MONTHLY PROGRESS REPORT

DATE OF REPORT 31.03.2020

Client Project Management Contractor


Consultant
NBCC –DWC-LLC M/s. City Diamond
[A subsidiary of NBCC Contracting LLC.
(India) Limited]

Page 1 of 9
EXECUTIVE SUMMARY
Name of Work Construction of India Pavilion at World Expo 2020
at Dubai i/c Design, Engineering, Operation &
Maintenance.
Sanctioned Cost INR 286.00 Cr (150,410,982.01 AED)
Built Up Area = Main Pavilion(B+G+3) 7879 sqm
8736 sqm Plaza (G+1) 857 sqm
Name of Contractor M/s. City Diamond Contracting LLC
Contract Value INR 232.78 Cr (122,520,375.00 AED)
Timeline of Completion of Pavilion 30.09.2019
Completion Construction
(with Completion of Interior 30.06.2020
contractor) Construction work
Completion of Exhibition 31.08.2020
Installation works
Expo Event Duration 20.10.2020 to 10.04.2021
Decommissioning/ Removal of Pavilion 30.09.2021

TIMEOVERVIEW

Enabling Work Permit 08.08.2019

Plot Possession 08.08.2019

Lay down Area for site office set up 08.08.2019

Final Design 10.11.2019

Building Permit 18.11.2019

Commencement date (DOS) 07.08.2019 -

Original Completion date 31.08.2020 -

Number of days as per contract document 390 Days -

Time elapsed 227 Days -


Extension of time NIL -
Revised completion date Not Applicable -

COSTOVERVIEW

Sanctioned Project Cost AED 150,410,982 (INR 286.00Cr) 100 %


Approved variations Nil
Project Cost after variations AED 150,410,982 100 %
Advance paid Nil
RA payment made AED 27,253,271.00 22.25%
Payment claim in progress Nil

Page 2 of 9
PHYSICAL PROGRESS as on 31.03.2020

A. EXPO Building

Activity Timeline as per Actual Status


Programme
Enabling work 14.09.2019 Completed -12.09.2019
Excavation work 28.09.2019 Completed-26.09.2019 (in 13 Days)
Earth Compaction 30.09.2019 Completed -27.09.2019
Lift and Sump pits 03.10.2019 Completed - 30.09.2019
PCC and masonry work
RCC for Raft of pavilion 22.10.2019 Completed -23.10.2019
building
Basement Wall, 26.12.2019 Completed-27.12.2019.
Columns and Slab
Casting
De-shuttering of GF 25.01.2020 Completed – 25.01.2020
slab
External 28.01.2020 Completed – 05.02.2020
Waterproofing
Backfilling 13.02.2020 Completed- 15.03.2020
Steel structure 24.03.2020 Zone 1, 2 & 3: Completed.
erection.
Zone 4: Coloumn errection completed.
(2500MT steel fabricated Trusses & Infill beams fixing in progress.
as on 31.03.2020) Material available at site.
All work will be completed by 04.04.2020

Staircase fabrication will be completed by


10.04.2020.
Deck slab casting 1st Floor- Zone 1:
03.03.2020 1st Floor: Completed.
2nd Floor: Completed
2nd Floor -
08.03.2020 Zone 3:
3rd Floor: Completed.
3rd Floor- Service Floor: Completed.
14.03.2020 Terrace: Deck sheet installation in progress.

Terrace- Zone-2:
18.03.2020 1st floor: Deck sheet installation & slab casting
completed.

Zone-4:
3rd floor & Terrace: Deck sheet installation &
slab will be completed by 10.04.2020
Internal Finishes and 04.06.2020 a.) Blockwork: Will be completed by 5.4.20
MEP • Basement: 98% completed.
• Toilets: 40% completed.
• Staircase: Pending.

b.) Plastering: Under progress in basement.


Page 3 of 9
c.) Highlevel MEP works:
• Basement: Completed.
• GF: 25 % Completed.

d.) FCUs Installation:


Under progress at Ground Floor.

e.) Intumescent painting:


• Zone-1: 1st & 2nd Floor completed.
• Zone-3: 3rd Floor completed.
• Zone-2 & 4: Yet to start.
External Glazing 30.04.2020 Sample fixing completed.
Work will be completed by 30.04.2020
External Catwalk and 30.06.2020 • Tender process completed.
Installation of Facade • Dubai Authority Development Control
approved Revised Façade Design on
22.03.2020 with comments. MEP design
under preparation and submitted to Expo
shortly.

B. Plaza Building:

Activity Timeline as per Actual Status


Programme
Excavation for foundation 12.12.2019 Completed
Antitermite/Laying of PCC 12.12.2019 Completed
Foundation Casting 29.01.2020 Completed
Pedestral casting 16.01.2020 Completed.
Pedestral waterproofing 20.01.2020 Completed
Grade slab casting 09.02.2020 Grade slab casting for 85% floor area.
Erection of structural steel GF- 03.03.2020 Fabrication work completed.
FF- 08.03.2020 03 columns erected out of 40.
Roof-18.03.2020 Work will be completed by 08.04.2020
Decking slab casting GF- 08.03.2020 GF slab- 13.04.2020
FF/Roof- 22.03.2020 FF slab- 15.04.2020
Physical Progress : 41%
Financial Progress : 27.07%
Manpower Deployment- On site: 192 Nos (Bar benders, Carpenters, Operators, Electricians,
Mechanics, MEP, Fire fighting).

Dynamic Façade of Building


❖ Ministry desired that the Façade of Building to be changed from GRC to
Dynamic/KineticFaçade.
❖ Based on various meetings and options submitted by NBCC Dynamic Façade with Moving
Blocks approved in principle by Ministry.
❖ NBCC floated open tender to invite bid from Dubai registered contractors for Dynamic façade.
Received single bid and the Price was abnormally high.
❖ Fresh Short Tender invited with revised parameters. Financial bid opened and negotiation
completed. Ready to place work order on receipt of Budget approval from Ministry/MOC.
❖ Dubai Authority Development Control approved Revised Façade Design on 22.03.2020 with
comments. MEP design under preparation and submitted to Expo shortly.

Curation and Exhibit Works:

Page 4 of 9
❖ During the initial estimation the Provision made for Hardware i.e. Hardware for Audio Video, Media,
Light, Graphic Exhibit etc for Curation considered in general based on the initial concept design.
❖ During the review of Project Ministry/FICCI desired that the Curation need to be designed with
Theme/Content etc with Special effects to show case India to International Participants.
❖ Keeping in view the inputs given by Ministry/FICCI during several meetings and presentations,
NBCC has finally prepared Design Concept of Curation. The revised Design Concept of Curation is
approved in principle by Ministry.
❖ Detailed design of Curation Content / Interior Decoration is in progress as per Budget of Rs. 55 Cr
given by Ministry.

SITE PHOTOGRAPH AS ON 31.03.2020

Page 5 of 9
Site Progress View

Page 6 of 9
Zone 2- 1st Floor slab ready to cast

Plaza structural steel erection in progress.

Page 7 of 9
Intumescent painting in progress in Zone-03

MEP and Blockwork in basement as on 30.03.2020

Page 8 of 9
Blockwork in progress at toilet area in Ground Floor

**************

Page 9 of 9