Вы находитесь на странице: 1из 35

Republic of the Philippines

ENERGY REGULATORY COMMISSION


San Miguel Avenue, Pasig City

IN THE MATTER OF THE APPLICATION


FOR AUTHORITY TO REVISE/UNBUNDLE
RATES IN ACCORDANCE WITH SECTION
36 OF R.A. 9136, AND FOR APPROVAL OF
APPRAISAL OF PROPERTIES, WITH
PRAYER FOR PROVISIONAL AUTHORITY.

ERC CASE NOS. 2002-18


and 2002-143

MANSONS CORPORATION (MANSONS)


Applicant.
x-----------------------------------------------------x

D E C I S I O N

Before the Commission for resolution is the application filed on January 16,

2002 by applicant Mansons Corporation (MANSONS) for authority to

revise/unbundle its rates in accordance with Section 36 of Republic Act No. 9136

(R.A. 9136) with prayer for provisional authority. Subsequently, on March 4, 2002,

MANSONS filed an “Amended Application”.

Having found the application sufficient in form and substance with the

required fees having been paid, an Order and a Notice of Public Hearing were

issued both dated April 10, 2002 setting the same for initial hearing on June 11,

2002.
Page 2 of 35

In the same Order, MANSONS was directed to publish at its own expense,

the Notice of Public Hearing twice for two (2) successive weeks in two (2)

newspapers of nationwide circulation in the country, the last date of publication to

be made not later than two (2) weeks before the scheduled date of initial hearing.

Copies of the application, the Order and the Notice of Public Hearing were

furnished the Office of the Solicitor General (OSG), the Commission on Audit

(COA) and the Committees on Energy of both Houses of Congress and were

requested to have their respective duly authorized representatives present at the

initial hearing.

Likewise, copies of the Order and the Notice of Public Hearing were

furnished the Offices of the Municipal Mayors of Floridablanca and Guagua, both

in the Province of Pampanga, for the appropriate posting thereof on their

respective bulletin boards.

During the June 11, 2002 initial hearing of this case, applicant and Atty.

Joel Jimenez of the Office of the Solicitor General appeared. Applicant presented

its proofs of compliance with the Commission’s publication and posting of notice

requirements and had these marked as Exhibits “A” to “C”, inclusive. Thereafter,

it moved for a resetting of the case to have its financial statements re-audited to

conform to the requirements of the Commission. Atty. Jimenez did not object.

At the September 10, 2002 hearing, applicant presented its witnesses,

Engr. Reynaldo Gimongala, applicant’s Head, Engineering Department and Mr.

Ricardo Limbauan, applicant’s External Auditor, for direct examinations. Engr.

Gimongala testified on the manner by which the applicant prepared its revised

rate application including the different schedules using the unbundling process.
Page 3 of 35

Mr. Limbauan testified on the re-audit made on applicant’s financial statements.

In the course thereof, documents were presented and marked as Exhibits “D” to

“DD”, inclusive.

The Commission propounded clarificatory questions on the witnesses. In

the course thereof, applicant was directed to submit the several explanations on

matters asked.

At the continuation of the hearing on November 15, 2002, applicant

presented its last witness, Engr. Roberto Mendoza, Assistant Vice President for

Machinery and Technical Specialties of Asian Appraisal, Inc., for direct

examination. He testified on the methodologies used in arriving at the sound

value appraisal of applicant’s properties. In course thereof, documents were

presented and marked as Exhibits “EE” to “FF-2”, inclusive. Thereafter the

Commission propounded clarificatory questions. Applicant then moved that it be

given ten (10) days from said date of hearing to submit its formal offer of exhibits

which the Commission granted.

On November 19, 2002, applicant filed its formal offer of exhibits which was

admitted for the purposes for which they were being offered.

On November 28, 2002, applicant was directed to submit its Assets

Additions and Retirements from 1993 to 1998 and amend its formal offer of

exhibits.

I. MANSONS PROPOSAL

MANSONS proposed to adopt and applies for approval the following rate

schedule which embody the unbundling of its rates in accordance with the sectors
Page 4 of 35

or functions identified in Section 5 of RA 9136. These rates were developed on

the basis of the data and calculations as contained in the schedules prescribed in

the Uniform Rate Filing Requirements (UFR) as per ERC Order dated October 30,

2001, as follows:
TABLE 1

RATE SCHEDULE
Residential Service
Commercial
Street Lights
Industrial 1
Industrial 2

MANSONS classified its existing Industrial customers into two (2)

categories based on load schedule, such as: Industrial 1, which shall be applied

to regular industrial customers; and Industrial 2, which shall be applied to large

industrial customer.

Further, MANSONS incorporated the Government Building customers in

the Residential class, while Hospital customer was included in Industrial 1 class.

MANSONS took into consideration that Government Building and Residential

class, Hospital and Industrial 1 class rate level are almost the same, respectively.

I.A. Revenue Requirement

MANSONS calculated its Total Revenue Requirement based on test year

2000 using the Return on Rate Base (RORB) methodology. The application

contains assets valued both at historical costs and appraised value. MANSONS’

calculation used the appraised or sound value of assets, as underlying basis for

the formulation and design of the Revised Rate Schedules. The submitted
Page 5 of 35

historical cost of assets, as required in the UFR, was solely for informational

purposes, and not as basis for ratemaking.

On the basis of the submitted schedule (Schedule B), the proposed Total

Revenue Requirement amounted to PhP 82,818,978, which was calculated by

adding the total cost of service and the total return on rate base (computed at 12%

of the rate base). Details as follows:


TABLE 2

Amount
Account Name (PhP)
Fuel 0
Purchased Power 63,039,806
Payroll 4,924,542
Operation & Maint.enance 6,068,284
Depreciation & Amortization 4,358,090
Income Taxes 0
Other Expense 0
Return On Rate Base 4,428,257
Revenue Requirement 82,818,978
Less: Other Revenue Items 0
Total Revenue Requirement 82,818,978

I.A.1. Operating Revenue

MANSONS reported a total operating revenue of PhP 65,326,040,

computed as follows:
TABLE 3

Total Revenue
Customer Type (PhP)
Residential 47,429,048
Commercial 7,848,835
Streetlights 1,701,975
Industrial 1 6,162,131
Industrial 2 2,184,051
Total 65,326,040

I.B. Rate Base

MANSONS proposed that Schedule B (Restated Value of assets) be used


Page 6 of 35

as basis in the determination of its rate base. Thus, MANSONS utilized the

appraised value of assets as of September 1, 1998 as reported by an

independent appraiser, Asian Appraisal Co., Inc. (AACI) in the rate base

determination. An adjustment was made by MANSONS to reflect additions,

retirements for the period September 2, 1998 to December 31, 2000. The

proposed rate base is as follows:


TABLE 4

Amount
(PhP)
Distribution Plant 64,360,260
General Plant 652,600
Total Plant In Service 65,012,860

Distribution Plant 40,138,830


General Plant 127,160
Total Accum. Depr. 40,265,990

Net Plant In Service 24,746,870


Cash Working Capital 12,155,270
Total Rate Base 36,902,140

I.B.1. Plant in Service

In support of its unbundled rate application, MANSONS submitted for

approval to the Commission a report of AACI with respect to the sound value of its

properties existing as of September 1, 1998. Based on the said report,

MANSONS’ assets were appraised based on cost level as of September 1998 at

the prevailing Peso-to-Dollar exchange rate of PhP 43.923 to US$1.00 with total

cost of reproduction, new of PhP 64,263,600 and sound value of PhP 28,355,700,

to wit:
TABLE 5

Cost of Reproduction,
Particulars New Sound Value
Electrical Distribution System PhP 63,686,000 PhP 27,821,000
Transportation Equipment 415,000 415,000
Furniture & Office Equipment 162,600 119,700
TOTAL PhP 64,263,600 PhP 28,355,700
Page 7 of 35

I.C. Weighted Average Cost of Capital (WACC)

MANSONS proposed a Weighted Average Cost of Capital of 12.00% or

equivalent to a return of PhP 4,428,257, computed as follows:


TABLE 6

Amount Component Component Weighted


Component As Of As % of Total Cost Of Cost Of
12/31/2000 Capital Capital
Common Equity PhP 30,544,246 100% 12.00% 12.00%
Total PhP 30,544,246 100% 12.00%
Rate Base PhP 36,902,140
Return On Rate Base PhP 4,428,257

I.E. Rate Design

MANSONS’ proposed rate structure consisted of charges for the following

specific functions: a) Generation/Transmission, b) Distribution, c) Supply, and

d) Metering.

I.E.1. Generation Charge

In calculating the Generation and Transmission Charge, MANSONS

submitted for approval the following formula:

Generation Charge without Demand Meter:

A 1
------------------- x -------
B-(C+C1+C2) 1-FT

Where:

A= Cost of power for the previous month (exclusive of prompt payment


discounts) less amount recovered from pilferage.
B= kWh purchased for the previous month
C= System loss equivalent to 15% (in kWh)
C1= 1% Company Used (in kWh) or actual whichever is lower
C2= kWh Lifeline consumption for the previous month
FT= Local and National Franchise Tax (2.5%)

Generation Charge with Demand Meter:


A 1
------------------- x -------
B-(C+C1+C2) 1-FT
Page 8 of 35

Where:

A= Cost of power for the previous month (exclusive of Demand charge and prompt
payment discounts and other discounts) less amount recovered from pilferage.
B= kWh purchased for the previous month
C= System loss equivalent to 15% (in kWh)
C1=1% Company Used (in kWh) or actual whichever is lower
C2= kWh Lifeline consumption for the previous month
FT= Local and National Franchise Tax (2.5%)

I.E.2. Transmission Charge

MANSONS likewise proposed a formula designed to calculate the

Transmission Charge:

A 1
------------------- x -------
B-(C+C1+C2) 1-FT

Where:

A= Cost of transmission for the previous month (exclusive of prompt payment


discounts and other discounts) less amount recovered from pilferage.
B= kWh purchased for the previous month
C= System loss equivalent to 15% (in kWh)
C1=1% Company Used (in kWh) or actual whichever is lower
C2= kWh Lifeline consumption for the previous month
FT= Local and National Franchise Tax (2.5%)

I.E.3. System Loss

MANSONS proposed a 15% system loss cap to be the recoverable rate for

its system loss through the proposed Generation and Transmission Charge

Formula. Since its franchise area covers mostly agricultural lands, MANSONS

proposed the following technical and non-technical losses per customer class, to

wit:
TABLE 7

Proposed Cap for technical loss:


Customer Class Proposed Ave. Cap/Mo. (%)
Commercial 2
Residential 3
Industrial 1
Street Lights 2
TOTAL 8
Page 9 of 35

TABLE 8

Proposed Cap for non-technical loss:


Customer Class Proposed Ave. Cap/Mo. (%)
Commercial 2
Residential 3
Industrial 0.5
Street Lights 1
Others 0.5
TOTAL 7.0

I.E.4. Distribution Charge

MANSONS proposed a peso per kilowatt-hour for distribution charge

applicable to all customer classes.

I.E.5. Supply and Metering Charges

MANSONS proposed a peso per kilowatt-hour for both metering and supply

function applicable to all customer classes.

I.F. Inter-Class Cross Subsidy

The total revenue requirement for each customer class was compared to

normalized existing rates, which resulted to the following inter-class cross subsidy

calculation:
TABLE 9

Rates per Cross


Customer Actual Average Total Revenue Subsidy
Class Average Rate Increase Requirement
Residential 4.9522 0.5823 5.5345 5.7329 (0.1984)
Commercial 5.0978 0.5823 5.6801 5.0868 0.5933
Streetlights 3.9816 0.5823 4.5639 4.8947 (0.3308)
Industrial 1 5.2125 0.5823 5.7948 5.1429 0.6518
Industrial 2 5.0917 0.5823 5.6739 5.3073 0.3667
Total 4.9921 0.5823 5.5744 5.5744
Page 10 of 35

I.G. Lifeline Rate

MANSONS proposed a rate of PhP 1.7865 per kWh for its lifeline

customers computed based on its proposed Distribution Charges. MANSONS’

basis for determining the consumption level for its lifeline customers is as follows:
TABLE 10

Quantiy Type of Load Watts


1 Incandescent Bulb 40
1 20 Watts Fluorescent Lamp 32
1 Convenience Outlet 13
Total 85

With regard to the recovery of loss in revenue due to lifeline rate,

MANSONS proposed the following:

1. Any loss in revenue due to lifeline rate will be recovered thru its

proposed Generation Charge Formula.

2. If the Commission will not consider the said formula, any loss in

revenue will be recovered by charging all customers by peso per

kilowatt-hour for lifeline loss, computed as follows:


TABLE 11

Computed Residential Rate PhP 5.7329


Less: Proposed Lifeline Rate Subsidy PhP 1.7865
Total PhP 3.9464
Multiply: kWh sold by lifeline customer/yr. 88,680
Revenue loss PhP 349,967
Divide: Total kWh sold 13,277,204
Less: kWh sold by lifeline customer 88,680
13,188,524
Recovery for lifeline loss:
Revenue Loss 349,967
KWh 13,188,524

= PhP 0.0265/kWh

I.G. Other Charges/Non-Recurring Rates

MANSONS’ proposed the following Other Charges and/or non-recurring


Page 11 of 35

charges, to wit:
TABLE 12

Other Charges Amount (PhP)


Reconnection at Service Drop 20.00
Reconnection due to withdrawal of meter 20.00
Transfer of meter location 20.00
Replacement of meter 20.00
New Connection – Single Phase Meter 20.00
New Connection – Three Phase Meter 75.00
Relocation of Secondary Pole Actual cost of labor
Bump damaged pole due to accident Actual cost of labor
Calibration of watt hour meter (as requested by 20.00
consumer)
Installation/Dismantling of transformer (private Actual cost of labor
construction)
Calibration of Industrial/Commercial Meter Based on ERC
(Polyphase) calibration rates
Reconnection, transfer of line and meter 25.00
Installation of transformer 50.00/kVa
Interruption Charge 2,500.00
Based on ERC
Calibration of Polyphase Industrial/Commercial calibration rates
Calibration Fee residential customer meter 20.00

II. COMMISSION DISCUSSIONS AND CONCLUSIONS:

In reaching the conclusion herein, the Commission took into consideration

the documents as well as the comments and issues presented by the applicant,

intervenor, and other interested parties who submitted their respective positions

on the instant application.

II.A. Determination of the Total Revenue Requirement

II.A.1. Test Year

The Commission finds MANSONS proposal to use the test year 2000 in its

unbundled rate application acceptable since it is consistent with Rule 15 Section 6

(c) of the Implementing Rules and Regulations (IRR) of R. A. 9136. Therefore,

the discussions and conclusions that follow are based on Schedule B, “Revalued

Cost by Function” (Cost of Service by Function-Historical Test Year).


Page 12 of 35

II.A.2. Generation and Transmission Costs

Generation Cost

The Commission updated the generation cost based on the most recent

approved NPC rate, i.e., ERC Case No. 2003-291 (In the Matter of the Application

for the Approval of the Revised Unbundled Generation Tariffs, National Power

Corporation (NPC) and Power Sector Assets and Liabilities Management

(PSALM) – Applicants) Order dated September 29, 2003. Notably, the

Commission approved the adoption of the Incremental Currency Exchange Rate

Adjustment (ICERA) in ERC Case No. 2003-498, Order dated December 4, 2003

(NPC and PSALM – applicants). The Commission directed NPC and PSALM to

refund to its customers the Deferred Accounting Adjustment (DAA) and FOREX

Correction for Luzon amounting to PhP (0.0065) per kWh within a period of six

months starting December 2003 to May 2004.

The total purchased power cost, as presented in the amended application

amounting to PhP 63,039,806 was adjusted to reflect the following:

a) The Commission decided to retain the system loss cap prescribed

under Rule IX Section 1 of the Implementing Rules and Regulation of

Republic Act No. 7832 pending the conduct of a comprehensive study

on the matter. Hence, the Commission used the maximum allowable

cap for system loss at 9.5% instead of the 15% proposed herein by

MANSONS and actual company use of 0.9542% for the year 2000.

(See further discussion on Section II.J.3).


Page 13 of 35

b) The Commission also used annualization in calculating the kilowatt-hour

purchase power cost. This is calculated as the sum of the products of

the average kilowatt-hour consumption for each rate class and the year-

end number of customers for each rate class; and

c) Since power rates are to be applied prospectively, the Commission also

updated the purchased power costs to the most recent levels available.

Based on December 2003 data submitted by MANSONS to the

Commission, MANSONS buys 100% of its power requirements from NPC. As

such, the generation cost as computed by the Commission reflects the cost of

electric power bought from NPC as of supply month December 2003. The

resulting total adjusted purchased power cost amounting to PhP 54,750,234 for

the test year 2000 was computed as follows:


TABLE 13

Purchased power cost submitted by MANSONS


(inclusive of transmission component) PhP 63,039,806
Adjustment due to update of purchased power
costs 4,424,479
Total PhP 67,464,285
Less: Excess system loss 12,714,051
Total Purchased Power Cost included in
Revenue Requirement PhP 54,750,234

Transmission Cost

The Commission’s Decision in ERC Case No. 2001-901 dated June 26,

2002 and Order dated September 20, 2002 set the transmission charges for the

TRANSCO without any provision for an automatic adjustment thereof. Since the

transmission rates to be paid by MANSONS are fixed, it is the decision of the

Commission to likewise fix the unbundled transmission rates to be billed to end-

users. The transmission charges approved for billing by MANSONS have been
Page 14 of 35

calculated based on the approved TRANSCO rates, which include cross subsidy

elements to be phased out over a three-year period.

System Loss

A separate charge to account for allowable system loss shall likewise be

provided. The Commission decided to retain the system loss cap prescribed

under Rule IX Section 1 of the I.R.R. of R.A. 7832 pending the conduct of a

comprehensive study on the matter. Hence, the Commission used the maximum

allowable cap for system loss at 9.5% or actual, whichever is lower.

Based on the new generation and transmission charges, as well as the

allowable system loss, the Commission has determined MANSONS unbundled

generation, transmission and recoverable system loss as follows:


TABLE 14

Generation Charge PhP 34,067,359


Transmission Charge 12,802,791
Recoverable System Loss 7,880,084
Total PhP 54,750,234

MANSONS approved generation charge shall remain fixed until changes in

NPC’s generation rate are approved and authorized by the Commission pursuant

to its Order dated February 24, 2003, ERC Case No. 2003-44 (GRAM) and ERC

Case No. 2003-498 (ICERA), Order dated December 4, 2003. In view thereof, the

Commission does not foresee the need for MANSONS to continue to implement

its Purchased Power Adjustment (PPA) clause. Towards this end, the

Commission hereby directs MANSONS to discontinue the implementation of its

PPA clause upon the effectivity of the herein approved unbundled rates.
Page 15 of 35

II.A.3. Operation and Maintenance (Less Power Cost & Payroll)

The general criteria in the evaluation of expenses to be allowed for

recovery are: (1) that the expense is a requisite of, or necessary in the operation

of the utility; (2) it is recurring; and (3) it redounds to the benefit of the utility’s

customers (Public Service Commission [PSC] Decision in Cases Nos. 85889,

85890 and 89893). The Commission enjoins MANSONS to incur only “prudent

and reasonable costs” for inclusion in the determination of retail rates. While a

distribution utility enjoys the benefit of passing its costs of purchased power and

other reasonable costs to the consumer, it is obligated as a public utility to ensure

that its costs of operations including payroll are kept at a minimum. The

distribution utility must bear in mind that as a service-oriented company, its

mandate is to advocate and transact judiciously for and in behalf of its consumers.

“Reasonable costs” refers to the costs of those goods and services which,

while may not be the lowest in price, need to be incurred with consideration of

quality, efficiency, reliability and security, which are characteristics of the service

delivered by the distribution utility. “Prudent costs” demand that the utility ensures

that its purchases of goods and services are at their minimum, without sacrificing

the foregoing characteristics. When making a purchase or executing a contract, a

utility cannot simply rely on its right to pass on its costs to its consumers. As

such, the Commission, in fulfillment of the policy of the EPIRA to establish a

regime of free and fair competition and full public accountability to achieve greater

operational and economic efficiency, enjoins MANSONS to institute and report to

the Commission their respective policies and procedures for cost-cutting and the

transparent and competitive procurement of goods and services.


Page 16 of 35

MANSONS customers have a right to receive safe, reliable, and adequate

service at a reasonable rate. To this end, MANSONS should view a petition for an

increase in rates to be the last recourse. In future filings, MANSONS should be

reminded that it has the burden of proving that all reasonable and appropriate cost

cutting measures have been taken before resorting to a petition to increase rates.

Operations and Maintenance account was adjusted to PhP 4,752,499 after

considering adjustment of PhP 1,315,785, computed as follows:


TABLE 15

O & M per MANSONS PhP 6,068,284


Adjustments:
Expenses excluded for ratemaking purposes PhP (321,461)
Franchise Tax (separate item) (994,324) (1,315,785)
Adjusted O & M PhP 4,752,499

Adjustments

The Commission finds some expenses to be unnecessary in the provision

of MANSONS electric service and therefore excluded the same for ratemaking

purposes, as follows:
TABLE 16

Particulars Amount
Donations PhP 115,326
Interest Expense 206,135
Total Expenses excluded for
ratemaking purposes PhP 321,461

Franchise tax shall appear as a separate line item on the customers’ bills

as percentage of the total monthly electricity charges. Given this rate design, it is

appropriate to remove the amount of PhP 994,324 associated with franchise taxes

from the revenue requirement as this is just a pass through item.

For future rate cases, MANSONS will continue to be required to make full

disclosures of all it’s O & M expenses in order for the Commission to determine
Page 17 of 35

the prudence of its expenditures. Unless otherwise justified by MANSONS,

expenses found to be unreasonably incurred shall not be allowed by the

Commission as part of its recoverable costs to be passed on to MANSONS end-

users.

II.A.4. Depreciation and Amortization

MANSONS is required to set up a depreciation fund each year

corresponding to the whole amount of depreciation that it has recorded on its

books. The setting up of this fund should be done on a monthly basis

corresponding to the monthly depreciation. MANSONS will be required to strictly

account for the expenditures out of this fund which should be used solely for

investment in electric plant. The utility is free to withdraw funds from this account

at any time but all withdrawals should be reported to the Commission within thirty

(30) days specifying the use of the funds. This report should be consolidated with

the monthly reportorial requirement (M-001 & M-002).

II.D. Rate Base

II.D.1. Net Plant in Service

The Commission has determined MANSONS’ net plant in service as of

December 31, 2000 considered in this case as follows:


TABLE 17

Plant, Property & Equipment Sound Value


Assets as of September 1, 1998 per Appraisal Report PhP 28,355,700
Add (Deduct) Adjustment :
Addition/(Retirement) from Sept. 2, 1998-Dec.2000 749,260
Depreciation Expense from Sept. 2,1998-Dec. 2000 (4,358,090)
Adjusted Net Plant in Service as of Dec. 31, 2000 PhP 24,746,870

The Commission considered appraisal of assets conducted by AACI of

MANSONS properties and equipment existing as of September 1, 1998 with a


Page 18 of 35

total value of PhP 64,263,600 as cost of reproduction, new and PhP 28,355,700

as sound value, as shown in Table 5 of this Decision.

II.D.2. Allowance for Cash Working Capital

Working capital is money a business must have available to meet payroll

and expenses until customers have paid for the service or product. Utilities are

usually allowed, as part of their rate base, an amount for working capital to cover

expenses during the time it takes for the customers to use the service, be billed

for it and collect payments.

MANSONS has included an amount equal to two (2) months cash

operating and maintenance expenses including purchased power costs as the

allowance for cash working capital.

The cash working capital allowance included in the rate base should

approximate the actual cash requirements of MANSONS based on the estimated

net lag in its cash flow. In order to refine the application of the formula used in

past rate proceedings, a more detailed review of the actual lag in cash flow

associated with the payments for purchased power and the inflow of cash from

MANSONS customers was undertaken. With respect to the outflow of cash

associated with the payments for purchased power, it was determined that the

time from the provision of service to the outflow of funds can be calculated as

follows:

15 days One-half of the billing cycle


5 days Meter reading and bill preparations
30 days Approximate time before payment is due
50 days Total
Page 19 of 35

Therefore, MANSONS has an average of approximately fifty (50) days from

the time service is provided until payment is due. With respect to the collection of

funds from its customers, it was determined that the time lag from the provision of

service to the inflow of funds can be calculated as follows:

15 days One-half of the billing cycle


10 days Meter reading, bill preparation
10 days Required time to collect the customer’s bill
without disconnection
5 days Processing time
40 days Total

Therefore, MANSONS waits for an average of approximately forty (40)

days before it receives payment for the services provided.

Based on MANSONS current billing and collection practices, there appear

to be no cash working capital requirement associated with purchased power. The

only potential finance costs associated with purchased power would be costs

caused by customers who do not pay their bills in accordance with MANSONS

collection policies. MANSONS customers who do pay on time should not be

penalized because other customers failed to comply with MANSONS payment

schedule. If additional finance costs are incurred because of late payment of bills,

these costs should be recovered in the form of penalties for late payment.

Therefore, the formula for the calculation of the cash working capital allowance is

modified by excluding purchased power costs.

The adjusted Cash Working Capital allowed by the Commission was

computed as follows:
Page 20 of 35

TABLE 18

Adjusted O & M PhP 68,785,365


Taxes & Non-cash items
Taxes Other than Income Tax 106,685
Depreciation 4,358,090
Purchased power cost 54,750,234

Total Taxes & Non-Cash Items PhP 59,215,009


Total O&M , net of Cash & Non-Cash Item PhP 9,570,356
Cash Working Capital – O&M (2 mos.) PhP 1,595,059

Adjusted Power Cost PhP 54,750,234


Cash Working Capital – Power Cost (0) 0
Total Cash Working Capital PhP 1,595,059

II.D.3. Summary of Rate Base

The following compares the rate base submitted by MANSONS with that

approved by ERC.
TABLE 19

Per MANSONS Per ERC


Net Plant In Service PhP 24,746,870 PhP 24,746,870
Cash Working Capital 12,155,270 1,595,059
Total Rate Base PhP 36,902,140 PhP 26,341,929

II.E. Rate of Return

The current form of rate regulation practiced for the privately owned electric

utilities is a cost based method known as the rate of return on rate base (RORB)

methodology. Power rates are set to recover cost of service prudently incurred

plus a reasonable rate of return on rate base. The rate of return pertains to the

percentage which when multiplied by the authorized rate base, provides a return

that will fairly compensate the company for the risk inherent to the investment of

capital. This simply means that a regulated utility is allowed to set rates which will

cover operating costs and provide an opportunity to earn a reasonable rate of

return on the assets utilized in the business.


Page 21 of 35

On the basis of current jurisprudence, the Commission has determined that

the 12% rate of return will be maintained in this case but the income tax thereon

will not be allowed as operating expense. Thus, the 12% rate of return is a pre-

tax rate of return which is equivalent to PhP 3,161,032, computed as follows:


TABLE 20

Adjusted Rate Base PhP 26,341,929


Rate of Return 12%
Return On Rate Base PhP 3,161,032

The Commission intends to adopt a new internationally accepted method of

rate regulation known as Performance-Based Regulation. The treatment of

income tax in this new method may be different from the present RORB method.

II.F. Revenue Requirement Summary

On the basis of the foregoing discussion, the Commission after

considering adjustments of PhP 10,872,582 approved a total revenue

requirement of PhP 71,946,397 equivalent to OATA of PhP 0.0344 per kWh or

0.66% increase from its existing average rate.


TABLE 21

Per Adjustments Adjusted


MANSONS ERC ERC
Fuel PhP 0 PhP 0 PhP 0
Purchased Power 63,039,806 (8,289,572) 54,750,234
Payroll 4,924,542 0 4,924,542
Operation & Maintenance 6,068,284 (1,315,785) 4,752,499
Depreciation & Amortization 4,358,090 0 4,358,090
Return on Rate Base 4,428,257 (1,267,225) 3,161,032
Total Revenue Requirement PhP 82,818,978 PhP (10,872,582) PhP 71,946,397
Adjusted Revenue (2000) PhP 71,475,841
Increase(Decrease) PhP 470,556
Annualized kWh Sales 13,683,319
Required Increase PhP/kWh 0.0344

The overall average tariff adjustment (OATA) is a measurement tool based

on the formula: (Total Revenue Requirement less Existing Revenue) divided by


Page 22 of 35

kilowatt-hour sales). This measurement is not meant to refer to any specific

customer class. MANSONS proposed an OATA of PhP 0.5823 per kWh.

II.G. Adjusted Operating Revenue

The Commission adjusted MANSONS actual operating revenue to

PhP 71,475,841, computed as follows:


TABLE 22

MANSONS actual operating revenue PhP 65,326,040


Add/(Deduct):
Franchise Tax (994,324)
Addtl. revenue due to increase in sales 2,789,899
Additl. Revenue due to increase in power cost 4,354,226
Total Adjusted Operating Revenue PhP 71,475,841

II.I. Billing Determinants and Customer Class Allocation

The Commission concurs with MANSONS billing determinants and

allocation factors except for the billing determinant and allocation factor used for

energy related costs. The Commission allocated the computed revenue

requirement using its existing customer class.

The Commission believes that any energy related costs should be

allocated based on annualized sales. Annualized sales were derived by

multiplying year-end number of customers with average annual kWh usage for

each customer class. This was performed to project for the future kWh sales for

the development of a more appropriate allocation factors and billing determinants

for each customer class. With the annualized sales per customer class, the

computed adjusted kilowatt-hour sold was 13,683,319.


Page 23 of 35

The Commission opines that in theory, the most appropriate way to allocate

costs among customer classes is through the use of the cost causation principles.

Thus, the Commission intends, through future proceedings to move even further

towards uniform definitions of customer classes based on cost causation

characteristics. However, the Commission believes that such a change would

best be accomplished through the issuance of guidelines of general applicability to

all utilities. Furthermore, R.A. 9136 requires the identification and removal of

interclass cross-subsidies. Substantive change in customer classes at this time

prevents precise calculation of cross-subsidy in existing rates. Therefore, no

changes in customer class allocations are ordered for MANSONS at this time.

II.J. Design and Calculation of Charges

II.J.1. Generation Charge

The Commission updated the generation cost based on the most recent

approved NPC rate, i.e., ERC Case No. 2003-291, Order dated September 29,

2003. Notably, the Commission approved the adoption of the ICERA under ERC

Case No. 2003-498, Order dated December 4, 2003. The Commission directed

NPC and PSALM to refund to its customers the DAA and FOREX Correction for

Luzon amounting to PhP (0.0065) per kWh within a period of six months starting

December 2003 to May 2004.

The NPC’s approved rate will remain fixed until changes are authorized by

the Commission. This eliminates the need for future Purchased Power

Adjustment.
Page 24 of 35

The Commission has developed a new recovery mechanism designed to

replace the purchased power adjustment clauses being used by the power

utilities. The Commission has promulgated the Implementing Guidelines on the

Generation Rate Adjustment Mechanism (GRAM) effective February 24, 2003. In

view thereof, the Commission does not foresee the need for the Purchased Power

Adjustment (PPA) clause. Towards this end, the Commission hereby directs

MANSONS to discontinue implementation of its PPA upon effectivity of the herein

approved unbundled rates.

II.J.2. Transmission Charge

The Commission’s decision in ERC Case No. 2001-901 and the

Commission’s Order dated September 20, 2002 fixed the transmission charges for

the TRANSCO without any provision for automatic adjustment thereof. Since the

transmission rates to be paid by MANSONS are fixed, it is the decision of the

Commission to likewise fix the unbundled transmission rates billed to its end-use

customers.

The transmission charge shall be billed on a fixed rate per kilowatt-hour for

all end-users except for Industrial customers. The transmission charge for

Industrial customers shall be billed using a combination of a fixed rate per kilowatt

(kW) and a rate per kilowatt-hour (kWh).

In consonance with the gradual phase-out of the intra-grid subsidies being

billed by TRANSCO, the Commission hereby sets the transmission charges for

the succeeding years, as follows:


Page 25 of 35

TABLE 23

Street Govt.
Period Charges Residential Commercial Lights Industrial Hospital Bldg.
Oct.2003 - Demand (PhP/kW) 138.07
Sept .2004 Transmission (PhP/kWh) 0.9667 0.8934 0.8301 0.4013 0.9036 0.9133
Oct.2004 - Demand (PhP/kW) 157.87
Sept. 2005 Transmission(PhP/kWh) 1.1053 1.0215 0.9491 0.4588 1.0332 1.0442
Oct.2005- Demand (PhP/kW) 177.66
Sept. 2006 Transmission(PhP/kWh) 1.2439 1.1496 1.0681 0.5163 1.1627 1.1751

II.J.3. System Loss Charge

The Commission defines System Loss for utilities to include technical loss

and administrative loss or the utility’s use of power for its own operations.

The Commission approves the recovery of allowed system loss through the

establishment of a separate System Loss Charge. The system loss charge shall

vary from one customer class to another depending on their respective

contributions to the system loss. The allowed system loss is equal to the actual

system loss for the test year or the existing system loss cap prescribed in R.A.

7832 whichever is lower.

The Commission believes that the present cap on System Loss of 9.5%

should be used in the calculation of revenue requirements at this time. This

would however be subject to change upon the approval of a new policy by the

Commission. The actual system loss or cap of 9.5% plus 1% of company use or

actual whichever is lower shall be deducted from total power cost and to be billed

separately as System Loss Charge.

II.J.4. Distribution Charge

The distribution charge shall be billed on a fixed rate per kilowatt-hour

(kWh) for all end-users except for Industrial customers. The distribution charge
Page 26 of 35

for Industrial customers shall be billed using a combination of a fixed rate per

kilowatt (kW) and a rate per kilowatt-hour (kWh).

Relevant to distribution charge, MANSONS’ proposed distribution wheeling

rates comprised of its proposed distribution and supply charges. The Commission

believes that wheeling rates are parallel to the cost of service functionalized under

Distribution. Thus, the Commission orders that the Distribution Charge provided

in the Rate Schedules be likewise utilized as Distribution Wheeling Charges

available to the future contestable market.

The Commission’s decision to allow a distribution utility to avail of the

Distribution Wheeling Charges of another distribution utility is based on the

general intent of R.A. 9136 to promote a competitive generation market.

Distribution utilities that currently or in the near future rely in full or in part on the

distribution facilities of another distribution utility should not be held captive by the

other distribution utility in the purchase of unbundled generation. Distribution

utilities are, therefore, prohibited from bundling or tying the sale of generation or

purchased power with the sale of unbundled distribution wheeling service.

II.J.5. Metering and Supply Charges

The Commission acknowledges that cost-causation rate design principles

suggest the recovery of customer-related costs through fixed monthly charges. In

addition to this cost of service principle, however, the Commission must also

consider rate design impacts across the spectrum of customers within each rate

class. Although RA 9136 requires the removal of inter-class cross subsidies, the

law does not require removal of intra-class cross-subsidies. The Commission has

the flexibility to consider other factors in determining rate design for a particular
Page 27 of 35

class of customers. Therefore to mitigate the impact on below-average

consumption of residential end-users, the Commission orders MANSONS to use a

combination of peso per customer per month and peso per kilowatt-hour for the

metering function. On the other hand, the Commission orders MANSONS to use

peso per kilowatt-hour rate for the supply function. All other end-users except for

Street Lights shall be charged fixed monthly customer charge for both metering

and supply functions. Street Lights will be charged fixed monthly customer charge

for supply function only.

II.J.6. Franchise Taxes

Franchise taxes shall appear as a separate line item on the customers’

bills. Given this rate design, it is appropriate to remove test year amounts

associated with franchise taxes from the revenue requirement used to calculate

other recurring electricity rates.

Pending issuance of guideline on this issue by the Department of Finance

(DOF), MANSONS is in the meantime directed to use the formula below in

calculating franchise taxes.

Franchise Tax:

Total Power Bill x FTx1,y

Where: FTx = National franchise tax of 2%


Fty = Applicable local franchise tax

II.K. Cross Subsidy Removal

The inter-class cross subsidies in existing rates are as follows:


Page 28 of 35

TABLE 24

Total Residential Commercial Streetlights Industrial Hospital Govt.Bldg.


New Cost-
Based Revenue 71,946,397 54,100,416 7,895,595 1,747,766 7,027,805 486,349 688,466
Existing Rates
Revenue 71,475,841 51,889,384 8,436,324 1,795,401 8,093,882 535,155 725,695
Total Change in
Revenue 470,556 2,211,032 (540,729) (47,635) (1,066,077) (48,806) (37,229)
% Change in
Revenue 0.6583%
Normalized
Revenue 71,946,397 52,230,993 8,491,863 1,807,221 8,147,168 538,678 730,472
Inter-class
Cross Subsidy 0 (1,869,423) 596,268 59,456 1,119,362 52,329 42,008
Class Billing
Determinants 13,683,319 10,000,842 1,578,998 380,481 1,482,377 98,449 142,172
(in kWh)
Inter-class
Cross Subsidy (0.1869) 0.3776 0.1563 0.7551 0.5315 0.2955
Rates (PhP/Kwh)

Section 74 of R.A. 9136 and Rule 16 Section 16, Section 5 of the

Implementing Rules and Regulation thereof provide that ERC shall prescribe a

scheme for phasing out all cross subsidies including subsidies within Grids,

between Grids, and between classes of end-users. The phasing out period shall

not exceed three (3) years from the establishment of the Universal Charge, which

may be extendible for a maximum period of one (1) year subject to certain

conditions.

The Commission approved the cross subsidy removal scheme for the

TRANSCO in its Decision dated June 26, 2002 in ERC Case No. 2001-901 which

impacts the unbundled transmission rates for MANSONS end users. This impact

is reflected in the three-year schedule for unbundled transmission charges

provided in Section II.J.2 above.

In the instant case, the Commission will order the cross subsidy removal

process at a later date following the establishment of the Universal Charge. Until
Page 29 of 35

such time, MANSONS will continue to charge the inter-class cross subsidy rates

set forth above.

II.L. Lifeline Rate

Section 4 (hh) of R.A. 9136 defines Lifeline Rate as the subsidized rate

given to low-income captive market end-users who cannot afford to pay at full

cost. Pursuant to Section 73 of R.A. 9136, the Commission hereby sets the level

of lifeline consumption and rate applicable to MANSONS.

In determining the lifeline level of consumption to be provided to the

marginalized end-users, the Commission calculated the probable load

requirement of typical low-income consumers by two (2) lighting facilities at 20

watts each and a 50-watt Radio that are being used at reasonable number of

hours. Thus, the Commission sets the lifeline consumption maximum level of 50

kilowatt-hours for MANSONS. The Commission considers the impact that the

subsidized Lifeline Rates will have on other end-users who must carry the costs

associated with such subsidy. This fact, combined with the desire to maximize the

benefit to as many marginalized end-users as possible, has led the Commission

to adopt the following graduated scale for lifeline discount for MANSONS. The

graduated scale is also based on the recognition that individual end-user

consumption may likely vary from month to month.


TABLE 25

KWh Consumption % Lifeline Discount


10 kWh and below 30%
11 – 20 kWh 25%
21 – 30 kWh 20%
31 – 40 kWh 15%
41 – 50 kWh 10%
Page 30 of 35

MANSONS shall apply these discounts to the following residential charges:

Generation, Transmission, Distribution, Supply, Metering and System Loss. In a

given billing period, an end-user at any of the above-consumption levels shall be

given the specified corresponding discount on each of these rate components. An

end-user with a level of consumption exceeding 50 kWh in a particular billing

period shall not be entitled to any discounted lifeline rate for said period.

The cost of subsidy to lifeline end-users shall be passed on to all non-

lifeline end users. For MANSONS, the lifeline discounts result in a Subsidy on

Lifeline by other end-users equal to PhP 0.0849/kWh.

II.M. Other Charges/Non-Recurring Rates

MANSONS existing Other Charges were considered in the determination of

the revenue requirement. The corresponding revenue derived from these charges

were appropriately deducted from the determination of the revenue requirement

allowed to MANSONS.

The Other Charges of MANSONS are hereby pegged at their existing

levels until such time that the Commission sets new rates on the same. Further,

MANSONS is ordered to make a compliance filing on its Other Charges a year

from date of this Decision using a format to be prescribed by the Commission.

The compliance filing for approval of Other Charges shall include rates that

are cost-based as well as all supporting cost justification for the rates, including

but not limited to the amount of actual time and wages of employees performing

each task encompassed by each type of Other Charges.


Page 31 of 35

II.N. Estimated Impact on Average Residential Consumer

A comparison of the estimated impact of all adjustments on the revenue

requirement on the monthly bill of a residential end-user consuming 99 kWh a

month using rates based on MANSONS actual existing rates as of December

2003 against the unbundled rates approved by the Commission is shown below:
TABLE 26

RESIDENTIAL
Consuming 99 kWh Peso/kWh Amount Peso/kWh Amount
Basic Charge 3.1912 315.92 Generation Charge 2.4897 246.48
Transmission Charge 0.9667 95.70
System Loss Charge 0.5759 57.01
PPA 2.1711 214.94 Distribution Charge 1.0331 102.27
Power Act Reduction (0.30) (29.70) Supply Charge 0.1538 15.23
Metering Charge:
Retail Customer Charge/Mo. 5.00 5.00
Metering System Charge 0.1292 12.79
Inter-Class Cross Subsidy Charge (0.1869) 8.41
Lifeine Rate Subsidy 0.0849 (18.51)
Power Act Reduction (0.30) (29.70)

SUB TOTAL 501.16 SUB TOTAL 494.69

Universal Charge Universal Charge


Missionary Electrification 0.0373 3.69 Miissionary Electrification 0.0373 3.69
Environmental Charge 0.0025 0.25 Environmental Charge 0.0025 0.25
Franchise Tax 2.5% 12.37

TOTAL BILL 505.10 511.00


Ave. Rate/kWh 5.1020 5.1616

Inc./(Dec.) In Rate 0.0596


Inc./(Dec.) In Bill 5.90

DISPOSITION

WHEREFORE, the foregoing premises considered, it is hereby decided as

follows:

1. To approve the unbundled schedule of rates of MANSONS, to be

effective the first billing cycle thirty (30) days after receipt of this

Decision, to wit;
Page 32 of 35

MANSONS CORPORATION (MANSONS)


ERC CASE NO. 2002-18 and 2002-143
RATE SCHEDULE

Residential Commercial Streetlights Industrial Hospital Govt.Bldg.


Generation Charge (PhP/kWh) 2.4897 2.4897 2.4897 2.4897 2.4897 2.4897
Transmission Charge (PhP/kWh) 0.9667 0.8934 0.8301 0.4013 0.9036 0.9133
(PhP/kW) 138.07
Distribution Charge (PhP/kWh) 1.0331 0.8950 0.6975 0.3589 0.9673 0.8284
(PhP/kW) 123.50
Customer Charges
Supply Charge (PhP/Meter/Mo.) 12.57 12.57 12.57 12.57 12.57
(PhP/kWh) 0.1538
Metering Charge (PhP/Cust./Mo.) 5.00 17.28 0 604.95 17.28 17.28
(PhP/kWh) 0.1292
System Loss Charge (PhP/kWh) 0.5759 0.5759 0.5759 0.5759 0.5759 0.5759
Inter-Class Cross
Subsidy (PhP/kWh) (0.1869) 0.3776 0.1563 0.7551 0.5315 0.2955
Lifeline Rate Subsidy (PhP/kWh) 0.0849 0.0849 0.0849 0.0849 0.0849 0.0849
Universal Charge (PhP/kWh)
Missionary Electrification 0.0373 0.0373 0.0373 0.0373 0.0373 0.0373
Environmental Charge 0.0025 0.0025 0.0025 0.0025 0.0025 0.0025
Note: Plus National and Local Franchise Taxes

2. To approve MANSONS net utility plant in service at sound value as of

September 1, 1998 amounting to PhP 28,355,700.

3. To direct MANSONS to comply with the following:

a) Discontinue charging the PPA upon effectivity of the approved

unbundled rates. MANSONS shall automatically bill its end-

user the new Generation Rate charged by NPC as approved

and authorized by the Commission;

b) Make a compliance filing with respect to its Other Charges a

year from date of this Decision;

c) Bill the amount of PhP 0.0373/kWh representing the missionary

electrification portion of the Universal Charge in accordance

with the Decision of the Commission in ERC Case No. 2001-

165 (In the Matter of the Petition for the Availments from the
Page 33 of 35

Universal Charge the Share for Missionary Electrification, NPC-

SPUG, Applicant);

d) Bill the amount of PhP 0.0025/kWh representing the

environmental portion of the Universal Charge in accordance

with the Commission’s Decision in ERC Case No. 2002-194 (In

the Matter of the Petition for the Availments from the Universal

Charge the Environmental Share/Charge for the Rehabilitation

and Management of Watershed Areas, NPC, Applicant);

e) To set up a depreciation fund each year corresponding to the

whole amount of depreciation that it has recorded on its books.

The setting up of this fund should be done on a monthly basis

corresponding to the monthly depreciation. MANSONS is

required to strictly account for the expenditures out of this fund

which should be used strictly for investment in electric plant and

all withdrawals from this fund should be reported to the

Commission within thirty (30) days from withdrawal;

f) To inform the end-users within its franchise area of the

approved unbundled rates not later than thirty (30) days after

receipt of this Decision;

g) Bill its respective end-users using a billing format which

contains at least the rate elements provided in Annex “A” (Rate

Schedule) of this Decision upon effectivity of the approved

unbundled rates;
Page 34 of 35

h) Bill its respective end-users using a billing format which

contains at least the rate elements provided in Annex “B” of this

Decision upon effectivity of the approved unbundled rates. The

rate elements provided in Annex “B” should appear on the end-

users’ bills even if the rate elements currently have a rate of

zero (0) or have not yet been determined by the Commission;

and

i) To submit for verification and confirmation purposes on or

before the twentieth (20th) day of the month following the

effectivity of the herein approved unbundled rates and every

month thereafter: (a) five (5) sample bills for each customer

class; (b) copy of bills from the generation and transmission

companies; and (c) M-001 and M-002 with all related

schedules;

SO ORDERED.

Pasig City, January 28, 2004.

RODOLFO B. ALBANO
Chairman

OLIVER B. BUTALID CARLOS R. ALINDADA


Commissioner Commissioner

LETICIA V. IBAY JESUS N. ALCORDO


Commissioner Commissioner
Page 35 of 35

Copy furnished:

1. Attys. Norberto F. Manjares and Norberto C. Manjares III


Counsel for Applicant
Law Office of Manjares & Manjares
Suite 211, Jiao Building
2 Timog Avenue, Quezon City 1100

2. Office of the Solicitor General


134 Amorsolo Street, Legaspi Village
City of Makati 1229

3. Commission on Audit
Commonwealth Avenue
Quezon City 0880

4. Senate Committee on Energy


GSIS Building, Roxas Boulevard
Pasay City 1307

5. House Committee on Energy


Batasan Hills, Quezon City 1126

6. The Municipal Mayor


Floridablanca, Pampanga 2006

7. Mansons Corporation
Floridablanca, Pampanga 2006

Вам также может понравиться