Applicability
2. Overview
For each project an HICT responsibility matrix shall be created indicating a list of all anticipated technologies within the construction
scope of each facility. For each technology, columns shall be provided to identify scope between the project design team members as
well as details relating to specifying, design, supply, installation interface and procurement responsibilities. This matrix shall be updated
on a regular basis in consultations with HMC HICT to de ne project scope and delivery methods.
The following list of systems is provided as a starting point for tting out the HICT system responsibility matrix:
Facilty
Clinical data network HMC HMC HMC HMC HMC
constructor
Facilty
Clinical servers HMC HMC HMC HMC HMC
constructor
Facilty
Non-clinical data network HMC HMC HMC HMC HMC
constructor
Facilty
Telephone equipment HMC HMC HMC HMC HMC
constructor
Facilty
Cellular services (GSM, 3G/4G) QTel QTel QTel QTel QTel
Constructor
Staff mobile communication sevices HMC HMC HMC HMC HMC HMC
Biomedical equipment ( xed and Facilty Facilty Facilty Facilty Facilty Facilty
mobile) constructor constructor constructor constructor constructor constructor