Client: Indian Hotels Co. Ltd.

Project: Taj Mahal Hotel, New Delhi

PROJECT CODE: ID0004
PROJECT NAME: TAJ MAHAL HOTEL, NEW DELHI
WORK ORDER NO. : IHCL/TMH/CHAMBER/SCG/2019-20/30
WORK DETAILS : Civil & ID works for Guest Floors renovations at Taj Mahal Hotel, Man Singh Road, New Delhi
DAVI CERTIFICATE NO
CONTRACTOR RA BILL NO. : RA-01

WORK DONE SUMMARY

Work Done Amount (Rs.)


Sr.No. Description Workorder Amount Remarks
Previous Bill This bill Cumulative Amount

A Annexure A

Repair & Civil Works + Structural Works 6,170,512.58 - 570,024.92 570,024.92

A Total for Annexure A 6,170,512.58 - 570,024.92 570,024.92

B Annexure B
12th Floor-Dining Area + Meeting Room &
20,122,135.50 - 977,210.16 977,210.16
Gym Area

B Total for Annexure B 20,122,135.50 - 977,210.16 977,210.16

C Annexure C
12th Floor-Wet Area + Kitchen 5,183,190.00 - 125,859.24 125,859.24

C Total for Annexure C 5,183,190.00 - 125,859.24 125,859.24

D Annexure D
13th Floor-Lounge Area + Offices 16,548,138.35 - 1,113,284.89 1,113,284.89

D Total for Annexure D 16,548,138.35 - 1,113,284.89 1,113,284.89

E Annexure E
Washroom + Lift Lobby 7,319,461.25 - 258,370.07 258,370.07

E Total for Annexure E 7,319,461.25 - 258,370.07 258,370.07

F Annexure F

Loose Furniture 3,978,382.00 - 592,186.00 592,186.00

F Total for Annexure F 3,978,382.00 - 592,186.00 592,186.00

G GRAND TOTAL 59,321,819.68 - 3,636,935.29 3,636,935.29 G= Sum A to F

Less : Debits (if any)

H1 GRAND TOTAL 59,321,819.68 - 3,636,935.29 3,636,935.29 H1= H - Debits

I1 Add: CGST : @ 9% on Item ( G1 )


I2 Add: SGST : @ 9% on Item ( G1 )
I3 Add: IGST : @ 18% on Item ( G1 ) 10,677,927.54 - 654,648.35 654,648.35
Sum of
I Total GST Amount 10,677,927.54 - 654,648.35 654,648.35 I1, I2, I3

Net Total Certified (Including


J 69,999,747 - 4,291,584 4,291,584 J = (H1+I)
Taxes)
Note:
1.Taxes Should be checked by A/c department.
2.TDS & WCT should be cheked & Confirm by Client.

Prepared By: Aman Srivastava Contractor Sign & Stamp :

03/05/2020 Summary Sheet


Client: Indian Hotels Co. Ltd. Project: Taj Mahal Hotel, New Delhi
PROJECT CODE: ID0004
PROJECT NAME: TAJ MAHAL HOTEL, NEW DELHI
WORK ORDER NO. : IHCL/TMH/CHAMBER/SCG/2019-20/30
WORK DETAILS : Civil & ID works for Guest Floors renovations at Taj Mahal Hotel, Man Singh Road, New Delhi
DAVI CERTIFICATE NO 0%
CONTRACTOR RA BILL NO. : RA-01

ANNEXURE A- REPAIR, CIVIL & STRUCTURAL WORKS

AS PER WORKORDER BILL QUANTITY BILL AMOUNT


Sr.
Description Unit Qty
No.
Rate Amount Previous bill This bill Cumulative Previous bill This bill Cumulative

A REPAIR WORKS
Note:
The rate for all demolishing and dismantling to include carting and disposing
of
Thethe debris
Site shouldat the
be site at designated
handed dumping
over in a clean grounds
state; removing andallfurther
debristofrom
the
approved
Necessaryplace,
Site propping, outside of theand
shoring hotel
/ orpremises,
underpinningby the NDMC
shall or any other
be provided for the
relevant
safety
Use wallof authority.
the adjoining
cutter/ breakerwork or property,
in place of handwhich
tools is to be left in tact, before
dismantling
The CONTRACTOR and demolishing
shall take is necessary
taken up and the workfrom
approvals shall beHotel
the carried out in
A.1 such a
Providingway
Management that
andor no damage
any temporary
fixing is caused
other Authority to the adjoiningof
beforebarricading
partitions/ disposing work
area or property.
themade
debris.of hard Sqm 20.00 3,075 61,500.00
wood,
Uptoframe
90%work and 6mm
on Pro-rata commercial
completion plywood on one side including all,
of works 2,768 - - 20.00 20.00 - 55,350.00 55,350.00
supporting and fixing arrangement and finished
10% upon completion of entire work and handing over with a flex sheet or printed 308 - - - - - -
A.2 wallpaper, as directed
Covering glass panes of towards
windows/ the doors/
guest facing side,bytoplywood
openings be maintained
or tin sheets Sqm 84.00 967 81,228.00 - - -
through
or pvc the required
sheets or as period and
directed, to the satisfaction
maintaining the aestheicof project
beautymanager.
of the area, to
Upto 90% on Pro-rata completion of works 870 - - 84.00 84.00 - 73,105.20 73,105.20
avoid
10%damage
upon to shutters of
completion and glasswork
entire panes
and including
handing using
over P.O.P. to clean 97 - - - - - -
Rateglass
the shall( be
if inclusive),of
required dismantling
removal of thetemporary
same afterpartition
completionand of
taking
work, always
A.3 Providing
from and making
site/ and
hotel premises core
at cutting in RCC Up to 200
the designated mm thickness, - - - - -
cleaning,
including making good local damage if place
any toand
the disposal
satisfactionsafely.
of the
a 50 to 100 cutting
mm diasteel reinforcement wherever required, cleaning, removing Nos 11.00 2,219 24,409.00 - - - - -
project
debris manager.
b For to at
150anmm
100 dimensions, indicated
please
dia location outside the site on
check measurements etcsite.
complete as per drawing Nos 11.00 3,117 34,287.00 - - - - -
c & directions
200 to 250 mm of the
diaproject manager. Nos 11.00 5,073 55,803.00 - - - - -
A.4 Dismantling, Demolishing, Cutting, Breaking, Removing & Cleaning Existing - - - - - -
a Items Carefully
Removing and Stacking
of existing flooring the useable
in areas Materials
including at sitematerials,
bedding or as Instructed
wooden Sqm 2200.00 198 435,600.00 - - - - -
including
planks
Upto 90% necessary tool, tackles,
on Pro-rata machineries,
completion of works requisite scaffolding, carting 178 - - 313.70 313.70 - 55,901.47 55,901.47
away10% debris
uponfrom site timeoftoentire
completion time or
workdisposing the material
and handing over at the municipal 20 - - - - - -
grounds as designated and specified by the project manager for the
b Removing of existing doors including door frames Sqm QRO 460 - - - - -
following Items. (The rate shall include all leads, lift and height)
c Removing of existing partitions/ paneling Sqm 2700.00 152 410,400.00 - - - - -
Upto 90% on Pro-rata completion of works 137 - - 283.06 283.06 - 38,721.99 38,721.99
10% upon completion of entire work and handing over 15 - - - - - -
d Removal of existing internal plaster with racking out the masonry joints. Sqm QRO 152 - - - - -
e Removing of existing internal 100 mm thick brick work Sqm QRO 161 - - - - -
f Removing of existing internal 150 mm thick brick work Sqm QRO 221 - - - - -
g Removing of existing internal 230 mm thick brick work Sqm 1000.00 286 286,000.00 - - - - -
Upto 90% on Pro-rata completion of works 257 - - 208.30 208.30 - 53,617.23 53,617.23
10% upon completion of entire work and handing over 29 - - - - - -
h Removing of existing counters - bar counters, vanity, etc. Sqm 100.00 1,381 138,100.00 - - - - -
Upto 90% on Pro-rata completion of works 1,243 - - 5.57 5.57 - 6,919.22 6,919.22
10% upon completion of entire work and handing over 138 - - - - - -
i Removing of existing curtains with pelmet Sqm 500.00 92 46,000.00 - - - - -
Upto 90% on Pro-rata completion of works 83 - - 4.93 4.93 - 408.14 408.14
10% upon completion of entire work and handing over 9 - - - - - -
j Removing of existing false ceiling with structural steel supports, framings, Sqm 2200.00 231 508,200.00 - - - - -
lightUpto
fittings,
90%wooden beams,
on Pro-rata etc. all complete
completion of works 208 - - 1,006.81 1,006.81 - 209,315.87 209,315.87
10% upon completion of entire work and handing over 23 - - - - - -
k Dismantling of RCC work Sqm 200.00 1,105 221,000.00 - - - - -
l Removing of existing Storage with all fixtures Sqm 300.00 691 207,300.00 - - - - -
Upto 90% on Pro-rata completion of works 622 - - 8.80 8.80 - 5,470.54 5,470.54
10% upon completion of entire work and handing over 69 - - - - - -
m Removal of the existing mezzanine floor including the false ceiing, wooden Sqm 150.00 341 51,150.00 - - - - -
stairs,
Upto floor
90%andonrailings,
Pro-ratapaneling, structural
completion steel members, etc. all
of works 307 - - 150.00 150.00 - 46,035.00 46,035.00
complete
10% upon completion of entire work and handing over 34 - - - - - -

TOTAL OF REPAIR WORKS 2,560,977.00 - 544,844.67 544,844.67

03/05/2020 ANNEX-A
Client: Indian Hotels Co. Ltd. Project: Taj Mahal Hotel, New Delhi
PROJECT CODE: ID0004
PROJECT NAME: TAJ MAHAL HOTEL, NEW DELHI
WORK ORDER NO. : IHCL/TMH/CHAMBER/SCG/2019-20/30
WORK DETAILS : Civil & ID works for Guest Floors renovations at Taj Mahal Hotel, Man Singh Road, New Delhi
DAVI CERTIFICATE NO 0%
CONTRACTOR RA BILL NO. : RA-01

ANNEXURE A- REPAIR, CIVIL & STRUCTURAL WORKS

AS PER WORKORDER BILL QUANTITY BILL AMOUNT


Sr.
Description Unit Qty
No.
Rate Amount Previous bill This bill Cumulative Previous bill This bill Cumulative

- - - - -
B CIVIL WORKS
B.1 Providing & doing well Burnt (First Class) Brick masonary in all location with -
conventional
a. 150mm thick type brickbricks
work in cement mortar 1:4 in superstructure including Sqm 34.00 1,381 46,954.00 - - - - -
striking
Uptojoints,90% on racking
Pro-rata out completion
joints, watering, of works scaffolding and cleaning etc. 1,243 - - 4.33 4.33 - 5,384.24 5,384.24
complete.
10% upon Ratecompletion
also included providing
of entire work &and laying
handingcast in over situ RCC band beam 138 - - - - - -
(Patli) in M:15 at 1200mm c/c with 2nos 8mm dia reinforcement including
b. 100mm thick brick work Sqm 11.00 NQ - -
shuttering, deshuttering, curing, cleaning etc. completed at all heights and
c. 230mm thick
satifaction to thebrick project work manager. Sqm 115.00 1,612 185,380.00 - - - - -
B.2 Providing and applying avg. 12 - 15mm thk. (avg.) internal plaster in cement Sqm 67.00 415 27,805.00 - - - - -
B.3 sand mortar
Providing and(1:4) for allCement
applying plain / curved sand rough surfaces of brick
Plaster 1:4,/ 12-15mm
block / RCC thickwalls
over Sqm 134.00 415 55,610.00 - - - - -
and finishing
Internal
Upto 90%the
Walls on same (smooth
/ Columns
Pro-rata / completion or broom)
RCC Surfaces of workstoinline
correct
10%level line,
uponandlevel plumb
completion & toplumb,
smooth
of 374 - - 8.66 8.66 - 3,236.00 3,236.00
making
finish
entire
10% of
accordingedges,
workcompletion
upon and corners,
to specifications.
handing sill,
of over jambs,
entireRate soffits,
workshall grooves,
and include
handingfor pattas
over etc. as
providing G.I.chicken per 42 - - - - - -
drawings
mesh made & relevant
outlaying specifications
of galvanised iron of including
nominal all necessary surface
B.4 Providing and average 75mm thick PCCthickness
1:3:6 with 0.3520mm mm down with a Zinc Sqm 147.00 424 62,328.00 - - - - -
preparation,
coating of 120 scaffolding,
gms per Sqmincludingat the p/f of PVC of
junctions chicken
masonry mesh andof nominal works
concrete
aggregate
Upto 90% complete
on Flooring
Pro-rata at the toilet
completion of floor area
works 10% after
upon the drainage
completion works. 382 - - 18.40 18.40 - 7,021.44 7,021.44
thickness
to a width 0.35
ofinclude
100 mm to with
125mm a Zinc coatingtying
including of 120 gms perwith
in position Sqmsuitable & width ofof100
The costupon
entire
10% to
work and
completion the labour,
handing over
ofstaging,all the
entire material, accessories over atcomplete as per 42 - - - - - -
to 125mm
clamps/screws, at all junctions
necessary of RCC &work masonry and handing
scaffolding work,
and hacking
curing ofallconcrete
levels and
B.5 the instruction
Providing and satisfaction of the project manager. Sqm 218.00 576 125,568.00 - - - - -
surface to &receive
elevations laying
etc., IPS flooring
plaster,
complete aswatering,at anycuring,
directed. location
Rate shall asinclude
cleaning specified
etc.for of
complete 75mmhacking,
proper at all
thickness
levels
Upto
cleaning and (avg.)
90%
and onwith
heights
as allcement
Pro-rata
directed complete
by concrete
completionas per
project nominal
ofthe
manager. works mix of
directions
10% ofproportion
upon project1:2:4
thecompletion manager.
of 518 - - 18.40 18.40 - 9,538.56 9,538.56
(cement
entire
10% upon : work
Sandcompletion
: Aggregate)
and handing in correct
of over
entire worklevel and /handing
slope atover all levels as per 58 - - - - - -
B.6 architectural drawings
Waterproofing includingfollowing
Works including mixing of: concrete in mixer, lifting, shifting to Sqm 74.00 1,027 75,998.00 - - - - -
the work location, compacting / vibrating, finishing smooth to the satisfaction
B.7 Providing and laying light weight AAC/ foam concrete blocks under sunken Cum 15.00 3,222 48,330.00 - - - - -
of the project
a) Waterproofing manager,treatment curing, and
: Cleaning cleaning
the the surface
surface our etc.
toramming complete.
requirements,
B.8 portion
Providing of floors
Pest control up to the
and depth of 300mm
Anti-termite including
treatment: Drill atand Sqm 210.00 231 48,510.00 - - - - -
(Mode
providing of measurements
and applying :Plan
polymer area
based of Flooring
flexible shall
cementitious beholes
measured the for
waterproof
junction
consolidation
of wall and floorall complete
at 1sqft as directed
intervals & by
inject the
in project
approved manager.
anti termite and
payment
coating consisting of acrylic polymer mixed with cement, applied in 2 coats
sealing
TOTAL the OF holes
CIVILthereafter
WORKS with white cement and spray all exposed walls 676,483.00 - 25,180.25 25,180.25
in
andtheflooring
form ofsurface slurry over with the antiRCC slab and
termiticide spray on bytheappointing
vertical surfaces a specialized up to a
height
agency1.50 as per mtr.the above F.F.L. or as
specifications instructed,
mentioned byincluding
the Bureau grouting
of Indian of,
C STRUCTURAL
construction joints,WORKS honeycombs locations, cracks etc. with crystalline based
Standards and Agencies specifications (whichever is higher), for General
C.1 Preparing
non shrink
Civil, Plumbing,/shop drawings,
cementitious Drainage grout obtaining
andtotimber/full consultant's/
saturation,
Carpentrymaking client approval,
works, small
Gypsum filletssupplying,
(wattas)
related -
fabricating,
around
For
work, Deck the delivering
periphery
slab, roof
including a 10extensionat site,
junctions
year guarantee hoisting
ponding
including and
under withfixing
columns,water,
suitable in position
curing
trusses,
undertaking including
testing
extension for
on stampall
ofwater MT 12.71 161,120 2,048,205.39 - - - - -
C.2 temorary
tightness
existing
Providing
paper etc, staging
by
members,
and ponding
complete fixingandsite supporting
with
welding
chemical
as water
directed. etc
grout work
for “and
7ofdays making
etc.,including
Hilti” for variousall structural
bars (12steel
protection to 25mm,work in Nos 40.00 1,796 71,840.00 - - - - -
C.3 accordance
screed/plaster
hilti
Mode make of with
chemical:
measurement etc the design,
complete
Re-500
to be drawings
and
max.
on 10 depthyrs
carpet-area
Supplying and installing in position Metal Decking Sheets ( Tata Bluescope and directions
guarantee
300 mm)
of floor on of
STAMP
including
and the
not project
PAPER
drilling
the area manager.
the ofOF
holes- Sqm 196.69 1,243 244,484.18 - - - - -
Thetherate
Rs.100/-
in of steel
complete.
concrete forwork shall
Measurement
anchoring include
the 1 coat
given
new is of redper
surface
reinforcement oxide
area primer
etc. (This isand 2 coats
basic of
C.4 surface
0.7mm
Providing
enamal
treated
thick Smartdeck
fabricating
paint assembly,
51 @
& erecting
welding,
7.35 kg/sqm)
structural
jointing,
as
steelwork
building
IS:1079
up in hotallsections
new
/complete
Galvanized
rolled sections
using
as per
for MT 2.00 230,171 460,342.00 - - - - -
requirement
the drawings contractor
and the to provide
directions detail product specification and
C.5 Steel
the
Providing (as per
staircase IS:277)
with
& laying grated
non Galvanized
traysgrout
shrink alloffinish.
the
bracings,
of project
The
FOSROCK manager.
metal
bolts, /sheets
plates
Sunanda to as
etc. be fixeddetailed
per
/ concrete
Krishna to/ the
MYK Cum 0.50 50,638 25,319.00 - - - - -
plates/
application.)
structural rolled section
one layer (including
on the cost
mother ofslabfasteners,
and 2nd nuts,
layer bolts
after and washers) layer
C.6 drawing
Laticrete
Reinforcement
and
after /framework
or
fabrication
piping
as per
Ardex
works for
out the
Endura
RCC with
of the
under workthe help
directions
Make
following
the GPof of
including
stone. 2,Thru-bolts
the
types project
undersupplying,
of
with
manager
side
structural
a minimum
ofdelivering
basesteelatplates
all heights
and
material
diameter
etc.
storing
with allofof
atand - - - - - -
½" and
levels shall
including be hot-dipped
removing galvanized
the scales or
&ofgrade stainless
burrs, of steel.
cleaning with Silicon
phosphoricwashers to
locations
various
Thermo
connections andusing
diameters heights
Mechanically as as required
required
Treated
plates, channels at
bars and
site of
and directions
work
angles,Fe-415 gussetthe
transporting, project
manufactured
plate, manager.
decoiling,
connectionby acid, MT 1.00 82,862 82,862.00 - - - - -
be used on
marking,
straightening, thecutting,
cutting, top andbending,
bottom
fabrication, of
hoisting the ,erecting
placing sheet while
in position bolting.
&tofixing
at Item includes
allindepths,
position, making
levels all
and
recommended
bolts,
material, cleats,
b) Treatment labour, listtools
fasteners
around of manufacturers
etc.
pipe
& as per
entry
tackles, the conforming
/ Scaffolding,
exit drawing.
locations :Steel IS conforming
Grouting
cleaning 1786
etc and- latest
complete torevision
sealing IS:226
as around
per
alignment
binding
as
and per withof 18-20
members,
specifications
IS:2062-Gr.A gauge,
with making
ofminimum
works soft andwelded/
drawn drgs.
yield bolted/of
locations
strength riveted
annealed
335 connections
steel binding andwire
the
TOTAL
the periphery
drawing OF joints
STRUCTURAL pipes passing
ofWORKS through the floorMpa and for
wallsplates.
in various 2,933,052.58 - - -
finishing
complete
(Fasteners,welding
locations by as and
etc complete.
filling
directions
per specifications
electrodes,
micro concrete
theand project
indrawings.
consumables
manager.
the gap between (Cost
will notofbe binding
the paid wireinshall
cut seperately.
outs be
the slab
borne
and theby
Rates the surface
inclusive
pipe contractor and& applying
of necessary binding
testswire as per
P.U. shall not be
technical
Sealant measured
specification)
around for payment.
the periphery joints
Rate includes cost of tests
of the pipes, as per manufacturers recommendation of materials by Contractor
GRAND TOTAL as specified
etc. complete (This is in the 6,170,512.58 - 570,024.92 570,024.92
Specifications
basic requirement and &IS) and preparing
contractor to provide and obtaining
detail product prior specification
approval of bar and
bending
application.) schedule .
For treatment around pipe entry will not be paid separately.
Contractor has to quote rate for entire system.
Prepared by: Aman Srivastava Contractor Sign & Stamp :

03/05/2020 ANNEX-A
Client: Indian Hotels Co. Ltd. Project: Taj Mahal Hotel, New Delhi

PROJECT CODE: ID0004
PROJECT NAME: TAJ MAHAL HOTEL, NEW DELHI
WORK ORDER NO. : IHCL/TMH/CHAMBER/SCG/2019-20/30
WORK DETAILS : Civil & ID works for Guest Floors renovations at Taj Mahal Hotel, Man
Singh Road, New Delhi
DAVI CERTIFICATE NO 0%
CONTRACTOR RA BILL NO. : RA-01

Measurement Sheet for Repair, Civil & Structural Work

Height /
Sr.No Item Ref. Desription Unit No. Length Width Quantity Remark
Depth

AS ITEM INCLUDES FIXING OF FLEX/ WALLPAPER ON ONE SIDE,


1 A.1 Providing and fixing temporary partitions/ barricading area
SO RATE HAS TO BE DECIDED ACCORDINGLY
made of hard
JMR Page No.wood,
19 frame work and 6mm commercial
plywood on one side including all, supporting
Barricading withTemporary Partitions- Lounge Area and fixing
arrangement and finished with a flex sheet or printed
Guest Lift Lobby 1 2.930 2.440 7.15
wallpaper, as directed towards the guest facing side, to be
JMR Page No. 28 0.00
maintained through the required period and to the
Barricading of
satisfaction withTemporary Partitions- Villa Madici Area
project manager. 0.00
Guest Lift Lobby 1 3.170 2.440 7.73
JMR Page
Rate No.
shall be 38
inclusive of dismantling temporary partition and 0.00
taking always
Barricading from site/ hotel
withTemporary premisesGuest
Partitions- at theLift
designated
Doors 0.00
place and disposal safely.
12th floor 4 1.020 2.000 8.16
13th floor 4 1.030 2.000 8.24
For dimensions, please check measurements on site.
Sqm Total Qty upto this bill 31.28
Sqm Less Qty upto previous bill 0.00
Net Qty upto this bill 31.28 Sqm

2 A.2 Covering glass panes of windows/ doors/ openings by


plywood
JMR Page or No.
tin sheets
19 or pvc sheets or as directed,
maintaining the aestheic
Window Protection beauty of the area, to avoid damage
with Plywood
to shutters
Grill and glass panes including using P.O.P. to clean
Area Window 4 3.330 2.250 29.97
the glass ( if required ), removal of the same after completion
Parliament Room Window 2 3.340 2.250 15.03
of work, cleaning, and making good local damage if any to
Villa Madici Window
the satisfaction of the project manager. 4 3.340 2.250 30.06
Lounge Area 4 3.340 1.950 26.05
JMR Page No. 28 0.00
Long Champ side door 1 2.000 2.440 4.88

Sqm Total Qty upto this bill 105.99


Sqm Less Qty upto previous bill 0.00
Net Qty upto this bill 105.99 Sqm

3 A.4 Dismantling, Demolishing, Cutting, Breaking, Removing &


a Cleaning Existing
Removing Items
of existing Carefully
flooring and Stacking
in areas including the useable
bedding
Materials
JMR Pageat
materials, site01
wooden
No. or planks
as Instructed including necessary tool,
tackles, machineries,
Dismantling of Flooringrequisite scaffolding,
in Pashmina Room carting away 1 7.600 5.580 42.41
debris from site time to time or disposing the material at the
2 1.110 0.100 0.22
municipal grounds as designated and specified by the project
JMR Page
manager forNo.
the13following Items. (The rate shall include all 0.00
Dismantling
leads, lift andofheight)
Kota Floor in Kitchen 1 19.550 7.770 151.90
Less - 1 3.200 0.400 -1.28
Less Shaft Area - 1 2.450 0.720 -1.76
Near Long Champ Entrance 1 3.515 2.570 9.03
1 2.340 2.120 4.96
Less Column - 4 0.520 0.420 -0.87
- 1 0.660 0.370 -0.24
JMR Page No. 14 0.00
Dismantling of Kota Floor in Cold Room 1 3.100 2.800 8.68
1 2.660 2.385 6.34
Less Offset - 1 0.740 0.365 -0.27
Less Offset - 1 0.730 0.530 -0.39
JMR Page No. 17 0.00
Dismantling of Marble Floor in Lounge Washroom 0.00
Entrance area 1 2.470 1.855 4.58
Threshold 1 0.900 0.150 0.14
Ladies Toilet Washbasin area 1 2.280 2.250 5.13
Counter area 1 1.490 0.350 0.52
Threshold 1 0.850 0.200 0.17
WC-1 1 1.320 0.980 1.29
WC-2 1 1.320 0.930 1.23
Threshold 2 0.720 0.200 0.29
Gents Toilet Washbasin area 1 2.860 2.115 6.05
Less Wall - 1 0.650 0.150 -0.10
Threshold 1 0.900 0.200 0.18

03/05/2020 MS - A
Client: Indian Hotels Co. Ltd. Project: Taj Mahal Hotel, New Delhi

PROJECT CODE: ID0004
PROJECT NAME: TAJ MAHAL HOTEL, NEW DELHI
WORK ORDER NO. : IHCL/TMH/CHAMBER/SCG/2019-20/30
WORK DETAILS : Civil & ID works for Guest Floors renovations at Taj Mahal Hotel, Man
Singh Road, New Delhi
DAVI CERTIFICATE NO 0%
CONTRACTOR RA BILL NO. : RA-01

Measurement Sheet for Repair, Civil & Structural Work

Height /
Sr.No Item Ref. Desription Unit No. Length Width Quantity Remark
Depth
Urinal area 1 1.660 1.975 3.28
WC=02 Nos 2 1.300 0.970 2.52
Threshold 2 0.750 0.200 0.30
JMR Page No. 25 0.00
Dismantling of Kota Flooring in Kitchen Service Corridor Pool 1 4.200 1.970 8.27
side
Less - 1 3.600 0.240 -0.86
1 8.000 1.970 15.76
MISSED MEASUREMENT 1 1.500 0.150 0.23
JMR Page No. 26 0.00
Dismantling of Kota Flooring in Kitchen Service Corridor Opp. 1 8.000 1.725 13.80
Cold Room 1 3.040 0.520 1.58
1 3.000 1.990 5.97
Near Cold Store Entrance 1 1.440 0.800 1.15
1 0.850 0.600 0.51
JMR Page No. 31 0.00
Dismantling of Marble Flooring in Guest Lift side Washroom 0.00
Entrance Area 1 1.750 1.690 2.96
Threshold 1 0.900 0.200 0.18
Threshold 1 0.870 0.190 0.17
Threshold 1 0.750 0.200 0.15
Ladies Toilet Washbasin Area 1 2.160 2.540 5.49
Less - 1 0.700 0.350 -0.25
WC=02 Nos 2 1.280 0.920 2.36
Threshold 2 0.680 0.200 0.27
Gents Toilet Washbasin Area 1 2.530 4.060 10.27
Less - 1 1.970 0.515 -1.01
Less - 1 0.600 0.160 -0.10
JMR Page No. 32 0.00
WC=02 Nos 2 1.280 0.920 2.36
Threshold 2 0.680 0.200 0.27
Less Column (Ladies Toilet) - 1 0.350 0.370 -0.13
0.00
Sqm Total Qty upto this bill 313.70
Sqm Less Qty upto previous bill 0.00
Net Qty upto this bill 313.70 Sqm

b Removing of existing doors including door frames


JMR Page No. 01
Removing of Doors in Pashmina Room 2 1.210 2.050 4.96
JMR Page No. 02 0.00
Removing of Doors in Parliament Room 2 1.210 2.050 4.96
JMR Page No. 06 0.00
Removing of Doors in Lounge Area 2 0.960 2.420 4.65
1 1.000 2.420 2.42
1 1.730 2.150 3.72
JMR Page No. 07 0.00
Removing of Doors in Lounge Area Corridor 1 1.700 2.100 3.57
Staircase Door 1 1.700 2.100 3.57
JMR Page No. 09 0.00
Removing of Doors & Glass Partitions in Kitchen 0.00
Entrance Door 1 1.200 2.280 2.74
Long Champ side Door 1 1.700 2.400 4.08
Cabin Doors 2 0.900 2.400 4.32
Glass Partitions (Cabin) 1 0.500 1.660 0.83
2 5.720 1.660 18.99
Less Door - 1 0.900 1.500 -1.35
1 2.475 1.660 4.11
Less Door - 1 0.900 1.500 -1.35
Middle Wall 1 2.320 1.660 3.85
JMR Page No. 16 0.00
Removing of Doors in Lounge Washroom 0.00
Ent. Door 2 0.900 2.120 3.82

03/05/2020 MS - A
Client: Indian Hotels Co. Ltd. Project: Taj Mahal Hotel, New Delhi

PROJECT CODE: ID0004
PROJECT NAME: TAJ MAHAL HOTEL, NEW DELHI
WORK ORDER NO. : IHCL/TMH/CHAMBER/SCG/2019-20/30
WORK DETAILS : Civil & ID works for Guest Floors renovations at Taj Mahal Hotel, Man
Singh Road, New Delhi
DAVI CERTIFICATE NO 0%
CONTRACTOR RA BILL NO. : RA-01

Measurement Sheet for Repair, Civil & Structural Work

Height /
Sr.No Item Ref. Desription Unit No. Length Width Quantity Remark
Depth
Ladies Toilet Ent. Door 1 0.850 2.120 1.80
Ladies Toilet WC Door 2 0.720 2.120 3.05
Gents Toilet WC Door 2 0.750 2.120 3.18
Removing of Mirrors in Lounge Washroom 1 1.380 1.250 1.73
1 0.720 2.320 1.67
1 2.080 1.280 2.66
JMR Page No. 20 0.00
Removing of Doors in Villa Madici (Service Lift side) 2 1.620 2.550 8.26
JMR Page No. 22 0.00
Removing of Doors in Grill Area 2 1.500 2.250 6.75
JMR Page No. 23 0.00
Removing of Doors in Passage Between Kitchen and Service 2 1.650 2.450 8.09
Lift
JMR Page No. 25 0.00
Removing of Doors in Kitchen Service Corridor Pool side 1 1.500 2.310 3.47
1 1.500 2.310 3.47
1 1.760 2.800 4.93
JMR Page No. 26 0.00
Removing of Doors in Kitchen Service Corridor Opp. Cold 1 1.725 2.290 3.95
Room
JMR Page No. 29 0.00
Removing of Doors in Guest Lift side Washroom 0.00
Main Door 1 0.900 2.100 1.89
Ladies Toilet Entrance Door 1 0.750 2.100 1.58
Ladies Toilet WC Door 2 0.680 2.100 2.86
Gents Toilet Entrance Door 1 0.870 2.130 1.85
Gents Toilet WC door 2 0.680 2.100 2.86
Removing of Mirrors 0.00
Ladies Toilet W/B Mirror 1 1.800 1.540 2.77
1 0.730 1.200 0.88
Full Height Mirror 1 0.720 2.350 1.69
Gents Toilet W/B Mirror 1 1.800 1.540 2.77
JMR Page No. 33 0.00
Removing of Doors in Kitchen passage Near Cold Store 1 0.700 1.100 0.77
1 0.900 1.150 1.04
Store Near Stairs door 1 0.900 2.100 1.89
JMR Page No. 37 0.00
Removing of Doors in Lounge Area Service Corridor 1 1.700 2.170 3.69
1 1.070 2.140 2.29
0.00
Sqm Total Qty upto this bill 149.69
Sqm Less Qty upto previous bill 0.00
Net Qty upto this bill 149.69 Sqm

c Removing of existing partitions/ paneling


JMR Page No. 01
Dismantling of Partitions / Panelling in Pashmina Room 2 5.580 3.670 40.96
Door Side Wall 1 7.600 0.700 5.32
Skirting 1 7.600 0.130 0.99
Less Door - 2 1.210 0.130 -0.31
Column sides 2 0.260 0.130 0.07
2 0.230 0.130 0.06
Wooden Moulding on walls 2 3.410 0.050 0.34
4 1.920 0.050 0.38
Bottom Panelling 1 7.600 0.900 6.84
Top Panelling 1 7.600 0.700 5.32
Vertical 2 0.260 2.075 1.08
2 0.330 2.075 1.37
JMR Page No. 02 0.00
Dismantling of Partitions / Panelling in Parliament Room 2 8.075 2.760 44.57
Skirting 2 7.780 0.160 2.49
Less Door - 2 1.210 0.160 -0.39
Column sides 4 0.520 0.160 0.33
2 0.240 0.160 0.08

03/05/2020 MS - A
Client: Indian Hotels Co. Ltd. Project: Taj Mahal Hotel, New Delhi

PROJECT CODE: ID0004
PROJECT NAME: TAJ MAHAL HOTEL, NEW DELHI
WORK ORDER NO. : IHCL/TMH/CHAMBER/SCG/2019-20/30
WORK DETAILS : Civil & ID works for Guest Floors renovations at Taj Mahal Hotel, Man
Singh Road, New Delhi
DAVI CERTIFICATE NO 0%
CONTRACTOR RA BILL NO. : RA-01

Measurement Sheet for Repair, Civil & Structural Work

Height /
Sr.No Item Ref. Desription Unit No. Length Width Quantity Remark
Depth

JMR Page No. 03 0.00


Dismantling of Partitions / Panelling in Villa Madici 0.00
Wooden Skirting 1 16.300 0.200 3.26
Column sides 6 0.300 0.200 0.36
Ent. Side 1 1.800 0.200 0.36
1 1.650 0.200 0.33
1 5.480 0.200 1.10
1 0.275 0.200 0.06
1 1.000 0.200 0.20
1 0.300 0.200 0.06
1 2.020 0.200 0.40
Side 1 0.400 0.200 0.08
Face 2 0.320 0.200 0.13
Sides 6 2.000 0.200 2.40
Face 2 0.400 0.200 0.16
1 3.175 0.200 0.64
1 3.150 0.200 0.63
1 1.400 0.200 0.28
Guest Lift side wall 1 8.050 0.200 1.61
JMR Page No. 04 0.00
Wooden Bands with Ceiling 2 14.670 0.200 5.87
1 7.050 0.200 1.41
1 1.560 0.200 0.31
1 1.650 0.200 0.33
Less Rafter - 10 0.150 0.200 -0.30
- 4 0.230 0.200 -0.18
JMR Page No. 06 0.00
Dismantling of Partitions / Panelling in Lounge Area 0.00
75mm thick Partition wall (Brick work + tile) 1 2.030 2.440 4.95
1 2.100 2.440 5.12
JMR Page No. 07 0.00
Dismantling of Partitions / Panelling in Lounge Area Corridor 2 5.400 1.970 21.28
2 2.450 1.970 9.65
JMR Page No. 18 0.00
Dismantling of Partitions / Panelling in Lounge Washroom 0.00
Entrance Area 2 2.470 2.270 11.21
2 1.855 2.270 8.42
Less door - 2 0.900 2.120 -3.82
Less door - 1 0.850 2.120 -1.80
Ladies Toilet Washbasin area 2 2.630 2.520 13.26
2 2.250 2.520 11.34
Less door - 1 0.850 2.120 -1.80
Less door - 2 0.720 2.120 -3.05
Gents Toilet Entrance side wall 1 2.860 2.280 6.52
Less door - 1 0.900 2.120 -1.91
side 1 0.230 2.280 0.52
1 1.660 2.280 3.78
Washbasin counter side wall 1 2.115 2.280 4.82
1 2.070 2.280 4.72
Partition wall sides 2 0.650 2.280 2.96
face 1 0.150 2.280 0.34
WC door wall 1 1.975 2.280 4.50
Less door - 2 0.750 2.120 -3.18
JMR Page No. 30 0.00
Dismantling of Partitions / Panelling in Guest Lift Washroom 0.00
Entrance Area 2 1.750 2.440 8.54
2 1.690 2.440 8.25
Less door - 1 0.900 2.100 -1.89
Less door - 1 0.750 2.100 -1.58
Less door - 1 0.870 2.130 -1.85
JMR Page No. 33 0.00
Dismantling of Partitions / Panelling in Store (Near Cold 0.00
Store)
03/05/2020 MS - A
Client: Indian Hotels Co. Ltd. Project: Taj Mahal Hotel, New Delhi

PROJECT CODE: ID0004
PROJECT NAME: TAJ MAHAL HOTEL, NEW DELHI
WORK ORDER NO. : IHCL/TMH/CHAMBER/SCG/2019-20/30
WORK DETAILS : Civil & ID works for Guest Floors renovations at Taj Mahal Hotel, Man
Singh Road, New Delhi
DAVI CERTIFICATE NO 0%
CONTRACTOR RA BILL NO. : RA-01

Measurement Sheet for Repair, Civil & Structural Work

Height /
Sr.No Item Ref. Desription Unit No. Length Width Quantity Remark
Depth
2 6.120 3.050 37.33
1 1.960 2.850 5.59
Stair sides 2 1.500 0.485 1.46
Offset 1 0.150 2.500 0.38
0.00
Sqm Total Qty upto this bill 283.06
Sqm Less Qty upto previous bill 0.00
Net Qty upto this bill 283.06 Sqm

d Removal of existing internal plaster with racking out the


masonry
JMR Pagejoints.
No. 19 0.00
Dismantling of Plaster of RCC Wall Lounge Area Corridor 1 16.320 1.100 17.95
(Villa Madici of
Dismantling side wall) in Villa Madici shaft side wall
Plaster 1 5.480 3.750 20.55
JMR Page No. 27 0.00
Dismantling of Plaster in Lounge Washroom 0.00
Entrance Area 2 2.570 2.500 12.85
2 1.945 2.500 9.73
Less Door - 2 1.000 2.150 -4.30
Less Door - 1 0.950 2.150 -2.04
Ladies Toilet 2 2.655 2.500 13.28
2 2.300 2.500 11.50
Less Door - 1 0.950 2.150 -2.04
Less Door - 2 0.800 2.150 -3.44
Gents Toilet 1 2.210 2.500 5.53
1 2.925 2.500 7.31
Less Door - 1 1.000 2.150 -2.15
1 2.170 2.500 5.43
Partition wall 2 0.650 2.500 3.25
1 0.100 2.500 0.25
Urinal area 1 1.640 2.500 4.10
WC door wall 1 2.165 2.500 5.41
Less door - 2 0.800 2.150 -3.44
JMR Page No. 28 0.00
Dismantling of Wall Plaster in Villa Madici 0.00
Kitchen side wall 1 1.950 2.550 4.97
1 2.400 2.250 5.40
1 4.860 2.250 10.94
1 2.400 2.250 5.40
side 1 0.480 2.550 1.22
Lift side wall 1 8.280 3.600 29.81
Window wall 1 16.130 2.800 45.16
Less Window - 4 3.350 2.250 -30.15
Columns sides 6 0.230 2.800 3.86
1 1.800 3.600 6.48
1 1.600 3.600 5.76
JMR Page No. 36 0.00
Dismantling of Wall Plaster in Guest Lift side washroom 0.00
Entrance Area 2 1.750 2.500 8.75
2 1.800 2.500 9.00
Less Door - 1 0.900 2.100 -1.89
Less Door - 1 0.750 2.100 -1.58
Less Door - 1 0.870 2.100 -1.83
0.00
Sqm Total Qty upto this bill 201.03
Sqm Less Qty upto previous bill 0.00
Net Qty upto this bill 201.03 Sqm

e Removing of existing internal 100 mm thick brick work


JMR Page No. 24
Dismantling of 330mm thick brick work in Lounge Area 1 0.600 2.700 1.62
with columns 1 0.400 3.770 1.51
MOVED OUT FROM 150MM THICK BRICK WORK 1 0.300 3.770 1.13

03/05/2020 MS - A
Client: Indian Hotels Co. Ltd. Project: Taj Mahal Hotel, New Delhi

PROJECT CODE: ID0004
PROJECT NAME: TAJ MAHAL HOTEL, NEW DELHI
WORK ORDER NO. : IHCL/TMH/CHAMBER/SCG/2019-20/30
WORK DETAILS : Civil & ID works for Guest Floors renovations at Taj Mahal Hotel, Man
Singh Road, New Delhi
DAVI CERTIFICATE NO 0%
CONTRACTOR RA BILL NO. : RA-01

Measurement Sheet for Repair, Civil & Structural Work

Height /
Sr.No Item Ref. Desription Unit No. Length Width Quantity Remark
Depth
1 0.200 3.770 0.75
1 0.600 3.100 1.86
Dismantling of 350mm thick Brick Wall Between Lounge Area 1 0.350 2.400 0.84
& Corridor (100mm thick)
Sqm Total Qty upto this bill 7.71
Sqm Less Qty upto previous bill 0.00
Net Qty upto this bill 7.71 Sqm

f Removing of existing internal 150 mm thick brick work


JMR Page No. 07
Dismantling of 150mm thick Brick Wall Between Lounge Area 1 4.100 2.650 10.87
& Corridor
Less Door - 1 1.000 2.420 -2.42
1 3.450 2.400 8.28
1 3.850 2.400 9.24
1 3.450 2.400 8.28
JMR Page No. 08 0.00
Dismantling of 150mm thick Brick Wall Between Lounge Area 1 2.055 2.950 6.06
& Corridor 1 0.530 2.950 1.56
1 1.820 2.950 5.37
JMR Page No. 19 0.00
Dismantling of 150mm thick Brick Wall Between Lounge Area 2 16.320 1.800 58.75
& Corridor
JMR Page (Villa
No. 23Madici side wall) 0.00
Dismantling of 150mm thick Brick Wall in Parliament Room 2 1.370 2.400 6.58
Dummy Columns
Dismantling (doorthick
of 150mm side)Brick Wall with columns in 1 0.400 2.400 0.96
Kitchen 1 0.400 2.400 0.96
1 0.150 2.400 0.36
JMR Page No. 28 0.00
Dismantling of 150mm thick brick work in Pashmina Room 1 2.150 3.850 8.28
Duct
Less Shaft
Beamside wall (300mm wide wall) - 1 2.150 0.750 -1.61
Wall 1 2.150 5.620 12.08
Less Beam - 1 2.150 0.750 -1.61
JMR Page No. 34 0.00
Dismantling of 150mm thick brick work in Lounge Area 0.00
Ladies
WC doorToilet
wall above Lintel Beam 1 2.100 1.050 2.21
WC Partition wall 1 1.350 3.250 4.39
JMR Page No. 36 0.00
Dismantling of 150mm thick brick work in Cold Store Wall 1 0.600 3.200 1.92
MOVED OUT FROM 230MM TTHICK BRICK WORK 1 0.240 3.200 0.77
1 3.600 3.200 11.52
1 6.120 3.200 19.58
1 1.550 0.450 0.70
0.00
Sqm Total Qty upto this bill 173.07
Sqm Less Qty upto previous bill 0.00
Net Qty upto this bill 173.07 Sqm

g Removing of existing internal 230 mm thick brick work


JMR Page No. 08
Dismantling of 350mm thick Brick Wall Between Lounge Area 1 0.350 2.400 0.84
& Corridor (350mm thick) 2 0.840 2.950 4.96
2 0.660 2.950 3.89
2 0.785 2.950 4.63
JMR Page No. 10 0.00
Dismantling of 230mm thick brick work in Kitchen 0.00
Cabin walls 2 5.720 0.900 10.30
Less Door - 1 0.900 0.900 -0.81
1 2.430 2.885 7.01
Less Window - 1 0.500 1.660 -0.83
Less Duct - 1 1.500 0.550 -0.83
Middle wall 1 2.320 0.900 2.09
Door wall 1 2.015 0.900 1.81
Less door - 1 0.900 0.900 -0.81

03/05/2020 MS - A
Client: Indian Hotels Co. Ltd. Project: Taj Mahal Hotel, New Delhi

PROJECT CODE: ID0004
PROJECT NAME: TAJ MAHAL HOTEL, NEW DELHI
WORK ORDER NO. : IHCL/TMH/CHAMBER/SCG/2019-20/30
WORK DETAILS : Civil & ID works for Guest Floors renovations at Taj Mahal Hotel, Man
Singh Road, New Delhi
DAVI CERTIFICATE NO 0%
CONTRACTOR RA BILL NO. : RA-01

Measurement Sheet for Repair, Civil & Structural Work

Height /
Sr.No Item Ref. Desription Unit No. Length Width Quantity Remark
Depth
Ledge wall 1 6.890 0.770 5.31
1 0.510 0.770 0.39
JMR Page No. 11 0.00
Dismantling of 230mm thick brick work in Kitchen 1 0.800 3.250 2.60
1 1.510 3.250 4.91
1 0.980 2.280 2.23
1 1.930 2.280 4.40
1 0.660 2.280 1.50
Shaft Wall 1 2.450 3.250 7.96
2 0.520 3.250 3.38
Corridor side wall 1 3.200 2.280 7.30
1 0.500 2.280 1.14
JMR Page No. 19 0.00
Dismantling of 230mm thick brick work in Villa Madici shaft 1 6.500 6.380 41.47
wall
JMR Page No. 20 0.00
Dismantling of 230mm thick brick work in Lounge Area shaft 1 2.600 3.100 8.06
wall
JMR Page No. 23 0.00
Dismantling of 230mm thick brick work in Pashmina Room 1 8.020 4.450 35.69
Service
JMR PageCorridor
No. 24side wall 0.00
Dismantling of 330mm thick brick work in Lounge Area 1 0.600 2.700 1.62
with columns 1 0.400 3.770 1.51
1 0.300 3.770 1.13
1 0.200 3.770 0.75
1 0.600 3.100 1.86
JMR Page No. 33 0.00
Cold Store Wall (200 mm) 1 0.850 3.200 2.72
1 0.615 3.200 1.97
1 0.800 3.200 2.56
1 1.050 3.200 3.36
1 0.900 3.200 2.88
Less Shaft door - 1 0.700 1.100 -0.77
Less Shaft door - 1 0.900 1.150 -1.04
1 3.000 3.200 9.60
Service Lift side 1 2.400 3.200 7.68
1 0.575 3.200 1.84
Corridor side wall 1 4.800 2.900 13.92
Less door - 1 0.900 2.100 -1.89
0.00
Sqm Total Qty upto this bill 208.30
Sqm Less Qty upto previous bill 0.00
Net Qty upto this bill 208.30 Sqm

h Removing of existing counters - bar counters, vanity, etc.


JMR Page No. 16 0.00
Dismantling of Washbasin Counters in Lounge Washroom 0.00
Ladies Toilet 1 1.390 0.860 1.20
1 0.790 0.560 0.44
Gents Toilet 1 2.120 0.860 1.82
JMR Page No. 29 0.00
Dismantling of Washbasin Counters in Guest Lift side 0.00
Washroom
Ladies Toilet 1 1.800 0.550 0.99
Gents Toilet 1 1.800 0.620 1.12
0.00
Sqm Total Qty upto this bill 5.57
Sqm Less Qty upto previous bill 0.00
Net Qty upto this bill 5.57 Sqm

i Removing of existing curtains with pelmet


Pelmet 2 3.620 0.230 1.67
Wooden Pelmet 1 16.320 0.200 3.26
MOVED OUT FROM PANELING ITEM
AS ITEM INCLUDES REMOVAL OF CURTAINS TOO, SO
ONLY ELEVATION AREA TO BE PAID

03/05/2020 MS - A
Client: Indian Hotels Co. Ltd. Project: Taj Mahal Hotel, New Delhi

PROJECT CODE: ID0004
PROJECT NAME: TAJ MAHAL HOTEL, NEW DELHI
WORK ORDER NO. : IHCL/TMH/CHAMBER/SCG/2019-20/30
WORK DETAILS : Civil & ID works for Guest Floors renovations at Taj Mahal Hotel, Man
Singh Road, New Delhi
DAVI CERTIFICATE NO 0%
CONTRACTOR RA BILL NO. : RA-01

Measurement Sheet for Repair, Civil & Structural Work

Height /
Sr.No Item Ref. Desription Unit No. Length Width Quantity Remark
Depth

Sqm Total Qty upto this bill 4.93


Sqm Less Qty upto previous bill 0.00
Net Qty upto this bill 4.93 Sqm

j Removing of existing false ceiling with structural steel


supports,
JMR Pageframings,
No. 01 light fittings, wooden beams, etc. all
complete
Dismantling of false ceiling in Pashmina Room 1 7.600 5.580 42.41
Vertical Wall False Panelling 1 7.600 0.900 6.84
Horizontal 1 7.600 0.260 1.98
JMR Page No. 02 0.00
Dismantling of false ceiling in Parliament Room 1 8.075 7.780 62.82
Vertical Ceiling 4 6.150 0.230 5.66
4 3.120 0.230 2.87
4 5.700 0.200 4.56
4 2.660 0.200 2.13
4 5.500 0.520 11.44
4 2.350 0.520 4.89
Ent. Door side Vertical 1 7.780 0.700 5.45
JMR Page No. 04 0.00
Dismantling of false ceiling in Villa Madici 1 14.670 7.050 103.42
1 1.560 1.650 2.57
Wooden Beam sides vertical 0 7.050 0.180
ITEM DESCRIPTIONS MENTIONS BEAMS SO ONLY PLAN 0 7.050 0.300
AREA WILL BE PAID 0 1.800 0.180
0 1.800 0.300
Window side wall Vertical 1 16.320 0.900 14.69
Wall False Cladding 1 14.650 3.800 55.67
Less Door - 1 1.730 2.155 -3.73
- 1 2.390 2.155 -5.15
- 1 4.900 2.155 -10.56
- 1 2.400 2.155 -5.17
- 1 1.750 2.155 -3.77
JMR Page No. 05 0.00
Dismantling of false ceiling in Villa Madici 6 2.620 1.890 29.71
1 2.620 2.550 6.68
1 3.175 2.550 8.10
Ceiling 1 2.620 2.020 5.29
Curve Ceiling 1 2.620 2.620 6.86
1 5.000 2.620 13.10
1 2.720 2.620 7.13
1 3.175 3.150 10.00
JMR Page No. 06 0.00
Dismantling of false ceiling in Lounge Area 1 18.430 2.620 48.29
1 6.340 2.030 12.87
Vertical 1 17.220 0.400 6.89
1 5.405 2.270 12.27
1 2.345 1.800 4.22
Vertical 1 5.185 1.360 7.05
1 5.405 2.185 11.81
1 2.400 0.800 1.92
1 1.750 1.730 3.03
Vertical 1 5.185 1.360 7.05
JMR Page No. 07 0.00
Dismantling of false ceiling in Lounge Area Corridor 1 5.450 2.320 12.64
Guest Lift to Staircase 1 26.760 1.700 45.49
Staircase Area 1 6.000 1.700 10.20
Vertical 1 1.700 1.150 1.96
3 times ceiling 3 2.650 1.700 13.52
Near Door Area 1 1.700 1.700 2.89
JMR Page No. 09 0.00
Dismantling of false ceiling in Kitchen 1 19.555 7.770 151.94

03/05/2020 MS - A
Client: Indian Hotels Co. Ltd. Project: Taj Mahal Hotel, New Delhi

PROJECT CODE: ID0004
PROJECT NAME: TAJ MAHAL HOTEL, NEW DELHI
WORK ORDER NO. : IHCL/TMH/CHAMBER/SCG/2019-20/30
WORK DETAILS : Civil & ID works for Guest Floors renovations at Taj Mahal Hotel, Man
Singh Road, New Delhi
DAVI CERTIFICATE NO 0%
CONTRACTOR RA BILL NO. : RA-01

Measurement Sheet for Repair, Civil & Structural Work

Height /
Sr.No Item Ref. Desription Unit No. Length Width Quantity Remark
Depth
Less Ent. Offset - 1 3.200 0.400 -1.28
Less Shaft Area - 1 2.450 0.720 -1.76
Less Columns - 4 0.520 0.420 -0.87
Less Columns - 1 0.660 0.370 -0.24
Near Long Champ Entrance 1 3.515 2.570 9.03
1 2.340 2.120 4.96
1 2.180 1.700 3.71
Vertical Ceiling 2 14.250 0.300 8.55
2 3.650 0.300 2.19
Window side Vertical 1 15.850 0.500 7.93
JMR Page No. 15 0.00
Dismantling of false ceiling in Lounge Washroom 0.00
Entrance Area 1 2.470 1.855 4.58
Ladies Toilet Washbasin area 1 2.280 2.250 5.13
Above washbasin 1 1.490 0.350 0.52
WC-1 1 1.320 0.980 1.29
WC-2 1 1.320 0.930 1.23
Gents Toilet Washbasin area 1 2.860 2.115 6.05
Urinal area 1 1.660 1.975 3.28
WC 2 1.300 0.970 2.52
JMR Page No. 23 0.00
Dismantling of false ceiling in Passage Between Kitchen and 0.00
Service LiftMadici
Near Villa 1 6.800 1.670 11.36
Near Lift 1 5.800 1.650 9.57
Near Pashmina Room 1 3.000 1.650 4.95
JMR Page No. 25 0.00
Dismantling of false ceiling in Kitchen Service Corridor Pool 1 4.200 1.970 8.27
side
Less - 1 3.600 0.240 -0.86
Vertical 1 1.970 0.250 0.49
1 3.600 0.250 0.90
1 8.000 1.970 15.76
JMR Page No. 26 0.00
Dismantling of false ceiling in Kitchen Service Corridor Opp. 1 8.000 1.725 13.80
Cold Room 1 3.040 0.520 1.58
Vertical 1 5.910 0.850 5.02
1 3.000 1.990 5.97
JMR Page No. 32 0.00
Dismantling of False Ceiling in Guest Lift side Washroom 0.00
Entrance Area 1 1.750 1.690 2.96
Ladies Toilet Washbasin Area 1 2.160 2.540 5.49
Less - 1 0.700 0.350 -0.25
WC=02 Nos 2 1.280 0.920 2.36
Gents Toilet Washbasin Area 1 2.530 4.060 10.27
Less - 1 1.970 0.515 -1.01
Less - 1 0.600 0.160 -0.10
WC=02 Nos 2 1.280 0.920 2.36
JMR Page No. 34 0.00
Dismantling of MDF Board Ceiling in Store (Near Cold Store) 1 6.120 0.870 5.32
Waist slab bottom 1 5.600 1.150 6.44
JMR Page No. 35 0.00
Dismantling of False Ceiling insulation in Pashmina Room 2 7.850 1.000 15.70
JMR Page No. 36 0.00
Dismantling of False Ceiling insulation in Lounge Area 1 2.100 2.100 4.41
JMR Page No. 37 0.00
Dismantling of False Ceiling in Lounge Area Service Corridor 1 2.990 2.395 7.16
Vertical with wall 1 2.395 2.170 5.20
1 2.995 2.225 6.66
1 3.500 1.830 6.41
Less Offset - 1 1.330 0.250 -0.33
JMR Page No. 38 0.00
Dismantling of False Ceiling in Guest Lift Lobby 0.00
12th Floor 1 6.830 2.210 15.09
1 5.300 2.840 15.05

03/05/2020 MS - A
Client: Indian Hotels Co. Ltd. Project: Taj Mahal Hotel, New Delhi

PROJECT CODE: ID0004
PROJECT NAME: TAJ MAHAL HOTEL, NEW DELHI
WORK ORDER NO. : IHCL/TMH/CHAMBER/SCG/2019-20/30
WORK DETAILS : Civil & ID works for Guest Floors renovations at Taj Mahal Hotel, Man
Singh Road, New Delhi
DAVI CERTIFICATE NO 0%
CONTRACTOR RA BILL NO. : RA-01

Measurement Sheet for Repair, Civil & Structural Work

Height /
Sr.No Item Ref. Desription Unit No. Length Width Quantity Remark
Depth
Lounge Floor Guest Lift Lobby 1 5.365 2.870 15.40
JMR Page No. 39 0.00
Dismantling of False Ceiling insulation in Villa Madici 2 3.620 1.200 8.69
0.00
Sqm Total Qty upto this bill 1006.81
Sqm Less Qty upto previous bill 0.00
Net Qty upto this bill 1006.81 Sqm

l Removing of existing Storage with all fixtures


JMR Page No. 20 0.00
Removing of Storage in Villa Madici Entrance (Service Lift 1 1.510 2.550 3.85
side)
JMR Page No. 29 0.00
Removing of Vanity Storage in Guest Lift side Washroom 0.00
Ladies Toilet 1 1.800 0.720 1.30
Gents Toilet 1 1.800 0.720 1.30
JMR Page No. 37 0.00
Removing of Storage in Lounge Area Service Corridor 1 1.100 2.140 2.35
0.00
Sqm Total Qty upto this bill 8.80
Sqm Less Qty upto previous bill 0.00
Net Qty upto this bill 8.80 Sqm

m Removal of the existing mezzanine floor including the false


ceiing,
JMR Pagewooden stairs, floor and railings, paneling, structural
No. 21 0.00
steel members,
Removal of theetc. all complete
existing mezzanine floor (Grill Area) 0.00
False Ceiling 1 18.100 8.120
Vertical 2 18.100 0.870
Vertical Central 2 18.100 0.870
Vertical (Peripheral) 2 18.100 0.530
2 3.750 0.530
2 1.065 0.530
Mezzanine Ceiling 1 5.870 3.780
1 6.400 3.680
Less Staircase Area - 1 2.100 0.800
1 5.890 3.790
Wall False Cladding 2 18.100 2.800
Less Opening - 8 2.100 2.175
Less Opening - 4 1.350 1.230
Less Opening - 2 2.870 2.175
4 1.050 2.800
Less Opening - 4 0.400 1.200
Opening sides 16 0.650 2.175
Opening Soffit 8 2.100 0.650
Opening sides 8 0.650 1.230
Opening Soffit 4 1.050 0.650
Opening sides 4 0.650 2.175
Opening Soffit 2 2.870 0.650
JMR Page No. 22
Opening sides 8 0.650 1.200
Opening Soffit 4 0.400 0.650
Along Staircase 2 2.600 2.900
2 1.300 2.900
1 2.100 1.430
Mezzanine Area Flooring 1 18.100 5.420
Less - 2 4.380 1.050
Less Staircase - 1 6.845 1.080
- 1 2.100 0.950
Ceiling Verticals 14 3.550 0.380
14 3.500 0.380
16 3.550 0.250
16 3.500 0.380
Mezzanine Ceiling Verticals 2 17.500 0.250

03/05/2020 MS - A
Client: Indian Hotels Co. Ltd. Project: Taj Mahal Hotel, New Delhi

PROJECT CODE: ID0004
PROJECT NAME: TAJ MAHAL HOTEL, NEW DELHI
WORK ORDER NO. : IHCL/TMH/CHAMBER/SCG/2019-20/30
WORK DETAILS : Civil & ID works for Guest Floors renovations at Taj Mahal Hotel, Man
Singh Road, New Delhi
DAVI CERTIFICATE NO 0%
CONTRACTOR RA BILL NO. : RA-01

Measurement Sheet for Repair, Civil & Structural Work

Height /
Sr.No Item Ref. Desription Unit No. Length Width Quantity Remark
Depth
2 15.400 0.250
4 5.000 0.250
2 5.000 0.250
8 3.470 0.250
6 1.500 0.250
JMR Page No. 27
Dismantling of Wall False Cladding in Grill Area (Mezzanine) 2 4.300 3.100
JMR Page No. 34
Dismantling of False Ceiling (Double Layer) in Grill Area 1 18.100 8.120
(Mezzanine)
Central Beam Vertical 2 18.100 0.870
0.00
Sqm Total Qty upto this bill 150.00 PROV.
Sqm Less Qty upto previous bill 0.00
Net Qty upto this bill 150.00 Sqm

B.1 Providing & doing well Burnt (First Class) Brick masonary in
all locationthick
a. 150mm with conventional
brick work type bricks in cement mortar 1:4
in
JMR superstructure
Page No. 37including striking joints, racking out joints, 0.00
watering,
Grill Area scaffolding
(Mezzanine) and cleaningside
Pashmina etc. door
complete. Rate also
closing 1 1.900 2.280 4.33
included providing & laying cast in situ RCC band beam
(Patli) in M:15 at 1200mm c/c with 2nos 8mm dia
reinforcement including shuttering, deshuttering, curing, Sqm Total Qty upto this bill 4.33
cleaning etc. completed at all heights and satifaction to the Sqm Less Qty upto previous bill 0.00
project manager. Net Qty upto this bill 4.33 Sqm

B.2 Providing and applying avg. 12 - 15mm thk. (avg.) internal


plaster
JMR Page in cement
No. 37sand mortar (1:4) for all plain / curved 0.00
surfaces
Grill Areaof(Mezzanine)
brick / blockPashmina
/ RCC wallssideand
doorfinishing
closingthebricksame
work 2 1.900 2.280 8.66
(smooth
both sideorplaster
broom) in correct line, level & plumb, making of
edges, corners, sill, jambs, soffits, grooves, pattas etc. as
Sqm Total Qty upto this bill 8.66
per drawings & relevant specifications including all necessary
surface preparation, scaffolding, including p/f of PVC chicken Sqm Less Qty upto previous bill 0.00
mesh of nominal thickness 0.35 mm with a Zinc coating of Net Qty upto this bill 8.66 Sqm
120 gms per Sqm & width of 100 to 125mm at all junctions of
B.4 RCC & masonry
Providing work,
and laying hacking75mm
average of concrete surface
thick PCC 1:3:6towith
receive
plaster,
20mm down watering, curing,complete
aggregate cleaningFlooring
etc. complete
at the at all levels
toilet floor
Pashmina Room 0.00
and
area heights theall
afterside completeworks.
drainage as perThe
the cost
directions of the
to include theproject
labour,
Window
manager. Passage Area:- P.C.C. below IPS Floor 1 8.000 2.300 18.40
all the material, accessories complete as per the instruction 0.00
and satisfaction of the project manager.
Sqm Total Qty upto this bill 18.40
Sqm Less Qty upto previous bill 0.00
Net Qty upto this bill 18.40 Sqm

B.5 Providing & laying IPS flooring at any location as specified of Sqm
75mm thickness
Pashmina Room(avg.) with cement concrete nominal mix of 0.00
proportion
Window side 1:2:4 (cement
Passage : Sand
Area:- : Aggregate)
P.C.C. below IPS in Floor
correct level / 1 8.000 2.300 18.40
slope at all levels as per architectural drawings including 0.00
mixing of concrete in mixer, lifting, shifting to the work
Sqm Total Qty upto this bill 18.40
location, compacting / vibrating, finishing smooth to the
satisfaction of the project manager, curing, and cleaning the Sqm Less Qty upto previous bill 0.00
surface etc. complete. (Mode of measurements :Plan area of Net Qty upto this bill 18.40 Sqm
Flooring shall be measured for payment

03/05/2020 MS - A
Client: Indian Hotels Co. Ltd. Project: Taj Mahal Hotel, New Delhi
PROJECT CODE: ID0004
PROJECT NAME: TAJ MAHAL HOTEL, NEW DELHI
WORK ORDER NO. : IHCL/TMH/CHAMBER/SCG/2019-20/30
WORK DETAILS : Civil & ID works for Guest Floors renovations at Taj Mahal Hotel, Man Singh Road, New Delhi
DAVI CERTIFICATE NO 0%
CONTRACTOR RA BILL NO. : RA-01

ANNEXURE B- 12TH FLOOR DINING, MEETING ROOM & GYM AREA

AS PER WORKORDER BILL QUANTITY BILL AMOUNT


Sr.
Description Unit Qty
No.
Rate Amount Previous bill This bill Cumulative Previous bill This bill Cumulative

III12TH FLOOR- DINING AREA


Note: Metal parts to be used while making furniture items shall be madde of
D SS + appropriate
FLOORING WORKS coating to match the finish and other work shall use SS +
D.1 PVD coating.
Providing & fixing in position 5 mm wide and 15mm high metal (MT-4001) Rmt 8.00 1,657 13,256.00 - - -
D.2 transition clipping
Providing and fixing trim of of
19mmapproved thick shapemachine and cut,pattern
machine for flooring
polishedjoint as per
approved Sqm 18.00 17,908 322,344.00 - - -
D.3 architectural
Italian
Providing marble drawing
& Laying (ST-4001) in and - instructions
position Vitrified of
Palissandro the(thickness
Classico
tiles project manager
on stair to treads including
and risers
be specified by the as Sqm 5.00 2,661 13,305.00 - - -
necessary
shown
manufacturers) hardware,
in drawing of or300mm drilling,
as directed cutting
x 300mm by the as project
size, specified
quality, and
typeas
manager. directed
Treadsas
& colour toby have
per the
Architect.
5mm
approved x 5mm (Running
sample chamferingforlength of
atWORKS
flooring front theand trimall
(conforming shall tobe
exposed ISmeasured
edgesinmachine
15622) for billing)
approved polished.
shape
TOTAL FOR FLOORING 348,905.00 - - -
Tread
and and riser
pattern in true marbleline and shalllevel be fixed over the
to required baseover
slope paneling
average made 20mm of BWR thick
Colour/
ply/ Bison Finish:
or sheraAntique board Hairline
using the
bedding of cement mortar 1:4 (1 cement : 4 coarse sand) floated with neat suitable adhesive etc. all complete at all
E WALL
Ref.
heights Dwg.FINISHING
and ID-1.6A.4-1
leads asWORKSper the drawing and to the approval of the project
cement slurry / paste (cement @ 4.5 kg/sqm) including chamfering of tiles
All plywood
manager.
wherever shall becutting
required, of BWR to grade
the requiredexceptsizes, for wash roompreparation,
surface or/ and wet areas
E.1 which
Providing
providing shall &andbe
laying, Marine
fixing of grade
100 mm
grouting plywood.
the high,
joints 20mm with white thickcement
having &10matching x 10mm shadow Rmt 55.00 1,404 77,220.00 - - -
E.2 gap, Solid&
Ref. Dwg:
Providing
pigments, Wood
ID-1.6A.4-1
applying
watering, (WD-4001)two or cleaning
curing, Skirting
more coats as of
etc per detailing
Acrylic
complete Premium
at allshown
floors in&drawing.
Emulsion
levelswateras per Sqm 66.00 314 20,724.00 - - -
E.3 Skirting
based of
paint,
the instructions
Providing approved
andfinish of the
applying colour
of approved
project
15-18mm and finish
manufacturer
manager. to be
thk ( avg.) POP fixed on
andplasterwall with
shadestoaswalls necessary
per using Sqm 66.00 359 23,694.00 - - -
E.4 hardwares
specifications
(Mode
approved
Fixing of in
wallquality approved
to
measurements
paper POP the
(WP-as adhesive,
interior :
4001) Only
per ISwall colour
surfaces
plan area
2547-1976,
finish and
of
includingover sealed
the building
flooring
providing with
shall
all plain/ approved
including
be
andcurved measured
fixing the quality
applying
surfaces
20mm for Sqm 32.00 432 13,824.00 - - -
sealant,
one coat
payment)
of
widebrickwooden/laid
of
block inbeading
Primer, /proper
RCC one line
and coat and
to
all-round oflevel.
be putty,
finished
the wall Finishing/
including
smooth
paper polishing
scaffolding,
asin per
correctthe todrawing
be
as as
line, directed
directed.
level and& 50mm by
E.5 Providing and fixing 6mm thick bronze mirror panelling (MI-4001) with Sqm 83.00 26,884 2,231,372.00 - - -
the project
(Make
plumb,
directions :Dulux
making manager.
orofequivalent
edges, Cost toasinclude
corners, per making
project
sill, jambs, groove
manager's
soffits, as per etc.
advice)
pattas specification,
as per
wide 35%
labour, metal onofframing
the
completion
materials,
project
wastages, ofmanager.
(MT4003) of
rawcleaning
shell Cost
required to size
(including
after
include preparing
on supporting
shutters)
completion, necessary
wall surface
aluminiumprotection 9,409 - 40.19 40.19 - 378,135.56 378,135.56
Colour/one
drawings
having
framework Finish-To
&as relevant
coat per ofmatch
theprimer ST-4001
specifications
detailedand puttyincluding
drawings. and Theall
one necessary
coat
12 mm of enamel surface
paint in proper
and 30%
inclusive
Material
Ref.fixed
Dwg:
preparation,
on
Code fixing
of
inNo:
ID-1.6A.4-1
making allof veneer/
lead,
(PT-4002) lifts laminate/
etc. complete, Fabric and
wallascovering
per theplywood
any other
instructions surface
finishing andshallto
to the
8,065 - - - -
line
be and
products
25%
level
with
on mirror
polishing/
all oflevel
direction
approved
painting
pads for
&
(Dada),
applying
make
fixing &
of
scaffolding,
shade,
accessories the hacking as per
mirror ofthe
shall surface
be properly 6,721 - - - -
satisfaction
Colour/
Base
receive rate:Code: of
Rs.
plaster, the
Dulux
100/- project
38YY
per
cleaning etc. manager.
sqft 72/117
complete – (sample
Indian to
Legendbe submitted
(Waterproof to designers
and Mould-
manufacturer
fixed using specification.
in combination of 3M make at all levels
double sidedand tapeheights all complete
with primer applied
group5%for
proof)
as per onapproval)
the virtual
directions completion 1,344 - - - -
to ply and mirror and of the project/ manager.
Dowcorning Mcoy make silicon sealants with
Finish: Matte
5%Supplied
Client
necessary on handoverEmulsion
arrangementsItem : WallasPaper per the detailed drawings and manufacturer 1,344 - - - -
E.6 Ref. Dwg.
Providing :- ID-1.6A.6-1
& fixing in(WP-4001) & 1.6A.7-3
positions Sqm 117.00 13,442 1,572,714.00 - - -
Material Code
specifications, No:
all complete as timber
per thepanellingdirections (WD-4001)
of the project as per manager.
Name:
architecturalRovere Oak (Colour
drawing and stain to match
instructions of theWD-4004).
project manager. The system
35% on completion of raw shell (including shutters) 4,705 - 58.05 58.05 - 273,098.43 273,098.43
Finish:
shall 30%
be comprising gloss, Water-based PU
Ref.30% on fixing of following:
Dwg.-ID-1.6A.6-1 & 1.6A.7-3
veneer/ laminate/ Fabric and any other finishing 4,033 - - - -
Aluminium
products
25% on polishing/frame workpainting - Providing, & fixing making and fixing aluminium frame work
of accessories 3,361 - - - -
made out of 50 x 25mm aluminium heavy box section @ 600mm c/c both
5% on virtual completion 672 - - - -
ways (spacing should not exceed more than 600mm depending on length
and5% on handover
height) fixed directly on wall as per drawing and thickness of panelling. 672 - - - -
E.7 Providing
Panelling -and fixing Lime
providing and Stonefixing 12mm CarvedBWR Panelling grade(ST-4002)
ply with 4mm - MocathickCrema Sqm 37.00 23,248 860,176.00 - - -
E.8 of size 25x20mm
Providing
veneer & Fixing
in the frame
combinationin positionand of 20mmskirting
solid thick
fluted carving
of following
and plainhoned
types
pattern finish
using with
withmaterial
5x5mm stone as per - - - -
frame
approved
shadow
100mm (ST-4001)
gapsample
high, and
10mm Palissandro
at all
20mm thickfloor
wideVitrifiedClassico
&beading
levels tilefixedonper
as
skirting walls
flushthecut to the
todrawing
the size
wallfixed and
surface
on the pattern
withframe Rmt 7.00 254 1,778.00 - - -
E.9 as
as per
per architectural
cement
Providing paste
drawingand of desired
including
fixing design including
consistency
cutting,
full height fixing
as per
necessary
laminated the
glass the same
pattern
hardware,
screen to(GL-4001)
the
given walltoetc.
drilling, etc. all
correct
ofall
12.89 line, Sqm 19.00 66,750 1,268,250.00 - - -
complete
level
complete.
mm & plumb
thickness as
The per(6 the
including
workmmalso directions
thkchasing
includes
Clear of
HSofthewall project
vertical
+ 0.89mm/ plaster
drops,manager.
thkwherever
curvature,
fabirc + 6mm required,
coves, surface
thk cutting
Clear &
HS)
preparation,
frametowork
fixed the and
SS filling
frame & finishing
providing and cut fillingthe
outthe joints
and gap with
withcement
necessary &necessary
support
sealant, approved
for switch quality
boxesall
supports
TOTAL
Ref. FOR
Dwg.-ID-1.6A.6-1 WALL FINISHING
& 1.6A.7-3 WORKS 6,069,752.00 - 651,233.98 651,233.98
colour
and lightpigments,
fittings cutting,
and cleaningmetering etc.
complete as per the dwg. and directions of the project manager. at edges,
completed curing,
at all cleaning,
floors. etc complete
as
All per the instructions
SS parts shall be finished of the project with PVD/ manager. Height as
Electroplated andper length of the
the hard
F CEILING
skirting
Ref. as FINISHING
per the to
Dwg.-ID-1.6A.6-1 WORKS
architectural
& 1.6A.7-3 drawings.finish. (Mode of measurements : Only
finishes schedule match the MT-4001
F.1 Providing
Running
Name:Fabric
Note: Rovereandtofixing
length at site shall
of skirting
Oak
be (Colour
sandwiched composite
stain be false
tomeasured
between match ceiling
theWD-4004) of POP
for payment)
glass shall be with acrylic
provided by the Sqm 200.00 16,849 3,369,800.00 - - -
F.2 emulsion
Finish: 30%
Providing
client. paint,gloss,
& fixing WoodTrap (WD4001)
Water-based
door (hinged) PUin combination
of sizes as of persoild
the fluted
drawings andwith plainthe Sqm 1.50 13,810 20,715.00 - - -
pattern
Base
suitable as
rate: per
Rs.
frame the
100/-
& drawing
per
suspenders
Ref. Dwg. - ID-1.6A6-3 & ID-11.6A.7-9 sqft with two
(section coats
50mm of sealer
x 50mm). and two
Single coats of
shutter water
made
based
out
TOTAL polish,
of 19mm FOR marine bronzeplywood
CEILING finish
FINISHING foil&leaf
teak(SF4001)
wood leaping
WORKS installedhingedflat or to taper
the frame or vertical
as 3,390,515.00 - - -
or Coveinordrawing
shown makingincluding grooves P/f on the Allen junction
key lock, of walls
hinges, andsafety
ceiling where ever
chain,
required to hardware,
necessary do so on grid framework
finished with 4mm comprising
thick approvedof rolledveneer galvanized on one metalside
G DOORS &The
sections. WINDOWSgrids shall WORKS
be (suspended
and synthetic enamel paint primer + 3 from coatsstructural
) of approved slab by makeMS&strap shade
*Note:
hangers
on other Rate sidequoted
25mmx3mm etc. complete forsize
frame shall
@as1000mm include
instructed C/C bythe theprovision
both ways from
project for structural
sub-frame
manager. of the
slab
(Mode by
of
G.1 required
Single
using soffit
measurementsleaf sizeDoor
cleatsas: per
(D4001),
and
Area directions 60 door
expandable
of trap mm of thethick project
wooden
fasteners.
opening manager.
shall shutter,
G.Ibewire 1 hour
mesh
measured rated
24forSWG fire
GI
payment) Nos 1.00 82,677 82,677.00 - - -
door,
shall
Teak be structural
wood stretched opening
of approved tight over sizethe
make - 1300mm
frame
(IC/ CPT): x 2440mm,
work and plaster bothofsides Paristoavg.12mm
be finished - - - -
with
thick
a) S.S 4mm buttthick
is applied, bearing veneer
trowelled of WD-4001
Hinges floated finish
or 102mm to in pattern
produce
x 76mm smooth
x 3mm shown Nos.in thei/c
- 4 surfaces drawing
providing - - - -
including
frame work all
b) Solid handle in SS hardwares
for light mentioned
fixtures , A/C below
grills, as
diffuser, per Hardware
shadow lineSchedule,
etc.as peras per - - - -
drawings,
drawing no. FFE Mode schedule & directionsarea
of measurement of theas project
seen inmanager.
plan area. Nothing will
c) SS Door Closer rack & pinion with standard arm - 1 No - - - -
be paid extra for verticals, grooves and drops etc.
G.2 Double
Ref. Dwg. Leaf Door (D4002): 1525mm x 2440mm 50 mm thick wooden
:- ID-D4001-1 Nos 1.00 109,101 109,101.00 - - -
shutter,
TeakDwg.
Ref. wood 1 hour rated fire make
:-ofID-1.6A.2
approved door, (IC/ innerCPT): & outer side to be finished with PT-4002 - - - -
paint finish as shown in the drawings including all hardwares mentioned
below as per Hardware Schedule, as per drawings, FFE schedule &
03/05/2020 directions of the project manager. ANNEX-B
Ref. Dwg. :- ID-D4002-1
Client: Indian Hotels Co. Ltd. Project: Taj Mahal Hotel, New Delhi
PROJECT CODE: ID0004
PROJECT NAME: TAJ MAHAL HOTEL, NEW DELHI
WORK ORDER NO. : IHCL/TMH/CHAMBER/SCG/2019-20/30
WORK DETAILS : Civil & ID works for Guest Floors renovations at Taj Mahal Hotel, Man Singh Road, New Delhi
DAVI CERTIFICATE NO 0%
CONTRACTOR RA BILL NO. : RA-01

ANNEXURE B- 12TH FLOOR DINING, MEETING ROOM & GYM AREA

AS PER WORKORDER BILL QUANTITY BILL AMOUNT


Sr.
Description Unit Qty
No.
Rate Amount Previous bill This bill Cumulative Previous bill This bill Cumulative
a) S.S Hinges 102mm x 76mm x 3mm - 6 Nos. - - - -
b) Solid handle in SS - - - -
c) S.S Rubber Door stopper - - - -
d) Vision panel of size 150mm x 600mm with 10mm thick fire rated glass on - - - -
each
e) SSleaveConcealed Door Closer rack & pinion with standard arm - 1 No - - - -
G.3 Providing, making and fixing in position selected seasoned (Ivory Coast/ Cum 0.20 294,619 58,923.80 - - -
CPT or as per approval) second class teak wood in frames of doors made to
size,
TOTAL shapeFORand DOORSdesignAND as shownWINDOWS in drawing,WORKS with mitred joints fixed with 250,701.80 - - -
40x3mm flat iron hold fast 400mm long embedding for concrete blocks
300mm x 100mm x 150mm in cement concrete 1:2:4 in contact with brick
H FIXED FURNITURES WORKS
wall or by approved dash fastener in contact with RCC as directed including
H.1 Coat
making Cabinet
necessary grooves, chamfering etc. including applying water proof No 1.00 117,571 117,571.00 - - -
H.2 Providing
Maitre D & placing
wood primer and 2 coats Coat of Cabinet
termiteasproof per details
paint on given in specification.
concealed surfaces, polish No 1.00 76,509 76,509.00 - - -
Providing
35% on&
in desired placing
completion
shade Maitre
of approved of raw D as per(including
shell
make details
and shade given
shutters)
over in specification.
a coat of approved 26,778 - 1.00 1.00 - 26,778.15 26,778.15
Item
primer No.
30% ason: per
FR4001 specification
fixing of veneer/etc. complete
laminate/ as per
Fabric anddetailed
any other drawings.
finishing(All paint/ 22,953 - - - -
Ref.
Item
polish Dwg.
No.
products : ID-FR4001-1
: FR4002
finish has to be painting water based).
25% on polishing/ & fixing of accessories 19,127 - - - -
Ref. Dwg No. : ID-FR4002-1
5% on virtual completion 3,825 - - - -
5% on handover 3,825 - - - -
H.3 Banquette Seat & Platform Set 1.00 1,023,799 1,023,799.00 - - -
H.4 Providing
Service Station & placing Banquette Seat & Platform as per details given in No 1.00 131,658 131,658.00 - - -
H.5 specification.
Providing
Service Station & placing Service Station as per details given in specification. No 1.00 169,498 169,498.00 - - -
Providing & placing Service Station as per details given in specification.
Item No.FOR FR4003
: FR4009
TOTAL FIXED FURNITURES WORKS 1,519,035.00 - 26,778.15 26,778.15
Ref. Dwg
FFE
Item Ref
No. No.: No.
FR4010- :FR-4009
ID-FR4003-1
FFE Ref No. - FR-4010
I MISCELLANEOUS WORKS
I.1 Installation, of following Miscellaneous Items as per specification described. - - - -
Ref.
ArtworkDwg. : ID-1.6A.5-1
- AR4001 No 1.00 921 921.00 - - -
I.2 Providing, fixing, fabricating railing above finish floor level, in profile made Rmt 15.00 14,731 220,965.00 - - -
I.3 out of 25mm
Providing anddia (minimum
fixing metal plates thickness (MT4001)1.5mm) in Stainless
sides andsteel base(grade
of the 304)
stair' Sqm 12.00 33,973 407,676.00 - - -
(MT4001)
steps with uprights
12mm thick (endBWR and intermediate)
grade ply to be atpasted
about 1100mm with suitable c/c and 50 mmor
adhesive
dia solid
supports wood
as per pipe
TOTAL FOR MISCELLANEOUS WORKSthe finish
drawing (WD4001)
and as
directions hand of rail,
the SS rosette
project cover
manager. fixed with 629,562.00 - - -
SS pins, dowels, clamps, rubber, screws, gaskets etc. including required
jointing
Ref. and sealing with1.6A.7-1
Dwg.-ID-1.6A.6-1, approved & quality
2 silicon sealant etc. all complete as
III 12TH FLOOR-
per detail drawing, MEETING
specification ROOM toAND entireGYM satisfaction of the project manager.
Note:
10 mmMetal thickparts clear to be used
glass (GL4002) while should
makingalso furniture
be provideditems shall be madde
in between theof
D SS +rail
FLOORING
stair appropriate
withWORKS the help coating to matchsteel
of stainless the finish
knob and and other screwwork shall
etc. all use SSand
complete +
D.1 PVD
as percoating.
Providing the&drawingfixing inand directions
position 5 mmofwide the project
and 15mm manager. high metal Work(MT-4001)
includes Rmt 22.00 1,657 36,454.00 - - -
D.2 preparing clipping
transition
Providing shopfixing
and drawings
trim of of19mm to scale
approved thickwith shape joinery
machine and and
cut, pattern fixing
machine fordetails
flooring
polished and further
joint as per
approved Sqm 14.00 17,908 250,712.00 - - -
includes
architectural
Italian providing
marble drawing samples
(ST-4001) and preparing
and- instructions
Palissandro fullproject
ofClassico
the scale
on stair mock-up
manager treads samples
including
and risers for as
approval.
necessary
shown hardware, drilling, cutting as project
specified and as directed
Treads tobyhave
TOTALinFOR drawing FLOORINGor as directed
WORKS by the manager. 287,166.00 - - -
All SS
Architect.parts shall
(Running be finished
length of with
the PVD/
trim
5mm x 5mm chamfering at front and all exposed edges machine polished. Electroplated
shall be measured as per
for the hard
billing)
finishes
Tread and schedule
riser marble to match shallthe beMT-4001
fixed overfinish. the base paneling made of BWR
E WALL
Colour/ FINISHING
Finish: AntiqueWORKS Hairline
ply/ Bison or shera board using the suitable adhesive etc. all complete at all
All plywood
heights shall
Dwg.-ID-1.6A.6-1,
Ref. Dwg. and ID-1.6B.4-1 be
leads as per of BWR
1.6A.7-1 grade
the drawing except
& 2 and to forthe wash approvalroom or/ andproject
of the wet areas
E.1 which
Providing
manager. shalland be fixing
Marine of grade
Dadoing plywood.
with Marble (ST-4004) fixed over White Sqm 1.00 15,468 15,468.00 - - -
E.2 cement mortar
Providing and fixing 1:4 asofper 100site mmconditions
high, 20mm to make
thick having the surface 10 x in level shadow
10mm with Rmt 141.00 1,404 197,964.00 - - -
E.3 quality
gap,
Providing seal
Solid coat
&Woodapplying application
(WD-4001)
two or more on all coats
Skirting sides,
as of laid
per in proper
detailing
Acrylic line and
shown
Premium level. The
in drawing.
Emulsion water Sqm 129.00 314 40,506.00 - - -
E.4 Dado
Skirtingshall
Location:
based
Providing paint,andbefinish
ofStairs
approved done
applyingofas per
colour
approved
15-18mm design
and finish / pattern
manufacturer
thk be as
(toavg.) fixed
POP specified
and on wallinwith
shades
plaster toall aspects
necessary
aswalls
per using and all Sqm 129.00 359 46,311.00 - - -
other
Ref. necessary
hardwares
Dwg:
specifications
approved to related
in approved
ID-1.6B.4-1 the works
&adhesive,
interiorID-1.6B.7-1
perwall ISas2547-1976,
shown
colour and
surfaces onof thesealed
the drawings.
building Cost
withincluding
approved to surfaces
include
quality
applying
E.5 Fixing wallquality
paper POP as
of following types: over all plain/ curved - - - -
labour,
sealant,
one
of coat
brick materials,
/laid in /proper
ofinclude
block Primer, RCCwastages,
one line
and coat and
to cleaning
oflevel.
be putty,
finished after
Finishing/
including
smoothcompletion,
polishing
scaffolding,
in correct necessary
toline,
be
as as protection
directed
directed.
level &out ofby
I Cost
12mm shall
thick BWR providing,
ply base making
paneling and
with fixing
aluminum the base
frame paneling. Wall - - - -
and
the
(Make
plumb,inclusive
project
:Dulux
making of
orofall
manager. lead,Cost
equivalent
edges, liftsto
as
corners,etc.
include
per complete,
making
project
sill, jambs, asgroove
manager'sper
soffits, the as perwork
instructions
advice)
pattas,
made and
specification, to the
a paper
38x should
50mm
a. WP-4001
satisfaction of
be
aluminum applied
(ID-1.6B.6-4)
the projectheavyevenly box
manager.
to avoid
section
Sample @bubbles.
600mm
to be c/c
submitted both grooves
ways
to designers
(10mm)
(spacing Sqm 35.00 4,741 165,935.00 - - -
labour,
etc. as permaterials,
drawings wastages,
&than
relevant cleaning after
specifications completion,
including necessary
all necessary protection
b should
b. WP-4002
group
and no be
forpreparation,
inclusiveapproval,exceed
with
ofNo: p/f(PT-4002)
all of 50lifts
machine
lead, 600mm
& 25mmpolishing/
etc. depending
widefinishing/
complete, wooden on
as per length
frame
cleaning and
(WD4001) height).
etchacking
the instructions as per and
andFrame
design Sqm 155.00 9,207 1,427,085.00 - - -
Material
surface
Client
shall be Code
Supplied
supported Item withmaking
: Wall
aluminum level
Paper pads
box (Dada),
section ofscaffolding,
38xgap 50mm @ 600mm of to the
c/c
c 10mm,
and
c. WP-40039mm
drawing,
satisfaction
Colour/ Code: wide
(Accent
of the
Dulux metal
specification Wall)
project
38YY trim and
with
manager.(MT4001)
72/117 as
p/f directed
of 9mm
(sample
–etc. withwide
Indian byshadow
toproject
Legend metal
be trim
submitted as(MT4001)
manager,
(Waterproof per
toanddrawing
etc. all
with
designers
and Mould-ID- Sqm 19.00 9,207 174,933.00 - - -
surface
fix on wallto receive
with plaster,
40x40x3mm cleaning
aluminum complete
angle for at
fixing all
thelevels
wall paperheights
and all
1.6B.6-2
complete.
3mm shadow& ID-1.6B.7-4
gapthe shown & 5
asframework
per
II groupbase
POP
proof)
complete for approval)
also including as paneling
per p/f 20mm
on grid
directions
thick basotectofthe
thedrawing comprising
project
foam in
no ID-1.6A.7-10
manager. of rolled galvanized metal
the frame as per drawing and
- - - -
sections
Finish:the
finish and
Matte
panelingG.I wire
Emulsion with mesh
approved 24 SWG wallGI shall beincluding
covering stretchedcutting, tight over the
necessary
Ref. Dwg.
03/05/2020 frame work:- ID-1.6B.6-2
ID-1.6B.6-1
and plaster &Paris
ID-1.6B.7-6
hardware,
Location: drilling, Vinyl of pvc avg. 12mm
gripper,. The work thick also is applied,
includestrowelled or
vertical drops, ANNEX-B
Name:
floated to Pantry
Rovere
produce Oaksmooth(Coloursurfaces stain to match i/c providingWD-4004). frame work for light fixtures,
curvature, coves, cutting & frame work and providing cut out and necessary
Finish: 30%
shadow line gloss,
etc.as Water-based
per the drawing PUand directions of the project manager.
support for switch boxes and lightfittings and cleaning etc. completed at all
Client: Indian Hotels Co. Ltd. Project: Taj Mahal Hotel, New Delhi
PROJECT CODE: ID0004
PROJECT NAME: TAJ MAHAL HOTEL, NEW DELHI
WORK ORDER NO. : IHCL/TMH/CHAMBER/SCG/2019-20/30
WORK DETAILS : Civil & ID works for Guest Floors renovations at Taj Mahal Hotel, Man Singh Road, New Delhi
DAVI CERTIFICATE NO 0%
CONTRACTOR RA BILL NO. : RA-01

ANNEXURE B- 12TH FLOOR DINING, MEETING ROOM & GYM AREA

AS PER WORKORDER BILL QUANTITY BILL AMOUNT


Sr.
Description Unit Qty
No.
Rate Amount Previous bill This bill Cumulative Previous bill This bill Cumulative
a WP-4001 (ID-1.6B.6-4) Sqm QRO 2,588 - - -
b WP-4002 with p/f of 50 & 25mm wide wooden frame (WD4001) and 10mm, Sqm QRO 7,052 - - -
c 9mm wide(Accent
WP-4003 metal trim Wall)(MT4001)
with p/f with
of 9mm shadow
wide gap
metalastrim
per (MT4001)
drawing ID-1.6B.6-2
with 3mm Sqm QRO 7,052 - - -
E.6 & ID-1.6B.7-4
shadow
Providing gap &
andshown 5 as
fixing 6mm perthick,
the drawing no ID-1.6A.7-10
25mm beveled edge bronze mirror panelling Sqm 41.00 13,350 547,350.00 - - -
(MI-4001)
35% onwith 50mm wide
completion wooden
of raw framing (WD4001)
shell (including shutters) of required size 4,673 - 19.35 19.35 - 90,408.20 90,408.20
including
30% on 9mm
fixingmetal trim (MT4001)
of veneer/ laminate/ and 3mmand
Fabric shadow gap on
any other supporting
finishing 4,005 - - - -
aluminium
products framework as per the detailed
25% on polishing/ painting & fixing of accessories drawings. The 12 mm plywood 3,338 - - - -
surface shall be fixed with mirror of approved make & shade, the mirror shall
5% on virtual 668 - - - -
be properly fixed completion
using in combination of 3M make double sided tape with
5% applied
primer on handoverto ply and mirror and Dowcorning / Mcoy make silicon 668 - - - -
E.7 Providing & fixing
sealants with necessary in positions timber panelling
arrangements (WD-4001)
as per the detailed as per
drawings and - - - -
a architectural
With 10mm metal
manufacturer drawingtrimand instructions
(ID-1.6B.7-2)
specifications, all complete of the
as project
per the manager.
directionsThe system
of the project Sqm 11.00 21,728 239,008.00 - - -
shall
manager.
35%be comprising
on completion following:
of raw shell (including shutters) 7,605 - 4.47 4.47 - 33,955.43 33,955.43
Aluminium frameof
30% on fixing work - Providing,
veneer/ laminate/ making
Fabricand
andfixing aluminium
any other frame work
finishing 6,518 - - - -
made out of 50 x 25mm&aluminium
Ref.products
Dwg.-ID-1.6B.6-2 1.6B.7-2,3 heavy box section @ 600mm c/c both
25% on polishing/ painting & fixing of accessories 5,432 - - - -
ways (spacing should not exceed more than 600mm depending on length
and5% on virtual
height) fixed completion
directly on wall as per drawing and thickness of panelling. 1,086 - - - -
5% on -handover
Panelling providing and fixing 12mm BWR grade ply with 4mm thick 1,086 - - - -
b With outwith
veneer 10mm10mm metal trim (ID-1.6B.6-1)
shadow gap as per the drawing fixed on the frame as per Sqm 78.00 10,598 826,644.00 - - -
drawing
35% on including
completioncutting, necessary
of raw hardware,
shell (including drilling, etc. all complete.
shutters) 3,709 - 38.70 38.70 - 143,542.49 143,542.49
The30% workonalso includes vertical
fixing of veneer/ laminate/ drops, Fabric
curvature,
and coves,
any othercutting & frame
finishing 3,179 - - - -
work 25%andon
products providing
polishing/ cutpainting
out and&necessary support for switch boxes and light
fixing of accessories 2,650 - - - -
fittings and cleaning etc. completed at all floors.
5% on virtual completion 530 - - - -
Ref.5% on handover
Dwg.-ID-1.6B.6-1 530 - - - -
E.8 Providing
Name: and fixing
Rovere Mirror Paneling
Oak (Colour (MI4001)
stain to match with 12 mm thick waterproof
WD-4004) Sqm 23.00 8,581 197,363.00 - - -
ply of IS30%
35%
Finish: 303completion
on gradeWater-based
gloss, backing
of raw6mmshell
PUthick the mirror
(including of approved make and
shutters) 3,003 - 10.42 10.42 - 31,291.90 31,291.90
10mm 30% on fixing of veneer/ laminate/ Fabric andbe
shadow gap etc. all complete. Rate shall anyinclusive of necessary
other finishing 2,574 - - - -
fittings and
products fixtures of S.S. 316. Machined
25% on polishing/ painting & fixing of accessories edge grounding of glass and 2,145 - - - -
fixing shall be on to the ply with standard grade mirror silicon ( Dow corning
5% on virtual completion 429 - - - -
make) as per the dfawaing and directions of the project manager.
5% on handover 429 - - - -
Ref. Dwg.: ID-1.6B.6-4
TOTAL FOR WALL FINISHING WORKS 3,878,567.00 - 299,198.03 299,198.03

F CEILING FINISHING WORKS


F.1 Providing and fixing at site False Ceiling of Plaster of Paris installed flat or Sqm 215.00 2,486 534,490.00 - - -
F.2 taper or vertical
Providing & fixing orTrap
Covedoor or making
(hinged) grooves
of sizesonasthe perjunction of wallswith
the drawings andthe Sqm 3.00 13,810 41,430.00 - - -
F.3 ceiling where
suitable
Providing frame ever
& applying required
& suspenders
paint on to(section
do so on
ceiling, gridsoffit,
50mm
Slab framework
x 50mm). comprising
beamsSinglecornice etcofatmade
shutter rolled
all Sqm 201.00 363 72,963.00 - - -
F.4 galvanized
out of 19mm
levels
Providing withand metal
two marine sections
coatsat
fixing plywood
ofall consisting
approved
height & teak primer
and of
wood the
levelsand main
leaping
bronze channels
three hinged
coats foil
finish (50mm
oftoapproved
the frame
leaf x 25mmas x
paint-
(SF-4001) Sqm 14.00 5,524 77,336.00 - - -
22SWG)
shown
Acrylic
over thein to
Premiumrun
drawing
ceiling in one direction
including
emulsion.,
with P/f at
including
proper adhesive 1000mm
Allen key c/c and
lock,preparation
labour,
including hinges, secondary
cleaning safety ceiling
chain, to apply
of surface,
the surface
section
necessary
levelling
the same, 70mm x23mm
hardware,
, scrapping,
leaving space x24SWG
finished
sand with
forpapering,
light at 450mm
4mm thickc/capproved
scaffolding,
fixtures, etc. in complete
all other
all direction
veneer
materials as asper connected
on one side
per
the
TOTAL
to main FOR
channel CEILING
with GI FINISHING
connecting WORKS
clips of 10)(Note:
SWG of approved 726,219.00 - - -
and synthetic
drawings
drawing andetc,theenamel
as directed paint
directions ( Project
byof primer
the project+Manager.
3 coats
manager. of approved makequality.
Measurement & as
shade
per
with
on
IS above
other
1200) side500mm
(Make etc. pattaorsmooth
complete
: Dulux finish
as instructed
equivalent asrequired
by project
per to put
the project light in advice).
manager.
manager line level.
(Mode The
Mode of
G DOORS
grids shall
measurements
of measurement& WINDOWS
be suspended
: Area
area as WORKS
from
of trap
seendoor structural
opening
in plan. slab
Nothing by
shallwillMS
bebe strap
measured hangers
paid extra for payment)
Ref. Dwg.-ID-1.6B.2-1
25mmx3mm
*Note: Rate quotedsize @for 1000mm
frame shall C/C bothinclude ways thefrom structural
provision slab by using
for sub-frame of the
G.1 soffit Finishing
required
Double
Item cleatssizeand
Leaf as
Door
No.expandable
per :- directions
(D4007):
PT-4001 fasteners.
1525mmof the project G.I wire
x 2450mm mesh
50 mm24thick
manager. SWG GI shall be
wooden Nos 2.00 168,853 337,706.00 - - -
stretched
shutter,
Ref.
Teak Dwg.
wood1 tight
hour over
ratedthe
:-ofID-1.6B.2-1
approved fireframe
door, work
make (IC/ and
innerCPT): plaster
& outer sideoftoParis avg. 12mm
be finished with thick
WD4001 is - - - -
applied,
finish trowelled or floated to produce smooth surfacesgap i/c providing
as shownframe
a) S.Sincluding
Colour/ Code:
Hinges 9mm
Dulux
102mm wide
45YY metal
82/098
x 76mm xtrim with
– Neutral
3mm - 63mm shadow
Garden
Nos. in the - - - -
work
drawings
Finish: for light fixtures
including
Matte Emulsion , A/C grills, diffuser, shadow
all hardwares mentioned below as per Hardware line etc.as per drawing no.
b) Solid
Mode handle
of measurement in SS area FFEas seen in plan - - - -
Schedule, as per drawings, schedule & area. Nothing
directions of thewillproject
be paid extra
c) S.S
for Rubber
verticals, Door stopper
grooves and drops etc. - - - -
manager.
d) SS Concealed Door Closer rack & pinion with standard arm - 1 No - - - -
G.2 Ref. Dwg.
Single
Ref. Dwg.leaf:-:-Door
ID-1.6A.2(D4008), 50 mm thick wooden shutter, 1 hour rated fire
ID-D4007-1 Nos 1.00 62,330 62,330.00 - - -
door,
Teak woodstructural opening make
of approved size - 950mm
(IC/ CPT): x 2450mm, both sides to be finished - - - -
with
a) S.S butt bearingfinish
PT4002 paint Hinges in pattern
102mmshown x 76mm in the
x 3mmdrawing including all
- 4 Nos. - - - -
hardwares
b) Solid handle mentionedin SS below as per Hardware Schedule, as per drawings, - - - -
FFE schedule & directions of the project manager.
03/05/2020 Ref. Dwg. :- ID-D4008-1 ANNEX-B
Client: Indian Hotels Co. Ltd. Project: Taj Mahal Hotel, New Delhi
PROJECT CODE: ID0004
PROJECT NAME: TAJ MAHAL HOTEL, NEW DELHI
WORK ORDER NO. : IHCL/TMH/CHAMBER/SCG/2019-20/30
WORK DETAILS : Civil & ID works for Guest Floors renovations at Taj Mahal Hotel, Man Singh Road, New Delhi
DAVI CERTIFICATE NO 0%
CONTRACTOR RA BILL NO. : RA-01

ANNEXURE B- 12TH FLOOR DINING, MEETING ROOM & GYM AREA

AS PER WORKORDER BILL QUANTITY BILL AMOUNT


Sr.
Description Unit Qty
No.
Rate Amount Previous bill This bill Cumulative Previous bill This bill Cumulative
c) SS Door Closer rack & pinion with standard arm - - - -
G.3 Double Leaf Door (D4009): 1525mm x 2450mm 50 mm thick wooden Nos 1.00 167,500 167,500.00 - - -
shutter,
Teak wood 1 hour rated fire make
of approved door, (IC/innerCPT): & outer side to be finished with WD4001 - - - -
finish
a) S.Sincluding
Hinges 102mm 9mm wide metal xtrim
x 76mm 3mm with- 63mm
Nos.shadow gap as shown in the - - - -
drawings including
b) Solid handle in SS all hardwares mentioned below as per Hardware - - - -
Schedule, as per drawings, FFE schedule & directions of the project
c) S.S Rubber Door stopper - - - -
manager.
d) SS Concealed Door Closer rack & pinion with standard arm - 1 No - - - -
G.4 Providing
Ref. Dwg. and fixing frameless fully glazed 10mm thk toughened double
:- ID-D4009-1 Nos 1.00 73,010 73,010.00 - - -
G.5 swing glass
Providing and door
fixinginclusive of side
in position fixed
tinted glazingsglass
frameless - 1500x2450mm
door (GL4003) withmade - - - -
a necessary
of following
D4011A patch
sizesfittings(approved
- 900x2450mm with 10 mm thickmake) toughned including
glass cutting,
inclusivemaking
of sideholes,
fixed Nos 1.00 37,656 37,656.00 - - -
b cutouts
glazing
D4011Bof in- 900x2450mm
the glass of
approved required
make fixed shape
to floorand andsize to of
soffit accommodate
ceiling or false fittings and
ceiling Nos 1.00 37,656 37,656.00 - - -
fixing the
rigidly and fittings
at in floors,
the (D4012), soffits,
centres wherever jams including
required in linenecessary
and level fixtures,
with srews,
SS fire
patch
G.6 Single Nos 1.00 78,811 78,811.00 - - -
sealentleaf
fittings, floor
Door
wherever spring required
of
50
and
approved
mm SS thick
cover
equivalent
wooden
over shutter,
patch
make, SS
1 hour
fittings.
Handle,
rated
Rate
door shall
stopper,
door, wood
Teak structural opening make
of approved size - 850mm
(IC/the CPT): x 2450mm, both sides to be finished - - - -
include
pivot necessary
hinge etc approved
complete. patch
Finally fitting
door locking besystems,
will3mm finished 1 pair
with S.S.
with
a)
HandlesWD4001
S.S butt finish
bearing
of approved and 9mm
Hinges
make, 102mmmetal
floor xtrim
springs, 76mmwith xmake
pivot 3mm shadow
hinges - 4andNos. gapSS
any in door
the
necessary - - - -
handle
pattern with
shown locking
in the arrangement
drawing of
including approved
all hardwares as per
mentionedthe hardware
below as
b) Solid
hardware with
schedule handle
itemsallas in SS
per hardware
enabling schedule & asFFE etc. all complete
drawingas, of per - - - -
per Hardware Schedule, asworks complete
per drawings, FFE per approved
schedule & directions the
the
c) drawings
SS Door Closer
specification and direction
and directions ofofthe
rack & pinion theProject
project
with manager.
standard
Manager. arm - - - -
project manager.
G.7 Providing, making and fixing in position selected seasoned (Ivory Coast/ Cum 0.30 294,619 88,385.70 - - -
Ref. ID-D4010-1
Ref. Dwg.
CPT or as -:-
Dwg. perID-D4011-1
approval) second class teak wood in frames of doors made to
ID-D4012-1
size,
TOTAL shapeFORand DOORS designAND as shown
WINDOWS in drawing, WORKS with mitred joints fixed with 883,054.70 - - -
40x3mm flat iron hold fast 400mm long embedding for concrete blocks
300mm x 100mm x 150mm in cement concrete 1:2:4 in contact with brick
H FIXED FURNITURES WORKS
wall or by approved dash fastener in contact with RCC as directed including
H.1 Meeting Table
making necessary grooves, chamfering etc. including applying water proof No 4.00 216,821 867,284.00 - - -
H.2 Providing
Pantry
wood primer & placing
Cabinet and 2 coats Meeting Table as
of termite proofperpaint
detailsongiven in specification.
concealed surfaces, polish No 2.00 315,886 631,772.00 - - -
H.3 Providing
Towel
in desiredDrop & placing
shade Pantry Cabinet
of approved make as and per details
shade overgiven
a coatin specification.
of approved No 1.00 138,471 138,471.00 - - -
H.4 Item
Towel No.
Providing
primer Drop :
as perFR4051
& @Gym
placing Towel Drop
specification as per details
etc. complete as pergiven in specification.
detailed drawings. (All paint/ No 1.00 37,564 37,564.00 - - -
Ref.
Item
polish Dwg.
No.
Providing :&
finish : ID-FR4051
FR4052
has to be
placing water
Towel based).
Drop @Gym as per details given in specification.
H.5 Built-in Cabinet No 1.00 46,495 46,495.00 - - -
Ref.
Item Dwg.
No. : : ID-FR4052
FR4054
Providing & placing Built-in Cabinet as per details given in specification.
Ref. Dwg.
Item No.FOR : ID-FR4054
: FR4055
TOTAL FIXED FURNITURES WORKS 1,721,586.00 - - -
Ref. Dwg.
Item : ID-FR4055
No. : FR4056
Ref. Dwg. : ID-FR4056
I MISCELLANEOUS WORKS
I.1 Installation, of following Miscellaneous Items as per specification described. - - - -
a Ref.
ArtworkDwg. : ID-1.6A.5-1
- AR4051 No 1.00 690 690.00 - - -
b Artwork - AR4052 @ PDR No 2.00 921 1,842.00 - - -
c Artwork - AR4053 No 1.00 690 690.00 - - -
I.2 Providing, fixing, fabricating railing above finish floor level, in profile made Rmt 25.00 14,731 368,275.00 - - -
I.3 out of 25mmx25mm
Providing and fixing recessed(minimummetal thickness strips1.5mm)
(MT4001) Stainless
under the steelstair'
(grade 304)
steps Rmt 25.00 1,823 45,575.00 - - -
(MT4001)
with 12mmuprightsthick BWR (endgrade
and intermediate)
ply to be pasted at about 1100mm
with suitable c/c and or
adhesive oval-
shaped solid
supports
TOTAL as per
FOR wood thepipe finishand
drawing
MISCELLANEOUS (WD4001)
directions
WORKS asofhand rail, SSmanager.
the project rosette cover fixed 417,072.00 - - -
with SS pins, dowels, clamps, rubber, screws, gaskets etc. including
required
Ref. jointing and sealing
Dwg.-ID-1.6B.6-1, 1.6B.7-1with approved quality silicon sealant etc. all
complete as per detail drawing, specification GRAND to entire
TOTAL satisfaction of the 20,122,135.50 - 977,210.16 977,210.16
project manager. 10 mm thick clear glass (GL4002) should also be provided
in between the stair rail with the help of stainless steel knob and screw etc.
all complete and as per the drawing and directions of the project manager.
Work
Prepared by: Amanincludes preparing shop drawings to scale with joinery and fixing
Srivastava Contractor Sign & Stamp :
details and further includes providing samples and preparing full scale
mock-up samples for approval.
All SS parts shall be finished with PVD/ Electroplated as per the hard
finishes schedule to match the MT-4001 finish.

Ref. Dwg.-ID-1.6B.6-1, 1.6B.7-1

03/05/2020 ANNEX-B
Client: Indian Hotels Co. Ltd. Project: Taj Mahal Hotel, New Delhi

PROJECT CODE: ID0004
PROJECT NAME: TAJ MAHAL HOTEL, NEW DELHI
WORK ORDER NO. : IHCL/TMH/CHAMBER/SCG/2019-20/30
WORK DETAILS :
Civil & ID works for Guest Floors renovations at Taj Mahal
Hotel, Man Singh Road, New Delhi
DAVI CERTIFICATE NO 0
CONTRACTOR RA BILL NO. : RA-01

Measurement Sheet for 12TH Floor - Dining, Meeting Room & Gym Area

Height /
Sr.No Item Ref. Desription Unit No. Length Width Quantity Remark
Depth

III 12TH FLOOR- DINING AREA


E WALL FINISHING WORKS
E.5 Providing and fixing 6mm thick bronze mirror panelling (MI-4001) with 50mm
wide metal
Delivery framing
Challan No.(MT4003) of requiredDt.size
DSP/19-20/0475 on supporting
14.02.2020, Delhialuminium
Sales Plywood Sqm 14 1.220 2.440 40.19
framework as per the detailed drawings. The 12 mm plywood surface shall
CONSIDERING ONLY 50% FOR NOW
be fixed with mirror of approved make & shade, the mirror shall be properly
fixed using in combination of 3M make double sided tape with primer applied
to ply and mirror and Dowcorning / Mcoy make silicon sealants with Sqm Total Qty upto this bill 40.19
necessary arrangements as per the detailed drawings and manufacturer Sqm Less Qty upto previous bill 0.00
specifications, all complete as per the directions of the project manager.
Net Qty upto this bill 40.19 Sqm
Ref. Dwg.-ID-1.6A.6-1 & 1.6A.7-3
E.6 Providing & fixing in positions timber panelling (WD-4001) as per
architectural
Delivery Challandrawing
No. and instructions ofDt.
DSP/19-20/0475 the14.02.2020,
project manager. The system
Delhi Sales Plywood Sqm 20 1.220 2.440 58.05
shall be comprising following:
CONSIDERING ONLY 50% FOR NOW
Aluminium frame work - Providing, making and fixing aluminium frame work
made out of 50 x 25mm aluminium heavy box section @ 600mm c/c both
ways (spacing should not exceed more than 600mm depending on length Sqm Total Qty upto this bill 58.05
and height) fixed directly on wall as per drawing and thickness of panelling. Sqm Less Qty upto previous bill 0.00
Panelling - providing and fixing 12mm BWR grade ply with 4mm thick
veneer in the combination of solid fluted and plain pattern with 5x5mm Net Qty upto this bill 58.05 Sqm
shadow gap and 20mm wide beading as per the drawing fixed on the frame
H as per drawing
FIXED FURNITURESincluding cutting, necessary hardware, drilling, etc. all
WORKS
H.2 complete.
Maitre D The work also includes vertical drops, curvature, coves, cutting &
frame work& and
Providing providing
placing Maitrecut outper
D as and necessary
details given support for switch boxes
in specification.
and light fittings and cleaning etc. completed at all floors. No 1 1.00
Item No. : FR4002
Ref. Dwg
Ref. Dwg.-ID-1.6A.6-1 & 1.6A.7-3
No. : ID-FR4002-1 No Total Qty upto this bill 1.00
Name: Rovere Oak (Colour stain to match WD-4004) No Less Qty upto previous bill 0.00
Finish: 30% gloss, Water-based PU
Net Qty upto this bill 1.00 No

III 12TH FLOOR- MEETING ROOM AND GYM


Note: Metal parts to be used while making furniture items shall be madde of
E SS
WALL + appropriate
FINISHINGcoating
WORKS to match the finish and other work shall use SS +
PVD coating.
E.6 Providing and fixing 6mm thick, 25mm beveled edge bronze mirror panelling
(MI-4001) with 50mm
Delivery Challan wide wooden framing
No. DSP/19-20/0475 (WD4001) ofDelhi
Dt. 14.02.2020, required
Salessize
Plywood Sqm 7 1.220 2.440 19.35
including 9mm metal trim (MT4001) and 3mm shadow gap on supporting
CONSIDERING ONLY 50% FOR NOW
aluminium framework as per the detailed drawings. The 12 mm plywood
surface shall be fixed with mirror of approved make & shade, the mirror shall
be properly fixed using in combination of 3M make double sided tape with Sqm Total Qty upto this bill 19.35
primer applied to ply and mirror and Dowcorning / Mcoy make silicon Sqm Less Qty upto previous bill 0.00
sealants with necessary arrangements as per the detailed drawings and
manufacturer specifications, all complete as per the directions of the project Net Qty upto this bill 19.35 Sqm
manager.
E.7 Providing & fixing in positions timber panelling (WD-4001) as per
a Ref.
With Dwg.-ID-1.6B.6-2
architectural drawing
10mm metal & 1.6B.7-2,3
trimand instructions of the project manager. The system
(ID-1.6B.7-2)
shall be comprising following:
Delivery Challan No. DSP/19-20/0475 Dt. 14.02.2020, Delhi Sales Plywood Sqm 2 1.220 2.440 4.47
Aluminium frame work - Providing, making and fixing aluminium frame work
CONSIDERING
made out of 50 xONLY
25mm50% FOR NOW
aluminium heavy box section @ 600mm c/c both
ways (spacing should not exceed more than 600mm depending on length
and height) fixed directly on wall as per drawing and thickness of panelling. Sqm Total Qty upto this bill 4.47
Panelling - providing and fixing 12mm BWR grade ply with 4mm thick
veneer with 10mm shadow gap as per the drawing fixed on the frame as per Sqm Less Qty upto previous bill 0.00
drawing including cutting, necessary hardware, drilling, etc. all complete. Net Qty upto this bill 4.47 Sqm
The work also includes vertical drops, curvature, coves, cutting & frame
b work
With outand10mm
providing
metalcuttrim
out(ID-1.6B.6-1)
and necessary support for switch boxes and light Sqm
fittings and cleaning etc. completed at all floors.
Delivery Challan No. DSP/19-20/0475 Dt. 14.02.2020, Delhi Sales Plywood 13 1.220 2.440 38.70
CONSIDERING
Ref. ONLY 50% FOR NOW
Dwg.-ID-1.6B.6-1
Name: Rovere Oak (Colour stain to match WD-4004)
Finish: 30% gloss, Water-based PU Sqm Total Qty upto this bill 38.70
Sqm Less Qty upto previous bill 0.00
Net Qty upto this bill 38.70 Sqm

E.8 Providing and fixing Mirror Paneling (MI4001) with 12 mm thick waterproof Sqm
ply of IS Challan
Delivery 303 grade
No.backing 6mm thick the
DSP/19-20/0475 Dt. mirror of approved
14.02.2020, make Plywood
Delhi Sales and 4 1.220 2.440 10.42
10mm shadow gap etc. all complete. Rate shall be inclusive of necessary
CONSIDERING ONLY 50% FOR NOW
fittings and fixtures of S.S. 316. Machined edge grounding of glass and
fixing shall be on to the ply with standard grade mirror silicon ( Dow corning
make) as per the dfawaing and directions of the project manager. Sqm Total Qty upto this bill 10.42
Sqm Less Qty upto previous bill 0.00
Ref. Dwg.: ID-1.6B.6-4
Net Qty upto this bill 10.42 Sqm

H FIXED FURNITURES WORKS

03/05/2020 MS - B
Client: Indian Hotels Co. Ltd. Project: Taj Mahal Hotel, New Delhi

PROJECT CODE: ID0004
PROJECT NAME: TAJ MAHAL HOTEL, NEW DELHI
WORK ORDER NO. : IHCL/TMH/CHAMBER/SCG/2019-20/30
WORK DETAILS :
Civil & ID works for Guest Floors renovations at Taj Mahal
Hotel, Man Singh Road, New Delhi
DAVI CERTIFICATE NO 0
CONTRACTOR RA BILL NO. : RA-01

Measurement Sheet for 12TH Floor - Dining, Meeting Room & Gym Area

Height /
Sr.No Item Ref. Desription Unit No. Length Width Quantity Remark
Depth
H.2 Pantry Cabinet No
Providing & placing
Delivery Challan No.Pantry Cabinet as per
DSP/19-20/0475 Dt.details given in
14.02.2020, specification.
Delhi Sales Plywood 2
TO BE CLAIMED AFTER MAKING IT'S RAW SHELL
Item No. : FR4052
Ref. Dwg. : ID-FR4052
Sqm Total Qty upto this bill 0.00
Sqm Less Qty upto previous bill 0.00
Net Qty upto this bill 0.00 Sqm

03/05/2020 MS - B
Client: Indian Hotels Co. Ltd. Project: Taj Mahal Hotel, New Delhi
PROJECT CODE: ID0004
PROJECT NAME: TAJ MAHAL HOTEL, NEW DELHI
WORK ORDER NO. : IHCL/TMH/CHAMBER/SCG/2019-20/30
WORK DETAILS : Civil & ID works for Guest Floors renovations at Taj Mahal Hotel, Man Singh Road, New Delhi
DAVI CERTIFICATE NO 0%
CONTRACTOR RA BILL NO. : RA-01

ANNEXURE C- 12TH FLOOR WET AREA & KITCHEN

AS PER WORKORDER BILL QUANTITY BILL AMOUNT


Sr.
Description Unit Qty
No.
Rate Amount Previous bill This bill Cumulative Previous bill This bill Cumulative

III 12TH FLOOR- WET AREA


Note: Metal parts to be used while making furniture items shall be madde of
D SS + appropriate
FLOORING WORKS coating to match the finish and other work shall use SS +
D.1 PVD coating.
Providing and laying of following types of approved machine cut, machine
a polished marble flooring (ST-4001) - Palissandro Classico in pattern and
General Flooring Sqm 10.00 14,123 141,230.00 - - - -
b size
Steamas Room
detailed in drawing
- Honed and
or slip as directed
resistance by the project manager. Marble
finish Sqm 25.00 15,560 389,000.00 - - - -
to be bedded over minimum 20mm thick cement sand mortar mix ratio 1:6 (1
c Shower & Steam Area - Mix pattern of textured
cement : 6 sand) including cleaning and preparing andthe
plain finishfor
surface (50mm/
bedding, Sqm 6.00 15,560 93,360.00 - - - -
100mm
spreadingwide)
neatascement
per theslurry
drawing
by using minimum cement about 3 kg/sqm
prior to bedding
TOTAL FOR FLOORING and spreading WORKS cement paste using minimum cement about 623,590.00 - - -
4.5 kg/sqm over bedding, joints to be cleaned and grouted with matching
E colour
WALL approved
FINISHING quality
WORKS polymer based readymade grout (Bal or Laticrete or -
equivalent approved), curing, cleaning, polishing to required line, level,
All plywood shall be of BWR grade except for wash room or/ and wet areas - - -
protecting till handing over etc. all complete at all heights and leads to the
E.1 which
Providing shalland be fixing
Marine of grade
100manager.
mm plywood.
high, 20mm thick having 10 x 10mm shadow Rmt 11.00 1,404 15,444.00 - - - -
satisfaction of the project
E.2 gap, Solidand
Providing Wood fixing(WD-4001)
of MarbleSkirting Dado (ST-4001)as per detailing shown
fixed over White in drawing.
cement - - - - -
a Skirting
mortar
With 6mm of approved
1:4 horizontal colour
as per siteVconditions grooves finish
and to make to be thefixed on wall
surface with with
in level necessary
quality Sqm 57.00 15,467 881,619.00 - - - -
hardwares
seal coatDado in approved
application adhesive, colour and sealed
on all sides, laid in proper line and level. The Dado with approved quality
b General
sealant, laid inas Work
proper line and level. Finishing/ polishing Sqm 1.00 14,639 14,639.00 - - - -
shall be done per design / pattern as specified havingto be asshadow
10mm directedgap by
E.3 Providing
the project
above 120mm and fixing
manager.above Cost of tinted
FFL and acid-etched
to include
3x3mm making frameless
chamfered groove partition
as per
edges (GL4003)
at specification,
the corners and Sqm 7.00 12,384 86,688.00 - - - -
E.4 glazing
labour,
on consisting
wall materials,
Providing to and
formfixing of
thewastages, 10mm toughened
cleaning
shower enclosures
V-grooves includingafter glass
in 10
soap of approved
completion,
mm thick
dish make
necessary
niche,frameless
marble bench,andclearfixing
protection WC Sqm 7.00 10,127 70,889.00 - - - -
with
and single
inclusive
toughened
ledge, etc. all leg
glassofspider,
all
other lead,
(GL4002) ceiling/
necessaryliftstoetc.bottom
be fixedtoworks
complete,
related byglass asas
means connector,
per ofthe
shown onglass
instructions
Stainless theSteel to glass
and
drawings 'U' to(ID- the
connector,
satisfaction
channel
1.6C.7-2). in etc,
of
the
Cost all
the
floor complete
project
with
to include all with
manager.
hardware,
labour,WORKS necessary
(sample
handle, fittings
to a beswingupto
submitted
materials, wastages, cleaning after all
openingheight
to including
designers
door as per
TOTAL
scaffolding FOR all WALL
complete FINISHING
as shown in 1,069,279.00 - - -
group fordrawing
detailed
completion, approval)
necessaryand directions
protection ofandtheattached
project manager.
inclusive drawing and
of all lead, as per
All lifts etc.the
hardware to be of
complete,
direction
as per theof
stainless steel theas Project
instructions per the Manager.
and hardware schedule with
to the satisfaction of the magnetic seals on the
project manager.
F CEILING
Ref. Dwg.
shower
Sample FINISHING
to :-
door. beID-1.6C.6-1
The
submitted WORKS
glass shall meet thegroup
to designers criteria foras per IS 2553
approval, machine part 1 and EN-
polishing/ -
F.1 Ref.
Name: Dwg.
Providing
finishing/ Rovere
12150-1:2015. - ID-1.6C.1
and
cleaning fixing
Oak
Alsoetc at&
(Colour
theas ID-1.6C.6-2,
site
shower
per False
stain
design Ceiling
to match
enclosure 4 of
and Plaster
WD-4004).
shall
drawing, of Paris
bespecification
as installed
per EN-14428:2015.
and as flat or Sqm 56.00 2,486 139,216.00 - - - -
F.2 taper
Finish:
Providingor vertical
30% & gloss,
fixing or Cobe
Water-based
Trap or
door
directed by project manager, etc. all complete. making
(hinged)PU grooves
of sizes on astheper junction
the of
drawings walls and
with the Sqm 1.00 13,810 13,810.00 - - - -
F.3 ceiling
Ref.
suitable
Providing where
Dwg.- ever
&ID-1.6C.1
frame applying required
& suspenders & 1.6C.6-4
paint onto(section
do so on
ceiling, 50mm
Slabgridsoffit,
framework
x 50mm). comprising
beamsSingle cornice etcofatmade
shutter rolled
all Sqm 56.00 363 20,328.00 - - - -
galvanized
out
Ref.ofDwg.
levels 19mm
with :-two metal
marine sections
ID-1.6C.6-1
coats plywood consisting
of approved & teak primer of the
wood and main
leaping
three channels
hinged
coats oftoapproved
the framepaint- as
(50mmx25mmx22SWG)
shown in
Acrylic drawingemulsion.,
Premium including to runP/f in onekey
allen
including direction
labour, at 1000mm
lock,preparation
hinges, of c/c
safety and
chain,
surface,
TOTAL
secondary
necessary FOR CEILING
ceiling
hardware, sand section FINISHING
finished70mm x23mm
with 4mm WORKS x24SWG
thick approved at 450mm
veneerason c/c in other
one side 173,354.00 - - -
levelling , scrapping, papering, scaffolding, all materials per
direction
and
drawings connected
syntheticetc, as enameldirectedtopaint
main by(channel
primer +Manager.
Project with
3 coats GI connecting
)(Note:
of approved clipsmake
Measurement of 10&SWG shade
as perof
G approved
DOORS
on
IS other &
1200) quality.
side
(MakeWINDOWS
etc. with above
complete
: Dulux WORKS as500mm
or equivalent instructed aspatta by smooth
per the project
project finish required
manager.
manager advice). to put
(Mode Mode of -
light
*Note:
of in Rate
line level.
measurements
measurement quoted The
: Area
area forgrids
offrame
as trap
seenshall in be
door
shall suspended
opening
include
plan. Nothing shall
the from
bebe
provision
will structural
measured
paidfor extra slabpayment)
for
sub-frame by of MSthe - - - - -
strap hangers
required size 25mmx3mm size @ 1000mm C/C both ways from structural
G.1 Providing andas per in
fixing directions
position of the project
tinted frameless manager.
glass door (GL4003) made - - - - -
slab
Item by using soffit
Finishing No. :-cleats
PT-4001 and expandable fasteners. G.I wire mesh 24
a of following
Entrance Door sizes with
(D4011B) 10 -mm thick toughned glass inclusive of side fixed
900x2450mm Nos 1.00 37,656 37,656.00 - - - -
SWG
Ref. Dwg. GI shall be
:- ID-1.6C.2 stretched tight over the frame work and plaster of Paris
b glazing
WC Door of (D4014A
approved &make fixed to floor and
B) - 700x2000mm soffit of ceiling or false ceiling
avg.
Colour/ 12mm Code: thickDuluxis applied,
45YY trowelled
82/098 or with
–required
Neutralfloated pulltobar
Garden produce smooth surfaces Nos 4.00 17,908 71,632.00 - - - -
rigidlyDwg.
Ref. and - atID-D4011-1
the centres wherever in line and level with SS patch
c i/c providing
Sauna/ Steam frame
Doorwork for light fixtures , A/C grills, diffuser, shadow line
Finish:
fittings,
Ref.
Matte
Dwg.floor Emulsion
spring of(D4015A&B)
approved equivalent - 800x2450mm make, with 100x50mm
SS Handle, doorSS fame
stopper, Nos 2.00 69,419 138,838.00 - - - -
etc.as per -drawingID-D4014-1 no.
pivot hinge etc complete. Finally the door will be finished with SS door
ModeDwg.
Ref. of measurement
- ID-D4015-1 area as seen in plan area. Nothing will be paid extra
TOTALwith
handle FORlocking DOORS arrangement
AND WINDOWS of approved WORKS make as per the hardware 248,126.00 - - -
for verticals, grooves and drops etc.
schedule with all enabling works complete as per approved drawing ,
H specification
FIXED FURNITURES and direction of the Project Manager.
Ref. Dwg. :- ID-1.6C.2 WORKS -
H.1 Towel's Display and Storage No 1.00 143,534 143,534.00 - - - -
Ref. Dwg. - ID-D4011-1 & ID-D4014-1
H.2 Providing &
Providing & fixing
placing Towel's
600mm deepDisplay box type and Storage
wooden as per details
lockers made given from 19mm in Sqm 19.00 28,909 549,271.00 - - - -
H.3 specification.
thick ply marine
Providing, making gradeand of approved
erecting 1200 makemm which wide and will 750mm
be finished highwith vanity 4mm Nos 1.00 196,382 196,382.00 - - - -
H.4 thick
counter
Providingveneer
with (WD4001)
space
fixingfor on inside
wash basin and made outside out except
of madeatof
19mm the19mm
marine bottomgrade storage
ply and
Item
which No.
will : and
FR4054
be finished
740mm
in matching
wide, 450mm
laminate/
deep thick Nos 2.00 37,564 75,128.00 - - - -
counter
marine
Ref. DWg
top
grade-
(including
ply shelves
ID-FR4054-1
facia) forand towels walls fixed in melamine
to have vanitymarble polish
wallstone
properly to the
ST4004
as per WD4001
withthe
finish.chamferedd
5mm The locker
architectural drawing shall
edges have
and SS hinges,
&instructions
ST4001 with of digital
6mm
the project lock, manager
V-grooves suitable arrangement
respectively
and finish asthe for
per
TOTAL
concealed FOR
the architectural FIXED
lighting and FURNITURES
other details, WORKS
etc. all complete as shown in the 964,315.00 - - -
shelves, side anddrawing back wall andwith instructions
4mm thick ofapproved
the project manager
make including
and colour
drawings
fixed storage
veneer and
(WD4001), as per
mademarble the
of 12mm directions
thick marine
counter of the
finishedply project
in finishedmanager.
ST4004 in with 4mm All
5mm the
thick edges
chamfered
I must
edgesbe
MISCELLANEOUS
approved sealed
havingveneer the with 10 mm
WORKS
(WD4001)
suitable thick
on outside
cutout teak
for wood beading
and inside
dropping glued
matching
the towels, door on Computer
laminate/
panel in -
I.1 controlled
melamine
Providing automatic
polish
and including
fixing Edge
6mm banding
all
thick necessary
clear
WD4001 finish and pull out trolley made of the same ply finished in machine
mirror with
consumables
with pre-milling
pencil viz.
edge operation
adhesive,
on 2 sides using
of
laminate/ Nos 2.00 99,526 199,052.00 - - - -
hot-melt glue
necessary
approved
melamine make
polish while
hardware, to pre-milling
with necessary
12mm
match thick
WD4001 function
beads
marinefinish,putting
moulding,
grade 'on' mode.(confirming
lipping,
plywood
arrangements The
for wholeto
fastenings,
concealed locker
fittings
IS
shall
710)
lighting,be
etc. completebased
backing
120mm over
as high
and directed50mm
120woodenx 10mm thick
and skirting IPS
asmetal flooring
specifiedframe10mm
with (which
by(MT4001)
the shadowwill
project be paid
onmanager.
four separately)
sides, 3mm
gap including
03/05/2020 and
Note:the
thick
providing vertical
Civil
metal allworks
frame side
necessarywill of
bethe
(MT4001) paid same
on
consumables top shall
separately. be adhesive,
& bottom
viz. matchedincluding with WD4001.
necessary
necessary SS (304)
hardware, ANNEX-C
studs, metal frames to be finished in approved
necessary beads moulding, lipping, fastenings etc. all complete at all floors shade, etc. all complete as
Ref.
Ref.
per
& Dwg.
Dwg.
the
heights -- ID-1.6C.7-5&6
drawings
as ID-1.6C.1 and to
specified &andID-1.6C.7-4
entire satisfaction
as directed by the of the project
project manager.
manager.
Client: Indian Hotels Co. Ltd. Project: Taj Mahal Hotel, New Delhi
PROJECT CODE: ID0004
PROJECT NAME: TAJ MAHAL HOTEL, NEW DELHI
WORK ORDER NO. : IHCL/TMH/CHAMBER/SCG/2019-20/30
WORK DETAILS : Civil & ID works for Guest Floors renovations at Taj Mahal Hotel, Man Singh Road, New Delhi
DAVI CERTIFICATE NO 0%
CONTRACTOR RA BILL NO. : RA-01

ANNEXURE C- 12TH FLOOR WET AREA & KITCHEN

AS PER WORKORDER BILL QUANTITY BILL AMOUNT


Sr.
Description Unit Qty
No.
Rate Amount Previous bill This bill Cumulative Previous bill This bill Cumulative

TOTAL FOR MISCELLANEOUS WORKS 199,052.00 - - -

III 12TH FLOOR- KITCHEN

A CIVIL WORKS
*Note: Supply and installation of SS false ceiling will be under client's scope.
A.1 Providing & Constructing Brick work 115mm thick masonry at all levels in Sqm 110.00 1,381 151,910.00
walls,
Upto piers90% and onarchitectural
Pro-rata completion features of using
works approved
10% upon blocks of required
completion of 1,243 - 59.19 59.19 - 73,569.24 73,569.24
strength
entire
10% upon cement
workcompletion
and mortar
handing1:5 Rate shall
of over
entire workbe and inclusive
handingofover 100 mm thick RCC 138 - - - -
band and shall be provided after every 1200mm height with concrete 1:2:4
A.2 Providing
reinforcedand withapplying
2 No. steel Cement
bars of sand 8 mm rough Plasterin1:4,
diameter 12-15mm
longitudinal thick over
direction Sqm 140.00 415 58,100.00 - - - -
Internal
andUpto
8mm Walls
90% / Columns
on
dia stirrups Pro-rataat 150/ completion
RCCmmSurfaces
centresof worksto transverse
in line10% level and
upon plumbas
completion
direction to specified
smooth
of 374 - - 140.00 140.00 - 52,290.00 52,290.00
finish
10% according
entire
for piers. upon to specifications.
workcompletion
Rate and
includes handing of over
curing, Rate
workshall
scaffolding,
entire include
andstaging, for
handingshuttering
overproviding G.I.chicken
& concreting 42 - - - - -
mesh
for RCC made bands outat ofallgalvanised
floors withironall of
leadnominal
and liftthickness
and aswith
per0.35 mm with a and
specification Zinc
A.3 Providing
coating of and120 laying average
Sqm at75mm thick PCC 1:3:6 20mm down works Sqm 100.00 424 42,400.00 - - - -
instructions
aggregate by gms
complete project per manager.
Flooring
the junctions
at the toilet
of masonry and concrete
A.4 Providing
to a width and of 100laying M:25 grade
to 125mm including tyingfloor
concrete with area
proper
in position after
with the
compaction drainage
suitable for works. Cum 3.00 14,271 42,813.00 - - - -
A.5 The cost tocasting
jacketing,
clamps/screws,
Waterproofing include theincluding
including
necessary
Works labour, all
breaking
staging, the material,
the old
: concrete
scaffolding
following accessories
and curing atcomplete
and carting away
all levels as
andper Sqm 350.00 1,027 359,450.00 - - - -
the instruction
debris
elevationsas specified and
etc.,making satisfaction
by the
complete of the all
consultant
as directed. project
Ratecomplete.manager.
shall
A.6 Providing and core cutting in RCC Up to include
200 mmforthickness,
proper hacking, - - - - -
a cleaning
a)
50 to 100and
Waterproofing
including mmas
cutting diadirected
treatment
steel by :project
Cleaning
reinforcement manager.
the surface
wherever to our cleaning,
required, requirements, removing Nos 4.00 2,219 8,876.00 - - - -
providing
debris andindicated
applyinglocationpolymeroutside based the flexible
site cementitious
etc complete waterproof
b 100 to at
coating 150 an mm diaof acrylic
consisting polymer mixed with cement,
as per drawing
applied in 2 coats Nos 4.00 3,117 12,468.00 - - - -
& directions of the project manager.
c 200
in thetoform
250 of mm dia over the RCC slab and on the vertical surfaces up to a
slurry Nos 4.00 5,073 20,292.00 - - - -
A.7 height 1.50
Providing andmtr. above
laying F.F.L.
light weight or as instructed,
AAC/ foam concrete including grouting
blocks under of,sunken Sqm 30.00 967 29,010.00 - - - -
A.8 construction
portion
Polished ofKota joints,
floors up honeycombs
Stone toflooring
the depth - 25oflocations,
300mm
mm cracks
thickincluding
stone slab etc. with crystalline
ramming
flooring and
( sample based
of Sqm 250.00 2,440 610,000.00 - - - -
non shrink
consolidation
kota stoneand cementitious
shallall complete
be approved grout
as to full
directed
by guards saturation,
by
the designer) the making
project small
manager. fillets
thick(wattas)
A.9 Providing fixing S.S. corner of full laid over
height up20 to mmthe ceiling base
from of Rmt 85.00 1,427 121,295.00 - - - -
around
cement the
mortarperiphery
1:4 junctions ponding with water, curing testing for water
A.10 finished
1st quality
tightness
floor,
bywall tiles( of
made
ponding
1
out cement
approved : 4make
of 16 gauge, course & sand
grade model 304 ) of
and jointed fixed
at corners
approved with
make cement
usinglike Sqm 300.00 1,450 435,000.00 - - - -
slurry
screws
KAJARIA with
etc. pigment
or all complete,
equivalent to with
match water
as
make the
per for
in detail
all
7 days
shade of the
drawings,
colours,
etc.,including
slab
shades, including
brush protection
finished
design grinding
and with
prints and
as
A.11 Providing
screed/plaster
mirror Pest
polishing control
etc and
complete
complete Anti-termite
andand also10 yrs treatment:
guarantee
protective sheetDrill
on to holes
STAMP
prevent atPAPER
the junction
scratches, OF Sqm 60.00 231 13,860.00 - - - -
protective
approved
of wall and coating,
by the
floor at rounded
project
1sqft manageredges&
intervals all
over as
inject per
12mm in instruction
thick
approved bed and
of
anti entire and
cement
termite mortar 1:3
Rs.100/-
curing
satisfaction complete.
etc., all
the complete
of Measurement
the as
project per the
manager. given
drawing is surface
and area (This
directions of is basic
the project
(1cement:
sealing
requirementthe 3holes
coarse sand)
thereafter
contractor to and
with
provide jointed
white
detail with
cement greyand
product cement
spray slurry
specification all @ 3.3kgwalls
exposed
and per
TOTAL
manager.
Sqm.flooringOF
including CIVIL WORKS
pointing inanti
white cement mixed with pigment 1,905,474.00 - 125,859.24 125,859.24
and
application.) surface
one layer withon the termiticide
mother slab spray
and by 2nd appointing
layer afterof matchinglayer
aconcrete
specialized
shade
agency
after complete.
as per
piping the40/sqft
specifications mentioned by the Bureau of Indian
Basic Rate -works
Rs. under the stone.
Standards and Agencies specifications (whichever GRAND TOTAL is higher), for General 5,183,190.00 - 125,859.24 125,859.24
Basic
Civil, rate - Rs
Plumbing,/
b) Treatment 35/Sqft
aroundDrainage and timber/
pipe entry Carpentry
/ exit locations works, Gypsum
: Grouting and sealing relatedaround
work, including joints
the periphery a 10 year of pipesguarantee
passingunder through suitable undertaking
the floor and wallson instamp
various
paper
locationsetc,by complete
filling micro as directed.
concrete in the gap between the cut outs in the slab
Mode
andAman
theofpipe
measurement
surface and to applying
be on carpet-area
P.U. Sealant of floor and not
around the the area ofjoints
periphery
Prepared by: Srivastava Contractor Sign & Stamp :
surface treated.
of the pipes, as per manufacturers recommendation etc. complete (This is
basic requirement & contractor to provide detail product specification and
application.) For treatment around pipe entry will not be paid separately.
Contractor has to quote rate for entire system.

03/05/2020 ANNEX-C
Client: Indian Hotels Co. Ltd. Project: Taj Mahal Hotel, New Delhi

PROJECT CODE: ID0004
PROJECT NAME: TAJ MAHAL HOTEL, NEW DELHI
WORK ORDER NO. : IHCL/TMH/CHAMBER/SCG/2019-20/30
WORK DETAILS : Civil & ID works for Guest Floors renovations at Taj Mahal Hotel, Man
Singh Road, New Delhi
DAVI CERTIFICATE NO Dec-99
CONTRACTOR RA BILL NO. : RA-01

Measurement Sheet for 12TH Floor - Wet Area & Kitchen

Height /
Sr.No Item Ref. Desription Unit No. Length Width Quantity Remark
Depth

III 12TH FLOOR- KITCHEN

A CIVIL WORKS
*Note: Supply and installation of SS false ceiling will be under client's scope.
A.1 Providing & Constructing Brick work 115mm thick masonry at all levels in Sqm
walls,
115mm piers
thickand architectural
Brick Work features using approved blocks of required 2 5.950 2.400 28.56
strength
Low Heightcement
Wall mortar 1:5 Rate shall be inclusive of 100 mm thick RCC 2 4.260 1.330 11.33
band and shall be provided after every 1200mm height with concrete 1:2:4
Wall
reinforced with 2 No. steel bars of 8 mm diameter in longitudinal direction 1 5.950 2.400 14.28
Less8mm
and Opening
dia stirrups at 150 mm centres in transverse direction as specified - 1 3.400 1.100 -3.74
for piers. Rate includes curing, scaffolding, staging, shuttering & concreting 1 0.750 2.400 1.80
for
WallRCC bands at all floors with all lead and lift and as per specification and 1 2.400 2.400 5.76
instructions by project manager.
1 0.500 2.400 1.20
0.00
Sqm Total Qty upto this bill 59.19
Sqm Less Qty upto previous bill 0.00
Net Qty upto this bill 59.19 Sqm

A.2 Providing and applying Cement sand rough Plaster 1:4, 12-15mm thick over Sqm
Internal Walls
15mm thick / Columns
plaster / RCC
on Brick wallSurfaces to line level and plumb to smooth 4 5.950 2.400 57.12
finish according
Low Height Wall to specifications. Rate shall include for providing G.I.chicken 4 4.260 1.330 22.66
mesh made out of galvanised iron of nominal thickness 0.35 mm with a Zinc
face
coating of 120 gms per Sqm at the junctions of masonry and concrete works 2 0.130 1.330 0.35
Wall
to a width of 100 to 125mm including tying in position with suitable 2 5.950 2.400 28.56
clamps/screws,
Less Opening necessary staging, scaffolding and curing at all levels and - 2 3.400 1.100 -7.48
elevations etc., complete as directed. Rate shall include for proper hacking, 1 0.750 2.400 1.80
cleaning and as directed by project manager. 1 0.865 2.400 2.08
Wall 2 2.400 2.400 11.52
1 0.920 2.400 2.21
Villa Madici side wall (Old hood side) 1 14.005 2.950 41.32
JMR Page No. 38 0.00
Extra 15mm thick Cement Plaster on Villa Madici side wall (Old Hood Area) 1 14.005 1.800 25.21
due to undolation of wall 0.00
Sqm Total Qty upto this bill 185.34
Sqm Less Qty upto previous bill 0.00
Net Qty upto this bill 185.34 Sqm

03/05/2020 MS - C
Client: Indian Hotels Co. Ltd. Project: Taj Mahal Hotel, New Delhi
PROJECT CODE: ID0004
PROJECT NAME: TAJ MAHAL HOTEL, NEW DELHI
WORK ORDER NO. : IHCL/TMH/CHAMBER/SCG/2019-20/30
WORK DETAILS : Civil & ID works for Guest Floors renovations at Taj Mahal Hotel, Man Singh Road, New Delhi
DAVI CERTIFICATE NO 0%
CONTRACTOR RA BILL NO. : RA-01

ANNEXURE D- 13TH FLOOR LOUNGE AREA & OFFICES

AS PER WORKORDER BILL QUANTITY BILL AMOUNT


Sr.
Description Unit Qty
No.
Rate Amount Previous bill This bill Cumulative Previous bill This bill Cumulative

IV 13TH FLOOR- LOUNGE AREA


Note: Metal parts to be used while making furniture items shall be madde of
D SS + appropriate
FLOORING WORKScoating to match the finish and other work shall use SS + -
PVD coating.
Providing & fixing in position 5 mm wide and 15mm high metal (MT-4001)
D.1 Rmt 98.00 1,657 162,386.00 - - - -
D.2 transition clipping
Providing & Layingtrim of approved
in position Vitrified shape tilesand pattern to
(thickness forbe flooring
specified jointby asthe
per Sqm 10.00 2,661 26,610.00 - - - -
architectural drawing
manufacturers) of 300mm and instructions
x 300mm of the project manager including
D.3 Providing & Laying in position 19 mmsize, avg.quality,
thick machinetype & colour
cut machine as per the Sqm 9.00 14,133 127,197.00 - - - -
necessary
approvedItalian hardware,
sample drilling,
for flooring cutting
(conforming as specified
to IS 15622) and as directed
in ofapproved by shape
polished Marble (ST-4001) - Palissandro Classico approved size, - - -
Architect.
and pattern (Running length of theto trim shall be measured for billing)
quality, typein & true
colour line asand perlevelthe approved required slope
sample over
for average
flooring 20mm thick
in approved
TOTAL
bedding FOR
of cement FLOORING mortar WORKS
1:4 and (1 cement 316,193.00 - - -
shape and pattern in true line level / :to4required coarse sand) slopefloatedover averagewith neat
Colour/ Finish:
cement slurry / Antique
pasteof Hairline 4.5 kg/sqm) including chamfering of tiles
(cement - - -
50mm thick bedding cement@ mortar (1:4) floated with neat cement slurry /
Ref. Dwg.required,
wherever ID-1.6A.4-2 cutting to the required sizes, surface preparation,
E WALL FINISHING WORKS
paste (cement @ 4.5 kg/sqm) including cutting to the required sizes, surface -
providing
preparation,
All plywood & laying,
providing
shall begrouting
of &BWR layingthegrade,joints
filling with
except white
& finishing
for wash cement
theroom joints&or/matching
with
andneat wetcement
areas - - - - -
pigments,
slurry & watering,
approved curing,
colour cleaning
pigments, etc complete at watering
all floors curing,
& levels as per
E.1 which
Providing
the
shall
instructions andbe fixing
Marine
of the
grade
ofproject
Dadoing plywood.withmirror
manager. Marble polishing,
(ST-4003) fixed over White Sqm 5.00 12,061 60,305.00 - - - -
cleaning
cementofmortar etc complete
1:4 asofper at all floors & levels as per the instructions of the
E.2 Providing
(Mode
project seal and fixing
measurements
manager. 100 : site
mmconditions
Only high,area
plan 20mm toofmake
thick
flooring theshall
having surface
10 in
bexmeasured
10mmlevel shadow
withfor Rmt 58.00 1,404 81,432.00 - - - -
quality
gap, Solid coat application on all sides, laiddetailing
in propershown line and level. The
E.3 payment)
Providing
(Mode
Dado &Wood
applying
of measurements
shall be done
(WD-4001)
as two per :orOnly Skirting
more
design plan coats
/
as of
area
pattern
per Acrylic
of flooring
as Premium
specified shallinbe all
in drawing.
Emulsion
measured
aspects water
andforall Sqm 106.00 314 33,284.00 - - - -
Skirtingpaint,
based
payment) of approved colour
finishofoffollowing
approved and finish manufacturerto be fixed andonshades wall with as necessary
per
E.4 Fixingnecessary
other wall paper related works types:
as shown on the drawings. Cost to include - - - - -
hardwares
Colour/
specifications in approved
Finish-To to the match adhesive,
interior ST-4001
wall colour and
surfaces of the sealed
building withincluding
approved quality
including
Cost
labour,
12mm shall
thick include
materials,BWR providing,
wastages,
ply base making
cleaning
paneling and
after
with fixing the
completion,
aluminum base
frame paneling.
necessary Wall
protection
I sealant,
Ref.
Ref. Dwg:
applying
Dwg. laid
one incoat
proper
ID-1.6A.4-2
-aluminum
ID-1.6A.4-2 line and
of Primer, one level.
coat Finishing/
of bubbles.
putty, polishing
including towork
be as
scaffolding,
made
directedout ofby
asto the - - - - -
paper
andprojectshould
inclusive beall
of applied evenly to avoid
a 38x
the
Base 50mm
WP-4001
directed.rate:(Make manager.
with
Rs. p/f
100/-oflead,
:Dulux
heavy
Cost
20mm
per lifts
orsqft to etc.
box
wideinclude
equivalent
complete,
section
metal making
as
@ 600mm
frame asgroove
per project
per
(MT4001). the asinstructions
c/c both
manager's
and
ways (spacing
per specification,
advice) Sqm 14.00 9,207 128,898.00 - - - -
satisfaction
should
labour, no of the
be exceed
materials, project manager.
than 600mm Sample
depending to be submitted
on lengthnecessary to
and height).designers Frame
b WP-4002
Client
group Supplied(PDR Item
forsupported
approval, & wastages,
Meeting
: Wall
machine
cleaning
Room)
Paper
polishing/ withafter p/f ofcompletion,
finishing/ 50mm wide timber
cleaning etc@as600mm
protection
frame
per design Sqm 29.00 9,207 267,003.00 - - - -
shall be
and inclusive ofNo: with
all (PT-4002)
lead, aluminum
lifts etc. box section
complete, of
as with
per 38xthe 50mm
instructions and c/cthe
Material
(WD4001)
Ref.
WP-4003 Code & 10mm
Dwg.-ID-1.6A.6-7 widewith metal trim (MT4001) 3mm shadowetc. gap asto per
c fix wall (Accent
andondrawing,
satisfaction with
of Wall)
specification
40x40x3mm
the project and p/fas
aluminum
manager. of directed
9mm wide
angle
(sample byto metal
project
for fixing
be trim (MT4001)
manager,
the
submitted walltopaper with
all
designersand 3mm Sqm 8.00 9,207 73,656.00 - - - -
Colour/
the drawing
shadow Code:
gap no Dulux
shownID1.6A.7-10
as38YY per 72/117
the –
drawing foam Indian Legend
no ID-1.6A.7-10 (Waterproof and Mould-
II complete.
also
POP
group including
base
for approval) p/f 20mm
paneling on thick
grid basotect
framework comprising in the of frame
rolled asgalvanized
per drawing and
metal - - - - -
proof)
a finish
sections
WP-4001 theand paneling
withG.I ofwith
p/fwire mesh
20mm approved24 SWG
wide wallGI
metal covering beincluding
shall (MT4001).
frame stretchedcutting, tight over necessary
the Sqm QRO 7,052 - - - -
Finish: Matte Emulsion
Ref.
frame
Ref. Dwg.
hardware, work:-and
Dwg. :- ID-1.6A.6-2
drilling, Vinyl
plaster of&Paris
ID-1.6A.6-1 pvc 4 gripper,. The work also
avg. 12mm thick is applied, trowelled or includes vertical drops,
b WP-4002
Name: (PDR & cutting
Meeting Room) with p/f andof 50mm wide timber frame Sqm QRO 7,052 - - - -
Name: Moca
curvature,
floated coves,
to produce
Rovere Crema
Oak smooth
(Colour & surfaces
frame
stain to work i/c providing
match providing
WD-4004). frame cut workout for
andlightnecessary
fixtures,
(WD4001)
WP-4003 &switch
10mmboxes
(Accent widewith metal trim (MT4001) with 3mm shadow gap
withas per
c Finish: 30%
support
shadow
Finish: Honed
for
line etc.asWall)
gloss, per the
Water-based and p/f
drawing of 9mm
lightfittings
PU wide
and metal
and directions cleaning oftrim
theetc.(MT4001)
completed
project manager. 3mm
at all Sqm QRO 7,052 - - - -
the drawing
shadow
floors asgap no ID1.6A.7-10
E.5 Providing andshown
per the drawing
applying as per thedirections
and
15-18mm drawingthk( avg.) noof ID-1.6A.7-10
the
POP project
plaster manager.
to walls using Sqm 106.00 359 38,054.00 - - - -
E.6 approved &
Providing quality
fixingPOP as per IS
in positions timber2547-1976,panelingover all plain /as
(WD-4001) curved
per surfaces Sqm 104.00 21,406 2,226,224.00 - - - -
of brick / block
architectural / RCC and
drawing and instructions
to be finished of smooth
the project in correct
manager. line,The level &
system
35% on completion of raw shell (including shutters) 7,492 - - 50.61 50.61 - 379,145.21 379,145.21
plumb,
shall bemaking
comprising of edges, following: corners, sill, jambs, soffits, pattas etc. as per
30% on
drawings & fixing
relevant of veneer/
specifications laminate/ Fabricall
including and any othersurface
necessary finishing 6,422 - - - - -
Aluminum frame work - Providing, making and fixing aluminum frame work
products
preparation,
25% making level pads&(Dada), ofscaffolding, hacking of surface to
made outonofpolishing/
50 x 50mm painting
aluminum fixing
heavy accessories
box section @ 600mm c/c both 5,352 - - - - -
receive
ways plaster,
5%(spacing
on virtual cleaning
should
completion notetc. exceed complete moreat than all levels
600mm and heights all
depending oncomplete
length 1,070 - - - - -
as per
and the directions
height) fixed directly of the onproject
wall asmanager. per drawing and thickness of paneling.
5% on handover 1,070 - - - - -
Panelling - providing and fixing 12mm thick ply of BWR grade with 4mm
E.7 Providing & Fixing in
thick veneer including 10mm metal trim position skirting of inside
following thetypessquare using
box material
fixed on as theper - - - - -
approved
100mm
frame ashigh, sample
per 10mm
drawing at allthick floor
including & levels
Vitrified tilefixed
cutting, skirting flush to the
necessary wall surface
hardware, with
drilling, etc. all Rmt 20.00 253 5,060.00 - - - -
cement paste
complete. Theof desired
work also consistency
includes as per
vertical the pattern
drops, curvature, given to correct
coves, line,
E.8 Providing and fixing full height laminated glass screen (GL-4001) ofcutting
12.89 & Sqm 11.00 66,750 734,250.00 - - - -
level
frame &work
plumb and including
providing chasing
cut out of wallnecessary
/ plaster wherever required, surface
E.9 mm thickness
Providing and (6 mm Stone
Fixing thk Clear CladdingHSand + 0.89mm
STwith 4004 thk support
fabric +Fantasy
- Breccia for
6mm switch
thk boxes
Clear
Imperial HS) Sqm 2.00 19,381 38,762.00 - - - -
preparation,
and light filling
fittings and & finishing
cleaning the
etc. joints cement & approved quality
fixed
polishedto the laid SS frame and filling thecompleted
gap with at allasfloors.
sealant, necessary (supports
per all
E.10 colour pigments,
Providing andwith fixingmatching
cutting,
of double colour
mitering skinat cement
edges,
solid joints
wooden/ curing, ply per
cleaning, FF &etc
partition Ewith as6mm
complete Sqm 72.00 43,732 3,148,704.00 - - - -
complete
approved as per the
sample) atdwg.PDR and
Counter directions with of the project 1:4 manager.
as
Ref.per
grooves
35% the over
on instructions
columns,
completion
Dwg.-ID-1.6A.6-4 of
&of the
20mmrawproject
1.6A.7-7 wide Wall
shell manager.
metal
(including trimrequired
Height and
(MT4003)
shutters)
cement
andlength
50x50mm backing
of the 15,306 - - 35.72 35.72 - 546,768.08 546,768.08
All SS
mortar
skirting parts
and
as shall
cement
per the bebacking
finished with
applied PVD/@ Electroplated
3kg/m2, grinding, as permirrorthepolishing.
hard
wooden
Name: sections
Rovere Oak atarchitectural
the endsstain
(Colour (Dwgdrawings.
to -match
1.6A.7-6). (Mode
WD-4004) Allofinside
measurements
frame shall: Only
be
finishes
Cost30% to schedule
on
include fixing to veneer/
of
providing match the
sailen MT-4001
laminate/
/ siloxin Fabric finish.
solvent and any other
based finishing
protective sealer coat 13,120 - - - - -
Running
made
Finish: of30%length
aluminumgloss, of skirting
member’s size
Water-based shall be
PU measured for payment)
of 50mm x 25mm x 1.6mm thick section
products
onmaximum
all side onofpolishing/
the processed
at 25% 600mm c/c both/ finished
painting & fixing
ways. 10mmstone etc. plywood
of accessories
thick All complete on bothas per sidesdetail,
shall 10,933 - - - - -
Note: Fabric
specifications, to be sandwiched between the glass shall be provided by the
Base
be 5%rate:
finished withdrawings
Rs.
on virtual 100/
4mm sqft
completion thick and to the (WD4001)
veneer satisfactionofofapproved the Project make Manager.
& shade. All 2,187 - - - - -
client.
Mode of measurement : areaasasper seen in elevation. Nothing willinstructions
be paid extra
other
5% finishes
on handover shall be done detail drawings and as per of 2,187 - - - - -
Ref.insertions
for Dwg. - ID-1.6A6-3
& overlaps &etc.
ID-11.6A.7-9
the project manager. Rate to include cost of all materials, labour, transport,
E.11 Providing, making and fixing metal open
taxes of all kind etc complete. Partition should be fixed up to ceiling & wall screen (MT4003) consisting of Sqm 6.00 41,661 249,966.00 - - - -
E.12 frames
Ref. Dwg.
Providing
properly ofonly
size 50x50mm
&- ID-1.6A.6-7
fixing
visible 4mm area and
Veneer
below 30mm falsewide
panelling ceiling metal will trim
(WD4001) onApproved
of
be considered one sidefor inlcuding
Shade & Sqm 3.00 13,442 40,326.00 - - - -
making
Texture
measurements.the
on 12mmbase frame thick BWR to elevate grade the whole screen
Plywood with Marine 50mmadhesive from theincluding
FFL as
per the architectural drawing and directions of the project manager to of the - - -
the groove Pattern etc. all complete as per the drawing and directions
TOTAL FOR
properly WALLthe
reinforcing FINISHING
stable structure WORKS with (E)the required arrangement etc. 7,125,924.00 - 925,913.29 925,913.29
project
Ref. Dwg. manager.
ID-1.6A.1-2
all complete.
03/05/2020 Location: PDR Room ANNEX-D
Ref.
Ref. Dwg.
Dwg. -- ID-1.6A.7-7
ID-1.6A.6-7
Client: Indian Hotels Co. Ltd. Project: Taj Mahal Hotel, New Delhi
PROJECT CODE: ID0004
PROJECT NAME: TAJ MAHAL HOTEL, NEW DELHI
WORK ORDER NO. : IHCL/TMH/CHAMBER/SCG/2019-20/30
WORK DETAILS : Civil & ID works for Guest Floors renovations at Taj Mahal Hotel, Man Singh Road, New Delhi
DAVI CERTIFICATE NO 0%
CONTRACTOR RA BILL NO. : RA-01

ANNEXURE D- 13TH FLOOR LOUNGE AREA & OFFICES

AS PER WORKORDER BILL QUANTITY BILL AMOUNT


Sr.
Description Unit Qty
No.
Rate Amount Previous bill This bill Cumulative Previous bill This bill Cumulative
- - -
F CEILING FINISHING WORKS -
F.1 Providing and fixing at site composite false ceiling of POP with acrylic Sqm 256.00 6,878 1,760,768.00 - - - -
F.2 emulsion
Providing paint,
& fixing Wood
Trap(WD4001)
door (hinged) in combination
of sizes as of persoild
the fluted
drawings andwithplainthe Sqm 0.60 13,810 8,286.00 - - - -
pattern
suitableas per the
frame drawing with
& suspenders two coats of sealer and two coats of water
F.3 Providing and fixing into place(section
moulding 50mm x 50mm).
of size 50mm xSingle25mmshutteras permade Rmt 45.00 253 11,385.00 - - - -
based
out polish,marine
of 19mm bronzeplywood
finish foil&leaf
teak (SF4001)
wood installed
leaping flat or
hinged to taper
the or vertical
design made from plaster of paris. Item shall include painting withframe
2 coatsas of
- - -
or Coveinordrawing
shown makingincluding
grooves P/f on the
Allenjunction
key lock, of walls
hinges,andsafety
ceiling where ever
chain,
plastic emulsion paint over a coat of primer of approved shade to match the
required
TOTAL
necessary to
FOR do so
CEILING
hardware, on grid framework
FINISHING
finished comprising
WORKS (F) of rolled galvanized metal 1,780,439.00 - - -
finish (PT4001) with cost of allwith 4mm thick
materials approved
as directed veneer
by the on one
project side
manager.
sections.
and synthetic The enamel
grids shall be (suspended
paint primer + 3 from coatsstructural slab by
) of approved MS&strap
make shade - - -
hangers
on other 25mmx3mm
side etc. size @as1000mm
complete instructed C/C by both
the ways from
project structural
manager. slabof
(Mode by
G DOORS
Ref. Dwg.&ID-1.6A.7-6
WINDOWS WORKS -
using soffit cleats
measurements and of
: Area expandable
trap door fasteners.
opening G.Ibe
shall wire mesh 24for
measured SWG GI
payment)
*Note: Rate quoted for frame shall include the provision
shall be stretched tight over the frame work and plaster of Paris avg.12mm for sub-frame of the - - - - -
G.1 required
Single
thick isleafsize
applied, as trowelled
Concealed per directions
Door of thetoproject
or (D4003),
floated 40 mmmanager.
produce thick shutter,
smooth 1 houri/crated
surfaces fire
providing No 1.00 75,864 75,864.00 - - - -
door,
frame structural
Teak woodwork of opening
forapproved
light size, A/C
fixtures
make - 950mm
(IC/grills,
CPT): xdiffuser,
2600mm, both side
shadow line to be finished
etc.as per in - - - - -
paint
drawing (PT-4002)
no. bearing
Mode with 6mm
ofHinges V-grooves
measurement to match theinpattern on wall including
a) S.S butt 102mm area x 76mm as seen
x 3mm plan area.
- 4 Nos. Nothing will
- - - - -
all
be hardwares
paid extra for mentioned
verticals,below
grooves as per
andHardware
drops etc.Schedule, as per drawings,
b) Solid
FFE handle
schedule & in SS
directions of the project manager - - - - -
c) SS
Ref. Dwg.Concealed
:- ID-1.6B.2 Door Closer rack & pinion with standard arm - - - - -
G.2 Ref.
SingleDwg.leaf:-Door
ID-D4003-1
(D4004), 50 mm thick shutter, 1 hour rated fire door, Nos 1.00 126,594 126,594.00 - - - -
structural
Teak wood opening
of approved size - make
1000mm (IC/xCPT):
2800mm, both side to be finished with 4 - - - - -
mm thick veneer (WD-4001), 9mm wide metal strip (MT4001) with 3mmm
a) S.S butt bearing Hinges 102mm x 76mm x 3mm - 4 Nos. - - - - -
shadow gap on top and bottom including all hardwares mentioned below as
b)
perSolid
Hardwarehandle in SS as per drawings, FFE schedule & directions of the
Schedule, - - - - -
project manager. Door Closer rack & pinion with standard arm
c) SS Concealed - - - - -
G.3 Double Leaf Door (D4005): Structural opening size 1800mm x 2440mm, 50 Nos 2.00 134,880 269,760.00 - - - -
Ref.
mm Dwg.wooden
:- ID-D4004-1
Teakthick
wood of approved shutter, 1 hour
make (IC/rated
CPT): fire door, inner & outer side to be - - - - -
finished with paint (PT4002) finish including all hardwares mentioned below
a) S.S Hinges 102mm x 76mm x 3mm - 6 Nos. - - - - -
as per Hardware Schedule, as per drawings, FFE schedule & directions of
b) Solid
the project handle
manager. in SS - - - - -
c) S.S Rubber Door stopper - - - - -
Ref.Vision
d) Dwg. panel
:- ID-D4005-1
of size 150mm x 600mm with 10mm thick fire rated glass on - - - - -
each
e) SSleaveConcealed Door Closer rack & pinion with standard arm - - - - -
G.4 Double Leaf Door (D4006): Structural opening size 1524mm x 2440mm 50 Nos 1.00 168,853 168,853.00 - - - -
mm
Teakthick
wood wooden
of approvedshutter, 1 hour
make (IC/rated
CPT): fire door, inner & outer side to be - - - - -
finished with 3mm thick veneer of WD-4001 finish including all hardwares
a) S.S Hinges 102mm x 76mm x 3mm - 6 Nos. - - - - -
mentioned below as per Hardware Schedule, as per drawings, FFE
b) Solid handle
schedule in SS of the project manager.
& directions - - - - -
c) S.S Rubber Door stopper - - - - -
Ref.
d) SS Dwg. :- ID-D4006-1
Concealed Door Closer rack & pinion with standard arm - - - - -
G.5 Providing, making and fixing in position selected seasoned (Ivory Coast/ Cum 0.40 294,619 117,847.60 - - - -
CPT or as per approval) second class teak wood in frames of doors made to - - -
size, shape and design as shown in drawing, with mitred joints fixed with
TOTAL FOR DOORS AND WINDOWS WORKS (G) 758,918.60 - - -
40x3mm flat iron hold fast 400mm long embedding for concrete blocks
300mm x 100mm x 150mm in cement concrete 1:2:4 in contact with brick - - -
H FIXED
wall or byFURNITURES
approved dash WORKS
fastener in contact with RCC as directed including -
H.1 making necessary
Reception Desk grooves, chamfering etc. including applying water proof No 1.00 144,823 144,823.00 - - - -
wood
Providing
35% primer and 2 coats
on& completion
placing of of
Reception
rawtermite
shell proof
Desk(including
as per paint on concealed
details surfaces, polish
given in specification.
shutters) 50,688 - - 1.00 1.00 - 50,688.05 50,688.05
in desired shade of approved make and shade over a coat of approved
30%
primer on
as: perfixing of veneer/ laminate/ Fabric and any other
specification etc. complete as per detailed drawings. (All paint/ finishing 43,447 - - - - -
Item No. FR4025
products
Ref.25%
polishDwg onNo.
finish polishing/
has to be painting
: ID-FR4025-1 & fixing of accessories
water based). 36,206 - - - - -
5% on virtual completion 7,241 - - - - -
5% on handover 7,241 - - - - -
H.2 Bookcase No 2.00 130,369 260,738.00 - - - -
Providing & placing Bookcase as per details given in specification.
03/05/2020 Item No. : FR4029 ANNEX-D
Ref. Dwg No. : ID-FR4029-1
Client: Indian Hotels Co. Ltd. Project: Taj Mahal Hotel, New Delhi
PROJECT CODE: ID0004
PROJECT NAME: TAJ MAHAL HOTEL, NEW DELHI
WORK ORDER NO. : IHCL/TMH/CHAMBER/SCG/2019-20/30
WORK DETAILS : Civil & ID works for Guest Floors renovations at Taj Mahal Hotel, Man Singh Road, New Delhi
DAVI CERTIFICATE NO 0%
CONTRACTOR RA BILL NO. : RA-01

ANNEXURE D- 13TH FLOOR LOUNGE AREA & OFFICES

AS PER WORKORDER BILL QUANTITY BILL AMOUNT


Sr.
Description Unit Qty
No.
Rate Amount Previous bill This bill Cumulative Previous bill This bill Cumulative
H.3 Bar & Back Bar No 1.00 864,705 864,705.00 - - - -
H.4 Providing
Service & placing Bar & Back Bar as per details given in specification.
Station No 1.00 129,080 129,080.00 - - - -
H.5 Providing
PDR Pantry & placing
CabinetService Station as per details given in specification. No 1.00 241,955 241,955.00 - - - -
Item No. : FR4034
H.6 Providing
PDRDwg Dining & placing
Table PDR Pantry Cabinet as per details given in specification. No 1.00 146,849 146,849.00 - - - -
Ref. No.
Item No. : FR4035 : ID-FR4034
Providing & placing PDR Dining Table as per details given in specification. - - -
Ref. Dwg
Item No. : No. FR4036 : ID-FR4035-1
TOTAL
Ref. Dwg FOR FIXED FURNITURES WORKS 1,788,150.00 - 50,688.05 50,688.05
Item No. : No. FR4038 : ID-FR4036
Ref. Dwg No. : ID-FR4038-1 - - -
I MISCELLANEOUS WORKS -
I.1 Installation, of following Miscellaneous Items as per specification described. - - - - -
a Ref.
AR4021Dwg.Artwork: ID-1.6A.5-2
@ Wall Panel No 5.00 690 3,450.00 - - - -
b AR4022 Artwork @ Corridor No 2.00 460 920.00 - - - -
c AR4023 Artwork @ PDR Entrance No 1.00 690 690.00 - - - -
d AR4024 Artwork @ PDR No 1.00 690 690.00 - - - -
I.2 Providing, fixing, fabricating railing above finish floor level, in profile made Rmt 14.00 14,731 206,234.00 - - - -
out of 25mm dia (minimum thickness 1.5mm) Stainless steel (grade 304)
uprights (end and intermediate) at about 1100mm c/c and 50 mm dia solid
TOTAL FOR MISCELLANEOUS WORKS 211,984.00 - - -
wood pipe finish (WD4001) as hand rail, SS rosette cover fixed with SS pins,
dowels, clamps, rubber, screws, gaskets etc. including required jointing and
IV 13TH FLOOR-
sealing with approved OFFICES quality silicon sealant etc. all complete as per detail
drawing,
Note: Metal specification
parts to betoused entire satisfaction
while of the project
making furniture itemsmanager.
shall be madde 10 mmof
thick+ clear
SS glass (GL4002)
appropriate coating toshould matchalso be provided
the finish and other in between
work shall theuse stair
SSrail
+
D FLOORING WORKS -
with the
PVD help of stainless steel knob and screw etc. all complete and as per
coating.
D.1 Providing
the drawing & fixing in position
and directions of5themm wide and
project 15mmWork
manager. high metal
includes (MT-4001)
preparing Rmt 13.00 1,657 21,541.00 - - - -
D.2 transition
Providing
shop drawingsclipping
and fixing trim
to scale of of19mmapproved
with thick shape
joinery machine
and fixing andcut,pattern
machine
details for flooring
and polished
further joint
includes as per
approved Sqm 14.00 17,908 250,712.00 - - - -
architectural
Italian
providing marble drawing
samples (ST-4001)
and and - instructions
Palissandro
preparing ofClassico
full scale themockup
project manager
on stair
samples treads including
for and risers as
approval.
necessary hardware, drilling, cutting as project
specified and as as per
directed - - -
shown in drawing
All SS parts shall or as
be directed
finished with byPVD/
the manager.
Electroplated Treads tobyhave
the hard
TOTAL
Architect. FOR FLOORING
(Running WORKS 272,253.00 - - -
5mm
finishesx 5mmschedule to length
chamfering match at of the
front
the trimall
and
MT-4003 shall be measured
exposed
finish. edges machinefor billing) polished.
Tread and riser marble shall be fixed over the base paneling made of BWR - - -
E Colour/
WALL
ply/
Ref. Bison Finish:
FINISHING
Dwg.-ID-1.6A.6-1, Antique
or shera WORKS board Hairline
using the
1.6A.7-1 & 2suitable adhesive etc. all complete at all -
Ref.
All Dwg.
heights
plywood and ID-1.6B.4-2
leadsbe
shall asofper BWRthe grade
drawing and to
except forthe
wash approval
room or/ of theandproject
wet areas - - - - -
E.1 manager.
which
Providing shalland be fixing
Marine of grade
100 mm plywood.
high, 20mm thick having 10 x 10mm shadow Rmt 144.00 1,404 202,176.00 - - - -
E.2 gap, Solid&Wood
Providing applying (WD-4001)
two or more Skirting coats as ofperAcrylic
detailing shownEmulsion
Premium in drawing. water Sqm 181.00 314 56,834.00 - - - -
Location: ofStairs
Skirtingpaint, approved
E.3 based
Providing
Ref. Dwg: and finish
ID-1.6B.4-2 ofcolour
applying approved
&15-18mm
and finish
ID-1.6B.7-1
to be fixed
manufacturer
thk ( avg.) POP andon wall with
shades
plaster
necessary
toaswalls
per using Sqm 181.00 359 64,979.00 - - - -
hardwares in approved
specifications to the adhesive,
interior wall colour and
surfaces sealed
of the withincluding
building approvedapplying quality
E.4 approved
Fixing
sealant, wallquality
paper POP as per
of following ISlevel.
2547-1976,
types: over all plain/ tocurved surfacesby - - - - -
one
of coat/laid
brick block
in proper
of Primer, / RCC one line
and coat andof
to be putty,
finished
Finishing/
including
smooth
polishing
scaffolding,
in correct
be
as as
line,
directed
directed.
levelWall&
I Cost
the
12mm shall
project
thick include
manager.
BWR providing,
ply Cost
base to making
include
paneling and
making
with fixing
aluminum the
groove base
as
frame paneling.
per specification,
work made out of - - - - -
(Make :Dulux
plumb, makingbe orofequivalent
edges, evenly as per sill,
corners, project
jambs, manager's advice)grooves (10mm)
soffits, pattas,
paper
labour,
38x 50mmshould
materials,
aluminum applied
wastages,
heavy box to
cleaning avoid
section bubbles.
after
@ completion,
600mm c/c necessary
both ways protection
(spacing
a a. WP-4001
etc. as per drawings(ID-1.6B.6-6 & ID-1.6B.7-8)
& relevant specifications including all necessary Sqm 86.00 4,741 407,726.00 - - - -
and inclusive
should
Material no ofNo:
be exceed
Code all (PT-4002)
lead,
than lifts etc. complete,
600mm depending as onperlength
the instructions
and height). and to the
Frame
surface
35% preparation,
on completion making level
of manager.
raw shellpads (Dada),
(including scaffolding, hacking of
Client
shall
Colour/ beSupplied
satisfaction of the
supported
Code:
Item
Dulux
: Wall
project
with
38YY aluminumPaper
72/117 box (sample
–etc. section
Indian toshutters)
be38x
of
Legend submitted
50mm @ to 600mm
designers c/c 1,659 - - 41.68 41.68 - 69,153.41 69,153.41
surface
Ref. to
on receive
Dwg.-ID-1.6A.6-7
30% fixing ofplaster,
veneer/ cleaning
laminate/ complete
Fabric and at(Waterproof
any allother
levels andand
finishing
Mould-
heights all 1,422 - - - - - -
group
fix on
proof) for
wall approval)
with 40x40x3mm aluminum angle for fixing the wall paper and
complete
products as per the directions of the project manager.
also including
25% on p/f
polishing/
Finish: Matte Emulsion 20mm thick
painting basotect
& fixing foam
of in the
accessories frame as per drawing and 1,185 - - - - - -
Ref.5%
finishDwg.
the :- ID-1.6B.6-6
onpaneling
virtual with approved wall covering including cutting, necessary
completion 237 - - - - - -
Name: Rovere
hardware, drilling,OakVinyl(Colour pvc stain
gripper,.to match
The work WD-4004).
also includes vertical drops,
5%
Finish: on
30% handover
gloss,
curvature, coves, cutting Water-based & framePU work and providing cut out and necessary 237 - - - - - -
b WP-4002for
support with p/f ofboxes
switch 50 & 25mm wide wooden
and lightfittings frame (WD4001)
and cleaning etc. completed and 10mm, at all Sqm 21.00 9,207 193,347.00 - - - - -
9mm
floors
35%wide
ason permetal
completiontrim (MT4001)
the drawing of and with(including
raw directions
shell shadowof thegap as per
project
shutters) drawing (ID-1.6B.6-
manager. 3,222 - - 10.42 10.42 - 33,574.71 33,574.71
6 & ID-1.6B.7-8&9)
30% on fixing of veneer/ laminate/ Fabric and any other finishing 2,762 - - - - - -
products
25% on polishing/ painting & fixing of accessories 2,302 - - - - - -
5% on virtual completion 460 - - - - - -
5% on handover 460 - - - - - -
c WP-4003 (Accent Wall) with p/f of 9mm wide metal trim (MT4001) with 3mm Sqm 48.00 9,207 441,936.00 - - - -
shadow gap shown as per the drawing (ID-1.6B.6-6 & ID-1.6B.7-8)
03/05/2020 ANNEX-D
Client: Indian Hotels Co. Ltd. Project: Taj Mahal Hotel, New Delhi
PROJECT CODE: ID0004
PROJECT NAME: TAJ MAHAL HOTEL, NEW DELHI
WORK ORDER NO. : IHCL/TMH/CHAMBER/SCG/2019-20/30
WORK DETAILS : Civil & ID works for Guest Floors renovations at Taj Mahal Hotel, Man Singh Road, New Delhi
DAVI CERTIFICATE NO 0%
CONTRACTOR RA BILL NO. : RA-01

ANNEXURE D- 13TH FLOOR LOUNGE AREA & OFFICES

AS PER WORKORDER BILL QUANTITY BILL AMOUNT


Sr.
Description Unit Qty
No.
Rate Amount Previous bill This bill Cumulative Previous bill This bill Cumulative
II POP base paneling on grid framework comprising of rolled galvanized metal - - - - -
a sections
WP-4001and G.I wire mesh
(ID-1.6B.6-6 24 SWG GI shall be stretched tight over the
& ID-1.6B.7-8) Sqm QRO 2,588 - - - -
frame work and plaster of Paris avg. 12mm thick is applied, trowelled or
b WP-4002 with p/f of 50 & 25mm wide wooden frame (WD4001) and 10mm, Sqm QRO 7,052 - - - -
floated to produce smooth surfaces i/c providing frame work for light fixtures,
9mm
WP-4003 wide(Accentmetal trim (MT4001) p/f with shadow wide gap astrim
per drawing (ID-1.6B.6-
c shadow line etc.asWall) per the withdrawing of 9mmand directions metal of the(MT4001)
project manager.with 3mm Sqm QRO 7,052 - - - -
6 & ID-1.6B.7-8&9)
shadow gap shown
E.5 Providing & fixing in as per thetimber
positions drawing (ID-1.6B.6-6
panelling (WD-4001)& ID-1.6B.7-8)
as per - - - - -
architectural
With out 10mm drawing
metal and trim instructions
(ID-1.6B.6-8) of the project manager. The system Sqm 11.00 21,728 239,008.00 - - - -
shall be comprising following:
35% on completion of raw shell (including shutters) 7,605 - - 4.47 4.47 - 33,955.43 33,955.43
Aluminium frame work - Providing, making and fixing aluminium frame work
made 30% outonoffixing
50 x 25mm of veneer/ laminate/
aluminium Fabric
heavy boxand any other
section @ 600mm finishingc/c both 6,518 - - - - -
ways products
25% (spacing
on polishing/should painting
not exceed moreofthan
& fixing 600mm depending on length
accessories 5,432 - - - - -
and5% height) fixed completion
on virtual directly on wall as per drawing and thickness of panelling. 1,086 - - - - -
Panelling - providing and fixing 12mm BWR grade ply with 4mm thick
5% on handover
veneer with 10mm shadow gap as per the drawing fixed on the frame as per 1,086 - - - - -
drawing including cutting, necessary hardware, drilling, etc. all complete. - - - -
The
TOTAL work FOR alsoWALL includes vertical drops,
FINISHING WORKS curvature, coves, cutting & frame 1,606,006.00 - 136,683.55 136,683.55
work and providing cut out and necessary support for switch boxes and light - - -
fittings and cleaning etc. completed at all floors.
F CEILING FINISHING WORKS -
F.1 Providing
Ref. and fixing at site False Ceiling of Plaster of Paris installed flat or
Dwg.-ID-1.6B.6-1 Sqm 190.00 2,486 472,340.00 - - - -
F.2 taper
Name:orRovere
Providing vertical
& fixing orTrap
Oak Cove
(Colour or making
door stain togrooves
(hinged) of sizes
match onasthe
WD-4004) per junction of wallswith
the drawings andthe Sqm 3.50 13,810 48,335.00 - - - -
ceiling
suitable where
frame ever required
& suspenders to doPU so on grid framework comprising of rolled
F.3 Finish: 30%
Providing gloss,
& applying paint on(section
Water-based ceiling, Slab50mm x 50mm).
soffit, beamsSinglecornice shutter
etc atmade
all Sqm 190.00 363 68,970.00 - - - -
galvanized
out of 19mm metal
marine sections consisting of the main channels (50mm x 25mmas x
levels
Providing withand two coats plywood
ofin approved & teak wood
primer andleaping hinged
coats oftoof
threefeatures the frame
approved paint-
F.4 22SWG)
shown in to runerecting
drawing in one position
direction
including P/f at following
Allen1000mm
key ceiling
c/chinges,
lock, and secondary
safety POP in size
ceiling
chain, to - - - - -
Acrylic
the false Premium
ceiling/ emulsion.,
junction of including
the ceiling labour,
and preparation
wall including of surface,
filling the gaps with
a section
Moulding
necessary 70mm x23mmfinished
- hardware,
50x25mm x24SWG withat 4mm
450mm thickc/capproved
in other direction
veneerason connected
one side Rmt 65.00 253 16,445.00 - - - -
levelling
POP & , scrapping,
painting the sandwith
same papering,
2 coats scaffolding,
of Acryllic all materials
Emulsion paint per
over a coat
to main
and channel
synthetic with GI
enamel connecting
paint primer clips of 10) SWG of approvedmakequality.
b Cornice
drawings
of
- etc,
100x100mm
as directed by( Project +Manager.
3 coats of approved
(Note: Measurement & as
shade
per Rmt 144.00 470 67,680.00 - - - -
onprimer
with
IS
above
other
1200)
of500mm
side
(Make
approved
etc. pattacolour
complete
: Dulux
smooth
asand texture
instructed
or equivalent as per
as
by per
finish required the the
to putdrawing
project
project
light inand
manager.
manager
linedirections
level.
advice).(Mode The
Mode of - - - -
of the
grids project
shall be manager:
suspended from structural slab by MS strap hangers
measurements
of measurement : Area
area of trap
as seen door
in opening
plan. Nothing shallwill
bebe measured
paid extra for payment)
TOTAL FOR size
25mmx3mm CEILING @ 1000mm FINISHING C/C both WORKS ways from structural slab by using 673,770.00 - - -
Ref.
soffitDwg.
cleats- ID and- 1.6B.7-10
expandable fasteners. G.I wire mesh 24 SWG GI shall be - - -
Item Finishing No. :- PT-4001
G stretched
DOORS &tight
WINDOWSover the WORKS frame work and plaster of Paris avg. 12mm thick is -
Ref. Dwg.
applied, :- ID-1.6B.2-1
trowelled or floated toshall
produce smooth surfacesfor i/c sub-frame
providing frame
*Note: Rate
Colour/ Code: quoted
Duluxfor 45YY frame 82/098 –include
Neutral the provision
Garden of the - - - - -
work
requiredfor light
size fixtures
as per , A/C
directions grills,
of diffuser,
the project shadow
manager. line etc.as per drawing no.
G.1 Finish:
Single Matte
leaf DoorEmulsion
(D4013), 50 mm thick wooden shutter, 1 hour rated fire Nos 5.00 103,116 515,580.00 - - - -
Mode of measurement area as seen in plan area. Nothing will be paid extra
door,
Teak
for structural
wood
verticals, opening
ofgrooves
approved size
andmake drops - 950mm
(IC/
etc.CPT): x 2400mm, both sides to be finished - - - - -
with WD4001 finish and 9mm metal strip having 3mm shadow gap in pattern
a) S.S butt bearing Hinges 102mm x 76mm x 3mm - 4 Nos. - - - - -
shown
Ref. Dwg. in the drawing including all hardwares mentioned below as per
:- ID-1.6A.2
b) Solid handle
Hardware Schedule, in SSas per drawings, FFE schedule & directions of the - - - - -
project manager. Door Closer rack & pinion with standard arm
c) SS Concealed - - - - -
G.2 Providing, making and fixing in position selected seasoned (Ivory Coast/ Cum 0.25 294,619 73,654.75 - - - -
Ref.
CPT Dwg.or as :- perID-D4013-1
approval) second class teak wood in frames of doors made to - - - -
size, shape and design as shown in drawing, with mitred joints fixed with
TOTAL FOR DOORS AND WINDOWS WORKS 589,234.75 - - -
40x3mm flat iron hold fast 400mm long embedding for concrete blocks
300mm x 100mm x 150mm in cement concrete 1:2:4 in contact with brick - - -
H FIXED
wall or byFURNITURES
approved dash WORKSfastener in contact with RCC as directed including -
H.1 making
Cabinet necessary grooves, chamfering etc. including applying water proof No 2.00 129,080 258,160.00 - - - -
H.2 wood
Providingprimer
Meeting Table & and
placing 2 coats
Cabinet of termite proof paint
as per details given oninconcealed
specification. surfaces, polish No 1.00 52,341 52,341.00 - - - -
in desired &
Providing shade
placing of approved
Meeting Table makeas andpershade
details over
given a coat of approved
in specification.
H.3 Cabinet
primer
Item No.as: perFR4060 specification etc. complete as per detailed drawings. (All paint/ No 1.00 107,720 107,720.00 - - - -
H.4 Providing
Meeting
polishDwg.finish & placing
Table has to be Cabinet
water as per details given in specification.
based). No 1.00 88,109 88,109.00 - - - -
Ref.
Item No. : ID-FR4060
: FR4061
H.5 Providing
Cabinet & placing Meeting Table as per details given in specification. No 3.00 120,149 360,447.00 - - - -
Ref. Dwg.
Item No. : FR4063 : ID-FR4061-1
H.6 ProvidingTable
Meeting & placing Cabinet as per details given in specification. No 3.00 46,218 138,654.00 - - - -
Ref.
Item Dwg. : ID-FR4063-1
No. : FR4064
Providing & placing Meeting Table as per details given in specification. - - - -
Ref. Dwg.
Item : ID-FR4064-1
No. : FR4065
TOTAL
Ref. Dwg. FOR FIXED FURNITURES WORKS
: ID-FR4065-1 1,005,431.00 - - -
Item No. : FR4066
Ref. Dwg. : ID-FR4066-1 - - -

03/05/2020 ANNEX-D
Client: Indian Hotels Co. Ltd. Project: Taj Mahal Hotel, New Delhi
PROJECT CODE: ID0004
PROJECT NAME: TAJ MAHAL HOTEL, NEW DELHI
WORK ORDER NO. : IHCL/TMH/CHAMBER/SCG/2019-20/30
WORK DETAILS : Civil & ID works for Guest Floors renovations at Taj Mahal Hotel, Man Singh Road, New Delhi
DAVI CERTIFICATE NO 0%
CONTRACTOR RA BILL NO. : RA-01

ANNEXURE D- 13TH FLOOR LOUNGE AREA & OFFICES

AS PER WORKORDER BILL QUANTITY BILL AMOUNT


Sr.
Description Unit Qty
No.
Rate Amount Previous bill This bill Cumulative Previous bill This bill Cumulative
I MISCELLANEOUS WORKS -
I.1 Installation, of following Miscellaneous Items as per specification described. - - - - -
a Ref. Dwg.
Artwork : ID-1.6A.5-1
- AR4051 No 1.00 690 690.00 - - - -
b Artwork - AR4053 No 1.00 690 690.00 - - - -
c Artwork - AR4054 No 5.00 921 4,605.00 - - - -
I.2 Providing, fixing, fabricating railing above finish floor level, in profile made Rmt 25.00 14,731 368,275.00 - - - -
I.3 out of 25mmx25mm
Providing (minimummetal
and fixing recessed thickness
strips1.5mm)
(MT4001)Stainless steelstair'
under the (grade 304)
steps Rmt 25.00 1,823 45,575.00 - - - -
(MT4001)
with 12mmuprights
thick BWR(endgrade
and intermediate)
ply to be pasted at about 1100mm
with suitable c/c and or
adhesive oval-
shaped solid wood - - - -
supports as per thepipe finishand
drawing (WD4001)
directionsasofhand rail, SSmanager.
the project rosette cover fixed
TOTAL
with SS FOR
pins, MISCELLANEOUS
dowels, clamps, rubber, WORKSscrews, gaskets etc. including 419,835.00 - - -
required jointing and sealing
Ref. Dwg.-ID-1.6B.6-1, 1.6B.7-1 with approved quality silicon sealant etc. all
complete as per detail drawing, specification to entire satisfaction of the
project manager. 10 mm thick clear glass GRAND
(GL4002)TOTAL
should also be provided 16,548,138.35 - 1,113,284.89 1,113,284.89
in between the stair rail with the help of stainless steel knob and screw etc.
all complete and as per the drawing and directions of the project manager.
Work includes preparing shop drawings to scale with joinery and fixing
Prepared by: Aman
details andSrivastava
further includes providing samples and preparing full scale Contractor Sign & Stamp :
mock-up samples for approval.
All SS parts shall be finished with PVD/ Electroplated as per the hard
finishes schedule to match the MT-4001 finish.

Ref. Dwg.-ID-1.6B.6-1, 1.6B.7-1

03/05/2020 ANNEX-D
Client: Indian Hotels Co. Ltd. Project: Taj Mahal Hotel, New Delhi

PROJECT CODE: ID0004
PROJECT NAME: TAJ MAHAL HOTEL, NEW DELHI
WORK ORDER NO. : IHCL/TMH/CHAMBER/SCG/2019-20/30
WORK DETAILS : Civil & ID works for Guest Floors renovations at Taj Mahal
Hotel, Man Singh Road, New Delhi
DAVI CERTIFICATE NO 0%
CONTRACTOR RA BILL NO. : RA-01

Measurement Sheet for 13th Floor - Lounge Area & Offices

Height /
Sr.No Item Ref. Desription Unit No. Length Width Quantity Remark
Depth

IV 13TH FLOOR- LOUNGE AREA


E.6 Providing & fixing in positions timber paneling (WD-4001) as per Sqm
architectural
Delivery drawing
Challan No. and instructions ofDt.
DSP/19-20/0475 the14.02.2020,
project manager.
Delhi The 17 1.220 2.440 50.606
system shall be comprising
Sales Plywood
CONSIDERING ONLY 50%following:
FOR NOW
Aluminum frame work - Providing, making and fixing aluminum
frame work made out of 50 x 50mm aluminum heavy box section Sqm Total Qty upto this bill 50.61
@ 600mm c/c both ways (spacing should not exceed more than Sqm Less Qty upto previous bill 0.00
600mm depending on length and height) fixed directly on wall as Net Qty upto this bill 50.61 Sqm
per drawing and thickness of paneling.
Panelling - providing and fixing 12mm thick ply of BWR grade with
E.10 Providing and fixing of double skin solid wooden/ ply partition with Sqm
4mm thick veneer including 10mm metal trim inside the square box
6mm grooves
Delivery over columns,
Challan 20mm wideDt. metal trim (MT4003)
Delhi and
fixed on the frameNo. DSP/19-20/0475
as per drawing including 14.02.2020,
cutting, necessary 12 1.220 2.440 35.722
50x50mm
Sales wooden
Plywood
CONSIDERING sections
ONLY 50% at the NOW
FOR ends (Dwg - 1.6A.7-6). All inside
hardware, drilling, etc. all complete. The work also includes vertical
frame shall be made of aluminum member’s size of 50mm x 25mm
drops, curvature, coves, cutting & frame work and providing cut out Sqm Total Qty upto this bill 35.72
x 1.6mm thick section at maximum 600mm c/c both ways. 10mm
and necessary support for switch boxes and light fittings and Sqm Less Qty upto previous bill
thick plywood on both sides shall be finished with 4mm thick 0.00
cleaning etc. completed at all floors.
veneer (WD4001) of approved make & shade. All other finishes Net Qty upto this bill 35.72 Sqm
shall be done as per detail drawings and as per instructions of the
Ref. Dwg.-ID-1.6A.6-4 & 1.6A.7-7
project manager. Rate to include cost of all materials, labour,
H.1 Name: Rovere
Reception DeskOak (Colour stain to match WD-4004) No
transport, taxes of all kind etc complete. Partition should be fixed
Finish:
Providing
30%
Reception &Desk
placing
gloss, Water-based
Reception DeskPU as per details given in 1 1.000
up to ceiling & wall properly only visible area below false ceiling will
specification.
be considered for measurements.
Item No. : FR4025 No Total Qty upto this bill 1.00
Ref. Dwg. ID-1.6A.1-2 No Less Qty upto previous bill
Ref. Dwg No. : ID-FR4025-1 0.00
Net Qty upto this bill 1.00 No

IV 13TH FLOOR- OFFICES


E.4 Fixing wall paper of following types:
I Cost shall
12mm thickinclude
BWR plyproviding, making with
base paneling and aluminum
fixing the base
framepaneling.
work
a Wall
made paper
out ofshould
a. WP-4001 38x 50mmbe applied
(ID-1.6B.6-6 evenly
aluminum to avoid
heavy
& ID-1.6B.7-8) bubbles.
box section @ 600mm c/c Sqm
both ways
Delivery (spacing
Challan No.should no be exceedDt. than 600mm depending
Client
on Supplied
length Item
and height). : DSP/19-20/0475
Wall
FramePaper 14.02.2020, Delhi
shall be supported with aluminum
14 1.220 2.440 41.675
Sales
Ref. Plywood
CONSIDERING
Dwg.-ID-1.6A.6-7 ONLY 50% FOR NOW
box section of 38x 50mm @ 600mm c/c fix on wall with
40x40x3mm aluminum angle for fixing the wall paper and also Sqm Total Qty upto this bill 41.68
including p/f 20mm thick basotect foam in the frame as per drawing Sqm Less Qty upto previous bill 0.00
and finish the paneling with approved wall covering including Net Qty upto this bill 41.68 Sqm
cutting, necessary hardware, drilling, Vinyl pvc gripper,. The work
also includes vertical drops, curvature, coves, cutting & frame work
b WP-4002
and providing with cut
p/f out
of 50 & 25mm
and widesupport
necessary woodenfor frame (WD4001)
switch boxes and Sqm
and 10mm,
Delivery
lightfittings 9mm
Challan
and wideDSP/19-20/0475
No.
cleaning metal
etc. trim (MT4001)
completed Dt. with shadow
14.02.2020,
at all floors gap
theas
Delhi
as per 4 1.220 2.440 10.419
per
Salesdrawing
drawing Plywood
CONSIDERING (ID-1.6B.6-6
and directions
ONLY of & ID-1.6B.7-8&9)
theFOR
50% project
NOWmanager.
Sqm Total Qty upto this bill 10.42
Sqm Less Qty upto previous bill 0.00
Net Qty upto this bill 10.42 Sqm

E.5 Providing & fixing in positions timber panelling (WD-4001) as per


architectural
With out 10mm drawing
metal and
trim instructions
(ID-1.6B.6-8)of the project manager. The Sqm
system shall
Delivery be comprising
Challan following: Dt. 14.02.2020, Delhi
No. DSP/19-20/0475 2 1.220 2.440 4.465
Aluminium
Sales frame work - Providing, making and fixing aluminium
Plywood
CONSIDERING
frame work madeONLYout of50%
50 xFOR25mm NOW
aluminium heavy box section
@ 600mm c/c both ways (spacing should not exceed more than Sqm Total Qty upto this bill 4.47
600mm depending on length and height) fixed directly on wall as Sqm Less Qty upto previous bill 0.00
per drawing and thickness of panelling. Net Qty upto this bill 4.47 Sqm
Panelling - providing and fixing 12mm BWR grade ply with 4mm
thick veneer with 10mm shadow gap as per the drawing fixed on
the frame as per drawing including cutting, necessary hardware,
drilling, etc. all complete. The work also includes vertical drops,
curvature, coves, cutting & frame work and providing cut out and
necessary support for switch boxes and light fittings and cleaning
etc. completed at all floors.

Ref. Dwg.-ID-1.6B.6-1
Name: Rovere Oak (Colour stain to match WD-4004)
Finish: 30% gloss, Water-based PU

03/05/2020 MS - D
Client: Indian Hotels Co. Ltd. Project: Taj Mahal Hotel, New Delhi

PROJECT CODE: ID0004
PROJECT NAME: TAJ MAHAL HOTEL, NEW DELHI
WORK ORDER NO. : IHCL/TMH/CHAMBER/SCG/2019-20/30
WORK DETAILS : Civil & ID works for Guest Floors renovations at Taj Mahal Hotel, Man Singh Road, New Delhi
DAVI CERTIFICATE NO 0%
CONTRACTOR RA BILL NO. : RA-01

ANNEXURE E- WASHROOM & LIFT LOBBY

AS PER WORKORDER BILL QUANTITY BILL AMOUNT


Sr.
Description Unit Qty
No.
Rate Amount Previous bill This bill Cumulative Previous bill This bill Cumulative

V WASHROOM
Note: Metal parts to be used while making furniture items shall be madde of
D SS + appropriate
FLOORING WORKS coating to match the finish and other work shall use SS + -
D.1 PVD coating.
Providing and laying of following types of approved machine cut, machine - - - - -
a polished Flooring
General marble flooring(ST1004) in pattern and size as detailed in drawing and as Sqm 38.00 10,588 402,344.00 - - - -
directed by the project
Name: Botticino Fioritomanager. Marble to be bedded over minimum 20mm
b Accent Flooring (ST1004 with ST1002 border) Sqm 18.00 11,232 202,176.00 - - - -
thick cement
Finish: Silver
Polished sand mortar mix ratio 1:6 (1 cement : 6 sand) including
Name: Portoro (ST1002)
cleaning and preparing the surface for bedding, spreading neat cement - - - -
Finish: Polished
slurry
TOTAL byFOR usingFLOORING
minimum cement WORKS about 3 kg/sqm prior to bedding and 604,520.00 - - -
spreading cement paste using minimum cement about 4.5 kg/sqm over - - - -
bedding, joints to be cleaned and grouted with matching colour approved
E WALL FINISHING WORKS -
quality polymer based readymade grout (Bal or Laticrete or equivalent
All plywoodcuring,
approved), shall becleaning,
of BWR polishing grade except for wash
to required room
line, or/protecting
level, and wet areas till - - - - -
E.1 which
Providing
handing shall
overand beetc.Marine
fixingall of grade
Marbleplywood.
complete Dado fixed over
at all heights andwhiteleadscement mortar 1:4 as
to the satisfaction of - - - - -
a per site
the project
General conditions
Stone manager. to
(ST1004) make the surface in level with quality seal coat Sqm 58.00 12,015 696,870.00 - - - -
application
Name: Botticino on all sides,
Fiorito laid in proper line and level. The Dado shall be done
b Accent Stone (ST1006) Sqm 4.00 34,342 137,368.00 - - - -
as
Ref.per
Finish: design
Dwg. / pattern as specified inclduing providing 10mm shadow gap
- ID-1.6D.4
Polished
Name: Tiger
Providing Onyx
E.2 as shown and , soap fixing
dish125mmniche, WC highledge,
approved etc. machine cut, machine
all other necessary polished
related Rmt 180.00 1,685 303,300.00 - - - -
Finish:
19mm Polished
thick
E.3 works as
Providing & approved
shown fixingononthe marble
sitedrawings.
Veneer stoneWall(ST1004)
Cost to include
panelling skirting
labour,
(WD-1002) including
materials,
finish10mm made of Sqm 38.00 9,364 355,832.00 - - - -
shadow
wastages, gap as shown in completion,
the drawing and as directed by the ofproject
12mm oncleaning
35%thick MR grade
completion after plywood
of raw shell necessary
over(including
Aluminium protection
framework
shutters) and inclusive
size 25x50 of 3,277 - - 17.86 17.86 - 58,537.64 58,537.64
manager.
all lead,
mm lifts
sections Marble
etc.
as per shall
complete, be fixed
as per
manufacturer's over
the pre-plastered
instructions and
specifications masonry/
with to the RCC
spacing surfaces
satisfaction
of 16" - 24" of
by 30%
theusing on fixing
approved of veneer/ laminate/ Fabric and any other finishing 2,809 - - - - -
c/c project
horizontally manager.andcompatible
Sample both
vertically toadhesive
beways
submitted (Bal or
.The toLaticrete
12mm thickor
designers equivalent
group
plywood for
surface to
products
approved)
25% onmachine
approval, to correct
polishing/ line, level
painting
polishing/ and plumb.
& fixing
finishing/ of Joints
accessories
cleaning are well cleaned and 2,341 - - - - -
be finished with 3 mm thick veneer as per designetc andasdrgs.per design
as perand drg,
grouted
drawing,
including
5% on with
all matching
specification
necessary
virtual completion colour
and
endas approved
directed by
mouldings, polymer
project based
moulding manager,
pattern, readymade
etc.polish.
and grout
Ant and
all complete. 468 - - - - -
cured, cleaned
termite treatment andto including
plywood finishing junction
including all leads of& plaster
lifts etc. all as
complete complete
per theat
all 5%
heightson handover 468 - - - - -
Ref. Dwg.
detailed drg. :-and leads toand
ID-1.6D.6-1
& design theas satisfaction
instructedofbythe project
project manager.
manager.
E.4 Providing and fixing mirror panelling (MI1001) with 15mm wide metal border Sqm 18.00 38,300 689,400.00 - - - -
(MT1001)
Ref.
Ref.35%Dwg.
Dwg.: on
- ID-1.6D.6-1of raw shell (including shutters) drawings. The frame
aluminium
ID-1.6D.4
on -completion framework as per the detailed 13,405 - - 8.93 8.93 - 119,706.65 119,706.65
work shall be fixed to the wall with necessary anchor screws.The 12mm
30% on fixing of veneer/ laminate/ Fabric and any other finishing 11,490 - - - - -
thick marine grade plywood shall have provision of indirect lighting, if
products
25% on polishing/
required. The plywoodpainting surface &shall fixingbeoffixedaccessories
with 6mm thick edge polished 9,575 - - - - -
clear5%mirror.
on virtual The completion
mirror shall be properly fixed using in combinolion of 3M 1,915 - - - - -
make double
5% on handover sided tape with primer applied lo ply and mirror and 1,915 - - - - -
Dowcorning / Mcoy make silicon sealants with necessary
E.5 Fixing wall paper (WP- 1001) finish
SS studs arrangements as per the drawing and directions . Cost to include preparing of the wall surface
project Sqm 36.00 433 15,588.00 - - - -
E.6 having
Providing
manager. one& The coat
fixing of5primer
frame mmandx 15 andmm putty and
high one trim
metal coat(MT-1001)
of enamel in paint
the in proper
marble Rmt 172.00 1,059 182,148.00 - - - -
line ply
dado
the and levelbe
running
shall in all direction
vertically
see inside andand foronlyapplying
horizintally mirror towall
be covering
fixed
shall bewih as peras
adhesive
projected theper
in thethe
manufacturer specification. - - - -
pattern,
drawing. shade, etc. as per drawing & instruction of the project manager.
TOTAL FOR WALL FINISHING WORKS 2,380,506.00 - 178,244.29 178,244.29
ClientDwg.
Ref. Supplied ID-1.3.6-1Item : Wall Paper
- ID-1.6D.6-1 - - - -
F Ref.
CEILINGDwg.FINISHING
:- ID-1.6D.6-2 WORKS -
F.1 Providing and fixing at site False Ceiling of Plaster of Paris installed flat or Sqm 56.00 2,624 146,944.00 - - - -
F.2 taper or vertical
Providing & fixing orTrap
Cobedoor or making
(hinged) grooves
of sizesonasthe perjunction of wallswith
the drawings andthe Sqm 1.50 13,810 20,715.00 - - - -
ceiling where
suitable ever required to(section do so on grid framework comprising of rolled
F.3 Providingframe & applying& suspenders
paint on ceiling, Slab 50mm x 50mm).
soffit, beamsSingle cornice shutter
etc atmade
all Sqm 56.00 363 20,328.00 - - - -
galvanized
out of 19mm metal
marine sections consisting of theleaping
main channels
levels
Providingwithand two coats plywood
installing of approved
POP
& teak
Cornice
wood
primer and
size three
of lock, 20
hinged
coats toapproved
20ofmm
the framepaint-as
F.4 (50mmx25mmx22SWG)
shown in drawing including to run
P/f in onekey
allen direction atmm
hinges,1000mm xsafety c/c shapes
and
chain, as per Rmt 95.00 184 17,480.00 - - - -
Acrylic
drawing Premium
including emulsion.,
all supporting including labour,
material, preparation
POP , lead of surface,
lift etc complete.
secondary
necessary ceiling section
hardware, sand finished70mm x23mm
with 4mm x24SWG
thick approved at 450mm c/c
veneerason in other
one side - - - -
levelling
direction ,connected
scrapping, topaint
main papering,
channel scaffolding,
with GI connectingall materialsclipsmake
of 10 per
and
TOTAL synthetic
drawings FOR enamel
CEILING by( Project
FINISHING primerWORKS+Manager.
3 coats )(Note:
of approved &SWG
shade of 205,467.00 - - -
Ref. Dwg etc,
approved -quality.as
0.4.7-1 directed
with above 500mm patta smooth
Measurement
finish required (Mode
as per
to put of
on other side etc. complete as instructed
IS 1200) (Make : Dulux or equivalent as per project manager advice). Mode by the project manager. - - - -
light in line level.: Area
measurements The grids of trap shalldoor beopening
suspended from
shallwillbebe structural for
measured slabpayment)
by MS
G of measurement
DOORS
strap & WINDOWS
hangers area as
25mmx3mm seen
WORKS sizein@ plan.
1000mm Nothing C/C both paid
waysextrafrom structural -
*Note:
slab byRate
usingquoted for frame
soffit cleats andshall include fasteners.
expandable the provision G.Ifor sub-frame
wire mesh 24of the - - - - -
Item Finishing
required size asNo. :- directions
PT-1003 of the project manager.
SWG GI
Toilet Door shall beper
stretchedand tight
fixingover the frame workdoor and plaster of Paris
G.1 Ref. Dwg. :-- ID-1.6D.2
Providing 50 mm thick flush shuttersof size Nos 4.00 126,364 505,456.00 - - - -
avg. 12mm
1000mm thick is applied, trowelled or floated to produce smooth surfaces
G.2 WC Door x- 2350mm
Providingconforming
and fixing 50 to IS:
mm2202
thick(Part
flushI)door
decorative
shutterstype, solid
of size Nos 8.00 113,704 909,632.00 - - - -
i/c providing
wood
800mm (IC/CPT)
x 2350mmframecorework for light fixtures
of WD-1002
conforming with , A/C
frame ofgrills,
1st diffuser,
class hardshadow
wood solidline
(IC/CPT)
G.3 Providing,
etc.as per making and
drawing no. fixing in to IS: 2202
position (Part
selected I)seasoned
decorative type,
(Ivory Coast/ Cum 0.55 294,619 162,040.45 - - - -
size as(IC/CPT)
wood per the drawing and well matched
core of WD-1002 with frame teak 3 ply
of 1st veneering
class hard with (IC/CPT)
15mm
CPT
Modeor
wide ofas
metal per approval)
measurement
moulding second
area
finished as
in class
seen inteak
MT-1002 plan
on wood
area.
both in frames
Nothing
faces of of wood
will doors
be paid
shutters asmade
extrato
per
size as per the drawing andshown
well matched teakwith
3 ply veneering with 15mm
03/05/2020 size,
design
shape
for verticals,
of the
and design as
grooves
drawingand anddrops
in drawing,
etc.
directions of theonproject
mitred
manager
joints fixed
including
with ANNEX-E
wide metal
40x3mm flatmoulding
iron holdfinished
fast 400mmin MT-1002
long embeddingboth faces of shutters
for concrete as per
blocks
Stainless
design ofx steel
the (304 Grade)
drawing butt hinges the
and directions withproject
two ball bearings, 100 mm X
300mm
Ref. Dwg. 100mm
:-mm x 150mm
ID-1.6D.2 in cementofconcrete 1:2:4manager including
in contact with brick
75 mm
StainlessX 3steel of ofGrade)
(304 approved buttmake
hingeswith necessary
with screws, with
two ball bearings, 100allmm X
Client: Indian Hotels Co. Ltd. Project: Taj Mahal Hotel, New Delhi

PROJECT CODE: ID0004
PROJECT NAME: TAJ MAHAL HOTEL, NEW DELHI
WORK ORDER NO. : IHCL/TMH/CHAMBER/SCG/2019-20/30
WORK DETAILS : Civil & ID works for Guest Floors renovations at Taj Mahal Hotel, Man Singh Road, New Delhi
DAVI CERTIFICATE NO 0%
CONTRACTOR RA BILL NO. : RA-01

ANNEXURE E- WASHROOM & LIFT LOBBY

AS PER WORKORDER BILL QUANTITY BILL AMOUNT


Sr.
Description Unit Qty
No.
Rate Amount Previous bill This bill Cumulative Previous bill This bill Cumulative
- - - -
TOTAL FOR DOORS AND WINDOWS WORKS 1,577,128.45 - - -
- - - -
H FIXED FURNITURES WORKS -
H.1 Providing & fixing vanity counter/ splashback with ST-1005 finish fixed Nos 2.00 71,261 142,522.00 - - - -
including moulding and polishing to edges to give high gloss finish, with 2 - - - -
drawers under to be finished in timber (WD-1003) finish using 12mm and
TOTAL FOR FIXED FURNITURES WORKS 142,522.00 - - -
19mm the marine plywood and approved veneer, Teak wood stepped
design moulding in front, soft closing runners for drawers and other - - - -
I MISCELLANEOUS
hardware from Hafele WORKS
or approved make as per Hardware Schedule and -
I.1 interior
Providing of the cabinet
& fixing to have
10 mm thick1frosted
mm thick laminateglass
toughened finishurinal
to match ST-1005
partitions (GL- No 4.00 29,370 117,480.00 - - - -
I.2 finish
1003) etc
of as
size per
450drawing
mm and required
x 1275
Installation of Artwork (AR1051) with MS
mm@Washroom frame
brass work
frame and
as ply
of section
Entrance backing.
per20 mm x 10
specification No 2.00 460 920.00 - - - -
Quoted
mm of rate
size to
450 be
mminclusive
x 1825 for
mm fixing and
(MT-1001)
described & directed by the project manager. fittings required
around the to
glass,install
to be and
fixed with
maintian,
SS hardwarewithofconcealed
Hafele orscrews
approvedfixed at the
make as bottom, the units
per drawing and to the
& directions of the - - - -
TOTAL FOR
satisfaction
project MISCELLANEOUS
of the Project Manager.
manager. WORKS 118,400.00 - - -
Ref. Dwg. : ID-1.6D.5

VI Ref.
LIFTDwg.
LOBBY-ID-1.6D.6-1
ID-1.6D.5
Note: Metal parts to be used while making furniture items shall be madde of
D SS + appropriate
FLOORING WORKS coating to match the finish and other work shall use SS + -
D.1 PVD coating.
Supplying ,fitting and fixing of (ST-401) Marble Flooring with accent stone Sqm 63.00 17,033 1,073,079.00 - - - -
flooring (ST-402) with uniform texture and without decorative veins in floor - - - -
with 15 mm thick (avg) cement mortar 1:2 including making suitable
TOTAL FOR FLOORING WORKS 1,073,079.00 - - -
arrangement to hold stone properly by adhesives including pointing the
cement mortar (1:2) (1 white cement :2 marble dust) with admixture of - - - -
E WALL FINISHING
pigment matching the WORKS
marble/ stone shade, pattern & all sizes as per the -
E.1 drawings, and
Providing all complete
fixing of 100mm as per direction of project
high (ST-401) manager.marble
pre-polished (Using skirting
cement Rmt 60.00 1,897 113,820.00 - - - -
E.2 slurryaPunning:
with
POP at
5mm backside
chamfering of marble/
Providing onandtopstone
edge@skirting
applying 315-18mm
Kg/ sqm and white
of approved
average cement
colour
thick andslurry
POP finish
punning for Sqm 53.00 359 19,027.00 - - - -
jointplastered
on fillingto@existing
matching 1.8 Kg/
walls sqm) hacking
flooring
including fixed on ofwall with necessary
existing surface andhardwares
all staging in
E.3 Providing & fixing on site Veneer Wall panelling (WD-401) made of 12mm Sqm 46.00 10,254 471,684.00 - - - -
approved necessary
including grout, colour and sealed
scaffolding, with approved
materials, labour,quality
lead, sealant,
lifts, laid in
necessary
thick
35% MRon
Location:
proper grade
Lift plywood
completion
Lobby ofover
raw Aluminium framework
shell (including shutters) of size 25x50 mm 3,589 - - 22.33 22.33 - 80,125.78 80,125.78
finishes,line
sections in
asof
and
true
per
level.
'line &Finishing/Polishing
levels, tospecifications
manufacturer's
to be
plumb, right as directed
angle, withoutby
with spacing
the project
waves,
of smooth
16" - 24" c/c
Base
manager.
30% Rate onCost
finish, all complete Marble:
fixing to include
of Rs.
veneer/
as directed400/sqft
labour, materials,
laminate/
by Fabric
the.The
project wastages,
and any
manager. cleaning
other after
finishing 3,076 - - - - -
horizontally
Ref.products and
Dwg. :- necessary vertically
ID-0.4.4, 0.4.7-1 both ways
& ID-1.6E.4 12mm thick plywood surface to be
completion,
25% with on polishing/ protection
painting and
& fixing inclusive of all lead, lifts etc. complete,
finished 3 mm thick veneer, 45mmofx accessories
10mm or 25mm x 10mm (at edges/ 2,564 - - - - -
as per
Ref. Dwg.the :- instructions
ID/0.1.4 and to the satisfaction of the project manager.
bottom/
5% on top) moulding with 5 mm grooves provided as per drg, including all
(Sample tovirtual completion
be submitted to designers group for approval) 513 - - - - -
necessary
5% on handover moulding pattern, and polish. Ant termite treatment to plywood 513 - - - - -
including all leads & lifts complete as per the detailed drg. & design and as
E.4 Ref. Dwg. and
Providing :-ID-0.4.7-2
fixing all sides polished natural stone (ST-402) as specified in Rmt 13.00 4,935 64,155.00 - - - -
instructed by project manager.
E.5 the drawing
Providing of approved
& Fixing 4mm Veneerquality, panelling
pattern, colour
(WD4001) and thickness
of Approved for door
Shade & Sqm 12.00 9,667 116,004.00 - - - -
architraves
Texture
Ref. Dwg.: (150
on -12mm mm
ID-0.4.6-3,thickwideBWR x 50
0.4.7-2&3 mm&thick)
grade Plywood including
ID-1.6E.4 preparing
with Marine the surface
adhesive including
andgroove
levelling in the etc. desired line, machine cutting, jointingand in approved - - - -
the Pattern all complete as per the drawing directions of the
TOTAL
adhesives, FOR WALL FINISHING WORKS
levelling, smooth cement plastering along the sides to match the 784,690.00 - 80,125.78 80,125.78
project manager.
existing surface in cement mortar, filling the joints with pigment mixed with - - - -
F cement, cleaning,
Smokingfinishing,
CEILING FINISHING
Location: RoomWORKS curing etc complete as directed by project -
F.1 manager.
Ref. Dwg. and
Providing - ID-1.6E.6-2
fixing at site False Ceiling of Plaster of Paris installed flat or Sqm 63.00 1,910 120,330.00 - - - -
F.2 taper
Providingor vertical
and or CobePOP
installing or making
Cornice grooves
of sizeon100 themm junction
x 100ofmm walls and as
shapes Rmt 60.00 470 28,200.00 - - - -
Ref. Dwg.:
ceiling where - ID-0.4.6-3
ever required & ID-0.4.7-2
to do so material,
on grid framework comprising of rolled
F.3 per drawing
Providing & including
applying all supporting
paint on ceiling, Slab POP
soffit, , lead
beams lift etc complete.
cornice etc at all Sqm 63.00 363 22,869.00 - - - -
galvanized metal sections consisting of the main channels
levels with two coats of approved primer and three coats of approved paint- - - - -
(50mmx25mmx22SWG)
Ref. Dwg - 0.4.7-1 & to run in one direction at 1000mm c/c and
ID-1.6E.2
Acrylic Premium emulsion., including labour, preparation of surface,
secondary
TOTAL FOR ceiling
CEILING section 70mm x23mm
FINISHING WORKS x24SWG at 450mm c/c in other 171,399.00 - - -
levelling , scrapping, sand papering, scaffolding, all materials as per
direction connected to main channel with GI connecting clips of 10 SWG of - - - -
drawings etc, as directed by Project Manager. (Note: Measurement as per
approved quality. with above 500mm patta smooth finish required to put
G DOORS
IS 1200) & WINDOWS
(Make : DuluxWORKS or equivalent as per project manager advice). Mode -
light in line level. The grids shall be suspended from structural slab by MS
of measurement
Single leaf Door ,area
50 mm as seen
thick in plan. (concealed
Nothing willdoor), be paid extrarated fire
G.1 strap hangers 25mmx3mm sizeshutter
@ 1000mm C/C both 1 hour
ways from structural No 2.00 69,926 139,852.00 - - - -
door,
Teak
slab by structural
wood
using opening
of soffit
approved size
cleatsmakeand- expandable
950mm
(IC/ CPT):x 2600mm,
fasteners. inner G.Iside
wiretomesh
be finished
24 - - - - -
Item Finishing
in paint (PT-401) No. :- PT401
& outer side to over
be finished withwork
4 mm thick veneer (WD-
SWG
a) S.S GI shall
butt:-bearingbe stretched
Hinges tight the frame
102mm x 76mm x 3mm - 4 Nos. and plaster of Paris - - - - -
Ref.
401) Dwg.
including ID/0.4.2
all & ID-1.6E.2
hardwares mentioned below as per Hardware Schedule,
avg. 12mm thick is applied, trowelled or floated to produce smooth surfaces
as per drawings,
i/c providing frame FFE workschedule
for light&fixtures
directions
, A/C ofgrills,
the project
diffuser, manager
shadow line
03/05/2020 (Location
etc.as per:drawing Staircase no.Entry Door) ANNEX-E
Mode of measurement area as seen in plan area. Nothing will be paid extra
Ref. Dwg. :- ID-D12-1
for verticals, grooves and drops etc.
Client: Indian Hotels Co. Ltd. Project: Taj Mahal Hotel, New Delhi

PROJECT CODE: ID0004
PROJECT NAME: TAJ MAHAL HOTEL, NEW DELHI
WORK ORDER NO. : IHCL/TMH/CHAMBER/SCG/2019-20/30
WORK DETAILS : Civil & ID works for Guest Floors renovations at Taj Mahal Hotel, Man Singh Road, New Delhi
DAVI CERTIFICATE NO 0%
CONTRACTOR RA BILL NO. : RA-01

ANNEXURE E- WASHROOM & LIFT LOBBY

AS PER WORKORDER BILL QUANTITY BILL AMOUNT


Sr.
Description Unit Qty
No.
Rate Amount Previous bill This bill Cumulative Previous bill This bill Cumulative
b) Solid handle in SS packaged with mortise lockset 55mm backseat 20 SS - - - - -
fronted, SS strike
c) SS Door Closerplate
rackand EP Cylinder 
& pinion with standard arm - 1 No. - - - - -
d) S.S. Panic bar with 1 point locking with external trim & EP cylinder - - - - -
e) S.S 350mm long x 22mm dia D type pull handles - 2 Nos. - - - - -
f) Auto drop down door seal & in tumescent strip - - - - -
G.2 Providing & fixing 10 mm thick toughened glass partition in combination of - - - - -
a fixed/openable
Fixed part glass of ht 2440 mm up to false ceiling having 3 sides 50x50 Sqm 3.00 6,721 20,163.00 - - - -
mm and bottom 50x90 mm wooden frame finished in WD4001 with 10mm
b Door No 1.00 41,431 41,431.00 - - - -
wide metal strip all round with the frame etc. all complete. Openable glass to
G.3 Providing,
be supported making and fixing
on special patchin fittings
positionatselected
directed seasoned (Ivory
locations with Coast/
openable Cum 0.20 294,619 58,923.80 - - - -
CPT
door or as per approval)
operated secondhaving
on Patch fittings class teak wood in frames
upper/lower/side of doors
patch made to
with EPC - - - -
size,
lock, shape
SSFOR and &
handle design
strike as shown
plate in drawing,
of approved withPivot
make, mitred jointsFloor
hinge, fixedSpring
with
TOTAL DOORS AND WINDOWS WORKS 260,369.80 - - -
40x3mm flat iron as
etc. all complete hold
perfast
the400mm
drawinglong andembedding forthe
directions of concrete
projectblocks
manager.
300mm x 100mm x 150mm in cement concrete 1:2:4 in contact with brick - - - -
H MISCELLANEOUS
wall
Ref. or
Dwgby -approved
ID-D4018-1 WORKS
dash fastener in contact with RCC as directed including -
making necessary
Installation, grooves,
of following chamfering Items
Miscellaneous etc. including applying water
as per specification proof
described. - - - - -
H.1 wood
Ref.
AR primer
- Dwg.
401 IDand
- :Artwork 2 coats of termite proof paint on concealed surfaces, polish
0.4.1 No 2.00 690 1,380.00 - - - -
in desired shade of approved make and shade over a coat of approved
primer as per specification etc. complete as per detailed drawings. (All paint/ - - - -
TOTALfinish
polish FORhas MISCELLANEOUS
to be water based). WORKS 1,380.00 - - -

GRAND TOTAL 7,319,461.25 - 258,370.07 258,370.07

Prepared by: Aman Srivastava Contractor Sign & Stamp :

03/05/2020 ANNEX-E
Client: Indian Hotels Co. Ltd. Project: Taj Mahal Hotel, New Delhi ]

PROJECT CODE: ID0004
PROJECT NAME: TAJ MAHAL HOTEL, NEW DELHI
WORK ORDER NO. : IHCL/TMH/CHAMBER/SCG/2019-20/30
WORK DETAILS : Civil & ID works for Guest Floors renovations at Taj Mahal Hotel,
Man Singh Road, New Delhi
DAVI CERTIFICATE NO 0%
CONTRACTOR RA BILL NO. : RA-01

Measurement Sheet for Washroom & Lift Lobby

Height /
Sr.No Item Ref. Desription Unit No. Length Width Quantity Remark
Depth

V WASHROOM
E.3 Providing & fixing on site Veneer Wall panelling (WD-1002) finish made of Sqm
12mm
Deliverythick MR grade
Challan plywood over Aluminium
No. DSP/19-20/0475 framework
Dt. 14.02.2020, of Sales
Delhi size 25x50
Plywood 6.00 1.220 2.440 17.861
mm sections as per manufacturer's specifications with spacing of 16" - 24"
CONSIDERING ONLY 50% FOR NOW
c/c horizontally and vertically both ways .The 12mm thick plywood surface to
be finished with 3 mm thick veneer as per design and drgs. as per drg, Sqm Total Qty upto this bill 17.86
including all necessary end mouldings, moulding pattern, and polish. Ant Sqm Less Qty upto previous bill 0.00
termite treatment to plywood including all leads & lifts complete as per the Net Qty upto this bill 17.86 Sqm
detailed drg. & design and as instructed by project manager.

E.4 Providing
Ref. Dwg.:and fixing mirror panelling (MI1001) with 15mm wide metal border
- ID-1.6D.6-1 Sqm
(MT1001) on aluminium
Delivery Challan framework as per
No. DSP/19-20/0475 Dt.the detailed drawings.
14.02.2020, The
Delhi Sales frame
Plywood 3.00 1.220 2.440 8.930
work shall be fixed to the wall with necessary anchor screws.The 12mm
CONSIDERING ONLY 50% FOR NOW
thick marine grade plywood shall have provision of indirect lighting, if
required. The plywood surface shall be fixed with 6mm thick edge polished Sqm Total Qty upto this bill 8.93
clear mirror. The mirror shall be properly fixed using in combinolion of 3M Sqm Less Qty upto previous bill 0.00
make double sided tape with primer applied lo ply and mirror and Net Qty upto this bill 8.93 Sqm
Dowcorning / Mcoy make silicon sealants with necessary
SS studs arrangements as per the drawing and directions of the project
VI LIFT LOBBY
manager. The frame and
E.3 the ply shall
Providing be see
& fixing oninside and only
site Veneer mirror
Wall shall be
panelling projected
(WD-401) as per
made the
of 12mm Sqm
drawing.
thick MRChallan
Delivery grade plywood over AluminiumDt.
No. DSP/19-20/0475 framework of size
14.02.2020, 25x50
Delhi Salesmm
Plywood 7.50 1.220 2.440 22.326
sections as per manufacturer's specifications with spacing of 16" - 24" c/c
CONSIDERING ONLY
Ref. Dwg. - ID-1.6D.6-1 50% FOR NOW
horizontally and vertically both ways .The 12mm thick plywood surface to be
finished with 3 mm thick veneer, 45mm x 10mm or 25mm x 10mm (at edges/ Sqm Total Qty upto this bill 22.33
bottom/ top) moulding with 5 mm grooves provided as per drg, including all Sqm Less Qty upto previous bill 0.00
necessary moulding pattern, and polish. Ant termite treatment to plywood Net Qty upto this bill 22.33 Sqm
including all leads & lifts complete as per the detailed drg. & design and as
instructed by project manager.

Ref. Dwg.: - ID-0.4.6-3, 0.4.7-2&3 & ID-1.6E.4

03/05/2020 MS - E
Client: Indian Hotels Co. Ltd. Project: Taj Mahal Hotel, New Delhi

PROJECT CODE: ID0004
PROJECT NAME: TAJ MAHAL HOTEL, NEW DELHI
WORK ORDER NO. : IHCL/TMH/CHAMBER/SCG/2019-20/30
WORK DETAILS : Civil & ID works for Guest Floors renovations at Taj Mahal Hotel, Man Singh Road, New Delhi
DAVI CERTIFICATE NO 0%
CONTRACTOR RA BILL NO. : RA-01

ANNEXURE F- LOOSE FURNITURES

AS PER WORKORDER BILL QUANTITY BILL AMOUNT


Sr.
Description Unit Qty
No.
Rate Amount Previous bill This bill Cumulative Previous bill This bill Cumulative

VII LOOSE FURNITURES


*Note- The nominclature of the furnitres are based on the "Furntiure General
Arrangement"
Metal parts to bedrawing. In case
used while of anyfurniture
making difference between
items the
shall be nominclatures
madde of SS +
A mentioned
appropriate
DINING ROOM incoating
FF&E from the mentioned
to match drawing,
the finish and please
other work keep
shall in SS
use mind that
+ PVD -
A.1 both are
coating. the same
Dining Table Type 1 items. In case of any doubts, please consult the project No 2.00 50,545 101,090.00 - - - -
manager/
Providing Architect.
& placing Dining Table Type 1 as per details given in specification.
A.2 Dining Chair No 42.00 15,560 653,520.00 - - - -
Providing
35% on& completion
placing Dining
of rawChair as(including
shell per detailsshutters)
given in specification. 5,446 - - 42.00 42.00 - 228,732.00 228,732.00
Item30%
No.on
: FR4004
fixing of veneer/ laminate/ Fabric and any other finishing 4,668 - - - - - -
FFE Ref No.
Itemproducts
No.on -
: FR4005FR-4004
25% polishing/ painting & fixing of accessories 3,890 - - - - - -
FFE Ref No. - FR-4005
5% on virtual completion 778 - - - - - -
5% on handover 778 - - - - - -
A.3 Dining Table Type 2 No 4.00 30,843 123,372.00 - - - - -
A.4 Providing
Dining & placing
Table Type 3Dining Table Type 2 as per details given in specification. No 3.00 38,761 116,283.00 - - - - -
A.5 Providing
Dining Table& placing
Type 4Dining Table Type 3 as per details given in specification. No 4.00 29,554 118,216.00 - - - - -
Item No. : &
Providing FR4006
placing Dining Table Type 4 as per details given in specification. - - - - -
FFE Ref
Item No.
No.FOR - FR-4006
: FR4007
TOTAL DINING ROOM 1,112,481.00 - 228,732.00 228,732.00
FFE Ref
Item No. No. - FR-4007
: FR4008
FFE Ref No. - FR-4008
B WET AREA -
B.1 Dressing Stool No 2.00 8,378 16,756.00 - - - -
Providing & placing Dressing Stool as per details given in specification. - - - -
TOTAL FOR WET AREA 16,756.00 - - -
Item No. : FR1051
Ref. Dwg No. : ID-FR1051-1
C MEETING ROOMS & GYM -
C.1 Lounge Chair Type 1 No 2.00 11,232 22,464.00 - - - -
C.2 ProvidingTable
Cocktail & placing Lounge Chair Type 1 as per details given in No 2.00 33,697 67,394.00 - - - -
specification.
Providing
35% on& completion
placing Cocktail
of rawTable
shell as per details
(including given in specification.
shutters) 11,794 - - 1.00 1.00 - 11,793.95 11,793.95
30% on fixing of veneer/ laminate/ Fabric and any other finishing 10,109 - - - - - -
Itemproducts
No. : FR4022
FR4028
25% on polishing/ painting & fixing of accessories 8,424 - - - - - -
FR-4022
FFE Ref No. - FR-4028
5% on virtual completion 1,685 - - - - - -
5% on handover 1,685 - - - - - -
C.3 Sofa No 2.00 47,783 95,566.00 - - - - -
C.4 Providing
Dining & placing Sofa as per details given in specification.
Chair No 32.00 15,560 497,920.00 - - - - -
Providing
35% on& completion
placing Dining
of rawChair as(including
shell per detailsshutters)
given in specification. 5,446 - - 32.00 32.00 - 174,272.00 174,272.00
Item30%
No.on
: FR4031
fixing of veneer/ laminate/ Fabric and any other finishing 4,668 - - - - - -
FFE Ref No.
Itemproducts
No.on -
: FR4037FR-4031
25% polishing/ painting & fixing of accessories 3,890 - - - - - -
FFE Ref No. - FR-4037
5% on virtual completion 778 - - - - - -
5% on handover 778 - - - - - -
C.5 Side Table No 2.00 28,725 57,450.00 - - - - -
Providing
35% on& completion
placing SideofTable as per
raw shell details given
(including in specification.
shutters) 10,054 - - 1.00 1.00 - 10,053.75 10,053.75
30% on fixing of veneer/ laminate/ Fabric and any other finishing 8,618 - - - - - -
Itemproducts
No.on
25% : FR4039
polishing/ painting & fixing of accessories 7,181 - - - - - -
FFE Ref No. - FR-4039
5% on virtual completion 1,436 - - - - - -
5% on handover 1,436 - - - - - -
C.6 Console No 1.00 23,201 23,201.00 - - - - -
Providing
35% on& completion
placing Console
of rawas per (including
shell details given in specification.
shutters) 8,120 - - 1.00 1.00 - 8,120.35 8,120.35
30% on fixing of veneer/ laminate/ Fabric and any other finishing 6,960 - - - - - -
Itemproducts
No.on
25% : FR4053
polishing/ painting & fixing of accessories 5,800 - - - - - -
FFE Ref No. - FR-4053
5% on virtual completion 1,160 - - - - - -
5% on handover 1,160 - - - - - -

03/05/2020 ANNEX-F
Client: Indian Hotels Co. Ltd. Project: Taj Mahal Hotel, New Delhi

PROJECT CODE: ID0004
PROJECT NAME: TAJ MAHAL HOTEL, NEW DELHI
WORK ORDER NO. : IHCL/TMH/CHAMBER/SCG/2019-20/30
WORK DETAILS : Civil & ID works for Guest Floors renovations at Taj Mahal Hotel, Man Singh Road, New Delhi
DAVI CERTIFICATE NO 0%
CONTRACTOR RA BILL NO. : RA-01

ANNEXURE F- LOOSE FURNITURES

AS PER WORKORDER BILL QUANTITY BILL AMOUNT


Sr.
Description Unit Qty
No.
Rate Amount Previous bill This bill Cumulative Previous bill This bill Cumulative
C.7 Lounger No 2.00 26,424 52,848.00 - - - - -
Providing & placing Lounger as per details given in specification. - - - -
TOTAL FOR MEETING ROOM & GYM 816,843.00 - 204,240.05 204,240.05
Item No. : FR4057
FFE Ref No. - FR-4057
D LOUNGE AREA -
D.1 Console No 1.00 195,277 195,277.00 - - - -
D.2 Providing
Lounge & placing
Chair Type 1Console as per details given in specification. No 22.00 11,232 247,104.00 - - - -
Providing
35% on& completion
placing Lounge Chair
of raw shellType 1 as per
(including details given in
shutters) 3,931 - - 16.00 16.00 - 62,899.20 62,899.20
Item30%
No.on
: FR4021
specification.fixing of veneer/ laminate/ Fabric and any other finishing 3,370 - - - - - -
FFEproducts
Ref No. - FR-4021
25% on polishing/ painting & fixing of accessories 2,808 - - - - - -
Item No. : FR4022
5% on virtual completion 562 - - - - - -
FFE Ref No. - FR-4022
5% on handover 562 - - - - - -
D.3 Cocktail Table No 12.00 26,055 312,660.00 - - - - -
Providing
35% on& completion
placing Cocktail
of rawTable
shell as per details
(including given in specification.
shutters) 9,119 - - 1.00 1.00 - 9,119.25 9,119.25
30% on fixing of veneer/ laminate/ Fabric and any other finishing 7,817 - - - - - -
Itemproducts
No.on
25% : FR4023
polishing/ painting & fixing of accessories 6,514 - - - - - -
FFE Ref No. - FR-4023
5% on virtual completion 1,303 - - - - - -
5% on handover 1,303 - - - - - -
D.4 Console No 2.00 24,951 49,902.00 - - - - -
D.5 Providing
Reception&Chairplacing Console as per details given in specification. No 1.00 21,636 21,636.00 - - - - -
Providing
35% on& completion
placing Reception Chair(including
of raw shell as per details given in specification.
shutters) 7,573 - - 1.00 1.00 - 7,572.60 7,572.60
Item30%
No.on
: FR4024
fixing of veneer/ laminate/ Fabric and any other finishing 6,491 - - - - - -
FFEproducts
Item Ref
No. No.
: - FR-4024
FR4026
25% on polishing/ painting & fixing of accessories 5,409 - - - - - -
FFE Ref No. - FR-4026
5% on virtual completion 1,082 - - - - - -
5% on handover 1,082 - - - - - -
D.6 Sofa Type 1 No 1.00 40,142 40,142.00 - - - - -
D.7 ProvidingTable
Cocktail & placing Sofa Type 1 as per details given in specification. No 2.00 33,697 67,394.00 - - - - -
D.8 Providing
Sofa Type&2placing Cocktail Table as per details given in specification. No 2.00 52,847 105,694.00 - - - - -
D.9 Item
Sofa No.
Providing :
Type& FR4027
3placing Sofa Type 2 as per details given in specification. No 1.00 47,783 47,783.00 - - - - -
FFE
Item Ref
No.
Providing No.
:& - FR-4027
FR4028
placing Sofa Type 3 as per details given in specification.
D.10 Side Table No 2.00 24,214 48,428.00 - - - - -
FFE
Item Ref
No.
Providing No.
: - FR-4028
FR4030
35% on& completion
placing Side
ofTable as per
raw shell details given
(including in specification.
shutters) 8,475 - - 1.00 1.00 - 8,474.90 8,474.90
FFE Ref
Item No. No.
: - FR-4030
FR4031
30% on fixing of veneer/ laminate/ Fabric and any other finishing 7,264 - - - - - -
FFEproducts
Item Ref
No. No.
: - FR-4031
FR4032
25% on polishing/ painting & fixing of accessories 6,054 - - - - - -
FFE Ref No. - FR-4032
5% on virtual completion 1,211 - - - - - -
5% on handover 1,211 - - - - - -
D.11 Lounge Chair Type 2 No 16.00 12,705 203,280.00 - - - - -
Providing
35% on& completion
placing Lounge Chair
of raw shellType 2 as per
(including details given in
shutters) 4,447 - - 16.00 16.00 - 71,148.00 71,148.00
specification.
30% on fixing of veneer/ laminate/ Fabric and any other finishing 3,812 - - - - - -
products
25% on polishing/ painting & fixing of accessories 3,176 - - - - - -
Item No. : FR4033
635 - - - - - -
FFE5%RefonNo.
virtual completion
- FR-4033
5% on handover 635 - - - - - -
D.12 PDR Dining Chair No 8.00 15,560 124,480.00 - - - - -
D.13 Providing
Side Table& placing PDR Dining Chair as per details given in specification. No 2.00 28,725 57,450.00 - - - - -
Providing & placing Side Table as per details given in specification. - - - -
Item
TOTAL No.FOR
: FR4037
LOUNGE AREA 1,521,230.00 - 159,213.95 159,213.95
FFE Ref
Item No. No. - FR-4037
: FR4039
FFE Ref No. - FR-4039
E OFFICES -
E.1 Lounge Chair Type 1 No 4.00 11,785 47,140.00 - - - -
E.2 Providing
Side Table& placing Lounge Chair Type 1 as per details given in No 2.00 28,725 57,450.00 - - - -
E.3 specification.
Providing & placing Side Table as per details given in specification.
Console No 1.00 23,201 23,201.00 - - - -
Providing & placing Console as per details given in specification.
FR4022
Item No. : FR4039
03/05/2020 Item
FFE Ref
No. No. FR-4022
- FR-4039
: FR4058 ANNEX-F
FFE Ref No. - FR-4058
Client: Indian Hotels Co. Ltd. Project: Taj Mahal Hotel, New Delhi

PROJECT CODE: ID0004
PROJECT NAME: TAJ MAHAL HOTEL, NEW DELHI
WORK ORDER NO. : IHCL/TMH/CHAMBER/SCG/2019-20/30
WORK DETAILS : Civil & ID works for Guest Floors renovations at Taj Mahal Hotel, Man Singh Road, New Delhi
DAVI CERTIFICATE NO 0%
CONTRACTOR RA BILL NO. : RA-01

ANNEXURE F- LOOSE FURNITURES

AS PER WORKORDER BILL QUANTITY BILL AMOUNT


Sr.
Description Unit Qty
No.
Rate Amount Previous bill This bill Cumulative Previous bill This bill Cumulative
E.4 Console No 1.00 57,360 57,360.00 - - - -
E.5 Providing
Office & placing Console as per details given in specification.
Table No 3.00 99,894 299,682.00 - - - -
Providing & placing Office Table as per details given in specification. - - - -
Item No.
TOTAL FOR: FR4059
OFFICES 484,833.00 - - -
FFE Ref
Item No. No. - FR-4059
: FR4067
FFE Ref No. - FR-4067
F LIFT LOBBY -
F.1 Console Table No 1.00 26,239 26,239.00 - - - -
Providing & placing Console Table as per details given in specification. - - - -
TOTAL FOR LIFT LOBBY 26,239.00 - - -
Item No. : FR401
Ref. Document : Lift Lobby & Corridor FFE
Ref. Dwg No. : ID0.4.1 GRAND TOTAL 3,978,382.00 - 592,186.00 592,186.00

Prepared by: Aman Srivastava Contractor Sign & Stamp :

03/05/2020 ANNEX-F
Client: Indian Hotels Co. Ltd. Project: Taj Mahal Hotel, New Delhi ]

PROJECT CODE: ID0004
PROJECT NAME: TAJ MAHAL HOTEL, NEW DELHI
WORK ORDER NO. : IHCL/TMH/CHAMBER/SCG/2019-20/30
WORK DETAILS : Civil & ID works for Guest Floors renovations at Taj
Mahal Hotel, Man Singh Road, New Delhi
DAVI CERTIFICATE NO 0%
CONTRACTOR RA BILL NO. : RA-01

Measurement Sheet for Loose Furnitures

Height /
Sr.No Item Ref. Desription Unit No. Length Width Quantity Remark
Depth

A.2 Dining Chair No


Providing
Chair & placing Dining Chair as per details given in specification. 42 42.000
Item No. : FR4005
FFE Ref No. - FR-4005 No Total Qty upto this bill 42.00
No Less Qty upto previous bill 0.00
Net Qty upto this bill 42.00 No

C.2 Cocktail Table No


Cocktail Table
Providing & placing Cocktail Table as per details given in specification. 1 1.000

Item No. : FR4028 No Total Qty upto this bill 1.00


FFE Ref No. - FR-4028
No Less Qty upto previous bill 0.00
Net Qty upto this bill 1.00 No

C.4 Dining Chair No


Providing & placing Dining Chair as per details given in specification.
Dining Chair 32 32.000

Item No. : FR4037


No Total Qty upto this bill 32.00
FFE Ref No. - FR-4037
No Less Qty upto previous bill 0.00
Net Qty upto this bill 32.00 No

C.5 Side Table No


Providing
Side Table& placing Side Table as per details given in specification. 1 1.000

Item No. : FR4039


No Total Qty upto this bill 1.00
FFE Ref No. - FR-4039
No Less Qty upto previous bill 0.00
Net Qty upto this bill 1.00 No

C.6 Console No
Providing
Console & placing Console as per details given in specification. 1 1.000

Item No. : FR4053 No Total Qty upto this bill 1.00


FFE Ref No. - FR-4053
No Less Qty upto previous bill 0.00
Net Qty upto this bill 1.00 No

D.2 Lounge Chair Type 1 No


Providing
Chair & placing Lounge Chair Type 1 as per details given in 16 16.000
specification.
No Total Qty upto this bill 16.00
Item No. : FR4022
FFE Ref No. - FR-4022 No Less Qty upto previous bill 0.00
Net Qty upto this bill 16.00 No

D.3 Cocktail Table No


Providing & placing Cocktail Table as per details given in specification.
Cocktail Table 1 1.000

Item No. : FR4023


No Total Qty upto this bill 1.00
FFE Ref No. - FR-4023
No Less Qty upto previous bill 0.00
Net Qty upto this bill 1.00 No

D.5 Reception Chair No


Providing
Reception&Chair
placing Reception Chair as per details given in specification. 1 1.000
Item No. : FR4026
No Total Qty upto this bill 1.00
FFE Ref No. - FR-4026
No Less Qty upto previous bill 0.00
Net Qty upto this bill 1.00 No

D.10 Side Table No


Providing
Side Table& placing Side Table as per details given in specification. 1 1.000

Item No. : FR4032 No Total Qty upto this bill 1.00


FFE Ref No. - FR-4032
No Less Qty upto previous bill 0.00
Net Qty upto this bill 1.00 No

03/05/2020 MS - F
Client: Indian Hotels Co. Ltd. Project: Taj Mahal Hotel, New Delhi ]

PROJECT CODE: ID0004
PROJECT NAME: TAJ MAHAL HOTEL, NEW DELHI
WORK ORDER NO. : IHCL/TMH/CHAMBER/SCG/2019-20/30
WORK DETAILS : Civil & ID works for Guest Floors renovations at Taj
Mahal Hotel, Man Singh Road, New Delhi
DAVI CERTIFICATE NO 0%
CONTRACTOR RA BILL NO. : RA-01

Measurement Sheet for Loose Furnitures

Height /
Sr.No Item Ref. Desription Unit No. Length Width Quantity Remark
Depth

D.11 Lounge Chair Type 2 No


Providing
Chair & placing Lounge Chair Type 2 as per details given in 16 16.000
specification.
No Total Qty upto this bill 16.00
Item No. : FR4033
FFE Ref No. - FR-4033 No Less Qty upto previous bill 0.00
Net Qty upto this bill 16.00 No

03/05/2020 MS - F