Project : Hasang HEPP

Date : August 6, 2019


Weather : Bright
Rainfall / Temporature : - mm / 30°
Rainfall Time :
Working Time : 8 hour
Construction Quantity Man Power Status August 6, 2019
Person
DescrIptIon Q'ty Unit Status
in Description
Prev. Today Total Percent. P.DAY TODAY ACCU.
Charge
1 POWER HOUSE Project manager 36 - 36
1.1 EARTH WORK Site Manager 348 1 349
a) Common soil Chief Supervisor 358 1 359
Weathered Rock excavated random,
1) 90~95% 6,707.95 M3 130.00 130.00 13.00% Supervisor 945 1 946
compaction
b) Embankment Chief Surveyor 355 1 356
Backfill 4,383.84 M3 1,943.96 1,943.96 44.34% Surveyor 558 1 559
Backfill(Rubble Stone) For power house M3 852.97 852.97 34.67% As Surveyor 922 1 923
2,460.16
Backfill(Rubble Stone) For Penstock M3 262.40 262.40 10.67% Qc Office 67 - 67
1.2 CONCRETE WORK Safety Officer 357 1 358
a) Concrete Admin Officer 306 - 306
1) Concrete fck=24MPa 5,098.88 M3 2,545.48 2,545.48 49.92% Material Control 357 1 358
2) Lean Concrete fck=13MPa 117.69 M3 208.33 208.33 177.02% Logistic 359 1 360
3) Concrete fck=30MPa M3 172.00 172.00 Asst. Logistic 307 - 307
b) Formwork 3~6 times 3,184.72 M2 3,924.31 3,924.31 123.22% Driver 718 1 719
c) Timbering 776.78 M3 78.00 78.00 10.04% Foreman 978 - 978
d) Scaffolding steel pipe 1,863.20 M2 2,987.77 2,987.77 160.36% Skill Labor 1,664 3 1,667
e) Rebar H13~H32 340.20 ton 203.01 203.01 59.67% Helper 201 - 201
f) Rubblework h=1.5m 192.40 M3 28.00 28.00 14.55% Security 971 1 972
g) Grating Cover Operator 1,111 1 1,112
PT. BAGAS ADHI PERKASA

h) Additional Block-Out For Anchor M2 63.00 63.00 Electrican 532 1 533


1) Grating Cover 1.0 x 1.0 3.00 EA Mechanic 4,985 - 4,985
2) Grating Cover 1.2 x 3.0 1.00 EA Worker 15,188 19 15,207
CIVIL

h) Ladder 7.20 M
2 TAILRACE
2.1 EARTH WORK
a) Backfill 547.86 M3 560.00 560.00 102.22%
b) Rock Cleaning 1,400.00 M2 Total 31,623 35 31,658
c) Rubble Stone M3 10.00 10.00
2.2 CONCRETE WORK
a) Concrete
1) Concrete fck=24MPa 1,090.23 M3 1,102.19 1,102.19 101.10%
2) Lean Concrete fck=13MPa 62.09 M3 203.50 203.50 327.75% Equipment Status August 6, 2019
b) Formwork wood 2,500.00 M2 1,787.70 1,787.70 71.51% Description Dim P.DAY TODAY ACCU.
c) Scaffolding steel pipe 1,600.00 M2 621.50 621.50 38.84% Exavator 100 HP 1,947 1 1,948
d) Spacer 1,514.77 M2 BulDozer 150 HP 505 - 505
e) Water Tightness 90.00 M 75.00 75.00 83.33% Dump Truck 10 Ton 739 - 739
f) Drain Pipe VC Pipe D=100mm 60.00 M Dump Truck 5 Ton 925 1 926
g) Drain Board 650.00 M 2
Mini Pick up 989 1 990
h) Rebar Breaker 386 - 386
i) Rebar H13 - H 32 141.73 Ton 54.07 54.07 38.15% Vibro Roler 428 - 428
j) Non-woven fabric 650.64 M Tangki truck 523 1 524
k) Sealant 20 x 25 194.67 M Mini bus 516 - 516
l) Styrofoam 121.98 M2
m) Dowel Bar D 32 mm, L= 1,000 mm 86.00 Nos 78.00 78.00 90.70% Total 6,958 4 6,962
n) P V C Water Stop W= 300,9t 44.94 M 300.50 300.50 668.67%

3 PENSTOCK
3.1 EARTH WORK
a) Excavation
1) Common Soil 216,140.00 M3 204,059.88 204,059.88 94.41%
2) Weathered Rock 13,147.00 M3 28,049.11 28,049.11 213.35%
3) Weak Rock 1,831.00 M3 3,540.47 3,540.47 193.36%
4) Excavation strucktur M3
b) Embankment
1) Common Soil 8,334.33 M3 11,700.00 11,700.00 140.38%
excavated random,
2) Backfill 90~95% compaction 608.80 M 3
4,809.30 4,809.30 789.96%

3) Riprap t=300mm 809.49 M 3


97.81 97.81 12.08%
4) Subbase 523.78 M3
5) Toe fck=18Mpa 54.55 M3 6.89 6.89 12.63%
3.2 CONCRETE WORK
a) Concrete
1) Concrete fck=24MPa 4,395.46 M3 3,945.41 3,945.41 89.76%
2) Lean Concrete fck=13MPa 184.71 M3 651.91 651.91 352.94%
b) Formwork 3~6 times 4,801.86 M2 5,081.22 5,081.22 105.82%
c) Scaffolding steel pipe 2,727.47 M2 3,604.72 3,604.72 132.16%
d) Rebar H13~H32 285.44 Ton 181.51 181.51 63.59%
e) Ladder 146.50 M
f) Rock Anchor 132.10 M 56.00 56.00 42.39%
Project : Hasang HEPP
Date : August 6, 2019
Weather : Bright
Rainfall / Temporature : - mm / 30°
Rainfall Time :
Working Time : 8 hour
Construction Quantity Man Power Status August 6, 2019
Person
DescrIptIon Q'ty Unit Status
in Description
Prev. Today Total Percent. P.DAY TODAY ACCU.
Charge
3.3 FOUNDATION TREATMENT
a) Drilled File
Drilling Hole For Drille
1) DIA. 600mm 2,717.55 m 937.72 937.72 34.51%
File
2) Filling Quantity For Hole Cement Mortar 769.07 M3 265.00 265.00 34.46%
3) Filling Quantity For Holefck=13MPa From POSCO 769.07 M3 265.00 265.00
Instaling Casing Tube
4) For Soil Layer 2,717.55 m
and Removal
DRILLING SURVEY IN CONSTRUCTION
b)
PHASE
1) Drilling Soil NX 220.00 m 41.50 41.50 18.86%
2) Drilling Weathered Rock NX 75.90 m 38.00 38.00 50.07%
3) Drilling Soft Rock NX 12.10 m
4) Standard Penetration Test INTERVAL=1m 295.90 TIMES 72.00 72.00 24.33%
5) Pile Loading Test FOR 29.70 TIMES
6) Plate Bering Test For Shallow Foundation
31.90 TIMES 2.00 2.00 6.27%
3.4 DRAINAGE WORK
a) Drainage Structure
1) Corrugated/Hume Pipe D 800 36.75 m 127.00 127.00 345.58%
2) Corrugated/Hume Pipe D 1,000 16.59 m 44.00 44.00 265.22%
3) Excavation 38.04 M3 271.00 271.00 712.41%
4) Ruber Stone 38.04 M3
5) Backfil Stone M3
6) Sano 38.04 M3
PT. BAGAS ADHI PERKASA

7) Common Soil 38.04 M3


8) Trench cut 39.20 M3 445.61 445.61 1136.76%
9) Concrete fck=24MPa 75.58 M3 7.10 7.10 9.39%
CIVIL

10) Concrete fck=21MPa 32.08 M3 66.50 66.50 66.50%


11) Concrete fck=13Mpa M3 41.00 41.00
12) FORM 312.04 m2 668.00 668.00 214.08%
13) Rebar D13 0.69 ton 4.00 4.00 579.71%
b) Ditch
1) Trench cut 1,866.31 M3 347.11 347.11 18.60%
2) Riprap 754.83 M3 614.00 614.00 81.34%
3) Mortar t=50mm 254.64 M3 216.00 216.00 84.83%
4) Concrete (Slope protection+Out 0f Conctract) M3 156.50 156.50
3.5 PROVISIONAL SUM 1.00 LS
3.6 ADDITIONAL WORK
1) Prepare Location M² 415.00 415.00 #DIV/0!
2) Instal Form Work M² 261.00 261.00 #DIV/0!
3) Instal Ware Mash Nos 144.00 144.00 #DIV/0!
4) Concrete FCK=24MPa M³ 135.80 135.80
5) Concrete FCK=21MPa M³ 192.50 12.00 204.50
6) Concrete FCK=18MPa M³ 125.00 125.00 #DIV/0!
7) Concrete FCK=13MPa M³ 199.00 199.00
8) Daywork for Excavator (0.7 - 1.0) Day 12.00 12.00
9) PVC pipe M1 24.00 24.00
10) Galvanized Pipe M 30.00 30.00
11) Incentive pay -1 (Rush Job) Ls 1.00 1.00
12) Incentive pay -2 (Rush Job) Ls 1.00 1.00

Material Use :

TODAY'S WORK ACTIVITY TOMORROW'S WORK ACTIVITY


- ADDITIONAL WORK - ADDITIONAL WORK
- Concrete FC 21 Access Road Power House = 12.00 M3 - Formwork Drainase = 20.00 M2

2. Complaint 2. Complaint

SIGNATURE
PT. BAGAS ADHI PERKASA PT. POSCO E & C

(..................................................................) (............................................................) (...........................................) (............................................) (..................................................)