Академический Документы
Профессиональный Документы
Культура Документы
ITEM 1
TOP SOIL EXCAVATION
Excavate topsoil to remove vegetable soil-m2
Material - nil
Labour
Plant
Cost of hiring machine = N75,000.00
Output per day = 800m2
Cost / m2 = N75,000 = N93.75
800
25% profit & OH = 23.48
= 117.23
ITEM 2
DISPOSAL OF TOPSOIL
Deposit excavated material away from site – m2
Material-Nil
Labour
Plant
Output of labour = 10m3/day
Cost of labour = N2000.00/day
Cost/m3 = N2000
10
Cost / m3 = N200.00
74
Add 10% for small tools = 20
= #220
Add 25% profit & OH = N55
Total Cost / m3 N275
ITEM 3
TRENCH EXCAVATION
Excavate foundation trench starting from stripped level maximum depth (1.0m3)
Material - Nil
Labour
Plant
Output of labour = 4m3/ man day
Multiplying factors = 0.6m3 x 4m2 = 2.4m3
2.4m3
Cost of labour = N2000
Cost /m3 = N2000 = N833.33
2.4
625
Allow 5% for small tools = N41.66
N874.99
ITEM 4
PIT EXCAVATION
Excavate for pit 0.90 x 0.90m starting from stripped level depth i.e. 1.0m3
Material - Nil
Labour
Plant
Output of labour = 3.5m3/M.D
Cost of labour = N2,000 / M.D
74
Cost / m3 = N2000
3.5 = N571.43
Add 5% for small tools = N28.57
= N600.00
Allow 25% profit & overhead = N150.00
Cost / m3 = N700.00
ITEM 5
BACK FILLING
Filling in trench with previous excavated materials – m3
Material - Nil
Labour
Plant
Output of labour = 15m3//day
Cost of labour = N2,000 / day
Cost / m3 = N2000
20 = N100.00
Add 10% for small tools = N10.00
= N110.00
Allow 25% profit & overhead = N27.50
Cost / m3 = N137.50
ITEM 6
DISPOSAL OF SURPLUS
Fill in trench with previous excavated materials – m3
Material - Nil
Labour
Plant
Output of labour = 15m3//day
Cost of labour = N2,000 / day
Cost / m3 = N2000
15 = N133.33
74
Add 10% for small tools = N6.67
= N140.00
Allow 25% profit & overhead = N35
Cost / m3 = N140.00
ITEM 7
LEVELLING AND COMPACTING
Material - Nil
Labour
Output of labour = 20m3//day
Cost of labour = N2,000 / day
Cost / m3 = N2000
20 = N100
Add 10% for small tools = N10
= N110
Allow 25% profit & overhead = N27.50
Cost / m3 = N138.50
= N138.00
ITEM 8
ANTI-TERMITE SOLUTION
Apply diedtrex 20 anti-termite solution to bottom and sides of excavation.
(a) Material - Nil
Cost of anti-termite / 4litres = N3,500.00
Allow 20% waste = N700.00
= N4,200,00
Capacity / 4 litres = 50m2
Cost / m2 = 4200
50 = N84.00
(b) Labour
Output of labour / day = 150m2
Cost of labour = N2000 / day
Cost / m = N13.33
74
(c ) Small Tools
Add 5% for cost of labour = N0.67
= N14.00
TO COLLECTION
Material = N84.00
Labour = N13.33
Small tools = N0.67
N98.00
Add 25% profit & overhead = N24.50
Cost / m3 = N122.50
ITEM 9
EARTH WORK SUPPORT
Earth work support to sides of trench maximum depth not exceeding 1.0m distance between
opposing face not-exceeding 2.0m QTY 40mm length.
Material
Polling board = 300mm x 50mm at 1m c/c
Walling board = 1500mm x 500mm
Struts = 100mm x 100mm at 2m c/c
Polling board at 1 meter c/c
Nrs = 2 (No + 1) = 82
Volume content = 82 (1.0 x 0.3 x 0.05) = 1.23
Walling board
2(40) = 80
Volume content = (80 x 0.15 x 0.05) = 0.60m
Struts at 2m c/c
74
40 + 1 = 21
2
Volume content = 21 x 1.8 x 0.10 x 0.10 = 0.38
Total cubic content
1.23
0.60
0.38
2.21
Considering the length (40m) and depth 1.0m
Area = 40m2
2 sides = 2 x 40 = 80
Cost per m2
Cost of timber (soft wood) N1,100
2.21 will cover N2,431
Labour
4 carpenters using 6 hrs each N15,000
24 men /hr at N625.00
Fixing and removal of timber
Total of 3 men = hour (unskilled labour is involved )
1 m 400 x 3 = N1200
Cost of labour N15,000 + N1200 = N16,200
Summary
Material cost
Timber N759.69
Nails N113.95
Add 15% N16200
74
Labour N17,073.64
ITEM 10
DAMP PROOF COURSE
Horizontal damp proof course 300mm wide of single layer
(a) Material
Cost of damp proof course (20m) N1,500.00/roll
Cost / m 1200 = N50.00
30
Add 10% waste N5.00
N55.00
Allow 10% cost of material N5.50
(b) Labour
Allow 10% cost of labour N0.55
CARRIED TO COLLECTION
(a) Material - N55.00
(b) Labour - N5.50
(c) Small tools - N0.55
N61.05
Add 25% profit /overhead = N15.26
Cost/m = N76.31
74
ITEM 11
LATERITE FILLING
Laterite filling to make up level under floors deposited and compacted in 150mm thick layer to
receive hardcore – m3.
Material
Tipper load (3.8m3 ) of laterite = N20,000.00
Add 10% waste N2,000.00
N22,000.00
Cost /m3 of laterite = 22000
3. 81 = N5,774.28
Labour
Output of labour / M.D = 8m3
Cost of labour / M.D. = N2,000.00
Cost / m3 of laterite = 2,000
8 = N250.00
Small tools
Add 5% cost of labour = N12.50
TO COLLECTION
Materials = N5,774.28
Labour = N250.00
Small tool = N12.50
N6,036.78
Add 25% profit and overhead = N509.20
N6,545.98
ITEM 12
HARDCORE
Hardcore filling to make up level under floor well arranged compacted and consolidated to
receive concrete – m3
Material
1 tipper load (3. 81m3) of hardcore = N37,500.00
74
Add 10% waste = N3,750.00
41,250. 00
Cost /m3 of hardcore = N41,250. 00
3. 81 = N10,826.77
Labour
Output of labour / MD = 8m3 /MD
Cost of labour = 2,000
8
Cost/m3 = N250.00
Small tools
Add 5% of labour = N12.50
TO COLLECTION
Material = N10,826.77
Labour = N250.00
Small tools = N12.50
N11,861.59
Add 25% profit and OH = N2,772.3
Cost / m3 N13,861.59
CONCRETE WORKS
ITEM 13
REINFORCED CONCRETE
Reinforced in – situ concrete (1:2:4-19mm aggregate)
(a) Material
(ai) Cement
COST/m3 of cement= N86,000.00 (as before calculated)
(aii) Sand
2m3 of sand (3.81) @ N20,000 / tipper = N5,249.34
Cost /m3 = 20000 = N10,498.68
3.81
74
2m3 (2 x 5249.34) = N1,049.87
Add 10% waste N11,548.55
(aiii) Gravel
3.81m3 of gravel N32,750 / tipper
Cost /m3 = 32,750 = N8,595.80
3.81
4m3 (4 x 8,595.80) = N34,383.20
Add 10% waste = N3.438.32
Total cost N37,821.52
Add (ai) + (aii) + (aiii) = N86,130 + N11,548.55 + N37,821.52
= N135,500.07
Add 25% shrinkage = N33,875.02
N169,375.09
Cost/m3 = N169,375.09 = N24,196.44
7
(b) Labour
(bi) Unloading and stacking of cement required = 29 bags
7
= 4.143
74
Output = 20m3/ plant / day
Cost of plant /m3 = 20,500 = N1025.25/m3
20
TO COLLECTION
(a) Materials - N24,196.44
(b) Labour -
(i) Unloading - N103.58
(ii) Placing - N680.00
(c) Small tools - N34.00
(d) Plant - N1025.20
N26,039.27
Add 25% profit/and OH = N6,509.82
N32,549.09
ITEM 14
FORMWORK
Formwork to the sides of column in foundation
(a) Material 3.6m (25 x 300mm) rough sawn hardwood - N1,500.00
Add 10% nail - N150.00
Add 20% for bracing - N30.00
N1,680.00
Add 10% waste N168.00
N1,848
3.6m plank = 1,848
3.6 = N513.33
(b) Labour
Add 25% cost of material = N128.33
(c) Small tools
Add 5% cost of labour = N6.42
74
N 743.08
Add 25% profit /overhead = N185.07
N928.15
ITEM 15
Prepare and apply 3 coast of emulsion paint on general surface of door
Material
(2.40x6.60x3) = 47.52
Cost per bucket of 20liters = 4500
M2 = 4500/47.52 = N94.70
Cost of material = N94.70
Labour
0.24hr/m2 = N62.50
Add 5% tools = N3.13
= N65.63
SUMMARY
Material = N94.70
Labour = N65.63
= N160.33
Add 25% P/OH = N40.08
= N200.41
ITEM 16
CONCRETE SCREED
12mm thick cement and laid on concrete base (1:4) qty-180m2
Material
Cost of 1m2 of cement (as before calculated) N86,130.00
Sand (soft sand)
Cost of 4m2 of sand (as before calculated) N20,997.38
N107,127.38
Add 25% shrinkage N26,781.85
N133,909.23
Cost /m3 133,909.23 = N26,781.85
5
Volume of mortar required (0.04 x 180) = N7.20
Add 25% waste = N1.80
N9.00
Cost of mortar (9 x 26,781.85) = N241,036.65
74
(b) Labour
Unloading and stacking of cement
Number of cement required 30 = 6 bags
3
1.5 bags
7.5 bags
(7.5 x 9) = 67.5 bags
74
(Aii) Sand
3m3 of sand (3. 81) at N20,000 / tipper
Cost// m3 = 20,000
3.81 = N5249.34
3 x 3,937. 00 N15, 748.02
Add 10% waste N1574.80
N17,22.82
(Aiii) Gravel
6m3 of gravel (3.81) at N32, 750.00 / tipper
Cost /m3 32,750
3.81 = N8,595.80
6 x 8,595.80 N51,574.80
Add 10% waste N5,157.48
N56,732.28
Add Ai + Aii + Aiii = 86,130 + 17,322.82 + 56,732.28
= N160,185.10
Add 25% shrinkage N40,046.28
N200,231.38
1m3 = N200,231.38/10 N20,023.14
(Bi) Labour
Unloading and stacking of cement
1 x 10 x 30 bags = 3 bags
10 1
Add 25% waste and shrinkage = 0.75 + 4 = 4 bags
Output of labour for unloading = 100bas / M.D
Cost of labour = N2000 / M.D
Total cost = N2,000 x 4 = N80.00
100
(Bii) Placing of concrete
2 tradesmen + 6 labour
Cost of labour = (2 x 2,500) + (6 x 2000)
= 5,000 + 12,000
74
= N17,000.00
Output of gang = 2.5m3 / M.D
Cost of labour N17,000
25 = N680.00
(C) Small tools
Add 5% of labour = N34.00
Plant
Cost of hiring + cost of tradesmen
15,000 + 5,500
= N20,500.00
Output 20m3/day
20,500
20
= N1025
TO COLLECTION
Material = N20,023.14
Labour
Unloading = N80.00
Placing = N680.00
Small tools = N34.00
Plant = N1025.00
= N21,842.14
Add 25% of profit and overhead = N5,460.54
N27,302.68
= N22,013.00
ITEM 18
REINFORCEMENT
12mm diameter high yield reinforcement bar in column BS4449 laid straight and bent in kg
(a) Material
(ai) 12mm /one
Per tone = N189,000.00
74
Add 10% waste = N1,890.00
Add 1.5% rolling margin = N383.5
N210,735.00
(aii) 30kg binding wire per one = N7,600
Capacity = 1.8 tons of 12mm Ө bar cost of wire per ton = 7600
1.8
= N4,222.22
Add 10% waste = N422.22
N4,644.44
(b) Labour
Output of labour = 1 tonne / G.D
Cost of labour = 1 tradesman + 2 labour
= 2500 + 4000
= N6,500.00
(c) Small tools
Add 5% cost of labour = N325.00
TO COLLECTION
Materials = N210,735.00
Binding man = N4,644.44
Labour = N6,500.00
Small tools = N325.00
N222,204.44
Add 25% profit and overhead = N5,555.11
N277,755.55
Cost/kg = 277,755.55
1000
= N277.756
74
ITEM 19
16mm diameter high yield reinforcement bar in columns B.S 4449 laid bend –kg
(a) Material
(ai) 16mm /tonne = N300,000.00
Add 10% waste = N15,000.00
Add 1.5% rolling margin = N4,750
N319,750.00
(aii) 30kg binding wire per one= N7,600
Capacity = 1.8 ton of 16mm Ө bar
Cost of wire per tonne = 7600 = N3,518.52
2.16
Add 10% waste = N351.85
N3,870.37
(b) Labour
Output of labour = 1 tonne / G.D
Cost of labour = N5,000
(c) Small tools = N5,000
Add 5% cost of labour = N250.00
TO COLLECTION
Materials
Bar - N319,750.00
Binding wire N 3870.37
Labour - N5,000.00
Small tools - N250.00
N328,870.37
Add 25% profit/overhead = N82,217.59
N411,087.96
Cost /kg = N411,087.59 = N411.09
100
74
ITEM 20
10mm diameter high yield reinforcement bar in columns B.S 4449 laid bend –kg
(a) Material
(ai) 10mm /tonne = N194,000.00
Add 10% waste = N9,700.00
Add 1.5% rolling margin = N3,055.50
N206,755.50
(aii) 30kg binding wire per one= N7,600
Capacity = 2.16 ton of 10mm Ө bar
Cost per tonne = 7600 = N3,518.52
2.16
Add 10% waste = N351.85
N3,870.37
(b) Labour
Output of labour = 1 tonne / G.D
Cost of labour = N5,000
(c) Small tools = N5,000
Add 5% cost of labour = N250.00
TO COLLECTION
Materials
Bar - N206,755.50
Binding wire N 3870.37
Labour - N5,000.00
Small tools - N250.00
N215,875.87
Add 25% profit/overhead = N53,968.96
N269,844.77
Cost /kg = N269,844.77 = N269.85
100
74
ITEM 21
Fabric Mesh
Cost / roll N7,600.00
Area per roll 4.5 x 2.00 = 9.00.00
Roll per 100cm2 = 100 = 11.1 + 1 = 12 roll
9
Cost = 12 x 7,600 = N91,200.00
Labour
25% cost of material N22,800.00
Small tools
Add 5% cost of labour N1,140.00
TO COLLECTION
Materials - N91,200.00
Labour - N22,800.00
Small tools - N1,140.00
N115,140.00
Add 25% profit/overhead = N28,785
N143,925.00
Cost /kg = N143,925.00 = N1,439.25
10
ITEM 22
BLOCKWALL
225mm thick of block wall in foundation jointed with sand and cement mortar (1:4)– m 2
(Assume 100m2)
(a) Material
(ai) Block wall
Number of block /m2 (with mortar) = 9 Nos
Per 100m2 = 9 x 100 = N900.00
Cost of 225mm block /one = N200.00
Total cost = (900 x 180) = N180,000.00
Add 10% waste = N18,000.00
74
N198,200.00
Cost of block /m2 = 198,200 = N1982
100
(aii) Mortar (1:4)
1m3 of cement (30 bags) @ N2,700.00
30 x 2,700 - N78,300.00
Add 10% waste - N7,830.00
N86,130.00
74
29 bags
Cost of labour for unloading = 4,000 x 30 = N1160
1000
(bii) Stacking of blocks
Output of labour = 150 nos/M.D
No of M.D required = 10 x 100 = 6.67 = 7 M.D
150
Cost of labour for stacking = 8 x 2,000 = N16,000.00
(biii) Laying of blocks
Output for laying = 9m2/G.D
No of gang / day required = 100 = 11.11 = 11 G.D
9
Cost of gang / day = 1 tradesman + 2 labour
= 2500 + 4000= 6,500
= 11 x 5,500 = N60,500.00
(biv) Mixing of mortar (using manual)
Output = 0.5m3/ M.D
Total number of M.D required 5.50 = 11M.D
0.50
Total cost of mixing = 11 x 1500 = 16,500
(c) Small tools
Add 5% of cost of laying block + mixing
71,500 + 16,500 = 88,000.00
= N4,400
TO COLLECTION
(a) Materials
(ai) Block - N198,200.00
(aii) Mortar - N13,173.65
(b) Labour
(bi) Cement stacking - N1160.00
(bii) Stacking of block - N16000
(biii) Laying of block - N71,500
74
(biv) Mixing - N16,500
(c) Small tools - N4,400
N320,933.65
Add 25% profit / overhead = N80.233.41
N401,167.06
Cost /m2 = 401,167.06 = N4,011.67
100
ITEM 23
RENDERING
12mm thick cement and sand (1:4) mixed rendered on wall – Qty = 100m2
(a) Material
(b) Labour
(c) Plant
(a) Material (1:4) mortar
(ai) Cement
1m3 of cement contain 30 bags of cement
@ N2,700.00 x 30 = N81,000.00
Allow 10% waste = N8,100.00
N89,100.00
(aii) 4m3 of sand at N3275 / m3 = N13,000
Allow 10% waste = N1310
N14,410
TO COLLECTION
Cement - N89,100.00
Sand - N14,410.00
N103,510.00
Allow 25% shrinkage and void = N25,877.50
N129,387.50
Cost /m2 = N129,387.000 = N25,877.50
5
74
Considering the volume of mortar required
12 x 100 = 1.2m3
100
Allow 25% of waste irregularly of surface compact utilization = 0.6m2
Cost of mortar = 1.8 x N25,877.50 = N46,579.50
(b) Labour
(bi) Unloading and stacking of cement mix (1:4) contain 30 bags of cement
Allow 50% shrinkage and void 15 bags
45 bags
No of bag/m3 = 45 = 9 bags
5
For 1.8m3 = 1.8 x 9 = 16.2 bag = 17 bags
Output of labour = 100 bags / M.D
No of bag required = 17 = 0.17 bags x N2700.00
100
Amount of labour = N459.00
(bii) Output = 2.5m2/G.D (2 tradesmen + 3 labour)
Cost / day (2 x 2500 + 3 x 2000)
5,000 + 6,000 = N11,000.00
No of G/O required = 100 = 4 GD
25
Cost of rendering = 11,000 x 4 = N44,000.00
Allow 5% for small tools = N2,200
TO COLLECTION
(a) Materials - N46,579.50
(b) Labour
(bi) - N459.00
(bii) - N44,000.00
(biii) - N2,200.00
N93.238.50
Allow 25% profit / overhead = N23.309.63
74
N116,593.13
Cost /m2 = 116,593.13
100 = N1,165.93
ITEM 24
ROOF COVERING
Long span aluminium roofing sheet nailed with nails and washer on sawn hardwood purlin laps
150mm sides and bloom end.
(a) Material
Effective covering area = [(2.40 – 0.10) x (1.20 – 0.15)
= 2.30 x 1.05 x 1.05 = 2.45m2
Cost of roofing sheet/ bundle (10 sheets) = N14,500
Cost / one N22,500 = N22,500.00
10
Cost /m2 = 22,500.00
2.45 = N918.37
Allow 5% waste = N45.92
N964.29
(b) Labour
Output of labour = 50m2/G.D
Cost of labour (2 tradesmen + 1 labour) = (2 x 3000) + 2,000
= N8,500.00/G.D
Cost /m2 8,000 = N160.00
50
(c) Small tools
Allow 5% cost of labour = N8.00
TO COLLECTION
Material = N964.29
Labour = N160.00
Small tools = N8.00
74
N1132.29
Add 25% profit /overhead = N283.07
N1415.36
ITEM 25
Ridge and hip cap
Long span aluminium roofing sheet in ridge cap and hip cap
(a) Material
Cost of material / bundle (20 sheets) = N11,000.00
Cost / sheet 11,000 = N550.00
20
Add 5% for nail and washer = N27.50
N577.50
(b) Labour
A gang of 1 labour and 2 carpenters = N2000 +2(2,500)
= N7,000.00
Per hour = 7,000.00 = N875.00
8
Output 2.5/hr = 0.25 gang / hr @ N875.00 = N218.75
10m2
(c) Small tools
Allow 5% cost of labour = N10.94
N229.69
Add 25% P/H = N57.92
N287.11
ITEM 26
ROOF CONSTRUCTION
WALL PLATE
100mm x 75mm thick treated hardwood wall plate
(a) Material
Cost of 3.6m (100mm x 75mm) / length = N950
Cost/m 950.00
3.60 = N263.89
Add 5% for nail = N13.20
74
Add 10% waste = N26.38
N303.47
Labour
Allow 5% cost of materials N15.17
Small tools
Allow 5% cost of labour = N0.76
N319.48
Add 25% profit/overhead N79.85
Cost /m N399.25
= N399
ITEM 27
RAFTER STRUCT TIE BEAM AND KING POST
150 x 50mm hardwood treated, rafter, strut, tie beam and king post
(a) Material
Cost of 3.6m (150mm x 50mm) / length = N1100.00
Add 10% waste = N110.00
N1210.00
Cost/m 1210.00
3.60 = N336.11
Add 20% Of nai = N67.22
N403.33
(b) Labour
Allow 10% cost of material = N40.33
(c) Small tools
Allow 5% cost of labour = N2.02
N445.68
Add 25% profit and overhead N111.42
N557.10
ITEM 28
PURLIN
50mm x 75mm thick treated hardwood purlin
(a) Material
Cost of 3.6m (50mm x 75mm) / length = N400.00
Add 10% waste = N40.00
N440.00
Cost/m 440.00
3.60 = N122.22
74
Allow 20% nail N24.44
(b) Labour
Allow 20% cost of material = N29.33
(c) Small tools
Allow 5% cost of labour = N1.47
N177.46
Add 25% profit and overhead N44.37
N221.83
ITEM 29
FASCIAL BOARD
300mm x 25mm hard treated hardwood fascial board and badge board
(a) Material
Cost of 3.6m (25mm x 300mm) / length = N1,200.00
Add 10% waste = N120.00
N1,320.00
Cost/m 1320.00
3.6 = N366.67
Allow 20% nail N 73.33
N 440.00
Labour
Allow 10% cost of material = N40.00
(c) Small tools
Allow 5% cost of labour = N2.00
N482.00
Add 25% profit and overhead N120.00
N602.00
ITEM 30
FIXING STRAP
100mm wide metal strap fixed to wall plate
(a) Material
Cost of bundle (20) = N1250.00
Cost of 2.1m long / one 1250
20 = N62.50
Cost/m 62.50
2.1 = N29.76
74
Allow 10% waste = N2.98
= N32.74
(b) Labour
Allow 25% cost of material = N8.19
TO COLLECTION
(a) Material N32.74
(b) Labour N8.19
(c) Small tools N2.05
N42.98
Add 25% profit /overhead = N10.74
N53.72
Cost /m = N53.72
ITEM 31
FLASHING
Aluminium sheet flashing nailed to fascial and badge board
(a) Material
Cost of material (1.8m) = N1006.26
Cost/m 1006.26
1.8 = N559.03
74
(c) Small tools
Allow 25% cost of labour = N1.61
N676.63
Allow 25% profit and overhead = N169.16
N845.79
ITEM 32
NOGGINS
50mm x 50mm thick sawn hardwood noggin
(a) Material
3.6 length cost = N450.00
Add 10% nail and solignum = N45.00
Add 10% waste = N45.00
N540.00
Cost / m 540
3.6 = N150.00
(b) Labour
Allow 25% of material / for labour = N37.50
Allow 5% of labour for small tools = N1.88
N189.38
Add profit and overhead 25% = N47.35
N236.73
ITEM 33
DOOR FRAME
50x100 rebated hardwood door frame plugged as screwed to block wall in
(a) Material
Cost of material = N500.00
Assured 20 nos
20x500 = N10000
74
(c) Small tools
Allow 5% cost of labour = N325.00
TO COLLECTION
(a) Material N15500
(b) Labour N6500
(c) Small tools N325
N22325.00
Add 25% profit /overhead = N5581.25
N27906.25
Cost per no N27906.25 N1395.31
20
ITEM 34
50mm thick polished wrought hardwood approved panel door fixed to the door frame nominal
size 824x2062mm high nr
(a) Material (4 Nos)
824x2062mm high panel door per one
Cost of material = N10000.00
Assured 4 nos
4x10000 = N40000
TO COLLECTION
74
(a) Material N42000
(b) Labour N9000
(c) Small tools N450
N51450.00
Add 25% profit /overhead = N12862.50
N64312.50
Cost per no N64312.50 = N16078.13
4
ITEM 35
44mm thick polished wrought hardwood approved wood frame door fixed to the door frame
nominal size 674x2062mm high nr
(a) Material (4 Nos)
674x2062mm high panel door per one
Cost of material = N9000.00
Assured 4 nos
4x9000 = N36000
TO COLLECTION
(a) Material N37800.00
(b) Labour N9000.00
(c) Small tools N450.00
N47250.00
74
Add 25% profit /overhead = N11812.50
N59062.50
Cost per no N59062.50 = N14765.63
4
ITEM 36
Supply and fix double swing metal door size 1200x2100mm to door opening
(a) Material
1200x2100mm high panel door per one
Cost of material = N35000.00
Allow 5% for re plastering = N1750.00
N36750.00
(b) Labour
Allow 5% cost of material N1750.00
(c) Small tools
Allow 2% cost of labour = N35.00
TO COLLECTION
(a) Material N36750.00
(b) Labour N1750.00
(c) Small tools N35.00
N38535.00
Add 25% profit /overhead = N9633.75
N48168.75
ITEM 37
HINGES
100mm pair steel butt Hinges fixed to door shutter and frame with matching screw set of lever
handle fixed to rebate in door
(a) Material
74
Allow 15% cost of material N65.63
(c) Small tools
Allow 5% cost of labour = N3.28
N506.41
Add 25% P/OH N126.60
N633.00
ITEM 38
PAINTING
Prepare and apply 3 coast of gloss paint to the surface of door leaf and frames
(a) Material
(ai) A gallon of paint for 1 coat will cover = 45m2/coat
Therefore for new work 45/3 = 15m2 / 3 coat
Cost of paint /4litres = N5,000
2
Cost/m (5000/15) = N333.33
allow 20% waste = N66.67
= N400.00
(ii) Poly filler
Allow 10% for poly filler = N40.00
(b) Labour
Output of labour =20m2/GD
Cost of labour /GD = N5,000.00
Cost /m2 = N5,000/20 = N250.00
Small tools
Allow 10% cost of labour =N25.00
TO COLLECTION
(a) Material
(i)Paint N400.00
(ii) poly filler N40.00
(b) Labour N250.00
(c) Small tools N25.00
N715.00
74
ITEM 39
Prepare and apply 3 coat of textcote paint on rendered wall 100m2
(a) Material
(ai) A gallon of paint
1 coat will cover 45m2 per coat
Therefore for new work 45/3 = 15m2 / 3 coat
(aii) brushes =60m2 /coat
(aiii) Poly filler =0.005kg/ m2
A3 Poly filler
0.005 kg/m2 for 100m2 0.5kg
Allow 20% waste 0.1kg
0.6kg = 1 kg
Cost N300/kg
1 kg = N300.00
(b) Labour
60m2 for new work = 20m2/G.D
74
No G.D required = 100 = 5 G.D
20
Cost of labour 5 x 5000.00 = N25,000.00
Allow 5% for cost of small tools = N1,250.00
N26,250.00
TO COLLECTION
Material N34.650.00
N1.250.00
N300.00
N26,250.00
N64,450.00
Add 25% profit /overhead = N15.612.50
N80.062.50
Cost /m2 = N80.062.50
100
= N801.86
ITEM 40
TILES
300 x 300 x 10mm thick fully glazed non vitrified non-slip ceramic floor tiles on screeded bed.
(a) Material
Cost / tiles (11 Nos) = N2,400.00
Cost / one 2400 = N218.18
11
Add 10% waste = N21.81
N239.99
(aii) White cement
Cost of white cement /25kg = N2,500.00
Add 5% waste = N125.00
N2,625.00
Capacity of white cement = 100m2 of tiles
Cost 1m2 1 x 2625 = N24.00
100
(b) Labour
74
Output of labour = 16m2/G.D for unloading, laying & pouring
Cost of labour required = 3000 = N187.50
16
(c) Small tools
Add 5% cost of labour = N9.38
TO COLLECTION
(a) Material = N239.99
(ai) White cement = N24.00
(b) Labour = N187.50
(c) Small tools = N9.38
N460.87
Add 25% profit /overhead = N115.22
N576.09
ITEM 41
TILLING
400 x 400 x 10mm thick approved glazed ceramic floor tiles laid in approved pattern on florr bed
all grids pointed with white cement (m/s) – m2
(a) Material
Cost /m2 (0.99) or less = N1200.00
Add 10% waste = N120.00
N1,320.00
(aii) White cement
Cost of white cement / 25kg = N2,500.00
Add 5% waste = N125.00
= N2,625.00
Capacity of white cement 100m2 of tiles
Cost /m2 = 1 x 2625 = N26.25
100
(b) Labour
Output of labour 16m2/(G.D) for unloading and pouring
Cost of labour required = 3,000 = N187.50
16
74
(c) Small tools
Add 5% cost of labour = N9.38
TO COLLECTION
(a) Material = N1,320.00
(ai) White cement = N26.25
(b) Labour = N187.50
(c) Small tools = N9.38
N1,543.13
Add 25% profit /overhead = N385.78
N1,928.91
ITEM 42
DOOR 1
Supply and fix double leave swing steal door. Size ( 2100 x 1800).
= N 175,000.00
DOOR 2
Supply and fix double leave swing steal door. Size ( 2100 x 1200)
(a) Material
Cost of 2100mm x 1200mm steal door/ one = N 30,000.00
Add 25% profit and OH = N 7,500
Cost = N 37,500.00
DOOR 3
74
Supply and fix single leave swing steal door. Size ( 900mm x 2100mm)
(a) Material
= N 22,500
DOOR 4
Supply and fix single leave swing steal door. Size ( 2100 x 750)
Cost = N 20,000.00
ITEM 52
ALUMINIUM WINDOW
WINDOW 1
Size 600 x 600 high supplied and fix aluminum sliding window with all
accessories
Cost N6,000
N6,300
Labour
Plant
74
Allow 5% of cost of labour N15.75
To collect
Material - N6,300
Labour - N315.75
Plant - N15,75
N6,631.50
Cost = N8,289.38
WINDOW 2
Size 1200 x 1,200 high supplied and fix aluminum sliding with all accessories
Cost N15,000
= N15,750.00
Labour
74
Plant
To collect
Material - N15750
Labour - N787.50
Plant - N39.38
N16,576.88
N18,234.57
WINDOW 3
Size 1500 x 1,200 high supplied and fix aluminum sliding window with all
accessories
Cost = N18,000
N18,900.00
Labour
Plant
TO COLLECT
74
Material - N18,900
Labour - N945.00
Plant - N47.25
N19,892.25
N24.865.31
ITEM 54
12MM thick cement and sand to wall (1:4) m2
Material
Volume of mortar = 0.104) m2
Cement per m3
1m3 of cement and asand
1m3 of cement = 28.8bag @2700 = N77,760.00
Unload and stack 3mm hr/@125
3x125x28.8/60 =N108.08
N77,868.00
Allow 5% waste = N3,893.04
= N81,761.04
4m3 of sand @20000 per load
3.81m3 = 20000
1m3 = 20000/3.81 = N6,289.31
Allow 10% stockpile waste = N628.93
Allow 20% for bulking of sand = N1257.86
= N8176.10
Allow 15% shrinkage = N1226.42
= N9402.52
SUMMARY
Cost of cement = N81761.04
Cost of sand = N9402.52
= N91163.56
74
Cost per 0.014 = N18233.11x0.014 = N255.26
Add 25% P/OH N63.82
= N319.08
ITEM 56
CEILING COVER
6mm thick asbestos 1200x1200 fixed to 50x50 sawn hardwood noggin with 36mmx13mm cover
fillet with nail
(a) Material
1200x1200 ceiling board per one
Cost of material = N1100
(b) Labour
Output of gang (1 trade man +1 labour) =30m3/GD
Cost = N2500 + 2000 = N4500.00
Cost of labour per m3 =4500/30 = N150.00
TO COLLECTION
(a) Material N1331.00
(b) Labour N150.00
(c) Small tools N7.50
N1488.50
Add 25% profit /overhead = N372.13
N1,860.63
74
ITEM 57
COVER FILLET
38mmx13mm cover fillet
(a) Material
38x13mmthick wrought hardwood = N120
(b) Labour
Add 25% of material N10.08
TO COLLECTION
(a) Material N40.33
(b) Labour N10.08
(c) Small tools N0.50
N50.91
Add 25% profit /overhead = N12.73
N63.64
74
MARKET SURVEY OF BUILDING MATERIALS 2017. BY OLOFINTOYE ADEREMI
A CEMENT
3. Per bag
White Cement 5kg 3,800
6.
Blue cement Per bag 25kg 2,500
B BLOCK
74
C Laterite 3.81m3 20,000
3.81m3 25,000
Unwashed gravel
D REINFORCEMENT
6mm diameter Tonne 300,000
E TIMBER
74
50 x 150mm hardwood 3.6m/length 1100 Falegan, Ado-
3.6m/length Ekiti
50 x 100mm hardwood 500
3.6m/length
50 x 50mm hardwood 300
F ROOF COVERING
Per bundle
Longspan aluminium (coloured) 0.33 24,500 Bank road,
G NAILS
74
2” size ordinary Per bag 9,500
3/4
” size Per bag 10,000
3/4
” size concrete nail Per packet 360
H WINDOWS ALUMINIUM
74
J DOOR
K DOORS
1800 x 2100mm double leaf metal door Per one 140,000 Idemo, Ado-
Ekiti
1200 x 2100 single leaf metal door Per one 35,000
74
L IRON MONGARY
M PAINTS
Per 4 litre
N TILES
P 6mm x 6mm white colour ceramic wall Per carton 1,600 Bank Road,
tiles Ado-Ekiti
Per carton 1,600
20mmx30mm white colour ceramic wall
Per carton 3,000
tiles
Per carton 1,200
600x600mm vitrified floor tiles
Per carton 2,300
300x30mm vitrified floor tiles
Per carton 1,200
74
40x40mm vitrified floor tiles
Per carton 2,400
30x30mm vitrified floor tiles
Per carton 2,800
40x40mm vitrified floor tiles
74
Shower curtain and rail Per one 2,500
Per one
Bath white 17,500
74
FITTINGS PIPES
3/4
” All in
Per length 280
Bank road
Ado - Ekiti
1” Per length 400
3/4
mm Per length 400
25mm
Per length 250
13mm P.V.C pipe of 6m length Per length 350
3/4
mm P.V.C pipe of 6m length Per length 400
25mm P.V.C pipe of 6m length Per length 500
50mm P.V.C pipe of 6m length Per length 700
75mm P.V.C pipe of 6m length Per length 900
100mm P.V.C pipe of 6m length Per length 1100
125mm P.V.C pipe of 6m length Per length 1100
150mm P.V.C pipe of 6m length Per length 50
74
Per length
4” Bend P.V.C fittings 150
Per length
2” P.V.C Tee 50
Per length
3” P.V.C Tee 100
Per length
4” P.V.C Tee 200
Per length
1” P.V.C Tee 50
Per length
1” P.V.C Elbow 50
Per length
12/3” x 3/4” P.V.C Elbow
Per length 50
12/3” x 3/4” P.V.C Elbow
Per length 50
3/4
1” x ” P.V.C Elbow
Per length 40
2/3 3/4
1 ”x ” P.V.C Elbow
Per length 50
11/2” iron shower
Per length 450
Union joint 15mm
Per length 100
Union joint 25mm
Per length 150
Union joint 50mm
Per length 250
1/2
Union joint 1 mm
Per length 300
Tee joint 13mm
Per length 40
Tee joint 25mm
Per length 50
Tee joint 50mm
Per length 100
Tee joint 25mm
Per length 50
Per length 40
74
Socket joint 13mm
Socket joint Per length 80
Distribution switch D4
74
Per one 1,000
Change over 2pole 30mm Per one
200
Lamp holder angle Per one
200
Lamp holder straight Per one
500
Smart socket 15amps Per one
400
Smart socket 13amps
Per one
1,500
Golden socket 15amps
Per one 100
Ceiling rose
Per one -
Fluorescent holder celotex 1,500
Per one
Suspended core 3,500
Per one
20mm Diameter conduit pipe 4,500
Per one
25mm Diameter conduit pipe 700
Per one
40 watts bulb 700
Per one
60 watts bulb 100
Per one
100 watts bulb 150
Per one
200 watts bulb 500
Per one
Fluorescent 4feet length (Maspion) 350
Per one
Fluorescent 4feet length (Maspion) 400
Per one
Fluorescent 4feet length (philip) 500
Per one
Decoration light half moon 2,000
Per one
Decoration security light Per one 50,000
74
Decoration security chandler light
74