CONTINUATION OF ROOFING SYSTEM FOR ONE (1) BASKETBALL COURT, TWO (2) VOLLEYBALL COURTS AND ONE (1)

LAWN TENNIS Page 1

TECHNICAL SPECIFICATIONS

This set of Specifications shall govern the methods of construction and the kinds
of materials to be used for the CONTINUATION OF ROOFING SYSTEM FOR ONE (1)
BASKETBALL COURT, TWO (2) VOLLEYBALL COURTS AND ONE (1) LAWN TENNIS
shown in the plans and detail drawings.

The plans, detail drawings and these Specifications shall be considered as


complementing each other, so that what is mentioned or shown in one, although not
mentioned or shown in the other, shall be considered as appearing on both. The
reference line of the CONTINUATION OF ROOFING SYSTEM FOR ONE (1)
BASKETBALL COURT, TWO (2) VOLLEYBALL COURTS AND ONE (1) LAWN TENNIS
as specified on the plans. It covers from Footing/Foundation to the Roof extended
from Tennis Court to Volleyball Court. (please refer to plans)

GENERAL CONDITIONS

All parts of the construction shall be finished with first class workmanship, to the
fullest talent and meaning of the plans and these Specifications, and the entire
satisfaction of the Architect/Engineer.
The construction shall conform to all the requirements of the National Building
Code, as well as the local rules and regulations of the Office of the Building Official of
Naval, Biliran, Philippines.

ITEM NO. I - BIPSU STANDARD PROJECT BILLBOARD


- The Contractor shall provide a Standard Project Bulletin with a size of 4 feet
by 8 feet to be hang at the front of the Construction site.
CONTRACTOR’S SCHEDULE & PROGRESS REPORTING
a) Progress Reporting. Throughout the Contract duration, the Contractor shall
be responsible for taking detailed and accurate measurements of the actual
progress of all aspects of the works.
b) Weekly Progress Report. The Contractor shall maintain a Master Project
Schedule to summarize the status of the work; work in progress and the
percentage completed. This summary report shall be updated and issued at the
end of every week.
c) Contractor shall submit during the entire duration of the contract a weekly
progress report under cover of a transmittal sheet and shall include as a minimum
the following:
-
Management/Executive Report (Narrative)
-
Construction Progress
-
Forecast for the next one month/Daily-Monthly Weather Chart
-
Manpower (Management and Workforce)
-
Areas of Concern
-
Photographic Report
d) Meetings. Contractor Key Personnel shall meet with BiPSU representative
upon request of BiPSU to discuss matters related to the project. Contractor shall
arrange to record the minutes of meeting and submit for approval.

e) Minimum Mobilization of Key Personnel


CONTINUATION OF ROOFING SYSTEM FOR ONE (1) BASKETBALL COURT, TWO (2) VOLLEYBALL COURTS AND ONE (1)
LAWN TENNIS Page 2

Project Manager: full time from Contract award up to completion of Works, to be


mobilized on site during the construction phase;
Site/Construction Engineer: full time from initiation of site mobilization activities
up to provisional acceptance of the works
f) Testing Work. The testing work will include all tests and checks on:
- all concrete mixtures poured on footings, columns, flooring, slabs, beams and
required tests on concrete, structural steel members and reinforcing bars
- testing the effectiveness and workability of electrical lines

ITEM NO. II - CONSTRUCTION SAFETY AND HEALTH

The Contractor shall be responsible for safety of all workmen and other
persons entering the Works and shall at his own expense; where not stated
otherwise take all measures, subject to the Engineer's approval, necessary to
ensure their safety. Such measures shall include but not be limited to:
• Provision of safety and emergency regulations for fire, gas, and electric shock
prevention, together with rescue operation plan
• Safe control of flowing water
• Provision and maintenance of suitable lighting to provide adequate
illumination at place of work with appropriate spares and standby unit
• Provision and maintenance of safe, sound slings, pulleys, ropes, net and other
lifting device
• Provision of safe access to any part of the works.
• Provision of notices in local dialect temporarily or permanently during
construction at locations likely to be used by the public. Placement of such
notices shall depend on the existence of the nature of work in the vicinity.
These notices shall be in addition to any other statutory requirements
demanded of the Contractor
- The Contractor shall ensure that all his Employees are fully conversant
with the regulations, emergency and rescue procedures etc. and shall
enforce a rule that will instantly dismiss any employee committing a serious
breach of such regulations.

- The Contractor shall provide one (1) First Aider and (1) one Part-time Safety
Practitioner

Provision of First Aid/Medical Facilities

 Provision of first aid/medical facilities shall be made along with


commencement of work to provide quick medical service to injured/sick work
person, and employees. Services shall also include on-the-way service and
other arrangements required for taking them to the nearest hospital in case of
emergency.

 The scope of work shall include service of at least one part-time experienced
health worker/health assistant with a minimum of once a week full time site
visit as work assignment. The Contractor shall also supply and provide
adequate medicines and facilities required for standard first aid.

 The Contractor shall inform the Engineer regarding the medical facility
within a week after its establishment and operation.
CONTINUATION OF ROOFING SYSTEM FOR ONE (1) BASKETBALL COURT, TWO (2) VOLLEYBALL COURTS AND ONE (1)
LAWN TENNIS Page 3

Safety Equipment:
Safety Helmets
Safety Shoes
Safety Gloves
Safety Vest
Rubber Boots

ITEM NO. V - REMOVAL OF STRUCTURE & OBSTRUCTION


Refer to Standard Plan: All Removal of existing activities shall have barricades and
warning signs displayed prior to execution to ensure safety of every individual. No
execution of activity shall commence without the presence of a safety officer or an
Engineer in-charge on site. Activity shall cover existing Perimeter Wall including the
cyclone wires shall be removed completely wherein such removed materials shall be
properly displaced away from the passersby to keep the safety of every individual. Part
of the removed materials will be used as embankment for Item VI together with the
excavated earth. Additionally, existing structures outside the wall but within the
perimeter of the building shall be removed also on the course of implementing the
drainage canal system along the perimeter of the building.
- Dump Truck (12yd³)
- Air Compressor w/ Jackleg (Jackhammer) - Minor Tools

ITEM NO. VI - STRUCTURE EXCAVATION

All excavations shall be made to grade indicated in the drawings. Where the
construction site is covered with any kind of fill, the excavation for footings should be
made deeper until the stratum for safe bearing capacity of the soil is reached.

Whenever water is encountered in the excavation process, it shall be removed by


bailing or pumping, care being taken that the surrounding soil particles are not disturbed
or removed.

Equipment:
- Excavator w/ breaker (Cap. 0.28 cu.m.) - Dump Truck (12yd³)
- Diesel Powered Water Pump - Minor Tools

ITEM NO. VII – EMBANKMENT FROM EXCAVATION & REMOVED MATERIALS


(BACKFILLING, GRADING & COMPACTION)
Lay backfilling with a thickness of 0.20 m from the existing flooring, should be thoroughly
compacted and wetted by tamping or rolling. Materials to be filled in shall consist of
excavated soil from excavation activity mixed well with crushed removed materials from
Removal activity. This shall extend to area as indicated in the plan.

Equipment:
- Excavator with breaker (Cap. 0.28 cu.m.)
- Dump Truck (5 cu.m capacity)
- Plate Compactor
- Minor Tools
CONTINUATION OF ROOFING SYSTEM FOR ONE (1) BASKETBALL COURT, TWO (2) VOLLEYBALL COURTS AND ONE (1)
LAWN TENNIS Page 4

ITEM NO. VIII. GRAVEL BEDDING


All Reinforced concrete Structures below Natural Grade line (NGL) shall be filled in
completely with well compacted crushed gravel of size ¾’’ and thickness of at least 50
cm.
Structures include: Canal flooring, Column Footing, Wall Footing

Materials:
Crushed Gravel ¾”

ITEM NO. IX – REINFORCED CONCRETE

All concrete shall be mixed thoroughly until there is uniform distribution of the
cement and aggregates, and should be deposited as nearly as practicable in its final
position, care being taken to avoid segregation of the aggregates.

Water to be used for mixing concrete shall be clean and free from injurious
amount of oil, acids, alkalis, salt and other organic materials.

PROPORTIONING OF CONCRETE

All concrete work shall be done in accordance with the standard specifications for
plain and reinforced concrete as adopted by the Government. Cement to be used shall
be Portland Cement.

The following proportion of concrete mixture shall be used for the various parts of
the building:
Columns, footings, Wall Footing &
Footing tie beam - Class A (1 : 2 : 4)
Concrete Hollow Blocks - Class B (1 : 3)
Reinforced Concrete Beams and Slabs - Class A (1 : 2 : 4)
Concrete slab floor (suspended) - Class A (1 : 2 : 4)
The fine aggregate for concrete shall consist of natural sand, or of inert materials
with similar characteristics, having clean, hard and durable grains, free from organic
matter or loam.

The coarse aggregate for concrete shall consist of crushed rock or durable or
strong qualities or clean and hard gravel. Size of the coarse aggregate to be used shall
vary from 20mm to 40mm (3/4” to 1-1/2”)
Materials: Equipment:
- Portland Cement, Type I, 40Kg Concrete Mixer, 1-2.0 bagger
- Washed Fine Sand Concrete Vibrator
- Crushed Gravel ¾”

Description of Works: Columns, Footings, Footing Tie Beams, Beams, Suspended Slabs
(Concrete Bleacher Top), Slab on fill (Elevated floor) & Canal
Flooring.

CONCRETE SLABS ON FILL


CONTINUATION OF ROOFING SYSTEM FOR ONE (1) BASKETBALL COURT, TWO (2) VOLLEYBALL COURTS AND ONE (1)
LAWN TENNIS Page 5

Concrete slab on fill shall be poured on a gravel bed of not less than 50mm thick.
Each concrete slab course to be poured shall not be more than one meter wide, and
each course shall be poured alternately to the indicated floor finish.
Stainless Floor Drains size 4” in diameter shall be provided on the floor at
every 5-meter span of perimeter wall which will be attached to 4” in diameter pvc
Elbow with 4’’ to 2’’ Reducing bush and 2” diameter pvc pipe going to the drainage
canal outside the building. Please refer to the Structural Design as indicated in the
plans.
Materials:
4” Stainless Floor drain Bee hive type
4’’ pvc elbow, sch.40
4” to 2” Reducing bush, sch.40
2” diam. pvc pipe, sch.40

ITEM NO.X - MASONRY WORKS


Concrete Hollow Blocks: Non load bearing type with even texture and well-
defined edges, with a minimum compressive strength of 350 psi.
- Use 4” X 8” X 16” (125mm thick.) masonry unit
- Reinforcing bars and tie wires: use 12 mm in diameter vertical bars at 600mm
on center and 10 mm diameter horizontal bars at every third layer.
- All concrete hollow blocks shall be extended unless otherwise specified and
anchored up to the bottom of the slab, beams and columns.
- Mortar and plaster works: With mix and texture as required.
- Mortar shall be composed of one (1) part Portland cement and three (3)
parts sand.
- Plastering shall consist of one (1) part Portland cement and two (2) parts sand
for external and internal walls of the building including comfort rooms and Walls
Adjusted.
- Cement Plaster Finish with a thickness of 0.016m for both Internal walls &
External Walls of the building.
- Tile Works shall be well placed provided that no voids shall be present between
the tiles and the concrete surface.

Materials: Equipment:
- 4” Concrete Hollow Block (Interior Walls) Concrete Mixer, 1.5-2.0
bagger
- Portland Cement, Type I, 40 kg
- Washed Fine Sand
- 12mm dia.x 6m Deformed RSB Bars Grade 40
- 10mm dia.x 6m Deformed RSB Bars Grade 40
- 0.60m x 0.60m Glazed Tile
- 0.20mx 0.30m Glazed tile
- Tile Adhesive & Tile Joint

Description of Works: All Exterior walls - Plastering of 0.016 m at both sides


All Interior walls - Plastering of 0.016 m at both sides

ITEM NO. XI - REINFORCING STEEL BARS

All steel reinforcing bars to be used in this construction shall consist of round
deformed bars with lugs or projections on their sides to provide greater bond between
the concrete and steel. All steel reinforcing bars to be used shall be:
CONTINUATION OF ROOFING SYSTEM FOR ONE (1) BASKETBALL COURT, TWO (2) VOLLEYBALL COURTS AND ONE (1)
LAWN TENNIS Page 6

Materials: Equipment:
12 mm ø x 6 m Deformed RSB
16 mm ø x 6 m Deformed RSB Rebar Cutter
10 mm Ø x 6m Deformed RSB Hacksaw Blade
G.I Tie Wire Ga.#16
Heavy Duty Hacksaw Blade

All steel reinforcing bars shall be accurately placed and secured against
displacement by tying them together at each bars intersection with Gauge # 16
galvanize iron wire.
The steel reinforcing bars indicated for footings, columns, slabs, beams girders
and other concrete members shall all conform to the number, size and spacing as
indicated in the drawings or schedule of steel reinforcements.
No metal reinforcement shall be installed in place unless it is free from rust, scale
or other coatings, which will destroy or reduced the bond with concrete. Use Rust
converter in removing the presence of rust prior to fabrication of Steel Reinforcement.
For Safety Hand Railings at the Reinforced Concrete Ramp, use 2” diameter
Stainless Steel Pipe Welded in accordance to satisfactory quality using stainless welding
rod with distances indicated on the drawing.

Description of Works: Columns, Column Footings, Wall & Wall footing, Footing Tie
Beams, Beams, Suspended Slabs (Bleacher Top), Slab on fill,
Canal Wall & Canal flooring, Bleachers Support, Sag Rod & Turn
buckle

ITEM NO. XII- WELDING works

All work shall comply with all applicable codes including National
Mechanical Code as adopted by the local government.
Provide all materials, tools and labor required to perform the work shown
on the drawing and described in these specifications. If any material, devices,
equipment or related accessories not included on the plans but are required to complete
the system and installation shall be included of the contractor. Mechanical contractor
shall not proceed to any installation due to changes without proper submittal and
approval. All materials to be used shall be new and shall conform to the
Reference Code and Standards Layout dimension shown in drawing are approximate
only and intended to serve as an installation guide. Dimension may be adjusted as
required to meet field condition.

Submit AS-BUILT Plan when all installation is done.

Work shall include fabrication and installation of steel trusses, Louver Windows &
Door, Safety Harness, Entrance Door Roof Purlins and Support

Materials Equipment
2" x 3" x 1.2 mm thick Rectangular Tube Portable Welding Machine
2" x 4" x 1.2 mm thick Rectangular Tube Generator Set 1 KVA
2" x 4" x 1.5 mm thick Rectangular Tube Oxyacetylene Cutting outfit
2" x 3" x 1.5 mm thick Rectangular Tube Electrical Saw 12” diam.
Steel Plate 12 mm Thick x 4' x 8’ Crawler Crane 46-50T

Expansion Bolt 4''


1/4" thick x 4" x 4" Angle Bar
1/4" thick x 2'' x 2'' Angle Bar
CONTINUATION OF ROOFING SYSTEM FOR ONE (1) BASKETBALL COURT, TWO (2) VOLLEYBALL COURTS AND ONE (1)
LAWN TENNIS Page 7

1/4" thick x 1/2" x 1-1/2" Angle Bar


1/4” thick x 0.15 m x 0.20 Gusset Plate
Heavy Duty Welding Rod
Stainless Welding Rod
12 mm ø x 6 m Stainless Round bar
12 mm ø x 6 m Deformed RSB
16mm∅ Stainless Steel Safety Harness anchor ring w/ 1/2" thick. Base Plate
Turn Buckle
12 mm thick Steel Buckle Plate
16mm ∅ x 6 m Steel Round Bar, Grade 40

ITEM NO. XIII - FORMS AND SCAFFOLDING

All forms for concrete works shall be properly braced or connected together so as
to maintain the correct position and shapes of the concrete members. Forms shall be
constructed sufficiently tight to prevent bulging and seepage of water.

Forms shall not be removed until the concrete has attained sufficient strength to
support its own weight and any loads that may be placed on it. Side forms of beams and
girders maybe removed earlier than the bottom forms but additional post or shoring
must be placed under the beams or girders until they have attained the strength.

Materials:
1/4'' thck x 4' x 8' US Marine Plywood
2" x 2" x 12' Coco Lumber
2" x 2" x 10' Coco Lumber
2" x 6" x 12' Coco Lumber
2" x 3" x 12' Coco Lumber
# 4 CWN
# 2 CWN
# 1 1/2 CWN
G.I Tie Wire Ga.# 16
Metal Scaffolding

ITEM NO. XIV – ROOFING WORKS


Roofing works shall be implemented according to plan design and measurements.
Roof Sheets shall be locked with J-Bolts attached to C-Purlins (Refer to plans) with
Insulation sheets.
Entrance Door Roofing shall have a slope of 2% using whole Polycarbonate sheet
6mm thick sealed with breather tape on the edge and attached on top of C-Purlins using
self-tapping screw and sealed on the wall with Roof Sealant.
Materials:

6 mm. THK. Pre-Painted Dura Curved Rib Type Roofing Long Span (22.94 m x 1.2
m)
Stainless J Bolt 1/4 x 2-1/2 with bonded washer and hex nut
C-Purlins 2'' x 6'' x 6 m, 0.8 thick
G.I Flashing
50 mm x 50 mm x 6m x 4mm thick Angle bar
Stainless Hexagon Bolts with Nut and Washer 8mm (1/4") ø x 65 mm
Reflective Bubble insulation (Single Bubble Double Foil) 1.0 m x 50.0 m
Twin Wall Polycarbonate Sheet 6mm (1/4″) thick Bronze 6mm x 5.80 m x 1.22 m
Polycarbonate Roofing Screw (self-Tapping) w/ Rubber washer #14 x 1-1/2″
CONTINUATION OF ROOFING SYSTEM FOR ONE (1) BASKETBALL COURT, TWO (2) VOLLEYBALL COURTS AND ONE (1)
LAWN TENNIS Page 8

Anti -Dust Breather tape for Poly carbonate sht 25mm x 33m
Silicon Sealant, 300 ml Clear
0.40mm x 19mm x 50 mm x 5m Single metal furring
Metal Screw 2"

ITEM NO. XV – PAINT WORKS

Paint works shall conform to proper painting procedure where surface area to be
painted must be free from dust, water and rust for steel surfaces. For presence of rust,
rust converter must be applied prior to painting. Fresh or new concrete or masonry shall
be treated with neutralizer and sealant prior to primer (2 coats) and top coat finish (2
coats). Rectangular tubes shall be painted with Red Oxide Primer (2 coats) and Metallic
Gray Acrylic Paint Finish (2 coats). (Refer to plans)

Materials:
For Steel Trusses
Metal Primer Red Oxide
Quick dry Enamel Red
Paint Thinner
Roller Brush 2 inches
Paint Brush 2-1/2 inches
Paint Tray 7 inches

For Walls
Flat Wall latex
Semi-Gloss Flat Latex
Concrete Neutralizer
Concrete Sealer (Acrytex Primer)
Roller Brush 7 inches
Paint Tray 7 inches
Acrytex Cast

For Columns
Flat Wall latex
Semi-Gloss Flat Latex
Concrete Neutralizer
Concrete Sealer (Acrytex Primer)
Roller Brush 7 inches
Paint Brush 2-1/2 inches
Paint Tray 7 inches
Acrytex Cast

For Rubberized Flooring


Epoxy Sealer Primer
Epoxy Reducer
Rubberized Floor CRB Crystal Blue
CRB Reducer
Roller Brush 7 inches
Paint Tray 7 inches
Paint Brush 2-1/2 inches
Rubber floor CRB Marking Yellow
Rubber floor CRB White

For Rectangular Tube Louver window


CONTINUATION OF ROOFING SYSTEM FOR ONE (1) BASKETBALL COURT, TWO (2) VOLLEYBALL COURTS AND ONE (1)
LAWN TENNIS Page 9

Metal Primer Red Oxide


Quick dry Enamel Red
Paint Thinner
Roller Brush 2 inches
Paint Brush 2-1/2 inches
Paint Tray 7 inches

For Rectangular Tube Louver door, Roof purlins & frame support
Metal Primer Red Oxide
Quick dry Enamel Red
Paint Thinner

ITEM NO. XVI – ELECTRICAL & AUXILIARY WORKS


All electrical works shall have done accordance with the provisions of the latest
edition of the Philippine Electrical Code.
The electrical works herein shall be done under the direct and immediate
supervision of a duly qualified licensed electrical engineer.
All wires shall be of type letter THHN for power and lighting system and be Color
Coding. Smallest branch circuit wire shall be 3.5mm² in raceway 15mmø size conduit.
Method of wiring shall be as follows; unless otherwise specified in drawings. All branch
circuit homerun for power and lighting shall not be combined in the same raceway. All
convenience outlet will be 3 prong and be grounded, and
The wiring of A/C unit shall be 5.5 mm² or higher wire size depending the size of
aircon capacity needed in raceway 15mmø size conduit and rated 2Phase or 3Phase,
30AT and 20AT.
All Electrical conduits must be recessed or concealed properly with the standard
length of supports and fittings.
Layout dimension shown in drawing are approximate only and intended to serve
as an installation guide. Dimension may be adjusted as required to meet field condition.
Any material, devices, equipment or related accessories not included on the plans
but are required to complete the system and installation shall be included of the
contractor. Electrical contractor shall not proceed to any installation due to changes
without proper submittal and approval.
Submit AS-BUILT Plan when all installation is done.

The Electrical Contractor’s scope of work shall be followed:


 Supply and Installation of ECB’s and Panel Boards w/ branch circuit breakers
 Supply and Installation of Electrical Cabling Works
 Supply and Installation of Conduit, Boxes, Fittings and Frame Works
 Supply and Installation of Main & Sub-Feeders Three Phase Secondary Line
w/ grounding
 Supply and Installation of Lighting & Power Fixtures and Accessories
 Supply and Installation of Fire Detection & Alarm System (Conventional)
 Supply and Installation of CCTV Systems and Accessories.
 Supply and Installation of Sound System Equipment’s
Materials/Equipment:
1. ECB’s, Panel Boards, & Wires
 300AF Tapping Point with 150AT MCCB, 3P, 230V, Powder
Coated enclosure copper busbar, with secondary cover,
terminal lugs, and grounding Terminal
CONTINUATION OF ROOFING SYSTEM FOR ONE (1) BASKETBALL COURT, TWO (2) VOLLEYBALL COURTS AND ONE (1)
LAWN TENNIS Page 10

 8 Branches Panel Board w/ Ground Terminal, 40AT Center Main


Bolt-on Type, 50AF, 3P, 230V, MCCB, Branches: 6-15AT & 2-
20AT CB
 8 Branches Panel Board w/ Ground Terminal, 40AT Center Main
Bolt-on Type, 50AF, 3P, 230V, MCCB, Branches: 5-15AT & 3-
20AT CB
 3.5mm² THHN Copper Wire 150m/roll
 8.0mm² THHN Wire 150m/roll
 30mm² THHN Wire
 60mm² THHN Wire
2. Conduits, Boxes, Fittings, & Frameworks
 1/2" Ø x 3m PVC Electrical Conduit Thick
 1/2" Ø PVC Electrical Connector w/lock nut
 1" Ø x 3m PVC Electrical Conduit Thick
 1" Ø PVC Electrical Connector w/lock nut
 1 1/2" Ø x 3m (50mmØ) PVC Pipe Thick
 1 1/2" Ø PVC Elbow
 1 1/2" Ø PVC Locknut, bushing, & coupling
 1/2" Ø Metalic Flexible hose Thick, 30m/roll
 1/2" Ø Straight Connector
 Utility Box Poly, Deep type
 Junction Box Poly, Deep type
3. Lighting & Power Fixtures and Accessories
 200W Round LED High Bay Light 24000Lm, 133Lm/W, IP65,
110-277VAC, w/ reflector, box cover, and accessories
 10W IP65 Flood Light LED SMD Wash Spot Light Outdoor type
(Waterproof)
 12W LED bulb with lamp holder
 Two Gang Switch
 Weatherproof Universal Duplex Outlet with ground (3-prong)
 Rechargeable Twin head Emergency light
4. CCTV Systems and Accessories
 1080P HDCVI Dome Camera 4megapixel, 120 dB Wide
Dynamic Range, 30m Max IR length, 24 VAC/ 12VDC Power
Supply
 DVR 16 Channel, Flat Type
 Video Balun (Power+Video Transfer)
 RG6 Siamese Cable w/ power DC (305m/roll)
 HDD 4TB
 Centralized Power Supply
 40 inches LED TV
 UPS 1200VA
 2-Feet Wall -Mounted Data Cabinet
 Roughing-Ins (PVC pipes, support, fittings, and other
accessories)

5. Fire Detection & Alarm System (Conventional)


 8-inch 240V Weatherproof Fire Alarm Bell (Red)
 Waterproof 12V 120Ma Safe Security Alarm Strobe Signal
Safety Warning Red Flashing Led Light
 Manual Pull/Push Station
CONTINUATION OF ROOFING SYSTEM FOR ONE (1) BASKETBALL COURT, TWO (2) VOLLEYBALL COURTS AND ONE (1)
LAWN TENNIS Page 11

 6 Zone - Fire Alarm Control Panel


 1.25mm2 Twisted TF Wire (150mtrs/roll)
 Roughing-Ins (PVC pipes, support, fittings, and accessories)

6. Sound System Equipment for each Court


 250 Watts Powered Speaker (Wharfedale)
 Speaker Bracket (Imix)
 Dynamic Microphone P6-58
 Shelded Wire Stereo Quantum
 XLR Female (Amphenol)
 XLR Male (Amphenol)
 Weatherproof Universal Duplex Outlet with ground (3-prong)

7. Other Expenses (Overall)


 Testing, Commissioning, and Installation charges
 Miscellaneous and Consumables (Electrical tape, rubber tape,
Tec screw, solvent, elbows, G.I wires, support, fittings and etc.)

ITEM XVII.SPORT EQUIPMENT/IMPROVEMENT


The following are the specifications for the identified sport equipment improvement
facilities.:
1. 2 sets for two basketball courts - "Basketball Backstop Including Installation Hydro
Play club portable Basketball backstop; High Quality Hydraulic basketball stand,
reclining rings and nets, 3 years Warranty, Materials: (1. backboard material:
Tempered Glass Backboards) Backboard dimensions: 1800mm*1050mm*12mm Pole
Diameter: 165mm round (standard size) Base size: 1600mm*1000mm 2. Pole
Material: Steel with powder-coated paint finish to prevent rust 3. Base Material:
international Q235 Steel"
2. 5 sets for each court - Digital Electronic LED Indoor Wireless Multi-Purpose
Scoreboard with External Shot Clock, Wireless Handheld Controller, Airhorn and Shot
Clock cables (29 inches (W) x 21 inches (H) x 3 inches (D) for scoreboard
3. 4 sets - Basketball Coaching Board - 2 Sided - with Numbers (Erasable) Easily
Portable - Magnetic Markers, Magnetic Pitch Pad & Clip on Planner Pad Included

ITEM NO. XVIII – PLUMBING WORKS


All plumbing works shall be done in accordance with the provisions of the latest
edition of the National Plumbing Code.
See plans for proper location of fixtures.
Materials:
Stainless Floor drain (Bee Hive) 4"
PVC Sanitary Elbow 4" ø x 90˚, sch 40
PVC Sanitary Pipe 2" ø x 3mts, sch 40
PVC Reducer 4" ø x 2" ø x 3mts, sch 40
Teflon Tape 2"