Вы находитесь на странице: 1из 50

REHABILITATION OF MULTI - PURPOSE BUILDING

CAINGIN, BOCAUE, BULACAN

ITEM NO DESCRIPTION UNIT

PART II OTHER GENERAL REQUIREMENTS


B.1 Offices, Shops, Stores and Workmens Accomodation for Contractor L.s.
B.5 Project Billboard / Signboard Ea.
B.7 (1) Occupational Safety and Health Mo.
Sub-Total Part II
PART III CIVIL, MECHANICAL, ELECTRICAL AND SANITARY/ PLUMBING WORKS
PART A - EARTHWORKS
803(1)a Structure Excavation ( Common Soil ) Cu.m.
804(1)b Embankment From Borrow Cu.m.
804(4) Gravel Fill Cu.m.
Sub-Total Part A
PART B - PLAIN AND REINFORCED CONCRETE WORKS
900(1)c1 Structural Concrete (Class A, 28days) Cu.m.
902(1)a1 Reinforcing Steel, Grade 40 (Deformed) Kgs.
903(2) Forms and Falseworks Sq.m.
Sub-Total Part B
PART C - FINISHING WORKS
1043(2)b Masonry Unit (150mm Wall) Sq.m.
1014(1)b2 Prepainted Metal Sheets, Long Span, Rib Type, 0.5mm thk Sq.m.
1013(2)a Fabricated Metal Roofing Accessory (Ridge Roll, 0.6mm thk) L.m.
1013(2)b Fabricated Metal Roofing Accessory (Flashing, 0.6mm thk) L.m.
1013(2)c Fabricated Metal Roofing Accessory (Gutter, 0.6mm thk) L.m.
1047(2)a Structural Steel, Trusses Kgs.
1047(2)b Structural Steel, Purlins Kgs.
1047(6) Metal Structure Accessories, Steel Plates Kgs.
1047(7)b Metal Structure Accessories, Sag Rods Kgs.
1047(4) Metal Structure Accessories, Cross Bracing Kgs.
1047(3)c Metal Structure Accessories, Turn Buckle Pc.
Sub-Total Part C
PART D - PLUMBING/ SANITARY WORKS
Sub-Total Part D
PART E - ELECTRICAL WORKS
Sub-Total Part E
Sub-Total Part III
GRAND TOTAL

Contract Amount

Net Collectible
Total Direct Cost

SOP 3.00%
PROPONENT 8.00%
BAC 3.00%
PRECON 2.00%
16.00%

PROFIT 67.25%

Materials 0.00%
Equipment 0.00%
Labor 0.00%

ESTIMATED BY:

LEONARDO ROBERTO S. DELOS SANTOS


REHABILITATION OF M
CAINGIN, BOCAUE, BU

QUANTITY UNIT COST AMOUNT ITEM


NO.
B.1
1.00 44,000.00 44,000.00
1.00 5,090.00 5,090.00
4.00 5,625.00 22,500.00 M
71,590.00 A
T
E
14.72 353.26 5,200.00 R
121.07 712.22 86,228.00 I
2.10 986.29 2,071.20 A
93,499.20 L
S
7.03 5,490.75 38,600.00
502.26 54.01 27,124.90
36.80 0.00 -
65,724.90

18,694.94 0.25 4,620.00


173,891.72 0.00 -
15.00 0.00 -
36.00 0.00 -
42.00 0.00 - E
4,102.09 0.00 - Q
2018.24 0.00 - U
1,076.76 0.00 - I
49.73 0.00 - P
176.85 0.00 - M
2.00 0.00 - E
4,620.00 N
T
-

-
163,844.10
235,434.10 L
A
B
O
R

₱ 1,499,693.01

₱ 1,405,962.20
₱ 235,434.10 INDIRECT UNIT COST
a. Overhead/Contingenci
₱ 42,178.87 b. Contractor's Profit
₱ 112,476.98 c. Value Added Tax
₱ 42,178.87
₱ 28,119.24
₱ 224,953.95

₱945,574.14
REHABILITATION OF M
₱ - CAINGIN, BOCAUE, BU
₱ -
₱ -
ITEM
NO.
B.5

M
A
T
E
R
I
A
L
S

E
Q
U
I
P
M
E
N
T

L
A
B
O
R

INDIRECT UNIT COST


a. Overhead/Contingenci
b. Contractor's Profit
c. Value Added Tax

REHABILITATION OF M
CAINGIN, BOCAUE, BU

ITEM
NO.
B.7 (1)

M
A
T
E
R
I
A
L
S

E
Q
U
I
P
M
E
N
T

L
A
B
O
R

INDIRECT UNIT COST


a. Overhead/Contingenci
b. Contractor's Profit
c. Value Added Tax

REHABILITATION OF M
CAINGIN, BOCAUE, BU

ITEM
NO.
803(1)a

M
A
T
E
R
I
A
L
S
E
Q
U
I
P
M
E
N
T

L
A
B
O
R

INDIRECT UNIT COST


a. Overhead/Contingenci
b. Contractor's Profit
c. Value Added Tax

REHABILITATION OF M
CAINGIN, BOCAUE, BU

ITEM
NO.
804(1)b

M
A
T
E
R
I
A
L
S

E
Q
U
I
P
M
E
N
T

L
A
B
O
R

INDIRECT UNIT COST


a. Overhead/Contingenci
b. Contractor's Profit
c. Value Added Tax

REHABILITATION OF M
CAINGIN, BOCAUE, BU

ITEM
NO.
804(4)

M
A
T
E
R
I
A
L
S

E
Q
U
I
P
M
E
N
T

L
A
B
O
R

INDIRECT UNIT COST


a. Overhead/Contingenci
b. Contractor's Profit
c. Value Added Tax
REHABILITATION OF M
CAINGIN, BOCAUE, BU

ITEM
NO.
900(1)c1

M
A
T
E
R
I
A
L
S

E
Q
U
I
P
M
E
N
T

L
A
B
O
R
INDIRECT UNIT COST
a. Overhead/Contingenci
b. Contractor's Profit
c. Value Added Tax

REHABILITATION OF M
CAINGIN, BOCAUE, BU

ITEM
NO.
902(1)a1

M
A
T
E
R
I
A
L
S

E
Q
U
I
P
M
E
N
T
L
A
B
O
R

INDIRECT UNIT COST


a. Overhead/Contingenci
b. Contractor's Profit
c. Value Added Tax

REHABILITATION OF M
CAINGIN, BOCAUE, BU

ITEM
NO.
903(2)

M
A
T
E
R
I
A
L
S

E
Q
U
I
P
M
E
N
T

L
A
B
O
R

INDIRECT UNIT COST


a. Overhead/Contingenci
b. Contractor's Profit
c. Value Added Tax

REHABILITATION OF M
CAINGIN, BOCAUE, BU

ITEM
NO.
1043(2)b

M
A
T
E
R
I
A
L
S
E
Q
U
I
P
M
E
N
T

L
A
B
O
R

INDIRECT UNIT COST


a. Overhead/Contingenci
b. Contractor's Profit
c. Value Added Tax

REHABILITATION OF M
CAINGIN, BOCAUE, BU

ITEM
NO.
1014(1)b2

M
A
T
E
R
I
A
L
S

E
Q
U
I
P
M
E
N
T

L
A
B
O
R

INDIRECT UNIT COST


a. Overhead/Contingenci
b. Contractor's Profit
c. Value Added Tax

REHABILITATION OF M
CAINGIN, BOCAUE, BU

ITEM
NO.
1013(2)a

M
A
T
E
R
I
A
L
S

E
Q
U
I
P
M
E
N
T

L
A
B
O
R

INDIRECT UNIT COST


a. Overhead/Contingenci
b. Contractor's Profit
c. Value Added Tax

REHABILITATION OF M
CAINGIN, BOCAUE, BU

ITEM
NO.
1013(2)b

M
A
T
E
R
I
A
L
S

E
Q
U
I
P
M
E
N
T

L
A
B
O
R

INDIRECT UNIT COST


a. Overhead/Contingenci
b. Contractor's Profit
c. Value Added Tax

REHABILITATION OF M
CAINGIN, BOCAUE, BU

ITEM
NO.
1013(2)c

M
A
T
E
R
I
A
L
S

E
Q
U
I
P
M
E
N
T

L
A
B
O
R

INDIRECT UNIT COST


a. Overhead/Contingenci
b. Contractor's Profit
c. Value Added Tax

REHABILITATION OF M
CAINGIN, BOCAUE, BU

ITEM
NO.
1047(2)a

M
A
T
E
R
I
A
L
S
E
Q
U
I
P
M
E
N
T

L
A
B
O
R

INDIRECT UNIT COST


a. Overhead/Contingenci
b. Contractor's Profit
c. Value Added Tax

REHABILITATION OF M
CAINGIN, BOCAUE, BU

ITEM
NO.
1047(2)b

M
A
T
E
R
I
A
L
S

E
Q
U
I
P
M
E
N
T

L
A
B
O
R

INDIRECT UNIT COST


a. Overhead/Contingenci
b. Contractor's Profit
c. Value Added Tax

REHABILITATION OF M
CAINGIN, BOCAUE, BU

ITEM
NO.
1047(6)

M
A
T
E
R
I
A
L
S

E
Q
U
I
P
M
E
N
T

L
A
B
O
R

INDIRECT UNIT COST


a. Overhead/Contingenci
b. Contractor's Profit
c. Value Added Tax
REHABILITATION OF M
CAINGIN, BOCAUE, BU

ITEM
NO.
1047(7)b

M
A
T
E
R
I
A
L
S

E
Q
U
I
P
M
E
N
T

L
A
B
O
R
INDIRECT UNIT COST
a. Overhead/Contingenci
b. Contractor's Profit
c. Value Added Tax

REHABILITATION OF M
CAINGIN, BOCAUE, BU

ITEM
NO.
1047(4)

M
A
T
E
R
I
A
L
S

E
Q
U
I
P
M
E
N
T
L
A
B
O
R

INDIRECT UNIT COST


a. Overhead/Contingenci
b. Contractor's Profit
c. Value Added Tax

REHABILITATION OF M
CAINGIN, BOCAUE, BU

ITEM
NO.
1047(3)c

M
A
T
E
R
I
A
L
S

E
Q
U
I
P
M
E
N
T

L
A
B
O
R

INDIRECT UNIT COST


a. Overhead/Contingenci
b. Contractor's Profit
c. Value Added Tax
REHABILITATION OF MULTI - PURPOSE BUILDING
CAINGIN, BOCAUE, BULACAN

DETAILED UNIT COST ANALYSIS


DESCRIPTION UNIT COST
Offices, Shops, Stores and Workmens Accomodation for Contractor
1.00 L.s. 44,000.00
NAME & SPECIFICATION QUANTITY UNIT UNIT COST COST

Field Office (rental/ maintenance of iffice bldg. 4.00 mos. 8,000.00 32,000.00
laboratory and quarters (at least 7m x 9m furnished/ -
equipped with complete office facilities and supplies -
-
Electricity and Water Utilities 4.00 mos. 3,000.00 12,000.00
-
-
-
-
-
-
-
-
-
-
TOTAL FOR MATERIALS 44,000.00
NAME AND CAPACITY NO. OF UNITS
NO.OF HOUR HOURLY RATE AMOUNT

-
-
-
-
-
-
-
-
-
-
TOTAL FOR EQUIPMENT -
DESIGNATION NO. OF PERSONS
NO.OF HOUR HOURLY RATE AMOUNT

-
-
-
-
-
-
-
-
TOTAL FOR LABOR -
TOTAL DIRECT COST 44,000.00
INDIRECT UNIT COST
a. Overhead/Contingencies/Miscellaneous
b. Contractor's Profit
c. Value Added Tax

TOTAL INDIRECT COST -


TOTAL COST 44,000.00
UNIT COST 44,000.00
REHABILITATION OF MULTI - PURPOSE BUILDING
CAINGIN, BOCAUE, BULACAN

DETAILED UNIT COST ANALYSIS


DESCRIPTION UNIT COST
Project Billboard / Signboard
1.00 Ea. 5,090.00
NAME & SPECIFICATION QUANTITY UNIT UNIT COST COST

Ordinary Plywood (1/2" x 4' x 8') 2.00 pc. 400.00 800.00


Good lumber - 4 uses 42.00 bd.ft. 55.00 2,310.00
Project Sign (Tarpaulin) 96.00 sq.ft 15.00 1,440.00
-
-
-
-
-
-
-
-
-
-
-
-
TOTAL FOR MATERIALS 4,550.00
NAME AND CAPACITY NO. OF UNITS
NO.OF HOUR HOURLY RATE AMOUNT

-
-
-
-
-
-
-
-
-
-
TOTAL FOR EQUIPMENT -
DESIGNATION NO. OF PERSONS
NO.OF HOUR HOURLY RATE AMOUNT

Construction Foreman 1.00 2 100.00 200.00


Skilled Labor 1.00 2 70.00 140.00
Unskilled Laborer 2.00 2 50.00 200.00
-
-
-
-
-
TOTAL FOR LABOR 540.00
TOTAL DIRECT COST 5,090.00
INDIRECT UNIT COST
a. Overhead/Contingencies/Miscellaneous
b. Contractor's Profit
c. Value Added Tax

TOTAL INDIRECT COST -


TOTAL COST 5,090.00
UNIT COST 5,090.00
REHABILITATION OF MULTI - PURPOSE BUILDING
CAINGIN, BOCAUE, BULACAN

DETAILED UNIT COST ANALYSIS


DESCRIPTION UNIT COST
Occupational Safety and Health
4.00 Mo. 5,625.00
NAME & SPECIFICATION QUANTITY UNIT UNIT COST COST

Safety Shoes 20.00 Pc 950.00 19,000.00


Safety Helmet 20.00 Pc 150.00 3,000.00
Safety Gloves 20.00 Pc 25.00 500.00
-
-
-
-
-
-
-
-
-
-
-
-
TOTAL FOR MATERIALS 22,500.00
NAME AND CAPACITY NO. OF UNITS
NO.OF HOUR HOURLY RATE AMOUNT

-
-
-
-
-
-
-
-
-
-
TOTAL FOR EQUIPMENT -
DESIGNATION NO. OF PERSONS
NO.OF HOUR HOURLY RATE AMOUNT

-
-
-
-
-
-
-
-
TOTAL FOR LABOR -
TOTAL DIRECT COST 22,500.00
INDIRECT UNIT COST
a. Overhead/Contingencies/Miscellaneous
b. Contractor's Profit
c. Value Added Tax

TOTAL INDIRECT COST -


TOTAL COST 22,500.00
UNIT COST 5,625.00
REHABILITATION OF MULTI - PURPOSE BUILDING
CAINGIN, BOCAUE, BULACAN

DETAILED UNIT COST ANALYSIS


DESCRIPTION UNIT COST
Structure Excavation ( Common Soil )
14.72 Cu.m. 353.26
NAME & SPECIFICATION QUANTITY UNIT UNIT COST COST

-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
TOTAL FOR MATERIALS -
NAME AND CAPACITY NO. OF UNITS
NO.OF HOUR HOURLY RATE AMOUNT

Cargo Truck 1.00 1.00 1,000.00 1,000.00


Backhoe Wheel-Type 1.00 2.00 1,800.00 3,600.00
-
-
-
-
-
-
-
-
TOTAL FOR EQUIPMENT 4,600.00
DESIGNATION NO. OF PERSONS
NO.OF HOUR HOURLY RATE AMOUNT

Construction Foreman 1.00 2 100.00 200.00


Unskilled Labor 4.00 2 50.00 400.00
-
-
-
-
-
-
TOTAL FOR LABOR 600.00
TOTAL DIRECT COST 5,200.00
INDIRECT UNIT COST
a. Overhead/Contingencies/Miscellaneous
b. Contractor's Profit
c. Value Added Tax

TOTAL INDIRECT COST -


TOTAL COST 5,200.00
UNIT COST 353.26
REHABILITATION OF MULTI - PURPOSE BUILDING
CAINGIN, BOCAUE, BULACAN

DETAILED UNIT COST ANALYSIS


DESCRIPTION UNIT COST
Embankment From Borrow
121.07 Cu.m. 712.22
NAME & SPECIFICATION QUANTITY UNIT UNIT COST COST

Common Borrow 151.34 cu.m. 320.00 48,428.00


-
-
-
-
-
-
-
-
-
-
-
-
-
-
TOTAL FOR MATERIALS 48,428.00
NAME AND CAPACITY NO. OF UNITS
NO.OF HOUR HOURLY RATE AMOUNT

Backhoe Wheel Type 1.00 13.00 1,800.00 23,400.00


Road Roller 1.00 8.00 1,500.00 12,000.00
-
-
-
-
-
-
-
-
TOTAL FOR EQUIPMENT 35,400.00
DESIGNATION NO. OF PERSONS
NO.OF HOUR HOURLY RATE AMOUNT

Construction Foreman 1.00 12 100.00 1,200.00


Unskilled Labor 2.00 12 50.00 1,200.00
-
-
-
-
-
-
TOTAL FOR LABOR 2,400.00
TOTAL DIRECT COST 86,228.00
INDIRECT UNIT COST
a. Overhead/Contingencies/Miscellaneous
b. Contractor's Profit
c. Value Added Tax

TOTAL INDIRECT COST -


TOTAL COST 86,228.00
UNIT COST 712.22
REHABILITATION OF MULTI - PURPOSE BUILDING
CAINGIN, BOCAUE, BULACAN

DETAILED UNIT COST ANALYSIS


DESCRIPTION UNIT COST
Gravel Fill
2.10 Cu.m. 986.29
NAME & SPECIFICATION QUANTITY UNIT UNIT COST COST

G1 Gravel Bedding 2.21 cu.m. 640.00 1,411.20


-
-
-
-
-
-
-
-
-
-
-
-
-
-
TOTAL FOR MATERIALS 1,411.20
NAME AND CAPACITY NO. OF UNITS
NO.OF HOUR HOURLY RATE AMOUNT

Backhoe Wheel Type 1.00 0.20 1,800.00 360.00


-
-
-
-
-
-
-
-
-
TOTAL FOR EQUIPMENT 360.00
DESIGNATION NO. OF PERSONS
NO.OF HOUR HOURLY RATE AMOUNT

Construction Foreman 1.00 1 100.00 100.00


Unskilled Labor 4.00 1 50.00 200.00
-
-
-
-
-
-
TOTAL FOR LABOR 300.00
TOTAL DIRECT COST 2,071.20
INDIRECT UNIT COST
a. Overhead/Contingencies/Miscellaneous
b. Contractor's Profit
c. Value Added Tax
TOTAL INDIRECT COST -
TOTAL COST 2,071.20
UNIT COST 986.29
REHABILITATION OF MULTI - PURPOSE BUILDING
CAINGIN, BOCAUE, BULACAN

DETAILED UNIT COST ANALYSIS


DESCRIPTION UNIT COST
Structural Concrete (Class A, 28days)
7.03 Cu.m. 5,490.75
NAME & SPECIFICATION QUANTITY UNIT UNIT COST COST

Ready Mix Concrete 8.00 cu.m. 4,000.00 32,000.00


-
-
-
-
-
-
-
-
-
-
-
-
-
-
TOTAL FOR MATERIALS 32,000.00
NAME AND CAPACITY NO. OF UNITS
NO.OF HOUR HOURLY RATE AMOUNT

-
-
-
-
-
-
-
-
-
-
TOTAL FOR EQUIPMENT -
DESIGNATION NO. OF PERSONS
NO.OF HOUR HOURLY RATE AMOUNT

Construction Foreman 1.00 15 100.00 1,500.00


Skilled Labor 2.00 15 70.00 2,100.00
Unskilled Labor 4.00 15 50.00 3,000.00
-
-
-
-
-
TOTAL FOR LABOR 6,600.00
TOTAL DIRECT COST 38,600.00
INDIRECT UNIT COST
a. Overhead/Contingencies/Miscellaneous
b. Contractor's Profit
c. Value Added Tax

TOTAL INDIRECT COST -


TOTAL COST 38,600.00
UNIT COST 5,490.75
REHABILITATION OF MULTI - PURPOSE BUILDING
CAINGIN, BOCAUE, BULACAN

DETAILED UNIT COST ANALYSIS


DESCRIPTION UNIT COST
Reinforcing Steel, Grade 40 (Deformed)
902(1)a1 502.26 Kgs. 54.01
NAME & SPECIFICATION QUANTITY UNIT UNIT COST COST

Reinforcing Steel Bar, Grade 40 527.37 kgs. 43.00 22,677.04


# 16 Tie Wire (1% of RSB) 5.27 kgs. 47.00 247.87
Oxygen/Acetelyne 1.00 set 2,000.00 2,000.00
-
-
-
-
-
-
-
-
-
-
-
-
TOTAL FOR MATERIALS 24,924.90
NAME AND CAPACITY NO. OF UNITS
NO.OF HOUR HOURLY RATE AMOUNT

-
-
-
-
-
-
-
-
-
-
TOTAL FOR EQUIPMENT -
DESIGNATION NO. OF PERSONS
NO.OF HOUR HOURLY RATE AMOUNT

Construction Foreman 1.00 5 100.00 500.00


Skilled Labor 2.00 5 70.00 700.00
Unskilled Labor 4.00 5 50.00 1,000.00
-
-
-
-
-
TOTAL FOR LABOR 2,200.00
TOTAL DIRECT COST 27,124.90
INDIRECT UNIT COST
a. Overhead/Contingencies/Miscellaneous
b. Contractor's Profit
c. Value Added Tax

TOTAL INDIRECT COST -


TOTAL COST 27,124.90
UNIT COST 54.01
REHABILITATION OF MULTI - PURPOSE BUILDING
CAINGIN, BOCAUE, BULACAN

DETAILED UNIT COST ANALYSIS


DESCRIPTION UNIT COST
Forms and Falseworks
36.80 Sq.m. -
NAME & SPECIFICATION QUANTITY UNIT UNIT COST COST

-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
TOTAL FOR MATERIALS -
NAME AND CAPACITY NO. OF UNITS
NO.OF HOUR HOURLY RATE AMOUNT

-
-
-
-
-
-
-
-
-
-
TOTAL FOR EQUIPMENT -
DESIGNATION NO. OF PERSONS
NO.OF HOUR HOURLY RATE AMOUNT

-
-
-
-
-
-
-
-
TOTAL FOR LABOR -
TOTAL DIRECT COST -
INDIRECT UNIT COST
a. Overhead/Contingencies/Miscellaneous
b. Contractor's Profit
c. Value Added Tax

TOTAL INDIRECT COST -


TOTAL COST -
UNIT COST -
REHABILITATION OF MULTI - PURPOSE BUILDING
CAINGIN, BOCAUE, BULACAN

DETAILED UNIT COST ANALYSIS


DESCRIPTION UNIT COST
Masonry Unit (150mm Wall)
1043(2)b 18,694.94 Sq.m. 0.25
NAME & SPECIFICATION QUANTITY UNIT UNIT COST COST

CHB 6" 420.00 pcs. 11.00 4,620.00


-
-
-
-
-
-
-
-
-
-
-
-
-
-
TOTAL FOR MATERIALS 4,620.00
NAME AND CAPACITY NO. OF UNITS
NO.OF HOUR HOURLY RATE AMOUNT

-
-
-
-
-
-
-
-
-
-
TOTAL FOR EQUIPMENT -
DESIGNATION NO. OF PERSONS
NO.OF HOUR HOURLY RATE AMOUNT

-
-
-
-
-
-
-
-
TOTAL FOR LABOR -
TOTAL DIRECT COST 4,620.00
INDIRECT UNIT COST
a. Overhead/Contingencies/Miscellaneous
b. Contractor's Profit
c. Value Added Tax

TOTAL INDIRECT COST -


TOTAL COST 4,620.00
UNIT COST 0.25
REHABILITATION OF MULTI - PURPOSE BUILDING
CAINGIN, BOCAUE, BULACAN

DETAILED UNIT COST ANALYSIS


DESCRIPTION UNIT COST
Prepainted Metal Sheets, Long Span, Rib Type, 0.5mm thk
1014(1)b2 173,891.72 Sq.m. -
NAME & SPECIFICATION QUANTITY UNIT UNIT COST COST

-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
TOTAL FOR MATERIALS -
NAME AND CAPACITY NO. OF UNITS
NO.OF HOUR HOURLY RATE AMOUNT

-
-
-
-
-
-
-
-
-
-
TOTAL FOR EQUIPMENT -
DESIGNATION NO. OF PERSONS
NO.OF HOUR HOURLY RATE AMOUNT

-
-
-
-
-
-
-
-
TOTAL FOR LABOR -
TOTAL DIRECT COST -
INDIRECT UNIT COST
a. Overhead/Contingencies/Miscellaneous
b. Contractor's Profit
c. Value Added Tax

TOTAL INDIRECT COST -


TOTAL COST -
UNIT COST -
REHABILITATION OF MULTI - PURPOSE BUILDING
CAINGIN, BOCAUE, BULACAN

DETAILED UNIT COST ANALYSIS


DESCRIPTION UNIT COST
Fabricated Metal Roofing Accessory (Ridge Roll, 0.6mm thk)
1013(2)a 15.00 L.m. -
NAME & SPECIFICATION QUANTITY UNIT UNIT COST COST

-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
TOTAL FOR MATERIALS -
NAME AND CAPACITY NO. OF UNITS
NO.OF HOUR HOURLY RATE AMOUNT

-
-
-
-
-
-
-
-
-
-
TOTAL FOR EQUIPMENT -
DESIGNATION NO. OF PERSONS
NO.OF HOUR HOURLY RATE AMOUNT

-
-
-
-
-
-
-
-
TOTAL FOR LABOR -
TOTAL DIRECT COST -
INDIRECT UNIT COST
a. Overhead/Contingencies/Miscellaneous
b. Contractor's Profit
c. Value Added Tax

TOTAL INDIRECT COST -


TOTAL COST -
UNIT COST -
REHABILITATION OF MULTI - PURPOSE BUILDING
CAINGIN, BOCAUE, BULACAN

DETAILED UNIT COST ANALYSIS


DESCRIPTION UNIT COST
Fabricated Metal Roofing Accessory (Flashing, 0.6mm thk)
1013(2)b 36.00 L.m. -
NAME & SPECIFICATION QUANTITY UNIT UNIT COST COST

-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
TOTAL FOR MATERIALS -
NAME AND CAPACITY NO. OF UNITS
NO.OF HOUR HOURLY RATE AMOUNT

-
-
-
-
-
-
-
-
-
-
TOTAL FOR EQUIPMENT -
DESIGNATION NO. OF PERSONS
NO.OF HOUR HOURLY RATE AMOUNT

-
-
-
-
-
-
-
-
TOTAL FOR LABOR -
TOTAL DIRECT COST -
INDIRECT UNIT COST
a. Overhead/Contingencies/Miscellaneous
b. Contractor's Profit
c. Value Added Tax

TOTAL INDIRECT COST -


TOTAL COST -
UNIT COST -
REHABILITATION OF MULTI - PURPOSE BUILDING
CAINGIN, BOCAUE, BULACAN

DETAILED UNIT COST ANALYSIS


DESCRIPTION UNIT COST
Fabricated Metal Roofing Accessory (Gutter, 0.6mm thk)
42.00 L.m. -
NAME & SPECIFICATION QUANTITY UNIT UNIT COST COST

-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
TOTAL FOR MATERIALS -
NAME AND CAPACITY NO. OF UNITS
NO.OF HOUR HOURLY RATE AMOUNT

-
-
-
-
-
-
-
-
-
-
TOTAL FOR EQUIPMENT -
DESIGNATION NO. OF PERSONS
NO.OF HOUR HOURLY RATE AMOUNT

-
-
-
-
-
-
-
-
TOTAL FOR LABOR -
TOTAL DIRECT COST -
INDIRECT UNIT COST
a. Overhead/Contingencies/Miscellaneous
b. Contractor's Profit
c. Value Added Tax

TOTAL INDIRECT COST -


TOTAL COST -
UNIT COST -
REHABILITATION OF MULTI - PURPOSE BUILDING
CAINGIN, BOCAUE, BULACAN

DETAILED UNIT COST ANALYSIS


DESCRIPTION UNIT COST
Structural Steel, Trusses
1047(2)a 4,102.09 Kgs. -
NAME & SPECIFICATION QUANTITY UNIT UNIT COST COST

-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
TOTAL FOR MATERIALS -
NAME AND CAPACITY NO. OF UNITS
NO.OF HOUR HOURLY RATE AMOUNT

-
-
-
-
-
-
-
-
-
-
TOTAL FOR EQUIPMENT -
DESIGNATION NO. OF PERSONS
NO.OF HOUR HOURLY RATE AMOUNT

-
-
-
-
-
-
-
-
TOTAL FOR LABOR -
TOTAL DIRECT COST -
INDIRECT UNIT COST
a. Overhead/Contingencies/Miscellaneous
b. Contractor's Profit
c. Value Added Tax

TOTAL INDIRECT COST -


TOTAL COST -
UNIT COST -
REHABILITATION OF MULTI - PURPOSE BUILDING
CAINGIN, BOCAUE, BULACAN

DETAILED UNIT COST ANALYSIS


DESCRIPTION UNIT COST
Structural Steel, Purlins
1047(2)b 2,018.24 Kgs. -
NAME & SPECIFICATION QUANTITY UNIT UNIT COST COST

-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
TOTAL FOR MATERIALS -
NAME AND CAPACITY NO. OF UNITS
NO.OF HOUR HOURLY RATE AMOUNT

-
-
-
-
-
-
-
-
-
-
TOTAL FOR EQUIPMENT -
DESIGNATION NO. OF PERSONS
NO.OF HOUR HOURLY RATE AMOUNT

-
-
-
-
-
-
-
-
TOTAL FOR LABOR -
TOTAL DIRECT COST -
INDIRECT UNIT COST
a. Overhead/Contingencies/Miscellaneous
b. Contractor's Profit
c. Value Added Tax

TOTAL INDIRECT COST -


TOTAL COST -
UNIT COST -
REHABILITATION OF MULTI - PURPOSE BUILDING
CAINGIN, BOCAUE, BULACAN

DETAILED UNIT COST ANALYSIS


DESCRIPTION UNIT COST
Metal Structure Accessories, Steel Plates
1,076.76 Kgs. -
NAME & SPECIFICATION QUANTITY UNIT UNIT COST COST

-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
TOTAL FOR MATERIALS -
NAME AND CAPACITY NO. OF UNITS
NO.OF HOUR HOURLY RATE AMOUNT

-
-
-
-
-
-
-
-
-
-
TOTAL FOR EQUIPMENT -
DESIGNATION NO. OF PERSONS
NO.OF HOUR HOURLY RATE AMOUNT

-
-
-
-
-
-
-
-
TOTAL FOR LABOR -
TOTAL DIRECT COST -
INDIRECT UNIT COST
a. Overhead/Contingencies/Miscellaneous
b. Contractor's Profit
c. Value Added Tax
TOTAL INDIRECT COST -
TOTAL COST -
UNIT COST -
REHABILITATION OF MULTI - PURPOSE BUILDING
CAINGIN, BOCAUE, BULACAN

DETAILED UNIT COST ANALYSIS


DESCRIPTION UNIT COST
1047(7)b
1047(7)b 49.73 Kgs. -
NAME & SPECIFICATION QUANTITY UNIT UNIT COST COST

-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
TOTAL FOR MATERIALS -
NAME AND CAPACITY NO. OF UNITS
NO.OF HOUR HOURLY RATE AMOUNT

-
-
-
-
-
-
-
-
-
-
TOTAL FOR EQUIPMENT -
DESIGNATION NO. OF PERSONS
NO.OF HOUR HOURLY RATE AMOUNT

-
-
-
-
-
-
-
-
TOTAL FOR LABOR -
TOTAL DIRECT COST -
INDIRECT UNIT COST
a. Overhead/Contingencies/Miscellaneous
b. Contractor's Profit
c. Value Added Tax

TOTAL INDIRECT COST -


TOTAL COST -
UNIT COST -
REHABILITATION OF MULTI - PURPOSE BUILDING
CAINGIN, BOCAUE, BULACAN

DETAILED UNIT COST ANALYSIS


DESCRIPTION UNIT COST
Metal Structure Accessories, Cross Bracing
176.85 Kgs. -
NAME & SPECIFICATION QUANTITY UNIT UNIT COST COST

-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
TOTAL FOR MATERIALS -
NAME AND CAPACITY NO. OF UNITS
NO.OF HOUR HOURLY RATE AMOUNT

-
-
-
-
-
-
-
-
-
-
TOTAL FOR EQUIPMENT -
DESIGNATION NO. OF PERSONS
NO.OF HOUR HOURLY RATE AMOUNT

-
-
-
-
-
-
-
-
TOTAL FOR LABOR -
TOTAL DIRECT COST -
INDIRECT UNIT COST
a. Overhead/Contingencies/Miscellaneous
b. Contractor's Profit
c. Value Added Tax

TOTAL INDIRECT COST -


TOTAL COST -
UNIT COST -
REHABILITATION OF MULTI - PURPOSE BUILDING
CAINGIN, BOCAUE, BULACAN

DETAILED UNIT COST ANALYSIS


DESCRIPTION UNIT COST
Metal Structure Accessories, Turn Buckle
2.00 Pc. -
NAME & SPECIFICATION QUANTITY UNIT UNIT COST COST

-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
TOTAL FOR MATERIALS -
NAME AND CAPACITY NO. OF UNITS
NO.OF HOUR HOURLY RATE AMOUNT

-
-
-
-
-
-
-
-
-
-
TOTAL FOR EQUIPMENT -
DESIGNATION NO. OF PERSONS
NO.OF HOUR HOURLY RATE AMOUNT

-
-
-
-
-
-
-
-
TOTAL FOR LABOR -
TOTAL DIRECT COST -
INDIRECT UNIT COST
a. Overhead/Contingencies/Miscellaneous
b. Contractor's Profit
c. Value Added Tax

TOTAL INDIRECT COST -


TOTAL COST -
UNIT COST -

Вам также может понравиться