1. Move In
No. of Laborers: 5
Duration: 7 days
3. Earthworks
3.1 Clearing and Grubbing
MH
Rate: 0.25
m3
Total Volume: 1760 m3
MH 440 MH
MD = 0.25 ×1760 m 3= =55 MD
m 3
8H/D
No. of Laborers: 10
55 MD
Duration = =5.5 days
10 M
Duration: 6 days
Page | 97
3.3 Backfilling and Compaction
m3
Rate: 0.82
hr
Total Volume: 1067.98 m3
1067.98× 1 M
MD = m3 H = 162.80MD
0.82 × 8
hr D
No. of Laborers: 30
162.80 MD
Duration = =5.43 days
30 M
Duration: 6 days
Page | 98
Page | 99
3.6 Embankment/ Earth Fill
m3
Rate: 3.60
hr
Total Volume: 850 m3
850 ×1 M
MD = m3 H = 29.51MD
3.60 ×8
hr D
No. of Laborers: 10
29.51 MD
Duration = =2.95 days
10 M
Duration: 3 days
4. Concrete Works
4.1 Concrete Footing
Total Volume: 58.368 m3
m3
Rate: 2 men=1.874
day
m3
1 man=0.937
day
58.368 m³ X 1 M
MD = =62.29 MD
0.937/ D
No. of Laborers: 10
62.29 MD
Duration: =6.5 days
30 M
Duration: 7 days
Page | 100
8.785 MD
Duration: =1.76 days
5M
Duration: 2 days
Page | 101
4.3 Ground Floor Column
Total Volume: 28.12 m3
m3
Rate: 2 men=1.874
day
m3
1 man=0.937
day
28.12 m ³ X 1 M
MD = =8.785 MD
0.937 m ³/ D
No. of Laborers: 6
8.785 MD
Duration: =5 days
8M
Duration: 5 days
Page | 102
15.47 MD
Duration: =2.58 days
4M
Duration: 3 days
Page | 103
4.6 Ground Tie Beam
Total Volume: 34 m3
m3
Rate: 2 men=1.874
day
m3
1 man=0.937
day
34 m3 X 1 M
=36.286 MD
MD = 0.937 m3
D
No. of Laborers: 8
32.286 MD
Duration: =4.536 days
6M
Duration: 5 days
Page | 104
30.95 MD
Duration: =3.869 days
10 M
Duration: 4 days
Page | 105
4.9 Ground Floor Slab
Total Volume: 100 m 3
m3
Rate: 2 men=1. 874
day
m3
1 man=0.937
day
100 m³ X 1 M
MD = =106.7 MD
0.937 m ³/ D
No. of Laborers: 12
106.7 MD
Duration: =8.89 days
12 M
Duration: 9 days
Page | 106
11.74 MD
Duration: =1.957 days
6M
Duration: 2 days
Page | 107
4.12 Stair Case
Total Volume: 8 m3
m3
Rate: 2 men=1.60
day
m3
1 man=0.80
day
8m³ X1 M
MD = =10 MD
0.80 m ³/ D
No. of Laborers: 4
10 MD
Duration: =2.5 day
4M
Duration: 3 day
4.14 Cistern
Total Volume: 5 m3
m3
Rate: 2 men=1.80
day
m3
1 man=0.90
day
5 m³ X 1 M
MD = =5.556 MD
0.90 m ³/ D
No. of Laborers: 3
Page | 108
5.556 MD
Duration: =1.85 days
3M
Duration: 2 days
Page | 109
5. Reinforcement Bars
5.1 Concrete Footing
No. of bars = 280 pcs @16mm diameter
Rate: .07MH/ kg
Total weight of bars = 280 x 14.8 = 4144 kg
MH
.07
kg
MD = 4144x = 36.26 MD
8H
D
No. of Laborers: 6
Duration = 79.86 / 6 = 6.04 days say, 6 days
Page | 110
MH
.08
kg
MD = 3963.42 = 39.6342 MD
8H
D
No. of Laborers: 6
Duration = 39.6342 / 6 = 6.61 days say, 7 days
Page | 111
No. of bars = 169 @ 12mm diameter
No. of bars = 508 @ 10mm diameter
Rate: .012MH/ kg
Total weight of bars = (213x14.8) + (155 x 9.47) +
(169 x 5.33) + (508 x 3.08) = 7085.66kg
MH
.08
kg
MD =7085.66 = 70.8566 MD
8H
D
No. of Laborers: 12
Duration = 70.8566 / 12 = 5.90 days say, 6 days
Page | 112
Duration = 74.921/12 = 6.24 days say, 7 days
Page | 113
5.11 Stair Case
No. of bars = 407 @ 10mm diameter
Rate: .08MH/ kg
Total weight of bars = (407 x 3.08) = 1253kg
MH
.08
kg
MD = = 1253 = 12.53 MD
8H
D
No. of Laborers: 4
Duration = 12.53 / 4 = 3.13 days say, 4 days
Page | 114
5.13 CHB Temperature Bars
No. of bars = 1699 @ 10mm diameter
Rate: .07MH/ kg
Total weight of bars = (1699 x 3.08) = 5232.92kg
MH
.07
kg
MD = 5232.92 = 45.788 MD
8H
D
No. of Laborers: 10
Duration = 45.788 / 10 = 4.578 days say, 5 days
6. Masonry Works
6.1 CHB Walls and Partition
Total Volume: 792 m3
m3
Rate: 2 men=30.50
day
m3
1 man=15.25
day
792m ³ X 1 M
MD = =51.934 MD
15.25 m ³/ D
No. of Laborers: 4
51.934 MD
Duration: =12.984 days
4M
Duration: 13 days
Page | 115
Duration: 15 days
Page | 116
6.3 Concrete Topping and Tile Work (Toilet)
Total Volume: 1,104 m3
m3
Rate: 2 men=86
day
m3
1 man=43
day
1,104 m ³ X 1 M
MD = =25.674 MD
43 m³ /D
No. of Laborers: 2
25.674 MD
Duration: =12.837 days
2M
Duration: 13 days
8. Carpentry Works
8.1 Scaffolding
bdft
Rate of 1 man=232
day
Total Area: 18,520 bdft
18,520bdft X 1 M
=79.828 MD
MD = bdft
232
day
No. of Laborers: 5
79.828 MD
Duration: =15.966 days
5M
Page | 117
Duration: 16 days
Page | 118
8.2 Form Works
bdft
Rate of 1 man=89
day
Total Area: 6,948 bdft
6,948 bdft X 1 M
=78.067 MD
MD = bdft
89
day
No. of Laborers: 5
78.067 MD
Duration: =15.613 days
5M
Duration: 16 days
8.3 Ceiling
bdft
Rate of 1 man=12
day
Total Area: 993.6 bdft
993.6 bdft X 1 M
=82.8 MD
MD = bdft
12
day
No. of Laborers: 4
82.8 MD
Duration: =20.7 days
4M
Duration: 21 days
9.2 Windows
Rate: 5 men = 2.10 pcs/ day
Page | 119
No. of jambs: 25pcs
25 pcs
MD = 2.10 pcs = 11.90 say 12 days for 5 men
day
Duration: 12 days
Page | 120
432 m2
MD = m2 = 25.412MD
17
md
No. of Laborers: 4
25.412md
Duration = = 6.353 days
4m
Duration: 7 days
Page | 121
12. Plumbing Works
A = 1 lot (850m2)
Rate for 1 man: 29 m 2
850 m2
MD = m2 = 29.31MD
29
md
No. of Laborers: 2
21.690 md
Duration = = 14.66 days
2m
Duration: 15 days
Page | 122
15. Steel Works
MH
Rate: 0.12
kg
Weight of bars: 198pcs x 3.7 kg + 352 kg= 1084.60 kg
MH
0.12
MD = kg
1084.60 kg × =16.27 MD
8H
No. of Laborers: 8
16.27 MD
Duration: =2.03 da ys
8M
Duration: 3 days
Page | 123