Вы находитесь на странице: 1из 63

ENVIRONMENTAL  IMPACT ASSESSMENT 

for the setup of an RO plant at Equator Village,  
Gan‐ Addu Atolll, Maldives. 

Client: Gan Invest Maldives Pvt, Ltd

Signature:  

Prepared by 

Ahmed Jameel & Abdul Aleem for Water Solutions Pvt. Ltd., Maldives     

  

  

October 2010                                                       
EIA for the setup of RO plant at equator Village, Gan‐Seenu Atoll   

1 Table of Contents
1  Table of Contents ...................................................................................................... 2 
2  Table of Figures ......................................................................................................... 6 
3  List of Tables ............................................................................................................. 6 
4  List of Acronyms ........................................................................................................ 7 
5  Executive Summary ................................................................................................... 8 
6  Introduction .............................................................................................................. 9 
6.1  Structure of this EIA Report .......................................................................................... 9 
6.2  Aims and Objectives of the EIA ..................................................................................... 9 
6.3  EIA Implementation...................................................................................................... 9 
6.4  Terms of Reference ..................................................................................................... 10 

7  Project Setting ......................................................................................................... 11 
7.1  Overview ..................................................................................................................... 11 
7.2  Applicable Policies, Laws and Regulations ................................................................... 11 
7.3  Environmental Protection and Preservation Act .......................................................... 11 
7.4  Second National Environment Action Plan (1999) ........................................................ 12 
7.5  National Biodiversity Strategy and Action Plan ............................................................ 13 
7.6  Consultation and Public Participation Laws ................................................................. 13 
7.7  Environmental Permits required for the Project .......................................................... 13 
7.7.1  EIA Decision Statement ................................................................................................................ 13 

7.8  Regulations for Installing and Operating Desalination Plants in the Maldives .............. 14 
7.9  Roles and Responsibilities of Groups Involved ............................................................. 14 
7.9.1  Environment Ministry .................................................................................................................. 15 
7.9.2  Environmental Protection Agency ............................................................................................... 15 
7.9.3  Project Proponent ........................................................................................................................ 15 
7.9.4  Environmental Consultants .......................................................................................................... 15 

8  Project Description .................................................................................................. 16 
8.1  Description of the Project Proponent .......................................................................... 16 
8.2  Project Location and boundary .................................................................................... 16 
8.3  Need and Justification ................................................................................................. 17 
8.4  Project Duration .......................................................................................................... 17 
8.5  Description of the Project Components ....................................................................... 18 
8.5.1  Location of the RO Plant and Plant House ................................................................................... 18 
8.5.2  Capacity of RO Plant .................................................................................................................... 18 
8.5.3  Method of Feed Water Intake ..................................................................................................... 18 

   
Page 2 

   
EIA for the setup of RO plant at equator Village, Gan‐Seenu Atoll   

8.5.4  Energy for the RO Plant ............................................................................................................... 18 
8.5.5  Operational Staff .......................................................................................................................... 18 
8.5.6  Description of the beach well ...................................................................................................... 18 
8.5.7  Properties of Output Water ......................................................................................................... 18 
8.5.8  Disposal of Concentrated Brine ................................................................................................... 18 
8.5.9  Water Quality Monitoring ............................................................................................................ 19 
8.5.10  Water Production Process ....................................................................................................... 19 
8.5.11  Project Inputs .......................................................................................................................... 19 
8.5.12  Project Outputs ....................................................................................................................... 20 

8.6  Project Schedule and Life Span .................................................................................... 22 

9  Methodology ........................................................................................................... 23 
9.1  Mapping and Location Identification ........................................................................... 23 
9.2  Ground Water Quality Assessment .............................................................................. 23 
9.3  Marine Environment Surveys ....................................................................................... 23 
9.4  Aerial Photos ............................................................................................................... 23 

10  Existing Environment ........................................................................................... 24 
10.1  Geography ................................................................................................................... 24 
10.2  Hazards and Disasters .................................................................................................. 24 
10.2.1  Natural Vulnerability of the Island of Gan ............................................................................... 24 

10.3  Climatic Setting ........................................................................................................... 28 
10.3.1  Monsoons ................................................................................................................................ 28 
10.3.2  Rainfall ..................................................................................................................................... 28 
10.3.3  Temperature ............................................................................................................................ 29 
10.3.4  Wind ........................................................................................................................................ 29 
10.3.5  Waves ...................................................................................................................................... 30 
10.3.6  Tides ........................................................................................................................................ 30 
10.3.7  Currents ................................................................................................................................... 31 

10.4  Existing Terrestrial Environment .................................................................................. 32 
10.4.1  Terrestrial flora and fauna ....................................................................................................... 32 
10.4.2  Groundwater ........................................................................................................................... 32 
10.4.3  Existing Groundwater Quality .................................................................................................. 32 

10.5  Existing Marine Environment ....................................................................................... 34 
10.5.1  Section Brief ............................................................................................................................ 34 
10.5.2  Marine Water Quality .............................................................................................................. 34 
10.5.3  Description of Marine Environment ........................................................................................ 34 
10.5.3.1  Marine environment at the feed water intake location ..................................................... 34 
10.5.3.2  Marine environment at the brine discharge location ......................................................... 34 

11  Environmental Impacts ........................................................................................ 35 
11.1  Introduction ................................................................................................................ 35 
11.2  Impact Identification ................................................................................................... 35 
11.3  Identifying Mitigation Measures .................................................................................. 36 

   
Page 3 

   
EIA for the setup of RO plant at equator Village, Gan‐Seenu Atoll   

11.3.1  Mitigation Options ................................................................................................................... 36 

11.4  Existing Environmental Concerns ................................................................................. 37 
11.4.1  Natural Hazard Vulnerability ................................................................................................... 37 

11.5  Constructional Impacts ................................................................................................ 37 
11.5.1  Civil works ................................................................................................................................ 37 
11.5.1.1  Impacts ................................................................................................................................ 37 
11.5.1.2  Mitigation Measures ........................................................................................................... 38 
11.5.2  Construction of the plant house .............................................................................................. 39 
11.5.2.1  Impacts ................................................................................................................................ 39 
11.5.2.2  Mitigation Measures ........................................................................................................... 39 

11.6  Operational Impacts .................................................................................................... 39 
11.6.1  Energy Use and Air Quality ...................................................................................................... 39 
11.6.1.1  Impacts ................................................................................................................................ 39 
11.6.1.2  Mitigation measures ........................................................................................................... 39 
11.6.2  Groundwater Quality ............................................................................................................... 39 
11.6.2.1  Impacts ................................................................................................................................ 39 
11.6.2.2  Mitigation ............................................................................................................................ 39 
11.6.3  Coral Reef and the Marine Environment ................................................................................. 40 
11.6.3.1  Impacts ................................................................................................................................ 40 
11.6.3.2  Mitigation Measures ........................................................................................................... 40 
11.6.4  Impact of Rising Marine Water Temperature ......................................................................... 40 
11.6.4.1  Impacts ................................................................................................................................ 40 
11.6.5  Positive economic Impacts ...................................................................................................... 40 
11.6.5.1  Impacts ................................................................................................................................ 40 
11.6.5.2  Mitigation Measures ........................................................................................................... 41 
11.6.6  Health Impacts ......................................................................................................................... 41 
11.6.6.1  Impacts ................................................................................................................................ 41 
11.6.6.2  Mitigation Measures ........................................................................................................... 41 

12  Stakeholder Consultations ................................................................................... 43 
12.1  Consultation with the client ........................................................................................ 43 
12.2  Consultation with Southern Utilities company ............................................................. 43 
12.3  Consultations with the hotel staff and management ................................................... 43 
12.4  List of Persons Consulted ............................................................................................. 44 

13  Alternatives ......................................................................................................... 45 
13.1  No Project Option ........................................................................................................ 45 
13.2  Design Alternatives ..................................................................................................... 45 
13.3  Alternative Locations for the plant house .................................................................... 45 
13.4  Alternative Method for Feed Water Intake .................................................................. 46 
13.5  Alternative water source ............................................................................................. 47 
13.6  Alternative for RO Plant Installation ............................................................................ 47 
13.7  Preferred Alternative ................................................................................................... 47 

   
Page 4 

   
EIA for the setup of RO plant at equator Village, Gan‐Seenu Atoll   

13.7.1  Mitigation Measures for the Preferred Alternative ................................................................ 47 

14  Environmental and Social Impact Monitoring ...................................................... 49 
14.1  Introduction ................................................................................................................ 49 
14.2  Cost of Monitoring ...................................................................................................... 49 
14.3  Aspects of monitoring ................................................................................................. 49 
14.4  Methods of monitoring ............................................................................................... 49 
14.5  Monitoring responsibility ............................................................................................ 49 
14.6  Monitoring Report ....................................................................................................... 50 

15  Conclusion and Recommendations ....................................................................... 53 
16  Declaration of the consultants ............................................................................. 54 
17  References ........................................................................................................... 55 
18  Annex: EIA Terms of Reference ............................................................................ 56 
19  Annex: Map of Equator Village showing the Project Site ...................................... 57 
20  Annex: Site Plan of the RO Plant House within the premises ................................ 58 
21  Annex: Photos of the project site. ........................................................................ 59 
22  Annex: Guidelines for water quality ..................................................................... 61 
23  Annex: Commitment from the client to undertake the Monitoring....................... 62 
24  Annex: Output Water Quality .............................................................................. 63 
 

   
Page 5 

   
EIA for the setup of RO plant at equator Village, Gan‐Seenu Atoll   

2 Table of Figures
FIGURE 1: PROJECT SCHEDULE ................................................................................................................................... 22 
FIGURE 2: CYCLONIC WIND HAZARD MAP (ADOPTED FROM, UNDP 2006) ...................................................................... 25 
FIGURE 3: EARTHQUAKE HAZARD ZONE (ADOPTED FROM UNDP, 2006) .......................................................................... 26 
FIGURE 4: TSUNAMI HAZARD ZONES (ADOPTED FROM UNDP, 2006) .............................................................................. 27 
FIGURE 5: EXISTING GROUNDWATER WELL IN THE PREMISES ............................................................................................ 59 
FIGURE 6: PROPOSED LOCATION OF THE RO PLANT ....................................................................................................... 59 
FIGURE 7: EXISTING GROYNE ON THE NORTH SIDE ALONG WHICH THE INTAKE PIPE WILL BE LAID. ............................................ 59 
FIGURE 8: THE NORTHERN SIDE FACE OF THE HOTEL ....................................................................................................... 60 
FIGURE 9: CORAL RUBBLE MOUND GROYNE ALONG WHICH THE INTAKE PIPE WILL BE LAID. .................................................... 60 

3 List of Tables
TABLE 1: ROLES AND RESPONSIBILITIES OF STAKEHOLDERS DURING THE EIA PROCESS .......................................................... 14 
TABLE 2: MATRIX OF MAJOR INPUTS DURING CONSTRUCTION PERIOD ............................................................................... 19 
TABLE 3: MATRIX OF MAJOR OUTPUTS OF ENVIRONMENTAL SIGNIFICANCE DURING CONSTRUCTION STAGE ............................... 20 
TABLE 4: MATRIX OF MAJOR OUTPUTS OF ENVIRONMENTAL SIGNIFICANCE DURING OPERATIONAL STAGE ................................. 21 
TABLE 5: KEY METEOROLOGICAL INFORMATION ............................................................................................................ 28 
TABLE 6: TIDAL LEVELS AT HULHULÉ. .......................................................................................................................... 31 
TABLE 7: SUMMARY OF GROUNDWATER, SEAWATER AND SWIMMING POOL WATER QUALITY AT EQUATOR VILLAGE ................... 33 
TABLE 8: SUMMARY OF THE IMPACTS AND THEIR CHARACTERIZATION ............................................................................... 42 
TABLE 9: ADVANTAGES AND DISADVANTAGES OF THE NO PROJECT OPTION ......................................................................... 45 
TABLE 10: PROPOSED MONITORING PROGRAMME ........................................................................................................ 51 

   
Page 6 

   
EIA for the setup of RO plant at equator Village, Gan‐Seenu Atoll   

4 List of Acronyms

 
DO  Dissolved Oxygen 
EC  Electrical Conductivity 
EIA  Environmental Impact Assessment 
EPZ  Environmental Protection Zone 
ERC  Environmental Research Centre 
g/L  Grams per Litre 
GIS   Geographical Information Systems 
GPS  Global Positioning System 
IEE  Initial Environmental Examination 
IDC  Island Development Committee 
LIT  Line Intercept Transect 
lpd  Litres per Day 
MEEW  Ministry of Environment, Energy and Water 
mg/L  Milligrams per Litre 
MHUD  Ministry of Housing and Urban Development Board 
MPND  Ministry of Planning and National Development 
mS/cm  Millisiemens per Centimeter 
MWSA  Maldives Water and Sanitation Authority 
MWSC  Male' Water and Sewerage Company 
NTU  Nephlometric Turbidity Unit 
ppt  Parts per Thousand 
PQ  Photo Quadrate  
RO Plant  Reverse Osmosis Plant also commonly known as RO Plant 
STELCO  State Electrical Company Ltd 
TC  Total Coliform 
FC  Faecal Coliform 
TDS  Total Dissolved Solids 
ToR  Terms of Reference 
UNDP  United Nations Development Programme 
uS/cm  Microsiemens per Centimeter 
WHO  World Health Organization 

 
 

   
Page 7 

   
EIA for the setup of RO plant at equator Village, Gan‐Seenu Atoll   

5 Executive Summary

 
• This report discusses the findings of an environmental impact study undertaken by Water 
Solutions  Pvt.  Ltd.  for  the  establishment  of  a  RO  desalination  plantat  Equator  Village,  in 
Gan island, Seenu Atoll. 

• The aim of this project is to ensure that the hotel has adequate and continuous supply of 
safe water for their daily operational needs.

• The proponent of this project is Gan Invest Maldives Pvt, Ltd.  

• The  purpose  of  this  EIA  is  to  identify  all  significant  environmental  impacts  (positive  and 
negative,  direct,  indirect  and  cumulative).  This  is  to  ensure  that  any  potential  negative 
consequences  that  may  arise  from  the  proposed  activities  are  avoided  or  minimized  and 
any potential benefits from the project are maximized. 

• The project aims to setup a 100 tonnes per day water production RO plant. It is proposed 
to take the raw water direct from the lagoon. 

• In order to undertake the study, baseline environmental surveys were undertaken within 
the  project  boundary.  A  groundwater  quality  assessment  was  undertaken  to  assess  the 
baseline quality of groundwater (within the boundary of the Equator Village). The results of 
these are discussed in the relevant sections.   

• The project does not have any major negative environmental issues, but rather have found 
to have more positive impacts. Discharge of concentrated brine has been identified as the 
most  important  impact  as  far  as  the  environment  is  considered,  but  not  considered 
significant as disposal is proposed to the open sea. 

• The  project  will  have  several  benefits  to  the  hotel,  including  access  to  safe  water 
depending  on  the  demand  and  not  having  to  depend  on  the  main  water  supply  of  the 
island, which is not only inadequate, but also contaminated.  

• Few alternatives to the project has also been suggested. A detail monitoring plan has been 
suggested  towards  the  end  with  details  of  the  costs.  It  is  important  to  undertake  this 
monitoring in order to abide the EIA regulations. The report also provides recommendation 
to improve the project.   

   
Page 8 

   
EIA for the setup of RO plant at equator Village, Gan‐Seenu Atoll   

6 Introduction

This Environmental Impact Assessment (EIA) report has been prepared to fulfil the requirements of 
the Environmental Protection and Preservation Act, law no. 4/93 in order to assess the impacts of 
the  proposed  project  of  setting  up  a  Reverse  Osmosis  desalination  plant  or  RO  plant  at  Equator 
Village, a city hotel located in Gan‐Seenu Atoll. The aim of this project is to ensure that the resort 
has access to safe and adequate water to meet their needs. 

The project proponent is Kaimoo Hotels and Travel Services who is the operator of the hotel. 

6.1 Structure of this EIA Report 

This report has been structured to meet the requirements of the EIA Regulations 2007 issued by 
the Ministry of Housing and Environment. Hence, the report will provide an executive summary at 
the  beginning.  The  report  will  then  describe  the  project  in  detail,  existing  environmental 
conditions,  project  justifications  and  predicted  impacts  of  the  proposed  project.  This  will  be 
followed  by  describing  the  alternatives  of  the  proposed  project  in  terms  of  location,  design  and 
technologies.  Finally, a mitigation plan and a monitoring programme for both constructional and 
operational phase of the proposed project will be outlined.  

The  major  findings  of  this  report  have  been  based  on  qualitative  and  quantitative  assessments 
undertaken during the site visit in October 2010. In addition, information provided by the operator 
and other stakeholders has been utilised. The impact assessment methodology has been restricted 
to  the  collected  field  data,  available  long  term  data,  stakeholder  consultations  as  well  as 
experience and professional judgment.  

6.2 Aims and Objectives of the EIA 

The objective of the report is to: 
• Promote informed and environmentally sound decision making. 
• To  fulfill  the  obligations  of  the  proponent  to  undertake  an  EIA  under  Clause  5  of  the 
Environmental Protection and Preservation Act of the Maldives.  
• Undertake the proposed project work with minimum damage to the environment. 
• Ensure that all the social aspects of the project are addressed. 
 

6.3 EIA Implementation 

This  EIA  has  been  prepared  by  a  local  environmental  consulting  firm,  Water  Solutions  Pvt.  Ltd. 
Water Solutions have been chosen by the client as the environmental consultants to undertake the 
EIA of this project. The team members for this project include: 
ƒ Abdul Aleem, BSc (Env.Health), MPH, (EIA Registration no: EIA 09/07) 
ƒ Ahmed  Jameel  BEng  (Environmental),  MSc  (Hazard  and  Disaster  Management)  (EIA 
Registration no: EIA 07/07) 
ƒ Mohamed Riyaz, ‐ Assistant Surveyor 
 

   
Page 9 

   
EIA for the setup of RO plant at equator Village, Gan‐Seenu Atoll   

6.4 Terms of Reference 

The  terms  of  reference  (ToR)  for  this  EIA  have  been  attached  as  an  annex.  This  EIA  has  been 
prepared based on these terms of reference.  

   
Page 10 

   
EIA for the setup of RO plant at equator Village, Gan‐Seenu Atoll   

7 Project Setting
7.1 Overview 

The  project  takes  place  in  the  Maldives  Environment.  Therefore,  the  extent  to  which  the  project 
conforms to existing plans, policies, guidelines, regulations and laws of the Maldives needs to be 
considered.  Hence,  this  section  will  look  at  the  context  in  which  the  project  activities  take  place 
and the legal and policy aspects relevant to those activities. It is important to note that the project 
is of a local and regional scale and also has some bearing at a national context. 

7.2 Applicable Policies, Laws and Regulations 

There  are  few  environmental  policies,  regulations  and  standards  of  specific  relevance  to  the 
project.  These  are  considered  in  this  section.  The  main  legal  instrument  pertaining  to 
environmental protection is the Environmental Protection and Preservation Act (Law No. 4/93) of 
the  Maldives  passed  by  the  Citizen’s  Majlis  in  April  1993.  This  Act  provides  the  Ministry  of 
Environment,  Energy  and  Water  with  wide  statutory  powers  of  environmental  regulation  and 
enforcement. This umbrella law covers issues such as environmental impact assessment, protected 
areas management and pollution prevention. 

Water  and  Sanitation  regulations,  standards,  guidelines  and  design  criteria  are  of  specific 
relevance.  However,  there  are  no  regulations  on  water  and  wastewater  in  force  except  the 
National  Desalination  Regulation,  which  was  passed  by  the  Government  in  2001.  A  set  of 
regulations on water and sanitation was drafted by an international consultant in 1999. However, 
there was no further development of these draft regulations. 

7.3 Environmental Protection and Preservation Act 

The main legal instrument pertaining to environmental protection and preservation for sustainable 
development in the Maldives is the Environmental Protection and Preservation Act (Law No. 4/93) 
passed by the Citizen’s Majlis in April 1993. The following clauses of the Environmental Protection 
and Preservation Act (Law No. 4/93) are relevant to the project: 
• Clause 5a: An impact assessment study shall be submitted to the Ministry of Environment, 
Energy and Water before implementing any development project that may have a 
potentially detrimental impact on the environment. 

• Clause 5b: The Ministry of Environment, Energy and Water shall formulate the guidelines 
for EIA and shall determine the projects that need such assessment as mentioned in 
paragraph (a) of this clause. 

• Clause 6: The Ministry of Environment, Energy and Water has the authority to terminate 
any project that has an undesirable impact on the environment. A project so terminated 
shall not receive any compensation. 

• Clause 9a: The penalty for minor offences in breach of this law or any regulations made 
under this law, shall be a fine ranging between Rf5.00 (five Rufiyaa) and Rf500.00 (five 
hundred Rufiyaa), depending on the actual gravity of the offence. The fine shall be levied 

   
Page 11 

   
EIA for the setup of RO plant at equator Village, Gan‐Seenu Atoll   

by the Ministry of Environment, Energy and Water or by any other government authority 
designated by that Ministry. 

• Clause 9b: Except for those offences that are stated in (a) of this clause, all major offences 
under this law shall carry a fine of not more than Rf100,000,000.00 (one hundred million 
Rufiyaa), depending on the seriousness of the offence. The fine shall be levied by the 
Ministry of Environment, Energy and Water. 

• Clause 10: The government of the Maldives reserves the right to claim compensation for 
all damages that are caused by activities that are detrimental to the environment. This 
includes all activities mentioned in Clause No. 7 (stated below) of this law as well as those 
activities that take place outside the projects that are identified here as environmentally 
damaging. 

• Clause 7 (a) Any type of wastes, oil, poisonous gases or any substance that may have 
harmful effects on the environment shall not be disposed within the territory of the 
Maldives.

• Clause 7 (b) In cases where the disposal of the substances stated in paragraph (a) of this 
clause becomes absolutely necessary, they shall be disposed only within the areas 
designated for the purpose by the government. If such waste is to be incinerated, 
appropriate precautions should be taken to avoid any harm to the health of the 
population. 

Clause 5 is of specific relevance to this EIA. The EIA Regulations, which came into force in May 2007 
has been developed by the powers vested by the above umbrella law. 

7.4 Second National Environment Action Plan (1999) 

The aim of NEAP II is to protect and preserve the environment of the Maldives and to sustainably 
manage its resources for the collective benefit and enjoyment of present and future generations. 

Main strategies of the NEAP II are: 
ƒ Continuous assessment of the state of the environment in the Maldives, including impacts 
of human activities on land, atmosphere, freshwater, lagoons, reefs and the ocean; and the 
effects of these activities on human well‐being 
ƒ Development  and  implementation  of  management  methods  suitable  for  the  natural  and 
social  environment  of  the  Maldives,  and  maintain  or  enhance  environmental  quality  and 
protect human health, while at the same time using resources on a sustainable basis 
ƒ Consultation  and  collaboration  with  all  relevant  sectors  of  society  to  ensure  stakeholder 
participation in the decision making process 
ƒ Preparation  and  implementation  of  comprehensive  national  environmental  legislation  in 
order to provide for responsible and effective management of the environment 
ƒ Adhering  to  international  and  regional  environmental  conventions  and  agreements  and 
implementation of commitments embodied in such conventions. 
ƒ NEAP II specifies priority actions in the following areas. 
ƒ Climate change and sea level rise; coastal zone management;  

   
Page 12 

   
EIA for the setup of RO plant at equator Village, Gan‐Seenu Atoll   

ƒ Biological diversity conservation; integrated reef resources management;  
ƒ Integrated water resources management;  
ƒ Management of solid waste and sewerage;  
ƒ Pollution control and management of hazardous waste;  
ƒ Sustainable tourism development;  
ƒ Land resources management and sustainable agriculture 
ƒ Human settlement and urbanisation 

NEAP  II  contains  environmental  policies  and  guidelines  that  should  be  adhered  to  in  the 
implementation  of  the  proposed  project  activities,  especially  impact  assessment,  stakeholder 
consultation, biodiversity conservation and human settlement and urbanisation. 

7.5 National Biodiversity Strategy and Action Plan 

The goals of the National Biodiversity Strategy and Action Plan are: 
ƒ Conserve biological diversity and sustainably utilize biological resources. 
ƒ Build capacity for biodiversity conservation through a strong governance framework, and 
improved knowledge and understanding. 
ƒ Foster community participation, ownership and support for biodiversity conservation. 

In  implementing  the  proposed  project  activities  due  care  has  to  be  taken  to  ensure  that  the 
national  biodiversity  strategies  are  adhered  to.  In  fact,  surveys  were  undertaken  at  the  design 
stage to find out if biological resources of value and protected nature are affected by the proposed 
project.  There  will  not  be  any  cutting  of  trees  to  construct  the  plant  house  as  it  will  be  setup  in 
open space. 

7.6 Consultation and Public Participation Laws 

In the Maldives public participation has been limited to the review stages of the EIA until recently 
with the EIA Regulation, which considers public consultation as an important and integral part of 
the  EIA  process.  Hence,  this  EIA  has  also  taken  stakeholder  views  into  consideration.  In  fact, 
stakeholder  consultations  were  conducted  in  order  to  take  their  opinion,  views,  suggestions  and 
expectations into consideration.  Chapter 15 will provide details of the Stakeholder Consultations. 

7.7 Environmental Permits required for the Project 

7.7.1 EIA Decision Statement 

The  most  important  environmental  permit  to  initiate  construction  work  in  Equator  Village  would 
be  a  decision  regarding  this  EIA  from  the  Ministry  of  Environment,  Energy  and  Water.  The  EIA 
Decision  Statement,  as  it  is  referred  to,  shall  govern  the  manner  in  which  the  project  activities 
must  be  undertaken.  This  EIA  report  assists  decision  makers  in  understanding  the  existing 
environment and potential impacts of the project. Therefore, the Decision Statement may only be 
given to the Proponent after a review of this document following which the Ministry may request 
for further information or provide a decision if further information is not required. In some cases, 
where  there  are  no  major  environmental  impacts  associated  with  the  project,  the  Ministry  may 
provide the Decision Statement while at the same time requesting for further information. 

   
Page 13 

   
EIA for the setup of RO plant at equator Village, Gan‐Seenu Atoll   

7.8 Regulations for Installing and Operating Desalination 
Plants in the Maldives  

There is a set of regulations in the Maldives consisting of 19 clauses that governs the installation 
and operation of desalination plants in the Maldives. This project will conform to all the 19 clauses 
of this regulations.  

7.9 Roles and Responsibilities of Groups Involved 

There are various organizations and parties involved in the EIA process. There are national agencies 
responsible  for  environmental  protection  as  well  as  the  key  stakeholders  and  the  project 
proponent,  each  with  a  role  and  responsibility  within  the  EIA  process.  One  key  principle  in  EIA 
implementation is to involve these groups and provide them the opportunity to participate in the 
EIA  process  so  that  their  concerns  are  addressed.  This  section  discusses  the  roles  and 
responsibilities of national groups involved in the EIA system, with specific focus on the proposed 
project.  Table  below  provides  a  summary  of  the  roles  and  responsibilities  of  each  group  in  the 
different stages of the EIA process.   
 
Table 1: Roles and Responsibilities of Stakeholders during the EIA Process 

Stage  Environment  Proponent  EIA  Other  Govt  Public  and 


Ministry  Consultants  Agencies  Interest 
(ERC)  Groups 

Screening  Screen  Provide  necessary  Provide  Raise  issues   


Project  information  technical  and 
advice  concerns 

Scoping  Approve TOR  Provide TOR  Prepare TOR  Provide  Participate 


Review IEE  Provide IEE  Prepare IEE  comments/  in 
feedback  consultation 

EIA study  Provide  Provide EIA  Prepare EIA    Participate 


scope/  Comment 
Approve TOR 

Review  Review EIA    Revise EIA  Assist  in   


review 
Comment 

Approval  Approve  EIA    Provide  Approve   


Attach terms  technical  relevant 
advice  components 

Environmental    Implement  Conduct  Implement  w


Management  mitigation  monitoring  Monitoring 
measures  and 
monitoring 
programme 

Post Audit and  Evaluate  Provide  necessary    Assist  in  the  Provide  info 

   
Page 14 

   
EIA for the setup of RO plant at equator Village, Gan‐Seenu Atoll   

Evaluation  project information audit to auditors

Source: Adapted from Lohani et al (1997) 

7.9.1 Environment Ministry 

The  Ministry  of  Environment,  Energy  and  Water  plays  the  main  role  within  the  Government  for 
implementing  EIA  and  other  environmental  matters.  It  has  central  control  over  environmental 
protection and related issues. Water has specific focus and a Section within the Ministry has been 
established  for  water  and  sanitation.  This  section  has  two  wings:  a  planning  wing  and  an 
implementation wing. 

The Environment Research Centre (ERC) of the Ministry has responsibility for efficient operation of 
the EIA process. This encompasses a number of tasks, including screening of projects and provision 
of general procedural advice to the project proponents throughout the EIA process. ERC manages 
the review of the EIA report and is responsible for any approvals or recommendations associated 
with the EIA. ERC is playing a commendable role in the EIA administration process although it still 
lacks the capacity to undertake audits and enforce environmental monitoring during construction 
and post‐construction stage. 

7.9.2 Environmental Protection Agency 

Former Maldives Water and Sanitation Authority (MWSA) and presently a section under EPA is the 
government  authority  responsible  for  water  and  wastewater  regulation  in  the  Maldives.  EPA’s 
regulatory functions and capacity are still at an infant stage. Under the proposed project, EPA will 
provide the Authority Criteria and Guidelines for water quality. EPA would also assist in preparing 
the scope of  the  EIA and  evaluating  the EIA proposed for the project.  EPA will issue a License to 
install  the  proposed  RO  plant  once  the  proponent  registers  the  plant.  EPA  is  also  the  regulatory 
body to ensure that the water quality is maintained according to international guidelines. 

7.9.3 Project Proponent 

The project proponent is the party responsible for the effective implementation of the project. The 
proponent for the proposed project is Kaimoo Travels and Hotel Services.   

7.9.4 Environmental Consultants 

As the EIA forms an integral part of the project, the EIA component needs to be integrated which 
would help in the design of the project in a sustainable manner. Water Solutions was contracted to 
undertake the EIA for the project.  

   
Page 15 

   
EIA for the setup of RO plant at equator Village, Gan‐Seenu Atoll   

8 Project Description
8.1 Description of the Project Proponent 

This project is proposed by Gan Invest Maldives Pvt, Ltd. Ninety Nine percent of the sharesin Gan 
Invest  Maldives  is  held  Kaimoo  Travels  and  Hotel  Services.  Kaimoo  Hotels  and  Travels  have  wide 
experience in hospitality service in the Maldives. With over 20 years experience, this company has 
seen  tremendous  changes  in  the  way  tourism  was  developed  in  the  Maldives.  Kaimoo  Hotels  is 
committed to providing excellence in service and have fine‐tuned its resorts and hotels to suit the 
requirements  of  the  average  traveler.  The  proponent  is  engaged  in  a  number  of  tourism  related 
hotels and resorts in Male and outside Male’ and includes the following resort and hotel portfolios 
among other businesses.  

Embudu Village is a three star resort suited both for the active adventurer and people who like to 
do nothing at all. It is located only half an hour by fast boat from Male' International Airport. The 
resort is operated by the proponent.  

• Summer Island Village is an all‐inclusive three star resort in north Male’ atoll.  
• Equator Village is located in Gan, the very southern end of Maldives. This is a city hotel. 
• Mookai Suites is an apartment complex based in Male’.  
• KAM hotel is a five star hotel in Male’. 
• Sakamoo, an apartment style hotel based in Male’. 
• KAI lodge, a guest house in Male’. 

All  these  properties  were  developed  and  are  managed  by  the  proponent.  In  addition,  the 
proponent also has other business establishments outside Maldives.  

8.2 Project Location and boundary 

Seenu Atoll (S) is located between latitude 0° 36' S and 0° 44' S south of the equator. Addu Atoll is 
the second populous atoll apart from Male'. The project takes place in the island of Gan within the 
boundary of Equator Village, a city hotel based on the north of the island. Equator Village is located 
in the Gan Island , approximately 1 Km from Gan International Airport. Gan Island is 5 Km length 
and 3 Km width. It is one of the largest Islands in Addu Atoll.  

The  proposed  project  is  limited  within  the  boundary  of  the  Equator  Village  (see  site  plan  for 
details). The project will install and setup a 100 ton RO plant on the north‐west side of the property 
premises and a pipe network will be setup to distribute water to the rooms and other facilities. The 
project  boundary  is  therefore  the  hotel  with  emphasis  on  the  north‐west  side.  Equator  village  is 
located  on  the  north‐west  side  of  Gan  in  Seenu  atoll.    The  geographical  coordinates  are 
0°41'14.95"S and  73° 8'48.93"E. The hotel is operated by Kaimoo Travels and Hotel Services. The 
hotel caters to mostly European clients and throughout the year, the hotel is visited by guests from 
a variety of countries. During the peak tourist season in Maldives, the resort’s bed capacity reaches 
to approximately 80 %.  

   
Page 16 

   
EIA for the setup of RO plant at equator Village, Gan‐Seenu Atoll   

8.3 Need and Justification 

At present, the power and the water for the resort’s purpose is obtained through the main 
power  grid  and  the  water  supply  of  Gan  respectively.  Presently,  the  hotel  is  faced  with 
water supply and water quality issues that are affecting the operations negatively and at a 
very  significant  level.  Following  are  some  of  the  water  related  issues  faced  by  the  hotel 
due to being dependent on the main water supply network. 

 
‐ Not enough supply: Dependence on the island’s Water supply system creates water 
availability  issues  that  are  beyond  the  control  of  the  hotel  operations.  Water  for 
the  hotel  is  required  continuously  and  consistently  in  order  to  ensure  that  guest 
services  and  the  smooth  operation  of  the  resort  is  not  affect.  Fluctuations  in  the 
quantity  of  water  available  are  creating  difficult  operational  issues  and  guest 
complaints.  Depending  on  the  overall  water  demand  for  GAN,  water  availability 
keeps  fluctuating  and  there  are  times  when  water  is  not  sufficiently  available  for 
the hotel operations.   
 
‐ Guest  complains:  Due  to  the  water  shortage  issues,  the  hotel  is  constantly 
bombarded with guest complains, that is not only affecting the hotel’s operation, 
but the overall image of the tourism sector.   
 
‐ Smelly  water:    The  main  water  supply  in  Gan  is  derived  from  ground  and  is  not 
suitable  for  consumption  in  a  resort  as  most  of  the  time  the  water  is  smelly.  At 
times,  the  water  has  a  very  high  percentage  of  impurity  and  suspended  solids. 
According  to  the  hotel  staff,  the  water  supply  in  GAN  has  lot  of  issues  and  as  a 
result,  it  is  causing  the  foul  odour.  Such  water  cannot  be  justified  to  be  made 
available in a resort, which is not only an operational issue, but a health hazard to 
the staff and guests. 
 
‐ Negative  affects  to  the  hotel  operations:    The  present  water  issues  faced  by  the 
resort are causing a major impact on the operation of the resort. Guests and tour 
operators  are  continuously  pressuring  the  resort  management  to  have  an 
independent  and  safe  water  supply  which  is  directly  linked  with  the  hotel 
operations.  
 

Hence, for these reasons, an in house desalination system is urgently necessary in order to 
run the hotel more smoothly.  

8.4 Project Duration 

The proposed project is expected to be completed within a maximum of six months. 

   
Page 17 

   
EIA for the setup of RO plant at equator Village, Gan‐Seenu Atoll   

8.5 Description of the Project Components 

8.5.1 Location of the RO Plant and Plant House 

The RO plant will be located in the north‐west corner of the hotel boundary. The area is open and 
does not contain any vegetation except grass (see annex for photos). The adjacent area contains 
the laundry and the tennis courts, hence there will be minimal disturbance to guest rooms.   

8.5.2 Capacity of RO Plant 

The  proposed  project  will  install  a  100  m3  day  RO  plant.  The  plant  will  be  purchased  by  an 
approved supplier. The RO plant will be installed and commissioned by the supplier. Once the RO 
plant is commissioned, it will be tested and registered with EPA before water is used in the hotel.  

8.5.3 Method of Feed Water Intake 

Due to the shorter distance from the seashore to the plant site and the composition of beach, it 
has been proposed to construct a beach well for feed water intake. The beach well will be placed in 
the lagoon and the pipe connected to it. Feed water will then be drawn from the beach well. The 
beach well will be constructed using concrete and placed in the lagoon.  

8.5.4 Energy for the RO Plant 

Southern Utilities have confirmed that they have enough spare capacity available for the operation 
of  the  RO  plant.  Hence,  electricity  for  the  RO  plant  will  be  obtained  from  the  GAN  island  main 
electricity grid. 

8.5.5 Operational Staff  

The engineering department will employ two operators. 

8.5.6 Description of the beach well 

The beach well will be constructed using cement. It will be a cylindrical well with a height of 4 feet 
and  a  diameter  of  3  feet.  Both,  top  and  the  bottom  will  be  covered  with  and  the  sides  will  be 
perforated with holes to allow water to seep in to the well. 

8.5.7 Properties of Output Water  

On average, the daily output of potable water will be 80 cubic meters per day (product water) and 
the  output  quality  will  be  as  per  the  WHO  standards  (If  product  water).  Product  water  refers  to 
water  that  is  distributed  for  consumption.  Although  the  water  will  not  be  used  for  drinking 
purpose, the water will adhere to these standards as it will be used for cooking among other uses. 

8.5.8 Disposal of Concentrated Brine  

It  is  proposed  to  dispose  the  concentrate  brine  in  to  the  northern  lagoon  70  meters  east  of  the 
intake location. This area is indicated in the site plan attached. The receiving environment is prone 
to  strong  waves  and  long  shore  currents,  which  is  expected  to  dilute  the  concentration  of  brine. 
There is no concern for the brine to be accumulated near the feed‐water area. Baseline conditions 

   
Page 18 

   
EIA for the setup of RO plant at equator Village, Gan‐Seenu Atoll   

of the receiving environment have been studied both at the intake location and discharge location 
to  understand  and  record  the  types  of  corals  and  marine  life  existing  in  this  area.  Details  of  the 
survey are described under the section “Existing Marine Environment”. 

8.5.9 Water Quality Monitoring 

Weekly water quality monitoring will be undertaken by the hotel to ensure that the output water 
quality  is  safe.  Water  will  be  tested  by  sending  samples  to  either  Hithadhoo  Regional  hospital 
laboratory or to Male’. 

8.5.10 Water Production Process 

 The water production process will follow the following hierarchy. 
• Saltwater intake from the lagoon at 5 bar pressure using pumps located on land inside the 
RO plant room. 

• Pre‐treatment of the intake water using filtration, sedimentation etc. 

• Reverse osmosis by passing the water through the membrane using high pressure pumps. 

• Storage and treatment of product water in storage tanks.  

• Distribution of water to the hotel through pressurized system to the outlets (guest rooms 
and main facilities). Water quality monitoring will be undertaken weekly. The present 
piping system will be connected to the product water distribution network. 

8.5.11 Project Inputs 

The types of resources that will go into the project and from where and how these will be obtained 
are given in the following table. 
Table 2: Matrix of major inputs during construction period 

INPUT RESOURCE(S)  SOURCE/TYPE  HOW TO OBTAIN RESOURCES 

Construction workers  Maldivians   Open bidding to contractors from Addu Atoll. 


(5) 

Water supply  Groundwater  Groundwater from the island (GAN) 


(construction period) 

Electricity/Energy  Gan island’s main power grid.  Through the utilities company. 


(construction period) 

Construction machinery  Concrete  mixer  and  general   Local suppliers 


construction tool  

Telecommunications  obile  phones,  fax  and  Already this services is available in the island 


telephone  

Transport (sea)  Materials  to  be  transported   Already  established.  Contractor  to  be  in 
from  one  of  the  connected  charge of this. 
islands,  either  Feydhoo, 

   
Page 19 

   
EIA for the setup of RO plant at equator Village, Gan‐Seenu Atoll   

INPUT RESOURCE(S)  SOURCE/TYPE  HOW TO OBTAIN RESOURCES 


Maradhoo,  maradhoo‐
Feydhoo  or  Hithadhoo.  All 
construction  debris  will  be 
disposed  to  the  waste 
disposal  site  in  Addu  atoll 
hithadhoo. 

Food during  Available  from  the  hotel  /  Available from the island / hotel 


construction period  island 

Ordinary Portland  Approximately 250 Bags  Purchase from local sources 


Cement 

Sand  Approximately  500  to  800  Purchase from local sources 


  Bags 

8.5.12 Project Outputs 

The type of outputs (products and waste streams) and what is expected to happen to the outputs 
are given in the next table. 
Table 3: Matrix of major outputs of environmental significance during construction stage 

PRODUCTS  AND  WASTE  ANTICIPATED  METHOD OF DISPOSAL / CONTROL 


MATERIALS  QUANTITIES 

Construction waste from  2 to 5 cubic meters of  Dispose at the waste disposal site in Hithadhoo. 


construction activities,  debris in total and 
mainly cement bags,  general construction 
timber, and other  waste.   
construction waste during 
the construction of the 
plant house. 

Noise   Localised to the  Guest will be informed of the construction and 


construction area only  the time period for construction will be limited 
to a minimum. 

Air pollution  Limited quantities of  Mainly arising as a result of dust emission from 


dust.  the construction work such as cement mixing, 
and other construction process while the plant 
house is under construction. Only localised to 
the area only. 

   

   
Page 20 

   
EIA for the setup of RO plant at equator Village, Gan‐Seenu Atoll   

Table 4: Matrix of major outputs of environmental significance during operational stage 

PRODUCTS  AND  WASTE  ANTICIPATED  METHOD  OF  DISPOSAL  /  CONTROL  / 


MATERIALS  QUANTITIES  DISTRIBUTION 

Potable  water  (product  Approximately  800m3  Store in storage tanks and distribute via the pipe 


water)  per day  network to the hotel. 

Concentrated brine  Approximately  1800m3  Dispose  to  the  marine  environment,  northern 


per day  side  lagoon.  Refer  to  the  existing  marine 
environment. 

Noise   Localised  to  the  plant  Plant  house  will  be  enclosed  so  noise  will  be 
house   under control. 

Co2 emission  Not available.  Indirect CO2 emission through the use of energy 


for  the  operation.  Not  expected  to  be 
significant.   

   
Page 21 

   
 

8.6 Project Schedule and Life Span 

As  soon  as  the  EIA  is  approved  and  a  decision  statement  is  issued,  work  will  commence  for  the 
construction  of  the  RO  plant  house  and  other  civil  works  such  as  laying  out  the  intake  pipe  and  
brine discharge pipe. 

 
   2010  2011 

Nov 

Dec 
Sep 

Feb 
Oct 

Jan 
  
Preparation of EIA report     x   x             
Approval of EIA      x             
Construction of the Ro plant house         x          
Construction of the beach well         x          
Completion of the plant house            x       
RO plant installation            x   x    
Commissioning and testing               x 
Figure 1: Project schedule 

 
 
EIA for the setup of RO plant at equator Village, Gan‐Seenu Atoll   

9 Methodology

The  section  covers  methodologies  used  to  collect  data  on  the  existing  environment.  The  key 
environmental  components  of  this  proposed  project  were  ground  water  quality  of  the  island 
(within the hotel premises) and an assessment of the proposed intake and discharge locations and 
the terrestrial environment. In addition the economic environment and the hazard vulnerability of 
the island were assessed. 

 The  following  data  collection  methodologies  were  used  during  the  field  visit  undertaken  in 
October 2010.  

9.1 Mapping and Location Identification 

The  location  of  data  collection  sites  were  marked  using  a  handheld  GPS.  These  data  collection 
points include groundwater sampling locations, marine water sampling locations and the proposed 
location for the RO plant and brine discharge location. 

9.2 Ground Water Quality Assessment 

Groundwater  quality  was  assessed  by  collecting  samples  from  two  locations  that  were  selected 
from the island using YSI 6820 multi parameter handheld water quality meter. In addition, water 
quality  was  also  tested  at  the  National  Health  Laboratory.  Groundwater  wells  existing  in  the 
premises of the hotel were used to test the water. 

9.3 Marine Environment Surveys 

Marine environmental surveys were conducted to collect data on key environmental components 
(i.e.  the  coral  reef  system  and  the  lagoon),  that  will  be  impacted  due  to  the  project  (discharge 
location). Two methods were primarily used to collect data, namely: 

• Detail photo transect,  

• Qualitative surveys through visual observations.  

Purpose of the surveys was to define and establish marine environmental baseline conditions for 
impact evaluation during and after the proposed project. Surveys were based on standard marine 
environmental surveys so that they can be repeatedly carried out to monitor and record changes 
and  assess  possible  impacts  on  the  marine  environment  from  the  proposed  project.  Surveys 
include quantitative and qualitative methods. In addition, photos were taken for comparison. 

9.4 Aerial Photos 

Aerial photos were obtained to compliment the GPS mapping.    

   
Page 23 

   
EIA for the setup of RO plant at equator Village, Gan‐Seenu Atoll   

10 Existing Environment

This section will discuss the existing environmental conditions of the hotel premises.  

10.1 Geography 

Seenu Atoll (S) is located between latitude 0° 36' S and 0° 44' S south of the equator. Addu Atoll is 
the second populous atoll apart from Male'. The project takes place in the island of Gan within the 
boundary of Equator Village, a city hotel based on the north of the island. Equator Village is located 
in the Gan Island , approximately 1 Km from Gan International Airport. Gan Island is 5 Km length 
and 3 Km width. It is one of the largest Islands in Addu Atoll.  

10.2 Hazards and Disasters 

10.2.1 Natural Vulnerability of the Island of Gan 

The islands of the Maldives have natural characteristics which make them vulnerable to disasters 
such  as  tsunami.  An  island’s  Natural  Vulnerability  depends  on  geographic  and  geomorphologic 
characteristics  of  the  island.  These  include  geographic  features  of  the  island  like  the  side  of  the 
country where the island is located, the formation of the island, location of the island with respect 
to the atoll, orientation of the island, region of the country where island is located, level of shadow 
to the island from the reefs and other islands; area of the inland lake found on the island, width of 
the island’s house reef, coastal defence structures on the island, shape of the island and the area 
of the island.  

A  Model  to  Integrate  the  Management  of  Hazards  and  Disasters  in  the  National  Sustainable 
Development  Planning  of  the  Maldives  which  was  developed  as  part  of  the  Masters  of  Science 
(Hazard  and  Disaster  Management)  thesis  at  the  University  of  Cantebruy  (2007)  identified  the 
relationship  between  natural  characteristics  of  the  island  and  the  natural  vulnerability  of  the 
islands  using  the  data  that  was  collected  following  the  Indian  Ocean  Tsunami.  Based  on  this 
research, the natural vulnerability of Gan Island was found to be high for earthquake hazards while 
the vulnerability is low for cyclonic wind hazards and flooding disasters caused by high waves or a 
tsunami approaching the island from the east.  

The following figures indicate the vulnerability of Gan Island (Addu Atoll) to Cyclonic wind hazard, 
earthquake hazard and Tsunami hazard respectively. 

   
Page 24 

   
EIA for the setup of RO plant at equator Village, Gan‐Seenu Atoll   

Male'

Very High
High
Moderate
Low
Very Low
Equator

 
Figure 2: Cyclonic Wind Hazard Map (adopted from, UNDP 2006) 

   
Page 25 

   
EIA for the setup of RO plant at equator Village, Gan‐Seenu Atoll   

Very High
High
Moderate
Low
Very Low
Equator

 
Figure 3: Earthquake Hazard Zone (adopted from UNDP, 2006) 

   
Page 26 

   
EIA for the setup of RO plant at equator Village, Gan‐Seenu Atoll   

N
S

Probable Max Wave Hight


Very High 320 - 450 cm
S High 250 - 320 cm
S Safer Island Moderate 80 - 250 cm
Airport Low 30 - 80 cm
Atoll Capital Low Less than 30 cm

Equator

0 50 100 150 200 Km


 
Figure 4: Tsunami Hazard Zones (adopted from UNDP, 2006) 

 
 

   
Page 27 

   
 

10.3 Climatic Setting 

The  Maldives,  in  general,  has  a  warm  and  humid  tropical  climate  with  average  temperatures 
ranging between 25°C to 30°C (MHAHE, 2001) and relative humidity ranging from 73 per cent to 85 
per  cent.  The  country  receives  an  annual  average  rainfall  of  1,948.4mm.  There  is  considerable 
variation  of  climate  between  northern  and  southern  atolls.  Table  5  provides  a  summary  of  key 
meteorological  findings  for  Maldives.  General  studies  on  climatic  conditions  of  Maldives  were 
taken into account during study as local level time‐series data are limited for longer periods at the 
nearest meteorological station. 
Table 5: Key meteorological information 

Parameter Data

Average Rainfall 9.1mm/day in May, November


1.1mm/day in February

Maximum Rainfall 184.5 mm/day in October 1994

Average air temperature 30.0 C in November 1973


31.7 C in April

Extreme Air Temperature 34.1 C in April 1973


17.2 C in April 1978

Average wind speed 3.7 m/s in March


5.7 m/s in January, June

Maximum wind speed W 31.9 m/s in November 1978

Average air pressure 1012 mb in December


1010 mb in April

10.3.1 Monsoons 

Monsoons of Indian Ocean govern the climatology of the Maldives. Monsoon wind reversal plays a 
significant  role  in  weather  patterns.  Two  monsoon  seasons  are  observed:  the  Northeast  (Iruvai) 
and the Southwest (Hulhangu) monsoon. Monsoons can be best characterized by wind and rainfall 
patterns. The southwest monsoon is the rainy season which lasts from May to September and the 
northeast  monsoon  is  the  dry  season  that  occurs  from  December  to  February.  The  transition 
period of southwest monsoon occurs between March and April while that of northeast monsoon 
occurs from October to November.  

10.3.2 Rainfall 

Annual average rainfall in Maldives is about 1900mm. There is a marked variation in rainfall across 
Maldives with an increasing trend towards south. The annual average rainfall in north is 1977mm 
and for south is 2470mm.  

The  southwest  monsoon  is  known  as  the  wet  season  with  monthly  average  rainfall  ranging  from 
125‐250mm. The northeast monsoon is known as the dry season with average monthly rainfall of 
50‐75mm.  
EIA for the setup of RO plant at equator Village, Gan‐Seenu Atoll   

Rainfall records indicate an average annual rainfall of 2500mm. The intensity of rainfall is a concern 
in the Maldives since intensity is high with low frequency. Excessive rainfall may be a concern for 
GAN since the island lies in the south of Maldives.  

10.3.3 Temperature 

Daily temperatures of Maldives vary little throughout the year with a mean annual temperature of 
28°C.  The  annual  mean  maximum  temperature  recorded  for  Male’  during  the  period  1967‐1995 
was  30.4°C  and  the  annual  mean  minimum  temperature  for  the  same  period  was  25.7°C.  The 
highest  recorded  temperature  for  Male’  was  34.1°C  on  16th  and  28th  of  April  1973.  The  hottest 
month recorded was April 1975 with a maximum monthly average temperature of 32.7°C, the next 
highest  being  32.6°C  in  April  1998.  The  lowest  minimum  average  temperature  of  23.7°C  was 
recorded in July 1992. 

10.3.4 Wind 

Wind has been shown to be an important indirect process affecting formation, development and 
seasonal dynamics of the islands in the Maldives. Winds often help to regenerate waves that have 
been  weakened  by  travelling  across  the  reef  and  they  also  cause  locally  generated  waves  in 
lagoons.  Therefore  winds  are  important  here,  as  being  the  dominant  influence  on  the  sediment 
transportation  process  (waves  and  currents).  With  the  reversal  of  winds  in  the  Maldives,  NE 
monsoon period from December to March and a SW monsoon from April to November, over the 
year, the accompanying wave and current processes respond accordingly too. These aspects have 
ramification  on  the  seasonal  sediment  movement  pattern  on  the  islands  and  also  the 
delivery/removal  of  sediments  from  the  reef  platform/island.  These  also  determine  where 
structures  such  as  jetties  and  mooring  areas  in  resorts  are  located  and  this  data  is  vital  in 
determining this at the design stage.  

The  two  monsoon  seasons  have  a  dominant  influence  on  winds  experienced  across  Maldives. 
These monsoons are relatively mild due to the country’s location close to the equator and strong 
winds and gales are infrequent. However, storms and line squalls can occur, usually in the period 
May to July; gusts of up to 60 knots have been recorded at Male’ during such storms. 

Wind  was  uniform  in  speed  and  direction  over  the  past  twenty‐plus  monsoon  seasons  in  the 
Maldives  (Naseer,  2003).  Wind  speed  is  usually  higher  in  central  region  of  Maldives  during  both 
monsoons,  with  a  maximum  wind  speed  recorded  at  18  m.s‐1  for  the  period  1975  to  2001. 
Maximum wind speed recorded in the south was 17.5 m.s‐1 during the period 1978 to 2001. Mean 
wind  speed  was  highest  during  the  months  January  and  June  in  the  central  region,  while  wind 
speed was in general lower and more uniform throughout the year in the southern region. Wind 
analysis indicated that the monsoon was considerably weaker in the south (Naseer, 2003). During 
the peak months of the SW monsoon, southern regions have a weak wind blowing from the south 
and south‐eastern sectors. 
   

   
Page 29 

   
EIA for the setup of RO plant at equator Village, Gan‐Seenu Atoll   

10.3.5 Waves  

Wave energy is important for sediment movements and settlement, and it is also a crucial factor 
controlling  coral growth and reef development. Waves have been attributed to the  diversity and 
the abundance of coral and algal species. These aspects have implications for the type and perhaps 
the supply of sediment s into the island. 

Studies by Lanka Hydraulics (1988a & 1998b) on Malé reef indicated that two major types of waves 
on  Maldives  coasts:  wave  generated  by  local  monsoon  wind  and  swells  generated  by  distance 
storms.  The  local  monsoon  predominantly  generates  wind  waves  which  are  typically  strongest 
during April‐July in the south‐west monsoon period. During this season, swells generated north of 
the equator with heights of 2‐3 m with periods of 18‐20 seconds have been reported in the region. 
Local  wave  periods  are  generally  in  the  range  2‐4  seconds  and  are  easily  distinguished  from  the 
swell waves.  

Distant cyclones and low pressure systems originating from the intense South Indian Ocean storms 
are reported to generate long distance swells that occasionally cause flooding in Maldives (Goda, 
1988). The swell waves that reached Malé and Hulhule in 1987, thought to have originated from a 
low  pressure  system  of  west  coast  of  Australia,  had  significant  wave  heights  in  the  order  of  3 
metres.  

In addition, Maldives has recently been subject to earthquake generated tsunami reaching heights 
of  4.0m  on  land  (UNEP,  2005).  Historical  wave  data  from  Indian  Ocean  countries  show  that 
tsunamis have occurred in more than one occasion, most notable been the 1883 tsunami resulting 
from the volcanic explosion of Karakatoa (Choi et al, 2003). 

Gan  is  exposed  to  waves  generated  by  swells  combined  with  short‐wind‐generated  waves 
travelling outside the atoll from south , east and north‐east side during the two monsoons. Waves 
breaking on the eastern side may be considered to be stronger because of the narrow reef extent 
on this side in comparison to the southern side.  

10.3.6 Tides 

The tidal regime is semi‐diurnal with diurnal inequalities (twice daily). That means 2 high tides and 
2 low tides per day, with different heights. Typical spring and neap tidal ranges are approximately 
1.0 m and 0.3 m, respectively. 

Tides in the Maldives are mixed semi‐diurnal / diurnal. There are no permanent tidal record.  

Binnie  Black  &  Veatch  (SEA)  (2000)  gives  tide  levels  at  Hulhule  relative  to  Mean  Sea  level,  chart 
datum (Lowest Astronomical Tide Level) (Table 6).    
Tidal level Referred to MSL (taken as 0.56m Referred to Chart Datum (Source:
above Chart Datum) Admiralty Tide Tables, Vol 3)

Highest Design Water Level (JICA, + 1.08m + 1.64m


1992)

   
Page 30 

   
EIA for the setup of RO plant at equator Village, Gan‐Seenu Atoll   

Highest Astronomical Tide (HAT) + 0.64m + 1.2m

Mean Higher High Water (MHHW) + 0.34m + 0.9m

Mean Lower High Water (MLHW) + 0.14m + 0.7m

Mean Sea Level (MSL) 0.0m + 0.56m

Mean Higher Low Water (MHLW) - 0.16m + 0.4m

Mean Lower Low Water (MLLW) - 0.36m + 0.2m

Lowest Astronomical Tide (LAT) - 0.56m 0.0m

Table 6: Tidal levels at Hulhulé. 

The tidal levels given above are predicted astronomical tide levels.  In reality, the tide levels may 
vary from the predicted levels at a given time and location due to meteorological conditions at the 
location.  However, variation in Mean Sea Level in the Maldives, according to the Department of 
Meteorology, is negligible. 

10.3.7 Currents 

Studies  on  current  flow  within  a  reef  flat  in  Male’  Atoll  suggests  that  wave  over  wash  and  tides 
generate  currents  across  the  reef  platforms,  which  are  also  capable  of  transporting  sediments 
(Binnie Black & Veatch, 2000). However, available information suggests that tidal currents are not 
strong due to small tidal range. 

Generally,  current  flow  through  the  Maldives  is  driven  by  the  dominating  two‐monsoon  season 
winds.  Westwardly  flowing  currents  are  dominated  from  January  to  March  and  eastwardly  from 
May to November. The change in currents flow pattern occurs in April and December. In April the 
westward  currents  flow  are  weak  and  eastward  currents  flow  will  slowly  take  place.  Similarly  in 
December eastward currents flows are weak and westward currents will take over slowly.  

Studies  on  current  flow  process  within  a  coral  atoll  have  shown  that  waves  and  tides  generate 
currents across the reef platforms, which are capable of transporting sediments on them. Currents, 
like waves are also modified by reef morphology. Under low‐input wave conditions (0.5m heights), 
strong lagoon ward surge currents (>60cm/sec) are created by waves breaking at the crest. Studies 
on current flow across reef platforms have shown that long‐period oscillations in water level cause 
transportation  of  fine‐grained  sediments  out  of  the  reef‐lagoon  system,  while  strong,  short 
duration  surge  currents  (<5sec.)  transport  coarse  sediments  from  the  breaker  zone  to  seaward 
margin  of  the  backreef  lagoon.  Always  sediment  accumulates  at  the  lee  of  high‐speed  current 
zones. Generally zones of high current speed (jets or rips, 50‐80cm/sec) are systematically located 
around islands. 
 

   
Page 31 

   
EIA for the setup of RO plant at equator Village, Gan‐Seenu Atoll   

10.4 Existing Terrestrial Environment 

For  this  project,  groundwater  has  been  considered  as  the  component  of  the  terrestrial 
environment  that  will  be  studied  and  described  as  the  project  is  related  to  the  groundwater 
quality. 

10.4.1 Terrestrial flora and fauna 

The proposed project site where the plant house is to be constructed is empty land and no trees 
will be cut. The area is only covered in green grass and hence, there will only be the loss of grass 
found  on  the  footprint  of  the  building.  No  plants  or  any  plants  that  is  home  to  birds  will  be 
required to cut in this project. 

Refer to annex to see the photos of the project site.  

10.4.2 Groundwater 

Generally, the islands of the Maldives have superficial groundwater lenses below about a metre of 
coralline sandy soil with a very narrow humus layer on top. The groundwater lenses so formed are 
formed due to density differences between percolated rainwater and saltwater beneath the island. 
The  freshwater  lens  floats  on  top  of  the  saltwater.  This  makes  it  extremely  fragile  and  prone  to 
saltwater intrusion due to over‐abstraction. This is the problem experienced in GAN.  

For  the  purpose  of  this  assessment,  groundwater  wells  existing  inside  the  premises  of  the  hotel 
boundary were tested. The results are illustrated in the following table. 

10.4.3 Existing Groundwater Quality 
The groundwater wells were visually inspected, and samples were tested for electrical conductivity 
(salinity)  and  various  other  parameters,  namely  pH,  TDS,  DO  and  Phosphates  and  Nitrates. 
Summary of the water quality results are attached as an annex. During the survey, it was observed 
that wells were covered and had a pungent smell.  
 
 
   

   
Page 32 

   
EIA for the setup of RO plant at equator Village, Gan‐Seenu Atoll   

Table 7: Summary of groundwater, seawater and swimming pool water quality at Equator Village 

   Well 1  Well 1  Seawater at   Seawater at   Swimming pool 


(G1)  (G2)  intake location  discharge location  water 
(S1)  (S2) 
pH  8  8.2  8  8  9.4 
EC (uS/cm)  2580  3200  57700  57700  3000 
TDS (mg/L)  1221  1593          
TDS (g/L)        33.6  33.6    
Temp (C)  30.9  26.8  29.4  28  29 
Salinity (ppt)  1.2  1.6  35  35  1.4 
Nitrate (mg/L)  12.5  5.6  0  0    
Phosphate  3.9  2.4  0.8  0    
(mg/L) 
Turbidity (NTU)  ‐  ‐  1.5  1  0 

 
 

   
Page 33 

   
EIA for the setup of RO plant at equator Village, Gan‐Seenu Atoll   

10.5 Existing Marine Environment 

10.5.1 Section Brief 

This section will look at the existing marine environment of the project site with specific emphasis 
on  the  northern  lagoon  where  concentrate  brine  will  be  discharged  and  also  in  areas  where  the 
pipeline will be laid to intake the water. 

10.5.2 Marine Water Quality  

The  primary  objective  of  the  marine  water  quality  sampling  was  to  determine  the  baseline 
conditions  of  the  marine  water  quality  of  the  lagoon  at  two  locations,  that  is  the  RO  feed  water 
intake location and the brine discharge location. Table 7 outlines the results of the water quality 
test. 

10.5.3 Description of Marine Environment 

10.5.3.1 Marine environment at the feed water intake location 

The feed water intake location was surveyed to assess the status of coral reef and the amount of 
live corals. The feed water intake location is away from the reef and close to the existing groyne. 
The lagoon in this area does not have any live corals and contains dead rock. The area also contains 
rock debris from the breakwater that was constructed during the British occupation. As this area 
does  not  contain  any  live  corals,  during  the  survey,  no  fish  species  were  recorded  within  a  time 
period of 15 minutes, except some gobies and pipefish, that were found at the lagoon bottom.  

10.5.3.2 Marine environment at the brine discharge location 
The  brine  location  was  surveyed  to  assess  the  status  of  coral  reef  and  the  amount  of  live  corals. 
The location is also away from the reef and close to an existing groyne, within the boundary of the 
hotel.  The lagoon in this  area does have only sand  and no live  corals. Efforts to count any fishes 
were not productive as very few species of fish were found, in the range less than 10. Fish species 
identified were 3 gobies and 7 Surgeonfishes.  

   
Page 34 

   
EIA for the setup of RO plant at equator Village, Gan‐Seenu Atoll   

11 Environmental Impacts
11.1 Introduction 

This section covers potential environmental impacts due to proposed setup of a desalination plant 
at Equator Village. The section also describes the mitigation measures for each identified impact. 

Analysis of environmental issues within the lifecycle of the project identifies the major issues and 
concerns that are likely to evolve over the life of a project. For the proposed project, these issues 
include  location  and  design  of  the  plant  house,  constructional  and  operational  impacts  and  the 
positive  economic  benefits.  The  environmental  aspects  of  the  project  would  impact  upon  the 
following resources or elements of the environment. 
ƒ Groundwater – quality and quantity 
ƒ Coral reef areas around the outfall locations – marine biodiversity 
ƒ Marine and coastal water quality 
ƒ Lagoon and beaches – aesthetics 
ƒ Economic benefits 

The potential environmental impacts of various activities pertaining to project components during 
planning and construction phase of the proposed project components and appropriate mitigation 
measures are elaborated in the following sections. 

11.2 Impact Identification 

Impacts  on  the  environment  from  various  activities  of  the  proposed  development  work 
(constructional impacts) and operation of the RO plant (operational impacts) have been identified 
through: 
ƒ A consultative process within the EIA team 
ƒ Existing  literature  on  similar  developments  in  small  island  environments  and  other 
research data specific to the context of the Maldives 
ƒ Baseline environmental conditions described in this report. 

Possible  negative  impacts  on  the  environment  have  been  considered  in  worst‐case  scenario  to 
recommend  mitigation  measures  in  the  best  possible  ways  so  that  these  impacts  would  be 
minimized and perhaps eliminated in both constructional and operational phases.  

Impacts  on  the  environment  were  identified  and  described  according  to  their  location/attribute, 
extent  (magnitude)  and  characteristics  (such  as  short‐term  or  long  term,  direct  or  indirect, 
reversible  or  irreversible)  and  assessed  in  terms  of  their  significance  according  to  the  following 
categories: 

1. Negligible – the impact is too small to be of any significance; 

2. Minor adverse – the impact is undesirable but accepted; 

   
Page 35 

   
EIA for the setup of RO plant at equator Village, Gan‐Seenu Atoll   

3. Moderate  adverse – the impact give rise to some  concern  but is likely  to be  tolerable in 


short‐term  (e.g.  construction  phase)  or  will  require  a  value  judgement  as  to  its 
acceptability; 

4. Major  adverse  –  the  impact  is  large  scale  giving  rise  to  great  concern;  it  should  be 
considered unacceptable and requires significant change or halting of the project. 

Since  it  is  difficult  to  distinguish  between  direct  impacts  (i.e.  resulting  directly  from  a  specific 
activity)  and  indirect  impacts  (i.e.  induced  by  a  series  of  ecological,  social  or  economic  knock  on 
effects and bearing no apparent connection to any specific activity), such distinction has not been 
made. All possible impacts that may be related to project specific activities have been discussed. 

11.3 Identifying Mitigation Measures 

Where  an  impact  identified  can  be  mitigated,  mitigation  measures  are  identified  and  discussed 
along  with  the  identification  of  the  impact.  For  existing  environmental  concerns  or  impacts, 
mitigation measures have been identified. The mitigation measures proposed will help to alleviate 
environmental  problems  before  they  occur.  Mitigation  measures  are  important  because  if 
identified  impacts  are  significant  and/or  important,  it  would  be  necessary  to  identify  and 
implement  mitigation  measures.  Mitigation  measures  are  selected  to  reduce  or  eliminate  the 
severity  of  any  predicted  adverse  environmental  effects  and  improve  the  overall  environmental 
performance  and  acceptability  of  the  project.  Where  mitigation  is  deemed  appropriate,  the 
proponent should strive to act upon effects, in the following order of priority, to: 
1. Eliminate or avoid adverse effects, where reasonably achievable. 
2. Reduce adverse effects to the lowest reasonably achievable level. 
3. Regulate adverse effects to an acceptable level, or to an acceptable time period. 
4. Create  other  beneficial  effects  to  partially  or  fully  substitute  for,  or  counter‐balance, 
adverse effects. 

11.3.1 Mitigation Options 

Possible mitigation options include: 
ƒ Design alterations (e.g., different location for discharge outfalls, etc.) 
ƒ Work method alterations (e.g. changes in construction scheduling) 
ƒ Provision of environmental protection and health and safety equipment (e.g., provision of 
first  aid  or  noise  mufflers,  pollution  abatement  equipment)  –  this  is  not  relevant  for  this 
project. 
ƒ Changes in  management practices  (e.g., contractor’s awareness on environmental issues, 
keeping work areas clean, public awareness). 

   
Page 36 

   
EIA for the setup of RO plant at equator Village, Gan‐Seenu Atoll   

ƒ Changes in operation (e.g. operational procedures, specific responsibilities for clean up and 
maintenance). 

11.4 Existing Environmental Concerns 

11.4.1 Natural Hazard Vulnerability 

The natural vulnerability of Gan Island was found to be moderate for earthquake hazards and low 
for  cyclonic  wind  hazards  and  flooding  disasters  caused  by  high  waves  or  a  tsunami  approaching 
the island from the east. However, the 2004 Indian Ocean Tsunami has been a warning that Indian. 
Gan was not affected during the tsunami of 2004. The proposed location for RO plant is considered 
as the same level as the island and being close to the shore, is not considered to be a risk arising 
from flooding. Therefore, there will be no need for designing mitigation measures for such events.  

11.5 Constructional Impacts 

Construction is often a stage where the environmental impacts are underestimated, but in fact is 
very real and can be damaging. As construction requires lot of processes that typically impact the 
location by bringing about physical modifications, environmental impacts are felt almost in every 
aspect. Very often if these impacts are not mitigated, they may result in more significant long term 
environmental  problems  which  may  be  more  difficult  to  rectify.  The  purpose  of  this  section 
therefore is to summarize the measures that can be undertaken during the construction stage to 
mitigate the impact on environment during the construction stage. These recommendations may 
seem  exhaustive;  nevertheless  they  must  be  followed  if  impacts  are  to  be  mitigated.  In  most 
instances,  these  recommendations  only  require  little  effort  which  only  needs  to  be  considered 
during  construction  stage.  In  this  regard,  the  impact  and  mitigation  measures  recommended 
during the construction stage are summarized below. These measures reflect the general aspects 
of the construction phase that involves both land and marine based activities. 

11.5.1 Civil works 

11.5.1.1 Impacts 

The undertaking of the proposed setup of a RO plant at Equator Vilage involves multiple tasks and 
use  of  machinery  and  other  construction  processes  that  will  have  its  related  impacts  on  the 
environment.  During  the  construction  stage,  environmental  impacts  are  likely  to  occur  as  civil 
works  will  be  undertaken.  This  work  will  result  in  generation  of  noise  and  dust  during  the 
construction stage. It may also induce some sedimentation of the immediate lagoon during laying 
of the intake and outfall pipe of the RO plant. However, sedimentation will not considered to be an 
issue  as  the  plant  is  located  in  close  proximity  to  the  lagoon  and  there  is  very  little  excavation 
required from the pipe to the lagoon intake position. 

The impact from civil works in the construction phase will have the direct short‐term impacts and 
long‐term  impacts  on  the  island’s  terrestrial  and  marine  environment.  These  impacts  will  result 
from the following activities. 
ƒ Excavation and laying of the intake and outfall pipe of the RO plant  

   
Page 37 

   
EIA for the setup of RO plant at equator Village, Gan‐Seenu Atoll   

ƒ Excavation of the ground to construct the plant house. 
ƒ Possibility of sedimentation from excavated soil in case of rain 
ƒ Noise impacts during construction period. 
ƒ Minor  sedimentation  arising  from  the  works  undertaken  in  the  lagoon,  especially  while 
fixing the beach well and laying the intake and outfall pipes. 

Most  of  these  activities  are  considered  to  have  minor  environmental  impacts.  Impacts  of 
constructional noise would be moderate to significant as to the environment as well as the guests. 
The  equator  village  compound  has  high  percentage  of  trees  on  which  bird  species  such  as  Dhon 
Dheeni breed and nest. Hence, during the construction stage, noise could impact the birds if there 
is excessive noise. 

There will be negligible impact on the flora of the island as the location in which the plant house is 
to  propose  to  be  constructed  does  not  have  any  trees.  Excavation  works  to  lay  the  concrete 
footings  of  the  plant  house  building  is  also  considered  to  have  negligible  impacts  on  the 
groundwater  aquifer  and  does  not  require  detailed  analysis.  Intake  and  outfall  pipes  will  be  laid 
above  the  groundwater  table.  Hence,  there  would  be  very  minimal  need  for  dewatering  as  the 
groundwater table is well below 2 meters from the ground level. 

Minor  impacts  will  also  arise  from  sedimentation  of  the  lagoon  during  the  process  of  laying  the 
intake and outfall pipes and fixing  the  beach well on the lagoon. This impact  is considered to be 
minor. 

11.5.1.2 Mitigation Measures 

The following measures to minimize general impacts of construction will help to reduce or mitigate 
the impacts. 
ƒ During  the  construction  stage  all  activities  to  be  properly  supervised  to  ensure  that 
construction is according to the required specification or standards. 
ƒ Appropriate waste handling, transportation and disposal methods for all waste generated 
during the construction works should be implemented to ensure that construction wastes 
do not pollute the environment.  
ƒ Ensure that no leaks and accidental spillages of oil occur from any machinery used in the 
construction stage.  
ƒ Careful control should be exercised to ensure that no materials and machinery fuels enter 
the marine environment and cause contamination. 
ƒ Construction of the intake and outfall pipe should be done with minimal destruction to the 
physical marine environment by minimizing activities like excavation of the sea bed etc.   
ƒ Dewatering, if required to be undertaken as per the dewatering regulation set by MWSA. 

   
Page 38 

   
EIA for the setup of RO plant at equator Village, Gan‐Seenu Atoll   

ƒ Lay  the  pipes  above  the  groundwater  table  and  away  from  any  sewer  lines  as  much  as 
possible, that is inside the Equator Village premises. 

11.5.2 Construction of the plant house 

11.5.2.1 Impacts 
Construction  of  the  plant  house  will  not  have  any  impact  on  the  trees,  as  the  area  is  free  from 
trees. However, during the construction stage, there will be noise impacts from construction work. 

11.5.2.2 Mitigation Measures 

Ensure that noise minimization measures are undertaken such as proper supervision of the work 
and  ensuring  that  only  the  necessary  works  are  undertaken.  Also  construction  area  should  be 
limited to the areas that require construction and a proper perimeter defined. 

11.6 Operational Impacts 

11.6.1 Energy Use and Air Quality 

11.6.1.1 Impacts 

Extra emissions from power plant due to the increase energy use will contribute to CO2 emissions. 
This impact is considered as an indirect impact and minor. In the case of the RO plant in Equator 
Village,  it  is  expected  that  its  operations  would  contribute  very  little  towards  the  national 
emissions of greenhouse gases . 

11.6.1.2 Mitigation measures 

Green  house  gas  emissions  can  be  reduced  by  reducing  or  maintaining  the  operation  to  a 
minimum.  This  can  be  achieved  through  increasing  product  water  storage  capacity,  regular 
monitoring  of  water  demand  to  understand  the  peak  demand  periods  both  during  the  day  and 
during  the  month  among  other  measures.  These  measures  will  become  more  effective  once  the 
operation begins which will provide useful information to enable achieve the mitigation measures.  

11.6.2 Groundwater Quality 

11.6.2.1 Impacts 

With the availability of fresh, clean and safe water, it is likely to ease the demand for groundwater 
for other uses. For example, this project will provide water for the entire hotel, meaning that there 
will be an overall reduction in water demand and hence the burden on the groundwater aquifer of 
GAN  island.  Less  demand  means  less  extraction,  so  although  minor,  there  will  be  an  overall 
reduction of groundwater use and an increase in groundwater quality. 

11.6.2.2 Mitigation 

No mitigation required. 

   
Page 39 

   
EIA for the setup of RO plant at equator Village, Gan‐Seenu Atoll   

11.6.3 Coral Reef and the Marine Environment   

11.6.3.1 Impacts 

The effluent in the waste is a heavily concentrated brine solution. Discharge of brine and chemicals 
from anti‐corrosion, anti‐scaling and anti‐fouling agents that may be used during the operational 
phase of the RO plant may cause adverse impacts on the marine environment such as algal growth 
(Hoepner 1999). After the brine solution is discharged, it has the potential to kill marine organisms. 
Although the brine solution contains natural ingredients of the seawater it may cause damage by 
its unnatural concentration to marine population near the outlet. Another concern is the Chemicals 
from  pre  treatments  and  from  membrane  periodical  cleaning  that  can  harm  the  habitat.  The 
proposed  discharge  location  is  a  surf  zone  with  strong  waves  and  currents.  In  addition,  the 
immediate  marine  environment  is  subjected  to  strong  current  flow  and  a  very  large  water  body 
that  is  unenclosed.  Therefore,  the  discharge  of  concentrated  brine  is  not  expected  to  be  very 
significant. The existing marine environment of the disposal site does not contain any live corals as 
the reef is further north. Hence no damage to live corals will occur. 

11.6.3.2 Mitigation Measures 

Minimizing the chemical use will reduce their concentration and hence will reduce the impact on 
marine environment. Alternatively, the discharge pipe should be ideally close to the reef or in very 
deep water and in an area with strong  currents, so that dilution will take place more effectively. 
Current studies undertaken on the day of the survey reveal that the predominant direction of flow 
is  towards  east  to  west.  Another  mitigation  option  is  to  dilute  the  brine  by  mixing  it  with  grey 
water from the resort before discharge. 

11.6.4 Impact of Rising Marine Water Temperature 

11.6.4.1 Impacts 

The discharged waste has the potential to raise the temperature of coastal waters near the outlet. 
This can have adverse effect on marine life and water quality. In case of Gan, due to the high wave 
action on the northern shore, the temperature of the receiving environment is not expected to rise 
due to the large surface area.  

11.6.5 Positive economic Impacts 

11.6.5.1 Impacts 

Access to ample, safe and adequate water will have several economic benefits to the hotel since; 
the  ground  water  of  GAN  is  considered  to  be  polluted.    Although  rainwater  is  harvested  in  the 
resort, it is not even close to being adequate for the whole resort’s operation. With the project in 
place, the hotel staff and guests will have access to safe and adequate amounts of water. This is a 
direct positive influence to attracting and retaining more customers to the hotel and increases the 
value of the hotel.   

   
Page 40 

   
EIA for the setup of RO plant at equator Village, Gan‐Seenu Atoll   

11.6.5.2 Mitigation Measures 

Not required 

11.6.6 Health Impacts 

11.6.6.1 Impacts 

Safe water is an essential component of public health, whether it is a community or a hotel or a 
resort.  Availability  of  safe  water  means  that  diseases  caused  by  unsafe  water  can  be  reduced 
significantly such as diarrhoeal diseases (if it is used for drinking) and skin diseases. Availability of 
safe  water  in  hotels  will  ensure  that  guests  have  access  to  safe  water.  The  overall  reduction  of 
these  health  risks  will  reduce  the  disease  burden  and  ease  the  health  system  to  function  more 
efficiently. Hence, the project will greatly benefit the well being of the hotel staff and guests. 

11.6.6.2 Mitigation Measures 

Not required 

  

   
Page 41 

   
EIA for the setup of RO plant at equator Village, Gan‐Seenu Atoll   

Table 8: Summary of the Impacts and their Characterization 

Environmental  Nature of impact  Magnitude of impacts  Significance of the impact  Duration of  Reversibility 


Aspect  (negligible/minor /minor  (low/moderate/high)  Impact 
adverse/moderate adverse/major 
adverse/ positive) 

Construction stage impacts 

Civil works  Cumulative  Minor  Low  Short term  Reversible 

Construction of the beachwell  Cumulative  Minor  Low  Short term  Reversible 

Noise and air pollution  Cumulative  Moderate  Moderate   Short term  Reversible 

Generation of construction debris  Cumulative  Minor  Low  Short term  Irreversible 

Operational Impacts 

Energy use and air quality  Cumulative  Minor  Low  Long term  Irreversible 

Increased demand for water  Cumulative  Moderate adverse  Moderate to high  Long term  Irreversible 

Groundwater quality  Cumulative  Minor / Positive  Low to moderate  Long term  Reversible 

Coral reef and the marine environment  Cumulative  Minor  Low   Long term  Reversible 

Rising marine  water temperature  Cumulative  Negligible  Low   Long term  Reversible 

Positive socio‐economic impacts  Cumulative  Positive   High   Long term  Irreversible 

Health impacts  Cumulative  Positive   High   Long term  Irreversible 

  

   
Page 42 

   
EIA for the setup of RO plant at equator Village, Gan‐Seenu Atoll   

12 Stakeholder Consultations

For  the  purpose  of  this  project,  stakeholder  consultations  were  limited  to  the  following 
parties. 

12.1 Consultation with the client 

Consultation was held with the client with regard to the project.  

The summary of the discussions brought forward were: 
• The client has had several discussions with the utilities company in an effort to 
solve this problem. However, although the Utilities company has informed that 
they were planning an island wide water distribution network, it was not clear 
when  the  project  would  be  launched  as  there  were  several  obstacles  and 
administrative procedures to overcome. 
• Water  shortages  and  water  quality  issues  are  almost  a  daily  occurance  and 
complaints from guests are made almost on a daily basis. 
• The  water  is  not  only  smelly,  but  yellowish  in  colour  which  is  proving  to  be 
impossible to deal with.  
• In addition to guest complaints, several tour operators are also intensifying their 
pressure to solve this problem. 
• Water  is  not  only  used  by  guest,  but  also  it  is  a  basic  requirement  for  staff  as 
well. Hence 

12.2 Consultation with Southern Utilities company 

Consultations  were  held  with  the  Utilities  company  with  regard  to  additional  energy 
requirements  for  the  RO  plant.  According  to  the  company,  their  power  capacity  would  be 
sufficient to provide power for the RO plant. 

12.3 Consultations with the hotel staff and management 

Consultations  were  held  with  selected  staff  of  the  hotel  with  regard  to  the  water  issues. 
Following are the issues identified. 
• The hotel’s water is not suitable for human use.  
• Water is smelly and yellowish in colour. 
• There are guest complaints almost on a daily basis. 

   

   
Page 43 

   
EIA for the setup of RO plant at equator Village, Gan‐Seenu Atoll   

12.4 List of Persons Consulted 

Following are the names and designation of persons consulted. 
Name  Designation  Office 

Mr.Aboobakuru Yusuf  Operations  and  guest  Kaimoo  Travels  and  Hotel 


relations manager  services. 
Mr.Wishvalingam  General Manager  Equator Village 
Mr. Marusoom  Dive school instructor  Equator Village 

Ms. Vareesha Mohamed  Receptionist  Equator Village 


Ms. Shamanaz Rasheed  Receptionist  Equator Village 

   
Page 44 

   
EIA for the setup of RO plant at equator Village, Gan‐Seenu Atoll   

13 Alternatives

EIA Regulation requires two alternatives to be suggested for such projects and therefore two 
alternatives  have  been  suggested  in  addition  to  the  no  project  alternative.  These 
alternatives are discussed below: 

13.1 No Project Option 
Table 9: Advantages and disadvantages of the no project option 

Strategy  Advantages  Disadvantages 


Not implement this project  • No  capital  cost  to  the  • Public health problems 
proponent.  related to lack of safe 
• No  maintenance  cost  to  water continues to 
the proponent.  increase for both guests 
and staff. 
• The  land  proposed  for 
the  RO  plant  setup  can  • Risk of diseases for 
be  utilized  for  some  groundwater water 
other  purpose  or  left  as  users. 
empty space.  • Cost the proponent in 
• No  concentrated  brine  terms of initial 
discharge  to  the  investments and ongoing 
environment.  cost. 

• No  need  to  drill  a  • RO plant operation 


borehole,  thus  reduces  requires additional 
the cost.   energy, hence cost of 
operation is high. 
 
 

13.2 Design Alternatives 

13.3 Alternative Locations for the plant house 

There  are  several  alternative  locations  that  can  been  considered.  However,  alternative 
locations for the RO plant was not considered a significant issue as the project takes place in 
the premises of the hotel. No community issues are expected to arise due to the location of 
the  RO  plant.  Water  related  infrastructure  being  a  crucial  component  for  the  hotels 
operation, it is generally believed that the location should be close to the main service areas 
rather  than  close  to  public  and  guest  facilities.  One  alternative  that  is  proposed  is  to  have 
the RO plant in the staff area (see the site plan).  

The  advantage  with  this  alternative  option  is  that  there  would  be  less  disaster  risk  to  the 
water  plant  infrastructure  if  wave  inundation  occurs.  Whereas,  the  disadvantage  with  this 
location is that it will be far away from the guest rooms and other main facilities and also will 
require a longer pipe, both intake and discharge.  

   
Page 45 

   
EIA for the setup of RO plant at equator Village, Gan‐Seenu Atoll   

Another disadvantage with this alternative option is that the water distribution piping to the 
main  guest  facilties  will  have  to  pass  through  the  main  road,  which  means  that  the  road 
surface will have to be excavated to convey the pipes.  

This  would  be  logistically  and  technically  more  challenging  as  any  such  work  will  involve 
considerable paper work and procedural protocols that has to be followed, all of which will 
take  time.  Furthermore,  permits  from  many  authorities  will  have  to  be  sort  in  order  to  do 
this.  Hence,  there  would  be  delays  in  implementing  the  project  and  it  may  extend  to  the 
extent  that  the  long  wait  may  not  even  be  feasible  for  the  project.  The  present  location 
being  close  to  the  seaside  is  also  more  convenient  in  terms  of  its  location  with  respect  to 
guest  facilities  and  will  not  pose  any  difficulties  as  the  plant  house  can  be  constructed 
without  requiring  any  further  permits  or  approval.  Therefore,  the  proposed  location  has 
been chosen for these reasons as the most appropriate.  

13.4 Alternative Method for Feed Water Intake 

Alternative  technology  for  this  project  has  been  considered  for  the  feed  water  intake 
method.  A  suggested  alternative  is  to  drill  a  borehole.  The  advantages  of  the  borehole 
against the existing method are analysed in the following table.  
Feed water intake direct from the lagoon Feed water intake through a borehole.

• The intake pipe method may be • Borehole intake method is more


cheaper than a borehole, but suitable as the borehole will itself be
requires more maintenance as it is located in the premises of the RO
prone to more damage from severe plant compound and hence not
weather as well as from vandalism. exposed making it less prone to
• Feed water intake from the sea damage due to bad weather or
surface is also considered more vandalism.
contaminated than extracting from a • Intake water is clean and less
borehole as there are likely to be contaminated.
more contaminants in open waters • Setting up is expensive, requiring
such as high levels of sedimentation, skilled contractors with knowledge,
debris such as seagrass,garbage experience and properly maintained
etc. machinery and materials.
• Setting up this system is fairly • Due to the specialized nature of the
straightforward and cheap, hence it work, only very limited companies
becomes economically very are available within Maldives who
attractive. can undertake the work, thus the
• Does not require specialized skills cost is very expensive.
and machinery. • Borehole is expensive and normally
boring will be charged per hole. As
this method will require atleast two
holes, one as a backup, the cost
gets doubled.
• In comparison to a feed water intake
from the lagoon, the cost of a
borehole is roughly four times more
expensive.

So what is the best option for this project? In analysing the two methods, a feedwater intake 

   
Page 46 

   
EIA for the setup of RO plant at equator Village, Gan‐Seenu Atoll   

has been opted over a borehole. The main reason behind this is that the proponent has only 
eight(8)  more  years  on  the  lease  agreement  after  which,  the  possibility  of  extending  the 
lease  is  very  unlikely.  The  government  has  already  made  an  agreement  with  a  foreign 
investor  to  lease  the  entire  island  of  GAN  to  be  developed  to  international  standards. 
Therefore, in terms of investment, it is not economically feasible for the proponent to invest 
on a borehole.  

The proponent also understands the disadvantages of a feed water intake system, but even 
after  the  disadvantages  is  compensated  with  the  following,  the  actual  cost  would  still  be 
much less than for a borehole system over a period of 8 years. Some of the methods of how 
the disadvantages will be compensated are: 
ƒ Making  sure  that  the  feed  water  pipe  is  of  high  density  polythene  and  anchoring 
with multiple concrete blocks to prevent it from damage. 
ƒ Construct a beach well which will ensure that the intake water is filtered from debris 
and garbage before drawing water. 
ƒ Invest in sedimentation tanks to store feedwater before it is passed through the RO 
plant.  This  is  an  investment  that  will  have  to  be  made  even  if  the  water  is  drawn 
from a borehole. So it makes sense to go for a feed water intake form the lagoon. 
 
Therefore, considering these issues, a feed water intake pipe is opted for this project.  
 

13.5 Alternative water source 

One  way  to  minimize  the  environmental  footprint  is  to  source  water  from  another  source 
such  as  a  main  water  supply  network  in  Gan.  At  present,  there  is  no  water  supply  in  Gan 
island except the existing groundwater system. Therefore, this option is not practical,  

13.6 Alternative for RO Plant Installation 

Although  the  present  location  for  the  RO  plant  poses  no  flooding  risk,  it  is  suggested  to 
install the RO plant on a raised platform so that the infrastructure will not be affected during 
an event of flooding.  The elevation of the platform has to be higher than the highest levels 
in the island. 

13.7 Preferred Alternative 

The preferred alternative  for this project is  to install the RO plant and all other associated 


infrastructure  on  a  raised  platform  and  have  the  feed  water  intake  from  the  nearshore 
lagoon. 

13.7.1 Mitigation Measures for the Preferred Alternative 

The following mitigation measures are proposed for the preferred alternative. 
1. Ensure that the RO plant and other associated infrastructure is constructed and 
installed on an elevated platform or foundation. 

2. Undertaking appropriate leveling to ensure that the elevation is higher than the 

   
Page 47 

   
EIA for the setup of RO plant at equator Village, Gan‐Seenu Atoll   

highest levels in the island. 

3. Construct the platform/foundation using reinforced concrete to ensure that it can 
support the infrastructure and extra dead loads. 

4. Ensure that the RO plant and other associated infrastructure is well contained and 
protected from rain.  

5. Construct a beach well and have it fixed properly on the lagoon from where the 
water would be drawn. 

6. Lay the intake pipe using HDPE and fix concrete blocks to avoid damage from bad 
weather. 

7. Place the beach well at an adequate depth so that the top of the well is at least half 
a meter from the lowest tide. 

   

   
Page 48 

   
EIA for the setup of RO plant at equator Village, Gan‐Seenu Atoll   

14 Environmental and Social Impact Monitoring


14.1 Introduction 

The environmental monitoring programme given below is for the proposed RO plant setup 
project. The following environmental components will be monitored. 
ƒ Ground  water  quality  of  the  island  (only  limited  to  the  boundary  of  the  hotel)  to 
monitor changes in groundwater quality, 
ƒ Coral reef monitoring for reef health and marine biodiversity around the outfall 
ƒ Socio‐economic aspects of the project 
ƒ Energy consumption of the project. 

The  proposed  monitoring  programme  will  be  undertaken  by  awarding  the  monitoring 
component  to  an  independent  consultant  during  and  after  the  construction  period.  The 
monitoring programme shall continue for a period of at least 1 year in order to understand 
the  impacts  and  benefits  of  the  system.  Annual  monitoring  reports  (summarizing  the 
findings from the annual monitoring) need to be submitted to EPA at the end of each year 
including monitoring records and field inspections during the construction phase. 

It is important that information and experience gained through the monitoring activities are 
fed  back  into  the  EIA  evaluation  and  analysis  system  to  improve  the  quality  of  future 
assessment studies. 

14.2 Cost of Monitoring 

The cost indicated in Table 12 is for monitoring the project during the construction stage and 
per  annum  during  the  operational  stage.  Monitoring  will  be  undertaken  by  subcontracting 
the  work  to  an  independent  consultant  or  a  consulting  firm.  Monitoring  cost  will  be  the 
responsibility of the operator. 

14.3 Aspects of monitoring 

Monitoring will include marine, terrestrial (groundwater) and socio‐economic aspects only. 
Summary  monitoring  reports  will  be  provided  every  three  months  and  final  report  will  be 
provided  at  the  end  of  the  construction  stage  and  will  adhere  to  Schedule  M  of  the  EIA 
Regulations, 2007.  

14.4 Methods of monitoring 

Environmental  monitoring  will  be  undertaken  using  standard  methods  described  in  the 
Methodology section.   

14.5 Monitoring responsibility 

Monitoring responsibility will be with the client and operator and financial provisions will be 

   
Page 49 

   
EIA for the setup of RO plant at equator Village, Gan‐Seenu Atoll   

made in the project to undertake the monitoring.   

14.6 Monitoring Report 

A detailed environmental monitoring report is required to be compiled and submitted to the 
Ministry of Environment / EPA after the construction stage and annually based on the data 
collected for the monitoring the parameters included in the monitoring plan. This report will 
need to be submitted in order to demonstrate compliance.  

The  report  will  include  details  of  the  site,  strategy  of  data  collection  and  analysis,  quality 
control measures, sampling frequency and monitoring analysis and details of methodologies 
and protocols followed.   

   
Page 50 

   
EIA for the setup of RO plant at equator Village, Gan‐Seenu Atoll   

Table 10: Proposed monitoring programme   

Monitoring Attribute  Indicator  Methodology  Monitoring Frequency   Cost during   Cost Per annum  


(construction phase)  (operational phase)  
         Construction  Operational stage       
stage 
Marine environment                   
Marine water quality   Physical  Quantitative  No required  Every four months  No cost  $450.00 
around the brine outfall  appearance,  pH,   Onsite testing 
location  Salinity, Temp & 
Electrical 
Conductivity (EC) 
, TDS 
Percentage of live corals  Percentage live  Qualitative &  No required  Annually  No cost  $450.00 
near the brine  outfall  cover  Quantitative 
(location from which 
baseline survey was 
undertaken) 
Terrestrial Environment                   
Ground water   pH, salinity, E‐ Quantitative  No required  Annually  No cost  $1,500.00 
Conductivity, 
TDS, nitrates and 
phosphorus  
Socio‐economic Environment             
Guest complaints  Increase or  Records from  No required  Annually  No cost  $1,500.00 
decrease in  the resorts main 
guest complaints  office or 
complaint 
registry. 
Information 

   
Page 51 

   
EIA for the setup of RO plant at equator Village, Gan‐Seenu Atoll   

Monitoring Attribute  Indicator  Methodology  Monitoring Frequency   Cost during   Cost Per annum  


(construction phase)  (operational phase)  
         Construction  Operational stage       
stage 
from the tour 
operators. 

General opinion about  Assess the  Survey and  No required  Annually  No cost  $200.00 


water quality and quantity  satisfaction level  interviews with 
from staff  and attitudes of  hotel staff 
the hotel staff 
towards the 
project. 
General attitudes and  Assess the  Survey and  No required  Annually  No cost  $200.00 
responses from repeat  satisfaction level  interviews with 
guests  and attitudes of  repeat guests 
repeat guests 
towards the 
project. 
Energy consumption             
Energy consumption  Increase amount  Records from  No required  Annually  No cost  ‐ 
in energy  the resorts 
spending.  accounts 
department 

   
Page 52 

   
EIA for the setup of RO plant at equator Village, Gan‐Seenu Atoll   

15 Conclusion and Recommendations

It has been assessed that the most significant  negative impacts from the proposed project 
will  be  resulting  from  the  discharge  of  brine  in  to  the  lagoon  and  the  increase  demand  in 
energy consumption. The impact period will be during the operational stage. Proper baseline 
surveys  have  been  undertaken  in  the  marine  environment  where  brine  will  be  discharged. 
The  surveys  indicate  continuous  current  flow  and  wave  action  in  the  northern  shore  side 
where  brine  will  be  discharged.  Presence  of  less  than  3%  live  corals  and  low  fish  diversity 
and  numbers  are  an  indication  that  the  marine  environment  will  not  be  very  significantly 
affected.  Regular  monitoring  has  been  suggested  to  ensure  that  this  receiving  marine 
environment will be regularly in check.  

The project aims to setup a 100 tonne per day water production RO plant and provide water 
to meet the daily needs of the hotel.  In light of this study, the following recommendations 
are made. It is strongly recommended to undertake these measures to improve the project 
output.  

• The location of the RO plant has selected appropriately by choosing an area where 
there  are  no  trees  and  also  in  close  proximity  to  the  seaside.  Although  there  is  o 
significant  risk  of  flooding,  it  is  recommended  to  construct  the  RO  plan  on  an 
elevated platform inside the plant house to avoid the risk of flooding in case there is 
a severe flooding  event. It is suggested to raise the  foundation at least 3 to 4 feet 
higher than the highest tidal levels.  Raising the foundation to this level will not incur 
very high cost. 

• Construct a beach well to make sure that feed water is clean and clear from debris 
and to provide that extra filtering.  

• Operate the RO plant according to the demand, which is by strategically altering the 
operational hours depending on the number of guests in the resort. 

• Install adequate storage tanks to ensure that adequate water is stored to meet the 
demands for at least a week in case if the RO plants breakdown. Increasing storage 
tank will also reduce energy consumption, thereby reducing the carbon foot print. 

• Sound  proofing  the  plant  house  so  that  noise  will  not  be  a  nuisance  for  guests  as 
well as the fauna, especially birds that take refuge in the trees in close proximity.  

Based  on  the  assessment,  it  appears  that  the  project  is  environmentally  and  economically 
justified.  The  project  will  have  several  benefits  to  the  tourism  industry  and  macro  level 
whereas there will be direct micro level benefits to the hotel and the staff. This project will 
be  an  important  milestone  in  reducing  the  health  risk  of  the  end  users,  namely  the  hotel 
guests  and  the  staff.  It  is  the  intention  of  the  proponent  to  start  this  project  as  soon  as 
possible due to the urgency of the need. As the high tourist season is approaching, the hotel 
will experience an influx of guests during the months of December to March, it is important 
that safe and adequate water is available in the hotel.    

   
Page 53 

   
EIA for the setup of RO plant at equator Village, Gan‐Seenu Atoll   

16 Declaration of the consultants

This EIA has been prepared according to the EIA Regulations 2007, issued by the Ministry of 
Environment,  Energy  and  Water.  The  EIA  was  carried  out  by  a  multidisciplinary  consulting 
team  representing  Water  Solutions  Private  Ltd.  In  preparing  this  report,  no  data  has  been 
manipulated. All data has been collected by field visits. 

We  certify  that  the  statements  in  this  Environmental  Impact  Assessment  study  are  true, 
complete and correct.    

Name: Abdul Aleem ( EIA 09/07 ) 

Signature:  

Name: Ahmed Jameel ( EIA 07/07 ) 

Signature:  

   
Page 54 

   
EIA for the setup of RO plant at equator Village, Gan‐Seenu Atoll   

17 References
Beswick  R.  (2000).  Water  Supply  and  Sanitation,  A  Strategy  and  Plan  for  the  Republic  of 
Maldives, Parts 1 & 2, Ministry of Health, Republic of Maldives. 
 
Carpenter,  Clive  (2005),  Water  Resources  Tsunami  Impact  Assessment  and  Sustainable 
Water Recovery, Maldives 
 
English, S., Wilkinson, C. and Baker, V. (1997). Survey Manual for Tropical Marine Resources. 
Australian Institute of Marine Science, Townsville, Australia. 390pp. 
 
Falkland  A.C.  (2000),  Report  on  Groundwater  Investigations,  SDR,  Maldives,  October‐
November  2000,  Regional  Development  Project,  Phase  One,  Ministry  of  Atolls 
Administration,  Ministry  of  Planning  and  National  Development,  financed  by  Asian 
Development Bank. MacAlister Elliott and Partners Ltd, OPT International and BFS Consulting 
Group, December 2000. 
 
Falkland,  A.  (2001),  Report  on  Integrated  Water  Resources  Management  and  Sustainable 
Sanitation for 4 Islands, Maldives, Maldives Water and Sanitation Authority, Maldives

Hoepner,  T  (1999),  A  Procedure  for  Environmental  Impact  Assessment  (EIA)  for  Seawater 
Desalination Plants, Desalination, vol.124, pp. 1‐12. 

MHAHE  (2001),  State  of  the  Environment  Report,  Ministry  of  Home  Affairs,  Housing  and 
Environment, Maldives. 
 
Ministry  of  Atolls  Development  Website:  (accessed  on  the  3rd  September  2008), 
http://www.atolls.gov.mv 
 
Ministry of Environment and Construction (2004), State of the Environment 2004, Maldives 
 
NDC and MWSC (2000), Development of sewerage systems in the Atolls, Ministry of Health, 
Maldives 
 
Roe D, Dalal‐Clayton & Hughes, R (1995)., A Directory of Impact Assessment Guidelines, IIED, 
Russell Press, Nottingham, UK.  
 
Salvat,  B  (1997).  Dredging  in  Coral  Reefs.  In  Human  Impacts  on  Coral  Reefs:  Facts  and 
Recommendations. B. Salvat, ed. Antene Museum . E.P.H.E., French Polynesia.  
 
SoE  (2002)  State  of  the  Environment  Report  2002,  Maldives.  Ministry  of  Home  Affairs, 
Housing and Environment.  
 
SoE  (2004)  State  of  the  Environment  Report  2004,  Maldives.  Ministry  of  Home  Affairs, 
Housing and Environment.   

UNDP  (2007),  Detailed  Island  Risk  Assessment  in  Maldives,  Detailed  Island  Reports:  Gdh. 
Thinadhoo, vol.3, no. 1. 

   
Page 55 

   
EIA for the setup of RO plant at equator Village, Gan‐Seenu Atoll   

18 Annex: EIA Terms of Reference

   
Page 56 

   
EIA for the setup of RO plant at equator Village, Gan‐Seenu Atoll   

19 Annex: Map of Equator Village showing the Project Site


 

   
Page 57 

   
EIA for the setup of RO plant at equator Village, Gan‐Seenu Atoll   

20 Annex: Site Plan of the RO Plant House within the


premises
 

   
Page 58 

   
EIA for the setup of RO plant at equator Village, Gan‐Seenu Atoll   

21 Annex: Photos of the project site.


 

 
Figure 5: Existing groundwater well in the premises 

 
Figure 6: Proposed location of the RO plant  

Figure 7: Existing groyne on the north side along which the intake pipe will be laid. 

   
Page 59 

   
EIA for the setup of RO plant at equator Village, Gan‐Seenu Atoll   

 
Figure 8: The northern side face of the hotel 

 
Figure 9: Coral rubble mound groyne along which the intake pipe will be laid. 

   

   
Page 60 

   
EIA for the setup of RO plant at equator Village, Gan‐Seenu Atoll   

22 Annex: Guidelines for water quality


 

   
Page 61 

   
EIA for the setup of RO plant at equator Village, Gan‐Seenu Atoll   

23 Annex: Commitment from the client to undertake the


Monitoring
   

   
Page 62 

   
EIA for the setup of RO plant at equator Village, Gan‐Seenu Atoll   

24 Annex: Output Water Quality

   
Page 63 

   

Вам также может понравиться