Академический Документы
Профессиональный Документы
Культура Документы
Assignment No: 01
Taxil
1
[Document title] [Date]
Concrete structures are constructed to provide a service during a limited time period and,
in some cases, the need for maintenance is foreseen. However, recently durability of
concrete has been a social concern due to the poor performance of concrete caused by
various environmental, physical, and chemical factors such as corrosion of reinforcement
bars due to carbonation or chloride ingress, freezing-thawing action, sulfate attack, alkali
aggregate reaction, and so forth. The resistance against these chemical erosions and
physical deteriorations depends on the chemical composition and the microstructure of
hardened cement matrix and on the environmental conditions.
The cause for deterioration of the concrete structure located in severe environment has
been explored both in field and in laboratory. Serious cracking and spalling appeared
upon surface of the concrete structure soon after the structure was put into service. Both
2
[Document title] [Date]
alkali- aggregate reaction and freeze-thaw cycles may result in similar macro visible
cracking and
3
[Document title] [Date]
spalling. The possibility of alkali-aggregate reaction was excluded by both field survey
and lab examination such as chemical analysis, petrographic analysis, and determination
of alkali reactivity of aggregates. According to results of freeze-thaw cycles,
impermeability testing, and microstructure analysis, it is deduced that the severe
environmental conditions plus the relatively inferior frost resistance cause the
deterioration of concrete.
4
[Document title] [Date]
c. Corrosion of Steel
Corrosion of reinforcing steel and other embedded metal is the leading cause of
deterioration in concrete.
Corrosion of reinforcement leads to volume expansion of the steel, which can cause
cover cracking and spalling; this weakens the bond of the reinforcement. The bond slip
model was extended to include corroded reinforcement. Analysis of corroded beams
using the methodology gave results which are on the safe side. However, for large
corrosion penetrations that lead to extensive cover cracking, more detailed modelling of
the surrounding concrete and stirrups is required. Under such conditions, when wide
cracks develop, the favorable effect of rust flowing through the cracks becomes
significant; this decreases the splitting stress around the bar. A previously developed
corrosion model was extended to include this phenomenon. The volume flow of rust
through a crack was assumed to depend on the splitting stress and the crack width.
5
[Document title] [Date]
Material assessment of the existing structures can be done by performing the following
tests
f. Trial Pits
6
[Document title] [Date]
obtain their individual sizes. The chiseled points were later filled and finished back to
original surface finish
.
5. Sub soil/ Geotechnical investigation
The output of the sub-soil investigation is detailed in the geotechnical
investigation findings including all activities undertaken by the laboratory to
ascertain the geotechnical conditions. For this purpose various tests have to be
performed, as given below
Test pit layer details were also examined recorded as profiles and are shown in detail
in the appendix. The stratigraphy revealed by each pit was carefully logged with
special note taken to the thicknesses and conditions of the various layers. The
soil descriptions and classifications discussed in this report and shown on the
attached test pit logs are generally based on visual observation and should be
considered approximate.
7
[Document title] [Date]
In this the Core cutter method was used. This was done to determine the dry density
(mass of dry soil per cubic meter) of natural or compacted soil in situ, since density is
also an important parameter of strength and a measure of the Degree of Compaction.
The core cutter is a cylindrical metal of known dimension (volume) and weight, and
has a cutting sharp edge. The core cutter was driven into the floor of the excavated pit
at a suitable depth using a steel dolly. The core cutter was then later carefully
extracted out of the pit, and it contained a core of soil. A small portion of soil was
also taken and placed in an air tight container for relative moisture content
determination. The weight of the core cutter and the sample in it was taken.
Calculations were done to obtain the field / insitu density
c. Sampling
Bulk samples were taken from each of the test pits at 1.0 – 1.5m depth
intervals for laboratory testing. Representative soil samples obtained throughout
the exploration program were placed in air tight containers and transported to
the laboratory. In the laboratory, the soil samples were classified in general
accordance with techniques outlined in the visual-manual identification procedure
(ASTM D 2488) and the Unified Soil Classification System.
Dynamic Cone Penetrometer (DCP) tests were conducted through the ground
belowsurfacing to provide an estimate of the in-situ bearing capacities of the layers
underneath.DCP tests at this stage were performed in the test pits at depth
intervals of 1.50m,commencing from ground level as presented in the appendix
on the site layout. Theprogram of dynamic cone penetrometer testing was carried
out, using the TRL model conepenetrometer with 8kg hammer falling through a shaft
of drop height 575mm, which internforces a 20mm diameter/60 degree cone into the
encountered strata.The TRL DCP is an instrument designed for the rapid in-situ
measurement of the structural
8
[Document title] [Date]
e. Chemical Test
Chemical tests were also conducted on the extracted soil samples, the sand material
found on site and also ground concrete samples from hardened concrete specimens.
I. Sulphate tests :
In this test, we use gravimetric method w. It involved obtaining 50gms of air dried
samples were placed in extraction bottles and 100ml of distilled water added to
each before covering tightly. These were then mounted onto shakers and
agitated for 16 hours. The soil suspensions were then filtered into clean and dry
flasks. 50ml of the soil suspensions were dissolved in distilled water, after
which Barium chloride solution was added to each, to form a precipitate of
Barium sulphate, which was collected, dried and weighed. The Sulphate content
was then calculated from the mass of water used in the analysis and the mass of
Barium sulphate precipitated.
f. Trial pits
Two trial pits were sunk at approximate nominal distribution as presented on the
site layout plan, each pit attaining a target depth of about 2.5 - 3.0m. Two of the test
pits were located at foundation points. The test pitting operations were carried out
manually with aid of hand tools such as hoes, spades and pick axes. The test pits were
located in alternate positions of the site as requested by the design team. The aim of the
excavation of trial pits was to determine the structure of existing sub soils, the type of
underlying soils, including extraction of both disturbed and undisturbed samples.
In-situ density tests to determine the actual density of the underlying strata where
carried out with aid of the core cutter method.
9
[Document title] [Date]
The following method is used for repairing and maintenance to prevent failure
i. This method involves enlarging the crack along its exposed face and sealing it
with a suitable joint sealant or rich mixed mortar.
ii. It can be used for both fine and larger isolated cracks.
iii. This techniques is mostly used for floors and pavements.
Reason
10
[Document title] [Date]
Advantages
I. In this method the crack is enlarged along its exposed face to form a V-shaped
groove up to a minimum width of 6 mm and a depth of 6 to 25 mm.
II. This method is commonly used for both fine pattern cracks and large isolated
Disadvantage
I. Routing and sealing of cracks in concrete can be used for dormant cracks not
involving the restoration of tensile strength
II. Cement grouts are avoided due to the chances of future cracking
III. One of the defect of this method is swelling with time.
2. Stitching
Stitching may be used when tensile strength must be re-established across major
cracks.
Stitching involves
11
[Document title] [Date]
Reason
I. Crack stitching is a permanent and very successful method of structural
repairing for properties suffering with cracks in the masonry and in the mortar
bed joints.
Advantage
Disadvantage
i. The development of cracking is due to the tensile stress ,thus can be arrested by
suppressing this stress
ii. Cracks can be closed by inducing a compression force to overcome the tensile
stresses.
iii. The compressive force is applied by
iv. Pre-stressing wires or rods
v. Wedging – by opening the cracks and filling with expanding mortar, by jacking
and grouting or by actual driving wedges
12
[Document title] [Date]
Reason
Advantage
Disadvantage
In case of minor cracking - the RC member can be repaired by injecting suitable grout as
follows:
13
[Document title] [Date]
v. Inject the grout till it comes out from the next nipple and then move to next nipple;
vi. After injection of grout through all the nipples is completed, re-plaster the surface
and finish as required.
Reason
Advantage
Disadvantage
i. Chisel out the crack to create a backward-angled cut, using a cold chisel and a
hammer.
ii. Clean loose material from the crack using a wire brush, or a portable drill with a
wire wheel attachment.
iii. Apply at thin layer of rich cement slurry for bonding between old and new
concrete
iv. apply rich screed over the prepared surface
Reason
Advantage
Disadvantage
I. Concrete overlays are thin and do not last as long as the slab beneath them.
II. Some overlays show durability problems within several years
15
[Document title] [Date]
III. Acid etching and other types of concrete color work tend to fade aeay over time
unless the floor is consistently sealed
Reason
Advantage
Disadvantage
I. It cost more than other method of repairing the cracks mean that it is
uneconomical method
II. A technical expert man is acquired to this job
III. It is to tedious method of repairing
16