Вы находитесь на странице: 1из 18

Mainstreaming Gender in the

Design
g and Monitoring
g
Framework
Peter Robertson COSO/PPMU
Learning New Approaches to Gender
Mainstreaming in Project Design
26 October 2010
The views expressed in this paper are the views of the author and do not necessarily reflect the views or policies of the Asian
Development Bank (ADB), or its Board of Governors, or the governments they represent. ADB does not guarantee the accuracy of
the data included in this p
paper
p and accepts
p no responsibility
p y for anyy consequence
q of their use. The countries listed in this p
paper
p do
not imply any view on ADB's part as to sovereignty or independent status or necessarily conform to ADB's terminology.

1
Managing for Development Results
Overall
International Agreements and Development
Commitments (MDGs etc
etc.)) Effectiveness

National Poverty
Po ert Reduction
Red ction Strateg
Strategy

Development
Results based Country
Results-based Impact
Partnership Strategy (CPS)

Sector Road Maps

Development
Programs Projects,
Programs, Projects TAs O t
Outcome/ /
2
Outputs
Design & Monitoring Framework

Design Performance Data Assumptions


Design Summary Targets Sources & Risks

IMPACT A&R
R
Results
lt Chain
Ch i
OUTCOME A&R

Objectives OUTPUT A&R

Problem ACTIVITIES & MILESTONES INPUTS


analysis
l i

Stakeholder
analysis
3
P3M Project Performance Report

4
Design
Summary
1st Step - Outcome
The Outcome
Th O t describes
d ib the
th change
h resulting
lti
from achieving all outputs by project completion
IMPACT
- performance change of organization,
institution, system, or
- behavioral change of beneficiaries
OUTCOME
9One
One (1) succinct outcome statement
9 Does not include means to achieve: i.e.
OUTPUTS
through,
g by,
y leading
g to, resulting
g in…
9 Phrased as an end situation – not an action
ACTIVITIES 9 Refers to beneficiary group or institution who
makes the change
9Is necessary but not sufficient to achieve the
p
Impact
Design
Summary
2nd Step - IMPACT
The Impact links the project with the CPS
IMPACT describing a higher result level – is same as or
supports sector or thematic outcomes in the
CPS andd roadmap.
d It outlines
tli the
th expected
t d
beneficial consequences on a defined group of
OUTCOME people or for sector performance. IT IS NOT
poverty reduction,
reduction economic growth…
growth
9 One (1) succinct impact statement
OUTPUTS
9 Does not include means to achieve: i.e. through,
by, leading to, resulting in….
ACTIVITIES 9 Phrased as an end situation – not an action
9 Is achievable 3-5 years after project completion
9 Reflects a direct means-end relationship (causal
linkage)
Design
Summary
3rd Step - Outputs
Outputs
O t t are the
th physical
h i l and/or
d/ tangible
t ibl goods
d
and/or services delivered by the project
IMPACT
Deliverables = Project Scope

9 Each output has to be necessary to achieve the


OUTCOME
outcome.
9 Phrased as an end situation – not an action
OUTPUTS 9 Achievable during the life of the project
9 Causal link to outcome

ACTIVITIES 9 No components – they are headings for a


collection of outputs.
9 Includes an output for “project management”
Design
Summary
4th Step - Activities
9 Action statements – what the project will DO!
IMPACT 9 Reflects the approach to be used to deliver the
output and is the basis for implementation plans
9 Lists key activities for each output
OUTCOME
9 Shows completion date/milestone per activity
y
9 Procuring goods, hiring consultants, reporting,
OUTPUTS monitoring, accounting, auditing etc. are general
tasks to be done by Project Management and are
included under the project management output
ACTIVITIES 9 Primary data sources – i.e. surveys to be carried
out as part of the project – must be included as
activities under the management output
Design 5 th Step - Inputs
Summary

IMPACT
9 A summary of main resources to carry
out the activities,
activities i.e.
i e civil works
works,
equipment, consulting services,
OUTCOME personnel, O & M
9G
Grouped d by
b financier
fi i – ADB,
ADB
Government, co-financier, beneficiaries,
OUTPUTS private sector, NGO

ACTIVITIES INPUTS
Indicators and
Performance Targets
• Indicators answer “how do I know that the
impact, outcome and outputs have been
achieved”
hi d”
• Indicators outline what will be measured.
• Performance
P f t
targets
t specify
if quantity
tit andd time
ti –
how much by when.
• Baseline data represents the starting point.
point
• Where appropriate gender disaggregate measures.
Data Sources and Reporting
Mechanisms
9 Where can information on the status of each
indicator be obtained (secondary data)
9 Who produces the data
9 How is the information collected (primary data),
i.e. sample or full surveys, project records,
participatory or rapid rural appraisal
methods, focus group discussions,
field observations, balanced score cards.
9 Hints Each indicator requires
q a data source
Project reports are not data sources.
If primary data will be used (i.e. through a
survey) is this included as a key activity?
survey),
Assumptions and Risks
9 A & R are outside the project’s
project s control
9 Are mitigating measures reflected in the DMF? Is this
elaborated in the RRP section IV.F Table 4?
9 Are assumptions and/or risks at the correct level?
9 Are there duplications at different levels?
9 Are special assurances, if outside the project, included
as assumptions?
9 Are A & R specific
p and verifiable as they
y need to be
monitored?
Graph Financial Modalities
2009 sample

Loan TA Grant MFF All


Impact 46% 70% 73% 53% 61%
Outcome 45% 58% 66% 49% 54%
Outputs 37% 52% 56% 52% 48%
Activities 29% 44% 51% 33% 39%
Indicators 38% 25% 54% 47% 35%
Data Sources 24% 33% 29% 20% 28%
Assumptions and Risks
Assumptions and Risks 51% 61% 78% 71% 62%

90%

80%

70%

60%

50%
Loan
TA
40%
Grant
MFF
30%
All

20%

%
10%

0%
13
Impact Outcome Outputs Activities Indicators Data Sources Assumptions and Risks
Gender Equity Theme
¾the project outcome directly addresses
gender equality and/or women's
empowerment

¾explicit gender equality and/or women


women'ss
empowerment outcome(s) and/or gender-
specific performance outcome indicators and
activities in the project DMF

14
Effective Gender Mainstreaming
• specific gender design features are included in the
majority of project outputs and/or components to
facilitate and ensure women's participation and access
to project benefits.
benefits Most of these outputs/components
should have at least 3 gender design features or
mechanisms.
mechanisms
• gender targets and performance and monitoring
indicators
d cato s in tthee pproject
oject DMF. Majority
ajo ty means
ea s 50% or
o
more of project components or outputs (inclusive of
50%).

15
GAP and DMF
How is the GAP reflected in
the DMF?
• Philippines Social Protection Support Project
• Vietnam Ha Noi Rapid Transit System
• Vietnam Ho Chi Minh Rapid Transit System
• P
Papua New
N Guinea
G i TTown El
Electrification
t ifi ti
Investment Project

17
Thank You

18

Вам также может понравиться