Вы находитесь на странице: 1из 95

INQUIRY NO.

: RD-PRD01-COW-CREQ-1019
WORK TITLE : MECHANICAL AND PIPING WORK PACKAGE-3
(GPP-SEPARATOR AREA - SCRUBER AREA )

RULES OF MEASUREMENT (PIPING)

WORK ITEM DESCRIPTION

A2.1 Wellpad Area


2.1.1 Shop Fabrication
2.1.2 Field Installation

A2.2 Pipeline area


2.2.1 Pipe Stringing
2.2.2 Field Welding

A2.3 Pipe Support


Cutting and adjust column head pile
(install plate and pipe sleeve)
Fabrication of Pipe shoes
Installation of Pipe shoes (include pre-
fabricated shoe)

Installation of Special support, Constant


load, spring, adjustable support,
Other Miscelleaneous Support (pipe
Anchor, stanchion, standard support,
guide, stopper, etc)
A2.4 Painting
A2.5 NDE
A2.6 Testing and Reinstatement
2.6.1 Linecheck and Punchkill
2.6.2 Testing
2.6.3 Reinstatement

A2.7 Scaffolding work


A2.8 Precommissioning
PIPING WORK PACKAGE-3
SCRUBER AREA )

RULES OF MEASUREMENT (PIPING)

RULES OF MEASUREMENT

work measured by Dia-in (DI) for each material and work category.
- Any other size and thickness combination might be regroup on similar pipe class rating or measured wall thickness.
- All smallbore material 1,5" and below is subject to field welding and site adjustment. Shop welding is considered as field weld.
- Shop welding Dia in shall include all welding work done at fabrication shop (in accordance with spool drawing)
- Field Installation Dia in shall include all welding work at site (in accordance with spool drawing)
- Any installation work including installation of valves, strainer, inline instrument, bolting, etc. required to complete pipeline installation shall be include in Field
in rate.
- Welding work for stainless shall include pickling work to remove all dirt, weld spatter, rusted to avoid further corrosion at stainless pipes

- Measured by total length of pipe being stringing at erection location (on position) (i.e, support or temporary support). Work measured in meter (m) length.
- Measured in Dia in (DI). This welding rate shall only related to welding work and segregated to pipe stringing

Note for Dia-in (DI)


* Dia in (DI) is calculated strictly on size of joint and has been segregated by thickness range
* Dia in (DI) for several geometry is calculated in accordance with attachment-1. Rule of measurement_Piping work volume factor

in general all support work to be measured in kg

Cutting of pile head and install base plate and pipe sleeve. 100% progress after completion each point support
100% progress of completion fabrication of each pipe shoe (if required).

100 % progress of installation of each pipe shoe, including erection of pre-fabricated pipe shoe.

100% progress of installation of each special, constant load, spring, adjustable support

consist of cutting, fabrication, and erection. Work progress consist of 50% fabrication, 50% erection of each support point
Painting to be measured by area to be painted (in m2) in accordance with painting specification, include touch up
to be done by CONTRACTOR -- to be xcluded from Subcontractor SOW
Completion of any comment rectification
100% progress of Completion of document preparation and punclist close prior testing. Ready for testing , Visual test is include this category
Hydrotest or Inservice test release inspection (Sign of testing certificate)
Complete of reinstatement and release of any punchlist comment (Sign of close comment)

Shall be offered in lumpsump


- Subcontractor to assist Contractor in providing personnel and their tools and equipment to carried out precommissioning work
- standard hand tools; grinder, hand drill, spanner, torque wrench, hammer, etc
- equipments : welding machine set and apparatus
Unit to be measured in Man month (MM) or equipment month (EM). To be detailed during technical clarification
PROJECT : RANTAU DEDAP G P P
JOB. NO. : 18-1105

.
s field weld.

pipeline installation shall be include in Field Installation Dia

sion at stainless pipes

rt). Work measured in meter (m) length.

t is include this category


COMPANY LETTERHEAD
DOC.NO : (Filled by Subcontractor Reference)
BIDDER NAME : PT.Azymuth Citra Perkasa
INQ./REQ.No. : RD-PRD01-COW-CREQ-1019
WORK TITLE : MECHANICAL AND PIPING WORK PACKAGE-3
(GPP-SEPARATOR AREA - SCRUBER AREA )

To,

PT. Rekayasa Industri (Persero)


Jl. Kalibata Timur I No. 36,
Kalibata-Jakarta, 127400
INDONESIA.

Up : Dwi Novianto S
Project Manager

With respect,

After read up all the tender document from PT. Rekayasa Industri for : "MECHANICAL AND PIPING WORK P
We proposed the cost for the works mentioned above in total price : Rp. _(amount)__
excluding income tax with lumpsump scheme for preparatory work and fixed unit price by provision sum basis
for permanent work in total duration of __(amount)__ month, commence from signage of Letter of Award.
The price above is fixed and valid until ___(duration)___days from the date of this Offering Letter.

If this offering accepted, we will send bank guarantee in assurance of work execution
in the amount of :Rp. __(amount)__ or 10% (ten percent) from Contract Price
before 14th days after Letter of Intent acceptance.

Supporting documents are attached with this letter for your evaluation.

This concludes our offering letter and thank you the opportunity to bid this work.
Please let us now if you need assitance regarding this letter.
ERHEAD
FORM No. : 1
DATE : 22 Agustus 2019
PROJECT NAME : RANTAU DEDAP G P P
JOB. NO. : 18-1105
REVISION : 2 ( 22-08-2019)

HANICAL AND PIPING WORK PACKAGE-3 " for Rantau Dedap Project,

unit price by provision sum basis


signage of Letter of Award.
f this Offering Letter.

With Respect,
PT………………………………………..

Postage

Name :
Position :
DOC. NO. : (Filled by Subcontractor Reference) FORM NO. : 2A
BIDDER : PT.Azymuth Citra Perkasa DATE : 22 Agustus 2019
INQUIRY NO. : RD-PRD01-COW-CREQ-1019 PROJECT : RANTAU DEDAP G P P
WORK TITLE : MECHANICAL AND PIPING WORK PACKAGE-3 JOB. NO. : 18-1105
(GPP-SEPARATOR AREA - SCRUBER AREA ) REVISION : 2 ( 22-08-2019)

COST SUMMARY
(WORK ITEM WISE)

COST CODE WORK ITEMS TOTAL PRICE (Rp)

I FIX INDIRECT COST 4,397,009,145.00

II PERMANENT WORK
2.1 MECHANICAL WORK
2.1.1 STEAM SEPARATOR & SCRUBBER 1,892,970,000.00
2.1.2 BRINE & CONDENSATE MIXING AND REINJECTION SYSTEM 3,608,724.14
2.1.3 THERMAL PONDS AND DRAINS 27,780,000.00
2.1.4 STEAM TURBIN AND AUXILIARIES 4,870,500,000.00
2.1.5 GENERATOR AND AUXILIARIES 1,365,760,000.00
2.1.6 CONDENSING AND GAS EXTRACTION 4,295,850,000.00
2.1.7 MAIN COOLING WATER SYSTEM 2,450,076,200.00
2.1.8 AUXILIARY COOLING WATER SYSTEM 176,280,000.00
2.1.9 COMPRESSED AIR 98,400,000.00
2.1.10 LIFTING EQUIPMENT 245,988,000.00
2.1.11 CHEMICAL TREATMENT SYSTEM 246,050,000.00
2.1.12 UTILITY WATER SYSTEM 73,222,200.00
2.1.13 FIRE WATER SYSTEM 37,326,366.00
2.1.14 FIRE PROTECTION SYSTEM 7,764,150.00
2.1.15 POWER TRANSFORMER 1,951,690,000.00
2.1.16 EMERGENCY SERVICE SYSTEM 88,235,000.00
2.1.17 MISCELENEAOUS 1,755,561,112.25

SUB TOTAL MECHANICAL WORK 19,587,061,752.39

2.2 PIPING WORK


2.2.1 WELDING WORK 33,408,070,023.13
2.2.2 PIPE SUPPORT 465,365,250.00
2.2.3 PAINTING (Pipe and Support) 1,237,644,030.88
2.2.4 NON DESTRUCTIVE TEST (by REKIND)
2.2.5 TESTING AND REINSTATEMENT 2,873,914,362.71
2.2.6 SCAFFOLDING 394,284,836.31
2.2.7 PRECOMMISSIONING 1,221,650,599.58

SUB TOTAL PIPING WORK 39,600,929,102.62


SUB TOTAL II PERMANENT WORK 59,187,990,855.01
GRAND TOTAL ( SUB TOTAL I + II ) 63,585,000,000.01
DOC. NO. : (Filled by Subcontractor Reference)
BIDDER NAME : PT.Azymuth Citra Perkasa
INQ./REQ.No. : RD-PRD01-COW-CREQ-1019
WORK TITLE : MECHANICAL AND PIPING WORK PACKAGE-3
(GPP-SEPARATOR AREA - SCRUBER AREA )

NO. DESCRIPTION SPECIFICATION Unit WEIHGT /


QTY

(A)

I FIX INDIRECT COST


1.1 Home office cost LS 1
1.2 Mobilization and demobilization for personel LS 1
1.3 Temporary facilities (cost, supply and demolition) LS 1
1.4 Salaries, wages, allowance for field personel/staff LS 1
1.5 Field expenses LS 1
1.6 Insurance LS 1
1.7 Direct labor service cost LS 1
1.8 Taxes, duties and other charge (Pajak, bea dan biaya lainnya ) LS 1
1.9 Pre financing cost LS 1

SUB TOTAL I FIX INDIRECT COST

II PERMANENT WORK

2.1 MECHANICAL WORK

2.1.1 STEAM SEPARATOR & SCRUBBER


Dimension Per Unit
Weight (each) QTY
Equipment (mm)
kg (ea)
LxWxH or ØxH
2.1.1.1 Anti Surge Tank 16700 x 4000 x 4050 52,200 1 Ton 52.20
2.1.1.2 HP Separator 18300 x 4000 x 4050 75,300 1 Ton 75.30
2.1.1.3 LP Separator 18300 x 4000 x 4050 67,500 2 Ton 135.00
2.1.1.4 HP Scrubber 13590 x 2470 x 2470 17,300 2 Ton 34.60
2.1.1.5 LP Scrubber 11450 x 2200 x 2200 14,000 2 Ton 28.00
2.1.1.6 Flash Vessel 3900 x 1800 x 1800 3,500 2 Ton 7.00
332.1
2.1.2 BRINE & CONDENSATE MIXING AND REINJECTION SYSTEM

2.1.2.1 Wellpad E Reinjection Pump 250 1 Ton 0.25


0.3
2.1.3 THERMAL PONDS AND DRAINS
2.1.3.1 CPI Separator 2692 x 2344 x 3175 2,954 1 Ton 2.95
2.1.3.2 HWP Pit Sump Pump 770 x 340 x 768 150 4 Ton 0.60
2.1.3.3 Oily Water Pump 770 x 340 x 769 150 1 Ton 0.15
3.7
2.1.4 STEAM TURBIN AND AUXILIARIES
2.1.4.1 Sub-Sole Plate 1000 x 900 x 650 800 2 Ton 1.60
2.1.4.2 Sole Plate and Anchor Bolts 3300 x 3200 x 1900 13,000 2 Ton 26.00
2.1.4.3 Turbine Rotor 8300 x 3200 x 3300 55,400 2 Ton 110.80
2.1.4.4 Casing Upper Front 3300 x 6000 x 2750 24,700 2 Ton 49.40
2.1.4.5 Casing Upper Rear 4200 x 6000 x 2750 34,500 2 Ton 69.00
2.1.4.6 Casing Lower Front 3600 x 6300 x 2750 30,100 2 Ton 60.20
2.1.4.7 Casing Lower Rear 4500 x 6300 x 2750 41,900 2 Ton 83.80
2.1.4.8 Bearing Pedestal Front 2400 x 2300 x 2000 7,800 2 Ton 15.60
2.1.4.9 Bearing Pedestal Rear 2000 x 2300 x 3400 8,800 2 Ton 17.60
2.1.4.10 Turbine Miscellaneous Parts 8,600 2 Ton 17.20
2.1.4.11 HP Steam Stop Valve (L&R) 2600 x 900 1,900 4 Ton 7.60
2.1.4.12 HP Steam Control Valve (L&R) 2600 x 900 1,900 4 Ton 7.60
2.1.4.13 LP Steam Stop Valve (L&R) 2600 x 1000 2,000 4 Ton 8.00
2.1.4.14 LP Steam Control Valve (L&R) 2600 x 1000 2,000 4 Ton 8.00
2.1.4.15 HP/LP Steam Strainer (L&R) 2450 x 1850 x 3250 4,200 8 Ton 33.60
2.1.4.16 Gland Steam Control Valve 800 x 1250 300 2 Ton 0.60
2.1.4.17 Lube Oil Console 5900 x 3800 x 3900 15,900 2 Ton 31.80
2.1.4.18 Control Oil Console 3400 x 2300 x 2400 3,700 2 Ton 7.40
2.1.4.19 Lube Oil Cooler 3400 x 1000 x 2400 2,700 4 Ton 10.80
2.1.4.20 Turbine Washing Pump 1720 x 470 x 480 200 2 Ton 0.40
2.1.4.21 Clean & Dirty Lube Oil Tank, include accessories 6000 x 2200 x 2400 3,000 2 Ton 6.00
573.0
2.1.5 GENERATOR AND AUXILIARIES
2.1.5.1 Generator Rotor 1350 x 8400 18,700 2 Ton 37.40
2.1.5.2 Generator Stator 3600 x 3500 x 3800 66,000 2 Ton 132.00
2.1.5.3 Bearing Stand, Metal & Packing Ring 1600 x 1500 x 1400 3,000 4 Ton 12.00
2.1.5.4 Bed Plate, Anchor Plate and Founadrion Bolt 3600 x 2100 x 900 4,400 2 Ton 8.80
2.1.5.5 Generator Sub-Sole Plate 1100 x 800 x 750 800 2 Ton 1.60
2.1.5.6 Fan Guide, Air Shield, Air Duct 2400 x 2300 x 1400 1,100 2 Ton 2.20
2.1.5.7 Air Cooler 4400x1300x900 1,400 6 Ton 8.40
2.1.5.8 Generator Miscellaneous Parts 5,500 2 Ton 11.00
213.4
2.1.6 CONDENSING AND GAS EXTRACTION
2.1.6.1 Condenser Lower Shell 1 6800 x 5000 x 4800 28,600 2 Ton 57.20
2.1.6.2 Condenser Lower Shell 2 6800 x 4800 x 4800 31,700 2 Ton 63.40
2.1.6.3 Condenser Lower Shell 3 6800 x 4800 x 4800 32,500 2 Ton 65.00
2.1.6.4 Condenser Lower Shell 4 6800 x5000 x 4800 30,400 2 Ton 60.80
2.1.6.5 Condenser Upper Shell 1 6400 x 3500 x 2300 8,600 2 Ton 17.20
2.1.6.6 Condenser Upper Shell 2 6400 x 3500 x 2300 8,600 2 Ton 17.20
2.1.6.7 Turbine Exhaust Connection 5300 x 2700 x 2700 17,400 4 Ton 69.60
2.1.6.8 Gas Outlet Pipe 1700 x 1700 x 900 250 4 Ton 1.00
2.1.6.9 Hotwell 4000 x 3500 11,000 2 Ton 22.00
2.1.6.10 Condenser parts (sole plate, etc.) 3,200 2 Ton 6.40
2.1.6.11 Steam Ejector 900 x 7550 x 1100 1,310 6 Ton 7.86
2.1.6.12 Intercondenser 7030 x 1900 x 1900 4,400 2 Ton 8.80
2.1.6.13 After Condenser 2240 x 6720 x 2510 3,800 2 Ton 7.60
2.1.6.14 Back-up Ejector 700 x 5060 x 900 850 2 Ton 1.70
2.1.6.15 Vacuum Pump 3520 x 10300 x 3300 37,605 4 Ton 150.42
2.1.6.16 Separator Tank 4320 x 2660 3,350 4 Ton 13.40
2.1.6.17 Sump Pump 870 x 690 x 1030 400 8 Ton 3.20

572.8
2.1.7 MAIN COOLING WATER SYSTEM
2.1.7.1 Cooling Tower Fan 5400 x 1760 x 840 890 12 Ton 10.68
2.1.7.2 Cooling Tower Motor 20000 x 13000 x 12000 1,400 12 Ton 16.80
2.1.7.3 Cooling Tower Gearbox 1040 x 1420 x 1190 1,222 12 Ton 14.66
2.1.7.4 Cooling Tower Accessories 37,996 2 Ton 75.99
2.1.7.5 Intake Screen 4100 x 3600 x 1880 2,300 4 Ton 9.20
2.1.7.6 HWP Barrel Case 5000 x3100 x 3610 9,600 4 Ton 38.40
2.1.7.7 HWP Base 3200 x 3070 x 830 2,900 6 Ton 17.40
2.1.7.8 HWP Discharge Elbow 2850 x 2680 x 2910 8,200 6 Ton 49.20
2.1.7.9 HWP Motor 3500 x 4400 x 2500 16,900 6 Ton 101.40
2.1.7.10 HWP Unit 5750 x 1900 x 2060 6,100 6 Ton 36.60
2.1.7.11 HWP Accessories 1,100 6 Ton 6.60
376.9
2.1.8 AUXILIARY COOLING WATER SYSTEM
2.1.8.1 Auxiliary Cooling Water Pump, include accessories 2960 x 1430 x 1620 2,700 4 Ton 10.80
2.1.8.2 Primary Secondary Water Heat Exchanger 1600 x 1250 x 1840 4,080 4 Ton 16.32
27.1
2.1.9 COMPRESSED AIR
2.1.9.1 Air Compressor skid 2600 x 1200 x 1700 1,600 3 Ton 4.80
2.1.9.2 Air Dryer skid 930 x 440 x 1400 1,000 2 Ton 2.00
2.1.9.3 Power Plant Air Receiver A 1470 x 4525 2,130 1 Ton 2.13
2.1.9.4 Power Plant Air Receiver B 1470 x 4525 2,130 1 Ton 2.13
2.1.9.5 Separator Station Air Receiver 1112 x 3833 1,040 1 Ton 1.04
2.1.9.6 Vent Station Air receiver 1112 x 3733 1,020 1 Ton 1.02
13.1
2.1.10 LIFTING EQUIPMENT
2.1.10.1 OH Crane Workshop Building See Detail Drawing 35,592 1 Ton 35.59
2.1.10.2 Turbine Generator OH Crane See Detail Drawing 4,950 1 Ton 4.95
2.1.10.3 Hoist for lifting intake screen See Detail Drawing 228 2 Ton 0.46
41.0
2.1.11 CHEMICAL TREATMENT SYSTEM
2.1.11.1 Acid Dosing Pump 1500 x 800 x 700 600 4 Ton 2.40
2.1.11.2 NaOH Dilution Tank LxWxH 4,200 2 Ton 8.40
2.1.11.3 Biocide Tank LxWxH 900 2 Ton 1.80
2.1.11.4 Biocide and NaOH Dosing Skid LxWxH 4,100 2 Ton 8.20
2.1.11.5 Accessories 800 2 Ton 1.60
2.1.11.6 Acid Dosing System LxWxH 3,500 1 Ton 3.50
25.9
2.1.12 UTILITY WATER SYSTEM
2.1.12.1 Utility Water Supply Pump LxWxH 150 1 Ton 0.15
2.1.12.2 Utility Water Distribution Pump LxWxH 250 1 Ton 0.25
2.1.12.3 Backwash Pump LxWxH 150 1 Ton 0.15
2.1.12.4 Fresh Water Storage Tank 3862 x 3480 2,895 1 Ton 2.90
2.1.12.5 Water Treatment System, UV filter, include accessories 4000 x 2000 x 4080 4,263 1 Ton 4.26
7.7
2.1.13 FIRE WATER SYSTEM
2.1.13.1 Diesel
ElectricEngine
DrivenDriven
Fire Fighting Main Pump
Fire Fighting 2700 x 890 x 2040
Backup Pump, include accessories 1,584 1 Ton 1.58
2.1.13.2 3050 x 1050 x 1700 1,749 1 Ton 1.75
2.1.13.3 Fire Water Jockey Pump 1100 x 300 x 1320 150 1 Ton 0.15
2.1.13.4 Diesel Engine Fuel Tank 1000 x 1000 x 1800 425 1 Ton 0.42
3.9
2.1.14 FIRE PROTECTION SYSTEM
2.1.14.1 Deluge Valve 2" 478 x 283 x 660 43 2 Ton 0.09
2.1.14.2 Deluge Valve 3" 478 x 283 x 661 48 4 Ton 0.19
2.1.14.3 Deluge Valve 4" 491 x 372 x 675 67 5 Ton 0.34
2.1.14.4 Deluge Valve 6" 550 x 514 x 720 100 2 Ton 0.20
0.8
2.1.15 POWER TRANSFORMER
2.1.15.1 Generator Transformer 118,000 2 Ton 236.00
2.1.15.2 Unit Auxiliary Transformer 23,270 2 Ton 46.54
2.1.15.3 Unit Service Transformer 8,860 2 Ton 17.72
300.3
2.1.16 EMERGENCY SERVICE SYSTEM
2.1.16.1 Emergency Diesel Generator 10,105 1 Ton 10.11
2.1.16.2 EDG Local Control Panel 500 1 Ton 0.50
2.1.16.3 Diesel Fuel Daily Tank 2,000 1 Ton 2.00
12.6
Total Lifting Ton 2,504.6
2.1.17 MISCELENEAOUS
Assembly of Cooling Tower Unit
- Including distribution pipe

- Spreader bar for Air Compressor Erction complete with


certification
Couple, Pre-alignment and Final alignment all rotating equipment Pcs 1.00
Dimension
(include tools).L 3120 x W 1500 mm
Include man power asist during solorun, mech. tun test, pre-
Foundation grouting
commissioning work (grouting material by Sub Cont.)
and commissioning.
2.1.17.1 70 m3 1 m3 70.00
(chipping,
Breakdowncleaning,
man powergrouting, finishing)
for asist pre-comm & comm (after install
equipment) also for welding equipment:
» Foreman → 1 person
»
ManMillpower
wrightassist
→ 4 person
for load tests of all lifting devices.
»
Subcontractor shall steel)
Welder (stainless provide→the8 person
base frame structure which
»
suitable to lifting the test loadperson
Welder (carbon steel) → 2 up to 82.0 ton
» Fitter → 16 person
2.1.17.2 Install anchor 37 in 1 in 37.00
» Helper → 12bolt (included in each equipment weight)
person
Welding Joint Condenser & Turbine Exhaust Connection, include
2.1.17.3 31 m 1 m 31.00
surface preparation and painting after welding

Welding Joint STG OHC, include surface preparation and painting


after welding

Man power assist for Pre-Comm and Comm of rotating equipment


» Foreman → 1 person (min.)
» Mill wright → 4 person (min.)

SUB TOTAL MECHANICAL WORK


2.2 PIPING WORK

2.2.1 WELDING WORK Material and rating Size range Welding Type 53,885.00
2.2.1.1 ABOVE GROUND PIPING WORK
2.2.1.1.1 Carbon steel
Carbon steel # 150 0,5" - 1,5" Shop/Field dia-inch 1,760
Carbon steel # 150 2" - 24" Shop dia-inch 9,856
Carbon steel # 150 2" - 24" Field dia-inch 8,064
Carbon steel # 150 26" - 48" Shop dia-inch 7,011
Carbon steel # 150 26" - 48" Field dia-inch 5,736
Carbon steel # 300 0,5" - 8" Shop/Field dia-inch 450
Carbon steel # 600 - 120
#1500 0,5" - 4" Shop/Field dia-inch

Subtotal CS steel 32,997.00


2.2.1.1.2 SS-304/316
SS-304/316 #150 0,5" - 1,5" Shop/Field dia-inch 2,991
SS-304/316 #150 2" - 24" Shop dia-inch 5,383
SS-304/316 #150 2" - 24" Field dia-inch 4,404
SS-304/316 #150 26" - 48" Shop dia-inch 2,124
SS-304/316 #150 26" - 48" Field dia-inch 1,737
SS-304/316 #150 50" and Over Shop dia-inch 1,941
SS-304/316 #150 50" and Over Field dia-inch 1,588
SS-304/316 #300 0,5" - 4" Shop/Field dia-inch 440
SS-304/316 #600 - 280
#1500 0,5" - 3" Shop/Field dia-inch

Subtotal SS steel dia-inch 20,888.00


2.2.1.1.3 DUPLEX SS
DUPLEX SS #150 2" - 24" Shop/Field dia-inch 0
DUPLEX SS #150 26" - 48" Shop/Field dia-inch 0

Subtotal DUPLEX SS dia-inch -


2.2.1.1.3 FRP,PVC
FRP All size Shop/Field dia-inch 11,443
PVC All size Shop/Field dia-inch 366
Threaded joint (All 350
Material) All size Field dia-inch

Subtotal FRP,PVC dia-inch 12,159.0


Sub Total Joint AboveGround
dia-inch 66,044.0

2.2.1.2 UNDERGROUND PIPING WORK


(consumables, Resin, wooven material tobe supplied by CONTRACTOR)
2.2.1.2.1 Joint / Welding work <lamination>
FRP 18" as procedure
<lamination> dia-inch 180.0
FRP 28" as procedure
<lamination> dia-inch 784.0
FRP 40" as procedure
<lamination> dia-inch 320.0
FRP 48" as procedure
<lamination> dia-inch 672.0
FRP 60" as procedure
<lamination> dia-inch 1,800.0
FRP 72" as procedure dia-inch 2,160.0
<buttweld
HDPE 3" joint>
<buttweld dia-inch 114.0
HDPE 4" joint>
<buttweld dia-inch 1,183.0
HDPE 6" joint>
<buttweld dia-inch 174.0
HDPE 8" joint> dia-inch 2,364.0
Sub Total Joint UnderGround
dia-inch 9,751.00

2.2.1.2.2 Excavation m3 15,432.2


2.2.1.2.3 Backfill and Compacting (include provision of sand) m3 13,888.9
2.2.1.2.4 Sand bedding for FRP and HDPE m3 2,314.8
2.2.1.2.5 Testing (underground portion) test package 34.0
2.2.1.2.6 Shoring m2 612.0
31,669.9

2.2.2 PIPE SUPPORT


Fabrication and installation of pipe support, indluding installation of prefabricated support

2.2.2.1 Carbon Steel Carbon Steel fabrication Ton 140


Installation (include pre-fab Ton 155
2.2.2.2 Stainless Steel Stainless Steel fabrication Ton 3
Installation Ton 4

2.2.3 PAINTING (Pipe and Support)


as per specification m2 5,772
2.2.4 NON DESTRUCTIVE TEST (by REKIND) Magnetic Particle Inspection (MPI) or Liquid
Radiography Test (RT) or UT* dia inch 16,783
mtr weld 2,787
Penetrant
(LPE)*
2.2.5 TESTING AND REINSTATEMENT 377.30
2.2.5.1 Linecheck and Punchkill work
Hydrostatic test test package 347
Visual Test (vent, drain, atmospheric line) test package 30

2.2.5.2 Testing
Hydrostatic test test package 27
Service test (cat D fluid,service water, air, inst, etc) test package 3

2.2.5.3 Reinstatement
Hydrostatic test test package 3
410

2.2.6 SCAFFOLDING Lot 1

2.2.7 PRECOMMISSIONING
(Assist of manpower including common tools, PPE,equipment,consumables, etc), estimated 3 month
Supervisor MM 3
Foreman MM 9
Welder MM 18
Fitter-1 MM 18
Semi skilled MM 27

SUB TOTAL PIPING WORK

SUB TOTAL II PERMANENT WORK

GRAND TOTAL ( SUB TOTAL I & II )


COST BREAKDOWN
(WORK ITEM WISE)

UNIT PRICE TO

Direct Labor Indirect Cost for


Direct Material Direct Equip't Direct Material Direct Equip't
Manhours Labor Rate Labor Cost Construction
(B) (C) (D) (E) ( F=DXE ) (G) ( H=AXB ) ( I=AXC )

282,501,243.00 -
375,701,246.00 -
496,052,346.00 -
891,501,246.00 -
519,101,246.00 -
524,617,646.00 -
532,181,246.00 -
572,851,680.00 -
202,501,246.00 -

30 45 25.00
1,710,000 2,565,000 1,425,000.00 - 89,262,000
1,710,000 2,565,000 1,425,000.00 - 128,763,000
1,710,000 2,565,000 1,425,000.00 - 230,850,000
1,710,000 2,565,000 1,425,000.00 - 59,166,000
1,710,000 2,565,000 1,425,000.00 - 47,880,000
1,710,000 2,565,000 1,425,000.00 - 11,970,000

- - - -
- - - -
4,149,749 6,728,748 3,556,399.57 - 1,037,437

- -
2,250,000 3,375,000 1,875,000.00 - 6,646,500
2,250,000 3,375,000 1,875,000.00 - 1,350,000
2,250,000 3,375,000 1,875,000.00 - 337,500
- - -
- -
2,550,000 3,825,000 2,125,000.00 - 4,080,000
2,550,000 3,825,000 2,125,000.00 - 66,300,000
2,550,000 3,825,000 2,125,000.00 - 282,540,000
2,550,000 3,825,000 2,125,000.00 - 125,970,000
2,550,000 3,825,000 2,125,000.00 - 175,950,000
2,550,000 3,825,000 2,125,000.00 - 153,510,000
2,550,000 3,825,000 2,125,000.00 - 213,690,000
2,550,000 3,825,000 2,125,000.00 - 39,780,000
2,550,000 3,825,000 2,125,000.00 - 44,880,000
2,550,000 3,825,000 2,125,000.00 - 43,860,000
2,550,000 3,825,000 2,125,000.00 - 19,380,000
2,550,000 3,825,000 2,125,000.00 - 19,380,000
2,550,000 3,825,000 2,125,000.00 - 20,400,000
2,550,000 3,825,000 2,125,000.00 - 20,400,000
2,550,000 3,825,000 2,125,000.00 - 85,680,000
2,550,000 3,825,000 2,125,000.00 - 1,530,000
2,550,000 3,825,000 2,125,000.00 - 81,090,000
2,550,000 3,825,000 2,125,000.00 - 18,870,000
2,550,000 3,825,000 2,125,000.00 - 27,540,000
2,550,000 3,825,000 2,125,000.00 - 1,020,000
2,550,000 3,825,000 2,125,000.00 - 15,300,000

- -
1,920,000 2,880,000 1,600,000.00 - 71,808,000
1,920,000 2,880,000 1,600,000.00 - 253,440,000
1,920,000 2,880,000 1,600,000.00 - 23,040,000
1,920,000 2,880,000 1,600,000.00 - 16,896,000
1,920,000 2,880,000 1,600,000.00 - 3,072,000
1,920,000 2,880,000 1,600,000.00 - 4,224,000
1,920,000 2,880,000 1,600,000.00 - 16,128,000
1,920,000 2,880,000 1,600,000.00 - 21,120,000

- -
2,250,000 3,375,000 1,875,000.00 - 128,700,000
2,250,000 3,375,000 1,875,000.00 - 142,650,000
2,250,000 3,375,000 1,875,000.00 - 146,250,000
2,250,000 3,375,000 1,875,000.00 - 136,800,000
2,250,000 3,375,000 1,875,000.00 - 38,700,000
2,250,000 3,375,000 1,875,000.00 - 38,700,000
2,250,000 3,375,000 1,875,000.00 - 156,600,000
2,250,000 3,375,000 1,875,000.00 - 2,250,000
2,250,000 3,375,000 1,875,000.00 - 49,500,000
2,250,000 3,375,000 1,875,000.00 - 14,400,000
2,250,000 3,375,000 1,875,000.00 - 17,685,000
2,250,000 3,375,000 1,875,000.00 - 19,800,000
2,250,000 3,375,000 1,875,000.00 - 17,100,000
2,250,000 3,375,000 1,875,000.00 - 3,825,000
2,250,000 3,375,000 1,875,000.00 - 338,445,000
2,250,000 3,375,000 1,875,000.00 - 30,150,000
2,250,000 3,375,000 1,875,000.00 - 7,200,000
- - -

6,500,000.00 1,950,000 2,925,000 1,625,000.00 - -


1,950,000 2,925,000 1,625,000.00 - 20,826,000
1,950,000 2,925,000 1,625,000.00 - 32,760,000
1,950,000 2,925,000 1,625,000.00 - 28,592,460
1,950,000 2,925,000 1,625,000.00 - 148,184,400
1,950,000 2,925,000 1,625,000.00 - 17,940,000
1,950,000 2,925,000 1,625,000.00 - 74,880,000
1,950,000 2,925,000 1,625,000.00 - 33,930,000
1,950,000 2,925,000 1,625,000.00 - 95,940,000
1,950,000 2,925,000 1,625,000.00 - 197,730,000
1,950,000 2,925,000 1,625,000.00 - 71,370,000
1,950,000 2,925,000 1,625,000.00 - 12,870,000
- -
1,950,000 2,925,000 1,625,000.00 - 21,060,000
1,950,000 2,925,000 1,625,000.00 - 31,824,000

- -
2,250,000 3,375,000 1,875,000.00 - 10,800,000
2,250,000 3,375,000 1,875,000.00 - 4,500,000
2,250,000 3,375,000 1,875,000.00 - 4,792,500
2,250,000 3,375,000 1,875,000.00 - 4,792,500
2,250,000 3,375,000 1,875,000.00 - 2,340,000
2,250,000 3,375,000 1,875,000.00 - 2,295,000

- -
1,800,000 2,700,000 1,500,000.00 - 64,065,600
1,800,000 2,700,000 1,500,000.00 - 8,910,000
1,800,000 2,700,000 1,500,000.00 - 820,800
- - - -
- -
2,850,000 4,275,000 2,375,000.00 - 6,840,000
2,850,000 4,275,000 2,375,000.00 - 23,940,000
2,850,000 4,275,000 2,375,000.00 - 5,130,000
2,850,000 4,275,000 2,375,000.00 - 23,370,000
2,850,000 4,275,000 2,375,000.00 - 4,560,000
2,850,000 4,275,000 2,375,000.00 - 9,975,000

- -
2,850,000 4,275,000 2,375,000.00 - 427,500
2,850,000 4,275,000 2,375,000.00 - 712,500
2,850,000 4,275,000 2,375,000.00 - 427,500
2,850,000 4,275,000 2,375,000.00 - 8,250,750
2,850,000 4,275,000 2,375,000.00 - 12,148,410

- -
2,865,000 4,297,500 2,387,500.00 - 4,539,020
2,865,000 4,297,500 2,387,500.00 - 5,011,057
2,865,000 4,297,500 2,387,500.00 - 431,125
2,865,000 4,297,500 2,387,500.00 - 1,216,708

- -
2,865,000 4,297,500 2,387,500.00 - 246,390
2,865,000 4,297,500 2,387,500.00 - 550,080
2,865,000 4,297,500 2,387,500.00 - 959,775
2,865,000 4,297,500 2,387,500.00 - 573,000

- -
1,950,000 2,925,000 1,625,000.00 - 460,200,000
1,950,000 2,925,000 1,625,000.00 - 90,753,000
1,950,000 2,925,000 1,625,000.00 - 34,554,000

- -
2,100,000 3,150,000 1,750,000.00 - 21,220,500
2,100,000 3,150,000 1,750,000.00 - 1,050,000
2,100,000 3,150,000 1,750,000.00 - 4,200,000

100,000,000.00 35,000,000 25,000,000 52,307,219.55 100,000,000 35,000,000

374,400.00 13,047,600 2,115,646 5,079,569.10 26,208,000 913,331,993

118,486 192,123 101,544.57 - 4,383,991


1,138,488 923,020 673,948.32 - 35,293,132

126,208,000.00 6,337,414,128.30
400,000.00 120,000 180,000 100,000.00
120,000 180,000 100,000.00 - 211,200,000
120,000 180,000 100,000.00 - 1,182,720,000
120,000 180,000 100,000.00 - 967,680,000
120,000 180,000 100,000.00 - 841,320,000
120,000 180,000 100,000.00 - 688,320,000
120,000 180,000 100,000.00 - 54,000,000
120,000 180,000 100,000.00 - 14,400,000
- -

- -
165,000 247,500 137,500.00 - 493,515,000
165,000 247,500 137,500.00 - 888,195,000
165,000 247,500 137,500.00 - 726,660,000
165,000 247,500 137,500.00 - 350,460,000
165,000 247,500 137,500.00 - 286,605,000
165,000 247,500 137,500.00 - 320,265,000
165,000 247,500 137,500.00 - 262,020,000
165,000 247,500 137,500.00 - 72,600,000
165,000 247,500 137,500.00 - 46,200,000
- -
- -

- -
- -
37,500 56,250 31,250.00 - 429,112,500
37,500 56,250 31,250.00 - 13,725,000
37,500 56,250 31,250.00 - 13,125,000
- -
- -
- -
- -
- -
90,000 135,000 75,000.00 - 16,200,000
90,000 135,000 75,000.00 - 70,560,000
90,000 135,000 75,000.00 - 28,800,000
90,000 135,000 75,000.00 - 60,480,000
90,000 135,000 75,000.00 - 162,000,000
90,000 135,000 75,000.00 - 194,400,000
- -
90,000 135,000 75,000.00 - 10,260,000
90,000 135,000 75,000.00 - 106,470,000
90,000 135,000 75,000.00 - 15,660,000
90,000 135,000 75,000.00 - 212,760,000
- -

- -
34,650 29,550 26,256.61 - 534,724,344
34,650 29,550 26,256.61 - 481,251,910
350,000.00 35,000 30,000 26,256.61 810,188,400 81,018,840
350,000.00 35,000 30,000 26,256.61 11,900,000 1,190,000
867,850.00 35,000 30,000 26,256.61 531,124,200 21,420,000

1,500,000 35,000 8,500.00 - 209,250,000


1,500,000 35,000 8,500.00 - 232,500,000
1,500,000 35,000 8,500.00 - 4,500,000
1,500,000 35,000 8,500.00 - 6,000,000

65,000 35,000 114,422.04 - 375,180,000

-
-
2,025,000 2,250,000 1,487,486.56 - 399,395,350
2,025,000 2,250,000 1,487,486.56 - 60,750,000

11,351,000 5,250,000 5,737,448.14 - 306,477,000


11,351,000 5,250,000 5,737,448.14 - 34,053,000
- -
- -
2,140,000 5,250,000 2,468,246.92 - 6,420,000

245,142,857 52,000,000 97,141,979.17 - 245,142,857

16,082,218 5,257,600.78 - -
14,392,218 4,705,105.77 - -
16,082,218 5,257,600.78 - -
10,075,772 3,293,972.47 - -
10,075,772 3,293,972.47 - -

1,353,212,600.0 11,738,985,800.7

1,479,420,600.0 18,076,399,929.0

1,479,420,600.0 18,076,399,929.0
HARUS S
FORM NO. : 2B
DATE : 22 Agustus 2019
PROJECT : RANTAU DEDAP G P P
JOB. NO. : 18-1105
REVISION : 2 ( 22-08-2019)

TOTAL PRICE
Total Unit Price (Rp) Total Cost (Rp) Total Manhours
Direct Labor Indirect Cost for Construction

( J=AXF ) ( K=AXG ) ( L=B+C+F+G ) ( M=AXL ) ( N=AXD )

- 282,501,243 282,501,243 282,501,243.00


- 375,701,246 375,701,246 375,701,246.00
- 496,052,346 496,052,346 496,052,346.00
- 891,501,246 891,501,246 891,501,246.00
- 519,101,246 519,101,246 519,101,246.00
- 524,617,646 524,617,646.00
- 532,181,246 532,181,246 532,181,246.00
- 572,851,680 572,851,680 572,851,680.00
- 202,501,246 202,501,246 202,501,246.00

- 3,872,391,499.00 4,397,009,145.00 4,397,009,145.00


133,893,000 74,385,000 5,700,000 297,540,000.00
193,144,500 107,302,500 5,700,000 429,210,000.00
346,275,000 192,375,000 5,700,000 769,500,000.00
88,749,000 49,305,000 5,700,000 197,220,000.00
71,820,000 39,900,000 5,700,000 159,600,000.00
17,955,000 9,975,000 5,700,000 39,900,000.00
1,892,970,000.00
- - - -
- - - -
1,682,187 889,100 14,434,897 3,608,724.14
3,608,724.14
- - - -
9,969,750 5,538,750 7,500,000 22,155,000.00
2,025,000 1,125,000 7,500,000 4,500,000.00
506,250 281,250 7,500,000 1,125,000.00
27,780,000.00
- - - -
6,120,000 3,400,000 8,500,000 13,600,000.00
99,450,000 55,250,000 8,500,000 221,000,000.00
423,810,000 235,450,000 8,500,000 941,800,000.00
188,955,000 104,975,000 8,500,000 419,900,000.00
263,925,000 146,625,000 8,500,000 586,500,000.00
230,265,000 127,925,000 8,500,000 511,700,000.00
320,535,000 178,075,000 8,500,000 712,300,000.00
59,670,000 33,150,000 8,500,000 132,600,000.00
67,320,000 37,400,000 8,500,000 149,600,000.00
65,790,000 36,550,000 8,500,000 146,200,000.00
29,070,000 16,150,000 8,500,000 64,600,000.00
29,070,000 16,150,000 8,500,000 64,600,000.00
30,600,000 17,000,000 8,500,000 68,000,000.00
30,600,000 17,000,000 8,500,000 68,000,000.00
128,520,000 71,400,000 8,500,000 285,600,000.00
2,295,000 1,275,000 8,500,000 5,100,000.00
121,635,000 67,575,000 8,500,000 270,300,000.00
28,305,000 15,725,000 8,500,000 62,900,000.00
41,310,000 22,950,000 8,500,000 91,800,000.00
1,530,000 850,000 8,500,000 3,400,000.00
22,950,000 12,750,000 8,500,000 51,000,000.00
4,870,500,000.00
- - - -
107,712,000 59,840,000 6,400,000 239,360,000.00
380,160,000 211,200,000 6,400,000 844,800,000.00
34,560,000 19,200,000 6,400,000 76,800,000.00
25,344,000 14,080,000 6,400,000 56,320,000.00
4,608,000 2,560,000 6,400,000 10,240,000.00
6,336,000 3,520,000 6,400,000 14,080,000.00
24,192,000 13,440,000 6,400,000 53,760,000.00
31,680,000 17,600,000 6,400,000 70,400,000.00
1,365,760,000.00
- - - -
193,050,000 107,250,000 7,500,000 429,000,000.00
213,975,000 118,875,000 7,500,000 475,500,000.00
219,375,000 121,875,000 7,500,000 487,500,000.00
205,200,000 114,000,000 7,500,000 456,000,000.00
58,050,000 32,250,000 7,500,000 129,000,000.00
58,050,000 32,250,000 7,500,000 129,000,000.00
234,900,000 130,500,000 7,500,000 522,000,000.00
3,375,000 1,875,000 7,500,000 7,500,000.00
74,250,000 41,250,000 7,500,000 165,000,000.00
21,600,000 12,000,000 7,500,000 48,000,000.00
26,527,500 14,737,500 7,500,000 58,950,000.00
29,700,000 16,500,000 7,500,000 66,000,000.00
25,650,000 14,250,000 7,500,000 57,000,000.00
5,737,500 3,187,500 7,500,000 12,750,000.00
507,667,500 282,037,500 7,500,000 1,128,150,000.00
45,225,000 25,125,000 7,500,000 100,500,000.00
10,800,000 6,000,000 7,500,000 24,000,000.00
- - - -
4,295,850,000.00
- - 13,000,000 -
31,239,000 17,355,000 6,500,000 69,420,000.00
49,140,000 27,300,000 6,500,000 109,200,000.00
42,888,690 23,827,050 6,500,000 95,308,200.00
222,276,600 123,487,000 6,500,000 493,948,000.00
26,910,000 14,950,000 6,500,000 59,800,000.00
112,320,000 62,400,000 6,500,000 249,600,000.00
50,895,000 28,275,000 6,500,000 113,100,000.00
143,910,000 79,950,000 6,500,000 319,800,000.00
296,595,000 164,775,000 6,500,000 659,100,000.00
107,055,000 59,475,000 6,500,000 237,900,000.00
19,305,000 10,725,000 6,500,000 42,900,000.00
2,450,076,200.00
- - - -
31,590,000 17,550,000 6,500,000 70,200,000.00
47,736,000 26,520,000 6,500,000 106,080,000.00
176,280,000.00
- - - -
16,200,000 9,000,000 7,500,000 36,000,000.00
6,750,000 3,750,000 7,500,000 15,000,000.00
7,188,750 3,993,750 7,500,000 15,975,000.00
7,188,750 3,993,750 7,500,000 15,975,000.00
3,510,000 1,950,000 7,500,000 7,800,000.00
3,442,500 1,912,500 7,500,000 7,650,000.00
98,400,000.00
- - - -
96,098,400 3,296,861 6,000,000 213,552,000.00
13,365,000 7,425,000 6,000,000 29,700,000.00
1,231,200 684,000 6,000,000 2,736,000.00
- - - 245,988,000.00
- - - -
10,260,000 5,700,000 9,500,000 22,800,000.00
35,910,000 19,950,000 9,500,000 79,800,000.00
7,695,000 4,275,000 9,500,000 17,100,000.00
35,055,000 19,475,000 9,500,000 77,900,000.00
6,840,000 3,800,000 9,500,000 15,200,000.00
14,962,500 8,312,500 9,500,000 33,250,000.00
246,050,000.00
- - - -
641,250 356,250 9,500,000 1,425,000.00
1,068,750 593,750 9,500,000 2,375,000.00
641,250 356,250 9,500,000 1,425,000.00
12,376,125 6,875,625 9,500,000 27,502,500.00
18,222,615 10,123,675 9,500,000 40,494,700.00
73,222,200.00
- - - -
6,808,529 3,782,516 9,550,000 15,130,065.00
7,516,585 4,175,881 9,550,000 16,703,523.00
646,688 359,271 9,550,000 1,437,084.00
1,825,062 1,013,924 9,550,000 4,055,694.00
37,326,366.00
- - - -
369,585 205,325 9,550,000 821,300.00
825,120 458,400 9,550,000 1,833,600.00
1,439,663 799,813 9,550,000 3,199,250.00
859,500 477,500 9,550,000 1,910,000.00
7,764,150.00
- - - -
690,300,000 383,500,000 6,500,000 1,534,000,000.00
136,129,500 75,627,500 6,500,000 302,510,000.00
51,831,000 28,795,000 6,500,000 115,180,000.00
1,951,690,000.00
- - - -
31,830,750 17,683,750 7,000,000 70,735,000.00
1,575,000 875,000 7,000,000 3,500,000.00
6,300,000 3,500,000 7,000,000 14,000,000.00
88,235,000.00

25,000,000 52,307,220 212,307,220 212,307,219.55

148,095,220 355,569,837 20,617,215 1,443,205,049.89

7,108,568 3,757,149 412,154 15,249,708.40


28,613,605 20,892,398 2,735,456 84,799,134.41

1,755,561,112.25

8,233,050,941.86 4,840,297,543.23 1,046,306,941.35 19,587,061,752.39


;

33,408,070,023.13

316,800,000 176,000,000 400,000 704,000,000.00


1,774,080,000 985,600,000 400,000 3,942,400,000.00
1,451,520,000 806,400,000 400,000 3,225,600,000.00
1,261,980,000 701,100,000 400,000 2,804,400,000.00
1,032,480,000 573,600,000 400,000 2,294,400,000.00
81,000,000 45,000,000 400,000 180,000,000.00
21,600,000 12,000,000 400,000 48,000,000.00

13,198,800,000.00
- - - -
740,272,500 411,262,500 550,000 1,645,050,000.00
1,332,292,500 740,162,500 550,000 2,960,650,000.00
1,089,990,000 605,550,000 550,000 2,422,200,000.00
525,690,000 292,050,000 550,000 1,168,200,000.00
429,907,500 238,837,500 550,000 955,350,000.00
480,397,500 266,887,500 550,000 1,067,550,000.00
393,030,000 218,350,000 550,000 873,400,000.00
108,900,000 60,500,000 550,000 242,000,000.00
69,300,000 38,500,000 550,000 154,000,000.00
- - - -
- - - 11,488,400,000.00

- - - -
- - - -
643,668,750 357,593,750 125,000 1,430,375,000.00
20,587,500 11,437,500 125,000 45,750,000.00
19,687,500 10,937,500 125,000 43,750,000.00
- - - -
1,519,875,000.00
- - - -
- - - -
- - - -
- - - -
24,300,000 13,500,000 300,000 54,000,000.00
105,840,000 58,800,000 300,000 235,200,000.00
43,200,000 24,000,000 300,000 96,000,000.00
90,720,000 50,400,000 300,000 201,600,000.00
243,000,000 135,000,000 300,000 540,000,000.00
291,600,000 162,000,000 300,000 648,000,000.00
- - - -
15,390,000 8,550,000 300,000 34,200,000.00
159,705,000 88,725,000 300,000 354,900,000.00
23,490,000 13,050,000 300,000 52,200,000.00
319,140,000 177,300,000 300,000 709,200,000.00
- - - -
2,925,300,000.00
- - - -
456,020,328 405,196,203 90,457 1,395,940,875.13
410,418,295 364,676,583 90,457 1,256,346,787.62
69,444,720 60,779,430 441,257 1,021,431,390.47
1,020,000 892,725 441,257 15,002,724.73
18,360,000 16,069,045 959,107 586,973,245.18
4,275,695,023.13

4,882,500 1,185,750 1,543,500 215,318,250.00


5,425,000 1,317,500 1,543,500 239,242,500.00
105,000 25,500 1,543,500 4,630,500.00
140,000 34,000 1,543,500 6,174,000.00
465,365,250.00

202,020,000 660,444,031 214,422 1,237,644,030.88


2,174,186,177.60

781,425,000 516,604,081 5,762,487 2,001,311,580.91


67,500,000 44,624,597 5,762,487 172,874,596.68

141,750,000 154,911,100 22,338,448 603,138,099.91


15,750,000 17,212,344 22,338,448 67,015,344.43
- - - -
- - - -
15,750,000 7,404,741 9,858,247 29,574,740.77
2,873,914,362.71

52,000,000 97,141,979 394,284,836 394,284,836.31

48,246,655 15,772,802 21,339,819 64,019,457.30


129,529,965 42,345,952 19,097,324 171,875,916.84
289,479,930 94,636,814 21,339,819 384,116,743.80
181,363,888 59,291,504 13,369,744 240,655,392.66
272,045,832 88,937,257 13,369,744 360,983,088.99
1,221,650,599.58

16,272,245,863.3 9,932,597,688.6 39,600,929,102.62

24,505,296,805.1 14,772,895,231.8 59,187,990,855.01

24,505,296,805.1 18,645,286,730.8 63,585,000,000.01


HARUS SAMA DENGAN FORM 3B . 1.2
DOC. NO. : (Filled by Subcontractor Reference) FORM NO. :
BIDDER : PT.Azymuth Citra Perkasa DATE :
INQUIRY NO. : RD-PRD01-COW-CREQ-1019 PROJECT :
WORK TITLE : MECHANICAL AND PIPING WORK PACKAGE-3 JOB. NO. :
(GPP-SEPARATOR AREA - SCRUBER AREA ) REVISION :

COST SUMMARY
(COST ITEM WISE)

NO. DESCRIPTION TOTAL PR

1 Direct cost
1.1 1.1 Direct material
1.2 1.2 Direct labor
1.3 1.3 Direct construction equipment

TOTAL DIRECT COST

2 Indirect Cost
2.1 Fix Indirect Cost
2.1.1 Home office cost
2.1.2 Mobilization and demobilization for field personel/staff
2.1.3 Temporary facilities (cost, supply and demolition)
2.1.4 Salaries, wages, allowance, meals for field personel/staff
2.1.5 Field expenses
2.1.6 Insurance
2.1.7 Direct labor service cost
2.1.8 Taxes, duties and other charge (Pajak, bea dan biaya lainnya )
2.1.9 Pre financing cost

SUB TOTAL FIX INDIRECT COST

2.2 Indirect Cost for Construction


2.2.1 Mobilization & Demobilization Equipment & tools
2.2.2 Utilities consumption for construction
2.2.3 Maintenance cost for equipment
2.2.4 Consumables for Construction

SUB TOTAL INDIRECT COST FOR CONSTRUCTION


TOTAL INDIRECT COST

GRAND TOTAL
3A
22 Agustus 2019
RANTAU DEDAP G P P
18-1105
2 ( 22-08-2019)

OST SUMMARY
OST ITEM WISE)

TOTAL PRICE (Rp)

1,479,420,600.00
24,505,296,805.12
18,076,399,929.05

44,061,117,334.17

550,000,000.00
783,000,000.00
1,740,000,000.00
5,953,758,070.32
1,141,500,000.00
1,155,291,000.00
1,174,200,000.00
1,276,122,384.16
350,000,000.00

14,123,871,454.48

1,165,011,211.36

4,235,000,000.00

5,400,011,211.36
19,523,882,665.83

63,585,000,000.00
DOC. NO. : (Filled by Subcontractor Reference) FORM NO. : 3B
BIDDER NAME : PT.Azymuth Citra Perkasa DATE : 22 Agustus 2019
INQ./REQ.No. : RD-PRD01-COW-CREQ-1019 PROJECT : RANTAU DEDAP G P P
WORK TITLE : MECHANICAL AND PIPING WORK PACKAGE-3 JOB. NO. : 18-1105
(GPP-SEPARATOR AREA - SCRUBER AREA ) REVISION : 2 ( 22-08-2019)
COST BREAKDOWN
(COST ITEM WISE)

NO DESCRIPTION UNIT QUANTITY UNIT PRICE (Rp) TOTAL PRICE (Rp)

1 Direct Cost
1.1 Direct material (Material guna langsung) LS 1 1,479,420,600.00 1,479,420,600.00
1.2 Direct labor ( Tenaga kerja langsung ) LS 1 24,505,296,805.12 24,505,296,805.12
1.3 Direct construction equipment ( Peralatan konstruksi langsung ) LS 1 18,076,399,929.05 18,076,399,929.05

TOTAL DIRECT COST 44,061,117,334.17

2 Indirect cost

2.1 Fix Indirect Cost (Biaya tidak langsung Tetap )


2.1.1 Home office cost ( Biaya Kantor Pusat ) LS 1 550,000,000.00 550,000,000.00

Mobilization and demobilization Home Office - Location of Project for personel


2.1.2
( Mobilisasi dan demobilisasi Personil dari kantor pusat ke lokasi proyek)

2.1.2.1 Direct Man Power (Tenaga Kerja Lansung : Skill,Semi Skill,Operator)


LS 3,000,000.00 205 5,000,000.00 615,000,000.00
2.1.2.2 Indirect Man Power ( Tenaga Kerja Tidak Langsung ;staff ) LS 4,000,000.00 42 4,000,000.00 168,000,000.00

Temporary facilities (cost, supply and demolition)/Fasilitas sementara (biaya, pasokan


2.1.3
dan pembongkaran)
Temporary building facilities ( office,workshop,warehouse) and accessories /
2.1.3.1 LS 1
Bangunan sementara ( kantor,gudang, Bengkel) beserta fasilitas dan aksesoris.
750,000,000.00 750,000,000.00
2.1.3.2 Camp or housing ( Kamp atau perumahan ) LS 1 140,000,000.00 140,000,000.00
2.1.3.3 Temporary electrical ( Listrik sementara ) LS 1 350,000,000.00 350,000,000.00
2.1.3.4 Temporary water distribution (Distribusi air sementara ) LS 1 500,000,000.00 500,000,000.00

Salaries, wages, allowance for Indirect Man Power (Gaji, upah, tunjangan unt tenaga
2.1.4 LS 1
kerja tidak langsung ) 5,953,758,070.32 5,953,758,070.32

2.1.5 Field expenses ( Biaya lapangan ) -


2.1.5.1 Print and stationeries ( Alat Tulis Kantor ) LS 1 165,000,000.00 165,000,000.00
2.1.5.2 Communication expense ( Biaya komunikasi ) LS 1 178,500,000.00 178,500,000.00
2.1.5.3 Welfare expense (Biaya kesejahteraan) LS 1 120,000,000.00 120,000,000.00
2.1.5.4 Third parties inspection (Inspeksi pihak ketiga) LS 1 378,000,000.00 378,000,000.00
2.1.5.5 Other expenses ( Biaya lain lain ): APD LS 1 300,000,000.00 300,000,000.00

2.1.6 Insurance

2.1.6.1 Workmen's compensation, employer's liability and social insurance LS 1


(Kompensasi pekerja, tanggung jawab pemberi kerja dan asuransi sosial) 562,000,000.00 562,000,000.00
2.1.6.2 Automobile liability insurance ( Asuransi Kendaraan /alat berat ) -
2.1.6.3 Marine/cargo insurance (Asuransi kelautan / kargo ) -
2.1.6.4 Other insurance : All Risk LS 1 593,291,000.00 593,291,000.00

2.1.7 Direct labor service cost (Biaya layanan tenaga kerja langsung ) -
2.1.7.1 Welfare expense (Biaya kesejahteraan) LS 1 250,000,000.00 250,000,000.00
2.1.7.2 Recruiting expense (Biaya rekrutmen ) LS 1 179,000,000.00 179,000,000.00
2.1.7.3 Training expense (Biaya pelatihan) LS 1 150,000,000.00 150,000,000.00
2.1.7.4 Lunch service cost (Biaya makan siang ) M/D 1176 200,000.00 235,200,000.00
2.1.7.5 Other expenses ( Biaya lain lain )sebutkan. M/D 360 1,000,000.00 360,000,000.00

2.1.8 Taxes, duties and other charge (Pajak, bea dan biaya lainnya ) ls 1 1,276,122,384.16 1,276,122,384.16
2.1.8.1 Stamp duty tax (Pajak materai )
2.1.8.2 Local government tax ( Pajak pemerintah daerah)
2.1.8.3 Other duties and tax (Bea dan pajak lainnya)

2.1.9 Pre financing cost (Biaya pra pendanaan) LS 1 350,000,000.00 350,000,000.00

Sub Total Fix Indirect Cost (Sub Biaya tidak langsung Tetap) 14,123,871,454.48

2.2 Indirect Cost for Construction (Biaya Tidak Langsung untuk Konstruksi )
Mobilization & Demobilization Equipment ,vehicle,tools ( Mobilisasi dan demobilisasi
2.2.1 LS 1
Alat berat,kendaraan dan peralatan) 1,165,011,211.36 1,165,011,211.36
2.2.2 Utilities consumption for construction (Konsumsi utilitas untuk konstruksi )
2.2.2.1 Temporary electrical ( Listrik sementara ) LS 1 inc
2.2.2.2 Temporary water distribution (Distribusi air sementara ) LS 1 inc
2.2.2.3 Temporary road and drainage,( Jalan dan drainase), if necessary LS 1 inc
2.2.3 Maintenance cost for equipment (Biaya perawatan peralatan )
2.2.3.1 Maintenance cost ( Biaya perawatan ) LS 1 inc
2.2.3.2 Spare parts ( suku cadang ) LS 1 inc
2.2.4 Consumables for Construction (Perlengkapan Habis pakai untuk Konstruksi )
2.2.4.1 Consumables ( habis pakai ) LS 1 560,000,000.00 560,000,000.00
2.2.4.2 Gases ( Gas ) LS 1 845,000,000.00 845,000,000.00
2.2.4.3 Fuels and lubrications ( Bahan Bakar & Pelumas ) LS 1 1,750,000,000.00 1,750,000,000.00
2.2.4.4 Hand tool ( Perkakas tangan ) LS 1 730,000,000.00 730,000,000.00
2.2.4.5 Drinking water ( Air Minum ) LS 1 350,000,000.00 350,000,000.00
2.2.4.6 Others ( Lainnya ) sebutkan

Sub Total Indirect Cost for Construction 5,400,011,211.36


DOC. NO. : (Filled by Subcontractor Reference) FORM NO. : 3B
BIDDER NAME : PT.Azymuth Citra Perkasa DATE : 22 Agustus 2019
INQ./REQ.No. : RD-PRD01-COW-CREQ-1019 PROJECT : RANTAU DEDAP G P P
WORK TITLE : MECHANICAL AND PIPING WORK PACKAGE-3 JOB. NO. : 18-1105
(GPP-SEPARATOR AREA - SCRUBER AREA ) REVISION : 2 ( 22-08-2019)
COST BREAKDOWN
(COST ITEM WISE)

NO DESCRIPTION UNIT QUANTITY UNIT PRICE (Rp) TOTAL PRICE (Rp)

TOTAL INDIRECT COST 19,523,882,665.83

GRAND TOTAL 63,585,000,000.00


DOC.NO : (Filled by Subcontractor Reference)
BIDDER NAME : PT.Azymuth Citra Perkasa
INQ./REQ.No. : RD-PRD01-COW-CREQ-1019
WORK TITLE : MECHANICAL AND PIPING WORK PACKAGE-3
(GPP-SEPARATOR AREA - SCRUBER AREA )

SUPERVISION AND LABOR RATE

OVERTIME
REGULAR RATE PER
RATE/HOUR
NO. CLASSIFICATION DAY
NORMAL DAY
(Rp) (Rp)
A Indirect Manpower
1 SM/Construction manager 1,135,650.00 227,130.00
2 Project Control 985,650.00 197,130.00
3 Superintendent 875,950.00 175,190.00
4 Engineering 875,950.00 175,190.00
5 QA/QC Koordinatr 875,950.00 175,190.00
6 QC Inspector 487,650.00 97,530.00
7 Drafter / Doc Con 372,432.16 74,486.43
8 Supervisor 548,450.00 109,690.00
9 Material Controller & Purchaser 428,107.68 85,621.54
10 Progress Control 375,620.00 75,124.00
11 HSE Koordinator 548,450.00 109,690.00
12 Safety Officer/Man 325,450.00 65,090.00
13 Surveyor 325,450.00 65,090.00
14 Project Administrator 315,325.00 63,065.00
15 Office Boy/Girl 185,650.00 37,130.00
16 Security/Humas 225,750.00 45,150.00
17 First Aid 275,640.00 55,128.00
18 Driver 185,650.00 37,130.00

B Direct Manpower
1 Blaster 320,425.00 64,085.00
2 Electric 320,425.00 64,085.00
3 Fitter 320,425.00 64,085.00
4 Foreman 348,750.00 69,750.00
5 Helper 325,450.11 65,090.02
6 Mill wright 325,850.00 65,170.00
7 Oiler 403,030.86 80,606.17
8 Operator 425,350.00 85,070.00
9 Painter 403,030.86 80,606.17
10 painter foreman 348,750.00 69,750.00
11 Piping Foreman 348,750.00 69,750.00
12 Riger 374,507.73 74,901.55
13 Welder Foreman 348,750.00 69,750.00
14 Welder SS 443,850.00 88,770.00
15 Welder CS 486,565.00 97,313.00
16 Mechanic 403,030.86 80,606.17
17 Scaffolder 374,507.73 74,901.55

TOTAL MANMONTHS

Keterangan:
1. Jam kerja normal adalah 10 jam tiap hari,25 hari /bulan
2. Isi posisi yang dirasa perlu untuk pekerjaan saja
3. Tambahkan jika ada posisi yang kurang dan hapus jika ada posisi yang tidak diperlukan
4. Direct Man rate tidak termasuk biaya lembur, makan siang,kesejehteraan,pelatihan,rekruitmen
5. Indirect Man rate sudah termasuk Gaji, biaya lembur, makan siang,tunjangan kesejehteraan
FORM NO. : 4
DATE : 22 Agustus 2019
PROJECT : RANTAU DEDAP G P P
JOB. NO. : 18-1105
REVISION : 2 ( 22-08-2019)

RVISION AND LABOR RATE

OVERTIME OVERTIME
RATE/HOUR RATE/HOUR
NORMAL DAY HOLIDAY/SUNDAY
(Rp) (Rp)

227,130.00 454,260.00
197,130.00 394,260.00
175,190.00 350,380.00
175,190.00 350,380.00
175,190.00 350,380.00
97,530.00 195,060.00
74,486.43 148,972.86
109,690.00 219,380.00
85,621.54 171,243.07
75,124.00 150,248.00
109,690.00 219,380.00
65,090.00 130,180.00
65,090.00 130,180.00
63,065.00 126,130.00
37,130.00 74,260.00
45,150.00 90,300.00
55,128.00 110,256.00
37,130.00 74,260.00
###

64,085.00 128,170.00
64,085.00 128,170.00
64,085.00 128,170.00
69,750.00 139,500.00
65,090.02 130,180.05
65,170.00 130,340.00
80,606.17 161,212.35
85,070.00 170,140.00
80,606.17 161,212.35
69,750.00 139,500.00
69,750.00 139,500.00
74,901.55 149,803.09
69,750.00 139,500.00
88,770.00 177,540.00
97,313.00 194,626.00
80,606.17 161,212.35
74,901.55 149,803.09

###

###
DOC.NO : (Filled by Subcontractor Reference)
BIDDER NAME : PT.Azymuth Citra Perkasa
INQ./REQ.No. : RD-PRD01-COW-CREQ-1019
WORK TITLE : MECHANICAL AND PIPING WORK PACKAGE-3
(GPP-SEPARATOR AREA - SCRUBER AREA )

SUB CONTRACTOR'S DIRECT MANPOWER SCHEDULE

MAN- Month
NO. DESCRIPTION
MONTH -1 0 1 2 3 4 5 6 7 8 9
Mecanical Installation
1 Operator 1 40 4 4 6 6 6 6 4 4
2 Rigger 60 6 8 8 8 8 8 8 6
3 Mill Wright 40 4 4 6 6 6 6 4 4
4 Helper 72 8 8 10 10 10 10 8 8
5 Mechanic 8 1 1 1 1 1 1 1 1
6 Oiler 16 2 2 2 2 2 2 2 2
7 Electrician 16 2 2 2 2 2 2 2 2
8 Scaffolder 40 4 4 6 6 6 6 4 4
9 Helper Scaffolder 32 4 4 4 4 4 4 4 4

Piping Installation
1 Piping Foreman 28 2 4 4 4 4 4 4 2
2 Pipe Fitter 1 121 6 10 18 18 18 18 18 15
3 Helper 121 6 10 18 18 18 18 18 15
4 Welder Foreman 16 2 2 2 2 2 2 2 2
5 Welder CS 141 8 10 22 22 22 22 20 15
6 Welder SUS 100 8 10 16 16 16 16 10 8
7 Helper Welder 111 4 10 18 18 18 18 15 10

Fabrikasi & Install FRP & HDPE


1 Foreman 12 2 2 2 2 2 2
2 Pipe Fitter 1 42 6 8 8 8 6 6
3 Helper 42 6 8 8 8 6 6

Blasting & Painting


1 Foreman 5 1 1 1 1 1
2 Blaster 13 2 3 3 3 2
3 Painter 10 2 2 2 2 2
4 Helper 16 2 4 4 4 2

Fabrikasi & Install Pipe Support


1 Piping Foreman 6 1 1 1 1 1 1
2 Fitter 20 2 4 4 4 4 2
3 Helper 20 2 4 4 4 4 2
4 Welder CS 24 4 4 4 4 4 4
5 Helper Welder 24 4 4 4 4 4 4

Pre commisioing
1 Supervisor 3 1
2 Foreman 3 1
3 Welder CS 6 2
4 Fitter 6 2
5 Foreman 1
6 Mill Wright 4
7 Welder SS 1
8 Welder CS 1
9 Helper 8

TOTAL MANMONTHS 1229


TOTAL Direct 1229 71 113 184 188 188 185 151 116 6
TOTAL InDirect 430 34 36 39 42 42 42 42 42 41
Grand Total Direct + Indirect 1659 105 149 223 230 230 227 193 158 47

Keterangan:
1. Jam kerja normal adalah 10 jam tiap hari,25 hari kerja /bulan
2. Isi posisi yang dirasa perlu untuk pekerjaan saja
3. Tambahkan jika ada posisi yang kurang dan hapus jika ada posisi yang tidak diperlukan
FORM NO. : 5
DATE : 22 Agustus 2019
PROJECT : RANTAU DEDAP G P P
JOB. NO. : 18-1105
REVISION : 2 ( 22-08-2019)

DIRECT MANPOWER SCHEDULE

Month
REMARK
10 11 12 13 14
1 1
1 1
2 2
2 2
1
4
1
1
8

6 21
36 34

42 55
DOC.NO :
BIDDER NAME : PT.Azymuth Citra Perkasa
INQ./REQ.No. : RD-PRD01-COW-CREQ-1019
WORK TITLE : MECHANICAL AND PIPING WORK PACKAGE-3
(GPP-SEPARATOR AREA - SCRUBER AREA )

SUB CONTRACTOR'S INDIRECT MANPOWER SCHEDULE

MAN Month
NO. DESCRIPTION
-MONTH -1 0 1 2 3 4 5 6 7 8 9 10
1 SM/Construction Manager 11 1 1 1 1 1 1 1 1 1 1
2 Project Control 11 1 1 1 1 1 1 1 1 1 1
3 Superintendent 22 2 2 2 2 2 2 2 2 2 2
4 QA/QC Koordinator 11 1 1 1 1 1 1 1 1 1 1
5 QC Inspector 38 2 3 4 4 4 4 4 4 4 3
6 Engineering 33 3 3 3 3 3 3 3 3 3 3
7 Drafter / Doc Con 33 3 3 3 3 3 3 3 3 3 3
8 Supervisor 37 2 2 3 4 4 4 4 4 4 3
9 Material Controller & Purchaser 19 2 2 2 2 2 2 2 2 1 1
10 HSE Koordinator 11 1 1 1 1 1 1 1 1 1 1
11 Safety Officer/Man 28 2 2 2 3 3 3 3 3 3 2
12 Progress Control 11 1 1 1 1 1 1 1 1 1 1
13 Surveyor 11 1 1 1 1 1 1 1 1 1 1
14 Project Administrator 22 2 2 2 2 2 2 2 2 2 2
15 Office Boy/Girl 22 2 2 2 2 2 2 2 2 2 2
16 Security/Humas 37 2 3 3 4 4 4 4 4 4 3
17 First Aid 22 2 2 2 2 2 2 2 2 2 2
18 Driver 51 4 4 5 5 5 5 5 5 5 4

TOTAL MANMONTHS
430 34 36 39 42 42 42 42 42 41 36
Keterangan:
Jam kerja normal adalah 10 jam tiap hari,25 hari / bulan
Isi posisi yang dirasa perlu untuk pekerjaan saja
Tambahkan jika ada posisi yang kurang dan hapus jika ada posisi yang tidak diperlukan
FORM NO. :6
DATE : 22 Agustus 2019
PROJECT : RANTAU DEDAP G P P
JOB. NO. : 18-1105
REVISON : 2 ( 22-08-2019)

DIRECT MANPOWER SCHEDULE

Month
REMARK
11 12 13 14
1
1
2
1
2
3
3
3
1
1
2
1
1
2
2
2
2
4

34
DOC.NO : (Filled by Subcontractor Reference)
BIDDER NAME : PT.Azymuth Citra Perkasa
INQ./REQ.No. : RD-PRD01-COW-CREQ-1019
WORK TITLE : MECHANICAL AND PIPING WORK PACKAGE-3
(GPP-SEPARATOR AREA - SCRUBER AREA )

LIST AND SCHEDULE OF


CONSTRUCTION EQUIPMENT AND VEHICLES

NO. DESCRIPTION TYPE PROPERTY/ MACHINE Month


CAP LOCATION MONTH -1 0 1 2 3 4 5 6
Mecanical
1 Crawler Crane 250 Ton 250 Ton 2 1 1
2 Mobile Crane 80 Ton 80 Ton 6 1 1 1 1 1
3 Mobile Crane 50 Ton 50 Ton 6 1 1 1 1 1
4 Mobile Crane 25 Ton 25 Ton 11 1 1 1 1 1 1
5 Electric Winch 3 Ton 3 ton 14 2 2 2 2 2
6 Air Compressor 175 cfm 175 CFM 8 1 1 1 1 1 1
7 Air Compressor 350 cfm 350 CFM 8 1 1 1 1 1 1
8 Diesel Generator 250kVA 250 KVA 24 2 2 3 3 3 3
9 HT Pump 7 1 1 1 1 1
10 Water Filling Pump 7 1 1 1 1 1
11 Strand Jack (4 nos @ 40 Ton) 7 1 1 1 1 1
12 Forklift 11 1 1 1 1 1 1
13 Excavator PC200 + Hook PC200 6 1 1 1 1 1 1
14 Dump Truck 10 m3 12 2 2 2 2 2 2
15 Compactor Roller 2.5 ton 6 1 1 1 1 1 1

Piping
1 Welding Machine 320 10 20 40 40 40 40
2 Rectifier 41 2 5 6 6 6 6
3 Handtools and Others 434 3 41 66 73 73 69
4 Diesel Engine 80 Kva 39 2 2 4 6 6 6
5 Scaffolding 11 1 1 1 1 1 1

Transport
1 ELF 21 1 2 2 2 2 2
2 Pick up ( 4 WD ) 22 2 2 2 2 2 2
3 Trailer 11 1 1 1 1 1 1
4 Uni Crane 5T 11 1 1 1 1 1 1
5 Mobile Tranport ( 4 WD ) 22 2 2 2 2 2 2
6 Mobile Ambulance 11 1 1 1 1 1 1

TOTAL MCHMONTHS
36 95 144 154 154 149
LEGEND :

Keterangan:
Jam kerja normal adalah 10 jam tiap hari
Isi nama peralatan yang dirasa perlu untuk pekerjaan saja
Tambahkan jika ada nama peralatan yang belum terdaftar dan hapus jika ada nama peralatan yang tidak diperlukan
FORM NO. : 13
DATE : 30 December 1899
PROJECT : RANTAU DEDAP G P P
JOB. NO. : 18-1105
REVISION : 2 ( 22-08-2019)

CHEDULE OF
PMENT AND VEHICLES

Month REMARK
7 8 9 10 11 12 13 14

1
1
1 1 1 1 1
2 2
1 1
1 1
3 2 1 1 1
1 1
1 1
1 1
1 1 1 1 1

40 40 35 10 5
6 4
67 24 6 6 6
6 3 2 1 1
1 1 1 1 1

2 2 2 2 2
2 2 2 2 2
1 1 1 1 1
1 1 1 1 1
2 2 2 2 2
1 1 1 1 1

143 92 56 30 25
DOC.NO : (Filled by Subcontractor Reference)
BIDDER NAME : PT.Azymuth Citra Perkasa
INQ./REQ.No. : RD-PRD01-COW-CREQ-1019
WORK TITLE : MECHANICAL AND PIPING WORK PACKAGE-3
(GPP-SEPARATOR AREA - SCRUBER AREA )

CONSTRUCTION EQUIPMENT AND VEHICLES RATE

NO DESCRIPTION SPECIFICATION OWNED RENTAL LOCATION

1 Crawler Crane 250 Ton Rental Jakarta


2 Mobile Crane 80 Ton Rental Jakarta
3 Mobile Crane 50 Ton Rental Jakarta
4 Mobile Crane 25 Ton Rental Jakarta
5 Electric Winch 3 Ton Rental Jakarta
6 Air Compressor 175 cfm Rental Jakarta
7 Air Compressor 350 cfm Rental Jakarta
8 Diesel Generator 250kVA Rental Jakarta
9 HT Pump Rental Jakarta
10 Water Filling Pump Rental Jakarta
11 Strand Jack (4 nos @ 40 Ton) Rental Jakarta
12 Forklift Rental Jakarta
13 Excavator PC200 + Hook Rental Palembang
14 Dump Truck Rental Palembang
15 Compactor Roller Rental Palembang

16 Welding Machine Rental Jakarta


17 Rectifier Rental Jakarta
18 Handtools and Others Rental Jakarta
19 Diesel Engine 80 Kva Rental Jakarta
20 Scaffolding Rental Jakarta

21 ELF Rental Jakarta


22 Pick up ( 4 WD ) Rental Jakarta
23 Trailer Rental Jakarta
24 Uni Crane 5T Rental Jakarta
25 Mobile Operasional ( 4 WD ) Rental Jakarta
25 Ambulance Rental Jakarta

TOTAL

NOTE : Equipment rate tidak termasuk operator cost, fuel cost and maintenance cost

Keterangan:
Jam kerja normal adalah 10 jam tiap hari,25 hari /bulan Total Equipment Month x Rate
Isi nama peralatan yang dirasa perlu untuk pekerjaan saja dengan form 3B
Tambahkan jika ada nama peralatan yang belum terdaftar dan hapus jika ada nama peralatan yang tidak diperlukan
FORM NO. : 13A
DATE : 22 Agustus 2019
PROJECT : RANTAU DEDAP G P P
JOB. NO. : 18-1105
REVISION : 2 ( 22-08-2019)

ICLES RATE

RATE RATE
(Rp) (Rp/MONTH)
2,718,269.23 706,750,000.00 684,250,000.00 22,500,000.00 706,750,000.00
1,280,769.23 333,000,000.00 310,500,000.00 22,500,000.00 333,000,000.00
834,615.38 217,000,000.00 203,000,000.00 14,000,000.00 217,000,000.00
384,615.38 100,000,000.00 86,000,000.00 14,000,000.00 100,000,000.00
192,307.69 50,000,000.00 700,000,000.00
173,076.92 45,000,000.00 360,000,000.00
42,307.69 11,000,000.00 88,000,000.00
250,000.00 65,000,000.00 1,560,000,000.00
230,769.23 60,000,000.00 420,000,000.00
151,923.08 39,500,000.00 276,500,000.00
57,692.31 15,000,000.00 105,000,000.00
48,520.03 12,615,207.37 138,767,281.11
250,000.00 65,000,000.00 390,000,000.00
96,153.85 25,000,000.00 300,000,000.00
173,076.92 45,000,000.00 270,000,000.00

28,846.15 7,500,000.00 2,400,000,000.00


96,153.85 25,000,000.00 1,025,000,000.00
57,692.31 15,000,000.00 6,510,000,000.00
576,923.08 150,000,000.00 5,850,000,000.00
173,076.92 45,000,000.00 495,000,000.00

134,615.38 35,000,000.00 735,000,000.00


96,153.85 25,000,000.00 550,000,000.00
211,538.46 55,000,000.00 605,000,000.00
134,615.38 35,000,000.00 385,000,000.00
96,153.85 25,000,000.00 550,000,000.00
115,384.62 30,000,000.00 330,000,000.00

25,327,017,281.11

Total Equipment Month x Rate Month ,harus sama


dengan form 3B.1.3
DOC.NO :
BIDDER NAME : PT.Azymuth Citra Perkasa
INQ./REQ.No. : RD-PRD01-COW-CREQ-1019
WORK TITLE : MECHANICAL AND PIPING WORK PACKAGE-3
(GPP-SEPARATOR AREA - SCRUBER AREA )

DETAIL CONSTRUCTION SCHEDULE

NO. DESCRIPTION Month


-1 0 1 2 3 4 5 6 7 8 9 10 11
1 PREPARATORY WORK
1.1 Mobilization
1.2 Temporary Site Facilities (office, shop, etc)
1.3 Equipment & Tools (inspection & ready)
1.4 Manpower (recruitment, test, placement)

Mohon merefer kpd Schedule yg diberikan Rekind (11


1.5 Consumable material (purchasing, storing)
1.6 Demobilization

2
2.1
PERMANENT WORK didevelop lebih detail menjadi level 4 atau 5( lihat f
2.2
2.3
2.4
2.5
2.6
2.7
LEGEND :

Note:
FORM NO. : 14
DATE : 22 Agustus 2019
PROJECT : RANTAU DEDAP G P P
JOB. NO. : 18-1105
REVISION : 2 ( 22-08-2019)

NSTRUCTION SCHEDULE

Month REMARK
12 13 14

e yg diberikan Rekind (11 bulan) dan


njadi level 4 atau 5( lihat form 14.1)
DOC. NO. :
BIDDER : PT.Azymuth Citra Perkasa
INQUIRY N: RD-PRD01-COW-CREQ-1019
WORK TIT: Requisition for Mechanical Work (GPP and Separator Area) and Piping Work Package-3 (GPP and Scrubber Area)

CONSTRUCTION SCHEDULE
MECHANICAL AND PIPING WORK PACKAGE-3

M16 (Aug 19) M17 (Sep 19) M18 (Oct 19) M19 (Nov 19) M20 (Dec 19) M21 (Jan 20)
QTY
No. Description Wight (Ton) M0 M1 M2 M3 M4 M5
DB w1 w2 w3 w4 w1 w2 w3 w4 w1 w2 w3 w4 w1 w2 w3 w4 w1 w2 w3 w4 w1 w2

1 Mobilization / Preparation Lot

2 Equipment Installation
Steam Separator & Scrubber 332.10

Brine and Condensate Mixing and Reinjection System 0.25

Thermal Ponds and Drains 3.70

Steam Turbine and Auxiliaries 573.00

Generator and Auxiliaries 213.40

Condensing and Gas Extraction -

Main Cooling Water System 376.93

Auxiliary Cooling Water System 27.12

Compressed Air 13.12

Lifting Equipment 41.00


Chemical Treatment System 25.90

Utility Water System 7.71

Fire Water System & Fire Protection System 0.81

Power Transformer 300.26

Emergency Service System 12.61

3 Punchlist and Punchkilling (Mechanical Work) Lot

4 Underground Pipe Installation 9,751.00


Fab&Instal NDT, including Line Check, Punchlist, and Hydrotest

5 Aboveground Pipe Installation 66,044.00


Fab&Instal NDT, including Line Check, Punchlist, and Hydrotest

6 Pipe Suppot 302.00


Fabrication,Painting & Installation

7 Precommissioning (Mechanical and Piping Work) 410.00

Note: Subcontractor to follow Contractor schedule to achieve completion of Mechanical and Piping Work
FORM NO. : 14
DATE : 08 Agustus 2019
PROJECT : RANTAU DEDAP GPP
JOB. NO. : 18-1105
REVISION : 0

1 (Jan 20) M22 (Feb 20) M23 (Mar 20) M24 (Apr 20) M25 (May 20) M26 (Jun 20) M27 (Jul 20)

M5 M6 M7 M8 M9 M10 M11
w3 w4 w1 w2 w3 w4 w1 w2 w3 w4 w1 w2 w3 w4 w1 w2 w3 w4 w1 w2 w3 w4 w1 w2 w3 w4
DOC. NO. :
BIDDER : PT.Azymuth Citra Perkasa
INQUIRY NO. : RD-PRD01-COW-CREQ-1019
WORK TITLE : Requisition for Mechanical Work (GPP and Separator Area) and Piping Work Package-3 (GPP and Scrubber Area)

CONSTRU
MECHANICAL AND

Sprcification QTY
Dimension Per Unit (mm) QTY
No. Description Weight (each) kg Wight (Ton)
LxWxH or ØxH (ea)
DB

1 Mobilization / Preparation Lot

2 Equipment Installation
2 . 1 Steam Separator & Scrubber 332.10
2 . 1 1 Anti Surge Tank 16700 x 4000 x 4050 52,200 1 52,200
2 . 1 2 HP Separator 18300 x 4000 x 4050 75,300 1 75,300
2 . 1 3 LP Separator 18300 x 4000 x 4050 67,500 2 67,500
2 . 1 4 HP Scrubber 13590 x 2470 x 2470 17,300 2 17,300
2 . 1 5 LP Scrubber 11450 x 2200 x 2200 14,000 2 14,000
2 . 1 6 Flash Vessel 3900 x 1800 x 1800 3,500 2 3,500

2 . 2 Brine and Condensate Mixing and Reinjection System 0.25


2 . 2 1 ###
Wellpad E Reinjection Pump 250 1 0.25

2 . 3 Thermal Ponds and Drains 3.70


2 . 3 1 CPI Separator 2692 x 2344 x 3175 2,954 1 2.95
2 . 3 2 HWP Pit Sump Pump 770 x 340 x 768 150 4 0.60
2 . 3 3 Oily Water Pump 770 x 340 x 769 150 1 0.15

2 . 4 Steam Turbine and Auxiliaries 573.00


2 . 4 1 Sub-Sole Plate 1000 x 900 x 650 800 2 1.60
2 . 4 2 Sole Plate and Anchor Bolts 3300 x 3200 x 1900 13,000 2 26.00
2 . 4 3 Turbine Rotor 8300 x 3200 x 3300 55,400 2 110.80
2 . 4 4 Casing Upper Front 3300 x 6000 x 2750 24,700 2 49.40
2 . 4 5 Casing Upper Rear 4200 x 6000 x 2750 34,500 2 69.00
2 . 4 6 Casing Lower Front 3600 x 6300 x 2750 30,100 2 60.20
2 . 4 7 Casing Lower Rear 4500 x 6300 x 2750 41,900 2 83.80
2 . 4 8 Bearing Pedestal Front 2400 x 2300 x 2000 7,800 2 15.60
2 . 4 9 Bearing Pedestal Rear 2000 x 2300 x 3400 8,800 2 17.60
2 . 4 10 Turbine Miscellaneous Parts 8,600 2 17.20
2 . 4 11 HP Steam Stop Valve (L&R) 2600 x 900 1,900 4 7.60
2 . 4 12 HP Steam Control Valve (L&R) 2600 x 900 1,900 4 7.60
2 . 4 13 LP Steam Stop Valve (L&R) 2600 x 1000 2,000 4 8.00
2 . 4 14 LP Steam Control Valve (L&R) 2600 x 1000 2,000 4 8.00
2 . 4 15 HP/LP Steam Strainer (L&R) 2450 x 1850 x 3250 4,200 8 33.60
2 . 4 16 Gland Steam Control Valve 800 x 1250 300 2 0.60
2 . 4 17 Lube Oil Console 5900 x 3800 x 3900 15,900 2 31.80
2 . 4 18 Control Oil Console 3400 x 2300 x 2400 3,700 2 7.40
2 . 4 19 Lube Oil Cooler 3400 x 1000 x 2400 2,700 4 10.80
2 . 4 20 Turbine Washing Pump 1720 x 470 x 480 200 2 0.40
2 . 4 21 Clean & Dirty Lube Oil Tank, include accessories 6000 x 2200 x 2400 3,000 2 6.00

2 . 5 Generator and Auxiliaries 213.40


2 . 5 1 Generator Rotor 1350 x 8400 18,700 2 37.40
2 . 5 2 Generator Stator 3600 x 3500 x 3800 66,000 2 132.00
2 . 5 3 Bearing Stand, Metal & Packing Ring 1600 x 1500 x 1400 3,000 4 12.00
2 . 5 4 Bed Plate, Anchor Plate and Founadrion Bolt 3600 x 2100 x 900 4,400 2 8.80
2 . 5 5 Generator Sub-Sole Plate 1100 x 800 x 750 800 2 1.60
2 . 5 6 Fan Guide, Air Shield, Air Duct 2400 x 2300 x 1400 1,100 2 2.20
2 . 5 7 Air Cooler 4400x1300x900 1,400 6 8.40
2 . 5 8 Generator Miscellaneous Parts 5,500 2 11.00

2 . 6 Condensing and Gas Extraction 572.78


2 . 6 1 Condenser Lower Shell 1 6800 x 5000 x 4800 28,600 2 57.20
2 . 6 2 Condenser Lower Shell 2 6800 x 4800 x 4800 31,700 2 63.40
2 . 6 3 Condenser Lower Shell 3 6800 x 4800 x 4800 32,500 2 65.00
2 . 6 4 Condenser Lower Shell 4 6800 x5000 x 4800 30,400 2 60.80
2 . 6 5 Condenser Upper Shell 1 6400 x 3500 x 2300 8,600 2 17.20
2 . 6 6 Condenser Upper Shell 2 6400 x 3500 x 2300 8,600 2 17.20
2 . 6 7 Turbine Exhaust Connection 5300 x 2700 x 2700 17,400 4 69.60
2 . 6 8 Gas Outlet Pipe 1700 x 1700 x 900 250 4 1.00
2 . 6 9 Hotwell 4000 x 3500 11,000 2 22.00
2 . 6 10 Condenser parts (sole plate, etc.) 3,200 2 6.40
2 . 6 11 Steam Ejector 900 x 7550 x 1100 1,310 6 7.86
2 . 6 12 Intercondenser 7030 x 1900 x 1900 4,400 2 8.80
2 . 6 13 After Condenser 2240 x 6720 x 2510 3,800 2 7.60
2 . 6 14 Back-up Ejector 700 x 5060 x 900 850 2 1.70
2 . 6 15 Vacuum Pump 3520 x 10300 x 3300 37,605 4 150.42
2 . 6 16 Separator Tank 4320 x 2660 3,350 4 13.40
2 . 6 17 Sump Pump 870 x 690 x 1030 400 8 3.20

2 . 7 Main Cooling Water System 376.93


2 . 7 1 . Cooling Tower Fan 5400 x 1760 x 840 890 12 10.68
2 . 7 2 Cooling Tower Motor 20000 x 13000 x 12000 1,400 12 16.80
2 . 7 3 Cooling Tower Gearbox 1040 x 1420 x 1190 1,222 12 14.66
2 . 7 4 Cooling Tower Accessories 37,996 2 75.99
2 . 7 5 Intake Screen 4100 x 3600 x 1880 2,300 4 9.20
2 . 7 6 HWP Barrel Case 5000 x3100 x 3610 9,600 4 38.40
2 . 7 7 HWP Base 3200 x 3070 x 830 2,900 6 17.40
2 . 7 8 HWP Discharge Elbow 2850 x 2680 x 2910 8,200 6 49.20
2 . 7 9 HWP Motor 3500 x 4400 x 2500 16,900 6 101.40
2 . 7 10 HWP Unit 5750 x 1900 x 2060 6,100 6 36.60
2 . 7 11 HWP Accessories 1,100 6 6.60

2 . 8 Auxiliary Cooling Water System 27.12


2 . 8 1 Auxiliary Cooling Water Pump, include accessories 2960 x 1430 x 1620 2,700 4 10.80
2 . 8 2 Primary Secondary Water Heat Exchanger 1600 x 1250 x 1840 4,080 4 16.32

2 . 9 Compressed Air 13.12


2 . 9 1 Air Compressor skid 2600 x 1200 x 1700 1,600 3 4.80
2 . 9 2 Air Dryer skid 930 x 440 x 1400 1,000 2 2.00
2 . 9 3 Power Plant Air Receiver A 1470 x 4525 2,130 1 2.13
2 . 9 4 Power Plant Air Receiver B 1470 x 4525 2,130 1 2.13
2 . 9 5 Separator Station Air Receiver 1112 x 3833 1,040 1 1.04
2 . 9 6 Vent Station Air receiver 1112 x 3733 1,020 1 1.02

2 . 10 Lifting Equipment 41.00


2 . 10 1 OH Crane Workshop Building See Detail Drawing 35,592 1 35.59
2 . 10 2 Turbine Generator OH Crane See Detail Drawing 4,950 1 4.95
2 . 10 3 Hoist for lifting intake screen See Detail Drawing 228 2 0.46

2 . 11 Chemical Treatment System 25.90


2 . 11 1 Acid Dosing Pump 1500 x 800 x 700 600 4 2.40
2 . 11 2 NaOH Dilution Tank LxWxH 4,200 2 8.40
2 . 11 3 Biocide Tank LxWxH 900 2 1.80
2 . 11 4 Biocide and NaOH Dosing Skid LxWxH 4,100 2 8.20
2 . 11 5 Accessories 800 2 1.60
2 . 11 6 Acid Dosing System LxWxH 3,500 1 3.50
.
2 . 12 Utility Water System 7.71
2 . 12 1 Utility Water Supply Pump LxWxH 150 1 0.15
2 . 12 2 Utility Water Distribution Pump LxWxH 250 1 0.25
2 . 12 3 Backwash Pump LxWxH 150 1 0.15
2 . 12 4 Fresh Water Storage Tank 3862 x 3480 2,895 1 2.90
2 . 12 5 Water Treatment System, UV filter, include accessories 4000 x 2000 x 4080 4,263 1 4.26
.
2 . 13 Fire Water System & Fire Protection System 4.72
2 . 13 1 ElectricEngine
Diesel DrivenDriven
Fire Fighting Main Pump
Fire Fighting 2700 x 890 x 2040
Backup Pump, include accessories 1,584 1 1.58
2 . 13 2 3050 x 1050 x 1700 1,749 1 1.75
2 . 13 3 Fire Water Jockey Pump 1100 x 300 x 1320 150 1 0.15
2 . 13 4 Diesel Engine Fuel Tank 1000 x 1000 x 1800 425 1 0.42

2 . 13 1 Deluge Valve 2" 478 x 283 x 660 43 2 0.09


2 . 13 2 Deluge Valve 3" 478 x 283 x 661 48 4 0.19
2 . 13 3 Deluge Valve 4" 491 x 372 x 675 67 5 0.34
2 . 13 4 Deluge Valve 6" 550 x 514 x 720 100 2 0.20

2 . 14 Power Transformer 300.26


2 . 14 1 Generator Transformer 118,000 2 236.00
2 . 14 2 Unit Auxiliary Transformer 23,270 2 46.54
2 . 14 3 Unit Service Transformer 8,860 2 17.72

2 . 15 Emergency Service System 12.61


2 . 15 1 Emergency Diesel Generator 10,105 1 10.11
2 . 15 2 EDG Local Control Panel 500 1 0.50
2 . 15 3 Diesel Fuel Daily Tank 2,000 1 2.00

3 Punchlist and Punchkilling (Mechanical Work) Lot

4 Underground Pipe Installation


Fab&Instal NDT, including Line Check, Punchlist, and Hydrotest
FRP 18" as Procedure dia-inch 180.0
FRP 28" as Procedure dia-inch 784.0
FRP 40" as Procedure dia-inch 320.0
FRP 48" as Procedure dia-inch 672.0
FRP 60" as Procedure dia-inch 1,800.0
FRP 72" as Procedure dia-inch 2,160.0

HDPE 3" Buttweld joint dia-inch 114.0


HDPE 4" Buttweld joint dia-inch 1,183.0
HDPE 6" Buttweld joint dia-inch 174.0
HDPE 8" Buttweld joint dia-inch 2,364.0
5 Aboveground Pipe Installation 9,751.00
Fab&Instal NDT, including Line Check, Punchlist, and Hydrotest
Carbon steel # 150 0,5" - 1,5" Shop/Field dia-inch 1,760
Carbon steel # 150 2" - 24" Shop dia-inch 9,856
Carbon steel # 150 2" - 24" Field dia-inch 8,064
Carbon steel # 150 26" - 48" Shop dia-inch 7,011
Carbon steel # 150 26" - 48" Field dia-inch 5,736
Carbon steel # 300 0,5" - 8" Shop/Field dia-inch 450
CS # 600 - #1500 0,5" - 4" Shop/Field dia-inch 120

SS-304/316 #150 0,5" - 1,5" Shop/Field dia-inch 2,991


SS-304/316 #150 2" - 24" Shop dia-inch 5,383
SS-304/316 #150 2" - 24" Field dia-inch 4,404
SS-304/316 #150 26" - 48" Shop dia-inch 2,124
SS-304/316 #150 26" - 48" Field dia-inch 1,737
SS-304/316 #150 50" and Over Shop dia-inch 1,941
SS-304/316 #150 50" and Over Field dia-inch 1,588
SS-304/316 #300 0,5" - 4" Shop/Field dia-inch 440
SS-304/316 #600 - #1500 0,5" - 3" Shop/Field dia-inch 280

FRP All size Shop/Field dia-inch 11,443


PVC All size Shop/Field dia-inch 366
Threaded joint (All Material) All size Field dia-inch 350

6 Pipe Suppot 302.00


Fabrication,Painting & Installation
Fit up
Welding
Blasting & Painting
Installation

7 Precommissioning (Mechanical and Piping Work) 410.00

Note: Subcontractor to follow Contractor schedule to achieve completion of Mechanical and Piping Work
FORM NO. : 14
DATE : 08 Agustu
PROJECT : RANTAU D
JOB. NO. : 18-1105
REVISION : 0

CONSTRUCTION SCHEDULE
NICAL AND PIPING WORK PACKAGE-3
M16 (Aug 19) M17 (Sep 19) M18 (Oct 19) M19 (Nov 19) M20 (Dec 19) M21 (Jan 20) M22 (Feb 20) M23 (Mar 20) M24 (Apr 20) M25 (Ma

Duration M0 M1 M2 M3 M4 M5 M6 M7 M8 M9
w1 w2 w3 w4 w1 w2 w3 w4 w1 w2 w3 w4 w1 w2 w3 w4 w1 w2 w3 w4 w1 w2 w3 w4 w1 w2 w3 w4 w1 w2 w3 w4 w1 w2 w3 w4 w1

20
5
5
5
2
2
1

2
2

6
2
2
2

29
1
2
4
2
2
2
2
1
1
1
1
1
1
1
1
1
1
1
1
1
1

18
4
4
3
1
1
1
2
2

27
2
2
2
2
2
2
2
1
2
1
1
1
1
1
2
1
2

22
2
2
2
2
2
2
2
2
2
2
2

3
2
1

6
1
1
1
1
1
1

7
3
2
2

12
3
2
2
2
2
1

6
1
1
1
1
2

8
1
1
1
1

1
1
1
1

3
1
1
1

6
2
2
2
14
08 Agustus 2019
RANTAU DEDAP GPP
18-1105

M25 (May 20) M26 (Jun 20) M27 (Jul 20)

M9 M10 M11
w2 w3 w4 w1 w2 w3 w4 w1 w2 w3 w4
MECHANICAL AND PIPING WORK PACKAGE-3
(GPP-SEPARATOR AREA - SCRUBER AREA )

Persiapan dan Tahapan Aktifitas Pengangkatan

A . Data tekhnis Gambar Obyek


1 . Berat Obyek yang akan di angkat (Ton)
2 . Dimensi Panjang x Lebar x Tinggi
3 . Posisi dan Quantity Lifthing, Pad eye pada jarak yang telah di tentukan
4 . Data COG atau kalkulasi data COG

B . Data Gambar General Arangement Lokasi Pengangkatan


1 . Posisi Laydown Area obyek
2 . Route/jarak pengangkatan dari point A ke Point B
3 . Pastikan Route Pengankatan tidak ada gangguan
4 . Pastikan Bearing kapasiti untuk Route pengankatyan jalur crawler crane sudah aman
tiak amblas pada saat di lalui
5 . Berapa Ketinggian yang akan di angkat

C. Memilih alat Angkat/ Crawler Crane dan Lifting Gear


1 . Kapasitas Crane harus sesuai dengan beban obyek yang akan di angkat
2 . Tentukan panjang Boom Crane dan Radius Pengankatan harus sesuai dengan berat obyek
( Lihat pada tabel Load Chart Crane )
3 . Menentukan Lifting Gear (Sachkle, Wire Sling, Speder Bar ) jika diperlukan
yang akan di gunakan sesuai dengan berat obyek
4 . Semua Lifting Gear Crane dan SIO Operator harus Valid Sertifikat

D . Perhitungan dan Gambar Pengangkatan Obyek


1 . Berat Obyek
2 . Kapasitas Lifting Pad eyes
3 . Kapasitas Masing Masing Lifting Gear
4 . Kalkulasi Radius crane Terhadap obyek
5 . Jarak COG antara Lifting Pad eyes ( dalam meter)
6 . Perhitungan Pengangkatan
- Berat obyek + Contingency Factor + DAF
- Perhitungan Sling Force, Lifting padeye, Sachkle
- Perhitungan kapasitas Crane, Panjang Boom crane Radius Crane terhadap Obyek

E . Pekerjaan Lifthing dari Segi HSE


1 . Persiapan JSA untuk aktifitas Pekerjaan Lifting
2 . Ispeksi crane, Lifting Gear, Valid Certificate cranem SIO Operator
3 . Jika Crane Sudah Tiba di Lokasi harus dilakukan Load Test
4 . Technical Meeting (team engineering,team excecutor, sebelum di lakukan pekerjaan
5 . Jika semua pihak sudah menyetujui ( Approval) Chek list harus di tanda tangani bersama
6 . Semua Team harus memonitor selama proses lifting di lakukan
untuk memastikan semua berjalan sesuai dengan rencana
at obyek
MECHANICAL AND PIPING WORK PACKAGE-3
(GPP-SEPARATOR AREA - SCRUBER AREA )

Pelaksanaan Pekerjaan Mekanikal

1 . UNLOADING
1 . Persiapan Kerja Lifting 1 (satu) hari sebelum Eqauipment tiba di Lokasi Termasuk Safety
Working Permit Meeting
2 . Equipment Sampai Di lokasi Proyek
3 . Chek Fisik Equipment dari Kemungkinan Kerusakan dalam perjalanan Transportasi
4 . Unloading equipment dari Trailer ke Laydown area yang telah di siapkan
a . Memastikan Area Laydown untuk penempatan Equipment dalam kondisi yang Aman
b . Mempersiapkan support atau landasan yang cukup kuat agar equipment tidak amblas
(Minimum 20cm-30cm di atas permukaan Tanah )
5 . Chek Kembali Dimensional antara Bolt to Bolt holes ( hanya utk internal )
6 . Menutup Seluruh Body Equpment Menggunakan Terpal ( Blue Sheet ) untuk menghindari
terik matahari, debu, hujan

2 . PERSIAPAN PEKERJAAN
1 . Persiapan pekerjaan lifthing satu hari sebelum installation equipment
a . Work Permit meeting
b . Mempersiapkan perlengkapan Lifthing Gear dan memastikan semua dalam kondisi baik
dan bersertifikat
c . Memastikan kondisi area tracking dalam kondis baik dan tidak terhalang benda apapun
d . Memastikan pengecekan kembali bolt to bolt dimensi
e . Pembersihan area ( Clean up point) dan di tutup kembali menggunakan Terpal ( Blue Sheet )
f . Mempersiapkan Liner/shim plate, Hand Tools dan Alat alat kerja Lain nya
g . Penempatan posisi crane

3 . INSTALLATION
1 . Tool box Meeting dilakukan bersam team team yang terkait sebelum dilakukan pekerjaan lifthing
2 . Memulai Pekerjaan Lifting
a . Instal alat alat Lifting Gear
b . Proses Pengankatan equipment dan Moving cran untuk penempatan equipment pada posisi
yang telah di tentukan
c . Setting Up equipment dan monitoring by QC Surveyor
d . Disconcted alat Lifting / pad eyes
e . Crane Moving Kembali ke area aman
f . Setelah equipment pada posisi yang telah di tentukan maka di cover kembali
menggunakan Terpal ( Blue sheet )
Sheet )

posisi
Pelaksanaan Pekerjaan Piping CS & SS

Fabrikasi Carbon Steel & Stainless Steel


1 . Cek Material oleh material Control untuk pekerjaan fabrikasi sesuai dengan Isometric Drawing
Baik itu Pipa ataupun Fitting dan Pipe Support Material
2 . Untuk Material yang sesuai dengan Isometric drawing
akan kita kirim ke Workshop Piping untuk dilakukan pemotongan pipa atau material pipe support
sesuai dengan Isometric dan soft drawing
3 . Material yang sudah dilakukan pemotongan akan dikirim ke bagian fit up welding
4 . Pekerjaan Fit up dan pengelasan akan di mulai sesuai dengan Isometric drawing dan shop drawing berikut Taging
5 . Sebelum dilakukan pengelasan pihak QC akan melakukan pengecekan orientasi Pipe Spool dan dimensional cek
6 . Setelah selesai Pengelasan Pihak QC akan melakukan Visual Cek terhadap mutu pengelasan
7 Pipe Spool yang sudah Completed fabrikasi akan di kirim ke safe area untuk dilakukan pengujian NDT
8 . Apabila terdapat hasil NDT yang menyatakan "Repair" dan harus dilakukan repair
Spool di kembalikan ke Workshop utk perbaikan mutu pengelasan
9 . Untuk pipe spool yang lolos NDT akn di kirim ke area sand Blasting and painting Area
10 . Untuk Pipe support setelah finishing dan pengecekan QC selanjutkan akan dikirim ke area sand blasting dan painti
11 . Pipe spool dan Pipe Support yang sudah selesai dilakukan sand blasting dan painting
selanjutnya akan di kirimkan ke Instalation Area sesuai dengan lokasi masing masing
12 . Untuk Pekerjaan Pipa stainless steel sesuai dengan perlakuan Prosedur material SS

Installation Carbon Steel & Stainless Steel


1 . Pipe Spool akan di Angkat ke Pipe Rack menggunakan crane ataupun Cain Block
2 . Fit up pipe spool CS & SS akan di lakukan di atas Pipe Rack sesuai dengan drawing installation ( Arrangement dra
3 . Setelah Selai Fit up di atas Pipe Rack, Quality Control akan melakukan pengecekan sesuai dengan Isometric draw
4 . Setelah Approval dari QC maka akan dilakukan pengelasan yang di sebut Field Weld
5 . Quality Cotrol kembali akan melakukan pengecekan setelah pengelasan selesai ( Visual Chek)
6 . Setelah selesai Pekerjaan Pengelasan makaakan dilakukan uji Quality by NDT
7 . NDT di lakukan pada jam jam tertentu
8 . Pemasangan Pipe support akan di lakukan sesuai kebutuhan
pipe support

n shop drawing berikut Taging


pe Spool dan dimensional cek

an pengujian NDT

e area sand blasting dan painting area

g installation ( Arrangement drawing)


sesuai dengan Isometric drawing

isual Chek)
Pelaksanaan Pekerjaan FRP & HDPE
FRP ( Fibre Reinforce Pad Pipe )

Fabrikasi FRP & HDPE


1 . Pemotongan dilakukan sesuai dengan Isometric Drawing
2 . Setelah dilakukan pemotongan ujung dari material FRP yang akan di Joint dengan Fiiting
dilakukan pengikisan outside diameter untuk menyesuaikan Inside diameter Fitting
3 . Penyambungan pipa dan fitting akan di lakukan dengan menggunakan Lem khusus ( Epoxy Glue )
4 . Setelah selasi di lakukan nya penyambungan akan di panaskan ( Heating) dengan alat khusus ( Aligment)
5 . Durasi untuk kekeringan Lem tsb kurang Lebih 8 Jam maksimum
6 . Untuk pengecekan bocor atau tidak nya sambungan tersebut di lakukan (Holiday Test)
7 . FRP akan di kirim ke lokasi Installation

Installation FRP & HDPE


1 . Pipe Spool akan di Alokasikan ke areanya masing - masing
2 . Fit Up akan di lakukan di area yang telah di tentukan
3 . Setelah Fit up selesai di lakukan selanjutnya di lakukan pengecekan oleh Quality Cotrol
4 . Setelah Approval dari QC maka akan dilakukan pengeleman di site area
5 . Quality Cotrol kembali akan melakukan pengecekan setelah pengeleman selesai ( Visual Chek)
6 . Setelah selesai Pekerjaan Pengeleman maka akan dilakukan Uji Quality ( Holiday Test )
( Epoxy Glue )
alat khusus ( Aligment)

Visual Chek)
Pelaksanaan Pekerjaan Precommisioning

1 . Memastikan Bahwa Spool sudah terpasang Complete berikut pipe support


2 . Line Chek per System harus dilakukan bersamaan dengan Client
3 . Punch List akan di terbitkan oleh Client dan di laksanakan oleh Kontraktor
4 . Pengecekan ulang setelah Punch List ACC by Client
5 . Dilakukan Bolt Tigtening dengan menggunakan Torque Wrenchs by Manual and Hydrolic
6 . Sebelum Filling Water di lakukan, akan di lakukan Flushing menggunakan Air Compressor
7 . Filling Water untuk setiap Test Package dari Low Point sampi ke Hi Point
8 . Setelah Air Penuh akan dilakukan Penekanan di dalam Pipa dengan Menggunakan Hydrotest Pump
Sesuai dengan Presure / Tekanan yang telah di tentukan yaitu 1,5 x Design pressure
9 . Setelah selesai Hydrotest selanjutnya di lakukan pekerjaan Blowing menggunakan Air Compressor
10 . Setelah Blowing Selesai akan dilakukan Pekerjaan Reinstatement
11 . Final Precommisioning Furging and Drying by Nitrogen (inclued Touch Up Painting )
Hydrotest Pump

Air Compressor
Safety APD, Hand Tools And Power Tools Equipment List

Safety APD
No, Description Qty
1 . Safety Helmet sesuai keburuhan
2 . Safety Shoes sesuai keburuhan
3 . Baju Seragam (warepack) sesuai keburuhan
4 . Safety Glass sesuai keburuhan
5 . Masker Filter sesuai keburuhan
6 . Ear Plug sesuai keburuhan
7 . Body Hardness sesuai keburuhan
8 . Hand Glove sesuai keburuhan
9 . Welding Glove sesuai keburuhan
10 . Hand Sleve sesuai keburuhan
11 . Appron sesuai keburuhan
.

Hand Tools And Power Tools Equipment List


No, Description Qty

1 . Site Office Container 40" 1


2 Container Store 20" 2
3 . Spreader Bar 75T 1
4 . Spreader Bar 25T 1
5 . Crawler Crane 250 Ton 1
6 . Gantry Crnae 1
7 . Mobile Crane 80 Ton 1
8 . Mobile Crane 50 Ton 1
9 . Mobile Crane 25 Ton 1
10 . Electric Winch 3 Ton 2
11 . Air Compressor 175 cfm 1
12 . Air Compressor 350 cfm 1
13 . Diesel Generator 250kVA 2
14 . HT Pump 1
15 . Water Filling Pump 1
16 . Strand Jack (4 nos @ 40 Ton) 5
17 . Forklift 1
18 . Excavator PC200 + Hook 1
19 . Dump Truck 1
20 . Compactor Roller 1
21 . Welding Machine 45
22 . Rectifier sesuai kebutuhan
23 . Handtools and Others sesuai kebutuhan
24 . Diesel Engine 80 Kva sesuai kebutuhan
25 . Scaffolding sesuai kebutuhan
26 . ELF 2
27 . Pick up 2
28 . Trailer 1
29 . Uni Crane 1
30 . Mobile Transport 2
31 . Ambulance 1
32 . Meteran KDS 5M sesuai kebutuhan
33 . Roll Meter SS 50M 1
34 . Roll Meter SS 30M 1
35 . Siku Besar sesuai kebutuhan
36 . Siku Kecil sesuai kebutuhan
37 . Water Pas sesuai kebutuhan
38 . Hi Low Gap sesuai kebutuhan
39 . Tapper Gap sesuai kebutuhan
40 . Chain Block 1 Ton 5
41 . Chain Block 2 Ton 5
42 . Chain Block 3 Ton 5
43 . Chain Block 5 Ton 4
44 . Chain Block 10 Ton 2
45 . Level Block 1 Ton 4
46 . Level Block 2 Ton 8
47 . Level Block 3 Ton 8
48 . Sling Belt 3 Ton 3M 10
49 . Sling Belt 2 Ton 3M 10
50 . Sling Belt 5 Ton 3M 10
51 . Sling Belt 10 Ton 3M 10
52 . Sling Belt 3 Ton 6M 4
53 . Sling Belt 10 Ton 6M 4
54 Cutting Torch 4
55 . Grinding Machine 4 inch 20
56 . Grinding Machine 5 inch 20
57 . Grinding Machine 7 inch 10
58 . Cabel Power sesuai kebutuhan
59 . Welding Cable sesuai kebutuhan
60 . Requlator OXY LPG sesuai kebutuhan
61 . Regulqtor Gas Argon sesuai kebutuhan
62 . Tungsten ( Stang Las Argon) sesuai kebutuhan
63 . Welding Holder ( Stang Las ) sesuai kebutuhan
64 . Welding Conector sesuai kebutuhan
65 . Terminal Conector sesuai kebutuhan
66 . Grinding Rotary ( grinda Baby) 5
67 . Hot Box ( Quiver ) sesuai kebutuhan

Вам также может понравиться