ITEM # SCOPE OF WORK

V CONCRETE WORKS
LIBRARY CONCRETE SLAB FOR 2ND FLOOR CR & CONCRETE RAMP FOR PWD
A. CR DATA:
Total Width = 6.00 m 2nd floor slab
Width = 1.40 m For M&F Wastage Factor = 1.02
Length = 3.30 m Note: For Materials only
Thickness = 0.10 m Column Post side = 0.30 m
# of units = 2.00 units For 3 Units @2nd Flr
Width = 2.00 m For PWD Slab Area = 15.84 sq.m
Slab Volume = 21.60 cu.m
Proposed Type: Class A (1:2:4) Reinforced Concrete Two Way Slab
MATERIALS
1. CEMENT
cement = 21.60 x 9 x 1.02 wastage factor
cement = ### bags
2. SAND
sand = 21.60 x 0.50 x 1.02 wastage factor
sand = 11.02 cu.m
3. GRAVEL
gravel = 21.60 x 1.00 x 1.00 wastage factor
gravel = 21.60 cu.m

B. REINFORCED CONCRETE RAMP


DATA: RAMP SLA (Excluding Landing) RAMP Column 1 (Square)
@ slope 12˚ From footing to NGL
Width = 1.20 m Width = 0.25 m
Linear Meter Length = 6.44 m Length = 0.25 m
Thickness = 0.10 m Height = 1.07 m
# of set = 2.00 sets # of set = 1.00 sets
Volume = 1.55 cu.m Volume = 0.07 cu.m
DATA: RAMP Column 1 (Square) RAMP Column 1 (Square)
From footing to Ramp slab midpoint From footing to Higher Landing
Width = 0.25 m Width = 0.25 m (all sides)
Length = 0.25 m Length = 0.25 m
Height = 2.72 m Height = 2.36 m
# of set = 1.00 sets # of set = 4.00 sets
Volume = 0.17 cu.m Volume = 0.59 cu.m
DATA: RAMP Column 1 (Square) RAMP Landing
From footing to Terrace Connecting Terrace
Width = 0.25 m Width = 1.45 m
Length = 0.25 m Length = 1.45 m
Height = 3.50 m Thickness = 0.10 m
# of set = 2.00 sets # of set = 1.00 units
Volume = 0.44 cu.m Volume = 0.21 cu.m
RAMP Terrace RAMP Landing
Width = 1.60 m Ground & Halfway
Length = 3.03 m Width = 1.20 m
Thickness = 0.10 m Length = 2.45 m
# of set = 1.00 sets Thickness = 0.10 m
Volume = 0.48 cu.m # of set = 2.00 units
Volume = 0.59 cu.m
DATA: RAMP Beam RAMP Beam
RMB 1 @ Terrace RMB 1 Slant Length
Width = 0.20 m (all sides) Width = 0.20 m (all sides)
Length = 3.98 m Length = 6.44 m
# of set = 2.00 sets # of set = 4.00 units
Volume = 0.32 cu.m Volume = 1.03 cu.m
DATA: RAMP Beam RAMP Footing
RMB 2 @ higher Landing Width = 0.95 m
Width = 0.20 m (all sides) Length = 0.95 m
Length = 2.40 m Thickness = 0.25 m
# of set = 2.00 sets # of set = 7.00 units
Volume = 0.19 cu.m Volume = 6.00 cu.m
DATA: RAMP TIE BEAM DETAILS RAMP Railing Concrete Support
Thickness = 0.25 m both sides of Ramp
width = 0.20 m Width = 0.15 m
L.M. Length = 17.45 m L.M. Length = 41.79 m
FTB Vol = D x W x L Thickness = 0.10 m
FTB Vol = 0.87 cu.m Volume = 0.63 cu.m
Total Ramp Conc. Volume= Slab+Column+Beam+Landing +Tie Beam
Volume = 13.13 cu.m
Proposed Type: Class A (1:2:4) Reinforced Structural Concrete
MATERIALS
1. CEMENT
cement = 13.13 x 9 x 1.02 wastage factor
cement = ### bags
2. SAND
sand = 13.13 x 0.50 x 1.02 wastage factor
sand = 6.70 cu.m
3. GRAVEL
gravel = 13.13 x 1.00 x 1.00 wastage factor
gravel = 13.13 cu.m

C. REINFORCED CONCRETE BEAM FOR CR SLAB SUPPORT


DATA: BEAM DETAILS
Thickness = 0.30 m
width = 0.20 m
L.M. Length = 12.60 m
Beam Conc. Vol = D x W x L.M length
Beam Conc. Vol = 0.76 cu.m

MATERIALS
1. CEMENT
cement = 0.76 x 9 x 1.02 wastage factor
cement = 6.94 bags
2. SAND
sand = 0.76 x 0.50 x 1.02 wastage factor
sand = 0.39 cu.m
3. GRAVEL
gravel = 0.76 x 1.00 x 1.00 wastage factor
gravel = 0.76 cu.m

D. DRAINAGE CANAL
FLOORING
Width = 0.50 m
Linear Meter Length = 55.00 m
Thickness = 0.10 m
Volume = 2.75 cu.m
MATERIALS
1. CEMENT
cement = 2.75 x 9 x 1.02 wastage factor
cement = 25.25 bags
2. SAND
sand = 2.75 x 0.50 x 1.02 wastage factor
sand = 1.40 cu.m
3. GRAVEL
gravel = 2.75 x 1.00 x 1.00 wastage factor
gravel = 2.75 cu.m

E. CANAL CONCRETE LATERAL BRACE


Area 1 = 0.1355 sq.m Thickness = 0.0750 m
Area 2 = 0.0859 sq.m
Area Total = 0.2214 sq.m
Volume = 0.02 cu.m
MATERIALS
1. CEMENT
cement = 0.02 x 9 x 1.02 wastage factor
cement = 0.15 bags
2. SAND
sand = 0.02 x 0.50 x 1.02 wastage factor
sand = 0.01 cu.m
3. GRAVEL
gravel = 0.02 x 1.00 x 1.02 wastage factor
gravel = 0.02 cu.m

F. ADJUSTMENT IN VENT OPENING FOR AWNING WINDOW INSTALLATION


Original width = 0.20 m Original length = 3.70 m
Proposed width = 0.30 m Proposed length = 3.60 m
Adjustment = 0.10 m Adjustment = 0.10 m
Adjustment Volume = 0.0540 m3 To be removed
Adjustment Volume = Length Adjustment x Proposed width x Thickness
Adjustment Volume = 0.0045 m3 To be filled in
Proposed Type: Class A (1:2:4) Reinforced Structural Concrete
MATERIALS
1. CEMENT
cement = 0.0045 x 9 x 1.02 wastage factor
cement = ### bags
2. SAND
sand = 0.0045 x 0.50 x 1.02 wastage factor
sand = ### cu.m
3. GRAVEL
gravel = 0.0045 x 1.00 x 1.02 wastage factor
gravel = 0.0046 cu.m
Total Concrete Volume = Ramp + CR Slab + Adjustment Volume
38.25 cu.m

SUMMARY OF MATERIALS Total Conc.Vol = 34.74 cu.m


Item Qty say Qty Unit
AVR
Portland Cement Type I 0.04 say 1 bags
Washed Fine Sand 0.0023 say 0.50 cu.m
Crushed Gravel 3/4'' 0.0046 say 0.50 cu.m
Library
Portland Cement Type I 351.20 say 352 bags
Washed Fine Sand 19.51 say 20 cu.m
Crushed Gravel 3/4'' 38.26 say 39 cu.m
Sahara Compound (For CR slab) 198.29 say 199 bags