ABC (M) SDN BHD - S2 HEIGHTS

JOINT MEASUREMENT
Part 1 : General Information Ref No : ________________________
Project Name / Project Code : R.E.Wall Date Of Measurement : ____________
Sub-Contractor : CDE Construction Sdn Bhd
Item : Descriptions Unit Quantity
R.E.Wall Area (m ) 2

1 Area A = 0.5 x (5.19 + 1.94) x 14.40 m2 51.34

2 Area B = [0.5 x (6.23 + 5.19) x 4.60]


+ (3.75 x 6.23) m2 49.63

3 Area C = 3.29 x 6.23 m2 20.50

4 Area D = 3.20 x 6.33 m2 20.26

5 Area E = 3.20 x 6.43 m2 20.58

6 Area F = 9.58 x 6.53 m2 62.56

7 Area G = 3.20 x 6.43 m2 20.58

8 Area H = 3.20 x 6.33 m2 20.26

9 Area I = 3.14 x 6.23 m2 19.56

10 Area J = [0.5 x (6.23 + 5.19) x 4.60]


+ (3.75 x 6.23) m2 49.63

11 Area K = 0.5 x (5.19 + 2.68) x 11.20 m2 44.07

Total m2 378.97
Note : Please Attach Relevant Sketches If Necessary
Prepared By : Verified By : Approved :

________________________ ________________________ _______________________


Sub-Contractor Representative : ABC Site Supervisor ABC Site Agent / P.Manager
Name : Name : Name :
Date : Date : Date :
Part 2 : Control Reference ( To Be Completed By Quantity Surveyor )
Site Direction Ref. No : Progress Payment No : Period Ending :

________________________ ________________________ ________________


Remark :
Amount Payable : _________________ Signature : ______________________
( Name : )