Академический Документы
Профессиональный Документы
Культура Документы
FEBRUARY 2010
†
These standards are based on the original Anglo Coal South Africa (ACSA) Fire Protection
Standards (2007) and De Beers Consolidated Mines (DBCM) Limited Fire Protection Guidelines
(2006) with modifications and inputs from other Anglo operations globally to the original document,
particularly from commodities viz., platinum, base, diamond, ferrous, KIO. Time to time additional
procedures or changes will be made to this document and up-to-date version of this document be
consulted with the custodian bbelle@angloamerican.co.za.
TABLE OF CONTENTS
Introduction to the Standards 1
Classification of Fires 4
Extinguishing Media 5
Standard Title
G1 Electrical cables 7
G2 Fire sprinkler systems - manual 9
G3 Fire sprinkler systems - automatic 11
G4 Fire sprinkler systems - automatic (in cable trenches) 13
G5 High velocity water deluge systems 15
G6 Fixed foam fire suppression systems 18
G7 Fixed gaseous fire suppression systems - room flooding 21
G8 Fixed gaseous fire suppression systems - in cabinet 25
G9 Passive versus aspirated detection systems 28
G10 Fire protection requirements for surface vehicles 30
G11 Oxy-acetylene cutting and welding 39
G12 Compressed gas cylinder stores 41
G13 Single storey office buildings 43
G14 Multi-storey office buildings 45
G15 Archives 48
G16 Vehicle workshops on surface 50
G17 Other workshops on surface 52
G18 Critical substations and MCCs on surface 54
G19 Other substations and MCCs on surface 58
G20 Mini substations on surface 62
G21 Transformer installations on surface 63
G22 Main MV switch and transformer yards on surface 65
G23 Emergency and standby generator installations on surface 66
G24 Control rooms on surface 68
G25 IT rooms 70
G26 Plant structures 73
G27 Battery charging bays on surface 76
G28 Hand-held fire extinguishers 77
G29 65 mm Fire hydrants and related equipment 79
G30 Fire fighting water supply and fire pumps 82
G31 25 mm fire hosereels 84
G32 Hydraulic lubrication and power packs 86
G33 Bunding 87
G34 Fire / separating walls 89
G35 Perfect party walls 91
G36 Fire stopping and intumescent coating of cables 92
G37 Bulk flammable liquid storage facilities on surface 94
G38 Storage facilities on surface for flammable liquids or chemicals in 96
containers
G39 Storage of tyres on surface 98
Standard Title
U1 Headgear hoist rooms 131
U2 Stand-alone surface hoist rooms 134
U3 Vertical shafts, stations and surface banks 137
U4 Inclines 139
U5 Underground conveyors 141
U6 Stonedusting 143
U7 Flameproof zones 148
U8 Fixed underground substations 149
U9 Sectional electrical equipment 151
U10 Mobile underground electrical installations 152
U11 Feeder / breakers 153
U12 Use of plastic pipes underground 154
U13 Proto teams 155
U14 Battery charging bays located underground 157
U15 Fixed refuge bays, escape ways & self-rescuers 158
U16 Mobile containerised refuge bays 160
U17 Worked out areas 162
U18 Underground environmental monitoring systems 163
U19 Underground vehicle fire detection and fixed / portable suppression 167
requirements
U20 Underground diesel & oil stores, including oil separation equipment 169
Standard Title
IM1 Inspection, maintenance and testing of 65 mm fire hydrant standpipe 171
and hose systems
IM2 25 mm fire hosereels 182
IM3 Hand held portable fire extinguishers 185
IM4 Detection and fire alarms 198
IM5 Gaseous extinguishing systems - CO2 (carbon dioxide) systems 223
IM6 High pressure mist (HP) 233
IM7 Inspection and maintenance of sprinkler systems and other water 237
based system
IM8 Private fire service mains 244
IM9 Fire pumps 248
IM10 Water storage tanks 257
IM11 Water spray fixed systems 261
IM12 Foam water fixed systems 267
IM13 Valves, valve components and trim 276
IM14 Emergency escapes 289
IM15 Fire separation fire walls 299
IM16 Fire and emergency signs (FES) 304
IM17 Flammable and combustible liquids bulk storage/ usage 308
Appendix A1 Suggested EMV Suppression System Component Siting Track Dozer D10
DCP
Appendix A2 Suggested EMV Suppression System Component Siting Track Dozer D10
AFFF
Appendix A3 Suggested EMV Suppression System Component Siting Track Dozer D10
Electrical
Appendix B1 Suggested EMV Suppression System Component Siting Grader CAT 14/16
DCP
Appendix B2 Suggested EMV Suppression System Component Siting Grader CAT 14/16
AFFF
Appendix B3 Suggested EMV Suppression System Component Siting Grader CAT 14/16
Electrical
Appendix C1 Suggested EMV Suppression System Component Siting Diesel/Electric
Truck DCP
Appendix C2 Suggested EMV Suppression System Component Siting Diesel/Electric
Truck AFFF
Appendix C3 Suggested EMV Suppression System Component Siting Diesel/Electric
Truck Electrical
This Anglo American Fire Protection Manual is based on the original Anglo Coal South Africa
(ACSA) Fire Protection Standards (2007) and De Beers Consolidated Mines (DBCM) Limited
Fire Protection Guidelines (2006) with modifications and inputs from other Anglo operations
globally to the original document, particularly from commodities viz., platinum, base,
diamond, ferrous. Time to time additional procedures or changes will be made to this
document and up-to-date version of this document be consulted.
The original coal and diamond fire standard was modified to meet the global nature of Anglo
operations and wide commodities to achieve the goal of true standardisation at all
operations. It was noted that it is often not possible for personnel from one mine to have
ready access to another mine within the Group to enable the free cross pollination of ideas
that would see a solution implemented reliably and confidently at one operation, which has
already proven its worth at another.
Conversely, because of the diversity of the operations, a solution from one mine might not
necessarily be the best option at another, and so such cross pollination of ideas might be
futile in any case. Consultation was made through respective Champions from the Anglo
operations to overcome the challenges.
Some mines may want to implement only the minimum necessary. But at an operation with a
low appetite for risk, and the necessary funds available for more comprehensive protection,
added measures may be specified at the discretion of site or project managers.
With these extremes in mind, these standards have been drawn up to promote uniformity of
fire standards throughout the Anglo operations, without removing all discretion from site
management. To that end they are designed to be sufficiently generic to allow for different
local needs and constraints to be accommodated.
These standards describe the minimum standard that is required in the prevention and
minimisation of fire and related perils. It must be stressed that these are the minimum
standards that are acceptable. Individual circumstances will often require these standards to
be exceeded.
During project planning and execution, or even retrospectively if conditions change, the
correct level of protection must be professionally determined, specified and implemented for
each new project or application.
This may exceed the requirements stated in these standards, but will very seldom require
less than what is stipulated herein. So strict adherence to these standards alone means that
a sound basic effort has been made, but might not be a guarantee that ‘everything
necessary’ has been done!
On the subject of Project Planning, it is most important to note that these are generic
Standards. They are meant to provide a basic list of the requirements necessary for various
typical installations at Group operations. But being generic, they can never fully address the
unique needs of each application.
For this reason, these standards are no substitute for a proper assessment of risk conducted
during the planning phase of each new project, which will specify tailor made solutions
exactly appropriate for each situation. As stated above however, such site specific
requirements must always either equal or exceed, but may never be less than what is
specified in these generic standards.
Failure to conduct an effective risk assessment during project planning can result in:
Over-specifying which is wasteful and unnecessary
Under-specifying for the unique risk profile of a particular application, which…
- can necessitate expensive retrofits later,
- may actually constitute a breach the relevant legislation (e.g. SANS 10400:
The National Building Regulations or country specific regulations),
- or may even deliver a product which is ‘uninsurable’, or which will detract from
the generally good risk profile of the operation or even the Group.
Thus the measures implemented will always have as their objective, the effective
management of fire risk using cost effective measures best suited to the operational
requirements of each individual site. In summary, the objectives are:
To ensure that pre-determined minimum standards are met.
To provide a list of basic requirements for new projects.
To provide a benchmark for operations when preparing for external inspections and
risk assessments.
To ensure that all operations become and remain a ‘fit subject of insurance’.
To ensure that all operations meet at least the minimum legal requirements.
That the Group as a whole is on par with world standards in terms of fire protection.
To assist in the correct selection of new fire protection equipment at new or
refurbished installations.
To assist in disseminating best practices throughout the Group.
To aid cost saving by ensuring that ‘fit-for-purpose’ solutions, rather than state of the
art measures, are specified.
To aid cost saving by curtailing unnecessary repeat research and decision-making.
Site personnel at each operation should not need to “re-invent the wheel” each time
the project is repeated at a new site.
To provide a definitive reference manual of fire protection Standards for use
throughout the Group.
This manual is a dynamic document which will require ongoing input from site personnel who
have knowledge of new technology or applications. Persons who have been able to improve
on existing methods and measures are invited to submit their input for possible inclusion in
this manual. However, no new standards will be included that do not exceed or better the
existing minimum standard prescribed.
Self Evaluation Checklists – Also known as SECs, these checklists are summaries
of selected G and U standards. They are intended for the shop floor and will assist
self evaluation in preparation for assessments / audits.
This document was jointly compiled and contributions made by the following people:
It is noted that this document is likely to require fairly frequent revision to cope with improved
understanding of the mine fire risks at workplace and associated engineering controls. We
hope however that it will be useful contribution at the moment and a good basis for future
development.
The above team members would be liaising through the Custodian of the fire standards is
responsible for the ongoing maintenance and revision of the fire standards with a view to
ensuring that they remain current and appropriate by best practice world-wide standards.
CLASSIFICATION OF FIRES
Fires are classified according to five general categories. Fires can be combinations of the
five general classifications. The classifications below are according to European and
American standards. (Classification in Australia differs in that Class C is for flammable gases
and Class E is for energised electrical equipment.)
Class A
Class A fires involve ordinary solid combustible materials, e.g. coal, paper, plastics, rubber,
wood and textiles.
Class B
Class B fires involve flammable or combustible liquids (which vaporise to burn) such as
alcohol, benzene, oil, paraffin, petrol, kerosene and common organic solvents. These liquids
can mostly float on water and will thus continue to burn while in contact with air. Water would
not be a suitable extinguishing medium.
Class C
Class C fires can be Class A, B, D or E type fires, occurring in the presence of energized
electrical equipment such as electrical cables, generators, transformers, switchboards and
switchgear, substations, MCCs, etc.
Water is not a suitable extinguishing medium in the initial stages, when the equipment is still
live, due to the risk of electrical shock. Area hydrants are however still required to allow for
foam generation, and to fight the fire later in its developed stages, when the electrical supply
has tripped / been isolated, and the fire has developed to full involvement of the building, to
become a structural rather than an electrical fire.
Specialized water mist extinguishers, or fixed micromist systems, may also be appropriate,
but for reasons of standardisation, should be avoided unless there is a compelling reason to
deviate.
Class D
Class D fires involve combustible metals and include easily oxidised metals. Combustion
temperatures and energy are normally high compared to Class A fires. Chemical reactions
with air, water and other chemicals are generally violent.
Class D2 fires involve alkali metals, e.g. sodium, potassium and lithium.
Class E
Class E fires involve flammable gases, e.g. methane, propane, natural gases.
Class F/K
This classification was added for kitchen fires in particular. Cooking oils and fat are
included in this category.
EXTINGUISHING MEDIA
Medium Limitations
Water
Water has better cooling properties than any Water is a conductor of electricity and can
other agent and is therefore best used on be very dangerous if used on Class C fires,
Class A fires. Class A fires can re-ignite if not i.e. fires in the vicinity of live electrical
adequately cooled. Water will also penetrate current. It will also cause Class B fires to
readily to reach deep-seated fires. flare up and spread, and if used on Class D
fires, may cause violent explosions.
Dry powder
Dry powder is generally the best Dry powder has no cooling properties and
extinguishing medium for use on Class B will therefore not prevent re-ignition. For this
fires. Extinguishers containing dry powders reason it is not as effective as foam on
are capable of dealing with burning contained flammable liquid fires which have
flammable liquids, spread over large areas, been burning for a long time. Generally,
more effectively than other extinguishers of powders are messy and some form sticky
comparable size. They are effective too on deposits on surfaces which must be
fires involving free-flowing liquids, e.g. scraped and washed away after the fire.
spillages over vertical surfaces. Since dry These deposits can have a detrimental
powder is a non-conductor of electricity, it is effect on delicate machinery and equipment.
safe to use on Class C fires. (Re-ignition of Class A fires is preventable
by using multi-purpose powder).
Foams
Foam extinguishes Class B fires by forming a Most foams have to form a blanket to
blanket of bubbles on the surface of the extinguish the fire and since it is not
liquid and therefore has a smothering effect possible to cover flowing flammable liquids,
on the fires. Foam extinguishers are best foams are not effective. Foam is water-
suited to dealing with small, contained based and therefore a conductor of
flammable liquid fires or for fires which have electricity. It is dangerous to use on live
been burning for some time, causing the electrical equipment. Foams will also tend to
container to become very hot and increasing break down when coming into contact with
the chances of re-ignition. liquids such as alcohols, and this will
prevent the production of an effective
blanket.
Carbon dioxide
Carbon dioxide extinguishers are suitable for The cooling properties of CO2 gas are
dealing with small Class B fires, whether limited and it therefore provides no
spillages or contained. CO2 gas is a non- protection against re-ignition. Since CO2 is a
conductor of electricity and is therefore one gas, draughty or windy conditions will affect
of the safest mediums to use on live its performance. The effective range of a
electrical equipment. The gas will not CO2 extinguisher is also limited. Direct
contaminate foodstuffs or cause a mess, and impingement of CO2 onto delicate electrical
because it is emitted as a gas, will not cause or electronic equipment could cause
unnecessary damage through impact as in additional damage through cold-shock.
the case of solid material, e.g. dry powder. Under dry conditions, the discharge of CO2
extinguishers generates static electricity
which can be uncomfortable to the user.
Other gases
Apart from carbon dioxide, discussed above, The cooling properties of all suppressant
the only other gases approved for use in gases are limited and therefore provide no
fixed fire suppression systems at group protection against re-ignition. Gases are
operations are Argonite and NAF S125. CO2 therefore not the best choice of suppression
remains the preferred choice of gas except medium for inherently hot fires, such as
on draglines, where the low-lying, enclosed those involving flammable liquids, rubber or
areas justify the additional cost incurred by plastic.
these gases which are not harmful to
persons for short periods of exposure. Refer Gases are also only suitable in areas which
in particular to Standards G10 (Fire are routinely tightly sealed, and so draughty
Protection Requirements for Surface or windy conditions are a contra-indicator
Vehicles) and G7 (Fixed Gaseous Fire for the use of any gas as a suppression
Suppression Systems - Room Flooding), medium.
regarding the correct choice of suppressant
gas. These three gases are all more expensive
to install and maintain than CO2. They offer
no material advantage over CO2, except
that persons can survive exposure of short
duration. Nonetheless, CO2 remains
acceptable in almost all applications. The
only application in AngloCoal which
mandates the use of one of these three
gases, is on draglines.
1. From a fire protection perspective, it is desirable for cables to be of the ‘red stripe’
fire-retardant type, or of the white stripe ‘Lotox’ halogen-free type in confined areas
where there is a gassing risk to persons. However, this cannot be regarded as an
absolute requirement, and must always be subject to electrical engineering and
budgetary considerations.
It must be noted that both types are fire retardant only to a degree, and their use
may therefore reduce fire risk. However, fire risk will not be eliminated
altogether. For this reason, other requirements like fire stopping and intumescent
coating remain necessary even with the use of red or white stripe cables. Refer
to Standard G36.
Red stripe cabling has an outer sheath of flame-retardant PVC, but its core
insulation and bedding are both of conventional PVC.
White stripe cable has core insulation, bedding and outer sheath all of halogen
free PVC. NB: the outer sheath of white stripe cables disintegrates in direct
sunlight. Cables must therefore be kept out of direct sunlight.
Thus it is clear that red stripe cabling offers some fire retardancy, but the toxicity
of fumes given off during combustion remains the same as in the case of
conventional cabling. White stripe cables are less toxic during combustion than
other cable types, but do not offer any material fire retardancy benefits, e.g.
retarding the propagation of fire.
2. There is a strong indication for white stripe cable to be used whenever there is a
gassing risk to persons if it should burn. This will apply in particular in enclosed areas
which are difficult to vacate quickly. It does not necessarily apply in general
underground areas, although these too can be confined, because persons
underground are issued with self contained self rescuers to mitigate their exposure to
gassing.
3. Any blasting cables must be suspended completely clear of any other electrical
cables.
4. All electrical cables are to be suspended not less than 300mm clear of any
combustible material. This requirement may be waived where excessively low seams
make the practice impractical. “Combustible material” in this context shall not include
unmined coal in situ (e.g. in pillars and rib-sides).
6. Wherever cables enter a substation, MCC, control room, transformer bay, generator
room, hydraulics room, compressor room, or similar, the aperture where the cables
breach the wall(s) of such room must be fire stopped, and the cables passing through
the breach must be intumescent coated for a distance of at least 1 metre on either
side of such fire stopping. Painting of cables shall not be applicable where the cables
are made to pass through a ‘sand box’ at the wall. See Standard G36 for details on
intumescent coating of cables and fire stopping of cable penetration apertures.
7. It is recommended that all cable racks be secured vertically ‘on their side’, since
horizontal cable trays allow coal dust to accumulate on top of the cables which form a
platform, adding to the fire risk.
Application
2. Manual sprinkler systems are required at all compressed gas cylinder stores.
Requirements
1. Manual sprinkler systems must be dry-pipe systems with an activating valve located
outside the risk area. This activating valve must be no less than 15 metres and no
more than 25 metres from the area at risk, or it may be positioned at a lesser distance
if it is located in such a way as to be adequately protected, so that persons can
operate the valve safely even after the outbreak of fire: for example, around a corner
or behind a wall.
2. There may be only one control valve at which the water supply to the system can be
turned off. If other valves exist, then they must be chained in the open position, or
their handles must be removed to ensure that they cannot be closed.
3. Erect demarcation signage at the activation valve. Suitable wording would be:
“Activation valve for the sprinkler system protecting the (name of location)”.
4. All manual systems must be fitted with ‘dry’ nozzles producing flow and spray
characteristics suitable for the application.
5. Such manually activated sprinkler systems must cover the entire area at risk. In the
case of gas cylinder stores where full and empty cylinders are separated, either
spatially (at least 5m) or structurally (steel plate or brick wall), it is acceptable to
provide sprinklers only on the ‘full’ side.
6. Such systems must be fitted with a supply pipe of minimum diameter 50mm. The
pipes supplying the individual nozzles must be at least 25mm in diameter.
10. At the end of each sprinkler spur line, provide a flush valve. Each line must be flushed
and tested for a minimum of 3 minutes each month to prevent the build up of sludge
in the system, which could clog the heads. Results are to be logged.
Application
1. In buildings where persons need to travel more than 45m before reaching fresh air
(e.g. in a large warehouse), or where the size of the structure and / or the fire load
makes manual fire fighting too dangerous, or unlikely to be effective, automatic
sprinkler systems are required in terms of SABS 0400: The National Building
Regulations, due to life safety concerns.
Considerations
Automatically activated fire sprinkler systems only need to conform to ASIB requirements
and the requirements of SABS 0287 if life safety depends on them (e.g. as contemplated in
Application 1 above).
Otherwise, the designer of the automatic sprinkler system should be informed of the purpose
of the sprinklers, which will typically be to protect assets and to guard against business
interruption losses. The only requirement then is that the designer must warrant that his
design is fit for the purpose, i.e. that it will effectively suppress fire, given the envisaged
structural, stored and operational fire load in the area to be protected.
Requirements
1. The system must be fed from the dedicated fire main. Depending on the requirements
as determined by the designer of the system, the water supply in the dedicated fire
main may or may not be adequate. If not, then appropriate arrangements must be
made either to boost pressure and flow in the dedicated fire main, or to provide a
separate, superior source for the sprinkler system.
Even for systems that are not required to be ASIB compliant, the designer must still
ensure that the system is supplied at adequate pressure and flow to ensure effective
suppression of fire in the protected area, having due cognisance of the fire load, and
the foreseeable type of fire. See ‘Considerations’ above.
2. Colour-code all sprinkler pipe work and above-ground supply lines red.
5. The control equipment for the sprinkler system should include butterfly stop valve(s),
non-return valve(s), control valve(s), and an hydraulic alarm, as described in detail in
NFPA 13.
6. At the control location, the system must be fitted with glycerine-filled pressure
gauges, to ensure that the available pressure in the system can be easily monitored.
7. At the position in which the control valves for the automatic fire sprinkler system are
located, a flow operated hydraulic alarm bell must be fitted, which will sound in
response to the flow induced by the activation of one or more sprinkler heads.
8. At the end of each sprinkler spur line, provide a flush valve. Each line must be flushed
and tested for a minimum of 3 minutes each month to prevent the build up of sludge
in the system, which could clog the heads. Results are to be logged.
Application
Under certain circumstances, automatic sprinkler systems may be specified in cable trenches
and cable basements associated with main or critical surface substations, or in cable tunnels
that lead to a vertical underground shaft, and therefore have the potential to pollute the air
being drawn down that shaft.
Considerations
One way of providing such suppression is to install an automatically activating (fusible glass
link) sprinkler system. The system should be designed by an appropriately qualified person,
(e.g. an ASIB approved sprinkler installer, although full ASIB compliance is not required in
such application, since life safety will not be dependent upon the system) which will be
intended primarily to protect assets and to prevent business interruption losses.
Such installer should be informed that the system will not be critical to life-safety, to guard
against unnecessary over design, whilst still ensuring compliance with all relevant sections of
NFPA 13, SABS 0287, and ASIB. The designed sprinkler density, water pressure, and flow,
must allow for the foreseeable fire load represented by the planned concentration of cables
to be installed in the trenches or basement.
Requirements
1. The system must be fed from the dedicated fire main. Depending on the requirements
as determined by the designer of the system, the water supply in the dedicated fire
main may or may not be adequate to ensure effective suppression of fire in the cable
trenches, having due cognisance of the density and type of cable intended to be
installed therein. If not, then appropriate arrangements must be made either to boost
pressure and flow in the dedicated fire main, or to provide a separate, superior source
for the sprinkler system.
3. The control equipment for the sprinkler system should include butterfly stop valve(s),
non-return valve(s), control valve(s), and an hydraulic alarm, as described in detail in
NFPA 13.
4. At the control location, the system should be fitted with glycerine-filled pressure
gauges, to ensure that the available pressure in the system may be easily monitored.
5. At the position in which the control valves for the automatic fire sprinkler system are
located, a flow operated hydraulic alarm bell must be fitted provided, which will sound
in response to the flow induced by the activation of one or more sprinkler heads.
7. At the end of each sprinkler spur line, provide a flush valve. Each line must be flushed
and tested for a minimum of 3 minutes each month to prevent the build up of sludge
in the system, which could clog the heads. Results are to be logged.
8. Colour-code all sprinkler pipe work and aboveground supply lines red.
Application
High velocity water deluge systems are used for installations or equipment which have a high
fire load and / or high energy level, and which are critical to continued production. Such
systems are always automatically activated.
High velocity water deluge systems are particularly useful where such equipment is located
within areas filled with other densely installed equipment, so that effective spatial or structural
separation of the risk is difficult to achieve. Typical examples are transformers, hydraulic
power packs and large lubrication packs, located in an unseparated position within a large
plant building. Large, critical main transformers, even if well separated, are also often so
protected.
Requirements
High velocity deluge systems should be installed in accordance with the provisions of NFPA
15. They must comply inter alia with the following requirements:
However, note that the system designer / installer will need, in terms of NFPA 15, to
warrant the efficacy of the system to suppress fire in the protected areas, based upon
an assessment of the calorific value constituted by the equipment in these areas, and
the physical conditions prevailing, and may specify a higher required flow1 and
pressure2 to satisfy these requirements. In such case, such higher requirements must
be met.
2. Hydrostatic pressure tests must be conducted prior to sign-off. All spray system pipe
work should be pressure tested to 1.5 times the working pressure (i.e. 1.5 x 400kPa
or the pressure specified by the designer), or 1500 kPa, whichever is the higher, for a
period of 24 hours. These tests should be witnessed by the Project Engineer or a
responsible person deputed by him, who must warrant in writing that the test has
been completed satisfactorily. The date and length of the test, and the pressure to
which the system was subjected, must also be recorded.
3. All piping in the deluge system up to and including 300 mm diameter is to be medium
quality galvanised SABS 62.
4. All piping over 200 mm diameter is to be galvanised and have a wall thickness of at
least 4.5 mm. It should comply with SABS 719.
7. All flanges in the system are to comply with SABS 1123 1600/3.
10. Piping of diameter 65 mm and above is to be welded after fabrication before hot dip
galvanising.
13. Each deluge valve must include inter alia, the following:
- The necessary small bore pipe work, including strainers, to enable the control
valve to operate automatically.
- A pressure switch for transmitting a signal when the control valve has operated.
14. Deluge control valves for such systems should be installed in a safe and easily
accessible position, between 15m and 25m away from the protected installation, or
around a corner where they can be safely accessed.
16. Each deluge control valve is to include any pressure-reducing device that may be
necessary in the opinion of the system designer / installer to protect the system if the
available water pressure in the supply exceeds that of the spray system demand.
17. Isolating valves at the deluge control valve must be so arranged as to enable the
deluge valve to be tested without discharging water into the spray system.
18. The selection of the type and size of spray nozzles to be used in the high velocity
deluge system should be made by the designer / installer having due consideration of
all pertinent situational factors, such as the physical character and calorific value of
the items to be protected, the foreseeable draught and/or wind conditions, and any
other relevant factor.
19. Nozzles which are preferred are those which have waterways that are not easily
obstructed by debris, sediment, sand or other impurities in the water.
20. In general, the designer / installer should specify a spray nozzle capable of producing
flow and spray characteristics similar to those of the “BETA” type N spiral nozzles.
21. Spray nozzles are to be placed in any position necessary within the protected zones
to obtain proper coverage of the protected area. For this reason, the system should
be so designed as to apply water both to the top and sides of the equipment which
they protect. The particular nozzle design and the profile of the water spray produced
will be guiding factors in selecting suitable positions for the nozzles.
22. All high velocity water deluge systems are to be fitted with a flush valve and the
system is to be flushed for a minimum of 3 minutes at periods not exceeding 1 month.
Results are to be logged.
NFPA 15 - Standard for Water Spray Fixed Systems for Fire Protection
Relevant sections of SABS 62 - Steel pipes
Relevant sections of SABS 719 - Electric welded low carbon steel pipes for aqueous fluids
(large bore)
Relevant sections of SABS 1123 1600/3 - Pipe flanges
Relevant sections of SABS 509 - Malleable cast-iron pipe fittings
Relevant sections of BS 1640 - Steel Butt-Welding Pipe Fittings for the Petroleum Industry
Standard G29 - 65 mm Fire hydrants and related equipment
Standard G30 - Fire fighting water supply and fire pumps
Application
Foam-based fire suppression systems are adequately used to protect areas which are at risk
to flammable liquid fire. Therefore, they may be installed at reagent storage areas, flammable
liquid stores, hydraulic power packs, lubrication packs and other similar installations.
Requirements
1. The design basis for each fixed foam fire extinguishing system shall follow the criteria
laid down in Clauses 4.3.2 and 4.3.3 of NFPA 16, under the heading “Discharge
criteria and discharge duration”, in order to provide for a quantity of foam solution
adequate to cover the total area to be protected, at a rate of application of 6.5
litres/minute/m² of protected area, sustained for at least 10 minutes.
2. Where the foam suppression system is required to protect more than one area, and
where application in one area may be required without necessarily involving another,
the deluge valves of the foam suppression system shall have a dedicated foam
proportioner. Independent supplies shall be taken to the respective areas to be
protected, at which point the solution would be routed through a distribution pipe
network fitted with self-aspirating foam spray heads specifically designed for the
application of foam.
3. Such heads must be suitably spaced and positioned so as to cover the entire area to
be protected.
6. The foam system deluge valves must be directly fed from a bladder foam tank of
adequate capacity to meet the requirement stated in 1 above.
7. The system shall be so designed and configured as to ensure that the foam
concentrate injection device is activated automatically by, or concurrently with, any
activation of the main water supply control valve supplying the foam generating
system.
8. Where the foam suppression system will be required to protect more than one area,
and where activation in one area may occur without activation necessarily occurring
in the others, the system pressure and flow must be suitably designed to allow it to
vary according to the demand on the system. To this end, a balanced pressure
system must be used. The proportioning system must be a centralised foam unit in
the form of a bladder tank, equipped with fixed orifices in the water and foam-
concentrate lines. Orifices must each be of the correct area ratio in relation to one
another.
9. The bladder tank foam proportioning system shall comprise two parts, namely the
bladder tank and the foam proportioner.
10. The bladder tank must be a pressure vessel containing a reinforced flexible rubber
bag to hold the foam concentrate.
11. The foam proportioner, known as a TP proportioner, shall make use of an orifice to
create pressure drop in the water line. The pressure drop shall be fed to the outside
of the rubber bag located within the bladder tank, thereby applying pressure to the
bag which shall release foam concentrate. This foam concentrate shall be discharged
via a pipe leading to the downstream side of the TP proportioner.
12. The TP proportioning unit shall have four orifices, namely the water inlet, the solution
outlet, the foam concentrate inlet, and the water outlet.
13. The water inlet and solution outlet orifices on the TP proportioning unit must be wafer-
mounted in line in the fire water line.
14. Mounted at right angles to the water inlet and solution outlet orifices of the TP
proportioning unit must be the foam concentrate orifice, fed from the bladder tank,
with an adjustable proportioning unit to regulate the foam concentrate ratio into the
water.
15. The water outlet orifice must be located opposite the foam concentrate orifice to
provide pressure in the bladder tank which will squeeze the rubber bag containing the
foam concentrate.
17. To ensure automatic activation of the foam suppression system, automatic detection
equipment shall be provided. This shall be so configured as to alarm both in the case
of fire, and in the event that failure of detection equipment is detected by the system.
This is intended to result in clear notification to a constantly monitored control
location, not only of fire, but also of abnormal system conditions.
17. All system piping relating to fixed foam fire suppression systems shall be hydraulically
designed for the specific project, in order to ensure relative uniformity of the foam and
water distribution between different parts of the system. This must allow for frictional
loss of head in water supply piping, which is proportional to diameter and length. A
maximum variation of 20% above the specified discharge rate per sprinkler or nozzle
must be permitted. Pipe sizes must be adjusted to compensate, based on detailed
friction-loss calculations. Such calculations must show the relationship between the
water supply and the water demand. A suitably qualified person shall, on behalf of the
designer / installer, certify these calculations to be correct.
18. Where used in a corrosive atmosphere, the detection devices shall be of materials
not subject to corrosion, or adequately protected to resist corrosion.
19. Where automatic detection equipment of the electric type is used, such detection and
equipment and any related auxiliary equipment must be designed specifically for use
in hazardous areas. Certification must be checked before equipment selection is
finalised.
20. The system shall be so designed and arranged as to allow tests and inspections to be
made without discharging the foam solution to the system piping. Without this, there
would be no way of checking the system without affecting the equipment which the
system is designed to protect.
21. Any system designer / installer appointed to design or install a fixed foam fire
suppression system shall be bound to supply on completion of the project:
All piping layout drawings.
Electrical schematics.
Hydraulic calculations.
All literature and instructions provided by the manufacturer of any equipment
and devices installed, as described for the proper operation and maintenance
of such equipment and devices.
A copy of NFPA 25, the standard for the inspection, testing, and maintenance
of water and foam-based fire protection systems.
Application
Room-flooding (sometimes called ‘total flooding’) fixed gaseous fire suppression systems are
indicated in applications where there is:
One of the most common applications is conventional MV substations equipped with oil-filled
switchgear.
In-cabinet suppression systems and total-flooding suppression systems are not direct
alternatives to each other. They each perform a subtly different function, and for maximum
protection, a total-flooding system should be installed, with in-cabinet systems installed
additionally in the most critical panels in the room.
The recommendation is that the gas selected should be CO2 because of its ready
availability, proven efficacy, good safety record, environmental friendliness, ease of service
and recharge, the availability of detailed installation and maintenance standards, and more.
However, CO2 (and CO) is heavier than air. For this reason, it can accumulate in low lying
areas which are poorly ventilated. Persons entering these areas can be overcome and may
expire as a result of such gas accumulations. CO2 should therefore not be used aboard
draglines and any enclosed basements.
NAF S125 (Afrox FS 125) and Argonite are also acceptable, but their selection will incur
additional expense, and because they are less common than CO2, they may take longer to
replace after discharge, leaving the area unprotected. This is a particular concern in remote
areas. The onus rests with the client to determine whether the additional expense and
possible replacement / service difficulties are justified.
No gases containing HCFCs are acceptable. Thus FM100 and FM200, NAF S III and Halon
in all its forms, are not recommended.
Aerosol extinguishing agents (FEAG / FEAS) are also not recommended. To eliminate the
possibility of a secondary heat source within a protected area, no system may be installed
whose method of operation generates heat, for example by an exothermic reaction. The
suppression medium / system selected should not discharge any solid residues or parts of
the container upon, during or after discharge.
Products containing HFCs are not specifically excluded on the basis of their HFC content
alone, provided that they meet all other requirements. There is concern however, that HFCs
may be banned for the same environmental reasons as HCFCs. If this occurs, systems
containing HFCs would need to be replaced. It is therefore difficult to understand any
justification for choosing any media which contains an HFC.
Installation requirements
Rooms should be treated independently of each other. However, consider that such systems
are intended to contain fire originating in the protected room, and not fire spreading inwards
from other areas, which is one reason for physical subdivision of the complex by perfect
party walls and fire stopping. The following are the most important requirements which must
be met:
1. All doors belonging to the protected room must be fitted with automatic closing
mechanisms, to ensure that they are kept closed at all times, so that the suppressant
gas will not escape to atmosphere, diluting the concentration in the room, and
rendering the system ineffective.
2. It is important in calculating the required gas volume of the cylinder bank, to include
the volume of the ceiling void, if any. From a fire risk perspective, a reinforced
concrete roof is always preferable.
4. This signage should also inform persons that upon entering, the system must be
switched to manual discharge mode by means of a key or switch provided outside, in
close proximity to each door. It is usual to have such key or switch integrated with the
manual call point at such door.
5. Primarily to ensure the safety of people, no system may be installed which cannot be
completely isolated (turned off). It is most important to ensure compliance with this
requirement in the case of systems which have more than one actuation mechanism,
like sealed aerosol (FEAG / FEAS) units.
6. Any electrically operated fan or air-conditioner installed for the purpose of ventilating
or cooling a room protected by a room flooding fire suppression system must be
interlocked with the control panel of the passive fire detection system, so that such
fan or air-conditioner will be caused to trip out, and to cease operating, in response to
any manually or automatically actuated alarm signal received by such panel in
relation to that particular fire zone. Failure to provide such interlock will result in the
suppressant gas being diluted, and not operating as per design. Also, such fan or air
conditioner would continue to ventilate the fire, assisting fire growth and propagation.
7. Ensure that the room is effectively sealed, i.e. that doors are tight fitting, that no doors
have louvres or other openings, and that any other apertures in the roof or walls are
effectively sealed.
8. On the bank of cylinders serving the gaseous suppression system, ensure that at
least two actuators per bank are operated by electric solenoid. All other actuators on
the bank may be pressure activated by the gas released from the electrically
activated cylinders. The reason is to ensure that if one of the two fails, the system will
still discharge by the actuation of the other.
9. The cylinders in the bank must be secured to a supporting wall by means of properly
designed brackets, as described in the relevant section of NFPA 12. Looped chains
etc are not acceptable!
10. Primarily to ensure the safety of people, whether working in the protected area, or
responding to a fire (i.e. fire teams), no cylinder, canister or container for a
suppressant gas or agent may be positioned within a fire zone or in any area where it
could foreseeably be subjected to heat in a fire situation.
For this reason, it would be unsuitable to position such cylinders anywhere within a
substation complex or similar. The cylinder bank should be located externally, where
it must be suitably positioned to protect it from the elements and from possible impact
damage by vehicles.
11. The primary means whereby the fixed gaseous total flooding fire suppression
systems will discharge, will be automatically in response to a “double knock” alarm
received from the appropriate zone of the automatic fire detection monitoring panel.
12. The secondary means whereby a fixed gaseous total flooding fire suppression
system will discharge, will be in response to a manual alarm received from a
dedicated call point (usually a break-glass panel) positioned outside one of the doors
leading to the affected zone.
13. Manual call points (break-glass panels) intended for the manual discharge of a fixed
gaseous fire suppression system, or a zone of such system, shall be colour-coded
red.
14. Where there is any room for doubt as to which zone a discharge break-glass panel
pertains to, such panel must be clearly demarcated to indicate the zone to which it
relates. This might be the case where a multi-zone system has entrances to two or
more of its zones located close to each other, for example leading off a common
central room or foyer.
15. After installation and prior to commissioning, the system must be tested by activation
and full gas discharge, to ensure its operability, efficacy and the integrity of the
sealing arrangements. The degradation rate of the extinguishing gas must be
determined and indicated on the test certificate.
Maintenance requirements
All fixed room flooding suppression systems shall be checked weekly by a mine employee
suitably trained and appointed in writing to perform such work. The results of such
inspections shall be recorded in a logbook to be kept for that purpose.
If during the weekly inspection of such system, the appointed employee becomes aware of a
problem affecting the operation or reliability of the system, it shall be his responsibility to
initiate such steps as are necessary to reinstate the system, and / or to have the necessary
repairs effected by a suitably qualified service provider.
All fixed room flooding suppression systems shall be serviced at least twice annually, as
prescribed in NFPA 12, by an accredited service provider. All elements of all systems must
be physically tested to determine their reliability. Inter alia:
The contents of at least 20% of all cylinders (i.e. 40% per annum) must be checked at
every inspection.
Application
In-cabinet systems are appropriate where the fire risk is mostly limited to the panels or other
equipment installed, i.e. where there is little other fire loading in the room.
They are also useful where it would be difficult to seal the room effectively, so that the gas
from a room-flooding system would become diluted before it could be effective.
Also, where relatively few panels are installed in a very large room, or in an open area, total
flooding would require too much gas to reach the required concentration, and so might prove
too expensive, and impractical.
In-cabinet systems are beneficial in that the gas is applied directly to the seat of the fire, and
so is likely to extinguish the fire more quickly, limiting the damage to fewer panels.
However, in-cabinet systems are complicated, and their infrastructure is therefore more
expensive, although the smaller quantities of gas make them cheaper to recharge after they
have been activated.
Because the pipe work, nozzles and detectors of in-cabinet systems are located in the
panels, these are often disconnected or damaged by persons working on the panels, so that
the systems may not function reliably when needed.
In-cabinet systems offer protection only against fires originating in the protected panel, and
do not protect against fire originating elsewhere in the room (e.g. on cables or unprotected
panels in the room), or spreading inwards from other parts of the building.
In-cabinet suppression systems and total-flooding suppression systems are not really direct
alternatives to each other. They each perform a subtly different function, and for maximum
protection, a total-flooding system should be installed, with in-cabinet systems additionally
installed in the most critical panels in the room.
The recommendation is that the gas selected should be CO2 because of its ready
availability, proven efficacy, good safety record, environmental friendliness, ease of service
and recharge, the availability of detailed installation and maintenance standards, and more.
However, CO2 (and CO) is heavier than air. For this reason, it can accumulate in low lying
areas which are poorly ventilated. Persons entering these areas can be overcome and may
expire as a result of such gas accumulations. CO2 should therefore not be used aboard
draglines and any enclosed basements.
NAF S125 (Afrox FS 125) and Argonite are also acceptable, but their selection will incur
additional expense, and because they are less common than CO2, they may take longer to
replace after discharge, leaving the area unprotected. This is a particular concern in remote
areas. The onus rests with the client to determine whether the additional expense and
possible replacement / service difficulties are justified.
No gases containing HCFCs are acceptable. Thus FM100 and FM200, NAF S III and Halon
in all its forms, are not recommended.
Aerosol extinguishing agents (FEAG / FEAS) are also not recommended. To eliminate the
possibility of a secondary heat source within a protected area, no system may be installed
whose method of operation generates heat, for example by an exothermic reaction. The
suppression medium / system selected should not discharge any solid residues or parts of
the container upon, during or after discharge.
Products containing HFCs are not specifically excluded on the basis of their HFC content
alone, provided that they meet all other requirements. There is concern however, that HFCs
may be banned for the same environmental reasons as HCFCs. If this occurs, systems
containing HFCs would need to be replaced. It is therefore difficult to understand any
justification for choosing any media which contains an HFC.
Installation requirements
Consider that such systems are intended to contain fire originating in the panel which they
protect, and not fire spreading inwards from other parts of the structure or of the same room.
This is one reason for physical subdivision of the complex by perfect party walls and fire
stopping, and for keeping unnecessary fire loading and ignition points in the room to a
minimum. However, this is why in-cabinet systems are not appropriate in rooms containing a
complex risk which is not confined to the cabinets, e.g. a substation with significant quantities
of cable in the room housing the electrical panels / cabinets.
The following are some of the most important requirements which such systems must meet:
3. For in-cabinet systems, the automatic discharge and actuation system must be
provided independently of any system installed to detect fire in the general room
space for alarm purposes.
4. Although each panel should have its own detector(s), the gaseous suppression
system installed for each room should discharge simultaneously into all panels in that
room in response to a signal received from any one of the in-cabinet detectors in that
room (but not from the room detection system).
5. The in-cabinet suppression systems should also be capable of manual activation, via
break-glass panel(s) positioned in reasonably close proximity to the panel it serves.
6. Such break-glass panel(s) must be clearly demarcated as to which of the panels they
serve, as there may be several systems installed in one room.
7. Although such systems pose far less risk to people than room flooding systems,
signage should still be erected at every door leading to an in-cabinet gas protected
area warning of the presence of such system, and advising that the door should
never be closed or locked whilst persons are inside.
8. On each bank of cylinders serving a gaseous suppression system, ensure that at
least two actuators per bank are operated by electric solenoid. All other actuators on
the bank may be pressure activated by the gas released from the electrically
activated cylinders. The reason for no less than two of the cylinders to be electrically
actuated is to ensure that if one of the two fails to operate, the system will still
discharge due to actuation of the other. However, note that this will usually not be
appropriate in the case of in-cabinet systems, as each system will typically use only
one cylinder!.
9. The cylinder(s) in each bank must be securely fastened to a supporting wall or similar
by means of properly designed brackets, as described in the relevant section of
NFPA 12. Looped chains etc are not acceptable!
10. Primarily to ensure the safety of people, whether working in the protected area, or
responding to a fire (i.e. fire teams), no cylinder, canister or container for a
suppressant gas or agent may be positioned within a fire zone or in any area where it
could foreseeably be subjected to heat in a fire situation. For this reason, it would be
unsuitable to position such cylinders anywhere within a substation complex or similar.
The cylinder bank should also be protected from possible impact damage by vehicles.
Maintenance requirements
All in-cabinet suppression systems shall be checked weekly by a mine employee suitably
trained and appointed in writing to perform such work. The results of such inspections shall
be recorded in a logbook to be kept for that purpose.
If during the weekly inspection of such system, the appointed employee becomes aware of a
problem affecting the operation or reliability of the system, it shall be his responsibility to
initiate such steps as are necessary to reinstate the system, and / or to have the necessary
repairs effected by a suitably qualified service provider.
All in-cabinet suppression systems shall be serviced at least twice annually, as prescribed in
NFPA 12, by an accredited service provider. All elements of all systems must be physically
tested to determine their reliability. Inter alia, the discharge mechanism on every cylinder
must be checked at every inspection. The contents of at least 20% of all cylinders (i.e. 40%
per annum) must be checked at every inspection.
Definition
A passive system is one in which the detectors or heads are installed in the zone to
be monitored, and ‘wait’ for smoke or heat to reach them before they are activated.
These are cheap, robust systems with reasonable reliability.
An aspirated system has ‘sniffer’ pipes installed in the critical areas of the area to be
sampled. There are small apertures in the pipe. This pipe is connected to the
sampling unit, where a fan sucks air through the apertures, along the pipe, and into
the processing unit where the system measures for smoke and various
predetermined gases. These systems are thus active, and react faster than passive
systems. However, they are expensive and sensitive to dust and moisture. Their
benefits often do not warrant their extra cost and sensitivity to external influences.
Application
1. Passive fire detection systems are cheaper to install, easier to maintain, and less
susceptible to false alarms in harsh, dusty environments than aspirated fire detection
systems. Passive detection systems will therefore usually be indicated in the vast
majority of applications.
2. Aspirated fire detection systems respond faster to an incipient fire, and may therefore
be indicated in high value applications, where the fastest possible response is
essential, and where the environment is relatively mild, so that it will not affect the
functioning of the sensitive aspirated system.
3. Where passive fire detection systems are installed, each zone should be provided
with at least two detector heads, to ensure firstly that an alarm will be forthcoming
even if one of the heads is out of order, and secondly, so that a mixture of smoke and
heat detection heads may be provided in each zone.
4. Where passive fire detection heads are to be installed in a room / zone, there should
be an approximate 50/50 split between smoke and heat detector heads, since smoke
detectors will alarm most efficiently in some circumstances, and heat detectors will
alarm most efficiently in other circumstances, so that a mixture will provide the best
possible response.
Note however, that in certain applications, smoke detector heads are inappropriate,
such as in a kitchen.
5. The electronic control panel of the detection system should be set up to alarm
automatically in response to any signal received from a detector head which it
monitors.
6. The system should be capable of raising a visual and audible local alarm which
should be relayed automatically to a remote, constantly monitored point, so as to
raise a simultaneous remote alarm and ensure the quickest possible response to the
expected fire.
7. Where the electronic fire alarm control panel relies upon the PLC / SCADA system, it
must interface with such system via two alternative routes, not located within the
same cable trench or on the same cable rack.
Application
1. Early detection of fire is critical in mitigating the effects of fire on mobile mining
equipment. Detection devises are therefore required on all mobile mining equipment.
2. Both fixed and portable suppression systems are essential for safeguarding mobile
equipment and personnel against fire and related hazards.
3. Portable and / or fixed suppression systems are required on all mobile mining
equipment.
1. All LDVs and trucks are to be fitted with at least one 9 kg hand-held DCP fire
extinguisher. On larger vehicles such as haul trucks, the number should be increased
to at least two 9 kg units. These should be securely mounted in brackets and should
be positioned in easily accessible and clearly visible positions.
Requirements
1. All units aboard larger trucks should be dual systems using dry powder followed by
foam application to cool and prevent re-ignition.
2. All systems should include linear wire for early detection purposes. The linear wire
must span the length of the engine compartment and also the first metre of all main
harnesses at the fuse box/panel.
3. All systems to have an additional two manual activation points, one in the cab and
one accessible from the ground.
4. Dry powder and foam must be distributed via a flexible hose system complying to
SAE100R5/R1 specification in red material with ‘FIRE HOSE’ demarcations along the
length.
5. All nozzles should be made of brass with protective blow off caps.
two of these tanks will suffice. On trucks of 170t to 190t e.g. Caterpillar 789, four to
five tanks may be used as per the installer’s specification.
8. Foam application systems should use Aqueous Film Forming Foam (AFFF)
containers selected to give a two minute discharge. Only one 65 litre tank capable of
supporting a maximum of twelve nozzles is required. Turbochargers must be
protected by foam. Foam application nozzle quantity is two per turbocharger below
250 mm in housing diameter and three if larger.
1. All dozers, wheel loaders, road scrapers, etc must be fitted with at least one 9 kg
hand-held DCP fire extinguisher. On larger vehicles, the number should be increased
to at least two 9 kg units which must be securely mounted in brackets located in
easily accessible and clearly visible positions on the machine.
Requirements
1. All units aboard larger equipment should be dual systems using dry powder followed
by foam application to cool and prevent re-ignition.
2. All systems should include linear wire for early detection purposes. The linear wire
must span the length of the engine compartment and also the first metre of all main
harnesses at the fuse box/panel.
3. On larger machinery e.g. Caterpillar 994 front end loaders, the system must have an
additional two manual activation points, one in the cab and one accessible from the
ground.
4. Dry powder and foam must be distributed via a flexible hose system complying to
SAE100R5/R1 specification in red material with ‘FIRE HOSE’ demarcations along the
length.
5. All nozzles should be made of brass with protective blow off caps.
8. Foam application systems should use Aqueous Film Forming Foam (AFFF)
containers selected to give a two minute discharge. Only one unit varying in size from
45litres to 106litres depending on the piece of equipment is required. A 45litre
container can support a maximum of 6 nozzles whilst a 206 litre container can
support twelve. Turbochargers must be protected by foam. Foam application nozzle
quantity is two per turbocharger below 250mm in housing diameter and three if larger.
2. A fixed dry chemical powder and foam suppression system must be provided in all
high-risk areas such as engine rooms, gearboxes and hydraulics areas. The dual
system uses dry powder followed by foam application to cool and prevent re-ignition.
This should be capable of automatic activation by means of linear wire routed
throughout the abovementioned high-risk areas in which nozzles for the suppression
system are located. It should also be capable of manual discharge by means of an
activation button or plunger located in the driver’s cabin, and by a second activation
button or plunger located at an external position near ground level, usually at the foot
of the ladder way leading to the machine’s deck.
On larger machines, where the system is split between the different risk areas, more
than one plunger will be provided in the driver’s cabin and at the external position,
one for each zone. In such case, the plungers or activation button must be clearly
demarcated so that the appropriate system may be selectively discharged.
3. Where such machine has a separate electrical room, such room must be protected by
means of a fixed gaseous suppression system. Refer to Standards G7 and G8.
Break-glass panel manual activation points for such gaseous suppression system(s)
should be provided next to the door outside the room being protected.
Draglines
Rationale
1. Draglines have extremely high business interruption loss potential. This is because
firstly, they are long lead items which cannot easily or rapidly be replaced if lost to fire
or any other catastrophe. Secondly, there are relatively few draglines at any
operation, and the loss of a dragline therefore represents a direct loss of production
which translates into loss of revenue. Thirdly, draglines represent a fairly dense
concentration of numerous fire risks. Fire arising anywhere on the machine and not
contained in its initial stages is likely to spread uncontrolled throughout the dragline,
resulting in extensive damage or complete destruction which will translate into
significant loss of revenue.
2. The draglines operate in the mining pit where there is no ready access to secondary
fire fighting measures, i.e. large bore hydrants and hoses. There is therefore
complete reliance upon fixed systems on the dragline. Normally, fixed systems do not
cover the entire dragline and neither are they designed to cope with a well-developed
fire. Their modus operandi is to extinguish fire in its initial stages. If they fail to do this,
it is likely that the fire will spread to other parts of the machine and cause extensive
damage or even total destruction. For this reason, it is important that fixed
suppression systems must respond quickly, automatically, and effectively, in the very
early stages of any fire’s development.
3. The fire load (calorific value) represented by a dragline is relatively high, as there is
extensive use of electric cabling and flammable liquids. This means that fire spread
will be rapid and fire intensity will be high.
4. The dragline is built largely of steel. This means that its structural integrity is much
lower than, for example, a conventional building constructed of brick and mortar.
Steel will buckle and fail at temperatures as low as 500°C.
The conclusion is that response to any fire occurring on a dragline needs to be:
Effective (the suppression medium must be suitable for the risk type, and must
be adequate in size and volume to adequately suppress fire in the area which it
is designed to protect)
Requirements
Note that these requirements are specific to a Bucyrus Erie 1570 dragline, but are relevant to
all draglines in the Group.
1. All fire detection systems on draglines, including fire detection systems which also
serve as the automatic actuation system for a fixed fire suppression system, must
report to a main electronic fire system repeater panel.
2. The main electronic fire system repeater panel must be so positioned in the
operator’s cabin of the dragline as to be easily visible from the operator’s chair.
Additionally, the system must be equipped with both a visible (e.g. a flashing light)
and an audible (e.g. a bell or panel buzzer) means of alerting the operator if fire is
detected.
3. A secondary external, audible alarm (e.g. a bell or siren) must be provided, and must
be of such intensity that it is clearly audible anywhere in or on the dragline, and
anywhere within 100 metres of the dragline.
4. Not withstanding the requirements stated in 2 and 3 above, every local control panel
must be equipped with both a visible (e.g. a flashing light) and an audible (e.g. a bell
or siren) means of raising an alarm if fire is detected in that zone. Both visible and
audible means of alarm must be located at the entrance to the protected area.
5. From the main electronic fire system control panel, links must be established to a
remote, constantly monitored control room or to a designated person or other
location, so that the system will simultaneously raise a remote alarm when an alarm
is triggered on the dragline.
6. The following areas of all draglines are identified as high fire risk areas which must be
equipped with a fixed automatic fire detection system. Note that in the following
list, the areas stated are common to all draglines. Depending on the particular
dragline layout, the need for additional zones on the automatic fixed fire detection
system may exist.
Left propel room 50:50 split: passive heat & passive optical
Right propel room 50:50 split: passive heat & passive optical
Upper control room 50:50 split: passive heat & passive optical
Lower control room 50:50 split: passive heat & passive optical
Compressor room, where one exists 50:50 split: passive heat & passive optical
Compressors, when free-standing in the Passive in-cabinet heat probe, or internal linear
general machine room wire
Diesel or petrol – driven generators Passive heat
7. The following areas of all draglines are identified as high fire risk areas which must be
equipped with fixed fire suppression systems. All suppression systems must be
capable of automatic and manual actuation. This shall not apply in the case of propel
rooms which use a manually activated foam system shared with the machine room.
The suppression agent will vary according to area, and the accepted type by area is
indicated below.
Choice of gas. Note that in the case of draglines, fixed gaseous fire suppression
systems may only use Argonite or FM200 (including NAFS 125) as their suppression
agent. If NAFS III or is already installed, it need not be changed, but no new fixed
gaseous fire suppression system should be installed that makes use of this gas.
NAFS III once discharged, must be replaced with one of the named approved gasses.
No other gases or aerosols are to be used on a dragline.
Note that in the following list, the areas stated are common to all draglines.
Depending on the particular dragline layout, the need for suppression in additional
zones may exist.
Left propel room Manually activated, fixed nozzle foam suppression system, sharing
a foam-source with a manual foam application system (38mm hose
and nozzle) in the machine room,
OR a dedicated automatic foam system.
Right propel room Manually activated, fixed nozzle foam suppression system, sharing
a foam-source with a manual foam application system (38mm hose
and nozzle) in the machine room,
OR a dedicated automatic foam system.
Lubrication room Fixed automatic combined DCP and foam fire suppression system,
with sequential discharge of DCP then foam.
Compressor and Fixed automatic DCP fire suppression system
Generator rooms
Left MV room Fixed automatic total flooding gaseous fire suppression system
Right MV room Fixed automatic total flooding gaseous fire suppression system
Upper control room Fixed automatic total flooding gaseous fire suppression system
Lower control room Fixed automatic total flooding gaseous fire suppression system
Centre pintle (MV Optional fixed automatic DCP fire suppression system
rings)
Above tub, between Manually activated, fixed nozzle foam suppression system, sharing
rack and rollers a foam-source with a manual foam application system (38mm hose
and nozzle) in the machine room
Swing shaft Dedicated automatic foam system per compartment
compartments
8. With respect to detection and suppression in the Upper and Lower Control Rooms,
the fixed fire system shall be configured such that a trigger in one room
simultaneously triggers the system in the other. In effect, the two rooms must be
configured to behave as one room.
9. In all instances where a fixed automatic fire suppression system is installed, the
system shall be configured to discharge only in response to a “double knock” alarm
received from the associated automatic detection system, as a safeguard against
discharging the suppression medium in response to a false alarm received from any
single detector.
10. In any of the following cases, power must be tripped automatically as below:
Upon receipt of a “double knock” alarm from Trip power in the MV rooms and auxiliary
either Control room transformers
11. In the case of all fixed suppression systems, the designer / installer of the system
must show, as part of the handover documentation provided to the client at the time
of system delivery, all calculations necessary to demonstrate the adequacy of the
volume of suppression medium installed, to suppress fire in that room, having due
cognisance of the volume of the room and the medium concentration required for
effective operation, determined in accordance with the specifications provided by the
manufacturer of the product used in each particular case.
12. Because of its size and complexity, it is not appropriate or suitable to install a fixed
suppression system in the machine room. Nonetheless, given its multitude of
potential ignition sources and its relatively high fire load, it is imperative to provide
some effective means of secondary fire fighting capability in the machine room.
Therefore, a fixed foam tank of minimum size 1 000 litres and foam applicator /
generator, must be provided on the left and right sides of each dragline, near to an
entrance leading into the machine room, so that any fire occurring in the machine
room can be fought simultaneously from two sides. These tanks may operate on the
stored pressure principle, for which purpose an associated nitrogen or similar
cylinder, of adequate capacity, must be provided and maintained at the foam tank.
On each side, the hose(s) provided must be of adequate length to reach all
parts of the machine house, plus 10 m. Providing 2 x 30 m hoses on each
side is likely to suffice.
On each side, at the foam tank, provide clearly worded instructions describing
the use and application of the system.
These same tanks may serve alternately as the foam supply source for the
fixed, manually actuated foam-based fire suppression system installed in the
propel room on that respective side of the dragline. See 7 above.
13. Where a fixed total flooding gaseous fire suppression system is installed, e.g. at the
control rooms and MV rooms, every effort must be made to keep the protected zone
airtight, as fixed total flooding gaseous fire suppression systems rely upon the
principle of oxygen deprivation to asphyxiate the fire.
To this end, cable penetration and other apertures must be sealed, doors must be
fitted with self-closing mechanisms and kept in the closed position at all times,
ventilation louvres and opening windows are not permitted, and any ventilating fan or
air-conditioner must be interlinked with the fire detection system, which must trip
power to such fan or air-conditioner and cause it to cease operating simultaneously
with the discharge of suppressant gas in the protected zone. This shall not apply to
any recirculating fan or air-conditioner such as a split unit air-conditioner.
14. Where foam systems are installed, containment is not required, and there is therefore
no requirement for apertures to be sealed or doors to be kept closed.
15. Wherever a fixed fire suppression system is provided, irrespective of the suppression
medium, an activation button or break-glass panel must be provided in close
proximity to the protected area, to allow the system to be discharged manually should
the automatic activation mechanism have failed to respond for whatever reason.
Located outside the protected zone. Location of such button or panel within
the protected zone may render it inaccessible once a fire has started, or may
place person’s lives in danger if they attempt to activate it after a fire has
broken out.
16. 9 kg DCP or 5 kg CO2 hand-held fire extinguishers must be provided at the following
positions in the quantities indicated.
All extinguishers should be mounted at a bracket height of 1.2 metres above floor
elevation. Where an extinguisher position is clearly visible, demarcation with the
relevant symbolic signage is adequate. Where an extinguisher is in an obscured
position, it may be necessary to add directional signage to the symbolic sign.
In general, DCP fire extinguishers should be used. However, in areas where sensitive
electronic equipment is installed, for example in control rooms and PLC rooms, CO2
extinguishers are preferable, since the use of DCP on such equipment may damage it
to the extent that it may need to be replaced.
Extinguishers must always be mounted outside the area which they serve, to ensure
that they remain readily accessible even after a fire has broken out.
Maintenance
Requirements
1. A flashback arrestor must be provided both at the torch and at the cylinder gauges,
both on the oxygen and on the acetylene hoses.
2. Flashback arrestors to be used must be of the newer “in-line” type, and not of the
older “grenade” type.
3. If hoses are to be secured together in pairs, they must not be cable tied or wired
together. Only the approved metal clip is acceptable, since this allows paired hoses to
be ripped apart if a fire occurs on the hoses, thus separating the oxygen from the
acetylene.
4. Only the approved “crimp-on” type clamp is acceptable for securing oxygen or
acetylene hoses to their metal fittings, or for joining hoses. Jubilee clamps, wire, etc.
are all unacceptable.
5. Only the approved ridged hoses are to be used for oxygen and acetylene. The older
smooth type of hoses is no longer to be used.
6. All compressed gas cylinders are to be fitted with guards to protect their valves.
7. All mobile cutting / welding torch trolleys are to be fitted with a DCP fire extinguisher
of minimum capacity 2.5 kg. On fixed stationary cutting / welding torch sets (e.g. in a
workshop), a 9 kg hand-held DCP fire extinguisher is to be provided for each cutting /
welding torch set.
9. Both oxygen and acetylene cylinders must be secured in the upright position by
means of clamps or chains, both when stored, and when in use.
10. A suitable gauge, as is available from the oxy-acetylene cutting / welding torch
equipment manufacturer, is to be provided on both the oxygen and acetylene cylinder
in each cutting / welding torch set. These should be replaced or repaired if defective.
No cutting / welding equipment may be used if the gauges are defective.
12. When hot work is to be performed at any position other than in a workshop, the
operator must be in possession of a valid and current hot work permit, authorised by
the responsible engineer or such competent person as he may appoint to issue such
hot work permits.
13. After use, the valves on the cylinders are to be closed, and the hoses purged. It is
unacceptable simply to close the gas supply to the torch.
14. On all oxy-acetylene cutting equipment, the valves on both compressed gas cylinders
must be fitted with a key or other arrangement, which shall allow the key to be
removed, or the valves to be otherwise secured by the trained person to whom the
equipment has been issued, so as to avoid tampering with the equipment by other
persons. To that end, such key or other measure must be removed and kept by the
person responsible for the equipment when such person is not in attendance at the
said equipment.
15. Whenever hot work has been performed in any location other than in a workshop, a
fire watch must be kept for at least 30 minutes after cessation of the cutting / welding
torch operations.
16. All cutting / welding torch sets are to be inspected on a monthly basis by the
responsible engineer, or such other competent person as such engineer may have
appointed to be responsible for cutting torch equipment in his section. The results of
such inspections shall be logged in a register kept for this purpose.
17. As part of the monthly inspection, the hoses belonging to all cutting / welding torch
sets must be inspected for damage and to ascertain whether they are perished or
remain serviceable. Partially damaged or perished hoses must be cut back to a
sound position and then re-affixed to the equipment. Hoses which are extensively
damaged or perished, should be replaced altogether.
Requirements
1. Gas cylinder stores are to be sited no closer than 5 metres from any other building, or
if attached or adjoining a building, the interleading wall must be 2-hour fire rated (e.g.
225 mm - double brick thickness) and must be unbreached.
3. All cylinders to be stored upright and chained or otherwise secured in that position.
4. Cylinders must be separated by type. In the case of gases which constitute a danger
if they react together, types must be structurally or spatially separated. Separate
stores, at least 5 metres apart, would constitute spatial separation. Structural
separation could be achieved by building a 225 mm brick wall or erecting a 5 mm
steel plate between types. Such separating wall must extend at least 30 cm higher
than the tallest cylinder so separated. Note that the requirement for spatial or
structural separation by type does not apply if less than 4 cylinders of each type are
stored.
6. Compressed gas cylinder stores must have a roof to protect the cylinders from the
elements. Consistent with Requirement 2 above, roof material must be incombustible,
e.g. IBR sheeting or similar.
7. To prevent unauthorised access, the store must be enclosed and must have lockable
gates.
8. The walls on at least two sides of a compressed gas cylinder store must be of welded
mesh, expanded metal, diamond mesh, or similar, to allow good ventilation of the
store and to dissipate any gas which may leak, so as to obviate a dangerous build-up
of gas in the store.
9. If the total number of stored full compressed gas cylinders, of whatever type, in a
store is greater than 12, or if more than 12 compressed gas cylinders of any one type,
are stored in a compressed gas cylinder store, such store must be provided with
overhead sprinkler protection. Refer to Standard G2 regarding manual sprinkler
systems which are the norm for compressed gas cylinder stores, or to Standard G3
regarding automatic sprinkler systems which would also be acceptable as an
alternative at a compressed gas cylinder store.
10. Provide at least 2 x 9 kg DCP hand-held fire extinguishers outside the compressed
gas cylinder store. These should be positioned between 5 and 15 metres away from
the store, to ensure that they are readily accessible even after the outbreak of fire.
Their position should be clearly demarcated using the appropriate symbolic and
directional signage.
11. Symbolic and informational signage must be posted up to the walls of the store, inter
alia, prohibiting smoking and naked flames, and demarcating the cylinder stores
according to type.
12. Hazardous data sheets are to be provided for all gas types stored.
Requirements
1. Fire escape routes from all office buildings must adhere to the “45 metre rule” as
prescribed by SABS 0400 - 1990, the National Building Regulations. This dictates
that within 15 metres of travel from any point in the building, a person seeking to
escape must have the option of choosing between two alternative escape routes.
After this point, such person must be able to access fresh air unhindered within a
further 30 metres of travel.
2. Passive point heat and smoke detector heads must be installed in each room of any
single storey office complex having a total floor area of more than 1000m2. Detectors
must be affixed to the roof or ceiling. A choice between smoke and heat detector
heads must be made according to the prescriptions of SABS 0139. Inter alia, this
dictates that heat detectors alone (i.e. no smoke detectors, should be deployed in a
kitchen. At least two heads must be provided per room / zone to ensure that an alarm
will still be raised even if one of the heads is defective. For offices and other areas
where SABS 0139 does not prescribe the detector type, an approximate 50/50 split is
to be adopted between smoke and heat detector heads.
3. Passive point detector heads must report to a centralised electronic fire control panel,
located at a frequently occupied position in the building (e.g. reception) from whence
a local audible and visible alarm will be raised.
5. To make access to fire fighting equipment and escape doors possible under all
circumstances, a clearance area of 1.2 metres x 1.2 metres must be demarcated on
the floor and must be maintained in front of all fire fighting equipment and emergency
escape doors. This will include inter alia mounted fire extinguishers, 25 mm fire
hosereels, 65 mm fire hydrants and fire equipment storage boxes.
6. Provide manual call points (break-glass panels) at strategic positions throughout the
building. Inter alia, break-glass panels must be provided at each main entrance to the
building. These should be connected to the centralised main electronic fire control
panel contemplated in the previous requirements. The purpose of such manual call
points shall be to raise an alarm, if a fire is detected before the automatic fire
detection system has responded, or if the automatic fire detection system it defective.
7. Hand-held fire extinguishers are to be provided and deployed in accordance with the
requirements of Standard G28.
8. Firewalls, where provided, are to have a 60 minute fire rating and must extend up to
roof height, i.e. extend through the ceiling where necessary.
9. All fire doors, if any, must open outwards in the direction of egress and are to be a
minimum of 810 mm wide.
10. Where emergency escape doors are provided which will normally be kept in the
closed / locked position for security reasons, these must be provided with an
internally positioned opening mechanism such as a Redlam bolt or a panic bar which
will allow the door to be opened from the inside unassisted by any person on the
outside of the building. An emergency door may not be locked from the outside and
persons seeking to escape must be able to use the door unhindered and unaided.
Note that it is not acceptable to use a conventional door as an emergency escape
door if the keys are kept by a key holder, on a hook, or in a break-glass panel located
near the door. All emergency escape doors must be suitably demarcated as such
using the approved symbolic and directional signage.
11. Where the escape route to an emergency escape door is circuitous or confusing,
symbolic signage must be erected at each change in direction, to ensure that persons
are able to escape easily, even in difficult conditions.
12. All escape routes must discharge directly to the outside of the building to a safe area
which is adequately lit at night.
13. An emergency evacuation assembly area must be designated in a safe area remote
from the building.
14. Any building of more than 250 m² floor area must be provided with a single 30 metre
fire hosereel for every 500 m² or part thereof of floor area and must be so positioned
as to ensure that the hose will reach any point of the area protected. Refer to
Standard G31 for 25 mm fire hosereel requirements.
15. Single storey office buildings must be so designed and constructed as to ensure
structural fire stability of at least 30 minutes duration, to ensure that persons have
adequate time to evacuate. Structural fire stability of the building must be of no less
than 30 minutes.
Requirements
1. Fire escape routes from all office buildings must adhere to the “45 metre rule” as
prescribed by SABS 0400 - 1990, the National Building Regulations. This dictates
that within 15 metres of travel from any point in the building, a person seeking to
escape must have the option of choosing between two alternative escape routes.
After this point, such person must be able to access fresh air unhindered within a
further 30 metres of travel.
2. Passive point heat and smoke detector heads must be installed in each room of the
office complex, affixed to the roof or ceiling. A choice between smoke and heat
detector heads must be made according to the prescriptions of SABS 0139. Inter alia,
this dictates that heat detectors alone (i.e. no smoke detectors, should be deployed in
a kitchen. At least two heads must be provided per room / zone to ensure that an
alarm will still be raised even if one of the heads is defective. For offices and other
areas where SABS 0139 does not prescribe the detector type, an approximate 50/50
split is to be adopted between smoke and heat detector heads.
3. Passive point detector heads must report to a centralised electronic fire control panel,
located at a frequently occupied position in the building (e.g. reception) from whence
a local audible and visible alarm will be raised.
5. To make access to fire fighting equipment and escape doors possible under all
circumstances, a clearance area of 1.2 metres x 1.2 metres must be demarcated on
the floor and must be maintained in front of all fire fighting equipment and emergency
escape doors. This will include inter alia mounted fire extinguishers, 25 mm fire
hosereels, 65 mm fire hydrants and fire equipment storage boxes.
6. Provide manual call points (break-glass panels) at strategic positions throughout the
building. Inter alia, break-glass panels must be provided at each main entrance to the
building. These should be connected to the centralised main electronic fire control
panel contemplated in the previous requirement. The purpose of such manual call
points shall be to raise an alarm, if a fire is detected before the automatic fire
detection system has responded, or if the automatic fire detection system it defective.
7. Hand-held fire extinguishers are to be provided and deployed in accordance with the
requirements of Standard G28.
8. Firewalls, where provided, are to have a 60 minute fire rating and must extend up to
roof height, i.e. extend through the ceiling where necessary.
9. All fire doors, if any, must open outwards in the direction of egress and are to be a
minimum of 810 mm wide.
10. Where emergency escape doors are provided which will normally be kept in the
closed / locked position for security reasons, these must be provided with an
internally positioned opening mechanism such as a Redlam bolt or a panic bar which
will allow the door to be opened from the inside unassisted by any person on the
outside of the building. An emergency door may not be locked from the outside and
persons seeking to escape must be able to use the door unhindered and unaided.
Note that it is not acceptable to use a conventional door as an emergency escape
door if the keys are kept by a key holder, on a hook, or in a break-glass panel located
near the door. All emergency escape doors must be suitably demarcated as such
using the approved symbolic and directional signage.
11. Where the escape route to an emergency escape door is circuitous or confusing,
symbolic signage must be erected at each change in direction, to ensure that persons
are able to escape easily, even in difficult conditions.
12. All escape routes must discharge directly to the outside of the building to a safe area
which is adequately lit at night.
13. An emergency evacuation assembly area must be designated in a safe area remote
from the building.
15. Any building of more than 250 m² floor area must be provided with a single 30 metre
fire hosereel for every 500 m² or part thereof of floor area and must be so positioned
as to ensure that the hose will reach any point of the area protected. Refer to
Standard G31 for 25 mm fire hosereel requirements.
16. For office buildings in excess of three storeys in height, a 65 mm fire hydrant point
must be provided on each level. Usually, it would be acceptable to position this in the
centre of each floor, but where the footprint of the building exceeds 1 000 m², one
hydrant must be provided for every 1 000 m² or part thereof on each level. Refer to
Standard G29.
18. Where electrical cables are routed vertically between levels, all cable penetration
apertures between floors must be adequately fire stopped with an approved material.
See Standard G36.
19. Where fire stopping has been provided in accordance with the previous requirement,
cables passing through such fire stopping must be intumescent coated for a minimum
distance of 1 metre on either side of the fire stopping, over their entire circumference.
20. Where cables are vertically routed in a service shaft, the abovementioned
requirements for fire stopping and intumescent coating are no longer relevant.
However, in such case, a 2 metre firebreak must be constituted on all cable racks on
every second level. Such firebreak may be achieved by intumescent coating all
cables in the group over their entire circumference with intumescent paint for the full
required distance of 2 vertical metres. Also see Standard G36 in this regard.
Rationale
One of the most disastrous consequences of a fire is the loss of vital records, be they
contracts, plans, specifications, computer tapes or orders to name a few. Records are almost
always combustible and hence there is always a need to protect them protect against fire.
The most effective way of limiting the possibility of loosing records is to make duplicates
which are stored separately. This Standard will however only concern itself with the
protection of documents in archives.
Requirements
2. Where provided, gaseous fire suppression systems must be provided with a means of
turning them to manual actuation mode, and this mode must be selected, whenever
persons are in attendance. When in manual actuation mode, it must be possible to
activate the system by means of one or more break-glass panels provided at suitable
positions outside the archive. At least one such break-glass unit must be provided
outside the main entrance door leading to the archive.
3. A passive point or aspirated automatic fire detection system must be installed in all
archives. Refer to Standard G9 for further details.
4. Where a fixed gaseous fire suppression system is installed, this should be capable of
automatic actuation (for use when the archive is unoccupied) and this automatic
actuation should be by means of the abovementioned automatic fire detection
system.
6. Signage must be erected at all archives prohibiting smoking and naked lights.
FPA Bulletin 23
Standard G7 - Fixed gaseous fire suppression systems - room flooding
Standard G8 - Fixed gaseous fire suppression systems - in cabinet
Standard G9 - Passive versus aspirated detection systems
Standard G28 - Hand-held fire extinguishers
Standard G47 - Definition of criticality
Rationale
Most vehicles can be lost to fire or other catastrophic event without significantly affecting
production. This is because there is good duplicity afforded by the multiple vehicles in
service. However, where a significant number of vehicles are likely to be lost simultaneously,
business interruption could become significant.
One of the most common locations where several vehicles can be lost to fire simultaneously
is in workshops, because here the vehicles are parked close together, and fire spread
between the vehicles is likely to be rapid.
Manual fire fighting in such case has been proven historically to be ineffective given the high
energy levels present (rubber tyres and fuel tanks) and the speed with which vehicles burn
and fire propagates between vehicles. Resultantly, reliance in vehicle workshops, particularly
large ones, upon hand-held fire fighting devices, is not adequate. Moreover, structural sub-
division of the risk is not practicable, since workshops need to be large open areas so that
work can proceed smoothly.
Requirements
1. In vehicle workshops covering a floor area in excess of 250 m², a 30 metre long, 25
mm fire hosereel must be provided for every 500 m² or part thereof of floor area.
These hosereels must be positioned so as to ensure that the hose will reach any
point in the area protected by the hosereel. See Standard G31 regarding 25 mm fire
hosereel requirements.
2. 65 mm fire hydrants are not required inside any workshop. However, there must be
ready access to at least 2 x 65 mm “area hydrants”, i.e. hydrants located outside the
workshop.
It would be usual to provide a hydrant on either side of the workshop, so that a fire
occurring in the workshop can be attacked from two sides. Also, depending on wind
direction, it may not be possible to fight fire from a particular direction on a particular
day. These hydrants should not be positioned within 10 metres of the workshop
structure, so that they will remain accessible even after the outbreak of fire. However,
neither should they be positioned further than 30 metres from the workshop structure.
Pressure flow and other requirements pertaining to fire hydrants are contained in
Standard G29.
3. Either a fire hose box containing at least 3 x 65 mm flat lay fire hoses and a single 65
mm nozzle must be provided at each hydrant point contemplated in the preceding
requirement, or there must be ready access on site to a cache of at least 9 x 65 mm
flat lay fire hoses, and 3 x 65 mm nozzles.
4. At least one 50 kg foam trolley must be provided. The trolley will satisfy the need for
advanced primary fire fighting and justifies the omission of a sprinkler or fixed foam
system. Also see Standard G49.
5. Combustible materials are not to be used in the construction of workshops, save that
wooden beams in the roof, and “Marley” tiles shall be permissible.
6. If translucent sheets are set in the cladding of the workshop structure, these should
be positioned in horizontal rows, rather than vertical columns, since fire spreads
vertically most easily, and vertical translucent inserts will assist in the more rapid
propagation of fire.
7. Fire escape routes from all workshops must adhere to the “45 metre rule” as
prescribed by SABS 0400 - 1990, the National Building Regulations.
This dictates that within 15 metres of travel from any point in a building, a person
seeking to escape must have the option of choosing between two alternative escape
routes. After this point, such person must be able to access fresh air unhindered
within a further 30 metres of travel.
8. To make access to fire fighting equipment and escape doors possible under all
circumstances, a clearance area of 1.2 metres x 1.2 metres must be demarcated on
the floor and must be maintained in front of all fire fighting equipment and emergency
escape doors. This will include inter alia mounted fire extinguishers, 25 mm fire
hosereels, 65 mm fire hydrants and fire equipment storage boxes.
9. All emergency escape routes, and doors (where applicable), are to be clearly
demarcated using the correct symbolic and directional signage.
11. Although it is not an absolute requirement that an automatic fire detection and alarm
system be provided in a workshop, some means must be provided for raising an
alarm in cases of fire and other emergency. This may be manually actuated, for
example, a siren.
12. All rubber-lined equipment in this structure must be demarcated as such, to warn
persons intending to conduct hot work of the increased fire risk, so that they may
know to take additional precautions.
Requirements
1. All piped oxygen and acetylene supplies, if any, are to be suitably colour-coded.
4. Translucent welding screens are to be provided around all positions in which arc
welding is regularly and routinely performed, to protect workers in other parts of the
workshop from being exposed to the light emitted from the arc welding operations.
7. In other surface workshops covering a floor area in excess of 250 m², a 30 metre
long, 25 mm fire hosereel must be provided for every 500 m² or part thereof of floor
area. These hosereels must be positioned so as to ensure that the hose will reach
any point in the area protected by the hosereel. See Standard G31 regarding 25 mm
fire hosereel requirements.
8. 65 mm fire hydrants are not required inside any workshop. However, there must be
ready access to at least 2 x 65 mm “area hydrants”, i.e. hydrants located outside the
workshop. It would be usual to provide a hydrant on either side of the workshop, so
that a fire occurring in the workshop can be attacked from two sides. Also, depending
on wind direction, it may not be possible to fight fire from a particular direction on a
particular day.
These hydrants should not be positioned within 10 metres of the workshop structure,
so that they will remain accessible even after the outbreak of fire. However, neither
should they be positioned further than 30 metres from the workshop structure.
Pressure flow and other requirements pertaining to fire hydrants are contained in
Standard G29.
9. Either a fire hose box containing at least 3 x 65 mm flat lay fire hoses and a single 65
mm nozzle must be provided at each hydrant point contemplated in the preceding
requirement, or there must be ready access on site to a cache of at least 9 x 65 mm
flat lay fire hoses, and 3 x 65 mm nozzles.
11. If translucent sheets are set in the cladding of the workshop structure, these should
be positioned in horizontal rows, rather than vertical columns, since fire spreads
vertically most easily, and vertical translucent inserts will assist in the more rapid
propagation of fire.
12. Fire escape routes from all workshops must adhere to the “45 metre rule” as
prescribed by SABS 0400 - 1990, the National Building Regulations.
This dictates that within 15 metres of travel from any point in a building, a person
seeking to escape must have the option of choosing between two alternative escape
routes. After this point, such person must be able to access fresh air unhindered
within a further 30 metres of travel.
13. To make access to fire fighting equipment and escape doors possible under all
circumstances, a clearance area of 1.2 metres x 1.2 metres must be demarcated on
the floor and must be maintained in front of all fire fighting equipment and emergency
escape doors. This will include inter alia mounted fire extinguishers, 25 mm fire
hosereels, 65 mm fire hydrants and fire equipment storage boxes.
14. All emergency escape routes, and doors (where applicable), are to be clearly
demarcated using the correct symbolic and directional signage.
15. Workshop buildings must be so designed and constructed as to ensure structural fire
stability of at least 30 minutes duration, to ensure that persons have adequate time to
evacuate.
16. Although it is not an absolute requirement that an automatic fire detection and alarm
system be provided in a workshop, some means must be provided for raising an
alarm in cases of fire and other emergency. This may be manually actuated, for
example, a siren. Alternatively, an electrically powered alarm is acceptable. In such
case, break-glass panels or pushbuttons must be provided in strategic and easily
accessible, well demarcated positions, throughout the workshop. As a minimum, such
activation mechanisms must be provided at all main entrances to a workshop.
17. All rubber-lined equipment in this structure must be demarcated as such, to warn
persons intending to conduct hot work of the increased fire risk, so that they may
know to take additional precautions.
Definition
A surface substation or MCC shall be deemed “critical” if safety of persons depends upon the
power distributed through that substation or MCC, or if power outage at such substation or
MCC has the potential to interrupt operations in an extensive part of the workings and would
result in significant loss of production.
Application
The contents of this Standard shall be binding with respect to new installations built after 1
January 2007. Any necessary deviation from the Standard must be approved before
implementation thereof by the Fire Standards Committee and written dispensation granted.
Regarding existing substations and MCC rooms, all practicable modifications must be made
to bring them as far as possible in line with the requirements of this Standard.
Requirements
The recommended substation structure will have a concrete floor, double brick
thickness brick walls, and a flat reinforced concrete roof. If a pitched roof is required,
then the roof panels must be incombustible (such as corrugated iron or IBR sheeting),
and the roofing beams should be of steel. A fire resistant ceiling should be provided in
such a case. Doors are to be steel set in steel frames, or SABS 2-hour fire rated.
2. Where the various sections of a substation building, for example, the MV room, the
LT room, the PLC room, the cable basement / room, etc., are structurally separated
from each other, separating walls must have a minimum fire resistance of 2-hours. A
225 mm brick wall is deemed to offer such resistance. All separating walls shall be
“perfect party walls”, i.e. they are to reach from true floor elevation all the way up to
roof height, passing through any false floor or ceiling which may exist. See Standard
G35 regarding “perfect party walls”. Any interleading doors set in such separating
walls shall be SABS-rated as having a 2 hour resistance to fire, and shall be self-
closing.
box’ located at the wall. Such intumescent coating shall be applied to the entire
circumference of each cable to such thickness as is stipulated by the manufacturer of
the particular intumescent product chosen, as being adequate to provide an SABS
rated fire resistance of at least 2 hours. See Standard G36 regarding intumescent
coating.
5. As far as possible, all power cables used must be of the “red stripe” flame retardant
type. Where possible, all other cables should also be flame retardant. See Standard
G1.
Windows are permissible in the outer walls of all substations, provided that these do
not overlook oil-filled transformers or oil-filled power factor correction equipment
which may be installed alongside the substation.
In substation rooms where a fixed gaseous total flooding automatic fire suppression
system is installed, windows must be closed at all times or must preferably be non-
opening to ensure containment of the suppressant gas after discharge.
11. A passive point fire detection system must be provided in all critical substations and
MCCs. Each room should be treated as a separate zone on the electronic control
panel to which the detector heads report. In each room, an approximate 50/50 split of
passive smoke and heat detection heads should be installed. See Standard G9 for
details of passive fire detection systems.
12. Coupled to the abovementioned electronic fire control panel must be at least one
manual call point (break-glass panel), to enable an alarm to be raised manually if, for
whatever reason, the automatic detection system has failed to detect fire, or if the fire
is observed before the detection system has had time to trigger.
13. At all new installations, oil-filled switchgear is to be avoided. Only SF6 or vacuum-type
switchgear is to be used. At existing facilities whose remaining life is assessed as
being 5 years or more, consideration should be given to converting to SF6 or vacuum-
type switchgear.
14. In all critical substations where oil-filled switchgear is installed, a fixed total flooding
gaseous fire suppression system MUST be installed in the MV rooms and in all cable
rooms and basements associated with MV rooms.
A fixed total flooding gaseous fire suppression system MAY be installed in LT rooms
and PLCs. The presence of oil filled equipment is a strong indicator for this additional
protection. See Standard G7 for details on fixed total-flooding gaseous fire
suppression systems. Note in particular, the requirements for manual and automatic
actuation.
Where there is no ignition source and / or fire loading in the room other than the
electrical panels, an in-cabinet fixed gaseous fire suppression system may be an
acceptable alternative to room flooding. See Standard G8 for details on fixed in-
cabinet gaseous fire suppression systems. Note in particular, the requirements for
manual and automatic actuation.
15. Whether a fixed gaseous fire suppression system is installed or not, any ventilation
fans and air-conditioners provided in substation rooms are to be interconnected with
the fire detection system so that these will be tripped out and will cease to operate in
response to any fire detected by the automatic detection system.
16. Cable trenches passing beneath a substation must be fire stopped wherever cables
pass from one substation room to another. Such fire stopping can be achieved with
‘sand boxes’ at the separating wall. At all fire stoppings, the cables must be
intumescent coated for a distances of 1 metre on either side of such fire stopping. In
this regard, see Requirements 3 and 4 above.
17. See Standard G21 regarding transformer installations associated with substations.
18. If a fire occurring at a substation or transformer installation is not contained within its
developmental stages, it will evolve into a fully involved structural fire and will require
intervention by fire teams using secondary fire fighting measures such as large bore
hydrants, hoses and foam applicators once the power source feeding the installation
has been isolated. Each transformer installation and / or substation complex must be
located within the 90 metre radius of at least 2 x 65 mm hydrant points. Ideally, these
hydrant points will be located on opposite sides of the substation or transformer bank,
so that a fire can be fought from two sides, and access will remain possible
irrespective of wind direction. For requirements pertaining to fire hydrants and
equipment on surface, refer to Standard G29.
19. Either at each hydrant point, provide a fire equipment box containing at least 3 x 65
mm flat lay fire hoses and a single 65 mm nozzle, or…
Definition
“Other” substations shall be deemed to mean all surface substations and MCCs not
classified as “critical”, as contemplated in Standard G18.
Application
The contents of this Standard shall be binding with respect to new installations built after 1
January 2007. Any necessary deviation from the Standard must be approved before
implementation thereof by the Fire Standards Committee and written dispensation granted.
Regarding existing substations and MCC rooms, all practicable modifications must be made
to bring them as far as possible in line with the requirements of this Standard.
Requirements
The recommended substation structure will have a concrete floor, double brick
thickness brick walls, and a flat reinforced concrete roof. If a pitched roof is required,
then the roof panels must be incombustible (such as corrugated iron or IBR sheeting),
and the roofing beams should be of steel. A fire resistant ceiling should be provided in
such a case. Doors are to be steel set in steel frames, or SABS 2-hour fire rated.
Converted shipping containers and similar are acceptable structures in which “other”
substations and MCCs may be located, provided that the roof and walls of such
containers adhere to the requirement of incombustibility. Therefore, they should have
no insulation material in the walls. This specifically excludes any types of styrene or
urethane. Flooring, which is often made of timber will be acceptable.
2. Where the various sections of a substation building, for example, the MV room, the
LT room, the PLC room, the cable basement / room, etc., are structurally separated
from each other, separating walls must have a minimum fire resistance of 2-hours. A
225 mm brick wall is deemed to offer such resistance. All separating walls shall be
“perfect party walls”, i.e. they are to reach from true floor elevation all the way up to
roof height, passing through any false floor or ceiling which may exist. See Standard
G35 regarding “perfect party walls”. Any interleading doors set in such separating
walls shall be SABS-rated as having a 2 hour resistance to fire, and shall be self-
closing.
5. As far as possible, all power cables used must be of the “red stripe” flame retardant
type. Where possible, all other cables should also be flame retardant. See Standard
G1.
Windows are permissible in the outer walls of all substations, provided that these do
not overlook oil-filled transformers or oil-filled power factor correction equipment
which may be installed alongside the substation.
In substation rooms where a fixed gaseous total flooding automatic fire suppression
system is installed, windows must be closed at all times or must preferably be non-
opening to ensure containment of the suppressant gas after discharge.
11. A passive point fire detection system may be provided in these “other” substations
and MCCs. Where a substation and / or MCC is remotely located, in an area where
occupancy is rare, a passive point fire detection system becomes an absolute
requirement.
Each room should be treated as a separate zone on the electronic control panel to
which the detector heads report.
12. Coupled to the abovementioned electronic fire control panel, if installed, must be at
least one manual call point (break-glass panel), to enable an alarm to be raised
manually if, for whatever reason, the automatic detection system has failed to detect
fire, or if the fire is observed before the detection system has had time to trigger.
13. At all new installations, oil-filled switchgear is to be avoided. Only SF6 or vacuum-type
switchgear is to be used. At existing facilities whose remaining life is assessed as
being 5 years or more, consideration should be given to converting to SF6 or vacuum-
type switchgear.
14. In all “other” substations where oil-filled switchgear is installed, a fixed total flooding
gaseous fire suppression system shall be installed the MV rooms, and in all cable
rooms and basements associated with MV rooms.
A fixed total flooding gaseous fire suppression system shall be installed in LT rooms
and PLCs. The presence of oil filled equipment is a strong indicator for this additional
protection. See Standard G7 for details on fixed total-flooding gaseous fire
suppression systems. Note in particular, the requirements for manual and automatic
actuation.
Where there is no ignition source and / or fire loading in the room other than the
electrical panels, an in-cabinet fixed gaseous fire suppression system may be an
acceptable alternative to room flooding. See Standard G8 for details on fixed in-
cabinet gaseous fire suppression systems. Note in particular, the requirements for
manual and automatic actuation.
15. Whether a fixed gaseous fire suppression system is installed or not, any ventilation
fans and air-conditioners provided in substation rooms must be linked with the fire
detection system, so that these fans and air conditioners will be tripped out and will
cease to operate in response to any fire detected by the automatic detection system.
16. Cable trenches passing beneath a substation must be fire stopped wherever cables
pass from one substation room to another. Such fire stopping can be achieved with
‘sand boxes’ at the separating wall. At all fire stoppings, the cables must be
intumescent coated for a distances of 1 metre on either side of such fire stopping. In
this regard, see Requirements 3 and 4 above.
17. See Standard G21 regarding transformer installations associated with substations.
18. If a fire occurring at a substation or transformer installation is not contained within its
developmental stages, it will evolve into a fully involved structural fire and will require
intervention by fire teams using secondary fire fighting measures such as large bore
hydrants, hoses and foam applicators once the power source feeding the installation
has been isolated. Each transformer installation and / or substation complex must be
located within the 90 metre radius of at least 2 x 65 mm hydrant points. Ideally, these
hydrant points will be located on opposite sides of the substation or transformer bank,
so that a fire can be fought from two sides, and access will remain possible
irrespective of wind direction. For requirements pertaining to fire hydrants and
equipment on surface, refer to Standard G29.
19. Either at each hydrant point, provide a fire equipment box containing at least 3 x 65
mm flat lay fire hoses and a single 65 mm nozzle, or…
Requirements
1. Electrical cables must be intumescent coated for at least 1 metre at the entry / exit
points. Alternatively, cables may be buried in a sand-filled trench. Such sand filling to
extend for at least 1 metre and preferably 2 metres.
Application
This standard applies to all transformers located on surface other than those contained in MV
switching yards. See Standard G22 regarding transformers located in MV switching yards.
NB. Transformer separating walls need not be retrofitted in transformer installations built
before 2000.
Requirements
NB.: The transformer bays must be adequate not to impair transformer cooling, that
is, they must not de-rate any transformer located therein.
2. In the case of transformers located in transformer bays which are spatially well
separated from the associated substation, transformers must be separated from each
other by means of a 225 mm thick brick wall, buttressed on the free end, built
between each adjoining pair of transformers. Such wall must extend to a height at
least 90 cm higher than the highest point on the highest transformer so separated
(usually the oil conservator).
4. Where three or less transformers are grouped together, 1 x 9 kg hand-held DCP fire
extinguisher must be provided per transformer in a central position. Where four or
more transformers are grouped together, 4 x 9 kg hand-held DCP fire extinguishers
must be provided in a central position.
The required number of fire extinguishers should be divided between two positions
each located between 5 and 15 metres from the transformer bank, to make them
easily accessible even after the outbreak of fire. Where one or both such positions
are located around a corner out of direct line of site of the transformers, it is
acceptable to reduce the minimum distance to less than 5 metres, if access to the
extinguishers would be safe and possible even after the outbreak of fire.
5. Some means such as lockable gates must be provided across the front of transformer
bays to ensure that access is not readily possible by unauthorised persons.
7. Each transformer bay must be individually bunded. See Standard G33 regarding the
requirements for bunding.
8. If transformers are installed within a building, then a passive point fire detection
system must be provided in the area in which the transformers are installed.
10. If a fire occurring at a substation or transformer installation is not contained within its
developmental stages, it will evolve into a fully involved structural fire and will require
intervention by fire teams using secondary fire fighting measures such as large bore
hydrants, hoses and foam applicators once the power source feeding the installation
has been isolated. Each transformer installation and / or substation complex must be
located within the 90 metre radius of at least 2 x 65 mm hydrant points. Ideally, these
hydrant points will be located on opposite sides of the substation or transformer bank,
so that a fire can be fought from two sides, and access will remain possible
irrespective of wind direction. For requirements pertaining to fire hydrants and
equipment on surface, refer to Standard G29.
11. At each hydrant point, provide a fire equipment box containing at least 3 x 65 mm flat
lay fire hoses and a single 65 mm nozzle,
Or, at a central easily accessible position on surface, provide a central cache of fire
fighting equipment including at least 9 x 65 mm flat lay fire hoses and 3 x 65 mm
nozzles.
Application
The contents of this Standard shall be binding with respect to new installations built after 1
January 2007. Any necessary deviation from the Standard must be approved before
implementation thereof by the Fire Standards Committee and written dispensation granted.
Regarding existing main MV switch and transformer yards on surface, all practicable
modifications must be made to bring them as far as possible in line with the requirements of
this Standard.
Requirements
1. The yard must be securely fenced with locked gates to prevent unauthorised access.
3. Robust brick separating walls must be constructed between all oil-filled transformers
and MV switches located next to each other, unless these are separated spatially by
a distance of at least 30 metres. Such walls must be buttressed on their free ends to
ensure their strength, and should not be breached in any position. They may be
constructed of 300 mm reinforced concrete or 225 mm wide brick. Each separating
wall must extend to a height at least 90 cm higher than the highest point on the
highest transformer separated by the wall, usually the oil conservator. NB.
Transformer separating walls need not be retrofitted in transformer installations built
before 2000. Also see Standard G34 regarding fire / separating walls.
Rationale
It is important to protect emergency and standby generators from any event which could
foreseeably interrupt normal power supply, since they are intended to provide back-up in
exactly those circumstances. Therefore, generator installations must be spatially or
structurally well separated from all other facilities, and must have automatic protection
against fire originating in the generator room.
Requirements
Standby and emergency generator installations on surface should comply with any relevant
Anglo American Co. specifications. Notwithstanding anything contained therein, the following
are the minimum requirements necessary to ensure adequate fire protection in relation to
such generator installations.
All interior, interleading walls of the generator room must be 2-hour fire rated
perfect party walls. See Standard G35 regarding the requirements for perfect
party walls.
To ensure adequate ventilation of the generator room, and to allow heat from
the generator to be dissipated, provide an extraction fan or fans of adequate
capacity to ensure sufficient air changes to achieve the heat dissipation.
These may only be mounted in an exterior wall. Ventilation louvres or ducts of
corresponding size must also be provided in the exterior wall of the generator
room.
If the structure has multiple levels, then the roof of the generator room must
be of reinforced concrete.
The generator room door must have a fire resistance rating of at least 2 hours,
and must be self-closing.
The generator room floor, roof, and interior, interleading walls should not be
breached. If an aperture exists, then it must be fire stopped in accordance
with the requirements described in Standard G36.
Rationale
Control rooms have significant potential for business interruption losses, since it is from here
that process control is exercised. Particularly with increased automation and growing reliance
on PLC and SCADA control, this issue is of greater concern than ever before. Conversely,
the phasing out of mimic panel control rooms in favour of more modern PC-based process
control, has made speed with which control rooms can be constructed or substituted much
more rapid than was previously the case.
Another consideration with control rooms is that they are usually constantly occupied, so that
any catastrophe affecting the control room should be rapidly detected by the staff in
attendance, who would then be able to initiate fire fighting efforts.
With the newer PC-based process controls, fire loading and ignition risk in a typical modern
control room is relatively low, especially where the control room is housed in a facility which
is separate from substations, MCCs, etc.
Where control rooms are housed in multi-level complexes, shared with substations and
MCCs, the fire risk to the CR is greatly increased by these external ignition sources and fire
loads. In such cases, perfect structural separation of the CR from the rest of the structure
becomes imperative.
Requirements
1. Control rooms may be protected by means of room flooding or in-cabinet gaseous fire
suppression systems, but these are not an absolute requirement. Refer to Standards
G7 and G8 regarding fixed gaseous fire suppression systems.
2. Where provided, gaseous fire suppression systems must be provided with a means of
turning them to manual actuation mode, and this mode must be selected, whenever
persons are in attendance. When in manual actuation mode, it must be possible to
activate the system by means of one or more break-glass panels provided at suitable
positions outside the control room. At least one such break-glass unit must be
provided outside the main entrance door leading to the control room.
3. A passive point or aspirated automatic fire detection system must be installed in all
control rooms. Refer to Standard G9 for further details.
4. Where a fixed gaseous fire suppression system is installed, this should be capable of
automatic actuation (for use when the control room is unoccupied) and this automatic
actuation should be by means of the abovementioned automatic fire detection
system.
5. Signage must be erected at all control rooms prohibiting smoking and naked lights.
extinguishers should be provided at each control, one inside the main entrance door
and one outside. At control rooms where no fixed gaseous fire suppression system is
installed, a further 2 x 5 kg CO2 fire extinguishers must be provided inside the control
room (total of 4). Such fire extinguishers must be mounted in easily accessible
positions at a height above floor elevation of 1.2 metres. They must be clearly
demarcated by means of the relevant symbolic signage. Refer to Standard G28.
Requirements
A1. Access to IT rooms must be strictly controlled, with only authorised personnel
allowed.
A2. Every cable penetration aperture in any outer wall of an IT room, or cable trench
exiting such facility, shall be fire stopped with an inert material. See Standard G36
regarding fire stopping.
A3. Any electrical or instrumentation cables passing through a fire stopped cable
penetration aperture as contemplated in the previous requirement shall be
intumescent coated for minimum distance of 1 metre on either side of such fire
stopping, using suitable intumescent coating or cables must pass through a ‘sand
box’ located at the wall. Such intumescent coating shall be applied to the entire
circumference of each cable to such thickness as is stipulated by the manufacturer of
the particular intumescent product chosen, as being adequate to provide an SABS
rated fire resistance of at least 2 hours. See Standard G36 regarding intumescent
coating.
A4. Under no circumstances must hand-held DCP fire extinguishers be provided inside,
or in close proximity to an IT room. Instead, at least 2 x 5 kg hand-held CO2 fire
extinguishers should be provided at each room, one inside the main entrance door
and one outside. At control rooms where no fixed gaseous fire suppression system is
installed, a further 2 x 5 kg CO2 fire extinguishers must be provided inside the control
room (total of 4). Such fire extinguishers must be mounted in easily accessible
positions at a height above floor elevation of 1.2 metres. They must be clearly
demarcated by means of the relevant symbolic signage. Refer to Standard G28.
A6. Whether a fixed gaseous fire suppression system is installed or not, any ventilation
fans and air-conditioners provided in IT rooms are to be interconnected with the fire
detection system, if any, so that these will be tripped out and will cease to operate in
response to any fire detected by the automatic detection system.
A9. Where any of the perfect party walls contemplated in the abovementioned paragraph
are breached, possibly to allow for the passage of cables, such apertures must be fire
stopped using an inert material, and any cables passing through the fire stopping
must be intumescent coated over their entire circumference for a distance of at least
1 metre on either side of the fire stopping. See Standard G36 regarding the
requirements for fire stopping and the intumescent coating of cables.
The criticality of IT rooms must be assessed with particular consideration for potential loss of
data and business interruption. Where such facilities are assessed as “critical”, the
following additional requirements shall pertain:
C1. A fixed passive point or aspirated fire detection system must be provided. See
Standard G9 pertaining to such systems.
C2. A fixed total flooding gaseous suppression system must be installed to cover the
entire room or rooms in which the facility is located. This should be capable of manual
actuation by means of break-glass panels and automatic actuation via the automatic
fire detection system contemplated in 1 above. See Standard G7 regarding fixed
gaseous room flooding fire detection systems.
C3. Any under floor cable void, if any, must be treated as a separate zone, both for
detection and suppression purposes.
C4. The fixed automatic room flooding gaseous fire suppression system must be fitted
with a manual override so that the system may be placed in manual actuation mode
when persons are in attendance. Automatic actuation mode should be resumed when
the premises are vacated.
C5. The facility must be tightly sealing with all external doors fitted with automatic closing
mechanisms. The fire extinguishing system must be tested on completion of
installation and a test certificate issued, indicating the deterioration rate of the
extinguishing medium within the confines of the facility.
Requirements
1. 65 mm fire hydrants are to be installed at the rate of one per level in all buildings
exceeding 12 metres in height.
2. In all structures with a footprint exceeding 1000 m², fire hydrants will be installed on
all levels at a rate of one per 1000 m² or part thereof.
4. A minimum of one hand-held fire extinguisher shall be deployed per 2000 m² of floor
area. This number should be increased where there is excessive fire loading or there
is high risk of ignition. Additional fire extinguishers may also be required where an
area is sub-divided, for example, for security reasons or process purposes, or where
densely installed equipment makes access to extinguishers difficult from certain
positions.
Fire extinguishers are to be mounted at a height of 1.2 metres above the floor
or ground elevation in easily accessible positions, clearly demarcated with the
relevant symbolic signage.
5. Fire escape routes from all plant structures must adhere to the “45 metre rule” as
prescribed by SABS 0400 - 1990, the National Building Regulations. This dictates
that within 15 metres of travel from any point in a structure, a person seeking to
escape must have the option of choosing between two alternative escape routes.
After this point, such person must be able to access fresh air unhindered within no
more than a further 30 metres of travel.
6. All escape routes are to be clearly demarcated as such by means of the relevant
symbolic and directional signage, both at the escape doors, and internally, at every
change in direction of an escape route.
In all plant structures with two or more levels, escape must be possible via at least
two stairwells. These stairwells must comply with the following requirements:
9. In addition to the hydrant points contemplated above, which are intended for
secondary fire fighting purposes, the National Building Regulations, SABS 0400 -
1990, requires that 25 mm fixed fire hosereels must be installed at the rate of one per
500 m² of floor area or part thereof, on each level. Fire hosereels must comply with all
requirements as stated in Standard G31.
10. Fire protection of electrical installations located within the structure, if any, is to be in
accordance with the requirements stated in Standards G7 and G8.
11. Some means must be provided on each level of the structure for raising an audible
alarm in cases of fire and other emergency. Where an automatic fire detection system
is installed, this may be by means of one or more break-glass panels provided on the
levels, coupled to the control panel of such detection system. Actuation of the manual
call points will then trigger an alarm in the system.
At least one manual call point (button or break-glass panel) or manually operated
alarm is required per 1000 m² of floor area per level. These should ideally be
positioned close to escape routes / stairwells / main doors and should be clearly
demarcated.
12. Where electrical or instrumentation cables pass vertically from one level to another,
through a fire rated floor (e.g. reinforced concrete), such cable penetration aperture
must be fire stopped using a suitable inert material. Cables must be intumescent
coated for a distance of at least 1 metre on either side of such fire stopping, over their
entire circumference. See Standard G36 regarding the requirements for fire stopping
and intumescent coating.
Where cables pass vertically between levels through a non-fire rated floor (e.g.
Mentis-type grating), or where cables are routed in a service shaft, a 2 metre high
firebreak must be constituted on the cables as a group on every 2nd level. This may
be achieved by coating the cables with an intumescent paint over their entire
circumference for a distance of at least 2 metres. See Standard G36 regarding the
requirements for intumescent coating. Note that no fire stopping is required in such
case.
13. All rubber-lined equipment in this structure must be demarcated as such, to warn
persons intending to conduct hot work of the increased fire risk, so that they may
know to take additional precautions.
Relevant Standards and Codes of Practice
SABS 1128, Part 1 - Fire fighting equipment: Components of underground and above-ground
hydrant systems
SABS 0400 – 1990 - National Building Regulations
Standard G7 - Fixed gaseous fire suppression systems - room flooding
Standard G8 - Fixed gaseous fire suppression systems - in cabinet
Standard G28 - Hand-held fire extinguishers
Standard G31 - 25 mm fire hosereels
Standard G36 - Fire stopping and intumescent coating of cables
Application
Requirements
2. All shelves on which batteries are charged are to be of wood or must be rubber-lined.
4. At least one hand-held fire extinguisher must be provided at the facility. This should
be mounted outside the main entrance door or gate. Either a DCP fire extinguisher or
a CO2 fire extinguisher is suitable. The fire extinguisher should be mounted at a
height of 1.2 metres above floor or ground elevation and should be suitably
demarcated by means of appropriate symbolic and directional signage. See Standard
G28 for further details.
7. All parts of battery charging bays must be declared “no smoking zones”. Signage
must be erected prohibiting smoking and naked lights. Work in battery charging bays
must only be permitted under a hot work permit system, which includes a fire watch
being kept until completion of hot work, as contemplated in Standard G11.
Requirements
3. In offices and areas where there are many female staff members, or disabled
persons, who may find 9kg units difficult to handle, 2 x 4.5kg hand-held DCP units
may be substituted for every 9kg DCP unit. Note that this concession is never
appropriate in an industrial area such as a workshop or plant building, where 9 kg
units are an absolute requirement.
4. In areas where sensitive electronic equipment, foodstuffs, and medicines are present,
5 kg hand-held CO2 fire extinguishers should be substituted in place of the 9kg hand-
held DCP fire extinguishers.
5. Fire extinguishers are to be mounted 1.2 metres above ground or floor level, against
a wall or other suitable support.
6. The relevant symbolic signage indicating the position of each fire extinguisher shall
be posted up. Such signage must comply with SABS 0400 TT29, FPA Bulletin 19,
NFPA 170 & SABS 1186.
8. An area of 1.2 metres x 1.2 metres shall be demarcated on the floor where fire
extinguishers are mounted, and shall be kept clear of obstructions at all times, to
make access to the fire extinguishers possible whenever required.
10. Servicing by an accredited external agency is to be performed on each unit once per
year.
12. Fire extinguishers located inside plant buildings should ideally be mounted within see-
through “Extinguimate” type extinguisher cabinets, to prevent them from deterioration
due to the harsh environment.
13. Fire extinguishers located externally, and which are exposed to the elements should
ideally be mounted within glass or steel extinguisher cabinets, to protect them from
the elements.
14. Fire extinguishers inside buildings which do not constitute harsh environments, such
as office blocks, workshops, substations, stores and similar, do not require cabinets
and may be hung from a wall bracket.
FPA Bulletin 19
NFPA 10 - Standard for Portable Fire Extinguishers
NFPA 170 - Standard for Fire Safety Symbols
SABS 0400 TT29 - National Building Regulations
SABS 1186 - Symbolic Signs
SABS 1475 : Part I - The production of reconditioned fire-fighting equipment: Portable and
wheeled (mobile) rechargeable fire extinguishers (Formerly, The production of reconditioned
fire-fighting equipment: Portable rechargeable fire extinguishers)
SABS 0105 : Part I - The use and control of fire-fighting equipment (Formerly, The
classification, use, and maintenance of portable fire extinguishers)
Requirements
1. Area hydrants should be positioned on a 90m x 90m grid. By ‘area hydrants’ is meant
hydrants which are located at ground level and are intended to cover a wide area
such as a plant, a multiple workshop complex, or an office park, where a number of
unattached buildings are located. Area hydrants serve two purposes:
They obviate the need for internal hydrants in some of the smaller buildings,
since reliance may be placed upon the area hydrants alone.
They offer a fall-back fire fighting strategy for use when a fire in a structure has
developed past the point where fire fighting operations can be conducted
internally using internally provided hydrants and hosereels. At this point, fire
fighters will retreat to a safe position outside the building, and will spray water
on the flames using area hydrants. The purpose of this activity might be to
attempt to contain fire to only certain levels of the structure, or to prevent the
fire from spreading to other areas of the plant or other complex.
Note however, that hydrants associated with specific buildings (“structural hydrants”),
may in some instances satisfy the requirement for area hydrants.
2. 65 mm fire hydrants are to be installed at the rate of one per level in all buildings
exceeding 12 metres in height.
3. In all structures with a footprint exceeding 1000 m², fire hydrants will be installed on
all levels at a rate of one per 1000 m² or part thereof.
4. In close proximity to each “structural hydrant” located in a building, a fire hose box or
cupboard must be provided, containing a minimum of 3 x 65 mm flat lay fire hoses
and a single 65 mm nozzle.
5. In the case of “area hydrants”, either a fire hose box containing at least 3 x 65 mm
flat lay fire hoses and a single 65 mm nozzle must be provided in a fire equipment
box at each hydrant point, or there must be ready access in a central position on site
to a cache of at least 9 x 65 mm flat lay fire hoses, and 3 x 65 mm nozzles.
In either case, the receptacle in which the fire equipment is kept must be colour
coded red and must be suitably demarcated with appropriate symbolic signage.
6. 65 mm fire nozzles, also called branches, shall have a 65 mm male fitting, and an
internal diameter of 16mm. They may be fixed or variable jet, except that where
nozzles are provided primarily for the use of fire teams only, then at least 50% of the
nozzles provided shall be variable jet, to cater for specialist applications.
Notwithstanding the above, no more than 3 x 65 mm fire hydrants may be taken off
any 100 mm spur line leading off the ring main. If additional hydrants are required,
then the spur line must be increased to 300 mm, in diameter, in which case the
number may increase to five.
8. Single hydrants may be fed off a spur line of minimum diameter 75 mm, provided that
no such 75mm spur line should exceed 300m in length. This requirement shall also
apply to the standpipes of single hydrants.
9. Concerning the minimum diameters specified above, note that at no point on the
supply line may the supply pipe be restricted or reduced to a lesser diameter,
irrespective of for how short a distance. This is based on the principle that the
effective diameter of a pipe is equal to its diameter at the narrowest point in its length.
10. All fire water mains and supply lines right up to the hydrant point must be of steel,
unless they are buried underground, in which case, Class 6 HDPE pipe is acceptable.
11. Colour-code all hydrant points and above ground fire mains red.
12. Irrespective of the aforegoing requirements, all hydrants on the system must be
supplied at a minimum static pressure of 300 kPa. If necessary, increase the
diameter of the pipes to achieve this pressure.
13. Irrespective of the aforegoing, the water supply in the fire mains must be adequate to
ensure a minimum flow rate at each hydrant of 1200 l/min, measured when any three
hydrants on the system are open simultaneously. If necessary, increase the diameter
of the fire mains to achieve this required flow.
14. All “area hydrants” are to be located at least 3 metres away from any structure or
installed equipment, so that they can be accessed even if the fire has already taken
hold on that structure or equipment. This does not apply to “structure hydrants”.
15. Hydrants should be located as close as possible to hard surfaces / roadways, so that
fire engines connecting to them do not sink into the mud that will develop from
prolonged fire fighting.
16. All 65 mm hydrant points, and fire hose boxes, cabinets, cupboards and other
receptacles, must be inspected monthly by persons appointed in writing to perform
this task. Such persons should be suitably trained and the results of the inspections
must be logged. Any deviations noted must be rectified in the shortest possible time,
as befits the importance of all emergency equipment.
17. All 65 mm hydrant points, and fire hose boxes, cabinets, cupboards and other
receptacles, must be inspected annually by an accredited external service provider.
Effective hydrants and equipment are to be replaced or repaired as directed, again in
the shortest possible time.
18. No process / service water may be drawn from a fire main. Fire mains must be
dedicated to fire fighting purposes, from the reservoir to the point of delivery.
19. 65 mm hydrants, hoses and nozzles will not be used for any purpose other than fire
fighting. This requirement does not pertain to area hydrants.
20. The relevant symbolic signage indicating the position of each structural hydrant shall
be posted up. Such signage must comply with SABS 0400 TT29, FPA Bulletin 19,
NFPA 170 & SABS 1186.
21. Directional signage is only necessary if the structural hydrants are in an obscured
position (e.g. around a corner). Otherwise the symbolic signage and the red colour of
the structural signage shall serve as adequate indication of its position. This
requirement does not pertain to area hydrants.
Requirements
1. The capacity of the water supply reservoir, dam or tank which must be always readily
available via the fire water mains which supply inter alia the 65 mm hydrant points
and the 25mm fire hosereels, shall be adequate to sustain fire fighting from 3
hydrants operating simultaneously for 120 minutes, i.e. 3 x 1200 litres per minute x
120 minutes which equates to a minimum reservoir capacity of 432 kl, dedicated to
fire.
2. The standard governing fire water supply is SABS 0287 which deals inter alia with fire
pump requirements.
3. Ideally, water for fire fighting purposes will be gravity fed which will remove all need
for fire pumps, and all risk of a lack of fire fighting water as a result of power or pump
failure. However, if this is not possible, then fire pumps must be provided. Most
importantly, the fire pumps should comply with the following requirements:
- The electrically driven jockey pump conjoined with the electrically driven
main fire pump cannot cope with the demand, and / or…
- There is a power failure, so that the electrically driven jockey pump and
main fire pump cannot run.
This pump should turn on automatically in response to any pressure drop in the
system with which the jockey pump and the electrically driven main fire pump cannot
cope, and should turn off once the required pressure has been attained and is being
maintained. A timing factor should also be built into the PLC of this unit to ensure that
it does not switch on and off repeatedly at short intervals. This pump needs to be able
to supply 75% of the stated maximum demand of 3600 l/min at 300kPa static
pressure, sustainable for 120 minutes.
4. Note (1) that it is acceptable to forego the requirement to provide a main electrically
driven fire pump as contemplated in the second bullet point above, on condition that:
The capacity of the installed diesel driven fire pump is at least 120% of the
stated maximum demand of 3600 l/min at 300 kPa static pressure,
sustainable for 120 minutes, and
Life-safety does not depend upon the fire fighting water supply.
5. Note (2) that it is acceptable to forego the requirement to provide a diesel driven
standby main fire pump as contemplated in the second bullet point above, on
condition that.
The capacity of the installed electrically driven fire pump is at least 120% of
the stated maximum demand of 3600 l/min at 300 kPa static pressure,
sustainable for 120 minutes, and
Life-safety does not depend upon the fire fighting water supply.
Adequate emergency diesel powered generating capacity is installed at the
plant to allow for the running of such pump in addition to all the other functions
for which such emergency supply is required.
NFPA 14 - Standard for the Installation of Standpipe and Hose Systems (Part WW
NFPA 20 - Standard for the Installation of Stationary Pumps for Fire Protection
SABS 0287 - Automatic sprinkler installations for fire-fighting purposes
ASIB (compliance is mandatory only where the pumps supply sprinkler systems, upon which
life safety depends)
Requirements
1. In all buildings, including inter alia warehouses, plant structures, workshops and
offices complexes, 25 mm hosereels must be installed at the rate of 1 per 500 m² of
building floor area.
2. Each 25 mm fire hosereel must be fed via a steel takeoff line of minimum diameter 32
mm.
3. These 32 mm take-off lines should be fed off a steel fire water main of minimum
diameter 100 mm.
4. The water supply to the 25 mm fire hosereels shall be sourced from the main ring fed
water main. Also see Standard G30.
5. Where a conveyor path is protected by 25mm fire hosereels, the main 100mm supply
line should be positioned alongside the conveyor path, not above it. If possible, it
should also be positioned at least 1m away from the conveyor belt. Refer to
Standards G41, G42 and G43.
6. Fire hose reels should be supplied at a water pressure of no less than 300 kPa static
pressure.
7. Each fire hosereel must be able to deliver a flow of no less than 0.5 litres per second
(30 litres per minute).
10. All fire hosereels must be inspected annually by an accredited external service
provider, who, on completion of their inspections, shall provide a detailed report per
hosereel, indicating any faults which may have been found. As befits critical
emergency equipment, all such faults shall be rectified, or the equipment replaced as
soon as practicable.
11. No process water point may be fed off the fire water main. This includes all supply
lines leading to 25 mm fire hosereels.
12. Hosereels and fire fighting water shall not be used for any purpose other than fire
fighting.
13. The hosereels and above ground supply lines should be colour-coded red.
14. All supply lines, from the source to the hosereel must be of steel, unless they are
buried underground, in which case Class 6 HDPE is acceptable.
15. An area of 1.2 metres x 1.2 metres must be demarcated on the floor at all positions in
which 25 mm fire hosereels are mounted. This area must be kept free of obstructions
at all times, to ensure easy access to the fire hosereels in an emergency.
16. The relevant symbolic signage indicating the position of each 25 mm fire hosereel
shall be posted up. Such signage must comply with SABS 0400 TT29, FPA Bulletin
19, NFPA 170 & SABS 1186.
Requirements
1. All hydraulic power and lubrication packs are to be adequately bunded. NB. No
containment in the form of bunding or drip trays shall be required on heavy machinery
e.g. stackers.
2. Where hydraulic power and lubrication packs, and similar equipment, are located in a
critical area (see Standard G47), and where the flammable liquid content of a single
unit, or of a number of units grouped together, exceeds 300 litres, an automatically
activated high velocity water deluge fire suppression system (see Standard G5) or a
fixed foam automatic fire suppression system (see Standard G6) must be provided at
such unit or group of units.
3. Absorbent mineral, such as mineral granules, must be used for the absorption of any
spillage which may occur in the bunded area. No flammable or combustible material
such as sawdust or wood shavings may be used for this purpose.
6. Obvious ignition sources in the immediate vicinity of hydraulic power and lubrication
packs must be avoided. Electrical cables, motors, switchgear and lights, unless
intrinsically safe, should not be located within a bund, unless they are raised, for
example on a plinth, above the level of the bund wall.
Application
Bunds are to be constructed around oil-filled transformers, oil/diesel stores, hydraulic power
packs, lubrication packs and similar, to prevent burning liquids from flowing and spreading
fire elsewhere, in the event of a fire at these installations.
Requirements
1. Construct bund walls of 225mm wide brick (i.e. double brick thickness), or 300 mm
wide reinforced concrete.
Such bund walls should be pinned or otherwise affixed to the underlying concrete
floor, to ensure their robustness and resistance to impact damage. Bunds may be
integrated with fire-rated separating-walls. In fact, such walls, where relevant, may
simultaneously serve as bund walls.
Although it is not necessary to provide any means of draining each bund to the
outside, provision for drainage may be provided by inserting a pipe of minimum
diameter 50mm in the bund wall at the lowest point in the bund, if this is required by
the user. Such drainpipe, if provided, must be fitted with a lockable draincock of equal
diameter, complete with a means of locking it in the closed position under normal
operating conditions.
4. Mandatory U-pipes
The drain pipe leading from the bund(s) to the sump should be of minimum
diameter 50mm, and made of steel or a concrete compound. Since this pipe
may contain flaming oil, it may not be made of any combustible or flammable
material such as plastic.
The drain pipe should slope below the horizontal in the direction of the sump
at a gradient of at least 1:20.
The sump should be constructed to have a volume equal to at least twice the
volume of the largest bund which it serves. (This is relevant where one sump
is provided for a number of related bund areas, such as a bank of individually
bunded transformers). This implies that the sump would be able to
accommodate at least 110% of the flammable liquid contents of the installed
equipment located in any two bunds simultaneously, since this may be
regarded as the worst foreseeable case at such an installation.
Aggregate filled bunds do offer better protection than ‘empty’ bunds. However, if an
area is known to be dusty, and if regular maintenance of the aggregate cannot be
guaranteed, it is best to avoid aggregate filling of bunds. The reason for the above is
that unless a proper maintenance programme can be upheld to ensure that the
aggregate filling stays clean, a layer of dust will settle on the surface of the
aggregate, and work its way into the aggregate, ultimately solidifying and reducing
the capacity and effectiveness of the bund. When filling a bund to half its height with
19 mm aggregate, the factor for bund capacity rises from 110% to 250% of the
volume of the retained flammable liquid contained in the equipment installed within
the bund.
Rationale
Transformers and similar large oil filled equipment must each be located individually in
discrete transformer bays, to prevent fire / explosion on any particular unit from spreading to
neighbouring units, equipment, or structures.
NB. Transformer separating walls need not be retrofitted in transformer installations built
before 2000.
Requirements
In order to constitute such bays, separating walls must be constructed between the units,
and between the units and any equipment or structure located alongside (e.g. a substation).
2. There must be no breach whatsoever in the walls of a transformer bay. If such wall
must be breached, then the resultant aperture must be fire stopped and the cables
passing through the fire stopping must be intumescent coated. Refer to Standard G36
regarding the requirements for fire stopping and intumescent coating of cables.
3. The walls must be at least 90 cm higher than the highest point on either of the items
which the wall is intended to separate. In the case of transformers, this will usually be
the oil conservator located on top of the tallest transformer in the pair. Note however,
that in the case of walls intended to separate transformers from an adjacent structure
like a substation, the two highest points under consideration will be the highest point
on the transformer and the highest point on the adjacent structure which will in all
likelihood be the apex of the pitched roof. The sketch below illustrates this rationale.
At least 90 cm
At least 90cm
At least 90cm
4. When viewed in plan, separating walls must extend at least 90 cm beyond the sides
of the transformers which the walls will separate.
Rationale
“Perfect party walls” are internal walls which provide an effective barrier to fire spread. They
would typically be constructed as a division between fire zones, for example between
different rooms in a substation. Areas not so sub-divided cannot be regarded as separate fire
zones. By definition, perfect party walls have a fire resistance of 2 hours.
Requirements
1. Perfect party walls must be constructed of 225 mm wide brick (double brick
thickness). This is deemed to have a fire resistance of 2 hours.
2. The walls should extend from a solid (e.g. concrete) floor, and must reach the full
height of the roof, if the roof is solid, e.g. reinforced concrete. However, if the roof is
not resistant to fire (e.g. corrugated iron or tiles) then the perfect party wall must
extend above the roofline by at least 30 cm, to form a gable.
3. No roof support trusses, whether of steel, timber or other material, may pass through
the perfect party wall. Such trusses, and the roof itself if it is of corrugated iron, tiles,
or similar, must abut the wall on either side.
4. No cable penetration apertures must be allowed to breach a perfect party wall. Where
it is unavoidable for cables to penetrate a perfect party wall, whether above floor
elevation, or via an under floor cable trench, such cable penetration aperture or cable
trench must be effectively fire stopped, and where the cables pass through the fire
stopping, they must be intumescent coated for at least 1 metre on either side of the
fire stopping. See Standard G36 for details of fire stopping and intumescent coating
of cables.
5. Any door set in a perfect party wall must have a fire resistance rating of at least 2
hours, certified by an approved test authority like the SABS or CSIR. Fire doors must
be fitted with an automatic closing mechanism and must be kept closed at all times,
so that fire cannot spread through the doorway, thereby rendering the perfect party
wall ineffective in limiting the extent of fire spread.
6. All doorframes and fittings associated with fire doors must be incombustible and of a
type which will not impair or compromise the fire-rating of the said door.
Where a wall is intended to be a barrier to fire spread, such as in the case of perfect party
walls (Standard G35) or fire / separating walls (Standard G34), it is necessary to fire stop any
breach in such separating wall. Failure to do so removes any benefit that the sub-division
into separate fire zones, might have offered. Fire stopping may be achieved by plastering up
the hole using conventional mortar or mortar made using perlite as a building sand
substitute. Alternatively, an inert material such as “rock wool” or “mineral wool” may be used
to block the hole. This stopping material must then be covered over using an intumescent
coating. Adhere to the specifications laid down by the manufacturer of the intumescent
product to achieve a 2 hour fire rating for the aperture, or the 2 hour fire rating of the wall will
be impaired.
1. Where cables pass through a fire stopped aperture in a wall which separates fire
zones, any electrical or instrumentation cable passing through such fire stopping
must be intumescent coated on either side of the fire stopping for a linear distance of
at least 1 metre unless it is contained in a sand filled trench (of at least 1 m but
preferably 2 m). Such intumescent coating must be applied to the entire
circumference of each cable to be effective, and must be applied to a suitable
thickness, as specified by the manufacturer of the particular intumescent product
used, as being adequate to ensure a fire resistance rating of at least 2 hours. Any
new cables added later, must be similarly intumescent coated.
2. Where electrical and instrumentation cables are routed vertically in a plant structure
or building, these may not always be routed through fire stopped cable penetration
apertures in the interleading floors, in which case, the requirements stated in 1 above
would apply.
Instead, such cables may either be routed in open service shafts, on vertical cable
racks, or through open floors (for example, Mentis-type grating). In such case, where
fire stopping is not appropriate, 2 metre high firebreaks must be provided on all
cables in each group of cables, on every 2nd level. As stated in 1 above, intumescent
coating must be provided over the entire circumference of each cable, and must be
applied to the minimum thickness as stipulated by the manufacturer of the particular
intumescent product used, as being adequate to ensure a fire resistance rating of at
least 2 hours.
conversely will prevent fire originating in the structure from spreading along cable
paths and propagating the fire into other parts of the operation.
Such firebreak may be constituted in one of two ways:
Requirements
1. All bulk flammable liquid storage facilities on surface must be adequately bunded.
Refer to Standard G33 in this regard.
2. Where bulk flammable liquids storage facilities are located in a crowded area, where
spatial separation does not segregate them from other risks, it may be appropriate to
protect them by means of high velocity water deluge systems, or fixed foam fire
suppression systems. See Standards G5 and G6 in this regard. A risk assessment
should be performed to determine the risk level and criticality of the installation in
deciding whether such measure is necessary.
3. The activation valve is to be positioned at a point 1,8 metres above ground level and
suitably demarcated with the relevant symbolic signage.
4. All bulk flammable liquid storage tanks must be earthed. Earthing cables must be
affixed to a dedicated lug on each tank. Earthing cables must be secured to an earth
spike driven at least 1 metre into the surrounding earth, or to an earth mat. Both the
connection between the earthing cable and the tank and between the earthing cable
and the earth spike or mat, must be cleaned down to bright metal on an annual basis
and tightly re-secured. Note that earthing cables may not be affixed to the stands or
other appurtenances belonging to flammable liquid storage tanks, as these may not
make good contact with the tanks themselves.
These hydrants would typically be used in the generation of foam to fight a flammable
liquid fire.
These hydrants should not be positioned within 10 metres of the bulk flammable
liquid storage facility, so that they will remain accessible even after the outbreak of
fire. However, neither should they be positioned further than 30 metres from the
storage structure. Pressure, flow and other requirements pertaining to fire hydrants
are set out in Standard G29.
6. Either a fire hose box containing at least 3 x 65 mm flat lay fire hoses and a single 65
mm nozzle must be provided at each hydrant point contemplated in the preceding
requirement, or there must be ready access on site to a cache of at least 9 x 65 mm
flat lay fire hoses, and 3 x 65 mm nozzles.
7. No electrical switchgear, cables, motors or lights may be positioned within the bund
area surrounding flammable storage tanks, unless these are raised on plinths or
platforms and are located at a height above the height of the bund wall.
8. Symbolic signage visible from all four sides must be provided at the facility,
prohibiting smoking and naked lights.
9. An earthing clamp must be provided at the refuelling point which may be affixed to
any vehicle whilst flammable liquid transfer between the vehicle and the tank is in
progress.
11. If the bulk flammable liquid storage facility is located within a building, all electrical
lighting and equipment in the building must be intrinsically safe.
Requirements
1. Stores for flammable liquids in containers and for chemicals in containers shall be
housed in separate buildings, either structurally or spatially separated from each
other.
The ideal containerised flammable liquid store, or chemical store, will have a concrete
floor, brick walls, and a flat reinforced concrete roof. If a pitched roof is required, then
the roof panels must be incombustible (such as corrugated iron or IBR sheeting), and
the roofing beams should be of steel. No ceiling should be provided. All doors are to
be steel, set in steel frames. Alternatively, doors rated by an approved test authority
such as the SABS or CSIR, as having a fire resistance of at least 2 hours, are
acceptable.
4. If the structure has a steel roof, this must be earthed. The structure as a whole must
be bunded. At the entrance, a bund ramp of height equal to the bund wall, may be
provided, to facilitate the transfer of flammable liquid or chemical containers into and
out of the store. Refer to Standard G33 for bunding requirements.
6. Symbolic signage must be displayed on the main entrance door of all containerised
flammable liquid stores and chemical stores prohibiting smoking and naked lights.
7. Inside the facility, material safety data sheets must be made available which are
pertinent to all substances stored in such facility.
8. Outside the main entrance door to every containerised flammable liquid store and
every chemical store, at least 2 x 9 kg hand-held DCP fire extinguishers shall be
provided, in a position clearly demarcated with the relevant symbolic signage.
9. Particularly where volatile substances are stored, the store must be adequately
ventilated to prevent the build-up of fumes and gases.
10. Where the length of a containerised flammable liquid store or chemical store exceeds
20 metres, or where the floor area exceeds 100 m², an emergency escape door must
be provided at the point furthest from the main entrance door. Such emergency
escape door shall be provided with an internally positioned opening mechanism such
as a Redlam bolt or a panic bar, and such door may not be locked from the outside.
The door shall be suitably demarcated as an emergency escape route with the
appropriate symbolic and directional signage, erected inside the store.
Requirements
1. Based upon the fire load which they constitute, a maximum of 12 LDV tyres or 8 truck
tyres may be stored in a general workshop area. No earthmoving vehicle tyres may
be stored in such area.
2. All earthmoving vehicle tyres must be stored in a dedicated store as described below,
or on open ground spatially well separated from any structure or facility or obvious
ignition source.
3. Any quantity of LDV or truck tyres which exceeds the quantities specified in 1 above,
must be stored in a dedicated tyre store.
4. If a tyres store does not exist for the storage of earthmoving tyres, and it is necessary
to store earthmoving tyres on open ground as a temporary measure, these must be
laid flat to prevent them falling over and injuring persons. However, horizontal storage
of tyres is incorrect from a fire protection perspective, and therefore no more than two
tyres should be placed in any pile. Moreover, piles must be separated from each
other by at least 5 metres.
5. Earthmoving tyres may only be so stored on open ground in quantities exceeding four
(i.e. two piles of two each) if there is ready access to at least 2 x 65 mm “area
hydrants” in the area. It would be usual to locate these hydrants on opposite sides of
the area in which earthmoving tyres will be stored. By so doing, a fire occurring on the
stored tyres could be attacked from two sides. Also, depending on wind direction, it
may not be possible to fight fire from a particular direction on a particular day. These
hydrants should be positioned more than 10 metres and less than 30 metres from the
perimeter of the tyre storage area, so that they can still be accessed even after the
outbreak of fire. Pressure, flow and other requirements pertaining to fire hydrants are
contained in Standard 29.
6. Proper storage for all tyres is in a dedicated tyre store. Such stores must comply with
the following requirements:
The store must be spatially or structurally well separated from all surrounding
structures, installations and ignition sources.
A manually activated water spray system must be provided over the entire
storage area within the building. Refer to Standard G2 for requirements of
such sprinkler systems.
All tyres must be stored in the upright position in steel tyre racks designed to
be sufficiently robust for the size of tyre which they are intended to support. A
minimum 10 mm spacing is required between the tyres.
It is not necessary to eliminate electric lights and power points from a tyre
store, but hot work should not be permitted within the tyre store.
7. Either a fire hose box containing at least 3 x 65 mm flat lay fire hoses and a single 65
mm nozzle must be provided at each hydrant point contemplated in the preceding
requirement, or there must be ready access on site to a cache of at least 9 x 65 mm
flat lay fire hoses, and 3 x 65 mm nozzles.
Definition
Plastic pipes include all forms of plastic pipe, for example, HDPE, uPVC and PVC.
Requirements
1. Plastic pipes may not be used as part of the fire water main on surface, unless they
are buried. In such case, Class 6 HDPE pipe is recommended. Notwithstanding this
concession, no plastic pipe in excess of 300 mm diameter should be used in the fire
water main system.
2. Plastic pipes may be used on surface, for functions unrelated to fire, at the discretion
of site management, save that the following exclusions apply:
Plastic pipes should not be installed where there is an obvious ignition risk,
such as where hot processes are conducted, or near oil-filled transformers or
switchgear.
Because plastic pipes can ignite and will then assist in the rapid propagation
of fire, plastic pipes should not be installed in multi-level structures with a
large footprint. Therefore, if the footprint of the structure exceeds 1 000 m², or
if the structure exceeds 12 metres in height, plastic pipe should not be
installed in the structure. If this requirement is not adhered to, then the same
requirements regarding fire stopping between levels and intumescent coating,
as applies to electrical cables, must be adopted. Refer to Standard G36 in this
regard.
Again because of the concern that plastic pipes can assist in the propagation
of fire, plastic pipes should not be used to link critical installations. See
Standard G47 regarding the process to be followed in determining criticality.
Where plastic pipes are so used, a firebreak must be provided on the plastic
pipe, similar to that described in relation to electrical cables, in Standard G36.
3. Notwithstanding the above, pipes which are incombustible, e.g. steel pipes and
reinforced concrete pipes, are always preferable from a fire risk perspective. Where
possible, obviate the use of plastic pipes altogether.
Definition
Requirements
2. At every drive and at every head or tail pulley, a 9 kg hand-held DCP fire extinguisher
must be provided in an easily accessible position. See Standard G28 regarding the
requirements for hand-held fire extinguishers.
3. On at least one side of the overland conveyor path, a road must be provided and
maintained in an acceptable state of repair, to allow access by heavy vehicles so that
fire fighting on the conveyor path using mobile fire appliances and / or water bowsers
is possible. 65 mm fire hydrants and 25 mm fire hosereels are not required along
overland conveyor belt paths, since reliance for secondary fire fighting will be upon
mobile fire appliances and fire equipped water bowsers. However, once an overland
conveyor enters a plant area, or any other area where “area hydrants” are required,
an overland conveyor structure is deemed to form part of the plant infrastructure, and
must be protected by the “area hydrants” provided on a 90 x 90 metre grid in such
plant or other area. Refer to Standard G29 in this regard.
4. Particular care must be taken to avoid any accumulation of spillage under the belt
since this can lead to friction and ultimately fire.
5. Where possible, all electrical cables should be of the red stripe (flame retardant) type.
Where this requirement cannot be met, electrical cables must be intumescent coated
for 4 m every 50 m. Such intumescent coating must be applied to the entire
circumference of each cable, to the required thickness as stipulated by the
manufacturer of the product as being adequate to ensure a fire resistance rating of at
least 2 hours. See Standard G36 in this regard.
Definition
An “elevated conveyor” is a conveyor belt path elevated above ground elevation on steel or
other supports. Elevated conveyors are usually constructed to allow material to be conveyed
from a lower elevation to a higher elevation in a different structure. The requirements below
pertain to conveyors which are elevated 7 or more metres above ground elevation. Elevated
conveyors which do not exceed this height, are deemed to be “plant conveyors”, and are
subject instead to the requirements stated in Standard G44.
Rationale
The primary concern with elevated conveyors is that they are generally supported on steel
structures which will buckle and fail early in the development stages of a fire occurring on the
elevated conveyor. This would necessitate the reconstruction not only of the conveyor belt
path, but of the fabricated steelwork support structure. Significant lead time is therefore
anticipated. Because the function of an elevated conveyor is generally to convey material
from a lower level to a higher level, it is often not possible to temporarily substitute other
means of conveyance (like loaders and trucks) as a contingency while the elevated conveyor
belt path is being reconstructed. Resultantly, of all surface conveyor structures, elevated
conveyor belt paths represent the most significant potential business interruption losses, and
are therefore deserving of the highest possible level of fire protection.
Requirements
7. Particular care must be taken to avoid any accumulation of spillage under the belt
since this can lead to friction and ultimately fire.
8. In order to reduce the fire load represented by the conveyor structure, combustible
products should be avoided as far as possible in the equipment chosen. Therefore:
If drives or return pulleys are to be lagged, the lagging should, where possible,
be ceramic rather than rubber.
9. Except where they are routed into electrical motors or switchgear, all electrical cables
running along conveyor belt paths should be secured a minimum of 500 mm from the
actual belt. Moreover, all cables are to be red stripe flame retardant.
11. Where a conveyor belt tips into a silo, special fire protection measures are required to
protect both the belt and the silo. In order to fight a fire occurring in the silo, or on the
belt leading up to the silo, a 65 mm hydrant point must be provided. This should be so
positioned that it is not directly over the silo, or it may be inaccessible if a fire has
broken out in the silo. Thus it would usually be best not to position the hydrant at the
very end of the conveyor gantry, close to the tipping position. Some distance down
the belt would be a more suitable position, providing a greater likelihood that the
hydrant will remain accessible for longer.
At this hydrant point, provide a fire hose box containing at least 2 x 65 mm flat lay fire
hoses and a single 65 mm fire fighting nozzle.
Because of the combustible load to be carried by these belts, the requirements above
pertain even if the belt in use is fire retardant.
Definitions
These are surface conveyors located in tunnels, bunkers and other confined areas, such as
under a stockpile.
Rationale
The particular concern with ‘tunnel, bunker and silo conveyors’ is that access to these
conveyors during a fire would be particularly hazardous to personnel, and manual response
to fire is therefore not a feasible option. Moreover, fire affecting such a tunnel conveyor could
easily generate temperatures which could cause a steel or concrete supported excavation to
fail which could see the entire stockpile collapsing into the conveyor tunnel.
Therefore, business interruption loss potential is high, and great danger exists to persons, if
attempts should be made to fight the fire manually.
Therefore, the requirements stated below are based upon the principles that a fire in a
conveyor tunnel would have significant consequences, and such a fire must be addressed by
automatic means to ensure the safety of persons.
Requirements
The requirements for protecting ‘tunnel, bunker, silo and related conveyors’ against fire risk
are as follows:
1. Where a ‘tunnel, bunker, silo and related conveyor’ installation has been assessed as
“critical”, in terms of the requirements in Standard G47, a fixed automatic fire sprinkler
system contemplated in Standard G3, or a high velocity water deluge system, as
contemplated in Standard G5, must be installed over the entire length of the tunnel,
up to the point where the belt structure exits the tunnel, whereafter the belt is
classified as a “surface plant conveyor” (see Standard G44 for the relevant
requirements thereafter).
2. For all other ‘tunnel, bunker, silo and related conveyors’, a manually operated fire
sprinkler system must be provided over the entire belt length, up to the point where
the ‘tunnel, bunker, silo and related conveyors’ becomes a “surface plant conveyor”.
Refer to Standard G2 for the requirements of such manual fire sprinkler system. Note
that all control valves for such system must be clearly demarcated to indicate the
area to which they apply, and such valves must be located in fresh air on surface in a
safe position, so that they may be actuated even after the outbreak of fire on the
tunnel conveyor.
4. Particular care must be taken to avoid any accumulation of spillage under the belt
since this can lead to friction and ultimately fire.
5. In order to reduce the fire load represented by the conveyor structure, combustible
products should be avoided as far as possible in the equipment chosen. Therefore:
Drives or return pulleys are to be lagged, the lagging should be ceramic and
not rubber.
6. Fire load in conveyor tunnels must be kept to a bar minimum. Therefore, combustible
materials should not be used in constructing the tunnel, and storage of flammables or
combustibles within the tunnel should not be permitted.
7. Except where they are routed into electrical motors or switchgear, all electrical cables
running along conveyor belt paths should be secured a minimum of 500 mm from the
actual belt. Moreover, all cables to are be red stripe flame retardant.
8. Where a conveyor belt tips into a silo, special fire protection measures are required to
protect both the belt and the silo. In order to fight a fire occurring in the silo, or on the
belt leading up to the silo, a 65 mm hydrant point must be provided. This should be so
positioned that it is not directly over the silo, or it may be inaccessible if a fire has
broken out in the silo. Thus it would usually be best not to position the hydrant at the
very end of the conveyor gantry, close to the tipping position. Some distance down
the belt would be a more suitable position, providing a greater likelihood that the
hydrant will remain accessible for longer.
At this hydrant point, provide a fire hose box containing at least 2 x 65 mm flat lay fire
hoses and a single 65 mm fire fighting nozzle.
Definition
Requirements
1. In order to reduce the fire load represented by the conveyor structure, combustible
products should be avoided as far as possible in the equipment chosen. Therefore:
Drives or return pulleys are to be lagged, the lagging should be ceramic and
not rubber.
2. Except where they are routed into electrical motors or switchgear, all electrical cables
running along conveyor belt paths should be secured a minimum of 500 mm from the
actual belt. Moreover, all cables are to be red stripe flame retardant.
4. Reliance for secondary fire fighting shall be on “area hydrants” which must cover all
occupied plant areas which shall include areas in which surface plant conveyors are
installed. See Standard G29 regarding the requirements for, and purpose of, “area
hydrants”.
5. Where a risk assessment has classified a surface plant conveyor as “critical” in terms
of the standards laid down in Standard G47, 65 mm fire hydrants or 25 mm fire
hosereels may be provided along the entire length of a surface plant conveyor. See
Standard G42 for more details.
But in the case of surface plant conveyors, full cladding on both sides of the conveyor
structure will prevent water from “area hydrants” from being sprayed onto the belt to
suppress fire. Therefore, at least one side of the conveyor structure should be open
sided, to allow access with fire fighting equipment.
Definition
These standards pertain to all large covered storage areas, for example, mine stores and
other warehouses. They are not necessarily pertinent to small sectional stores. They also do
not apply to storage yards. Requirements for storage yards are stated in Standard G46.
Requirements
1. An automated sprinkler system must be installed in any covered storage area if the
sum of the replacement value of the structure and all stored material and equipment
within the structure will at any time exceed US$2.5 million. See Standard G3
regarding the requirements for automated sprinkler systems.
4. 25mm hosereels must be installed in all covered stores and warehouses which have
a footprint in excess of 500 m². They must be installed at the rate of 1 per 500 m² of
building floor area or part thereof, and should be spaced evenly throughout the
structure. Refer to Standard G31 for standards pertaining to 25 mm hosereels.
5. Hand-held fire extinguishers must be installed in all covered stores and warehouses
at the rate of 1 per 200 m² of building floor area or part thereof. These should be
evenly spaced throughout the building. 9 kg hand-held DCP fire extinguishers are the
norm, but under certain circumstances, 5 kg CO2 extinguishers should be substituted.
See Standard G28 regarding mounting requirements, colour coding, selection
between DCP and CO2, and other requirements pertaining to the deployment of hand-
held fire extinguishers.
6. 65 mm hydrants must be provided within any mine store or warehouse, the footprint
of which exceeds 1000 m². Hydrants must be provided at the rate of 1 per 1000 m² of
building floor area, or part thereof. See Standard G29 regarding the requirements for
65 mm hydrants.
7. A fire hose box containing at least 3 x 65 mm flat lay fire hoses and a single 65 mm
nozzle, must be provided at each of the abovementioned structural hydrant points.
Where the footprint of the mine store or warehouse does not exceed 1000 m², the
requirement for a hose box per structural hydrant may be dispensed with, providing
there is ready access and easily accessible external position within 100 metres of the
structure to a cache of at least 9 x 65 mm flat lay fire hoses and 3 x 65 mm nozzles.
8. In addition to the structural fire hydrants and fire hose boxes contemplated above,
there must also be ready access to at least 2 x 65 mm externally positioned “area
hydrants”. It would be usual to provide a hydrant on either side of the mine store or
warehouse, so that a fire occurring in the structure which cannot be addressed
satisfactorily with the internal hydrants, can be attacked from a fall-back position
outside the structure, using the area hydrants to attack the fire from two sides. Also,
depending on wind direction, it may not be possible to fight fire from a particular
direction on a particular day.
These “area hydrants” should be positioned further than 10 metres but within 30
metres of the mine store or warehouse structure, so that they will be readily
accessible even after a fire has taken hold of the structure. Pressure, flow and other
requirements pertaining to fire hydrants are contained in Standard G29.
Note that this requirement for “area hydrants” may in certain circumstances be
satisfied by the requirements stated in Standard G46.
9. A fire hose box containing at least 3 x 65 mm flat lay fire hoses and a single 65 mm
nozzle must be provided at each hydrant point contemplated in the preceding
requirement, or there must be ready access on site to a cache of at least 9 x 65 mm
flat lay fire hoses, and 3 x 65 mm nozzles.
Note that where the concession stated in Requirement 7 has been utilised, and there
is a cache of hoses maintained outside the structure for use with the internally located
“structural fire hydrants”, this would simultaneously satisfy the requirement for a
cache of hoses and nozzles to be used with the “area hydrants”.
11. If an automated sprinkler system has been installed in the mine store or warehouse in
accordance with Requirement 1 above, then this must be coupled to an alarm system
which will automatically raise an audible and visible alarm on site in response to a
fire. Moreover, this signal must be relayed to a remote point with 24 hour monitoring.
This is particularly important in the case of a store or warehouse which will typically
not be occupied after hours. Such remote alarm will ensure that a fire is timeously
detected and that response is forthcoming in the shortest possible time to extinguish
the fire and limit the extent of damage.
12. Where an automated sprinkler system has not been installed as contemplated in
Requirement 1 above, then a passive point fire detection system must be installed
throughout the mine store’s structure or warehouse. This must be capable of raising a
local and remote alarm, as contemplated in the preceding requirement. Refer to
Standard G9 regarding the requirements for passive fire detection systems.
13. Smoking must not be permitted in any mine stores building or warehouse. Erect the
appropriate symbolic signage at all entrances to such structures to ban smoking and
naked lights.
14. If hot work must be performed in a mine stores structure or warehouse, then all
provisions of Standard G11 must be adhered to, to the letter. In particular, such work
must be conducted at a suitable time as will ensure that the premises are not vacated
(for example at the end of the shift) within 2 hours of the cessation of hot work on the
premises. A fire watch must be kept for the full period of 2 hours.
Requirements
1. Provide 65 mm “area hydrants” on a 90 x 90 m grid to cover the entire stores yard and
the buildings located in the yard. These hydrants may satisfy the requirements stated
in G45 Requirement 6 above.
2. No matter how small the yard, provide at least 2 hydrants, one on either side of the
store yard, so that a fire occurring in the yard which cannot be addressed satisfactorily
from one hydrant because of wind direction, may be fought from the alternate hydrant
point.
3. Pressure, flow and other general requirements pertaining to fire hydrants are contained
in Standard G29.
4. A fire hose box containing at least 3 x 65 mm flat lay fire hoses and a single 65 mm
fixed jet fire fighting nozzle must be provided at each hydrant point contemplated in the
preceding requirement, or there must be ready access on site to a central cache of at
least 9 x 65 mm flat lay fire hoses, and 3 x 65 mm nozzles.
5. Flammable liquids in drums and similar containers must be stored within bunds or
drip trays. See Standard G33 for requirements pertaining to bunding, and Standard
G38 for requirements pertaining to storage facilities on surface for flammable liquids or
chemicals in containers.
6. Bulk flammable liquid storage facilities in the yard must comply with the requirements
of Standard G37.
8. Tyres and rubber products in the storage yard must be stored according to the
requirements of Standard G39.
Definition
Definition
Fire retardant
“Fire retardant” is one of several terms that for all practical purposes within the context of this
document mean roughly the same thing. Other terms in the group are “fire resistant”, “flame
retardant” and “flame resistant”. The following discussion is relevant to all of these terms.
These terms refer to materials which are so composed or treated as to inhibit combustion.
But flame retardant material may still combust if there is an outside heat source acting upon
it. Manufacturers of flame retardant materials often claim that it ‘will not support combustion’,
but if heat from another source, like other burning materials, is applied to it, it will still
combust upon reaching its particular ignition temperature, whereupon it will burn in
conjunction with the external heat source, adding to the energy levels available for release
during the fire. This will hasten structural collapse and propagation of the fire to unaffected
areas, because the fire will ‘burn that much hotter’.
Sometimes, once the external heat source has been removed, the fire retardant material will
cease to burn, but it can happen that if sufficiently high temperatures have been reached
before the external heat source has been removed, the ‘fire retardant’ material will still
continue to burn, despite its supposed ‘flame retardancy’.
From the above, it is obvious that ‘flame retardant’ materials have very limited use, and
actually offer little advantage. An example is styrene which normally ignites at around 200O.
Flame retardant styrene is claimed only to ignite at around 300O. However, when one
considers that structure fires easily reach 1000O quite quickly, then it is obvious that this
difference is just academic.
In reality, the term ‘fire retardant’ is misleading, and project managers would do well to aim
for ‘incombustible” construction materials in almost all cases in Plants and similar. ‘Flame
retardant’ materials may have some use in low risk, low value facilities where life safety is not
an issue, but within AngloCoal, there are not many such applications.
Incombustible
This term refers to a material which under all normal conditions cannot burn. Examples are
brick, concrete, mineral wool, rock wool and perlite. In most cases, project managers will
need to use such materials for walls, support structures and similar.
Note, though, that even ‘incombustible’ materials will lose their structural integrity when
subjected to extreme heat, although they will never actually burn, and will therefore never
contribute to the fire load in a building. For example, steel starts to buckle at a relatively low
500O. Even concrete will decompose under really extreme conditions (e.g. the World Trade
Centre disaster), when the concrete reverted to powder.
Application
At hydraulic power packs, lubrication packs, areas where flammable liquids are involved, and
in other areas where the application of foam offers an effective means of suppression, but
where the size of the risk does not justify a fixed system, a foam trolley can offer a solution.
At such locations, the provision of such trolley would be deemed to satisfy the need for
advanced primary fire protection, and may justify the omission of a high velocity deluge
system, or a fixed foam system.
In multilevel structures, the Viking hoses provided will make it possible to use the foam trolley
to fight fires on the levels immediately above and below, without the necessity of moving the
trolley to those levels.
Requirements
1. The unit should be fitted with solid rubber wheels of minimum diameter 400 mm.
3. The chassis should be corrosion protected and suitable for outdoor use and storage.
6. The foam trolley should be fitted with a variable foam inductor capable of 225
litres/minute, with an induction rate of 3%.
8. The trolley must be provided with a foam branch pipe capable of delivering 225
litres/minute.
NFPA 16 - Standard for the Installation of Foam-Water Sprinkler and Foam-Water Spray
Systems
Concern
Associated with flotation plants, is the bulk storage of reagent / frother. Being kerosene-
based, fire and environmental concerns exist with this storage.
Requirements
2. The reagent storage yard must be declared a non-smoking area. To this end, erect
signage prohibiting smoking and naked lights on all sides of the fence surrounding
the yard, and in particular, at all entrances to the yard.
3. Hot work is permissible in the reagent storage area, provided that all requirements of
Standard G11 are complied with. Note however, that only hot work associated with
installed equipment is permissible. Where equipment can be removed, and the work
performed elsewhere, such hot work should not be conducted within the reagent
storage yard.
4. In order to reduce the structural fire load in the area, combustible materials must not
be used in the construction of the facility. See Standard G48 for an explanation of the
term “incombustible”.
5. Other than the contents of the reagent storage tanks themselves, additional and
unnecessary combustible and / or flammable materials should not be stored in the
reagent storage yard/area.
6. Some form of fixed fire suppression must be installed at the reagent storage tanks,
and should extend to cover all areas in which reagents are handled. Nozzles should
be positioned so as to adequately cover the tanks, i.e. above, under and / or on the
sides of the tanks. Systems which may be considered are:
Provided that where manually operated systems are chosen, the location of the
control valves must be sufficiently far removed from the facility, or must be so
protected, as will enable them to be safely operated, even after the outbreak of fire.
7. The yard in which the reagent storage area is located should be so positioned as to
ensure that none of the reagent storage tanks or equipment are within 10 metres of
any other structure or facility. The distance of 10 metres is conditional upon full
compliance with Requirement 8 below.
8. The reagent storage tanks must be individually or globally bunded. Refer to Standard
G33 for bunding requirements. Note in particular, that the 110% rule applies, and the
optional remote sump arrangement described in Standard G33 is strongly
recommended.
9. An earthing clamp must be provided which may be affixed to any vehicle whilst
transfer of reagent between the vehicle and the tanks is in progress.
10. No electrical switchgear, cables, motors, or lights, may be positioned within the bund
area(s) surrounding the tanks, unless these are raised on plinths or platforms and are
located at a height above the height of the bund wall.
11. The capacity of each reagent storage tank must be clearly demarcated on the side of
the tank.
12. At least 1 x 9 kg hand-held DCP fire extinguisher must be provided on each side of
the reagent storage building / area. The position of these fire extinguishers must be
clearly demarcated by means of the relevant symbolic signage, and they should be
mounted at a height of 1.2 metres above the floor or ground elevation. Refer to
Standard G28 regarding the requirements for hand-held fire extinguishers.
13. The reagent storage tanks should ideally be protected from the elements, for
example, by means of an IBR sheeting roof, and possibly walls.
14. There must be ready access to at least 2 x 65 mm “area hydrants” within 30 metres
of, but not closer than 10 metres to, the reagent storage yard / area. These should be
located on opposite sides of the facility, so that a fire occurring in the yard may be
attacked from two sides. Also, depending on wind direction, it may not be possible to
fight fire from a particular direction on any given day. These hydrants could typically
also be used to generate foam to fight fire occurring on the reagent tanks. Pressure,
flow and other requirements pertaining to fire hydrants are set out in Standard G29.
15. All reagent tanks must be earthed. Earthing cables must be affixed to a dedicated lug
on each tank. Earthing cables must be secured to an earth spike driven at least one
metre into the surrounding earth, or to an earth mat. Both the connection between the
earthing cable and the tank and between the earthing cable and the earth spike or
mat, must be cleaned down to bright metal on an annual basis, and tightly re-
secured. Note that earthing cables may not be affixed to the stands or other
appurtenances belonging to reagent tanks, as these may not make good contact with
the tanks themselves.
Consideration
One of the primary reasons why fire engines are often found to be inadequate when required
for service, is that they are incorrectly chosen in relation to their intended purpose. There are
many classes of fire engine, but for the purposes of these standards, three classes of fire
engine are considered. These are:
Initial attack fire appliances. As the name implies, initial attack fire appliances are
meant to provide a first response to the outbreak of fire in an area. They would be
suitable for the early stages of a fire in a single storey structure, for bush fires, and for
an initial response to an earthmoving vehicle fire. However, they are unsuitable for
well-developed fires in any structure, and certainly for fires in multi-level structures.
They are also not suitable for sustained fire fighting operations where a
supplementary source of water is unavailable, for example, in an opencast pit. Initial
attack fire appliances have limited pumping capacity, and are therefore also not
suitable for use where it is necessary to boost the water pressure and flow from
another source. This is the function of a pumper appliance (see below). Standard
G52 provides details of the requirements pertaining to initial attack fire appliances.
Pumper fire appliances. Pumper appliances are suitable for response to well-
established fires where high water volumes, possibly in elevated locations, are
required. However, the on-board supply of water is fairly limited on a pumper
appliance and it is therefore unsuitable to operate in areas where an additional water
supply is unavailable, for example, in an opencast pit. Refer to Standard G53 for the
requirements pertaining to pumper appliances.
Mobile water-supply fire appliances. Mobile water supply fire appliances are
designed to be operated in areas where an external supply of water is unavailable, for
example, in an opencast pit. Note however, that by definition, a mobile water-supply
fire appliance is not specifically required to have any pumping capacity. It is therefore
unsuitable to operate alone. It would typically be used in conjunction with a pumper
appliance. Refer to Standard G54 for requirements pertaining to mobile water-supply
fire appliances.
A water bowser, as used in opencast operations for watering roads, etc., is suitable to be
equipped as a mobile water-supply fire appliance. Note however, that where a pumper
appliance is not available on site, or where it would foreseeably take a long time to reach an
area in which the water bowser is operating, consideration should be given to equipping the
water bowser as a hybrid mobile water supply fire appliance cum pumper appliance. In this
regard, consider the requirements stated in Standard G53 and G54.
Requirements
1. Fire Pump
The appliance shall be equipped with a fire pump with a minimum rated capacity of
950 litres/min. (In accordance with NFPA 1901 Chapter 14 - Fire Pump and
Associated Equipment).
2. Water Tank
Initial attack appliances shall be equipped with a water tank that has a minimum
certified capacity of 757 litres.
3. Equipment Storage
4. Hose Storage
Two areas, each a minimum of 0.1 m³, to accommodate 38-mm or larger pre-
connected fire hose lines
Ground Ladders.
All ground ladders carried on the appliance shall meet the requirements of NFPA
1931.
A 3.7 metre or longer extension-type ground ladder shall be carried on the appliance.
Suction Hose.
A minimum of 6 m of hard suction hose shall be carried. Suction hose shall meet the
requirements of NFPA 1961. Where a hard suction hose is provided, a suction
strainer shall be furnished.
6. Minor Equipment
The following fire hose and nozzles shall be carried on the appliance:
Miscellaneous Equipment.
Requirements
1. Fire Pump
The appliance shall be equipped with a fire pump that has a minimum rated capacity
of 2850 litres/min. (In accordance with NFPA 1901 Chapter 14 – Fire and Associated
Equipment).
2. Water Tank
The pumper shall be equipped with a water tank(s) that has a minimum certified
capacity (combined, if applicable) of 1136 litres.
3. Equipment Storage
4. Hose Storage
Hose bed area(s), compartments, or reels that shall be provided to accommodate the
following. These areas need not be contiguous.
Ground Ladders
All ground ladders carried on the appliance shall meet the requirements of NFPA
1931.
Suction Hose.
A minimum of 6 m of hard suction hose shall be carried. Suction hose shall meet the
requirements of NFPA 1961. Where a hard suction hose is provided, a suction
strainer shall be furnished.
6. Minor Equipment
Brackets or compartments shall be furnished so as to organize and protect the
equipment.
The following fire hose and nozzles shall be carried on the appliance:
Miscellaneous Equipment
Requirements
1. Pump
If the appliance is equipped with either a fire pump, transfer pump, or both, the
pump(s) shall meet the requirements of NFPA 1901 Chapter 14 or Chapter 16
respectively.
2. Water Tank
The mobile water supply appliance shall be equipped with a water tank(s) that meets
the requirements of NFPA 1901 Chapter 17 and that has a minimum certified
capacity (combined, if applicable) of 3800 litres.
3. Equipment Storage
4. Hose Storage
A minimum hose storage area of 0.17 m³ for 65 mm fire hose that shall be
provided.
If the appliance is equipped with a fire pump, two areas, each a minimum of
0.1 m³, to accommodate 38 mm or larger pre-connected fire hose lines shall
be provided.
5. Suction Hose
6. Minor Equipment
If the mobile water supply appliance is equipped with a fire pump, the following shall
be provided:
61 m of 38 mm fire hose
Two combination spray nozzles, 360 l/min minimum
Miscellaneous Equipment
Mobile water supply fire appliance shall be equipped with at least the following
equipment:
One 2.7 kg flathead or pick head axe mounted in a bracket fastened to the
appliance
One 2 m or longer pike pole or plaster hook mounted in a bracket fastened to
the appliance
Two portable hand lights mounted in brackets fastened to the appliance
Two approved 9 kg dry chemical portable fire extinguishers mounted in a
bracket fastened to the appliance
One SCBA complying with NFPA 1981 but not less than two, mounted in
brackets fastened to the appliance or stored in containers supplied by the
SCBA manufacturer
One spare SCBA cylinder for each SCBA carried, each mounted in a bracket
fastened to the appliance or stored in a specially designed storage space(s)
One first aid kit
Two combination spanner wrenches mounted in a bracket fastened to the
appliance
One hydrant wrench mounted in a bracket fastened to the appliance
One double female adapter, sized to fit 65 mm or larger fire hose, mounted in
a bracket fastened to the appliance
One double male adapter, sized to fit 65 mm or larger fire hose, mounted in a
bracket fastened to the appliance
Two wheel chocks, mounted in readily accessible locations, that meet or
exceed the requirements of SAE J348, Standard for Wheel Chocks, for the
wheel diameter on which the chocks are to be used.
If the mobile water supply appliance is equipped with a pump, the following
equipment shall additionally be carried on the appliance:
One gated swivel intake connection with pump intake threads on one end and
one or more female connections compatible with the supply hose carried on
the other end
One rubber mallet, for use on suction hose connections, mounted in a bracket
fastened to the appliance
Neither the hydrants nor the monitor may be used for any purpose
except for fire fighting, and must be kept readily available for that
purpose at all times.
Maintenance
8. Operators
All water bowser operators are to be trained as fire team members, and must
be able to operate both water and foam equipment on the bowser.
Requirements
1. Surface fire team members must form the core of the fire response effort on site. As
such, they must be adequately trained and equipped to deal with the following fire-
related situations:
Fires where the use of breathing apparatus is necessary. To this end, each
team member must be trained in the use of breathing apparatus, and
moreover, at least 20 breathing apparatus sets must be provided and
maintained on site, and either, for each set, a spare cylinder must be kept. All
recharging of breathing apparatus facilities must be available on site.
Fires in elevated structures. This would include tall plant buildings, and
elevated conveyor belt paths.
Fires in confined spaces. This could also include elevated, enclosed conveyor
belt paths, draglines, and some areas in the plant.
2. Whilst volunteer fire team members need not be trained to the same level of
proficiency in these aspects of fire fighting, as professional fire team members, they
must nonetheless be adequately trained, in the opinion of professional fire training
body such as the FPASA, to conduct and lead initial fire fighting efforts on site until
the arrival of professional fire teams from local municipalities. Cognisance must
therefore be taken of the likely response times of the available professional teams,
allowing for a worst case situation when an emergency so exists in the municipal area
served by such professional teams.
3. Irrespective of the availability of the abovementioned surface fire team, all employees
on site must also be proficient to some degree in the use of the fire fighting
equipment provided on site. Expected minimum proficiency levels of the general
workforce are as follows:
At least 50% of the workforce, and this may include the volunteer fire team
discussed above, must be proficient in the use of both primary fire fighting
measures (as described above) and secondary fire fighting measures (65 mm
hydrants and hoses) as provided on site. These persons do not require the
specialist skills required of the volunteer fire team members (see above), but
should be proficient in the use of all primary and secondary fire fighting
measures on site, so that they can assist volunteer and professional fire team
members under their direction.
Requirements
1. Remove the power source from all non essential equipment. Lock out and tag
the equipment.
2. Remove all trash. Ensure that the area or building is free of rags, debris, and
packing material.
5. Where fire protection systems are still operable, these must be inspected
maintained in accordance with these Standards.
Definition
Headgear hoist rooms are hoist rooms located on top of the headgear. Typically, these will
be equipped with Koepe winders, and may occupy one or more levels at the top of the
headgear.
Concern
The main concern of headgear hoist rooms, is that if a fire occurring in such hoist room
reaches sufficient intensity, it can result in impairment of the structural integrity of the
headgear and may even result in conveyances being dropped down the shaft.
Application
The contents of this Standard shall be binding with respect to new installations built after 1
January 2007. Any necessary deviation from the Standard must be approved before
implementation thereof by the Fire Standards Committee and written dispensation granted.
Regarding existing hoist rooms, all practicable modifications must be made to bring them as
far as possible in line with the requirements of this Standard
Requirements
3. All levels of headgear hoist rooms must be protected by a fixed passive point
automatic fire detection system as contemplated in Standard G9.
4. All electrical cables installed are to be of the red stripe flame retardant type.
Notwithstanding this requirement, all cables are to be suspended at least 300 mm
from any combustible materials or equipment. Refer to Standard G1 in this regard.
5. To reduce the fire load in this critical installation to the lowest possible level, only
working quantities of flammable and combustible materials may be retained within the
hoist room. Where it is necessary to store larger quantities in close proximity to the
hoist room, these must be located in a separate and independent flammable
materials store, located at ground elevation, and spatially well separated from the
headgear structure. Refer to Standard G38.
6. Where electric panels and switchgear are located in the general area of a headgear
hoist room, it is recommended that in-cabinet automatic fixed gaseous fire
suppression systems be provided within the panels. See Standard G8 in this regard.
Early warning aspirated detection systems, linear wire or passive point detector
heads are all acceptable means of detecting fire in the cabinets, and automatically
actuating the in-cabinet suppression systems.
7. Any electrical panels located in the general area of a headgear hoist room, must have
any electrical cables entering and leaving the panels intumescent coated for a
distance of at least 1 metre at the point of entry / exit. Such intumescent coating must
be applied to the entire circumference of each cable, to the required thickness as
stipulated by the manufacturer of the product as being adequate to ensure a fire
resistance rating of at least 2 hours. See Standard G36 in this regard.
8. Substations, MCCs and similar should not be located within the headgear at all new
installations. Where a substation or MCC is located within headgear structure, it must
enjoy perfect structural separation from all other areas / zones of the headgear, and
must be treated in the same way as a critical surface substation or MCC. See
Standard G18 in this regard.
10. At a central, easily accessible position in every headgear hoist room, provide a
trolley-mounted bulk foam fire extinguisher. Where a headgear hoist room is split over
several levels, it is acceptable to place the foam trolley on the central level, provided
that:
There is free access between the levels over which the headgear hoist room
is spread (for example, a stairwell).
11. In headgear hoist rooms, hot work is only permissible if it must be performed in situ to
maintain installed equipment. The requirements as stated in Standard G11 must be
adhered to. Hot work may not be routinely performed in any headgear hoist room,
and no headgear hoist room should serve as a permanent workshop of any sort.
12. Any hydraulic power packs and / or lubrication packs which may be installed within a
headgear hoist room, must adhere to the relevant requirements as stated in Standard
G32. The requirements for bunding as stated in Standard G33, also pertain.
13. Due to the criticality of headgear hoist rooms, as described in the introduction above,
every effort must be made to eliminate ignition sources. For that reason, the
headgear superstructure as a whole must be declared a “no smoking” area, and
signage must be erected prohibiting smoking and naked lights. Refer to Requirement
11 above regarding hot work in underground hoist rooms.
14. In order to reduce the structural fire loading of headgear hoist rooms, the use of
flammable or combustible materials in the construction of hoist rooms is
unacceptable. Refer to Standard G48 in this regard.
Definition
By “stand-alone surface hoist room” is meant the structure housing winders and related
equipment, serving the shaft leading to the underground workings, but which structure is
located at ground elevation in a position spatially well separated from the headgear. This
arrangement would typically be the case where Koepe winders are not installed.
Concern
The concern with stand-alone surface hoist rooms is that energy levels are high, and a fire is
foreseeable. a fire in a hoist room is likely to cause significant damage to property, and to
result in significant business interruption during reconstruction. In an extreme case, a fire
could result in hoist ropes being severed by the heat, dropping conveyances down the shaft.
However, unlike headgear hoist rooms as contemplated in Standard U1, stand-alone surface
hoist rooms eliminate the risk that a hoist room fire could affect the structural integrity of the
headgear itself.
Requirements
1. MV transformers and switchgear should not be positioned within hoist rooms. Where
transformers and switchgear are positioned within the hoist room, they must be of the
vacuum-type or SF6 filled, in order to reduce the ignition risk and fire loading in this
critical area.
3. The entire hoist room must be protected by a fixed passive point automatic fire
detection system as contemplated in Standard G9.
4. All electrical cables installed to be of the red stripe flame retardant. Notwithstanding
this requirement, all cables are to be suspended at least 300 mm from any
combustible materials or equipment. Refer to Standard G1 in this regard.
5. To reduce the fire load in this critical installation to the lowest possible level, only
working quantities of flammable and combustible materials may be retained within the
hoist room. Additional quantities of flammable and combustible materials must be
stored in a dedicated flammable materials store, spatially well separated from the
stand-alone headgear hoist room. Refer to Standard G38 in this regard.
6. Where electric panels and switchgear are located in the general space of a stand-
alone surface hoist room, consider providing in-cabinet automatic fixed gaseous fire
suppression systems within the panels. See Standard G8 in this regard. The decision
as to whether to provide such systems should be based upon the outcome of a risk
assessment conducted on the panels within the context of the hoist room, to
determine their criticality in accordance with the standards laid down in G47.
7. All electrical cables entering or leaving any electrical panels which may be located in
the general space of a stand-alone surface hoist room, must be intumescent coated
for a distance of at least 1 metre at the point of entry / exit into the panels. Such
intumescent coating must be applied to the entire circumference of each cable, to the
required thickness as stipulated by the manufacturer of the product as being
adequate to ensure a fire resistance rating of at least 2 hours. See Standard G36 in
this regard.
8. Substations and MCCs should not be located within a stand-alone surface hoist room
and neither should they be located adjacent to such structure. Instead, they must be
spatially separated from the structure.
10. At a central, easily accessible position in the stand-alone surface hoist room, provide
a trolley-mounted bulk foam fire extinguisher. Refer to Standard G49 for the
applicable requirements. Note that the adequacy of this requirement is conditional
upon full compliance with all other related requirements, and especially those stated
in 9, 11 and 12.
11. 65 mm fire hydrants are not required inside a stand-alone surface hoist room.
However, There must be ready access to at least 2 x 65 mm “area hydrants”, i.e.
hydrants located outside the hoist room. It would be usual to provide a hydrant on
either side of the hoist room structure, so that a fire occurring in the structure can be
attacked from two sides. Also, depending on wind direction, it may not be possible to
fight fire from a particular direction on a given day.
These hydrants should be positioned between 10 and 30 metres from the structure,
so that they will remain accessible event after the outbreak of fire.
Note that the adequacy of this requirement is conditional upon full compliance with all
other related requirements, and especially those stated in 9, 10 and 12. Pressure,
flow and other requirements pertaining to fire hydrants are contained in Standard
G29.
12. Either a fire hose box containing at least 3 x 65 mm flat lay fire hoses and a single 65
mm nozzle must be provided at each hydrant point contemplated in the preceding
requirement, or there must be ready access on site to a cache of at least 9 x 65 mm
flat lay fire hoses, and 3 x 65 mm nozzles. Note that the adequacy of this requirement
is conditional upon full compliance with all other related requirements, and especially
those stated in 9, 10 and 11 above.
13. No workshops, particularly workshops in which hot work is routinely performed, like
boilermaking workshops, are to be located within any stand-alone surface hoist room.
Obviously, when hot work must be performed in situ in the hoist room, to maintain
installed equipment, this is permissible as long as the requirements as stated in
Standard G11 are adhered to. However, hot work may not be routinely performed in a
stand-alone surface hoist room.
14. Any hydraulic power packs and / or lubrication packs which may be installed within a
stand-alone surface hoist room, must adhere to the relevant requirements as stated
in Standard G32. The requirements for bunding as stated in Standard G33, also
pertain.
15. Due to the criticality of stand-alone surface hoist rooms, every effort must be made to
eliminate ignition sources. For that reason, these structures must be declared “no
smoking” areas, and signage must be erected prohibiting smoking and naked lights at
all entrances leading to the stand-alone surface hoist rooms. Refer to Requirement
13 above regarding hot work in stand-alone surface hoist rooms.
16. Due to the criticality of stand-alone surface hoist rooms, fire load must be kept to the
barest minimum. Resultantly, structural fire loading must be reduced as far as
possible, by avoiding combustible and flammable materials in the construction. Refer
to Standard G48 in this regard.
Requirements
1. Water sprays are required at the collar of every shaft. These must cover the entire
shaft area, and heads must be so located and positioned that the entire excavation
will be effectively wet when the sprays are activated. Pipes, valves and other
appurtenances are to be colour coded red. All pipes used must be steel. The sprays
are to be manually activated by means of a clearly demarcated valve located
between 15 and 25 m from the shaft, to make it accessible even in an emergency
situation.
The shaft spray system must discharge water at the rate of 1 litre/second/m² of the
cross-sectional shaft footprint.
3. On the shaft bank and on every underground shaft station, provide a 65 mm fire
hydrant point. Refer to Standard G29 regarding pressure and flow requirements. At
each hydrant, provide a fire hose box or cabinet containing at least 4 x 65 mm flat lay
fire hoses, a Y-branch, and two 65 mm nozzles. Hydrant points must be located no
closer than 10 metres and no further than 30 metres from the shaft, in the case of the
surface bank. In the case of the underground stations, hydrants must be within 30
metres of the shaft. Hydrant positions are to be demarcated with the appropriate
symbolic and directional signage.
4. One or more 25 mm fire hosereels may also be installed on the shaft bank and the
underground stations, but these do not remove the strict requirement for hydrants as
stated in 3 above.
5. Timber and other combustibles must not be used when equipping an underground
shaft.
7. At the surface bank, where electrical cables enter the shaft, measures must be taken
to prevent fire spread along the cables from entering the shaft. This is of particular
concern where the shaft is an intake airway. The following measures are acceptable
means whereby this can be achieved:
All cables leading to the shaft can be completely buried for a distance of at
least 2 metres at some position within 10 metres of the edge of the shaft.
STD U4 - INCLINES
Definition
By “incline” is meant an incline roadway or excavation linking the underground workings with
surface. Inclines may typically serve as a route for services such as electrical power and
water, they may have one or more conveyor belt paths running in them, and may serve as an
accessway to the workings for persons on foot and / or vehicles (roadway).
Requirements
1. Irrespective of what other function an incline may serve, an incline in which one or
more conveyor belt paths is installed, shall be subject to the requirements stated in
Standard U5, Underground Conveyors.
2. In an incline in which the requirements stated in 1 above do not apply, but where
rubber-tyred vehicles travel, 65 mm fire hydrants must be provided at 90 metre
intervals. A fire equipment box should be provided at every 3rd hydrant (i.e. at
intervals of 270 metres) containing 3 x 65 mm flat lay fire hoses and a single 65 mm
nozzle.
3. In inclines where no conveyor belt is installed and where no vehicles travel, there is
no requirement for water-based fire fighting capability.
4. Electrical cables installed should be of the red stripe flame retardant type or of the
white stripe “Lotox” type.
5. Having due regard for the direction of the ventilating current, and allowing for possible
reversals in the direction of ventilation, such as may occur during a power outage, or
as a result of an underground fire, underground environmental monitoring stations
should be established to effectively detect fire in every incline.
6. Hot work must only be performed in inclines subject to the provisions of Standard
G11.
7. Combustible materials such as timber should not be used for support or other
purposes in an incline in which vehicles operate and / or in which one or more
conveyor belt paths are installed.
8. Electrical substations and mini substations should not be installed within an incline
excavation if such excavation houses one or more installed conveyor belt paths. In
such case, the substation must be located at the top of the incline, at the bottom of
the incline, or in a side excavation taken off the main incline excavation.
9. Electrical cables and switchgear must be located on the opposite side of the incline to
the conveyor belt. Where the conveyor belt is positioned in the centre of the
excavation, the cables and switchgear must be installed against the sidewall as far as
possible from the conveyor belt path, and in any event, no closer than 1 metre from
the conveyor belt path. The conveyor structure should not be used as a cable rack.
Requirements
2. In order to reduce the fire load represented by the conveyor belt path, no rubber-lined
conveyor idlers should be used. Where drive and other pulleys are lagged, the
lagging must be ceramic, and not rubber.
4. At every “belt risk area” (see below), provide a 65 mm hydrant and a fire hose box
containing at least 2 x 65 mm flat lay fire hoses and 1 x 65 mm fire fighting nozzle.
6. At every second hydrant point contemplated in 5 above, and in any case, at intervals
not exceeding 200 metres, provide a fire hose box containing at least 3 x 65 mm flat
lay fire hoses, and 1 x 65 mm fire fighting nozzle. Where a hose box as contemplated
in 4 above, falls within the spacing requirements of this requirement 6, it shall be
acceptable to rely upon the hose box as contemplated in 4 above, provided that the
number of hoses kept in such box is increased from 2 to at least 3.
Moreover, this exemption shall be applicable only if a site specific risk assessment, to
be repeated at annual intervals, has shown that:
ii) …it can be shown that the extent of the workings of the particular mine are of
such extent as would make the implementation of requirement of 6 above
impracticable and unduly costly.
8. Where a decision has been taken to provide fire fighting hoses and nozzles on
vehicles as contemplated in 7 above, any pre start checklist for such vehicles must
make provision for the inspection of the condition and completeness of the fire
equipment.
9. No fire equipment box or receptacle may be locked or in any other way be made
inaccessible to the general workforce, so that fire fighting equipment is readily
available to any person discovering a fire. Save that this requirement shall not apply
in the case of the fire equipment receptacles to be carried on vehicles. In such case,
the receptacle may be locked, provided that the key is kept together with the key of
the vehicle, in the possession of the allocated driver.
10. At least 1 x 9 kg hand-held DCP fire extinguisher must be provided at every conveyor
drive. This is primarily for use in case of a fire on a drive motor or gearbox, for which
water is unsuitable.
11. All conveyors are to be fitted with belt slip detection devices.
13. Sectional conveyors are to be located only in the out-by in return ventilation, except in
cases where the VOHE Department has determined, for good reason, that a different
location is acceptable.
STD U6 – STONEDUSTING
In terms of the ‘Guideline for the Compilation of a Mandatory Code of Practice for the
Prevention of Flammable Gas and Coal Dust Explosions in Collieries’, Annexure 2,
Section 3 (DME16/3/2/1-A1), every mine shall have in place a Code of Practice
relevant to Stonedusting. This shall be more detailed and mine-specific than the
generic requirements stated below. The COP shall not offer less protection than that
stated below, unless compelling reasons exist which indicate that such lesser
measures would be adequate and where applicable, the relevant DME exemption
must be sought.
Application
In order to effectively control the potential for coal dust explosions, stone dust barriers are
required outbye of each working section, and elsewhere as may be determined by the VOHE
department. The use of bagged stone dust barriers is an alternative to water barriers, and is
the preferred option for AngloCoal operations.
Requirements
1. Four stone dust sub-barriers must be maintained in the outbye of each working section
– See Requirement 8 below.
2. Each plastic bag must contain either 5 kg for low seams or 6 kg for high seams of dry
stone dust complying with the specifications specified previously.
3. The quality, hook and ring as well as the rupture characteristics of the plastic bags
used in bagged stone dust barriers must comply with the specifications of the products
tested at the GP Badenhorst research facility. Documentary evidence as to the source
and quality at each batch of bags purchased must be kept at the mine.
4. The COP(s) in use at the operation must detail how the bags are to be closed so as to
exude water when bags are installed in barriers underground.
5. The COP(s) in use at the operation must clearly specify how the bags are to be
suspended below the roadway roof. The system must ensure that the vertical distance
between suspended bags and the roof, and the horizontal distance between bags and
between the outer bags and sidewalls, are to be maintained at all times.
6. The horizontal distance between the hooks of the bags on a plane must be not less
than 0.4 m and not greater than 1.0 m when measured across the roadway width. The
actual distances are determined by the total mass of stone dust that needs to be
incorporated into a barrier which is itself determined by the roadway dimensions.
for roads in the height range of less than 3,0 m, each row must have a single
level of bags suspended below the roof;
for roads in the height range 3,0 m to 3,5 m, each row must have a single level
of bags suspended not more than 0,5 m below the roof;
for roads in the height range 3,5 m to 4,5 m, each row must have two levels of
bags suspended at approximately 3,0 m and 4,0 m above floor level;
for roads in the height range of more than 4,5 m but less than 6,0m, each row
must have three levels of bags suspended at approximately 3,0 m, 4,0 m and
5,0 m above floor level;
the distance between the bags and the side of the pillar must not be nearer
than 0,5m and not further than 1,0m, the distance measured along the road
between rows of bags within the barrier must be not less than 1,5 m and not
greater than 3,0m;
8. In terms of layout, a full-bagged stone dust barrier must consist of four sub-barriers
installed over a minimum distance of 100 meters of continuous roadway. Three
complete sub-barriers must be in position at all times, while the fourth sub-barrier may
be in the process of being moved ahead as the section advances.
the first sub-barrier, closest to the last road, must not be installed closer than 60m
and not further than 120m from the last through road;
the fourth sub-barrier, furthest from the last through road, must be installed not
more than 120 meters from the first sub-barrier;
the two intermediate sub-barriers must be equidistant between the first and fourth
sub-barriers;
10. In terms of the siting of bagged stone dust barriers, a barrier must be provided:
Every single entry must be protected with a barrier, as for conveyor belt roads.
Application
In order to control the potential for coal dust explosions by the effective inertisation of coal
dust, stone dusting of pillars and rib sides is required. Inertisation of coal dust by the use of
water is also an acceptable alternative, but the preferred method in AngloCoal is the
application of stone dust.
Requirements
Outbye the face area: intake airways must be maintained at a minimum of 65%
incombustible matter content. Workshops, sub-stations, battery charging stations
and other similar places where work is done or equipment is maintained, situated in
intake air must nevertheless be maintained at a minimum of 80% incombustible
matter content.
All accessible roads within 250m radius from areas in the process of being sealed
off, must contain a minimum percentage by mass of incombustible matter content
of 80%, unless the area has been sealed off with explosion proof seals, or other
seals as determined by a risk assessment.
Before any area is sealed off, the roof, sides and floor, as far as reasonably
practicable, must be stone dusted to ensure a minimum percentage by mass of
incombustible matter content of 80%.
2. The following requirements pertain to the minimum quality requirements for stone
dust, as stated in Section 8 of the ‘Guideline for the Compilation of a Mandatory Code
of Practice for the Prevention of Flammable Gas and Coal Dust Explosions in
Collieries’ (DME16/3/2/1-A1).
Stone dust must preferably be pulverized limestone or dolomite and light in colour;
Stone dust must contain not less than 95% by mass of incombustible matter, and
have a density similar or equal to that of pulverised limestone;
Stone dust must contain not more than 5% by mass of free silica, or any other toxic
substance in concentrations detrimental to health;
Stone dust must be of such fineness that, when dry, 100% will pass through a
sieve of 600 micrometers aperture, and at least 50% (by mass) will pass through a
sieve of 75 micrometers aperture;
Stone dust must not cake, and must readily disperse into the air, unless it is directly
wetted by water;
Should any other incombustible dust be used, compliance with the ability to stop
flame propagation of a coal dust explosion must be tested and approved for use at
a SANAS accredited institution.
3. The following requirements pertain to the extent of stone dust application required in
terms of Section 8 of the ‘Guideline for the Compilation of a Mandatory Code of
Practice for the Prevention of Flammable Gas and Coal Dust Explosions in Collieries’
(DME16/3/2/1-A1).
Stone dust must be applied to within 10m of all working faces, unless such workings
are:
inaccessible,
unsafe to enter, or
extend to the face from and including the last through road, in which the coal dust
has been washed from the roof and sides and the floor is too wet to propagate an
explosion.
In pillar extraction operations, stone dust must be applied on a retreat basis at the
same frequency rate as for face areas.
In total extraction operations, stone dust must be injected regularly into the mined
areas before the occurrence of the initial goaf, so as to inert the dust cloud that
will be raised when it occurs.
In return airways of both longwall and shortwall mining operations, stone dust
must be introduced into the return airways during coal winning.
Guideline for the Compilation of a Mandatory Code of Practice for the Prevention of
Flammable Gas and Coal Dust Explosions in Collieries (DME16/3/2/1-A1).
Definition
“Flameproof equipment” is equipment for which a certificate has been issued, declaring it to
be “flameproof”.
Requirements
Definition
Requirements
3. All electrical cables installed underground are to be of the red stripe flame retardant
type. In all new underground applications, white stripe “Lotox” type cable must be
used.
8. The fixed underground substations must always be located in a return airway, or must
be ventilated to a return airway. Arrangements must be provided which can be
activated from a place of safety outside the substation, to open any vents or similar,
necessary to ensure that the smoke and fumes of combustion are effectively routed
directly into the return air system.
10. All MV rooms must be kept locked to prevent unauthorised access. Where
practicable, LT rooms, MCCs and PLC rooms should also be kept locked. Keys must
be kept by a competent person, e.g. an electrician.
11. Whether a fixed gaseous fire suppression system is installed in the fixed underground
substation or not, any ventilation fans and air-conditioners provided in substation
rooms are to be interconnected with the fire detection system so that these will be
tripped out and will cease to operate in response to any fire detected by the automatic
detection system.
12. Any cable trenches interconnecting a substation room with another, or a substation
room with a transformer bay, must be fire stopped wherever cables pass from one
substation to another. At all fire stoppings, the cables must be intumescent coated for
a distance of one meter on either side of such fire stopping unless it is contained in a
sand filled trench of at least 1 m but preferably 2 m. In this regard, refer to Standard
G36.
Identification
A mobile transformer and switch bank forms part of the standard equipment in the coal
cutting / welding section. This is mobile equipment which moves forward as the section
advances. The position in which such equipment is located is therefore a temporary
installation which must nonetheless comply with the following requirements.
Requirements
2. The transformer(s) and all switchgear must be of the dry type (vacuum-type or SF6
filled) to remove the inherent fire load of oil-filled electrical equipment.
5. Lock-out provision must be provided on all electrical switches and sockets on the
mobile switch bank.
Identification
Requirements
3. MV and LT panels must be kept locked at all times, or must be otherwise secured.
The keys should be held by a suitably qualified person, for example, an electrician.
4. All electrical equipment must be of the dry type (i.e. vacuum-type or SF6 filled).
2. There must be access to a 65 mm hydrant point and a fully equipped fire hose box
close within 30 m of every feeder/breaker. In this regard, refer also to Standard U5
pertaining to underground conveyors.
Rationale
The use of all types of plastic piping underground is to be discouraged for four reasons:
All plastic piping is flammable to a lesser or greater degree. Therefore, its use
underground inevitably leads to increased fire loading in the workings.
During combustion, all plastic pipes emit noxious fumes which pollute the
ambient air, posing a health and safety risk to persons in the area.
Plastic pipes constitute an obvious path by which fire may be propagated from
one area to another.
If plastic pipes are used for water, and the water supply routed through the
plastic pipes is used inter alia for fire fighting purposes (via hydrants and / or
hosereels), the risk exists that if the plastic pipes were damaged in a fire, this
could interrupt supply to the hydrants and hosereels and render these
measures ineffective at the very time that they are needed most. Since plastic
pipes will foreseeably fail much sooner than steel pipes in a fire situation,
plastic pipes are undesirable when used to supply hydrants and hosereels.
Requirements
1. No new purchases to be made of uPVC and HDPE piping for use in underground
workings.
2. All existing HDPE piping greater than 50 mm in diameter must be replaced with steel
piping. Where HDPE pipe is already installed underground, and its diameter does not
exceed 50 mm, it may be left in situ, although it is not ideal, providing that the
following requirement is met. Small diameter HDPE pipes may only remain if they are
suspended individually (i.e. not clustered) 300 mm apart.
3. Where pre-existing uPVC and small diameter HDPE piping remains in use, a
firebreak in the pipeline must be constituted by installing a length of steel pipe every
10th pipe length. Note that such firebreak may not be constituted by intumescent
coating or cladding a plastic pipe.
4. Pre-existing uPVC and small diameter HDPE piping which remains in service
underground, must be suspended on the opposite side of the excavation to electric
cables routed in the same excavation. Where this is not possible, a distance of at
least 1 metre must be maintained between the nearest plastic pipe and the
suspended cables.
One or more proto teams must be maintained and equipped in respect of each mine which
has underground operations.
Requirements
Every mine site must have access to at least ten trained Proto Team members within
a reasonable time of being called out.
2. Training
A Proto team shall only be deemed to be competent once all members have
undergone the relevant training as outlined in the Minerals Act and Regulations. This
includes, but is not limited to, exercises with breathing and other mine rescue
apparatus, the reading of mine plans and the detection of poisonous and flammable
gases.
3. Apparatus
All mines must have access to well maintained sets of portable breathing apparatus.
At least two sets per team should be available at any one time. Such equipment must
have sufficient capacity to sustain the wearer for two hours in an irrespirable
environment.
Where a mine is not in possession of the above equipment, the Manager must be
able to produce evidence that the mine has secured the rights to access such
equipment from neighboring mines or some other nearby location.
Two or more devices for the testing of toxic gases and the deficiency of
oxygen.
5. Proto trailers
One or more trailers shall be maintained on surface for the use of the proto teams
when actively engaged on underground fires. Trailers should be positioned close to
the shaft in a position where they can easily be coupled to a vehicle in an emergency.
They should not be kept in a locked yard or building.
Such trailers shall be equipped with adequate quantities of the following equipment,
as determined by the proto manager responsible for the relevant operation. A list of
such equipment, complete with required quantities, shall be taped on each proto
trailer.
Requirements
1. The location and orientation of battery charging bays are comprehensively dealt with in
SANS 1654.
2. Provide at least 2 x 9 kg hand-held DCP fire extinguishers for each battery charger
installed. Of these, at least one must be located at each entranceway leading to the
battery charging bay. Refer to Standard G28 for the mounting requirements pertaining
to fire extinguishers.
3. A clearly worded procedure must be posted up, detailing the steps to be taken during
battery charging.
4. All relevant Material Safety Data Sheets must be posted up in a conspicuous position.
SANS 1654 – DC Powered (battery operated) machines for use in hazardous locations in
mines.
Standard G28 - Hand-held fire extinguishers
Any related mine specific COP
Requirements
2. From all working sections, a lifeline with directional cones must be provided leading to
the refuge bay serving the section, to lead persons to safety even in zero visibility
conditions.
3. In addition to the lifeline and directional cones, symbolic signage must be provided at
every change in direction in the escape route leading from each section to the refuge
bay serving that section. The distance between such signage should in any case not
exceed 300 metres, even if there is no change in direction.
4. A refuge bay must be provided within 1000 metres, or 750m if so prescribed by the
mine standard, of every working section. Moreover, a refuge bay must be available
within 1000 metres (or 750m) of any location in which persons are required to work.
Cognisance must be taken of persons working in back areas.
5. Where, for whatever reason, it is not possible to comply with the 1000 metre
requirement described in Requirement 4 above, persons working in the affected area
must be issued with additional standard self-contained self-rescuers, or long-life self-
contained self-rescuers. All units so issued must be approved by the inspectorate, and
such allowance is only permissible if a dispensation has been granted by the
inspectorate.
6. The size of each refuge bay shall be calculated to allow 1.8 m² per person working in
the area if possible. In no case shall a factor less than 0.5 m² per person be used.
7. Where at all possible, fixed refuge bays should be cut into a solid pillar, so that only the
front wall is vulnerable. The length of built wall should be minimised as far as possible,
since this is more vulnerable to damage in an emergency that walls cut into the solid
pillar.
8. Refuge bays must be provided within the maximum distance which persons have been
determined to be able to travel within the duration of the self-contained self-rescuers
with which they are issued upon proceeding underground. A risk assessment must be
conducted in terms of the relevant legislation, to determine such distance.
Such risk assessment must take cognisance of the physical capacity of all persons
regularly employed in the area served by the refuge bay in question, and the physical
characteristics of the route through which such persons will be required to travel. In
any case, the distance of travel to the refuge bay must not exceed 1000m from any
place where persons are required to work.
All construction materials used in the refuge chamber and all equipment
installed must be incombustible.
Not positioned between an intake airway and a return airway such that there
could be leakage of fumes through the chamber. The refuge chamber may
however be positioned wholly in either intake or return airways.
As far as possible, permanent refuge chambers must be cut into solid coal
with a single entry and bricked off with two stopings equipped with steel man
doors.
An air supply must be provided which is independent of the ambient air.
Provided that the chosen measure can be shown to be adequate, an
alternative supply of respirable air, other than e.g. air drawn through a surface
borehole, may be utilised (e.g. a bank of oxygen candles).
A chemical toilet.
A double airlock door arrangement that provides an effective seal.
A means to communicate effectively and reliably with surface, e.g. a
telecommunications link.
An up-to-date list of telephone numbers must be posted up, where the
communications link to surface is a telephone.
The refuge bay must be clearly demarcated with suitable symbolic and
informational signage to ensure that it is visible from all directions and from all
possible access ways leading to it.
An effective audible and visual signalling system must be provided to indicate
the position of the refuge bay.
An adequate supply of first aid equipment, including blankets and stretchers.
Quantities will depend upon the number of persons served by the refuge
chamber.
Refuge bays must be named according to the underground area that they
serve. The name will be posted up using reflective signs on the inside and
outside of the chamber with a similar number on the borehole enclosure on
surface.
The refuge chambers must be indicated on the mine ventilation and rescue
plans and will be numbered corresponding to the refuge chambers.
Notices must be posted up on which are legibly printed in English and another
appropriate language, simple directions setting forth the approved procedures
for the immediate treatment of cases of gassing, heat stroke, heat exhaustion,
drowning and electric shock.
Adequate illumination.
Underground environmental monitoring detection heads of types deemed
suitable for this application by the VOHE Department, must be provided in the
refuge chamber, and must report to the surface control room.
Where any of the above requirements are dependent upon electrical power,
except lighting, an uninterruptible power supply must be provided.
Regulation 24.20.2.1
Regulation 24.20.2.2
Regulation 24.1.1
Regulation 24.1.2
Regulation 24.6
Requirements
Mobile refuge bays must comply with the relevant requirements for refuge bays as stated in
Standard U15. The following requirements pertain in particular to mobile refuge bays:
1. Since the mobile / containerised refuge bay will have steel walls, it is not intended to
protect persons inside if the area in which the chamber is located is itself involved in
the fire. Therefore, containerised refuge chambers must be carefully located to
ensure ambient temperatures in the immediate vicinity are unlikely to rise to
unbearable levels, or the refuge container will not sustain life.
2. All mobile refuge chambers must be fitted with some form of oxygen generator,
unless a permanent supply of fresh air can be provided, as for a fixed refuge
chamber.
3. All mobile refuge chambers must be fitted with some form of carbon dioxide scrubber,
unless a permanent supply of fresh air can be provided, as for a fixed refuge
chamber.
4. Every mobile containerised refuge chamber must be equipped with a refrigeration unit
of adequate capacity to maintain temperatures which can sustain human life, given
the maximum number of persons permitted to take refuge in such mobile chamber,
and the highest foreseeable ambient temperature in the area in which the mobile
chamber is to be located.
6. The position in which any mobile containerised refuge chamber is positioned, must be
surveyed in and accurately demarcated on the relevant survey plans, on the same
day that the mobile container is so positioned. This is vital to ensure that it is possible
to drill an emergency borehole from surface accurately in order to evacuate persons
taking refuge in such a mobile container during an emergency. Furthermore,
cognisance must be taken of surface structures to ensure that the Rescue brigade
drill rig will have access to the correct site.
8. Whilst all equipment listed in Standard U15, Requirement No 3, remain relevant in the
case of mobile containerised refuge chambers, particular attention is drawn to the
requirement for a double airlock door, a feature which most containerised refuge
chambers available at the time of writing, do not provide. Since most mobile refuge
chambers will rely upon an oxygen generator and a carbon dioxide scrubber
arrangement to maintain a respirable atmosphere within the chamber, it is vital that
repeated opening of the door does not permit contaminated air to enter the refuge
chamber, since it is not foreseeable that these devices could cope with this added
demand and the atmosphere within the refuge chamber could otherwise become
unsuitable to sustain life, rendering the refuge chamber useless.
It is desirable to seal off worked out areas where possible. This limits the extent of the
workings over which supervision must be exercised, and reduces the potential area in which
a fire can start which could affect the current workings.
Worked out areas must be sealed off according to a method laid down in a COP specific to
the particular mine, and compiled in accordance with the guidelines prescribed by the DME.
Introduction
Continuous on–line monitoring systems will facilitate the establishment and maintenance of a
safe environment underground if well installed, maintained and monitored.
Such a system will give early warning of a fire, spontaneous combustion heating, abnormal
methane or carbon monoxide gas concentrations and a failure or weakening of the air flow.
Prompt action can then be taken to deal safely with the abnormal situation provided controls
are in force.
It is the policy of Anglo Coal that all collieries must be equipped with environmental
monitoring systems. The following guidelines will assist in selecting an appropriate
environmental monitoring system. In all instances attention is drawn to the requirements of
the Mines and Works Act and Regulations which are minimum requirements.
Monitoring Strategy
The Mine Manager assisted by the consulting Mechanical and Electrical Engineer and the
Environmental Engineering Department should determine an appropriate monitoring strategy
for each mine.
All collieries are to be equipped with a mine wide fire detection system. The siting of
the monitors is detailed in Requirement 1.
Requirements
The monitoring of air velocity at strategic positions will indicate the status of the air
distribution in the mine on a continuous basis. The velocity monitors will give early
warning of a weakening in airflow or a ventilation failure. It will also indicate a
weakening trend in airflow and action can therefore be taken timeously and before a
gas accumulation develops.
4. Barometric Pressure
5. Main Fans
Main fans should be monitored to give warning of a fan failure by a fail to safe
system. Underground power feeders shall be interlocked with the fan operation. Other
main fan functions may also be included.
6. Lightning Protection
In areas where there is a high lightning ground flash density, suitable lighting
protection must be fitted to ensure the effective operations of the monitoring system.
7. Control Room
A facility must be provided to give alarms for each monitoring point taking into
account gas concentrations and duration of peaks that may be caused by
diesels and blasting. Unwanted alarms can thereby be eliminated.
The control room must be manned 24 hours a day. Where this is not possible
an automatic dial-out facility or other arrangements to be made.
The operator in the control room plays an important part in the effective
operations of the system. He therefore requires thorough training in the
operation of the system. He must be fully conversant with the alarm
diagnostics and call-out procedures in the event of an alarm.
The monitoring points must be shown clearly on a rescue plan kept in the
control room, plan to updated quarterly as well as on the installation and
removal of all monitoring points.
8. Maintenance
The section engineer or other appointed person should be responsible for the
installation and maintenance of the environmental monitoring equipment.
The environmental officer must specify his requirements and bring to the
attention of the responsible section engineer or person any problems
regarding the installation or maintenance of the equipment in writing.
cleaning of monitors
The system must be inspected and checked from the control room on a
regular basis by the Electrical Foreman or other person responsible for the
maintenance of the system.
The telemetry cable should preferably have a distinctive colour for easy
recognition, i.e. a canary yellow colour is being used at present.
Continuous Miners
2. The airflow across the cutting heads shall be appropriate in relation to the position of
the continuous methane monitor on the machine so that the methane detector
samples air returning from the cutting heads.
3. Continuous miners shall be equipped with a means of constantly monitoring the water
supply pressure and flow rate to the machine and of automatically raising an alarm if
the pressure drops below a predetermined level. Such system shall also cause the
machine to cut out if the pressure drops below a lower predetermined level.
4. Each operating continuous miner shall have readily available, a hose of minimum
diameter 25 mm and minimum length 15 metres, connected to the high pressure
water supply to the machine which may be used inter alia for manual fire fighting in
the area in which the CM is operating.
5. All continuous miners must have a valid, current, flameproof certificate before being
permitted to operate.
Sectional vehicles
1. Such vehicles shall not be required to carry on-board fixed automatic detection and
suppression systems, or on-board hand-held fire extinguishers, on condition that:
In one or more central and easily accessible position within the relevant
section, a minimum of 6 x 9 kg hand-held DCP fire extinguishers must be
kept.
2. All sectional vehicles must have a valid, current, flameproof certificate before being
permitted to operate.
The following requirements pertain to all vehicles which operate primarily underground, but
which may move freely throughout all areas of the underground workings, whether within the
flameproof zones in each section or not, and which may travel periodically to surface.
1. Depending on the size of the vehicle, one or two 9 kg hand-held DCP fire
extinguishers shall be securely mounted in easily accessible positions on the vehicle.
2. Such vehicles are to be fitted with fixed dry chemical powder fire extinguishing
systems covering all risk areas of the machine such as the engine, gearbox and
hydraulics areas. The system should be capable of automatic discharge in response
to a signal received via linear wire routed throughout the abovementioned risk areas
in which the nozzles are located, or manually by means of activation buttons or
plungers to be provided at least at the driver’s cabin in the case of smaller machines
or at the driver’s cabin and at one other external position in the case of larger
machines. Such buttons or plungers are to be colour-coded red, and if necessary,
demarcated.
All discharge nozzles on fixed on-board fire suppression systems are to be fitted with
caps to prevent the clogging of such nozzles. The inspection of such anti-clog caps is
to be included in the pre-use checklists applicable to each machine.
STD U20 - UNDERGROUND DIESEL & OIL STORES, INCLUDING OIL SEPARATION
EQUIPMENT
Requirements
1. Diesel and oil stores must be bunded. Aggregate filling of bunds is inappropriate in
the underground environment. See Standard G33 regarding bund requirements.
2. No electric motor, cable, light or switch may be positioned within the bund of an
underground diesel or oil store unless such equipment is intrinsically safe, or unless it
is raised on a platform or plinth and is resultantly located at a height higher than the
top of the bund wall.
3. Where diesel or oil is stored in a bulk tank (i.e. not in drums or containers), such bulk
container must be effectively earthed.
4. Where the intention of the facility is to transfer any flammable liquid between a bulk
tank and a rubber-tyred vehicle, an earthing clamp must be provided, and a
procedure must be enforced which requires the driver of such vehicle to affix the
earthing clamp to his vehicle during any such transfer of flammable liquid between his
vehicle and the bulk tank in question.
5. Bulk flammable liquid tanks in the underground workings must be totally enclosed in a
cubby excavated for that express purpose. The front of the cubby must be sealed off
with a 225 mm brick wall, in which is set a tightly fitting steel door which must be kept
closed under all normal circumstances.
6. All cable and pipe apertures in wall(s) of the bulk flammable liquid store must be fire
stopped with a suitable inert material of similar fire resistance to the wall itself (i.e. 2
hours). Refer to Standard G36 regarding requirements for fire stopping.
10. Post signage on the outer wall of the enclosure within which the tank(s) are located,
prohibiting smoking and naked lights. These must be clearly visible to persons
entering the enclosure via the entrance door or doors provided.
11. The criticality of the diesel or oil store must be evaluated in terms of the criteria set
down in Standard G47. If the installation is assessed as critical, additional protection
should be provided. This may be in one of the following forms:
A manually activated fire sprinkler system, discharging over the tanks. Refer to
Standard G2 for the requirements pertaining to such systems.
A high velocity water deluge system, discharging over the tanks. Refer to
Standard G5 for the requirements pertaining to such systems.
A foam fixed fire suppression system, discharging over the tanks. Refer to
standard G6 for the requirements pertaining to such systems.
12. Where an installation has been assessed as critical, and where a manual or
automatic fire sprinkler system has been installed over the storage tanks, a flush
valve must be fitted to the end of each pipe on which sprinkler heads are mounted.
The system must be tested and flushed for at least 3 minutes once in every 30 days.
The results of such test must be logged, and signed off by the responsible mine
overseer. Where deviation is noted, such mine overseer shall initiate the necessary
action to ensure that the deviation is rectified in the shortest possible time.
13. Oil separation equipment may be globally bunded but must be bunded separately
from the diesel and / or oil store.
14. All feed and supply lines must be able to inhibit fire spread either by means of
inverted u-tubes or non-return valves.
16. All diesel, oil stores and oil separation equipment must be located in areas which are
ventilated to a return airways or a return air pass.
17. The volume of each oil or diesel tank must be clearly demarcated on the tank itself.
This standard must be read in addition to Standards G29, G30 and G31.
1.1 General
This Standard provides the minimum requirements for the routine inspection, testing,
and maintenance of standpipe and hose systems. Table 1 must be used to determine
the minimum required frequencies for inspection, testing, and maintenance.
1.2 Inspection
Table 2 must be used for the inspection, testing, and maintenance of all
classes of standpipe and hose systems.
1.3 Testing
A flow test must be conducted every 5 years at the hydraulically most remote
hose connection of each zone of an automatic standpipe system to verify the
water supply still provides the design pressure at the required flow.
Where a flow test of the hydraulically most remote outlet(s) is not practical, the
supervisor having jurisdiction must be consulted for the appropriate location
for the test.
All systems must be flow tested and pressure tested at the requirements in
effect at the time of the installation.
A main drain test must be performed on all standpipe systems with automatic
water supplies in accordance with the requirements of NFPA 25.
The test must be performed at the low point drain for each standpipe or the
main drain test connection where the supply main enters the building (when
provided).
Pressure gauges must be provided for the test and must be maintained.
Where provided, water flow alarm and supervisory devices must be tested on
a quarterly basis.
1.6 Maintenance
Hose Connections. After each use, all hose connected to sprinkler systems must be
cleaned, drained, and thoroughly dried before being placed in service. Hose that has
been exposed to hazardous materials must be disposed of in an approved manner or
must be decontaminated by a method approved for the contaminant and by the hose
manufacturer’s recommendation. Equipment that does not pass the inspection or the
testing requirements must be repaired and tested again or replaced.
2.1 Introduction
A water pressure and flow test must be conducted at intervals not exceeding 90 days
on all fire water distribution systems to determine the rate of flow and pressure
available for fire-fighting purposes.
2.2 Procedure
Tests must be conducted during a period of expected normal demand. The procedure
must consist of discharging water at a measured rate of flow from the system at a
given location and observing the corresponding pressure drop in the mains.
All new systems must be tested prior to the occupancy of the building or area which
they serve. Any installing contractor must provide an appropriate test certificate.
All piping in the system must be flushed with a sufficient volume of water in order to
remove any construction debris and trash accumulated in the piping prior to the
completion of the system and prior to the installation of the fire department
connection.
Installers of all new systems must have their system(s) hydrostatically tested in
accordance with SABS 1128 - Part 2 and SABS 0287, and must provide at their cost,
The hydrostatic test pressure must be measured at the lowest elevation point
of the individual system or zone being tested. The piping system must show
no leakage.
During the hydrostatic test, the pressure gauge at the extremities of the piping
must be observed and the pressure recorded.
The water supply must be tested to verify compliance with the design.
This test must be conducted by flowing water from the hydraulically most remote and
high hose connection (hydrant).
Static and residual inlet pressure and static and residual outlet pressure and flow
must be recorded on the contractor’s test certificate.
The main drain valve must be opened and must remain open until the system
pressure stabilises. The static and residual pressure must be recorded on the
contractor’s test certificate.
Any alarm or detector (supervisory device) associated with the fire fighting water
supply must be tested in accordance with NFPA 72.
3.5 Instructions
A copy of NFPA 25, the Standard for the Inspection, Testing, and Maintenance
of Water-Based Fire Protection Systems
4.1 Frequency
A hydrant test under simulated fire conditions must be conducted at intervals not
exceeding 12 months, in every building or area served by the fire water system.
After the location where the test is to be conducted has been determined, a
representative group of test hydrants are selected in the vicinity. Once selected, due
consideration is given to potential interference with traffic flow patterns, damage to
surroundings (e.g. roadways, sidewalks, landscapes, vehicles, and pedestrians), and
potential flooding problems both local and remote from the test site.
One hydrant, designated the residual hydrant, is chosen to be the hydrant where the
normal static pressure will be observed with the other hydrants in the group closed,
and where the residual pressure will be observed with the other hydrants flowing.
This hydrant is chosen so it will be located between the hydrant to be flowed and the
large mains that constitute the immediate sources of water supply in the area.
Figure 1
In the figure above, test layouts are indicated showing the residual hydrant
(designated ‘R’) and hydrants to be flowed (designated ‘F’). The number of hydrants
used in any test depends upon the number of hydrants which will foreseeably be
used in combating a fire in the particular area, save that in no case are more than 3
hydrants required to be tested simultaneously.
4.3 Equipment
The equipment necessary for field work consists of a single Bourdon pressure
gauge, a number of Pitot tubes and a special hydrant cap tapped with a hole
into which a short length of brass pipe is fitted. This pipe is provided with a T
connection for the gauge and a cock at the end for relieving air pressure.
Pressure gauges are to be calibrated every 12 months, or more frequently,
depending on use.
When more than one hydrant is flowed, it can be desirable and necessary to
use portable radios to facilitate communications.
In a typical test, the gauge is attached to one of the 65 mm outlets of the residual
hydrant using the special cap, the cock on the gauge piping is opened, and the
hydrant valve is opened full. As soon as the air is exhausted from the barrel, the cock
is closed. A reading (static pressure) is taken when the needle comes to rest.
At a given signal each of the other hydrants is opened in succession, with discharge
taking place directly from the open hydrant butts. Hydrants should be opened one at
a time. With all hydrants flowing, water should be allowed to flow for a sufficient time
to clear all debris and foreign substances from the stream(s).
At that time, a signal is given to the people at the hydrants to read the Pitot pressure
of the streams simultaneously while the residual pressure is being read. The final
magnitude of the pressure drop can be controlled by the number of hydrants used
and the number of outlets opened on each.
After the readings have been taken, hydrants should be shut down slowly, one at a
time, to prevent undue surges in the system.
In practically all cases, the 65 mm outlets are filled across the entire cross
section during flow. When measuring the Pitot pressure of a stream of
practically uniform velocity, the orifice in the Pitot tube is held downstream
approximately one-half the diameter of the hydrant outlet or nozzle opening,
and in the centre of the stream. The centreline of the orifice should be at right
angles to the plane of the face of the hydrant outlet. The air chamber on the
Pitot tube should be kept elevated. Pitot readings of less than 70 kPa and
more than 200 kPa should be avoided, if possible. Opening additional hydrant
outlets will aid in controlling the Pitot reading.
With dry barrel hydrants, the hydrant valve should be wide open. The hydrant
valve for the flowing outlet should be wide open. This opening gives a more
streamlined flow and a more accurate Pitot reading.
Figure 2
If a Pitot tube is not available for use to measure the hydrant discharge, a 3.5 or 4.0
bar gauge tapped into a hydrant cap can be used.
The hydrant cap with gauge attached is placed on one outlet, and the flow is allowed
to take place through the other outlet at the same elevation.
The readings obtained from a gauge so located, and the readings obtained from a
gauge on a Pitot tube held in the stream, are approximately the same.
Flow test results show the strength of the distribution system and do not necessarily
indicate the degree of adequacy of the entire water works system. Consider a system
supplied by pumps at one location and having no elevated storage. If the pressure at
the pump station drops during the test, it is an indication that the distribution system is
capable of delivering more than the pumps can deliver at their normal operating
pressure.
It is necessary to use a value for the drop in pressure for the test that is equal to the
actual drop obtained in the field during the test, minus the drop in discharge pressure
at the pumping station.
If sufficient pumping capacity is available at the station and the discharge pressure
could be maintained by operating additional pumps, the water system as a whole
could deliver the computed quantity. If, however, additional pumping units are not
available, the distribution system would be capable of delivering the computed
quantity, but the water system as a whole would be limited by the pumping capacity.
The portion of the pressure drop for which a correction can be made for tests on
systems with storage is generally estimated upon the basis of a study of all the tests
made and the pressure drops observed on the recording gauge at the station for
each. The corrections can vary from very substantial portions of the observed
pressure drops for tests near the pumping station, to zero for tests remote from the
station. It is preferable to flow water past the residual hydrant.
Hydrant reticulation must be fitted with strategically placed stop valves which
facilitate isolation of damaged sections of the installation without interruption
to the remaining reticulation.
Nozzle sizes must never exceed 16mm diameter. Where pressure and/or flow
is relatively poor 13 mm nozzles may be used to produce an effective jet.
Fire hoses must always be stored correctly made up with the female fitting on
the inside of the roll.
Each fire hose must have water passed through it at least once every year
and must then be thoroughly dried before being re-made up.
Hose coupling lugs must be oiled after water has been passed through the
hose.
The water supply for the hydrant system, as stated below, is over and above all water
supply requirements, where applicable, for any:
Moreover, supply to meet domestic and service water requirements must be provided
separately and independently of the supply for fire fighting purposes.
5.5 Testing
A fire team member, fire officer, fire marshal, or other appointed person must
carry out daily visual checks on lugs, washers, hand wheels, open and shut
valve indicators and water pressures (where a gauge is provided).
The minimum frequency for hydrant testing under simulated fire conditions is
once in every 12 months, and following any structural maintenance or
alterations to system(s).
The water level must be checked daily in all supply dams, tanks or reservoirs.
Electric Pumps
Diesel Pumps
a) Ensure that the temperature of the pump house or area where the pump is
located is above 10°C.
b) Check oil level in the engine sump.
c) Check water level in the engine closed circuit cooling system.
d) Check batteries by means of a hydrometer or low voltage tester to ensure that
each cell is charged and that electrolyte is at correct level.
e) Check that the battery charger is working correctly.
f) Check that the engine fuel tank is full and that there is a reserve supply
sufficient to run the engine on full load for 6 hours.
g) The pump should start automatically in response to a pressure drop in the
system.
h) The pump should also be capable of starting by means of a manual start
button.
i) Run the pump for at least 30 minutes and record the running hour total shown
on the hour meter after the test.
j) Replenish the fuel used during the test.
l) The engine must be serviced in accordance with the manufacturer's
specifications.
1. SYSTEM REQUIREMENTS
Hosereel stop valves must be sealed with lead or plastic seals and reserved
solely for fire fighting purposes.
The internal diameter of the service pipe feeding a hosereel system must be a
minimum of:
o 32 mm if it serves 1 to 3 hosereels.
o 38 mm if it serves 4 or 5 hosereels.
o 50 mm if it serves more than 5 hosereels.
Every hosereel system must be fitted with one or more pressure gauges
reading up to 2 500 kPa. One must be situated at the hosereel furthest from
the incoming water supply.
The following is a typical hosereel system layout, illustrating the application of the
above requirements.
Figure 1
2.3.1 Reconditioning
Carry out reconditioning in accordance with SABS 1475: Part I once every 3 years or
more frequently when circumstances so require.
In years where reconditioning is not required, carry out on-site maintenance annually
in accordance with the following guidelines:
a) Remove and check the nozzle-cock for blockage, then refit the nozzle-cock.
b) Hosereels must be fully extended once a year. Note that more frequent
extension causes damage to the hosereel spindle and glands. Completely
unwind the hose from the reel. During the unwinding operation, check:
Whether the reel rotates freely on its spindle. If necessary, lubricate the
spindle or replace the spindle and / or spindle bush.
Whether the hose runs out freely through the hose run-out guide. If
necessary, lubricate or replace the run-out guide.
c) Open the discharge nozzle-cock and, using water, purge all air from the reel
and hose. Close the nozzle-cock, increase the water pressure to 2 000 kPa
and, while the hose is under pressure, check
f) Rewind the hose neatly but without undue tension on the reel. Place the
discharge nozzle-cock in its stowage bracket.
g) Sign the maintenance label or sign and attach a new maintenance label.
SABS 1475: Part 1 - The production of reconditioned fire-fighting equipment: Portable and
wheeled (mobile) rechargeable fire extinguishers (Formerly, The production of reconditioned
fire-fighting equipment: Portable rechargeable fire extinguishers)
Standard G31 - 25 mm fire hosereels
1. GENERAL
1.1 Distribution
The following are examples for some of the more common occupancy types.
In Anglocoal, the ‘Wholesaler’ classification would apply to Mine Stores and Mine
Offices, and ‘High Risk Commercial would apply to all plant areas, for example.
1.2 Siting
extinguisher is deployed. The points below are guidelines only, and it may be
necessary to deviate from them in certain situations:
To ensure ready access, distribute units evenly over the entire floor area.
Special risk areas such as flammable liquid magazines, dip tanks, transformer
rooms, spray booths etc. should have extinguishers near at hand but not too
close to the risk where they could become involved in the fire themselves, or
be impossible to reach. Position units in cases such as this, more than 15 m
from the risk, but not more than 25 m away, or around a corner.
Low temperatures are liable to affect the operation of most extinguishers and
for this reason they should not be sited in areas where the temperature is
likely to drop below 4°C. If water extinguishers ar e exposed to severe weather
conditions then suitable antifreeze should be considered (consult the
manufacturers).
1.8 The high-level red and white diagonal stripes with the symbolic sign below should be
easily seen from a distance. Demarcated lines on the floor indicate that nothing may
be placed on the floor below the extinguisher.
1.9 High temperatures could lead to the rupturing of stored pressure type, vaporising
liquid and carbon dioxide extinguishers. The foam compound in foam extinguishers
could deteriorate in hot areas and if temperatures are likely to exceed 43°C it is
advisable to consult the extinguisher suppliers or manufacturers.
1.10 Corrosive atmospheres could reduce the life expectancy of the extinguisher body and
it is therefore important that inspections are carried out at most frequent intervals than
is normally recommended.
1.11 Vibration also constitutes a siting problem in that dry powder may become compacted
in areas such as hammer mills, and when mounted on vehicles. Under such
conditions it is essential that the extinguisher is securely bracketed and frequently
inspected.
1.3 Maintenance
Stored
Stainless steel 1 5 5
pressure
Cartridge 1 1
Mild steel NA
Stored
Foam Mild steel pressure NA 1 5
Stored
Stainless steel 1 5 5
pressure
Stored
CO2 - 1 5 5
pressure
Stored
Mild steel 1 5 5
pressure
Mild steel
Cartridge NA 1 3
Dry powder
Stored
Aluminium pressure 1 5 5
Stored
Stainless steel 1 5 5
pressure
More frequent maintenance is required for extinguishers that are mounted on vehicles
or that are subject to vibration, because the powder is more likely to become
compacted.
For convenience, the following checklists are organised into two parts. The first,
Table 3, is arranged by mechanical parts (components and containers) common to
most fire extinguishers. The second, Table 4, is arranged by extinguishing material
and expelling means and involves a description of the problems peculiar to each
agent.
2.1 Recordkeeping
In addition to the required tag or label, a permanent file record should be kept for
each fire extinguisher. This file record should include the following information, as
applicable:
a) The maintenance date and the name of person or agency performing the
maintenance
b) The date when last recharged and the name of person or agency performing
the recharge
c) The hydrostatic retest date and the name of person or agency performing the
hydrostatic test
d) Description of dents remaining after passing a hydrostatic test
e) The date of the 6-year maintenance for stored-pressure dry chemical.
The “Verification of Service” collar design also requires that the valve be removed
before the collar can be attached to the extinguisher. The collar provides the
authorities having jurisdiction with a more convenient visual proof that the
extinguisher was disassembled and that maintenance was performed. This standard
does not specifically require a “Verification of Service” collar when a hydrostatic test
is performed on a fire extinguisher cylinder.
All extinguishers are to have the valve removed for hydrotesting and are to be
subsequently recharged before they are returned to service. To be valid, the date on
the “Verification of Service” collar should always be the same or more recent than the
date on the hydrotest label.
a) Make sure all pressure is vented from fire extinguisher before attempting to
remove valve body or fill closure.
WARNING: Never connect the fire extinguisher to be charged directly to the high-
pressure source. Connecting directly to the high-pressure source could cause the
container to rupture, resulting in injury. Never leave a fire extinguisher connected to
the regulator of a high-pressure source for an extended period of time. A defective
regulator could cause the container to rupture due to excess pressure
j) Use proper safety seals, as other types, such as meter seals, could possibly
fail to break at the prescribed requirements.
3.1 Some manufacturers require that their fire extinguishers be returned to the factory for
recharging.
3.2 To determine the gross weight, the entire fire extinguisher should be weighed empty.
The weight of the specified recharge agent should be added to this amount.
The leak test required for stored-pressure and self-expelling types should be
sufficiently sensitive to ensure that the fire extinguisher will remain operable for at
least 1 year. Any tamper indicators or seals need to be replaced after recharging.
The intent of this provision is to maintain the efficiency of each fire extinguisher as
produced by the manufacturer and as labelled by one or more of the fire testing
laboratories. For example, the extinguishing agent and the additives used in the
various types of dry chemical fire extinguishers vary in chemical composition and in
particle size and, thus, in flow characteristics. Each fire extinguisher is designed to
secure maximum efficiency with the particular formulation used. Changing the agent
from that specified on the fire extinguisher nameplate could affect flow rates, nozzle
discharge characteristics, and the quantity of available agent (as influenced by
density), and would void the label of the testing laboratory.
Dry powder used for combustible metal fires (Class D) should not become damp as
the powder will not be free flowing. In addition, when dry powder contains sufficient
moisture, a hazardous reaction could result when applied to a metal fire.
3.5 Mixing multipurpose dry chemicals with alkaline based dry chemicals could result in a
chemical reaction capable of developing sufficient pressures to rupture a fire
extinguisher. Substituting a different formulation for the one originally employed could
cause malfunctioning of the fire extinguisher or result in substandard performance.
In general, carbon dioxide obtained by converting dry ice to liquid will not be
satisfactory unless it is properly processed to remove excess water and oil. If dry ice
converters are used, the following required steps should be taken.
b) An extra operation is required to minimise the water within the converter. This
operation consists of blowing off a short burst of liquid carbon dioxide from the
bottom of the converter in order to blow off free water. This operation can only
be performed above 32°F (0°C). With the converter c ontents colder than 32°F
(0°C), blowing off is ineffectual.
a) Gauges intended for use with aluminium or plastic valve bodies are marked
with a line above the gauge manufacturer’s code letter.
b) Gauges intended for use with brass or plastic valve bodies are marked with a
line below the manufacturer’s code letter.
c) Universal gauges that can be used with aluminium, brass, or plastic valve
bodies are marked with lines above and below the manufacturer’s code letter
or by the absence of any line above or below the manufacturer’s code letter.
Using the proper replacement gauge as to pressure range, extinguishing
agent, and valve body compatibility is recommended to avoid or to reduce
gauge-related problems.
1. GENERAL
1.1 Scope
The minimum requirements for the inspection, testing, and maintenance of the fire
alarm systems are described in this Standard.
1.1.1 Inspection, testing, and maintenance programs must satisfy the requirements of
these Standards, must conform to the equipment manufacturer’s recommendations,
and must verify correct operation of the fire alarm system.
1.1.2 System defects and malfunctions must be corrected. If a defect or malfunction is not
corrected at the conclusion of system inspection, testing, or maintenance, the system
owner or the owner’s designated representative must be informed of the impairment
in writing within 24 hours.
1.1.3 Nothing in this Standard must be intended to prevent the use of alternate test
methods or testing devices. Such methods or devices must provide the same level of
effectiveness, and safety, and must meet the intent of the requirements of this
standard.
1.1.4 The requirements of this standard must apply to both new and existing systems.
1.2 The owner or the owner’s designated representative must be responsible for
inspection, testing, and maintenance of the system and alterations or additions to this
system. The delegation of responsibility must be in writing, with a copy of such
delegation provided to any jurisdiction upon request.
1.2.2 Service personnel must be qualified and experienced in the inspection, testing, and
maintenance of fire alarm systems.
1.3 Notification
1.3.1 Before proceeding with any testing, all persons and facilities receiving alarm,
supervisory, or trouble signals, and all building occupants, must be notified of the
testing to prevent unnecessary response. At the conclusion of testing, those
previously notified (and others, as necessary) must be notified that testing has been
concluded.
1.3.2 The owner or the owner’s designated representative and service personnel must
coordinate system testing to prevent interruption of critical building systems or
equipment.
1.4 Prior to system maintenance or testing, the system certificate and the information
regarding the system and system alterations, including specifications, wiring
diagrams, and floor plans, must be provided by the owner or a designated
representative to the service personnel upon request.
Requirements pertinent to testing the fire alarm systems initiating fire suppression
system releasing functions must be covered by the following points:
1.5.1 Testing personnel must be qualified and experienced in the specific arrangement and
operation of a suppression system(s) and a releasing function(s) and cognisant of the
hazards associated with inadvertent system discharge.
1.5.2 Occupant notification must be required whenever a fire alarm system configured for
releasing service is being serviced or tested.
1.5.4 Testing must include verification that the releasing circuits and components energised
or actuated by the fire alarm system are electrically supervised and operate as
intended on alarm.
1.5.5 Suppression systems and releasing components must be returned to their functional
operating condition upon completion of system testing.
All new systems must be inspected and tested in accordance with the requirements
of this standard.
1.6.2.2 Changes to all control units connected or controlled by the system executive
software must require a 10 percent functional test of the system, including a
test of at least one device on each input and output circuit to verify critical
system functions such as notification appliances, control functions, and off-
premises reporting.
2. TEST METHODS
At the request of the authority having jurisdiction or approved inspection authority, the
installation must be inspected for complete information regarding the system,
including specifications, wiring diagrams, and floor plans that have been submitted for
approval prior to installation of equipment and wiring.
2.2 Fire alarm systems and other systems and equipment that are associated with fire
alarm systems and accessory equipment must be tested according to the following
table.
Device Method
Batteries – General Prior to conducting any battery testing, the person conducting
Tests the test shall ensure that all system software stored in volatile
memory is protected from loss.
a) Visual Inspection Batteries shall be inspected for corrosion or leakage. Tightness
of connections shall be checked and ensured. If necessary,
battery terminals or connections shall be cleaned and coated.
Electrolyte level in lead – acid batteries shall be visually
inspected.
b) Battery Batteries shall be replaced in accordance with the
Replacement recommendations of the alarm equipment manufacturer or when
the recharged battery voltage or current fall below the
manufacturer’s recommendations.
c) Charger Test Operation of battery charger shall be checked in accordance
with charger test for the specific type of battery.
d) Discharge Test With the battery charger disconnected, the batteries shall be
load tested following the manufacturer’s recommendations. The
voltage level shall not fall below the levels specified.
Exception: An artificial load equal to the full fire alarm load
connected to the battery shall be permitted to be used in
conducting this test.
e) Load Voltage With the battery charger disconnected, the terminal voltage shall
Test be measured while supplying the maximum load required by its
application.
The voltage level shall not fall below the levels specified for the
specific type of battery. If the voltage falls below the level
specified, corrective action shall be taken and the batteries shall
be retested.
Exception: An artificial load equal to the full fire alarm load
connected to the battery shall be permitted to be used in
conducting this test.
Battery Tests (Specific Types)
a) Primary Battery The maximum load for a primary battery shall not be more than
Load Voltage 2 amperes per cell. An individual (1.5 volt) cell shall be replaced
Device Method
Test when a load of 1 ohm reduces the voltage below 1 volt. A 6 volt
assembly shall be replaced when a test load of 4 ohms reduces
the voltage below 4 volts.
Device Method
resistance per volt. Systems in which each circuit is
supplied by an independent current source require tests
between ground and each side of each circuit. Common
current source systems require voltage tests between
ground and each terminal of each battery and other
current source.
d) Ground current reading shall be permitted in lieu of c). If
this method of testing is used, all grounds showing a
current reading in excess of 5 percent of the supplied
line current shall be given immediate attention.
e) Voltage across terminals of common battery, on
switchboard side of fuses.
f) Voltage between common battery terminals and ground.
Abnormal ground readings shall be investigated
immediately.
Tests specified in c) and f) shall apply only to those systems
using a common battery. If more than one common battery is
used, each common battery shall be tested.
Lightning protection equipment shall be inspected and
maintained per the manufacturer’s specifications.
Additional inspections shall be required after any lightning
strikes.
Equipment located in moderate to severe areas outlined in
NFPA 780. Standard for the Installation of Lightning Protection
Systems, Appendix H, shall be inspected semi-annually and
after any lighting strikes.
Control Unit Trouble Signals
a) Audible and Operation of panel trouble signals shall be verified as well as
Visual ring back feature for systems using a trouble-silencing switch
that requires resetting.
b) Disconnect If control unit has disconnect or isolating switches, performance
switches of intended function of each switch shall be verified and receipt
of trouble signal when a supervised function is disconnected
shall also be verified.
c) Ground Fault If the system has a ground detection feature, the occurrence of
Monitoring ground-fault indication shall be verified whenever any installation
Circuit conductor is grounded.
d) Transmission of An initiating device shall be actuated and receipt of alarm signal
Signals to Off- at the off-premises location shall be verified.
Premises
Location
A trouble condition shall be created and receipt of a trouble
signal at the off-premises location shall be verified.
A supervisory device shall be actuated and receipt of a
supervisory signal at the off-premises location shall be verified.
If a transmission carrier is capable of operation under a single or
multiple fault condition, an initiating device shall be activated
during such fault condition and receipt of a trouble signal at the
off-premises location shall be verified, in addition to the alarm
signal.
Remote Annunciators The correct operation and identification of annunciators shall be
verified. If provided, the correct operation of annunciator under a
fault condition shall be verified.
Conductors Metallic
a) Stray voltage All installation conductors shall be tested with a voltmeter to
verify that there are no stray (unwanted) voltage between
installation conductors or between installation conductors and
Device Method
ground. Unless a different threshold is specified in the system
installed equipment manufacturer’s specifications, the maximum
allowable stray voltage shall not exceed 1 volt addt.
b) Ground All installation conductors other than those intentionally and
Faults permanently grounded shall be tested for isolation from ground
per the installed equipment manufacturer’s specifications.
c) Short Circuit All installation conductors other than those intentionally
Faults connected together shall be tested for conductor-to-conductor
isolation per the installed equipment manufacturer’s
specifications. These same circuits also shall be tested
conductor-to-ground.
d) Loop With each initiating and indicating circuit installation conductor
Resistance pair short-circuited at the far end, the resistance of each circuit
shall be measured and recorded. It shall be verified that the loop
resistance does not exceed the installed equipment
manufacturer’s specified limits.
Conductors Non- Each initiating device, notification appliance, and signalling line
metallic circuit shall be tested to confirm that the installation conductors
are monitored for integrity in accordance with the requirements
of NFPA 72E, National Fire Alarm Code.
a) Circuit The fibre optic transmission line shall be tested in accordance
Integrity with the manufacturer’s instruction by the use of an optical
power meter or by an optical time domain reflectometer used to
measure the relative power loss of the line. This relative figure
for each
b) Fibre Optics The fibre optic transmission line shall be tested in accordance
with the manufacturer’s instructions by the use of an optical
power meter or by an optical time domain reflectometer used to
measure the relative power loss of the line. This relative figure
for each fibre optic line shall be recorded in the fire alarm control
panel. If the power level drops 2 percent or more from the value
recorded during the initial acceptance test, the transmission line,
section thereof, or connectors shall be repaired or replaced by a
qualified technician to bring the line back into compliance with
the accepted transmission level per the manufacturer’s
recommendations.
Supervision Introduction of a fault in any supervised circuit shall result in a
trouble indication at the control unit. One connection shall be
opened at not less than 10 percent of the initiating device,
notification appliance, and signalling line circuit.
Each initiating device, notification appliance, and signalling line
circuit shall be tested for correct indication at the control unit. All
circuits shall perform as indicated in NFPA 72E. National Fire
Alarm Code.
Initiating Devices
a) Electromechanical
Releasing Device
1. Non-restorable-type Correct operation shall be verified by removal of the fusible link
link and operation of the associated device. Any moving parts shall
be lubricated as necessary.
2. Restorable-type link Correct operation shall be verified by removal of the fusible link
and operation of the associated device. Any moving parts shall
be lubricated as necessary.
b) Fire Extinguishing The switch shall be mechanically or electrically operated and
System(s) or receipt of signal by the control panel shall be verified.
Suppression
System(s) Alarm
Device Method
Switch
c) Fire-Gas and Other Fire-gas detectors and other fire detectors shall be tested as
Detectors prescribed by the manufacturer and as necessary for the
application.
d) Heat Detectors
1. Fixed Temperature, Heat test shall be performed with a heat source per the
Rate of Rise, Rate manufacturer’s recommendations for response within 1 minute.
of Compensation, A test method shall be used that is recommended by the
Restorable Line, manufacturer or other method shall be used that will not damage
Spot Type the non-restorable fixed-temperature element of a combination
(excluding rate of rise fixed-temperature element.
Pneumatic Tube
Type)
2. Fixed Temperature, Heat test shall not be performed. Functionality shall be tested
Non-restorable Line mechanically and electrically. Loop resistance shall be
Type measured and recorded. Changes from acceptance test shall be
investigated.
3. Fixed-Temperature, After 15 years from initial installation, all devices shall be
Non-Restorable replaced or two detectors per 100 shall be laboratory tested.
Spot-type The two detectors shall be replaced with new devices. If a failure
occurs on any of the detectors removed, additional detectors
shall be removed and tested to determine either a general
problem involving faulty detectors or a localised problem
involving one or two defective detectors.
If detectors are tested instead of replaced, tests shall be
repeated at intervals of 5 years.
4. Non-restorable Heat tests shall not be performed. Functionality shall be tested
(General) mechanically and electrically.
5. Restorable Line Heat tests shall be performed (where test chambers are in
Type. Pneumatic circuit) or a test with pressure pump shall be conducted.
Tube Only
6. Fire Alarm Boxes Manual fire alarm boxes shall be operated per the
manufacturer’s instructions. Key-operated pre-signal and
general alarm manual fire alarm boxes shall both be tested.
7. Radiant Energy Flame detectors and spark ember detectors shall be tested in
Fire Detectors accordance with the manufacturer’s instructions to determine
that each detector is operative.
Flame detector and spark ember detector sensitivity shall be
determined using any of the following:
a) Calibrated rest method
b) Manufacturer’s calibrated sensitivity test instrument
c) Listed control unit arranged for the purpose
d) Other approved calibrated sensitivity test method that is
directly proportional to the input signal from a fire,
consistent with the detector listing or approval.
If designed to be field adjustable, detectors found to be outside
of the approved range of sensitivity shall be replaced or adjusted
to bring them into the approved range.
Flame detector and spark ember detector sensitivity shall not be
determined using a light source that administers an unmeasured
quantity of radiation at an undefined distance from the detector.
g) Smoke Detectors
1. System detectors The detectors shall be tested in place to ensure smoke entry
into the sensing chamber and an alarm response. Testing with
smoke or listed aerosol approved by the manufacturer shall be
permitted as acceptable test methods. Other methods approved
Device Method
by the manufacturer that ensure smoke entry into the sensing
chamber shall be permitted.
Any of the following tests shall be performed to ensure that each
smoke detector is within its listed and marked sensitivity range:
a) Calibrated test method
b) Manufacturer’s calibrated sensitivity test instrument
c) Listed control equipment arranged for the purpose
d) Smoke detector control unit arrangement whereby the
detector causes a signal at the control unit when its
sensitivity is outside its listed sensitivity range
e) Other calibrated sensitivity test method approved by the
authority having jurisdiction
2. Single Station The detectors shall be tested in place to ensure smoke entry
Detectors into the sensing chamber and an alarm response. Testing with
smoke or listed aerosol approved by the manufacturer shall be
permitted as acceptable test methods. Other methods approved
by the manufacturer that ensure smoke entry into the sensing
chamber shall be permitted.
3. Air Sampling Per manufacturer’s recommended test methods, detector alarm
response shall be verified through the end sampling port on
each pipe run; airflow through all other ports shall be verified as
well.
4. Duct Type Air duct detectors shall be tested or inspected to ensure that the
device will sample the air stream. The test shall be made in
accordance with the manufacturer’s instructions.
5. Projected Beam The detector shall be tested by introducing smoke, other
Type aerosol, or an optical filler into the beam path.
6. Smoke Detector Both portions of the detector shall be operated independently as
with built-in thermal described for the respective devices.
element
7. Smoke Detectors It shall be verified that the control capability shall remain
with Control Output operable even if all of the
Functions
h) Initiating Devices,
Supervisory
1. Control Valve Valve shall be operated and signal receipt shall be verified to be
Switch within the first two revolutions of the hand wheel or within one
fifth of the travel distance, or per the manufacturer’s
specifications.
2. High or Low Air Switch shall be operated. Receipt of signal obtained where the
Pressure Switch required pressure is increased or decreased a maximum 10 psi
(70 kPa) from the required pressure level shall be verified.
3. Room Temperature Switch shall be operated. Receipt of signal to indicate the
Switch decreases in room temperature to 40°F (44°C) and it s
restoration to above 40°F (44°C) shall be verified.
4. Water Level Switch Switch shall be operated. Receipt of signal indicating the water
level raised or lowere4d 3 in. (76.2mm) from the required level
within a pressure tank, or 12 in (305 mm) from the required level
of a non-pressure tank, shall be verified, as shall its restoral to
required level.
5. Water Temperature Switch shall be operated. Receipt of signal to indicate the
Switch decrease in water temperature to 40°F (4.4°C and it s restoration
to above 40°F (4.4°C) shall be verified.
Mechanical, Water shall be flowed through an inspector’s test connection
Electrosonic, or indicating the flow of water equal to that from a single sprinkler
Pressure-Type of the smallest orifice size installed in the system for wet-pipe
Device Method
Water Flow Device systems, or an alarm test bypass connection for dry-pipe, pre-
action, or deluge systems in accordance with NFPA 25,
Standard for the Inspection, Testing, and Maintenance of Water-
Based Fire Protection Systems.
Alarm Notification
Appliances
a) Audible Sound pressure level shall be measured with sound level motor
meeting ANSI S1.4a, Specifications for Sound Level Motors,
Type 2 requirements. Levels throughout protected area shall be
measured and recorded.
b) Audible Textural Sound pressure level shall be measured with sound level motor
Notification meeting ANSI S1.4a, Specifications for Sound Level Motors,
Appliances Type 2 requirements. Levels throughout protected area shall be
(Speakers and other measured and recorded.
Appliances to
Convey Voice
Messages)
Audible information shall be verified to be distinguishable and
understandable.
c) Visible Test shall be performed in accordance with the manufacturer’s
instructions. Device locations shall be verified to be per
approved layout and it shall be confirmed that no floor plan
changes affect the approved layout.
Special Hazard
Equipment
a) Abort Switch (IRI Abort switch shall be operated. Correct sequence and operation
Type) shall be verified.
b) Abort Switch Abort switch shall be operated. Development of correct matrix
(Recycle Type) with each sensor operated shall be verified.
c) Abort Switch Abort switch shall be operated. Correct sequence and operation
(Special Type) in accordance with authority having jurisdiction shall be verified.
Sequencing on as built drawings or in owner’s manual shall be
observed.
d) Cross Zone One sensor or detector on each zone shall be operated.
Detection Circuit Occurrence of correct sequence with operation of first zone and
then with operation of second zone shall be verified.
e) Matrix-Type Circuit All sensors in system shall be operated. Development of correct
matrix with each sensor operated shall be verified.
f) Release Solenoid Solenoid shall be used with equal current requirements.
Circuit Operation of solenoid shall be verified.
g) Squibb Release AGI flashbulb or other test light approved by the manufacturer
Circuit shall be used. Operation of flashbulb or light shall be verified.
h) Verified, Sequential, Required sensors at a minimum of four locations in circuit shall
or Counting Zone be operated. Correct sequence with both the first and second
Circuit detector in alarm shall be verified.
i) All above Devices or Supervision of circuits shall be verified by creating an open
Circuits or circuit.
Combinations
Thereof
Supervising Station Fire
Alarm Systems -
Transmission
Equipment
a) All Equipment Test shall be performed on all system functions and features in
accordance with the equipment manufacturer’s instructions for
correct operation in conformance with the applicable sections of
Chapter 5.
Device Method
Initiating device shall be actuated. Receipt of the correct
initiating device at the supervising station with 90 seconds shall
be verified. Upon completion of the test, the system shall be
restored to its functional operating condition.
If test jacks are used, the first and last tests shall be made
without the use of the test jack.
b) Digital Alarm Connection of the DACT to two separate means of transmission
Communicator shall be ensured.
Transmitter (DACT)
Exception: DACTs that are connected to a telephone line
(number) that is also supervised for adverse conditions by a
derived local channel.
DACT shall be tested for line seizure capability by initiating a
signal while using the primary line for a telephone call. Receipt
of the correct signal at the supervising station shall be verified.
Completion of the transmission attempt within 90 seconds from
going off-hook to on-hook shall be verified.
The primary line from the DACT shall be disconnected.
Indication of the DACT trouble signal at the premises shall be
verified as well as transmission to the supervising station within
4 minutes of detection of the fault.
The secondary means of transmission from the DACT shall be
disconnected. Indication of the DACT trouble signal at the
premises shall be verified as well as transmission to the
supervising station within 4 minutes of detection of the fault.
The DACT shall be caused to transmit a signal to the DACR
while a fault in the primary telephone number is simulated.
Utilisation of the secondary telephone number by the DACT to
complete the transmission to the DACR shall be verified.
c) Digital Alarm Radio The primary telephone line shall be disconnected. Transmission
Transmitter (DART) of a trouble signal to the supervising station by the DART within
4 minutes shall be verified.
d) McCulloh Initiating device shall be actuated. Production of not less than
Transmitter three complete rounds of not less than three signal impulses
each by the McCulloh transmitter shall be verified.
If end-to-end continuity is present and with a balanced circuit,
each of the following four transmission channel fault conditions
shall be caused in turn, and receipt of correct signals at the
supervising station shall be verified:
a) Open
b) Ground
c) Wire-to-wire short
d) Open and ground
If end-to-end metallic continuity is not present and with a
properly balanced circuit, each of the following three
transmission channel fault conditions shall be caused in turn and
receipt of correct signals at the supervising station shall be
verified.
a) Open
b) Ground
c) Wire-to-wire short
e) Radio Alarm A fault between elements of the transmitting equipment shall be
Transmitter (RAT) caused. Indication of the fault at the protected premises shall be
verified or it shall be verified that a trouble signal is transmitted
to the supervising station.
Supervising Station Fire
Device Method
Alarm Systems -
Receiving Equipment
a) All Equipment Tests shall be performed on all system functions and features in
accordance with the equipment manufacturer’s instructions for
correct operation in conformance with the applicable sections of
Chapter 5 of NFPA 72E National Fire Alarm Code.
Initiating device shall be actuated. Receipt of the correct
initiating device signal at the supervising station within 90
seconds shall be verified upon completion of the test, the
system shall be restored to its functional operating condition.
If test jacks are used, the first and last tests shall be made
without the use of the test jack.
b) Digital Alarm Each telephone line (number) shall be disconnected in turn from
Communicator the DACR and audible and visual annunciation of a trouble
Receiver (DACR) signal in the supervising station shall be verified.
A signal shall be caused to be transmitted on each individual
incoming DACR line at least once every 24 hours. Receipt of
these signals shall be verified.
c) Digital Alarm Radio The following conditions of all DARRs on all subsidiary and
Receiver (DARR) repeater station receiving equipment shall be caused. Receipt at
the supervising station of correct signals breach of the following
conditions shall be verified:
a) AC power failure of the radio equipment
b) Receiver malfunction
c) Antenna and interconnecting cable failure
d) Indication of automatic switchover of the DARR
e) Data transmission line failure between the DARR and the
supervising or subsidiary station
d) McCulloh Systems The current on each circuit at each supervising and subsidiary
station under the following conditions shall be tested and
recorded:
a) During functional operation
b) On each side of the circuit with the receiving equipment
conditioned for an open circuit
A single break or ground condition shall be caused on each
transmission channel. If such a fault prevents the functioning of
the circuit, receipt of a trouble signal shall be verified.
Each of the following conditions at each of the supervising or
subsidiary stations and all repeater station radio transmitting and
receiving equipment shall be caused; receipt of correct signals
at the supervising station shall be verified.
a) RF transmitter in use (radiating)
b) AC power failure supplying the radio equipment
c) RF receiver malfunction
d) Indication of automatic switchover
e) Radio Alarm Each of the following conditions at each of the supervising or
Supervising Station subsidiary stations and all repeater station radio transmitting and
Receiver (RASSR) receiving equipment shall be caused, receipt of correct signals
and Radio Alarm at the supervising station shall be verified:
Repeater Station
Receiver (RARSR)
f) Private Microwave Each of the following conditions at each of the supervising or
Radio Systems subsidiary stations and all repeater station radio transmitting and
receiving equipment shall be caused; receipt of correct signals
at the supervising station shall be verified:
a) RF transmitter in use (radiating)
Device Method
b) AC power failure supplying the radio equipment
c) RF receiver malfunction
d) Indication of automatic switchover
Emergency
Communications
Equipment
a) Amplifier / Tone Correct switching and operation of backup equipment shall be
Generators verified
b) Call-in Signal Function shall be operated and receipt of correct visual and
Service audible signals at control panel shall be verified
c) Off – hook Indicator Phone set shall be installed or phone shall be removed from
(Ring Down) hook and receipt of signal at control panel shall be verified.
d) Phone Jacks Phone jack shall be visually inspected and communications path
through jack shall be initiated.
e) Phone Set Each phone set shall be activated and correct operation shall be
verified.
f) System System shall be operated with a minimum of any five handsets
Performance simultaneously. Voice quality and clarity shall be verified.
Interface Equipment Interface equipment connections shall be tested by operating or
simulating the equipment being supervised. Signals required to
be transmitted shall be verified at the control panel. Test
frequency for interface equipment shall be the same as the
frequency required by the applicable NFPA standard(s) for the
equipment being supervised.
Guards Tour Equipment The device shall be tested in accordance with the manufacturers
specifications.
Special Procedures
a) Alarm Verification Time delay and alarm response for smoke detector circuits
identified as having alarm verification shall be verified.
b) Multiplex Systems Communications between sending and receiving units under
both primary and secondary power shall be verified.
Communications between sending and receiving units under
open circuit trouble conditions shall be verified.
Communications between sending and receiving units in all
directions where multiple communications pathways are
provided shall be verified.
If redundant central equipment is provided, switchover and all
required functions and operations of secondary equipment shall
be verified.
All system functions and features shall be verified in accordance
with manufacturer’s instructions.
Low – Power Radio The following procedures describe the additional acceptance
(Wireless Systems) and reacceptance test methods to verify wireless protection
system operation:
a) The manufacturer’s manual and the as built drawings
provided by the system supplier shall be used to verify
correct operation after the initial testing phase has been
performed by the supplier or by the supplier’s designated
representative.
b) Starting from the functional condition, the system shall be
initialised in accordance with the manufacturer’s manual. A
test shall be conducted to verify the alternative path, or
paths, by turning off or disconnecting the primary wireless
repeater. The alternative communications path shall exist
between the wireless control panel and peripheral devices
used to establish initiation, indicating, control and
Device Method
annunciation. The system shall be tested for both alarm
and trouble conditions.
c) Batteries for all components in the system shall be
checked monthly. If the control panel checks all batteries
and all components daily, the system shall not require
monthly testing of the batteries.
3.2 Testing
Testing must be performed in accordance with the schedules in Table 2 or more often
if required by the authority having jurisdiction. If automatic testing is performed at
least weekly by a remotely monitored fire alarm control unit specifically listed for the
application, the manual testing frequency must be permitted to be extended to
annual. Table 3 must then apply.
3.2.1 Detector sensitivity must be checked within 1 year after installation and every
alternate year thereafter. After the second required calibration test, if sensitivity tests
indicate that the detector has remained within its listed and marked sensitivity range
(or 4 percent obscuration light grey smoke, if not marked), the length of time between
calibration tests must be permitted to be extended to a maximum of 5 years. If the
frequency is extended, records of detector-caused nuisance alarms and subsequent
trends of these alarms must be maintained. In zones or in areas where nuisance
alarms show any increase over the previous year, calibration tests must be
performed. To ensure that each smoke detector is within its listed and marked
sensitivity range, it must be tested using any of the following methods:
Detectors found to have a sensitivity outside the listed and marked sensitivity range
must be cleaned and recalibrated or be replaced.
The detector sensitivity must not be tested or measured using any device that
administers an unmeasured concentration of smoke or other aerosol into the
detector.
3.2.2 Test frequency of interfaced equipment must be the same as specified by the
applicable NFPA standards for the equipment being supervised.
3.2.3 For restorable fixed-temperature, spot-type heat detectors, two or more detectors
must be tested on each initiating circuit annually. Different detectors must be tested
each year, with records kept by the building owner specifying which detectors have
been tested. Within 5 years, each detector must have been tested.
3.2.4 For testing addressable and analog-described devices, which are affixed to either a
single, moulded assembly or a twist-lock type affixed to a base, testing must be
conducted using the signalling style circuits (Styles 0.5 through 7 of NFPA 72E
National Fire Alarm Code). Analog-type detectors must be tested with the same
criteria.
3.2.5 Test of all circuits extending from the central station must be made at intervals of not
more than 24 hours.
3.3.1 Emergency power sources other than batteries must be operated to supply the
system for a continuous period of 1 hour at least weekly. This test must require
simulated failure of the normal power source.
3.3.2 Testing facilities must be installed at the communications center and each subsidiary
communications center, if used.
4. MAINTENANCE
4.1 Fire alarm system equipment must be maintained in accordance with the
manufacturer’s instructions. The frequency of maintenance must depend on the type
of equipment and the local ambient conditions.
4.2 The frequency of cleaning must depend on the type of equipment and the local
ambient conditions.
4.3 All apparatus requiring rewinding or resetting to maintain normal operation must be
rewound or reset as promptly as possible after each test and alarm. All test signals
received must be recorded to indicate date, time, and type.
4.4 The retransmission means must be tested at intervals of not more than 12 hours. The
retransmission signal and the time and date of the retransmission must be recorded
in the central station.
5. RECORDS
5.2.1 Records must be retained until the next test and for 1 year thereafter.
5.2.2 A permanent record of all inspections, testing, and maintenance must be provided
that includes the following information regarding tests and all the applicable
information requested in a - o below.
a) Date
b) Test frequency
c) Name of property
d) Address
e) Name of person performing inspection, maintenance, tests, or combination
thereof, and affiliation, business address, and telephone number
f) Name, address, and representative of approving agency(ies)
g) Designation of the detector(s) tested, for example, “Tests performed in
accordance with Section __________.”
h) Functional test of detectors
i) Functional test of required sequence of operations
j) Check of all smoke detectors
k) Loop resistance for all fixed-temperature, line -type heat detectors
l) Other tests as required by equipment manufacturers
m) Other tests as required by the authority having jurisdiction
n) Signatures of tester and approved authority representative
o) Disposition of problems identified during test (for example, owner notified,
problem corrected/successfully retested, device abandoned in place)
5.2.3 For supervising station fire alarm systems, records pertaining to signals received at
the supervising station that result from maintenance, inspection, and testing, must be
maintained for not less than 12 months. Upon request, a hard copy record must be
provided to the authority having jurisdiction. Paper or electronic media must be
permitted.
5.2.4 If the operation of a device, circuit, control panel function, or special hazard system
interface is simulated, it must be noted on the certificate that the operation was
simulated, and the certificate must indicate by whom it was simulated.
6.1 All premises must have an effective means of giving warning in case of fire.
6.2 The type of alarm and method of operation (automatic and/or manual) will depend
upon the degree of risk in the building. In certain cases a fire alarm system capable of
both automatic and manual operation is a legal requirement, e.g. in occupied areas of
any buildings over 30 m in height or if there is a storey or floor area exceeding 5 000
m2. (Refer to National Building Regulations - TT31) (B4).
6.3 In operations of high and medium fire risk or where the site is extensive in size or the
buildings have upper storeys, an alarm system is required.
6.4 A public address system may be used to supplement the fire alarm providing an
alternate power source, independent of the main electricity supply, is available.
6.5 In each case the fire alarm must be clearly audible throughout the premises. It is
provided to protect and the sound emitted must not be mistaken for any other sound
than that of a fire alarm.
6.6 An exercise must be undertaken in terms of which employees must report any area
where the fire alarm cannot be clearly heard. Where excessive machinery noise
exists, the audible alarm system must be coupled to a visual system, e.g. flashing
lights or illuminated signs.
7. GENERAL DESIGN
7.1 Initiating alarm points must be provided in all parts of the building. No person should
walk more than 30 m in order to reach an alarm.
7.2 Initiating alarm points must be of the same type throughout. Initiating alarm points
must be sited at all exit points, including staircases, and indicated by conspicuous
signs.
7.3 Initiating points must be conspicuous and mounted 1.5 m above floor level and have
clear operating instructions.
7.4 All fire alarm systems must be fully monitored and DC battery operated, generally
12V or 24V. Many installations fitted with step-down transformers are mains operated
with battery back-up.
7.5 The system design should be in accordance with SABS 0139, NFPA 72E or BS 5839.
8. INSTALLATION
8.1 The system must be installed and designed by a specialist manufacturer and be
commissioned by him with appropriate certificates giving adequate guarantees. He
should be a member of the FDIA (Fire Detection Industry Association).
9.1 All manual break-glass and automatic points must signal back to a central
annunciator panel and be zoned to monitor the areas involved commensurate with
the risk and the building design. In small systems these may be wired together.
Specific guidance must be obtained from the SABS 0139, NFPA 72E and BS5839
standards.
The evaluation of the need for, and design of fire detection systems is a specialist
function and must always be referred to a specialist consultant. There are a large
number of suppliers of such systems and a great variety of equipment, but the range
of suitable and reliable suppliers and equipment is very limited and the advice of
specialist consultants is essential for the right selection.
The system must be regularly inspected and serviced by the installing engineers, as
per Table 2 and 3 described earlier, including functional testing of all circuits, and an
annual overhaul of all equipment. The user must inspect the system controls and
indicators, the alarms, including the fire brigade connection, by simulating a fire
condition on one of the detectors. A programmed sequence of testing must be
arranged so that a different detector zone is used each time. Thus, over a period of
time all detectors can be checked.
12.1 Detectors
Detectors are designed to react to one or more of the following characteristics of fire.
Heat
Smoke
Flames
Detectors are capable of being reset and are also fitted with a small indicator light
which goes on to indicate which detector was operated.
There are two types. Fixed temperature detectors only activate when a
predetermined temperature is reached, whereas rate of rise detectors response to
Fusible alloys
The melting of an alloy at a predetermined temperature completes an
electrical circuit to operate the alarm. Normal operating temperatures vary
between 55°C and 180°C.
Ionisation type
These have a chamber or two chambers incorporating a radioactive source
and a positive and negative electrode. Air within the chamber is irradiated and
ionised creating positive or negative ions depending on whether electrons are
gained or lost. These then move either to the positive or negative electrodes
to become neutralised. This movement reduces the resistance of the air
causing a small current to flow in the circuit. When smoke particles enter the
chamber charged ions attach themselves to the particles. The charged
particles move more slowly enabling them to meet charged particles or ions of
opposite polarity and become neutralised. A reduction in the current flowing in
the chamber occurs initiating an alarm.
Optical Type
These detectors have a light source and photo-electric cell in a light proof
housing which allows free ingress of smoke. They operate on the light scatter
principle where light is deflected by the smoke particles which enter the
chamber onto the photocell and/or the light obscuration principle where smoke
entering the chamber obscures the light beamed onto the photocell. This
change in light configuration is sensed, causing the detector to actuate.
In addition to visible light, flames also emit infra-red and ultra-violet radiation which is
detectable.
characteristic of the flicker of a flame. A scanning type which will rotate and
monitor through 360° in the horizontal plane is als o available. Radiation is
reflected by the scanner onto an IR detecting photocell to trigger an alarm.
Ultra-violet detectors use either an ultra-violet (UV) sensitive photocell or a UV
sensitive gas-filled tube in conjunction with an amplifier to detect UV radiation
from flames.
12.2 Wiring
The wiring transmits signals from the detectors to the annunciator panel and to the
audible alarms. It should be protected from accidental damage and the installation
thereof should be of the highest quality to facilitate signal transfer. The wiring should
be in metal conduit and be kept away from lifts and unprotected stair shafts and
openings to reduce the possibility of damage by fire.
Note: When evacuation and voice communication systems are interconnected to the
detection system all wiring should be of the fire resistant type.
The control unit acts as a terminal for the detector and internal and external alarm
circuits. It houses the test facilities, alarm silence button, fire or fault signalling and
power supply monitoring equipment. The size of the control unit will depend on the
complexity of the detection installation and the total number of zones of which it is
comprised. Each zone has a series of detectors off a loop of wiring enabling easy
location of a fire within a zoned compartment, usually restricted to about 2 000 m2 or
less. An indicator panel, together with a plan of the premises with zone identification
should be provided at the main entrance of the building where it will be seen by fire
brigade or other personnel responding to an alarm.
12.4 Alarms
Alarms, which should be of the highest quality, include sirens, hooters, bells and
electronic audible devices. A rough guide on minimum recommended sound
intensities is:
65 dBA or 5 dBA more than any background noise likely to last more than 30
seconds.
1.1 Inspection
All system hose, including those used as flexible connectors, must be tested at
17,240 kPa for high-pressure systems, and at 6205 kPa for low-pressure systems.
Hose must be tested as follows:
1.2.1 All system hose including those used as flexible connectors must be tested every 5
years.
1.2.2 Maintenance
A manufacturer’s test and maintenance procedure must be provided to the owner for
testing and maintenance of the system. This procedure must provide for the initial
testing of the equipment as well as for periodic test inspection and maintenance of
the system.
1.2.3 The following must be verified by competent personnel at least annually using
available documentation.
1) Check and test the carbon dioxide system for proper operation
2) Check that there have been no changes to the size, type, and configuration of
the hazard and system
1.2.4.1 The goal of this maintenance and testing must be not only to ensure that the system
is in full operating condition, but must indicate the probable continuance of that
condition until the next inspection.
1.2.4.2 Suitable discharge tests must be made when any maintenance indicates their
advisability. Prior to testing, proper safety procedures must be reviewed.
1.2.5 A maintenance report with recommendations must be filed with the owner.
1.2.6 Between the regular service contract maintenance or tests, the system must be
inspected visually or otherwise by approved or competent personnel who follow an
approved schedule.
1.2.7 At least semi-annually, all high-pressure cylinders must be weighed and the date of
the last hydrostatic test noted. If, at any time, a container shows a loss in net content
of more than 10 percent, it must be refilled or replaced.
1.2.8 At least weekly, the liquid level gauges of low-pressure containers must be observed.
If at any time a container shows a loss of more than 10 percent, it must be refilled,
unless the minimum gas requirements are still provided.
1.2.9 These systems must be kept in full operating condition at all times. Use, impairment,
and restoration of this protection must be reported promptly to the authority having
jurisdiction. Any troubles or impairments must be corrected at once by competent
personnel.
1.2.10 Instruction
2. AGENTS USED
Carbon dioxide (CO2) is a colourless, odourless, inert gas which extinguishes a fire by
reducing the concentrations of the oxygen in the air, or the gaseous phase of the fuel
in the air, to a point where combustion ceases (suffocation).
1) Personnel training.
2) Pre-discharge alarms must be provided.
3) All persons that can at any time enter a space protected by carbon
dioxide must be warned of the hazards involved, given an alarm signal,
and provided with safe evacuation procedures.
4) The pre – discharge, warning signal must provide a time delay of
sufficient duration to allow for evacuation under worst-case conditions.
5) Dry runs must be made to determine the minimum time needed for
persons to evacuate the hazard area, allowing time to identify the
warning signal.
WARNING
CARBON DIOXIDE GAS
WHEN ALARM OPERATES VACATE IMMEDIATELY
WARNING
CARBON DIOXIDE GAS
WHEN ALARM OPERATES DO NOT ENTER UNTIL VENTILATED
CAUTION:
CARBON DIOXIDE DISCHARGE INTO A NEARBY SPACE
CAN COLLECT HERE. WHEN ALARM OPERATES
VACATE IMMEDIATELY
CAUTION:
CARBON DIOXIDE GAS
VENTILATE THE AREA BEFORE ENTERING. A HIGH CARBON
DIOXIDE GAS CONCENTRATION CAN OCCUR IN THIS AREA AND
CAN CAUSE SUFFOCATION
WARNING
ACTUATION OF THIS DEVICE WILL CAUSE CARBON
DIOXIDE TO DISCHARGE. BEFORE ACTUATING, BE
SURE PERSONNEL ARE CLEAR OF THE AREA
The installation company should also refer to the NFPA 72, National Fire
Alarm Code, chapter on visual signalling for guidance for installation of
referenced visual alarms. The “public mode” for visual appliance operation
should be used.
The installation company / contractor must ensure that plans are drawn up to indicate
scale and/or be suitably dimensioned. Ensure that the plans contain sufficient detail
to enable the authority having jurisdiction to evaluate the hazard or hazards and to
evaluate the effectiveness of the system.
If the field conditions have changed from approved plans, the change must be
submitted to the authority having jurisdiction for approval.
When such changes from approved plans are made, corrected “as-installed” plans
must be supplied to the owner and the authority having jurisdiction.
As the owner you should maintain an instruction and maintenance manual that
includes a full sequence of the operation, and a full set of system drawings and
calculations.
The completed system must be inspected and tested by qualified personnel to meet
the approval of the authority having jurisdiction. Only listed or approved equipment
and devices must be used in the system. To determine that the system has been
properly installed and will function as specified, the following must be performed:
1) A thorough visual inspection of the installed system and hazard area. The
piping, operational equipment and discharge nozzles should be inspected for
proper size and location. The locations of alarms and manual emergency
releases should be confirmed. The configuration of the hazard should be
compared to the original hazard specification. The hazard must be inspected
closely for un - closable openings (which were noted i.e. doors ventilation/ air-
conditioning system openings) and sources of agent loss that could have
been overlooked in the original specification.
(a) System
(b) Hazard
Size
Configuration
Openings which cannot be closed
Fuels
Other aspects that could impact effectiveness of the extinguishing systems
e) Power supply
(g) Detectors
Electric type
Exercise functions
Check time limit
Check that the timer will complete its cycle even though wiring between it and
the detector circuit is interrupted
(i) Alarms
Exercise functions
Reset properly
Mechanical type
Electric type
Test manual release
Check that covers are in place
Check pneumatic releases
Check accessibility during fire
Separate main and reserve manual pulls that require only one operation, to
obtain discharge of either main or reserve supply of gas
Clearly mark and identify all manual releases
(n) Piping
(o) Nozzles
Check orientation and orifice size; make sure it is unchanged from original
design
Check cleanliness
Check security
Check seals where needed
(p) Containers
(q) Test
Perform recommended discharge tests when there is any question about the
adequacy of the system
Perform recommended full discharge test when cylinder hydrostatic test is
required
As is the case with all fire control installations, gaseous systems require regular
inspection and maintenance. Only personnel who have received thorough training
should perform these tasks as accidental discharge may occur.
Prior to commissioning, the system needs to be tested to show that it has been
correctly installed and is functional. Tests should include: pressure testing of system,
a visual examination to ensure system is complete as per specification including
signs, notices and instruction manuals a discharge test, where practical, to confirm
coverage of risk where local application is being used and to check agent
concentrations where total flooding systems are concerned. The future users of the
system should be present during these tests.
It is recommended that regular inspections such as those listed in the table below be
carried out.
Intervals
Test Weekly Monthly 6- Annually
monthly
Thorough inspection and test for proper x
operation to ensure system is fully
operational
Visual checks to be carried out between x
annual tests following an acceptable
checklist or schedule
The mass of all high pressure cylinders x
to be taken and date of last hydrostatic
pressure test noted
Readings from low pressure CO2 x
containers. Liquid level gauges to be
noted. Replace / refill if 10% of content
has been noted
A discharge test should be carried out where regular tests show this is necessary.
Cylinders require hydrostatic pressure testing at regular intervals as required by the
Occupational Health & Safety Act Vessels under Pressure Regulation.
An inspection report showing results of all tests and recommendations should be kept on the
premises.
3.5.1 An inspection is a “quick check” to give reasonable assurance that the extinguishing
system is fully charged and operable is done by seeing that the system is in place,
that it has not been activated or tampered with, and that there is no obvious physical
damage or condition to prevent operation. As a minimum, the inspection should
determine the following:
2) (For low-pressure storage unit, that pressure gauge shows normal pressure,
that tank shutoff valve is open, and that pilot pressure supply valve is open.
Liquid level gauge should be observed. If at any time a container shows a loss
4) All manual actuators are in place and tamper seals are intact.
5) Nozzles are connected, properly aligned, and free from obstructions and
foreign matter.
6) Detectors are in place and free from foreign matter and obstructions.
1.1 The responsibility for properly maintaining a water mist fire protection system must be
the obligation of the property owner. By means of periodic inspection, tests, and
maintenance, in accordance with the standard and manufacturers’ requirements this
equipment must be shown to be either in good operating condition and that defects or
impairments exist.
1.3 The owner or occupant must notify the authority having jurisdiction, the fire
department (if required), and the alarm receiving facility before shutting down a
system or its supply. The notification must include the purpose for the shutdown, the
system or component involved, and the estimated time needed. The authority having
jurisdiction, the fire department, and the alarm receiving facility must be notified when
the system, supply, or component is returned to service.
1.4 The owner or occupant must promptly correct or repair deficiencies, damaged parts,
or impairments found while performing the inspection, test, and maintenance
requirements of this standard. Corrections and repairs must be performed by qualified
maintenance personnel or a qualified contractor.
1.5 The owner or occupant must give special attention to factors that might alter the
requirements for a continued approved installation. Such factors must include, but
must not be limited to, the following:
1) Occupancy changes
2) Process or material changes
3) Structural revisions such as relocated walls, added horizontal or vertical
obstructions, or ventilation changes
4) Removal of heating systems in spaces with piping subject to freezing
1.6 Where changes in the occupancy, hazard, water supply, storage arrangement,
structural modification, or other condition that affects the installation criteria of the
system are identified, the owner or occupant must promptly take steps to evaluate the
adequacy of the installed system to protect the hazard in question, such as contacting
a qualified contractor, consultant, or engineer.
Where the evaluation reveals a deficiency, the owner must notify the insurance
underwriter, the authority having jurisdiction, and the local fire department.
1.7 Where a water mist system is returned to service following an impairment, it must be
verified that it is working properly.
All components and systems must be inspected and tested to verify that they function
as intended. The frequency of inspections and tests must be in accordance with
Tables 1 and 2 or as specified in the manufacturer’s listing, whichever is more
frequent. Following tests of components or portions of water mist systems that require
valves to be opened or closed, the system must be returned to service, with
verification that all valves are restored to their normal operating position. Plugs or
caps for auxiliary drains or test valves must be replaced.
2.1 Test results must be compared with those of the original acceptance test and with the
previous test results.
2.2 Inspection and testing requirements for each component are provided in Tables 1 and
2.
2.3 Specialized equipment required for testing must be in accordance with the
manufacturer’s specifications.
2.4 High pressure cylinders used in water mist systems must not be recharged without a
hydrostatic test (and remarking) if more than 5 years have elapsed from the date of
the last test. Cylinders that have been in continuous service without discharging must
be permitted to be retained in service for a maximum of 12 years, after which they
must be discharged and retested before being returned to service.
2.5 Maintenance
2.5.1 Maintenance must be performed to keep the system equipment operable or to make
repairs. As-built system installation drawings, original acceptance test records, and
device manufacturer’s maintenance bulletins must be retained to assist in the proper
care of the system and its components.
2.5.2 Preventive maintenance includes, but is not limited to, lubricating control valve stems,
adjusting packing glands on valves and pumps, bleeding moisture and condensation
from air compressors and air lines, and cleaning strainers. Scheduled maintenance
must be performed as outlined in Table 3.
2.5.3 Corrective maintenance includes, but is not limited to, replacing loaded, corroded, or
painted nozzles, replacing missing or loose pipe hangers, cleaning clogged fire
pumps, replacing valve seats and gaskets, and restoring heat in areas subject to
freezing temperatures where water-filled piping is installed.
2.5.4 Emergency maintenance includes, but is not limited to, repairs due to piping failures
caused by freezing or impact damage, repairs to broken water mains, and replacing
frozen or fused nozzles, defective electric power, or alarm and detection system
wiring.
2.5.5 Specific maintenance activities, where applicable to the type of water mist system,
must be performed in accordance with the schedules in Table 3.
2.5.7 After each system operation, a representative sample of operated water mist nozzles
in the activated zone must be inspected.
2.5.8 The representative sample should include 10 percent of the water mist nozzles in the
activated zone. If contamination of filters or strainers is found on inspection, it is
recommended that all nozzles within the activated zone also be inspected.
2.5.9 After each system operation due to fire, the system filters and strainers must be
cleaned or replaced.
2.5.10 Training
All persons who might be expected to inspect, test, maintain, or operate water mist
systems must be trained thoroughly in the functions they are expected to perform.
Refresher training must be provided as recommended by the manufacturer or by the
authority having jurisdiction.
1.1 The owner or occupant must provide ready accessibility to components of water-
based fire protection systems that require inspection, testing, or maintenance.
1.2 The responsibility for properly maintaining a water-based fire protection system must
be that of the owner of the property.
1.3 The owner or occupant must notify the authority having jurisdiction, the fire
department, if required, and the alarm-receiving facility before testing or shutting
down a system or its supply.
The notification must include the purpose for the shutdown, the system or
component involved, and the estimated time of shutdown.
The supervisor having jurisdiction, the fire department, and the alarm-
receiving facility must be notified when the system, supply, or component is
returned to service.
The building owner or occupant must not make changes in the occupancy, the
use or process, or the materials used or stored in the building without
evaluation of the fire protection systems for their capability to protect the new
occupancy, use, or materials.
2. RECORDS
2.1 Records of inspections, tests, and maintenance of the system and its components
must be made available to the supervisor having jurisdiction upon request.
2.2 Records must indicate the procedure performed (e.g. inspection, test, or
maintenance), the organisation that performed the work, the results, and the date.
2.4 Original records must be retained for the life of the system.
2.5 Subsequent records must be retained for a period of 1 year after the next inspection,
test, or maintenance required by the standard.
This Standard provides the minimum requirements for the routine inspection, testing,
and maintenance of sprinkler systems. Table 1 must be used to determine the
minimum required frequencies for inspection, testing, and maintenance.
3.1 Inspection
Sprinklers must not show signs of leakage, must be free of corrosion, foreign
materials, paint, and physical damage; and must be installed in the proper orientation
(e.g. upright, pendent, or sidewall).
Any sprinkler must be replaced that has signs of leakage; is painted, corroded,
damaged, or loaded; or in the improper orientation.
Sprinklers installed in concealed spaces such as above suspended ceilings must not
require inspection.
Sprinklers installed in areas that are inaccessible for safety considerations due to
process operations must be inspected during each scheduled shutdown.
The supply of spare sprinklers must be inspected annually for the following:
Sprinkler pipe and fittings must be inspected annually from the floor level.
Pipe and fittings must be in good condition and free of mechanical damage,
leakage, corrosion, and misalignment.
Pipe installed in areas that are inaccessible for safety considerations due to
process operations must be inspected during each scheduled shutdown.
Sprinkler pipe hangers and seismic braces must be inspected annually from
the floor level.
Hangers and seismic braces that are damaged or loose must be replaced or
refastened.
Hangers installed in areas that are inaccessible for safety considerations due
to process operations must be inspected during each scheduled shutdown.
3.4 Gauges
Alarm devices must be inspected quarterly to verify that they are free of
physical damage.
3.8 Testing
3.8.1 Sprinklers
Where one sprinkler within a representative sample fails to meet the test
requirement, all sprinklers represented by that sample must be replaced.
3.8.2 Gauges
Gauges must be replaced every 5 years or tested every 5 years by comparison with a
calibrated gauge. Gauges not accurate to within 3 percent of the full scale must be
recalibrated or replaced.
Water-flow devices including, but not limited to, mechanical water motor
gongs and pressure switch type must be tested quarterly.
Fire pumps must not be turned off during testing unless all impairment
procedures contained in IM11 are followed.
Testing the water-flow alarm on dry pipe, pre-action, or deluge systems must
be accomplished by using the bypass connection.
3.9 Maintenance
3.9.1 Sprinklers
(1) Style
(2) Orifice size and K-factor
(3) Temperature rating
(4) Coating, if any
(5) Deflector type (e.g. upright, pendent, sidewall)
(6) Design requirements
A supply of spare sprinklers (never fewer than six) must be maintained on the
premises so that any sprinklers that have operated or been damaged in any
way can be promptly replaced.
The sprinklers must correspond to the types and temperature ratings of the
sprinklers in the property.
The stock of spare sprinklers must include all types and ratings installed and
must be as follows:
(1) For protected facilities having under 300 sprinklers — no fewer than 6
sprinklers
(2) For protected facilities having 300 to 1000 sprinklers — no fewer than
12 sprinklers
(3) For protected facilities having over 1000 sprinklers — no fewer than 24
sprinklers
4. SAFETY
4.1 Confined spaces. Legally required precautions must be taken prior to entering
confined spaces such as tanks, valve pits, or trenches.
4.2 Fall protection. Legally required equipment must be worn or used to prevent injury
from falls to personnel.
4.3 Special hazards. Precautions must be taken to address any special hazards, such
as protection against drowning where working on the top of a filled embankment or a
supported, rubberized fabric tank, or over open water or other liquids.
5. HAZARDOUS MATERIALS
5.1 Legally required equipment must be used where working in an environment with
hazardous materials present.
5.2 The owner must advise anyone performing inspection, testing, and maintenance on
any system under the scope of this document, with regard to hazardous materials
stored on the premises.
6. ELECTRICAL SAFETY
7. CORRECTIVE ACTION
1. General
This Standard provides the minimum requirements for the routine inspection,
testing, and maintenance of private fire service mains and their
appurtenances. Table 1 must be used to determine the minimum required
frequencies for inspection, testing, and maintenance.
3. Fire hose
Fire hose must be maintained in accordance with NFPA 1962, Standard for
the Care, Use, and Service Testing of Fire Hose Including Couplings and
Nozzles.
5. Exposed piping
Piping installed in areas that are inaccessible for safety considerations due to
process operations must be inspected during each scheduled shutdown.
6. Underground Piping
7. Mainline strainers
Mainline strainers must be inspected and cleaned after each system flow exceeding
that of a nominal 50 mm orifice and must be removed and inspected annually for
failing, damage, and corroded parts with the necessary corrective action taken as
shown in Table 3.
Dry barrel and wall hydrants shall be inspected annually and after each operation with
the necessary corrective action taken as shown in Table 4.
Wet barrel hydrants must be inspected annually and after each operation the
necessary corrective action as shown in Table 5 must be taken.
Monitor nozzles must be inspected semiannually with the necessary corrective action
taken as shown in Table 6 below.
Hose houses must be inspected quarterly with the necessary corrective action taken
as shown in Table 7.
12. Testing
Underground and Exposed Piping Flow Tests. Underground and exposed piping
must be flow tested to determine the internal condition of the piping at minimum 5-
year intervals.
Any flow test results that indicate deterioration of available water flow and
pressure must be investigated to the complete satisfaction of the authority
having jurisdiction to ensure that the required flow and pressure are available
for fire protection.
13. Maintenance
General
1. FIRE PUMPS
1.1 General
This Standard provides the minimum requirements for the routine inspection,
testing, and maintenance of fire pump assemblies. Table 1 must be used to
determine the minimum required frequencies for inspection, testing, and
maintenance.
Water Supply to Pump Suction. The suction supply for the fire pump
must provide the required flow at a gauge pressure of zero (0) bar [zero
(0) psi] or higher at the pump suction flange to meet the system demand.
Energy Source. The energy sources for the pump driver must supply the
necessary brake horsepower of the driver so that the pump meets system
demand.
Driver. The pump driver must not overload beyond its rating (including any
service factor allowance) when delivering the necessary brake
horsepower.
1.2 Inspection
The purpose of inspection must be to verify that the pump assembly appears to be in
operating condition and is free from physical damage.
a) Heat is adequate, not less than 4.4°C (40°F) (21 °C (70°F) for
pump room with diesel pumps without engine heaters).
a) Pump suction and discharge and bypass valves are fully open.
b) Piping is free of leaks.
c) Suction line pressure gauge reading is normal.
1.3 Testing
A weekly test of fire pump assemblies must be conducted without flowing water.
The automatic weekly test timer must be permitted to be substituted for the
starting procedure.
If available suction supplies do not allow flowing of 150 percent of the rated
pump capacity, the fire pump must be permitted to operate at maximum
allowable discharge.
Use of the Pump Discharge Via the Hose Streams. Pump suction and
discharge pressures and the flow measurements of each hose stream must
determine the total pump output. Care must be taken to prevent water
Use of the Pump Discharge Via the Bypass Flow meter to Drain or
Suction the Reservoir. Pump suction and discharge pressures and the flow
meter measurements must determine the total pump output.
Use of the Pump Discharge Via the Bypass Flow meter to Pump Suction
(Closed-Loop Metering). Pump suction and discharge pressures and the
flow meter measurements must determine the total pump output.
(a) Record the electric motor voltage and current (all lines)
(b) Record the pump speed in rpm
(c) Record the simultaneous (approximately) readings of pump
suction and discharge pressures and pump discharge flow
For installations having a pressure relief valve, the operation of the relief valve
must be closely observed during each flow condition to determine if the pump
discharge pressure exceeds the normal operating pressure of the system
components.
The pressure relief valve must also be observed during each flow condition to
determine if the pressure relief valve closes at the proper pressure.
A pressure relief valve that is open during a flow condition will affect test
results.
The pressure relief valve must be closed during flow conditions if necessary to
achieve minimum rated characteristics for the pump and reset to normal
position at the conclusion of the pump test.
For installations having an automatic transfer switch, the following test must
be performed to ensure that the overcurrent protective devices (i.e., fuses or
circuit breakers) do not open:
(1) Simulate a power failure condition while the pump is operating at peak
load
(2) Verify that the transfer switch transfers power to the alternate power
source
(4) Remove the power failure condition and verify that after a time delay,
the pump is reconnected to the normal power source
After the water-flow portions of the annual test or fire protection system
activations, the suction screens must be inspected and cleared of any debris
or obstructions.
Parallel and angular alignment of the pump and driver must be checked
during the annual test. Any misalignment must be corrected.
(1) The test matches the initial unadjusted field acceptance test curve.
1.3.6 Maintenance
1. General
This Standard provides the minimum requirements for the routine inspection,
testing, and maintenance of water storage tanks. Table 1 must be used to
determine the minimum required frequencies for inspection, testing, and
maintenance.
(1) Before conducting any test or procedure that could result in the
activation of an alarm
Tanks equipped with supervised water level alarms that are connected to a
constantly attended location must be inspected quarterly.
3. Water temperature
The temperature of water tanks must not be less than 4°C (40°F).
4. Exterior inspection
The exterior of the tank, supporting structure, vents, foundation, and catwalks
or ladders, where provided, must be inspected quarterly for signs of obvious
damage or weakening.
The area surrounding the tank and supporting structure, where provided, must
be inspected quarterly to ensure that the following conditions are met:
Expansion joints, where provided, must be inspected annually for leaks and
cracks.
5. Interior inspection
The interior of all other types of tanks must be inspected every 5 years.
The tank interior must be inspected for signs of pitting, corrosion, spalling, rot,
other forms of deterioration, waste materials and debris, aquatic growth, and
local or general failure of interior coating.
6. Testing
Level indicators must be tested every 5 years for accuracy and freedom of
movement.
7. Maintenance
The hatch covers in the roofs and the door at the top of the frost-proof casing
must always be kept securely fastened with substantial catches as a
protection against freezing and windstorm damage.
No waste materials, such as boards, paint cans, trim, or loose material, must
be left in the tank or on the surface of the tank.
The exposed surfaces of embankment-supported coated fabric (ESCF) tanks
must be cleaned and painted every 2 years or in accordance with the
manufacturer's instructions.
Silt must be removed during interior inspections or more frequently as needed
to avoid accumulation to the level of the tank outlet.
The maintenance of ESCF tanks must be completed in accordance with this
section and the tank manufacturer’s instructions.
8. Records
1. General
This Standard provides the minimum requirements for the routine inspection,
testing, and maintenance of water spray protection from fixed nozzle systems
only. Table 1 must be used to determine the minimum required frequencies
for inspection, testing, and maintenance.
This Standard does not cover water spray protection from portable nozzles,
sprinkler systems, monitor nozzles, or other means of application.
NFPA 15, Standard for Water Spray Fixed Systems for Fire Protection, must
be consulted to determine the requirements for design and installation,
including acceptance testing.
When a water spray fixed system or any portion thereof is out of service for
any reason, notice must be given to facility management, the local fire
department, the on-site fire brigade, and other authorities having jurisdiction,
as applicable.
The components described in this section must be inspected and maintained at the
frequency specified in Table 1 and in accordance with this standard and the
manufacturer’s instructions.
Items in areas that are inaccessible for safety considerations due to factors such as
continuous process operations and energized electrical equipment must be inspected
during each scheduled shutdown but not more than every 18 months.
Other maintenance intervals must be permitted depending on the results of the visual
inspection and operating tests.
Nozzle discharge patterns and direction must be checked during the annual test.
Nozzle strainers must be removed, inspected, and cleaned during the flushing
procedure for the mainline strainer.
Mainline strainers must be removed and inspected every 5 years for damaged and
corroded parts.
Deluge valves must be inspected, tested, and maintained in accordance with NFPA
25.
System piping, fittings, hangers, and supports must be inspected and maintained to
ensure continuity of water delivery to the spray nozzles at full water flow and design
pressure.
Hangers and supports must be inspected for the following and repaired as necessary:
Water spray nozzles must be inspected and maintained to ensure that they
are in place, continue to be aimed or pointed in the direction intended in the
system design, and are free from external loading and corrosion.
Where caps or plugs are required, the inspection must confirm they are in
place and free to operate as intended.
Drainage. The area beneath and surrounding a water spray fixed system
must be inspected visually on a quarterly basis to ensure that drainage
facilities, such as trap sumps and drainage trenches, are not blocked and
retention embankments or dikes are in good repair.
3. Operational tests
Water spray fixed systems must be serviced in accordance with this standard
and with the manufacturer’s instructions.
Under test conditions, the heat detection systems, where exposed to a heat
test source, must operate within 40 seconds.
Under test conditions, the flammable gas detection system, where exposed to
a standard test gas concentration, must operate within 20 seconds.
The water discharge patterns from all of the spray nozzles must be observed
to ensure that patterns are not impeded by plugged nozzles and to ensure
that nozzles are correctly positioned and that obstructions do not prevent
discharge patterns from wetting surfaces to be protected.
Where obstructions occur, the piping and nozzles must be cleaned and the
system retested.
Where the reading taken at the riser indicates that the water supply has
deteriorated, a gauge must be placed on the hydraulically most remote nozzle
and the results compared with the required design pressure.
Return to Service. After the full flow test, the water spray system must be
maintained and returned to service in accordance with the manufacturer’s
instructions.
Main drain tests must be conducted at the main riser to determine whether
there has been any change in the condition of the water supply piping and
controlling valves.
Readings must be compared with those made at the time of the original
acceptance tests or with those made at the time of the last test to determine
whether there has been any deterioration of the water supply.
To prevent freezing and corrosion, all low point drains in aboveground piping
must be opened, the pipe drained, and the valves closed and plugs replaced.
Where weep holes are provided in lieu of low point drains, they must be
inspected to ensure they are clear and unobstructed.
Systems out of service must be tested before being placed back in service.
All detectors must be tested and inspected monthly for physical damage and
accumulation of deposits on the lenses of optical detectors.
Controllers must be inspected for faults at the start of each working shift.
Valves on the water supply line must be inspected at the start of each working
shift to verify they are open.
1. General
This Standard provides the minimum requirements for the routine inspection,
testing, and maintenance of foam-water systems. Table 1 must be used to
determine the minimum required frequencies for inspection, testing, and
maintenance.
Fire pumps, water storage tanks, and valves common to other types of water-
based fire protection systems must be inspected, tested, and maintained as
specified in Table 1.
This section must not include systems detailed in NFPA 11, Standard for Low-
Expansion Foam.
The inspection must verify that all components, including foam concentrate
discharge devices and proportioning equipment, are installed in accordance
with their listing.
4. Proportioning system
To avoid false alarms where a supervisory service is provided, the alarm receiving
facility must be notified by the owner or designated representative as follows:
(1) Before conducting any test or procedure that could result in the
activation of an alarm
(2) After such tests or procedures are concluded
6. Inspection
System Piping and Fittings. System piping and fittings must be inspected for
the following:
Hangers and Supports. Hangers and supports must be inspected for the
following and repaired as necessary:
Where caps or plugs are required, the inspection must confirm they are in
place and free to operate as intended.
8. Water supply
9. Strainers
10. Drainage
Inspection of the concentrate tank must include verification that the quantity of
foam concentrate satisfies the requirements of the original design.
(1) Ball drip valves (automatic drains) are free and opened.
(2) External corrosion on foam concentrate storage tanks is not present.
(1) Strainers
(2) Verification that pressure vacuum vent is operating freely
(3) A check for external corrosion on foam concentrate storage tanks
(1) Strainers
(2) Verification that pressure vacuum vent is operating freely
(3) Verification that gauges are in good operating condition
(4) Verification that sensing line valves are open
(5) Verification that power is available to foam liquid pump
(1) Strainers
(2) Verification that pressure vacuum vent is operating freely
(3) Verification that gauges are in good working condition
(4) Verification that sensing line valves at pump unit and individual
proportioner stations are open
(5) Verification that power is available to foam liquid pump
(1) Strainers
(2) Verification that pressure vacuum vent is operating freely
(3) Verification that gauges are in good working condition
(4) Verification that power is available to foam liquid pump
Response Time. Under test conditions, the automatic fire detection systems,
when exposed to a test source, must operate within the requirements of NFPA
72, National Fire Alarm Code, for the type of detector provided and the
response time must be recorded.
Discharge Time. The time lapse between operation of detection systems and
water delivery time to the protected area must be recorded for open discharge
devices.
The discharge patterns from all of the open spray devices must be observed
to ensure that patterns are not impeded by plugged discharge devices and to
ensure that discharge devices are correctly positioned and that obstructions
do not prevent discharge patterns from covering surfaces to be protected.
Where obstructions occur, the piping and discharge devices must be cleaned
and the system retested.
During the full flow foam test, a foam sample must be taken.
Return to Service. After the full flow test, the foam-water system must be
returned to service and the foam concentrate tank must be replenished to
design level.
14. Maintenance
15. Proportioners
a) The ball drip (automatic type) drain valves must be disassembled, cleaned,
and reassembled.
b) The foam liquid storage tank must be drained of foam liquid and flushed.
(Foam liquid must be permitted to be salvaged and reused.)
c) The foam liquid tank must be inspected for internal and external corrosion and
hydrostatically tested to the specified working pressure.
a) The foam concentrate tank must be inspected for internal corrosion. Pickup
pipes inside the tank must be inspected for corrosion, separation, or plugging.
b) The foam concentrate tank must be drained and flushed. (Foam concentrate
must be permitted to be salvaged and reused.)
a) The vent must be removed from the expansion dome. While the vent is
removed, it must be ensured that the opening is not blocked and that dirt or
other foreign objects do not enter the tank.
b) The vest bonnet must be removed. The vacuum valve and pressure valve
must be lifted out.
c) The vent body must be flushed internally and the vacuum valve and the
pressure valve must be washed thoroughly. It must be ensured that the
screen is not clogged, and the use of any hard, pointed objects to clear the
screen must be avoided.
d) If the liquid has become excessively gummy or solidified, the vent body and
parts must be soaked in hot soapy water.
e) The vent body must be turned upside down and drained thoroughly. Parts
must be dried by placing them in a warm and dry area or by using an air hose.
f) Parts must be sprayed with a light Teflon® coating, and the vent must be
reassembled. The use of any type of oil for lubrication purposes must be
avoided, as oil is harmful to the foam liquid.
g) The vent bonnet must be replaced, and the vent must be turned upside down
slowly a few times to ensure proper freedom of the movable parts.
h) The vent must be attached to the liquid storage tank expansion dome.
1. General
This Standard provides the minimum requirements for the routine inspection,
testing, and maintenance of valves, valve components, and trim. Table 1 must
be used to determine the minimum required frequencies for inspection,
testing, and maintenance.
1.2 PROVISIONS
All system valves must be protected from physical damage and must be
accessible.
The general appearance and condition of all valves must be observed and
noted, and it must be verified that all valves are in the appropriate open or
closed position.
Main Drain Test. A main drain test must be conducted annually at each
water-based fire protection system riser to determine whether there has been
a change in the condition of the water supply piping and control valves.
Systems where the sole water supply is through a backflow preventer and / or
pressure reducing valves, the main drain test of at least one system
downstream of the device must be conducted on a quarterly basis.
Gauges must be inspected monthly to verify that they are in good condition
and that normal pressure is being maintained.
Gauges not accurate to within 3 percent of the full scale must be recalibrated
or replaced.
Each control valve must be identified and have a sign indicating the system or
portion of the system it controls.
When the valve is returned to service, a drain test (either main or sectional
drain, as appropriate) must be conducted to determine that the valve is open.
2.1 Inspection
The valve inspection must verify that the valves are in the following condition:
2.2 Testing
Each control valve must be operated annually through its full range and
returned to its normal position.
Post indicator valves must be opened until spring or torsion is felt in the rod,
indicating that the rod has not become detached from the valve.
Post indicator and outside screw and yoke valves must be backed a one-
quarter turn from the fully open position to prevent jamming.
A main drain test must be conducted annually at each system riser and any
time the valve is closed at each system riser or feed main after the control
valve has been closed to determine whether there has been a change in the
condition of the water supply piping and control valves.
A distinctive signal must indicate movement from the valve’s normal position
during either the first two revolutions of a hand wheel or when the stem of the
valve has moved one-fifth of the distance from its normal position.
The signal must not be restored at any valve position except the normal
position.
2.4 Maintenance
The operating stems of outside screw and yoke valves must be lubricated
annually.
The valve then must be completely closed and reopened to test its operation
and distribute the lubricant.
3. System valves
Alarm valves must be externally inspected monthly and must verify the
following:
Alarm valves and their associated strainers, filters, and restriction orifices
must be inspected internally every 5 years unless tests indicate a greater
frequency is necessary.
3.2 Maintenance
Inspection.
Valves must be inspected internally every 5 years to verify that all
components operate correctly, move freely, and are in good condition.
Maintenance.
Internal components must be cleaned, repaired, or replaced as necessary in
accordance with the manufacturer’s instructions.
Inspection.
Valve enclosure heating equipment for pre-action and deluge valves subject
to freezing must be inspected daily during cold weather for its ability to
maintain a minimum temperature of at least 4°C (40° F).
The gauge on the supply side of the pre-action or deluge valve must indicate
that the normal supply water pressure is being maintained.
The interior of the pre-action or deluge valve and the condition of detection
devices must be inspected annually when the trip test is conducted.
3.5 Testing
Each deluge or pre - action valve must be trip tested annually at full flow in
warm weather and in accordance with the manufacturer’s instructions.
Protection must be provided for any devices or equipment subject to damage
by system discharge during tests.
Where the nature of the protected property is such that water cannot be
discharged for test purposes, the trip test must be conducted in a manner that
does not necessitate discharge in the protected area.
Where the nature of the protected property is such that water cannot be
discharged unless protected equipment is shut down (e.g. energized electrical
equipment), a full flow system test must be conducted at the next scheduled
shutdown. In all cases, the test frequency must not exceed 3 years.
The water discharge patterns from all open sprinklers or spray nozzles must
be observed to ensure that patterns are not impeded by plugging and to
ensure that they are correctly positioned and that obstructions do not prevent
discharge patterns from wetting surfaces to be protected.
Where the reading taken at the riser indicates that the water supply has
deteriorated, a gauge must be placed on the hydraulically most remote nozzle
or sprinkler and the results compared with the required design pressure.
Return to Service. After the full flow test, the system must be returned to
service in accordance with the manufacturer’s instructions.
Grease or other sealing materials must not be applied to the seating surfaces
of pre-action or deluge valves.
Records indicating the date the pre-action or deluge valve was last tripped
and the tripping time as well as the individual and organization conducting the
test must be maintained at a location or in a manner readily available for
review by the authority having jurisdiction.
3.7 Maintenance
During the annual trip test, the interior of the pre-action or deluge valve must
be cleaned thoroughly and the parts replaced or repaired as necessary.
4.1 Inspection
a) The gauge on the supply side of the dry pipe valve must indicate that
the normal supply water pressure is being maintained.
b) The gauge on the system side of the dry pipe valve must indicate that
the proper ratio of air or nitrogen pressure to water supply pressure is
being maintained in accordance with the manufacturer’s instructions.
Systems equipped with low air or nitrogen pressure alarms must be inspected
monthly.
The dry pipe valve must be externally inspected monthly to verify the
following:
The interior of the dry pipe valve must be inspected annually when the trip test
is conducted.
4.2 Testing
Each dry pipe valve must be trip tested annually during warm weather.
Dry pipe valves protecting freezers must be trip tested in a manner that does
not introduce moisture into the piping in the freezers.
Every 3 years and whenever the system is altered, the dry pipe valve must be
trip tested with the control valve fully open and the quick-opening device, if
provided, in service.
During those years when full flow testing is not required, each dry pipe valve
must be trip tested with the control valve partially open.
Grease or other sealing materials must not be applied to the seating surfaces
of dry pipe valves.
A tag or card that shows the date on which the dry pipe valve was last tripped
and the name of the person and organization conducting the test must be
attached to the valve.
Separate records of initial air and water pressure, tripping air pressure, and
dry pipe valve operating conditions must be maintained on the premises for
comparison with previous test results.
Records of tripping time must be maintained for full flow trip tests.
4.3 Maintenance
Leaks resulting in air pressure losses greater than 70 kPa per week must be
located and repaired.
During the annual trip test, the interior of the dry pipe valve must be cleaned
thoroughly and parts replaced or repaired as necessary.
Low points in dry pipe sprinkler systems must be drained after each operation
and before the onset of freezing weather conditions.
All valves must be inspected quarterly to verify that the valves are in the
following condition:
A full flow test must be conducted on each valve at 5-year intervals and must
be compared to previous test results.
A partial flow test adequate to move the valve from its seat must be conducted
annually.
A full flow test must be conducted on each valve at 5-year intervals and must
be compared to previous test results.
A partial flow test adequate to move the valve from its seat must be conducted
annually.
A full flow test must be conducted on each valve at 5-year intervals and
compared to previous test results.
A partial flow test adequate to move the valve from its seat must be conducted
annually.
Hose valves must be inspected to ensure that hose caps are in place and not
damaged.
Hose valves must be inspected to ensure that restricting devices are present.
4.8 Testing
Class I and Class III standpipe system hose valves must be tested annually
by opening and closing the valves.
Hose valves that are difficult to operate or leak must be repaired or replaced.
Hose valves that are difficult to operate or leak must be repaired or replaced.
Maintenance. Hose valves that do not operate smoothly or open fully must be
lubricated, repaired, or replaced.
The inspection must verify that water flows through the valve when the fire
pump is operating at shut-off pressure (i.e., churn) to prevent the pump from
overheating.
During the annual fire pump test, the closure o f the circulation relief valve
must be verified to be in accordance with the manufacturer’s specifications.
The inspection must verify that the pressure downstream of the relief valve
fittings in the fire pump discharge piping does not exceed the pressure for
which the system components are rated.
During the annual fire pump flow test, the pressure relief valve must be
verified to be correctly adjusted and set to relieve at the correct pressure and
to close below that pressure setting.
The double check assembly (DCA) valves and double check detector
assembly (DCDA) valve must be inspected weekly to ensure that the OS&Y
isolation valves are in the normal open position.
5.1 Testing
For backflow preventers sized 50.8 mm (2 in.) and under, the forward flow test
must be acceptable to conduct without measuring flow, where the test outlet is
of a size to flow the system demand.
Where water rationing must be enforced during shortages lasting more than 1
year, an internal inspection of the backflow preventer to ensure the check
valves will fully open must be acceptable in lieu of conducting the annual
forward flow test.
Where connections do not permit a full flow test, tests must be completed at
the maximum flow rate possible.
The forward flow test must not be required where annual fire pump testing
causes the system demand to flow through the backflow preventer device.
All backflow devices installed in fire protection water supply must be tested
annually at the designed flow rate of the fire protection system, including
required hose stream demands.
Where connections do not permit a full flow test, tests must be conducted at
the maximum flow rate possible.
5.2 Maintenance
If fire department connection plugs or caps are not in place, the interior of the
connection must be inspected for obstructions, and it must be verified that the
fire department connection clapper is operational over its full range.
NFPA 25 - Standard for the Inspection, Testing, and Maintenance of Water Based Fire
Protection Systems
Because of the wide variation in the type of workplaces, it is only possible to give a
general guide to the level of precautions needed in most workplaces. So this
Standard does not seek to give specific advice about each individual type of
workplace.
This Standard uses an established method for assessing means of escape which has
been found to be generally acceptable in all but the most particular circumstances.
This method is based upon limiting travel distances according to the category of
potential fire risk the workplace falls into. These distances ensure that people will be
able to escape within the appropriate period of time.
2.1 High
Where highly flammable or explosive materials are stored or used (other than in small
quantities). Where unsatisfactory structural features are present such as:
lack of fire-resisting
separation; vertical or horizontal openings through which fire, heat and smoke
can spread in long and complex escape routes created by extensive
subdivision of large floor areas by partitions, or the distribution of display units
in shops or machinery in plants;
large areas of flammable or smoke-producing surfaces on either walls or
ceilings.
Where permanent or temporary work activities are carried out which have the
potential for fires to start and spread such as:
workshops in which highly flammable materials are used, e.g. paint spraying;
areas where the processes involve the use of naked flame, or produce
excessive heat;
refuse chambers and waste disposal areas; and
areas where foamed plastics or upholstered furniture are stored.
treatment or care is provided where the occupants have to rely upon the
actions of limited numbers of staff for their safe evacuation;
groups of people are working in isolated parts of the premises such as
basements, roof spaces, cable ducts and service tunnels etc; and
2.2 Normal
Where any outbreak of fire is likely to remain confined or only spread slowly, allowing
people to escape to a place of safety.
Where the number of people present is small and the layout of the workplace means
they are likely to be able to escape to a place of safety without assistance.
2.3 Low
Where there is minimal risk to people's lives and where the risk of fire occurring is
low, or the potential for fire, heat and smoke spreading is negligible.
The work done on assessing the risks and reducing the risk of fire occurring, together
with the knowledge gained about the location of people at risk, should generally
provide the information needed to establish the risk category or categories of the
workplace.
3.1 Other than in small workplaces, or from some rooms of low or normal fire risk, there
should normally be alternative means of escape from all parts of the workplace.
3.2 Routes which provide means of escape in one direction only (from a dead-end)
should be avoided wherever possible as this could mean that people have to move
towards a fire in order to escape.
3.3 Each escape route should be independent of any other and arranged so that people
can move away from a fire in order to escape.
3.4 Escape routes should always lead to a place of safety. They should also be wide
enough for the number of occupants and should not normally reduce in width.
3.5 Escape routes and exits should be available for use and kept clear of obstruction at
all times.
The aim is, from the time the fire alarm is raised, for everyone to be able to reach a
place of relative safety.
The time for people to reach a place of relative safety should include the time it takes
them to react to a fire warning. This will depend on a number of factors including:
what they may have had to do before starting to escape, eg turn off
machinery, help other people etc; and
their knowledge of the building and the training they have received about the
routine to be followed in the event of fire.
Where necessary, these can be checked by carrying out a practice drill. To ensure
that the time available for escape is reasonable, the length of the escape route from
any occupied part of the workplace to the storey exit should not exceed 45 metres.
There should be enough available exits, of adequate width, from every room, storey
or building. The adequacy of the escape routes and doors can be assessed by
reference to TT20 and TT21 of the NBR (B4 – National Building Regulations)
4.2 Corridors
Corridors should generally be about 1 metre wide. To avoid having to travel long
distances in corridors affected by smoke, those corridors which are more than 45
metres should be subdivided into approximately equal parts by providing, close-fitting,
self-closing fire doors.
4.3 Stairways
A stairway should be of sufficient width for the number of people who are likely to use
it in an emergency and it should not normally be less than 1 metre wide. However, a
narrower one may be adequate if one is sure that only a few people, who are familiar
with the stairway, will use it.
Where more than one stairway is provided, it should be assumed that the widest one
may be unusable as a result of the fire. This means that the remaining stairway(s) will
need to provide a satisfactory escape route for everyone present. There may be no
need to discount the widest stairway where each stairway is reached through a
protected lobby. Certain other compensatory features, such as sprinklers or smoke
control systems, may also be considered.
the stairway links no more than two floors and those floors are not linked to
another floor by an unprotected stairway; and
it is additional to that required for escape purposes; and
no escape route from a dead-end situation on an upper floor passes the
access to such a stairway.
People should not have to pass through a protected stairway to reach an alternative
stairway. Where this cannot be achieved, a stairway may be by-passed, for instance
by using doors connecting adjacent rooms. In such situations the doors should be
kept free from obstruction and available for use at all times.
A single stairway may be suitable for means of escape in workplaces of low or normal
fire risk, provided that people on each floor can reach it within the appropriate travel
time. It also needs to:
There is no need to provide protected lobbies where the workplace is of low fire risk.
This also applies to workplaces of normal fire risk, provided that either an automatic
fire detection system or sprinklers linked directly into the fire alarm system are
installed in the rooms or areas leading directly onto the protected stairway.
the stairway provides access between the ground and first floor and/or ground
floor and basement only, and an exit can be reached from any part of those
floors within the escape times given for single escape routes earlier in this
section; and
access to the stairway is clearly visible from any part of the floor it serves and
it exits not more than 6 metres from a storey exit leading direct to open air at
ground level.
Where an external stairway is provided, any door or window (other than toilet
windows) opening onto the stairway, or within 3 metres of it, should be fire-resisting.
Windows should be unopenable and doors should be self-closing.
Emergency escape routes and exit doors that are not in common use should be
clearly indicated, as appropriate, by suitable signs.
All signs should be in positions where they can be seen clearly. These signs must
take the form of a pictogram which may incorporate a directional arrow. The sign can
also be supplemented by words such as 'Fire Exit'. Fire safety signs must comply with
the relevant requirements of the Regulations
Doors people have to pass through in order to escape from the workplace should
open in the direction of travel where:
People escaping should be able to open any door on an escape route easily and
immediately, preferably without the use of a key. All outward opening doors used for
means of escape, which have to be kept fastened while people are in the building,
should be fitted with a single form of release device such as a panic latch, a panic
bolt, or a push pad.
Items which pose a potential fire hazard or those which could cause an obstruction
should not be located in corridors or stairways intended for use as a means of
escape. In particular, the following items should not be located in protected routes, or
in a corridor and stairwell which serves as the sole means of escape from the
workplace, or part of it:
All exits, emergency exits, and fire escapes afford unobstructed passage to a
safe area.
Grounds surrounding the facility are clear of accumulations of combustible
material and brush.
The checklist below should be used to assess Emergency preparedness for escape
purposes in surface areas:-
pagers etc.)
3) If messengers must be used, have they been
properly instructed?
4) Is the communication system in good working
condition?
5) Under what emergency conditions is it used
and who operates it?
6) Is the communications system protected from
sabotage?
7) Do all occupants know how to contact building
control to report a dangerous situation?
8) Is the building’ emergency communications
system tested monthly? By whom and to what
extent?
VIII. Additional Comments
All escape routes, including external ones, must have sufficient lighting for people to
see their way out safely. Emergency escape lighting may be needed if areas of the
workplace are without natural daylight or are used at night.
Before providing emergency escape lighting, check the relevant parts of the
workplace with the lights off to see whether there is sufficient borrowed light from
other sources to illuminate the escape route, e.g. street lights or unaffected lighting
circuits.
Where it is decided that there is insufficient light, it will be necessary to provide some
form of emergency lighting.
Emergency lighting needs to function not only on the complete failure of the normal
lighting, but also on a localised failure if that would present a hazard.
In smaller workplaces and outdoor locations with few people, the emergency escape
lighting could take the form of battery-operated torches placed in suitable positions
where employees can quickly get access to them in an emergency, e.g. on an escape
route. In other cases, you should provide an adequate number of electrically operated
emergency lighting units, installed to automatically come on if the power to the normal
lighting supply circuit, which they are connected to, fails.
Figure 1
9.2 Emergency lighting units should be sited to cover specific areas, for example:
intersections of corridors;
at each exit door;
near each staircase so that each flight of stairs receives direct light;
close to a change in floor level;
outside each final exit; by exit and safety signs that are required elsewhere
following the risk assessment;
within lift cars;
near fire-fighting equipment; and
near each fire alarm call point.
The lighting units should be placed as low as possible but at least 2 metres above
floor level (measured to the underside of the lighting unit). There may be need to
consider alternative mounting arrangements in areas where smoke could accumulate
and make the lighting ineffective. Where it is considered that an electrical emergency
lighting system is required, the system should be installed in accordance with British
Standard 5266: Part 1. The advice of a competent person who specialises in the
installation of these systems should be sought.
Emergency generators should have weekly and annual maintenance tags attached
for recording the inspector’s initials, date, and confirmation of
This standard prescribes minimum requirements for fire walls and fire barrier walls for use in
providing safety to life and protection of property from fire. These requirements apply to walls
that are required to separate buildings or subdivide a building to prevent the spread of fire.
Fire walls must be designed and constructed to remain stable after the
collapse of the structure due to fire on either side of the wall.
All fire walls and their supports must be designed to withstand a minimum
uniform load of 0.24 kPa from either direction applied perpendicular to the
face of the wall. All fire walls must be non-load-bearing. Structural framing
within the plane of the wall must be permitted to be load-bearing.
Where the fire wall or fire protective covering of a structural member is subject
to impact damage from moving vehicles or the handling of merchandise or
other activity, protection against impact damage must be provided for an
appropriate height but not less than 1.5 mm from the finished floor.
The framework on each side must be designed so that it resists the maximum
lateral pull that can be developed due to framework collapse in a fire on the
opposite side. Tied fire walls must be supported laterally by the building
framework with flexible anchors. Where centred on a single column line,
structural framing (i.e., columns and beams or trusses) at the column line
must have a fire resistance rating of not less than the required fire resistance
rating of the fire wall.
Where the wall is installed between double column lines, framing along the
first column line immediately on each side of the fire wall must have a fire
resistance rating of not less than the required fire resistance rating of the fire
wall.
A double fire wall must consist of two back-to-back walls. There must be no
connections, other than to the flashing, between the walls.
Each fire wall must be supported laterally by the building frame on its
respective side and must be independent of the fire wall and framing on the
opposite side.
Where the roofs on opposite sides of a fire wall are not of the same elevation, the fire
wall assembly must be arranged as described in either (a) or (b).
6. CLEARANCE
must be maintained by the protection of these joints. Protection for expansion and
seismic joints must be installed in accordance with tested design specifications.
The fire resistance of expansion, seismic, and control joints in fire walls must be
determined in accordance with ANSI/UL 2079, Tests for Fire Resistance of Building
Joint Systems, or ASTM E 1966, Standard Test Method for Fire Resistive Joint
Systems.
8. TERMINATION POINTS
A fire barrier wall must extend from the foundation or floor below to the underside of
the roof or floor deck above. Any voids or gaps created by the meeting of the wall and
floor below and the underside of the roof or floor deck above must be filled with an
approved material with a fire resistance rating at least equal to that of the fire wall.
Exception: The fire barrier wall must be permitted to terminate at the underside of an
individually protected structural member in the same plane. The structural member
must have a fire resistance rating of not less than that required for the fire barrier wall
and must prevent the passage of flame and hot gases.
9. FIRE RESISTANCE
The fire resistance rating of the wall assembly must be as required by the
applicable code or standard. Assemblies must be tested and rated in
accordance with NFPA 251, Standard Methods of Tests of Fire Endurance of
Building Construction and Materials.
Double wall assemblies must be considered to have a combined assembly fire rating
as specified in Table 1.
10.1 Parapets
Fire walls must be provided with parapets at least 0.76 m high. The parapet height
must be measured from the top surface of the roof being protected. Roofs sloped
greater than 6 mm per 305 mm downward toward the wall must be provided with a
minimum 0.9 m parapet.
Built-up roofs must be surfaced with gravel or slag for at least 7.6 m on both
sides of the fire wall. The application rate must be at least 19 kg / m2.
All single-ply membrane roof coverings must be protected by non-combustible
paver blocks, or No. 3 [nominal 2.54 cm to 5.08 cm diameter] gravel ballast in
accordance with ASTM D 448, Standard Classification for Sizes of Aggregate
for Road and Bridge Construction. Complete membrane coverage must be
provided at a rate not less than 48.8 kg / m2 for at least 7.6 m on both sides of
the fire wall.
Heat and smoke vents, skylights, and unprotected roof penetrations for air-
handling equipment or smoke control systems must be located at least 7.6 m
from fire walls requiring a fire resistance rating of more than 2 hours and at
least 1.3 m from fire walls requiring a fire resistance rating of 2 hours or less.
The length and arrangement of end walls must be in accordance with Table 2.
The fire resistance rating of the end walls must be from the outside and must
be a minimum of 1 hour but must be not more than two hours less than that of
the fire wall.
The following alternative to 10.5 must be permitted for light hazard and
ordinary hazard (Group 1 or 2) occupancies as defined in NFPA 13, Standard
for the Installation of Sprinkler Systems. The fire wall must extend to a
distance of at least 0.76 m beyond the exterior face of the exterior walls.
Figure 1
1. INTRODUCTION
Signs are used in buildings for imparting information to the occupants which is not
obvious or apparent in any other way. Safety signs are a particular type of such signs
which are displayed for the purpose of maintaining the well-being of the occupants of
the building. It is important therefore that occupants are aware of the meaning and
purpose of the signs and interpret them consistently.
In the past safety signs have been designed and produced for each building or
building type and have differed widely. Often signs have contained words which some
occupants are unable to understand either through illiteracy or unfamiliarity with
official languages.
The need to co-ordinate their design in the interest of safety is apparent and
nationally recognisable standard symbols desirable.
The requirements of local authorities vary depending on the town or city and must be
complied with. However, most accept SABS 1186 as the standard specification for
symbolic signs and these are illustrated in FPA bulletin No 19. These signs also
comply with NOSA and OHSAct requirements. SABS 1186 does not specify the sizes
of signs.
The signs are divided into five categories. Each type is recognisable by colour and
with one exception also by shape. The colours shown in this document are only
representative. The actual colours of the signs are to conform to SABS 1091 as
shown in the table below.
CATEGORY COLOUR
Border / Oblique Background Symbol
Diagonal
P Prohibitory Signal Red (All) White Black
M Mandatory - Ultramarine (F09) White
I Informatory - Emerald Green (F14) White
F Fire - White Signal Red (All)
W Warning Black Golden Yellow (B49) Black
3. POSITIONING OF SIGNS
All safety signs must be placed where they can be easily seen and provide the best
warning of the presence of a hazard. Generally they are best placed at high levels.
Obviously the sign should not be so placed as to create a hazard. To ensure that the
sign is easily seen it may be necessary to place it at 90 degrees to the passage or
walkway. (See Figure 1).
Figure 1
4. FIXING OF SIGNS
All signs that are not self supporting should be attached to flat surfaced or backing
plates. The edges of the backing plate should not protrude beyond the edges of the
sign. The sign may be framed but the frame should not dominate the sign and the
visible area of the sign should conform to the sizes given above. For attaching the
sign, galvanised nuts, bolts and washers should be used. In an atmosphere that
contains corrosive chemicals, these nuts, bolts and washers should be coated. The
colour of the heads of the rivets or bolts and nuts, should be the same as that part of
the sign in which they are placed.
Suitable precautions should be taken to prevent the penetration of moisture into the
joint between a metal sign and its support.
5. LIGHTING OF SIGNS
Figure 2
6. DEMARCATION
6.1 In respect of fire fighting equipment, additional indication should be provided by way
of broad red and white diagonal stripes painted on the wall or column as illustrated on
the attached sketch.
6.2 To prevent obstruction of equipment a similar square painted on the floor may also be
necessary.
7. POSITIONING OF SIGNS
7.1 When any building is occupied, signs indicating the direction to be travelled in the
case of any emergency must be provided.
7.2 In certain cases the regulations require these signs to be capable of being illuminated
for not less than 60 minutes in the event of a mains supply failure.
Figure 3
8. MAINTENANCE
Signs must be inspected regularly and kept clean and legible. Signs which are
damaged should be replaced.
SABS 1186 - Symbolic safety signs Part 1: Standard signs and general requirements
FPA Bulletin 19
SABS 1091 - National Colour Standard
STD IM17 - FLAMMABLE AND COMBUSTIBLE LIQUIDS BULK STORAGE/ DAY USAGE
Aboveground tanks that receive and transfer Class I liquids from mainline pipelines
must follow formal written procedures to prevent overfilling of tanks utilizing one of the
following methods of protection:
a) Instructions covering methods to check for proper line-up and receipt of initial
delivery to tank designated to receive shipment.
b) Provision for training and monitoring the performance of operating personnel.
c) Schedules and procedures for inspection and testing of gauging equipment
and high-level instrumentation and related systems. Inspection and testing
intervals must not exceed 1 year.
1.4 An underground tank must be equipped with overfill prevention equipment that will
operate as follows:
1) Automatically shut off the flow of liquid into the tank when the tank is no more
than 95 percent full
2) Alert the transfer operator when the tank is no more than 90 percent full by
restricting the flow of liquid into the tank or triggering the high-level alarm.
The application of NFPA 704, Standard System for the Identification of the Hazards of
Materials for Emergency Response, to storage tanks containing liquids must not be
required except where the contents have a health or reactivity degree of hazard of 2
or more or a flammability rating of 4. The marking must not need to be applied directly
to the tank but must be located where it can readily be seen, such as on the shoulder
of an accessway or walkway to the tank or tanks or on the piping outside of the bund
area. If more than one tank is involved, the markings must be so located that each
tank can readily be identified.
1.5.2 Unsupervised, isolated aboveground storage tanks must be secured and marked in
such a manner as to identify the fire hazards of the tank and the tank’s contents to
the general public. The area in which the tank is located must be protected from
tampering or trespassing, where necessary.
Operating Instructions
Operating instructions or procedures to be followed in a flood emergency must
be readily available.
Personnel Training
Personnel relied upon to carry out flood emergency procedures must be
informed of the location and operation of valves and other equipment
necessary to effect the intent of these requirements.
General
The procedures outlined in this subsection must be followed when taking
underground tanks temporarily out of service, closing them in place
permanently, or removing them. All applicable safety procedures associated
with working in proximity to flammable and combustible materials must be
strictly adhered to.
Temporary Closure
Tanks must be rendered temporarily out of service only when it is planned that
they will be returned to active service, closed in place permanently, or
Tanks remaining temporarily out of service for more than 1 year must be
permanently closed in place or removed.
Disposal of Tanks
1) Before a tank is cut up for scrap or landfill, the atmosphere in the tank
must be tested to ensure that it is safe.
2) The tank must be made unfit for further use by cutting holes in the tank
heads and shell.
Documentation
Only those used tanks that comply with the applicable sections of this
standard and are approved by the authority having jurisdiction must be
installed for flammable or combustible liquids service.
Each tank must be maintained liquid tight. Each tank that is leaking must be emptied
of liquid or repaired in a manner acceptable to the supervisor having jurisdiction.
Tanks that have been structurally damaged, have been repaired or reconstructed, or
are suspected of leaking must be tested or in a manner acceptable to the supervisor
having jurisdiction.
Tanks and all tank appurtenances, including normal vents and emergency vents and
related devices, must be properly maintained to ensure that they function as
intended.
Openings for gauging on tanks storing Class I liquids must be provided with a vapour-
tight cap or cover. Such covers must be closed when not gauging.
2. PIPING SYSTEMS
This chapter must apply to piping systems consisting of pipe, tubing, flanges, bolting,
gaskets, valves, fittings, flexible connectors, the pressure-containing parts of other
components such as expansion joints and strainers, and devices that serve such
purposes as mixing, separating, snubbing, distributing, metering, controlling flow, or
secondary containment of liquids and associated vapours.
2.1 Testing
Unless tested in accordance with the applicable sections of ASME B31, Code for
Pressure Piping, all piping must be tested before being covered, enclosed, or placed
in use. Testing must be done hydrostatically to 150 percent of the maximum
anticipated pressure of the system or pneumatically to 110 percent of the maximum
anticipated pressure of the system, and the test pressure must be maintained for a
sufficient time to conduct a complete visual inspection of all joints and connections. In
no case must the test pressure be less than gauge pressure of 34.5 kPa measured at
the highest point of the system, and in no case must the test pressure be maintained
for less than 10 minutes.
Existing piping must be tested in accordance with this subsection if there is indication
that the piping is leaking. Piping that could contain a Class I, Class II, or Class IIIA
liquid or vapour must not be tested using air.
This checklist is based upon Standard G29. For more information please consult this
Standard.
This checklist is based upon Standard G28. For more information please consult this
Standard.
This checklist is based upon Standard G31. For more information please consult this
Standard.
SEC 4 – SUBSTATIONS
This checklist is based upon Standards G18, G19, G20, G21 and G33. For more information
please consult these Standards.
hours?
3) Is there at least one 9 kg DCP fire extinguisher per
transformer? (Maximum of four where four or more
transformers are grouped together)
4) Are fire extinguishers located between 5 and 15
metres from the transformer bank, to make them
easily accessible even after the outbreak of fire?
5) Is some means such as lockable gates provided
across the front of transformer bays to ensure that
access is not readily possible for unauthorised
persons?
6) Is the transformer bay free from additional articles of
material or equipment, particularly combustible or
flammable materials?
7) Where a transformer is installed in a building, check
that the fire control panel is on and free from any
faults?
III. Bunding
1) Where drainage is provided for bunding, is the
draincock locked in the closed position under normal
operating conditions?
2) Where a bund has been filled with aggregate, is this
aggregate free from a dust layer which would
otherwise reduce its capacity?
IV. Additional Comments
This checklist is based upon Standard G26. For more information please consult this
Standard.
This checklist is based upon Standard G10. For more information please consult this
Standard.
This checklist is based upon Standards G32 and G33. For more information please consult
these Standards.
This checklist is based upon Standard U5. For more information please consult this
Standard.
This checklist is based upon Standards U8, U9 and U10. For more information please
consult these Standards.
This checklist is based upon Standard G41. For more information please consult this
Standard.
This checklist is based upon Standards G42 and G44. For more information please consult
these Standards.
This checklist is based upon Standard U12. For more information please consult this
Standard.