Вы находитесь на странице: 1из 9

DERIVED/ OUTPUT

ITEM NO. DESCRIPTION UNIT


(UNIT/MANDAYS) (UNIT/HOURS)
I. EARTHWORKS
800 - Clearing and Grubbing
a) Undergrowth and trees 12" dia sq.m. 136.00 m2/MD 17.0000 m2/Hr
b) Undergrowth and small bushes sq.m. 272.00 m2/MD 34.0000 m2/Hr

803 - Structures Excavation


a) Common Earth cu.m. 1.00 m3/MD 0.1250 m3/Hr
b) Sand cu.m. 1.30 m3/MD 0.1625 m3/Hr
c) Clay cu.m. 0.90 m3/MD 0.1125 m3/Hr
d) Rock cu.m. 0.85 m3/MD 0.1063 m3/Hr

804 - Embankment
a) Backfilling cu.m. 2.50 m3/MD 0.3125 m3/Hr
b) Spreading, Tamping and Grading cu.m. 2.50 m3/MD 0.3125 m3/Hr
c) Placing Escrombo Fill cu.m. 2.50 m3/MD 0.3125 m3/Hr
d) Gravel Fill
d-1) Hand Placed cu.m. 1.36 m3/MD 0.1700 m3/Hr
d-2) Placing Binder-gravel cu.m. 4.00 m3/MD 0.5000 m3/Hr

II. TERMITE CONTROL


1000 - Termite Control Works
a) Soil Poisoning - Cordoring sq.m. 20.40 m2/MD 2.5500 m2/Hr
b) Soil Poisoning - Drenching sq.m. 34.00 m2/MD 4.2500 m2/Hr
c) Wood Preservation sq.m. 20.40 m2/MD 2.5500 m2/Hr

III. DAMPROOFING/MOISTURE CONTROL


SPL - Damprooifng/ Moisture Control
a) Polyethelene Sheets (Spreading) sq.m. 54.40 m2/MD 6.8000 m2/Hr
b) Hydrolithic Waterproofing sq.m. 20.40 m2/MD 2.5500 m2/Hr

IV. CONCRETE WORKS


900 - Reinforced Concrete
A. FORMWORK INSTALLATION
a) Wall on ground sq.m. 3.40 m2/MD 0.4250 m2/Hr
b) Wall above ground sq.m. 2.86 m2/MD 0.3575 m2/Hr
c) Beams sq.m. 2.18 m2/MD 0.2725 m2/Hr
d) Columns sq.m. 2.86 m2/MD 0.3575 m2/Hr
e) Suspended Slab
e.1) 0 to 0.50 m sq.m. 4.01 m2/MD 0.5013 m2/Hr
e.2) 0.50m to 1.0m sq.m. 2.04 m2/MD 0.2550 m2/Hr
e.3) 1.0m up sq.m. 2.04 m2/MD 0.2550 m2/Hr
f) Elevated & Shored Slab
f.1) Forming Only sq.m. 0.75 m2/MD 0.0938 m2/Hr
f.2) Forming and Shoring sq.m. 0.61 m2/MD 0.0763 m2/Hr

B. FORMWORKS FABRICATION sq.m. 6.26 m2/MD 0.7825 m2/Hr


C. STRIPPING OF FORMWORKS
a) Wall on ground sq.m. 27.20 m2/MD 3.4000 m2/Hr
b) Wall above the ground sq.m. 5.24 m2/MD 0.6550 m2/Hr
c) Beams sq.m. 6.60 m2/MD 0.8250 m2/Hr
d) Columns sq.m. 7.96 m2/MD 0.9950 m2/Hr
e) Suspended Slab
e.1) 0 to 0.50 m sq.m. 8.16 m2/MD 1.0200 m2/Hr
e.2) 0.50m to 1.0m sq.m. 6.26 m2/MD 0.7825 m2/Hr
e.3) 1.0m up sq.m. 6.26 m2/MD 0.7825 m2/Hr
f) Elevated & Shored Slab sq.m. 1.91 m2/MD 0.2388 m2/Hr
g) Slab on Grade Strip of Forms sq.m. 2.38 m2/MD 0.2975 m2/Hr

D. FORMWORKS
Time required for erecting and
stripping forms per 100m2 of
Contract Surface

a) Concrete Footing and Foundation sq.m. 1.77 m2/MD 0.2213 m2/Hr


b) Concrete on Slab on Grade sq.m. 2.58 m2/MD 0.3225 m2/Hr
c) Concrete Columns and Beams sq.m. 1.22 m2/MD 0.1525 m2/Hr
d) Concrete Walls sq.m. 1.36 m2/MD 0.1700 m2/Hr
e) Concrete Structural Slab
Cast-In-Place Culvert and
Manholes sq.m. 1.29 m2/MD 1.1825 m2/Hr

In general, two men can erect 20BD.FT./HR or remove forms at the rate of 44BD.FT./HR

404 E. REINFORCEMENT
a) Fabrication(cut & bend) kg. 68.00 kg/MD 8.5000 kg/Hr
b) Placing
b.1) Footing and Foundations
Structural kg. 95.74 kg/MD 11.9575 kg/Hr
b.2) Slab on Grade kg. 95.74 kg/MD 11.9575 kg/Hr
b.3) Columns, Beams and R.C. Wall kg. 85.00 kg/MD 10.6250 kg/Hr
b.4) Cast-In-Place Culert and Manholes kg. 61.00 kg/MD 7.6250 kg/Hr

909 F. CONCRETING
a) Place, Finish & Cure Concrete
a.1) Footing anfd Foundation cu.m. 3.32 m3/MD 0.4150 m2/Hr
a.2) Slab on Grade cu.m. 1.89 m3/MD 0.2363 M2/Hr
a.3) Columns cu.m. 1.02 m3/MD 0.1275 m2/MD
a.4) R.C. Walls cu.m. 0.94 m3/MD 0.1175 m2/Hr
a.5) Structural Slabs cu.m. 0.88 m3/MD 0.1100 M3/Hr
a.6) Cast-InPlace Culverts cu.m. 1.32 m3/MD 0.1650 m3/Hr
a.7) Cast-In-Place Manholes cu.m. 2.65 m3/MD 0.3313 m3/Hr
b)Placing Concrete
b.1) Salb on Fill cu.m. 1.36 m3/MD 0.1700 m3/Hr
b.2) Slip Form cu.m. 0.27 m3/MD 0.0338 m3/Hr
b.3) Chute form Truck cu.m. 0.95 m3/MD 0.1188 m3/Hr
b.4) Crane and Bucket cu.m. 0.48 m3/MD 0.0600 m3/Hr
b.5) Wheeling cu.m. 0.20 m3/MD 0.0250 m3/Hr
b.6) Concrete pour on elevated cu.m. 0.34 m3/MD 0.04250 m3/Hr
and shored slab chute and Fortalift
b.7) Floor Fin, Unhardened cu.m. 6.80 m3/MD 0.8500 m3/Hr
b.8) Concrete Fin, Hardened cu.m. 4.76 m3/MD 0.5950 m3/Hr

c) Concrete Mixing
c.1) Manual Mixing sq.m. 0.41 m3/MD 0.0513 m3/Hr
c2) One-Bagger Mixing sq.m. 3.81 m3/MD 0.4763 m3/Hr

V. MASONRY WORKS
506(1) - Masonry Works
a) CHB Laying
a.1)chb 4" sq.m 5.10 m2/MD 0.6375 m2/Hr
a.2) CHB 6" sq.m 4.25 m2/MD 0.5313 m2/Hr
a.3) CHB 8" sq.m 3.40 m2/MD 0.4250 m2/Hr
b) Brick Works (1.0 x 2.0m) sq.m 13.60 m2/MD 1.7000 m2/Hr
c) Red Bricks (1/4" x 2" x 8") sq.m 0.1700 m2/Hr
d) Laying of Adobe sq.m 5.98 m2/MD 0.7475 m2/Hr

VI. CARPENTRY WORKS


1003 - Carpentry and Joinery
a) Wall
a.1) Plywood Partitons pc. 6.80 PC/MD 0.8500 PC/Hr
a.2) T& G Siding bf. 48.55 BF/MD 6.0688 BF/Hr
a.3) Siding Frame Works bf. 25.16 BF/MD 3.1450 BF/Hr
a.4) wood Wall and Partitions cu.m. 13.60 m3/MD 1.7000 m3/MD
a.5) Wood Walls Partitions cu.m. 13.60 m3/MD 1.7000 m3/MD
a.6) Panel Wall sq.m. 0.95 m2/MD 0.1188 m2/MD
a.7) Double Wall Partiotion cu.m. 5.98 m2/MD 1.7000 m3/MD

b) Floor
b.1) T & G Flooring bf 48.55 BF/MD 6.0688 bf/Hr
b.2) Floor Framing bf 14.01 BF/MD 1.7513 bf/Hr

c.) Wooden Post Erection bf 1.98 BF/MD 1.9975 BF/Hr

d.) Ceiling
d.1) Ceiling Frame(Joist, Nailers, sq.m. 5.10 m2/MD 0.6375 BF/Hr
and handrails)
d.2) Plywood Installation shts. 6.80 shts/MD 0.8500 shts/Hr
d.3) Fiber Cement Board Installation shts. 6.80 shts/MD 0.8500 shts/Hr
d.4) Accoustic Ceiling sq.m. 5.64 m2/MD 0.7050 m2/Hr
d.5) Ceiling Eaves Installation sq.m. 5.64 m2/MD 0.7050 m2/Hr
d.6) Fascia Board Installation sq.m. 16.32 m2/MD 2.0400 m2/Hr

e.) Cabinet
e.1) Cabinet Framing bf. 52.29 BF/MD 6.5363 BF/Hr
e.2) Cabinet Boarding 37.61 BF/MD 4.7263 BF/Hr
e.3) Built-In Wood Cabinet 37.81 BF/MD 4.7263 BF/Hr

f) Base Board Insatallation lm 34.00 LM.MD 4.2500 LM/Hr


g) Wooden Stairs plight 17.00 plight/MD 2.1250 plight/Hr
h) Wooden Molding/Cornice lm 61.81 Lm/MD 7.7262 LM/Hr

VII. FABRICATED MATERIALS AND HARDWARES


1004 - Hardwares and Accessories
a) Hinges Installation
1. Loose Pin pc. 15.00 pc/Md 1.8750 pcs/Hr
2. Piano Hinges lim.m. 25.00 lm/MD 3.1250 lm/Hr
3. Double Swing pcs. 10.00 pcs/MD 1.2500 pcs/Hr
4. Barrel Boris pcs. 15.00 pcs/MD 1.8750 pcs/Hr

1005 - Steel Windows


a) Casement Type pc. 1.00 pc/MD 0.1250 pc/Hr
b) Awning Type pc. 1.00 pc/MD 0.1250 pc/Hr
c) French Type pc. 1.00 pc/MD 0.1250 pc/Hr
d) Fixed Steel pc. 1.00 pc/MD 0.1250 pc/Hr
e) Louver Window
1. Fixed Metal Louver pc. 1.00 pc/MD 0.1250 pc/Hr
2. Fixed G.I. Sheets pc. 1.00 pc/MD 0.1250 pc/Hr

1006 - Steel Door and Frames


a) Hollow Metal Door
1.Fabrication pc 0.07 pc/MD 0.0088 pc/Hr
2. Installation pc 1.00 pc/MD 0.0125 pc/Hr
b) Steel Bars pc 1.00 pc/MD 0.0125 pc/Hr

1007 - Aluminum Glass Doors


a) Aluminum Frame pc. 0.68 pc/MD 0.0850 pc/Hr
b) Sliding Glass Door pc. 0.54 pc/MD 0.0675 pc/Hr

1008 - Aluminum Glass Window pc.


a) Aluminum Frame pc. 1.00 pc/MD 0.1250 pc/Hr

1009 - Jalousie Window


a) Aluminum Jalousie sq.m. 2.70 m2/MD 0.3375 m2/Hr
b) Glass Jalousie sq.m. 2.70 m2/MD 0.3375 m2/Hr
c) Wood Jalousie sq.m. 2.70 m2/MD 0.3375 m2/Hr

SPL - Louver Windows


a) Fixed Asbetos pc. 1.00 pc/MD 0.1250 pc/Hr
b) Fixed Glass pc. 1.00 pc/MD 0.1250 pc/Hr

1010 - Wooden Doors and Windows


a) Doors
1. Hollow Core
Fabrication m2 1.03 m2/MD 0.1288 m2/Hr
Installation m3 1.89 m2/MD 0.2363 m2/Hr
2. Panel Door m4 1.89 m2/MD 0.2363 m2/Hr

b) Windows
1. Casement Type m2 1.92 m2/MD 0.2400 m2/Hr
2. Jalousie Type m3 1.92 m2/MD 0.2400 m2/Hr
3. Fixed Wooden m4 1.92 m2/MD 0.2400 m2/Hr

c) Frames and Locksets


1. Wood Door Jambs unit 2.50 uni/MD 0.3125 uni/Hr
2. Wood Window Jambs unit 1.60 uni/MD 0.2000 uni/Hr
3. Steel Door Jambs unit 1.000 uni/MD 0.1250 uni/Hr
4. Steel Window Jambs unit 1.000 uni/MD 0.1250 uni/Hr
5. Door lockset set 4.25 set/MD 0.5313 set/Hr

1011 - Rolling Up Doors pc. 0.27 pc/MD 0.0338 pc/Hr

SPL - Grills and Rollings


a) Steel Gates sq.m. 1.00 m2/MD 0.1250 M2/Hr
b) Window Grills pc. 1.00 pc/MD 0.1250 pc/Hr
c) Steel Railings lin.m 10.00 lm/MD 1.0625 lm/Hr
d) Stainless Railings lin.m 10.00 lm/MD 4.0463 lm/Hr
e) Cyclone Wire sq.m. 2.10 m2/MD 0.2625 m2/Hr
d) Steel Fire Escape set 0.25 set/MD 0.0313 set/Hr

VIII. ROOF FRAMING WORKS


402 - Timber Structure
a) Wooden Truss
1. Fabrication Bd.Ft 19.38 bf/Md 2.4225 BF/Hr
2. Erections set 0.10 set/MD 0.0125 set/Hr
3. Installation Bd.Ft 8.50 bf/Md 1.0625 BF/Hr
b)Wood grift Installation Bd.Ft 32.27 bf/Md 4.0463 BF/Hr
c) Wood Plate Installation Bd.Ft 21.90 bf/Md 2.7375 BF/Hr
d) Wood Purlines Intsllation Bd.Ft 25.16 bf/Md 3.1450 BF/Hr
e) Wood Media Aqua Frame Bd.Ft 50.0 bf/Md 6.2500 BF/Hr

403 - Metal Structures


a) Steel Truss
1. Fabrication kg 136.00 kg/MD 17.0000 kg/hr
Heavy Sections
a) Erections set 0.10 set/MD 0.0125 set/hr
b. Installation set 0.10 set/MD 0.0125 set/hr
Light Sections
a) Erections set 0.40 SET/Md 0.0500 set/hr
b. Installation set 0.40 SET/Md 0.0500 set/hr
2. Painting lin.m. 34.00 Lm/MD 4.2500 lm/hr
a) Steel Purlins Installations lin.m. 36.00 lm/MD 4.5000 lm/hr
b) Steel Media Aqua Frame kgs 68.00 kg/MD 8.5000 kg/hr

IX. ROOFING WORKS


1013 - Corrugated Metal Roofing
1014 - Pre-Painted Metal Sheets
a) Installation o GI sheets sq.m. 8.30 m2/MD 1.0375 m2/Hr
b) Installation of Ridge Rolls lin.m. 42.50 lm/MD 5.3125 lm/Hr
c) Installation of Valley Roll lin.m. 42.50 lm/MD 5.3125 lm/Hr
d Installation of Flashing lin.m. 42.50 lm/MD 5.3125 lm/Hr
e) Installation of Gutters lin.m. 42.50 lm/MD 5.3125 lm/Hr

1017 - Roof Drains ans Stainers


a) Installation of Roof Strainers pc 8.00 pc/MD 1.0000 PC/Hr
b) Installation of Downspout lin.m. 51.00 lm/MD 6.3750 lm/Hr
c) Installation of Insulation sq.m 14.00 m2/MD 1.7500 m2/Hr

X. FINISHES
1018 - Ceramic Tiles
a) Ceramic Glazed Tiles sq.m. 2.24 m2/MD 0.28000 m2/Hr
b) Ceramic unglazed Tiles sq.m. 1.56 m2/MD 0.1950 m2/Hr

1019 - Wood Tiles


a) Narra Parquet Finish sq.m. 9.30 m2/MD 1.1625 m2/Hr
b) Tanguile Parquet Finish sq.m. 9.30 m2/MD 1.1625 m2/Hr

1020 - Vinyl Floor Tiles sq.m. 3.81 m2/MD 0.4763 m2/Hr

1021 - Plain Cement Finish


a) Plain Cement Floor Tiles sq.m. 9.52 m2/MD 1.1900 m2/Hr
b) Plain Cement Floor Finish with color sq.m. 4.83 m2/MD 0.6038 m2/Hr

1022 - Stucco Finish


a) Plain Cement Stucco Finish sq.m. 4.08 m2/MD 0.5100 m2/Hr
b) Plain Cement Stucco Finish With Color sq.m. 3.5 m2/MD 0.4375 m2/Hr

1023 - Granolithic Marble Works sq.m. 2.31 m2/MD 0.2888 m2/Hr


1024 - Pea Gravel Wah Out Finish sq.m. 4.76 m2/MD 0.5950 m2/Hr
1025 - Buh Hammered Finish sq.m. 2.5 m2/MD 0.3125 m2/Hr
1026 - Peeble Wash OuT Finish sq.m. 4.76 m2/MD 0.5950 m2/Hr
1027 - Cement Plaster Finish sq.m. 9.50 m2/MD 1.1875 m2/Hr
1028 Synthetic Adobe Finish sq.m. 2.50 m2/MD 0.3125 m2/Hr
1029 - Granite WAH Out Finish sq.m. 4.76 m2/MD 0.5950 m2/Hr
SPL a) Marble Tile Finish sq.m. 3.40 m2/MD 0.4250 m2/Hr
b) Granite Tile Finish sq.m. 3.40 m2/MD 0.4250 m2/Hr
c) 1/2" X 2" X 8" Red Block sq.m. 1.36 m2/MD 0.1700 m2/Hr
d) Manolithic Terrazo Finish sq.m. 6.04 m2/MD 0.7550 m2/Hr
e) Synthetic Marble Tiles sq.m. 1.49 m2/MD 0.1863 m2/Hr
f) Wall Papers sq.m. 0.88 m2/MD 0.1100 m2/Hr
g) Plastered Ceiling sq.m. 2.24 m2/MD 0.2800 m2/Hr
h) Mozaic Floor Tiles sq.m. 0.82 m2/MD 0.1025 m2/Hr

XI. PAINTING/VARNISHING WORKS


1032 - Painting, Varnishing and other related Works
A. Painting
a) Plain Cement Paint Exterior sq.m. 16.73 m2/MD 2.0913 m2/Hr
b) Plain Cement Paint Metal sq.m. 16.73 m2/MD 2.0913 m2/Hr
c) Exposed Aggregates Tool Paint Finish sq.m. 16.73 m2/MD 2.0913 m2/Hr
d) Ferrous Metal Finish sq.m. 13.94 m2/MD 1.7425 m2/Hr
e) Galvanized Metal sq.m. 13.94 m2/MD 1.7425 m2/Hr
f) Steel Ducco Finish sq.m. 6.97 m2/MD 0.8713 m2/Hr
g) Wood Paint sq.m. 23.05 m2/MD 2.8813 m2/Hr
h) Wood Ducco Finish sq.m. 6.97 m2/MD 0.8713 m2/Hr
i) Textured Paint sq.m. 6.97 m2/MD 0.8713 m2/Hr
j) Glass Paint sq.m. 10.87 m2/MD 1.3713 m2/Hr
B. Varnishing
a) Plain Varnish Paint sq.m. 15.78 m2/MD 1.9725 m2/Hr
b) Ducco Varnish Paint sq.m. 7.89 m2/MD 0.9863 m2/Hr

XII. WATERPROOFING WORKS


1016 - Waterproofing
a) Cement - Base Integral sq.m. 5.00 m2/MD 0.6250 m2/Hr
b) Membrane Waterproofing 12.81 m2/MD 1.6013 m2/Hr
c) Liquid Waterproofing 15.39 m2/MD 1.9238 m2/Hr
d) Hydraulic Waterproofing 12.31 m2/MD 1.5388 m2/Hr
e) Water Installation 10.20 m2/MD 1.2750 m2/Hr

XIII. SANITARY WORKS


1001 - Storm Drainage & Sewage System
a) Laying of RCCP
a.1) 24" dia ln.m. 1.70 lm/MD 0.2125 lm/Hr
a.2) 36" dia ln.m. 1.02 lm/MD 0.1275 lm/Hr
a.3) 48" dia ln.m. 0.61 lm/MD 0.0765 lm/Hr
a.4) 6" dia ln.m. 5.10 lm/MD 0.6375 lm/Hr

b) Laying of Asbestos
b.1) 1/2" dia ln.m. 0.41 lm/MD 0.0531 lm/Hr
b.2) 3/4" dia ln.m. 0.41 lm/MD 0.0513 lm/Hr
b.3) 1" - 1 1/4" dia ln.m. 0.47 lm/MD 0.0588 lm/Hr
b.4) 1 1/2 - 2" dia ln.m. 0.52 lm/MD 0.0650 lm/Hr
b.5) 2 1/2" dia ln.m. 0.62 lm/MD 0.0775 lm/Hr
b.6) 3" dia ln.m. 0.68 lm/MD 0.0850 lm/Hr
b.7)4" dia ln.m. 0.83 lm/MD 0.1038 lm/Hr

c) Cast Iron Pipe


c.1) 2" dia ln.m. 1.39 lm/MD 0.1738 lm/Hr
c.2) 4" dia ln.m. 2.07 lm/MD 0.2588 lm/Hr
c.3)6" dia ln.m. 3.11 lm/MD 0.3888 lm/Hr
c.4) 8" dia ln.m. 4.15 lm/MD 0.5188 lm/Hr
c.5) 10" dia ln.m. 6.22 lm/MD 0.7775 lm/Hr
c.6) 12" dia ln.m. 6.57 lm/MD 0.8213 lm/Hr
c.7) 14" dia ln.m. 7.63 lm/MD 0.9538 lm/Hr
c.8) 16" dia ln.m. 8.67 lm/MD 1.0838 lm/Hr
c.9) 18" dia ln.m. 9.72 lm/MD 1.2150 lm/Hr
c.10) 20" dia ln.m. 10.37 lm/MD 1.2963 lm/Hr
c.11) 22" dia ln.m. 11.51 lm/MD 1.4388 lm/Hr

1012 - Plumbing Works


a) G.I Pipes
a.1) 1/2" dia lin.m 16.70 lm/MD 2.0875 lm/Hr
a.2) 3/4" dia lin.m 15.18 lm/MD 1.8975 lm/Hr
a.3) 1" dia lin.m 13.80 lm/MD 1.7250 lm/Hr
a.4) 1 1/4" dia lin.m 12.54 lm/MD 1.5675 lm/Hr
a.5) 1 1/2" dia lin.m 11.41 lm/MD 1.4263 lm/Hr
a.6) 1 3/4" dia lin.m 10.35 lm/MD 1.2938 lm/Hr
a.7) 2" dia lin.m 8.65 lm/MD 1.0813 lm/Hr
a.8) 3" dia lin.m 7.20 lm/MD 0.9000 lm/Hr
a.9) 4" dia lin.m 6.00 lm/MD 0.7500 lm/Hr

b) PVC Pipes
b.1) 1/2" dia lin.m 0.42 lm/MD 0.0525 lm/Hr
B2.) 1- 1/2" dia lin.m 1.56 lm/MD 0.1950 lm/Hr
b.3) 1 1/2" - 2" dia lin.m 1.70 lm/MD 0.2125 lm/Hr
b.4) 2 1/2" dia lin.m 2.04 lm/MD 0.2550 lm/Hr
b.5) 3" dia lin.m 0.68 lm/MD 0.0850 lm/Hr
b.6) 4" dia lin.m 0.83 lm/MD 0.1038 lm/Hr
b.7) 5" dia lin.m 1.04 lm/MD 0.1300 lm/Hr
b.8) 6" dia lin.m 1.56 lm/MD 0.1950 lm/Hr

XIV. ELECTRICAL WORKS


1100 - Conduits, Boxes and fittings
a) Conduits lin.m 36.00 lm/MD 4.5000 Lm/Hr
b) Boxes and Fittings pcs 28.00 pc/MD 3.5000 pc/Hr

1101 - Wire and Wiring Devices


a) Wiring lin.m. 15.00 lm/MD 18.7500 lm/Hr
b) Devices set 10.00 set/MD 1.2500 pcs/Hr
1102 - Power Load Center, Switch Gear and Panel Boards
a) Lighting sets 8.00 set/MD 1.0000 set/Hr
b) Panel Boards circuit 8.00 set/MD 1.0000 set/Hr

SOURCES AND REFERENCES


1. DPWH Standard Specifications, vol. II & III, 1995 edition
2. DPWH - BOC dta on various building structures previously implemented
3. Construction Manpower Development Foundation (CMDF)
4. Construction Estimate Handbook by Velasco

Вам также может понравиться