DOC. TITLE :-

PRODUCTION SCHEDULE

for

BASKET STRAINER SP1040, SP1041, SP1042

PROJECT NAME: SEPAT EARLY PRODUCTION SYSTEM PROJECT - MOPU

OWNER: PETROFAC

PRSB CLIENT: KENCANA HL SDN BHD

PURCHASE ORDER NO.: C100031-ME-059-11PB

PRSB JOB NO.: J11-PE188

1 20-Apr-11 INCORPORATING CLIENT'S COMMENTS HARUTA HARUTA HARUTA


0 23-Mar-11 ISSUE FOR REVIEW / APPROVAL HARUTA HARUTA HARUTA
REV DATE DESCRIPTION PREPARED CHECKED APPROVED
HARUTA KOREA CORP
BUYER PETRA FABRICATORS SDN BHD PRODUCTION SCHEDULE
ITEM NAME 3units of Basket strainer PO NO : J11-PE188-001 PRODUCTION PERIOD : 2011.03.15 ~ 2011.04.13 MANUFACTURER: Haruta Korea
YEAR 2011
Article MONTH 3 4 REMARKS
DATE 15 18 21 23 25 27 29 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 20

ITEM No. EQUIPMENT Maker (%) (%)

Basket strainer 3PCS HARUTA


1. ENGINEERING 10
1) PREPARING DRAWINGS 3 ⇒
2) CHECK DATA SHEET 2 ⇒
3) CHECK APPROVAL DATA SHEET 2 ⇒
4) APPROVAL DRAWINGS 3 ⇒
2.PURCHASE & INCOME RAW MATERIAL 30
1) WOODEN PATTERN
2) CASTING 20 ⇒ ⇒
3) SCREEN 4 ⇒
4) FLANGE 2 ⇒
5) BOLT & NUT 2 ⇒
6) GASKET 2 ⇒
3. MANUFACTURING 60
1) MACHINING 10 ⇒ ⇒
2) DRILLING 10 ⇒ ⇒
3) SCREEN 5 ⇒
4) ASSEMBLY 10 ⇒ ⇒
5) HYDROTEST 10 ⇒ ⇒
6) PAINTING 5 ⇒
7) 3RD PARTY INSPECTION 5 ⇒
8) SHIPMENT 5 ⇒
T O T A L 100 100
PLAN 7 10 13 6 4 5 5 5 5 5 5 5 5 5 5 5 5 100
SUB
RESULT
RATE OF PROCESS(%)
PLAN 7 17 30 36 40 45 50 55 60 65 70 75 80 85 90 95 100
TOTAL
RESULT