Activity ID Activity Name Original Start Finish 2020


Duration
Feb Mar Apr May Jun Jul Aug
1309 31-Aug-16 08:00 AM A 31-Mar-20 04:00 PM
Civil Division
Divis Schedule -Rev.02 (MES)_25Feb2020 (PM+45)
1309 31-Aug-16 08:00 AM A 31-Mar-20 04:00 PM
CIVIL
STEEL STRU
STRUCTURE, CONCRETE STRUCTURE AND BUILDING 1309 31-Aug-16 08:00 AM A 31-Mar-20 04:00 PM

GENERAL SERVICE
S BUILDING 1309 31-Aug-16 08:00 AM A 31-Mar-20 04:00 PM

STORAGE HOUSE 1309 31-Aug-16 08:00 AM A 31-Mar-20 04:00 PM

ENGINEERING
ENGINEERIN 502 31-Aug-16 08:00 AM A 14-Jan-18 12:00 AM A
A240050 Engineering of Storage House 502 31-Aug-16 08:00 AM A 14-Jan-18 12:00 AM A

CONSTRUCTION
CONSTRUCT 807 25-Mar-18 12:00 AM A 31-Mar-20 04:00 PM
A240200 Construction of Storage House 807 25-Mar-18 12:00 AM A 31-Mar-20 04:00 PM Construction of Storage House

A2402010 Excavation 15 16-Apr-18 08:00 AM A 30-Apr-18 04:00 PM A

A2402020 Grounding 31 01-May-18 08:00 AM A 31-Jul-18 04:00 PM A

A2402030 Ground Floor Structure Works (Pile Cap, Pedestal & Tie Beam) 83 13-May-18 08:00 AM A 28-Jul-18 04:00 PM A

A2402050 Steel Structure Works erection and installation 103 31-Jul-18 08:00 AM A 25-Aug-18 04:00 PM A

A2402040 Ground Floor Slab 39 25-Aug-18 08:00 AM A 18-Oct-18 04:00 PM A

A245820 Finishing of Storage House 503 26-Sep-18 08:00 AM A 31-Mar-20 04:00 PM Finishing of Storage House

A2402060 CHO for Structure Works 0 10-Nov-19 04:00 PM A

Actual Work Critical Remaining Work BVI ERECTION & COMMISSIONING SCHEDULE-PM45(25-Feb-20 TASK filter: Chemical Warehouse.
Remaining Work Milestone Page 1 of 1 © Oracle Corporation