U403 Veria 1 Bldg., 62 West Ave.

, West Triangle, Quezon City


Tel Nos. (02) 376-3036,244-3488, Website:rhajteklinointernational.com

PROJECT: 1800 & 1880 EASTWOOD TOILET RENOVATION


PROJECT LOCATION: E. RODRIGUEZ JR. AVE. BRGY. BAGUMBAYAN 9999 QUEZON CITY
CONTRACTOR: RHAJTEK-LINO INTERNATIONAL CORPORATION

LIST OF REQUIREMENTS

Status
Requirements Date of Completion Remarks
Pending Completed
Orgazinational Chart for Rhajtek Team 1/7/2020

1880 Eastwood Inspection for as-built 1/14/2020

Initial Construction Schedule 1/17/2020 The initial schedule has a series type of schedule

Layout for OFM 1/17/2020


The revised construction schedule has an overlapping type of
Revised Construction Schedule 1/28/2020
schedule with a 1 week interval only in each floor

1800 Eastwood Inspection for as-built 1/29/2020

Request for OFM 1/29/2020

RFI 1/31/2020

Safety Requirements 1/31/2020


Confirmation regarding the as-built dimension PPID requested confirmation if all toilet doors has a dimension
2/5/2020
of all toilet doors of 900mmW and 2100mmH
Checklist for the site condition prior to the start
2/5/2020 PPID will handle the checklist
of construction
Certification of Moisture Resistance for Gypsum Supplier will issue MR Certification upon purchasing of
-
Board to be used in ceiling Gypsum Boards