Vibro Waste for Blower Room for BNR 65,290.18 Approved but were
removed by WABAG
from Progress Billings
(included in
Vibro Waste for MCC-DG for BNR 266,630.10 22.262million)
Approved. Billed in
Progress Billing. Waiting
Lighting Post 252,878.60
for PO release. c/o
Marjorie and Julius
Approved by Wabag.
Community Property Repair (CARI). Waiting for PO
168,431.04 release. c/o Marjorie
and Julius
Approved by Wabag.
(CARI). Waiting for PO
Repair of Residential/ House at Site 82,921.28
release. c/o Marjorie
and Julius
Dissapproved by Wabag
Additional Works for Rebar Bending of Bored Piles at FET 12,007.12 & VMM. For higher
Management decision.
Denied by Wabag.
V.O. on Application of Construction Joint Sealant on Mat Foundation. 97,885.76
Claim Issue.
Billed in Progress
Billings. Waiting for PO
Billing For Filler Board On Slab On Grade Edge At Motor Pool & Fuel Handling 79,893.00
release. c/o Marjorie
and Julius
SCIC VO to Wabag
Construction of Light Vehicle Parking Lots at Motorpool & BNR Area 408,262.00 approved. Wabag issues
SI to SCIC.
SCIC VO to Wabag
Construction of Ramp at Chemical Handling (BNR) 88,379.20 approved. Wabag issues
SI to SCIC.
TOTAL 31,298,436.97