This report is the study of progress of on going project which is give to us by national
highway authority to solve the visibility problem during fog on motor way. The project is
to install the fog lights on the motorway. The project time is a total of 2 months from July
3, 2010 to September 3, 2010, to solve this problem we have to work day and night to
The fog light installment is in progress. The fog light has been almost installing the half
of the ways of the motorway. The following is the list of work which were already been
completed.
The high quality road reflectors were already been install on the half of the motor
way.
To increase the visibility we also start paint the road curbs and lane
The first big problem we face is heat stroke because we started the work in the
month of July so suddenly the temperature increase and labor was unable to work
in that heat.
The second problem is the road reflectors, were imported from china so there is
delay of getting the delivery because of land sliding in the northern areas and
heavy snowfall
The another problem is the traffic which can interrupt in the work an can cause
delay.
We hope that our project will be complete before due date that is 3rd September 2010, if
the is on delay in getting the delivery of the fog lights and reflectors. We recommend that
we requires more labor and more resources so we can complete the project and also solve
the issue of traffic which causes delay, to solve this issues there is need of diversion