of lenders and private investors to en-
fore and after works. courage them to participate financially in the devel-
opment of the power sector.
9.2.2.4. Durability of results. The economic analysis 2. The management must organize the reduction of
(even if it is based on a simulation on a 5 – 10 years losses as a genuine investment project sometimes to
scale) will not provide a basis for making good deci- be conducted over a period of several years.
sions concerning more than the first few years, because 3. A loss reduction project may practically concern all
the system may actually evolve quite differently from the economic and social players of a country: public
the initial prediction. So it is useful to update the study authorities, consumers and customers, the company
periodically. If the company decides to maintain the
as an institution, personnel and lenders.
loss level at an economic optimum in time, it will have
4. The losses reduction project must comprise
to acquire an elaborate organizational and methodolog-
4.1. The objectives to be reached.
ical structure, forecast system, data collection process,
4.2. A study of the benefits and costs.
and computer systems. The corresponding tools for the
given context and requirements already exist and can be 4.3. Clear implementation stages.
made available, along with the initial training and 4.4. Organization and means.
adequate accompanying services. 4.5. Results measurement system.
4.6. The risk and/or uncertainties.
9.3. Implementing the action plan 5. The losses reduction project can be broken down
into three major phases:
The object of this phase is to apply the Action Plan, 5.1. The diagnosis of the existing situation, identifi-
with follow-up and evaluation of the results. It is cation of losses and their main causes.
generally up to the company to implement the recovery 5.2. Establishment of an action plan so as to reduce
plan, which may require exceptional funds and means. the detected losses.
Often, a local Action Plan head should be named, who 5.3. Implementation of the action plan and follow-
will participate in the measurement and evaluation up of the results obtained.
phase and in writing the plan. 6. Not only must the company seek to reduce the
The company’s personnel has to be involved right losses, but also endeavor to continuously struggle to
from the beginning of the project, with training in reduce losses.
methodology and the use of the tools, and participation 7. When an external consultant participates in drawing
in the corresponding activities (data collection, mea- up the project, the company management should be
surements, calculations, and so forth). The main con- closely involved in all three phases, as part of a
cerns in the accompaniment of this phase are: complete learning process, because the implementa-
1. Suitable assistance.
tion of the Action Plan and the lasting value of the
2. Persistent commitment to transferring know-how.
results depends entirely on them.
3. Critical analysis of progress achieved.
8. When an external consultant is a factor for success.
4. Durability of the results.
Indeed he provides:
The project team assembled at the beginning of the
8.1. An externally and necessarily new view.
operation must remain actively involved throughout
this phase in order to supervise and coordinate the 8.2. Neutrality indispensable to the carrying out of
activities. the project.
8.3. Wealth of experience and solutions acquired in
various contexts.
10. Conclusions 9. This paper recommends reducing the losses
based on strict technical and economical rules,
which are generally reflected in an action plan, with
1. The reduction of losses is a major priority — even each action item supported by a profitability
a vital one in some cases, for electrical utilities, for analysis.

Вам также может понравиться