Академический Документы
Профессиональный Документы
Культура Документы
WTP
1 DM plant 24 hrs operation completed with one auto regeneration cycle
Cooling Tower
1 Pickiling and passivation of cooling water piping under progress
2 Side stream filter inside distrubutor pipes fixed , media to be charged
Nitrogen plant
1 PSA nitrogen passed thro' 1 copper catalyst unit and run the booster
compressor with a pressure of 18 Kg/ cm2, system operation to be continued
for 6 hrs to introduce hydogen into the De-oxo system
2 Ammonia cracker brought inline, initial venting is in progress
3 Tapping from the main header to SSP and DSD is under progress at OSBL
limit
Air compressor
1 Centrifugal compressor X-8601 coupling alignment work under progress
2 Reciprocating air compressor X-8801-A unloading problem rectification work
under progress
3 Air dryrer X-8703 A&B leak test completed, insulation work under progress
4 Moisture seperator fabrication for 15PA line under progress
5 15PA reciever outlet line to pipe rack welding work under progress