Академический Документы
Профессиональный Документы
Культура Документы
by
( ROMANIA )
Abstract
Romania and Hungary intent to have an between RENEL (Romanian Electricity Authority) and
interconnection at 400 kV voltage in the next future. between MVMT company (Hungarian Electricity
The existing link between Arad in Romania and Szeged Authority) in 1997the operation to 400 kV of the
in Hungary, has been operating for about 25 years at interconnection line between the two systems is to be
220 kV voltage, on the structures initially designed for done by linking this line to 400 kV substations at
400 kV conditions. During this time, the reference Sandorfalva (Hungary) and Mintia (Romania). The
standards for meteorological conditions and achievement of the interconnection to 400 kV between
methodologies of the line elements design were two national power systems, required the execution of
changed. important works at 400 kV substations in Sibiu and
Mintia and on the overhead electric lines Sibiu - Mintia
A complete expertise of the line on the Romanian (130 km) and Mintia - Arad (138 km) that were
territory was done and after that, the samples of operated at 220 kV voltage. The lines between Sibiu
conductors, earthwires, dampers, insulator strings and and Sandorfalva (373 km, out of which 53 km on the
guys were tested in the mechanical and electrical Hungarian territory) has been submitted to a complex
laboratories. A project was designed and now, the rehabilitation programme taking into consideration its
refurbishment of the line elements and the upgrading of importance.
the representative towers are ready.
Keywords: Interconnection/Upgrading/Refurbishment
1. General
Under the new political and economical conditions of
the Eastern and Central European countries after 1990,
Romania has made its opinion to extend the co-
operation with the European states in the energy field
and to interconnect the national power system to the
power systems affiliated to UCPTE. The transition of
the interconnection line Arad (Romania) - Szeged
(Hungary), (Fig. 1) to 400 kV operation is one of the
major requirements to interconnect the Romanian
power system to the power systems affiliated to
UCPTE. The overhead electric line Arad-Szeged,
designed to be operated at 400 kV voltage has been Fig. 1 Romanian network designed at 400 kV
running for about 25 years to 220 kV voltage taking
into consideration the energy requirements in the area. 2. Present condition of the line
In compliance with the agreement concluded in 1996 In order to retrofit the main, its present condition has
_____________________________________________ been examined by the visual analysis of all component
*) 1-3 Lacul Tei Blvd, Bucharest 72301
elements on the Romanian entire route and by painted or bolted-zinc plated, of common steel or
speciality laboratory tests upon its mechanical and CORTEN) presented damages as follows:
electric elements n tower elements bent at the lower side of structures
2.1 Visual analysis due to agricultural equipment (Fig.4);
The analysis performed on the entire line pointed out n deviations from the verticality and rotations of the
the necessity of some intervention works to all guyed portal towers;
component elements of the line. In the hilly zone of the
line, due to the geological instability, a series of
anchored portal towers showed deviations from the
vertical line. In the afforested zones, the line right of
way didn’t meet the 400 kV voltage level. Generally,
the towers foundations were in good condition, but
faults that resulted in the corrosion of reinforcing steel
shielding bare have been remarked. The following have
been noticed:
n cracks caused by the chemical action of the
polluting agents in the sulphates, chlorides,
carbonates zone (Fig. 2);
n damages due to the agricultural equipment impact;
n soil off-covering caused by rain flooding;
5. Line upgrading
The recalculation according to the present standards of
the line towers achieved in compliance with the
existing standards in different periods of time was
aimed at assuring the safety parameters necessary for
the operation of an overhead line that interconnects two
network systems to 400 kV voltage. In case of Y type
towers, the recalculation based on the present standard
led to the necessity of reinforcing of some diagonal
members in the beam where the efforts were exceeded
two times and the reinforcement in certain cases of
upper haunch main members and the joint bolts as well
as the achievement of horizontal bracings in order to
avoid the distortion of the section front sides (to be
remarked at the existing towers)
In case of guyed towers, the recalculation based on the
present standard implied the taking into consideration
of the longitudinal loads in case of broken conductors
and the results showed the necessity of replacing some