Академический Документы
Профессиональный Документы
Культура Документы
PROJECT TITLE
DOCUMENT TITLE
DOCUMENT NUMBER
OML30-ERU-PRS-DOC-00002-00
Page 21 of 35
ERIEMU Well 11T Surface Facilities Upgrade in OML 30 Process Simulation Report Review
Document No:
OML30-ERU-PRS-DOC-00002-
PROCESS 00
SIMULATION REPORT
Revision No:
F02
Abbreviations
API American Petroleum Institute
ANSI America National Standard Institute
ASME American Society of Mechanical Engineer
BDEP Basic Design and Engineering Package
BDV Blowdown Valve
BFD Basis for Design
BOPD Barrel of Oil per day
CFD Computational Fluid Dynamics
CGR Condensate to Gas Ratio
CITHP Closed-in Tubing Head Pressure
Client NPDC/SNRL
DED Detailed Engineering Design
E&I Electrical & Instrumentation
EPCIC Engineer, Procure, Construct, Install, & Commission
EPCIC Contractor Mavi Energy Dev. Company Ltd/Pavillion Petroleum Ltd
Consortium
ESD Emergency Shut-Down
ESDV Emergency Shut-Down Valve
HIPS High Integrity Protective System
HTRI Heat Transfer Research Institute
FCV Flow Control Valve
FEED Front End Engineering and Design
FS Flowstation
HAZID Hazard Identification
HAZOP Hazard and Operability
HC Hydrocarbon
HEOSL Heritage Energy Operational Services Ltd
HP High Pressure
IPF Instrumented Protective Function
IPS Instrumented Protective System
LP Low Pressure
LTI Lost Time Injury
Mbopd ‘000 barrels of oil per day
MEDCL Mavi Energy Development Company Ltd
MMSCFD Million Standard Cubic Feet per Day
NPDC Nigerian Petroleum Development Company Ltd
OSD Operational Shutdown
Page 2 of 35
ERIEMU Well 11T Surface Facilities Upgrade in OML 30 Process Simulation Report Review
Document No:
OML30-ERU-PRS-DOC-00002-
PROCESS 00
SIMULATION REPORT
Revision No:
F02
Page 3 of 35
ERIEMU Well 11T Surface Facilities Upgrade in OML 30 Process Simulation Report Review
Document No:
OML30-ERU-PRS-DOC-00002-
PROCESS 00
SIMULATION REPORT
Revision No:
F02
Table of Contents
Abbreviations………………………………………………………………………………………………………………………………………………………………………………………2
1.0 INTRODUCTION ................................................................................................................................................................................ 6
Page 4 of 35
ERIEMU Well 11T Surface Facilities Upgrade in OML 30 Process Simulation Report Review
Document No:
OML30-ERU-PRS-DOC-00002-
PROCESS 00
SIMULATION REPORT
Revision No:
F02
Page 5 of 35
ERIEMU Well 11T Surface Facilities Upgrade in OML 30 Process Simulation Report Review
Document No:
OML30-ERU-PRS-DOC-00002-
PROCESS 00
SIMULATION REPORT
Revision No:
F02
1.0 INTRODUCTION
1.1 Project Background
Eriemu Well 11T, previously an oil well, was re-completed in 2010 as a gas well
to provide lift gas for other oil wells in Eriemu field, but has remained shut in
due to high pressures recorded for the well at re-completion. The Closed-in
Tubing Head Pressure (CITHP) of the well is 2844.2 Psig, a pressure much higher
than the capacity of existing flowline, and inlet facilities in Eriemu flowstation.
This project is aimed at safe evacuation of the Eriemu well 11T fluid in line with
NPDC specification and process control/safeguarding principles as well as,
protecting the downstream surface facilities.
The project includes but not limited to Engineering, Procurement,
Construction/ Installation, Testing and Commissioning of the following:
- A new 4’’ x 800m Carbon Steel API 5L X52, Sch. xxs flowline.
- One (1) no. Water Bath Heater.
- One (1) no. Shell and Tube Heat Exchanger
- A Corrosion inhibition package.
- Pressure Control Valve at the Eriemu XHP Separator inlet.
- Various pneumatic field instruments, to enable safe production of the
well.
- Associated Civil, Instrumentation, and Electrical installations for
effective functioning, and integration of the new facilities with existing
Eriemu F/S facilities.
- Integration of the new equipment with existing Eriemu F/S facilities.
1.3 Definitions
The words following are used in the contexts defined against them, in this
document:
Page 6 of 35
ERIEMU Well 11T Surface Facilities Upgrade in OML 30 Process Simulation Report Review
Document No:
OML30-ERU-PRS-DOC-00002-
PROCESS 00
SIMULATION REPORT
Revision No:
F02
Page 7 of 35
ERIEMU Well 11T Surface Facilities Upgrade in OML 30 Process Simulation Report Review
Document No:
OML30-ERU-PRS-DOC-00002-
PROCESS 00
SIMULATION REPORT
Revision No:
F02
Units of Measurements
Description Unit
wall Thickness Mm
Area m²
Liquid Volume m³
Density kg/m³
Temperature C
Viscosity cP
Page 8 of 35
ERIEMU Well 11T Surface Facilities Upgrade in OML 30 Process Simulation Report Review
Document No:
OML30-ERU-PRS-DOC-00002-
PROCESS 00
SIMULATION REPORT
Revision No:
F02
Page 9 of 35
ERIEMU Well 11T Surface Facilities Upgrade in OML 30 Process Simulation Report Review
Document No:
OML30-ERU-PRS-DOC-00002-
PROCESS 00
SIMULATION REPORT
Revision No:
F02
Page 10 of 35
ERIEMU Well 11T Surface Facilities Upgrade in OML 30 Process Simulation Report Review
Document No:
OML30-ERU-PRS-DOC-00002-
PROCESS 00
SIMULATION REPORT
Revision No:
F02
OML30-ERU-PRS-DOC-
3 Utility Report
00009-00
OML30-ERU-PPL-DOC-
4 Pipeline Design Report
00004-00
Page 11 of 35
ERIEMU Well 11T Surface Facilities Upgrade in OML 30 Process Simulation Report Review
Document No:
OML30-ERU-PRS-DOC-00002-
PROCESS 00
SIMULATION REPORT
Revision No:
F02
4.1 Terrain
The Eriemu facility is situated on a relatively even surface land area with a
good drainage system but with seasonal swamp occurrences
4.2 Temperatures
- Mean minimum temperature: 23 oC (73oF)
- Minimum temperature: 18oC (65oF)
- Mean maximum temperature: 31oC (88oF)
- Peak temperature: 41oC (106oF)
- Humidity: 100%
4.3 Rainfall
Heavy rainfall can be expected in the wet season during the months of April
through October.
- Average annual rainfall: 3800mm (150-inch)
- Mean maximum hourly rainfall: 100mm (4-inch)
4.6 Lightning
Lightning is frequent in the rainy season.
4.9 Dust
During November-December of every year, which is the harmattan season,
the atmosphere is laden with extremely fine dust (particle size of 5 microns or
less), which can penetrate equipment, block air filters etc.
Page 12 of 35
ERIEMU Well 11T Surface Facilities Upgrade in OML 30 Process Simulation Report Review
Document No:
OML30-ERU-PRS-DOC-00002-
PROCESS 00
SIMULATION REPORT
Revision No:
F02
The Lowest Design Temperature (LDT) calculated for the piping between
(100-UZV-111) and (100-XZV-107) after depressurization is 18.9oC. The minimum
temperature of piping downstream the (100-HCV-001) after blowdown is -
75oC. Hence, austenitic stainless steel is the material recommended for piping
downstream the (100-HCV-001).
Page 13 of 35
ERIEMU Well 11T Surface Facilities Upgrade in OML 30 Process Simulation Report Review
Document No:
OML30-ERU-PRS-DOC-00002-
PROCESS 00
SIMULATION REPORT
Revision No:
F02
Table 1: Well 11T Compositions at Flowing conditions on dry and wet basis
Page 14 of 35
ERIEMU Well 11T Surface Facilities Upgrade in OML 30 Process Simulation Report Review
Document No:
OML30-ERU-PRS-DOC-00002-
PROCESS 00
SIMULATION REPORT
Revision No:
F02
Design Flowrate
Item
(MMSCF/D)
Flowline 26
XHP Separator 13
The design flow for the XHP Separator is 13MMSCFD, a minimum flow of
4.3MMSCFD was considered for the simulation report.
Eriemu
243.3 63.89 29.83 195 196
Well 11T
Page 15 of 35
ERIEMU Well 11T Surface Facilities Upgrade in OML 30 Process Simulation Report Review
Document No:
OML30-ERU-PRS-DOC-00002-
PROCESS 00
SIMULATION REPORT
Revision No:
F02
Inner Wall
Design Outer
Diamet Thickness Length
Pipeline pressure Diamet
er WT incl. (km)
(barg) er (mm)
(mm) CA (mm)
Well 11T Please refer to the Pipeline Design Report
to(100U (document OML30-ERU-PPL-DOC-00004-00) for
ZV-111) details of the flowline selection and sizing.
Page 16 of 35
ERIEMU Well 11T Surface Facilities Upgrade in OML 30 Process Simulation Report Review
Document No:
OML30-ERU-PRS-DOC-00002-
PROCESS 00
SIMULATION REPORT
Revision No:
F02
The total flowline length is 875.68m which is due to the total straight pipe
length and the equivalent length due to fittings.
Page 17 of 35
ERIEMU Well 11T Surface Facilities Upgrade in OML 30 Process Simulation Report Review
Document No:
OML30-ERU-PRS-DOC-00002-
PROCESS 00
SIMULATION REPORT
Revision No:
F02
Page 18 of 35
ERIEMU Well 11T Surface Facilities Upgrade in OML 30 Process Simulation Report Review
Document No:
OML30-ERU-PRS-DOC-00002-
PROCESS 00
SIMULATION REPORT
Revision No:
F02
Page 19 of 35
ERIEMU Well 11T Surface Facilities Upgrade in OML 30 Process Simulation Report Review
Document No:
OML30-ERU-PRS-DOC-00002-
PROCESS 00
SIMULATION REPORT
Revision No:
F02
100-FCV-105 was used to choked down the well fluid from 130 barg to 72
barg and 31.84oC which is the operating pressure of XHP separator (V-105)
Page 20 of 35
ERIEMU Well 11T Surface Facilities Upgrade in OML 30 Process Simulation Report Review
EPCIC FOR ERIEMU WELL 11T SURFACE FACILITIES
UPGRADE PROJECT IN OML 30
TO GASLIFT MANIFOLD
(100-HCV-002) (100-HCV-001)
TO AFIESERE COMP.
STATION
P
I
WELL-11T
GAS
WELLHEAD
(105-UZV-002) (105-LCV-001)
(P-1810A/B)
FIGURE 1: Process Schematic for Eriemu Well-11T Surface Facilities Upgrade Project
Page 21 of 35
ERIEMU Well 11T Surface Facilities Upgrade in OML 30 Process Simulation Report Review
EPCIC FOR ERIEMU WELL 11T SURFACE FACILITIES
UPGRADE PROJECT IN OML 30
Page 22 of 35
ERIEMU Well 11T Surface Facilities Upgrade in OML 30 Process Simulation Report Review
Document No:
OML30-ERU-PRS-DOC-00002-
PROCESS 00
SIMULATION REPORT
Revision No:
F02
CASE 2A
Pipeline will be considered as being in contact with Wet Sand throughout the
pipeline length at an ambient temperature of 23oC and at normal operating
flow rate of 4.3 MMSCFD.
Case 2B
Pipeline will be considered as being in contact with swamp water and wet
sand throughout the pipeline length at an ambient temperature of 18 oC and
at normal operating flow rate of 4.3 MMSCFD.
Case 2C
The dry season scenario will be modeled as pipeline in contact with wet sand
throughout its length at an ambient temperature of 31oC and at normal
operating flow rate of 4.3 MMSCFD.
Page 23 of 35
ERIEMU Well 11T Surface Facilities Upgrade in OML 30 Process Simulation Report Review
Document No:
OML30-ERU-PRS-DOC-00002-
PROCESS 00
SIMULATION REPORT
Revision No:
F02
8.0 RESULT
For stream properties, please refer to Heat and Material Balance report
(OML30-ERU-PRS-DOC-00001-00)
Page 24 of 35
ERIEMU Well 11T Surface Facilities Upgrade in OML 30 Process Simulation Report Review
Document No:
OML30-ERU-PRS-DOC-00002-
PROCESS 00
SIMULATION REPORT
Revision No:
F02
hydrate formation zone and also reduce the operational and economic
effects of operating these heaters at higher duty should these temperature
i.e (44oC and 50oC) are increased further.
Page 25 of 35
ERIEMU Well 11T Surface Facilities Upgrade in OML 30 Process Simulation Report Review
Document No:
OML30-ERU-PRS-DOC-00002-
PROCESS 00
SIMULATION REPORT
Revision No:
F02
Fluid Velocity@26mmscfd
Page 26 of 35
ERIEMU Well 11T Surface Facilities Upgrade in OML 30 Process Simulation Report Review
Document No:
OML30-ERU-PRS-DOC-00002-
PROCESS 00
SIMULATION REPORT
Revision No:
F02
8.6.1 Start-Up
Option 1: During back start, pressure decreases across the (100-FCV-106) and
(100-FCV-105) from 195barg upstream to 0barg downstream (see figure 1).
The LDT related to this scenario has been calculated using an adiabatic flash
of the entire composition and assuming an ambient temperature of 18oC
(conservative approach). This results in an LDT of -74oC downstream of both
valves.
This is a very conservative approach that considers the flowline as infinite. In
reality, long before the pipe wall temperature reaches -74oC, the gas
upstream (100-FCV-106) and (100-FCV-105) shall be at normal flowing
temperature of (22.84oC), leading to a minimum temperature of -65.5oC.
Option 2: The back pressurization of piping downstream (100-FCV-106) and
(100-FCV-105) using fuel gas to 10barg during black start set the pressure
downstream (100-FCV-105) to 10 barg. This results in an LDT of -63.4oC
downstream of both valves, assuming conservative ambient temperature of
18oC. With the Well fluid gas flowing at a temperature of 23.2oC at upstream
of the (100-FCV-106) and (100-FCV-105), leads to a LDT of -55.7oC
Page 27 of 35
ERIEMU Well 11T Surface Facilities Upgrade in OML 30 Process Simulation Report Review
Document No:
OML30-ERU-PRS-DOC-00002-
PROCESS 00
SIMULATION REPORT
Revision No:
F02
related to this scenario has been calculated using an adiabatic flash of the
entire composition and assuming an ambient temperature of 18oC
(conservative approach).
The blowdown was done for 4 hours with an orifice area of 7.77 mm2 and the
peakflow calculated is 1070 kg/h, while LDT calculated for downstream and
upstream piping (100-HCV-002) is -66.8oC and 17.69oC.
Page 28 of 35
ERIEMU Well 11T Surface Facilities Upgrade in OML 30 Process Simulation Report Review
Document No:
OML30-ERU-PRS-DOC-00002-
PROCESS 00
SIMULATION REPORT
Revision No:
F02
Page 29 of 35
ERIEMU Well 11T Surface Facilities Upgrade in OML 30 Process Simulation Report Review
Document No:
OML30-ERU-PRS-DOC-00002-
PROCESS 00
SIMULATION REPORT
Revision No:
F02
Page 30 of 35
ERIEMU Well 11T Surface Facilities Upgrade in OML 30 Process Simulation Report Review
Document No:
OML30-ERU-PRS-DOC-00002-
PROCESS 00
SIMULATION REPORT
Revision No:
F02
10.0 REFERENCE
1. Design Report of Eriemu Well 11T Surface Facility over-pressure
Protection Project, FOP-TPEF-ERIF1-PX8380-00001-000
2. Eriemu Flowstation PEFS For Wellhead 11t (Gas Well), OML30-ERI-PRS-
DRG-00040-01_A01
3. Eriemu Flowstation PFD For Inlet Manifold and Process Facilities Tie-In,
OML30-ERI-PRS-DRG-00030-01_A01
4. Eriemu Flowstation PEFS For Inlet Manifold and ESD Valves, OML30-ERI-
PRS-DRG-00040-02_A01
5. API 14E_Recommended Practice for Design and Installation of Offshore
Production Platform Piping Systems, 5th Edition.
6. Condensate study report [Heritage Energy Eriemu-11T Recomb-final
rep]
Page 31 of 35
ERIEMU Well 11T Surface Facilities Upgrade in OML 30 Process Simulation Report Review
Document No:
OML30-ERU-PRS-DOC-00002-
PROCESS 00
SIMULATION REPORT
Revision No:
F02
Page 32 of 35
ERIEMU Well 11T Surface Facilities Upgrade in OML 30 Process Simulation Report Review
Document No:
OML30-ERU-PRS-DOC-00002-
PROCESS 00
SIMULATION REPORT
Revision No:
F02
Page 33 of 35
ERIEMU Well 11T Surface Facilities Upgrade in OML 30 Process Simulation Report Review
Document No:
OML30-ERU-PRS-DOC-00002-
PROCESS 00
SIMULATION REPORT
Revision No:
F02
Appendix II: Eriemu Well 11t Flowline and Facilities Simulation for (Case 1)
Page 34 of 35
ERIEMU Well 11T Surface Facilities Upgrade in OML 30 Process Simulation Report Review
Document No:
OML30-ERU-PRS-DOC-00002-
PROCESS 00
SIMULATION REPORT
Revision No:
F02
Appendix III: Eriemu Well 11t Flowline and Facilities Simulation for (Case 2)
Page 35 of 35
ERIEMU Well 11T Surface Facilities Upgrade in OML 30 Process Simulation Report Review