Академический Документы
Профессиональный Документы
Культура Документы
&
Bus Switching Scheme
1
• A new generating station
• A new development or a new industry
• Network expansion such as new interconnections
• Voltage upgrades
• Introduction of dc lines
• Back-to-back stations for interconnecting two different
networks
• Supply electric power to consumers continuously
• Supply of electric power within specified voltage limits
• Shortest possible fault duration
• Optimum efficiency of electrical network
• Supply of electrical energy to consumers at lowest cost
• Terminal substations zone substations distribution
substations
Terminal Substations
High voltage transmission lines interconnected around the network at terminal
substations
Step down transmission voltage and supply power to zone substations.
(Secondary transmission)
Secondary transmission voltages -132kV, 66kV and 33kV
Zone substations
− Further step down voltage and supply to distribution networks
− Typical output voltage - 6.6kV ~ 33kV
Distribution substations
− Receive power from zone substations, supply power to distribution network and end
users after stepping down voltage (MV or LV)
• Substations can be of many types depending on their
placement in a network and function such as:
– Generation substations
– Transmission substations
– Terminal yards/substations
– Zone substations (= sub-transmission substations)
– Distribution substations
– Industrial (= consumer owned) substations
– HVDC transmission substations
• A new substation or changes to an existing substation will
have to be based on a process of design which involves all or
some of the following:
– Identifying a suitable site
– Defining the substation configuration
– Planning a layout
– Selecting the right equipment to be used
– Planning the facilities required to install
– Equipment maintenance
➢ With increasing constraints of transmission
line corridors, difficulty in availability of
land due to urbanization and economic
development, emergence of stringent social
& environmental regulations and public
awareness, the task of site selection for a
substation has become more and more
complex.
7
✓ Technical factors
- Area Requirement
• Voltage levels, Number of feeders, No. of Transformers/ Reactors,
Other facilities like housing, Present and Future requirement
- Corridors for line, aeronautics and forest
- Pollution
✓ Physical factor
- Topography :
Site Levelling, adoption of standard design
- Geological : Soil Properties, water table
- Geography :
Aeronautical corridor, mines, landslide, flood prone
8
✓ Infrastructural factor
- Easy Access
- Amenities Availability
- Reliable power & water supply
✓ Social & Environmental factor
- Habitation
- Govt. or Private land
- Forest encroachment
- Landscaping
✓ Commercial factor
- Cost
9
• Inputs:
– Function of the substation
– Power system parameters
– Load expected to be handled
– Site ambient conditions
– General area of substation location
• Output:
– Site selection and substation alignment
– Preliminary design and drawings
– Detailed design and drawings
➢ Single Main Bus Scheme
– with sectionaliser & without sectionaliser
➢ Double Main Bus Scheme
➢ Single Main & Transfer Bus Scheme
➢ Double Main with by-pass isolator Bus scheme
➢ Double Main & Transfer Bus Scheme
➢ One & Half Breaker Bus Scheme
➢ Double bus two breaker Scheme
➢ Ring Bus Scheme
11
SINGLE BUS SCHEME
12
SINGLE BUS WITH SECTIONALISER
13
14
SINGLE MAIN AND TRANSFER SCHEME
15
DOUBLE BUS SCHEME
16
DOUBLE BUS WITH BY-PASS SCHEME
17
DOUBLE BUS WITH BY-PASS SCHEME
18
DOUBLE MAIN AND TRANSFER SCHEME
20
DOUBLE BUS TWO BREAKER SCHEME
21
RING BUS SCHEME
22
❖ Reliability
❖ Operation Flexibility
❖ Ease of Maintenance
❖ Short Circuit Level Limitation
❖ Simplicity of Protection Arrangement
❖ Ease of Future expansion
❖ Land availability
❖ Cost
23
24