Академический Документы
Профессиональный Документы
Культура Документы
concrete Only for 4 inch slab/beams without including cost for columns max 500 cubic ft = 14.5 meter cube = 14.5
*4300rs = 62350rs
For an average residential construction (Complete from foundation, construction, electrification, plumbing, tiling,
doors Nd windows etc Ofcourse of normal ranges);
So, for 800 sq.ft normally you can calculate it as (800x1000) = Rs.800000/- ( Eight lakes only)
Construction cost of 800sft area RCC Slab by considering it as a 100 mm thick Slab in residential
Building.
Including the shuttering area of beam sides & slab outside total area of Suttering will be 918sft .
(A) Shuttering with Marine Ply Wood / Plastic Coated Ply Wood of 12mm thick with all necessary Supports and
Scaffolding.
Calculation for Volume of Concrete for 800Sft = 74.35 Sqm x 0.10m = 7.44Cum
Kindly add the volume of Concrete for Beam as per the Drawing with you
(B1 )20 mm size Stone aggregate required for the Slab Concrete = 7 Cum (247 cft )
(B2) River Sand required for the Slab Concrete = 4 Cum ( 142 cft )
If the Concrete Mix is M15 grade / 1:2:4 Cement Required is 6.2 bags
If this Slab is a Floor Slab 669 kg Steel is required and If it is a Roof Slab 558 kg Steel is required.
Quantity of 20mm Stone aggregate , River Sand and Cement is given above . To get the cost of material You can
multiply this Quantity with Rate of material in Your Area . All Labour charges for Concrete Work , Concrete
Mixing, Shifting concrete to the slab, Skilled mason required is 918Sft x Rs 4/sft =Rs 3672/=( this Rs 4/sft is
variable according to the Location of work ).
( D)If we are using Lift/ Builders Hoist for shifting concrete from Ground Floor to upper floor Rs
1500/= to be added as Rent for a day.