MATERIAL REQUISITION FOR FILTER Rev.: 1
SEPERATORS
SCOPE
This document includes the technical and commercial requirements for filter
seperators within the scope of Reconstruction Of The International Airport
Astana.
1. DEFINITIONS
Supplier: The Bidder becomes the Supplier when his Bid is accepted and a
Purchase Order or a Supply Agreement is made between the Bidder and the
Contractor.
Bid: Technical and commercial proposal presented by the bidder including all
the requirements of this document.
Contract: The main Contract between the Employer and the Contractor.
2. TECHNICAL REQUIREMENTS
The supplier shall deliver the digital (electronic) files of all engineering
documents (including installation operation and maintenance manuals, where
applicable) in all transmissions (i.e. from the initial “for approval” versions until
“as-built” stage.
3. COMMERCIAL REQUIREMENTS
Applicable commercial contract documents are presented in Appendix II.
Page 1 / 9
Doc. No. Reconstruction Of The International Airport Prep.By:
Astana
MATERIAL REQUISITION FOR FILTER Rev.: 1
SEPERATORS
APPENDIX – I
All filter-seperators within the scope of this requisition shall be designed, built,
tested and shipped according to the provisions of API 1581.
General requirements related with the manufacture and supply of the filter
seperators include the following:
All filter-seperators (body, sump, cover, davit arm, coalescer, filters, etc.)
shall in all respects be suitable for reliable and continuous operation in the
service conditions at the Astana Airport.
Low: -40°C
High: +50°C
1.2. Medium:
1.3. Materials:
1.4. Construction:
Page 2 / 9
Doc. No. Reconstruction Of The International Airport Prep.By:
Astana
MATERIAL REQUISITION FOR FILTER Rev.: 1
SEPERATORS
Connections of the filter seperators shall be flanged as per ANSI B16.5 class
150#.
The cover plate shall be supported by a davit arm assembly that shall be
capable of moving the cover plate clear from the elements for maintenance.
Unit shall be provided with coalescers and separators that have been
qualified to the performance requirements of API Publication 1581, Group II,
Class B. Separators shall be 200 mesh stainless steel coated on both sides
with teflon. Coalescers shall have a minimum capacity of 5.7 mL/s per mm of
length, and separators shall have a minimum capacity of 20.7 mL/s per mm
of length.
Acceptance Criteria for fuel exiting the filter separator after the flushing
procedure is completed shall be as follows:
a. All fuel samples must be clear and bright. Other visual clues must be
observed and acted upon accordingly, i.e.; feel, color, odor, etc. This
test shall be performed with a minimum of 3 gallons of jet fuel.
Page 3 / 9
Doc. No. Reconstruction Of The International Airport Prep.By:
Astana
MATERIAL REQUISITION FOR FILTER Rev.: 1
SEPERATORS
1.6. Ancillaries:
Each filter-seperator shall have a pressure relief valve that complies with
the provisions of the specification attached hereto. Pressure relief valve
setting shall be continuously adjustable up to 12 barg, however shall be
delivered factory set to 8 barg. The outlet of the relief valves shall be
threaded or flanged for easy connection to drain lines.
Each filter-seperator shall have an indicator for displaying the pressure drop
between the inlet and outlet of the elements. The indicator shall clearly
indicate the safe operation range of the elements at maximum flow values
and shall be provided with vents to atmosphere to check free travel of the
indicator in both directions during operation. Furthermore, the indicator
assembly shall provide a hydraulic signal to the slug valve to shut it off
when the difference in pressure increases above the preset value.
- Sampling Connections:
Two sampling connections (one at the inlet and one at the outlet of the filter-
seperator) shall be provided on the equipment. The connections shall be
made of stainless steel and inlet line shall be trimmed to 60 deg. With the
opening facing to the flow direction and extending approximately to the
centerline of the pipe it is mounted on.
Each filter seperator shall be equipped with a sump at the bottom. Water
collected in this sump shall automatically monitored by a float and be
discharged after a certain limit is reached. The sump shall be insulated and
heated electrically via an external resistance.
- Slug Valve:
Each filter seperator shall be equipped with a slug valve. The valve shall
continuously monitor the signal inputs from the pressure difference indicator
and the automatic water discharge float. If any of the signals rises above
Page 4 / 9
Doc. No. Reconstruction Of The International Airport Prep.By:
Astana
MATERIAL REQUISITION FOR FILTER Rev.: 1
SEPERATORS
the preset values, the valve shall automatically shut the flow off and should
not re-open without operator interference.
The valves shall be flanged. Flanges shall be raised face as per ANSI
B16.5 class 150#.
Internal surface of the body and cover in contact with the fuel shall be
blast cleaned to SA 2.5 (near white metal). The surface, then shall be
cleaned of any rust, scale, dust, traces of water, grease and oil prior to
application of coating.
1.7.2. Lining:
The dry film thickness of the finished lining shall be 350 microns
minimum.
External surface of the body and cover in contact with the fuel shall be
blast cleaned to SA 2.5 (near white metal). The surface, then shall be
cleaned of any rust, scale, dust, traces of water, grease and oil prior to
application of coating.
1.8.2. Painting:
The surface shall be coated with two coats of anticorrosive paint, each
25 microns thick and 2 coats of enamel paint in white color according
to Attachment 2.
The dry film thickness of the finished system shall be 100 microns
minimum.
1.9.1 General:
Page 5 / 9
Doc. No. Reconstruction Of The International Airport Prep.By:
Astana
MATERIAL REQUISITION FOR FILTER Rev.: 1
SEPERATORS
they will. The supllier shall furnish a production and inspection plan for the
manufacturing of the filter-seperators before the commencement of the works
and clearly indicate the inspection points and dates. Such inspections may
be performed in the absence of the Employer’s representative if the
Employer agrees so. The Employer may assign a third party inspection body
to represent himself for observation or performance of the inspections and
approve the results. Absence of the Employer or his representative shall not
free the Supplier to carry out the inspections and record and present the
results.
Check analysis shall be carried out for materails used for the body, flanges,
cover, sump, etc. Furthermore, magnetic particle inspection shall be carried
out for all castings in accordance with ASTM Standards, or equivalent,
relevant to the material used.
1.10. Marking:
1. Supplier
2. Model
3. Serial Number
4. Max. Flow Capacity (m3/h)
5. Maximum Pressure (Barg)
6. Pressure Design Standard
7. Design Standard (API 1581)
1.11. Documentation:
The Bidder shall furnish to the Contractor the documents specified below for
evaluation.
Page 6 / 9
Doc. No. Reconstruction Of The International Airport Prep.By:
Astana
MATERIAL REQUISITION FOR FILTER Rev.: 1
SEPERATORS
Index
Description of machinery and accessories
Maintenance instructions
Safety instructions
List of enclosures (diagram, drawings, pamphlets)
List of all parts of each filter-seperator, including filtration elements
and coalescer, together with catalogue number for eventual orders
Purchasing specification
Identification number
Instructions for repairs and replacement with details of mounting
clearances for the slug valve.
As described in attachment 1.
2.2. Training:
As described in attachment 1.
As described in attachment 1.
The filter-seperators shall be supplied ready to run complete with all the
elements required. In addition the Supplier shall provide the following spare
parts:
Page 7 / 9
Doc. No. Reconstruction Of The International Airport Prep.By:
Astana
MATERIAL REQUISITION FOR FILTER Rev.: 1
SEPERATORS
One of the sets will be used during the flushing operation and the other set
will be left with the Owner for routine replacement.
As described in attachment 1.
3.1. General
Inlet and outlet flanges of the slug valve and the filter-seperator shall be
carefully closed by shock-proof plugs or plates.
Page 8 / 9
Doc. No. Reconstruction Of The International Airport Prep.By:
Astana
MATERIAL REQUISITION FOR FILTER Rev.: 1
SEPERATORS
APPENDIX-II
COMMERCIAL DOCUMENTS
1. BID BASIS
The Bidder will propose their best prices, best possible delivery, transport and
payment.
Data Sheets for the below listed pumps are attached to this Material Requisition.
3. COMPLIANCE STATEMENT
The Bidder shall certify submittals forwarded to SMLA with the following certifying
statement: "I hereby certify that the (equipment) (material) (article) shown and
marked in this bid is that proposed to be incorporated with Astana Airport
Reconstruction Project, is in compliance with the attached specification and is
submitted for the SMLA approval”.
If there is discrepancy between bid and specification, Bidder shall clearly mention in
this statement.
Bidder must sign and stamp all the pages of specification and its attachments and
provide with the compliance statement.
Bids submitted without compliance statement and signed and stamped specification
will not be evaluated.
Page 9 / 9