Академический Документы
Профессиональный Документы
Культура Документы
DOCUMENT INFORMATION
ORIGINATOR: ACTIVITY: TYPE OF DOCUMENT:
CQA Manager Quality Assurance & Control Project Quality Plan
COPYRIGHT
The copyright in this document and the information contained therein is the exclusive property of TORO YA AFRICA AND SOCRASYNC JV. Acceptance of this document constitutes
an agreement that it will be treated as confidential and neither the document nor the information contained therein will be used for any purpose other than that for which it was originally
intended. This document is not to be communicated, disclosed, copied or published to any third person except as previously authorised by the Project Quality Manager.
DATE: 09/07/2019
TORO YA AFRICA AND SOCRASYNC JV
REV: 2
PROJECT QUALITY PLAN
PAGE: 2 of 39
P1127672-LS-C002-QMP-MMA-002
TABLE OF CONTENTS
1. INTRODUCTION......................................................................................................................................................6
1.1 SAFETY, HEALTH, ENVIRONMENTAL AND QUALITY (SHEQ) POLICY STATEMENT......................................7
1.2 PROJECT LIMITS OF AUTHORITY, QUALITY STAFF RESPONSIBILITIES AND KEY PERSONNEL ORGANOGRAM
7
1.3 PROJECT DESCRIPTION........................................................................................................................ 8
1.4 PROJECT RISKS................................................................................................................................... 8
1.5 PROJECT OBJECTIVES AND TARGETS.................................................................................................... 8
2. COMMUNICATION AND DOCUMENT DISTRIBUTION AND CONTROL.................................................9
2.1 PROJECT COMMUNICATION................................................................................................................... 9
3. TORO YA AFRICA AND SOCRASYNC JV SUPPORT FUNCTIONS...........................................................11
4. PROJECT CONTROL AND DATA PACKS.......................................................................................................11
4.1 DOCUMENTATION CONTROL................................................................................................................ 11
4.2 PROJECT QUALITY MANAGEMENT AND DELIVERY.................................................................................14
4.3 DESIGN COORDINATION (REFER TO GST 001 DESIGN CONTROL)........................................................15
4.4 PROJECT QUALITY ASSURANCE AND ISO 9001...................................................................................15
4.4.1 ROLES & RESPONSIBILITIES........................................................................................................ 15
5. SITE QUALITY INSPECTION AND CONTROL..............................................................................................18
5.1 PROJECT QUALITY CONTROL PLAN..................................................................................................... 18
5.2 PROJECT METHOD STATEMENTS......................................................................................................... 18
5.3 QCP’S............................................................................................................................................... 19
5.4 FIC’S AND FIR’S................................................................................................................................ 19
5.5 AUDITING........................................................................................................................................... 19
5.6 SD PROCEDURES.............................................................................................................................. 19
5.7 SUBCONTRACTOR COORDINATION....................................................................................................... 20
5.8 INSPECTION AND TESTING................................................................................................................... 20
5.9 INSPECTION, MEASURING AND TESTING EQUIPMENT............................................................................23
6. APPROVED INSPECTION AUTHORITY..........................................................................................................24
6.1 STORES / PROTECTION OF THE WORKS (HANDLING, PACKAGING, STORAGE AND DELIVERY).................24
6.2 SPECIAL PROCESSES AND PROCEDURES............................................................................................. 24
6.3 MATERIAL SPECIFICATIONS, TRACEABILITY AND CERTIFICATION............................................................24
6.4 NON-CONFORMANCE, FEQ’S, CONCESSIONS, EARLY WARNINGS AND CE’S..........................................25
6.5 PROJECT SPECIFIC SUPPORT FUNCTIONS........................................................................................... 25
7. PROCESS REVIEW AND IMPROVEMENT......................................................................................................25
7.1 MONITORING AND MEASURING............................................................................................................ 25
7.2 PRODUCT NON-CONFORMANCES......................................................................................................... 26
7.3 CORRECTIVE ACTION REQUEST AND REPORTING.................................................................................27
7.4 SERVICE AND MAINTENANCE PLAN...................................................................................................... 27
8. QA DATA DOSSIER...............................................................................................................................................27
COPYRIGHT
The copyright in this document and the information contained therein is the exclusive property of TORO YA AFRICA AND SOCRASYNC JV. Acceptance of this document constitutes
an agreement that it will be treated as confidential and neither the document nor the information contained therein will be used for any purpose other than that for which it was
originally intended. This document is not to be communicated, disclosed, copied or published to any third person except as previously authorised by the Project Quality Manager.
DATE: 09/07/2019
TORO YA AFRICA AND SOCRASYNC JV
REV: 2
PROJECT QUALITY PLAN
PAGE: 3 of 39
P1127672-LS-C002-QMP-MMA-002
ANNEXURE A: ORGANOGRAM………………………………………………………………….…….29
ANNEXURE B: AUDIT DATE SCHEDULE………………………………………………………….….
….31
ANNEXURE C: QA DATA DOSSIER…………………………………………………………….……...34
ANNEXURE D: METHOD STATEMENT REGISTER……………………….……………………..….….37
ANNEXURE E: QCP REGISTER……………………………………………………………………….39
COPYRIGHT
The copyright in this document and the information contained therein is the exclusive property of TORO YA AFRICA AND SOCRASYNC JV. Acceptance of this document constitutes
an agreement that it will be treated as confidential and neither the document nor the information contained therein will be used for any purpose other than that for which it was
originally intended. This document is not to be communicated, disclosed, copied or published to any third person except as previously authorised by the Project Quality Manager.
DATE: 09/07/2019
TORO YA AFRICA AND SOCRASYNC JV
REV: 2
PROJECT QUALITY PLAN
PAGE: 4 of 39
P1127672-LS-C002-QMP-MMA-002
LIST OF ACRONYMS
ORIGINATOR
HSO Health & Safety Officer TYAS Toro Ya Africa and Socrasync JV
ACTIVITY OR TRADE
COPYRIGHT
The copyright in this document and the information contained therein is the exclusive property of TORO YA AFRICA AND SOCRASYNC JV. Acceptance of this document constitutes
an agreement that it will be treated as confidential and neither the document nor the information contained therein will be used for any purpose other than that for which it was
originally intended. This document is not to be communicated, disclosed, copied or published to any third person except as previously authorised by the Project Quality Manager.
DATE: 09/07/2019
TORO YA AFRICA AND SOCRASYNC JV
REV: 2
PROJECT QUALITY PLAN
PAGE: 5 of 39
P1127672-LS-C002-QMP-MMA-002
TYPE OF DOCUMENT
CAR Corrective Action Request IMTE Inspection Measuring and Test Equipment
QAL-STD-001 Control
COPYRIGHT
The copyright in this document and the information contained therein is the exclusive property of TORO YA AFRICA AND SOCRASYNC JV. Acceptance of this document constitutes
an agreement that it will be treated as confidential and neither the document nor the information contained therein will be used for any purpose other than that for which it was
originally intended. This document is not to be communicated, disclosed, copied or published to any third person except as previously authorised by the Project Quality Manager.
DATE: 09/07/2019
TORO YA AFRICA AND SOCRASYNC JV
REV: 2
PROJECT QUALITY PLAN
PAGE: 6 of 39
P1127672-LS-C002-QMP-MMA-002
1. INTRODUCTION
COPYRIGHT
The copyright in this document and the information contained therein is the exclusive property of TORO YA AFRICA AND SOCRASYNC JV. Acceptance of this document constitutes
an agreement that it will be treated as confidential and neither the document nor the information contained therein will be used for any purpose other than that for which it was
originally intended. This document is not to be communicated, disclosed, copied or published to any third person except as previously authorised by the Project Quality Manager.
DATE: 09/07/2019
TORO YA AFRICA AND SOCRASYNC JV
REV: 2
PROJECT QUALITY PLAN
PAGE: 7 of 39
P1127672-LS-C002-QMP-MMA-002
The success of the policy and its application will be reviewed at the 3 monthly management
meeting and these meetings will co-inside with the External audit dates and are indicated on
the Audit Schedule attached as Annexure B. This is a live control document and will be
reviewed, adjusted and distributed as and when needed.
TYAS’s activities for the project are diagrammatically represented on the PQP Integrated
System Diagram (refer to Figure 8.4 Page 6).
1.1 Safety, Health, Environmental and Quality (SHEQ) Policy Statement
Our Quality Policy specifies the Degree of Excellence as “all activities of the organization will
be carried out in a systematic manner in accordance with defined and documented Policies
and Procedures, will meet applicable legislative requirements, will be visible and auditable,
and will ensure that the needs of employees and Stakeholders are met.
TYAS JV is committed to providing construction and consultancy services that satisfy our
customers’ needs and expectations in safety, quality & reliability while complying with all
relevant requirements, regulations, legislation and standards. We are committed to continually
improving how we deliver our services to our customer through the understanding of their
requirements and application of consistent methodology and disciplined processes.
Our top management is committed to continually improving the effectiveness of our quality
management system and the customer experience through training & development of
employees and sub-contractors, continuous collection of customer feedback, internal and
external auditing of our standards and procedures, setting and reviewing our Quality
Objectives each year and ensuring the suitability of the Quality Management System so we
can deliver customer satisfaction on a suitable basis.
This can only be achieved through the support of our employees & sub-contractors and their
compliance at all times with our processes and procedures.
1.2 Project Limits of Authority, Quality Staff responsibilities and Key Personnel
Organogram
On the Project, certain project specific Limits of Authority have been defined regarding Project
Procurement and Project Administration for the relevant activities. (Limits of authority TYAS
010 document & specimen signatures TYAS 020). All construction personnel, including Sub-
contractor’s managers will be trained on the quality control system and procedures and will be
responsible to conduct all visual pre-inspections, prior to arranging inspections by senior
construction or quality personnel. Since the Assistant Construction Manager, General
Foreman and the Foremen will have to conduct visual inspections and Equipment testing,
relevant training of staff will be conducted and experience on Equipment must be confirmed in
relevant documentation. The management staff for quality on site will comprise of the quality
Manager and the quality control clerk. The key personnel organogram is attached as
Annexure A. The Head Office Support Organogram has been compiled and approved.
COPYRIGHT
The copyright in this document and the information contained therein is the exclusive property of TORO YA AFRICA AND SOCRASYNC JV. Acceptance of this document constitutes
an agreement that it will be treated as confidential and neither the document nor the information contained therein will be used for any purpose other than that for which it was
originally intended. This document is not to be communicated, disclosed, copied or published to any third person except as previously authorised by the Project Quality Manager.
DATE: 09/07/2019
TORO YA AFRICA AND SOCRASYNC JV
REV: 2
PROJECT QUALITY PLAN
PAGE: 8 of 39
P1127672-LS-C002-QMP-MMA-002
Corrective Action Requests will be issued in writing to the Client and managed by the
Contracts Manager. This includes compensation events and the finalization and approval of
Provisional items, as per BOQ.
The Site Management construction team QS will perform evaluations on the Variations and
Corrective Actions, to determine the time and cost implications.
Costing is done on a daily and a weekly basis on site and discussed in the site meetings –
once-a-week. The Assistant Project Manager is responsible for costing and Payment controls.
A cost report will be presented at the weekly meetings. Any Compensation events will be
added and reported on separately.
TYAS Reference Documentation: Operational and Project Risk Management
Site Conditions;
Subcontractors;
Own Performance;
Human Resources
These risks are reviewed at the Risk Review at weekly Meetings, where the Risk Register is
updated by the Client’s Risk Manager. The Project Risk Register is further reviewed at the
Point Meetings and forms part of the agenda.
1.5 Project Objectives and Targets
The Toro Ya Africa and Socrasync JV Key Objective will be measured as follows:
Reference Table in item 5.5
JV and Site SHEQ Compliance
COPYRIGHT
The copyright in this document and the information contained therein is the exclusive property of TORO YA AFRICA AND SOCRASYNC JV. Acceptance of this document constitutes
an agreement that it will be treated as confidential and neither the document nor the information contained therein will be used for any purpose other than that for which it was
originally intended. This document is not to be communicated, disclosed, copied or published to any third person except as previously authorised by the Project Quality Manager.
DATE: 09/07/2019
TORO YA AFRICA AND SOCRASYNC JV
REV: 2
PROJECT QUALITY PLAN
PAGE: 9 of 39
P1127672-LS-C002-QMP-MMA-002
The SHEQ Site Management, along with JV Project management and External Auditors, will
evaluate the effectiveness of their SHEQ System on a quarterly basis by completing a SHEQ
Report. This report is submitted and evaluated by the Client. Contents of the report will
conform to the ISO 9001 standards.
At 90% completion of the project, the Contracts Manager will forward a questionnaire Form
(SFD) to the client.
Client Questionnaire feedback on TYAS performance is reported to TYAS Management in the
Internal Audit Report and at the Management Review.
Section 13
The Contracts Manager is responsible for the Site organogram. Latest Site Organogram will
be displayed at the Site office of the Construction Manager.
2.1 Project Communication
All formal documented project communication will occur through Transmittal emails (Electronic
Copies), distribution of project documentation (Hard Copies) and records storage (Data
Packs).
The TYAS Quality system provides for Field Engineering Query (FEQ), Compensation Events
(referred to as CE) and Early Warning, whenever there is a fundamental deviation from
reference designs or a cost implication.
Internal Communication
COPYRIGHT
The copyright in this document and the information contained therein is the exclusive property of TORO YA AFRICA AND SOCRASYNC JV. Acceptance of this document constitutes
an agreement that it will be treated as confidential and neither the document nor the information contained therein will be used for any purpose other than that for which it was
originally intended. This document is not to be communicated, disclosed, copied or published to any third person except as previously authorised by the Project Quality Manager.
DATE: 09/07/2019
TORO YA AFRICA AND SOCRASYNC JV
REV: 2
PROJECT QUALITY PLAN
PAGE: 10 of 39
P1127672-LS-C002-QMP-MMA-002
Internal communication will be addressed to all affected personnel at various levels in line with
the organisational charts (one level up / one level down / lateral).
Records of all relevant internal communication (e.g. minutes of meetings, internal emails) will
be retained by the Document Controller.
External Communication
External parties can contact TYAS Head office telephonically or via email.
Any complaints, compliments or feedback made by an external party using any one of above
methods must be forwarded to the Contracts Director, who will ensure it is recorded and
controlled by completing an SFD and distributing to Interested and Affected Person/s Register
(IAP Register).
Response to the query or complaint must be given to the external party as soon as is
reasonably practicable.
Any communication to external parties and customers that could impact on the image of TYAS
or the Employer (client) must be approved by the Communications Manager (TYAS Head
Office).
Client Communication
Client details must be kept on record; all communication should be through written
communication, including a Transmittal Control Document and must be sent to TGC
Document Control. Relevant persons on the distribution list may be copied with the transmittal.
PROJECT MEETINGS
External Project Meetings
Client Monthly and Fortnightly Meetings (chaired by the Project Manager) – Scope of work
Sec 6.1
Internal Project Meetings
After the transfer meeting, a SHEQ kick-off meeting will determine the process control
requirements. This meeting is attended by Project Management and SHEQ Personnel (SFD
controlled) and will take place once Site is Established and prior to Construction work
commencement.
Transfer Objective and Point Meeting (chaired by Project Manager)
The Transfer, Objective and Point Meetings for the Project will be scheduled as follows:
Transfer Meeting Completed
COPYRIGHT
The copyright in this document and the information contained therein is the exclusive property of TORO YA AFRICA AND SOCRASYNC JV. Acceptance of this document constitutes
an agreement that it will be treated as confidential and neither the document nor the information contained therein will be used for any purpose other than that for which it was
originally intended. This document is not to be communicated, disclosed, copied or published to any third person except as previously authorised by the Project Quality Manager.
DATE: 09/07/2019
TORO YA AFRICA AND SOCRASYNC JV
REV: 2
PROJECT QUALITY PLAN
PAGE: 11 of 39
P1127672-LS-C002-QMP-MMA-002
A formal work planning meeting shall take place on a weekly basis from the commencement
date until the issue of the Taking over certificate. The meeting is chaired by the Assistant
Construction Manager and attended by the subcontractor staff.
Management Review
TYAS Reference Documentation: OCP 002 Management Review and Improvement. This
meeting will take place on quarterly basis.
SHEQ Management,
Together with Project Management, SHEQ Management will evaluate the effectiveness of the
SHEQ System on a quarterly basis. On completion a copy will be forwarded to the SHEQ
Department (Head Office). This information will be analysed and presented to management at
the JV Management Review as above.
3. TORO YA AFRICA AND SOCRASYNC JV SUPPORT FUNCTIONS
TYAS support functions at Head Office will assist the Project in meeting the Employer’s
requirements for the Project. Assistance is provided by the Financial, Commercial (Legal),
HR, IT, SHEQ, Methods / Estimating, and Plant on a direct support and ad hoc basis.
The functions below are only indicative of the departments’ role toward the Project.
4. PROJECT CONTROL AND DATA PACKS
COPYRIGHT
The copyright in this document and the information contained therein is the exclusive property of TORO YA AFRICA AND SOCRASYNC JV. Acceptance of this document constitutes
an agreement that it will be treated as confidential and neither the document nor the information contained therein will be used for any purpose other than that for which it was
originally intended. This document is not to be communicated, disclosed, copied or published to any third person except as previously authorised by the Project Quality Manager.
DATE: 09/07/2019
TORO YA AFRICA AND SOCRASYNC JV
REV: 2
PROJECT QUALITY PLAN
PAGE: 12 of 39
P1127672-LS-C002-QMP-MMA-002
To ensure protection of manual / hard copy generated records, critical records will be
duplicated (e.g. client records) and stored on a remote server, password protected, and
password issued to a second person under the control of the QA Clerk / Document Controller.
The PRP 001 (Project Record Procedure) identifies records; responsibilities; retention and
client records.
A comprehensive register of the following documents but not limited to will be kept on site:
Compensation Events (CE’s);
Document Register;
FEQ Register;
QCP Register;
FIR Register;
NCRs;
CAR/PAR Register
Client Complaints;
Document Control
All documents will be controlled by the JV Doc Control Officer. Document controller will only
manage documents and distribute to those who need to use the information. Documents must
be transmitted to Doc Control, electronically. Doc Control will then print, copy and distribute
the relevant document to relevant recipients. The Electronic and Hard copies are kept as part
of the Data Packs.
COPYRIGHT
The copyright in this document and the information contained therein is the exclusive property of TORO YA AFRICA AND SOCRASYNC JV. Acceptance of this document constitutes
an agreement that it will be treated as confidential and neither the document nor the information contained therein will be used for any purpose other than that for which it was
originally intended. This document is not to be communicated, disclosed, copied or published to any third person except as previously authorised by the Project Quality Manager.
DATE: 09/07/2019
TORO YA AFRICA AND SOCRASYNC JV
REV: 2
PROJECT QUALITY PLAN
PAGE: 13 of 39
P1127672-LS-C002-QMP-MMA-002
Control of documents
Documents will be controlled through the process of formal submission and distribution
through the doc control system. If a document is replaced or superseded, it will be removed
from the file, stamped and placed in redundant document file. See also the document control
registers. Latest revisions of all documents shall always be available on site at the point of use
.
Control of Records
The Document Controller shall be responsible for the control of records. All documents, as
listed above, and all other documents will be recorded in Document Control Register and a
Document Distribution Register. The Document Control Register include the number,
description, originator, discipline, recipient & control dates and must be updated daily.
The Document Distribution Register include the document number, description, distribution
list, distribution date, the document revision number and a record of the collection of previous
revisions and superseding procedure. This register is also updated daily. Both registers must
be cross referenced with each other daily for control purposes and include distribution to the
Client and JV Management.
A remote server shall be used as a backup for all records. This server will be encrypted with
passwords to limit access from unauthorised persons. All hard copies shall be handed over to
the client on completion of the project, and soft copies shall be retained for a period of 5 years
after project completion.
After the retention period has lapsed, the soft shall be shredded using a specialised & secure
data wipe programme while all hard copies shall be shredded fiscally.
The copyright in this document and the information contained therein is the exclusive property of TORO YA AFRICA AND SOCRASYNC JV. Acceptance of this document constitutes
an agreement that it will be treated as confidential and neither the document nor the information contained therein will be used for any purpose other than that for which it was
originally intended. This document is not to be communicated, disclosed, copied or published to any third person except as previously authorised by the Project Quality Manager.
DATE: 09/07/2019
TORO YA AFRICA AND SOCRASYNC JV
REV: 2
PROJECT QUALITY PLAN
PAGE: 14 of 39
P1127672-LS-C002-QMP-MMA-002
Standard Forms Control; including Files for FEQ’s, EWC, CE’s, PMI’s, NCR’s and Site
Instructions;
Quality; Including Project Quality Plan, Quality Management Policy, Review Meetings
records and Audit reports;
Health & Safety; including Training, Management and Inspections;
COPYRIGHT
The copyright in this document and the information contained therein is the exclusive property of TORO YA AFRICA AND SOCRASYNC JV. Acceptance of this document constitutes
an agreement that it will be treated as confidential and neither the document nor the information contained therein will be used for any purpose other than that for which it was
originally intended. This document is not to be communicated, disclosed, copied or published to any third person except as previously authorised by the Project Quality Manager.
DATE: 09/07/2019
TORO YA AFRICA AND SOCRASYNC JV
REV: 2
PROJECT QUALITY PLAN
PAGE: 15 of 39
P1127672-LS-C002-QMP-MMA-002
work methods, sequence of operations, type of equipment and, where required, special
working measures.
The Quality Control Plans (QCP’s) will specify which sequence or item is to be inspected and
will set out the applicable accepted/rejected criteria. The content of the QCP’s will be agreed
on in conjunction with the Construction Manager & TGC Quality Manager. Improvement or
variation requests will be implemented by means Corrective Action Request Procedure (GCP
006) to correct deficiencies and the control of non-conformances. A PAR and/or a CAR will be
issued immediately on the discovery of any deviation from the drawings, specifications or
additional activities in the Scope of Works. A CAR and PAR register will be kept and updated
weekly and distributed to all relevant recipients.
TYAS is required to provide certain permits, licences and approvals prior to commencement of
the works. Enough time must be allowed in the programme for obtaining these.
4.3 Design Coordination (Refer to GST 001 Design Control)
No work will be done until the Request for information and / or CAR has been approved by the
client’s representative (Project Manager / Supervisor). Any designs that are to be undertaken
and completed by the JV must be approved through the CAR process, prior to any work
commencement.
4.4 Project Quality Assurance and ISO 9001
4.4.1 Roles & Responsibilities
Construction Manager (CM)
The Construction Manager reports directly to the Contract Director and is responsible for:
Is overall responsible for the QA System (ISO 9001 and QAL STD 001)
Project co-ordination with respect to forward planning, manpower allocation, plant
utilisation, cost control, quantity surveying and engineering support where required.
Establish, ensure, maintain and monitor SHEQ requirements in terms of legislation,
project specific requirements and company policies.
Establish and maintain a competent staff complement according to the site organisation
structure and the responsibility pertaining to the respective position.
Establish the contracts contractual and overall program.
Profit Management: i.e. Daily/weekly/ monthly Cost Control.
Ensure that the detailed programs sub-contractors comply and adhere to the contractual
program.
Managing, monitoring and ensuring that the works remains on programme, and that all
contractual dates are met.
Managing, monitoring and ensuring that the contracts budget is maintained; controlled
and meets the targets set out in the objective.
COPYRIGHT
The copyright in this document and the information contained therein is the exclusive property of TORO YA AFRICA AND SOCRASYNC JV. Acceptance of this document constitutes
an agreement that it will be treated as confidential and neither the document nor the information contained therein will be used for any purpose other than that for which it was
originally intended. This document is not to be communicated, disclosed, copied or published to any third person except as previously authorised by the Project Quality Manager.
DATE: 09/07/2019
TORO YA AFRICA AND SOCRASYNC JV
REV: 2
PROJECT QUALITY PLAN
PAGE: 16 of 39
P1127672-LS-C002-QMP-MMA-002
The copyright in this document and the information contained therein is the exclusive property of TORO YA AFRICA AND SOCRASYNC JV. Acceptance of this document constitutes
an agreement that it will be treated as confidential and neither the document nor the information contained therein will be used for any purpose other than that for which it was
originally intended. This document is not to be communicated, disclosed, copied or published to any third person except as previously authorised by the Project Quality Manager.
DATE: 09/07/2019
TORO YA AFRICA AND SOCRASYNC JV
REV: 2
PROJECT QUALITY PLAN
PAGE: 17 of 39
P1127672-LS-C002-QMP-MMA-002
Senior Foreman reports directly to the Construction Manager. Foremen reports to the Senior
Foreman
Inspection of materials received
Supervision of the works (process control)
Responsible for the quality of the works
Traceability of all inspections
Undertake work according to Site / Work Instruction Documents
On-going checking of the quality of the workmanship
Notify the Contracts Manager of product non-conformances
Inspection of the work before covering up (closing with shutters, concrete, etc.)
Safeguarding of Inspection measuring and testing equipment (IMTE) under his/her
responsibility
Verification of accuracy of instrumentation
Comply with the OHS Act, Act 85 of 1993 and Construction Regulations of 18 July 2003
Setting out; tracing the shapes/ positions & dimensions of the works
Checking and verifying works already set out
Checking of the works
Maintain beacons and control on site
Aiding and working with the Assistant Construction Manager in establishing, managing
and maintaining a competent labour complement
TYAS will use ISO 9001 as the basis of all Quality Control and manufacturing control.
The following main ISO 9001 Checklists will be employed:
COPYRIGHT
The copyright in this document and the information contained therein is the exclusive property of TORO YA AFRICA AND SOCRASYNC JV. Acceptance of this document constitutes
an agreement that it will be treated as confidential and neither the document nor the information contained therein will be used for any purpose other than that for which it was
originally intended. This document is not to be communicated, disclosed, copied or published to any third person except as previously authorised by the Project Quality Manager.
DATE: 09/07/2019
TORO YA AFRICA AND SOCRASYNC JV
REV: 2
PROJECT QUALITY PLAN
PAGE: 18 of 39
P1127672-LS-C002-QMP-MMA-002
COPYRIGHT
The copyright in this document and the information contained therein is the exclusive property of TORO YA AFRICA AND SOCRASYNC JV. Acceptance of this document constitutes
an agreement that it will be treated as confidential and neither the document nor the information contained therein will be used for any purpose other than that for which it was
originally intended. This document is not to be communicated, disclosed, copied or published to any third person except as previously authorised by the Project Quality Manager.
DATE: 09/07/2019
TORO YA AFRICA AND SOCRASYNC JV
REV: 2
PROJECT QUALITY PLAN
PAGE: 19 of 39
P1127672-LS-C002-QMP-MMA-002
5.3 QCP’s
Reference Documents QCP-Ref-OOO, as per QCP register, attached as Annexure E.
With reference to the PQCP, all work activity inception and execution control will be
compiled and submitted by the Quality manager (QM), prior to construction work starting
on specific designated construction discipline. The QM will then compile the relevant QCP
to align construction with the Method Statement and Quality Assurance.
5.5 Auditing
Reference Documents AUD-Ref-OOO, as per Audit register.
Reference to item 1.5
The Audit Schedule is attached as Annexure B. This document will remain unchanged,
unless the dates on the attached schedule have changed and communicate to the relevant
personnel. This will ensure that all relevant personnel are informed timeously regarding
Audit dates and that all Audits are executed as per Planned Schedule.
5.6 SD Procedures
All procedures regarding Supplier Appointments, Database, HR and IR will be defined in the
SD Plan as submitted and approved by TGC. Local employment specifications and SMME
adaptation and procurement are specified through affirmative action and employment policies.
The copyright in this document and the information contained therein is the exclusive property of TORO YA AFRICA AND SOCRASYNC JV. Acceptance of this document constitutes
an agreement that it will be treated as confidential and neither the document nor the information contained therein will be used for any purpose other than that for which it was
originally intended. This document is not to be communicated, disclosed, copied or published to any third person except as previously authorised by the Project Quality Manager.
DATE: 09/07/2019
TORO YA AFRICA AND SOCRASYNC JV
REV: 2
PROJECT QUALITY PLAN
PAGE: 20 of 39
P1127672-LS-C002-QMP-MMA-002
The Contracts Manager / QS will ensure that the list of “Project Sub-contractors” (SFD 0701 or
similar) is completed and a copy is forwarded to the QA Clerk / Document Controller who will
file it accordingly.
Nominated subcontractors will be assessed by the Construction Manager and the results
forwarded to JV Head Office.
Approved sub-contractor interim performance appraisals will be done on the sub-contractors
by the Construction Manager three monthly. (SFD 0708) Final subcontractor performance
appraisals will be done at project completion.
Results of the sub-contractor performance will be communicated to the sub-contractor to
ensure continuous improvement and once signed off, will be submitted to TYAS Head Office
to ensure that the sub-contractor list remains updated.
All sub-contractors are required to submit their PQPs, Works Quality Plans/Method
Statements, H&S Plans and reference documentation to TYAS for submission to the
Construction Manager prior to works commencing. When the sub-contractor does not have
any Quality Control Procedures, they will be obliged to use the TYAS Quality System. All
relevant documentation will be submitted for approval prior to commencement of work, to the
Contracts Manager. We are in the process of identifying and approving sub-contractors
through the Resource Approval system of TGC. The list of Sub-contractors will be a live
document.
COPYRIGHT
The copyright in this document and the information contained therein is the exclusive property of TORO YA AFRICA AND SOCRASYNC JV. Acceptance of this document constitutes
an agreement that it will be treated as confidential and neither the document nor the information contained therein will be used for any purpose other than that for which it was
originally intended. This document is not to be communicated, disclosed, copied or published to any third person except as previously authorised by the Project Quality Manager.
DATE: 09/07/2019
TORO YA AFRICA AND SOCRASYNC JV
REV: 2
PROJECT QUALITY PLAN
PAGE: 21 of 39
P1127672-LS-C002-QMP-MMA-002
Manufacturer guarantee;
Test results, with comparison to specified values or limits identifying non-compliances, where
relevant.
Inspection and Test Records will form part of the QA Data Dossier
Refer to the Project Inspection Flow Chart, Fig 8.5, below, for Inspection and Testing.
Further Reference to test processes and procedures is referred to in this section.
Material manufacturers will conform to ISO 9001 control standards and will be evaluated
according to the following;
Material Specifications;
Material delivery;
Material certification;
COPYRIGHT
The copyright in this document and the information contained therein is the exclusive property of TORO YA AFRICA AND SOCRASYNC JV. Acceptance of this document constitutes
an agreement that it will be treated as confidential and neither the document nor the information contained therein will be used for any purpose other than that for which it was
originally intended. This document is not to be communicated, disclosed, copied or published to any third person except as previously authorised by the Project Quality Manager.
DATE: 09/07/2019
TORO YA AFRICA AND SOCRASYNC JV
REV: 2
PROJECT QUALITY PLAN
PAGE: 22 of 39
P1127672-LS-C002-QMP-MMA-002
COPYRIGHT
The copyright in this document and the information contained therein is the exclusive property of TORO YA AFRICA AND SOCRASYNC JV. Acceptance of this document constitutes
an agreement that it will be treated as confidential and neither the document nor the information contained therein will be used for any purpose other than that for which it was
originally intended. This document is not to be communicated, disclosed, copied or published to any third person except as previously authorised by the Project Quality Manager.
DATE: 09/07/2019
TORO YA AFRICA AND SOCRASYNC JV
REV: 2
PROJECT QUALITY PLAN
PAGE: 23 of 39
P1127672-LS-C002-QMP-MMA-002
Ensuring that inspection and testing are in accordance with the Project QCPs.
The results on the above-mentioned test requests are received by the Quality Manager and
attached to the original copy of the test request and presented to the TGC CM who will accept
or reject the results and sign off the documentation and the results will be recorded in the
register.
The Quality Manager will monitor and document trends and will present the findings during the
Project Meeting.
Materials and equipment that are manufactured off site will be inspected when required by
either qualified outside inspection agents or by TYAS QC Inspectors. Inspections are planned
and coordinated by the Quality Manager in conjunction with the respective Manager/s. TYAS
inspection and intervention points for subcontractors/suppliers, manufacturing plans and
controls, are implemented in accordance with Procedure GST 003 Project Delivery and GCP
007 - “Subcontractor Evaluation”.
5.9 Inspection, Measuring and Testing Equipment
TYAS Reference Documentation: GST 005 Calibration Testing Equipment, for a list of IMTE
used and calibration frequencies on this project refer to SFD 1202. This document
incorporates the expiry and recalibration dates of IMTE. The handheld tapes don’t require
IMTE control, as they are not critical for measurement control. The Construction Manager will
manage all IMTE.
All subcontractors will be responsible for the calibration of their measuring and monitoring
equipment. Copies of these certificates must be filed in the relevant Data Pack. Once
calibration certificates have expired, equipment must be sent away for recalibration.
TYAS require all Testing Equipment to be Calibrated every twelve months unless otherwise
specified by the manufacturer. Relevant calibration certificates will form part of the quality
control data pack. Equipment not conforming will be moved off site for re-calibration or
replacement.
COPYRIGHT
The copyright in this document and the information contained therein is the exclusive property of TORO YA AFRICA AND SOCRASYNC JV. Acceptance of this document constitutes
an agreement that it will be treated as confidential and neither the document nor the information contained therein will be used for any purpose other than that for which it was
originally intended. This document is not to be communicated, disclosed, copied or published to any third person except as previously authorised by the Project Quality Manager.
DATE: 09/07/2019
TORO YA AFRICA AND SOCRASYNC JV
REV: 2
PROJECT QUALITY PLAN
PAGE: 24 of 39
P1127672-LS-C002-QMP-MMA-002
COPYRIGHT
The copyright in this document and the information contained therein is the exclusive property of TORO YA AFRICA AND SOCRASYNC JV. Acceptance of this document constitutes
an agreement that it will be treated as confidential and neither the document nor the information contained therein will be used for any purpose other than that for which it was
originally intended. This document is not to be communicated, disclosed, copied or published to any third person except as previously authorised by the Project Quality Manager.
DATE: 09/07/2019
TORO YA AFRICA AND SOCRASYNC JV
REV: 2
PROJECT QUALITY PLAN
PAGE: 25 of 39
P1127672-LS-C002-QMP-MMA-002
COPYRIGHT
The copyright in this document and the information contained therein is the exclusive property of TORO YA AFRICA AND SOCRASYNC JV. Acceptance of this document constitutes
an agreement that it will be treated as confidential and neither the document nor the information contained therein will be used for any purpose other than that for which it was
originally intended. This document is not to be communicated, disclosed, copied or published to any third person except as previously authorised by the Project Quality Manager.
DATE: 09/07/2019
TORO YA AFRICA AND SOCRASYNC JV
REV: 2
PROJECT QUALITY PLAN
PAGE: 26 of 39
P1127672-LS-C002-QMP-MMA-002
TYAS has compiled a JV Quality Audit Schedule which identifies months in which audits will
be conducted to ensure that TYAS complies with all ISO requirements. This schedule
considers all Project and Head Office Support Functions. Schedule is included in item 5.5
above.
Quality review and improvement also are agenda items on all Point, Technical and Project
meetings. Every review and process, controls and increase effectiveness of Quality control.
COPYRIGHT
The copyright in this document and the information contained therein is the exclusive property of TORO YA AFRICA AND SOCRASYNC JV. Acceptance of this document constitutes
an agreement that it will be treated as confidential and neither the document nor the information contained therein will be used for any purpose other than that for which it was
originally intended. This document is not to be communicated, disclosed, copied or published to any third person except as previously authorised by the Project Quality Manager.
DATE: 09/07/2019
TORO YA AFRICA AND SOCRASYNC JV
REV: 2
PROJECT QUALITY PLAN
PAGE: 27 of 39
P1127672-LS-C002-QMP-MMA-002
On completion of the defects or outstanding works, the individual CAR Notices will be signed
off.
7.3 Corrective Action Request and Reporting
TYAS Reference Documentation: GCP 006 Corrective Action Procedure
Corrective Action is controlled as follows:
The Construction Manager will control and maintain the status list on the non-
conformances (system and product);
The Construction Manager will ensure the effective closure of Corrective Action
Requests (CAR) within the stipulated time frame, as stipulated by the client.
The Service and Maintenance Plan will include all necessary parts and operating manuals
from the Electrical and Mechanical Sub-contractors.
The SMP will be issued for use before handover.
8. QA DATA DOSSIER
The Quality Assurance Dossier, indicating relevant planned Data Packs are included as
Annexure C.
This is a live document that will be updated on a monthly basis. This dossier form an integral
part of the Data Pack Control System and are further expanded to the Data Pack
Register/Index.
COPYRIGHT
The copyright in this document and the information contained therein is the exclusive property of TORO YA AFRICA AND SOCRASYNC JV. Acceptance of this document constitutes
an agreement that it will be treated as confidential and neither the document nor the information contained therein will be used for any purpose other than that for which it was
originally intended. This document is not to be communicated, disclosed, copied or published to any third person except as previously authorised by the Project Quality Manager.
DATE: 09/07/2019
TORO YA AFRICA AND SOCRASYNC JV
REV: 2
PROJECT QUALITY PLAN
PAGE: 28 of 39
P1127672-LS-C002-QMP-MMA-002
COPYRIGHT
The copyright in this document and the information contained therein is the exclusive property of TORO YA AFRICA AND SOCRASYNC JV. Acceptance of this document constitutes
an agreement that it will be treated as confidential and neither the document nor the information contained therein will be used for any purpose other than that for which it was
originally intended. This document is not to be communicated, disclosed, copied or published to any third person except as previously authorised by the Project Quality Manager.
DATE: 09/07/2019
TORO YA AFRICA AND SOCRASYNC JV
REV: 2
PROJECT QUALITY PLAN
PAGE: 29 of 39
P1127672-LS-C002-QMP-MMA-002
Annexure A
Project Organogram
COPYRIGHT
The copyright in this document and the information contained therein is the exclusive property of TORO YA AFRICA AND SOCRASYNC JV. Acceptance of this document constitutes
an agreement that it will be treated as confidential and neither the document nor the information contained therein will be used for any purpose other than that for which it was
originally intended. This document is not to be communicated, disclosed, copied or published to any third person except as previously authorised by the Project Quality Manager.
DATE: 09/07/2019
TORO YA AFRICA AND SOCRASYNC JV
REV: 2
PROJECT QUALITY PLAN
PAGE: 30 of 39
P1127672-LS-C002-QMP-MMA-002
COPYRIGHT
The copyright in this document and the information contained therein is the exclusive property of TORO YA AFRICA AND SOCRASYNC JV. Acceptance of this document constitutes
an agreement that it will be treated as confidential and neither the document nor the information contained therein will be used for any purpose other than that for which it was
originally intended. This document is not to be communicated, disclosed, copied or published to any third person except as previously authorised by the Project Quality Manager.
DATE: 09/07/2019
TORO YA AFRICA AND SOCRASYNC JV
REV: 2
PROJECT QUALITY PLAN
PAGE: 31 of 39
P1127672-LS-C002-QMP-MMA-002
Annexure B
Audit Schedule
COPYRIGHT
The copyright in this document and the information contained therein is the exclusive property of TORO YA AFRICA AND SOCRASYNC JV. Acceptance of this document constitutes
an agreement that it will be treated as confidential and neither the document nor the information contained therein will be used for any purpose other than that for which it was
originally intended. This document is not to be communicated, disclosed, copied or published to any third person except as previously authorised by the Project Quality Manager.
DATE: 09/07/2019
TORO YA AFRICA AND SOCRASYNC JV
REV: 2
PROJECT QUALITY PLAN
PAGE: 32 of 39
P1127672-LS-C002-QMP-MMA-002
Final Review Final Review Final Review Final Review Final Review
COPYRIGHT
The copyright in this document and the information contained therein is the exclusive property of TORO YA AFRICA AND SOCRASYNC JV. Acceptance of this document constitutes
an agreement that it will be treated as confidential and neither the document nor the information contained therein will be used for any purpose other than that for which it was
originally intended. This document is not to be communicated, disclosed, copied or published to any third person except as previously authorised by the Project Quality Manager.
DATE: 09/07/2019
TORO YA AFRICA AND SOCRASYNC JV
REV: 2
PROJECT QUALITY PLAN
PAGE: 33 of 39
P1127672-LS-C002-QMP-MMA-002
Annexure C
Quality Assurance DATA Dossier
COPYRIGHT
The copyright in this document and the information contained therein is the exclusive property of TORO YA AFRICA AND SOCRASYNC JV. Acceptance of this document constitutes
an agreement that it will be treated as confidential and neither the document nor the information contained therein will be used for any purpose other than that for which it was
originally intended. This document is not to be communicated, disclosed, copied or published to any third person except as previously authorised by the Project Quality Manager.
DATE: 09/07/2019
TORO YA AFRICA AND SOCRASYNC JV
REV: 2
PROJECT QUALITY PLAN
PAGE: 34 of 39
P1127672-LS-C002-QMP-MMA-002
11 Non-conformances/Corrective Actions 9
13 Inspection, Measuring and Test Equipment (IMTE) Refer to file no. 3 for Index / Contents Page
COPYRIGHT
The copyright in this document and the information contained therein is the exclusive property of TORO YA AFRICA AND SOCRASYNC JV. Acceptance of this document constitutes
an agreement that it will be treated as confidential and neither the document nor the information contained therein will be used for any purpose other than that for which it was
originally intended. This document is not to be communicated, disclosed, copied or published to any third person except as previously authorised by the Project Quality Manager.
DATE: 09/07/2019
TORO YA AFRICA AND SOCRASYNC JV
REV: 2
PROJECT QUALITY PLAN
PAGE: 35 of 39
P1127672-LS-C002-QMP-MMA-002
COPYRIGHT
The copyright in this document and the information contained therein is the exclusive property of TORO YA AFRICA AND SOCRASYNC JV. Acceptance of this document constitutes
an agreement that it will be treated as confidential and neither the document nor the information contained therein will be used for any purpose other than that for which it was
originally intended. This document is not to be communicated, disclosed, copied or published to any third person except as previously authorised by the Project Quality Manager.
DATE: 09/07/2019
TORO YA AFRICA AND SOCRASYNC JV
REV: 2
PROJECT QUALITY PLAN
PAGE: 36 of 39
P1127672-LS-C002-QMP-MMA-002
Annexure D
Method Statement Register
COPYRIGHT
The copyright in this document and the information contained therein is the exclusive property of TORO YA AFRICA AND SOCRASYNC JV. Acceptance of this document constitutes
an agreement that it will be treated as confidential and neither the document nor the information contained therein will be used for any purpose other than that for which it was
originally intended. This document is not to be communicated, disclosed, copied or published to any third person except as previously authorised by the Project Quality Manager.
DATE: 09/07/2019
TORO YA AFRICA AND SOCRASYNC JV
REV: 2
PROJECT QUALITY PLAN
PAGE: 37 of 39
P1127672-LS-C002-QMP-MMA-002
COPYRIGHT
The copyright in this document and the information contained therein is the exclusive property of TORO YA AFRICA AND SOCRASYNC JV. Acceptance of this document constitutes
an agreement that it will be treated as confidential and neither the document nor the information contained therein will be used for any purpose other than that for which it was
originally intended. This document is not to be communicated, disclosed, copied or published to any third person except as previously authorised by the Project Quality Manager.
DATE: 09/07/2019
TORO YA AFRICA AND SOCRASYNC JV
REV: 2
PROJECT QUALITY PLAN
PAGE: 38 of 39
P1127672-LS-C002-QMP-MMA-002
Annexure E
QCP Register
COPYRIGHT
The copyright in this document and the information contained therein is the exclusive property of TORO YA AFRICA AND SOCRASYNC JV. Acceptance of this document constitutes
an agreement that it will be treated as confidential and neither the document nor the information contained therein will be used for any purpose other than that for which it was
originally intended. This document is not to be communicated, disclosed, copied or published to any third person except as previously authorised by the Project Quality Manager.
DATE: 09/07/2019
TORO YA AFRICA AND SOCRASYNC JV
REV: 2
PROJECT QUALITY PLAN
PAGE: 39 of 39
P1127672-LS-C002-QMP-MMA-002
COPYRIGHT
The copyright in this document and the information contained therein is the exclusive property of TORO YA AFRICA AND SOCRASYNC JV. Acceptance of this document constitutes
an agreement that it will be treated as confidential and neither the document nor the information contained therein will be used for any purpose other than that for which it was
originally intended. This document is not to be communicated, disclosed, copied or published to any third person except as previously authorised by the Project Quality Manager.