Construction of the 202 x 102-foot concrete slab for the Kiel Center ice rink, St. Louis, was complicated by requirements for a flat, level surface with no joints
BY ANNE BALOGH
lacing the ice rink floor for of polyethylene heating pipe. This Placing the Concrete
P the Kiel Center, St. Louis’
new sports and entertain- ment facility, was one of the biggest challenges of the build- ing’s construction. The 664,240- piping system, which carries warm b ri n e, is designed to prevent frost heave of the subgrade. On top of the polyethylene pipe, crews placed 8 inches of sand, then covered the Two The pour began at 7 a.m. and was completed at about 12:30 p.m. truck-mounted pumps—a 31-meter pump sta- boom
tioned at one end of the rink and a
square-foot facility, which opened sand with 4 inches of rigid poly- 32-meter pump stationed at the last fall, is home to the St. Louis styrene insulation as additional opposite end—placed the con- Blues professional hockey team. protection from frost heave. c re t e. Both pumps operated con- Because smooth ice is critical for Once the ice rink floor insulation tinuously throughout the pour. hockey play, uniform flatness and was in place, workers began in- Placement started at one end of levelness of the slab are essential. stalling the 14 tons of rebar required the rink, and the boom truck on But the greatest challenge, says to reinforce the floor. This rebar mat the opposite end was equipped Dennis Ahal, president of Ahal supports the 131⁄2 miles of 1-inch-di- with enough pipe sections and Contracting Co., Bridgeton, Mo., ameter steel re f ri g e rant piping hose to transport concrete to the was to pour the 202 x 102-foot, 8- needed for ice production. Finally, a pour area. As the pour proceeded inch-thick slab monolithically. Be- layer of 4x4-inch wire mesh was in- to the opposite end, the pipe and cause of an elaborate system of re- stalled to help minimize shrinkage hose were disconnected section by f ri g e rant piping embedded in the cracking of the concrete. section from the first pump, then slab to produce and maintain the ice, the slab could have no joints. Ahal Contracting tack- led the 536-cubic-yard pour last June with joint- venture partner Williams Concrete Contractors Inc., St. Louis. The pour was completed in just 51⁄2 hours using two pumps.
1312⁄ Miles of Pipe and
14 Tons of Rebar Before concrete place- ment could begin, seve ra l layers of fill, piping, insu- lation, and reinforcement had to be installed. The first layer—3 feet of sand placed directly on top of Workers placed concrete for the joint-free ice rink floor in just 51⁄2 hours. To meet the b e d ro c k — p rovided a critical flatness and levelness requirements, they used two laser-controlled, 52-foot- cushion for the next layer wide vibratory screeds to strike off the concrete. MIX DESIGN FOR ICE RINK FLOOR
Material Per Cubic Yard
Type C fly ash 80 lb. Type I portland cement 611 lb. Meramec sand 1,268 lb. #67 limestone 1,723 lb. Water 304 lb. Water-reducing admixture 3 oz.
Specified compressive strength 5000 psi
Water-cement ratio 0.44 Concrete unit weight 147 pcf Slump 6 in.
attached to the other pump to ex- levelness of the concrete surface
tend its reach. with a transit. Immediately after “We really only had one opportu- finishing, a computerized measur- nity to do the job right,” says Ahal. ing device was used to gauge flat- Because of the heavy re i n f o rc e- ness and levelness. ment and miles of piping in the To retard shrinkage of the slab floor, tearing out improperly in- and minimize cracking, a slow 14- stalled concrete would have been day cure was specified. The slab extremely difficult and costly. was covered with polyethylene The 5000-psi mix design for the sheeting to foster curing, and then slab concrete included fly ash for lu- soaker hoses under the polyethyl- brication (see table). “The fly ash al- ene were turned on periodically for lowed us to pour a little bit higher the first seven days to keep the sur- slump than normal and still main- face moist. tain a good water-cement ratio,” says Ahal. A high-slump mix was impor- Credits tant on this project because there is only a 2-inch gap between adjacent Construction manager: J. S. Alberici Construction Co. Inc., St. Louis sections of refrigerant piping. Hand- held vibrators with small-diameter Rink contractor: Cimco of Toronto heads were used to consolidate the Concrete subcontractors: Ahal Con- concrete. tracting Co., Bridgeton, Mo.; Williams Concrete Contractors Inc., St. Louis Concrete Finishing and Curing To control the flatness and level- Ready mix supplier: Five-Star Con- crete, St. Louis ness of the floor and aid in consoli- dation, finishers used two laser- Pump manufacturers: Elba Concrete controlled, 52-foot-wide vibratory Pumps Inc., Rock Hill, S.C.; Putzmeis- screeds to strike off the concrete. ter America Inc., Gardena, Calif. This project marked the first use of Screed manufacturer: Allen Engineer- l a s e r- c o n t rolled screeds in the St. ing, Paragould, Ark. Louis area. Finishers monitored the PUBLICATION # C950472