COMPUTATION OF DURATION PER ACTIVITY

1. Move In
No. of Laborers: 5
Duration: 7 days

2. General Technical Requirements


No. of Carpenters: 4
No. of Laborers: 4
Duration: 3 days

3. Earthworks
3.1 Clearing and Grubbing
MH
Rate: 0.25
m3
Total Volume: 1760 m3
MH 440 MH
MD = 0.25 ×1760 m 3= =55 MD
m 3
8H/D
No. of Laborers: 10
55 MD
Duration = =5.5 days
10 M
Duration: 6 days

3.2 Excavation for Foundation


MH
Rate: 8.00
m3
Total Volume: 217.98 m3
MH 1743.84 MH
MD = 8.00 ×217.98 m 3= =217.98 MD
m 3
8H/D
No. of Laborers: 30
217.98 MD
Duration = =7.27 days
30 M
Duration: 8 days

Page | 97
3.3 Backfilling and Compaction
m3
Rate: 0.82
hr
Total Volume: 1067.98 m3
1067.98× 1 M
MD = m3 H = 162.80MD
0.82 × 8
hr D

No. of Laborers: 30
162.80 MD
Duration = =5.43 days
30 M
Duration: 6 days

3.4 Soil Poisoning


m2
Rate: 320
hr
Total Area: 850 m2
850 m2 × 1 M
=0.33 MD
MD = m2 H
320 ×8
hr D
No. of Laborers: 2
0.33 MD
Duration = =0.165 days
2M
Duration: 1 day

3.5 Gravel Bed


m3
Rate: 0.3
hr
Total Volume: 118m3
118 m3 ×1 M
MD = m3 H = 49.17MD
0.3 x8
hr D
No. of Laborers: 10
49.17 MD
Duration = =4.92 days
10 M
Duration: 5 days

Page | 98
Page | 99
3.6 Embankment/ Earth Fill
m3
Rate: 3.60
hr
Total Volume: 850 m3
850 ×1 M
MD = m3 H = 29.51MD
3.60 ×8
hr D
No. of Laborers: 10
29.51 MD
Duration = =2.95 days
10 M
Duration: 3 days

4. Concrete Works
4.1 Concrete Footing
Total Volume: 58.368 m3
m3
Rate: 2 men=1.874
day
m3
1 man=0.937
day
58.368 m³ X 1 M
MD = =62.29 MD
0.937/ D
No. of Laborers: 10
62.29 MD
Duration: =6.5 days
30 M
Duration: 7 days

4.2 Column Neck


Total Volume: 8.232 m 3
m3
Rate: 2 men=1. 874
day
m3
1 man=0.937
day
8.232m ³ X 1 M
MD = =8.785 MD
0.937 m ³/ D
No. of Laborers: 5

Page | 100
8.785 MD
Duration: =1.76 days
5M
Duration: 2 days

Page | 101
4.3 Ground Floor Column
Total Volume: 28.12 m3
m3
Rate: 2 men=1.874
day
m3
1 man=0.937
day
28.12 m ³ X 1 M
MD = =8.785 MD
0.937 m ³/ D
No. of Laborers: 6
8.785 MD
Duration: =5 days
8M
Duration: 5 days

4.4 Second Floor Column


Total Volume: 21 m3
m3
Rate: 2 men=1.874
day
m3
1 man=0.937
day
21m ³ X 1 M
MD = =21.41 MD
0.937 m ³/ D
No. of Laborers: 6
21.41 MD
Duration: =3.74 days
8M
Duration: 4 days

4.5 Roof Extended Column


Total Volume: 14.5 m3
m3
Rate: 2 men=1.874
day
m3
1 man=0.937
day
14.5 m³ X 1 M
MD = =15.47 MD
0.937 m ³/ D
No. of Laborers: 6

Page | 102
15.47 MD
Duration: =2.58 days
4M
Duration: 3 days

Page | 103
4.6 Ground Tie Beam
Total Volume: 34 m3
m3
Rate: 2 men=1.874
day
m3
1 man=0.937
day
34 m3 X 1 M
=36.286 MD
MD = 0.937 m3
D
No. of Laborers: 8
32.286 MD
Duration: =4.536 days
6M
Duration: 5 days

4.7 Floor Beam


Total Volume: 59 m3
m3
Rate: 2 men=1.874
day
m3
1 man=0.937
day
59 m³ X 1 M
MD = =62.967 MD
0.937 m ³/ D
No. of Laborers: 11
62.967 MD
Duration: =5.724 days
10 M
Duration: 6 days

4.8 Roof Beam


Total Volume: 29 m3
m3
Rate: 2 men=1.874
day
m3
1 man=0. 937
day
29 m³ X 1 M
MD = =30.95 MD
0.937 m ³ /D
No. of Laborers: 8

Page | 104
30.95 MD
Duration: =3.869 days
10 M
Duration: 4 days

Page | 105
4.9 Ground Floor Slab
Total Volume: 100 m 3
m3
Rate: 2 men=1. 874
day
m3
1 man=0.937
day
100 m³ X 1 M
MD = =106.7 MD
0.937 m ³/ D
No. of Laborers: 12
106.7 MD
Duration: =8.89 days
12 M
Duration: 9 days

4.10 Second Floor Slab


Total Volume: 62 m3
m3
Rate: 2 men=1.874
day
m3
1 man=0. 937
day
62m ³ X 1 M
MD = =66.17 MD
0.937 m ³/ D
No. of Laborers: 12
66.17 MD
Duration: =5.51 days
12 M
Duration: 6 days

4.11 Concrete Gutter


Total Volume: 11 m 3
m3
Rate: 2 men=1.874
day
m3
1 man=0.937
day
11 m ³ X 1 M
MD = =11.74 MD
0.937 m ³/ D
No. of Laborers: 6

Page | 106
11.74 MD
Duration: =1.957 days
6M
Duration: 2 days

Page | 107
4.12 Stair Case
Total Volume: 8 m3
m3
Rate: 2 men=1.60
day
m3
1 man=0.80
day
8m³ X1 M
MD = =10 MD
0.80 m ³/ D
No. of Laborers: 4
10 MD
Duration: =2.5 day
4M
Duration: 3 day

4.13 Septic Tank


Total Volume: 6 m3
m3
Rate: 2 men=1.80
day
m3
1 man=0.90
day
6m³ X1 M
MD = =6.667 MD
0.90 m ³ /D
No. of Laborers: 4
5.556 MD
Duration: =1.667 days
3M
Duration: 2 days

4.14 Cistern

Total Volume: 5 m3
m3
Rate: 2 men=1.80
day
m3
1 man=0.90
day
5 m³ X 1 M
MD = =5.556 MD
0.90 m ³/ D
No. of Laborers: 3

Page | 108
5.556 MD
Duration: =1.85 days
3M
Duration: 2 days

Page | 109
5. Reinforcement Bars
5.1 Concrete Footing
No. of bars = 280 pcs @16mm diameter
Rate: .07MH/ kg
Total weight of bars = 280 x 14.8 = 4144 kg
MH
.07
kg
MD = 4144x = 36.26 MD
8H
D
No. of Laborers: 6
Duration = 79.86 / 6 = 6.04 days say, 6 days

5.2 Column Neck


No. of bars = 46 @ 20mm diameter
No. of bars = 46 @ 16mm diameter
No. of bars = 125 @ 10mm diameter
Rate: .07MH/ kg
Total weight of bars = (46 x 14.8) + (46 x 9.47) +
(125 x 3.08) = 1501.42kg
MH
.07
kg
MD = 1501.42 x = 13.13 MD
8H
D
No. of Laborers:4
Duration = 13.13 / 4 = 3.28 days say, 4 days

5.3 Ground Floor Column


No. of bars = 118 @ 20mm diameter
No. of bars = 118 @ 16mm diameter
No. of bars = 357 @ 10mm diameter
Rate: .08MH/ kg
Total weight of bars = (118x14.8) + (118 x 9.47) +
(357 x 3.08) = 3963.42kg

Page | 110
MH
.08
kg
MD = 3963.42 = 39.6342 MD
8H
D
No. of Laborers: 6
Duration = 39.6342 / 6 = 6.61 days say, 7 days

5.4 Second Floor Column


No. of bars =99 @ 20mm diameter
No. of bars = 106 @ 16mm diameter
No. of bars = 196 @ 10mm diameter
Rate: .08MH/ kg
Total weight of bars = (99 x 14.8) + (106 x 9.47) + (196 x 3.08)
= 3072.7kg
MH
.08
kg
MD = 3072.7 x =30.727 MD
8H
D
No. of Laborers: 7
Duration = 30.727 / 7 = 4.4 days say, 5 days

5.5 Ground Tie Beam


No. of bars =418 @ 20mm diameter
No. of bars = 920 @ 10mm diameter
Rate: .08MH/ kg
Total weight of bars = (418 x 14.8) + (920 x 3.08) = kg
MH
.08
kg
MD = 9020 x = 90.2MD
8H
D
No. of Laborers: 12
Duration = 90 /12 = 7.52 days say, 8 days

5.6 Floor Beam


No. of bars = 213 @ 20mm diameter
No. of bars = 155 @ 16mm diameter

Page | 111
No. of bars = 169 @ 12mm diameter
No. of bars = 508 @ 10mm diameter
Rate: .012MH/ kg
Total weight of bars = (213x14.8) + (155 x 9.47) +
(169 x 5.33) + (508 x 3.08) = 7085.66kg
MH
.08
kg
MD =7085.66 = 70.8566 MD
8H
D
No. of Laborers: 12
Duration = 70.8566 / 12 = 5.90 days say, 6 days

5.7 Roof Beam


No. of bars = 310 @ 20mm diameter
No. of bars = 172 @ 16mm diameter
No. of bars = 80 @ 12mm diameter
No. of bars = 638 @ 10mm diameter
Rate: .08MH/ kg
Total weight of bars = (310x14.8) + (172 x 9.47) + (80 x 5.33)
+ (638 x 3.08) = 8608.52 kg
MH
.08
kg
MD = 8608.52 = 86.085 MD
8H
D
No. of Laborers: 12
Duration = 86.085 / 12 = 7.174 days say, 8 days

5.8 Ground Floor Slab


No. of bars = 2780@ 10mm diameter
Rate: .07MH/ kg
Total weight of bars = (2780 x 3.08) = 8562.4kg
MH
.07
kg
MD = 8562.4 = 74.921 MD
8H
D
No. of Laborers: 12

Page | 112
Duration = 74.921/12 = 6.24 days say, 7 days

5.9 Second Floor Slab


No. of bars = 3134 @ 10mm diameter
Rate: .08MH/ kg
Total weight of bars = (3134 x 3.08) = 9652.72kg
MH
.08
kg
MD = 9652.72 = 96.527 MD
8H
D
No. of Laborers: 12
Duration = 96.527 / 12 = 8.04 days say, 8 days

Page | 113
5.11 Stair Case
No. of bars = 407 @ 10mm diameter
Rate: .08MH/ kg
Total weight of bars = (407 x 3.08) = 1253kg
MH
.08
kg
MD = = 1253 = 12.53 MD
8H
D
No. of Laborers: 4
Duration = 12.53 / 4 = 3.13 days say, 4 days

5.12 Stair Footing


No. of bars = 50 @ 10mm diameter
Rate: .08MH/ kg
Total weight of bars = (50x 3.08) = 154kg
MH
.08
kg
MD = 154 = 1.54 MD
8H
D
No. of Laborers: 2
Duration = 1.54 / 2 = 0.77 days say, 1 day

Page | 114
5.13 CHB Temperature Bars
No. of bars = 1699 @ 10mm diameter
Rate: .07MH/ kg
Total weight of bars = (1699 x 3.08) = 5232.92kg
MH
.07
kg
MD = 5232.92 = 45.788 MD
8H
D
No. of Laborers: 10
Duration = 45.788 / 10 = 4.578 days say, 5 days

6. Masonry Works
6.1 CHB Walls and Partition
Total Volume: 792 m3
m3
Rate: 2 men=30.50
day
m3
1 man=15.25
day
792m ³ X 1 M
MD = =51.934 MD
15.25 m ³/ D
No. of Laborers: 4
51.934 MD
Duration: =12.984 days
4M
Duration: 13 days

6.2 Wall Plaster


Total Volume: 1,662 m3
m3
Rate: 2 men=37
day
m3
1 man=18.50
day
1,662m ³ X 1 M
MD = =89.838 MD
18.50 m ³/ D
No. of Laborers: 6
89.838 MD
Duration: =14.973 days
6M

Page | 115
Duration: 15 days

Page | 116
6.3 Concrete Topping and Tile Work (Toilet)
Total Volume: 1,104 m3
m3
Rate: 2 men=86
day
m3
1 man=43
day
1,104 m ³ X 1 M
MD = =25.674 MD
43 m³ /D
No. of Laborers: 2
25.674 MD
Duration: =12.837 days
2M
Duration: 13 days

7. Water Proofing for Toilet and Roof Deck Slab


m2
Rate: 2 men=15.2
d ay
m2
1 man=7.6
day
Total Area: 532 m2
532m 2 X 1 M
MD = =70 MD
7.6 m 2 /D
No. of Laborers: 7
70 MD
Duration: =10 days
7M
Duration: 10 days

8. Carpentry Works
8.1 Scaffolding
bdft
Rate of 1 man=232
day
Total Area: 18,520 bdft
18,520bdft X 1 M
=79.828 MD
MD = bdft
232
day
No. of Laborers: 5
79.828 MD
Duration: =15.966 days
5M
Page | 117
Duration: 16 days

Page | 118
8.2 Form Works
bdft
Rate of 1 man=89
day
Total Area: 6,948 bdft
6,948 bdft X 1 M
=78.067 MD
MD = bdft
89
day
No. of Laborers: 5
78.067 MD
Duration: =15.613 days
5M
Duration: 16 days

8.3 Ceiling
bdft
Rate of 1 man=12
day
Total Area: 993.6 bdft
993.6 bdft X 1 M
=82.8 MD
MD = bdft
12
day
No. of Laborers: 4
82.8 MD
Duration: =20.7 days
4M
Duration: 21 days

9. Doors and Windows


9.1 Doors
Rate: 2 men = 2.75 pcs/ day
No. of jambs: 78pcs
78 pcs
MD = 2.75 pcs = 28.36 say 29 days for 2 men
day
So, 14.18 say 15 days for 4 men
Duration: 15 days

9.2 Windows
Rate: 5 men = 2.10 pcs/ day

Page | 119
No. of jambs: 25pcs
25 pcs
MD = 2.10 pcs = 11.90 say 12 days for 5 men
day
Duration: 12 days

10. Wall Cladding


m2
Rate: 2 men=11
day
m2
1 man=5.5
day
Total Area: 156.20 m2
156.20 m2 X 1 M
MD = =28.40 MD
5.5 m 2 /D
No. of Laborers: 2
28.40 MD
Duration: =14.20 days
2M
Duration: 15 days

11. Painting Works


11.1 External Painting
m2
Rate: 12.5
md
A = 342m2
342 m2
MD = m2 = 27.36MD
12.5
md
No. of Laborers: 4
27.36 md
Duration = = 6.84 days
4m
Duration: 7 days

11.2 Internal Painting


m2
Rate: 17
md
A = 432m 2

Page | 120
432 m2
MD = m2 = 25.412MD
17
md
No. of Laborers: 4
25.412md
Duration = = 6.353 days
4m
Duration: 7 days

Page | 121
12. Plumbing Works
A = 1 lot (850m2)
Rate for 1 man: 29 m 2
850 m2
MD = m2 = 29.31MD
29
md
No. of Laborers: 2
21.690 md
Duration = = 14.66 days
2m
Duration: 15 days

13. Electrical Works


A = 1 lot (850m2)
Rate for 1 man: 5.25 m2
629 m2
MD = m2 = 161.90 MD
5.25
md
No. of Laborers: 8
161.90 md
Duration = = 20.23 days
8m
Duration: 21 days

14. Catch Basin


Length = 72 linear meter (lm)
Rate for 1 man: 8.5 lm
72 m2
2
MD = m = 8.47MD
8.5
md
No. of Laborers: 2
8.47 md
Duration = = 4.24 days
2m
Duration: 5 days

Page | 122
15. Steel Works
MH
Rate: 0.12
kg
Weight of bars: 198pcs x 3.7 kg + 352 kg= 1084.60 kg
MH
0.12
MD = kg
1084.60 kg × =16.27 MD
8H
No. of Laborers: 8
16.27 MD
Duration: =2.03 da ys
8M
Duration: 3 days

16. Move Out


No. of Laborers: 10
Duration: 7 days