Demand Forecast
Costs
Item Cost
Materials cost/unit $ 100
Inventory holding cost/unit/month $ 2
Marginal cost of stockout/unit/month $ 5
Hiring and training cost/worker $ 200
Layoff cost/worker $ 250
Labor hours required/unit 5
Regular time cost/hour $ 4
Over time cost/hour $ 6
Marginal subcontracting cost/unit $ 20
Page 1
Planning
Page 2
2
Aggregate Plan
Period # Hired # Laid off # Workforce over time Inventory Stockout Subcontract
0 0 0 80 1000 0 0
1 0 18 62 0 1880 0 0
2 0 0 62 0 1360 0 0
3 0 0 62 620 795 0 0
4 0 0 62 620 0 370 0
5 0 0 62 620 65 0 0
6 0 0 62 620 500 0 0
Period Hiring Lay off Regular time Over time Inventory Stockout Subcontract
1 0 4500 39680 0 2820 0 0
2 0 0 39680 0 2040 0 0
3 0 0 39680 0 1192.5 0 0
4 0 0 39680 0 0 1850 0
5 0 0 39680 0 97.5 0 0
6 0 0 39680 0 750 0 0
Page 3
2
Production Demand
2480 1,600
2480 3,000
2635 3,200
2635 3,800
2635 2,200
2635 2,200
Page 4
3
Period Hiring Lay off Regular time Over time Inventory Stockout Subcontract
1 0 7,188 32,800 0 2,175 0 0
2 0 0 32,800 0 750 0 0
3 0 0 43,200 0 0 0 0
4 0 0 43,200 0 0 2,500 12,000
5 0 0 43,200 0 0 0 0
6 0 0 43,200 0 750 0 0
Page 5
3
Constraints
Material
205,000
205,000
270,000
270,000
270,000
270,000
Page 6