MML3 UGC-01 Station Related Works Schedule

I tem I ssue Dwg Ref Target Date


Cuffe Parade
1 Rock Anchors No Drawing
a Scheme received, Final Layout Drawing awaited
b Details of Rock Anchor
2 Strut and Walers No Drawing
Drawing details awaited. As of now we have only typical
a drawing
b Fabrication Drawings - Details of Welds with sizes
c Connection details
d Details of grout packing behind strut
e Pre- loading details
f Location of Load Cells
g Details of RCC walers
h Location of Joints in Struts - Recommended zones
3 Decking
Check Section 2, main beam resting on bolts without LTS- CVG- SCP- 1060- 001-
a bearing. Check. A0
LTS- CVG- SCP- 1060- 001-
b 10mm cheq plate required for spanning 310mm? Check A0
Weld details not available. Main Panel I SMB/Cheq
c connection in particular
d Fabrication Drawings - Details of Welds with sizes
e Drawing for Muck decking
f Anti Skid Paints
LTS- CVG- SCP- 1048- 001-
Plunge Columns
4 A2
a Drawing received not in line with discussions.
Details of Plunge Columns at entrances (except Taj
b Vivanta)
c Details of lacing
d Maximum un- laced length allowed while excavation
e Allowable vertical tolerance
f Finalization - grout details
g Connection of plunge column with top beams
h 225mm pipe is not readily available in market
i Scheme for supporting the 600mm pipe
Vidhan Bhawan
5 Rock Anchors No Drawing
Scheme awaited so that cost comparison can be carried
a out
6 Strut and Walers No Drawing
a Drawing details awaited. Related to above
LTS- CVG- SVB- 2022- 001-
Decking
7 A0, 2023
a Replace Built up sections with Standard Sections
b Fabrication Drawings - Details of Welds with sizes
Weld details not available. Main Panel I SMB/Cheq
c connection in particular
d 10mm cheq plate required for spanning 310mm? Check
MML3 UGC-01 Station Related Works Schedule

I tem I ssue Dwg Ref Target Date


e Feedback on cost comparison sent by Proj ect Team
f Anti Skid Paints
LTS- CVG- SVB- 2015- 001-
Plunge Columns
8 A0
a Drawing may change based on anchor / strut comparison.
b Critical plunge columns in abeyance
c Details of lacing
d Maximum un- laced length allowed while excavation
e Allowable vertical tolerance
f Finalization - grout details
g Connection of plunge column with top beams
h 225mm pipe is not readily available in market
i 300mm pipe cannot be drilled by DTH
Church Gate
9 Rock Anchors No Drawing
Scheme awaited so that cost comparison can be carried
a out
10 Strut and Walers No Drawing
a Drawing details awaited. Related to above
11 Decking
LTS- CVG- AA0- 0032- 001
a Typical panel drawing received. (REV- A0)
b 10mm cheq plate required for spanning 310mm? Check
c Drawing details awaited. Related to above
d Anti Skid Paints
LTS- CVG- SCG- 3020- 001-
Plunge Columns
12 A0
a Details of lacing
b Maximum un- laced length allowed while excavation
c Allowable vertical tolerance
d Finalization - grout details
e Connection of plunge column with top beams
f 225mm pipe is not readily available in market
Hutatma Chowk
13 Rock Anchors No Drawing
Scheme awaited so that cost comparison can be carried
a out
14 Strut and Walers No Drawing
a I nstallation sequence
b Drawing details awaited. Related to above
c Fabrication Drawings - Details of Welds with sizes
d Connection details
e Details of grout packing behind strut
f Pre- loading details
g Location of Load Cells
h Details of RCC walers
i Location of Joints in Struts - Recommended zones
15 Decking
MML3 UGC-01 Station Related Works Schedule

I tem I ssue Dwg Ref Target Date


LTS- CVG- AA0- 0032- 001
a Typical panel drawing received. (REV- A0)
b 10mm cheq plate required for spanning 310mm? Check
c Drawing details awaited. Related to above
d Decking for entrance to the North
Corelation with Strut waler - design to consider chain
e pulley for strut erection
f Detail of Crash Barrier
g Detail of Board Fixing Arrangement
Connection of main beam with secondary beam - on bolts
h without bearing - check
i Anti Skid Paints
LTS- CVG- SHC- 4015- 001-
Plunge Columns
16 A0
a Details of lacing
b Maximum un- laced length allowed while excavation
c Allowable vertical tolerance
d Finalization - grout details
e Connection of plunge column with top beams
f 225mm pipe is not readily available in market
MML3 UGC-01 Station Related Works Schedule

I tem I ssue Dwg Ref Target Date


Cuffe Parade
1 Rock Anchors No Drawing
a Scheme received, Final Layout Drawing awaited
b Details of Rock Anchor
2 Strut and Walers No Drawing
Drawing details awaited. As of now we have only typical
a drawing
b Fabrication Drawings - Details of Welds with sizes
c Connection details
d Details of grout packing behind strut
e Pre- loading details
f Location of Load Cells
g Details of RCC walers
h Location of Joints in Struts - Recommended zones
3 Decking
Check Section 2, main beam resting on bolts without LTS- CVG- SCP- 1060- 001-
a bearing. Check. A0
LTS- CVG- SCP- 1060- 001-
b 10mm cheq plate required for spanning 310mm? Check A0
Weld details not available. Main Panel I SMB/Cheq
c connection in particular
d Fabrication Drawings - Details of Welds with sizes
e Drawing for Muck decking
f Anti Skid Paints
LTS- CVG- SCP- 1048- 001-
Plunge Columns
4 A2
a Drawing received not in line with discussions.
Details of Plunge Columns at entrances (except Taj
b Vivanta)
c Details of lacing
d Maximum un- laced length allowed while excavation
e Allowable vertical tolerance
f Finalization - grout details
g Connection of plunge column with top beams
h 225mm pipe is not readily available in market
i Scheme for supporting the 600mm pipe
Vidhan Bhawan
5 Rock Anchors No Drawing
Scheme awaited so that cost comparison can be carried
a out
6 Strut and Walers No Drawing
a Drawing details awaited. Related to above
LTS- CVG- SVB- 2022- 001-
Decking
7 A0, 2023
a Replace Built up sections with Standard Sections
b Fabrication Drawings - Details of Welds with sizes
Weld details not available. Main Panel I SMB/Cheq
c connection in particular
d 10mm cheq plate required for spanning 310mm? Check
MML3 UGC-01 Station Related Works Schedule

I tem I ssue Dwg Ref Target Date


e Feedback on cost comparison sent by Proj ect Team
f Anti Skid Paints
LTS- CVG- SVB- 2015- 001-
Plunge Columns
8 A0
a Drawing may change based on anchor / strut comparison.
b Critical plunge columns in abeyance
c Details of lacing
d Maximum un- laced length allowed while excavation
e Allowable vertical tolerance
f Finalization - grout details
g Connection of plunge column with top beams
h 225mm pipe is not readily available in market
i 300mm pipe cannot be drilled by DTH
Church Gate
9 Rock Anchors No Drawing
Scheme awaited so that cost comparison can be carried
a out
10 Strut and Walers No Drawing
a Drawing details awaited. Related to above
11 Decking
LTS- CVG- AA0- 0032- 001
a Typical panel drawing received. (REV- A0)
b 10mm cheq plate required for spanning 310mm? Check
c Drawing details awaited. Related to above
d Anti Skid Paints
LTS- CVG- SCG- 3020- 001-
Plunge Columns
12 A0
a Details of lacing
b Maximum un- laced length allowed while excavation
c Allowable vertical tolerance
d Finalization - grout details
e Connection of plunge column with top beams
f 225mm pipe is not readily available in market
Hutatma Chowk
13 Rock Anchors No Drawing
Scheme awaited so that cost comparison can be carried
a out
14 Strut and Walers No Drawing
a I nstallation sequence
b Drawing details awaited. Related to above
c Fabrication Drawings - Details of Welds with sizes
d Connection details
e Details of grout packing behind strut
f Pre- loading details
g Location of Load Cells
h Details of RCC walers
i Location of Joints in Struts - Recommended zones
15 Decking
MML3 UGC-01 Station Related Works Schedule

I tem I ssue Dwg Ref Target Date


LTS- CVG- AA0- 0032- 001
a Typical panel drawing received. (REV- A0)
b 10mm cheq plate required for spanning 310mm? Check
c Drawing details awaited. Related to above
d Decking for entrance to the North
Corelation with Strut waler - design to consider chain
e pulley for strut erection
f Detail of Crash Barrier
g Detail of Board Fixing Arrangement
Connection of main beam with secondary beam - on bolts
h without bearing - check
i Anti Skid Paints
LTS- CVG- SHC- 4015- 001-
Plunge Columns
16 A0
a Details of lacing
b Maximum un- laced length allowed while excavation
c Allowable vertical tolerance
d Finalization - grout details
e Connection of plunge column with top beams
f 225mm pipe is not readily available in market