Bill of Quantities
Dr Kayode Oduwole

Dated: September 14, 2015

Dr. Kayode Oduwole

e-Mail: kayode.oduwole@gmail.com
EH004 - Dr Kayode Oduwole
GRA Ext - BQ: 001 - Bill of Quantities for BQ at rear of main building
002 - SUBSTRUCTURES
Ref Description Quantity Units Rate Value
SITE PREPARATION

Vegetation, shrubs and small trees including


stumps and roots

A girth < 500 2 Nr 3,300.00 6,600.00

Cut trees and remove stumps from site

B girth 500 - 1000 3 Nr 8,250.00 24,750.00

To Collection: 31,350.00
001-002/1

PROPOL FINISHERS LIMITED


EH004 - Dr Kayode Oduwole
GRA Ext - BQ: 001 - Bill of Quantities for BQ at rear of main building
002 - SUBSTRUCTURES
Ref Description Quantity Units Rate Value
EXCAVATION AND EARTHWORKS

Excavation

A Excavate topsoil; average 200mm thick 239 m2 152.25 36,387.75

B Excavate to reduce level; < 1.0m deep m3 Included

C Excavate foundation trench 750mm deep, 750mm


wide 70 m3 525.00 36,750.00

Disposal

D Disposal of excavated materials on site; in


temporary spoil heaps average distance < 1km
from excavation 28 m3 500.00 14,000.00

E Dispose excess materials off-site 42 m3 1,500.00 63,000.00

F keeping surfaces of site and excavation free from


water Sum Included

G Level bottom of excavation, in foundation


trenches 94 m2 500.00 47,000.00

Concrete

H Concrete in foundation; 250mm thick; poured


against faces of excavation 22 m3 31,531.38 693,690.36

I Concrete in floor slab; 150mm thick 27 m3 31,531.38 851,347.26

J Blockwork in foundation; 225mm blockwork in


stretcher bond; 1:4 mortar 131 m2 4,000.12 524,015.72

Filling

L laterite filling to faces of excavation and voids; in


150mm thick layers 73 m3 2,061.44 150,485.12

M hardcore filling to faces of excavation; 200mm


thick 31 m3 9,000.47 279,014.57

N Level and compact faces of backfilling 156 m2 549.28 85,687.68

O 1200 guage DPM 172 m2 500.00 86,000.00

Formwork

P Formwork; 300mm thick around perimeter of slab 64 m 535.42 34,266.88

To Collection: 2,901,645.34
001-002/2

PROPOL FINISHERS LIMITED


EH004 - Dr Kayode Oduwole
GRA Ext - BQ: 001 - Bill of Quantities for BQ at rear of main building

Ref Description Quantity Units Rate Value


Collection for SUBSTRUCTURES

001-002/1 31,350.00
001-002/2 2,901,645.34

To Summary: 2,932,995.34

PROPOL FINISHERS LIMITED


EH004 - Dr Kayode Oduwole
GRA Ext - BQ: 001 - Bill of Quantities for BQ at rear of main building
003 - EXTERNAL WALLS
Ref Description Quantity Units Rate Value
BRICKWORK AND BLOCKWORK

Blockwork

225mm Blockwork bedded in mortar (1:4); in


stretcher bond

Walls

A > 300mm thick 192 m2 4,000.12 768,023.04

Concrete forms including formwork and


reinforcement

Lintols

B 225mm x 225mm cross sectional area; 32 m 2,500.00 80,000.00

Parapet wall complete with Headcourse

C 450mm x 450mm cross sectional area 66 m 4,000.00 264,000.00

To Collection: 1,112,023.04
001-003/1

PROPOL FINISHERS LIMITED


EH004 - Dr Kayode Oduwole
GRA Ext - BQ: 001 - Bill of Quantities for BQ at rear of main building
004 - INTERNAL WALLS
Ref Description Quantity Units Rate Value
BRICKWORK AND BLOCKWORK

Blockwork

225mm Blockwork bedded in mortar (1:4); in


stretcher bond

Walls

A > 300mm thick 153 m2 4,000.12 612,018.36

150mm Blockwork bedded in mortar (1:4); in


stretcher bond

Walls

B > 300mm thick 26 m2 3,776.01 98,176.26

To Collection: 710,194.62
001-004/1

PROPOL FINISHERS LIMITED


EH004 - Dr Kayode Oduwole
GRA Ext - BQ: 001 - Bill of Quantities for BQ at rear of main building
009 - ROOF STRUCTURE AND FINISHES
Ref Description Quantity Units Rate Value
ROOF STRUCTURE

PROVISIONAL AND PC SUM

Provisional Sum

Allow the provisional sum of N880,000 for providing


roof structure, trusses and the like to receive roof
finishes

A Roof structure 1 Sum TBA

B Attendance and BWIC 1 Sum TBA

ROOF FINISHES

Provisional Sum

Allow the provisional sum of N2.2m for providing


winchtech roof finishes, all in accordance with
architects and engineers details and specification,
complete with eaves detail, gutters and downpipes

C Roof finishing 1 Sum TBA

D Attendance and BWIC 1 Sum TBA

To Collection:
001-009/1

PROPOL FINISHERS LIMITED


EH004 - Dr Kayode Oduwole
GRA Ext - BQ: 001 - Bill of Quantities for BQ at rear of main building
Bill Collection for Bill of Quantities for BQ at rear of main building
Ref Description Quantity Units Rate Value
002 SUBSTRUCTURES 2,932,995.34
003 EXTERNAL WALLS 1,112,023.04
004 INTERNAL WALLS 710,194.62
009 ROOF STRUCTURE AND FINISHES

Total: 4,755,213.00

Bill Collection for Bill of Quantities f

PROPOL FINISHERS LIMITED


EH004 - Dr Kayode Oduwole

Summary for GRA Ext - BQ


Ref Description Quantity Units Rate Value
001 Bill of Quantities for BQ at rear of main building 4,755,213.00

Total: 4,755,213.00

Summary for GRA Ext - BQ

PROPOL FINISHERS LIMITED


EH004 - Dr Kayode Oduwole

Estimate Summary
Ref Description Quantity Units Rate Value
0011 GRA Ext - Main Building
0012 GRA Ext - BQ 4,755,213.00
0021 Ewang Estate - Main Building
0022 Ewang Estate - BQ

Total: 4,755,213.00

Estimate Summary

PROPOL FINISHERS LIMITED