Revision: 00
1 of 5
Table of Contents:
Sr. Page
No. Description No.
1 Objective 2
2 Field Application 2
3 Resources 2
4 Procedure 3
5 Quality & Safety Control 3
6 Crane Load Chart 4&5
(1) Objective:
The purpose of this lifting procedure is to describe required resources and procedure
for the erection of cooling tower assembled FRB structure at a designated location.
(3) Resources:
A) Manpower
The workforce planned for this operation would include:
Section Engineer/Supervisor 1
Rigger Foreman 1
HSE Supervisor 1
Riggers 6
2of 5
B) Equipment’s Required
(4) Procedure:
3 of 5
55T Crane Load Chart
4 of 5