Академический Документы
Профессиональный Документы
Культура Документы
The Site Supervisory Team shall be headed by the Site Agent and assisted by
the Site Supervisors to ensure that the requirements of approved designs are
strictly implemented.
2.0 MATERIALS
2.1 Concrete
Steel bars of Grade 460 weldable to be used in the works shall comply with
B.S. 4449: 1997. The steel bar to be used in this work shall be based on
materials supplied by Main-Contractor.
3.1.1 The Contractor shall use the block pegging drawing as endorsed by licensed
surveyor in accordance with architect’s setting out plan. Temporary Bench
Mark (TBM) and the established TBMs will now be the datum for daily use for
surveying of ground level (To be provided by main contractor)
3.1.2 All pile positions will be pre-surveyed and properly marked using suitable
steel bars. The peg(s) will be planted such that about 25-50mm of the peg
protruded above the ground level.
3.1.3 Every peg position will be randomly checked again by the Contractor’s
Supervisor prior to boring.
Contiguous bored pile walls are formed by constructing continuity of reinforced concrete
bored piles. The piles are reinforced with steel rebar and construct similarly as per
methodology construction of bored pile.
As similarly of the construction of bored pile, peg will be given by surveyor (Provided
by Main Contractor) for the center position of each bored pile. The gap between two
bored piles is typically 50mm.
The vibro-hammer drives a casing into the ground, leaving about 1 meter length of
the casing protruding from the ground
The auger, a drilling tool, cuts and removes the soil within the casing to form primary
borehole. The soil surrounding the borehole is supported by the casing. If the casing
is not long enough to reach the required depth in the ground, water will be use as
stability fluid to support the soil below the casing.
The crane lifts up the steel cage and places it within the borehole.
Step 1.0 – 6.0 are repeated till the entire length of the bored pile wall construction is
completed.
100mm diameter grout columns are provided behind the interfacing area of contiguous
bored piles to act as water-barrier system to prevent loss of water and fine materials behind
the contiguous bored pile wall. A gunite wall with BRC will be formed in front of the
contiguous bored pile wall to further block any ingress of water or alternatively skin wall will
be cast against the contiguous bored pile wall.