RECAP FINAL
POZO CELEUS 1
Table of Contents
1. WELL BLUEPRINT
2. RESUMEN DEL POZO
3. CONCLUSIONES Y RECOMENDACIONES
4. COSTO TOTAL DEL POZO
5. RESUMEN DEL INTERVALO
6. DISCUSION DEL INTERVALO
7. COSTO DEL INTERVALO
8. PROPIEDADES DEL FLUIDO
9. CONCENTRACION DE LOS PRODUCTOS
10. VOLUMENES
11. RESUMEN OPERACIONAL, DIA A DIA
12. GRAFICAS
PROPIEDADES LODO BASE AGUA vs. PROFUNDIDAD 1
PROPIEDADES LODO BASE AGUA vs. PROFUNDIDAD 2
PROPIEDADES LODO BASE AGUA vs. PROFUNDIDAD 3
COSTO DIARIO vs. PROFUNDIDAD
ANEXOS
SIMULACIONES DFG
Created: 04-23-2012
Blue Print
Distance Drilled ft 11,412 Fluid Cost Per Fluid Volume* $/bbl 30.48
Maximum Deviation º 43.67 Fluid Cost Per Length Drilled* $/ft 19.01
Max. Horz. Displacement ft 7,710 Fluid Cost/Vol of Hole Drilled* $/bbl 122.26
Casing Design
Description Set Date & Top MD Top TVD End MD End TVD CSG OD CSG ID Max. Hole Hole MD Hole TVD
Time Size
ft ft ft ft in in in ft ft
13.375 K-55 54.50 03-15-2012 00:00 0 0 585 585 13.375 12.615 20.000 585 585
9.625 N-80 43.50 04-04-2012 12:00 0 0 8,388 7,800 9.625 8.755 13.000 8,863 8,320
7.000 N-80 29.00 04-19-2012 00:00 8,223 7,824 11,619 8,223 7.000 6.184 8.500 11,619 8,223
Interval BHT Max. Fluid Cost Total Total Total Interval Cost $
Int # Fluid Name
Days Dens Material Charges
Charges Not in
Not in Fluid
Fluid
ºF ppg Plan Actual Variance
Executive Summary
RESUMEN EJECUTIVO
La primera sección del pozo Celeus 1 se perforó con hueco de 17 ½¨ desde superficie hasta 587 ft
verticalmente. Este intervalo se perforó con BHA convencional a través de la Formación Guayabo utilizando
el sistema de fluido AQUAGEL/X-TEND II. Este intervalo estaba programado para ser perforado hasta 2500
ft pero por problemas de retorno de lodo por el hueco conductor se decidió dejar el intervalo hasta 587 ft. Se
bajó revestimiento de 13 3/8'' hasta 585 ft. Durante el retorno de lodo por el hueco conductor y superficie de
la locación, se bombearon píldoras LCM de fibra fina y gruesa para solventar el incidente.
La segunda sección se perforó con Broca PDC de 12 1/4” y BHA direccional desde 587 ft hasta 8863 ft,
aunque estaba programado hasta 10250 ft se debió detener para corregir trayectoria de pozo sentando
casing 9 5/8" a 8388 ft, para luego bombear tapón de cemento y retomar trayectoria. Se emplearon en esta
sección, los sistemas de fluido de perforación POLIMERO FILTRADO RELAJADO y POLIMERO INHIBIDO a
través de las Formaciones GUAYABO, LEON, CARBONERA C1 y C2 diseñado por HALLIBURTON para
suministrar una adecuada limpieza del pozo, además de asegurar la estabilidad química y mecánica del
mismo con. El sistema de fluidos se mantuvo con propiedades de filtrado relajado las cuales fueron ajustadas
previo al ingreso a la Formación León, buscando lavar la zona arcillosa de la Formación Guayabo. A partir de
la Formación León se ajustaron las concentraciones de los productos para alcanzar mejor control de filtrado y
proporcionar las condiciones óptimas para lograr la estabilidad química y mecánica del pozo. La unidad de
floculación selectiva (UFS) fue operada hasta 8863 ft, final de sección.
La fase final de 8 ½” se empleó sistema BARADRIL-N, que se mantuvo en los tanques del activo mientras se
realizó el drill out con agua en circuito corto por la canal hacia el tanque de píldora. La adición de CLAYSEAL
PLUS como inhibidor, FILTER-CHEK y PAC L/R como controladores de filtrado, BARAZAN D PLUS como
viscosificante, BARACARB DF 25/50, como densificantes y BARACARB DF 150 como material puenteante,
contribuyó al logro de los objetivos de la operación relacionadas con el programa de fluidos. Adicionalmente,
a solicitud de la operadora, se adicionó lubricante BARO-LUBE GOLD SEAL para contrarrestar el torque
generado por trabajo direccional. La sección finalizo a 11624 ft sentando liner de 7”.
Created: 04-23-2012
CONCLUSIONES Y RECOMENDACIONES
SECCION 17 ½”
• El lodo suministró buenas condiciones de limpieza del hueco, reflejadas en los viajes de tubería y en
la corrida del revestimiento de 13 3/8”.
• Para minimizar el taponamiento del flow line, se debe trabajar con una reología del fluido baja, VF
entre 40 - 50 seg, VP entre 10 – 14 cp, YP entre 12 - 16 lbs/100 ft2 y Geles no progresivos.
• El usar una de las bombas del taladro para limpiar el flow line hace que el taponamiento de este sea
menor.
• Se recomienda mantener una ROP controlada para prevenir cargar el anular con cortes y no causar
taponamientos del flow line.
• Para minimizar o prevenir pérdidas de fluido en subsuelo durante la perforación de esta fase es
recomendable no repasar con tanta rapidez la parada perforada para evitar el efecto pistón
(surgencia) considerando las propiedades reológicas del lodo para garantizar una limpieza adecuada
del hueco.
SECCION 12 ¼”
• Se debe continuar con la buena práctica operacional de repasar cada parada perforada 2 ó 3 veces,
obteniendo un tiempo total de circulación entre conexiones de aproximadamente de 10 a 15 minutos,
para ayudar a descargar el anular de cortes perforados debido a las altas ratas de penetración que
se alcanzan en esta fase. Esta práctica contribuye a evitar que los cortes se queden pegados a las
Created: 04-23-2012
paredes de la formación, taponen el flow line y aumenten la presión por una alta carga anular que
puede inducir pérdidas.
• La concentración de CLAYSEAL en promedio de 6 ppb, mostró una buena inhibición de las arcillas
de las formaciones perforadas de acuerdo a los cortes observados en las shaker’s. De igual manera
el hueco viajado y acondicionado presentó estabilidad e integridad hasta el final de las operaciones
de la segunda fase.
• Se recomienda perforar la segunda sección con mallas finas, siempre y cuando el caudal de bomba
lo permita, optimizando así el sistema primario de control de sólidos.
• Ampliar capacidad de tanque Intermedio 2 para proveer mejor control del peso y de sólidos
incorporados al fluido, ya que de éste tanque succionan las centrifugas decantadoras.
• Dividir tanque de succión en dos compartimientos para mayor funcionalidad. Con esto se podrían
fabricar fluidos diferentes, con diferentes configuraciones en circuito corto empleando canal.
• Modificar tanque de trampa de arena. Actualmente solo cuenta con paso por rebose al tanque de
retorno y su descarga inferior no esta conectada al catch tank. Sólo el tanque de retorno está
conectado al catch tank, dificultando la remoción de sólidos de la trampa y favoreciendo enorme
acumulación en el mismo por su gran volumen. Se recomienda un diseño no rectangular como es
actualmente.
• Disminuir la altura de los agitadores con el fin de garantizar una adecuada mezcla de aditivos.
• Para agilizar llenado de los tanques del sistema y de reserva con agua, se recomienda instalar línea
directa desde el tanque de agua del equipo con opción de conectar a las bombas del mismo, o
instalar línea de mayor capacidad.
Created: 04-23-2012
• No existe clara señalización de las válvulas, no se sabe cuando esta 100% cerrada o 100% abierta,
dando a lugar a mezclas no requeridas de fluidos, algunos de ellos como por ejemplo
contaminados con cemento. Es necesario corregir este sistema de información y a su vez cambiar
muchas de ellas debido al mal estado en que se encuentras y no ofrecen un óptimo desempeño
• El equipo actualmente no posee un mud bucket apropiado, en los viajes la cantidad de lodo perdido
es alta, debido a la ausencia de éste elemento, este elemento debe tener una manguera de
desfogue al flow line o en su defecto al cellar, no como se está manejando en la actualidad.
• Revisar los embudos ya que en varias ocasiones se taponan por sí solos, es evidente falta de
mantenimiento de los mismos, evidencia corrosión interna y fatiga del material.
Created: 04-23-2012
Engineering/Services
Drilling Fluids Engineer DAY 93 74,400.00
Tecnico Floculacion Selectiva DAY 17 5,950.00
SubTotal $ 80,350.00
Equipment Cost
Unidad de Floculación DAY 8 3,200.00
SubTotal $ 3,200.00
Fluids/Products: Cementing Cost
BARACARB-DF 25 50 kg BAG 200 2,500.00
BARACARB-DF 50 50 kg BAG 218 2,725.00
FILTER-CHEK 50 lbm BAG 15 1,560.00
GLUTARALDEHYDE - BIOCIDE 5 Gal CAN 1 82.00
PAC-L 50 lbm BAG 3 367.50
PAC-R 50 lbm BAG 2 245.00
WALL-NUT MEDIUM 50 lbm BAG 10 210.00
SubTotal $ 7,689.50
Fluids/Products: Drilling Cost
AQUAGEL 50 lbm BAG 479 10,538.00
BARACARB-DF 150 50 kg BAG 260 3,250.00
BARACARB-DF 25 50 kg BAG 520 6,500.00
BARACARB-DF 50 50 kg BAG 253 3,162.50
BARACARB-DF 600 50 kg BAG 20 250.00
BARAZAN D PLUS 25 lbm BAG 180 12,272.40
BAROFIBRE COARSE 40 lbm BAG 34 680.00
BAROFIBRE 25 lbm BAG 75 1,125.00
BARO-LUBE GOLD SEAL 275 Gal IBC 3 14,250.00
BARO-TROL PLUS 50 lbm BAG 100 6,100.00
CAUSTIC SODA 25 kg BAG 40 1,600.00
CLAY GRABBER 5 Gal CAN 61 5,490.00
CLAYSEAL PLUS 55 Gal DRUM 15 14,265.00
CLAYSEAL 55 Gal DRUM 50 52,025.00
FILTER-CHEK 50 lbm BAG 385 40,040.00
GLUTARALDEHYDE - BIOCIDE 5 Gal CAN 43 3,526.00
KWIK SEAL COARSE 40 lbm BAG 50 1,600.00
KWIK SEAL FINE 40 lbm BAG 54 1,728.00
LIME 25 kg BAG 50 450.00
PAC-L 50 lbm BAG 137 16,782.50
PAC-R 50 lbm BAG 68 8,330.00
STEELSEAL 100 50 lbm BAG 50 4,800.00
STEELSEAL 50 50 lbm BAG 50 4,800.00
THERMA-THIN 5 Gal CAN 32 2,688.00
X-TEND II 2 lbm BAG 55 742.50
SubTotal $ 216,994.90
Fluid/Product: Lost Damage
BAROFIBRE 25 lbm BAG 6 90.00
SubTotal $ 90.00
Engineering/ Other Cost
AQUAGEL 50 lbm BAG 2 44.00
BAROFIBRE COARSE 40 lbm BAG 4 80.00
SubTotal $ 124.00
Unknown
Movilizacion Unidad de Floculacion Selectiva EA 1 1,950.00
Unidad de Floculación DAY 4 1,600.00
SubTotal $ 3,550.00
Total Well Cost $ 311,998.40
Interval Summary
Interval# 01 Bit Size 17.500 in Avg Hole Size 19.153 in
Casing Design
Description Set Date & Top MD Top TVD EndMD EndTVD CSG OD CSG ID Max. Hole Hole MD Hole TVD
Time Size
ft ft ft ft in in in ft ft
13.375 K-55 54.50 03-15-2012 00:00 0 0 585 585 13.375 12.615 20.000 585 585
Alkalinity Control
LIME AQUAGEL / Chemical 25 kg BAG 6.000 54.00
Total $ 54.00
Lost Circulation Additive
BARACARB-DF 150 AQUAGEL / Chemical 50 kg BAG 21.000 262.50
BARACARB-DF 600 AQUAGEL / Chemical 50 kg BAG 16.000 200.00
BAROFIBRE COARSE AQUAGEL / Chemical 40 lbm BAG 25.000 500.00
BAROFIBRE AQUAGEL / Chemical 25 lbm BAG 75.000 1,125.00
KWIK SEAL COARSE AQUAGEL / Chemical 40 lbm BAG 50.000 1,600.00
KWIK SEAL FINE AQUAGEL / Chemical 40 lbm BAG 54.000 1,728.00
Total $ 5,415.50
Viscosifier
AQUAGEL AQUAGEL / Chemical 50 lbm BAG 467.000 10,274.00
X-TEND II AQUAGEL / Chemical 2 lbm BAG 46.000 621.00
Total $ 10,895.00
Interval Summary
Interval# 02 Bit Size 12.250 in Avg Hole Size 13.000 in
Casing Design
Description Set Date & Top MD Top TVD EndMD EndTVD CSG OD CSG ID Max. Hole Hole MD Hole TVD
Time Size
ft ft ft ft in in in ft ft
13.375 K-55 54.50 03-15-2012 00:00 0 0 585 585 13.375 12.615 20.000 585 585
9.625 N-80 43.50 04-04-2012 12:00 0 0 8,388 7,800 9.625 8.755 13.000 8,863 8,320
Alkalinity Control
CAUSTIC SODA AQUAGEL / Chemical 25 kg BAG 31.000 1,240.00
Polymer Mud
Polimero Inhibido
LIME AQUAGEL / Chemical 25 kg BAG 44.000 396.00
Polymer Mud
Polimero Inhibido
Total $ 1,636.00
Filtration Control
FILTER-CHEK No Fluid 50 lbm BAG 235.000 24,440.00
PAC-L No Fluid 50 lbm BAG 75.000 9,187.50
PAC-R No Fluid 50 lbm BAG 42.000 5,145.00
Total $ 38,772.50
Flocculant
CLAY GRABBER AQUAGEL / Chemical 5 Gal CAN 61.000 5,490.00
Polymer Mud
Polimero Inhibido
Total $ 5,490.00
Lost Circulation Additive
BARACARB-DF 150 AQUAGEL / Chemical 50 kg BAG 199.000 2,487.50
Polymer Mud
Polimero Inhibido
BARACARB-DF 25 No Fluid 50 kg BAG 324.000 4,050.00
BARACARB-DF 50 No Fluid 50 kg BAG 257.000 3,212.50
Interval Summary
Interval# 02 Bit Size 12.250 in Avg Hole Size 13.000 in
Product Function / Name Fluid Name Packaging Quantity Used Product Cost
Interval Summary
Interval# 03 Bit Size 8.500 in Avg Hole Size 8.550 in
Casing Design
Description Set Date & Top MD Top TVD EndMD EndTVD CSG OD CSG ID Max. Hole Hole MD Hole TVD
Time Size
ft ft ft ft in in in ft ft
13.375 K-55 54.50 03-15-2012 00:00 0 0 585 585 13.375 12.615 20.000 585 585
9.625 N-80 43.50 04-04-2012 12:00 0 0 8,388 7,800 9.625 8.755 13.000 8,863 8,320
7.000 N-80 29.00 04-19-2012 00:00 8,223 7,824 11,619 8,223 7.000 6.184 8.500 11,619 8,223
Alkalinity Control
CAUSTIC SODA BARADRIL-N 25 kg BAG 9.000 360.00
Drill Water
Total $ 360.00
Filtration Control
FILTER-CHEK BARADRIL-N 50 lbm BAG 165.000 17,160.00
Drill Water
PAC-L BARADRIL-N 50 lbm BAG 65.000 7,962.50
Drill Water
PAC-R BARADRIL-N 50 lbm BAG 28.000 3,430.00
Drill Water
Total $ 28,552.50
Lost Circulation Additive
BARACARB-DF 150 BARADRIL-N 50 kg BAG 40.000 500.00
Drill Water
BARACARB-DF 25 BARADRIL-N 50 kg BAG 396.000 4,950.00
Drill Water
BARACARB-DF 50 No Fluid 50 kg BAG 214.000 2,675.00
WALL-NUT MEDIUM No Fluid 50 lbm BAG 10.000 210.00
Total $ 8,335.00
Lubricant
BARO-LUBE GOLD SEAL BARADRIL-N 275 Gal IBC 3.000 14,250.00
Drill Water
Total $ 14,250.00
Interval Summary
Interval# 03 Bit Size 8.500 in Avg Hole Size 8.550 in
Product Function / Name Fluid Name Packaging Quantity Used Product Cost
Misc Additive
GLUTARALDEHYDE - BIOCIDE BARADRIL-N 5 Gal CAN 17.000 1,394.00
Drill Water
Total $ 1,394.00
Shale Control Agent
CLAYSEAL PLUS BARADRIL-N 55 Gal DRUM 15.000 14,265.00
Drill Water
Total $ 14,265.00
Thinner/Deflocculant
THERMA-THIN BARADRIL-N 5 Gal CAN 14.000 1,176.00
Drill Water
Total $ 1,176.00
Viscosifier
AQUAGEL No Fluid 50 lbm BAG 1.000 22.00
BARAZAN D PLUS BARADRIL-N 25 lbm BAG 30.000 2,045.40
Drill Water
Total $ 2,067.40
Interval Discussion
Interval# 01 Top of Interval (MD/TVD) 0/0
From Date 03-07-2012 Bottom of Interval (MD/TVD) 722 / 722 ft
To Date 03-18-2012 Avg Hole Size / Bit Size 19.153 / 17.500 in
SECCION 17 ½ ’’
FORMACION: GUAYABO
OBJETIVOS
Perforar hueco de 17 ½ ” desde superficie hasta 2500 ft a través de la Formación Guayabo para correr y
sentar revestimiento de 13 3/8”, utilizando el sistema de lodo AQUAGEL- X TEND II con las propiedades y
características necesarias para lograr la estabilidad del hueco y una buena capacidad de acarreo de cortes
hasta superficie.
El sistema de lodo utilizado para perforar esta sección fue el tipo AQUAGEL- X TEND II. Se prepararon 1010 bbl
de fluido de 8.6 ppg para el inicio de la fase.
La concentración de bentonita, AQUAGEL, fue 12 ppb, con el fin de no generar altas viscosidades y permitir
la reutilización de una parte del fluido para la siguiente sección al manejar valores bajos de MBT. Además,
se realizaron adiciones de X-TEND II como extendedor de bentonita a una concentración de 0.05 ppb para
obtener la reología necesaria para asegurar la limpieza del hueco perforado y un adecuado encapsulamiento
para mantener el control de las arcillas reactivas.
La densidad del fluido al inicio del intervalo fue de 8.6 ppg proporcionada por la adición de bentonita al
sistema activo y se mantuvo lo más bajo posible evitando al máximo la incorporación de sólidos. Los valores
de MBT manejados no superaron 7 ppb Eq. El pH se mantuvo en 8,5 a 10 para minimizar de esta manera la
incorporación de arcillas reactivas al sistema activo.
Una vez alcanzada la profundidad final de la fase, se bajó revestimiento de 13 3/8’’ y se realizó la
cementación de acuerdo al programa. Durante el viaje de acondicionamiento de hueco, corrida del
revestimiento, circulaciones y cementación del revestimiento de 13 3/8¨ siempre se observaron retornos
normales.
1097 bbl de lodo AQUAGEL- X TEND II fueron recuperados para ser utilizados en la etapa de 12 1/4”’.
Created: 04-23-2012
Interval Discussion
Interval# 01 Top of Interval (MD/TVD) 0/0
From Date 03-07-2012 Bottom of Interval (MD/TVD) 722 / 722 ft
To Date 03-18-2012 Avg Hole Size / Bit Size 19.153 / 17.500 in
• SHAKERS: La primera línea para el control de los sólidos de perforación consta de 3 shaker’s
Mongoose, vestidas con mallas 84 y 110 mesh.
Durante esta fase se prepararon 1656.7 bls de lodo AQUAGEL- X TEND II. El volumen del hueco perforando
fue de 92 bbl (Diámetro 17 ½”) y el volumen promedio en los tanques de superficie fue de 640 bbl. No fue
necesario diluir para bajar la reología del fluido. En total se perforaron 587 ft desde superficie hasta la
profundidad total del intervalo.
Created: 04-23-2012
Interval Discussion
Interval# 02 Top of Interval (MD/TVD) 722 / 722
From Date 03-19-2012 Bottom of Interval (MD/TVD) 8,863 / 8,320 ft
To Date 04-10-2012 Avg Hole Size / Bit Size 13.000 / 12.500 in
SECCION 12 1/4”
OBJETIVOS
Perforar hueco de 12 1/4” hasta 10250 ft para correr y sentar revestimiento de 9 5/8”, sin embargo, fue
necesario corregir trayectoria de pozo deteniendo perforación a 8863 ft, sentando casing 9 5/8" a 8388 ft,
para luego bombear tapón de cemento y retomar trayectoria. Se emplearon en esta sección, sistemas de
fluido de perforación POLIMERO FILTRADO RELAJADO y POLIMERO INHIBIDO con las propiedades y
características necesarias para lograr la estabilidad del hueco y una buena capacidad de transporte de cortes
hasta superficie.
Perforar el intervalo dentro del tiempo y presupuesto programado, cero horas perdidas y sin accidentes.
Created: 04-23-2012
Interval Discussion
Interval# 02 Top of Interval (MD/TVD) 722 / 722
From Date 03-19-2012 Bottom of Interval (MD/TVD) 8,863 / 8,320 ft
To Date 04-10-2012 Avg Hole Size / Bit Size 13.000 / 12.500 in
Los aditivos empleados para el sistema POLIMERO fueron: CLAYSEAL como inhibidor, CLAY GRABBER
como encapsulador de arcilla FILTER-CHEK y PAC L/R como controladores de filtrado, BARAZAN D PLUS
como viscosificante para aumentar los valores reológicos, BARACARB DF 25/50, para densificar y
BARACARB DF 150 como material puenteante.
La Formación Guayabo fue perforada, en esta sección, con un fluido de concentraciones moderadas de
polímero para asegurar lecturas de control de filtrado entre 7 – 8 ml permitiendo lavar la formación
previniendo problemas por hueco apretado por hinchamiento de arcillas, construyendo de esta manera un
hueco de mayor diámetro que no generara restricciones durante los viajes de tubería y permitiendo
igualmente perforar con altas ratas de penetración.
A partir de la Formación León se perforó con un incremento en la concentración de los polímeros FILTER-
CHEK y PAC L/R estos permitieron elevar el punto cedente, la fuerza de gel y controlar la rata de filtración
hacia las formaciones permeables. Estos materiales fácilmente dispersables, controlaron la pérdida de
filtrado taponando mecánicamente las lutitas y demás formaciones permeables expuestas. El filtrado se
mantuvo inferior a los valores programados (6-10 ml) durante toda la perforación de la fase a partir de León
basado en la experiencia de BAROID al perforar pozos del área. Además, la adición de BAROTROL PLUS
(adicionado antes de penetrar las lutitas de la Fm. León) también contribuyó en el control del filtrado
efectuando un bloqueo mecánico por aporte de sólidos a la torta del lodo. Además se realizó puenteo de
secciones permeables con BARACARB DF 50/150 y STEELSEAL 100/50 en forma horaria con el fin de
prevenir presiones diferenciales que conllevaran a pegas del mismo tipo.
Se adicionó CLAY SEAL durante toda la fase como inhibidor de la hidratación y la dispersión de las arcillas
reactivas de la Fm. Guayabo de 4 – 5 ppb y las lutitas de la Fm. León de 5 – 7 ppb hasta finalizar la fase para
proporcionar así estabilidad y disminuir la posibilidad de embotamiento de la broca.
Para mantener el fluido de perforación con la menor cantidad de sólidos de perforación se pretendió
optimizar el desempeño de la centrífuga LGS, mediante la adición de CLAY GRABBER diluido en agua,
desde la Unidad de Floculación Selectiva (UFS) pero las citadas centrifugas continuaron con pésima
eficiencia y funcionando a intervalos irregulares. Al entrar en contacto el producto diluido con el lodo que
entra a las centrífugas, instantáneamente se flocula la arcilla del lodo facilitando la remoción de estos sólidos
Created: 04-23-2012
Interval Discussion
Interval# 02 Top of Interval (MD/TVD) 722 / 722
From Date 03-19-2012 Bottom of Interval (MD/TVD) 8,863 / 8,320 ft
To Date 04-10-2012 Avg Hole Size / Bit Size 13.000 / 12.500 in
por la centrífuga. El proceso de floculación selectiva fue suspendido al finalizar la sección (8863 ft).
Durante la perforación de la fase se bombearon píldoras viscosas de limpieza aproximadamente cada 600 ft
y finalizando sección cada 400 ft. Estas píldoras ayudaron en la limpieza del hueco, observando un aumento
en el aporte de cortes al retornar las mismas.
Se empleó cal para mantener el pH del sistema. Adicionalmente, se trató el fluido con Soda caústica y
bactericida Glutaraldehído previo a los viajes de acondicionamiento para evitar la degradación por bacterias
del fluido al estar en condiciones estáticas durante tiempos prolongados en hueco abierto.
La densidad del fluido se mantuvo siempre en el rango programado de acuerdo al perfil de densidad
propuesto.
Los valores reológicos obtenidos durante la perforación de la sección, y durante los viajes de
acondicionamiento aseguraron la limpieza del hueco. El yield point se manejó dentro del siguiente rango 17 –
38 lb/100 ft2 y el Tau 0 entre 4 – 9 lb/100ft2
Para optimizar la limpieza del hueco se bombearon píldoras viscosas aproximadamente cada 600 ft
perforados. Las píldoras de limpieza que se emplearon con resultados favorables tienen como finalidad
disminuir la carga de cortes en el anular facilitando los viajes.
Además, se realizó seguimiento a las condiciones de limpieza mediante el software DFG®, el cual reflejo
condiciones favorables de limpieza con mínima carga efectiva de cortes en el anular y se continuó monitoreo
de cavings y parámetros de perforación para verificar el avance de la perforación.
Created: 04-23-2012
Interval Discussion
Interval# 02 Top of Interval (MD/TVD) 722 / 722
From Date 03-19-2012 Bottom of Interval (MD/TVD) 8,863 / 8,320 ft
To Date 04-10-2012 Avg Hole Size / Bit Size 13.000 / 12.500 in
En esta sección fue evidente el pésimo desempeño de la centrifugas decantadoras disponibles, lo cual
requirió fabricación de volúmenes adicionales para control de peso y MBT al igual que el descarte en
promedio de 200 bbls diarios del sistema.
• SHAKERS: La primera línea para el control de los sólidos de perforación consta de 3 shaker’s
Mongoose, vistiéndose con 4 mallas API 140-200. Se observó eficiente desempeño durante la fase.
• MUD CLEANER. La segunda línea de control de sólidos está compuesta de un desarenador con 2
conos de 12” y un desarcillador con 8 conos de 4”. Además, de una Shaker vestida con 3 mallas API
200. El desempeño observado durante la perforación fue excelente, alcanzando la presión de
operación y el fluido salía en spray, observándose un desempeño superior en su descarga al de las
centrifugas decantadoras.
Se mezclaron 3335.7 bbl de fluido. Se mantuvo la adición constante de lodo fresco a través de las píldoras
viscosas pesadas para mantener los niveles en superficie y diluir el sistema activo. En total se perforaron
8278 ft desde el inicio hasta la profundidad total del intervalo (TD @ 8863 ft).
El costo para esta sección incluye las diluciones programadas y realizadas para mantener el fluido dentro de
los parámetros propuestos y según los requerimientos de la operación.
Created: 04-23-2012
Interval Discussion
Interval# 03 Top of Interval (MD/TVD) 9,075 / 8,320
From Date 04-11-2012 Bottom of Interval (MD/TVD) 11,624 / 10,385 ft
To Date 04-20-2012 Avg Hole Size / Bit Size 8.550 / 8.500 in
SECCION 8 ½”
OBJETIVOS
Perforar hueco de 8 1/2’’ hasta 11386 ft para correr y sentar liner de 7”, utilizando el sistema de fluido de
perforación BARADRIL-N con las propiedades y características necesarias para lograr la estabilidad del
hueco y una buena capacidad de transporte de cortes hasta superficie.
Perforar el intervalo dentro del tiempo y presupuesto programado, cero horas perdidas y sin accidentes.
En la sección se fabricaron 1387.3 bbl de sistema BARADRIL-N para dar inicio a la perforación. Este sistema
se mantuvo en los tanques del activo mientras se realizó el drill out con agua en circuito corto por la canal
hacia el tanque de píldora.
La sección se caracterizó por la presencia de arcillas reactivas que se controlaron con la adición de
inhibidores químicos como consecuencia de la exposición de los miembros inferiores de la Fm. Carbonera
que no fue revestida en la sección anterior. Se observó durante la perforación de las formaciones arcillosas y
lutiticas, estabilidad mecánica con despreciable producción de cavings, inferiores a 0.2 cm.
Los aditivos empleados para el sistema BARADRIL-N fueron: CLAYSEAL PLUS como inhibidor, FILTER-
CHEK y PAC L/R como controladores de filtrado, BARAZAN D PLUS como viscosificante para aumentar los
valores reológicos, BARACARB DF 25/50, para densificar a 8.9 ppg iniciando y finalizando en 9.3 ppg y
BARACARB DF 150 como material puenteante. Adicionalmente, a solicitud de la operadora se adiciono
lubricante BARO-LUBE GOLD SEAL para contrarrestar el torque generado por trabajo direccional.
Created: 04-23-2012
Interval Discussion
Interval# 03 Top of Interval (MD/TVD) 9,075 / 8,320
From Date 04-11-2012 Bottom of Interval (MD/TVD) 11,624 / 10,385 ft
To Date 04-20-2012 Avg Hole Size / Bit Size 8.550 / 8.500 in
La sección fue perforada con fluido de concentraciones moderadas de polímero para asegurar lecturas de
control de filtrado entre 4 – 6 ml previniendo problemas por perdidas en formaciones con microfracturas o de
baja presión.
Se adicionó CLAY SEAL PLUS durante toda la fase como inhibidor de la hidratación y la dispersión de las
arcillas reactivas en una concentración de hasta 6 ppb para proporcionar así inhibicion y disminuir la
posibilidad de embolamiento de la broca en intervalos arcillosos.
Durante la perforación de la fase se bombearon píldoras viscosas de limpieza las cuales ayudaron en la
limpieza del hueco, observando un aumento en el aporte de cortes al retornar las mismas y previniendo la
formación de acumulación de cortes por alto ángulo de hueco.
Adicionalmente, se trató el fluido con Soda caústica y biocida Glutaraldehído previo a los viajes de
acondicionamiento para el viaje corto al zapato, viaje a superficie y corrida de liner para evitar la degradación
por bacterias del fluido al estar en condiciones estáticas durante tiempos prolongados en hueco abierto.
La densidad del fluido se mantuvo siempre en el rango programado de acuerdo al perfil propuesto.
Los valores reológicos obtenidos durante la perforación de la sección, y durante los viajes de
acondicionamiento aseguraron la limpieza del hueco. El Yield Point se manejó dentro del siguiente rango 14
– 27 lb/100 ft2 y el Tau 0 entre 1.8 – 8.5 lb/100ft2
Las píldoras de limpieza que se emplearon con resultados favorables tienen como finalidad disminuir la carga
de cortes en el anular facilitando el avance de la perforación y los viajes de tubería.
Además, se realizó seguimiento a las condiciones de limpieza mediante el software DFG®, el cual reflejo
condiciones favorables de limpieza con mínima carga efectiva de cortes en el anular y se continuó monitoreo
de cavings y parámetros de perforación para verificar el avance de la perforación.
Created: 04-23-2012
Interval Discussion
Interval# 03 Top of Interval (MD/TVD) 9,075 / 8,320
From Date 04-11-2012 Bottom of Interval (MD/TVD) 11,624 / 10,385 ft
To Date 04-20-2012 Avg Hole Size / Bit Size 8.550 / 8.500 in
• SHAKERS: La primera línea para el control de los sólidos de perforación consta de 3 shaker’s
Mongoose, vistiéndose con 4 mallas API 140-200. Se observó eficiente desempeño durante la fase.
• MUD CLEANER. La segunda línea de control de sólidos está compuesta de un desarenador con 2
conos de 12” y un desarcillador con 8 conos de 4”. Además, de una Shaker vestida con 3 mallas API
200. El desempeño observado durante la perforación fue excelente, alcanzando la presión de
operación y el fluido salía en spray.
• CENTRIFUGAS. La tercera línea de control de sólidos, para esta sección, estuvo compuesta por una
centrifuga decantadora SHARPLES 5400 que reemplazo a la ALFALAVAL . Su desempeño fue
apenas aceptable ya que hay que tener en cuenta que en esta sección se perfora mayoritariamente
formaciones de areniscas, sin embargo debió emplearse otra centrifugas hacia el final de la sección
para control de peso.
Se mezclaron 1387.3 bbl de sistema BARADRIL-N. En total se perforaron 2761 ft desde el inicio hasta la
profundidad total del intervalo (TD @ 11624 ft).
Created: 04-23-2012
Report MD/TVD FL Density Funn Rheology 120 ºF Filtration Filtrate Analysis MBT Sand Retort Analysis Rheometer Dial Readings
No Temp Visc
PV API HTHP Cake Cake Temp pH Pm Pf Mf Cl Total 600 300 200 100 6 3
lbfs^n/100ft2 % by vol
API HTHP Hardness
% by Corr NAP
ft ºF ppg sec/qt cp YP 10S 10M 30M mL/30min mL/30min 32nd in ºF mL mL mL mg/l mg/l ppb eq. LGS Water
vol Solid Base
001 0/0 8.60 75 10 20 7 9 11 8.5 0.10 0.10 0.50 220 40 1.3 0.4 98.5 40.0 30.0 21.0 15.0 8.0 6.0
006 0/0 8.60 64 9 19 7 10 12 9 0.20 0.10 0.30 250 20 1.8 1.4 98.0 37.0 28.0 23.0 18.0 11.0 8.0
006 0/0 8.60 64 9 19 8 10 12 9 0.20 0.10 0.30 300 50 1.7 1.4 98.0 37.0 28.0 23.0 17.0 11.0 7.0
006 0/0 90 8.60 65 9 18 8 11 13 9.1 0.20 0.10 0.30 300 50 0.10 1.7 1.4 98.0 36.0 27.0 22.0 18.0 12.0 8.0
007 350/350 8.70 66 10 19 8 10 12 9.2 0.20 0.10 0.30 300 50 5.0 0.20 1.7 0.7 98.0 39.0 29.0 21.0 18.0 12.0 8.0
007 350/350 8.70 66 10 19 8 10 12 9.1 0.20 0.10 0.30 300 50 5.0 0.10 1.7 0.7 98.0 39.0 29.0 22.0 17.0 12.0 8.0
007 350/350 8.70 66 10 19 7 9 11 9.1 0.20 0.10 0.30 300 50 5.0 1.7 0.7 98.0 39.0 29.0 21.0 16.0 11.0 7.0
008 587/587 8.80 66 10 19 9 10 14 10 0.21 0.15 0.30 300 50 7.0 2.8 1.9 97.0 39.0 29.0 21.0 16.0 11.0 9.0
008 587/587 8.70 66 9 19 7 10 12 10 0.21 0.15 0.30 300 50 7.0 1.7 0.7 98.0 37.0 28.0 20.0 15.0 10.0 7.0
008 587/587 8.70 66 10 18 7 10 12 10 0.21 0.15 0.30 300 50 7.0 1.7 0.7 98.0 38.0 28.0 21.0 15.0 12.0 7.0
009 587/587 8.70 66 10 19 8 10 12 10 0.21 0.15 0.30 300 50 7.0 0.10 1.7 0.7 98.0 39.0 29.0 22.0 15.0 11.0 7.0
009 587/587 8.70 66 10 17 7 9 11 9 0.21 0.10 0.25 280 50 7.0 0.10 2.8 2.7 97.0 37.0 27.0 22.0 16.0 9.0 8.0
009 587/587 8.70 67 10 17 7 9 11 9 0.15 0.10 0.25 280 50 7.0 0.10 2.8 2.7 97.0 37.0 27.0 22.0 16.0 9.0 8.0
010 587/587 8.70 67 10 17 7 9 11 9 0.15 0.10 0.25 280 50 7.0 0.10 1.7 0.7 98.0 37.0 27.0 22.0 16.0 10.0 7.0
010 587/587 8.70 66 9 17 7 10 12 9 0.15 0.10 0.25 280 50 7.0 0.10 1.7 0.7 98.0 35.0 26.0 21.0 15.0 11.0 7.0
010 587/587 8.70 66 9 17 7 10 12 10 0.30 0.25 0.35 300 60 7.0 0.10 1.7 0.7 98.0 35.0 26.0 21.0 15.0 11.0 7.0
011 587/587 8.70 66 8 16 7 10 11 10 0.30 0.25 0.35 280 50 7.0 0.10 1.7 0.7 98.0 32.0 24.0 20.0 14.0 10.0 7.0
011 587/587 8.70 65 8 16 7 10 11 10 0.30 0.25 0.35 280 50 7.0 0.10 1.7 0.7 98.0 32.0 24.0 20.0 14.0 10.0 7.0
011 587/587 8.70 66 8 16 7 10 11 10 0.30 0.25 0.35 280 50 7.0 0.10 1.7 0.7 98.0 32.0 24.0 20.0 14.0 10.0 7.0
012 587/587 8.70 66 8 16 7 10 11 10 0.30 0.25 0.35 280 50 7.0 0.10 1.7 0.7 98.0 32.0 24.0 20.0 14.0 10.0 7.0
012 587/587 8.70 67 8 16 7 10 11 10 0.30 0.25 0.35 280 50 7.0 0.10 1.7 0.7 98.0 32.0 24.0 20.0 14.0 11.0 7.0
012 722/722 8.70 66 10 19 7 11 13 11.5 0.70 0.40 1.30 320 70 7.0 0.10 1.7 0.7 98.0 39.0 29.0 23.0 17.0 10.0 9.0
lbfs^n/100ft
2
001
006
006
006
007
007
007
008
008
008
009
009
009
Report MD/TVD FL Density Funn Rheology ºF Filtration Filtrate Analysis MBT Sand Retort Analysis Rheometer Dial Readings
No Temp Visc
PV API HTHP Cake Cake Temp pH Pm Pf Mf Cl Total 600 300 200 100 6 3
lbfs^n/100ft2 % by vol
API HTHP Hardness
% by Corr NAP
ft ºF ppg sec/qt cp YP 10S 10M 30M mL/30min mL/30min 32nd in ºF mL mL mL mg/l mg/l ppb eq. LGS Water
vol Solid Base
013 1,034/1,034 100 8.80 66 10 19 7 10 12 10.8 0.50 0.30 0.80 300 60 0.10 2.8 1.9 97.0 39.0 29.0 23.0 16.0 10.0 8.0
013 1,748/1,748 115 8.80 67 10 19 7 12 14 10.5 0.60 0.25 0.35 300 60 7.0 0.10 3.3 2.9 96.5 39.0 29.0 23.0 17.0 12.0 8.0
013 2,554/2,554 120 9.10 68 14 23 8 12 15 8.0 1 10.5 0.60 0.30 0.35 380 80 7.0 0.10 3.3 0.7 96.5 51.0 37.0 30.0 22.0 12.0 9.0
014 3,061/3,061 125 9.10 58 14 23 6 12 15 12.0 1 0 10.5 0.60 0.30 0.35 380 80 10.0 0.20 5.8 5.7 0.0 94.0 51.0 37.0 26.0 19.0 11.0 9.0
014 3,757/3,757 125 9.20 60 17 24 9 13 17 10.0 1 0 10.5 0.60 0.30 0.35 380 80 10.0 0.25 6.3 6.0 93.5 58.0 41.0 31.0 22.0 12.0 9.0
014 4,620/4,620 125 9.20 65 17 25 8 14 18 10.0 1 0 10 0.50 0.30 0.35 380 80 10.0 0.25 6.3 6.0 93.5 59.0 42.0 31.0 22.0 12.0 9.0
015 4,978/4,978 125 9.20 65 16 25 8 15 21 10.0 1 0 10.1 0.50 0.30 0.37 380 80 10.0 0.25 5.8 5.0 94.0 57.0 41.0 32.0 21.0 12.0 8.0
015 5,314/5,312 130 9.20 64 18 24 9 15 21 10.0 1 0 10 0.50 0.30 0.35 380 80 13.0 0.25 5.8 5.0 94.0 60.0 42.0 32.0 22.0 12.0 8.0
015 5,770/5,766 125 9.20 67 18 25 9 15 22 8.0 1 10 0.50 0.30 0.35 400 80 16.0 0.25 5.8 5.0 94.0 61.0 43.0 33.0 22.0 12.0 10.0
016 5,973/5,958 130 9.30 67 17 25 9 15 21 8.0 1 0 10 0.50 0.30 0.35 400 80 20.0 0.25 5.8 4.2 94.0 59.0 42.0 31.0 21.0 12.0 9.0
016 6,247/6,222 130 9.30 69 17 25 9 16 23 8.0 1 0 10 0.50 0.30 0.35 400 80 22.0 0.25 5.8 4.2 94.0 59.0 42.0 34.0 23.0 13.0 9.0
016 6,480/6,436 130 9.30 66 18 26 9 18 25 7.0 1 10 0.50 0.25 0.40 400 80 25.0 0.25 5.8 4.2 94.0 62.0 44.0 34.0 24.0 12.0 9.0
017 5,973/5,958 130 9.30 65 17 25 7 17 19 7.0 1 0 10 0.50 0.25 0.40 420 80 27.0 0.20 6.8 6.2 93.0 59.0 42.0 30.0 21.0 11.0 7.0
017 6,700/6,637 130 9.30 67 18 24 8 14 18 6.0 1 0 10 0.50 0.30 0.35 420 80 25.0 0.20 5.8 4.2 0.0 94.0 60.0 42.0 32.0 23.0 12.0 8.0
017 6,861/6,780 138 9.30 57 11 16 9 18 27 6.0 1 10 0.50 0.20 0.50 800 80 25.0 0.20 6.9 2.0 92.8 38.0 27.0 22.0 16.0 14.0 9.0
018 6,982/6,883 140 9.30 57 12 17 8 14 19 6.0 1 10 0.70 0.20 0.60 800 80 25.0 0.20 6.9 2.0 92.8 41.0 29.0 24.0 17.0 14.0 8.0
018 7,018/6,914 140 9.30 60 19 21 9 14 20 6.0 1 0 10 0.60 0.20 0.40 800 80 20.0 0.20 6.9 2.0 92.8 59.0 40.0 31.0 21.0 14.0 9.0
018 7,018/6,918 9.30 60 19 21 9 14 20 6.0 1 10 0.60 0.20 0.40 800 8 20.0 0.60 6.9 2.0 92.8 59.0 40.0 31.0 21.0 14.0 9.0
019 7,018/6,918 9.30 60 11 18 9 14 20 6.0 1 10 0.60 0.20 0.40 800 80 20.0 0.20 6.9 2.0 92.8 40.0 29.0 24.0 16.0 14.0 9.0
019 7,018/6,918 9.30 65 12 20 9 14 21 6.0 1 0 10 0.60 0.20 0.40 800 80 20.0 0.20 7.7 15.6 92.0 44.0 32.0 25.0 16.0 13.0 9.0
019 7,039/6,933 125 9.30 50 11 20 8 18 27 5.6 1 10.5 0.80 0.30 0.70 800 80 25.0 0.20 6.9 2.0 92.8 42.0 31.0 26.0 21.0 12.0 8.0
020 7,190/7,063 130 9.30 59 12 20 6 16 5.5 1 10 0.70 0.30 0.70 1,400 80 25.0 0.20 6.9 2.4 92.8 44.0 32.0 19.0 14.0 12.0 6.0
020 7,557/7,328 140 9.40 62 15 20 9 12 19 5.6 1 0 10 0.70 0.30 0.70 1,400 40 25.0 0.20 7.7 4.0 92.0 50.0 35.0 20.0 15.0 11.0 9.0
020 7,694/7,429 148 9.40 60 14 22 10 22 35 5.6 1 10 0.60 0.30 0.60 1,400 40 25.0 0.20 7.8 5.7 91.9 50.0 36.0 30.0 22.0 12.0 10.0
lbfs^n/100ft lbs/100ft2
2
Report MD/TVD FL Density Funn Rheology ºF Filtration Filtrate Analysis MBT Sand Retort Analysis Rheometer Dial Readings
No Temp Visc
PV API HTHP Cake Cake Temp pH Pm Pf Mf Cl Total 600 300 200 100 6 3
lbfs^n/100ft2 % by vol
API HTHP Hardness
% by Corr NAP
ft ºF ppg sec/qt cp YP 10S 10M 30M mL/30min mL/30min 32nd in ºF mL mL mL mg/l mg/l ppb eq. LGS Water
vol Solid Base
021 7,916/7,594 148 9.40 56 11 18 9 22 35 5.6 1 10.2 0.80 0.30 0.70 1,500 40 27.5 0.20 7.9 7.5 91.8 40.0 29.0 19.0 16.0 12.0 9.0
021 8,200/7,809 150 9.40 60 13 19 9 22 34 5.5 1 0 10.2 0.80 0.30 0.70 1,500 50 27.5 0.30 7.7 4.1 92.0 45.0 32.0 20.0 16.0 12.0 9.0
021 8,280/7,850 150 9.40 52 11 18 9 26 38 5.5 1 10 0.70 0.20 0.60 1,400 40 27.5 0.20 7.5 0.6 92.2 40.0 29.0 19.0 16.0 13.0 9.0
022 8,389/7,945 150 9.40 56 12 19 9 22 34 5.5 1 10 0.70 0.20 0.40 1,400 100 27.5 0.20 7.7 4.0 92.0 43.0 31.0 22.0 16.0 13.0 9.0
022 8,437/7,980 9.40 60 12 20 9 23 32 5.5 1 0 10 0.70 0.20 0.50 1,200 40 25.0 0.20 7.7 3.9 92.0 44.0 32.0 23.0 18.0 12.0 9.0
022 8,437/7,980 9.40 60 12 20 9 23 32 5.5 1 10 0.70 0.20 0.50 1,200 40 25.0 0.20 7.7 3.9 92.0 44.0 32.0 23.0 18.0 12.0 9.0
023 8,437/7,980 9.40 60 12 20 9 23 32 5.0 1 0 10 0.70 0.20 0.50 1,200 40 25.0 0.20 7.7 3.9 92.0 44.0 32.0 23.0 18.0 12.0 9.0
023 8,437/7,980 9.30 63 15 26 10 25 38 5.0 1 10 0.70 0.20 0.50 1,100 50 25.0 0.20 7.1 5.6 92.6 56.0 41.0 33.0 26.0 15.0 10.0
024 8,438/7,980 9.40 58 11 18 9 26 37 5.2 1 9.8 0.60 0.20 0.50 1,450 50 25.0 0.20 7.6 2.4 92.1 40.0 29.0 24.0 19.0 12.0 9.0
024 8,438/7,980 107 9.40 72 12 24 10 32 39 5.2 1 10.5 1.00 0.30 0.90 1,400 110 27.5 0.20 7.6 2.3 92.1 48.0 36.0 30.0 24.0 15.0 10.0
024 8,438/7,980 128 9.50 60 13 25 10 27 38 5.1 1 10.2 0.85 0.26 0.60 1,500 50 28.0 0.20 8.6 7.5 91.1 51.0 38.0 31.0 25.0 13.0 10.0
025 8,438/7,940 135 9.40 59 11 16 10 28 39 5.1 1 9.8 0.90 0.20 0.60 1,550 50 27.5 0.30 7.7 4.1 92.0 38.0 27.0 23.0 17.0 13.0 10.0
025 8,669/8,148 145 9.40 62 11 17 9 29 38 5.0 1 10.2 1.00 0.20 0.70 1,500 120 27.5 0.20 7.5 0.7 92.2 39.0 28.0 23.0 18.0 14.0 9.0
025 8,806/8,273 148 9.40 58 11 18 10 25 35 5.2 1 10 0.90 0.27 0.65 1,500 100 28.0 0.20 7.7 7.5 92.0 40.0 29.0 24.0 19.0 12.0 10.0
026 8,853/8,312 145 9.40 55 11 14 9 23 33 5.0 1 10 1.00 0.20 0.70 1,400 150 28.0 0.20 7.7 4.0 92.0 36.0 25.0 21.0 16.0 11.0 8.0
026 8,863/8,320 150 9.60 58 11 18 9 23 32 5.0 1 10.8 1.30 0.40 1.10 1,400 150 27.5 0.20 8.9 0.5 90.8 40.0 29.0 22.0 16.0 11.0 9.0
026 8,863/8,320 9.60 55 14 19 10 25 33 5.1 1 10.7 1.30 0.38 0.95 1,450 160 28.0 0.20 9.2 5.7 90.5 47.0 33.0 27.0 19.0 11.0 9.0
027 8,863/8,320 9.60 60 14 19 10 27 32 5.0 1 10.1 1.30 0.40 1.00 1,450 120 27.5 0.20 9.2 5.7 90.5 47.0 33.0 27.0 19.0 11.0 10.0
027 8,863/8,320 9.60 61 15 17 10 26 33 5.0 1 10 1.20 0.36 0.95 1,450 130 27.5 0.20 9.3 7.4 90.4 47.0 32.0 27.0 19.0 11.0 10.0
028 8,863/8,320 9.60 72 15 25 11 28 39 5.0 1 10.2 1.30 0.30 0.90 1,450 120 27.5 0.20 9.2 5.7 90.5 55.0 40.0 34.0 27.0 14.0 11.0
028 8,863/8,320 9.60 67 16 20 10 25 35 5.0 1 10.2 1.20 0.30 0.80 1,450 150 27.5 0.20 9.2 5.7 90.5 52.0 36.0 28.0 20.0 10.0 9.0
029 8,863/8,320 9.60 53 11 18 12 28 40 5.0 1 10.1 1.00 0.30 0.60 1,450 120 27.5 0.20 9.3 7.4 90.4 40.0 29.0 24.0 18.0 11.0 10.0
029 8,863/8,320 115 9.60 51 14 16 10 19 24 5.1 1 10 0.90 0.20 0.70 1,450 120 27.5 0.20 9.1 8.8 90.6 44.0 30.0 23.0 16.0 12.0 10.0
030 8,388/7,944 9.00 64 13 13 3 5 7 6.2 1 10 1.10 0.30 0.90 2,200 40 12.5 0.20 4.9 4.7 94.8 39.0 26.0 19.0 11.0 4.0 3.0
030 8,388/7,944 9.00 58 15 10 3 6 8 6.0 1 10 1.00 0.27 0.77 2,000 40 13.0 0.20 4.9 4.9 94.8 40.0 25.0 19.0 11.0 4.0 3.0
lbfs^n/100ft lbs/100ft2
2
Report MD/TVD FL Density Funn Rheology ºF Filtration Filtrate Analysis MBT Sand Retort Analysis Rheometer Dial Readings
No Temp Visc
PV API HTHP Cake Cake Temp pH Pm Pf Mf Cl Total 600 300 200 100 6 3
lbfs^n/100ft2 % by vol
API HTHP Hardness
% by Corr NAP
ft ºF ppg sec/qt cp YP 10S 10M 30M mL/30min mL/30min 32nd in ºF mL mL mL mg/l mg/l ppb eq. LGS Water
vol Solid Base
031 8,863/8,320 92 8.80 59 11 26 11 23 27 6.7 1 10 0.80 0.30 0.70 2,000 40 12.5 0.20 3.3 1.3 96.4 48.0 37.0 34.0 27.0 12.0 11.0
031 8,863/8,320 8.90 71 19 27 5 6 7 5.2 1 11 1.20 0.50 1.20 2,700 80 2.5 0.01 4.1 3.3 95.6 65.0 46.0 35.0 21.0 7.0 5.0
031 8,863/8,320 130 9.30 44 14 14 6 12 16 6.5 1 12.1 1.90 0.80 1.10 2,000 400 15.0 0.20 7.0 4.4 92.7 42.0 28.0 22.0 14.0 7.0 5.0
032 8,863/8,320 9.30 44 14 14 5 7 13 6.5 1 12 2.00 1.10 2,000 400 15.0 0.20 7.0 4.4 92.7 42.0 28.0 22.0 14.0 7.0 5.0
032 8,862/8,319 130 9.30 31 13 4 2 4 7 7.8 1 12.3 1.70 0.70 1.20 2,300 430 12.5 0.40 7.1 6.3 92.6 30.0 17.0 13.0 4.0 2.0 1.0
033 8,863/8,320 105 8.90 44 5 2 2 3 6 9.2 1 12.5 4.00 2.00 3.00 1,200 320 12.5 0.20 4.1 2.4 95.6 12.0 7.0 5.0 3.0 2.0 1.0
033 8,863/8,320 9.00 37 5 2 2 3 6 9.5 1 12.5 4.00 2.00 3.00 1,200 320 12.5 0.40 4.7 0.7 95.0 12.0 7.0 5.0 3.0 2.0 1.0
034 8,863/8,320 9.00 39 5 2 2 3 6 9.5 1 12.5 4.00 3.00 4.00 1,200 320 12.5 0.20 4.7 0.7 95.0 12.0 7.0 5.0 3.0 2.0
034 8,863/8,320 9.00 40 6 2 2 3 6 10.0 1 0 12.5 4.00 3.00 4.00 1,200 320 10.0 0.20 4.7 0.7 95.0 14.0 8.0 5.0 3.0 2.0 1.0
035 8,863/8,320 9.00 50 6 2 2 3 10.0 12.5 4.00 3.00 4.00 1,200 320 10.0 0.20 4.7 0.7 95.0 14.0 8.0 5.0 2.0
035 8,863/8,320 9.00 40 6 2 2 3 12.0 1 1 12.5 4.00 3.00 1,200 320 10.0 0.20 4.7 0.7 95.0 14.0 8.0 5.0 2.0 1.0
lbfs^n/100ft lbs/100ft2
2
Report MD/TVD FL Density Funn Rheology ºF Filtration Filtrate Analysis MBT Sand Retort Analysis Rheometer Dial Readings
No Temp Visc
PV API HTHP Cake Cake Temp pH Pm Pf Mf Cl Total 600 300 200 100 6 3
lbfs^n/100ft2 % by vol
API HTHP Hardness
% by Corr NAP
ft ºF ppg sec/qt cp YP 10S 10M 30M mL/30min mL/30min 32nd in ºF mL mL mL mg/l mg/l ppb eq. LGS Water
vol Solid Base
036 8,654/8,169 105 8.90 71 19 27 6 7 9 5.0 1 11 1.20 0.50 1.20 2,700 80 2.5 0.01 4.1 3.3 95.6 65.0 46.0 35.0 21.0 8.0 6.0
036 9,075/8,461 135 9.00 50 16 14 5 6 10 6.0 1 11 1.05 0.60 1.10 1,800 120 7.5 0.10 4.7 1.0 95.0 46.0 30.0 23.0 15.0 4.0 3.0
037 9,253/0 130 9.00 55 16 18 6 7 10 5.5 1 11 1.10 0.60 1.10 2,000 120 7.5 0.10 4.7 1.2 95.0 50.0 34.0 25.0 15.0 6.0 5.0
037 9,417/8,727 130 9.00 59 12 25 5 9 10 4.9 1 10.5 1.40 0.40 1.10 2,300 120 7.5 0.20 4.7 1.4 95.0 49.0 37.0 26.0 15.0 9.0 5.0
037 9,683/8,931 135 9.00 65 20 16 7 10 12 5.0 1 10.5 1.25 0.45 1.10 2,100 120 7.5 0.20 4.7 1.2 95.0 56.0 36.0 28.0 18.0 9.0 6.0
038 9,900/0 140 9.10 67 20 17 7 10 13 4.8 1 10.5 1.25 0.45 1.10 2,000 120 0.20 5.5 2.8 94.2 57.0 37.0 29.0 20.0 8.0 6.0
038 10,080/9,229 140 9.10 63 17 19 7 17 20 5.0 1 10.2 1.20 0.40 1.10 2,100 120 10.0 0.20 5.5 2.9 94.2 53.0 36.0 28.0 18.0 9.0 7.0
038 10,454/0 145 9.10 68 19 21 7 11 14 5.0 1 10 1.05 0.38 1.00 2,100 120 10.0 0.20 5.7 3.2 2.0 92.0 59.0 40.0 32.0 22.0 7.0 6.0
039 10,710/0 140 9.10 63 18 19 7 14 20 5.0 1 10.2 1.10 0.40 1.00 2,000 160 10.0 0.20 5.7 3.2 2.0 92.0 55.0 37.0 30.0 21.0 7.0 6.0
039 10,943/9,879 150 9.10 70 20 20 7 15 22 5.0 1 9.8 0.60 0.20 0.60 2,200 160 10.0 0.20 5.7 3.3 2.0 92.0 60.0 40.0 29.0 19.0 12.0 7.0
039 11,212/0 150 9.10 63 18 19 7 10 15 5.0 1 9.8 0.70 0.25 0.65 2,200 160 10.0 0.20 5.7 3.3 2.0 92.0 55.0 37.0 29.0 21.0 8.0 6.0
040 11,440/0 150 9.10 60 20 19 8 15 20 5.0 1 9.5 0.55 0.15 0.60 1,600 160 10.0 0.20 5.8 4.6 2.0 91.9 59.0 39.0 31.0 22.0 9.0 7.0
040 11,624/10,385 152 9.30 68 20 21 9 18 23 4.8 1 10.8 1.20 0.40 1.10 1,600 160 10.0 0.20 7.1 2.8 2.0 90.6 61.0 41.0 34.0 24.0 10.0 9.0
040 11,624/0 9.30 65 20 21 7 10 15 5.0 1 10.8 1.20 0.40 1.10 1,600 160 10.0 0.20 7.1 2.8 2.0 90.6 61.0 41.0 34.0 24.0 8.0 6.0
041 11,624/10,385 150 9.30 63 16 22 7 19 24 4.8 1 10.9 1.10 0.30 0.90 1,600 160 10.0 0.20 7.0 2.2 1.3 91.4 54.0 38.0 30.0 21.0 10.0 7.0
041 11,624/10,385 150 9.30 63 16 22 7 14 24 4.8 1 10.9 1.10 0.30 0.90 1,600 160 10.0 0.20 7.0 2.2 1.3 91.4 54.0 38.0 30.0 21.0 10.0 7.0
042 11,624/10,385 9.30 65 16 22 7 14 24 4.8 1 10.8 1.10 0.30 0.90 1,600 160 10.0 0.20 7.0 2.2 1.3 91.4 54.0 38.0 29.0 22.0 11.0 7.0
042 11,624/10,385 9.30 68 20 21 8 10 16 5.0 1 10.5 1.10 0.30 0.90 1,600 160 10.0 0.20 7.1 3.9 1.3 91.3 61.0 41.0 33.0 23.0 8.0 7.0
043 11,624/10,385 115 9.30 72 20 21 8 11 16 5.0 1 10 1.20 0.30 0.90 1,600 160 10.0 0.20 7.1 3.9 1.3 91.3 61.0 41.0 33.0 23.0 9.0 8.0
043 11,624/10,385 160 9.30 67 20 21 8 11 16 5.0 1 10 1.10 0.28 0.85 1,600 160 10.0 0.20 7.1 3.9 1.3 91.3 61.0 41.0 33.0 23.0 9.0 8.0
044 11,624/0 145 9.30 52 15 14 3 5 7 5.0 1 10 1.10 0.28 0.85 1,600 160 10.0 0.20 7.1 3.9 1.3 91.3 44.0 29.0 23.0 16.0 5.0 3.0
lbfs^n/100ft lbs/100ft2
2
bbl bbl bbl bbl bbl bbl bbl bbl bbl bbl bbl bbl bbl bbl bbl bbl bbl bbl bbl
Interval # 01
Fluid Name: AQUAGEL / Chemical
001 03-07-2012 * 1,000.0 16.0 1,016.0 554.0 462.0 1,016.0
006 03-12-2012 * 1,157.0 20.0 5.2 25.2 35.0 20.0 55.0 96.0 590.1 441.1 1,127.2
007 03-13-2012 * 1,127.2 150.0 3.0 153.0 93.2 30.0 123.2 89.9 611.1 456.0 1,157.0
008 03-14-2012 * 1,157.0 25.0 6.5 31.5 60.0 60.0 230.8 557.7 340.0 1,128.5
009 03-15-2012 * 1,128.5 8.8 8.8 135.0 135.0 91.2 450.1 461.0 1,002.3
010 03-16-2012 * 1,002.3 210.2 2.0 212.2 91.2 662.3 461.0 1,214.5
012 03-18-2012 * 1,214.5 50.0 3.1 53.1 171.0 171.0 98.5 537.0 461.0 1,096.5
bbl bbl bbl bbl bbl bbl bbl bbl bbl bbl bbl bbl bbl bbl bbl bbl bbl bbl bbl
Interval # 02
Fluid Name: AQUAGEL / Chemical
013 03-19-2012 * 1,096.5 445.0 12.1 457.1 230.0 230.0 379.2 483.4 461.0 1,323.6
015 03-21-2012 * 1,592.6 400.0 10.4 410.4 100.0 100.0 870.3 592.8 440.0 1,903.1
016 03-22-2012 * 1,903.1 211.0 9.6 220.6 40.0 200.0 240.0 992.1 581.7 310.0 1,883.8
Cumulative Volume 1,323.6 991.0 29.8 2,344.4 260.0 200.0 1,884.5 2,344.5
018 03-24-2012 * 1,633.1 59.3 8.0 67.3 114.8 7.0 121.8 1,146.6 432.0 1,578.6
019 03-25-2012 * 1,578.6 255.8 30.0 12.4 298.2 221.6 221.6 1,099.1 556.0 1,655.1
020 03-26-2012 * 1,655.1 106.0 121.3 14.6 241.9 6.0 120.0 126.0 1,206.1 565.0 1,771.1
021 03-27-2012 * 1,771.1 296.0 20.2 316.2 82.0 173.0 255.0 1,281.3 551.0 1,832.3
022 03-28-2012 * 1,832.3 11.4 11.4 4.7 65.3 70.0 1,298.6 475.1 1,773.7
024 03-30-2012 * 1,785.0 50.0 18.7 3.6 72.3 45.0 21.0 66.0 1,302.2 489.0 1,791.2
025 03-31-2012 * 1,791.2 277.5 107.7 8.9 394.1 6.0 321.0 327.0 1,355.4 503.0 1,858.4
026 04-01-2012 * 1,858.4 170.0 27.9 14.7 212.6 6.0 188.0 194.0 1,377.1 503.0 1,880.1
027 04-02-2012 * 1,880.1 19.1 3.0 4.7 26.8 3.6 35.0 38.6 1,448.2 417.0 1,865.2
028 04-03-2012 * 1,865.2 54.0 0.9 0.8 55.7 12.0 125.0 137.0 1,356.0 428.0 1,784.0
029 04-04-2012 * 1,784.0 2.1 2.1 16.0 1,049.5 18.0 1,083.5 702.6 702.6
bbl bbl bbl bbl bbl bbl bbl bbl bbl bbl bbl bbl bbl bbl bbl bbl bbl bbl bbl
Cumulative Volume 2,792.1 893.7 125.4 3,811.2 642.7 2,243.2 191.0 3,076.9
018 03-24-2012 143.0 210.0 3.3 213.3 59.3 59.3 297.0 297.0
019 03-25-2012 297.0 150.0 8.8 158.8 255.8 255.8 200.0 200.0
024 03-30-2012 267.2 99.7 0.1 99.8 50.0 50.0 317.0 317.0
025 03-31-2012 317.0 150.0 6.5 156.5 277.5 277.5 196.0 196.0
026 04-01-2012 196.0 200.0 10.1 210.1 170.0 170.0 236.1 236.1
bbl bbl bbl bbl bbl bbl bbl bbl bbl bbl bbl bbl bbl bbl bbl bbl bbl bbl bbl
Interval # 03
Fluid Name: Polimero Inhibido
036 04-11-2012 734.3 0.2 0.2 734.5 734.5
037 04-12-2012 * 924.9 157.1 8.1 165.2 44.0 59.0 103.0 626.2 361.0 987.2
038 04-13-2012 * 987.2 15.2 15.2 18.2 3.0 21.2 672.2 305.0 4.0 981.2
039 04-14-2012 * 981.2 43.0 45.0 1.0 89.0 11.9 11.9 721.3 333.0 4.0 1,058.3
040 04-15-2012 * 1,058.3 10.0 2.0 12.0 11.7 70.0 81.7 773.6 175.0 40.0 988.6
041 04-16-2012 * 988.6 53.4 10.1 63.5 24.2 24.2 822.8 205.0 1,027.8
041 04-16-2012 44.0 60.0 9.4 69.4 53.4 53.4 60.0 60.0
bbl bbl bbl bbl bbl bbl bbl bbl bbl bbl bbl bbl bbl bbl bbl bbl bbl bbl bbl
Fluid Treatment Mud Eng. Hernan Valera was at Location from 03-03-2012. Second Mud Eng. Wilmer Leon arrived 03-07-2012.
Built 1010 bbls of Spud Mud in the active System.
For Report # 002 On 03-08-2012 Operation at Depth(MD / TVD) 0/0 ft
Rig Activity continued rigging up 80%
Activity Rig Up
Activity Rig Up
Activity Rig Up
Activity Rig Up
Fluid Treatment Used Aquagel and X-tend for premix 157 bls. of mud LIME for alkalinity
Activity Drilling
Fluid Treatment Mixed and pumped 40 bls of pill LCM with 40 lpb of KWIK SEAL FINE
ROT: 110 RPM, TQ: 1.0 - 4.0 klb/ft. POOH Circulate BHA # 1 F/ 349’ TO 270’. Continued POOH STRING WITH
BHA # 1 F/270’ TO SURFACE. PERFORMED CEMENT JOB MOUSE HOLE.WOC. PERFORMED JOB IN FLOW LINE.
RIH BHA # 2 FROM SURFACE TO 349'. at report time Tripping
Activity Tripping
Fluid Treatment Used AQUAGEL,LIME AND X-TENDII for mixed 150 bls of mud
Fluid Treatment Mixed and pumped 50 bls of pill LCM 80 lpb of 40lbs BAROFIBER ,20 CACO3 150 and 20lbs CACO3 600 , used
LIME for Alkality
Fluid Treatment Mixed and pumped 50 bls of pill LCM 80 lpb of 40lbs KIWIK SEAL COARSE ,20 BAROFIBER and 20lbs
BAROFIBER COARSE.
For Report # 010 On 03-16-2012 Operation at Depth(MD / TVD) 587/587 ft
Rig Activity Cut casing 13 3/8" & removed conductor 20". performed top job. beveled casing 13 3/8". instaled well head
section "a" 9 5/8'' slip grip x 11'' - .tested section "a" (with 900 psi; o.k.) rig down tools sls M/U BOP's stack as
follow: changed bell flow line rig up joint dp 5" & conected test plug. tested bop's: tested 13 5/8" - 5m bop's as
follow: blinds rams + plug + choke manifold valves with 700 psi for 10 min; ok. blinds + plug hcr hidraulic with
3500 psi, for 10 min; ok. blins + plug + hcr manual + valve external with700 psi ,for 10 min; ok, and 3500 psi;
for 10 min; ok. blind + plug + hcr internal with 700 psi, for 10 min; ok, and 3500 psi, for 10 min; ok. kill line
external 700 psi - 3500 psi, for 10 min;ok. kill line internal with 700 - 3500 psi, for 10 min. pipe rams + plug +hcr
hidraulic with 700 - 3500 psi, for 10 min; ok. plug + annular preventor + hcr wth 600 - 3500 psi, for 10 min; ok.
pipe rams + hcr + valve internal preventor with 500 -3500 psi,for 10 min;ok. check valve + plug + pipe rams top
with 500 - 3500 psi, for 10 min; ok.
Activity Testing B.O.P.
Fluid Treatment Used AQUAGEL,LIME AND X-TENDII for mixed 200 bls of mud .
Fluid Treatment Used AQUAGEL AND X-TENDII for acondicioned parameters reology active sistem.
Activity Drilling
Fluid Treatment Used AQUAGEL AND X-TENDII for acondicioned parameters reology active sistem. Used BARAZAND-PLUS ,
PAC-R , PAC-L CLAYSEAL in adjusting the fluid mud is inhibited and mesh design changes shakers 140 175
and mud cleaner 250 and 210 for mantenied density of mud pumped 40 bbl of viscosity pill of ( 8.8 ppg -
180seg/qt) @ 1034' with q: 380 gpm, spp: 530 psi. pumped 40 bbl of viscosity pill of (8.8 ppg - 100 seg/qt) @
1509' with: q: 410 gpm, spp: 560 psi pumped 40 bbl of sweep pill of (9.1 ppg - 70 seg/qt) @ 1604' with: q: 785
gpm, spp: 1300 psi pumped 40 bbl of viscosty pill of (8.8 ppg - 100 seg/qt) @ 2030' with: q: 740 gpm, spp:
1750 psi pumped 40 bbl dispersed pil withl 20 lpb baracarb Df 150). of (9.1 ppg - 65 seg/qt) @ 2237' with: q:
750 gpm, spp: 1600
Activity Drilling
Fluid Treatment Used BARAZAN to control rheology, PAC L/R, to control loss filtrate. CLAY SEAL to inhibition of clays ,CLAY
GRABBER as encapsulate of clays tone & Cleaning the mud, as too to use in the flocculate Unit. changed.
screens of sheakers for control of solid . PUMPED 40 BBL OF VIS PILL OF ( 9.1 PPG - 180SEG/QT) @ 2743'
WITH Q: 580 GPM, SPP: 1000 PSI. /3346/3973/4446 Ft. and PUMPED 40 BBL DISPERSED PILL OF OF (9.2 PPG -
55 SEG/QT) @ 3783' WITH: Q: 800 GPM, SPP: 2040 PSI
Activity Drilling
Fluid Treatment Continued pumped pills of high and low every 500 Ft drilled .Used BARAZAN to control rheology, PAC L/R, to
control loss filtrate. CLAY SEAL to inhibition of clays ,CLAY GRABBER as encapsulate of clays tone &
Cleaning the mud, as too to use in the flocculate Unit transfer 400 bbls of mud fractank of Qmax for treatment
Losses & Gains enviado a fractan para deewater
Activity Drilling
Fluid Treatment Continued pumped pills of high and low every 500 Ft drilled .Used BARAZAN to control rheology, PAC L/R, to
control loss filtrate. CLAY SEAL to inhibition of clays ,CLAY GRABBER as encapsulate of clays tone &
Cleaning the mud, as too to use in the flocculate Unit transfer 200 bbls of mud fractank of Qmax for treatment
For Report # 017 On 03-23-2012 Operation at Depth(MD / TVD) 6,879/6,795 ft
Rig Activity Perfora seccion 12 1/4" rotando (127', 30.6%) y deslizando (272', 69.4%), desde 6480' hasta 6879'. (Q: 680 -
740 GPM, SPP:2000 - 2500 PSI).
Activity Drilling
Fluid Treatment Realiza dilución programada previa a ingreso Fm. León, descartando 200 bbls de sistema activo e
incorporando igual cantidad desde reservas con BAROTROL PLUS, ajustando filtrado y concentración de
inhibidor. Adición horaria de: BARACARB DF 150, STEEL SEAL. Deficiente desempeno de centrifugas
decantadoras.
Concetraciones: PAC L/R [2.9], CLAYSEAL [8], FILTERCHECK [0.6], BAROTROL PLUS [4] , STEEL SEAL [5],
CLAY GRABBER [0.9], BARAZAN D PLUS [1.6].
For Report # 018 On 03-24-2012 Operation at Depth(MD / TVD) 7,018/6,914 ft
Rig Activity Cont. drilling section 12 1/4". rotating (65 ft, 51.5 %, 1.5 hrs.) /sliding ( 61ft, 48.5 %, 5 hrs) f/6879' t/7018' (Q:
680 - 740 GPM, SPP:2000 - 2500 PSI, ROT: 60 - 70 RPM, TQ: 3.0 - 4.0 Klb-FT).( pumped 50 bls, 160 s/qt of visc.
pill @ 7006'). POOH string to surf. (tight spots: 5895', 5856'-5773',5735'-5727', 5705'-5697', 5671'-5666',
5639'-5632', 5610'-5597', 5410', 5380', 5340', 4988', 4959'-4949'). Worked string @ 4949', no success.
Conected top drive, reamed 4949'-5015'. circulated ok, ok. Rigging down directional tools at the end of report.
Fluid Treatment Discarded sand trap (100 bbls) to control unwanted solids. Added water, calcium carbonate, lime, STEEL
SEAL, BARAZAN and FILTERCHEK for: rehydration, bridging, pH, stability, rheological control and filtering,
respectively.
Activity Drilling
Fluid Treatment Discarded sand trap (200 bbls) to control unwanted solids. Added per hour: water, calcium carbonate, STEEL
SEAL, for: rehydration, bridging, stability. Added: lime, BARAZAN, CLAYSEAL PLUS and FILTERCHEK for: pH,
rheological control, inhibition and filtering, respectively.
Fluid Treatment Low efficiency of decanter centrifuges leads to discard sand trap (100 bbls) to control unwanted solids and
built needless volumes of fluid. Added per hour: water, calcium carbonate, STEEL SEAL, for: rehydration,
bridging, stability. Added: lime and FILTERCHEK for: pH and filtering, respectively.
Activity Drilling
Fluid Treatment Added water, calcium carbonate (BARACARB DF 150), lime, STEEL SEAL, BARAZAN and FILTERCHEK for
rehidration, bridging, pH, shale stability, rheology control and filtering respectively.
Activity Tripping
Fluid Treatment Added water, calcium carbonate (BARACARB DF 150), lime and FILTERCHEK for rehidration, bridging, pH and
filtering respectively.
Pills: Weighted-viscous (40 bls , 10.2 ppg, 120 seg/qt) @ 8438 ft.
For Report # 023 On 03-29-2012 Operation at Depth(MD / TVD) 8,438/7,980 ft
Rig Activity POOH BHA # 5 from 2266' to surface. Rig Down Motor and MWD tools. Rig Stand By. Safety meeting for Rig Up
BHA#6. RIH BHA#6 from surface to 80'.
Activity RIH BHA #6
Fluid Treatment Check active system levels during surface trip. Circulating active system to reduce unwanted solids with
selective flocculation unit. Add glutaraldehyde and lime to control alkalinity and prevent bacterial degradation.
For Report # 024 On 03-30-2012 Operation at Depth(MD / TVD) 8,438/7,980 ft
Rig Activity Test LWD memory and directional tool. RIH f/ 80' t/ 7187' (Tight spots: @ 4871', 7156', 7187'). Conected top
drive @ 7211' (1285 psi, 380 gpm), work string with success. Reaming from 7195' to 7855', geometry stuck
pipe attempt, work string with 100 klb Overpull, Pumped 40 bbl of abrasive pill. Release pipe and reaming to
7920' (w/ 576 GPM, SPP=1750 psi, 74 RPM)
Activity Tripping
Fluid Treatment Poor performance of decanter centrifuges. Check active system levels during surface trip. Added calcium
carbonate (BARACARB DF 150), lime/caustic soda and FILTERCHEK for bridging, pH/alkalinity control and
filtering respectively.
Pills: Abrasive (40 bbl, 9ppb BAROFIBRE COARSE, 50%Water)@7855'(stuck pipe attempt)
Top Carbonera C3 Formation @8740' MD, 8218' TVD. Lithology at 8740' - 8790' (50%SH, 20%CLST, 20%SD,
10%SLTST. TR. COAL, SST)
Activity Drilling
Fluid Treatment Low efficiency of decanter centrifuges leads to discard sand trap (300 bbls) to control unwanted solids and
built needless volumes of fluid (150 bbls). Added per hour water, calcium carbonate for: rehydration, bridging
and lime/ FILTERCHEK for: pH and filtering, respectively.
Lithology (8790'-8863'): 60% SD, 20% CLST, 10%SH, 10% SLTST. TR COAL, PYR, SST.
Activity Tripping
Fluid Treatment Low efficiency of decanter centrifuges leads to discard 170 bbls of active system to control unwanted solids
and built needless volumes of fluid (200 bbls). Added per hour water and calcium carbonate for: rehydration
and bridging. Added lime, caustic soda and glutaraldehyde to prevent bacterial degradation during trip.
Increased mud weight (9.6lpb) while circulating to compensate ECD.
Pills Viscous @ 8830' (150 sec/qt, 40 bbls), 8863' (200 sec/qt, 40 bbls), Heavy (11 ppg, 15 bbl) POOH.
Fluid Treatment Pumped 20 bbl of heavy pill (12.0 ppg)@5484'. Checked volumes of active system while tripping. Finished
cleaning and order of warehouse, updating inventory.
Fluid Treatment Added lime, soda and glutaraldehyde to prevent bacterial degradation. Discarded sand trap (120 bbls) to
unwanted solids control and transfer fluid from reserve tanks to maintain levels. Changed damaged mesh (1)
in shaker 3.
For Report # 029 On 04-04-2012 Operation at Depth(MD / TVD) 8,863/8,320 ft
Rig Activity Runned cng. 9 5/8" t/8388'. Circulated bottoms up, ok. Reduced rheology of active system. Cementing safety
meeting. Cementing job done as programmed (40 bbl Mud Flush, 60 bbl Biozan, 116 cement). Cleaned BOP and
cellar. Safety meeting for raise bop. Released bell, flow line and hydraulic lines.
Activity Nipple up B.O.P.
Fluid Treatment Once ended running casing, established short circuit shakers-pill tank to reduce fluid rheology adding
THERMATHIN as polymeric deflocculant. Discarded 667 bls of active system after cementing. Cleaned Pill and
Suction tank.
Charged 145 bags of BARACARB DF-50 for cementing operation. Received chemicals from Yopal's
Warehouse.
Fluid Treatment Cont. cleaning active system tanks and dumping mud. Started to built BARADRIL-N in reserve tanks, product
consumption will be charged at displacement day.
For Report # 031 On 04-06-2012 Operation at Depth(MD / TVD) 8,863/8,320 ft
Rig Activity RIH BHA#7 from surface to 8308' (TOC). Drill-Out from 8308' to 8388' (Shoe@8384') w/ Q=300-310 gpm,
1500-1800 psi, WOB=7-20 klb, TQ=7-10 klb-ft, 60 RPM. Reamed open hole f/8388' t/8863' w/ Q=200-410 gpm,
1500-2200 psi, WOB=5-15 klb, TQ=7-10 klb-ft, 50-70 RPM. Circulated @8863' w/ Q=400 gpm, 1500 psi.
Activity Circulating
Fluid Treatment Cont. building sytem BARADRIL-N in intermediate, suction and reserve tanks; product consumption will be
charged at displacement day.
For Report # 032 On 04-07-2012 Operation at Depth(MD / TVD) 8,863/8,320 ft
Rig Activity Circulated @8863' w/ 400 gpm, 1500 psi. POOH BHA#7 f/8863 t/8406' with circulation, w/o circulation f/8406 t/
surface. Rig Services. RIH BHA#8 (Open Ended pipe) and 3 1/2" tubing f/ surface t/8863'. Circulated w/
250-400 gpm, 400-700 psi.
Activity Circulating
Fluid Treatment Transfer 110 bbls of system BARADRIL-N to HALLIBURTON Cementing. Charged cost of 110 bbl of
BARADRIL-N system
For Report # 034 On 04-09-2012 Operation at Depth(MD / TVD) 8,863/8,320 ft
Rig Activity Cont. RIH driil string with directional tools. Drill out to 8155 ft at the end of report.
Fluid Treatment Cont. building sytem BARADRIL-N in intermediate, suction and reserve tanks; product consumption will be
charged at displacement day.
For Report # 035 On 04-10-2012 Operation at Depth(MD / TVD) 8,863/8,320 ft
Rig Activity Cont. drill-out with directional tools from 8155 ft to 8468 ft (450-500 gpm, 60-100 rpm, 1000-1350 psi, ROP
prom= 13 ft/hr ).
Activity Drill out
Fluid Treatment Prepared 1240 bls of system BARADRIL-N to drill section 8 1/2". Displaced contaminated system Inhibited
Polymer after drill-out. As required by Co-Man was added BARO-LUBE GOLD SEAL as lubricant. Changed
damaged mesh (4) in shakers and one in mud cleaner.
Product Concentration: CLAYSEAL PLUS [3.32 ppb], PAC L/R [1.42 ppb], FILTERCHECK [5.4 ppb]
For Report # 037 On 04-12-2012 Operation at Depth(MD / TVD) 9,740/8,972 ft
Rig Activity Continue drilling from 9075 ft to XXXX ft with 460 GPM, 90 RPM, Torq 20-25, Pressure 1600 psi, WOB 20-30.
At 9547 ft Pumped Hi Vis Pill for cleaning hole.
Activity Drilling
Fluid Treatment Added per hour water, sized calcium carbonate for: rehydration, bridging and BARAZAN, FILTERCHEK and
CLAYSEAL for: rheology control, filtration control and inhibition, respectively. Changed damaged mesh (2) in
shaker 2.
Product Concentration: CLAYSEAL PLUS [5.91 ppb], PAC L/R [3.3 ppb], FILTERCHECK [5.86 ppb].
Fluid Treatment Added FILTERCHECK and PAC L as filtration controler. As required by Co-Man, BARO-LUBE GOLD SEAL was
added (2% v/v) as lubricant. Mix and Pumped 40 bbl Hi Vis Pill (9.0 ppg, 200 seg/qt)
Product Concentration: CLAYSEAL PLUS [5.87 ppb], PAC L/R [3.55 ppb], FILTERCHECK [6.03 ppb], BAROLUBE
GOLD SEAL [2 % V/V].
Activity Drilling
Fluid Treatment Added water, sized calcium carbonate and BARAZAN for rehydration, bridging and rheology control. Changed
damaged mesh (2) in shaker 2-3. Transfered fluid from reserve tank to maintain level of active system.
Received products, sent residua/contaminatedl bags.
Product Concentration: CLAYSEAL PLUS [5.75 ppb], PAC L/R [3.71 ppb], FILTERCHECK 6.23 ppb], BAROLUBE
GOLD SEAL [2 % V/V].
Activity Tripping
Fluid Treatment Added water, sized calcium carbonate and FILTERCHEK for rehydration, bridging and filtration control. As
required, increased mud weight (9.3 ppg) while circulating previous to short trip. Added Caustic Soda and
Glutaraldehyde to avoid mud degradation.
Product Concentration: CLAYSEAL PLUS [5.76 ppb], PAC L/R [6.47 ppb], FILTERCHECK [3.7 ppb], BAROLUBE
GOLD SEAL [2 % V/V].
Fluid Treatment Pumped 40 bbl Hi Vis Pill (200 seg/qt) @ 11624' (TD) and circulated ok, ok. Prepared weighted pill (20 bbls, 12
ppg) @ cng shoe to POOH dry drillstring. Transfer fluid from reserve tanks to recover maintain active system
levels.
Added caustic soda and glutaraldehyde to prevent degradation while tripping.
Product Concentration: CLAYSEAL PLUS [5.85 ppb], PAC L/R [3.79 ppb], FILTERCHECK 6.58 ppb], BAROLUBE
GOLD SEAL [2 % V/V].
Fluid Treatment Checked active system levels while running liner 7 ". Clean Reserve tanks.
Product Concentration: CLAYSEAL PLUS [5.85 ppb], PAC L/R [3.79 ppb], FILTERCHECK 6.58 ppb], BAROLUBE
GOLD SEAL [2 % V/V].
For Report # 043 On 04-18-2012 Operation at Depth(MD / TVD) 11,624/10,385 ft
Rig Activity RIH DS w /liner & liner hanger from 7750 ft to 11624 ft. Circulate hole one BU changing pump rate ( 250 gpm,
270 gpm, 290 gpm and 310 gpm) and check pressures.
Activity Running Liner 7 "
Fluid Treatment Checked active system levels while running liner 7 ". Cont. cleanning reserve tanks.
Product Concentration: CLAYSEAL PLUS [5.85 ppb], PAC L/R [3.79 ppb], FILTERCHECK 6.58 ppb], BAROLUBE
GOLD SEAL [1.3 % V/V].
For Report # 044 On 04-19-2012 Operation at Depth(MD / TVD) 11,624/10,385 ft
Rig Activity Continue circulating one BU changing pump rate ( 330, 350, 370, 370, 390, 410 and 430 GPM) and checking
pressures. Safety meeting to cementing job. Cement 7" Liner according to the plan. POOH DS to surface. Rig
Down
Activity Rig down
Fluid Treatment Made short circuit to pill and added THERMA-THIN to adjust rheological properties previous to cementing job.
Mix 30 bbl abrasive pill added WALL-NUT. Send 1089 bbl BARABRIL-N to Dewatering.
For Report # 045 On 04-20-2012 Operation at Depth(MD / TVD) 11,624/10,385 ft
Rig Activity Rig Down
Se observa buena de limpieza con carga efectiva de cortes de 1.319 % (valor critico: 3%) @ 10454 ft con 500 gpm y MW: 9.1 ppg. Se recomienda continuar
con practicas operacionales repasando 2 veces parada perforada y bombeo de píldoras de limpieza c/ 400 ft.