 Daily Drilling Report


 
 
Well Name: AFE#:
Operator: API:
County: KB Elevation:

District: GL Elevation:
Activity Date: 3/11/2006 Start Depth: 0
Days Drilling: End Depth: 0
PO: WO rig to MI Footage: 0

Remarks: Making rig repairs, wash sub and derrick.
Viscosity: Rot Hrs:

Mud Weight: ROP Avg:
 
Daily Drlg Cost: $280,500.00 Cum Drlg Cost: $280,500.00
Daily Cmpltn Cost $0.00 Cum Cmpltn Cost: $0.00
Daily Total Cost: $280,500.00 Cum Total Cost: $280,500.00

Activity Date: 3/12/2006 Start Depth: 0


Days Drilling: End Depth: 0
PO: Work on rig repairs Footage: 0

Remarks: Repair rig. Wash sub & derrick.
Viscosity: Rot Hrs:
Mud Weight: ROP Avg:

Daily Drlg Cost: $11,492.00 Cum Drlg Cost: $291,992.00
Daily Cmpltn Cost $0.00 Cum Cmpltn Cost: $0.00
Daily Total Cost: $11,492.00 Cum Total Cost: $291,992.00

Activity Date: 3/13/2006 Start Depth: 0
Days Drilling: End Depth: 0
PO: MI rig Footage: 0

Remarks: 60% moved in.
Viscosity: Rot Hrs:
Mud Weight: ROP Avg:

Daily Drlg Cost: $3,792.00 Cum Drlg Cost: $295,784.00
Daily Cmpltn Cost $0.00 Cum Cmpltn Cost: $0.00
Daily Total Cost: $3,792.00 Cum Total Cost: $295,784.00

Activity Date: 3/14/2006 Start Depth: 0
Days Drilling: End Depth: 0
PO: MIRU Footage: 0

Remarks: Load out all rig equipment. Spot mud tank, pumps, spot sub, install middle braces, rotary table.
Set water tank. Sut conductor, dug mousehole and rathole.
Viscosity: Rot Hrs:
Mud Weight: ROP Avg:
Daily Drlg Cost: $179,792.00 Cum Drlg Cost: $475,576.00
Daily Cmpltn Cost $0.00 Cum Cmpltn Cost: $0.00
Daily Total Cost: $179,792.00 Cum Total Cost: $475,576.00

Page 1 of 9

 Daily Drilling Report

  


Activity Date: 3/15/2006 Start Depth: 0
Days Drilling:
End Depth: 0
PO: RU Footage: 0

Remarks: Spot generator house, change house, diesel tank. Power-up, rig up air & diesel lines. RU water
lines, flow line, choke manifold, gas buster. Continue RU back yard.
Viscosity: Rot Hrs:
Mud Weight: ROP Avg:

Daily Drlg Cost: $43,936.00 Cum Drlg Cost: $519,512.00
Daily Cmpltn Cost $0.00 Cum Cmpltn Cost: $0.00
Daily Total Cost: $43,936.00 Cum Total Cost: $519,512.00
Activity Date: 3/16/2006 Start Depth: 0
Days Drilling: End Depth: 0
PO: RU Footage: 0

Remarks: RU all gound work. Raise derrick @ 1200 P.M. Dress out same, PU kelly, flush out all mud lines.
Clean rig floor and top dog house.
Viscosity: Rot Hrs:
Mud Weight: ROP Avg:

Daily Drlg Cost: $9,404.00 Cum Drlg Cost: $528,916.00
Daily Cmpltn Cost $0.00 Cum Cmpltn Cost: $0.00
Daily Total Cost: $9,404.00 Cum Total Cost: $528,916.00
Activity Date: 3/17/2006 Start Depth: 0
Days Drilling: End Depth: 1,385'
PO: Circ @ 1,385' Footage: 1,385'

Remarks: PU & MU kelly and related subs. Flush thru pumps, mud lines and pressure up surface equipment
@ 1000 psi – O.K. Pre-spud inspection on rig – O.K. Rig on dayrate @ 1030 hours on
03.16.2006. NU 16” riser, flow line and strap and caliper BHA. Strap 9-5/8” casing. Service rig.
SPD WELL @ 1330 HOURS ON 03.16.2006. Drill: 60’-519’ (459’). Survey: 509’ – 0.46°. Drill:
519’-1,005’ (486’). Survey: 995’ – 0.14°. Drill: 1,005’-1,385’ (380’).
Viscosity: 42 Rot Hrs: 16
Mud Weight: 9.2 ROP Avg: 89


Daily Drlg Cost: $30,040.00 Cum Drlg Cost: $558,956.00


Daily Cmpltn Cost $0.00 Cum Cmpltn Cost: $0.00
Daily Total Cost: $30,040.00 Cum Total Cost: $558,956.00

Page 2 of 9

 Daily Drilling Report

  
  
Activity Date: 3/18/2006 Start Depth: 1,385'
Days Drilling:
End Depth: 1,385'
PO: NU BOP Footage: 0

Remarks: Circ BU @ 1,385’ for wiper trip. Survey: 1,365’ – 0.53°. Wiper trip to bit (very little hole problem
@ 60’ to 450’). Attempt to circ, work on plugged flow line. Circ BU @ 1,385’ with #1 pump @ 320
GPM. POOH, bit out rock bit & subs. RD 16” riser. RU casing crew to run 9-5/8” surface casing.
MU Davis-Lynch 9-5/8” float equipment and visual check same – O.K. Run 33 jts, J-55, 36.0#
STC with cross-over jt w/speed head – land same @ 1,365’. RD casing and RU Schlumberger to
circ @ 1,365’. Circ BU w/370 GPM. Switch & test lines @ 3000 psi. Pump 25 bbls spacer,
followed by 310 sacks @ 12.5 w/2.21 yield. Followed by 189 sacks Class “A” cement @ 15.6 ppg
w/1.18 yield for tail. Drop top plug. Displace w/98.5 bbls fresh water. Bump plug w/1000 psi over
ICP. Bled off pressure, float - O.K. RD and release Schlumberger (60 bbls cement back to
surface). LD 9-5/8” landing jt, PU pick-up lines for NU. NU BOP.
Viscosity: 38 Rot Hrs:
Mud Weight: 9.1 ROP Avg:

Daily Drlg Cost: $70,220.00 Cum Drlg Cost: $629,176.00
Daily Cmpltn Cost $0.00 Cum Cmpltn Cost: $0.00
Daily Total Cost: $70,220.00 Cum Total Cost: $629,176.00
Activity Date: 3/19/2006 Start Depth: 1,385'
Days Drilling: End Depth: 1,672'
PO: Drilling @ 1,672' Footage: 287'

Remarks: Finish NU, rotate head. Torqued stack. RU testers to test BOP’s. Test BOP’s, test mud lines to
pumps (test choke, blind & pipe rams @ 250 psi (low); 5000 psi (high). Test hydril @ 250 psi
(low); 3500 psi (high). Test HCR & kill lines @ 250 psi (low); 5000 psi (high) – Good test. RD
tester. Center stack and tie down same w/turnbuckles. RU flow line and gas buster – install and
lock in place, wear bushing. Service rig. LD 3 – 8” DC’s. Strap and caliper stabs, jars, pro drift
pony collar. TIH w/new BHA, tag @ 1,259’. Kelly up and wash down from 1,259’ to 1,280’. Test 9
-5/8” casing @ 1000 psi – O.K. Drill out float equipment and wash down rat hole. Circ. BU for
formation test at 1,365’. Run formation test @ 1,365’, EMW-12.5 ppg. Drill: 1,385’-1,457’ (72’).
Work w/ball up bit. Drill: 1,457’-1,672’ (215’).
Viscosity: 39 Rot Hrs: 4
Mud Weight: 8.8 ROP Avg: 64
Daily Drlg Cost: $111,876.00  Cum Drlg Cost: $741,052.00
Daily Cmpltn Cost $0.00  Cum Cmpltn Cost: $0.00
Daily Total Cost: $111,876.00  Cum Total Cost: $741,052.00
Activity Date: 3/20/2006 Start Depth: 1,672'
Days Drilling: End Depth: 3,776'
PO: Drilling @ 3,776' Footage: 2,104'
Remarks: Drill: 1,672'-2,542' (870'). Service rig. Drill: 2,542'-3,776' (1,234').
Viscosity: 43 Rot Hrs: 24
Mud Weight: 9.2 ROP Avg: 90
Daily Drlg Cost: $35,109.00  Cum Drlg Cost: $776,161.00
Daily Cmpltn Cost $0.00  Cum Cmpltn Cost: $0.00
Daily Total Cost: $35,109.00  Cum Total Cost: $776,161.00

Page 3 of 9

 Daily Drilling Report

  
  
Activity Date: 3/21/2006 Start Depth: 3,776'
Days Drilling:
End Depth: 5,133'
PO: Drilling @ 5,133' Footage: 1,357'



Remarks: Drill: 3,776'-4,393' (617'). Service rig. Drill: 4,393'-5,133' (740').
Viscosity: 43 Rot Hrs: 24
Mud Weight: 9.3 ROP Avg: 58
Daily Drlg Cost: $50,565.00  Cum Drlg Cost: $826,726.00
Daily Cmpltn Cost $0.00  Cum Cmpltn Cost: $0.00
Daily Total Cost: $50,565.00  Cum Total Cost: $826,726.00

Activity Date: 3/22/2006 Start Depth: 5,133'


Days Drilling: End Depth: 6,000'
PO: TIH on wiper trip Footage: 867'

Remarks: Drill: 5,133’-5,564’ (431’). Service rig. Drill: 5,564’-5,906’ (342’). Work of swivel packing. Change
out swab on #2 mud pump & start on motor. Drill: 5,906’-6,000’ (94’). Circ for wiper trip. POOH
from 6,000’ to 2,000’, hole slick.
Viscosity: 40 Rot Hrs: 17
Mud Weight: 9.5 ROP Avg: 51

Daily Drlg Cost: $64,700.00 Cum Drlg Cost: $891,426.00
Daily Cmpltn Cost $0.00 Cum Cmpltn Cost: $0.00
Daily Total Cost: $64,700.00 Cum Total Cost: $891,426.00
Activity Date: 3/23/2006 Start Depth: 6,000'
Days Drilling: End Depth: 6,660'
PO: Drilling @ 6,660' Footage: 660'

Remarks: TIH, move top stab to 3,400’ from bit. Drill: 6,000’-6,060’ (60’). Troubleshoot problem
w/generators #1 & #2. Change fuel filter on both. Drill: 6,060’-6,644’ (584’). Circ 10.1 ppg. Drill:
6,644’-6,660’ (16’). Drill w/orbit valve closed & 4” open going through gas buster. Will slowly raise
MW while drilling to control the gas from sand at 6,700’.
Viscosity: 41 Rot Hrs: 19
Mud Weight: 10.1 ROP Avg: 32

Daily Drlg Cost: $36,692.00 Cum Drlg Cost: $928,118.00
Daily Cmpltn Cost $0.00 Cum Cmpltn Cost: $0.00
Daily Total Cost: $36,692.00 Cum Total Cost: $928,118.00

Page 4 of 9

 Daily Drilling Report

  
  
Activity Date: 3/24/2006 Start Depth: 6,660'
Days Drilling:
End Depth: 7,152'
PO: POOH Footage: 492'

Remarks: Drill: 6,660’-6,675’ (15’). Drill: 6,675’-6,706’ (31’). Drill through sand, well calm. Service rig. Drill:
6,706’-6,825’ (119’). Repair flow line, leaking @ orbit valve. Drill: 6,825’-7,123’ (298’). Circ 30 bbl
sweep. Mud Weight: 10.3 ppg (in); 10.3 ppg (out) – hole static. Slug pipe & POOH up to 5,803’ –
hole slick. Circ 30 bbl sweep. Mud Weight: 10.3 ppg (in); 10.3 ppg (out). Max Gas: 1718 units.
Mud Cut: 10.3 ppg to 10.2 ppg. Slug pipe & POOH SLM out 29’ correction 7,152’ – hole slick &
proper fill ups. Had a depth correction. Had one more joint in the string than in the tally.

Corrected TD is 7,152’, not 7,123’ as reported yesterday evening.
Viscosity: 42 Rot Hrs: 13
Mud Weight: 10.3 ROP Avg: 38

Daily Drlg Cost: $79,791.00 Cum Drlg Cost: $1,007,909.00


Daily Cmpltn Cost $0.00 Cum Cmpltn Cost: $0.00
Daily Total Cost: $79,791.00 Cum Total Cost: $1,007,909.00
Activity Date: 3/25/2006 Start Depth: 7,152'
Days Drilling: End Depth: 7,162'
PO: POOH Footage: 10'

Remarks: RU lubricator. RU Schlumberger wireline equipment. Held safety meeting all hands. Run
Platform Express. WLM 7,158’. RD Schlumberger. MU 8RU lubricator. RU Schlumberger
wireline equipment. Held safety meeting all hands. Run Platform Express. WLM 7,158’. RD
Schlumberger. MU 8¾” PDC bit & TIH filling u p every 30 stands to 7,000’. Circ max gas w/10.3
ppg, 2,845 units, 9.8 ppg. Circ w/orbit closed & 4” on choke open. Increased MW to 10.5 ppg.
Max Gas: 300 units. Ream 7,035’-7,152’ (117’). Light reaming w/washing – not bad. Drill: 7,152’-
7,160’. Circ 30 bbl sweep. Mix & pump 200 bbl 13.5 ppg pill. POOH rack back 10 stands – hole
slick. RU LD machine. POOH, LD DP.
Viscosity: 43 Rot Hrs: 0
Mud Weight: 10.5 ROP Avg: 16

Daily Drlg Cost: $36,377.00 Cum Drlg Cost: $1,044,286.00
Daily Cmpltn Cost $0.00 Cum Cmpltn Cost: $0.00
Daily Total Cost: $36,377.00 Cum Total Cost: $1,044,286.00
Activity Date: 3/26/2006 Start Depth: 7,162'
Days Drilling: End Depth: 7,162'
PO: Install pack-off in wellhead Footage: 0

Remarks: Finish LD DP. Run 10 stands of DP out of derrick. Break kelly and all subs. Finish LD DP & BHA.
Pull wear bushing. Change top set of rams from 4½” to 7” and test to 2000 psi w/rig pump. RU
casing crew. MU 7” shoe & 2 jts 7”, 23.0#, P-110 float collar, 172 jts 7”, 23.0#, P-110,
Shoe @ 7,145’. Lost returns @ 5,908’. RU
Schlumberger cement head and lines & circ 290 bbls, no returns. Switch lines & test to 5000 psi.
Pump 5 bbls water, drop bottom plug & reload head w/top plug. Resume 20 bbls Spacer w/1 sx of
SAPP. Pump 71.5 bbls 200 sx lead cement @ 12.5 ppg. Pump tail 51.2 bbls 330 sx @ 16.4 ppg.
Drop top plug. Displace 266 bbls last 10 bbls pumped @ 2 BPM. Bump plug w/500 over. RD
Schlumberger. Back out landing joint & set pack-off.
Viscosity: 43 Rot Hrs:
Mud Weight: 10.5 ROP Avg:
Daily Drlg Cost: $351,326.00 Cum Drlg Cost: $1,395,612.00
Daily Cmpltn Cost $0.00 Cum Cmpltn Cost: $0.00
Daily Total Cost: $351,326.00 Cum Total Cost: $1,395,612.00

Page 5 of 9

 Daily Drilling Report

  
  
Activity Date: 3/27/2006 Start Depth: 7,162'
Days Drilling:
End Depth: 7,162'
PO: PU 3½” DP Footage: 0

Remarks: Test pack-off to 5000 psi. Change out kelly. RU & test BOP’s & all related equipment to same:
250 psi (low); 7500 psi (high). Test hydril: 250 psi (low); 3500 psi (high). Change out rotating
head & install orbit valve & flow line. Slip & cut 100’ of drill line. RU LD machine. MU 6-1/8” bit & PU
BHA. PU 3½” DP, drift each joint.
Viscosity: 68 Rot Hrs:
Mud Weight: 13.3 ROP Avg:

Daily Drlg Cost: $36,289.00 Cum Drlg Cost: $1,431,901.00
Daily Cmpltn Cost $0.00 Cum Cmpltn Cost: $0.00
Daily Total Cost: $36,289.00 Cum Total Cost: $1,431,901.00
Activity Date: 3/28/2006 Start Depth: 7,162'
Days Drilling: End Depth: 7,910'
PO: Drilling @ 7,910' Footage: 748'

Remarks: PU 3½” DP, drift each joint, tag up @ 6,990’. Displace water w/13.3 ppg OBM. Test casing to
2000 psi – test O.K. Drill float equipment & shoe & wash to bottom – 7,170’, plus 10’ to 7,180’.
Circ. Test shoe to EMW 16.5 ppg w/13.2 ppg OBM in hole. Drill: 7,180’-7,593’ (413’) with
a 6-1/8" bit. Cir. Survey: 7,553’ – 0.47°. Drill: 7,593’-7,910’ (317’).
Viscosity: 48 Rot Hrs: 16
Mud Weight: 13.2 ROP Avg: 47

Daily Drlg Cost: $42,037.00 Cum Drlg Cost: $1,473,938.00


Daily Cmpltn Cost $0.00 Cum Cmpltn Cost: $0.00
Daily Total Cost: $42,037.00 Cum Total Cost: $1,473,938.00
Activity Date: 3/29/2006 Start Depth: 7,910'
Days Drilling: End Depth: 8,891'
PO: Drilling @ 8,891' Footage: 981'

Remarks: Drill: 7,910’-8,303’ (393’). Service rig. Survey: 8,282’ – 5.50°. Drill: 8,303’-8,450’ (147’). Survey:
8,409’ – 4.16°. Drill: 8,450’-8,637’ (187’). Survey: 8,600’ – 4.27°. Drill: 8,637’-8,891’ (254’).
Viscosity: 48 Rot Hrs: 20
Mud Weight: 13.5 ROP Avg: 48

Daily Drlg Cost: $43,811.00 Cum Drlg Cost: $1,517,749.00
Daily Cmpltn Cost $0.00 Cum Cmpltn Cost: $0.00
Daily Total Cost: $43,811.00 Cum Total Cost: $1,517,749.00
Activity Date: 3/30/2006 Start Depth: 8,891'
Days Drilling: End Depth: 9,170'
PO: Drilling @ 9,170' Footage: 279'

Remarks: Control Drill: 8,891’-9,018’ (127’). Survey: 9,009’ – 6.79°. Control Drill: 9,018’-9,170’ (152’).
 
Viscosity: 49 Rot Hrs: 23
Mud Weight: 13.7 ROP Avg: 12


Daily Drlg Cost: $78,804.00 Cum Drlg Cost: $1,596,553.00


Daily Cmpltn Cost $0.00 Cum Cmpltn Cost: $0.00
Daily Total Cost: $78,804.00 Cum Total Cost: $1,596,553.00

Page 6 of 9

 Daily Drilling Report

  
  
Activity Date: 3/31/2006 Start Depth: 9,170'
Days Drilling:
End Depth: 9,325'
PO: Drilling @ 9,325' Footage: 155'

Remarks: Drill: 9,170’-9,227’ (57’). Pump slug. Survey: 9,199’ – 5.56°. POOH to PU Schlumberger power
“V” tool. PU power “V” tool and test – test O.K. TIH, fill up every 30 stands to 7,171’. Circ BU.
TIH to 9,126’. Ream: 9,126’-9,227’. Drill: 9,227’-9,325’ (98’).
Viscosity: 54 Rot Hrs: 2
Mud Weight: 13.9 ROP Avg: 17

Daily Drlg Cost: $60,148.00 Cum Drlg Cost: $1,656,701.00
Daily Cmpltn Cost $0.00 Cum Cmpltn Cost: $0.00
Daily Total Cost: $60,148.00 Cum Total Cost: $1,656,701.00
Activity Date: 4/1/2006 Start Depth: 9,325'
Days Drilling: End Depth: 9,945'
PO: Drilling @ 9,945' Footage: 620'

Remarks: Drill: 9,325’-9,549’ (224’). Service rig. Drill: 9,549’-9,649’ (100’). Circ BU to POOH to shoe. Only
one generator, other blew up. POOH to shoe 7,100’, hole slick. Change out #2 generator & motor
on skid. Run generator w/load – O.K. TIH to 9,572’, hole slick. Wash from 9,587’ to 9,649’ for

safety. Drill: 9,649’-9,945’ (296’). 0.8° angle on MWD.
Viscosity: 52 Rot Hrs: 12
Mud Weight: 14 ROP Avg: 50

Daily Drlg Cost: $54,918.00 Cum Drlg Cost: $1,711,619.00


Daily Cmpltn Cost $0.00 Cum Cmpltn Cost: $0.00
Daily Total Cost: $54,918.00 Cum Total Cost: $1,711,619.00
Activity Date: 4/2/2006 Start Depth: 9,945'
Days Drilling: End Depth: 11,200'
PO: Drilling @ 11,200' Footage: 1,255'



Remarks: Drill: 9,945’-10,183’ (238’). Service rig. Drill: 10,183’-11,200’ (1,017’).
Viscosity: 55 Rot Hrs: 12
Mud Weight: 14.2 ROP Avg: 53
Daily Drlg Cost: $62,442.00  Cum Drlg Cost: $1,774,061.00
Daily Cmpltn Cost $0.00  Cum Cmpltn Cost: $0.00
Daily Total Cost: $62,442.00  Cum Total Cost: $1,774,061.00

Activity Date: 4/3/2006 Start Depth: 11,200'


Days Drilling: End Depth: 11,500'
PO: Logging Footage: 300'

Remarks: Drill: 11,200’-11,327’ (127’). Service rig. Drill: 11,327’-11,500’ (173’). Circ BU. POOH from
11,500’ to 9,500’ & back to bottom, hole slick in & out. Circ BU. Max Gas: 2,644 units. Mud Cut:
14.2 ppg to 13.8 ppg. Building MW up to 14.4 ppg. POOH to log well. RU lubricator. RU
Schlumberger. Run Triple Combo.
Viscosity: 56 Rot Hrs: 5
Mud Weight: 14.4 ROP Avg: 60

Daily Drlg Cost: $62,161.00 Cum Drlg Cost: $1,836,222.00


Daily Cmpltn Cost $0.00 Cum Cmpltn Cost: $0.00
Daily Total Cost: $62,161.00 Cum Total Cost: $1,836,222.00

Page 7 of 9

 Daily Drilling Report

  
  
Activity Date: 4/4/2006 Start Depth: 11,500'
Days Drilling:
End Depth: 11,500'
PO: Circ @ shoe Footage: 0

Remarks: Log w/Triple Combo (11,541’-7,148’). RU Run #2. Log w/Sonic (11,489’-7,152’). RU Run #3.
Log w/OBMI (DipMeter) (11,541’-8,619’) – stuck same @ 8,619’. Work tool free. POOH
w/wireline. RD Schlumberger. MU 6?” bit & TIH slick. Slick to 7” casing shoe. Circ BU @ shoe.
Viscosity: 56 Rot Hrs: 5
Mud Weight: 14.4 ROP Avg: 60

Daily Drlg Cost: $229,139.00 Cum Drlg Cost: $2,065,361.00
Daily Cmpltn Cost $0.00 Cum Cmpltn Cost: $0.00
Daily Total Cost: $229,139.00 Cum Total Cost: $2,065,361.00
Activity Date: 4/5/2006 Start Depth: 11,500'
Days Drilling: End Depth: 11,500'
PO: Logging Footage: 0

Remarks: TIH to 11,396’. Wash & ream to 11,500’ for safety. Circ, surface to surface. Max Gas: 2924 units.
Mud Cut: 14.4 ppg to 13.2 ppg. TOH. Tight from 8,800’ to 8,100’. Pull out to shoe 7,145’. Slip &
cut 120’ of drill line & re-set com & check – O.K. TIH to 11,500’, hole slick. Circ, surface to
surface. Max Gas: 2272 units. Mud Cut: 14.4 ppg to 13.8 ppg. Pump slug & POOH to log, hole
slick. Install lubricator. RU Schlumberger wireline equipment & hold JSA. Run #1: OBMI
(DipMeter) – 11,100’ to 7,380’ @ 06:00. Will log up to shoe @ 7,145’.
Viscosity: 60 Rot Hrs: 5
Mud Weight: 14.6 ROP Avg: 60

Daily Drlg Cost: $34,470.00 Cum Drlg Cost: $2,099,831.00
Daily Cmpltn Cost $0.00 Cum Cmpltn Cost: $0.00
Daily Total Cost: $34,470.00 Cum Total Cost: $2,099,831.00
Activity Date: 4/6/2006 Start Depth: 11,500'
Days Drilling: End Depth: 11,500'
PO: Circ @11,500' Footage: 0

Remarks: Run #1 OBMI (DipMeter) - 11,100' to 7,145'. POOH & RD OBMI (DipMeter). WO rotary core
tools. RU rotary core tools & TIH to 11,456'. Recover 2 samples. POOH, tools fail, change out
tools. TIH w/Run #3. Rotary core tool to 11,352' & recover 36 samples from 11,352' to 7,850'.
Total of 36 plus 2 on first run (38 total). MU 6-1/8" bit & TIH, slick to shoe, start completion time @

2300 hours on 04.05.2006. Circ BU. TIH to 11,500', hole slick. Circ BU.
Viscosity: 63 Rot Hrs:
Mud Weight: 14.8 ROP Avg:

Daily Drlg Cost: $121,928.00 Cum Drlg Cost: $2,221,759.00


Daily Cmpltn Cost $0.00 Cum Cmpltn Cost: $0.00
Daily Total Cost: $121,928.00 Cum Total Cost: $2,221,759.00

Page 8 of 9

 Daily Drilling Report

  
  
Activity Date: 4/7/2006 Start Depth: 11,500'
Days Drilling:
End Depth: 11,500'
PO: Ran 4½” casing @ 5,930’ Footage: 0

Remarks: Circ BU @ 65 SPM (175 GPM). POH 10 stds. RU LD machine. LD 3½” DP. RIH w/10 stds from
derrick. Soft break kelly. Finish LD 3½” DP & 4¾” DC’s. Change out pipe rams. Install 4½”
rams. Rig casing tools, crews. Held safety meeting. MU 4½” float equipment & test same. Run
w/4½” 13.5# casing to 5,930’ (145 jts).
Viscosity: 63 Rot Hrs:
Mud Weight: 14.8 ROP Avg:

Daily Drlg Cost: $0.00 Cum Drlg Cost: $2,221,759.00
Daily Cmpltn Cost $58,638.00 Cum Cmpltn Cost: $58,638.00
Daily Total Cost: $58,638.00 Cum Total Cost: $2,280,397.00
Activity Date: 4/8/2006 Start Depth: 11,500'
Days Drilling: End Depth: 11,500'
PO: Setting dry hole tree Footage: 0

Remarks: Continue running 4½” casing to 9,306’. 229 joints total. RU circ swedge & break circ. Circ from
9,300’. Max Gas: 437 units. RU cement head. Test lines to 6000 psi. Pump 30 bbls MudPush II
Spacer @ 15.4 ppg & 375 sxs (94 bbls) Class “H” 16.4 ppg cement w/additives. Displaced w/137
bbls 3% KCL @ 3 BPM, plug down w/4600 psi. Floats held O.K. Good returns throughout cement
job. WO cement. RD tarps on pits, clean pits, clean stack/sub-base. RU stack lifters, PU stack &
set slips (70K lbs). Made rough cut, set out BOP’s, RD stack lifters. Make final cut/bevel, clean &
prep dry hole tree for installation & test.
Viscosity: 62 Rot Hrs:
Mud Weight: 14.8 ROP Avg:

Daily Drlg Cost: $0.00 Cum Drlg Cost: $2,221,759.00


Daily Cmpltn Cost $332,858.00 Cum Cmpltn Cost: $391,496.00
Daily Total Cost: $332,858.00 Cum Total Cost: $2,613,255.00
Activity Date: 4/9/2006 Start Depth: 11,500'
Days Drilling: End Depth: 11,500'
PO: RDMO Footage: 0

Remarks: Finish installing dry hole tree, set slips w/8500 psi, well secure.



RELEASED RIG @ 1130 HOURS ON 04.09.2006!!!

Viscosity: Rot Hrs:
Mud Weight: ROP Avg:
Daily Drlg Cost: $18,486.00 Cum Drlg Cost: $2,240,245.00
Daily Cmpltn Cost $0.00 Cum Cmpltn Cost: $391,496.00
Daily Total Cost: $18,486.00 Cum Total Cost: $2,631,741.00

Page 9 of 9