GNPOWER DINGININ LTD. CO.

CONSTRUCTION
GNPD 03 00 1 MCP 50XXX 0
MANAGEMENT

Mechanical Completion (Final Inspection) Punchlist

System Title: Back Energizing System Number: 00-D-1001


Sub-system Title: 500kV GIS System Sub-system Number: 00-D-1001-004
Drawing 1
Unit:
Number:
FI&TR Number: Date: August 5, 2019

P&ID Number:

(Strikethrough if not
applicable)
System Walk Down Inspection System WTP Inspection

Defect Category
Item Initiated
Discip Equipment Description P/L
No. By Comm
Initiator

500kV GIS MJN


Indoor and 09175616113 A
C Control 09338571266
1
Room
Cable
Trench Pit

- No cover for snake/rodent entry point

Defect Category Description: Discipline :


A - Must be corrected before system commissioning
B - Must be corrected before automated operation B = Boiler; T = Turbine; C = Civil; ECI = Electrical / Control
C - Must be corrected before performance/reliability test & Instrumentation; BoP = Balance of Plant
D - Must be corrected before commercial operation date
Mechanical Completion (Final Inspection) Punchlist Acceptance
GNPD Engineering GNPD Construction GNPD Quality GNPD Commissioning
Name:
Position:

Signature:

Date:

GNPD 03 00 1 TEM 50130 0 - Effective Date 2019.02.15 Page 1 of 1