Академический Документы
Профессиональный Документы
Культура Документы
AMT-SGEW – Q- xxx
Revision 00
TITLE of ACTIVITY
TABLE OF CONTENTS
P a g e 1 | 10
Doc. AMT-SGEW – Q- xxx
Revision 00
1. GENERAL ………………………………………………………………………………..3
2. PURPOSE………………………………………………………………………………….3
3.1 PROCEDURE…………………………………………………………………....6-9
4. EQUIPMENT.................................................................................................................... 9-10
P a g e 2 | 10
Doc. AMT-SGEW – Q- xxx
Revision 00
1. GENERAL
1.1 PURPOSE
The purpose of this Method Statement is to define the works specifically
for the Construction of Access Roads, (Asphalt and Rough Roads) as
described in the scope of works for Abdul Mohsen AH Al Tamimi
Partners Company under contract no. 6600045093.
1.2 SCOPE
This Method Statement covers the activities, from Survey, Cut and Fill up
to material disposal and inspections and is intended for South Ghawar UR
Early Works and TVF only.
P a g e 3 | 10
Doc. AMT-SGEW – Q- xxx
Revision 00
3. QUALITY ASSURANCE
All borrow materials will be subject for test to determine the soil characteristic in
accordance approved specification. Testing and inspection will be conducted
during all stages shall be implemented and to make sure that there will no
deviation. The QC manager will audit all records required in compliance with the
aforementioned.
P a g e 4 | 10
Doc. AMT-SGEW – Q- xxx
Revision 00
5. EXECUTION
5.3.3 Hand digging using hand tools shall be use for soft part of
particular small excavation. However if excavation is more than
three (3) meters deep, construction team together with Safety
P a g e 5 | 10
Doc. AMT-SGEW – Q- xxx
Revision 00
5.3.4 The suitable materials will be stockpiled at the designated area far
enough not to cause disruption in the excavation zone. The
unsuitable materials shall be disposed off through pay loader and
dump truck to Saudi Aramco approved Areas.
P a g e 6 | 10
Doc. AMT-SGEW – Q- xxx
Revision 00
5.5.6 After reaching the final elevation of the bottom level of particular
point of inspection, the project site Lead Engineer together with QC
Engineer shall have a joint inspection to check the smoothness of
surface. Any protruding materials, stones or any hard pointed
objects shall be immediately removed and re-compacted to make it
sure that the area is smooth and ready to accept foreign materials
in backfilling.
P a g e 7 | 10
Doc. AMT-SGEW – Q- xxx
Revision 00
6. REFERENCES
SAES-A-114 Excavation and Backfill.
PIP CVS02100 Site Preparation, Excavation, and Backfill Specification
7. INSPECTIONS
7.1 Inspections shall be carried pout with reference to the applicable SATIP
SATIP-A-114-01 Earthwork - Site Preparation, Excavation and Backfill During
Construction
SAIC-A-1001 Soil Sampling, Testing and Review of Test Reports
SAIC-A-1002 Fill, Select Fill and Marl Cap Materials Receiving Inspection
SAIC-A-1003 Soil Protection and Control, Drainage and De-watering
Inspection
SAIC-A-1004 Fill Placement and Compaction Inspection
SAIC-A-1005 Compaction Testing
SAIC-A-1006 Final Fill Inspection
3.2.1 Construction shall obtain IFC or approved shop drawing prior to start
execution per item of particular work.
P a g e 8 | 10
Doc. AMT-SGEW – Q- xxx
Revision 00
4. LIMITATIONS
5.0 Equipment
Lists of Equipments to use in the execution of Civil Earthworks
Excavator Heavy Equipment (for hard rock)
Back hoe or Loader for lifting of excavated materials
Dump truck haulers
Water truck
Compactor Vibrator Roller (for wider area)
JCB for trench excavation
Other equipments may add in expediting the task.
P a g e 9 | 10
Doc. AMT-SGEW – Q- xxx
Revision 00
Barricades shall be set up around the sites. Warning signs shall be 6.1
posted to caution other personnel on site of the ongoing work. The
Material Safety Data Sheet (MSDS) of a hazardous material shall be
.available whenever in use at site
P a g e 10 | 10