Академический Документы
Профессиональный Документы
Культура Документы
Indian Power Sector have been growing at a rapid pace with an overall installed capacity of 360.46 GW as
of 31 July 2019. As of 2018 with a power generation of 1,561.1 BU in 2018, India was the third largest
producer and the third largest consumer of electricity in the world, behind China (7,111.8 BU) and the
United States (4,460.8 BU). Out of the total power generated in India coal-based power generation
contributes to more than 60% of the share. Over the years there has been a significant improvement in
energy efficiency of coal based thermal power plants but still there is a scope for improvement in this area.
There has been a paradigm shift in the use of new and efficient technologies over time with a shift towards
super critical and ultra-super critical technology being adopted for the upcoming plants.
In alignment with the goals and objectives of the government and the industry stakeholders, CII – Godrej
GBC has been promoting the concept of “Making Indian Power Plants World Class”. As a part of the
initiative, CII – Godrej GBC offers a platform for information exchange, sharing of best practices through
visits to best operating plants both in National & International level and documenting the findings in manuals
for widespread dissemination among the stakeholders. CII – Godrej GBC also organizes the “Power Plant
Summit” every year as flagship event for enabling continuous interactions among the Industry, technology
providers and the government.
This manual is the 4th in the series of Best practice manual for Indian Thermal Power Plants which intends
to document few best practices, case studies and newer technological developments in Indian Power
sector. CII - Godrej GBC has collected these best practices with support of various industries, suppliers and
with their experiences in energy audits, energy awards and energy efficiency conferences, etc.
The objective of this manual is to act as a catalyst in accelerating adoption of best practices and latest
technologies across the sector. I take this opportunity to thank the power sector fraternity for their
contribution in preparing this manual and look forward to their continued support.
D. Sarkar
Chairman, Power Plant Summit 2019 &
Executive Director (OS), NTPC limited
Source: ibef.org
The electricity production is increasing at CAGR of 5.50% from the past 10 years. The peak power deficit
stood at 0.8 percent and the overall energy deficit remained 0.6 percent in 2018-19. The per capita
electricity consumption (kWh) stood at 1149 kWh in 2018.
Figure 5 Unburnt in Bottom Ash for FY 2017-18 compared to benchmark in similar-sized units
Figure 11 APH Primary Air side old and new sector plate
Results
There was an overall reduction of around 8 degrees in flue gas exit temperature with the implementation
of this project. The total annual coal savings from this project was 208.4 Lakhs per annum.
Benefit: For emissions reduction, LJUNGSTRÖM supports the retrofit of SCR installation to remove NOx by
upgrading the air preheater to a configuration suitable for operation after an SCR. These solutions have
been developed and refined by LJUNGSTRÖM since the 1970s when SCRs were first installed in Japan and
have since developed into the standard practices in use around the world today. LJUNGSTRÖM’s products
and solutions have an unmatched long and proven track record.
For Flue Gas Desulfurization (FGD) to remove SOx, LJUNGSTRÖM pioneered gas-gas heaters in the 1980s
and today the LJUNGSTRÖM Gas-Gas heater (GGH) platform is one of the most demonstrated designs on
wet limestone and seawater FGD globally.
One of the biggest challenges in the thermal power sector is variance. The coal power plants vary in
age, technology, size, location, ownership, load factor (utilisation factor), etc. AdvX™ technology has the
flexibility to be tailor-made for the entire range of thermal power plants in operation. It can also be deployed
in power plants having space constraints which prevent deployment of alternative technologies. Coupled
with its low-cost, simplicity and high effectiveness, this unquestionably makes AdvX™ the technology of the
future. Considering that any cost incurred in power generation is finally passed on to the consumer in one
form or the other, the huge cost benefit AdvX™ offers is a game changer in the arena of thermal power
plant operations.
Figure 21 Unit 3 CT Performance Test Results before Hot water manifold modification
Figure 23 Hot water manifold existing and proposed layout; %Area of CT Cell Air entry blocked by
Hot water manifold
The implementation has the following steps.
• Preparation of work scope.
• Overlaying of works of different departments namely Mechanical, Civil, etc.
• Preparation of Bill of Quantity (BOQ) and its Quality Assurance Procedure (QAP).
• Identification of vendors & material procurement.
• Execution of works.
• Commissioning.
The work is executed in two phases namely Pass - B duct and Pass - A duct during Unit # 3 outage
opportunity in the month of December 2015 and July 2016 respectively. The work execution has two major
departments involved Civil and Mechanical. The better planning, coordination & execution has resulted to
complete the work within stipulated time even in heavy monsoon period.
The civil and mechanical work carried out are described below:
Civil Work: Excavation, breaking of concrete blocks, raft, bed preparation, backfilling casting of trust blocks,
etc.
Mechanical Work: Supply of GRP fittings, removal of existing Hot Water Header, erection, joining, testing
and commissioning of new GRP Hot water header.
Following activities were carried out for completion of the job:
• Opening of dummy flange at end of header.
• Removal of access platform near riser valves.
• Cutting of GRP pipe at a predefined location and shifting to stipulated location.
• Providing access for cutting of riser pipe by mean of scaffolding.
• Cutting of riser pipes.
The plant team decided to install a variable frequency drive in the CEP to reduce the pressure drop across
the deaerator control valve. After installation of the variable frequency drive the deaerator control valve
was kept in a fully open condition and deaerator level control common was directly given to CEP VFD.
Benefits
The plant team was able to save 600
KW after installation of VFD in CEP.
Savings and Payback
Savings – Rs. 120 Lakhs
Investment – Rs. 150 Lakhs
Payback – 17 months
Benefits:
PA Fan
ff Duties: ff Characteristics:
– Damping down of Friction – High Power Density
– Wear Protection – Mid range up to locally high Operating Temperature
– Cooling
– Power Transmission
– Corrosion Protection
– Transport of Particles
The following are requirements on Hydraulics Oils:
Figure 56 Layers of an integrated data processing platform for applying artificial intelligence
In this architecture, two distinct systems - Operations technology (OT) and Information technology (IT) -
merge seamlessly. Historically, these two systems were developed in independent silos with different
problem sets in mind. With the convergence of these technologies, industrial customers can benefit
significantly by collaborating with IT service providers.
Figure 59 Sharp spikes and overall increase in vibration level from Day 30 onwards
Artificial Intelligence applied to data to determine root causes
At this point, the turbine expert was involved, and the operations team too was looking for root causes
for the problem. A detailed analysis did not lead to a definitive reason for the vibrations and some of the
process trials from operations too did not reduce the vibration levels.
In parallel, ExactSpace’s Artificial Intelligence-based analytics were being applied on over 600 process
parameters from across the system. This exercise considered all data collected in the two months leading
into the event and prior 9-month history as a reference set. Over 80,000 event alerts were generated
and correlated with each other continuously. From this large list, based on change detection, over a
million correlations and automated causal indications, the system narrowed down a few options and were
indicated to the operations team as potential causes. From these, the following stood out:
i) Control oil header pressure – Level changes were detected on two distinct occasions and seemed
correlated to the first event of vibration increase. It had changed from an initial value of 8.4 kg/cm2
to 9.0kg/cm2. On inspection of plant operations logs, it was observed that an oil filter was changed
when the first rise was observed. And the lube oil temperature was dropped when the pressure drop
was observed.
ii) Main oil temperature – In the same time period, the system detected changes in temperature of the
main oil. From a temperature range of 48 to 50 Deg, it dropped to 46 to 47 Deg and stayed at that
level.
Figure 61 Vibration and Control Oil Pressure positively correlated with a 1-minute lag
Similarly, when longer-term analysis of data for main oil temperature was carried out a pattern emerged.
However, the type of relationship was very different. Temperature and vibration displayed an inverse
relationship where the change in temperature caused the change in vibration. When temperature
decreased, the other increased. Also, the correlation between temperature and vibration lasted for a much
longer duration. The cross-correlation revealed that they displayed a relationship for nearly 40-60 hours.
This suggested that a change in one would affect the other even after a lag of 2 or more days.
Figure 63 Drop-in Vibrations after change in Oil pressure and temperature as recommended by the system
Benefits
The data analysis here was able to help the plant team avoid breakdown which could have been resulted
from increased vibrations.
Savings
The plant team was able to save a potential breakdown cost in the range of Rs. 1.0 – 1.5 crores (based on
estimated downtime) and maintenance costs related to it.
Overall energy savings achieved due to the above replacement was 556.6 kWh which resulted in annual
savings of Rs. 1.64 crores.
Solution:
A cost effective solution was required to address the above mentioned problems of maintaining high PLF
by preventing scaling for sustaining in open energy market, achieving zero plant effluent discharge for
environmental protection and conservation of water for reducing its share in cost of energy generation and
addressing the problem of scarcity.
General practice adopted are Softening plan for scaling problem, RO plant for water conservation, Multiple
effect evaporator for achieving ZLD but each of these measures require high capital and O&M expenses
and large area of land should be available which is difficult to allocate in a plant as it may affect future
expansion projects.
The Scaleban technology addresses all these problems in a very innovative and cost effective manner
and have benefitted a no. of power plants in India. The maximum pressure drop at condenser inlet with
Scaleban installed is around 0.12 bar. The plant decided to install this technology at both the 490 MW
power plant as both the power plants are sharing a common water bay.
Benefit:
The data collected and trend observed was highly encouraging. Although online ball cleaning system
was not in operation since last 6 months, still there was practically no variation in vacuum loss pattern as
compared with base line data.
As to check the physical condition of condenser during the trial period, condenser can’t be opened. But
as the plant has also installed Scaleban in PHE Unit 5, it was checked and compared with the PHE of Unit
6 which was without Scaleban. During inspection it was found that even after 11 months of continuous
service, it was found scale free and corrosion free. Even though dead algae and fly ash was found in the
water channel of its plates, there was no scaling behind that also. Entire plates can be cleaned by simply
water wash and wire brush.
Operational
APH basket corroded/
eroded/ fouled • Optimise excess air
• Operate APH soot blowers
• Put burner tilt operation on auto
Excess air ingress in • Put SADC in auto
Penthouse, furnace • Optimise number of mills in service
Maintenance
AH seal damage
• Repair/replace APH basket on weight
loss basis
• Repair APH leakage
AH/ Flue Gas duct leakages • AH seal setting/ replacement
• Extensive cleaning of furnace
• Water wall convection surfaces
cleaning
Expansion bellow leakages • Repair AH / flue gas duct leakages
• Repair and replace expansion bellows
• Repair of penthouse, ESP, air in leak
Sector plate undulation / points
damage • Improvement in mill loading
Moisture in coal
Operational
Incorrect fuel / air ratio
• Adjust fuel/ air ratio
• Calibrate fuel/ air control
• Optimise O2
Poor mill fineness • Optimisation of tramp/ cold air
• Optimise hot air temperature
PA& SA distribution
Reduced ID margin
Operational
Erosion of nozzle blocks • Maintain design HPT inlet
pressure & temperature
Erosion of turbine
blades
Deposits on blades
High TTD
Maintenance
• Repair Partition plate passing
Improper heater level • Repair of tube leaks
• Repair of orifice in vapour line
of heaters
Deviation in final FW temperature • Repair of bypass valve
Operational
Air ingress in condenser
• Water box venting
• Put in service stand by ejector/
vacuum pump
Poor CT performance causing
high CW inlet Temperature • Increase the CW flow
• Check cycle isolation
• Put in service stand by CW pump
High ambient temperature • Place stand by CT cells in service
Reduced CW pump
performance/ CW duct silting
Maintenance
High energy drain valve
passing • Repair cycle isolation valve
• Clean condenser water box and
tubes
Higher water box differential • Repair CW discharge control
pressure valve & CT
• Repair condenser air leaks
Reduced Ejector/ CVP • Eddy current test to identify,
performance repair/ replacement of leaking
condenser tubes
• Restoration of performance of
Reduced condenser tube Ejector / AEP
thickness
CW water quality/Bio-fouling
effect
Operational
Condition of fins
• Water chemistry correction (dosing
of chemicals-organophosphate,
chlorine etc.)
Mangrove and algae growth • Switching of individual cells as per
CW inlet temperature
Condition of nozzle
Wind Velocity/
Maintenance
Wet Bulb temperature • Regular chemical cleaning of fin
materials
Condition and fan algae of • PM of gear Box of oil (only for
blade induced draft of cooling tower)
• Removal of mangrove and algae
• Maintaining of drift eliminator
Gear box condition • Removal of vegetation growth
near CT area
Bio-fouling effect