03/01/2020 Establishing a Successful PMO

Breaking the PMO sound barrier

CONFERENCE PAPER ǀ PMO, Information Technology ǀ 23 October 2012


Clenchy, Carey | Mo, Johnny

How to cite this article:


Clenchy, C. & Mo, J. (2012). Breaking the PMO sound barrier. Paper presented at PMI® Global Congress 2012—North America,
Vancouver, British Columbia, Canada. Newtown Square, PA: Project Management Institute.

1. The Introduction
Project Management Offices (PMO's) over the past few years have had a difficult time gaining momentum in organizations and
demonstrating real value and business benefits. Typically PMO's are perceived by many in the organization as administrative
overhead and bureaucracy on projects that do not provide any tangible benefits in successfully executing projects “on time” and “on
budget”.

We started our PMO journey in February 2010 with decentralized functional groups, inconsistent project standards and practices,
and over half of our Information Technology projects in the portfolio (total of 53) requiring significant changes related to scope,
schedule and/or budget throughout the lifecycle of the project. Do any of these PMO challenges listed below resonate with you and
currently describe your PMO or projects?

1) Are internal and external stakeholders unclear on the role and responsibilities of your PMO? Is your PMO immature and advisory
only in nature?

2) Are your projects struggling and constantly costing more than what was initially estimated / budgeted for, or taking significantly
longer time than what was planned? Was this a shock to project stakeholders and/or the project sponsor?

3) Are project stakeholders and project sponsors not involved in risk management discussions and timely course correction?

4) Are resources inadequate and not available for projects or resource demand defined too late in your projects?

5) Are you struggling influencing project success and governing projects? Do you not have a consolidated view of your projects in
your portfolio and do you not manage your project portfolio collaboratively with stakeholders?

6) Are you dealing with inconsistent templates and reports? Even on the usage of the word “yellow”?

7) Did you find that your Project Managers were burning out or frustrated because there was no clear path of escalation?

8) Did the lessons learned from previous years just disappear or not get applied or even looked at?

9) Did staff turnover significantly impact your PMO and its sustainability and did all the important knowledge leave with them??

If you answered “yes” to any of these frustrating but common PMO challenges then you definitely need to continue following our
journey to gain valuable insights into strategies and tactics that you can leverage to help you overcome these PMO “disablers”.

The PMO journey is not for the faint of heart and requires tremendous commitment, patience and continuous change management
and effective communication in order to overcome and conquer the many battles you will face in your organization and the
challenging voyage ahead of you. Through our trials and tribulations we will share our journey and experiences with you and the
many secrets we have found to help you break the “PMO Sound Barrier” in warp speed! Our team was successfully able to break the
“PMO Sound Barrier” through various strategies and tactics deployed in Information Technology and across the organization. The
team achieved a 92% success rate across the IT project portfolio (in excess of 50 projects) adhering to defined scope, schedule and
budget commitments at a defined stage (Implementation Readiness) early on in the project lifecycle.

Are you ready to board our “wessel” as a famous sci-fi character would say – for your PMO Journey aboard the “Star Ship” PMO
enterprise? Hold on tight, we are about to engage............

2. Proof the problem exists


According to PM Solutions and Gantthead's current 2012 research report of 554 firms regarding ‘The State of PMO's in 2012’, “The
upward trend is unmistakable, both in the sheer numbers of PMOs and in their rising organizational clout”. In the 2000 research
report “only 48% of companies had a PMO”, and in their 2012 research finding the percentage has almost doubled over the last
decade to 87%. Percentage of organizations with PMO's over the last decade based on research findings in the report were:

https://www.pmi.org/learning/library/establishing-successful-pmo-applying-new-framework-6062 1/5
03/01/2020 Establishing a Successful PMO
2012 – 87%

2010 – 84%

2006 – 77%

2000 – 48%

The 2012 PM Solutions and Gantthead research report strongly supports the PMO challenges that our organization and team
identified at the beginning of our journey in early 2010. The top challenges in this research report identified by executives as their
two biggest aligned strongly to the initial challenges our team faced – “i) defining the role of the PMO and ii) demonstrating the value
of the PMO”. Other significant challenges identified in this research report that correlate directly with the additional challenges we
faced include iii) effective resource management on projects and across the project portfolio and iv) ensuring standards, practices
and procedures are consistently applied across the portfolio. These top challenges in this most recent research report were identical
to the key PMO challenges our team was faced with as we began our PMO transformation voyage in February 2010.

Other supporting PMO research was conducted by Planview in their 2010 PMO 2.0 Trending Survey, (downloadable at
www.planview.com/PMOtrends2010 ), which had more than 550 organization survey respondents, and provides similar
reinforcement to the PMO challenges our organization and team faced.

As can be seen in the Planview findings a large percentage of PMO survey participants were fairly immature in the implementation of
consistent PMO processes, standards and procedures across their portfolios.

Another significant problem that is increasing in nature with PMO's and that we initially faced was that there was no well defined
strategy or longer term plan for the PMO function. This is again supported in the Planview research.

Additionally managing the portfolio of projects in the PMO and review of projects and their approval are critical activities that often
become overlooked by PMO's if they are not governed across the project portfolio. This is again supported by the 2010 Planview
findings.

Also noteworthy to point out in these research findings are the planned 2011 activities PMO's will be undertaking which again aligned
strongly to some of our teams key objectives and activities that were identified as part of our 3 year plan. We will discuss these
planned activities in relation to our team's plan further on in this PMO journey.

3. Additional Problems
Ongoing studies of PMO's and project success specifically on Information Technology projects as well as research from other
leading consultants and analyst firms, confirm that Information Technology PMO's are a very difficult and extremely volatile
environment to manage projects and the overall portfolio. In addition another significant challenge is getting the many roles and
different levels of the organization appropriately involved in their projects in a consistent and cohesive manner so that they can
effectively support and sponsor their projects throughout the Project Lifecycle.

Our team has some additional insight on what strategies to employ to more effectively engage key stakeholders throughout a
project's lifecycle.

In the early stages our team was also faced with secondary problems related to inconsistent and incomplete project and PMO
standards and practices, ineffective project resource planning, poor forecasting processes, and limited performance measurement
reporting was in place. As PM

Solutions indicates in their 2012 Research report and which aligns closely to the additional problem areas we focused on “PMOs
plan to spend the coming year focusing on improving all their existing processes, with a particular focus on improving resource
planning and forecasting (59%), and implementing or improving performance measurement reporting, analytics, and dashboard tools
(54%)”.

Also gaining more attention and emphasis on projects is the topic of business change management. Organizations are starting to
discover that taking a more complete approach to business change management significantly improves project success and assists
in creating increased business value on projects. We will discuss the importance of effective business change management on our
projects and our strategy we employed to ensure we supported change management requirements throughout the Project Lifecycle.

We will begin our journey and case study by discussing the “As Is” state of our Information Technology PMO and processes and
conduct a 360 degree view of the way the PMO was initially perceived from both IT and business stakeholders, and how leadership
was influenced by senior executives within the company to take significant corrective action. We will then provide context into the
impetus for accelerating PMO governance and the maturity model, from a ‘walk’ before you ‘run’ approach to flat out sprinting with
strong executive support and drive.

4. The First Steps


A current state assessment was conducted in the IT PMO in February 2010 to help determine improvements required to better
support projects throughout their Project Lifecycle, to better define the PMO, and to improve project delivery success. The current
state assessment of the Information Technology PMO and projects was developed through consultation with various project key
stakeholders at all levels of the organization, to clearly identify gaps in an effort to build a suitable strategy and operational tactics to
help Information Technology (IT) improve project delivery across the organization.

The following PMO assessment findings were developed and communicated to relevant project stakeholders:

The Project Management Office had no clearly established role, was at an immature stage (level 1) and was perceived by
stakeholders to add little or no value, and adding bureaucracy to the project management process

https://www.pmi.org/learning/library/establishing-successful-pmo-applying-new-framework-6062 2/5
03/01/2020 Establishing a Successful PMO
Project management execution excellence on Information Technology projects was not predictable/repeatable
The PMO was advisory in nature and had little influence over projects as they progressed through the Project Lifecycle, and
provided little or no governance or oversight on projects in the portfolio
No clearly defined PMO methodology and Project Lifecycle existed within Information Technology for monitoring and controlling
projects in the portfolio
There was inconsistent use of standardized PMO processes, procedures and templates & document version control on the PMO
SharePoint site
PMO processes, procedures and templates required significant administration, were not clearly communicated, required several
stakeholder handoffs and were in dire need of streamlining
Limited project resource demand management, capacity planning and allocation was conducted across IT and resourcing tended
to be more reactive than forward looking
Business change management was not clearly understood and integrated into the IT project management process and project
key stakeholders had not been appropriately engaged or communicated with about their projects as they progressed through the
five stage Project Lifecycle process
The IT Project Portfolio Management (PPM) process was manual, adhoc, inefficient (excel based) and very labour intensive and
automation across the PMO project lifecycle was lacking
No standardized process was in place for PMO dashboard, reporting and analytics
A standardized issue & risk management process was not been defined, and was not consistently reported on by Project
Managers
Project managers struggle with following PMO processes, procedures, templates as no consistent standards were
communicated and little or no oversight or governance was in place.

The PM Solutions and Gantthead 2012 Research Report on “The State of the PMO in 2012” identify the top PMO functions that are
required by organizations and they include:

1. PMO methodology, standards, implementation and management


2. Project policies, procedures, templates, implementation and management
3. Project / program monitoring and controlling
4. PM coaching and mentoring
5. Project / program initiation
6. Governance process implementation and management
7. Multi-project coordination
8. Project / program closing
9. Project performance monitoring and controlling
10. Dashboard / scorecard implementation and management

Top immediate priorities of PMO's as defined by their 2012 report include:

Improving resource planning and financial forecasting process

Implement / enhance core project / program management processes

Implement / enhance reporting analytics, dashboard tools

Implement / enhance governance processes

Implement / enhance performance measurement process

As can be seen in our PMO assessment findings the areas we identified as requiring improvement align very closely to these top
PMO functions required and top immediate priorities identified above that PMO's should be focusing on.

The strategic method and tactics we used on our team to address these gaps will be discussed at our presentation at the PMI Global
Congress in October 2012 in Vancouver.. One additional gap stakeholders also identified was the need for more effective portfolio
management as the project portfolio grew to over 50+ projects. The need for including Portfolio Management as a key function within
a PMO is strongly supported by PM Solutions and Gantthead's 2012 Research report as they conclude “as PMO's increase their
capability, more of them engage in portfolio management, by successfully managing high-value tasks, they are entrusted with
increased responsibility”.

5. Our Conclusion
At the PMI Global Congress in October 2012, 2we will discuss the “To Be” future state and design of the Governing PMO, roles and
responsibilities, and the steps that were put in place “just in time” to help both business and IT stakeholders understand and apply
the new framework and practices.

https://www.pmi.org/learning/library/establishing-successful-pmo-applying-new-framework-6062 3/5
03/01/2020 Establishing a Successful PMO
We will focus on a real life case study of a large Utility organization and the strategies and tactics that the team deployed to
overcome their PMO challenges in Information Technology. You will learn how the team was able to transform an immature
struggling advisory IT PMO into a strong governing, continuously improving maturing “best in class” PMO. Through strategic and
operational tactics the team was successfully able to “break the PMO sound barrier” within a relatively short 18th month period of
time. We will share with you our continuously evolving

Project Lifecycle, our continuous improvement framework and governance methodology we employed to effectively manage projects
and our overall portfolio. The overall plan enabled us to move from a 50% conformance rate of baseline scope, schedule and cost
defined at the Implementation Readiness stage gate to an impressive 92% conformance performance achievement.

We will finally discuss the lessons we learned from accelerating PMO governance and maturity, and what we would do differently
now looking in the rear view mirror, the challenges we faced and the results that were achieved (the good, the bad and the ugly!).
Business change management, shared project governance, key stakeholder impacts and establishing and monitoring metrics will
also be discussed. The case study will show how you are able to accelerated PMO maturity and governance in an 18 month period
compared to what we heard from colleagues taking as long as 3 years or more.

REFERENCES
PM SOULTIONS (2012). The State of the PMO 2012, A PM solutions research report. Glen Mills, PA: PM Solutions.

Doerscher, Terry, (2010). 2010 PMO, Trending Survey Report. Austin, TX: Planview Inc.

This material has been reproduced with the permission of the copyright owner. Unauthorized reproduction of this material is strictly
prohibited. For permission to reproduce this material, please contact PMI or any listed author.
© 2012, Carey Clenchy, MBA & Johnny Mo, PMP
Originally published as a part of 2012 PMI Global Congress Proceedings – Vancouver, British Columbia

Related Content

CASE STUDY ǀ PMO ǀ October 2019

Developing a Project Management Office in the Department of


Energy, Energy Information Administration
This case example, a supplement to the report, PMIAA: Strengthening the Government Delivery
Foundation, highlights project and program management capability building within The U.S.
Energy…

ARTICLE ǀ PMO ǀ 1 September 2019

PM Network
Undivided Attention
By Mustafa, Abid ǀ There's always been a great divide between development and operations, particularly when it comes
to the role of the enterprise project management office (EPMO). EPMOs traditionally have limited…

ARTICLE ǀ PMO, Strategy, Program Management, Governance ǀ 1 August 2019

Project Management Journal


Modeling Organizational Project Management
By Müller, Ralf | Drouin, Nathalie | Sankaran, Shankar ǀ The contemporary discourse on organizational project
management (OPM) complements project, program, and portfolio management with emerging elements, such as
governance, projectification, the project…

ARTICLE ǀ Change Management, PMO ǀ 1 July 2019

PM Network
Unclogging the Pipeline
By Oyvetsky, Marat ǀ At sales-driven companies, a project can't start until a contract is signed. But in my experience at IT
organizations, the sales pipeline can easily clog. Sales executives end up playing tug of war…

ARTICLE ǀ Scheduling, PMO, Program Management ǀ 1 June 2019

Project Management Journal


A Study of the Critical Chain Project Management Method Applied to a
Multiproject System
https://www.pmi.org/learning/library/establishing-successful-pmo-applying-new-framework-6062 4/5
03/01/2020 Establishing a Successful PMO
By Cooper Ordoñez, Robert Eduardo | Vanhoucke, Mario | Coelho, Jose | Anholon, Rosley | Novaski, Olívio ǀ In 1997,
Eliyahu Goldratt proposed a method called critical chain project management (CCPM) to minimize the inefficiencies
identified in traditional project management. The project management…

© 2020 Project Management Institute, Inc. USA