Академический Документы
Профессиональный Документы
Культура Документы
WITH
MANAGEMENT PLAN
FOR
ANUPSHAHAR SEWERAGE SCHEME
(Distt Bulandshahar)
5
List of Figure
Figure 1 Tapped Nala ................................................................................................................24
Figure 2 Overflow of Nala falling into the river ..........................................................................24
Figure 3Existing STPs location....................................................................................................26
Figure 4STP-I, Zone-A, 0.805 MLD .............................................................................................28
Figure 5STP-II, Zone-B, 1.75 MLD...............................................................................................28
Figure 6 Plan of treated waste water used for irrigation purposes ............................................35
Figure 8 Flowchart describing the steps adopted for Project Impact Assessment ......................47
Figure 9Distribution of Dolphin in Upper Ganga System population up to October 2012
(source WWF) ...........................................................................................................................78
Figure 10 Temperature Variation & Precipitation ......................................................................80
Figure 11 Annual Temperature ..................................................................................................79
Figure 12 Annual Rainfall...........................................................................................................81
Figure 13 Land use & Cropping Pattern .....................................................................................82
Figure 14 Geology of the town ..................................................................................................83
Figure 15 Underground Sewer Line ...........................................................................................84
Figure 16 Groundwater Scenario of the Town ...........................................................................85
Figure 17 Wind Rose .................................................................................................................86
Figure 18 Air Sampling in progress ............................................................................................90
Figure 19 Noise Sampling ..........................................................................................................94
Figure 20 Water Sampling Site Pics..........................................................................................101
Figure 21 Drainage Pattern in whole State ..............................................................................102
Figure 22 Tourism Map of the State ........................................................................................106
Figure 23 Environmentally Sensitive Zones .................................... Error! Bookmark not defined.
Figure 24 Health Care in the State and Town...........................................................................109
Figure 25 Education Scenario in the town ...............................................................................110
Figure 26 Soils in different Parts of State and Town.................................................................112
Figure 27 Soil Collection for sampling purposes.......................................................................113
Figure 28Distribution of Dolphin in Upper Ganga System population up to October 2012
(source WWF) ............................................................................... Error! Bookmark not defined.
Figure 29 Socio-Economic Profile of the town .........................................................................118
Figure 30 Density of Population in the town............................................................................122
Figure 31 Mela pictures in Anupshahr .....................................................................................124
Figure 32 Cultural Significance in the state ..............................................................................125
6
List of Tables
7
ABBREVEATIONS
8
EXECUTIVE SUMMARY
In order to reduce the pollution load on the river, Ganga Action Plan (GAP) was launched. In
the GAP town was taken as the unit of planning. However, in view of the short comings
observed in the approach followed in the GAP it was felt necessary that the river
conservation plan needs to be revamped. To give a fresh impetus to pollution abatement of
River Ganga & its tributaries by adopting a holistic approach with river basin as the unit of
planning and management, National Ganga River Basin Authority (NGRBA) was set up in Feb
2009. Thus the objective has now shifted from town centric to river basin approach.
Anupshahr is a major town in distt. Bulandshahar UP. It is located 115 km away from
Delhi,95 km away from Noida,75 km away from Greater Noida, 55 km away from Aligarh
and 40 KM away from Bulandshahr This city is full of cultural and historical heritage. It is
located on the bank of Holy River Ganga, thousands of people take holy bath in River Ganga
through Anupshahr Ganga Ghat. The Town comprises of 25 nos. of wards and at presents
holds the population of 29700 as per the 2011 population survey data.
The Town comprises of 25 nos. of wards and for each and every ward there is a provision
for water supply line. There is no provision of private tube wells in the town. The water
supply within the area is adequate to cater the total population in different wards. The
Water Supply rate is different for the piped and stand posts connections. The 96 % of the
population is fed through proper piped water supply with the per capita rate of 120lpcd and
the remaining population which is utilizing the hand pumps and other sources will be fed
with a rate of rate of 15 lpcd.
Anupshahr town at present doesn’t have a sewerage network system. However, under
Ganga Action Plan-I, Nala tapping was done by intercepting the flow and diverting it into
two nos. of sewerage treatment Plants of 1.75 mld and 0.805 mld capacity respectively. At
present only the flow of Nalas is tapped and diverted to STP and treated water is discharged
into the River Ganga. However in the rainy seasons and the peak flow period (Mela period)
these 250mm sewer lines are collapsed and the overflow of the waste water creates the
unhygienic conditions for the people residing in the area.
The population projection including the floating population of the town has been worked
out by various statistical methods. The “Incremental Increase Method” has been adopted
9
for the population projections from all other methods as the population increase trends in
the Anupshahr town for the previous years is in accordance with the projected population
calculated from this method. The initial (2018), mid (2033) & ultimate (2048) stage
population adopted for the project are 38795, 49878 & 63635 respectively.
The rate of water supply for preparing the sewerage project has been taken as 135 lpcd
with a return factor of 0.8. Ground water infiltration has also been taken into consideration
where ever applicable. On this basis the waste water generation for initial, mid& ultimate
stage comes to4.19MLD 5.39 MLD & 6.87MLD respectively. The sewerage project has been
prepared on this basis.
The design is done by keeping in mind that there should be no requirement of IPS within
the sewerage network, apart from the main Pumping stations. The route of the sewerage
pipes is laid in such a way that wastewater mostly follows the gravity flow. The drawing
showing the sewerage network and the design sheet of the sewerage network is shown in
the later section of the report. After considering both the options, it is concluded that
option-II is more feasible than the earlier one in terms of financial and technical aspects.
Proposed sewerage system is designed for 30 years period. The major components of the
proposed project include:
The sewage network is designed to be laid down in the town considering the peak factor of
3.0; the total estimated length of sewage network is likely to be 60 kms (approx.) with
sewer ranging from 150mm dia to 600 mm dia. Non clog submersible pumps are proposed
to be provided at MPS and these pumping units are designed for the waste water flows
from the connected sewer. The capacity of each pump will be ¼ of peak flow. Six pumps will
be provided at each pumping station as the 50% standby is proposed. The rising main have
been designed for SPS in Zone-A and Zone-B for the lifting of waste water from the low lying
areas to the corresponding STPs. The design is made for the middle and peak capacities
having make of DI with dia of 300mm. There are two MPS proposed at the site located in
the plan. The existing two MPS will be dismantled once the construction of these new MPS
is done.
The Life Cycle costing (LCC) technique has been adopted to determine the most suitable
Technological option for the STP at Anupshahr. On this basis, MBBR has been adopted. This
10
option is cost effective, acquires lesser area and produces quality results.
The characteristics of the waste water carried by all the three drains in the town were
measured. The waste water characteristics’ of the samples taken from the drains is on
tower side & does not present the real picture of the characteristics of waste water
generated in the town. The STP has therefore been designed for BOD5 -220 mg/I, TSS-350
mg/I, Fecal coliform 106-109 MPN/100 ml, which are in general adopted for design of STPs
in similar towns. The Sewage Treatment Plant has been designed for year 2028 requirement
of 4.96mld capacity. Capacity of STP at Zone A& Zone B are 2.267 mld & 2.688 mld
respectively. Further modules can be added in future as & when required. The land for
proposed STP belongs to Nagar Panchayat.
The treated wastewater is very rich in terms of nutrients such as Nitrogen, Phosphorus.
Therefore, it shall be proposed to utilize it as a resource for agriculture. The treated waste
water will be carried by the RCC pipe of 600 mm dia. having length of 650 m to the River
Ganga for Zone-A and 600 mm dia. having length of 450 m for Zone-B, if it is not being
utilized for irrigation purposes.
The treated effluent is proposed to be disinfected by using a suitable methodology & then
used for irrigation purposes. Provision has also been made for staff quarters, administrative
building & lab, power connections, land for pumping station & 5 years O&M Cost etc.
As per the Environmental and Social Management Framework (NGRBA, 2011), the
implementation of such river pollution mitigation projects under the NGRBP is anticipated
to encounter a variety of environmental and social issues/problems. Therefore the study of
environment and social sector is required for analyzing the impacts of proposed project,
and suggesting the management plans to handle any negative impacts. The Detailed Project
Report and the Environmental and Social Assessment with Management Plan (ESAMP) is
being prepared on the basis of the Detailed Project Report that has been prepared by U.P.
Jal Nigam.
Most of the waste water of the town is discharged directly in the River Ganga which not
only adds to the pollution load of River Ganga but also creates unhygienic conditions in the
town, unhealthy environment & endangers public health. Therefore in order to reduce
pollution load of River Ganga and create a healthy environment in the town, pollution
11
abatement works in which a planned sewerage system is provided to the town, is a must.
The methodology adopted for the environmental and social assessment includes secondary
data analysis carrying out scoping in the field, survey of the host population and discussions
with key stakeholders including government officials, Nagar Panchayat and local residents.
Based on these outcomes, a screening activity was conducted with the help of the screening
checklist format provided in Environmental and Social Management Framework of NGRBA.
Thereafter, environmental and social impacts were identified and assessed and a mitigation
plan was developed based on the aforementioned.
The screening checklist includes criteria that details out the impact level of various activities
during the construction and operation phases. These criteria include environmental factors
such as the presence of eco-sensitive region in and around the project area, clearance of
tree cover, improper storage of excavation spoils, flooding of adjacent areas, noise and dust
levels & damage to existing utilities. Social criteria include factors such as requirement for
land acquisition if needed, displacement of habitants, and loss of livelihood and gender
issues.
Based on the criteria-wise screening activity and the categorization of potential sub projects
of the NGRBP, the present project of Sewerage work in Anupshahr town falls under low
impact category, which does not need any land acquisition and has an overall positive
impact by tapping the wastewater which was earlier polluting the river Ganga.
As a part of ESAMP, baseline study of the Anupshahr town was prepared to understand the
region's existing physical characteristics, cultural and social status of the residing
community.
While in baseline status of social section, it brings out the status of demographic
composition of the population, general land use feature of the wards and also details of the
social survey outcomes at various consultations held in different wards of the town.
Although there would not be any negative or adverse environmental or social impacts, but
these have temporary impacts on air quality (impact on health), traffic blockages, safety
hazards for pedestrians, possible interruption in commercial activity, and accidental
breakage of other public infrastructure such as water pipes.
12
These temporary impacts can be mitigated with appropriate mitigation plans, which have
been suggested in the ESAMP. The probable cost of environmental management plan, has
been estimated to be approximately Rs.70.59 lac. The details have been given in table 7.5 of
this report. The larger environmental value of the project greatly outweighs the temporary
disruptions and impacts mentioned above. The project is expected to benefit the town, as
the wastewater that currently flows untreated into the Ganga River will be arrested &
treated. The treated effluent is proposed to be used for irrigation and afforestation & may
have to be discharged into river Ganga during rainy season.
13
1 Introduction
The river Ganga has significant economic, environmental and cultural value in India.
Rising in the Himalayas and flowing in to the Bay of Bengal, the river traverses a course of
more than 2,500 km through the plains of north and eastern India. The Ganga main stem
- which also extends into parts of Nepal, China and Bangladesh - accounts for 26 per cent
of India's landmass, 30 per cent of its water resources and more than 40 per cent of its
population. The Ganga also serves as one of India's holiest rivers whose cultural and
spiritual significance transcends the boundaries of the basin.
Despite its importance, extreme pollution pressures from increasing population and
industrialization pose a great threat to the biodiversity and environmental sustainability of
the Ganga, with detrimental effects on both the quantity and quality of its flows.
Discharge of untreated sewage and industrial wastewater, non-point pollution sources
from religious activities along the river, agriculture and livestock as well as poor solid
waste management are the main causes for pollution in river Ganga.
15
The first project of such several phases of support aims at;
1. Establishing and operationalizing central and state level NGRBA institutions capable of
planning and implementing a multi sectorial river water quality improvement
program and;
2. Reducing pollution loads into the river through selected investments.
To achieve the above, the proposed World Bank assisted National Ganga River Basin
Project (NGRBP) envisages two main components.
1.3.1.1 Objective
The objectives of this component are to: (i) build functional capacity of the NGRBA's
operational institutions at both the central and state levels; and (ii) provide support to
associated institutions for implementing the NGRBA program.
The activities financed under this component are grouped under the following sub-
components:
(a) Sub-component A: NGRBA Operationalization and Program Management
(b) Sub-component B: Technical Assistance for ULB Service Providers
16
(c) Sub-component C: Technical Assistance for Environmental Regulators
Program Management for the Entire NGRBA Program: The sub-component will provide
for initial setup costs of office infrastructure and equipment, as well as provision of
critical consultancies, incremental staffing, training, and operation costs. Key NGRBA
program management activities included under this sub-component are described below:
17
1.3.1.4 Sub-component C: Technical Assistance for Environmental Regulator
This sub-component is aimed at addressing the key constraints faced by the CPCB and SPCBs
related to their functions regarding the Ganga. The subcomponent will support:
1.3.2.1 Objective
The objective of this component is to finance demonstrative infrastructure investments to
reduce pollution loads in priority locations on the river.
A) Provide a filter for all the NGRBA investments, for ensuring that the selected investments
are well-prepared and amongst the most effective in reducing the pollution loads;
18
1.3.2.3.1 Framework Criteria
The investments framework prescribes the criteria and quality assurance standards covering
various aspects including eligibility, prioritization, planning, technical preparation, financial
and economic analyses, environmental and social management, long term O&M
sustainability, community participation, and local institutional capacity.
19
1.4 Structure of the Report
The Environment and Social Assessment with Management Plan for the Sewerage works in
Anupshahr town, Uttar Pradesh rolls out the baseline status of the existing sewage situation
and analyzes the situation if the proposed project is implemented, with its possible
implications and to negate those implications management plan is advised which is as per
the Environment and Social Management Framework.
Chapter 1:starts with the introduction of the programme to clean up River Ganga and
various mechanisms to implement the project. This chapter details out the functionalities of
the institutions involved in the project.
Chapter 2:In this chapter, specific project description is discussed pertaining to the
proposed sewerage project in Anupshahr town. This chapter provides insight into the
various components of the proposed project.
Chapter 3: This chapter of the report talks about the methodology adopted for the
environmental and social assessment included secondary data analysis and identifying
information requirements and their sources, defining the project area and carrying out
scoping in the field, survey of the host population and discussion with key stakeholders
including Nagar Panchayat at government officials and local residents. Based on these
outcomes, a screening activity was conducted with the help of the screening checklist
format provided in ESMF report of NGRBA.
Chapter 4: In this chapter of the report presents the applicable laws and guidelines related
to such kind of projects and are in accordance with the ESMF report. It gives insight to
applicable environmental and social laws including land acquisition act and forest act.
Chapter 5:In this chapter, detailed baseline scenario of the information available for city and
for sewerage in Anupshahr town is presented for both environmental and social aspects.
Baseline scenario helps to assess the situation now and provides an indication of the
scenario after the project execution. In environmental scenario it reflects the status of
environmental entities like status of climate, geological features, air quality, water quality,
waste management. As part of the social scenario, it brings out the status of demographic
20
composition of the population, general land-use features of the wards and also details of
the social survey outcomes at various consultations held in different wards of the sewerage
district.
Chapter 6:In this chapter, environmental and social impacts were identified and assessed
which details out the key issues related to safety, environmental concerns and livelihood. It
identifies issues at various stages of the project cycle i.e. during design and development
phase, construction as well as during the operation phase.
The project activities would not have any negative or adverse environmental or social
impacts. There may however be temporary and very limited impacts due to various
construction activities to be undertaken. The identified environmental impacts have further
been classified under the heads of environmentally sensitive areas, air quality, water
resources and noise quality. The social impacts have further been classified under impacts
on human health, traffic congestion, impact on livelihood, land acquisition, impact on
utilities and existing infrastructure, noise levels, safety hazards and failure to restore
temporary construction sites.
Chapter 7:The temporary impacts which have been broadly described in the ongoing
chapters can be mitigated with appropriate mitigation plans, which have been focused upon
in this Chapter of the report, along with monitoring and evaluation of future projects.
However, keeping in view that the impacts will only be temporary and short lived, it is
concluded that the larger environmental value of the project greatly outweighs them. It also
chalks out management plan with specific environmental management plan and social
management plan and also brings out cost issues related to it. For better execution of the
project it presents the consultation framework for participatory planning and also talks
about the capacity of institutions involved.
21
Chapter 9: This is the final chapter concludes the inferences brought out from the
environmental and social analysis of the project activities in Anupshahr town. It also
highlights the conclusion based on the analysis which shows that the proposed project can
be categorized as low impact.
22
2 Project description
2.1.1 History
During the period of King Tarasingh (the 8th generation from Raja Anup Singh) this area
progressed very much. At that time the area was known for Ayurvedic medicine and for
business by boats in northern India.
In 1857, during the first war of independence the town of Anupshahr was the scene of
incidents against British rule. One message of revolution was carried
from Aligarh toBulandshahr by Pandit Narayan Sharma on 10 May 1857.
The Gujjars of Dadri and Sikandrabad destroyed inspection bungalows, telegraph offices
and government buildings as they were symbols of foreign rule. Anupshahr is also known
“Choti Kashi”as it is situated at the river bank of Ganges.
Anupshahr is a major town in distt. Bulandshahr UP. It is located 115 km away from Delhi,
95 km away from Noida, 75 km away from Greater Noida, 55 km away from Aligarh and 40
KM away from Bulandshahr.
Transport
There is no rail connectivity. To reach through rail one has to deboard at Dibai 22 km away
from the city.
23
This city is full of cultural and historical heritage. It is located on the bank of Holy River
Ganga, thousands of people take holy bath in River Ganga through Anupshahr Ganga
Ghat.In historical background Great Maharshi Dayananda Saraswati visited this place in 18th
century to raise awareness against various social evils present in the society at that time.
This city also have strong educational
infrastructure that's why it is also
known as "choti kashi".Anupshahr
has leading schools like "LDAV,
JAYPEE VIDYA MANDIR” and State
renowned "Durga Prasad Baljit Singh
PG College" and newly opened
"JAYPEE UNIVERSITY".
Figure 1 Tapped Nala Two state highways are providing
smooth connectivity to the city to other parts of UP. Bridge over Ganga provides a quick
connectivity to the area from northern parts like Bandaun, Moradabad etc.
The drainage system of the town is also Figure 2 Overflow of Nala falling into the river
24
2.1.4 Works Completed under Ganga Action Plan Phase - II (GAP-II)
3 towns namely Bijnore, Anupshahar and Chunar have been taken up under the GAP (Phase-
II) on the direction of Hon'ble Supreme Court of India. A total of 21 mldwaste water
discharging in the river Ganga is proposed to be intercepted, diverted and treated in these
towns. For this purpose 3 nos. STPs are proposed to be constructed.
A total of 17 schemes proposed for these towns, 10 schemes costing Rs. 12.74 crores have
been approved by Govt. of India, out of which works of 4 schemes have been completed
and an expenditure of Rs. 4.53 Crore has been incurred up to the end of December 2005.
25
The existing location of STPs is marked in the plan shown below.
26
27
Figure 4STP-I, Zone-A, 0.805 MLD Figure 5STP-II, Zone-B, 1.75MLD
Anupshahar town doesn’t have a sewerage network system. However, under Ganga Action
Plan-I, Nala tapping was done by intercepting the flow and diverting it into two nos. of
sewerage treatment Plants of 1.75 MLD and 0.805 MLD capacity respectively.
A proposal was issued by the Nagar Parishad on dated 02-01-2013 regarding sewerage
scheme of the town, which specifies that sewerage network has to be laid on the internal
roads has to be provided for the interconnections between the manholes used for tapping
nalas at the river bank so to avoid the overflow of waste water.
At present only the flow of Nalas is tapped and diverted to STP and treated water is
discharged into the River Ganga. However in the rainy seasons and the peak flow period
(Mela period) these 250mm sewer lines are collapsed and the overflow of the waste water
creates the unhygienic conditions for the people residing in the area.
Due to rapid urbanization and for better hygienic and sanitary conditions to improve living
standards sewerage networks along with related facilities are strongly required.
Also Anupshahr is the priority town as it lies on the bank of River Ganga and this river is the
sacred river for the Hindus. Pilgrims from many parts of the country in large quantity used
to visit this place for tasking holy dip in River Ganga, stay in the town and uses the facilities
of this town.
28
Therefore, there is a need of properly designing/constructing the sewer network and
appurtenant works in accordance with the current scenario.
The town is divided into two zones as zone-A and zone-B. The zoning is done in accordance
with the topography of the area. It is proposed that the wastewater generated from zone-A
will be directed towards the STP situated in zone-A with the existing capacity of 0.805 MLD
and similarly, the wastewater generated from zone-B will be directed towards STP in zone-B
with the existing capacity of 1.75 MLD.
The town possesses a tent shape profile as per the ground profile which helps the flow of
wastewater easily discharging into respective STPs in each zone.
The STP condition is fine as the year of construction of the STPs is 2005, the combined
capacity of the two existing STP’s equals to 2.55 MLD. This treatment capacity holds short
for the current discharge quantity and ultimately for the future discharge also. However no
extra land will be required for the construction of STP.On the basis of the discussion with
the Nagar Palika officers and staff, it was concluded that due to insufficient capacity of
existing treatment plants and pumping plants, there is a need of increasing the STPs
capacity.
However, the technology adopted for the treatment of waste water is MBBR Technology as
current i.e. Moving Bed Biofilm Reactor, but only the numbers of tanks are increased to
accommodate all the additional waste water which was flowing into the River Ganga directly
without any treatment from the STPs.
29
The total quantity of waste water generated in different wards for future years is
summarized below:
Zone wise wastewater generation for projected years (i.e. 2018, 2028, 2033 and 2048) in
MLD
Zone-A:
Zone-A comprises of 12 wards of which some portion of 4 wards lies in Zone-B also. The
details of ward wise population for Zone-A for the year 2018, 2028, 2033 and 2048 is shown
in the tabular form:
Zone-B:
30
Zone-B comprises of 13 wards of which some portion of 4 wards lies in Zone-B also. The
details of ward wise population for Zone-A for the year 2018, 2028, 2033 and 2048 is shown
in the tabular form:
The technology to be used in both the STPs will be MBBR (Moving Bed Biofilm Reactor)
which is very different from the WSP at present in operation at site. However, this
technology is most feasible for the small towns as this is cost effective&the capacity can be
easily upgraded in available land.
31
Design Parameters for STP
The proposed augmented capacities of both the STPs worked out are presented below in
the tabular form:
The outlet pipes will off shoot from various spots to irrigate the fields and for afforestation.
The land available around the STP area is adequate enough for 100% utilization of treated
32
effluent. Besides above it is also proposed to use the treated effluent in the area proposed
for afforestation in the STP site and nearby. In the rainy season the treated effluent may
have to be discharged in to the river Ganga.
The total area to be irrigated in Zone A is 15 hectares approx. and in zone B it is 12 hectares
approx. The plan of utilizing the treated waste water for next 10 years is presented in Table
4 below.
However, the total length of network laid for the irrigation supply in Zone-A is 200m and for
Zone-B is 200m.
As per the public consultation conclusions with the people, it was observed that people will
use the treated effluent for irrigating their fields.
Govt. of India has made it desirable that at least 20 % of treated wastewater should be
raised in any form. In this case, in the absence of industries in the nearby vicinity, it is
proposed to utilize waste water for the horticulture purposes, gardening or other possible
uses to the maximum extent, if any.
It is proposed to utilize all treated wastewater for agriculture in all seasons except monsoon,
for meeting the requirement of agriculture, necessary channels and pumping, if required
shall be proposed in DPR.
The treated wastewater is very rich in terms of nutrients such as Nitrogen, Phosphorus.
Therefore, it shall be proposed to utilize it as a resource for agriculture.
33
34
2023 2028
2023 2028 Year 1 2 3 4 5 6 7 8 9 10
2.09 2.27 % 10 15 25 30 50 60 75 80 90 100
1.67 1.81 Available Treated Water in MLD 0.167 0.251 0.418 0.501 0.835 1.088 1.360 1.451 1.632 1.814
Available Treated Water in Lts 167080 250620 417700 501240 835400 1088160 1360200 1450880 1632240 1813600
Area to be irrigated, Sqm 15000 22500 37500 45000 75000 90000 112500 120000 135000 150000
Zone-A
Water Required for this area, Lts 75000 112500 187500 225000 375000 450000 562500 600000 675000 750000
Unit Cost INR 2.25 2.25 2.25 2.25 2.25 2.5 2.5 2.5 2.5 2.5
35
Diverted to River Ganga, Lts 92080 138120 230200 276240 460400 638160 797700 850880 957240 1063600
Revenue fro Sale of Water, INR/Day 168750 253125 421875 506250 843750 1125000 1406250 1500000 1687500 1875000
The construction of a wastewater treatment plant will involve building large embankment
structures on what is a green field site. This will result in a loss of the options for alternative
land use and thus represents an irreversible commitment of land resources.
Although the loss of optional uses for the land in the future is considered to be a negative
impact, in this case the land is marginal in terms of alternative agricultural or residential use
and the impact is not considered significant.
Earth materials needed for construction (e.g. marl, sand) are normally obtained from quarry
and mining operations. Conscious or unwitting purchase of these materials from unlicensed
operations indirectly supports, encourages and promotes environmental degradation at the
illegal quarry sites and causes medium to long-term negative impacts at source.
Mitigation:
Earth materials must be obtained from officially licensed and approved quarries and copies
of the relevant licenses made available for inspection at the site by the Contractor.
3. Materials transportation
The various materials required for pond and building construction (e.g. steel, blocks,
lumber, marl, etc.) will be obtained from sources elsewhere and transported to the site.
Transportation of these materials, typically in over-laden and sometimes uncovered trucks,
usually results in undue road wear-and-tear. In the case of fine earth materials, dusting and
spillages occur on major roadways between source and site. Dusting degrades local air
quality and material spillages worsen driving conditions and increase the risk of road
accidents. These occurrences represent indirect, short-term, reversible, negative impacts on
public health and safety.
36
Mitigation:
All fine earth materials must be enclosed during transportation to the site to prevent
spillage and dusting. Trucks used for that purpose should be fitted with tailgates that close
properly and with tarpaulins to cover the materials. The cleanup of spilled earth and
construction material on the main roads should be the responsibility of the Contractor and
should be done in a timely manner (say within 2 hours) so as not to inconvenience or
endanger other road users. These requirements should be included as clauses within the
contracts made with relevant sub-contractors.
The transportation of lubricants and fuel to the construction site should only be done in the
appropriate vehicles and containers, i.e. fuel tankers and sealed drums. As far as possible,
transport of construction materials should be scheduled for off-peak traffic hours. This will
reduce the risk of traffic congestion and of road accidents on the access roads to the site.
4. Materials storage
The improper siting of stockpiles and storage of sand, gravel, cement, etc., at the
construction site could lead to fine materials being washed away, during heavy rainfall
events. This would not only represent a waste of materials but would also contribute to
turbidity and sedimentation with consequent negative impacts on water quality.
Refueling and maintenance of large vehicles and earth moving equipment will take place at
the construction site and therefore fuel and lubricants will have to be stored on the site.
This will create the opportunity for accidental spills of hydrocarbons and contaminants
could be washed into the river.
Mitigation:
The stockpiling of construction materials should be properly managed and controlled. Fine-
grained materials (sand, marl, etc.) should be stockpiled away from surface drainage
channels and features.
Low berms should be placed around the piles and/or tarpaulin used to cover open piles of
stored materials to prevent them from being washed away during rainfall. Safe storage
37
areas should be identified and retaining structures put in place prior to the arrival and
placement of material. Hazardous chemicals (e.g. fuels) should be properly stored in
appropriate containers and these should be safely locked away. Conspicuous warning signs
(e.g. ‘No Smoking’) should also be posted around hazardous waste storage and handling
facilities.
Mitigation:
Solid waste generated during site preparation and construction work would include cut
vegetation and typical construction waste (e.g. wasted concrete, steel, wooden scaffolding
and forms, bags, waste earth materials, etc.). This waste would negatively impact the site
and surrounding environment if not properly managed and disposed of at an approved
dumpsite. Cleared vegetation burnt onsite would generate smoke, possibly impacting
negatively on ambient air quality and human health. Vegetation and solid waste, if allowed
to accumulate in drainage ways, could cause localized pooling and flooding. Pooling of
water, in turn, would create conditions conducive to the breeding ofnuisance and health-
threatening pests such as mosquitoes. Poor construction waste management constitutes a
short-term negative impact.
Mitigation:
38
Vegetation and combustible waste must not be burned on the site. Reusable inorganic
waste (e.g. excavated sand) should be stockpiled away from drainage features and used for
in filling where necessary. Unusable construction waste, such as damaged pipes, formwork
and other construction material, must be disposed of at a dumpsite.
Inadequate provision of toilets for use by workers can lead to ad hoc defecation in secluded
areas on the site, thus creating unsanitary conditions and sources of fly infestation.
Improper disposal of food cartons and other domestic forms of construction camp garbage
could lead to littering of the site and pollution of adjacent water body.
Mitigation:
Proper solid waste receptacles and storage containers should be provided, particularly for
the disposal of lunch and drink boxes so as to prevent littering of the site.
Arrangements should be made for the regular collection of litter and for its disposal.
Landscaping and replanting of trees will be needed to recreate some semblance of the
original appearance and condition of the site and to provide some aesthetic quality. No
details of landscaping plans or planting material are available at this stage but the plant
species selected for replanting will in large part determine which types of birds, butterflies,
and other fauna, if any, inhabit the area surrounding the ponds after their construction. In
addition to enhancing the aesthetic appeal of the project site, landscaping provides the
means for partially restoring the site's natural elements and ecological habitats. It is
therefore a significant mitigation activity with a positive impact.
The landscaping plan should seek to avoid the use of non-native and potentially invasive
species. It should include low-maintenance local species and the types of trees and shrubs
used for feeding by local bird species. The landscape design should seek to encourage bird
life, especially for the endemics, and maximize shade.
39
9. Employment/Income generation
Several categories will be required during the construction phase. This will include skilled
and unskilled labourers, engineers, and a small number of other professionals. These levels
of short-term employment would have a positive impact on the local economy and on
regional unemployment.
Considering the land requirement of 0.3 Ha/mld for the STP, the land requirement is
calculated. The following land requirement is to be fulfilled to accommodate all the
components of the project for the ultimate year 2048 is presented below:
The land available with the local authorities in Anupshahr town for the STP purposes is
confined to the boundaries of the existing STPs; no additional land will be provided other
than the land available in the STP campus.
The ULB has cleared this with the issue of letter in this regard and the same is attached as
the Annexure 15 to this report.
No land has to be purchased for the construction of new SPS of larger capacity in zone-A &B;
this will be located very close to the existing SPS.
40
2.5.1.2 Land Acquisition
The land required for STPs and MPSs is already in possession of EA, there for acquisition of
land is not required to be done. There is no encroachment in the available land for
construction of STPs and MPSs at Anupshahar.
Ganga stretch at Brijghat to Narora is Ramsar site, the divisional director, deptt. Of forest
vide his letter no.439/14 dated Bulandshahr,july 26,2014 intimated that area in above said
stretch 1500 m on both banks of river Ganga is Ramsar site. But, at present, management
plan is under preparation by department of forest.
41
2.5.1.4 Sewerage Network
The sewage network is designed to be laid down in the town considering the peak
factor of 2.5; the total estimated length of sewage network is likely to be 60
kms(approx.). The length of pipes posing different diameters is presented in the
tabular form.
The largest pipe dia. used in the design consideration is 600 mm and the minimum pipe dia.
is 150 mm. The network drawing of sewerage scheme along with the discharge calculations
and the design sheets are attached herewith:
2.5.2 Manhole
The channels in manholes at junctions and bends shall be smooth with gradual transitions to
avoid turbulence and deposition of solids. Manholes are usually constructed directly over
the line of the sewer. They are circular, rectangular or square in shape. Manholes should be
of such size that will allow necessary cleaning and inspection. The circular manholes have
been proposed on all sewer lines. Poly elastomeric M S flats footrest has been provided for
entry into manholes.
All pipe and fittings shall be inspected prior to lowering into trench to insure no cracked,
broken, or otherwise defective materials are being used. The Contractor shall clean ends of
pipe thoroughly and remove foreign matter and dirt from inside of pipe and keep clean
during and after laying. Proper implements, tools, and facilities shall be used for the safe
and proper protection of the WORK. Pipe shall be lowered into the trench in such a manner
as to avoid any physical damage to the pipe. Pipe shall not be dropped or dumped into
trenches under any circumstances
Laying of sewer pipe shall be accomplished to line and grade in the trench only after it has
been dewatered and the trench has been prepared in accordance with specifications
outlined in DPR. Mud, silt, gravel and other foreign material shall be kept out of the pipe
and off the jointing surface. All pipe laid shall be retained in position so as to maintain
alignment and joint closure until sufficient backfill has been completed to adequately hold
the pipe in place. All pipes shall be laid to conform to the line and grade shown on the plans.
44
Variance from established line and grade, at any point along the length of the pipe, shall not
be greater than one-thirty second of an inch per inch of pipe diameter and not to exceed
one-half (½) inch, provided that any such variation does not result in a level or reverse
sloping invert.
Plugs for pipe branches, stubs or other open ends which are not to be immediately
connected shall be made of an approved material and shall be secured in place with a joint
comparable to the main line joint.
· Top soil may be used for agricultural purpose or development of city parks.
· Soil and debris may be managed for planned land filling and landscaping;
· Debris may be suitably stored to filling back the excavated areas after placing the
trunk sewer lines.
45
2.5.7 IMPLEMENTATION SCHEDULE
It is anticipated that entire work will be completed within 42 months from the date
of approval and allotment of funds.
FORM-'J'
Total GOI GOUP
Percentage
c Description Cost Share Share
Charges
of Works 70% 30%
1 2 3 4 5 6
1 Base cost of work 6587.988 4611.592 1976.396
2 Centage charges:
2.1 Project Preparation Charges 4 263.520 184.464 79.056
2.2 Project Supervision Charges 4 263.520 184.464 79.056
A Sub Total (1+2) 7115.027 4980.519 2134.508
3 Items on which no centage is admissible:
3.1 ESAMP 70.490 49.343 21.147
3.2 Communication and Public Outreach 20.000 14.000 6.000
3.3 GAAP 10.000 7.000 3.000
3.4 Power Connection 23.020 16.114 6.906
3.5 Operation and Maintenance cost for 5 years 340.000 238.000 102.000
B Sub Total (3) 463.510 324.457 139.053
C Project Cost (A+B) 7578.537 5304.976 2273.561
4 Component of works to be borne by GOUP
4.1 T&P for Operation and Maintenance 31.000 31.000
4.2 Cost of land 170.00 170.00
4.3 Contingencies on Rs. 6618.99 lac 2 132.380 132.380
4.4 Labour Cess on Rs 6618.99 lac 1 66.190 66.190
4.5 Centage @ (12.5-8) on Rs 6618.99 lac 4.5 297.855 297.855
D Sub Total (4) 697.424 697.424
Total cost of works (C+D) 8275.961 5304.976 2970.985
Say Rs. 8275.96 Lac
46
3 Approach and Methodology
As per Environmental and Social Management Frame work (NGRBA, 2011), the river
pollution mitigation projects under the NGRBP is anticipated to encounter a variety of
environmental and social problems. Hence, an environmental and social assessment with
corresponding management plans for the proposed project of sewerage works in Anupshahr
has been conducted using the following methodology:
Figure 7 Flowchart describing the steps adopted for Project Impact Assessment
48
from those with significant impacts and get a broad picture of the nature, scale and
magnitude of the issues. Team conducted screening process using the screening
checklist format provided in ESMF report of NGRBA, which is described in
subsequent section.
G. Identify and assess the impacts : Based on the analysis of the data gathered from
field survey, stakeholder interaction/ consultation and secondary sources, issues
related to the environmental and social sectors were been identified. The impacts so
identified were compared with the existing baseline environmental and social
condition of the study region. The impacts of the activities are mostly positive with
few adverse impacts.
H. Develop a mitigation plan: Based on the environmental and social issues identified,
and recommend any measures needed to prevent, minimize, mitigate, or
compensate for adverse impacts and improve environmental performance. The
mitigation plans is suggested in all three stages: designing phase, construction phase
and, operation and maintenance phase.
49
Table 6Screening Activity
Project location (Area/ district): Anupshahr Town Distt. Bulandshar, Uttar Pradesh
Assessment of
Screening Criteria category Explanatory note for categorization Evidence and references
(High/low)
1. Is the project in an eco-sensitive area or Yes, the Project is located in eco-sensitive
adjoining an eco-sensitive area? zone but, Anupshahr and around area is not
(Yes/No) protected under wildlife protection act
If Yes, Which is the area? 1972. However the Ganga river stretch
Elaborate impact accordingly. between Brijghat to Narora Barrage falls
High under RAMSAR site. Anupshahr is situated
on the bank of river Ganga within this
stretch. The proposed sewerage project
ensures 50% reuse of treated sewage and
over a period of time targeted to reuse of
100% of treated sewage.
2.
Will the project create significant/limited/no social impacts?
Land acquisition resulting in loss of income Sewer line would be laid on the public Refer Section 2.4
from agricultural land, plantation or other No impact roads. So there is no loss of income from
existing land-use. agricultural land.
Assessment of
Screening Criteria category Explanatory note for categorization Evidence and references
(High/low)
· For the construction of MPS in both
the zones land is available with nagar
Palika
· STP in Zone A and Zone B will be
constructed in the old campus.
Loss of livelihood would not take place since
mobile vendors can shift their position and
Loss of livelihood No Consultation with stakeholders)
only minor/temporary disruption in terms
of access to shops would occur
Google image showing the
Land acquisition resulting in Relocation of No social Land acquisition is not required. Relocation
location of STP components is
households. impacts of households is not required.
enclosed as DPR
Any reduction of access to traditional and
Field visits and consultations with
river dependent communities (to river and No social
No access problem to river the shop keepers, expert
areas where they earn for their primary or impacts
opinions
substantial livelihood).
Any displacement or adverse impact on tribal No social There are no tribal settlements in the Field visits and consultations with
Settlement. impacts project area. the shop keepers.
Will the project create significant / limited / no environmental impacts during the construction stage? (Significant / limited / no impacts)
No Sewer line will be laid on existing public Topographical map showing
Clearance of vegetation/ tree cover environmental roads therefore no cutting of trees will be roads and other features is
impacts done. enclosed as Annexure 11
Possibility of temporary flushing away of
Direct discharge of construction runoff, unmanaged spoils and construction wastes Interaction with UP Jal Nigam
improper storage and disposal of excavation during rainfall to river Ganga via storm and other
spoils, wastes and other construction Limited water drains. Government officials and
materials adversely affecting water quality If not appropriately managed, there may be consultation with local residents
and flow regimes. potential for temporarily affecting storm of town
water flows by obstruction to flows and
51
Assessment of
Screening Criteria category Explanatory note for categorization Evidence and references
(High/low)
blockage of drains, especially during rainfall.
As per departmental orders excavation of
trenches for laying of sewers in not taken up
during rains. However, in case of urgency if
U.P. Jal Nigam circular dated
Flooding of adjacent areas no sewer is needed to be laid during monsoons,
17/6/2013.
stockpiled areas to be bordered by berms. As
such there should be no flooding of adjacent
areas.
Improper storage and handling of substances The storage of construction related material Image showing a typical sewage
will not cause any contamination since these
leading to contamination of no construction area is enclosed as
materials would typically include: Concrete,
soil and water pipes, masonry, HDPE pipes. Annexure 6
For sewage works, construction is likely to
increase dust and noise levels temporarily.
55
3.2 Conclusion of Screening Activity
In order to facilitate effective management and mitigation of the any impacts arising from
the proposed projects, the Environmental and Social Management Framework of NRGBA
(Section # 4 of ESMF report, NGRBA 2011) has grouped the pollution abatement projects/
investments into the following two categories high and low
• High: Mainly include the sub-projects which are likely to have adverse impact on the
environmental and social aspects of the project influence area (including land acquisition).
This category projects will also include mandatory environmental clearance as per the EIA
notification.
• Low: Projects which are likely to cause minimal or no adverse environmental impacts
on human populations.
Based on the screening activity and the categorization of potential sub-projects of the
NGRBP, the present project of Sewerage work in Anupshahr town falls under High impact
category being located in Ramser Area, which however does not have any private land
acquisition. In view of the above, these projects would require preparation of an
Environmental and Social Assessment, as part of the DPR, and implementation of Generic
Safeguard Management Plan (SMP), relevant to the project.
Although there would not be any permanent negative or adverse environmental impacts,
but will have temporary impacts like traffic blockages, dust, noise, safety hazards for
pedestrians, possible damage to private property, possible interruption in commercial
activity, and accidental breakage of other public infrastructure such as water pipes. These
temporary impacts can be mitigated with appropriate mitigation plans. However, the large
environmental benefit of the project greatly outweighs the temporary inconveniences.
4 Regulations and Legal Framework
The following laws and regulations are applicable to the environmental and social aspects of
the investments implemented under the programme:
The Government of India has laid out various policy guidelines, acts and regulations
pertaining to environment. The Environment (Protection) Act, 1986 is umbrella legislation for
the protection of environment. As per this Act, the responsibility to administer the legislation
has been jointly entrusted to the Ministry of Environment and Forests (MoEF) and the
Central Pollution Control Board (CPCB)/ State Pollution Control Boards (SPCBs).
It is worthwhile to mention here that as a matter of prevalent practice once the project is
approved by the G.O.I no further consent of SPCB is obtained for establishing the STP.
However, SPCB regularly monitors the effluent parameters during O &M stage to ensure that
the discharged effluent is as per prescribed standards. However, as desired by NMCG, action
to obtain NOC from SPCB for establishing STP has been initiated. The regional officer UP
Pollution Control Board Shivpuri Bulandshahar has forwarded the case of issuing NOC by UP
Pollution Control Board to the Chief Environmental Officer UPPCB Lucknow after the UP Jal
Nigam submitted the required NOC fees & the desired application to UPPCB Bulandshahar
57
4.1.2 Key Environmental Laws and Regulations
The key environmental laws and regulations as relevant to the projects under the NGRBP are
given in Table below. The key environmental regulations can also be accessed at
www.moef.nic.in/rules-and-regulations.
All strategic interventions on human development, spread across all social issues, need
directives of policies and legal support to operationalize the appropriate actions. These
policies and legislations help to overcome the constraints and support administrator,
implementer, community and individual in delivery of justice. This section includes the
National policies and Acts as detailed under:
Regulatory Protection
· Protection and vesting of rights of STs on forestlands and other forest rights including
ownership over minor forest produce (MFP), minerals and water bodies through
appropriate legislations and conversion of all forest villages into revenue villages.
60
However, This act is not applicable for this project.
4.2.2 The right to fair compensation and transparency in land acquisition, rehabilitation
and resettlement act, 2013
• Makes a beginning towards giving communities and the public a voice in forest and
wildlife conservation.
61
No. as
1Land Owner – whose land and immovable property acquired and land assigned by state or central govt under
any scheme (Section 3 c (i) and (v))
62
loss of assets or access to
assets, loss of income
sources or means of
livelihood
Widows, divorcees,
abandoned women will be
considered as separate
family.
63
by acquisition.
64
appraise SIA and Group include members of
SIMP decentralized govt Institutes
(PRIs, ULBs).
11. Time stipulated Before the decision meeting Section 7(4): Submit its
for Group to for appraisal report within two months
submit its report from the date of its
constitution
65
15. Minimize impact Select feasible design that Section 10: In case multi-
on multi-crop land has minimal adverse crop land is to be acquired
impact. under exceptional
circumstances, the area to
be acquired cannot exceed
aggregate of land of all
projects in district or state.
The area to be acquired
cannot exceed the total net
sown area of the district or
state.
Wasteland equivalent to
twice the area acquired will
be developed.
16. Information Continuous part of the Section 11 (1), (2) & (3):
dissemination of preparation and Notice published in local
preliminary notice participation language and meetings
called of gram sabahs,
municipalities to provide
full information about the
purpose of the project,
summary of SIA and
particulars of administrator
appointed for R&R’
summary of R&R scheme
18. Census and To be part of RAP Section 16 (1) (2): carry out
preparation of census of affected people
R&R schemes and their assets to be
affected, livelihood loss and
66
common property to be
affected; R&R scheme
including time line for
implementation.
21. Final declaration Approved RAP including Section 19 (2): Only after the
of R&R Scheme budgetary provisions to requiring body has
implement it deposited the money will
the govt issue the notice
along with 19(1).
67
notice issued.
68
applicable years ago but land not taken
in possession or where
award declared but money
not deposited in the account
of majority of beneficiary.
30. R&R Award Total cost included in RAP Section 31, Second Schedule:
to resettle and rehabilitate A family as a unit will
the affected persons and receive R&R grant over and
assist in their efforts to above the compensation
improve their livelihoods and those who are not
and standards of living or at entitled to compensation.
least to restore them, in real
Second Schedule: Homeless
terms, to pre-displacement
entitled to constructed
levels or to levels prevailing
house, land for land in
69
prior to the beginning of irrigation projects in lieu of
project implementation, compensation, in case of
whichever is higher acquisition for urbanization
20% of developed land
reserved for owners at a
prices equal to
compensation’ jobs or one
time payment or annuity for
20 years’ subsistence grant,
transportation, land and
house registered on joint
name husband and wife, etc
38. Possession of land Taking of land and related Section 38(1): Land will be
assets may take place only taken over by the
after compensation has been government within three
paid and, where applicable, months of compensation
resettlement sites and and 6 months of R&R
moving allowances have benefits disbursed;
been provided to the infrastructure facilities at
displaced persons. resettlement sites will be
completed within 18
months from the date of
award made under section
30 for compensation; in case
of irrigation and hydle
projects R&R completed six
months prior to
submergence.
70
will be paid to displaced
71
Second Schedule: additional
provisions for SC&ST for
land for land in irrigation
projects, additional sum
over and above the
subsistence grant,
72
39. No change in Section 99: Once the land is
status of land acquired for a particular
acquired purpose, its purpose cannot
be changed
Construction stage generally involves equity, safety and public health issues. The
construction agencies therefore will be required to comply with laws of the land, which
include inter alia, the following:
1. Workmen's Compensation Act 1923 (the Act provides for compensation in case of injury by
accident arising out of and during the course of employment);
2. Payment of Gratuity Act, 1972 (gratuity is payable to an employee under the Act on
satisfaction of certain conditions on separation if an employee has completed 5 years);
3. Employees PF and Miscellaneous Provision Act 1952 (the Act provides for monthly
contributions by the employer plus workers);
4. Maternity Benefit Act, 1951 (the Act provides for leave and some other benefits to women
employees in case of confinement or miscarriage, etc.);
73
5. Contract Labor (Regulation and Abolition) Act, 1970 (the Act provides for certain welfare
measures to be provided by the contractor to contract labour);
6. Minimum Wages Act, 1948 (the employer is supposed to pay not less than the Minimum
Wages fixed by the Government as per provisions of the Act);
7. Payment of Wages Act, 1936 (it lays down as to by what date the wages are to be paid,
when it will be paid and what deductions can be made from the wages of the workers);
8. Equal Remuneration Act, 1979 (the Act provides for payment of equal wages for work of
equal nature to Male and Female workers and not for making discrimination against Female
employees);
9. Payment of Bonus Act, 1965 (the Act provides for payments of annual bonus subject to a
minimum of 83.3% of wages and maximum of 20% of wages);
10. Industrial Disputes Act, 1947 (the Act lays down the machinery and procedure for
resolution of industrial disputes, in what situations a strike or lock-out becomes illegal and
what are the requirements for laying off or retrenching the employees or closing down the
establishment);
11. Industrial Employment (Standing Orders) Act; 1946 (the Act provides for laying down
rules governing the conditions of employment);
12. Trade Unions Act, 1926 (the Act lays down the procedure for registration of trade unions
of workers and employers. The trade unions registered under the Act have been given
certain immunities from civil and criminal liabilities);
13. Child Labour (Prohibition and Regulation) Act, 1986 (the Act prohibits employment of
children below
14 years of age in certain occupations and processes and provides for regulation of
employment of children in all other occupations and processes. Employment of child labour
is prohibited in Building and Construction Industry);
74
14. Inter-State Migrant Workmen’s (Regulation of Employment and Conditions of Service)
Act, 1979 (the inter-state migrant workers, in an establishment to which this Act becomes
applicable, are required to be provided certain facilities such as housing, medical aid,
travelling expenses from home to the establishment and back, etc.);
15. The Building and Other Construction Workers (Regulation of Employment and Conditions
of Service) Act, 1996 and the Cess Act of 1996 (all the establishments who carry on any
building or other construction work and employs 10 or more workers are covered under this
Act; the employer of the establishment is required to provide safety measures at the building
or construction work and other welfare measures, such as canteens, first-aid facilities,
ambulance, housing accommodation for Workers near the workplace, etc.);
16. The Factories Act, 1948 (the Act lays down the procedure for approval of plans before
setting up a factory, health and safety provisions, welfare provisions, working hours and
rendering information-regarding accidents or dangerous occurrences to designated
authorities);
75
issues during the preparation stages of the sub-project, and to design interventions to
address women’s needs. Gender analysis will be part of the social assessment at the sub-
project level. The RPLAF, has a screening checklist to identify any adverse impact. The
project has also prepared an entitlement matrix to address the adverse impacts as given
below. The entitlement matrix is based on NPRR 2007 .
76
5 Baseline Status
The baseline environmental and social status is important to understand the region's
existing physical and biological characteristics along with cultural and social status of the
residing community. Information and data presented in this section is based on field
surveys, stake-holder interaction/consultation and secondary data collection which majorly
include the draft Detailed Project Report (DPR) of proposed sewerage work in Anupshahr
town, Baseline generation (Water/ Air/ Noise quality/ Soil monitoring) ,town census data
and others. The information on the baseline environmental conditions forms the basis to
analyses the probable impacts of the proposed project vis-à-vis the present background
environmental quality of the core study area.
The topography of the town is generally plain & slopes towards river Ganga. The huge water
body formed upstream of the barrage houses the dolphins. Upper Ganga stretch of the river
from Bijnor to Narora (165 km) is home to dolphins & forms a part of the RAMSAR Site.
WWF India has been working closely since late nineties with river bank communities and
aquatic species that could serve as a reliable indicator of the health of Ganga River. While
different strategies have been adopted by them from time to time, the focus has always
remained on the people & species.
The goal being to reduce the huge burden of pollution & other anthropogenic pressures that
Ganga River has borne particularly in the last few decades. The dolphin’s habitat parameters
in Ganga River with active participation of WWE (India) and based on their study during 2007-
2009, the population of dolphins in the study area between Bijnor and Narora was recorded
to have increased .The population of dolphins in the study area was recorded to have increase
(44 in 2007; 49 in 2008; 56 in 2009) during the project period (2007-2009). This signifies that
77
the recruitment and growth pattern on the population is increasing. This is most likely
because of the improvement in habitat conditions, as well as in the water quality. A decrease
in the death rate between 2007-2009 could also be a factor as of death was recorded in this
stretch.
Narora –Anupshahr (Zone I) 0-30 Deep pools, sandy and muddy river bank
island with vegetation
ph 7.05-8.70
The total dolphin population in upper Ganga system up to October 2012 was 671 with
following distribution. Ganga-261, Yamuna -31, Chambal-85, Ghaghara-231, Rapti-8, Geruwa-
39, Saryu-16. The distribution of total dolphin population is shown in figure below.
78
Figure 8Distribution of Dolphin in Upper Ganga System population up to October 2012 (source WWF)
5.1.2 Climate
The town has very hot climatic conditions in summers, the temperature rises up to 40
degrees Celsius and chilling winter is common. It receives heavy rainfall for three to
four months within a year. Source: http://www.climate-data.org
79
Figure 10 Temperature Variation & Precipitation
80
Figure 11 Annual Rainfall
81
5.1.3 Land Use Pattern
According to the land use data of 2004-05, the net area sown and current fallow land was
estimated at 298371 ha. (81.75 per cent) and 2456 (0.70 per cent) respectively of the total
reporting area in district Bulandshahr. The area under forest accounted for 7726 ha (2.12 per
cent). Land put to non-agricultural uses was estimated at 49710 ha. (13.62 per cent) and
uncultivable wasteland at 5111 ha.(1.40 per cent). Grazing land and area under trees and
82
orchards is negligible. The total reporting area covers 364974 ha. land in the district. It is
interesting to note that total reporting area of the district has decreased by 1.40 per cent
(5096 ha.). The forest area has also declined from 7726 ha, in 2004-05 to 7544 ha. in 2006-07
The net irrigated area in the district during 2004-05 was 263715 ha. which was 88.38 per
cent of the net area sown. Irrigation facilities are well developed in the district. The main
source of irrigation is private Tube wells which covers 220816 ha. land (84 per cent) of the
total net irrigated area. About 958 kms of canals and 199 canal tails provide irrigation to 10
per cent of irrigated area (25102 ha.) and wells account for 4.55 per cent area under
irrigation. States run Tube wells cover only 1.89 per cent area under irrigation
83
Water Quality Status
Although the Ganga flows along the entire length of the NCR fringing its eastern border, any
monitoring station has not been established. Apart from Garhmukhteshwar (Class III town),
Anupshahr (Class IV town) and Narora (Class IV Town), there are no major water pollution
issues in the Ganga Basin in this particular stretch.
The groundwater near Sewerage Treatment Plant present in zone A & B is more than 5m in
depth, which shows that ground water table there will not be polluted by the presence of
STP. As per survey and studies made, it is observed that in most part of the city the
groundwater is more than 5m.For sewer lines laid in regions having shallow depth,
infiltration factor has been considered.
Moreover, for every joints provision of sealant has been taken into account in order to
prevent intrusion of sewerage into ground water. Proper jointing and provision of cradles
has also been considered for preventing groundwater pollution.
84
Table 9Depth of Water below Ground level and its Hydro-geological Conditions in Anupshahr
Sub Ground
Region/Tehsil/Tow Land Water Hydro-Chemical
n Contour Contour Depth of Ground Water BGL Conditions
mts mts mts A B C D E
Anupshahr 185-200 195-190 10
85
5.1.5 Duration of Monitoring to generate the base line
The monitoring of air, water, soil, and noise quality was conducted during the month
of December 2014.
5.1.6 Meteorology
A meteorological station was set up at the project premises. Meteorological data was
generated during the 15 December 2013 to 15 January 2014.
The following parameters were recorded at hourly intervals continuously during monitoring
period is enclosed as Annexure8
· Wind speed
· Wind Direction
· Air Temperature
NORTH
20%
16%
12%
8%
4%
WEST EAST
WIND SPEED
(m/s)
>= 11.1
8.8 - 11.1
5.7 - 8.8
3.6 - 5.7
2.1 - 3.6
0.5 - 2.1
Calms: 29.05%
SOUTH
To quantify the impact of the project on the ambient air quality, it is necessary at first to
86
evaluate the existing ambient air quality of the area. To assess the ambient air quality
level, 4 (four) monitoring stations were set up. And one day monitoring has been done
i.e. 15/1/2014.
The existing ambient air quality has been monitored and 12 air parameters are analyzed
such as Particulate Matter-10 (PM10), Particulate Matter- 2.5 (PM2.5), Sulphur-dioxide
(SO2), Nitrogen Oxide (NO2), and Carbon Monoxide (CO), through a planned field
monitoring. All the parameters are within prescribed limit as per EPA.
The maximum concentration of Particulate Matter (PM10 &PM2.5) i.e. 73.4 & 47.65 µg
/m3 has been analyzed in AAQ4 (Near Nav Durga Medical Store) due to commercial place,
and minimum concentration is in campus of both the STPs.
The concentration of Sulphur Dioxide& Nitrogen Dioxide is high Near Bulandshahar Bus
Stand due to emission by huge vehicular traffic and minimum concentration is in campus
of both the STPs.
Similarly the concentration of Carbon Monoxide, Lead (as Pb), Nickel (as Ni), Arsenic (as
As), Ozone (as O3), Ammonia (as NH3), Benzene (as C6H6), Benzo(α) Pyrine- Particulate
Phase are also within the prescribed limit of EPA.Location map is enclosed as Annexure 2.
Fine particulate Sampler APM MFC550 was used for monitoring Particulate Matter (PM2.5
and PM10); gaseous pollutants like SO2, and NO2 was collected by Gaseous Pollutant
Sampler APM 433 and CO was monitored by Serinous 30 CO Analyser with NDIR detector.
87
Method for measurement of Particulate matter, SO2 & NO2
Method for measurement of Particulate Matter (PM10) in ambient air is done by Cyclonic
Flow Technique. Particles with aerodynamic diameter less than the cut-point of the inlet are
collected by a filter. Ambient air at the monitoring location is sucked through a cyclone.
Coarse and non-reparable dust is separated from the air stream by centrifugal forces acting
on the solid particles and these particles fall through the cyclone's conical hopper and get
collected in the sampling cap placed at the bottom. The fine dust (<10 microns) forming the
particulate matter (PM10) passes the cyclone and is retained on the filter paper The mass of
these particles is determined by the difference in filter weights prior to and after sampling.
The concentration of PM10 in the designated size range is calculated by dividing the weight
gain of the filter by the volume of air sampled. A tapping is provided on the suction side of
the blower to provide suction for sampling air through a set of impingers for containing
absorbing solutions for SO2 and NO2. Samples of gases are drawn at a flow rate of 0.2 liters
per minute. The APM MFC 550 is used for PM2.5. This system is a manual method for
sampling fine particles (PM2.5 fraction) and is based on Impactor designs standardized by
USEPA for ambient air quality monitoring.
PM2.5& PM10 have been estimated by gravimetric method. Improved West and Gaeke
method (IS-5182 part-II, 1969) has been adopted for estimation of SO2 and Modified Jacobs-
Hochheiser method (IS-5182 part-VI, 1975) has been adopted for the estimation of NO2.
88
Method for measurement of Carbon Monoxide – NDIR method
Instrument used: Ecotech Serinus 30 Carbon Monoxide
This analyzer is used to measure CO in ambient air, in the range of 0-200 ppm (220 mg/m3)
to a sensitivity of 0.05 ppm 55µg/m3). The Serinus 30 combines the benefits of Micro process
control with Non-Dispersive Infrared Spectrophotometry technology.CO Concentration is
automatically corrected for gas temperature and pressure changes.
89
Figure 17 Air Sampling
90 in progress
5.1.8 Noise Environment
Noise is one of the most undesirable and unwanted by-products of our modern life style. It
may not seem as insidious or harmful as air and water pollutants but it affects human health
and well-being and can contribute to deterioration of human well-being in general and can
cause neurological disturbances and physiological damage to the hearing mechanism in
particular. It is therefore, necessary to measure both the quality as well as the quantity of
noise in and around the site.
Methodology
The intensity of sound energy in the environment is measured in a logarithmic scale and is
expressed in a decibel, dB (A) scale. In a sophisticated type of sound level meter, an
additional circuit (filters) is provided, which modifies the received signal in such a way that it
replicates the sound signal as received by the human ear and the magnitude of sound level in
this scale is denoted as dB (A). The sound levels are expressed in dB (A) scale for the purpose
of comparison of noise levels, which is universally accepted by the international community.
Noise levels were measured using an Integrating sound level meter manufactured by Pulsar
Instruments Plc, Model NO. 91 (SL.No.B21625). It has an indicating mode of Lp and Leq.
Keeping the mode in Lp for few minutes and setting the corresponding range and the
weighting network in “A” weighting set the sound level meter was run for one hour time and
Leq was measured at all locations.
The day noise levels have been monitored during 6.00 am to 10.00 pm and night noise levels,
during 10.00 pm to 6.00 am at all the 5 locations, which covers residential areas, highways,
industrial areas, commercial areas, and silence zones, if available within 10 km radius of the
study area.
91
Sampling Locations
A preliminary survey was undertaken to identify the major noise generating sources in the
area. The noise survey was conducted to assess the background noise levels in different
zones. Gazettes Notification (S.O. 123(E)) of MoEF dated February 14, 2000 on ambient air
quality standards has different noise levels for different zones viz. project site, industrial,
commercial, and residential and silence zones.
In Anupshahr town the four locations has been identified for noise level monitoring in which
two are project sites and other two are commercial and silence zone the monitoring has
been done during day (6.00 Am to 10 Pm) and night (10:00 PM to 6:00 Am) both and after
analyzing the results, it is conclude that noise levels during day time and night are in
prescribed limit of CPCB.
Location code is given in table below and location map is enclosed as Annexure 3.
92
Table 11 Noise Ambient Quality
NAQ1 NAQ2 NAQ3 NAQ4 Requirement (as per CPCB Guidelines Limits in
S. No Test Parameters Results Results Results Results Units dB (A) Leq
EQUIVALENT NOISE dB(A) Category of Area/ Day
LEVEL 58.2 56.7 66.2 72.5 Zone Time Night Time
1 (6.0 AM TO 10.0 PM) Industrial Area 75 70
EQUIVALENT NOISE Commercial Area 65 55
LEVEL
2 37.7 38.4 42.1 46.4
(10.0 PM TO 6.0 AM) Residential Area 55 45
dB(A) Silence Zone 50 40
Figure 18 Noise Sampling
5.1.9 Water Environment
Water quality assessment is one of the essential components of EIA study. Such assessment
helps in evaluating the existing health of water body and suggesting appropriate mitigation
measures to minimize the potential impact from development projects.
The six samples have been drawn for water quality monitoring at STP inlet of both zone, STP
outlet of both Zones, Upstream of Ganga River and downstream of Ganga River with respect
to the discharge point of STPs.
At STP inlet five parameters have been analyzed i.e. which show the characteristics of waste
water in both the zones.
Similarly at STP outlet five parameters have been analyzed i.e. which show the
characteristics of treated water in both the zones
pH is (8.22-8.4), Total Suspended Solid (26-38), Chemical Oxygen Demand(as O2) (104-128)
, Biological Oxygen Demand(as O2) (20-24) and Oil & grease (2.2-2.6).
All the above mention parameters are within the prescribed limit of CPCB norms
95
Table 13 Water Quality at STP Outlet
As mention above samples are also drawn at Upstream and Downstream of Ganga River
with respect to the discharge points of STPs in both zones to assess the changes in water
quality of river due to discharge of waste water in river.
1. Microbiological
As per the requirement of IS 10500:2012 the concentration of Total Coliform
Bacteria & Fecal Coliform Bacteria should be absent/250 ml but due to discharge of
effluent at various point in upstream it comes around (520/100 ml & 180/100ml) and
similarly due to discharge of waste water of Anupshahr in river the same parameter
are changed at downstream of river i.e. (630/100 ml & 220/100ml).
96
3. General Parameters Concerning Substances Undesirable In Excessive Amounts
In upstream and downstream both Aluminum (as Al), Total Ammonia, Anionic
surface, Detergents (as MBAS), Barium (as Ba), Chloramines (as Cl2), Free Residual
Chlorine, Magnese (as Mn), Silver (as Ag), Sulphide(as H2S) are below the detection
limit. And Boron (as B), Calcium (as Ca), Chloride (as Cl), Copper (as Cu), Fluoride (as
F), Iron (as Fe), Magnesium (as mg), Nitrate (as NO3), Selenium (as Se), Sulphate (as
SO4), Alkalinity (as Ca CO3), Total hardness (as CaCO3), Zinc (as Zn) are below the
required acceptable limit.
MICROBIOLOGICAL REQUIREMENT
S.No. Parameter Test UP Stream Down Required as per IS-
Method Result Stream 10500:2012
Result
1 Total Coliform IS-1622 520/100ml 630/100 ml Absent/250ml
Bacteria
97
2 Odour IS- Agreeable Agreeable - Agreeable Agreeable
3025(P-
05)
3 Taste IS- Agreeable Agreeable - Agreeable -
3025(P-
07 & 08)
4 Turbidity IS- <1.0 <1.0 NTU 1 5
3025(P-
10)
5 pH value IS- 7.72 8.14 - 6.5-8.5 -
3025(P-
04)
6 Total IS- 144 346 mg/l 500 2000
dissolve 3025(P-
solid ( 16)
TDS)
98
General parameters concerning substances undesirable in excessive amounts
S.no. Parameter Test UP Down Unit Requirement Permissible
method Stream Stream (Acceptable Limit in
Result Result Limit) absence of
alternate
source
9 Copper (as IS : <0.05 <0.05 mg/l 0.05 1.5
Cu) 3025
(P-42)
10 Fluoride (as IS: 3025 0.29 0.17 mg/l 1 1.5
F) (P-60)
11 Free Residual IS: 3025 DL BDL mg/l 0.2 1
Chlorine (P-26)
100
Figure 19 Water Sampling Site Pics
101
5.1.10 Drainage System
The drainage system of the town is also very poor; the storm water is transported through
the common open drains along with domestic waste water. The condition worsens in the
rainy season and general problem of overflow of drains is encountered. The waste water
finds its way to low lying areas and creates unhygienic sanitary conditions.
Anupshahar town doesn’t have a sewerage network system. However, under Ganga Action
Plan-I, Nala tapping was done by intercepting the flow and diverting it into two nos. of
sewerage treatment Plants of 1.75 mld and 0.805 mld capacity respectively.
102
A proposal was issued by the Nagar Parishad on dated 02-01-2013 regarding sewerage
scheme of the town, which specifies that sewerage network has to be laid on the internal
roads has to be provided for the interconnections between the manholes used for tapping
nalas at the river bank so to avoid the overflow of waste water.
At present only the flow of Nalas is tapped and diverted to STP and treated water is
discharged into the River Ganga. However in the rainy seasons and the peak flow period
(Mela period) these 250mm sewer lines are collapsed and the overflow of the waste water
creates the unhygienic conditions for the people residing in the area.
Due to rapid urbanization and for better hygienic and sanitary conditions to improve living
standards sewerage networks along with related facilities are strongly required.
Also Anupshahr is the priority town as it lies on the bank of River Ganga and this river is the
sacred river for the Hindus. Pilgrims from many parts of the country in large quantity used
to visit this place for tasking holy dip in River Ganga, stay in the town and uses the facilities
of this town.
Waste generation is about 200 gms per capita per day in cities with the population of less
than 1 lac. The larger the city, the higher is the per-capita waste generation rate. The total
waste generation in Anupshahr town is estimated to be 48 metric tonnes per day at present
ie. year 2014. The type of solid waste generated in the town can be broadly classified into
Municipal Solid Waste, E-Waste, Plastic Waste, Construction and Demolition Waste,
Biomedical Waste
The solid waste management in Anupshahr town is handled by Nagar Panchayat Anupshahr.
The Nagar Panchayat has provided bins at different locations in the town where the local
inhabitants put their waste for transportation & disposal. Nagar Panchayat disposes of the
solid waste in the low lying areas of the town.
Composition of Waste:
103
Indian mixed waste has a large proportion of compostable material and inerts. As per NEERI
studies, compostable matters range from 30% to 57% and inert materials from 40% to 54%.
The component of recyclable material is between 5% to 10%.
During the span of festival/melas, the population of the town increases temporarily,
resulting in the increase of solid waste generation. At present, the only thing adopted to
cater this situation is increasing the number of trips of the transportation vehicles to the
dumping site. However no management plan is prepared for the particular span which
results in the collection of large amount of solid waste at the collection points for the longer
duration of time.
The solid wastes collected from 26 localities are dumped on the bypass road but this is
temporary location, final location has not been decided. Recyclable waste material is also
not segregated at source and is disposed of on the streets, along with domestic, trade and
other wastes. Construction and demolition wastes also pose a serious problem as these
wastes are also deposited on the roadside or open spaces, obstructing traffic and causing
nuisance.
Primary Collection
There is no system of primary collection of waste in the town. The waste thrown on the
streets is, therefore, collected from the streets and/or from the street bins, which are
inadequate in number and ill designed.
Open sites or cement concrete bins, metal bins, masonry bins and structures are used for
temporary bulk storage of wastes. These bins are very unhygienic and necessitate multiple
handling of wastes. Waste is more often seen outside the bins than inside them. They are
not cleared daily.
Street Sweeping
104
Street sweeping is not carried out regularly. Several streets are occasionally swept or are
not swept at all. No sweeping is done on Sundays and public holidays in many cities. The
tools used for street sweeping are also inefficient and outdated.
Transportation of wastes
Transportation of waste is done through a variety of vehicles such as bullock carts, three-
wheelers, tractors. Most transport vehicles are loaded manually and utilized in one shift
only, although the number of transport vehicles is inadequate.
1. Landfilling
2. Recycling of organic waste
3. Vermicomposting
105
5.2 Tourism
Anupshahris an old town famous for pilgrimages situated on the river Ganga. Several
religious bathings and festivals are organized all the year round. The town was named after
Raja Anup Rai Bargujar. Anupshahr is also called as Mini-Kashi due to river Ganga.
Anupshahrhas historic value and infrastructure support like banking, civic amenities,
dhramshalas, ghaats for Holy in Ganges, Dedicated Ghaats for women. A complete River
front development project will help to recreate and upgrade the existing status. Solid waste
and sanitation projects should also introduced to improve the overall condition of the
tourist to make it tourist friendly.
106
5.3 Environmentally Sensitive Zone
Anupshahr falls in the Ramsar Site which is highly environmentally sensitive. The
stretch of river Ganga at Anupshahar houses the dolphins. The 1.5 km stretch on either side
from the centre of river Ganga from Brij Ghat, Anupshahar to Narora falls under RamSar
Site. During discussions held with WWF India, they informed that they have been working
closely since late nineties with river bank communities and aquatic species that could serve
as a reliable indicator of the health of Ganga river. While different strategies have been
adopted by them from time to time, the focus has always remained on the people &
species, the goal being to reduce the huge burden of pollution & other anthropogenic
pressures that Ganga river has borne particularly in the last few decades. The dolphin
habitat parameters in Ganga river at Anupshahar, as informed by them during discussions,
are tabulated below:
Table: 5.1 Dolphin habitat parameters in Upper Ganga river (Narora- Anupshahar)
Narora –Anupshahar (Zone I) 0-30 Deep pools, sandy and muddy river bank island with vegetation
ph 7.05-8.70
As a result of the active participation of WWE (India) and based on their study during 2007-
2009, the population of dolphins in the study area between Bijnor and Narora was recorded
to have increased .The population of dolphins in the study area was recorded to have
increase (44 in 2007; 49 in 2008; 56 in 2009) during the project period (2007-2009). This
signifies that the recruitment and growth pattern on the population is increasing. This is
most likely because of the improvement in habitat conditions, as well as in the water
quality. A decrease in the death rate between 2007-2009 could also be a factor as o death
was recorded in this stretch.
107
During discussions, the WWF informed that the total dolphin population in upper Ganga
system upto October 2012 was 671. With following distribution. Ganga-261, Yamuna -31,
Chambal-85, Ghaghara-231, Rapti-8, Geruwa-39, Saryu-16. The distribution of total dolphin
population is shown in figure below.
108
5.4 Health Care
There are 2 major hospitals in the town. The list of all Hospitals in the town is presented
below:
· Janta Hospital
· Jahangirabad Community Health Centre
· Jeevan Jyoti Clinic
· Dr. Ved Prakash Clinic
· Kaushik Memorial Clinic
· Neetu Clinic & Maternity Home
· Jahangirabad Veterinary Hospital
109
5.5 Education
There are 4 nos. of schools in the town, 4 nos. of Inter colleges and 1 no. of PG College.
Some of the educational institutes in the town are listed below:
110
5.6 Soil
To identify the existing quality of soil at project area two samples are drawn at STPs in both
zones and in soil quality analysis, analyzed the 18 parameters are listed below:-
SOIL
STP Site STP Site
S.No. Parameter Test Method Zone A Zone B Units
Results Results
1 pH(1:5 suspension) IS:2720(Part-26) 7.94 8.6 -
Electrical Conductivity at
2 IS:2720(Part-21) 54 102 µS/cm
25 OC (1:5suspension.)
3 Organic Matter IS:2720(Part-22) 0.42 0.63 % by mass
111
18 Organic Carbon STP/SOIL 0.3 0.38 %by mass
112
Figure 25 Soil Collection for sampling purposes
1. Kunj Ghat
2. Rani Ghat
3. Asharfi Ghat
4. Triveni Shankar Ghat
5. Rakesh Ghat
6. Shivsharup Ghat
7. Shyamsunder Ghat
8. Dinesh Ghat
9. Patali Ghat
113
10. Ganga Parshad Ghat
11. Lal Mahadev Ghat
12. Ramesh Chand Ghat
13. Jai Krishan Ghat
14. Ganesh Mandir Ghat
15. New Ghat
16. Nagar Palika Ghat
17. Kanna Ghat
There are no important or archeologically identified gardens/ parks in town. However the
region has small residential parks provided by municipal bodies, which will not be
threatenedby the proposed sewer works, since the sewers are planned to be laid in the
middle of theroad and will not pass through these areas.
Tree Cover: Trees can be seen along the road side in almost all parts of town. Practically
none of the trees will be disturbed nor damaged (tree cutting), since they are located on the
edges and sides of roads, away from the center, along which the sewers are planned to be
laid.
Agriculture: There is no agricultural practice in town. This district is the core city area with
mix of residents, commercial areas, institutes, hospitals etc.
Literally environment stands for the totality of surrounding conditions. Animals and plants
form a vital part of this sum total. Flora and fauna of an area are inter-related to each other
and have a very crucial impact on human life. With changes in environmental conditions,
structure, density and composition of plants and animals undergo changes as well. The
present study was carried out in two separate headings for floral and faunal community.
Flora: Presently there is no forest cover in and around the town. The project site is mostly
residential area and does not have any protected or reserved forest area. The site also does
not fall under India’s notified ecological sensitive areas.
114
Table 16 List of Flora in the town
115
Dalbergia sissoo Roxb. Sheesham Fabaceae Tree
Dendrocalamus stricus Nees Bans/Bamboo Poaceae Grass
Dichrostachys cinerea L. - Mimosaceae Shrub
Diospyros melanoxylon Roxb. Tend/Tiril Ebenaceae Tree
Elephantopus scaberL. - Asteraceae Herb
Eulaliopsis binata (Retz.) C.E. Hubb. sabai Poaceae Grass
Euphorbia hirta L. - Euphorbiaceae Herb
Ficus bengalensis L. Bar Moraceae Tree
Ficus religiosa L. Pipal Moraceae Tree
Ficus tomentosa Roxb. Barun Moraceae Tree
Flacourtia Ramontchi Salpani Flacourticeae Shrub
Gmelina arborea Gamhar Verbenaceae Tree
Heteropogon contortus (L.) P. Beauv. Kher/Sauri Poaceae Grass
Holoptelea integrifolia Chilbil Ulmaceae Tree
Hygrophila spinosa T. Anders - Acanthaceae Herb
Imperata cylindrica (L.) P.Beauv. Ulu Poaceae Grass
Indigofera pulchela Jirhul Fabaceae Shrub
Ipomoea carnea Jacq. - Convolvulaceae Shrub
Justicia procumbens L. - Acanthaceae Herb
Kydia calycina Roxb. Puda Malvaceae Tree
Lannea coromandelica (Houttuyn) Merrill Genjan Anacaeaediac Tree
Lantana camara (L.) Moldenke. Putus Verbenaceae Shrub
Leonotis nepataiefolia R.Br. - Lamiaceae Herb
Madhuca indica J.F. Gmel. Mahua Sapotaceae Tree
Mangifera indica L. Aam Anacardiaceae Tree
Mimosa pudica L. - Mimosaceae Herb
Mukia maderaspatana Bilari Cucurbitaceae Climber
Parthenium histerophorus L. - Asteraceae Herb
Phoenix acaulis Roxb. Khejur Arecaceae Shrub
Pongamia pinnata (L.) Pierre. Kranj Fabaceae Tree
Pterocarpus marsupium Tree
Randia dumetorum Lamk Mowar Rubiaceae Shrub
Rubia cordifolia Jotsingh Rubiaceae Tree
Saccharum munja Roxb. Munj Poaceae Grass
Schleichera oleosa (Lour) Oken Kusum Sapindaceae Tree
Shorea robusta Roxb. Sal/ SaKhua Depterocarpaceae Tree
Sida acuta Burm.f. - Malvaceae Herb
Sida rhombifolia L. - Malvaceae Herb
116
Solanum nigrum Makoi Solanaceae Herb
Solanum surattense Burm. f. - Solanaceae Herb
Sphaeranthus indicus L. - Asteraceae Herb
Tectona grandis L.f. Saguan Verbenaceae Tree
Terminalia arjuna Bedd. Arjun Combretaceae Tree
Scientific name Local name Family Habit
Terminalia bellirica (Gaertn.) Roxb. Bahera Combretaceae Tree
Terminalia tomentosa Heyre ex. Roth Asan Combretaceae Tree
Thespesia lampas Ban kapasi Malvaceae Shrub
Tridax procumbens L. - Asteraceae Herb
Vetiveria zizanoides Nash Khus-Khus Poaceae Grass
Vitex negundo L. Sindwar Verbenaceae Shrub
Vitis latifolia Khopri Vitaceae Climber
Woodfordia fruticosa (L.) Kurz. Dhawai Lythraceae Shrub
Xanthium indicum L. - Asteraceae Herb
Zizyphus mauritiana Lam. Ber Rhamnaceae Tree
Zizyphus oenoplia Dhathora Rhamnaceae Shrub
Fauna:
The wild animal species that are mostly found in Anupshahar, are Jackal, Fox, Hare,
Neel Gai around the town. The Ganga supports rich Fauna and Flora, including the
endangered Ganga river dolphin (Platanista gangetica) and at least nine other species of
aquatic mammals. Reptile includes three species of crocodile along with one species of
monitor lizard (Varanus bengalensis) and eleven species of fresh water turtles. The Ganga
river dolphin is a true river dolphin and is extremely rare and thus considered ‘endangered’
by the IUCN. The Ganga river dolphin is important not only because it is endangered, but
perhaps more so because it is reliable indicator of the health of the Ganga, in fact the whole
Ganga river ecosystem. This is why the Government of India declared it as the National
Aquatic Animal in 2009.
Just like the tiger in the forest ecosystem, the Ganga river dolphin is an indicator species for
the river ecosystem. It is at the apex of the food chain. It is an endemic and rare charismatic
mega-fauna found only in the Indian subcontinent. At the same, time it is a part of our natural
aquatic heritage 165 kilometer reach of river Ganga from Bijnor to Naroa is rich in
biodiversity and the only promising habitat for the elusive species such as Ganga river
dolphins, smooth coated other and Muggar crocodile.
Besides above, a number of migratory birds can also be seen during winters at Anupshahr.
Rare Indian Skimmer Saras, Cranes and other birds love to visit Anupshahar every winter.
117
5.6.3 Socio Economic Baseline
Socio-economic impact assessment of the study area of a project is pre-requisite before the
project is put into implementation. The study area consists of the core area where the
proposed project is expected to come up and a buffer area encircling the core area. The
government of India has since made mandatory a “likely impact assessment” study for all
types of upcoming and expansion projects. Socio-economic impact assessment is a
technique to get acquainted with social, cultural and economic conditions of stakeholders,
which includes individuals, groups, communities and organizations.
The total population of Anupshahr Town is 29700, the average house hold size (per house) is
6 and total no of households are 3,929. The sex ratio in town is 882 and sex ratio (0-6) is
877, the percentage of literacy rate is about 67.0 % and total no of literates are 13,380. As
118
per census of India 2011 total no of workers in town are 7,399 in which main workers are
6,170 and marginal workers are 1,229.
Area Profile of Anupshahr (MB) Town of Bulandshahar district, Uttar Pradesh state
Number of Households 3,929 Average Household Size(per Household) 6.0
Population-Total 23,795 Proportion of Urban Population (%) 100
Population-Rural 0 Sex Ratio 882
Population-Urban 23795 Sex Ratio(0-6 Year) 877
Population(0-6Years) 3,746 Sex Ratio (SC) 877
SC Population 3,072 Sex Ratio (ST) 0.0
ST Population 0 Proportion of SC (%) 13.0
Literates 13,380 Proportion of ST (%) 0.0
Illiterates 10,415 Literacy Rate (%) 67.0
Total Workers 7,399 Work Participation Rate (%) 31.0
Main Worker 6,170 % of Main Workers 26.0
Marginal Worker 1,229 % of Marginal Worker 5.0
Non Worker 16,396 % of non-Workers 69.0
CL (Main+Marginal) 450 Proportion of CL (%) 6.0
Al (Main+Marginal) 424 Proportion of AL (%) 6.0
HHI (Main+Marginal) 621 Proportion of HHI (%) 8.0
OW (Main+Marginal) 5,904 Proportion of OW (%) 80.0
119
Source Census of India
120
Demography of Anupshahr Town
The Population distribution of Anupshahr town in 25 different wards as per the 2011
population data is given below:-
The total census population for the year 2011 is 29,700. This population data presented
above is tabulated on the basis of the information provided by the local authorities and the
supporting letter is attached as annexure 15 to this report. However, the present population
i.e. for the year 2013 is 32000.
121
Anoopshahr
122
Cultural significance
The distance between Anupshahr and Bulandshahr is 42 km. Anupshahr is easily accessible
from Bulandshahr by a car or bus.
Anupshahr is quaint town located on the ghats of River Ganga in Bulandshahr district. Best
time to visit Anupshahr is in February, March, October, November and December.
Anupshahr is very popular with the pilgrims especially during annual festivals like Kartik
mela. Anupshahr has been dubbed as “Choti Kashi”. Locals conduct evening aartiand offer
prayers on the banks of River Ganga, pilgrims and locals take baths in the holy
river. Anupshahr has several Hindu temples and guest houses to accommodate the pilgrims
and tourists.
A grand Mela is organized on the eve of Kartik Poornima when peoples use to come for holy
snan in Ganges River & purchase their essential commodities by staying in Anupshahr
city.Besides of this Mela there is a Holy Snan on every Poornima & Amavashiya & Ganga
Dassera
Anupshahr holds testament to the bold uprising of the locals against the British during
India’s War of Independence. Anupshahr is an ancient town founded in the 17th century by
Raja Anup Rai and it reached its most prosperous era during the reign of King Tara Singh.
King Tara Singh made Anupshahr a significant hub for the practice of Ayurvedic medicine.
Legends have it that Anup Rai had saved the life of Emperor Jahangir during his lion
expedition, pleased the Emperor had gifted this area to Anup Rai. King Anup Rai then
established a town and fort in this area.
In historical background Great Maharshi Dayananda Saraswati was visited here in 18th
century to raise awareness against various social evils present in the current society at that
time.
Anupshahr have leading schools like "LDAV, JAYPEE VIDYA MANDIR" etc.
Colleges like State renowned "Durga Prasad Baljit Singh PG College" and
above all newly opened "Jaypee University".
123
Two state highways is providing smooth connectivity to the city to other parts of UP.
Bridge over Ganga provides a quick connectivity to the area from northern parts like bandau,
Moradabad etc.
124
Figure 29 Cultural Significance in the state
125
Details of social survey
The approach and methodology followed for social baseline study as well as the social survey
has been discussed in the earlier Section of the report Consultation with stakeholder
consultations were performed during the field surveys to assess the situation and get the
feedback about the project from all the concerned stakeholders. Household owners & other
stake holders in 8 out of 11 wards were consulted, additionally other important set of
locals interviewed or consulted were pedestrians, shop-owners, school teachers, etc.
Some of these wards have academic and government institutions and most of them are
residential in land use.
All the local stakeholders were enthusiastic & had a positive gesture about the oncoming
sewerage project. Household’s survey were from both rich and poor localities. Most of the
household have access to drinking water facilities and electricity and some of the houses
have toilets as well, but since there is no sewerage system most of the waste water flows
directly in river Ganga. People, who were interacted with, were hopeful that the sewerage
scheme will improve the environment of the area & will have a positive impact on their
hygiene and health. They were also positive about taking sewer connections once the project
is implemented. They were also more concerned to do away with the present system of
discharging their waste water directly in the drain. They were hopeful that this would be
done away with after taking sewer connections & thus the overall environment of the town
would improve.
The Detailed analysis of the questionnaire is presented in the chapter 8 of this report.
126
6 Environmental and Social Impacts
This section addresses the basic concepts and methodological approach for conducting a
scientifically based analysis of the potential impacts likely to accrue as a result of the
proposed project. The Impact Assessment for quite a few disciplines is subjective in nature,
and cannot be quantified. Wherever possible, the impacts have been quantified and
otherwise, qualitative assessment has been undertaken. The proposed sub-project consists
of activities which include:
• Construction of approximately 60 km (approx.) long sewerage network
including all required trunk/ branch/ lateral sewer for year 2048.
• Construction of main sewage pumping stations for year 2048.
• Construction of 2 sewage treatment plant of 1.5 and 1 MLD capacity for year
2028.
Pollution abatement projects may prove beneficial for the environment and society or they
may have some adverse impacts as well. Planners and decision makers have realized the
importance of understanding the consequences of any such projects on both environmental
and social sectors, and have started taking steps to avoid any adverse impacts. Based on the
major findings obtained from the field visits and secondary data analysis, the possible
environmental and social issues with reference to the proposed sewer works in Anupshahr
has been discussed in these sections.
127
6.1.1 Design and Development Phase
Sewer lines
All sewer lines including trunk, lateral and branch sewer lines must be designed considering
the future population and waste generation rate. Otherwise the constructed sewer may not
carry the waste load, leading to failure and financial loss. The alignment of sewer lines and
sewerage pumping station must be properly planned; else it may lead to both technical and
social problems along with environmental issues of back flow creating foul smell and
unhygienic conditions.
Selection of a suitable technology for sewage treatment is governed by many factors such as
the location of STP, availability of land area, raw sewerage characteristics, capacity of plant,
required effluent quality, proven technology and reliability of process, intended disposal
method or reusing the treated effluent, capital cost, O&M requirement and other local
factors.
Comparative analysis of various technologies considered for selection is given in Table 6.1.
Table 17Comparative analysis of various sewage treatment technologies
128
Time
BOD Loading
Rate 0.03-0.05 0.3-0.4 NA 0.6-0.8 0.5-0.6 0.3-0.4
(Kg/m3/Day)
0.05-
F:M NA 0.05-0.15 NA NA 0.05-0.15
0.15
Oxygen
Natural 0.2-0.4
Requirement 0.2-0.4 ppm NA 0.2-0.4 ppm 0.2-0.4 ppm
Oxygen ppm
(ppm)
The project area falls under Ramsar site which is a sensitive area from the ecological point
of view, but it is not a protected area under wildlife protection act 1972. Prior to
implementation of the proposed project, the previous study of WWF indicates that:
1. The number of Dolphin from 2007 to 2009 has increased between Bijnor to Narora
along Ganga main stream 44 to 56.
129
2. D.O. level of river Ganga at Narora upstream and downstream of the main drain
discharging into it is 6.8 mg/l and 6.6 mg/l respectively which is within the
Dolphin habitat parameter
Therefore even with the present condition, the project area provides a preferred
habitat location for Dolphins and it is expected that with the treatment of waste water
the habitat condition for dolphin will further improve and hence the project overall
will have a positive impact.
As explained in section 5.1.10 of baseline environment status, town does not have any flora
and fauna components; there are no nearest eco-sensitive areas such as National Park and
wild life sanctuaries within a 100 km from the proposed project site. However the region has
small residential parks and road side trees, which will not be affected by the proposed
sewer works, since the sewers are planned to be laid in the middle of the road and will not
pass through these areas. With regard to sensitive aquatic areas and water bodies, there are
none. It was also observed that the major land use pattern of town is residential, with no
agricultural and no forest areas.
131
As part of the NGRBA programme, Dolphin status surveys are proposed in UP and are in
process of sanctioning which will also be repeated by the forest department on regular interval
(one in 3 years). The present Dolphin concentration in the area (23 in number) will thereby to
be monitored by these status surveys. Corrective actions may need to be taken if Dolphin
number are decreased over a period of time.
132
the town has more of residential land use, the number of people who will be affected is
more. Residential population includes more vulnerable groups such as the elderly and
children.
The main residential areas of Anupshahr is given below:-Delhi Dwar, Meera Anshik, Nehru
Ganj, Delhi Dwaar Anshik, Nehru Ganj, Madaar Dwaar, Jama Masjid , Nehru Ganj Anshik
Meera Delhi Dwaar Anshik , Meera Anshik Madaar Gate and Nehru Ganj anshik
133
Medical College area, etc. For elderly and students, noise is disturbing and affects their
comfort. This could be a problem especially in sensitive areas like school and hospitals.
Based on the enthusiasm and readiness the farmers shows during various
consultations, meeting conducted with them to discuss the issue of reuse the treated
effluent for irrigation purpose, it is clearly evident that the effluent will be recycled.
The network for achieving the 50 % of treated waste water used for irrigation purpose
in first five years and 100 % reuse of next 5 years of operation period will be adopted.
The required written consent from potential end users has already taken. Provision to
use is being made in the mitigation and management plan.
The sludge collected from STP will be stack within STP campus for short duration,
which will ultimately be sold/ distributed to farmers as manure. After drying, the
composted sludge as a soil conditioner in agriculture and horticulture returns carbon,
nitrogen, phosphorus essential for plant growth. Reuse may still be possible for
purposes such as highway landscaping or for landfill cover.
The garbage, brick bats, polyethylene waste screen out at screen chamber of pumping
stations will be screen out periodically and collected in the campus to dry. This waste
ultimately disposed of at solid waste disposal site as designated by Nagar Palika
Anupshahr.
Conclusion
Based on the overall secondary data analysis and field investigation, the proposed project is
expected to benefit the Anupshahr town, as the wastewater that currently flows untreated
into the Ganga river will be captured, treated and the remainder of the treated effluent will
134
be allowed to flow into the river. The likely
beneficial impacts of the projects include
• Improvement in sewerage collection and
treatment within the cities/towns
• Prevention of storm drains carrying sanitary
sullage or dry weather flow
• Prevention of ground water and soil
pollution due to infiltration of untreated liquid waste
• Prevention of discharge of untreated sewage
into River Ganga
• Improvement in water quality of River Ganga,
a national resource
• Improvement in environmental sanitation
health and reduction in associated health
hazards within the cities/towns
• Improvement in quality of life, human dignity and increased productivity
• Reduced nuisance of open defecation due to low cost sanitation and reduced malarial
risks and other health hazards
Although there would not be any permanent negative or adverse environmental impacts,
but will have temporary impacts, that can be mitigated with appropriate mitigation plans.
However, the large environmental benefit of the project greatly outweighs the temporary
inconveniences.
135
7 Mitigation and Management Plan
In general, the Uttar Pradesh Jal Nigam (with assistance from Contractor and Independent
Engineer/Supervision Consultant) is the responsible entity for ensuring that the mitigation
measures as suggested in the ESMP. The roles and responsibilities of the involved institutes
are described below.
· EMP clearance from NMCG and World Bank and disclosure as required;
· Integrating the EMP in the bid document of contractor as an addendum;
136
Clean Ganga (NMCG) for the progress made inimplementing the Environment Management
Plan.
Feedback from the local residents can also be taken from time to time to cross check the
contractor’s report. Project management consultants should make inspection visits at
construction site to check the implementation of Environment Management Plan as per the
contract.
137
Environment Management Plan
139
STPs water tanks, earthling with installation of earth
Short Circuiting) circuit breakers shall be made Walk
Accidental slip, trip ways designs shall be made with
and fall in walk ways or proper slope to avoid accumulation of
work areas rain water. Material handling and
Fire storage shall be so designed that walk
Exposure to toxic gas way surface remains free from wet or
such as oil surface situation to prevent slips,
Chlorine trip or fall accidents.
141
Main Pumping of Noise and odour Permanent · Ensure minimum noise generation at DBOOperator
sewage sewage to nuisance hazards to pump station inSPS by use of less
pumping STP neighboring areas. noise generating equipment
station Cutting of Trees meetingprescribed noise standards as
applicable and enclosedgenerators.
· No Tree cutting is involved. Tree
plantation aroundthe periphery of SPS
site and landscaping to prevent
spread of bad odour with large
canopy/ broad leaves trees like
Shisham, Neem, Bargad, Teak, Sal, etc.
· Accumulated screenings and grit in
each SPM to be cleaned on a daily
basis. Spraying of suitable herbicides
on accumulated material to reduce
odour, if it is not being cleaned on a
daily basis due to same exigencies.
· Provision for regular maintenance and
switching offequipment when not in
use.
Construction Phase:
Sewage Excavation Loss of topsoil due to excavation Temporary · Excavation shall be planned in such a DBOOperator
treatment activities. manner that such that no damage
plant and occurs to existing structures.
main sewage · Top soil shall be separately stockpiled
pumping and utilized for green belt
station development or landscaping after
completion of work
142
Construction waste Temporary · Excess soil generated from various DBOOperator
construction activities shall be proper
disposed in low lying areas, other
than water bodies.
· All construction vehicles, parking
location, fuel / lubricant storage
sites, vehicle, machinery and
equipment maintenance will be
located at least 500m from rivers and
irrigation canal /ponds.
· Normally, muck is disposed in low-
lying areas or depressions. Trees, if
any, are cut before muckdisposal,
however, shrubs, grass or other types
of undergrowth in the muck disposal
at sites perish. The total area
required for muck/sludge/solid waste
disposalfor year 2045 is 1 ha.
· The dumping of muck will be done in
the scientific manner by providing
appropriate protection walls with
deep foundations so that muck will
not flow and washed away in the
river. Masonry work and crate work
will also be provided wherever
necessary in order to avoid
thechances of soil erosion and to
ensure flow of silt, free water.
Besides these engineering measures,
proper plantation will be done at the
dumping sites for reclamation of the
dumping areas.
143
· Muck generally lacks nutrients and
therefore, is difficult to re-vegetate.
However, if no attempts to vegetate
the slopes are made, the muck could
slide lower down during rain and may
eventually wash off the protective
measures also. Bio-fertilizer
technique developed by National
Environmental Engineering Research
Institute (NEERI) can be adopted in
the proposed project.
· It is recommended that bituminous
waste to be disposed at approved
waste disposal sites, which shall be
finalized in consultation with district
administration and regional offices.
Soil Erosion Temporary · Provision of garland drain along DBOOperator
construction site, to divert runoff to
sumps for storage and settling of
separated solids.
· The required protective work i.e.
formation of traces, construction of
garland drains outside the periphery
of dump followed by settling tank to
avoid wash off.
Nuisance due to Temporary · Provide two bins for recyclable and DBO Operator
domestic solid waste disposal non-recyclable wastes.
· Ensure that recyclable and non-
recyclable wastes are collected in
segregated manner in theses bins
before disposal. Recyclable material
shall be sold. Non-recyclable material
144
shall be disposed to designated
landfill area of the city.
· Provide adequate sanitation facility
for workers at construction sites.
Dust Generation due to Temporary · Excavated material transported by DBO Operator
construction trucks will be covered and/or wetted
Activities to prevent dust nuisance.
· Suppressing dust generation by
spraying water on stockpiles and
unpaved movement areas
· Water sprinkling over excavated
areas, unpaved movement areas and
stockpiles.
· Transportation of loose construction
material through covered trucks.
· Use dust curtains (polysheets/
sheets) around the construction area
for containing dust spread.
· Construction equipment must
comply with pollution norms and
carry Pollution under Control
certificate
Temporary flooding due to Temporary · The construction waste material shall DBO Operator
uneven dumping of construction be stored on higher areas of the site
waste and or areas where water may not
accumulate creating flooding like
situation
Spillage of fuel and oil Temporary · Care to be taken to store fuel and oil DBO Operator
(if required) at a place away from any
drainage channel/nalla preferably to
be stored in drums mounted on a
145
concrete paved platform with slop
draining to small spills collection pit.
· All location and lay-out plans of such
sites will be submitted prior to the
establishment and will be approved
by the Engineer.
· Ensure that all vehicle / machinery
and equipment operation,
maintenance and refueling will be
carried out in such a fashion that
spillage of fuels and lubricants does
not contaminate the ground.
· Arrangement for collection, storing
and disposal of oily wastes to the
pre-identified disposal sites (list to be
submitted to Engineer) and approved
by the Engineer. All spills and
collected petroleum products will be
disposed off in accordance with
MoEF Engineer will certify that all
arrangements comply with
Noise and vibration Temporary · Construction activities to be carried DBOOperator
disturbances to out in day time with prior intimation
residents and to local residents and shop keepers.
businesses · Vehicles to be equipped with
mufflers recommended by the
vehicle manufacturer.
· Staging of construction equipment
and unnecessary idling of equipment
within noise sensitive areas to be
avoided whenever possible.
· Operators of heavy machinery and
146
workers in near vicinity will be
provided with ear plugs and other
protective measures for safety.
· Notification will be given to residents
within 300 feet (about 90 to 100 m)
of major noise generating activities.
· The notification will describe the
noise abatement measures that will
be implemented.
· Monitoring of noise levels will be
conducted during the construction
phase of the project. In case of
exceeding of pre-determined
acceptable noise levels by the
machinery will require the
contractor(s) to stop work and
remedy the situation prior to
continuing construction.
· Use of low noise and vibrating
equipment (such as enclosed
generators with mufflers,
instruments with built in vibration
dampening and improved exhaust),
to meet standards as prescribed by
Central Pollution Control Board
(CPCB1).
· Provision of personal protective
equipment (PPE) like ear muffs and
plugs for construction workers.
· Provision of noise barriers as feasible
in inhabited areas, particularly near
sensitive zones like hospitals, schools
147
etc.
· The maximum permissible sound
pressure level shall be75 dB(A) at a
distance of 1 m from the source.
152
Operation
Phase
Sewage Treatment River, land or ground water Permanent · Monitor the treated sewage quality DBO Operator
treatment and pollution due to discharge of and ensure compliance with PCB
plant and Disposal of untreated or partially treated standards for effluent disposal into
Sewage Treated sewage due to inadequate or surface water bodies, on land or for
pumping Water and inefficient STP operations. the agricultural use.
station Sludge · Follow standard operating
procedures for operation and
maintenance.
· Undertake periodic audit as per these
procedures.
· Comply with all applicable condition
of consent to operate Quarterly
monitoring of influent sewage,
treated sewage, upstream and
downstream point of treated sewage
disposal point to river.
· Quarterly monitoring of influent
sewage, treated sewage, upstream
and downstream point of treated
sewage disposal point to river, to
ensure thatNRCD standards of water
quality BOD<20 mg/l and SS <30 mg/l
mentioned under the design and
development phase of this table are
met.
Problems arising due to bad Temporary · Maintain the green belt as per DBO Operator
odour, insects, polluted air. provision of design to prevent
spread of bad odour with large
canopy/ broad leaves trees like
Shisham, Neem, Bargad, Teak, Sal,
etc.
· Accumulated sludge and solid waste
to be cleared within 24 hours and
spraying of suitable herbicides on
accumulated sludge/solid waste to
153
reduce odour.
· Quarterly monitoring of Ambient Air
Quality with respect to PM10, PM2 5,
S02 and N02, CO and Odour at three
locations (at STP site, minimum 500
m away from STP site in up-wind and
down-wind direction of STP area.
Increase in Ambient Noise Temporary · Proper handling and regular DBO Operator
Level and discomfort to maintenance of operating machines
neighboring people including pumps, generators, air
diffusers, etc.
· Quarterly Monitoring of Ambient
Noise level to check compliance to
standards.
· Quarterly monitoring of ambient
noise levels (day and night) at same
locations as of ambient air
monitoring
Indiscriminate disposal of Temporary · Prepare sludge disposal plan as per DBO Operator
sludge leading to desire stage provisions and
contamination of land and guidelines and adhere to the same.
soil.
Main Waste Bad odour, Health hazard and Temporary · Provision for regular clearance of DBO Operator
pumping Handling public nuisance sludge and solid waste to minimize
station odour nuisance
· Ensure maintenance of Green belt as
planned
· Periodic disposal of accumulated
sludge/solid waste to designated
land fill sites of the city.
General Workers Serious/health/safety Temporary · Safety shoes or boots with non-slip DBO Operator
Safety exposure to hazards soles will be provided to the workers at
hazardous site
materials/ · Personal protective equipment and
situations chemical resistant clothing to avoid
exposure of skin or eyes to corrosive
and/or polluted solids, liquids, gases or
154
vapors
· Electrical equipment for safety
before use will be checked; verified that
all electric cables are properly insulated
· Safety goggles will be provided to
operators in all cases where the eyes
may be exposed to dust, flying particles,
or splashes of harmful liquids
· Respirator or gas mask will be
provided to workers when exposed to
harmful aerosols, dusts, vapors or gases
· Extreme care will be taken when
handling highly corrosive agents such as
liquid or gaseous chlorine, concentrated
acids or alkalis, or when toxic gases may
be emitted from the reagents, etc.
· Workers will not be allowed to
smoke, eat or drink in areas where
chemical or biological contamination
may be expected
· All workers will undergo periodic
examinations by occupational physician
to reveal early symptoms of possible
chronic effects or allergies
· Follow safety measures and
Emergency preparedness plan evolved
at design stage
155
Table 19 Environmental Management Plan for Sewerage Network in Anupshahr
158
Temporary flooding due to Temporary • Stockpiled areas to be bordered by DBO Operator
excavation during monsoons berms
or blockage of surface drains • Stockpiles to be done in high areas to
avoid flow in storm water run-off
channels and erosion.
159
Nuisance due to solid waste Temporary • Provide two bins for recyclable and non- DBO Operator
disposal recyclable wastes.
• Ensure that recyclable and non-
recyclable waste is collected in
segregated manner in theses bins
before disposal. Recyclable material
should be sold. Non-recyclable material
should be disposed for designated land
fill area of the city. • Provide adequate
sanitation facility for workers at
construction sites.
Impact in sensitive area Temporary · The project area falls under Ramsar site which is DBO Operator
a sensitive area; the management plan for the
same is being prepared by UP forest department;
· During construction measures to be taken to
ensure that muck, debris generated from the
construction activities are strictly prohibited for
its entry to river Ganga; necessary signages,
barricades (if construction along Ganga is
envisaged) to be given at specific locations;
· High noise in the project area need to be
controlled and hence sheet piling to be avoided
· Construction vehicles need to have silencers to
minimize honking noise;
General: safety Accidents Safety hazards to labours Temporary • Comply with the Occupational health DBO Operator
during and public and Safety Act of India
construction • Ensure that the contact details of the
police or security company and
ambulance services nearby to the site.
• Ensure that the handling of equipment
and materials is supervised and
adequately instructed.
• Erect warning signs/ tapes and
temporary barriers and/or danger tape,
marking flags, lights and flagmen
around the exposed construction works
warn the public and traffic flow of the
160
inherent dangers.
• Provide adequate safety precautions
such as helmets, safety shoes, gloves,
dust masks, gumboots, etc. to workers
Monthly reporting of all accidents and
immediate reporting to DBO engineer
and owner.
Operation Phase
Sewer line Leakage/ Water pollution and Temporary • Regular monitoring of sewer line and DBO Operator
overflows possibility of mixing with manholes for visible leakages/ overflows.
water supply line Immediate repair operation for the
damaged portion of sewer line. De-
siltation of blocked sewers/ manholes
with sewage pumping machines-storing
and disposal at appropriate refusal area
after treatment.
E Ensure proper covering of manhole and
avoid dumping of solid waste to prevent
chocking of sewer line.
Sewage Waste Handling Bad odour, Health hazard Temporary Provision for regular clearance of sludge DBO Operator
Pumping and public nuisance and solid waste to minimize odour
Station nuisance
• Ensure maintenance of Green belt as
planned
Periodic disposal of accumulated
sludge/solid waste to disposal site as
approved by DBO engineer.
161
Sewage Extracted Bad odour, Health hazard Temporary • Ensure that extracted sewage sludge DBO Operator
Cleaning Sewage and public nuisance and collected during sewers cleaning are
Equipment Sludge possible land disposed to disposal site as approved by
handling and contaminations DBO engineer.
cleaning • Sewage solids shall not be disposed on
equipment road sides or non-designated areas.
maintenance • Equipment cleaning waste shall be
waste disposed to public sewer or STP inlet for
handling treatment
• Waste oil if any generated shall be
separately collected. It shall be sold to
authorized waste oil recyclers.
Impact in sensitive area Temporary · The project area falls under Ramsar site which is DBO Operator
a sensitive area; the management plan for the
same is being prepared by UP forest department;
· Further to monitor the baseline Dolphin
population, a status survey is being planned by
UP forest department which will be repeated
after every 3 years;
· Dolphins are sensitive to noise levels and hence
care to be taken that the noise from pumping and
other activities at SPS, STP are controlled
through some enclosures, noise mufflers;
· The sewage and STP sludge should be strictly
prohibited from disposing them directly to river
Ganga
General Safety Workers Serious/health/ safety Temporary • During cleaning/ maintenance DBO Operator
exposure to hazards operation, the sewer line will be
toxic gases in The toxic gases are likely to adequately vented to ensure that no
sewers and contract communicable toxic or hazardous gases are present in
hazardous diseases from exposure to the line.
materials during pathogens present in the Ensure availability of PPE for
sewer sewage. maintenance workers.
maintenance • Follow safety and Emergency
work Preparedness plan prepared at design
stage
Monthly reporting of all accidents and
162
immediate reporting to DBO engineer
and owner.
163
7.3 Environmental Monitoring Plan
The Environmental Monitoring Programme has been detailed out in Table 7.3.
Successful implementation of the Environmental Monitoring Program is contingent on
the following:
· The Project Management Consultant (PMC) along with Uttar Pradesh Jal Nigam to
request the Contractor to commence all the initial tests for monitoring (i.e. for Air,
Water Quality and Noise Levels) early in the Contract to establish 'base' readings (i.e.
to assess the existing conditions prior to effects from the Construction activities
being felt);
· The PMC along with Uttar Pradesh Jal Nigam to request the Concessionaire /
Contractor to submit for approval a proposed schedule of subsequent periodic tests
to be carried out;
· Monitoring by the PMC's Environmental Officer of all the environmental monitoring
tests and subsequent analysis of results;
· Where indicated by testing results, and any other relevant on-site conditions, PMC
to instruct the Concessionaire / Contractor to:
o Modify the testing schedule (dates, frequency);
o Modify (add to or delete) testing locations;
o Verify testing results with additional testing as/if required;
o Require recalibration of equipment, etc., as necessary; and,
o Request the Concessionaire to stop, modify or defer specific
construction equipment,
o Processes, etc., as necessary, that are deemed to have contributed
significantly to monitoring readings in excess of permissible
environmental "safe" levels.
Table 20Environment Monitoring Programme
Consider the
Physical
following methods:
Parameters:
Texture, Grain IS-2720 (Various
Size, Gravel, part);
Sand, Silt, Clay; PMC,
Sewer Contractor through
Chemical Once in every Anupshahr
Soil Construction Soil Chemical Construction approved monitoring
Parameters: pH, season Nagar
Analysis by M.L. Sites and SPS agency/Lab
Conductivity, Parishad and SPMG
JACKSON.
Calcium,
Magnesium,
Soil Test Method by
Sodium, Nitrogen,
Ministry of
Absorption Ratio
agriculture
Environment Institutional Responsibilities
Stage
Component Parameter Standards/Methods Locations Frequency Implementation Supervision
Physical
Parameter :
Consider the following
Texture, Grain
methods:
Size, Gravel,
Twice in a
Sand, Silt, Clay; IS-2720 (Various part); PMC,
year (Pre-
Chemical Along sewer Contractor through Anupshahr
monsoon and
Operation Parameter: pH, construction approved monitoring Nagar
Soil Chemical Analysis by Post
Conductivity, sites, SPS agency/Lab Parishad and
M.L. JACKSON. monsoon) for
Calcium, SPMG
first 5 years,
Magnesium,
Soil Test Method by
Sodium,
Ministry of agriculture
Nitrogen,
Absorption Ratio
7.4 Social Management Plan
Based on the identified social issues, doable mitigation plans are proposed. Some of these
measures are already listed in the DPRs, and some of them are additionally recommended
for social development of the project and the concerned stakeholders.
Mitigation plan involves the erection of temporary enclosures around construction sites.
These barriers will help entrap some of the dust that is brought up in digging. They will also
provide safety benefits, to be detailed below. According to the interaction/consultation
with the key stakeholders, it was said that contractors are doing water sprinkling in the
construction area.
2. Traffic Congestion
Mitigation Measure: Re-route traffic whenever possible and employing traffic police to
manage the traffic movement.
Traffic must be re-routed to facilitate ease of movement. Proper signage should provide
detailed information on the dates and duration of road closures and which detours will be
available, ideally well in advance of actual construction so residents can plan accordingly.
Strategic placement of traffic police at critical intersections will also facilitate better flow of
traffic. Plans and budget for these measures are already included in the DPR.
3. Impact on livelihood
Sewer constructions will invariable lead to road closures, which will adversely affect shops
on those streets. The first priority is for the contractor to take the necessary measures to
ensure that pedestrians always have access to shops, vendors, etc. For mobile vendors, this
may include adjusting the location of the cart, etc. to a similar location in the immediate
vicinity of the original location for the duration of the project. Projects should also proceed
on schedule so as to minimize disruption.
Additionally, clean-up of debris and clearance of blockages should commence immediately
after project completion so as to remove any potential obstacles that might prevent
customers from accessing businesses or other disruptions.
In the event that the contractor, despite best efforts, is unable to avoid blockages of the
roads and/or disruption of local businesses, some compensation is necessary. The ESMF
currently mandates compensation only in the case of permanent livelihood loss or
displacement and provides no provisions for livelihood loss of mobile vendors. Additionally,
no regulation, policy, guideline, etc. exists which can provide precedent or guidance in this
instance. ESMF clearly states that mobile/ambulatory hawkers: fruit cart vendors, etc. who
can easily relocate fall into this category. These vendors are most eligible for a temporary
relocation just outside the construction area, and will thus not be eligible for compensation
as is the case for this proposed project.
However if during the construction of the project any party faces livelihood loss due to the
proposed project, then that party should be compensated according to the entitlement
matrix given in the ESMF report.
Mitigation Measure:
• Circulating the layout plans of the existing underground alignment near the
work site
• Contacting the relevant department in case there is any damage to any of the
utility services andensuring prompt fixing/replacing ofdamaged infrastructure
Temporary shifting of power/water lines for construction purposes is already budgeted for
in the DPR. Nevertheless, all construction personnel must receive detailed layout plans of
existing underground structures to prevent accidental water/electricity supply disruptions.
The relevant departments should also be made aware of the timing and location of digging
near supply lines so they can make the necessary preparations to respond swiftly to
disruptions.
169
5. Safety hazards
Mitigation Measure: Fencing of the excavation site and providing proper caution sign
boards. As mentioned above, fencing should be erected around construction sites and
appropriately marked with caution signage. These fences/signs should remain in place even
if construction is not active, so long as a hazard (e.g. open pit) remains.
According to UP Jal Nigam officials, construction will take place after school hours or at
other times of school closing to avoid interfering with school functioning sensitive locations.
Beyond that, construction must simply proceed in a deliberate and judicious manner to
avoid unnecessary noise pollution. Noise barriers will be placed near sensitive receptors like
hospitals and schools
As mentioned above, provisions to rehabilitate roads and clear debris are already included
in the DPR.
8. Public Notice: According to the suggestion given by locals during the interview.
Government and contractor should give a prior notice to each and every locality with the
details of project, street wise start date of construction and street wise end date of
construction, contact person during emergency. This information would help them better
adjust to the situation and make necessary adjustments and provisions.
170
Table 21Social Management Plan
171
Activity Potential Negative Mitigation Measures Cost Issues
Impact/Concern
Temporary water , Circulation of layout Provision of Feeder
electricity, supply plan for all pillars has been made
interruptions underground for the proposed
infrastructure to infrastructure
ensure that contractor construction
is aware of
water/electricity lines
in construction zones
•Local utilities should
beamed aware of
timing/location of all
construction, enabling
them to respond swiftly
to supply disruption,
especially in the event
of flooding, etc.
172
consultation may be conducted where the mitigation plan is presented, and feedback
solicited from the community. Individual meetings with other key stake holders -
government officials, relevant NGOs, etc. could be scheduled to solicit their feedback as
well. Once construction begins and the mitigation plan is put into effect, third party
audits should be taken up so as to evaluate the efficacy of the mitigation plan, as well as
gauge local sentiments related to the construction and identify/address new issues that
may have arisen during construction.
173
d Adherence to RTI Act
The Right to Information act will be used to ensure transparency on all aspects of the
programme by proactive disclosure & sharing of information voluntarily & on demand
as prescribed under the law with key stake holders, communities and beneficiaries.
This information would be provided regarding all components of the project including
cost estimates, procurement plans, details of tender notices, details of award of
Contracts, Contract amounts, Selection of consultants & the details of officials
implementing the project.
GRIEVANCE REDRESSAL
Redressal of grievances contributes to a great extent to the positive perception of the
public regarding the project implementation. Therefore it is essential that any query or
a complaint vis a vis any aspect of the project implementation is promptly,
effectively& positively addressed. The Grievances will be submitted through various
mediums, in person, through phone calls, online or through letters. A single system for
redressal of grievances shall be adopted at the project level to ensure that its purpose is
met. The integrated grievance system will include the following.
i Establishing Grievances Redressal Cell (GRC) with dedicated project officer and
system at the local EA & ULB .At project level the proposed GRC includes Executive
Officer, Anupshahar Nagar Palika. Assistant Engineer, U.P.Jal Nigam will be
Grievance redressal officer at EA level including representative of DBO. Name and
contact information of GRO will be displayed at project site/Notice Board and also
disclosed on website of ULB, EA and SPMG.
ii The public also can submit their unresolved grievances at Tehsil Divas on every
second and fourth Tuesday of every month between 10:00 to 14:00, to District
Magistrate/Sub District Magistrate and all district level officials for quick redressal.
iii The SPMG & EA will prepare a half yearly report on grievance redressal under
GAAP and will be reviewed during meeting of CMCs and Social Audit.
iv The above arrangement will be in addition to the PIO official appointed under RTI
Act, under office of the General Manager, Yamuna Pollution Control Unit, U.P.Jal
Nigam, Ghaziabad.
174
external will be conducted annually at regular intervals to ensure that the financial
investments are put to proper use.
7.4.5 Assess the Capacity of Institutions and Mechanisms for Implementing Social
Development Aspects and Social Safeguard Plans; Recommend Capacity building measures
Roles and functions of the institutions are pre-defined, but they can enhance their
capacity for better implementation and operation of the project. There should be
synergies and continual interaction amongst the departments for better coordination.
The officers of the relevant departments can be trained in social sciences, social
management plan, etc.
Table 22Role of stakeholder in implementation and mitigation
Jal Sansthan While execution of projects Should ensure that the basic
related to sewerage line, Jal amenities are in order during
Sansthan is responsible for the the construction and
damage caused to the public operational phase of the
utility functions like drinking project
water pipe line.
Municipality Ensuring better access to Should ensure all the
households households envisaged at
project planning phase gets
access to the services. Weaker
section of the society should
get equitable share.
State, local Government Coordination Coordination Monitoring and
Monitoring and evaluation evaluation Ensure all the
safeguarding plans are in line
and acted upon.
175
NGOs, CSOs Awareness creation about the Public participation and
project activities Community coordination
participation for better project
implementation
176
· Ensuring storage of excavated soil material on the higher lying areas
· Solid Waste Management
The tentative cost breakup of the EMP is given in Table 7.4. These costs are to be considered
as estimated on a lump-sum basis, since the detailed cost estimates depend on site
condition and construction/operation practices.
177
Table 23 EMP Budget
Water sprinkling:
As per time schedule 24 months - 60
excluding monsoon period.
Per day, as estimated 100m will be
covered1000 L water will be consumed every-
day for 100m using sprinkler, average 2 times
a day.
Labour cost = Rs. 150/day Rs 300/tanker + Rs.
150/labourer = Rs. 450 Per meter cost =
Rs.450/100m = Rs. 4.50 Total cost for 60 km =
Water sprinkling on excavated Water tanker: Rs.
Rs.4.50 x 60,000 = Rs. 2,70,000
Dust material to suppress dust and 108000.00
No
generation provision of top cover when Keeping a 2-day margin for construction and
Top cover for dumper
transported through vehicles re-instatement per site:
truck: Rs. 22,500
= 4 x 270000 = Rs1080000/- Top cover:
Approximately 30 Sqm of top cover may be
required for each vehicle. Assume that 10 such
vehicles are required in transporting excess soil
to dumping location (considering construction
schedule and max excavated earth disposal).
Therefore: 10 trucks x required top cover 30
Sqm xCost of Tripol cover @Rs. 75/ Sqm = Rs.
22500
Phase Cost included in Cost in Rupees (or Remarks
Component of EMP Mitigation measure the DPR (Yes/no/not Details if provided in
clear) DPR)
179
As per the schedule, the construction of 60km
has to be executed in 24 months which implies
that approximately 10 days are required for
completing 1km or 100 m/day.
Setting up barricade frame:
• wooden rod (bamboo or babool) length =
10ft = 3m
Total rods (vertical) required = 250/3 = 83.3 ~
90.
Total rods (horizontal) required (2 layers) =
250/3 x 2 = 83.3 x 2 ~ 90 x 2 = 180. Total one
Setting up
side = 180 + 90 = 270 rods Total opposite side
barricades:
Total = 180+ 90 = 270
Usage of sound barriers or Rs. 43,500/-
Noise and vibrations No Rate for 1 wooden rod = Rs.75 per rod.
sheets. Setting up noise barriers
Total cost for frame = Rs.300 * 540 rods = Rs.
(installing GI sheets): Rs.
40,500 Labour Cost: 2 labourers per day = 2 x
3,37,000
150 = Rs.300
Total = Rs.300 x 10days for barricading= Rs.
3000
Using Galvanized Iron (GI) sheets as noise
barriers in sensitive zones: Based on
discussions with SPMG, noise barriers will be
setup only in sensitive regions hence, only 2.0
kms (estimated) of noise barrier would be
required. 2.0 km@250m/day would require 10
days.
Approximately 250 m of barricade is set up
On each side of construction site=
250mx2=500m per site
Each Gi sheet has dimensions of 10ft x 4ft=3m
x 1.2m
Laying each sheet horizontally, 2 sheets would
cover a height of 1.2 m + 1.2 m=2.4 m and a
length of 3.0 m
Number of GI sheets required for 250m
180
stretch(Left side)= 250/3*2=167 sheets
Number of GI sheets required for 250m
stretch(Right side)= 250/3*2=167 sheets
Total=334 sheets
Hence, 334 sheets x Cost of GI sheet Rs.
1000per sheet (Rs. 70-100 per Kg)+ Labour cost
for 10 Days(two laborers at average rate of Rs.
150.0 per day).
=334x 1000+(150x2x10)=Rs. 3,37,000.00
The above mentioned costs are generalized
cost for a 250m stretch for barricades, GI
sheets separately.
Alternate traffic rerouting
Temporary Flooding or Ensuring storage of excavated All the flooded water will be diverted in gravity
No NA
water logging soil material on the higher lying to the existing nalas.
areas
Increased traffic No
Traffic re-routing No such Heavy traffic can be seen in the town.
inconvenience
Total number of labourers is estimated
assuming 35% of total project working for
average 20 months (24 months for sewerage
and 16 months for STP). The labour camps can
be divided into 2 camps, for appropriate
Cost of construction of management and maintenance work. Each
Health hazards and pit and toilet building camp will have around 2000 labourers
Labour camps (if nuisance due to absence approximately Rs. A toilet with septic tank is been suggested for
Sanitation No sanitation facility at labour camps.
adopted) of facility for sanitation or 10,00,000
solid waste management Cleaning of all pits
Pit: Assuming single pit of 100cum would cover
1,20,000
1000 people.2 pits are needed in 1 camp.
Construction of one pit would cost
approximately Rs. 1, 50,000/-. So for 2 camps 2
pits each is required. So total cost of pit
construction would be Rs. 6,00,000
Construction of toilet building consisting of 15
181
toilets cost Rs 80,000. 5 such buildings will cost
4,00,000
Pit cleaning: The filled pit has to be cleaned
after 9 months by either disposing off at refusal
site or STP by concerned Municipal agency.
Cleaning of one pit would be approximately
Rs15, 000/-. So, for 4 pits in the given project
duration twice cleaning would be needed, So
total cost would be Rs. 1,20,000
As estimated 2000 labourers will be at one
camp, so approximately 400 families. Around
25 stand posts will be needed at one camp.
One stand post cost is Rs 6250/-So total cost of
Approximately construction will be Rs. 3,12,500.00
Water Supply No
Rs. 11,22,500/- For the standard of 135 LPCD, 5, 40,000 L of
water is needed for both the camps. At the rate
of Rs 2.5KL, the cost of water provisioning
would be Rs 1350.00 per day. For 20 months,
cost will be Rs. 8,10,000/-
Solid waste generation: Generally about 200
grams of solid waste is generated per 5 persons
every day. Hence 4 cluster dustbin (one for
Approximately
Dust bins No biodegradable waste and one for non-
Rs. 4,00,000
biodegradable waste of 1 cum size at the rate
of Rs. 2000/-) may handle solid waste
generated.
Ensure proper functioning of No treatment of sludge is required as the
Treatment and disposal of STP for digestion of sludge yearly exercise of sludge removal will take
No
sludge Aesthetic appearance by green place and the sludge removed will be used as
cover the manure.
The estimated cost of the environmental management plans that are not included in the DPR amount to Rs. 41, 25,500.00/-.
182
Table 24Cost of Environmental Monitoring Plan
Total
Unit Cost
Item Location SeasonYear Samples in Total Cost Rs.
Rs.
No.
Environment Monitoring during Construction Stage
Air quality monitoring 4 3 2 24 7,100 170400
Metrological data 1 3 2 6 5,000 30000
Noise / vibration 4 3 2 24 2,000 48000
Soil analysis 4 3 2 24 5,500 132000
Water Quality Assessment at
4 4 2 32 6,500 208000
2 STP and 2 SPS sites
Travel and Transportation of
Lump sum 3,00,000
monitoring Team
Green Belt Development
along the periphery of STP's Lump sum 2,00,000
and SPS's
Sub total Rs.1088400.00
Environment Monitoring Cost (Operation Stage)
The estimated cost of the Environmental Management Plans that are not included in the DPR amount
toRs. 41, 25,500.00/-. Total Cost of Environmental Monitoring is Rs. 2923400/-. Total EMP Budget
including monitoring cost is Rs.70, 48,900.00/- (Say 70.49 Lac).
8 Social Development Outcomes and Issues
Introduction:
The cultural and social status of the residing community is very important and can be
understand in accordance with the region's existing baseline social status. The various
suggestions were given in the public consultation and during focus group discussion (FGD).
The discussion with the stake holders are put forwarded in this chapter.
1. STP Zone-A, Anupshahr (Location, Odour, Treated effluent, Land requirement etc.)
2. STP Zone-B, Anupshahr (Location, Odour, Treated effluent, Land requirement etc.)
3. MPS Zone-A, Anupshahr (Location, Noise, Approach to MPS, Land requirement etc.)
4. MPS Zone-B, Anupshahr (Location, Noise, Approach to MPS, Land requirement etc.)
Minutes:-
1. The land adjacent of Existing campus of STPs in both zones are vacant and local
people and stake holders have no objection in acquisition of land for construction
STPs for subsequent years up to 2048.
2. Land acquisition resulting in Relocation of households.
3. The people of Anupshahr are highly appreciate the sewerage project introduced by
Jal Nigam and also show their cooperative nature in listening the objective and
significance of project. There are no tribal settlements in the project area.
4. Construction works near schools and colleges are carried out during vacations and
works near hospitals are completed on priority basis (in shorter time period with
alternate provision of traffic, accessibility of exit/entry gates etc.), the impacts may
be limited
5. Sewer construction leads to the temporary tearing up of roads and increase in large
construction vehicles, which might impair traffic movement, especially in the
narrower roads should also be considered
184
6. Although temporary, concerns regarding failure to restore construction sites
including failure to close and appropriately fence off open pits were cited as safety
concerns especially for children.
7. Due to the construction of sewer lines, raw sewage that currently flows into the river
and/or overflows into the streets will now be routed to the STP. This will prevent
flooding of adjacent areas.
8. There will be a significant improvement in water quality due to effluent discharge
being treated.
9. To avoid the Dust generation provision of Water sprinkling should be provided
10. While execution of projects related to sewerage line, Jal Sansthan is responsible for
the damage caused to the public utility functions like drinking water pipe line.
11. Ensuring better access to household.
185
Discussions at the Ghat, Near Intercept Sewer tapping
186
Discussions at MPS-A, Zone-A
187
· Awareness about the project to be implemented under Mission Clean Ganga.
Only 35% people are aware that the project is to be implemented under Mission Clean
Ganga. Majority of the public doesn’t know about the project and only 10% people have
little information regarding the project.
The Awareness of the project has been predicted by means of questionnaire and the results
are presented below:
7%
10%
Doesn't know
48% Know
Little Information
35%
Only heard the name of Mission Clean
Ganga
Majority of people were in favor of the project implementation. The project was favoured
by the people looking the sanitary conditions of the town in the future.
The conditions in the town are very serious and the people residing are agreed with the fact.
All the population of the town favours the improvement in the present sanitation conditions
except the small chunk of 5 %.The response on the present sanitation conditions in the town
are shown below:
188
5%
60%
Do not Bother
· Household connections
In the present scenario, there are no household connections in the Anupshahr Town.
Majority people of around 90% are willing that there toilet should be connected to sewer
line while 2% people do not bother regarding such issue and about8 % people do not want
such kind of scheme. The response on the willingness for the sewer connection in the town
is shown below:.
2%
8%
90%
189
· Major water borne and vector borne diseases in the area
Diarrhea, Malaria, Typhoid, Cholera and dengue are the major water borne and vector
borne diseases in the area.
Mostly all (94 %) people agreed that there will be improvement in the sanitation status of
the city after project implementation. The response on prospect of improving sanitation
status in the town is shown below:
190
3%
3%
94%
Around 95% of respondents felt that, the condition in the coming future will worsen if such
kinds of schemes are not taken up. This project will help in improving the
sanitation/environment condition in the town as well as the water quality of the river Ganga
will also improve. The response on future scenario in the absence of project is shown below:
2%
3%
Worst Situation
No effect
191
· Effects of project in post completion stage
Pollution reduction: This project will surely help in the pollution reduction of the city.
Better Sanitation: The sanitation conditions in the town will improve.
Reduction in smell/flies: There will be control over such problems as there will be no open
drains.
Access to River: River Ganga would be more accessible as the quality of the water will
improve and there would not be direct discharge of nallah in the river.
· Conflicts during implementation/construction of the project
Most of the people are in favour of the project and they do not perceive any conflict during
implementation/construction of the project.
· Improvement in Ganga river quality
Around 95% people agreed that the quality of river Ganga will improve as there will be no
direct discharge of untreated sewage in the river.
· Implementation of the project in a timely and efficient manner
Around 75% people answered that the state authority will implement the project in a timely
and efficient manner while 20 % people answered that the implementation of the project
will take more time than estimated period of completion.
· Redressal mechanism in case of any grievances
Mostly people suggested that there should be a Grievance Redressal Officer and whose
contact number should be available at sites so that general people can contact him and
address him about their grievances.
· Cultural issues/threats against similar projects in the past
Mostly people do not perceive any threat and cultural issues for such kind of projects. It was
suggested that implementing agency should give maximum employment to local people for
the project implementation.
· Temporary disruption/disturbance during the construction/operation phase
Around 80% people are ready to cope with the temporary disruption/disturbances during
the construction/operation phase as the project is beneficial for the town and river Ganga.
Around 15% people suggested that there should be a provision of compensation if any
property of individual is damaged.
192
8.1 Social Development Outcomes of the sub project
· Access to sewer network: This service will cater to the projected population until the
year 2048. According to the DPR, population is expected to increase, approx. 63635 by
2048. In this time, waste water generation is expected to increase approx. 6.87 MLD.
Hence the increase sewerage will prevent outflow of waste water to the Ganga.
· Decrease in water pollution: Because of the sewer line connection, all the waste water
will be collected and directed to treatment plant, which only after treatment will be
disposed off to the river, hence decreasing the pollutant load in the river.
· Increase in aesthetic value of the project area: connection to sewer lines enhance the
aesthetic value of the area, as there will be more cleanliness and no wastewater
discharge to open area. This will also lead to appreciation in the property value. This
will eventually lead to increase in standard of living of the people in the project site.
The support for this statement comes from the counter-factual scenario observed in
areas with only nalas (bad odor, insects, etc.).
· Reduction in cost of implementation: According to DPR, wherever possible
development of sewerage will be integrated with existing GAP infrastructure to reduce
the overall investment cost.
· Cultural sentiments: Proper sewage disposal would increase the river water quality. As
the holy river is attached to many rituals and customs, enhanced river water quality
193
would connect to sentiments of the people.
8.2 Social Development Issues in Project Vicinity and Social Services to be provided by
the project
The social benefits of the proposed project are given above. The social services required to
ensure that these benefits are realized are given below:
• Ensure backward section of the society gets the facility: Some residents complained
that they did not feel they personally would benefit from the project as their houses
did not have sewer connection. Thus, increasing household connections will ensure
that project benefits are equitably distributed. Plans for increasing connections are
detailed in the DPR. Special care should be taken to ensure access for backward and
vulnerable sections of the society. Full benefits of the facilities proposed under DPR
cannot be realized unless a programme to improve coverage of branch sewers and
household connection is carried in parallel.
• Increasing public toilet facilities: In this project the component of Latrines and
connection to BPL families is taken, to improve or increase the public toilet facilities will
ensure that residents of Anupshahr without permanent housing and tourists
(especially visiting during 'Mela' are able to benefit from the increased sewerage
access. Increasing toilet access will decrease practices such as Open Defecation. This
eventually would lead to better water quality and would have better environment and
social ramifications.
• Targeting of economically weaker communities: for construction jobs related to sub-
project: In order to ensure that the economic benefits of the sub-project is felt by those
in need, those from backward communities should be specifically targeted for relevant
jobs.
• Proper clean-up of project debris: In order to maximize aesthetic benefits and ensure
that debris does not clog sewer path, proper clean-up of project areas must be
performed after the project is completed. Collection and disposal of debris is essential
for proper function of other essential processes like traffic routing, pedestrian
pathways, and clearance of dust and particles causing pollution. Clean area will also
enhance the aesthetic value and increase the property rate of the area.
194
9 Conclusion
The project report of the proposed sub-project for sewerage in Anupshahr town after
environment and social analysis concludes that the project falls in 'low impact' category
and have overall positive benefits on the life and environment of the people. As per
environmental and social management framework guidelines of NGRBA, Environmental
and Social Assessment, with a Generic Safeguard Management Plan was conducted for
addressing possible issues/ concerns arising from proposed project.
Impacts of activities identified during the assessment fell under two separate categories
of Construction and Operation. Although no such permanently negative or adverse
environmental or social impacts were identified, there were certain temporary impacts,
for which appropriate mitigation plans have also been suggested. The environmental
management plan ensures to suggest appropriate mitigation measure against the
issues/ concerns identified during the environmental and social analysis study. All the
social and environmental issues were appropriately studied and have been
substantiated using appropriate evidences, to ascertain the magnitude of their impacts.
Even the issues of public grievances and public notice have been taken care in the
report to confirm transparency during the project implementation. Report also ensures
that well defined institutional mechanism is in place to monitor and evaluate the
progress of the project during construction, implementation and operation phases.
195
Annexure
Annexure
Page 12
2 Ambient Air Quality Monitoring location Map
3 Ambient Noise Monitoring location Map
4 Water Quality Monitoring Location Map
5 Soil Quality Monitoring Location Map
6 STP & MPS Plan with Green Area
a) Zone A
Storage of municipal
waste screen
d) MPS Zone B
Storage of municipal
waste screen
7 Minutes of Meeting
Minutes:-
1. The land adjacent of Existing campus of STPs in both zones are vacant and local
people and stake holders have no objection in acquisition of land for construction
STPs for subsequent years up to 2048.
2. Land acquisition resulting in Relocation of households.
3. The people of Anupshahr are highly appreciate the sewerage project introduced by
Jal Nigam and also show their cooperative nature in listening the objective and
significance of project.
There are no tribal settlements in the project area.
4. Construction works near schools and colleges are carried out during vacations and
works near hospitals are completed on priority basis (in shorter time period with
alternate provision of traffic, accessibility of exit/entry gates etc.), the impacts may
be limited
5. Sewer construction leads to the temporary tearing up of roads and increase in large
construction vehicles, which might impair traffic movement, especially in the
narrower roads should also be considered
6. Although temporary, concerns regarding failure to restore construction sites
including failure to close and appropriately fence off open pits were cited as safety
concerns especially for children.
7. Due to the construction of sewer lines, raw sewage that currently flows into the river
and/or overflows into the streets will now be routed to the STP. This will prevent
flooding of adjacent areas.
8. There will be a significant improvement in water quality due to effluent discharge
being treated.
9. To avoid the Dust generation provision of Water sprinkling should be provided
10. While execution of projects related to sewerage line, JalSansthan is responsible for
the damage caused to the public utility functions like drinking water pipe line.
11. Ensuring better access to household.
Signature of Participants:-
8 MET Data
Temperature Variation:
MET Data