Вы находитесь на странице: 1из 8

STRENGTH WEAKNESSES

SPACIOUS OUTSKIRT AREA


WAY TO AIRPORT 2 KM PUBLIC TRANSPORT FREQUENCY
POSH AREA DEVELOPING AREA
NEAR BY, HOSPITAL, SCHOOLS, MALL
AMENITIES, CLUB HOUSE, SWIMMING POOL,
THEATRE

OPPORTUNITIES THREATS
INCREMENT ON PRICE LOWER QUALITY
GOOD LOCALITY CRIME
EXTEND HOUSE IN FUTURE ACCIDENTS
PROJECT PROBLEM TREE

FINANCIAL CRISIS MARKET RATE INCREASE

MACHINERY BREAKDOWN PROJECT PROBLEM TREE

QUALITY OF MATERIAL ZERO TRANSPERANCY


EM TREE

LAND PRICE

UNWANTED WEATHER CONDITION

LACK OF RESOURCES
GOALS AND OBJECTIVES
PROJECT TITLE
CLIENT

PROJECT BACKGROUND

PROJECT OBJECTIVES

PROJECT BUDGET
PROJECT START
PROJECT FINISH

PROJECT INCLUDES
GOALS AND OBJECTIVES
70, WIND PARK BUNGALOW
MR. MEET BHATIYA

It is a well architecture projects on outskirt of city with all the advanced facilities and
for 5 person family house. The project given to the high reputed contractor for
constructing a house within a year. It is spacious inside as well as outside, good
landscape will be a part of the house with different types of trees and plants with
hanging jula.

The aim is to get good quality of work as per indian standard with in the calculated
budget amount. Handover the project to client within deadline. And if it is possible to
make decrese financial expenses with using alternatives

$ 1,29,536
1/1/2020
18/12/2020
Deals with architect and structure engineer,
cost estimation
market survey
Bar bending schedule
check list for activity
legalisation
drawing passing by local municipality
quality planning
risk planning
documentation
Material handling
time planning
CONTENT
sr no. description pg. no
1 Project initiation
1.1 description of the situation
1.2 Goals , objectives and problem tree
1.3 Swot analysis
1.4 stakeholder analysis
2 project organizational structure
3 project planning
3.1 time planning
3.1.1 work breakdown structure
3.1.2 gantt chart
3.1.3 network diagram
3.1.4 critical path evaluation
3.2 resouces planning
3.3 cost planning
3.4 quality planning
3.5 risk planning
3.6 control point identification card
4 project implementation / evaluation
5 conclusion
PROJECT MANAGER

1. ARCHITECT 2. STRUCTURE ENGINEER


3. SR. ENGINEER

3.1 JR. ENGINEER 3.2 SUPERVISOR

3.1.1 CARPENTER 3.2.1 SKILLED LABOUR


3.1.2 FITTER 3.2.2 UNSKILLED LABOUR

Вам также может понравиться