Emerging Technology Project Plan

Our company, Freestyle Machine, Inc., provides managed service support to customers who buy their
freestyle machines from us. Freestyle machines are machines that allow end users to choose their
flavored beverage (Coke, Sprite, water, Pepsi, etc.), which is then individually dispensed. You will often
find freestyle machines in service venues like hospitals, restaurants, and cruise ships. Our purpose is to
develop an IoT (Internet of Things) platform for the management of Netcomm modems deployed in the
field for the connectivity of Freestyle machines. 

During video conferences and communications through Slack we decided to use Teamweek as our
project management software, which offers the following: Free with unlimited time and unlimited
projects for up to five users, integration with Slack, a user-friendly interface, and easy account setup.
Carefully reviewing the requirements for the executive summary and video presentation for Project 2a
and 2b, we discussed each required task and milestone and determined the order in which each task
should be completed.  We discussed and agreed on which member(s) of the team is best suited for each
required task as well as their roles within the group. In addition to our individual tasks, Sean organizes
the meetings and keeps them on-track, Ashley provides graphic and writing expertise, Jay explains the
technical aspects of our new platform and how it affects our business, Adina coordinates assignments
and edits our plans, and Jeff ensures the project is fully integrated.
MIS – Project Plan 1
Page 2 of 2

Task Assigned To Start End


Project Plan Assignment
Draft Introduction to MIS 01/22 01/26
Edit introduction to MIS 01/22 01/26
Draft explanation of technology and project goal 01/22 01/26
Draft project plan items 01/22 01/26
Draft required paragraphs 01/26 01/27
Assign tasks for P2a and P2b 01/27 01/27
Review/update project plan tasks 01/27 01/30
Update plan in Teamweek 01/27 01/27
Discuss project plan 1 01/27 01/27
Review/edit project plan 1 01/31 02/01
Final review with team 01/31 02/02
Upload project plan 1 in D2L 02/01 02/03
Milestone – Project Plan 1 Deadline 02/03
Research/report two major advantages 01/28 02/03
Research/report two major disadvantages 01/28 02/03
Research/report two ways technology evolves 01/28 02/03
Review/edit project 2a 02/04 02/05
Upload project 2a in D2L 02/05 02/10

Introduction slides and speech 02/04 02/10


Impact slides and speech 02/04 02/10
Evolving slides and speech 02/04 02/10
Advantages slides and speech 02/04 02/10
Disadvantages slides and speech 02/04 02/10
Experts slides and speech 02/04 02/10
Presentation recording 02/10 02/15
Review/edit presentation recording 02/15 02/16
Upload project 2b into D2L 02/17 02/17