Вы находитесь на странице: 1из 728

The Organization and

Management of Construction
SHAPING THEORY AND PRACTICE

VOLUME TWO

Managing the Construction


Project and Managing Risk
CIB W65 (in conjunction with W92)

International Symposium for

The Organization and


Management of Construction
SHAPING THEORY AND PRACTICE

VOLUME TWO
Managing the Construction
Project and Managing Risk
Edited by
D.A. Langford and A. Retik
SPONSORED BY

E
glasgow
TheCHARTERED uk city of architecture
INSTITUTE OF + design
BUILDING 1999

GLASGOW

200 YEARS OF CALEDONIAN


USEFUL LEARNING
UNIVERSITY

@ Taylor & Francis


""e" Taylor & Francis Group

LONDON AND NEW YORK


Published by Taylor & Francis
2 Park Square, Milton Park, Abingdon, Oxon, OX14 4RN
270 Madison Ave, New York NY 10016

Transferred to Digital Printing 2009

First edition 1996


© 1996 Taylor & Francis
ISBN 0419222405 (Hbk) 041921030 X (Set)
Apart from any fair dealing for the purposes of research or private study,
or criticism or review, as permitted under the UK Copyright Designs and
Patents Act, 1988, this publication may not be reproduced, stored, or
transmitted, in any form or by any means, without the prior permission
in writing of the publishers, or in the case of reprographic reproduction
only in accordance with the terms of the licences issued by the
Copyright Licensing Agency in the UK, or in accordance with the terms
of licences issued by the appropriate Reproduction Rights Organization
outside the UK. Enquiries concerning reproduction outside the terms
stated here should be sent to the publishers at the London address
printed on this page.
The publisher makes no representation, express or implied, with
regard to the accuracy of the information contained in this book and
cannot accept any legal responsibility or liability for any errors or
omissions that may be made.
A catalogue record for this book is available from the British Library
Publisher's Note
This book has been produced from camera ready copy provided by the
individual contributors in order to make the book available for the
Conference.

The publisher has gone to great lengths to ensure the quality of this reprint
but points out that some imperfections in the original may be apparent.
CONTENTS

Foreword xiii
Introduction to Volume Two xvii

PART I PRODUCTIVITY 1

1 Labour productivity 3

Precast concrete box units - a case study


Bengt Hansson 4

The use of conversion factors for the analysis of concrete


formwork labor productivity
U.E.L. de Souza and H.R. Thomas 14

Development of an explanatory model for concrete formwork


labour productivity
U.E.L. de Souza and H.R. Thomas 27

Overmanning and the effects on labor efficiency


H. Randolph Thomas and Todd M. Arnold 39

Steel framing crew performance and variation


Gary R. Smith and Yu-Bin Lin 49

Analysis of construction delays


T.M. Lewis and B.A. Atherley 60

Client benchmarking of contractor performance


D. Baldry 72

2 Productivity estimates 83

Operative fatigue on the construction site


S. Tennant 84

Determination of an efficient contractor by using the new


method of multicriteria assessment
E. Zavadskas and A. Kaklauskas 94
vi Contents

A new approach to productivity estimation


H. Y. Ersoz and D. W. Halpin 105

The application of value management to the development of


project concepts
R.T. Barton 115

Linear programming for time and cost optimisation


E. Laptali, S. Wild and N.M. Bouchlaghem 124

A financial planning model based on risks for contracting firms


operating in inflationary environments
Elt;in Tas 138

PART II PLANNING AND SCHEDULING 149

1 Project planning 151

Cash flow management and time/cost escalation


Helen Lowe and John Lowe 152

Effectiveness of short-term planning for interface management


of trade contractors
S.J. Allen and A.G.F. Gibb 162

Practical behaviour of managing time-overrun risks in


construction projects
L. Y. Shen and W. K. Cheung 172

Time planning using the Zagreb method


~Petro0c 182

A study on the control of the decision-making process


in building production
Y. Omi and S. Matsumura 198

State space representation of linear projects


v.K. Handa and P. w.M. Tam 212

Raising the efficiency of studies by using the multicriteria


decision-making system
E Zavadskas and A. Kaklauskas 222

Cost growth in public sector buildings


F.H. Giritli 232
Contents vii

2 Construction process planning 235

Just in time applied to repetitive renovation projects


S. To~kanen 236

Planning and progressing project variations - a building


case study
A. T. Baxendale and T.J. Schofield 243

Financial and organizational impacts of project management


Young Hoon Kwak and G. William Ibbs 252

The application of constructability principles in the


Australian construction industry
A.C. Sidwell and V.E. Francis 264

Operational problems facing a sample of construction firms


in Trinidad and Tobago
T. Michael Lewis and Deogratius D. Mugishagwe 273

Integrating site-related activities into the planning and


scheduling of construction projects
Theophilus Adjei-Kumi, Arkady Retik and A viad Shapira 283

Cash flow trends for infrastructural works in residential


developments
S. Singh 293

PART III PROCUREMENT 303

1 Project procurement 305

Level and determinants of imports in Australian high rise


construction
G. Runeson and T. Uher 306

Procurement of a motorway - a case study


Bengt Hansson 316

French building procurement approaches - input to theory


and practice
G.S. Birrell 326

Integrating complexity
I.G. Jennings and R. Kenley 339
vIII Contents

Total resource assessment based on extension of traditional


procurement systems
C. Elliot and A. Palmer 352

The relationship between construction procurement strategies


and construction contract disputes
J. T. Conlin, D.A. Langford and P. Kennedy 360

The provision of infrastructure services in developing countries


W.H.E. Suite 372

Alternative dispute resolution methods in construction -


a Trinidad and Tobago case
W.H.E. Suite 380

Capital works procurement: owner's obligations under the


'tendering contract'
R. W. Craig and P. Davenport 391

2 Partnerlng 403

Long term co-operation between main contractor and its


suppliers in construction
T. Sarkilahti 404

'Constructing the team': a US perspective


V. King 414

The pricing of contract preliminaries: quantity surveyors and


contractors compared
P.A. Bowen, K.A. Hall and P.J. Edwards 424

Client-professional communication during the early stages of


project development
R.N. Gameson 437

Construction dispute minimisation


M.M. Kumaraswamy 447

The case for the integration of the project participants'


activities within a construction project environment
R.A.C. Luck and R. Newcombe 458

Subcontracting - the subcontractor's view


J.D. Matthews, A. Tyler and T. Thorpe 471
Contents Ix

The world according to subcontractors


Z. Sozen and M.A Kayak 481

PART IV PROCUREMENT VALUE MANAGEMENT 489

Value management 491

Management of specialist contractor design for mechanical


and electrical works
G.M. Price and AG.F. Gibb 492

Design quality concept to improve building quality


S.B. Me/hado and V. Agopyan 502

A design tool for incorporating construction knowledge


during design
Bob G. McCullouch 509

The cost of defects in construction


P-E. Josephson and Y. Hammarlund 519

Group decision support for value management


S.D. Green and S.J. Simister 529

International comparison of value management practice


A/bert P.C. Chan, Betty P. V. Ho and C.M. Tam 541

Professional integration in the building design team


A Whyte and H.M. Edge 551

Client management of the design process for buildings


Graham Miller 562

The construction project as a process of innovation


M.F. Dulaimi, A T. Baxendale and D.A Langford 572

PART V HUMAN RESOURCES ISSUES 579

New leadership patterns in construction


J-M. Junnonen 581

The importance of leadership in change initiatives


S. McCabe, J.A Rooke and D. E. Seymour 589
x Contents

The use and abuse of humour in construction management


J.G. Gunning 599

Aspirations, commitment and careers in construction management


P.R. Lansley 609

Intrinsic job satisfaction in construction


R.J. Davies and A. R. Duff 619

Rapid team integration to overcome the construction industry's


fragmentation
C. Gray and M. V. Suchocki 629

Perceived relative importance of training in contractor


development in Nigeria
o.A. Adams 640

The potential for employee involvement in construction


M. W. Coffey 650

Tasks performed by the site manager - a review of the literature


P. Farrell and A. Gale 659

People and projects - building successful combinations


J.E. Rowings, Jr and M.O. Federle 669

The influence of project size on site managers' effectiveness


R. Djebarni 680

PART VI INTERNATIONAL CONSTRUCTION 693

International projects 695

Reactivation of construction projects in Kuwait after the


Gulf War
Sami M. Fereig, Abdul-Hameed Darwish and
Hashim AI-Tabtabai 696

The effect of Saudi national development plans on students'


enrolment in construction-oriented programs in Saudi Arabia
Adel S. Aldosary and Sadi Assaf 704

International consortia in the European construction industry


S. Bonke, E. Campagnac, S. Stanghellini, G. Syben and
G. Winch (Le Groupe Bagnolet) 712
Contents xi

Are there monitoring and controlling systems in infrastructure


projects in Gaza strip?
Adnan Enshassi 722

Comparison of construction safety and risk between USA


and Taiwan
E. Koehn and C-S. Pan 737

A current vision of construction management practices in Chile


A Serpell, J. Crovetto and D. Seymour 747

Establishing quantity surveying as an academic discipline


in China
Ng Wing Fai 757

New challenges from Hong Kong's new airport


J.D. Gilleard and WS. Chong 767

Croatian managers in a changing industry environment


B. Mraovic 778

A framework for evaluating operational effectiveness of design


institutes in China
AM.M. Liu, H.E. Bosen and R.F. Fellows 788

PART VII MANAGING RISK 799

How do government regulations impact residential


construction activity?
D. Corbett, G. Smith and P. Tikalsky 801

Risk management: maintaining programmed construction time


in economies in transition
Mladen Radujkovic 811

Building contractors' risk management of subcontractors


in refurbishment projects
M.I. Okoroh and V.B. Torrance 820

Design management through quality evaluation


Jorge Moriera da Costa and Vitor Abrantes 829

Risk in determining the duration of manually performed


construction activities
A Flasar and S. Vukovic 843
xII Contents

Innovation model in construction


A.I. Sukhorukov 851

Total quality management of construction work: from safety


exclusion to a comprehensive management strategy
J.J. Smallwood and P.O. Rwelamila 859

Addressing construction worker safety in the design phase


J. Gambatese and J. Hinze 871

Beyond ADR - dispute reduction in the construction industry


through realistic contract risk allocation
G.A. Smith 881

Risk management and major construction projects


John Lowe and Tim Whitworth 891

Managing human resource in the Indonesian construction


industry: case study on construction workers' accident
compensation policy
B. W. Soemardi and K.S. Pribadi 900

Index 907
FOREWORD

The Chartered Institute of Building is pleased to be associated once again with


CIB and with Working Commission 65, in supporting this conference and the
'Managing the Construction Project and Managing Risk' session in particular.
Construction is metaphorically and in reality the bedrock of ordered society,
not only in providing the necessary shelter in which to live, but also in
facilitating those elements of life which transcend the mundane. By this I mean
those extensions of life which allow the enjoyment and practice of the arts,
religion, sporting recreation etc.
Once there is a need for construction, irrespective of the level of technology
applied, it is implicit that someone will be required to manage it: to manage the
three key elements of the construction process - materials, labour and money.
Nowadays, there is a fourth element - time - of little or no account to the
cathedral builders of the twelfth and thirteenth centuries but a key issue in
today's dynamic and impatient society.
The Institute in all its various forms during its 160 plus years of existence has
been close to the management function. As the 'Builders Society' in the early
nineteenth century it acted in the interests of the owners of building firms,
mainly in London, to 'uphold and promote reputable standards of building
through friendly intercourse, the useful exchange of information and greater
uniformity and respectability in business'.
When in 1884 it changed its name to the Institute of Builders its principal
objective was 'to promote excellence in the construction of building and just
and honourable practice in the conduct of business'. It goes without saying that
in fulfilling these aims the requirement to manage the project effectively was
paramount.
As an employers' association the Institute's influence waned as the
twentieth century progressed and increaSingly it turned its attention to
developing an educational base for those who were responsible for managing
the project as part of the contractor's team. In 1924 examinations were
introduced for Licentiates comprising papers on Building Construction,
Quantities and Estimating, Book-keeping and Accountancy, and a choice of
subjects, some of a craft character. As yet there was no hint of management as
a separate topic; this was to come in 1927 with the Associate examination
where one subject had the all-embracing title 'Finance, Book-keeping,
Costing and Management'.
From its inception in 1929, until 1947, the Institute in conjunction with the
government's Board of Education administered the scheme for National
Certificates and Diplomas in Building. The Institute's transformation to a
professional institution in which membership was achieved primarily through
examination was now complete.
xlv Foreword

However, it was not until the late 1950s that the Institute, through the Board
of Building Education (BBE), established jointly with the NFBTE in September
1955, began to take action in recognition of the fact that 'in building as in other
industries, attention has hitherto been directed almost entirely towards
technology training and insufficient thought has been devoted to the problems
of recruiting, selecting and formally training individuals for supervisory,
managerial and executive responsibility. As a consequence there is an acute
shortage of men qualified to apply the principles of modern management
techniques to the conduct of building affairs'.
Management Studies for the Buildinq Industry, published by the Institute in
1959 is the seminal work laying the foundations for the modern Institute which
embraces management as its focus.
The syllabus, specified in this report and adopted by the Institute for its
examinations in the 1960s, was in three parts: Law, and Economics of the
Industry in the first year; Management in the second. 'Management' was
tackled both in principle and practice, with the latter having within the
'Production' segment the generic subjects of Construction; Purchasing; Plant
and Vehicles; Work Study; and Statistics and Sampling. It is interesting and
indicative to note that the supporting reading matter for the complete syllabus
was limited to about 30 titles, with only three of these being directed
specifically to construction.
It did not take long for the Institute to develop its own guidance for the
systematic teaching of building management subjects. In 1962, largely under
the direction of John Andrews, the Building Management Notebook saw the
light of day. For many it was the 'bible', with a new edition appearing in 1972 to
meet the demands of yet another change in the structure of examination
syllabuses.
The 1960s were a productive period for the Institute as its membership grew
and its influence extended. Recognition of the significance of management in
a modernizing industry had created a long lead over other qualifying bodies.
Having tackled management in generic terms it then, once again through the
BBE, looked at the needs of the construction site. The report Construction
Management in Building: Present and Future published in 1964 provided a
blueprint for the recruitment and training of site managers. Having identified
the increased demands placed on construction management the book
recommended 'a properly planned programme of education and training for
different levels of responsibility'. Ultimately, this objective was realised by the
creation of the Site Management Education and Training Scheme.
In 1970 a research project was initiated aimed at investigating the potential
for mid-career education and training of site managers. The study involved
widespread consultation and the subsequent development of pilot pro-
grammes, the first course of which was completed in 1972. This and
associated studies led to a proposal for a training scheme based on a series of
modules covering the skills needed in site management, leading successively
to a certificate and diploma. Implementation took place in 1976 with ten
colleges taking part. The scheme has continued to prosper and to fulfil its
Foreword xv

aspirations. Now managed by the Construction Industry Training Board, at 1


January 1996 over 9,000 site managers have participated since the scheme
started.
The Institute's general examinations were restructured in 1984. Although
incorporating some radical concepts the speed of change was such that in less
than a decade a further comprehensive re-evaluation was necessary.
In 1994 the Education Frameworkwas published providing 'the knowledge
and understanding requirements for CIOB membership', and 'defining mini-
mum competencies required of a chartered building professional and setting
standards of attainments to be achieved'.
Within the Framework, management studies commence at 'Formation
Studies' level with an overview of the business environment, including law and
also a study of information and decision making. In 'Core Studies' manage-
ment is further developed and integrated with the process of building
production. Aspects of management are studied within the 'Professional
Studies' level (initially facilities management; commercial management;
project management; and construction management). 'Project Evaluation and
Development' uses the vehicle of project· management for learning and
assessment.
Even now there are further developments in the pipeline.
The need for improved management standards is being addressed by
supplementing the strategic management skills for directors of building firms
and by preparing those who work in contracting for the challenge of single
point responsibility. For both cases a substantive training programme has
been developed.
Designed to establish the UK as a world class centre for the teaching of
construction management, the Discipline Network in Building Management
was launched in 1995 with the support of the Department for Education and
Employment. Its aim is to promote techniques and practices that will improve
the standard of building education and tailor it more closely to the needs of
industry. By sharing best practice, senior teaching staff in construction
management have created an environment which cannot but improve the
quality of teaching and thereby enhance the management capability of
construction students. This programme is ongoing.
What then of research and construction management?
Inevitably, the Institute's involvement with research pales in comparison
with its track record in educational terms. Research into construction
management issues is a relatively recent phenomena: W65's first international
conference was as recent as 1976. Sponsoring the fifth conference in 1987
was an act of faith by the Institute and one which committed it to an acceptance
of the essential nature of construction management research. This investment
is now beginning to pay dividends!
Over the past three years the Institute's Innovation and Research Commit-
tee has looked long and hard at how the Institute should interface with
research. The result has been remarkable in its prescience!
Many of the proposals contained within the innovation and research
xvi Foreword

strategy for the Institute have anticipated their adoption by the industry itself.
Perhaps the most important, all-embracing objective is the desire to change
the way in which the industry regards research and innovation, for by doing so
it is believed that competitiveness and business efficiency can be substantially
improved.
The other key tasks addressed in the strategy relate to education -
incidentally in the Building Management Notebook referred to earlier it is
suggested that a one hour lecture should be adequate to cover research and
development - communications, priorities and international. The latter antici-
pates to a large degree a closer relationship with CIB and its Working
Commissions.
Much of the credit for the Institute's strategy must go to Dr Peter Morris, the
Committee's Chair and the keynote speaker for the 'Managing the Construc-
tion Project and Managing Risk' session.
I have attempted in preparing this contribution to highlight the CIOB's
involvement with, and support of, construction management. It is fitting to
conclude with the Institute's vision contained in Meeting the Challenge - a ten
year strategy for growth which was published in February of last year.
'Our vision is that, by the year 2005, the CIOB will be fully recognised as the
leading professional body for management in construction, thereby serving
society, the industry and its clients world-wide; and our members will be the
established leaders of the construction team.'
Peter Harlow
Innovation and Research Manager
Chartered Institute of Building
Ascot, Berkshire
April 1996
INTRODUCTION TO VOLUME TWO

Managing the Construction Project and Managing Risk is produced in


conjunction with the Chartered Institute of Building and the CIB W92 on
Procurement. This volume is the largest of the three and is the most wide
ranging. It contains seven sub-themes and ten sets. These are:
Sub-themes Sets
• Productivity Labour productivity
Productivity estimates
• Planning and scheduling Project planning
Construction process planning
• Procurement Project procurement
Partnering
• Procurement value management Value management
• Human resources issues [Organizational behaviour]
• International construction International projects
• Managing risk [Risk management and allocation]
The productivity sub-theme brings together research into the effective ways
of estimating likely productivity in the pre-construction stage and then goes on
to evaluate how productivity may be best measured when work is taking place
on site. The planning and scheduling theme reports research findings in the
areas of short-term planning and decision making around construction plans.
The second set of papers integrates this planning with other elements of
project control such as materials or money.
The procurement and procurement-value managernent sUb-theme is in the
province of W92 and papers have been presented in the popular area of
procurement routes, partnering and the application of value management and
value engineering techniques to construction.
Research into human resource issues, fundamental to successful project
management, is represented and work on leadership, team building training
and worker participation is presented.
The growing globalization and internationalization of construction projects is
recognized in the sub-theme bringing together the international project
experience and case studics of major projects in regions as diverse as the Gulf
states, Europe, India, South America and China demonstrate the true
international character of research reported under CIB W6S.
Finally, the risks that firms take in undertaking research is presented.
Managing risks is an increasingly demanding part of managing the enterprise
and issues of safety, risk allocation in projects and risks arising from regula-
tions imposed by outside agencies have all come within the purview of senior
management. Research in this important area is presented in this volume.
xviii Introduction

The structure of the volumes

To organize the range of topics covered by the W65 Commission the papers
have been structured into three volumes. Each volume focuses upon a
particular theme. These themes are:
• Managing the Construction Enterprise
• Managing the Project
• Managing Information
Within each theme there are sub-themes which collect together papers around
a specialist area of interest and then within each sub-theme there is a further
selection to collect together papers on similar topics.
This approach is intended to assist the reader in identifying and consolidat-
ing areas of special interest and to link together subjects appearing in each
volume.

Maintaining standards

In line with the growing confidence and maturity of the discipline, the papers
contained within the volumes have been subjected to exacting standards of
refereeing. Of the 241 abstracts received, 183 were selected for development
into full papers. All of the full papers received were then refereed and authors
invited to incorporate the referees' comments into their papers. At the time of
sending the material to the publishers 161 papers had been accepted. The
standards achieved ensure that the papers presented in the volumes are of a
standard expected in refereed journal articles.

Acknowledgments

We would like to record our special thanks to members of the organizing


committee, the scientific committee and the conference organizers, Meeting
Makers, especially Susan Miller and Elaine Bone. Particular thanks are due to
Edith Henry of E & FN Spon for the painstaking attention to the detail
associated with presenting the papers for the 8th International Symposium of
the W65 Commission on Organization and Management of Construction.
Dave Langford
Arkady Retik
Glasgow, June 1996
Part I
Productivity
1 Labour productivity
PRECAST CONCRETE BOX UNITS - A
CASE STUDY
Bengt Hansson
Department of Construction Management, Lund University,
Lund, Sweden

Abstract
The cost of building new housing rose substantially during the eighties, which
resulted in high living costs despite substantial subsidies. A decision was taken to
reduce housing subsidies. This, together with a number of other factors has brought a
reduction in the demand for new dwellings. This has motivated substantial efforts to
develop building techniques so that the costs of housing can be reduced in newly
produced dwellings to a level which the consumer can accept. The reductions in costs
which are required are of such an extent that a completely new approach is required.
A company in Ljusdal, Sweden, has developed a form of construction using
factory-made precast concrete box units and carried out the first large project. The
aim of the chosen method is to reduce costs by improving quality, rationalizing
production, more efficient purchasing and shortening the construction time.
An evaluation and production economic analysis of the construction techniques
developed has been carried out. The evaluation shows good prospects for reducing
the costs of housing by means of precast box unit construction. Further development
work is required, particularly with respect to production techniques at the factory and
the design of construction parts which are to be connected to the precast box units.
Keywords: Precast concret, box units.

Sommaire
Les coats, pour la construction d'irnmeubles, ont augments sensiblement durant les
annees -80, ce qui a donne des coUts d'habitation plus important malgre des subven-
tions interessantes. Des decisions visant II baisser ces subventions, ont ete prises.
Ceci, ainsi que d'autres raisons ont conuit II une baisse de la demande d'habitation
nouvelle. Cela motive de grands efforts pour developper la construction et ainsi creer
des habitations nouvelles II des niveaux de coats acceptables pour les clients. Les
reductions necessaires sont II ce point etendues qu'iJ faudrait de nouvelles idees pour
attaquer Ie probleme sur tous les cotes techniques.
Un groupe d'entrprises II Ljusdal, Suede, a developpe un systeme d'element de
volume prefabrique en beton, et ainsi a deja realise un premier grand projet. Le but de
cette methode est de baisser les coilts, par une meillure qualite, une production ratio-
nalisee, des achat plus efficaces et une duree de travaux plus courte.
Une evaluation et une analyse d'economie de la production de cette technique a ete
realise. Cette evaluation demontre les bonnes possibiliees de baisser les coOts
d'habitations par une construction avec des elements prefabriques.Il est necessaire de
continuer II travailler sur Ie developpement, particulierement sur les techniques de
production dans les usines ainsi que sur la conception de pieces de la construction qui
vont relier les elements prefabriquees.

1 Introduction
1.1 Background and the project aim
The initiators of this development project, for which precast box units are used to
reduce construction costs, analysed 1990 costs for the project carried out and came to
the conclusion that there was a possibility of reducing construction costs by more
than 20%. They believed that this could be done by reducing the construction time on

The Organization and Management of Construction: Shaping theory and practice (Volume Two).
Edited by D.A. Langford and A. Retik. Published in 1996 by E & FN Span. ISBN 0 419 22240 5.
Precast concrete box units 5

site and with a high degree of prefabrication. This opinion was supported by others
during the general debate.
In brief, the project concept was that by producing precast concrete box units in a
factory, it would be possible to reduce the building costs to a competitive level. Pro-
duction could be made more efficient as a result of factory production, which would
not be affected by weather conditions and would also facilitate a high level of quali-
ty.The precast box units will be heat insulated and finish constructed at the factory.
The foundations consist of spot footings and beams which require minimal ground
work at an early stage. The greater part of the ground work is intended to be done
after the building is complete. The precast box units are primarily intended for
offices, hotels, detached houses and multiple-unit dwellings.
The overall aim of the development project is to further develop the sketched
production method of factory manufactured precast box units and to test it in a larger
project.
The economic evaluation of production, which is briefly presented in this paper,
should, among other things, answer the question whether building costs can be re-
duced by 20% with this method of production and, if so, in which way thesereduc-
tions in costs are accomplished compaired to a traditional production.

1.2 Expected advanges and disadvanges with


The new production method is expected to provide the following advantages:
• Industrial production (higher efficiency and cheaper workforce). Since the precast
box units are manufactured with industrial methods, the production can, to a large
extent, be rationalized. Machinery can be used rationally when casting and working
on the concrete units.
• Independent of the weather
The production takes place in a factory, independent of climatic conditions outside.
As a result, the working environment is more favourable than when working out
doors.
• Shorter construction time.
Work on site is restricted to foundations, erection and groundwork.
• It is anticipated that costs will be approximately 20% lower totally than with
traditional construction.
• Quick building start since simplified design can be applied.
• High technical quality
A mixing plant is built adjacent to the unit production where production of concrete
can be checked and controlled to ensure a constant level of concrete quality is
obtained.
Among the expected disadvantages which the developers hoped to be able to
remove or reduce the significance of, were the following:
• Transport costs for precast box units are added
• Costs for the factory are added
• Modules restrict the freedom of the architect
• Normal resistance of interested parties in the construction process to new-fangled
ideas
• Larger volumes are required (in the long run, the production volume must exceed
the point for the critical volume). Precast box unit production is profitable with
large series and with few different types of unit, but this easily leads to choice
being limited for architects and proprietors.

1.3 Realization of the development project


The development work has been carried out in the following stages:
A. First the various production methods have been studied in order to be able to
undertake the production of the precast box units in the short and long term. It was
6 Hansson

then found that the most important operations are those of handling and transporting
the precast box units, since the loading during transport is probably dimensioned.
B. The precast box units are designed.
C. Some precast box units are produced and test handled.
D. The precast box units are re-designed.
E. The precast box units for a student accommodation are produced as a pilot
project under accurate evaluation and a well developed quality assurance system.
F. The student accommodation is erected under strict control and follow-up.
G. The experiences of those who took part and those who evaluated the project
have been compiled with the aim of providing basic data for future production.

2. The full-scale pilot project

2.1 General
In the early developed solution, the structure was to consist of concrete columns and
beams on which the precast boxes would be positioned. The load-bearing beams,
which were intended to be installed at each level in order to prevent underlying mod-
ules from being loaded, could be omitted. During the development work it was
shown that a system of columns and beams was not necessary since the units could
be stacked on one another. It should be possible to construct the foundations with a
simple system of spot footings on which a columnlbeam system would be laid as
support for the precast box units. With the aim of keeping the weight of the concrete
to a minimum, high performance concrete was to be used in the precast box units.

2.2 The precast box unit and other units


The project concept of the development group was that everything which was built
would, as far as possible, consist of units, normally concrete units. In addition to the
precast concrete box units which formed the most important component in thebuild-
ing system, many other concrete units were to be found in the pilot project.
The foundation was formed with prefabricated spot footings. Edge beams were
placed around the bottom floor structure. These consisted of a skirting, support for a
steel floor and shoulders of laminated wood which was to transfer the loads down-
ward through the insulated layer. Inside the edge beams under the house, concrete
flange beams were positioned which formed the support for the steel floor. For the
lift pit a completely finished lift pit was supplied.
The rectangular floor structure units are used as floor structures outside the precast
box units at corridors, public areas and stair enclosures. At the ends of the building
the precast box units must have a facade and heat insulation added which is also done
with the aid of traditional concrete units. Outer walls for the areas which are not built
with precast box units are formed from traditional prefabricated sandwich units.
The shape of the precast box units chosen by the development group can be varied
within certain limits. By setting in an intermediate floor structure, installations could
be located there and easily drawn to the ceiling over an access balcony or corridor. In
Fig. 1. is the plan for the module and the precast box for the student accommodation
projec and i Fig. 2. one plan of of the student accommodation for which the produc-
tion method was utilized commercially for the first time.
The precast box size is determined mainly by the precast boxes having to be
transported by trailer on public highways. In practice this sets the maximum
permitted width, without an escort car, at 3.1 m. With an escort car a dispensation can
be obtained for up to 4.2 m. For the loading and moving of the precast box unit
modules a truck which can take a load of 30 tons is required.
Precast concrete box units 7

4.4 m (5.4 m resp.)

~~~====~====~==~==~==~x

STUDENT ROOM

I
Figure 1. Plan of a student room, the student accommodation, Ljusdal. Drawing
made by Ljustech AB, Ljusd.~..

Figure 2. Ground floor plan, The student accommodation, Ljusdal. Drawing by


Ljustech AB, Ljusdal.
8 Hansson

2.51 Design of student accommodation

In Fig. 3. is a picture of the entrance-facade and Fig. 4. a section of the same build-
ing. The student accommodation contains 78 student rooms and approximately 90
room modules. In the student accommodation there are leisure, laundry, storage and
service areas for the property.

Figure 3. Facade, Hammaren student accommodation, Ljusdal.

Eaves structure formed from


prefabricated concrete units

Precast box units formed as comp-


letely ready-to-use prefabricated
modules for student rooms and
kitchens.

Rectangular floor structure units


used as a floor structure outside of
the precast boxes at corridors,
communal areas and stair
enclosures.

Foundations were formed with prefabricated spot footings. Edge beams


were positioned around the bottom floor structure. These consisted of a
skirting, support for a steel floor and shoulders of laminated wood which
were to transfer the loads downward through the insulated layer. Concrete
flange beams were positioned inside the edge beams under the building to
form the support for the steel floor.

Figure 4. Section with comments regarding the formation of the Hammaren student
accommodation, Ljusdal,
Precast concrete box units 9

The student module is normally 4.4 m long and 5.4 m for the handicapped adapted
module. Each student module contains a toilet and shower, plus a refri- gerator. The
student modules are grouped around a corridor with a communal kitchen and
assembly areas.

3. Factory production
The precast box unit system transfers the traditional construction from the site's
craftsmanship-oriented production to an industrial operation. The way to solve tasks
and problems that arise is more in line with that applied in engineering industry.
From a material flow point of view the production of precast box units can be
adapted to the modern just-in-time philosophy.

To begin with, it should be pointed out that the forming of the factory and the
production system should be seen as a small part of the overall concept to be tested.
There was not enough capital available within the framework of this project to
completely develop and analyze the production apparatus.
The flow contains the following production operations or production stations, see
Fig. 5. In the same figure the time required to carry out each respective operation has
been given for a precast box with fittings the equivatent of those in the student
module. Precast box units with many installations can take longer time. The total
throughput time is, with dif-ferent installations and taking into account the drying
time before and after painting, 12-14 working days.
This method of production, with casting of the walls and roof simultaneously,
proved to form a restriction on versatility. Variations in size namely meant an
expensive rebuilding of the tunnel form. In future production a casting method will
probably be chosen which will involve the casting of the flat concrete units with cast-
in steel plates which are welded together.
The material flow of concrete has been adapted to the just-in-time philosophy by
the concrete being produced in line with the demand. Consequently instead of
reducing transport costs for the concrete trucks by linking several smaller concrete
castings together, as soon as a form and the reinforcement were ready on each little
stage they were cast and this was also done even if the batch cast was relatively
small. The quantities in each individual batch could be adapted exactly to the amount
required when casting. If the concrete was transported by truck it would have been
necessary to have a little extra in the truck.

Production stations Time consumed


Concrete unit 3 days
Installation+floor+bathroom I day
Painting I day
Electrical installation 0,5 day
Fittings I day
Incasing in plastic+ transport to store 0,5 day

Total 7 days

Figure 5. Appropriate production stations and approximate time consumed when


producing precast concrete box units.
10 Hansson

4. Transport and building site erection

The cost of the precast boxes forms the dominant cost in the procuction with box
units. Two operations in the precast box unit concept are most important:
• The precast box units must, for economic reasons, be able to be mounted in position
immediately after factory production.
• The connection work following precast box unit erection must be carried out
quickly for both technical and financial reasons.
The prefabricated concrete units place special demands on the transport system
because of their size (for example with a maximum width of 3.8 m here compared
with a normally permitted 2.6 m on Swedish roads) The precast boxes coped with the
static and dynamic stresses during transporting without any mentionable problems.
The weight is 10-30 tons depending upon size.
During the concrete casting work the precast box is transported on its form and
supports which are used for casting concrete, and after that on a carriage equipped
with jacks with the help of which the precast box unit can be placed on trestles.,
The units are transported to the building site on a trailer. The carriage could take
two precast box units per trailer, Fig 6.

Figure 6. The units were transported between the factory and the building site on a
trailer drawn by a lorry.

5. Analysis of the consequences with respect of time

5.1 Evaluation method and analysis prerequisites


A comparative analysis method was chosen for the evaluation. This compares
construction with the precast box unit technique with traditional construction. By
traditional construction is meant here the anticipated production which a local builder
would have carried out for the building project in 1993. Based on conversations with
a local builder and a study made by The Swedish Precast Concrete Society of 12 resi-
dential blocks produced with the site casting technique, the hypothetical traditional
production of the student accommodation can briefly be described as:
• A concrete structure cast on site using a tunnel or angle form .
• The construction time was estimated as being one year .
• The facades would be made of precast concrete units.
Based on this brief description and one application, the student accommodation, an
evaluation of the precast box unit concept was made.
Precast concrete box units 11

5.2 Precast box unit versus traditional construction


For the student accommodation which was constructed, it was decided to mix precast
box units and traditional concrete units which meant that the project was not a pure
precast box unit project. Corridors and common areas were constructed using
traditional concrete units but, since this production operation involved considerable
disruption, the student accommodation did not sufficiently reflect the characteristic
differences between traditional production and precast box unit production. The
differences between traditional production and construction using precast box units is
in principal illustrated in Fig. 7. This figure clearly show that a delay in the following
work has substantial financial consequences since a large part of the resources have
been consumed.

100%

Precast concrete
box units

On site construction

Designing

Time

Figure 7. Principal figur showing use of resources during the time for production
with precast concrete box units and on traditional site construction respectively (here
showing a production of an hotel consisting of 40 room with a total time of 33 weeks
if on site production is chosen and 16 weeks for the alternative box units.

6 Quality assurance
A fundamental concept in the development project was that the production was
mainly to be carried out at a factory. As a result the quality required would be
ensured and the number of faults minimized. Factory production is also an important
prerequisite for being able, for example, to cast with high performance concrete.
For the production a quality plan was drawn up for production at a factory and
building site which was adapted to ISO 9001. The quality work at the factory and
building site was coordinated. Consultation meetings and self-inspection led to
continual improvement of the production.
An important hypothesis for the development group was, against the background of
the production method chosen, that the occurrence of faults on the work site should
be fewer than for traditional production. A survey of the examination report after the
final examination shows few faults internally in the room modules but a lot of dam-
age to the door frames and similar. Furthermore the survey shows that the total num-
ber of faults was no less than for a randomly chosen examination of a housing pro-
ject, which the same inspector carried out at approximately the same time as the
examination of this student accommodation. Types of fault noted in the report from
12 Hansson

the final examination are different for precast box unit production and traditional
production. Few faults occurred on the building site in the room modules. Those
which occurred were mainly due to faults in sealing in plastic during the construction
period. Quality assurance within the manufacturing had functioned well and the room
modules had left the production with few faults.

7. Economic consequences conclusions


A financial comparison of the project realized, the Hammaren student accommoda-
tion, has been carried out relative to traditional production. The result of the compari-
son is presented in Fig. 8. The distribution of costs of various elements of cost for
precast box unit production and the necessary revision to the traditional option (also
given in SEK per m2) were made at 1994 cost levels.
The value added tax, 25%, has been calculated on all costs except for the ground
and other proprietor's costs.
From the previous section the following summary can be made:
• Working time consumption increases by more than 34% with traditional produc-
tion instead of precast box unit production. Other work is not affected measurably by
the change of production techniques.
• Capital costs are halved and a reduction in the order of just over 3% of the
production costs is obtained.
• A delay after the precast box units are produced involves large capital costs since a
large part of the resources have then been invested in the project.
• The prerequisites for the right quality increase when there is precast box unit
production but the financial differences could not be shown in the project.
• Site costs increase by approximately 19% with traditional production.
Against the background of this summary and previously accounted experience, an
Nature of expenses IPrecast box unit ISite built I
production SEK SEK
ISEK 11m2 SEK 11m2 %
Materials
In precast box units 3098506 1299 3315401 1390
Other materials 2661726 1116 2661726 1116
Building workers' wages
In precast boxes 829188 348 1111112 466
Other wages 1 941 600 814 1 941 600 814
Sub-contractors
In precast boxes 2812980 1 179 3 198358 1341
Other sub-contractors 2291000 961 2291000 961
Site costs 1570000 658 1870000 784
Design and plannin& 1280000 537 1280000 537
ConstrutlOn and desIgn 15205000 6375 16389 198 6872 7,8
Municipal fees 1000 1000
Land & other proprietor costs 800 800
Value Added Tax 1844 1968
Credit costs 283 678
Total production cost 10 302 11 318 9,9

Interest rate 12,0%


Dwelling area 2385 m2

Figure 8. The cost for production using precast box unit and traditional on site built
respectively.
Precast concrete box units 13

assessment and calculation can be made of the total effects in the case of traditional
construction being carried out. The actual results of the municipal fees have not been
studied here.

8 Conclusions and experiences .


Even if only one project is realized, certain generalizable conclusions can be drawn.
-The total working time will be shorter
During the undertaking of the project the time taken to cast the precast concrete box
units was followed-up. This follow-up suggested that the time taken by the workers
would have been substantially longer with traditional construction.
-Shorter construction time than for traditionel building
Building with the precast box unit technique in the case gave a shortening of the
construction time of 56 % compaired with traditional construction. A shortening of
the building time can of course be achieved in another way but this was not studied
here. A generalizable experience of the project is that with the precast box unit
technique the construction time can be halved in relation to traditional production.
- Site costs reduced
The time-dependent site costs reduce when the construction time reduces. Conse-
quences of production disruptions at a late stage are significant. With this project it
was established that disruptions at the final stage of precast box unit production can
have significant financial and technical consequences. It is particularly important to
ensure that the operations following the precast box unit erection function as planned.
-Building costs are reduced
Building costs can be reduced and cost reductions as a percentage are largest for
site costs, credit costs and wage costs.
-Precast box unit construction relative to the rationalization measures
From this project no conclusions can be drawn as to whether precast box unit con-
struction is better or worse than other measures which can be taken to reduce con-
struction costs. Shorter construction time in itself gives the same cost reducing effects
as the precast box unit technique. However, studying other measures lies outside the
confines of this work. This first trial, with precast concrete box units, has shown that
technically the production is achievable and that the method has large potential possi-
bilities for cost-reduction relative to traditional production methods.
The biggest problem with this building concept is that there must be continual
production for a project, i.e. there must be a demand which keeps the factory going.
With reference to the rate of erection of approximately 10 precast boxes/day, the
factory should achieve approximately the same production so that it is not forced to
build up a stock before the start of each erection of units. This gives a need in the
order of 1000-2000 units. This means that the manufacturer must take a substantial
share of the construction market.
-Develop the production technique at the factory
The production technique can, and needs to be, developed at the factory. Manufac-
turing concrete slabs which are assembled together (welded) to form precast boxes
can make it possible to produce the approximately 10 precast boxes/day which is nec-
essary to keep the rate of work at the factory in line with the erection. Essential if
stocks are to be avoided.

8 References
Hansson B (1995) Precast concrete box units -production analysis, Department of
construction management, Lund University, Lund, Sweden.
THE USE OF CONVERSION FACTORS
FOR THE ANALYSIS OF CONCRETE
FORMWORK LABOR PRODUCTIVITY
U.E.L. de Souza
Department of Civil Construction, University of Sao Paulo,
Sao Paulo, Brazil
H.R. Thomas
Deparment of Civil Engineering, Pennsylvania State University,
University Park, Pennsylvania, USA

Abstract
Labor productivity management is important to the success of a project. The
concrete formwork operation is a labor intensive task ([1], [2], [3]) which influences
substantially the total cost of construction ([1], [2], [4], [5]).
Traditional cost systems follow a time consuming routine that includes: the break
of the work in pieces (items); the measurement of the amount done and the
workhours spent for every item. In doing so, several times one commits mistakes in
assigning workhours to each item. The "conversion factors" (CF) are used to avoid
this problem and to create an easier way to measure productivity. They estimate how
much easier (or more difficult) different formwork situations may be, identifying the
relation between the effort (expressed as workhours) necessary to accomplish one unit
of a certain item and the effort necessary to accomplish one unit of a standard item.
This paper presents the calculation of CF related to form work for walls and
columns. The following steps were followed: collection of productivity rates for
cases presenting different factors affecting the performance, from American
estimating manuals; choice of the most important factors in explaining productivity
variation; definition of a standard item for formwork (steel framed plywood panels
for walls until 8 feet height); definition of equations to estimate the CF for any non-
standard item of form work.
Since the CF has been calculated, one may transform quantities of any item in
equivalent quantities of the standard item. And then, measuring only the hours spent
on the work as a whole (the formwork in this case), its productivity can be
evaluated.
Keywords: construction management, conversion factors, labor productivity, work
measurement.

The Organization and Management of Construction: Shaping theory and practice (Volume Two).
Edited by D.A. Langford and A. Retik. Published in 1996 by E & FN Spon. ISBN 0419222405.
Conversion factors for analysis 15

Sommaire
La gestion de la productivite est cruciale dans Ie succes d'un projet La
realisation de coffrages est tres couteuse en temps et en hommes ([1], [2], [3]),
et pese en consequence sur la globalite des couts des travaux ([1], [2], [4], [5]).
Traditionnellement, les systemes de couts observent des procedures
particulierement chronophages dont Ie detail du travail en items et Ie calcul
du travail et du temps fournis par item. TI n'est pas rare, au cours de ces
operations, de faire des erreurs d'attribution des heures/hommes par item.
Pour circonvenir ce probleme et creer un instrument de mesure de la
productivite plus facile a manier, on a recours aux "facteurs de conversion"
(CF). TIs evaluent Ie degre de difficuIte de la realisation du coffrage en
etablissant Ie lien entre l'effort necessaire (en heures/hommes) a la realisation
d'une unite d'un item particulier et l'effort necessaire a la realisation d'une
unite d'un item standard.
Ce papier presente les calculs de CF propres au coffrage des murs et
des colonnes. Les etapes en ont ete : recueil, dans des manuels d'evaluation
americains, des taux de productivite pour des cas presentant des facteurs de
natures diverses influenc;ant les performances, definition d'un item standard
pour Ie coffrage (panneaux de contreplaque a cadre acier pour des murs
allant jusqu'a 2m de hauteur), definition d'equations permettant d'estimer les
CF pour tout item non-standard.
Sur la base des CF calcules, on peut alors se permettre de convertir les
quantites propres a n'importe quel item en quantites equivalentes de l'item
standard. Et ainsi, par Ie calcul des heures fournies pour la realisation
globale du coffrage (pour Ie cas qui nous interesse ici), sa productivite peut
etre estimee.
16 de Souza and Thomas

1 Introduction

For the purposes of this paper, productivity is measured by means of the unit rate,
that is defined [6] as the relation between the inputs (workhours) and the outputs
(amount of work done) of ajob. The inputs are measured in workhours (wh) and the
outputs in square feet (st).
The effort to complete 1 sf of form work may vary according to several features
like: the system used; type of element (column or wall, in this case); height of the
element; etc. To take these features into account, one has to defme a standard
condition and calculate correction factors to transform quantities of any other
condition into equivalent "units" of the standard one.
The conversion factor (CF) allows this transformation [6]. It is expressed as:

CFO) = unit rate(j) / unit rate(std)

where:
CF(j) = conversion factor for condition "j",
unit rate(j) = unit rate for the condition "j",
unit rate(std) = unit rate for the standard condition.

Then, the equivalent quantity may be estimated by:

output(std) = output(j) * CF(j)


where:
output(std) = equivalent quantities in the standard condition,
output(j) = quantities in the condition "j".

The use of CF, as described on Figure 1, allows the estimation of an equivalent


amount of work: first it is necessary to measure the amount of units for each type of
work done; then, to transform these amounts into standard units; and, fmally, the
summation represents the total work done.
The conversion factors, for wall and column formwork, were developed following
the steps: formwork classification and choice of the standard; collection of
productivity rates, for cases presenting different factors affecting the performance,
from American estimating manuals; choice of the most important factors in explaining
productivity variation; defmition of equations to estimate the CF for any non-standard
item of formwork.
Conversion factors for analysis 17

2 Formwork classification

To allow the deftnition of conversion factors, one ftrst needs to defme a framework
at the same time comprehensive (to include as many types of formwork as possible),
simple (avoiding excessive slightly different classiftcations), and easy to understand
(avoiding misuses and inducing its use).

conversion equivalent
quanti1les factors quantities
~ w.l

comparison
to
SUM
the equivalent
quantities
~t8nd8rd Co

c.;

Figure 1- The conversion factor's role in measuring the amount of work.

Figure 2 shows the framework used to classify wall and column formwork and to
calculate the CF. The ftrst division is related to the element being formed (wall or
column). The second division defmes the following broad categories:

- for walls:
* stick (#) = built-in-place formwork;
* non-stick (N#) = prefabricated (both in-site or out-site);
- for columns:
* stick (#) = built-in-place;
* non-stick rectangular (N#rec) = prefabricated (both in-site or out-site) with
rectangular section;
* non-stick round (N#rou) = prefabricated (both in-site or out-site) with round
section.

These terms, that represent a compromise between the simplicity and accuracy, ftts
the methods and the language used in construction. More than it, this division is
necessary to create groups of forms whose productivity is expected to be influenced
by the same factors (for example, "#" must be isolated from "N#" to study the
influence of "ganging panels").
18 de Souza and Thomas

The several levels below the two divisions represent factors (for example "height")
that have influence on the classes defmed by each vertical line (for example, "C#").
As a consequence of such a division, there are factors that have influence on one
category of fonn but not (or have a different influence) on another (for example,
"height" may have influence on the productivity of "C#" but not of "CN#rec").

other
factors
I--+----+----+---+_ t.i
conversion factors equations

Figure 2- Framework to defme the conversion factors for fonnwork.

3 Choice of the standard

The fonnwork job may be done under different kind of "factors" (as previously
shown on Figure 2); to describe a case, one must detect and quantify the existing
factors. The standard case is the one chosen as the gauge for comparisons. The
chosen case should be the most often used in practice in order to: improve the
accuracy of the comparisons; simplify the understanding of equivalent quantities
estimated using this standard.
The features of the standard condition for fonnwork were chosen as: fonn for wall
non-stick, with height not exceeding 8', and using plywood as surface material.

4 Measuring factors' effects

Although the procedures to get the data are sometimes not well understood, and may
vary from one manual to another, the estimating manuals represent an accumulated
experience extremely significant. Mainly because to collect data in construction is
neither an easy nor a cheap task.
Each case presented by a manual, expressed in tenns of accumulated unit rate at
the completion of the project, represents an average of the results obtained for similar
conditions in several sites.
Conversion factors for analysis 19

The following criteria were used in order to choose the manuals to serve as source
of data: to be recognized by the technicians as a good manual; to describe in detail
the cases analyzed; to avoid the use of manuals with the same origin.
The five chosen manuals were: "Structural Concrete Cost Estimation" [7]; "The
1984 Berger Building & Design Cost File" [8]; "1988 Dodge Unit Cost Data" [9];
"Means Man-hours Standards" [10]; "General Construction Estimating
Standards"[ll].

Table 1 shows how many cases were collected from each manual, while Table 2
shows the kind of information provided by the manuals.

Table 1- Number of cases collected in the manuals, for walls and columns.

Manual Element
wall column
Clark: 2 1
Berger 48 32
Dodge 12 43
Means 21 52
Richardson 104 24
TOTAL 187 152

Table 2- Information provided by the manuals.

Information Walls Columns


cumulative unit rate X X
perimeter X
section format X
section area X
curvature X X
tickness X
height X X
material/system X X
number of uses X X
gang size X X
use of crane X X
maximum dimension X

5 Transforming unit rates into conversion factors

The data collected from the Manuals expressed productivity in terms of unit rates for
each case. The transformation of this information into conversion factors followed the
20 de Souza and Thomas

steps: the cases were classified according to the "categories of fonnwork" previously
defmed: column stick, column non-stick round, column non-stick rectangular, wall
stick, and wall non-stick (generating five subset of data); for each subset it is
necessary to detect which Manuals have the standard as a case; when the Manual has
the standard, CF=1 is assigned to this case and the CF's for the remaining cases of
this Manual are calculated according to the defmition previously explained (ratio of
unit rates); when the Manual doesn't have the standard as a case, it is necessary to
calculate the unit rate for a "estimated" standard (the unit rate for the standard if it
was present in the subset), and then the CFs for all the cases are calculated in the
same way just described. In order to estimate the standard unit rate it is necessary
to make comparisons among comparable situations relating the manuals.
The unit rates for the standard, expressed in wh/sf, are: 0.236 for "Clark"; 0.131
for "Berger"; 0.073 for "Dodge"; 0.075 for "Means"; and 0.067 for "Richardson".
Notice that, although each data point in a Manual may represent an average of
several collections, there are no established standard procedures, common to all the
Manuals, to calculate the productivity rates. Then, it is very common to fmd different
unit rates related to the same case, as it happened with the unit rates for the standard.
Some explanations are: certain Manuals are more conservative than others; some may
consider the management hours as part of the input, while others only take into
account the direct labor; etc. But, many times, the comparable values in two distinct
Manuals differ roughly by a constant. This is the typical situation in that the use of
conversion factors will improve the fit of data, as illustrated in Figure 3: the unit
rates and the conversion factors for walls non-stick coming from two distinct Manuals
(Berger and Means) are plotted; although there is a significant difference between the
unit rates proposed by them, there is a close agreement in relation to the conversion
factors.

6 Calculation of the conversion factors for non-standard conditions

The process of defming equations to estimate the conversion factors for each category
of fonns, as illustrated by Figure 4, follows the steps: for each "category of
fonnwork" one must list all the variables that potentially can affect the conversion
factors (CF); during a "preliminary individual evaluation" , each variable, one by one,
will be checked by means of "graphical analysis" (for example plotting the CF in
relation to the variable), "statistical analysis" (for example using individual ANOYA
and individual regression analysis), "personal evaluation" (taking into account past
experience and common sense), and "confidence on the data" (involving both the
number of available data points and the clearness of Manual's infonnation); the
remaining variables (named "potential variables") are now evaluated together, by
means of "graphs" and "statistical analysis", to take into account the eventually
present interactions effects; the variables in the fmal equation will be the ones with
good statistics, with significant impact over the CF being calculated, and the ones
that are considered causal variables.
Conversion factors for analysis 21

0.20 0
0 0
0 0
0 0
0 0
2 0.15 0 0 aJ
E 0
0
0
::i 0

''"
0.05
}+
+
+
+

10 15 20 0 Berger
height + Means

2.1 -

0
1.6 -
0
LL. 0 + 0
0 0 0 bJ
+ 0 0
0 0
1.1 - + 0 0
0 0
+ 0
0

+
0.6
10 15 20
height

Figure 3- Comparison between the infonnation from two Estimating Manuals (Berger
and Means) for walls non-stick: a)unit rates; b)conversion factors.
22 de Souza and Thomas

IIvlliiable vllriables

preliminary individual
evaluation

potencial variables
group evaluation

final equation

Figure 4- The process of defIning a conversion factor's equation.

The fmal equations can be seen on Figures 5, 6, 7, 8 e 9, respectively for columns


N, columns NNrec, columns NNrou, walls N and walls NN, as part of the regression
analysis that generate them.

Regression Analysis

CF = 1.95 - 0.00158*perimeter+ 0.109*(12'<h<=15')

predictor std dey. t-ratio p-value


constant 0.01742 111.99 0.000
perimeter 0.00019 -8.2 0.000
12'<h<=15' 0.01332 8.15 0.000

Figure 5- Regression analysis to estimate the CF equation for columns N.


Conversion factors for analysis 23

Regression Analysis

CF = 1.58 - 0.00407"petimeter - 0.0101*(pref.plywood syst.)*(petimeter - avg. perimeter) +


+ 0.000084*(pref.plywood syst.)*(petimeter - avg.perimeter)**2

predictor std dey. t-ratio p-yalue


constant 0.07942 19.95 0.000
perimeter 0.001142 -3.56 0.007
(pref.plywood syst.)*(petimeter - avg.perimeter) 0.001382 -7.3 0.000
(pref.plywood sysL)*(perimeter - avg.perimeter)"2 0.000011 -7.67 0.000

Figure 6- Regression analysis to estimate the CF equation for columns N#rec.

Regression Analysis

CF =0.966 - 0.006*(max.dim.) - 0.0115*(tiber surface)*(max.dim.) +


-0.341*(tiber surface) + 5.57"(tearable syst.)/(max.dim.)

predictor std dey. i-ratio p-yalue


constant 0.0612 15.79 0.000
max.dim. 0.001952 -3.1 0.003
(tiber surface)*(max.dim.) 0.002213 -5.21 0.000
tearable sysL 0.06958 -4.9 0.000
(tearable syst.)/(max.dim.) 1.193 4.67 0.000

Figure 7- Regression analysis to estimate the CF equation for columns N#rou.

Regression Analysis

CF = 1.19 + 0.397"(9'<h<=16') + 0.756*(h>=17') + 0.57"curved

predictor std dey. t-ratio p-yalue


constant 0.06562 18.14 0.000
9'<h<=16' 0.09659 4.11 0.001
h>=17' 0.1392 5.43 0.000
curved 0.1856 3.07 0.010

Figure 8- Regression analysis to estimate the CF equation for walls #.


24 de Souza and Thomas

Regression AnalYSis

=
CF 1 + 0.15*gang - 0.16*(steel surface) + 0.106*(9'<h<=16') +
+ 0.187*(h>=17') +0.321*curved

predictor std dey. t-ratio p-value


constant 0.04793 21.57 0.000
gang 0.05198 2.89 0.007
steel surface 0.05437 -2.95 0.006
9'<h<=16' 0.0632 1.67 0.105
h>=17' 0.04483 4.16 0.000
curved 0.05437 5.9 0.000

Figure 9- Regression analysis to estimate the CF equation for walls NU.

7 Using the conversion factors to estimate daily productivity

The following example uses data collected in Central Pennsylvania (United States of
America) in 1995 from the construction of a big gymnasium (seating capacity:
16,500). Table 3 illustrates the necessary steps to transform the quantities, measured
for each item, into equivalent quantities of the standard condition. Notice that, to take
into account the different efforts involved in assemble and strip the forms, these parts
of the item being done are tracked separetedely and receive weights respectively of
0.85 and 0.15 (for example: 100 sf of assembled form represent 85 sf of the item's
job, while the same amount of stripped forms mean only 15 sf). Finally, Table 4
shows the calculation of the daily unit rates: the total equivalent quantities represent
the summation of the several items performed that day; the workhours are the total
hours related to the formwork as a whole (and not for each item); the daily unit rate,
then, being connected to the standard condition, represents a standard measurement
of productivity.

8 Conclusion

Traditional cost systems break the work in pieces (items) and require the
measurement of both the amount of work done and the workhours spent for each
piece. This report showed that conversion factors can be used in order to simplify the
labor measurement and to create a gauge for productivity calculation.
Based on data collected from estimating manuals five equations (one for each
category of form: CU, CNURec, CNURou, WU, WN#) were developed to allow the
transformation of amounts of any type of formwork into standard equivalent
quantities. Using these equations, it is only necessary to track the total workhours
spent with forms instead of observing the labor consumption for each item. The use
of standard quantities turns the unit rate into a standard productivity measurement,
what makes the comparison between measurements in different days and/or sites
possible.
Conversion factors for analysis 25

Table 3- Transfonnation of item quantities into standard quantities.

item item assembled stripped item equivalent


wday number description quantities quantities quantities CF quantities
!~ !~ (sf) !~
1 1 WN#; h>=17'; straight; gang; surface=ply 0 330 50 1.37 68
1 2 CN#Rec; perimeter=8'; steel framed ply 0 32 5 1.15 6
1 3 WN#; h>=17'; straight; gang; surface=ply 387 0 329 1.37 451
1 4 W#; 9'<=h<=16'; straight 236 0 201 1.59 319
1 6 CN#Rec; perimeter=8'; steel framed ply 80 0 68 1.15 78
1 10 WN#; h>=17'; straight; handset; surface=ply 250 0 213 1.22 260
2 1 WN#; h>=17'; straight; gang; surface=ply 0 280 42 1.37 58
2 3 WN#; h>=17'; straight; gang; surface=ply 0 774 116 1.37 159
2 4 W#; 9'<=h<=16'; strai9ht 0 472 71 1.59 113
2 5 WN#; h>=17'; straight; gang; surface=ply 0 835 125 1.37 172
2 7 WN#; h>=17'; straight; gang; surface=ply 40 0 34 1.22 41
2 7 WN#; h>=17'; straight; gang; surface=ply 511 0 434 1.37 594
2 7 WN#; h>=17'; straight; gang; surface=ply 34 0 29 1.95 56
2 10 WN#; h>=17'; straight; handset; surface=ply 298 0 254 1.22 309
3 6 CN#Rec; perimeter=8'; steel framed ply 0 80 12 1.15 14
3 8 WN#; h<=8'; straight; gang; surface=ply 161 0 137 1.18 162
3 9 WN#;9'<= h<=16'; straight; gang; surface=ply 181 0 154 1.29 198
3 10 WN#; h>=17'; straight;handset; surface=ply 328 0 278 1.22 340
4 7 WN#; h>=17'; straight; gang; surface=ply 106 0 90 1.22 110
4 7 WN#; h>=17'; straight; gang; surface=ply 360 0 306 1.37 419
4 10 WN#; h>=17'; straight;handset; surface=ply 77 0 66 1.22 80
4 11 WN#; h>=17'; straight; handset; surface=ply 54 0 46 1.22 56
5 7 WN#; h>=17'; straight; gang; surface=ply 88 0 74 1.22 91
5 7 WN#; h>=17'; straight; gang; surface=ply 151 0 128 1.37 175
5 7 WN#; h>=17'; straight; gang; surface=ply 24 0 20 1.95 39
5 8 WN#; h<=8'; straight; gang; surface=ply 157 0 134 1.18 158
5 9 WN#;9'<= h<=16'; straight; gang; surface=ply 181 0 154 1.29 198

Table 4- Daily unit rate calculation.

workday total equivalent workhours daily unit rate


quantities (sf) (wh) (whist)
1 1181 124 0.10
2 1502 96 0.06
3 714 96 0.13
4 665 88 0.13
5 717 84 0.12

9 Table of conversions

1 foot (t) = 0.3048 meter (m);


1 square foot (st) = 0.0929 square meter (m2);
1 inch (in) = 0.0254 meter (m);
1 workhourper square foot (whist) = 10.7639 workhourper square meter (whlm2).
26 de Souza and Thomas

10 References

1 Bukhart, A.F. (1994) Selecting a wall fonning system for your next job, in
Selecting and Using Wall Forms. Aberdeen, Louisiana, pp.18-53.

2 Qabbani, Z.S. (1987) Formwork: economy and productivity analysis. University


of Colorado. 113p.

3 Adrian, J.J. (1975) Realistic calculations of costs for wall fonning systems.
Concrete Construction, June.

4 Aldana, L. (1991) Measurement and analysis of concrete formwork and steel


reinforcement productivity. University of Dundee, 163p.

5 Backe, C. (1994) Wall fonns: selecting the best ganged system, in Selecting and
Using Wall Forms. Aberdeen, Louisiana, pp.54-58.

6 Thomas, H.R. and Kramer, D.F. (1987) The manual of construction productivity
measurement and performance evaluation. crr, Austin, 168p.

7 Clark, J.E. (1983) Structural concrete cost estimating. McGraw-Hill, 298p.

8 Hlibok, A.J. (1984) The 1984 Berger building & design cost file. Hicksville,
Building Cost File Inc., VoU, 479p.

9 Iavarone, R.C. (1987) 1988 Dodge unit cost data. New Jersey, McGraw-Hill,
338p.

10 Cleveland, A.B. (1983) Means man-hours standards. Means, 576p.

11 Richardson Engineering Services (1987) General construction estimating


standards. Richardson, Vol.l.
DEVELOPMENT OF AN EXPLANATORY
MODEL FOR CONCRETE FORMWORK
LABOUR PRODUCTIVITY
U.E.L. de Souza
Department of Civil Construction, University of Sao Paulo,
Sao Paulo, Brazil
H.R. Thomas
Deparment of Civil Engineering, Pennsylvania State University,
University Park, Pennsylvania, USA

Abstract

Labor costs are very significant in construction. To manage this resource it is


important to know the factors that influence labor productivity variations, and by how
much.
Researchers have been trying to develop models to explain productivity variability
([1], [2], [3], [4], [5]), but this is not an easy task. Many activities in construction
(as formwork) are labor intensive and there are both operational and environmental
factor influences on the productivity.
The "Factor Model" approach, developed at Pennsylvania State University (PSU),
identifies these factors by means of statistical modeling. This paper presents the
development of a Factor Model for Concrete Formwork (it is restricted to concrete
walls and columns).
Some of the steps followed to complete this research were: a procedures manual
for formwork, developed at PSU, furnished a standard way to collect data; the author
collected daily information in the site construction of a gymnasium (capacity: 16,5
thousands seats) located in State College (pennsylvania - USA), for more than 250
workdays; data from 5 other projects [6], tracked with similar procedures, were also
used in this study.
After the reconciliation of all the information received from the sources above
discussed, a statistical analysis generated a mathematical expression that identifies the
factors and their influence on the labor productivity.

Keywords: construction management, construction model, formwork, labor


productivity.

The Organization and Management of Construction: Shaping theory and practice (Volume Two).
Edited by D.A. Langford and A. Retik. Published in 1996 by E & FN Spon. ISBN 041922240 5.
28 de Souza and Thomas

Sommaire
Les couts de main d'oeuvre sont loin d'etre negligeables dans Ie
batiment. n est indispensable, pour gerer au mieux les ressources humaines,
de connnaitre les facteurs qui influencent les variations de productivire, et
dans quelle mesure.
De nombreux chercheurs ont tenre de developper des modeles de
variabilire de la productivire ([1], [2], [3], [4], [5]); cette tache s'avere
cependant ardue. Nombre d'activires du bil.timent - tel Ie coffrage - sont!res
couteuses en temps et en hommes, et on observe que les facteurs agissant sur
la productivire sont de nature operationnelle autant qu'environnementale.
La modelisation des facteurs ("Factor Model") developpee a la
Pennsylvania State University (PSU), aux Etats-Unis, circoncit ces facteurs
statistiquement. Ce papier a pour objectif de presenter Ie developpement
d'une modelisation applicable au coffrage en beton, uniquement ici pour Ie
coffrage des murs et des colonnes.
Cette recherche s'est ainsi deroulee: un manuel des procedures pour Ie
coffrage, moyen standard de recolte des donnees, a ere developpe a la PSU;
l'auteur a recueilli des donnees quotidiennement, sur Ie chantier d'un
gymnase d'une capacire de 16 500 places et situe dans l'enceinte du State
College Pensylvania, Etats-Unis, pendant une periode de 250 jours travailles;
les donnees de 5 autres projets [6] observant les memes procedures ont par
ailleurs ere utilisees dans la presente etude.
Apres la reunion de toutes les informations recueillies aupres des
sources citees precedemment, l'analyse statistique a fait apparaitre une
equation mathematique qui identifie les facteurs et leur influence sur la
productivire humaine.
Explanatory model for labour productivity 29

1 Introduction

The observation of a real process for a certain period of time allows the construction
of models that provide understanding: the explanation of what has happened and the
forecast of future events. Figure 1, based on Casti [7], illustrates this mechanism.

r-----, r----,
I
I I
I
I
I inputs
I
I
Inputs
-.! encoding
(explanation)
observed
laws procr.ss sample model
01 a

I
process

I
outputsi'
I
decoding
forecactin 9)
i'OlltplllS
I
I
I
L-~ '--~
Figure 1- The modeling relations.

The Factor Model [8], based on the crew level productivity, was developed in the
Pennsylvania State University (PSU). Graphically shown in Figure 2, the
development of the model assumes the existence of an "standard condition of work";
under this condition, the daily productivity will be the "ideal" (here one may assume
the existence of learning or not); variances in the work scope and/or in the work
environment make the productivity vary in relation to the ideal. The model relates
the actual daily productivity to the daily work features.

~

o
t:
S WORICTYPE

a:I7~~
..
w
PHYSICAL ELf:MEHt'

g~ CONSTRUCTION METHOD

~ DESIGN REQUIREMEIiTS

UNrrSOFWORK

Figure 2- The Factor Model.


30 de Souza and Thomas

In this report the Factor Model approach is used in order to "explain" daily
productivity variability: detecting the factors that generate variation and their degree
of influence, based on nonnaI workdays (Figure 3).

disruptions/outliers

Figure 3- Explanatory model development.

To reach these goals the report discusses the following issues: standardization of
productivity measurement; collection of daily infonnation; preliminary evaluation of
the factors; modelling; and final checks.

2 Standardization of productivity measurement

This paper adopts, as a tool to measure daily productivity, the daily unit rate [9],
defmed as the ratio between the inputs (labor workhours) and the output (work
quantities). In order to establish a standard measurement, it is necessary to have
standard measurements of both the inputs and the outputs.
The measurement of labor consumption (input) was done as prescribed by a PSU's
manual for data collection [10]. The main recommendations are: to track the
workhours spent by one crew, that "consists of the foreman and the gang members";
"hours of absenteeism are not counted"; support personnel are only take into account
when their work is devoted exclusively to the crew; the recorded workhours are the
paid hours . (excluding eventual "premium"). The quantities measurement
standardization relies on the following ideas (Figure 4): to recognize the parts
(subtasks) that constitute a task and to record quantities individually allocated; to add
these quantities accordingly to the relative demanded efforts (rules of credit); to
transfonn the quantities for each different task into equivalent amounts of the
standard task (conversion factors) and to add them to fmd the daily quantities of
standard work. The units of measurement are: workhours (wh) for the inputs, and
square feet (st) of fonnwork for the outputs; then, the unit rate will be expressed in
workhours per square foot (whist).
Explanatory model for labour productivity 31

quantities

r c
u 0
I n
e
s
of
c a
r c
e t
d 0
r
s

Figure 4- Measuring quantities of work.

An extensive discussion about the output measurement process is provided elsewhere


[9]. But some aspects are worth to be presented here: some factors that have
influence on formwork labor productivity have ever been considered in the
development of the conversion factors (type of element, height, section size,
formwork system, format, handling system, surface material); the equivalent
quantities are expressed in terms of the following standard task: forms for walls not
higher than 8 feet, using handset panels with plywood surface.

3 Daily information

The description of daily performance includes both the calculation of the unit rate
(expressed in terms of standardized inputs and outputs) and the description of present
factors that may influence productivity. The standard measurements of amounts of
labor (input) and work (outputs) were previously discussed in this report. In relation
to the "productivity influencing factors", some additional comments are: some of
them were included in the conversion factors' equations; the remaining ones may be
divided into quantitative and qualitative variables; for the qualitative ones it is
necessary only to detect its presence or absence; the quantitative ones demand a
quantification task; the number of factors to be tracked should be as big as possible,
under the researcher's point of view, but as low as necessary to diminish the
spending time for future practical use of the fmal model by contractors; previous
experience helps in defming what factors must be tracked; try to avoid factors that
present difficulties in being measured; as far as possible, use factors common to
former data collections; because this report deals with an explanatory (and not a
forecasting) model, it is possible to use daily features as factors, instead of
information necessarily extracted from plans (for example, one can use the number
of the floor in execution in a certain day instead of the building'S height).
32 de Souza and Thomas

This report uses databases collected accordingly to the procedures developed at the
PSU. Table 1 summarizes the main features of the available databases.

Table 1- Databases' infonnation summary.

project cumulative u.r. at total total equiv. % of disr. or


name completion (whIst) worKdays area (1000 sf) outlier days
Bryce Jordan 0.12 256 208.9 34
Tertiary Filter -level 1 0.17 25 6.6 16
Tertiary Filter - level 2 0.12 39 16.7 21
Composting Facility 0.05 23 46.1 9
Art Museum Wing 0.05 43 15.6 21
ParKing Deck Garage 0.14 40 13.8 28

As it can be seen on Figure 5, the chosen factors to be analyzed ("available


variables"), grouped under the classes "design features/work content", "environment
conditions", and "construction methods", were: "boxout or pipesleeves" (Figures
6.a.l and 6.a.2), a qUalitative variable that states if the workday was significantly
affected by the execution of boxouts or the positioning of pipesleeves by the fonn
crew; "comers" (Figure 6.b), that can be treated either as a quantitative (counting the
number of fonn comers perfonned) or a qualitative variable (stating if there was
significant effort spent in fonning comers); "elevation changes" (Figure 6.c), with
approach similar to comers in relation to the existence of "steps" along the height of
the element being fonned; air "temperature" (represented by the temperature at
1:OOPM) and "relative humidity" (represented by the temperature of dew point at
1:00PM), whose summation is representative of weather comfort; "length of
workday", measured in hours; "bulkheads" (Figure 6.d), with approach similar to
comers in relation to the presence of this kind of fonnwork; "accessibility", a
qualitative variable that implies in classify an element as easily approachable (Figure
6.e.l) for workers and materials or as of not easy access (Figure 6.e.2); "pour
coordination", a qualitative variable that states if the fonn crew was involved with
concrete pouring in a certain day; "crew size", measuring the number of workers of
the crew in a certain day, from the foreman (included) down (hierarchically
speaking), independently of their skills.

4 Preliminary evaluation of available variables

Once the infonnation about the available variables has been collected in the fonner
step, it is time now to check which ones are really important for the model's
development: different approaches were used for quantitative and qualitative
variables; the checks include the use of graphical and statistical tools (analysis of
Explanatory model for labour productivity 33

variance, regression analysis, confidence intervals, scatter plots); as a result of this


evaluation, each available variable is "accepted" for further analysis or "excluded".

AVAILABLE VARIABLES

Figure 5- Available variables classification.


3.1) 8.21 bl
Iii! il II

v-l Ir;:1====+
~ -//-

e.1)
c)

e.2)

o dJ

Figure 6- Variables description: a)boxouts and pipesleeves; b)comers; c) elevation


changes; d)bulkbeads; e)accessibility.
34 de Souza and Thomas

Table 2 summarizes the results for the qualitative variables. Some additional
comments are: in relation to the 95% confidence intervals, a "good" plot is that one
with no superposition between the ranges of variation for the conditions being
checked; "difficult access" is considered to happen whenever there is not only
elements easily approachable being formed; although the results for "elevation
change" and "bulkheads" are not so bad, there is an inconsistency between the data
and the expected performance: days with these factors present have a smaller unit
rate than days without.

Table 2- Qualitative variables evaluation.

# of Anova ind.regr. 95%


variable cateQory obs. mean p r2-adj C.1. classification
boxout or 0 238 0.113 0.004 2.3% good accepted
pipesleeve 1 67 0.144
corners 0 150 0.122 0.771 0.0% bad excluded
1 155 0.119
elevation 0 280 0.123 0.033 1.2% good excluded
chanQes 1 25 0.088
bulkheads 0 195 0.127 0.051 0.9% bad excluded
1 110 0.109
difficult 0 125 0.097 0.000 5.8% good accepted
access 1 180 0.136
pour 0 203 0.105 0.000 6.8% gOOd accepted
coordination 1 102 0.150

Table 3 summarizes the results for the quantitative variables. Some additional
comments are: plotting the unit rate against the variables allows the visual detection
of the existence of a "trend" (possible flag for a relationship); in order to fit the
reality, the "density" of comers, elevation changes and bulkheads, separately, are
studied; "density" is defmed as the number of units of the factor (for example the
number of comers formed in that day) multiplied by 1000 and divided by the total
equivalent amount of form work job for the same day; "T1 +Tdp", the summation of
air temperature and temperature of the dew point at 1:00PM, is used to analyze the
effect of weather over the labor productivity.

5 Modelling

The fmal expression of the explanatory model is an equation generated by regression


analysis having the standard daily unit rates as dependent and the "accepted" factors
as independent variables:

unit rate = 0.080 + 0.030*(difficult) + 0.028*(pour coord) + 0.034*(boxipipe)


Explanatory model for labour productivity 35

On a day with standard condition of work (difficult = pour coord = box/pipe = 0)


the ideal daily unit rate, expressed in equivalent quantities of fonnwork, is 0.080
whlsf. Because all the factors in this final expression are qualitative, the presence of
anyone modifies the daily unit rate by the value of its coefficient (for example: in
a day with concrete pour, "pour coord" = 1, and the unit rate becomes 0.108 whist).

Table 3- Quantitative variables evaluation.

individual regression plot


variable J2-adj p - value trend? classification
comers density 0.0% 0.301 no excluded
elevation change density 0.6% 0.159 no excluded
bulk density 0.0% 0.922 no excluded
T1 + Tdp 2.1% 0.037 no excluded
length of wor1<day 0.0% 0.768 no excluded
crew size 0.2% 0.247 no excluded

6 Final checks

Four different approaches are showed to check the model's equation: coefficient's
statistics; infonnal evaluation; effect on the standard deviation; omitting databases.

Coefficient's statistics
Table 4 presents the main statistics related to the coefficients of the model's factors;
they are significant.

Table 4- Coefficient's statistics from the regression analysis.

factor t-ratio p-value


difficuH 4.45 0.000
poor coord 4.06 0.000
box/pipe 4.30 0.000

Informal evaluation of the coefficients


The coefficients are: 0.030 for "difficult" , what means an increase of 38 % in the unit
rate in relation to standard days; 0.028 for "pour coord", representing an increase of
35 %; 0.034 for "box/pipe", meaning a 43 % increase.
The literature review didn't provide a baseline to compare these values; but they
seem to be consistent with the reality, based on the researcher's personal experience.
36 de Souza and Thomas

Effect on the standard deviation


To verify the model's explanatory capability, one may compare the standard deviation
of the database "before" the standardization and modelling and "after" that. The
values are, respectively, 0.3077 and 0.0559. This means a very significant 82 %
reduction.

Omitting databases
When developing a forecasting model, the last stage of the process is to confront its
predictions with new data coming from a database not used in the model's
development. Although this is not the case (this report is concerned with an
explanatory model), a similar approach will be used in order to check the confidence
one can credit on the model: "new" equations were developed accordingly to the
same process used to create the "model's" equation, but making use of all databases
except one; because there were six databases, it is possible to develop six new
equations based on the five remaining databases; the intercept and coefficients values
for the "model's" and the six "new" equations can be seen on Table 5.

Table 5- Intercept and coefficients values for the "model's" and the six "new"
equations.

constants
intercept difficult pour coord. box or pipe
model 0.0797 0.0299 0.0282 0.0342
new 1 0.0716 0.0341 0.0299 0.0387
new 2 0.0905 0.0192 0.0279 0.0346
new 3 0.0854 0.0256 0.0254 0.0325
new 4 0.0810 0.0303 0.0239 0.0347
new 5 0.0761 0.0346 0.0264 0.0272
new 6 0.D705 0.0430 0.0520 0.0405

In order to check the agreement among all the generated models, all the equations are
plotted together, as can be seen on Figure 7, for different working conditions. The
visual evaluation shows a good harmony among them: the points are close to each
other.

7 Conclusion

Several factors may have influence on formwork labor productivity. In order to


standardize the measurement of outputs some of them were already considered: type
of element; height; section size; formwork system; format; handling system; and
surface material. The importance of several other factors were checked in this paper:
boxouts; pipesleeves; comers; elevation changes; air temperature; relative humidity;
Explanatory model for labour productivity 37

length of workday; bulkheads; accessibility; pour coordination; and crew size. The
Factor Model approach helped in create an equation that shows the factors to be
considered and quantifies their influence on the daily unit rate value: the ideal
productivity (standard condition of work) is 0.080 whlsf; "difficult" access represents
an increase of 0.030 whlsf; days with concrete "pour coordination" mean an
additional 0.028 whlsf; and extra 0.034 whlsf can be credit to days impacted by box
out or pipesleeve work. This kind of information can help the site management in
different ways: as baseline for performance evaluation; as source of information to
defme production goals; in defming strategies to make easy the "access" to the
elements (for example, to defme an advantageous forming sequence); in taking
decisions about having an special crew only for concrete pour; etc.

0.25

.. model ur
0.2
-+ new 1
.....
Q)
*new2
co
.... 0.15
:!:::! -B new 3
c:
:J ~new4

0.1 -fr new 5


.new6

0.05
different conditions

Figure 7- Plot of the "model's" and the six "new" equations for different working
conditions.
38 de Souza and Thomas

8 Table of conversions

1 foot (t) = 0.3048 meter (m);


1 square foot (st) = 0.0929 square meter (m2);
1 workhour per square feet (whist) = 10.7639 workhours per square meter
(wh/m2).

9 References

1 Thomas, H.R. and Yakoumis, I. (1987) Factor model of construction


productivity. ASCE Constr. Engrg. and Management, Vol. 113, No.4. pp.623-
639.

2 Thomas, H.R. and Sakarkan, A.S. (1994) Forecasting labor productivity using
the factor model. ASCE Constr. Engrg. and Management, Vol. 120, No. 1.

3 Sanders, S.R. and Thomas, H.R. (1991) Factors affecting masonry labor
productivity. ASCE Constr. Engrg. and Management, Vol. 117, No.4. pp.626-
644.

4 Qabbani, Z.S. (1987) Formwork: economy and productivity analysis.


University of Colorado. 113p.

5 Bennett, P.O. (1990) A case study of the validity of daily crew-based


productivity measurements. Pennsylvania State University. 87p.

6 Shumway, J.D. (1992) A comparative analysis of concrete form work


productivity influence factors. Pennsylvania State University. 103p.

7 Casti, J.L. (1990) Searching for certainty: what scientists can know about the
future? W. Morrow, New York, 496p.

8 Thomas, H.R. et alii (1990) Modelling construction labor productivity. ASCE


Constr. Engrg. and Management, Vol. 116, No.4. pp.705-726.

9 Thomas, H.R. and Kramer, D.F. (1987) The manual of construction


productivity measurement and peljormance evaluation. crr, Austin, 168p.

10 Thomas, H.R., Homer, R.M.W. and Smith, G.R. (1991) Procedures manual
for collecting productivity and related data of labor-intensive activities on
commercial construction projects: concrete formwork. PTI, State College, 63p.
OVERMANNING AND THE EFFECTS ON
LABOR EFFICIENCY
H. Randolph Thomas
Professor of Civil and Environmental Engineering,
Pennsylvania State University, University Park, Pennsylvania, USA
Todd M. Arnold
Graduate Assistant, Pennsylvania State University,
University Park, Pennsylvania, USA

SUMMARY

Schedule acceleration is a very troublesome problem for contractors because of the


potentially devastating effect on labor productivity. While much has been written
about scheduled overtime, little has been published about the effects of overmanning,
that is, managing a larger workforce than planned. This paper reports the results of
a survey of electrical contractors asking about the magnitude of inefficiencies due to
overmanning and the causes. The results show significant degradation in efficiency
as more craftsmen are hired and are reported by project type, however, the differences
are not significant.

SOl\1MAIRE

L'acceleration de l'horaire du travail pose des problemes pour les entrepreneurs a


cause de l'eventual effect detrimental sur la productivite de la main-d'oeuvre. Tandis
que beaucoup a ete ecrit au sujet des heures supplementaires, il y a tres peu d'etudes
sur l'effect et les problemes de gestion d'une main-d'oeuvre surchargee. Cette etude-
ci presente les resultats d'un sondage d'entrepreneurs d'electricite sur la manque de
l'efficacite cause par une main-d'oeuvre surchargee et ses causes. Les resultats
demontrent une manque d'efficacite lorsque plus d'employes sont engages, et ces
resultats sont decrits par project; neanmoins, les differences ne sont pas importantes.

INTRODUCTION

A survey was distributed to the membership of the National Electrical Contractors


Association (NECA) requesting pertinent information on projects that were accelerated
or compressed causing overmanned. These surveys provide two relevant pieces of
information: assessment of contractor perceptions of the extent of efficiency loss
caused by overmanning, and relative differences in loss of efficiency for different type
projects.

The Organization and Management of Construction: Shaping theory and practice (Volume Two).
Edited by D.A. Langford and A. Retik. Published in 1996 by E & FN Spon. ISBN 0419222405.
40 Thomas and Arnold

SURVEY INQUIRIES

The survey instrument requested the following infonnation about a specific project that
was accelerated or compressed:

• Project type
• Planned and actual number of electricians
• Estimated loss of efficiency caused by ovennanning
• Planned (budgeted) and actual workhours
• Estimated and actual schedule duration

In total, infonnation was provided on 129 projects. There were complete responses
for 110 projects. Table 1 summarizes the surveys according to the project type and
average planned maximum number of electricians. As can be seen, most projects
were industrial, commercial, or institutional. The average planned maximum number
of electricians ranges from 4 to 50. Comparatively few line projects were contributed.

Table 1. Summary statistics of survey responses.


Project Type Number of Average Planned
Projects Maximum
Number of
Electricians

Inside Projects:
Industrial 45 50
Commercial 26 40
Institutional 29 28
Communications I 4

Line Projects;
Transmission 1 9
Distribution 2 6
Substation I 10
Underground 0
Communications 5 43

TOTAL WSS OF EFFICIENCY

For the data analyses, several parameters were calculated. The first is the percent
ovennanned which was calculated as follows:
Overmanning and the effects on labour efficiency 41

Percent Overmanned (%) = ( Actual Max. No. of Elec. -1.0) x 100 (1)
Planned Max. No. of Elec.

The total loss of labor efficiency relies on the actual workhours and the budgeted
or planned workhours. These values are used in equation 2.

Total Loss of Efficiency (%) = (1.0 - Budgeted Workhours) x 100 (2)


Actual Workhours

Figure 1 shows the distribution of the total efficiency loss for all projects as a function
of the percent ovennanned. Using equation 2, an efficiency loss of 25 % means that
33 % more workhours were required than budgeted. As can be seen, the number of
workhours required can exceed the budgeted or planned workhours by a considerable
margin.
The relationship between the total loss of efficiency and the ratio of the actual
divided by the planned schedule duration was also investigated. From figure 2, this
relationship is unclear. However, it is obvious that few projects finish early or on
time. In the survey, 68 percent of all projects took more workdays than planned.

LOSS OF EFFICIENCY CAUSED BY OVERMANNING

The survey requested the estimated percentage of the total labor overrun attributed to
providing additional manpower resources, i.e., ovennanning. The distribution of
percentage estimates is shown in figure 3. It is obvious that the consensus of opinion
of electrical contractors is that ovennanning causes considerable loss of efficiency.
The average estimate is 29 percent, but in many instances, the estimated percentage
is much higher.
The net loss of efficiency caused by ovennanning was calculated by mUltiplying
the total loss of efficiency from equation 2 times the estimated percentage of the total
labor overrun attributed to ovennanning. The net efficiency loss is shown in equation
3.
Total Elf. Loss x Est. % From Overmanning (3)
Net Elf. Loss (%)
100

Figure 4 shows the relationship between the net loss of efficiency and the percent
ovennanned. The general trend is that as the percent ovennanned increases, the net
loss of efficiency also increases.
The net loss of efficiency from ovennanning was also investigated for other
relationships. No correlation was evident between the net loss of efficiency and the
42 Thomas and Arnold

planned size of the work force or the planned duration. Thus, from the survey, it
cannot be said that larger or longer duration projects have greater efficiency losses.
This observation may be different if there were more larger projects in the database.
Figure 5 shows that half of the database is from projects where the planned maximum
number of electricians was 20 or less.
The net loss of efficiency by project type was also investigated for indoor
projects. A linear regression equation was calculated for all indoor projects and
industrial, commercial, and institutional projects. These equations are shown in figure
6. As can be seen, when the percent overmanned is 25 percent or less, there is
minimal difference between the net loss of efficiency as a function of project type.
Because there were insufficient line projects to examine by type, a linear
regression equation was calculated for all line projects. Figure 7 compares the indoor
and line projects. There appears to be minimal difference between these two groups.
To validate the results of the survey, losses of efficiency were calculated for each
project type at 50 percent overmanned (see figures 6 and 7), and the results were
compared to the summary curves from the literature review. From the literature
review, the range of efficiency loss at 50 percent overmanned for small and large
projects is between 8 and 15 percent. As shown in figure 8, the results of the survey
are within this range.

SYNOPSIS

The results of the survey are generally consistent with the published literature on net
loss of efficiency caused by overmanning (homas et al. 1994). The data also show
that efficiency losses as a function of project type can vary. Table 2 summarizes the
difference between project types by showing relative increases and decreases in
efficiency loss. The category representing the analysis of all indoor projects is used
as the base for the indoor projects. The relative differences in table 2, called
efficiency loss multipliers, show that institutional projects are affected least and
industrial projects are affected the most. Further, the efficiency losses reported from
the survey showed no correlation to the planned size of the work force or planned
schedule duration.

CAUSES

The survey asked the respondents to indicate the principle cause of the acceleration.
The responses to this open-ended question are summarized in table 3. As can be seen,
the highest frequency of causes are related to design changes, change orders, and
scope alterations. Another category offrequent responses covers scheduling, planning,
and coordination. These factors may be as a result of problems with the design or the
inability of the prime contractor to adequately manage the project.
Overmanning and the effects on labour efficiency 43

CONCLUSIONS

The survey confmns in numerical tenns what has been generally known in the
construction industry, that is, staffmg a project with more craftsmen than was planned
leads to losses in labor productivity. This infonnation should be of value to both
contractor and owner in negotiating an equitable adjustment to the contract sum when
schedule acceleration requires the contractor to hire more craftsmen than planned.

REFERENCES

Thomas, H. R., A. A. Oloufa, and A. S. Hanna. Construction Productivity Losses


From Ovennanning: A Literature Review and Analysis. Report to the Electrical
Contracting Foundation, Inc., Bethesda, MD, 29 pp. (1994).
44 Thomas and Arnold

Table 2. Efficiency loss multipliers.


Project Type Loss of Efficiency Loss
Efficiency Multiplier

Indoor:
All 11.70 1.00
Industrial 12.25 1.05
Commercial 10.08 0.92
Institutional 9.65 0.82

Line:
All 10.80

All Indoor and Line 10.20


Projects

Table 3. Principle cause of the acceleration.


Cause of the Acceleration No. of Responses

Management (Scheduling, Planning, 54


Coordination)
Labor 9
Weather 1
Design 10
Change Orders/ Scope Alteration 50
Crowding 5
Materials and Equipment 8
Other 4
Overmanning and the effects on labour efficiency 45

>-
u
.~ 80
.~ 70
°° °
c......
~ 60
° °° ° °
50
c......
0 ° °° °
en 40 ~
00<ID
§
°8 00
0
0

en o 008 &C§ &0


030
--.l ~, ~ 0t C9 <ID0
- 20 0<6 8~ 0
CD 00 o ° 6b 0
~ 10 ° 0
o 0<6
0
I--
0 ° 00 Q)
0
0 @

0 10 20 30 40 50 60 70 80 90
Percent Overmann~d (%l
Figure 1. Total loss 0' erriciency vs. ~ercent overmanned.

~
- 80 o
>- o o
g 70 o
.~ 60 o 0 o
::: 50
w 40
c......
0 30
en
en 20
o
--.l 10
~ 0
o I
I-- 0 3 4 2
Actual Duration / Planned Duration
Figure 2. Total loss 0' erriciency vs. actual dur'ation I planned duration,
46 Thomas and Arnold

30
(!l
Q)
(J)
c
o
0.20
(J)
Q)
a::::
'"-
o
'- 10
Q)
..0
E
::J
20
0.0 0.1 0.2 0.3 0.4 0.5 0.6 OJ
Estimated Loss from o'Lermanning
Figure 3. Distribution or estimated proportion or total erriciency 105S attributed to overmanning.

o
>-40
() o o
C
Q)
o
·u 30
'"- o
'"- o
W
20 o o
'"- o
o
~ 10 o
o
---.J

a; a o
2
a 10 20 30 40 50 60 70 80 90
Percent Overman ned (%)
Figure 4. Net loss or err;ciency vs. percent overmanned.
Overmanning and the effects on labour efficiency 47

>-
()
c
~ 1.00
0-
(l)
'-
l.J....
(l)
>
...... 0.50
co
(l)
a::
(l)
>
......
co
:J 0.00
E
:J
U
o 20 406080100120140160180200
Planned Maximum Manning Level. Mp
Figure 5. Distribution of planned maximum manning level. Mp.

~25
>-
()
c(l) 20
.-
()
c.-
c.-
IS
w
' - 10
0
.(f)
(f)
0
5
---l
...... 0
(l)
z: 100
0 50
Percent Overmanned (%1
Figure 6. Net loss of efficiency vs. percent overmanned.
48 Thomas and Arnold

s.Q

>-20
u
c /
/ Indoor
Q) /
/

u /
/
/

/
'--
'--
w
'--
lO /
/
0 /
/

/
/
(J)
(J)
0
---l
...... 0
Q)
z: 50 laO
a
Percent Overmann~d (%1
Figure T. Net loss of efficiency vS. percent overmanned.

s.Q r-
l5 -
>-
u .---
c
Q) r-
r- .---
u lO - .---
.---
'--
'-- ,.--
w
'--
0
(J)
5 -
(J)
0
---l
...... --l L-J - '--
Q) 0 - . '-- l-
I I
z: ["du~trial In't1t~lional Small large
Commercial All Indoor
Indoor Line All Proj. Literature

Work Type-
Figure 8. Net loss of efficiency @ 50:: overmanned.
STEEL FRAMING CREW
PERFORMANCE AND VARIATION
Gary R. Smith and Yu-Bin Lin
Department of Civil and Environmental Engineering,
Pennsylvania State University, University Park, Pennsylvania, USA

Abstract
Traditional forecasting models, reported for labor-intensive productivity, have not
provided much insight into structural steel productivity and the factors affecting steel
construction crews. The factor model has introduced many new facets into evaluating
crew level performance in addition to providing a reasonably accurate model. Accurate
forecasts for crew-level performance can also be an important element of project control.
This paper examines those factors, which were identified through project based research,
that contribute to steel crew productivity variation. Understanding this variation is the key
to understanding process control and development of productivity improvement
procedures.
Data was compiled from nine steel frame construction projects. Each work day was
classified according to those factors and disruptions that had an impact on the crew that
day. When combined, 235 days of data were available for analysis. This data was
evaluated for the purpose of determining the most significant factors and their overall
influence on performance. A model of the crew performance was developed from the
significant factors. Process control chart concepts were reviewed to identify whether the
variability in the crew performance could have been identified in a manner that would
have permitted corrective action in a timely fashion. Although interpretation of the results
are somewhat limited, the combination of process control charts with forecasts may
provide a method to better understand project performance variation causes and provide
an opportunity to better control the field process.

Key Words: Productivity, Process Control, Steel Construction

The Organization and Management of Construction: Shaping theory and practice (Volume Two).
Edited by D.A. Langford and A. Retik. Published in 1996 by E & FN Span. ISBN 0419222405.
50 Smith and Yu-Bin Lin

Sommaire
Les modeles traditionnels de prevision des productivires couteuses en
heures de travail n'ont guere apporre jusqu'ici d'eclairage sur la productivite
structurelle de l'acier ni sur les facteurs affectant les equipes de la
construction acier. La modelisation des facteurs, qui s'avere etre relativement
precise, a mis en lumiere nombre de nouvelles facettes de l'evaluation du
niveau des performances des equipes. Des previsions precises du niveau de
performances des equipes peuvent etre un element important du controle de
projet. Le present papier examine les facteurs, identifies au cours d'un projet
de recherche, qui affectent les variations de la productivite des equipes acier.
Com prendre ces variations revient a com prendre Ie controle des processus et
les procedures d'amelioration du developpement de la productivite.
Les donnees ont He recueillies sur 9 chantiers de construction de
charpentes acier. Chaque journee de travail a ere classee selon ces facteurs et
selon les evenements qui sont venus deranger l'equipe ce jour-lao Une fois
compilees, ces donnees representaient 235 jours de donnees a analyser. Elles
l'ont ete dans Ie but de determiner les facteurs les plus importants et leur
influence sur les performances des equipes. Le concept des graphiques de
controle des processus a ere revu pour tenter d'identifier si la variabilite des
performances des equipes aurait pu etre identifiee d'une maniere qui aurait
permis une action correctrice a temps. Bien que l'interpretation des resultats
soit quelque peu limitee, la combinaison des graphiques de controle des
processus et des previsions pourrait s'averer un bon outil pour un meilleur
controle des processus sur Ie terrain.
Steel framing crew performance 51

1 Introduction

Developing accurate estimates is important during the planning and execution phases of
all construction projects. The purpose of this paper is to introduce quantified factors that
significantly affect steel erection productivity on the basis of field data. The factor
analysis is viewed as the first step toward developing accurate estimates. Process control
charts are employed to demonstrate the variability inherent in the process.
A key to effective forecasting is the development of an accurate model. Multivariate
factor models have been designed to respond to a range of factors [1]. Many factors have
been observed which influence productivity like temperature and humidity [2] and crew
size [3]. Sanders quantified significant factors for masonry construction [4]. Pace
demonstrated the model was a plausible alternative to conventional forecasting techniques
[5]. Sakarcan tested the model on international projects and found it to be reliable [6].
Detailed development of the model has been limited to masonry productivity.

1.1 Data Collection


The measure chosen for structural steel productivity was selected as the workhours per
piece (wh/pc). "While the material cost for structural steelwork is likely most dependent
on the weight of steel members, the labor installation cost may be more dependent on the
number of members to be placed. [7]"
An important element in model development is a source of consistent data whose
characteristics are known. Structural steel data was collected on nine low to mid-rise
projects. Table 1 lists the attributes of the projects included in the study. Daily data
collection and measurements were performed at the end of the work shift. Intermittent
visits to the site during the workday were performed to observe the crew and general site
conditions to supplement the data collection procedures. Production data and other
information were collected using physical measurements of completed work and from
observations. Brief discussions with crew supervisors identified or verified significant
problems, delays, interruptions, or disruptions that occurred during the day.

1.2 Data Characterization


Data are classified for further analysis according to the factors identified in the
"Procedures Manual [8]." Interruptions and disruption events were noted during data
collection. Interruptions are unplanned events or conditions that cause work to stop.
Examples of interruptions are strikes, accidents, and equipment breakdown. Disruptions
are unplanned events that impair crew productivity for a significant period of time. Work
does not come to a complete stop during a disruption, rather it proceeds at reduced
efficiency. Rainfall, rework, and poor material handling are examples of disruptions.
Disrupted and interrupted days are set aside from the model analysis data set to remove
the influence of large disruptions and interruptions in the model development. The
database contains 235 days of structural steel production recorded. Eighty (80) days have
been classified from the notes as disrupted workdays, leaving 155 workdays eligible for
factor model analysis.
52 Smith and Yu-Bin Lin

Table 1. Project Characteristics


Project Floor Area Steel Quantity Total
Number Project Type (sf) (pieces) Workhours
1 Classroom 10,816 642 1109
2 Condominium 13,000 496 902
3 Office 23,920 414 1256
4 Apartment 17,640 399 526
5 Apartment 10,926 86 152
6 Office 14,500 671 894
7 Commercial 45,000 408 891
8 Commercial 32,000 290 889
9 Medical Center 47,092 885 3020

1.3 Modeling
Project-related factors, weather zones, and crew sizes were evaluated using analysis of
variance techniques to determine the statistical significance of these factors prior to
including them in the model. After deciding which factors could be included in the
regression, the coefficients for the variables can be obtained though the regression
process. The effects of disruptions are addressed through an impact comparison to the
average non-disrupted productivity.

2 PROJECT FACTORS

Project factors are specific construction requirements, dictated by the design of the
project or construction methods, which can be identified from the plans and
specifications. In this study, project-related factors were classified as: Work Types,
Physical Elements, Design Details, and Construction Methods. Workdays are
classified according to the work performed that day.

2.1 Work Types


The Work Type category focuses on the structural system. Projects often progress
through more than one work type. This is associated with the work phase and work
type. Five classes of work types were included initially. Due to insufficient data in
some categories, only three Work Type factors were evident in the structures studied
are explained below. Table 2 lists the mean productivity for work types .

• Beam & Girder, Multistory - The structure has multiple floors with nearly identical
layouts. Floor loads are transmitted directly from the floor slabs to the steel beams
and girders.
Steel framing crew performance 53

• Beam & Joist, Multistory - The structure has multiple floors with nearly identical
layouts and floor loads are transmitted through web steel joists to beams and girders .
• Truss or Sloped Roof - Roof structure is not flat but is sloped. The roof system
wi11likely consist of roof purlins and metal deck rather than a concrete deck.

Table 2. Work Type Average Productivity


Work Type Number of Average
Observations (wh/pc)
Beam & Girder, Multistory 129 2.457
Beam & Joist, Multistory 22 3.437
Truss or Sloped Roof 4 6.285
Overall 155 2.695

An analysis of variance, with the data grouped by Work Type, indicates that there is a
statistically significant difference between the Work Types (F-ratio 12.527 and
Significance Level of 0.000). Two of the three work classes have relatively small
samples which were obtained from a single project and bias the response.

2.2 Physical Elements


Physical elements are structural components that can be identified from the
construction drawings. Each work day is classified based on the predominant physical
element used that day. Two physical elements classifications were used. Table 3
provides the mean values for these classifications. The classifications are:

• Beams, Columns, Girts, Bracing, etc. - Consists of regular shapes used in a


conventional manner .
• Trusses and Irregular Shaped Members - Work involving roof trusses, composite,
and irregular shaped members.

Table 3. Physical Element Classification Means


Physical Element Number of Average
Observations (wh/pc)
Beams, Columns, Girders 151 2.600
Truss/Irregular Shapes 4 6.285
Overall 155 2.695

The analysis of variance indicates a significant difference between these two factors (F-
ratio 18.053, Significance Level 0.000). This result is highly correlated to Work
Type.
54 Smith and Yu-Bin Lin

2.3 Design Details


Design details are specific features of the work that are more detailed than the physical
elements. Design Detail for this set of data pertains to different building heights
classified as the number of Tiers. Other than the mean productivity showing
improvement up to the 4th-7th Tier classification, little can be gained from detailed
analysis of the Tiers for this data. Analysis of variance indicated that some difference
can be identified between these groups (F-ratio 2.76 and Significance Level of 0.03).

2.4 Construction Methods


The Construction Methods classification indicates if any of the following circumstances
dominate the work on a particular day.

• Normal - No unusual methods or practices observed.


• Material Handling- Most of the day is spent performing material shakeout, stocking,
or resupply.
• Steel, Joists and/or Decking Together - Structural steel, joist and/or decking are
erected simultaneously by the same crew and the workhours cannot be separated.

The mean values obtained from this data classification are provided in Table 5.
Analysis of variance indicates there is a statistical difference between these group
means (F-ratio 12.968 and Significance Level 0.000).

Table 5. Construction Method Classification Means


Method Influence Number of Average
Observations (wh/pc)
Normal 129 2.391
Material Handling 4 3.530
Steel, Joist and Decking 22 4.323
Combined
Overall 155 2.695

3 OTHER FACTORS

3.1 Weather Zones


Weather information recorded with daily production included the temperature in
degrees Fahrenheit and the relative humidity. Precipitation events were also recorded.
The weather data was classified into three temperature ranges and three humidity
ranges. Those ranges create a matrix of nine weather zones. Analysis of variance was
performed for Temperature, Humidity, and Zones. While many other studies have
indicated weather has a direct influence, none of the analyses indicated a significant
effect by the weather. This may be due to the workers adjusting to the conditions or
Steel framing crew performance 55

other variability in performance is large enough to mask the effect of weather.

3.2 Crew Size


The distribution of crew sizes ranged from one to twelve workers. Analysis of variance
shows significant differences among the crew sizes, but with a great deal of inconsistency
in the responses. When considering the optimal structural steel crew size range, the job
site area and crane size should also be taken into consideration. This data was not
available for analysis. Therefore, crew size, until more variables affecting it are defined
and understood, should not be included in the model.

4 MODEL DEVELOPMENT
A stepwise regression analysis was used to determine the order of selection and which
variables would be selected for inclusion in the model. The stepwise model uses a
minimum F-value of 1.5 as the criteria to include or remove a factor from the model.
Table 7 summarizes the factor coefficients for the six variables included in the model.
The number in parentheses for the stepwise model indicates the order in which the
variables entered the model. The standard conditions of the model are:

• Work Type - Beam & Girder, Multistory


• Physical Elements - Beams, Columns, Girders, Bracing
• Design Detail - None
• Construction Method - Normal
• Weather-Zone 5 (Medium Temperatures 40°F-80°F and Medium Humidity 45 %-80%)

Table 7. Regression Model Coefficients and t-values


Factor Factor Coefficient t-value
(Selection Order)
Constant 3.45
Trusses or Sloped Roof 2.94 (2) 3.51
1st Tier -1.29 (5) 3.15
2nd-3rd Tier -1.77 (3) 4.58
4th-7th Tier -1.51 (4) 3.85
Steel, Joist and Decking
Together 1.90 (1) 4.49
Medium Temperature,
High Humidity 0.66 (6) 1.68
R-Square 30.85
56 Smith and Yu-Bin Lin

4.1 Model Evaluation


Qualitatively the results are consistent with the analysis of variance findings. The first
variable selected by a stepwise regression was the Steel, Joists and Decking placed
concurrently. The second variable included was the sloped roof and truss elements. This
factor will only be used in the event this particular type of work is encountered. Each of
the first two factors included in the regression represent fairly small data sets. Perhaps
the most significant factor group was the tier designations. The coefficients indicate that
productivity improves with increased floors. This is felt to be an influence of repetition
in the connections and consistency of the work activity. The final variable selected for
inclusion was the High Humidity, Medium Temperature zone. This shows a slightly
reduced productivity. High temperature and high humidity was not included due to a lack
of data.
An R-square of 30.85 shows that the model is a fairly weak predictor of the data set
from which it was derived. Since major disruptions have been set aside, the factor model
clearly indicates that there remains a significant amount of internal variability that is
unexplained.

5 DISRUPTION ANALYSIS

Table 8 summarizes the classifications of disruptions and the mean productivity value
determined for each set of data. Due to the small data sets for each noted disruption, the
results appear to be somewhat erratic. It would be expected that a disruption in
production would result in worsening productivity. In some cases the index shown here
would suggest improved productivity. The disruption index is the mean undisrupted
productivity divided by the mean disrupted productivity.

Table 8. Disruption Mean Values and Index


Type of Disruption Mean Value Disruption
(observations included) (wh/pc) Index
None (141) 3.20 1.00
Size/Layout of Material Storage Area (3) 6.57 0.49
Site Cleanliness (3) 2.53 1.26
Material Handling (4) 3.67 0.87
Material Availability (4) 5.12 0.62
Tool Availability (2) 4.89 0.65
Out of Sequence Work (8) 2.89 1.11
Rework/Fabrication Errors (8) 3.61 0.89
Equipment Availability (2) 0.55 5.85
Staffing (2) 2.33 1.37
Weather (8) 3.33 0.96
Steel framing crew performance 57

6 CONTROL CHART EVALUATION

While control charts are quite common in practice for quality control applications, it
was felt that they may provide a more relative measure for understanding project
productivity and variation. For this evaluation, the project with the most consistent
daily work output was selected as the basis for the mean and standard deviation. This
procedure provided more restrictive upper and lower control limits.
Figure 1 is representative of many projects that have only a few incidents that
significantly disrupt production. The average productivity for this project was lower
than the control chart mean, including the disrupted days. A large proportion of the
project data is noted as disrupted. The field notes indicate that this crew had many
tool and material problems, but the data plot would suggest that the crew compensated
for these problems and maintained a degree of control. Figure 2 illustrates a project
that was overwhelmed by disruptions. However, the project did have a series of days,
late in the project, that fall within the control region, which suggests that the project
had the potential to work within the control limits.
Superficially, the control charts can make average projects look fairly good.
Current upper and lower control limits range from 0.62 mh/pc to 3.19 mh/pc. This
wide range of "normal production" may cover a range that is too large for control
purposes. At this time much of the variability within this region is felt to be related to
the process itself and not necessarily to external factors considered by the models.
Whether the control charts can be useful for project control purposes is still
questionable because of the large variations permitted within the upper action limits.

DAIL Y PRODUCTIVITY
PROJECT 6
9 o Disruption Noted
~
.l 8 Within Limits
c:= ,
~

if) Disruption Noted


'" Outside Limits
>- 6
0-

> 5
u
~ 4
·0
UCL~3.190
- 3
0
CL
2 MU~1.904

LCL~0.6176
iJ
n 10 15 20 25 ItJorkday

Figure 1 Control Chart of A Typical Project


58 Smith and Yu-Bin Lin

DAIL Y PRODUCTIVITY
PROJECT 3
10
u
c-- 9
8
7
> 6
U 5
::J
-0
o 4
ct . 3 UCL=3.190
2 MU=1.904
LCL=0.6176
o
o 10 20 30 40

Workday

Figure 2 Control Chart for a Severely Disrupted Project

6 SUMMARY

The control charts show there is a great amount of fluctuation within "normal data"
which is not measured by the factors currently evaluated in the factor model. The
factor model and control charts demonstrate the difficulty of modeling performance
from field data. Large amounts of variation remain to be explained by either model.
However, the combination of techniques provides useful insight into improvements
needed in recording and measuring productivity at the project level for developing
forecasting tools.

7 REFERENCES

1 Thomas, H. R. and I. Yiakoumis, "Factor Model of Construction Productivity",


Journal of Construction Engineering and Management, ASCE, Vol. 113, No.4,
December 1987, pp 623-639.

2 Smith, G.R. and S. Kilroy, Operations Impact From Temperature and Humidity,
Proceedings of the Canadian Society for Civil Engineers 1994 Annual Meeting,
Winnipeg, Manitoba, Canada
Steel framing crew performance 59

3 Swank, Joseph. An Exploratory Study of the Effects of Crew Size on Productivity


in Masonry Construction. Master's Thesis, The Pennsylvania State University,
1989.

4 Sanders, S.R., An Analysis of Factors Affecting Labor Productivity in Masonry


Construction, Doctoral Thesis, The Pennsylvania State University, August 1989.

5 Pace, J.M., A Comparative Analysis of Work-Hour Forecastin2 Techniques at the


Crew level, Master of Science Thesis, The Pennsylvania State University,
December 1989.

6 Sakarcan, A. S., An Evaluation of Forecasting Capability of the Factor Model for


Masonry Projects, Master of Science Thesis, The Pennsylvania State University,
May 1992.

7 Adrian, J. J., Construction Estimating. Reston Publishing Co. Inc., Reston,


Virginia, 1982.

8 Thomas, H. R., M. W. Homer and, G. R. Smith. Procedures Manual for


Collecting Productivity and Related Data of Labor-Intensive Activities on
Commercial Construction Project: Structural Steel. December 1990.
ANALYSIS OF CONSTRUCTION DELAYS
T.M. Lewis
Department of Civil Engineering, University of the West Indies,
St Augustine, Trinidad
B.A. Atherley
Project Manager, W.W. Micron Ltd, Port of Spain, Trinidad

Abstract
This report presents the results of an investigation into the nature, length and cost of
delays, that occurred on thirty (30) building projects in Trinidad and Tobago.
This paper first discusses the circumstances that give rise to delays, the
classification of these according to responsibility and the effects they have on the
project cost and schedule. The data are presented, analysed, and conclusions drawn.

Sommaire
Ce travail present les resultats d'une recherche sur la nature duree et coilt des delais qui
se sont arrivee en trent (30) projets de construction a Trinite et Tobago. Ce travail
debatte premierement les circumstances qui donnent naissance aces delais, classifie
ceux-ci, selon la responsabilite et analyse les effets de ceux-ci sur Ie coilt et Ie progres
de chaque projet. Les donnees sont presentees, analysees et conclusions sont obtenues

Keywords: Delays, classification of delays, excusability, compensability,


responsibility, cost implications, survey, West Indies.

1. Introduction
When a piece of work is scheduled to be carried out on a particular day and for some
reason cannot be completed, a delay is said to have occurred. This may be of little
consequence, unless it affects subsequent work when it may become significant in
terms of both its planning and its financial implications. Significant delays that occur
during a construction project will either extend its duration or increase its cost or both.
In addition, if completion is delayed the client may also lose out financially by not
having the facility (and its potential income) available when wanted, and the contractor
may lose out by not having his resources released to take on other work.
Unfortunately, there are all too many factors that can cause delays to construction
work, from those inherent in the technology and its management, to those resulting
from the physical, social and financial environment. Because there are often financial

The Organization and Management of Construction: Shaping theory and practice (Volume Two).
Edited by D.A. Langford and A. Retik. Published in 1996 by E & FN Spon. ISBN 0 419 22240 5.
Analysis of construction delays 61

implications to delays, the parties involved are normally interested in determining their
causes and allocating responsibility. However, it is rarely easy to determine a unique
cause, or to allocate responsibility and this, naturally, leads to disputes between the
parties involved.
An assessment of delays should try to determine as many of the following factors
as possible, as these are inevitably the focus of disputes:
(a) what factor or factors caused the delay,
(b) who was responsible,
(c) how long was the delay attributable to anyone factor
(d) what extra costs were incurred as a result of a delay.
These are the factors that have been concentrated on here.
The standard forms of building contracts do not seem to be particularly well
designed for dealing with delays. As a result delays often lead to disputes, which can
easily lead to litigation aimed at trying to establish legal responsibility and allocate
additional costs. Because litigation is itself such an expensive and long winded
process, it is best avoided. If it is possible to identify the main causes of significant
delays then it may be possible to introduce contractual or policy measures which could
help them be avoided in future.
In order to investigate the structure of delays, their causes and the costs
associated with them, a survey was undertaken into experiences on a number of
construction projects (30) in Trinidad & Tobago over the period from 1979 - 1992. In
all cases, the projects were let by a client, used a design consultant, employed some
form of site supervision and were built by general and specialist contractors selected by
conventional tender methods. Taking a year that had statistics fairly typical of the
period, construction in Trinidad and Tobago for the year 1990 accounted for 8.8% of
the Gross Domestic Product (current prices) and for approximately 11% of the
employed labour force [6][7].

2. Definition and Classification of Delays


2.1 What is a Delay?
The traditional, and still the most common procedure for letting a contract is on the
basis of the lowest bidder. This contract document normally stipulates, amongst other
things, the starting date and a completion date for the project Problems which occur
during construction may cause a delay which results in the project duration being
extended beyond the scheduled completion date. On contracts which have interim
partial completion targets, a significant delay may occur when anyone of the target
dates is not met. There is also the disruptive element to consider, as delay in one
aspect may set back another aspect in a more than proportional amount, and this can
have a 'knock-on' effect
Most organisations are concerned with 'the bottom line', and the bottom line is
that a delay can increase costs and reduce profits. A delay may have direct cost
implications in terms of an extended construction period, which will mean extra
expense for the contractor in terms of salaries, plant and equipment expenses and
additional overheads. Depending on the cause, these additional costs mayor may not
be recoverable from the client, but this is only one part of the cost equation.
A delay may have implications which go far beyond the cost of the construction
phase of the project, because commercial or environmental 'windows' may not be
achieved. Such failures can have serious consequences in terms of the cash flow from
the project, because of additional financial charges to be met and lack of use of the
facilities being constructed. In the case of an offshore oil platform, for example, this
may mean loss of revenues in the hundreds of millions of dollars per week, and even
for a more normal commercial investment, the failure to meet a window of opportunity
like a peak seasonal deadline (e.g. Christmas) may change the project's whole
62 Lewis and Atherley

financial complexion. Because every project will have a different set of financial
implications associated with late delivery, little could be learned from attempting to
generalise from a few specifics. As a result, this investigation focuses on the
implications of delays on direct costs during the construction phase of projects.
As a result, because delays are both disruptive and expensive, they merit close
scrutiny.

2.2 Types of Delays


The general principle underlying a contract is that "a party under contract has an
absolute obligation to perform, barring breach or unfulfilled conditions by the other
side" [3]. Where one of the contract clauses stipulates a completion date, this becomes
one of the conditions of the contract that must be met, and, clearly, a delay may imply a
breach of that condition.
However, there are obviously circumstances when the cause of a delay is a factor
that is beyond the control of any party to the contract and it would be unfair to blame
one party for a breach. Thus, when examining delays, it is necessary to try to
establish where responsibility lies, and it is convenient to classify delays under three
main headings:
(i) Excusable delays,
(ii) Non-excusable delays,
(iii) Concurrent delays.

Taken from the viewpoint of the contractor, these classifications would be


expanded as,
(i) Excusable delays are those caused by unforeseeable factors outside the control
of the contractor. They may be either (a) Compensable excusable delays, i.e.
those for which the contractor is entitled to claim damages from the owner, or (b)
Non-compensable excusable delays, i.e. those for which no one can be held
responsible.
(ii) Non-excusable delays are those that are deemed to be the fault of the
contractor, because they were within his control and should have been
foreseeable.
(iii) Concurrent delays occur when two or more delays occur at the same time.

Any analysis is complicated by details, and when people are involved, details
proliferate. As an example of the sort of complications that can arise, the following
quotation is apposite: " ... suppose the owner failed to supply certain materials on time.
At the same time, the workers who would have installed the materials were on strike.
The contractor cannot claim damages for work that would not have been accomplished
had the owner-caused delay not occurred. He would, however, be entitled to a time
extension for the period of the strike unless it can be proved that the strike was due to
his own actions. This is an example of concurrent compensable and non-compensable
delays. The result is a time extension, but no damages for the contractor". [4]

3.Causes of Delays

3.1 Excusable Non-Compensable Delays


In the case of excusable non-compensable delays the following have been reported [3]
as being the most frequently given for excusing timely performance:
(i) Act of God - natural disasters such as earthquakes, tornadoes, hurricanes,
volcanic eruptions, floods and fire,
(ji) 'Force Majeure' (excepted or accepted risks) - all acts of God, war,
insurrection, riots, major labour strikes, Acts of the State,
Analysis of construction delays 63

(iii) Weather - when weather becomes unusually severe and surpasses the normal
(i.e. average conditions for an area over the previous ten years based on
meteorological data) for that particular locality during a specific season of the
year, it becomes a factor excusing delay.

3.2 Excusable Compensable Delays


Excusable compensable delays, which are attributable to the client, entitle the contractor
to an extension of time and a claim for damages. "The basis of recovery of damages for
delays is the implied obligation that the owner will co-operate with the contractor and
not impede the performance of the work of the contractor" [4]. Delays which are both
compensable and excusable are most frequently caused [3] by the following:
(i) failure to hand over the total site on time,
(ii) slow payments to the contractors,
(iii) errors in drawings and specifications,
(iv) late detailing of work,
(v) slow approval of fabrication drawings.

3.3 Non-Excusable Delays


Non-excusable delays are those deemed to be the responsibility of the contractor.
Thus, a contractor who extends his work beyond the original completion date for
causes which could be shown to be foreseeable and avoidable, is liable to the client for
monetary damages for the delay, in the form of actual or liquidated damages [4]. The
more common causes are reported [3] to be:
(i) failure to properly co-ordinate men, materials and equipment,
(ii) failure to properly finance the project,
(iii) failure to submit shop drawings promptly,
(iv) failure to employ competent personnel.

4. Effects of Delays
A delay tends to act like a virus - very slowly, but with far reaching effects. Like the
symptoms of a virus, there are symptoms which are indicative of a situation developing
which may lead to a delay, they are:
(a) a general slowing down of the job,
(b) inefficient use of the weather, i.e. not using dry weather effectively,
(c) improper sequencing of activities, leading to work stoppages on some tasks

In an attempt to solve these problems there is a tendency to want to accelerate the


work. However, acceleration is no guarantee that the job is going to be finished on
time, and it is almost certain to increased costs because it usually involves on of the
following:
(i) increase of the labour crew,
(ii) increase in the working hours of the present crew,
(iii) sub-contracting out sections of the work to specialists,
(iv) hiring more equipment or more up-to-date equipment,
(v) any combination of items (i) to (iv).

The increased cost of accelerating a job must be carefully considered by both the
client and contractor before the decision is taken. The contractor may favour
acceleration of the job at his own expense if he feels that he may be held responsible
for the delay and:
(i) the liquidated damages are more costly than acceleration,
(ii) certain operations are heading for an unfavourable time of year,
(iii) the same men and equipment are needed on another job,
64 Lewis and Ather/ey

(iv) specialist trades/services may be delayed and higher costs incurred.

The client may favour acceleration of the job at his own expense if he feels that he
is responsible for the delays and:
(i) he will have to pay penalty costs to the contractor for extending the period,
(ii) the original completion date has special significance,
(iii) the project will suffer a loss of profits greater than the cost of acceleration

In some cases, in the interests of goodwill, and where both parties perceive it to
be to their benefit, the costs of acceleration may be shared between owner and
contractor. It is also possible for delays to have a positive side effect, as when delays
are apparently inescapable, and the effects are sufficiently costly, the parties to the
contract may be inspired to seek new and innovative means of avoiding them. The
solutions that evolve may enable future problems to be avoided.
The worst effect of delays to a construction project is the termination of the
contract by either party. It is normally a last resort action taken by an owner, who
terminates the contract for excessive non-excusable delays. Any such termination must
take place within the legal framework of the contract.

5 Standard Contract Provisions For Delays


Claims can arise for many different reasons and between any of the parties involved in
or affected by a contract, however, this paper seeks only to examine the claims
between client and contractor resulting from delays on contracts using the most
common locally employed contract documents, i.e. the Trinidad and Tobago Institute
of Architects (TTIA) [8], standard form of building contract (with quantities-I974
edition) and the ICE (Institution of Civil Engineers) conditions of contract [2].

6 Analysis Of Delays From 30 Projects


The data collected are all from professionally designed and supervised projects, which
used the more common standard forms of building contracts. While the thirty (30)
projects studied were not sufficient for a statistically significant analysis, the sample
size was large enough to suggest trends in the data, and those trends are compatible
with results obtained from a study of the nature and extent of variations to building
contracts in Australia [1].

6.1 Accuracy and Consistency of Data


The data collected were for projects done between the years 1978 to 1992 inclusive.
There is no significance to be attached to these years, other than that more up-to-date
data were not available.
The details of the actual delays were reasonably well recorded because the
projects had used bar charts which had been regularly updated. The contract documents
required that scheduling techniques should be used and bar charts were all that were
used on all except two jobs. Hence, whether the information came from the contractor
or the consultant the point of reference was always the contractor's bar chart.
As far as the costing of the delays was concerned big differences were observed
between the contractors' records and those of the consultants. Where quantity
surveyor's letters were available, they were the points of reference for both parties,
since in most cases they detailed the sums in question. In their valuations, however,
the contractors tended to lump the cost of supervision, extra work, additions and
variations together, and to cost delays on the basis of what they spent directly to get the
job done rather than to try to break-down the cost of the work into elements and
Analysis of construction delays 65

associated overheads. By comparison, the consultants tended to try to identify items of


work associated specifically with the delays, broken-down into their elements and
valued at rates given in the bills of quantities, and these valuations were used to review
the contractors' claims with a view to their acceptance, rejection or reduction to
'acceptable' levels. Consultants did not normally increase bill rates or overhead
allowances to account for extra time required on the project.
It was rarely possible to check data on a specific delay with both consultants and
contractors involved because a questionnaire approach was used to collect data and it
was not possible to get responses on the same project from both. Personal interviews
were conducted with all but one respondent in order to discuss the details of the
projects and the delays involved, and a telephone interview was conducted with the
other respondent.

6.2 The Basic Data


The data was obtained from seven organisations representing a spread of interests in
the construction field. Their distribution and the number of projects analysed from
each were as follows:

lI-roup Type Projects


Consultants - Engineering firms (2) 8
Architectural firm 2
Contractors (2 independent firms) 12
Project Manager 7
Government - Ministry of Drainage 1
:ill

Table 1 lists the clients, the total cost of the contract, the total number, the total
cost and the total length of delays on each contract. All costs and values, are quoted in
Trinidad and Tobago dollars (approximately TT$6 =US$I).
The figures show that on contracts worth $56,626,485, 95 significant delays
occurred, the delays cost $4,561,963 and involved 424 lost weeks of work. The cost
of delays represents approximately 8% of the overall cost of the contracts. The total
cost shown is the cost of the particular contract involved, not of the entire project, for
example, the Hall of Justice (project #21) had an overall cost of over TT$400 million,
while the painting contract reported here was worth TT$1.4 million. All these projects
were professionally designed and supervised.
Table 2 gives a more detailed breakdown of the 95 specific delays that were
reported on the 30 projects. Briefly summarising the data in Table 2, 57 of the delays
were deemed excusable and compensable, and these delays accounted for $4,333,972
of extra cost and 290 extra weeks of work. The delays which were deemed to be non-
compensable numbered 38, and these accounted for $227,991 of extra cost and 132
weeks of extra work.
Included amongst the excusable/compensable figures are two items recorded as
"Claims for loss and expense". These account for $580,000 of extra cost and no extra
time. These were claims put in by the contractors for extra payments against increased
overheads and loss of other work, which were caused by their being delayed on a job
(for reasons deemed excusable/compensable), but not having claimed this
compensation against any other specific delay.
A degree of consistency was achieved in the analysis because in most cases the
description of the details and the nature of the delay were agreed between the
respondentsand the conductor of the survey.
66 Lewis and Atherley

Project/Client
-
TABLE 1 A n allysIS
. 0 f P roJects
Total Cost Total Total Cost Total
($) No. of of Delays Length
Delays ($) of Delay
(wks)
1. Housin1! Development 8,600,000 2 250,000 48
2. Housing Development 8,400,000 2 210,000 36
3. Bus Terminal 7,000,000 5 210,000 48
4. *M.o.W. Drainage Division 35,000 1 2
5. *U.W.I. Inflammable Stores 263,647 3 3
6. *U.w.I. Environmental Lab. 488,782 3 15,836 13
7. *U.W.I. Fluids Lab. 412,734 4 12,000 12
8. *D.W.I. Offices and Classrooms 1,330,716 4 259,724 4
9. *D.W.I. Electrical and Electronic Lab 948,133 5 82,767 13
10. Ghany Site 21,000 2 12,700 4
11. Ishmael Khan 63,000 2 16,000 8
12. Trinidad Cement Limited 63,000 3 8,000 4
13. National Petroleum Ltd. 5,800 1 2.5
14. Print Masters 29,440 1 4
15. Associated Bnmds 12,000 1 3
16. *T.S.T.T. 29,000 1 5
17. *NIHERST 46,000 1 1,285 2
18. Government Health Center 23,530 1 4.5
19. *U.W.I. Offices and Classrooms 2 12,628,046 5 278,591 16
20. Colsort Mall 450,000 6 190,000 14
21. Hall of Justice 1,400,000 5 1,060,000 29
22. Farrell House 150,000 7 75,000 28
23. *U.w.I. Hi1!h Volta1!e Lab. 878,810 8 465,000 43
24. *D.W.I. Food Technolo~ Lab. 3,909,682 7 845,012 36
25. Scotia Bank Not available 4 8
26. Free Zone 1,600,000 2 4
27. Bank of Commerce 2,300,000 2 4
28. *TELCO Head Office 4,800,000 3 500,000 16
29. Hand Arnold 580,000 2 50,000 6
30. *D.W.I. FoodProcessin~Lab. 158,165 2 20,048 4
Totals 56,626,485 95 4,561,963 424
.. ..
*M.o. W. - Ministry of Works, Government of Tnmdad & Tobago
* U. W.1. - University of the west Indies, St. Augustine Campus
*T.S.T.T.- Telecommunications Services of Trinidad and Tobago Limited
*NIHERST - National Institute of Higher Education (Research Science & Technology)
'TELCO - Telephone Company
Analysis of construction delays 67

TABLE 2 - NATURE, TYPE, COST AND LENGTH OF DELAYS


Project Nature of Delay Type Cost Length
No. * ($) (wks)
1. Payment delays by client E/C 150,000 24
Part of si te not available E/C 100,000 24
2. Part of site not available E/C 100,000 12
Payment delay by client E/C 110,000 24
3. Poor work sequencing by contractor NE
Procurement failures by contractor NE 24
Lack of manpower by contractor NE 16
Payment delay by client E/C 60,000 8
Extra works E/C 150,000
4. Heavy rains/floodin2 of iob site E/C 2
5. Subsurface different than expected E/C 0.5
Heavy rains ElNC 1
Procurin2 failures by subcontractor NE 1.5
6. Additional work demanded by client:
Furniture changes E/C 8,000 8
Equipment changes E/C 2,375 3
Structural work E/C 5,461 2
7. Additional work demanded by client:
Plumbing changes E/C 3,000 3
Structural Work E/C 4,229 3
Electrical Work E/C 3,000 4
Cupboards chan2ed E/C 1,771 2
8. Errors in plans & specs. E/C 22,784
Ambiguities in plans and specs. E/C 35,896
Change sequence by contractor NE 20,000
Additional work by owner E/C 181,044 4
9. Ambiguities in plans & specs. E/C 3,250 1
Oruissions in plans & specs. E/C 19,637 4
Errors in interpretation (floor finishes) ElNC 4,200 2
Additional work (client brief) EIC 22,142 2
Chan2e order by new client EIC 33,538 4
10. Change sequence by contractor NE 1
Utility not available by owner E/C 12,700 3
11. Change method by contractor NE
Poor scheduliDR of work bv contractor NE 16,000 8
12. Change method by contractor NE
Utility not available by owner E/C
Redo work by contractor NE 8,000 4
13. Change sequence by contractor NE 2.5
14. Procurement failures by contractor NE 4
15. Lack of productivity by contractor NE 3
16. Lack of productivity by contractor NE 5
17. Additional work b~_dient E/C 1,285 2
18. Chan2e sequence by contractor NE 4.5
19. Heavy rains ElNC 18,591 1.5
Oruissions in plans & specs. E/C 160,000 2.5
Procurement failures by contractor NE 36,000 4
Consultants change scope of work E/C 60,000 4
Late power supply connections E/C 4,000 4
68 Lewis and Atherley

TABLE 2 (Continued)
Project Nature of Delay Type Cost Length
No. * ($) (wks)
20 Errors in plans & specs. E/C 12,400 1
Ambiguities in plans and specs. E/C 14,600 1
Omissions in plans & specs. E/C 23,700 2
Strike by General Contractor E/C 10,000 4
Additional work E/C 102,300 4
Redo ftnished work NE 27,000 2
21. Ambiguities in plans & specs. E/C 106,000 2
Omissions in plans & specs. E/C 170,000 3.5
Day works E/C 200,000 4.5
Extra painting/variations E/C 500,000 17
Redo ftnished work NE 84,000 2
22. Heavy rains EtNC 1,000 3
Omissions in plans & specs. E/C 4,000 2
Change in sequence by contractor NE 4,000 2
Procurement failures by contractor NE 3,000 2
Strike by main contractor E/C 2,600 8
Redo work damaged by strike E/C 10,000 4
Additional work by client E/C 50,400 7
23. Errors in plans & specs. E/C 20,000 4
Ambiguities in plans & specs E/C 5,000 3
Omissions in plans & specs. E/C 100,000 7
Procurement failures by contractor NE ** 4
Procurement failures by contractor NE ** 4
Additional work by client E/C 260,000 20
Late shop drawing approval by consultant EtC ** 1
aaim for loss & expense E/C 80,000
24. Errors in plans & specs. E/C 17,750 4
Ambiguities in plans & specs. EtC 15,000 4
Omissions in plans & specs. EtC 31,948 2
Heavy rains no work EtNC ** 4
Procurement failures by contractor NE ** 4
Additional work E/C 280,314 18
aairns for loss & expense EtC 500,000
25. Poor means of sequencing by contractor NE 2
Procurement failures by contractor NE 2
Procurement failure by subcontractor NE 3
Poor scheduling of work by contractor NE 1
26. Procurement failures by contractor NE
Lack of manDOwer NE 4
27. Poor work sequencing by contractor NE 2
Lack of space at site meetings ? 2
28. Slow change in project brief requirements E/C 4
Poor work sequencing by contractor NE ** 6
Additional work by client E/C 500,000 6
29. Poor work sequencing by Contractor NE 6,200 3
Additional work E/C 43,800 3
30. Errors in plans & specs. EtC 2,200 2
Additional work bv client E/C 17,848 2
• EtC =Excusable Compensable; EINC =Excusable Non-Compensable; NE =Non-Excusable
** Difficult to quantify
Analysis of construction delays 69

6.3 The Data Collected


Given that some computation was necessary on the part of the respondents to separate
information related to the delay from the rest of the stored information, it was
gratifying to receive data on thirty (30) projects. The data covered some ninety five
(95) recorded delays caused by a fairly wide range of factors. Seven (7) individual
organisations were involved, and they provided information on projects as shown in
Table 2.

7. Discussion of Results
During the interviews with those involved, it was felt that the projects analysed here
were not untypical of the projects being constructed in Trinidad and Tobago at that
time, in other words, they were neither worse nor better than average in the number of
delays that they suffered.
Although each case study represented a 'project' to the company concerned, they
did not all represent complete projects to the clients involved, e.g. the painting contract
for the Halls of Justice was a project to the contractor, but only a very small element of
the total project to the client. This was not expected to make any difference to the
conduct of the work either by the contractor or by the client or his representative, or to
affect the results of this survey.
It is clear that the majority of the delays which were detailed fell into the category
'compensable excusable'. This bias almost certainly resulted from the fact that the
contractors would have been much more aware of the need to fully document delays
which they felt they could claim compensation for. Equally, the consultants would
have been aware of the contractor's intention to claim and would also have recorded
relevant details.
The non-compensable delays are made up of the portion of the delays that were
claimed for but rejected, as well as the delays that were recorded in diaries and minutes
of meetings but not claimed for. In no cases did the client enforce the 'liquidated
damages' or penalty clauses which were in the contract documents, even though very
significant delays (over 40 weeks) were experienced on some of the contracts.
Where values have been given for non-excusable or non-compensable delays
these figures were either on record as claims or were derived from the actual costs
involved in redoing work, or in accelerating the work to get it back on schedule.
One overall pattern that did emerge was that main contractors suffer more delays,
and more costly delays than subcontractors. This may have simply been a scale related
fact i.e. the more work you do the more likely you are to experience problems (which
seems to be substantiated in the related finding that larger jobs tended to have more
delays than smaller ones), or it may have been to do with the timing of their
participation in the works. The main contractor is likely to be involved earlier in the life
of a project, and hence at a time when it is likely to be least fully finalised, and when
the site is least prepared - subcontractors tend to get involved later on when things have
settled down, and problems causing delays are less likely to arise.
The general economic climate during the period under study was one of recession
and high levels of unemployment, and this generally tended to keep industrial action to
a minimum. Only two projects were affected by strike action, and in both cases it was
the work of the subcontractor being delayed by a strike affecting the main contractor
that was recorded. As a result, in those two instances, what would otherwise have
been an excusable but non-compensable delay became compensable as the
subcontractor claimed against the main contractor.
By far the largest factor leading to delays was the client requiring changes or
additions to be made to the project. If the 'top ten' causes for delays (by additional cost
incurred) are listed (see tabulation below) it will be seen that the quality of the drawings
and specifications that the contractors' had to work with appeared to leave much to be
70 Lewis and Atherley

desired. When the omissions, ambiguities and errors (items 4,7 & 9) in these
documents are added to variations required by the consultants, they accounted for
claims amounting to $1,528,365 and for delays totaling 72.5 weeks.
The consultants who were interviewed indicated that this was not a fair reflection
of their performance or competence as most of the variations and the problems with
drawings and specifications arose because of late design changes that emanated from
the clients. They, the consultants, had to respond and make the desired changes, and it
was this which caused the delays and cost increases.

# Nature Cost (:Ii) Length


1 Additional work by client 1,636,970 99 weeks
2 Variations by consultants 760,000 25.5 weeks
3 Claims for loss and expense 580,000
4 Omissions in drawings & specs. 509,285 23 weeks
5 Late payment by client 320,000 56 weeks
6 Unavailability of whole or part of site 212,700 39 weeks
7 Ambiguities in drawings & specs. 179,746 11 weeks
8 Redo work damaged by other trades 129,000 12 weeks
9 Errors in drawings and specs. 79,334 13 weeks
10 Poor scheduling or change of sequence 46,200 32 weeks

It should also be added that during recessionary times the process of decision
making on capital investments tends to slow down, as a result of this the period over
which the design process takes place tends to expand. In the projects examined, for
example, the design of project 19 (University buildings) took 5 years from conception
to tender. Given the rate of technological change, it is hardly surprising that the client
required changes to be made to the project definition between the time of the brief and
the tender and before the completion of the building when such time scales are
involved.

In addition to this, as Bromilow has noted "... Variations are needed to help the cost
steering process and to cope with new ideas, changes in technology and mistakes; they
are, contrary to the view of many, an inevitable part of the building process. "[I] We
are dealing with delays rather than variations, but in practice, they tend to be
interdependent. Delays are often a consequence of variations;

During recessionary times the pressure to meet cost targets increases, and this leads
clients to 'tinker' with their projects in order to try to effect savings. For example, on
this particular project, in the original design (carried out during the boom years) all
services were centrally controlled, there were not even light switches in the individual
rooms. With the onset of the recession before building got under way, increasing
awareness of the need to control energy costs led the client to demand a revision of the
design to allow lights to be switched off in each room. Such 'cost steering' variations
led to design changes, which led to delays. Although the effect of such tinkering may
be delays and extra costs in the short term, in the longer term they may well be cost
saving, and hence very cost effective.

8. References
1. Bromilow, F. J. (1969). Measurements and Scheduling of Construction Time
and Cost Performance in the Building Industry. Report of the Division of
Building Research Division. CIRlA: Melbourne.
Analysis of construction delays 71

2. ICE Conditions of Contract. (1979). Conditions of Contract and Forms of


Tender, Agreement and Bond for use in Connection with Works of Civil
Engineering Construction. 5th ed., London: The Institute of Civil Engineers.
3. Richter, I. E. (1983). International Construction Claims: Avoiding and Resolving
Disputes. New York: McGraw-Hill.
4. Rubin, R. A., Guy, S. A. and Maevis, A. C. (1983). Construction Claims
Analysis, Presentation. Defence New York: VanNostrand Reinhold.
S. Stokes, M. (1977). Construction Law in Contractors' Language. New York:
McGraw-Hill.
6. Trinidad and Tobago. Central Statistical Office. (1992). Review at the Economy
l!l!lL Port of Spain: Government Printery.
7. Trinidad and Tobago, Central Statistical Office. (1992). Annual Statistical Digest
1990' No. 37 Port of Spain: Government Printery.
8. Trinidad and Tobago Institute of Architects. (1974) Standard Form of Building
Contract with Quantities. Port of Spain: Trinidad and Tobago Institute of
Architects.
CLIENT BENCHMARKING OF
CONTRACTOR PERFORMANCE
D.8aldry
Department of Surveying, University of Salford, Salford, UK

Abstract
Substantial clients of construction with extensive development programmes invariably
employ a range of contracting organisations. Some clients, notably in the public sector,
may employ widely from an extensive panel of contractors, whereas others may adopt
an approach in which a single or limited number of contractors are engaged for the
completion of a programme, in a manner which has become known as partnering.
Notwithstanding the procurement approach adopted there is an ongoing necessity for
clients to have some means of objectively assessing the performance and reputation of
these contractors as a way of evaluating current activities and also influencing future
procurement directions.

Benchmarking has emerged as a means by which participants in an industrial or


commercial process may monitor performance by reference to verifiable evidence from
comparable activities, posSloly derived from some mutual information sharing
agreement. This paper examines ways in which significant construction industry
employers may adopt this process as an integral part of their procurement decision
making and action as a means of enhancing project performance and predictability.
Keywords: Benchmarking, contractors, performance, procurement

Sommaire
Des clients importants de l'industrie de la Construction, ayant de vastes programmes de
developpement, emploient en general une gamme d'enterprises de sous-traitants.
Certains clients, du secteur public notamnent, peuvent employer a grande echelle a
partir d'un large panneau de sous-traitants, alors que d'autres, peuvent adopter une
approche dans laquelle un seul sous-traitant est engage, ou bien il est fait appel a un

The Organization and Management of Construction: Shaping theory and practice (Volume Two).
Edited by D.A. Langford and A. Retik. Published in 1996 by E & FN Span. ISBN 0 419 22240 5.
Client benchmarking of contractor performance 73

nombre limite de sous-traitants pour terminer un programme, ce qui s'est fait connaitre
sous l'appellation de partenariat. Bien qu'il s'agisse d'approvisionnement, ou demande
d'achat, les clients doivent, en permanence, etre en mesure d'6valuer objectivement
l'execution et 1a reputation de ces sous-traitants, de maniere Ii 6valuer les activites
courantes et aussi Ii influer sur les orientations de l'approvisionnement futuro

L'evaluation des performances a fait son apparition comme moyen par lequel des
participants Ii un processus industriel ou commerciel peuvent piloter les performances,
en se referant a une evidence verifiable Ii partir d'activites comparables, peut-etre
derivee d'un certain accord sur Ie partage mutuel de l'information. La presente
communication examine les fayons dont les employeurs importants de l'industrie de 1a
construction peuvent adopter ce processus en tant que partie integrante de leur prise de
decision d'approvisionnement et d'action, et comme moyen de rehausser les
performances du projet et sa fiabilite.
Mots cles: Evaluation des performances, sous-traitants, performances,
approvisionnement

1 Introduction

Benchmarking as a term has a long history of application in the construction process,


being derived as it is from the technique used by map makers and surveyors to measure
a current position against an identified landmark or reference point known as the
"benchmark". In more recent times the term has become analogous to the business
process of establishing best practices, improving management systems, and providing
an aid to strategic procurement activities. For supply side organisations the process has
provided the means for observing in a disciplined manner the methods and practices of
others, both within a particular industry or area of commercial activity and also beyond
to other areas which offer methods and techniques which would be capable of beneficial
transfer, the intention being to adopt and adapt the most successful modes of operation
in order to pursue competitive advantage. For demand side organisations the approach
offers a way of developing a rigorous approach to supplier evaluation, applicable at pre-
contract, current, and post-contract stages, and as a means of assisting in critical
decision-making to optimise the procurement outcomes in terms of value for money,
certainty of performance, and operational reliability.

Benchmarking is characterised by a variety of definitions; Cousins [1] identifies a


number such as that of the Xerox Corporation which is one of the organisations
credited with the founding application of the approach:

"the continuous process of measuring products, services, and practices against the
toughest competitors or those companies recognised as industry leaders"

Ajoint definition from Coopers and Lybrand and the CBI states:

"the process for comparing business practices and performance levels against other
companies"
74 8a/dry

Cousins goes on to paraphrase the latter definition as:

"the process for comparing business and performance levels against others and
providing reassurance as to the validity of existing methods and costs or suggestions
for improvements as appropriate"

The tone and content of these definitions lean heavily towards supply side issues in
terms of references to competition, relative performance, and costs of production, with
an emphasis upon the ongoing continuity of the process. The operational relevance of
so much benchmarking activity may explain the alacrity with which the facilities
management industry has adopted this approach as a means of comparing and
evaluating a plethora of measurable performance indices (Varcoe [2]). However the
respective performance of organisations must extend beyond readily measurable
indicators of performance and present a profile of the totality of an organisation. France
[3] offers a quotation from Manton, an acknowledged expert in the benchmarking field,
who states "A company or industry .......... must focus not just on numerical
comparisons but on business vision, business strategy, management processes and
current best practice".

For a commercial client the process of benchmarking offers the opportunity for a
structured means of comparing and evaluating supplier characteristics as an aid to
developing a procurement strategy capable of delivering reliable and superior
performance. A well considered benchmarking process should allow a client to focus
upon those issues of supplier performance which are critical to the successful
accomplishment of client organisational objectives. For regular or prospective clients of
the construction industry a benchmarking mechanism allows for appropriate weightings
to be applied to contractor performance in terms of price competitiveness, programme
reliability, technical expertise, experience of building type, product quality, claims
awareness, etc., to reflect the significance of these issues for the project sponsors
primary business.

2 Expectations of Construction Clients

Sponsors and clients of construction services vary in their level of experience,


sophistication, and degree of awareness of the construction process and marketplace.
All however are seeking some degree of reassurance that the procurement decisions
that are made, and in particular the selection of contractual supply partners, are those
which are most likely to result in a high level of customer satisfaction. Chicken [4]
suggests that major decisions are not the product of a single event or action but arise
from protracted discussion, investigation, and consideration. The final decision is often
the product of a whole series of subsidiary decisions and the interaction of several
interested parties. The making of critical project decisions is a fundamental element of
the project sponsor's duties. Gorog [5] describes the strategic decision points in the
project process which largely determine the degree to which organisational objectives
Client benchmarking of contractor performance 75

are realised, the selection of supply contractors having a profound influence upon
project performance and outcomes.

The factors which can be identified which will influence the process of contractor
selection by the project sponsor may be stated as:

• General level of sponsor expertise and experience of the construction process


• Specific expertise in innovative or unorthodox procurement methods
• Awareness of supply organisations and their apparent capabilities
• Access to professional advice either in-house or externally commissioned
• Statutory controls over contractor qualification notably as set by European Union
codes
• Organisational policy over contractor qualification particularly in the public sector
• Organisational requirements for project performance priorities

When proposing to sponsor construction activity the client organisation enters a


process of selectivity to determine the supply organisation which will be finally
appointed as contractor to the project . This selection may take one of a number of
forms as determined by the procurement process of the sponsoring organisation:

• identification of a single contractor organisation with whom the sponsor intends to


enter into a negotiated contractual relationship
• formation of a restricted panel of selective contractors required to compete for the
project on a number of criteria, commonly price, but also possibly including
resource capacity, design skills, management expertise, or funding capability
• facilitation of an open tendering process in which a large number of responding
contractors compete for the project having normally first satisfied some
prequalification criteria

Whichever procurement approach is adopted there is an overriding requirement for


the project sponsor to be in possession of expert intelligence as to the characteristics,
merits, drawbacks, and performance record of potential contractors. An active and
effective process of benchmarking can provide the mechanism for determining criteria
against which past performance and current capability may be measured, for
establishing a set of minimum standards as a means of testing for prequalification, and
for forming the basis for negotiation in respect of risk allocation, range of services to be
provided, and the terms of the contractual relationship to be formed.

3 The Benchmarking Process

Benchmarking is commonly applied to key operational processes within a business to


determine those critical factors which create organisational success. The majority of
benchmarking activity has been in the form of peer assessment in which a supply side
organisation measures its capabilities, competencies, and ultimately its performance
outturns, against relevant and appropriate companies often from within the same
76 Ba/dry

industry. Codling [6] has identified how three distinct types of benchmarking have
evolved from mutual information sharing relationships:

• Internal - intra-company comparisons of practices and procedures to promote


harmonisation of perceived best practice.

• External - information exchange for mutual advantage occurring amongst


organisations within the same industry or on occasions across a range of industries.
This process often utilises the services of a third party organisation to moderate
information and, if required, to maintain confidentiality of participants.

• Best practice - the seeking out of the undisputed leader in a specific business
process which is critical to organisational success. Competitive forces may mean
that this approach often requires a partnership relationship to be developed with a
leading organisation in an alternative relevant industry to that occupied by the
benchmarking organisation.

It may be recognised from the above that the intensity of benchmarking activity
occurs within organisations which are part of a product or service supply chain, being
both providers and procurers of resources and key components. For an organisation
which is dominantly the end consumer of goods or services, such as the sponsor of
construction project services, the process requires adjustment and refinement to reflect
the external location of the client organisation, its limited direct access to market
intelligence, and its often infrequent and occasional participation in the procurement
process.

As has been noted the application of benchmarking techniques has been widely
adopted in process industries and., in particular, taken up with enthusiastic vigour by the
rapidly expanding facilities management industry which is largely building related in its
activities. Some particular difficulties do emerge however when applying the process to
a project based industry such as construction which do need to be overcome if optimal
benefits are to be derived. An opposing view to this is held by Karlof and Ostblom [7]
who propose that the project form of organisational activity is highly suited to the
application of benchmarking techniques as the formation of an optimal ad hoc team
with specialised qualifications offers flexibility and the ability to operate outside regular
channels without being hampered by organisational formalities. Nevertheless difficulties
do exist which to some degree distinguish construction from other industries and
include:

• very few projects are alike given the variety of locations, participants, and product
content
• projects are invariably conducted by teams of participants assembled for the
duration of the project only and which are broken up on completion
• the supply side of the industry is highly fragmented both in the number and diversity
of available organisations
• some project sponsors are regular and frequent commissioners of construction
services whilst others take part once-in-a-corporate-lifetime
Client benchmarking of contractor performance 77

• the highly competitive and commercial nature of construction activity does not
encourage either supply or purchasing organisations to be forthcoming with
information
• the data generated from construction activity may be complex and variable and
subject to differing interpretation
• the application of benchmarking in construction has only minority penetration to
date resulting in a lack of knowledge and enthusiasm for its potential and often
being limited to cost comparisons only

If these obstacles to effective benchmarking are to be overcome a prerequisite is an


improved industry wide culture of confidence and mutual trust, a condition which the
industry has largely avoided during its modem history. Hawke [8] highlights a quotation
from the Editor of Building magazine on the occasion of that journal's 150th
anniversary: ".... one theme comes twinkling through, the unchanging nature of human
behaviour. Professional jealousy, competitive friction, and contractual wrangles
preoccupied the Victorian building industry." Similarly Powell [9] identified how the
cultural image of the contemporary construction industry was working against the
formation of values of trustworthiness and integrity. The development and growth of
benchmarking is dependent on the existence of an atmosphere of co-operation, which
does not necessarily lead to a diminution in competitiveness, but may prove to be a
mechanism which is instrumental in assisting the creation of such a culture.

4 A Benchmarking Process for Construction Clients

Construction clients are commonly obliged to enter into demanding contractual


relationships with organisations with whom they have had limited contact and of whom
they have incomplete and inadequate knowledge. Construction projects contain a high
level of risk for both primary contracting parties, at a level which in some extreme
circumstances could threaten the survival of the organisation if a major risk impact was
to occur. Sponsorship of a major construction project requires the client organisation to
make significant decisions, notable of which is the selection of the contracting supply
partner (Chicken [4]).

For major projects a process of prequalification is often implemented which is


designed as the first part of a two stage process which requires putative tenderers to
satisfy some basic criteria to test suitability and capability to tender and to execute the
contract. Alternatively clients who are regular participants in the construction
marketplace may retain a continuing "approved" list of vetted contractors from which
an appropriately sized panel oftenderers may be drawn for a specific project. This latter
approach is a common occurrence in the public sector as described by Latham [10] who
particularly notes the CMIS list held by the Department of Environment to which
private clients may have access to determine whether a specific contractor is held on
that list. Latham goes on to comment how the preparation and maintenance of a
multitude of lists represents a wasteful duplication of effort which significantly adds to
client costs. To mitigate these costs some client organisations have attempted to levy
charges on contractors for admission to an approved list, an approach which has raised
78 8a/dry

the ire and contempt of contractors and their trade associations. The conclusion of
Latham is that it would be appropriate for the DOE to develop the CMIS scheme as a
centralised national resource to assist clients and their advisers to determine contractor
competence against a range of performance criteria.

From a client's perspective this paper suggests the following essential elements of an
effective scheme for benchmarking contractor capability:

• Comprehensive - containing an adequate range of contracting organisations to meet


the clients requirements in terms of frequency of contracting intentions,
geographical spread, and typical characteristics of contracts

• Interactive - capable of presenting the client with choices and alternatives with
which the client may engage to customise a search process

• Regularly updated - able to illustrate the most current and meaningful information
of contractor performance and capability

• Targeted - capable of allowing the client to select appropriate specialist contracting


organisations to serve expressed needs and requirements

• Economic - demonstrate ease of access and a reasonable cost profile so as to


promote regular and widespread utilisation

• Reciprocal - encourage participative feedback from client participants on contractor


performance and capability in a form which is defenSlole, appropriately confidential,
and which indemnifies contn"butors against actions in tort

The establishment of a national database of contracting organisations offers the


possibility for the assembly of factual and measurable information together with
verifiable value judgements to assist prospective clients to identifY those companies
which would prequalify for consideration for bid or negotiation opportunities by
satisfying whichever set of performance criteria the client wishes to impose, in addition
to those imposed by some other agency such as the European Union Works and
Services Directives. In this way a client may impose as it's benchmark standard the
highest degree of satisfaction level which may be achieved in those success criteria
which are most critical to itself and against which it would be posSlole to identifY those
companies whose performance record and verified capability came closest to matching.
The outcome of this approach would be to add an additional option to the range of
benchmarking approaches, as noted earlier in this paper by reference to Codling [6],
that of most desirable practice which would be an abstract achievement which mayor
may not be attained by any participating supply organisation but which exists as a pure
benchmark of performance.

Any database formed would be a combination of factual and evaluated information


derived from both the participating contracting organisations themselves and former
clients. Herein lies a particular dilemma as to the degree of access which should be
Client benchmarking of contractor performance 79

made available to contractors to verify the factual data on record and update if
necessary, and, if deemed appropriate, to examine the performance values placed
against them by contnbuting clients. It is proposed that it would be fair and reasonable,
and probably necessary to promote contractor confidence, to allow contractors full
access to the data file held against them in order to secure feedback on past client views
on their performance, the specific identities of these clients being necessarily concealed.

If such a benchmarking scheme is to maximise the potential benefits available the


body charged with the responSIbility for management would need to display the
following characteristics:

• be independent of contracting and client organisations or confederations


• be equally accessible to public sector and private sector client organisations
• be capable of providing a timely and efficient response to client enquiries
• have sufficient and appropriate marketing and information dissemination skills as to
be able to promote the uptake and utilisation of the scheme as widely as posSlble
without reliance upon powers of compulsory registration
• have the resources to process, manage, and intexpret data in a consistent and
reliable way to promote meaningful comparability

Latham is of the view that the DOE CMIS scheme could provide the framework for a
central United Kingdom resource for public sector contracts based upon an official
registration of contractors. It is suggested in this paper that such a system would have
limited acceptance into the private sector as the DOE would be too strongly identified
with the government in its role as a major client of the industry. Furthermore the
reluctance of government to directly intervene in commercial relationships in the
construction industry, and the limited capability of the utilisation of such a scheme
without legislative authority, would effectively hamper its widespread acceptance and
participation.

A preferred solution would be the formation of a benchmarking service which was


under the management of an organisation which was seen as neutral by all participants
in the construction process and could be relied upon to be effective custodians of the
client information service. The Building Research Establishment and the Construction
Industry Research and Information Association are two organisations whose function is
the conduct of research into building and associated matters and yet display the
desirable characteristics noted above, in particular the absence of any allegiance to any
sector of the construction market, demonstrable expertise in the gathering and
management of information which would be a perquisite of the service, and would be
likely to enjoy the support of contracting organisations, consultancy practices and
professional institutions, and the collective body of construction sponsors. In addition
the neutrality of such organisations should attract the support and recognition of a
secondary layer of organisations who have an interest in the success and efficiency of
the construction process, including material and component suppliers, insurers, unions,
and consumer associations.
80 Ba/dry

The identifiable success factors of such an arrangement would be the delivery of a


service which came to be relied upon as the authoritative source of support to the
client procurement decision making process. Watson [11] descnbes how these critical
success factors need to be measured in basic business terms and become the basic
process measures of a TQM approach. For a sponsor of construction activity the
selection of a supply partner which comes closest to that sponsor's specific model of
supply excellence will enhance the likelihood of the success of a contractual
relationship. Furthermore the spur of achieving and maintaining a presence on a widely
regarded and valued database of suppliers of construction services may result in an
elevation of the standards of petformance of contracting organisations to new levels of
excellence and customer satisfaction.

5 Conclusion

Construction clients are seeking to improve their procurement and supplier selection
process to reduce project risk and create conditions for a greater certainty and quality
of contractor performance. This paper has descnbed how the disciplined process of
benchmarking may be adapted from the conventional inter-company supply side
comparator of process activity into a means for the reliable and objective assessment of
contractor competence. Notwithstanding the obstacles presented by the peculiarities of
the construction process, when compared to the manufacturing or service industries,
and the particular necessity of the development of a culture of co-operation, it is
proposed that an effective and workable system meeting certain delivery criteria is
desirable and achievable. The types of organisation which would be suitable to accept
the responsibility for managing such a service have been reviewed and appropriate
bodies proposed. The outcome of the establishment and successful operation of a
contractor petformance benchmarking system is predicted to be a direct positive aid to
client procurement experiences, and it is also speculated that improved contractor
performance may result from the competitive forces arising from participation in a
formalised comparative process.

6 References

1. Cousins, R (1995) Guide to Benchmarking in Premises Management, in Premises


and Facilities Management, February, pp. 45-48.

2. Varcoe, B. (1993) Benchmarking for Competitive Advantage, in Premises and


Facilities Management, February, pp. 11-12.

3. France, G. (1994) On your Benchmarks, in Building, 2 December, p. 42.

4. Chicken, IC. (1994) Managing Risks and Decisions in Major Projects, Chapman
Hall, UK.
Client benchmarking of contractor performance 81

5. Gorog, M. (1995) Client Orientated Strategic Project Management, in Proceedings


of SOVNET Project Management Symposium, St. Petersburg, Russia.

6. Codling, S. (1992) Best Practice Benchmarking, Gower Publishing, UK

7. Karlo£: B. and Ostblom, S. (1993) Benchmarking: a Signpost to Excellence in


Quality and Productivity, John Wiley, UK

8. Hawke, M. (1994) Mythology and Reality: the perpetuation of mistrust in the


building industry, Construction Papers No. 41, Chartered Institute of Building, UK.

9. Powell, M. (1994) Building Trust, in Proceedings of Sixth Annual Conference of


ARCOM, UK.

10. Latham, M. (1994) Constructing the Team, Final Report of the


GovemmentlIndustry Review of Procurement and Contractual Arrangements in the
UK Construction Industry, HMSO, UK.

11. Watson, G. H (1992) The Benchmarking Workbook, Productivity Press, USA.


References

1 Labour productivity

Hansson B (1995) Precast concrete box units -production


analysis, Department of

construction management, Lund University, Lund, Sweden.


THE USE OF CONVERSION FACTORS FOR THE ANALYSIS OF
CONCRETE FORMWORK LABOR PRODUCTIVITY U.E.L. de Souza
Department of Civil Construction, University of Sao Paulo,
Sao Paulo, Brazil H.R. Thomas Deparment of Civil
Engineering, Pennsylvania State University, University
Park, Pennsylvania, USA Abstract Labor productivity
management is important to the success of a project. The
concrete formwork operation is a labor intensive task ([1],
[2], [3]) which influences substantially the total cost
of construction ([1], [2], [4], [5]). Traditional cost
systems follow a time consuming routine that includes: the
break of the work in pieces (items); the measurement of
the amount done and the workhours spent for every item. In
doing so, several times one commits mistakes in assigning
workhours to each item. The "conversion factors" (CF) are
used to avoid this problem and to create an easier way to
measure productivity. They estimate how much easier (or
more difficult) different formwork situations may be,
identifying the relation between the effort (expressed as
workhours) necessary to accomplish one unit of a certain
item and the effort necessary to accomplish one unit of a
standard item. This paper presents the calculation of CF
related to form work for walls and columns. The following
steps were followed: collection of productivity rates for
cases presenting different factors affecting the
performance, from American estimating manuals; choice of
the most important factors in explaining productivity
variation; definition of a standard item for formwork
(steel framed plywood panels for walls until 8 feet
height); definition of equations to estimate the CF for
any nonstandard item of form work. Since the CF has been
calculated, one may transform quantities of any item in
equivalent quantities of the standard item. And then,
measuring only the hours spent on the work as a whole
(the formwork in this case), its productivity can be
evaluated. Keywords: construction management, conversion
factors, labor productivity, work measurement.

The Organization and Management of Construction: Shaping


theory and practice (Volume Two).

Edited by D.A. Langford and A. Retik. Published in 1996 by


E & FN Spon. ISBN 0419222405. Conversion factors for
analysis 15

Sommaire La gestion de la productivite est cruciale dans


Ie succes d'un projet La

realisation de coffrages est tres couteuse en temps et en


hommes ([1], [2], [3]),

et pese en consequence sur la globalite des couts des


travaux ([1], [2], [4], [5]). Traditionnellement, les
systemes de couts observent des procedures

particulierement chronophages dont Ie detail du travail en


items et Ie calcul

du travail et du temps fournis par item. TI n'est pas rare,


au cours de ces

operations, de faire des erreurs d'attribution des


heures/hommes par item.

Pour circonvenir ce probleme et creer un instrument de


mesure de la

productivite plus facile a manier, on a recours aux


"facteurs de conversion"

(CF). TIs evaluent Ie degre de difficuIte de la realisation


du coffrage en

etablissant Ie lien entre l'effort necessaire (en


heures/hommes) a la realisation

d'une unite d'un item particulier et l'effort necessaire a


la realisation d'une

unite d'un item standard. Ce papier presente les calculs


de CF propres au coffrage des murs et

des colonnes. Les etapes en ont ete : recueil, dans des


manuels d'evaluation

americains, des taux de productivite pour des cas


presentant des facteurs de

natures diverses influenc;ant les performances, definition


d'un item standard

pour Ie coffrage (panneaux de contreplaque a cadre acier


pour des murs

allant jusqu'a 2m de hauteur), definition d'equations


permettant d'estimer les

CF pour tout item non-standard. Sur la base des CF


calcules, on peut alors se permettre de convertir les

quantites propres a n'importe quel item en quantites


equivalentes de l'item

standard. Et ainsi, par Ie calcul des heures fournies pour


la realisation

globale du coffrage (pour Ie cas qui nous interesse ici),


sa productivite peut

etre estimee. 16 de Souza and Thomas 1 Introduction For


the purposes of this paper, productivity is measured by
means of the unit rate, that is defined [6] as the
relation between the inputs (workhours) and the outputs
(amount of work done) of ajob. The inputs are measured in
workhours (wh) and the outputs in square feet (st). The
effort to complete 1 sf of form work may vary according to
several features like: the system used; type of element
(column or wall, in this case); height of the

element; etc. To take these features into account, one has


to defme a standard

condition and calculate correction factors to transform


quantities of any other

condition into equivalent "units" of the standard one.


The conversion factor (CF) allows this transformation [6].
It is expressed as:

CFO) = unit rate(j) / unit rate(std) where: CF(j) =


conversion factor for condition "j", unit rate(j) = unit
rate for the condition "j", unit rate(std) = unit rate
for the standard condition.

Then, the equivalent quantity may be estimated by:

output(std) = output(j) * CF(j) where: output(std) =


equivalent quantities in the standard condition, output(j)
= quantities in the condition "j". The use of CF, as
described on Figure 1, allows the estimation of an
equivalent
amount of work: first it is necessary to measure the
amount of units for each type of

work done; then, to transform these amounts into standard


units; and, fmally, the

summation represents the total work done. The conversion


factors, for wall and column formwork, were developed
following

the steps: formwork classification and choice of the


standard; collection of

productivity rates, for cases presenting different factors


affecting the performance,

from American estimating manuals; choice of the most


important factors in explaining

productivity variation; defmition of equations to estimate


the CF for any non-standard

item of formwork. Conversion factors for analysis 17

2 Formwork classification To allow the deftnition of


conversion factors, one ftrst needs to defme a framework

at the same time comprehensive (to include as many types


of formwork as possible), simple (avoiding excessive
slightly different classiftcations), and easy to understand

(avoiding misuses and inducing its use). quanti1les


conversion equivalent factors quantities ~ w.l
comparison to SUM the equivalent ~t8nd8rd Co
quantities c.;

Figure 1The conversion factor's role in measuring the


amount of work.

Figure 2 shows the framework used to classify wall and


column formwork and to

calculate the CF. The ftrst division is related to the


element being formed (wall or

column). The second division defmes the following broad


categories:

for walls: * stick (#) = built-in-place formwork; *


non-stick (N#) = prefabricated (both in-site or out-site);
for columns: * stick (#) = built-in-place; * non-stick
rectangular (N#rec) = prefabricated (both in-site or
out-site) with rectangular section; * non-stick round
(N#rou) = prefabricated (both in-site or out-site) with
round section. These terms, that represent a compromise
between the simplicity and accuracy, ftts

the methods and the language used in construction. More


than it, this division is

necessary to create groups of forms whose productivity is


expected to be influenced

by the same factors (for example, "#" must be isolated


from "N#" to study the

influence of "ganging panels").

18 de Souza and Thomas The several levels below the two


divisions represent factors (for example "height")

that have influence on the classes defmed by each vertical


line (for example, "C#").

As a consequence of such a division, there are factors


that have influence on one

category of fonn but not (or have a different influence) on


another (for example,

"height" may have influence on the productivity of "C#"


but not of "CN#rec"). I--+----+----+---+_ t.i conversion
factors equations other factors

Figure 2Framework to defme the conversion factors for


fonnwork.

3 Choice of the standard

The fonnwork job may be done under different kind of


"factors" (as previously

shown on Figure 2); to describe a case, one must detect and


quantify the existing

factors. The standard case is the one chosen as the gauge


for comparisons. The

chosen case should be the most often used in practice in


order to: improve the

accuracy of the comparisons; simplify the understanding of


equivalent quantities

estimated using this standard. The features of the


standard condition for fonnwork were chosen as: fonn for
wall

non-stick, with height not exceeding 8', and using plywood


as surface material.

4 Measuring factors' effects

Although the procedures to get the data are sometimes not


well understood, and may

vary from one manual to another, the estimating manuals


represent an accumulated

experience extremely significant. Mainly because to collect


data in construction is

neither an easy nor a cheap task. Each case presented by a


manual, expressed in tenns of accumulated unit rate at

the completion of the project, represents an average of the


results obtained for similar

conditions in several sites. Conversion factors for


analysis 19 The following criteria were used in order to
choose the manuals to serve as source

of data: to be recognized by the technicians as a good


manual; to describe in detail

the cases analyzed; to avoid the use of manuals with the


same origin. The five chosen manuals were: "Structural
Concrete Cost Estimation" [7]; "The

1984 Berger Building & Design Cost File" [8]; "1988 Dodge
Unit Cost Data" [9];

"Means Man-hours Standards" [10]; "General Construction


Estimating

Standards"[ll].

Table 1 shows how many cases were collected from each


manual, while Table 2
shows the kind of information provided by the manuals.

Table 1Number of cases collected in the manuals, for walls


and columns. Manual Element wall column Clark: 2 1
Berger 48 32 Dodge 12 43 Means 21 52 Richardson
104 24 TOTAL 187 152

Table 2Information provided by the manuals. Information


Walls Columns cumulative unit rate X X perimeter X
section format X section area X curvature X X
tickness X height X X material/system X X number of
uses X X gang size X X use of crane X X maximum
dimension X

5 Transforming unit rates into conversion factors

The data collected from the Manuals expressed productivity


in terms of unit rates for

each case. The transformation of this information into


conversion factors followed the 20 de Souza and Thomas
steps: the cases were classified according to the
"categories of fonnwork" previously defmed: column stick,
column non-stick round, column non-stick rectangular, wall
stick, and wall non-stick (generating five subset of
data); for each subset it is necessary to detect which
Manuals have the standard as a case; when the Manual has
the standard, CF=1 is assigned to this case and the CF's
for the remaining cases of this Manual are calculated
according to the defmition previously explained (ratio of
unit rates); when the Manual doesn't have the standard as a
case, it is necessary to calculate the unit rate for a
"estimated" standard (the unit rate for the standard if it
was present in the subset), and then the CFs for all the
cases are calculated in the same way just described. In
order to estimate the standard unit rate it is necessary
to make comparisons among comparable situations relating
the manuals. The unit rates for the standard, expressed in
wh/sf, are: 0.236 for "Clark"; 0.131 for "Berger"; 0.073
for "Dodge"; 0.075 for "Means"; and 0.067 for "Richardson".
Notice that, although each data point in a Manual may
represent an average of several collections, there are no
established standard procedures, common to all the
Manuals, to calculate the productivity rates. Then, it is
very common to fmd different unit rates related to the
same case, as it happened with the unit rates for the
standard. Some explanations are: certain Manuals are more
conservative than others; some may consider the management
hours as part of the input, while others only take into
account the direct labor; etc. But, many times, the
comparable values in two distinct Manuals differ roughly
by a constant. This is the typical situation in that the
use of conversion factors will improve the fit of data,
as illustrated in Figure 3: the unit rates and the
conversion factors for walls non-stick coming from two
distinct Manuals (Berger and Means) are plotted; although
there is a significant difference between the unit rates
proposed by them, there is a close agreement in relation to
the conversion factors. 6 Calculation of the conversion
factors for non-standard conditions The process of defming
equations to estimate the conversion factors for each
category of fonns, as illustrated by Figure 4, follows the
steps: for each "category of fonnwork" one must list all
the variables that potentially can affect the conversion
factors (CF); during a "preliminary individual evaluation"
, each variable, one by one, will be checked by means of
"graphical analysis" (for example plotting the CF in
relation to the variable), "statistical analysis" (for
example using individual ANOYA

and individual regression analysis), "personal evaluation"


(taking into account past

experience and common sense), and "confidence on the data"


(involving both the

number of available data points and the clearness of


Manual's infonnation); the

remaining variables (named "potential variables") are now


evaluated together, by

means of "graphs" and "statistical analysis", to take into


account the eventually

present interactions effects; the variables in the fmal


equation will be the ones with

good statistics, with significant impact over the CF being


calculated, and the ones

that are considered causal variables. Conversion factors


for analysis 21 0 0.20 0 0 0 0 0 0 0 2 0.15 0
0 0 0 aJ E 0 0 ::i 0 0 + ''" } + + 0.05 + 10
15 20 0 Berger height + Means 2.1 0 1.6 0 LL. 0 +
0 0 0 0 0 bJ + 0 0 0 1.1 + 0 0 + 0 0 0 0
+ 0.6 10 15 20 height

Figure 3Comparison between the infonnation from two


Estimating Manuals (Berger

and Means) for walls non-stick: a)unit rates; b)conversion


factors.

22 de Souza and Thomas final equation IIvlliiable


vllriables preliminary individual evaluation potencial
variables group evaluation

Figure 4The process of defIning a conversion factor's


equation.

The fmal equations can be seen on Figures 5, 6, 7, 8 e 9,


respectively for columns

N, columns NNrec, columns NNrou, walls N and walls NN, as


part of the regression

analysis that generate them. Regression Analysis CF =


1.95 0.00158*perimeter+ 0.109*(12'<h<=15') predictor
constant perimeter 12'<h<=15' std dey. 0.01742 0.00019
0.01332 t-ratio 111.99 -8.2 8.15 p-value 0.000 0.000
0.000

Figure 5Regression analysis to estimate the CF equation for


columns N. Conversion factors for analysis 23 Regression
Analysis CF = 1.58 0.00407"petimeter 0.0101*(pref.plywood
syst.)*(petimeter avg. perimeter) + +
0.000084*(pref.plywood syst.)*(petimeter avg.perimeter)**2
predictor constant perimeter (pref.plywood
syst.)*(petimeter avg.perimeter) (pref.plywood
sysL)*(perimeter avg.perimeter)"2 std dey. 0.07942
0.001142 0.001382 0.000011 t-ratio 19.95 -3.56 -7.3
-7.67 p-yalue 0.000 0.007 0.000 0.000

Figure 6Regression analysis to estimate the CF equation for


columns N#rec. Regression Analysis CF =0.966
0.006*(max.dim.) 0.0115*(tiber surface)*(max.dim.) +
-0.341*(tiber surface) + 5.57"(tearable syst.)/(max.dim.)
predictor std dey. constant 0.0612 max.dim. 0.001952
(tiber surface)*(max.dim.) 0.002213 tearable sysL 0.06958
(tearable syst.)/(max.dim.) 1.193 i-ratio 15.79 -3.1
-5.21 -4.9 4.67 p-yalue 0.000 0.003 0.000 0.000
0.000

Figure 7Regression analysis to estimate the CF equation for


columns N#rou. Regression Analysis CF = 1.19 +
0.397"(9'<h<=16') + 0.756*(h>=17') + 0.57"curved predictor
std dey. t-ratio p-yalue constant 0.06562 18.14 0.000
9'<h<=16' 0.09659 4.11 0.001 h>=17' 0.1392 5.43 0.000
curved 0.1856 3.07 0.010

Figure 8Regression analysis to estimate the CF equation for


walls #.

24 de Souza and Thomas Regression AnalYSis CF = 1 +


0.15*gang 0.16*(steel surface) + 0.106*(9'<h<=16') + +
0.187*(h>=17') +0.321*curved predictor std dey. t-ratio
p-value constant 0.04793 21.57 0.000 gang 0.05198
2.89 0.007 steel surface 0.05437 -2.95 0.006
9'<h<=16' 0.0632 1.67 0.105 h>=17' 0.04483 4.16
0.000 curved 0.05437 5.9 0.000

Figure 9Regression analysis to estimate the CF equation for


walls NU.

7 Using the conversion factors to estimate daily


productivity

The following example uses data collected in Central


Pennsylvania (United States of

America) in 1995 from the construction of a big gymnasium


(seating capacity:

16,500). Table 3 illustrates the necessary steps to


transform the quantities, measured

for each item, into equivalent quantities of the standard


condition. Notice that, to take

into account the different efforts involved in assemble and


strip the forms, these parts

of the item being done are tracked separetedely and receive


weights respectively of

0.85 and 0.15 (for example: 100 sf of assembled form


represent 85 sf of the item's

job, while the same amount of stripped forms mean only 15


sf). Finally, Table 4

shows the calculation of the daily unit rates: the total


equivalent quantities represent

the summation of the several items performed that day; the


workhours are the total

hours related to the formwork as a whole (and not for each


item); the daily unit rate,

then, being connected to the standard condition, represents


a standard measurement

of productivity.

8 Conclusion

Traditional cost systems break the work in pieces (items)


and require the

measurement of both the amount of work done and the


workhours spent for each

piece. This report showed that conversion factors can be


used in order to simplify the

labor measurement and to create a gauge for productivity


calculation. Based on data collected from estimating
manuals five equations (one for each

category of form: CU, CNURec, CNURou, WU, WN#) were


developed to allow the

transformation of amounts of any type of formwork into


standard equivalent

quantities. Using these equations, it is only necessary to


track the total workhours

spent with forms instead of observing the labor


consumption for each item. The use

of standard quantities turns the unit rate into a standard


productivity measurement,

what makes the comparison between measurements in different


days and/or sites

Selecting and Using Wall Forms. Aberdeen, Louisiana,


pp.18-53. 2 Qabbani, Z.S. (1987) Formwork: economy and
productivity analysis. University

of Colorado. 113p. 3 Adrian, J.J. (1975) Realistic


calculations of costs for wall fonning systems.

Concrete Construction, June. 4 Aldana, L. (1991)


Measurement and analysis of concrete formwork and steel
reinforcement productivity. University of Dundee, 163p. 5
Backe, C. (1994) Wall fonns: selecting the best ganged
system, in Selecting and

Using Wall Forms. Aberdeen, Louisiana, pp.54-58. 6


Thomas, H.R. and Kramer, D.F. (1987) The manual of
construction productivity

measurement and performance evaluation. crr, Austin, 168p.


7 Clark, J.E. (1983) Structural concrete cost estimating.
McGraw-Hill, 298p. 8 Hlibok, A.J. (1984) The 1984 Berger
building & design cost file. Hicksville,

Building Cost File Inc., VoU, 479p. 9 Iavarone, R.C.


(1987) 1988 Dodge unit cost data. New Jersey, McGraw-Hill,

338p.

10 Cleveland, A.B. (1983) Means man-hours standards. Means,


576p.

11 Richardson Engineering Services (1987) General


construction estimating

standards. Richardson, Vol.l. DEVELOPMENT OF AN


EXPLANATORY MODEL FOR CONCRETE FORMWORK LABOUR
PRODUCTIVITY U.E.L. de Souza Department of Civil
Construction, University of Sao Paulo, Sao Paulo, Brazil
H.R. Thomas Deparment of Civil Engineering, Pennsylvania
State University, University Park, Pennsylvania, USA
Abstract Labor costs are very significant in construction.
To manage this resource it is important to know the
factors that influence labor productivity variations, and
by how much. Researchers have been trying to develop
models to explain productivity variability ([1], [2], [3],
[4], [5]), but this is not an easy task. Many activities in
construction (as formwork) are labor intensive and there
are both operational and environmental factor influences
on the productivity. The "Factor Model" approach,
developed at Pennsylvania State University (PSU),
identifies these factors by means of statistical modeling.
This paper presents the development of a Factor Model for
Concrete Formwork (it is restricted to concrete walls and
columns). Some of the steps followed to complete this
research were: a procedures manual for formwork, developed
at PSU, furnished a standard way to collect data; the
author collected daily information in the site
construction of a gymnasium (capacity: 16,5 thousands
seats) located in State College (pennsylvania USA), for
more than 250 workdays; data from 5 other projects [6],
tracked with similar procedures, were also used in this
study. After the reconciliation of all the information
received from the sources above discussed, a statistical
analysis generated a mathematical expression that
identifies the factors and their influence on the labor
productivity. Keywords: construction management,
construction model, formwork, labor productivity.

The Organization and Management of Construction: Shaping


theory and practice (Volume Two).

Edited by D.A. Langford and A. Retik. Published in 1996 by


E & FN Spon. ISBN 041922240 5.

28 de Souza and Thomas

Sommaire Les couts de main d'oeuvre sont loin d'etre


negligeables dans Ie

batiment. n est indispensable, pour gerer au mieux les


ressources humaines,

de connnaitre les facteurs qui influencent les variations


de productivire, et

dans quelle mesure. De nombreux chercheurs ont tenre de


developper des modeles de

variabilire de la productivire ([1], [2], [3], [4], [5]);


cette tache s'avere

cependant ardue. Nombre d'activires du bil.timent tel Ie


coffrage sont!res

couteuses en temps et en hommes, et on observe que les


facteurs agissant sur

la productivire sont de nature operationnelle autant


qu'environnementale. La modelisation des facteurs
("Factor Model") developpee a la

Pennsylvania State University (PSU), aux Etats-Unis,


circoncit ces facteurs

statistiquement. Ce papier a pour objectif de presenter Ie


developpement

d'une modelisation applicable au coffrage en beton,


uniquement ici pour Ie
coffrage des murs et des colonnes. Cette recherche s'est
ainsi deroulee: un manuel des procedures pour Ie

coffrage, moyen standard de recolte des donnees, a ere


developpe a la PSU;

l'auteur a recueilli des donnees quotidiennement, sur Ie


chantier d'un

gymnase d'une capacire de 16 500 places et situe dans


l'enceinte du State

College Pensylvania, Etats-Unis, pendant une periode de 250


jours travailles;

les donnees de 5 autres projets [6] observant les memes


procedures ont par

ailleurs ere utilisees dans la presente etude. Apres la


reunion de toutes les informations recueillies aupres des

sources citees precedemment, l'analyse statistique a fait


apparaitre une

equation mathematique qui identifie les facteurs et leur


influence sur la

productivire humaine. Explanatory model for labour


productivity 29 1 Introduction The observation of a real
process for a certain period of time allows the
construction

of models that provide understanding: the explanation of


what has happened and the

forecast of future events. Figure 1, based on Casti [7],


illustrates this mechanism. r-----, I I -.! I Inputs I
encoding (explanation) laws procr.ss I outputsi' I I
decoding forecactin 9) L-~

Figure 1The modeling relations. r----, I I I inputs


observed I sample 01 a model process i'OlltplllS I
I I '--~

The Factor Model [8], based on the crew level productivity,


was developed in the

Pennsylvania State University (PSU). Graphically shown in


Figure 2, the
development of the model assumes the existence of an
"standard condition of work";

under this condition, the daily productivity will be the


"ideal" (here one may assume

the existence of learning or not); variances in the work


scope and/or in the work

environment make the productivity vary in relation to the


ideal. The model relates

the actual daily productivity to the daily work features.


~ £ .. o t: S WORICTYPE w ..a:I7~~ PHYSICAL
ELf:MEHt' ~ CONSTRUCTION METHOD g ~ DESIGN REQUIREMEIiTS
~ UNrrSOFWORK

Figure 2The Factor Model.

30 de Souza and Thomas

In this report the Factor Model approach is used in order


to "explain" daily

productivity variability: detecting the factors that


generate variation and their degree of influence, based on
nonnaI workdays (Figure 3). disruptions/outliers

Figure 3Explanatory model development.

To reach these goals the report discusses the following


issues: standardization of

productivity measurement; collection of daily infonnation;


preliminary evaluation of

the factors; modelling; and final checks.

2 Standardization of productivity measurement

This paper adopts, as a tool to measure daily


productivity, the daily unit rate [9],

defmed as the ratio between the inputs (labor workhours)


and the output (work

quantities). In order to establish a standard measurement,


it is necessary to have

standard measurements of both the inputs and the outputs.


The measurement of labor consumption (input) was done as
prescribed by a PSU's

manual for data collection [10]. The main recommendations


are: to track the

workhours spent by one crew, that "consists of the foreman


and the gang members";

"hours of absenteeism are not counted"; support personnel


are only take into account

when their work is devoted exclusively to the crew; the


recorded workhours are the

paid hours . (excluding eventual "premium"). The


quantities measurement

standardization relies on the following ideas (Figure 4):


to recognize the parts

(subtasks) that constitute a task and to record quantities


individually allocated; to add

these quantities accordingly to the relative demanded


efforts (rules of credit); to

transfonn the quantities for each different task into


equivalent amounts of the

standard task (conversion factors) and to add them to fmd


the daily quantities of

standard work. The units of measurement are: workhours (wh)


for the inputs, and

square feet (st) of fonnwork for the outputs; then, the


unit rate will be expressed in

workhours per square foot (whist). Explanatory model for


labour productivity 31 quantities r c u 0 I n e s
of c a r c e t d 0 r s

Figure 4Measuring quantities of work.

An extensive discussion about the output measurement


process is provided elsewhere

[9]. But some aspects are worth to be presented here: some


factors that have
influence on formwork labor productivity have ever been
considered in the

development of the conversion factors (type of element,


height, section size,

formwork system, format, handling system, surface


material); the equivalent

quantities are expressed in terms of the following


standard task: forms for walls not

higher than 8 feet, using handset panels with plywood


surface.

3 Daily information

The description of daily performance includes both the


calculation of the unit rate

(expressed in terms of standardized inputs and outputs)


and the description of present

factors that may influence productivity. The standard


measurements of amounts of

labor (input) and work (outputs) were previously discussed


in this report. In relation

to the "productivity influencing factors", some additional


comments are: some of

them were included in the conversion factors' equations;


the remaining ones may be

divided into quantitative and qualitative variables; for


the qualitative ones it is

necessary only to detect its presence or absence; the


quantitative ones demand a

quantification task; the number of factors to be tracked


should be as big as possible,

under the researcher's point of view, but as low as


necessary to diminish the

spending time for future practical use of the fmal model


by contractors; previous
experience helps in defming what factors must be tracked;
try to avoid factors that

present difficulties in being measured; as far as


possible, use factors common to

former data collections; because this report deals with an


explanatory (and not a

forecasting) model, it is possible to use daily features


as factors, instead of

information necessarily extracted from plans (for example,


one can use the number

of the floor in execution in a certain day instead of the


building'S height).

32 de Souza and Thomas This report uses databases


collected accordingly to the procedures developed at the

PSU. Table 1 summarizes the main features of the available


databases.

Table 1Databases' infonnation summary. project name


Bryce Jordan Tertiary Filter -level 1 Tertiary Filter
level 2 Composting Facility Art Museum Wing ParKing Deck
Garage cumulative u.r. at completion (whIst) 0.12 0.17
0.12 0.05 0.05 0.14 total worKdays 256 25 39 23
43 40 total equiv. % of disr. or area (1000 sf) outlier
days 208.9 34 6.6 16 16.7 21 46.1 9 15.6 21 13.8 28

As it can be seen on Figure 5, the chosen factors to be


analyzed ("available

variables"), grouped under the classes "design


features/work content", "environment

conditions", and "construction methods", were: "boxout or


pipesleeves" (Figures

6.a.l and 6.a.2), a qUalitative variable that states if the


workday was significantly

affected by the execution of boxouts or the positioning of


pipesleeves by the fonn

crew; "comers" (Figure 6.b), that can be treated either as


a quantitative (counting the
number of fonn comers perfonned) or a qualitative variable
(stating if there was

significant effort spent in fonning comers); "elevation


changes" (Figure 6.c), with

approach similar to comers in relation to the existence of


"steps" along the height of

the element being fonned; air "temperature" (represented by


the temperature at

1 :OOPM) and "relative humidity" (represented by the


temperature of dew point at

1:00PM), whose summation is representative of weather


comfort; "length of

workday", measured in hours; "bulkheads" (Figure 6.d), with


approach similar to

comers in relation to the presence of this kind of


fonnwork; "accessibility", a

qualitative variable that implies in classify an element as


easily approachable (Figure

6.e.l) for workers and materials or as of not easy access


(Figure 6.e.2); "pour

coordination", a qualitative variable that states if the


fonn crew was involved with

concrete pouring in a certain day; "crew size", measuring


the number of workers of

the crew in a certain day, from the foreman (included) down


(hierarchically

speaking), independently of their skills.

4 Preliminary evaluation of available variables

Once the infonnation about the available variables has been


collected in the fonner

step, it is time now to check which ones are really


important for the model's
development: different approaches were used for
quantitative and qualitative

variables; the checks include the use of graphical and


statistical tools (analysis of Explanatory model for
labour productivity 33

variance, regression analysis, confidence intervals,


scatter plots); as a result of this

evaluation, each available variable is "accepted" for


further analysis or "excluded". AVAILABLE VARIABLES

Figure 5Available variables classification. 3.1) Iii!


v-l ~ o c) dJ 8.21 il II e.1) e.2) bl I r;: 1====+
-//

Figure 6Variables description: a)boxouts and pipesleeves;


b)comers; c) elevation

changes; d)bulkbeads; e)accessibility.

34 de Souza and Thomas Table 2 summarizes the results for


the qualitative variables. Some additional

comments are: in relation to the 95% confidence intervals,


a "good" plot is that one with no superposition between
the ranges of variation for the conditions being

checked; "difficult access" is considered to happen


whenever there is not only

elements easily approachable being formed; although the


results for "elevation

change" and "bulkheads" are not so bad, there is an


inconsistency between the data

and the expected performance: days with these factors


present have a smaller unit

rate than days without.

Table 2Qualitative variables evaluation. # of Anova


ind.regr. 95% variable cateQory obs. mean p r2-adj C.1.
classification boxout or 0 238 0.113 0.004 2.3% good
accepted pipesleeve 1 67 0.144 corners 0 150 0.122
0.771 0.0% bad excluded 1 155 0.119 elevation 0 280
0.123 0.033 1.2% good excluded chanQes 1 25 0.088
bulkheads 0 195 0.127 0.051 0.9% bad excluded 1 110
0.109 difficult 0 125 0.097 0.000 5.8% good accepted
access 1 180 0.136 pour 0 203 0.105 0.000 6.8% gOOd
accepted coordination 1 102 0.150

Table 3 summarizes the results for the quantitative


variables. Some additional

comments are: plotting the unit rate against the variables


allows the visual detection

of the existence of a "trend" (possible flag for a


relationship); in order to fit the

reality, the "density" of comers, elevation changes and


bulkheads, separately, are

studied; "density" is defmed as the number of units of the


factor (for example the

number of comers formed in that day) multiplied by 1000


and divided by the total

equivalent amount of form work job for the same day; "T1 +
Tdp", the summation of

air temperature and temperature of the dew point at


1:00PM, is used to analyze the

effect of weather over the labor productivity.

5 Modelling

The fmal expression of the explanatory model is an


equation generated by regression

analysis having the standard daily unit rates as dependent


and the "accepted" factors

as independent variables:

unit rate = 0.080 + 0.030*(difficult) + 0.028*(pour coord)


+ 0.034*(boxipipe) Explanatory model for labour
productivity 35 On a day with standard condition of work
(difficult = pour coord = box/pipe = 0) the ideal daily
unit rate, expressed in equivalent quantities of fonnwork,
is 0.080 whlsf. Because all the factors in this final
expression are qualitative, the presence of

anyone modifies the daily unit rate by the value of its


coefficient (for example: in
a day with concrete pour, "pour coord" = 1, and the unit
rate becomes 0.108 whist).

Table 3Quantitative variables evaluation. individual


regression variable J2-adj p value comers density 0.0%
0.301 elevation change density 0.6% 0.159 bulk density
0.0% 0.922 T1 + Tdp 2.1% 0.037 length of wor1<day
0.0% 0.768 crew size 0.2% 0.247

6 Final checks plot trend? no no no no no no


classification excluded excluded excluded excluded
excluded excluded

Four different approaches are showed to check the model's


equation: coefficient's

statistics; infonnal evaluation; effect on the standard


deviation; omitting databases.

Coefficient's statistics

Table 4 presents the main statistics related to the


coefficients of the model's factors;

they are significant.

Table 4Coefficient's statistics from the regression


analysis. factor difficuH poor coord box/pipe t-ratio
4.45 4.06 4.30 p-value 0.000 0.000 0.000

Informal evaluation of the coefficients

The coefficients are: 0.030 for "difficult" , what means an


increase of 38 % in the unit

rate in relation to standard days; 0.028 for "pour coord",


representing an increase of

35 %; 0.034 for "box/pipe", meaning a 43 % increase. The


literature review didn't provide a baseline to compare
these values; but they

seem to be consistent with the reality, based on the


researcher's personal experience. 36 de Souza and Thomas
Effect on the standard deviation To verify the model's
explanatory capability, one may compare the standard
deviation of the database "before" the standardization and
modelling and "after" that. The values are, respectively,
0.3077 and 0.0559. This means a very significant 82 %
reduction.

Omitting databases

When developing a forecasting model, the last stage of the


process is to confront its

predictions with new data coming from a database not used


in the model's

development. Although this is not the case (this report is


concerned with an

explanatory model), a similar approach will be used in


order to check the confidence

one can credit on the model: "new" equations were


developed accordingly to the

same process used to create the "model's" equation, but


making use of all databases

except one; because there were six databases, it is


possible to develop six new

equations based on the five remaining databases; the


intercept and coefficients values

for the "model's" and the six "new" equations can be seen
on Table 5.

Table 5Intercept and coefficients values for the "model's"


and the six "new"

equations. constants intercept difficult pour coord.


box or pipe model 0.0797 0.0299 0.0282 0.0342 new 1
0.0716 0.0341 0.0299 0.0387 new 2 0.0905 0.0192
0.0279 0.0346 new 3 0.0854 0.0256 0.0254 0.0325 new
4 0.0810 0.0303 0.0239 0.0347 new 5 0.0761 0.0346
0.0264 0.0272 new 6 0.D705 0.0430 0.0520 0.0405

In order to check the agreement among all the generated


models, all the equations are

plotted together, as can be seen on Figure 7, for different


working conditions. The

visual evaluation shows a good harmony among them: the


points are close to each
other.

7 Conclusion

Several factors may have influence on formwork labor


productivity. In order to

standardize the measurement of outputs some of them were


already considered: type

of element; height; section size; formwork system; format;


handling system; and

surface material. The importance of several other factors


were checked in this paper:

boxouts; pipesleeves; comers; elevation changes; air


temperature; relative humidity; Explanatory model for
labour productivity 37

length of workday; bulkheads; accessibility; pour


coordination; and crew size. The

Factor Model approach helped in create an equation that


shows the factors to be

considered and quantifies their influence on the daily unit


rate value: the ideal

productivity (standard condition of work) is 0.080 whlsf;


"difficult" access represents

an increase of 0.030 whlsf; days with concrete "pour


coordination" mean an

additional 0.028 whlsf; and extra 0.034 whlsf can be credit


to days impacted by box

out or pipesleeve work. This kind of information can help


the site management in

different ways: as baseline for performance evaluation; as


source of information to

defme production goals; in defming strategies to make easy


the "access" to the

elements (for example, to defme an advantageous forming


sequence); in taking
decisions about having an special crew only for concrete
pour; etc. 0.25 .. model ur 0.2 -+ new 1 Q) *new2
..... co .... 0.15 -B new 3 :!:::! c: ~new4 :J 0.1
-fr new 5 .new6 0.05 different conditions

Figure 7Plot of the "model's" and the six "new" equations


for different working

productivity measurements. Pennsylvania State University.


87p. 6 Shumway, J.D. (1992) A comparative analysis of
concrete form work

productivity influence factors. Pennsylvania State


University. 103p. 7 Casti, J.L. (1990) Searching for
certainty: what scientists can know about the

future? W. Morrow, New York, 496p. 8 Thomas, H.R. et alii


(1990) Modelling construction labor productivity. ASCE
Constr. Engrg. and Management, Vol. 116, No.4. pp.705-726.
9 Thomas, H.R. and Kramer, D.F. (1987) The manual of
construction

productivity measurement and peljormance evaluation. crr,


Austin, 168p. 10 Thomas, H.R., Homer, R.M.W. and Smith,
G.R. (1991) Procedures manual

for collecting productivity and related data of


labor-intensive activities on commercial construction
projects: concrete formwork. PTI, State College, 63p.
OVERMANNING AND THE EFFECTS ON LABOR EFFICIENCY H.
Randolph Thomas Professor of Civil and Environmental
Engineering, Pennsylvania State University, University
Park, Pennsylvania, USA Todd M. Arnold Graduate
Assistant, Pennsylvania State University, University Park,
Pennsylvania, USA SUMMARY Schedule acceleration is a very
troublesome problem for contractors because of the
potentially devastating effect on labor productivity. While
much has been written about scheduled overtime, little has
been published about the effects of overmanning, that is,
managing a larger workforce than planned. This paper
reports the results of a survey of electrical contractors
asking about the magnitude of inefficiencies due to
overmanning and the causes. The results show significant
degradation in efficiency as more craftsmen are hired and
are reported by project type, however, the differences are
not significant.

SOl\1MAIRE

L'acceleration de l'horaire du travail pose des problemes


pour les entrepreneurs a

cause de l'eventual effect detrimental sur la productivite


de la main-d'oeuvre. Tandis

que beaucoup a ete ecrit au sujet des heures


supplementaires, il y a tres peu d'etudes

sur l'effect et les problemes de gestion d'une


main-d'oeuvre surchargee. Cette etude

ci presente les resultats d'un sondage d'entrepreneurs


d'electricite sur la manque de

l'efficacite cause par une main-d'oeuvre surchargee et ses


causes. Les resultats

demontrent une manque d'efficacite lorsque plus d'employes


sont engages, et ces

resultats sont decrits par project; neanmoins, les


differences ne sont pas importantes. INTRODUCTION A
survey was distributed to the membership of the National
Electrical Contractors Association (NECA) requesting
pertinent information on projects that were accelerated or
compressed causing overmanned. These surveys provide two
relevant pieces of information: assessment of contractor
perceptions of the extent of efficiency loss caused by
overmanning, and relative differences in loss of efficiency
for different type projects.

The Organization and Management of Construction: Shaping


theory and practice (Volume Two).

Edited by D.A. Langford and A. Retik. Published in 1996 by


E & FN Spon. ISBN 0419222405. 40 Thomas and Arnold SURVEY
INQUIRIES The survey instrument requested the following
infonnation about a specific project that was accelerated
or compressed: • Project type • Planned and actual number
of electricians • Estimated loss of efficiency caused by
ovennanning • Planned (budgeted) and actual workhours •
Estimated and actual schedule duration

In total, infonnation was provided on 129 projects. There


were complete responses

for 110 projects. Table 1 summarizes the surveys according


to the project type and

average planned maximum number of electricians. As can be


seen, most projects

were industrial, commercial, or institutional. The average


planned maximum number

of electricians ranges from 4 to 50. Comparatively few line


projects were contributed.

Table 1. Summary statistics of survey responses. Project


Type Number of Average Planned Projects Maximum Number
of Electricians Inside Projects: Industrial 45 50
Commercial 26 40 Institutional 29 28 Communications I 4
Line Projects; Transmission 1 9 Distribution 2 6
Substation I 10 Underground 0 Communications 5 43

TOTAL WSS OF EFFICIENCY

For the data analyses, several parameters were calculated.


The first is the percent

ovennanned which was calculated as follows: Overmanning


and the effects on labour efficiency 41 Percent Overmanned
(%) = ( Actual Max. No. of Elec. -1.0) x 100 (1) Planned
Max. No. of Elec. The total loss of labor efficiency
relies on the actual workhours and the budgeted

or planned workhours. These values are used in equation 2.


Total Loss of Efficiency (%) = (1.0 Budgeted Workhours) x
100 (2) Actual Workhours

Figure 1 shows the distribution of the total efficiency


loss for all projects as a function

of the percent ovennanned. Using equation 2, an efficiency


loss of 25 % means that

33 % more workhours were required than budgeted. As can be


seen, the number of

workhours required can exceed the budgeted or planned


workhours by a considerable

margin. The relationship between the total loss of


efficiency and the ratio of the actual

divided by the planned schedule duration was also


investigated. From figure 2, this

relationship is unclear. However, it is obvious that few


projects finish early or on
time. In the survey, 68 percent of all projects took more
workdays than planned.

LOSS OF EFFICIENCY CAUSED BY OVERMANNING

The survey requested the estimated percentage of the total


labor overrun attributed to

providing additional manpower resources, i.e., ovennanning.


The distribution of

percentage estimates is shown in figure 3. It is obvious


that the consensus of opinion

of electrical contractors is that ovennanning causes


considerable loss of efficiency.

The average estimate is 29 percent, but in many instances,


the estimated percentage

is much higher. The net loss of efficiency caused by


ovennanning was calculated by mUltiplying

the total loss of efficiency from equation 2 times the


estimated percentage of the total

labor overrun attributed to ovennanning. The net efficiency


loss is shown in equation

3. Net Elf. Loss (%) Total Elf. Loss x Est. % From


Overmanning (3) 100

Figure 4 shows the relationship between the net loss of


efficiency and the percent

ovennanned. The general trend is that as the percent


ovennanned increases, the net

loss of efficiency also increases. The net loss of


efficiency from ovennanning was also investigated for other

relationships. No correlation was evident between the net


loss of efficiency and the 42 Thomas and Arnold planned
size of the work force or the planned duration. Thus, from
the survey, it cannot be said that larger or longer
duration projects have greater efficiency losses. This
observation may be different if there were more larger
projects in the database. Figure 5 shows that half of the
database is from projects where the planned maximum number
of electricians was 20 or less. The net loss of efficiency
by project type was also investigated for indoor

projects. A linear regression equation was calculated for


all indoor projects and

industrial, commercial, and institutional projects. These


equations are shown in figure

6. As can be seen, when the percent overmanned is 25


percent or less, there is

minimal difference between the net loss of efficiency as a


function of project type. Because there were insufficient
line projects to examine by type, a linear

regression equation was calculated for all line projects.


Figure 7 compares the indoor

and line projects. There appears to be minimal difference


between these two groups. To validate the results of the
survey, losses of efficiency were calculated for each

project type at 50 percent overmanned (see figures 6 and


7), and the results were

compared to the summary curves from the literature review.


From the literature

review, the range of efficiency loss at 50 percent


overmanned for small and large

projects is between 8 and 15 percent. As shown in figure


8, the results of the survey

are within this range.

SYNOPSIS

The results of the survey are generally consistent with the


published literature on net

loss of efficiency caused by overmanning (homas et al.


1994). The data also show

that efficiency losses as a function of project type can


vary. Table 2 summarizes the

difference between project types by showing relative


increases and decreases in
efficiency loss. The category representing the analysis of
all indoor projects is used

as the base for the indoor projects. The relative


differences in table 2, called

efficiency loss multipliers, show that institutional


projects are affected least and

industrial projects are affected the most. Further, the


efficiency losses reported from

the survey showed no correlation to the planned size of


the work force or planned

schedule duration.

CAUSES

The survey asked the respondents to indicate the principle


cause of the acceleration.

The responses to this open-ended question are summarized


in table 3. As can be seen,

the highest frequency of causes are related to design


changes, change orders, and

scope alterations. Another category offrequent responses


covers scheduling, planning,

and coordination. These factors may be as a result of


problems with the design or the

inability of the prime contractor to adequately manage the


project. Overmanning and the effects on labour efficiency
43

CONCLUSIONS The survey confmns in numerical tenns what has


been generally known in the

construction industry, that is, staffmg a project with more


craftsmen than was planned

leads to losses in labor productivity. This infonnation


should be of value to both

contractor and owner in negotiating an equitable adjustment


to the contract sum when
schedule acceleration requires the contractor to hire more
craftsmen than planned.

Thomas, H. R., A. A. Oloufa, and A. S. Hanna. Construction


Productivity Losses

From Ovennanning: A Literature Review and Analysis. Report


to the Electrical

Contracting Foundation, Inc., Bethesda, MD, 29 pp. (1994).

44 Thomas and Arnold Table 2. Efficiency loss multipliers.


Project Type Indoor: All Industrial Commercial
Institutional Line: Loss of Efficiency 11.70 12.25
10.08 9.65 All 10.80 All Indoor and Line 10.20 Projects
Efficiency Loss Multiplier 1.00 1.05 0.92 0.82 Table
3. Principle cause of the acceleration. Cause of the
Acceleration Management (Scheduling, Planning,
Coordination) Labor Weather Design Change Orders/
Scope Alteration Crowding Materials and Equipment Other
No. of Responses 54 9 1 10 50 5 8 4 ~ >u .~ 80
.~ 70 c...... ~ 60 c...... 50 0 en 4 0 en 030 --.l
20 CD ~ 10 I-0 ~ 80 >g 70 .~ 60 ::: 50 w 40
c...... 0 30 en en 20 o --.l 1 0 ~ 0 o I-0
Overmanning and the effects on labour efficiency 45 ° °
° ° ° ° ° ° ° ° ° ° ° 00<ID 00 0 ~ § 8 0 o
008 &C§ &0 ~, ~ 0t C9 <ID0 0<6 8 ~ 0 00 o ° 6b 0 ° 0
o 0<6 0 ° 00 Q) 0 @ 0 0 10 20 30 40 50 60 70 80
90 Percent Overmann~d (%l Figure 1. Total loss 0'
erriciency vs. ~ercent overmanned. o o o o 0 o 2 3
I 4 o Actual Duration / Planned Duration Figure 2.
Total loss 0' erriciency vs. actual dur'ation I planned
duration,

46 Thomas and Arnold 30 (!l Q) (J) c o 0.20 (J) Q)


a:::: '"o '10 Q) ..0 E ::J 20 0.0 0.1 0.2 0.3 0.4
0.5 0.6 OJ Estimated Loss from o'Lermanning Figure 3.
Distribution or estimated proportion or total erriciency
105S attributed to overmanning. >-40 () C Q) ·u 30
'"'"W 20 '"o ~ 10 o ---.J a; a 2 o o o o o o o
o o o o a 10 20 30 40 50 60 70 80 90 Percent Overman
ned (%) Figure 4. Net loss or err;ciency vs. percent
overmanned. Overmanning and the effects on labour
efficiency 47 >() c ~ 1.00 0(l) 'l.J.... (l) >
...... 0.50 co (l) a:: (l) > ...... co :J 0.00 E
:J o 20 406080100120140160180200 U Planned Maximum
Manning Level. Mp Figure 5. Distribution of planned
maximum manning level. Mp. ~25 >() c 20 (l) .() c.IS
c.w '10 0 .(f) (f) 5 0 ---l ...... 0 (l) z: 0
50 100 Percent Overmanned (%1 Figure 6. Net loss of
efficiency vs. percent overmanned.

48 Thomas and Arnold s.Q >-20 u c Q) u '-'-w lO


'-0 (J) (J) 0 ---l ...... 0 Q) z: s.Q l5 >u c
Q) u lO '-'-w '-0 5 (J) (J) 0 ---l ...... Q) 0
z: a / / / / / / 50 / / / / / / / / Indoor
Percent Overmann~d (%1 laO Figure T. Net loss of
efficiency vS. percent overmanned. .--r.--.--. '-l--l
["du~trial In't1t~lional Commercial All Indoor Indoor
r.--L-J ,.-I Small r'-I large Line All Proj.
Literature Work TypeFigure 8. Net loss of efficiency @
50:: overmanned. STEEL FRAMING CREW PERFORMANCE AND
VARIATION Gary R. Smith and Yu-Bin Lin Department of
Civil and Environmental Engineering, Pennsylvania State
University, University Park, Pennsylvania, USA Abstract
Traditional forecasting models, reported for
labor-intensive productivity, have not provided much
insight into structural steel productivity and the factors
affecting steel construction crews. The factor model has
introduced many new facets into evaluating crew level
performance in addition to providing a reasonably accurate
model. Accurate forecasts for crew-level performance can
also be an important element of project control. This
paper examines those factors, which were identified through
project based research, that contribute to steel crew
productivity variation. Understanding this variation is the
key to understanding process control and development of
productivity improvement procedures. Data was compiled
from nine steel frame construction projects. Each work day
was classified according to those factors and disruptions
that had an impact on the crew that day. When combined,
235 days of data were available for analysis. This data
was evaluated for the purpose of determining the most
significant factors and their overall influence on
performance. A model of the crew performance was developed
from the significant factors. Process control chart
concepts were reviewed to identify whether the
variability in the crew performance could have been
identified in a manner that would have permitted
corrective action in a timely fashion. Although
interpretation of the results are somewhat limited, the
combination of process control charts with forecasts may

provide a method to better understand project performance


variation causes and provide an opportunity to better
control the field process.

Key Words: Productivity, Process Control, Steel Construction


The Organization and Management of Construction: Shaping
theory and practice (Volume Two).

Edited by D.A. Langford and A. Retik. Published in 1996 by


E & FN Span. ISBN 0419222405. 50 Smith and Yu-Bin Lin

Sommaire Les modeles traditionnels de prevision des


productivires couteuses en

heures de travail n'ont guere apporre jusqu'ici d'eclairage


sur la productivite

structurelle de l'acier ni sur les facteurs affectant les


equipes de la

construction acier. La modelisation des facteurs, qui


s'avere etre relativement

precise, a mis en lumiere nombre de nouvelles facettes de


l'evaluation du

niveau des performances des equipes. Des previsions


precises du niveau de

performances des equipes peuvent etre un element important


du controle de

projet. Le present papier examine les facteurs, identifies


au cours d'un projet

de recherche, qui affectent les variations de la


productivite des equipes acier.

Com prendre ces variations revient a com prendre Ie


controle des processus et

les procedures d'amelioration du developpement de la


productivite. Les donnees ont He recueillies sur 9
chantiers de construction de

charpentes acier. Chaque journee de travail a ere classee


selon ces facteurs et

selon les evenements qui sont venus deranger l'equipe ce


jour-lao Une fois

compilees, ces donnees representaient 235 jours de donnees


a analyser. Elles

l'ont ete dans Ie but de determiner les facteurs les plus


importants et leur

influence sur les performances des equipes. Le concept des


graphiques de

controle des processus a ere revu pour tenter d'identifier


si la variabilite des

performances des equipes aurait pu etre identifiee d'une


maniere qui aurait

permis une action correctrice a temps. Bien que


l'interpretation des resultats

soit quelque peu limitee, la combinaison des graphiques de


controle des

processus et des previsions pourrait s'averer un bon outil


pour un meilleur

controle des processus sur Ie terrain. Steel framing crew


performance 51

1 Introduction

Developing accurate estimates is important during the


planning and execution phases of

all construction projects. The purpose of this paper is to


introduce quantified factors that

significantly affect steel erection productivity on the


basis of field data. The factor

analysis is viewed as the first step toward developing


accurate estimates. Process control

charts are employed to demonstrate the variability inherent


in the process.

A key to effective forecasting is the development of an


accurate model. Multivariate

factor models have been designed to respond to a range of


factors [1]. Many factors have

been observed which influence productivity like temperature


and humidity [2] and crew

size [3]. Sanders quantified significant factors for


masonry construction [4]. Pace

demonstrated the model was a plausible alternative to


conventional forecasting techniques

[5]. Sakarcan tested the model on international projects


and found it to be reliable [6].

Detailed development of the model has been limited to


masonry productivity.

1.1 Data Collection

The measure chosen for structural steel productivity was


selected as the workhours per

piece (wh/pc). "While the material cost for structural


steelwork is likely most dependent

on the weight of steel members, the labor installation


cost may be more dependent on the

number of members to be placed. [7]"

An important element in model development is a source of


consistent data whose

characteristics are known. Structural steel data was


collected on nine low to mid-rise

projects. Table 1 lists the attributes of the projects


included in the study. Daily data

collection and measurements were performed at the end of


the work shift. Intermittent

visits to the site during the workday were performed to


observe the crew and general site

conditions to supplement the data collection procedures.


Production data and other

information were collected using physical measurements of


completed work and from

observations. Brief discussions with crew supervisors


identified or verified significant

problems, delays, interruptions, or disruptions that


occurred during the day.
1.2 Data Characterization

Data are classified for further analysis according to the


factors identified in the

"Procedures Manual [8]." Interruptions and disruption


events were noted during data

collection. Interruptions are unplanned events or


conditions that cause work to stop.

Examples of interruptions are strikes, accidents, and


equipment breakdown. Disruptions

are unplanned events that impair crew productivity for a


significant period of time. Work

does not come to a complete stop during a disruption,


rather it proceeds at reduced

efficiency. Rainfall, rework, and poor material handling


are examples of disruptions.

Disrupted and interrupted days are set aside from the model
analysis data set to remove

the influence of large disruptions and interruptions in


the model development. The

database contains 235 days of structural steel production


recorded. Eighty (80) days have

been classified from the notes as disrupted workdays,


leaving 155 workdays eligible for

factor model analysis. 52 Smith and Yu-Bin Lin Table 1.


Project Characteristics Project Floor Area Steel
Quantity Total Number Project Type (sf) (pieces)
Workhours 1 Classroom 10,816 642 1109 2 Condominium
13,000 496 902 3 Office 23,920 414 1256 4 Apartment
17,640 399 526 5 Apartment 10,926 86 152 6 Office
14,500 671 894 7 Commercial 45,000 408 891 8
Commercial 32,000 290 889 9 Medical Center 47,092 885
3020 1.3 Modeling Project-related factors, weather zones,
and crew sizes were evaluated using analysis of variance
techniques to determine the statistical significance of
these factors prior to including them in the model. After
deciding which factors could be included in the
regression, the coefficients for the variables can be
obtained though the regression

process. The effects of disruptions are addressed through


an impact comparison to the

average non-disrupted productivity.

2 PROJECT FACTORS

Project factors are specific construction requirements,


dictated by the design of the

project or construction methods, which can be identified


from the plans and

specifications. In this study, project-related factors were


classified as: Work Types,

Physical Elements, Design Details, and Construction


Methods. Workdays are

classified according to the work performed that day.

2.1 Work Types

The Work Type category focuses on the structural system.


Projects often progress

through more than one work type. This is associated with


the work phase and work

type. Five classes of work types were included initially.


Due to insufficient data in

some categories, only three Work Type factors were evident


in the structures studied

are explained below. Table 2 lists the mean productivity


for work types .

• Beam & Girder, Multistory The structure has multiple


floors with nearly identical layouts. Floor loads are
transmitted directly from the floor slabs to the steel
beams and girders. Steel framing crew performance 53

• Beam & Joist, Multistory The structure has multiple


floors with nearly identical

layouts and floor loads are transmitted through web steel


joists to beams and girders .

• Truss or Sloped Roof Roof structure is not flat but is


sloped. The roof system

wi11likely consist of roof purlins and metal deck rather


than a concrete deck.

Table 2. Work Type Average Productivity

Work Type Number of Observations

Beam & Girder, Multistory 129

Beam & Joist, Multistory 22

Truss or Sloped Roof 4

Overall 155 Average (wh/pc) 2.457 3.437 6.285 2.695

An analysis of variance, with the data grouped by Work


Type, indicates that there is a

statistically significant difference between the Work Types


(F-ratio 12.527 and

Significance Level of 0.000). Two of the three work


classes have relatively small

samples which were obtained from a single project and bias


the response.

2.2 Physical Elements

Physical elements are structural components that can be


identified from the

construction drawings. Each work day is classified based


on the predominant physical

element used that day. Two physical elements


classifications were used. Table 3

provides the mean values for these classifications. The


classifications are:

• Beams, Columns, Girts, Bracing, etc. Consists of regular


shapes used in a

conventional manner .
• Trusses and Irregular Shaped Members Work involving roof
trusses, composite,

and irregular shaped members.

Table 3. Physical Element Classification Means

Physical Element

Beams, Columns, Girders

Truss/Irregular Shapes

Overall Number of Observations 151 4 155 Average


(wh/pc) 2.600 6.285 2.695

The analysis of variance indicates a significant


difference between these two factors (F

ratio 18.053, Significance Level 0.000). This result is


highly correlated to Work

Type. 54 Smith and Yu-Bin Lin 2.3 Design Details Design


details are specific features of the work that are more
detailed than the physical elements. Design Detail for
this set of data pertains to different building heights
classified as the number of Tiers. Other than the mean
productivity showing improvement up to the 4th-7th Tier
classification, little can be gained from detailed
analysis of the Tiers for this data. Analysis of variance
indicated that some difference can be identified between
these groups (F-ratio 2.76 and Significance Level of 0.03).

2.4 Construction Methods The Construction Methods


classification indicates if any of the following
circumstances

dominate the work on a particular day. • Normal No unusual


methods or practices observed. • Material HandlingMost of
the day is spent performing material shakeout, stocking,
or resupply. • Steel, Joists and/or Decking Together
Structural steel, joist and/or decking are erected
simultaneously by the same crew and the workhours cannot be
separated.

The mean values obtained from this data classification are


provided in Table 5.

Analysis of variance indicates there is a statistical


difference between these group

means (F-ratio 12.968 and Significance Level 0.000).

Table 5. Construction Method Classification Means Method


Influence Normal Material Handling Steel, Joist and
Decking Combined Overall

3 OTHER FACTORS

3.1 Weather Zones Number of Observations 129 4 22 155


Average (wh/pc) 2.391 3.530 4.323 2.695

Weather information recorded with daily production included


the temperature in

degrees Fahrenheit and the relative humidity. Precipitation


events were also recorded.

The weather data was classified into three temperature


ranges and three humidity

ranges. Those ranges create a matrix of nine weather


zones. Analysis of variance was

performed for Temperature, Humidity, and Zones. While many


other studies have

indicated weather has a direct influence, none of the


analyses indicated a significant

effect by the weather. This may be due to the workers


adjusting to the conditions or Steel framing crew
performance 55

other variability in performance is large enough to mask


the effect of weather.

3.2 Crew Size

The distribution of crew sizes ranged from one to twelve


workers. Analysis of variance

shows significant differences among the crew sizes, but


with a great deal of inconsistency

in the responses. When considering the optimal structural


steel crew size range, the job

site area and crane size should also be taken into


consideration. This data was not

available for analysis. Therefore, crew size, until more


variables affecting it are defined

and understood, should not be included in the model.

4 MODEL DEVELOPMENT

A stepwise regression analysis was used to determine the


order of selection and which

variables would be selected for inclusion in the model. The


stepwise model uses a

minimum F-value of 1.5 as the criteria to include or remove


a factor from the model.

Table 7 summarizes the factor coefficients for the six


variables included in the model.

The number in parentheses for the stepwise model indicates


the order in which the

variables entered the model. The standard conditions of


the model are:

• Work Type Beam & Girder, Multistory

• Physical Elements Beams, Columns, Girders, Bracing

• Design Detail None

• Construction Method Normal

• Weather-Zone 5 (Medium Temperatures 40°F-80°F and Medium


Humidity 45 %-80%)

Table 7. Regression Model Coefficients and t-values

Factor Factor Coefficient t-value (Selection Order)

Constant 3.45

Trusses or Sloped Roof 2.94 (2) 3.51

1st Tier -1.29 (5) 3.15

2nd-3rd Tier -1.77 (3) 4.58


4th-7th Tier -1.51 (4) 3.85

Steel, Joist and Decking

Together 1.90 (1) 4.49

Medium Temperature,

High Humidity 0.66 (6) 1.68

R-Square 30.85 56 Smith and Yu-Bin Lin 4.1 Model


Evaluation Qualitatively the results are consistent with
the analysis of variance findings. The first variable
selected by a stepwise regression was the Steel, Joists and
Decking placed concurrently. The second variable included
was the sloped roof and truss elements. This factor will
only be used in the event this particular type of work is
encountered. Each of the first two factors included in the
regression represent fairly small data sets. Perhaps the
most significant factor group was the tier designations.
The coefficients indicate that productivity improves with
increased floors. This is felt to be an influence of
repetition in the connections and consistency of the work
activity. The final variable selected for inclusion was
the High Humidity, Medium Temperature zone. This shows a
slightly reduced productivity. High temperature and high
humidity was not included due to a lack of data. An
R-square of 30.85 shows that the model is a fairly weak
predictor of the data set from which it was derived. Since
major disruptions have been set aside, the factor model
clearly indicates that there remains a significant amount
of internal variability that is unexplained. 5 DISRUPTION
ANALYSIS Table 8 summarizes the classifications of
disruptions and the mean productivity value determined for
each set of data. Due to the small data sets for each noted
disruption, the results appear to be somewhat erratic. It
would be expected that a disruption in production would
result in worsening productivity. In some cases the index
shown here would suggest improved productivity. The
disruption index is the mean undisrupted

productivity divided by the mean disrupted productivity.


Table 8. Disruption Mean Values and Index Type of
Disruption (observations included) None (141)
Size/Layout of Material Storage Area (3) Site Cleanliness
(3) Material Handling (4) Material Availability (4) Tool
Availability (2) Out of Sequence Work (8)
Rework/Fabrication Errors (8) Equipment Availability (2)
Staffing (2) Weather (8) Mean Value (wh/pc) 3.20 6.57
2.53 3.67 5.12 4.89 2.89 3.61 0.55 2.33 3.33
Disruption Index 1.00 0.49 1.26 0.87 0.62 0.65 1.11
0.89 5.85 1.37 0.96 Steel framing crew performance 57

6 CONTROL CHART EVALUATION

While control charts are quite common in practice for


quality control applications, it

was felt that they may provide a more relative measure for
understanding project

productivity and variation. For this evaluation, the


project with the most consistent

daily work output was selected as the basis for the mean
and standard deviation. This

procedure provided more restrictive upper and lower control


limits.

Figure 1 is representative of many projects that have only


a few incidents that

significantly disrupt production. The average productivity


for this project was lower

than the control chart mean, including the disrupted days.


A large proportion of the

project data is noted as disrupted. The field notes


indicate that this crew had many

tool and material problems, but the data plot would


suggest that the crew compensated

for these problems and maintained a degree of control.


Figure 2 illustrates a project

that was overwhelmed by disruptions. However, the project


did have a series of days,

late in the project, that fall within the control region,


which suggests that the project

had the potential to work within the control limits.

Superficially, the control charts can make average projects


look fairly good.

Current upper and lower control limits range from 0.62


mh/pc to 3.19 mh/pc. This

wide range of "normal production" may cover a range that


is too large for control

purposes. At this time much of the variability within this


region is felt to be related to

the process itself and not necessarily to external factors


considered by the models.

Whether the control charts can be useful for project


control purposes is still

questionable because of the large variations permitted


within the upper action limits. 9

~ 8

.l

c:= ~

'" ,

>6

> 5

u 4 ~

·0

0 3

CL 2 iJ n DAIL Y PRODUCTIVITY PROJECT 6 o Disruption


Noted Within Limits if) Disruption Noted Outside Limits
UCL~3.190 MU~1.904 LCL~0.6176 1 0 15 20 25 ItJorkday

Figure 1 Control Chart of A Typical Project 58 Smith and


Yu-Bin Lin 10 u c-9 > U ::J -0 o 8 7 6 5 4 ct
. 3 2 o o DAIL Y PRODUCTIVITY PROJECT 3 1 0 20 30
Workday

Figure 2 Control Chart for a Severely Disrupted Project

6 SUMMARY 40 UCL=3.190 MU=1.904 LCL=0.6176


The control charts show there is a great amount of
fluctuation within "normal data"

which is not measured by the factors currently evaluated in


the factor model. The

factor model and control charts demonstrate the difficulty


of modeling performance

from field data. Large amounts of variation remain to be


explained by either model.

However, the combination of techniques provides useful


insight into improvements

needed in recording and measuring productivity at the


project level for developing

forecasting tools.

1 Thomas, H. R. and I. Yiakoumis, "Factor Model of


Construction Productivity", Journal of Construction
Engineering and Management, ASCE, Vol. 113, No.4, December
1987, pp 623-639.

2 Smith, G.R. and S. Kilroy, Operations Impact From


Temperature and Humidity, Proceedings of the Canadian
Society for Civil Engineers 1994 Annual Meeting, Winnipeg,
Manitoba, Canada Steel framing crew performance 59

3 Swank, Joseph. An Exploratory Study of the Effects of


Crew Size on Productivity in Masonry Construction.
Master's Thesis, The Pennsylvania State University, 1989.

4 Sanders, S.R., An Analysis of Factors Affecting Labor


Productivity in Masonry Construction, Doctoral Thesis, The
Pennsylvania State University, August 1989.

5 Pace, J.M., A Comparative Analysis of Work-Hour


Forecastin2 Techniques at the Crew level, Master of
Science Thesis, The Pennsylvania State University,
December 1989.

6 Sakarcan, A. S., An Evaluation of Forecasting Capability


of the Factor Model for Masonry Projects, Master of
Science Thesis, The Pennsylvania State University, May
1992.

7 Adrian, J. J., Construction Estimating. Reston


Publishing Co. Inc., Reston, Virginia, 1982.
8 Thomas, H. R., M. W. Homer and, G. R. Smith. Procedures
Manual for Collecting Productivity and Related Data of
Labor-Intensive Activities on Commercial Construction
Project: Structural Steel. December 1990. ANALYSIS OF
CONSTRUCTION DELAYS T.M. Lewis Department of Civil
Engineering, University of the West Indies, St Augustine,
Trinidad B.A. Atherley Project Manager, W.W. Micron Ltd,
Port of Spain, Trinidad Abstract This report presents the
results of an investigation into the nature, length and
cost of delays, that occurred on thirty (30) building
projects in Trinidad and Tobago. This paper first
discusses the circumstances that give rise to delays, the
classification of these according to responsibility and
the effects they have on the project cost and schedule.
The data are presented, analysed, and conclusions drawn.
Sommaire Ce travail present les resultats d'une recherche
sur la nature duree et coilt des delais qui se sont
arrivee en trent (30) projets de construction a Trinite et
Tobago. Ce travail debatte premierement les circumstances
qui donnent naissance aces delais, classifie ceux-ci,
selon la responsabilite et analyse les effets de ceux-ci
sur Ie coilt et Ie progres de chaque projet. Les donnees
sont presentees, analysees et conclusions sont obtenues
Keywords: Delays, classification of delays, excusability,
compensability, responsibility, cost implications, survey,
West Indies. 1. Introduction When a piece of work is
scheduled to be carried out on a particular day and for
some reason cannot be completed, a delay is said to have
occurred. This may be of little consequence, unless it
affects subsequent work when it may become significant in
terms of both its planning and its financial implications.
Significant delays that occur during a construction
project will either extend its duration or increase its
cost or both. In addition, if completion is delayed the
client may also lose out financially by not having the
facility (and its potential income) available when wanted,
and the contractor may lose out by not having his
resources released to take on other work. Unfortunately,
there are all too many factors that can cause delays to
construction work, from those inherent in the technology
and its management, to those resulting from the physical,
social and financial environment. Because there are often
financial The Organization and Management of Construction:
Shaping theory and practice (Volume Two).

Edited by D.A. Langford and A. Retik. Published in 1996 by


E & FN Spon. ISBN 0 419 22240 5. Analysis of construction
delays 61 implications to delays, the parties involved are
normally interested in determining their causes and
allocating responsibility. However, it is rarely easy to
determine a unique

cause, or to allocate responsibility and this, naturally,


leads to disputes between the

parties involved. An assessment of delays should try to


determine as many of the following factors

as possible, as these are inevitably the focus of


disputes: (a) what factor or factors caused the delay,
(b) who was responsible, (c) how long was the delay
attributable to anyone factor (d) what extra costs were
incurred as a result of a delay.

These are the factors that have been concentrated on here.


The standard forms of building contracts do not seem to be
particularly well

designed for dealing with delays. As a result delays often


lead to disputes, which can

easily lead to litigation aimed at trying to establish


legal responsibility and allocate

additional costs. Because litigation is itself such an


expensive and long winded

process, it is best avoided. If it is possible to identify


the main causes of significant

delays then it may be possible to introduce contractual or


policy measures which could

help them be avoided in future. In order to investigate


the structure of delays, their causes and the costs

associated with them, a survey was undertaken into


experiences on a number of

construction projects (30) in Trinidad & Tobago over the


period from 1979 1992. In

all cases, the projects were let by a client, used a design


consultant, employed some

form of site supervision and were built by general and


specialist contractors selected by

conventional tender methods. Taking a year that had


statistics fairly typical of the

period, construction in Trinidad and Tobago for the year


1990 accounted for 8.8% of

the Gross Domestic Product (current prices) and for


approximately 11% of the

employed labour force [6][7].

2. Definition and Classification of Delays

2.1 What is a Delay?

The traditional, and still the most common procedure for


letting a contract is on the

basis of the lowest bidder. This contract document


normally stipulates, amongst other

things, the starting date and a completion date for the


project Problems which occur

during construction may cause a delay which results in the


project duration being

extended beyond the scheduled completion date. On


contracts which have interim

partial completion targets, a significant delay may occur


when anyone of the target

dates is not met. There is also the disruptive element to


consider, as delay in one

aspect may set back another aspect in a more than


proportional amount, and this can

have a 'knock-on' effect Most organisations are concerned


with 'the bottom line', and the bottom line is that a
delay can increase costs and reduce profits. A delay may
have direct cost implications in terms of an extended
construction period, which will mean extra

expense for the contractor in terms of salaries, plant and


equipment expenses and

additional overheads. Depending on the cause, these


additional costs mayor may not
be recoverable from the client, but this is only one part
of the cost equation. A delay may have implications which
go far beyond the cost of the construction

phase of the project, because commercial or environmental


'windows' may not be

achieved. Such failures can have serious consequences in


terms of the cash flow from

the project, because of additional financial charges to be


met and lack of use of the

facilities being constructed. In the case of an offshore


oil platform, for example, this

may mean loss of revenues in the hundreds of millions of


dollars per week, and even

for a more normal commercial investment, the failure to


meet a window of opportunity

like a peak seasonal deadline (e.g. Christmas) may change


the project's whole 62 Lewis and Atherley financial
complexion. Because every project will have a different set
of financial implications associated with late delivery,
little could be learned from attempting to generalise from
a few specifics. As a result, this investigation focuses on
the implications of delays on direct costs during the
construction phase of projects. As a result, because
delays are both disruptive and expensive, they merit close

scrutiny.

2.2 Types of Delays The general principle underlying a


contract is that "a party under contract has an

absolute obligation to perform, barring breach or


unfulfilled conditions by the other

side" [3]. Where one of the contract clauses stipulates a


completion date, this becomes

one of the conditions of the contract that must be met,


and, clearly, a delay may imply a

breach of that condition. However, there are obviously


circumstances when the cause of a delay is a factor that
is beyond the control of any party to the contract and it
would be unfair to blame one party for a breach. Thus,
when examining delays, it is necessary to try to
establish where responsibility lies, and it is convenient
to classify delays under three main headings: (i)
Excusable delays, (ii) Non-excusable delays, (iii)
Concurrent delays. Taken from the viewpoint of the
contractor, these classifications would be

expanded as, (i) Excusable delays are those caused by


unforeseeable factors outside the control of the
contractor. They may be either (a) Compensable excusable
delays, i.e. those for which the contractor is entitled to
claim damages from the owner, or (b) Non-compensable
excusable delays, i.e. those for which no one can be held
responsible. (ii) Non-excusable delays are those that are
deemed to be the fault of the contractor, because they
were within his control and should have been foreseeable.
(iii) Concurrent delays occur when two or more delays occur
at the same time. Any analysis is complicated by details,
and when people are involved, details

proliferate. As an example of the sort of complications


that can arise, the following

quotation is apposite: " ... suppose the owner failed to


supply certain materials on time.

At the same time, the workers who would have installed the
materials were on strike.

The contractor cannot claim damages for work that would


not have been accomplished

had the owner-caused delay not occurred. He would, however,


be entitled to a time

extension for the period of the strike unless it can be


proved that the strike was due to

his own actions. This is an example of concurrent


compensable and non-compensable

delays. The result is a time extension, but no damages for


the contractor". [4]

3.Causes of Delays

3.1 Excusable Non-Compensable Delays

In the case of excusable non-compensable delays the


following have been reported [3]
as being the most frequently given for excusing timely
performance: (i) Act of God natural disasters such as
earthquakes, tornadoes, hurricanes, volcanic eruptions,
floods and fire, (ji) 'Force Majeure' (excepted or
accepted risks) all acts of God, war, insurrection, riots,
major labour strikes, Acts of the State, Analysis of
construction delays 63 (iii) Weather when weather becomes
unusually severe and surpasses the normal (i.e. average
conditions for an area over the previous ten years based on
meteorological data) for that particular locality during a
specific season of the year, it becomes a factor excusing
delay.

3.2 Excusable Compensable Delays

Excusable compensable delays, which are attributable to the


client, entitle the contractor

to an extension of time and a claim for damages. "The


basis of recovery of damages for

delays is the implied obligation that the owner will


co-operate with the contractor and

not impede the performance of the work of the contractor"


[4]. Delays which are both

compensable and excusable are most frequently caused [3]


by the following: (i) failure to hand over the total site
on time, (ii) slow payments to the contractors, (iii)
errors in drawings and specifications, (iv) late detailing
of work, (v) slow approval of fabrication drawings.

3.3 Non-Excusable Delays

Non-excusable delays are those deemed to be the


responsibility of the contractor.

Thus, a contractor who extends his work beyond the original


completion date for

causes which could be shown to be foreseeable and


avoidable, is liable to the client for

monetary damages for the delay, in the form of actual or


liquidated damages [4]. The

more common causes are reported [3] to be: (i) failure to


properly co-ordinate men, materials and equipment, (ii)
failure to properly finance the project, (iii) failure
to submit shop drawings promptly, (iv) failure to employ
competent personnel.

4. Effects of Delays

A delay tends to act like a virus very slowly, but with far
reaching effects. Like the

symptoms of a virus, there are symptoms which are


indicative of a situation developing

which may lead to a delay, they are: (a) a general slowing


down of the job, (b) inefficient use of the weather,
i.e. not using dry weather effectively, (c) improper
sequencing of activities, leading to work stoppages on
some tasks In an attempt to solve these problems there is
a tendency to want to accelerate the

work. However, acceleration is no guarantee that the job


is going to be finished on

time, and it is almost certain to increased costs because


it usually involves on of the

following: (i) increase of the labour crew, (ii) increase


in the working hours of the present crew, (iii)
sub-contracting out sections of the work to specialists,
(iv) hiring more equipment or more up-to-date equipment,
(v) any combination of items (i) to (iv). The increased
cost of accelerating a job must be carefully considered by
both the

client and contractor before the decision is taken. The


contractor may favour

acceleration of the job at his own expense if he feels


that he may be held responsible

for the delay and: (i) the liquidated damages are more
costly than acceleration, (ii) certain operations are
heading for an unfavourable time of year, (iii) the same
men and equipment are needed on another job, 64 Lewis and
Ather/ey (iv) specialist trades/services may be delayed
and higher costs incurred. The client may favour
acceleration of the job at his own expense if he feels
that he is responsible for the delays and: (i) he will
have to pay penalty costs to the contractor for extending
the period, (ii) the original completion date has special
significance, (iii) the project will suffer a loss of
profits greater than the cost of acceleration In some
cases, in the interests of goodwill, and where both
parties perceive it to be to their benefit, the costs of
acceleration may be shared between owner and contractor.
It is also possible for delays to have a positive side
effect, as when delays are apparently inescapable, and the
effects are sufficiently costly, the parties to the
contract may be inspired to seek new and innovative means
of avoiding them. The solutions that evolve may enable
future problems to be avoided. The worst effect of delays
to a construction project is the termination of the

contract by either party. It is normally a last resort


action taken by an owner, who terminates the contract for
excessive non-excusable delays. Any such termination must
take place within the legal framework of the contract.

5 Standard Contract Provisions For Delays

Claims can arise for many different reasons and between any
of the parties involved in

or affected by a contract, however, this paper seeks only


to examine the claims

between client and contractor resulting from delays on


contracts using the most

common locally employed contract documents, i.e. the


Trinidad and Tobago Institute

of Architects (TTIA) [8], standard form of building


contract (with quantities-I974

edition) and the ICE (Institution of Civil Engineers)


conditions of contract [2].

6 Analysis Of Delays From 30 Projects

The data collected are all from professionally designed and


supervised projects, which

used the more common standard forms of building contracts.


While the thirty (30)

projects studied were not sufficient for a statistically


significant analysis, the sample

size was large enough to suggest trends in the data, and


those trends are compatible
with results obtained from a study of the nature and
extent of variations to building

contracts in Australia [1].

6.1 Accuracy and Consistency of Data

The data collected were for projects done between the years
1978 to 1992 inclusive.

There is no significance to be attached to these years,


other than that more up-to-date

data were not available. The details of the actual delays


were reasonably well recorded because the

projects had used bar charts which had been regularly


updated. The contract documents

required that scheduling techniques should be used and bar


charts were all that were

used on all except two jobs. Hence, whether the information


came from the contractor

or the consultant the point of reference was always the


contractor's bar chart. As far as the costing of the
delays was concerned big differences were observed

between the contractors' records and those of the


consultants. Where quantity

surveyor's letters were available, they were the points of


reference for both parties,

since in most cases they detailed the sums in question. In


their valuations, however,

the contractors tended to lump the cost of supervision,


extra work, additions and

variations together, and to cost delays on the basis of


what they spent directly to get the

job done rather than to try to break-down the cost of the


work into elements and Analysis of construction delays 65
associated overheads. By comparison, the consultants tended
to try to identify items of work associated specifically
with the delays, broken-down into their elements and
valued at rates given in the bills of quantities, and these
valuations were used to review the contractors' claims
with a view to their acceptance, rejection or reduction to
'acceptable' levels. Consultants did not normally increase
bill rates or overhead allowances to account for extra
time required on the project. It was rarely possible to
check data on a specific delay with both consultants and
contractors involved because a questionnaire approach was
used to collect data and it was not possible to get
responses on the same project from both. Personal
interviews were conducted with all but one respondent in
order to discuss the details of the

projects and the delays involved, and a telephone interview


was conducted with the

other respondent.

6.2 The Basic Data

The data was obtained from seven organisations representing


a spread of interests in

the construction field. Their distribution and the number


of projects analysed from

each were as follows: lI-roup Type Projects Consultants


Engineering firms (2) 8 Architectural firm 2 Contractors
(2 independent firms) 12 Project Manager 7 Government
Ministry of Drainage 1 :ill Table 1 lists the clients,
the total cost of the contract, the total number, the total

cost and the total length of delays on each contract. All


costs and values, are quoted in

Trinidad and Tobago dollars (approximately TT$6 = US$I).


The figures show that on contracts worth $56,626,485, 95
significant delays

occurred, the delays cost $4,561,963 and involved 424 lost


weeks of work. The cost

of delays represents approximately 8% of the overall cost


of the contracts. The total

cost shown is the cost of the particular contract


involved, not of the entire project, for

example, the Hall of Justice (project #21) had an overall


cost of over TT$400 million,
while the painting contract reported here was worth TT$1.4
million. All these projects

were professionally designed and supervised. Table 2 gives


a more detailed breakdown of the 95 specific delays that
were

reported on the 30 projects. Briefly summarising the data


in Table 2, 57 of the delays

were deemed excusable and compensable, and these delays


accounted for $4,333,972

of extra cost and 290 extra weeks of work. The delays which
were deemed to be non

compensable numbered 38, and these accounted for $227,991


of extra cost and 132

weeks of extra work. Included amongst the


excusable/compensable figures are two items recorded as

"Claims for loss and expense". These account for $580,000


of extra cost and no extra

time. These were claims put in by the contractors for extra


payments against increased

overheads and loss of other work, which were caused by


their being delayed on a job

(for reasons deemed excusable/compensable), but not having


claimed this

compensation against any other specific delay. A degree of


consistency was achieved in the analysis because in most
cases the

description of the details and the nature of the delay were


agreed between the

respondentsand the conductor of the survey. 66 Lewis and


Atherley TABLE 1 A al . f P n lysIS 0 roJects
Project/Client Total Cost Total ($) No. of Delays 1.
Housin1! Development 8,600,000 2 2. Housing Development
8,400,000 2 3. Bus Terminal 7,000,000 5 4. *M.o.W.
Drainage Division 35,000 1 5. *U.W.I. Inflammable
Stores 263,647 3 6. *U.w.I. Environmental Lab. 488,782
3 7. *U.W.I. Fluids Lab. 412,734 4 8. *D.W.I. Offices
and Classrooms 1,330,716 4 9. *D.W.I. Electrical and
Electronic Lab 948,133 5 10. Ghany Site 21,000 2 11.
Ishmael Khan 63,000 2 12. Trinidad Cement Limited
63,000 3 13. National Petroleum Ltd. 5,800 1 14.
Print Masters 29,440 1 15. Associated Bnmds 12,000 1
16. *T.S.T.T. 29,000 1 17. *NIHERST 46,000 1 18.
Government Health Center 23,530 1 19. *U.W.I. Offices
and Classrooms 2 12,628,046 5 20. Colsort Mall 450,000
6 21. Hall of Justice 1,400,000 5 22. Farrell House
150,000 7 23. *U.w.I. Hi1!h Volta1!e Lab. 878,810 8
24. *D.W.I. Food Technolo~ Lab. 3,909,682 7 25. Scotia
Bank Not available 4 26. Free Zone 1,600,000 2 27.
Bank of Commerce 2,300,000 2 28. *TELCO Head Office
4,800,000 3 29. Hand Arnold 580,000 2 30. *D.W.I.
FoodProcessin~Lab. 158,165 2 Totals 56,626,485 95 . .
.. *M.o. W. Ministry of Works, Government of Tnmdad &
Tobago * U. W.1. University of the west Indies, St.
Augustine Campus *T.S.T.T.Telecommunications Services of
Trinidad and Tobago Limited Total Cost of Delays ($)
250,000 210,000 210,000 15,836 12,000 259,724 82,767
12,700 16,000 8,000 1,285 278,591 190,000 1,060,000
75,000 465,000 845,012 500,000 50,000 20,048
4,561,963 *NIHERST National Institute of Higher Education
(Research Science & Technology) 'TELCO Telephone Company
Total Length of Delay (wks) 48 36 48 2 3 13 12 4
13 4 8 4 2.5 4 3 5 2 4.5 16 14 29 28 43 36
8 4 4 16 6 4 424 Analysis of construction delays 67
TABLE 2 NATURE, TYPE, COST AND LENGTH OF DELAYS Project
Nature of Delay Type Cost Length No. * ($) (wks) 1.
Payment delays by client E/C 150,000 24 Part of si te
not available E/C 100,000 24 2. Part of site not
available E/C 100,000 12 Payment delay by client E/C
110,000 24 3. Poor work sequencing by contractor NE
Procurement failures by contractor NE 24 Lack of manpower
by contractor NE 16 Payment delay by client E/C 60,000
8 Extra works E/C 150,000 4. Heavy rains/floodin2 of
iob site E/C 2 5. Subsurface different than expected
E/C 0.5 Heavy rains ElNC 1 Procurin2 failures by
subcontractor NE 1.5 6. Additional work demanded by
client: Furniture changes E/C 8,000 8 Equipment
changes E/C 2,375 3 Structural work E/C 5,461 2 7.
Additional work demanded by client: Plumbing changes E/C
3,000 3 Structural Work E/C 4,229 3 Electrical Work
E/C 3,000 4 Cupboards chan2ed E/C 1,771 2 8. Errors
in plans & specs. E/C 22,784 Ambiguities in plans and
specs. E/C 35,896 Change sequence by contractor NE
20,000 Additional work by owner E/C 181,044 4 9.
Ambiguities in plans & specs. E/C 3,250 1 Oruissions in
plans & specs. E/C 19,637 4 Errors in interpretation
(floor finishes) ElNC 4,200 2 Additional work (client
brief) EIC 22,142 2 Chan2e order by new client EIC
33,538 4 10. Change sequence by contractor NE 1
Utility not available by owner E/C 12,700 3 11. Change
method by contractor NE Poor scheduliDR of work bv
contractor NE 16,000 8 12. Change method by contractor
NE Utility not available by owner E/C Redo work by
contractor NE 8,000 4 13. Change sequence by contractor
NE 2.5 14. Procurement failures by contractor NE 4
15. Lack of productivity by contractor NE 3 16. Lack
of productivity by contractor NE 5 17. Additional work
b~_dient E/C 1,285 2 18. Chan2e sequence by contractor
NE 4.5 19. Heavy rains ElNC 18,591 1.5 Oruissions in
plans & specs. E/C 160,000 2.5 Procurement failures by
contractor NE 36,000 4 Consultants change scope of work
E/C 60,000 4 Late power supply connections E/C 4,000 4

68 Lewis and Atherley TABLE 2 (Continued) Project Nature


of Delay Type Cost No. * ($) 20 Errors in plans &
specs. E/C 12,400 Ambiguities in plans and specs. E/C
14,600 Omissions in plans & specs. E/C 23,700 Strike by
General Contractor E/C 10,000 Additional work E/C
102,300 Redo ftnished work NE 27,000 21. Ambiguities
in plans & specs. E/C 106,000 Omissions in plans &
specs. E/C 170,000 Day works E/C 200,000 Extra
painting/variations E/C 500,000 Redo ftnished work NE
84,000 22. Heavy rains EtNC 1,000 Omissions in plans &
specs. E/C 4,000 Change in sequence by contractor NE
4,000 Procurement failures by contractor NE 3,000 Strike
by main contractor E/C 2,600 Redo work damaged by strike
E/C 10,000 Additional work by client E/C 50,400 23.
Errors in plans & specs. E/C 20,000 Ambiguities in plans
& specs E/C 5,000 Omissions in plans & specs. E/C
100,000 Procurement failures by contractor NE **
Procurement failures by contractor NE ** Additional work
by client E/C 260,000 Late shop drawing approval by
consultant EtC ** aaim for loss & expense E/C 80,000 24.
Errors in plans & specs. E/C 17,750 Ambiguities in plans
& specs. EtC 15,000 Omissions in plans & specs. EtC
31,948 Heavy rains no work EtNC ** Procurement failures
by contractor NE ** Additional work E/C 280,314
aairns for loss & expense EtC 500,000 25. Poor means of
sequencing by contractor NE Procurement failures by
contractor NE Procurement failure by subcontractor NE
Poor scheduling of work by contractor NE 26. Procurement
failures by contractor NE Lack of manDOwer NE 27. Poor
work sequencing by contractor NE Lack of space at site
meetings ? 28. Slow change in project brief requirements
E/C Poor work sequencing by contractor NE ** Additional
work by client E/C 500,000 29. Poor work sequencing by
Contractor NE 6,200 Additional work E/C 43,800 30.
Errors in plans & specs. EtC 2,200 Additional work bv
client E/C 17,848 • EtC = Excusable Compensable; EINC =
Excusable Non-Compensable; NE = Non-Excusable ** Difficult
to quantify Length (wks) 1 1 2 4 4 2 2 3.5 4.5
17 2 3 2 2 2 8 4 7 4 3 7 4 4 20 1 4 4 2
4 4 18 2 2 3 1 4 2 2 4 6 6 3 3 2 2
Analysis of construction delays 69 6.3 The Data Collected
Given that some computation was necessary on the part of
the respondents to separate information related to the
delay from the rest of the stored information, it was
gratifying to receive data on thirty (30) projects. The
data covered some ninety five (95) recorded delays caused
by a fairly wide range of factors. Seven (7) individual
organisations were involved, and they provided information
on projects as shown in Table 2. 7. Discussion of Results
During the interviews with those involved, it was felt that
the projects analysed here were not untypical of the
projects being constructed in Trinidad and Tobago at that
time, in other words, they were neither worse nor better
than average in the number of delays that they suffered.
Although each case study represented a 'project' to the
company concerned, they did not all represent complete
projects to the clients involved, e.g. the painting
contract for the Halls of Justice was a project to the
contractor, but only a very small element of the total
project to the client. This was not expected to make any
difference to the conduct of the work either by the
contractor or by the client or his representative, or to
affect the results of this survey. It is clear that the
majority of the delays which were detailed fell into the
category 'compensable excusable'. This bias almost
certainly resulted from the fact that the contractors
would have been much more aware of the need to fully
document delays which they felt they could claim
compensation for. Equally, the consultants would have been
aware of the contractor's intention to claim and would
also have recorded

relevant details. The non-compensable delays are made up


of the portion of the delays that were

claimed for but rejected, as well as the delays that were


recorded in diaries and minutes

of meetings but not claimed for. In no cases did the client


enforce the 'liquidated

damages' or penalty clauses which were in the contract


documents, even though very
significant delays (over 40 weeks) were experienced on
some of the contracts. Where values have been given for
non-excusable or non-compensable delays

these figures were either on record as claims or were


derived from the actual costs

involved in redoing work, or in accelerating the work to


get it back on schedule. One overall pattern that did
emerge was that main contractors suffer more delays,

and more costly delays than subcontractors. This may have


simply been a scale related

fact i.e. the more work you do the more likely you are to
experience problems (which

seems to be substantiated in the related finding that


larger jobs tended to have more

delays than smaller ones), or it may have been to do with


the timing of their

participation in the works. The main contractor is likely


to be involved earlier in the life

of a project, and hence at a time when it is likely to be


least fully finalised, and when

the site is least prepared subcontractors tend to get


involved later on when things have

settled down, and problems causing delays are less likely


to arise. The general economic climate during the period
under study was one of recession

and high levels of unemployment, and this generally tended


to keep industrial action to

a minimum. Only two projects were affected by strike


action, and in both cases it was

the work of the subcontractor being delayed by a strike


affecting the main contractor

that was recorded. As a result, in those two instances,


what would otherwise have

been an excusable but non-compensable delay became


compensable as the
subcontractor claimed against the main contractor. By far
the largest factor leading to delays was the client
requiring changes or

additions to be made to the project. If the 'top ten'


causes for delays (by additional cost

incurred) are listed (see tabulation below) it will be seen


that the quality of the drawings

and specifications that the contractors' had to work with


appeared to leave much to be 70 Lewis and Atherley
desired. When the omissions, ambiguities and errors (items
4,7 & 9) in these documents are added to variations
required by the consultants, they accounted for claims
amounting to $1,528,365 and for delays totaling 72.5
weeks. The consultants who were interviewed indicated that
this was not a fair reflection of their performance or
competence as most of the variations and the problems with
drawings and specifications arose because of late design
changes that emanated from the clients. They, the
consultants, had to respond and make the desired changes,
and it was this which caused the delays and cost
increases. # Nature Cost (:Ii) Length 1 Additional work
by client 1,636,970 99 weeks 2 Variations by consultants
760,000 25.5 weeks 3 Claims for loss and expense 580,000
4 Omissions in drawings & specs. 509,285 23 weeks 5 Late
payment by client 320,000 56 weeks 6 Unavailability of
whole or part of site 212,700 39 weeks 7 Ambiguities in
drawings & specs. 179,746 11 weeks 8 Redo work damaged
by other trades 129,000 12 weeks 9 Errors in drawings
and specs. 79,334 13 weeks 10 Poor scheduling or change
of sequence 46,200 32 weeks It should also be added that
during recessionary times the process of decision

making on capital investments tends to slow down, as a


result of this the period over

which the design process takes place tends to expand. In


the projects examined, for

example, the design of project 19 (University buildings)


took 5 years from conception

to tender. Given the rate of technological change, it is


hardly surprising that the client

required changes to be made to the project definition


between the time of the brief and
the tender and before the completion of the building when
such time scales are

involved.

In addition to this, as Bromilow has noted " ...


Variations are needed to help the cost

steering process and to cope with new ideas, changes in


technology and mistakes; they

are, contrary to the view of many, an inevitable part of


the building process. "[I] We

are dealing with delays rather than variations, but in


practice, they tend to be

interdependent. Delays are often a consequence of


variations;

During recessionary times the pressure to meet cost targets


increases, and this leads

clients to 'tinker' with their projects in order to try to


effect savings. For example, on

this particular project, in the original design (carried


out during the boom years) all

services were centrally controlled, there were not even


light switches in the individual

rooms. With the onset of the recession before building got


under way, increasing

awareness of the need to control energy costs led the


client to demand a revision of the

design to allow lights to be switched off in each room.


Such 'cost steering' variations

led to design changes, which led to delays. Although the


effect of such tinkering may

be delays and extra costs in the short term, in the longer


term they may well be cost

saving, and hence very cost effective.


1. Bromilow, F. J. (1969). Measurements and Scheduling of
Construction Time and Cost Performance in the Building
Industry. Report of the Division of Building Research
Division. CIRlA: Melbourne. Analysis of construction
delays 71

2. ICE Conditions of Contract. (1979). Conditions of


Contract and Forms of Tender, Agreement and Bond for use
in Connection with Works of Civil Engineering
Construction. 5th ed., London: The Institute of Civil
Engineers.

3. Richter, I. E. (1983). International Construction


Claims: Avoiding and Resolving Disputes. New York:
McGraw-Hill.

4. Rubin, R. A., Guy, S. A. and Maevis, A. C. (1983).


Construction Claims Analysis, Presentation. Defence New
York: VanNostrand Reinhold.

S. Stokes, M. (1977). Construction Law in Contractors'


Language. New York: McGraw-Hill.

6. Trinidad and Tobago. Central Statistical Office.


(1992). Review at the Economy l!l!lL Port of Spain:
Government Printery.

7. Trinidad and Tobago, Central Statistical Office. (1992).


Annual Statistical Digest 1990' No. 37 Port of Spain:
Government Printery.

8. Trinidad and Tobago Institute of Architects. (1974)


Standard Form of Building Contract with Quantities. Port
of Spain: Trinidad and Tobago Institute of Architects.
CLIENT BENCHMARKING OF CONTRACTOR PERFORMANCE D.8aldry
Department of Surveying, University of Salford, Salford, UK
Abstract Substantial clients of construction with
extensive development programmes invariably employ a range
of contracting organisations. Some clients, notably in the
public sector, may employ widely from an extensive panel
of contractors, whereas others may adopt an approach in
which a single or limited number of contractors are
engaged for the completion of a programme, in a manner
which has become known as partnering. Notwithstanding the
procurement approach adopted there is an ongoing necessity
for clients to have some means of objectively assessing
the performance and reputation of these contractors as a
way of evaluating current activities and also influencing
future procurement directions. Benchmarking has emerged
as a means by which participants in an industrial or
commercial process may monitor performance by reference to
verifiable evidence from comparable activities, posSloly
derived from some mutual information sharing agreement.
This paper examines ways in which significant construction
industry employers may adopt this process as an integral
part of their procurement decision making and action as a
means of enhancing project performance and predictability.
Keywords: Benchmarking, contractors, performance,
procurement Sommaire Des clients importants de
l'industrie de la Construction, ayant de vastes programmes
de developpement, emploient en general une gamme
d'enterprises de sous-traitants. Certains clients, du
secteur public notamnent, peuvent employer a grande echelle
a partir d'un large panneau de sous-traitants, alors que
d'autres, peuvent adopter une approche dans laquelle un
seul sous-traitant est engage, ou bien il est fait appel a
un

The Organization and Management of Construction: Shaping


theory and practice (Volume Two).

Edited by D.A. Langford and A. Retik. Published in 1996 by


E & FN Span. ISBN 0 419 22240 5. Client benchmarking of
contractor performance 73 nombre limite de sous-traitants
pour terminer un programme, ce qui s'est fait connaitre

sous l'appellation de partenariat. Bien qu'il s'agisse


d'approvisionnement, ou demande

d'achat, les clients doivent, en permanence, etre en


mesure d'6valuer objectivement

l'execution et 1a reputation de ces sous-traitants, de


maniere Ii 6valuer les activites

courantes et aussi Ii influer sur les orientations de


l'approvisionnement futuro L'evaluation des performances a
fait son apparition comme moyen par lequel des

participants Ii un processus industriel ou commerciel


peuvent piloter les performances,

en se referant a une evidence verifiable Ii partir


d'activites comparables, peut-etre

derivee d'un certain accord sur Ie partage mutuel de


l'information. La presente

communication examine les fayons dont les employeurs


importants de l'industrie de 1a
construction peuvent adopter ce processus en tant que
partie integrante de leur prise de

decision d'approvisionnement et d'action, et comme moyen de


rehausser les

performances du projet et sa fiabilite.

Mots cles: Evaluation des performances, sous-traitants,


performances, approvisionnement

1 Introduction

Benchmarking as a term has a long history of application in


the construction process,

being derived as it is from the technique used by map


makers and surveyors to measure

a current position against an identified landmark or


reference point known as the

"benchmark". In more recent times the term has become


analogous to the business

process of establishing best practices, improving


management systems, and providing

an aid to strategic procurement activities. For supply


side organisations the process has

provided the means for observing in a disciplined manner


the methods and practices of

others, both within a particular industry or area of


commercial activity and also beyond

to other areas which offer methods and techniques which


would be capable of beneficial

transfer, the intention being to adopt and adapt the most


successful modes of operation

in order to pursue competitive advantage. For demand side


organisations the approach

offers a way of developing a rigorous approach to supplier


evaluation, applicable at pre
contract, current, and post-contract stages, and as a
means of assisting in critical

decision-making to optimise the procurement outcomes in


terms of value for money,

certainty of performance, and operational reliability.


Benchmarking is characterised by a variety of definitions;
Cousins [1] identifies a

number such as that of the Xerox Corporation which is one


of the organisations

credited with the founding application of the approach:

"the continuous process of measuring products, services,


and practices against the

toughest competitors or those companies recognised as


industry leaders" Ajoint definition from Coopers and
Lybrand and the CBI states:

"the process for comparing business practices and


performance levels against other

performance. A well considered benchmarking process should


allow a client to focus

upon those issues of supplier performance which are


critical to the successful accomplishment of client
organisational objectives. For regular or prospective
clients of

the construction industry a benchmarking mechanism allows


for appropriate weightings

to be applied to contractor performance in terms of price


competitiveness, programme

reliability, technical expertise, experience of building


type, product quality, claims awareness, etc., to reflect
the significance of these issues for the project sponsors

primary business.

2 Expectations of Construction Clients

Sponsors and clients of construction services vary in their


level of experience,
sophistication, and degree of awareness of the
construction process and marketplace.

All however are seeking some degree of reassurance that


the procurement decisions

that are made, and in particular the selection of


contractual supply partners, are those

which are most likely to result in a high level of


customer satisfaction. Chicken [4]

suggests that major decisions are not the product of a


single event or action but arise

from protracted discussion, investigation, and


consideration. The final decision is often

the product of a whole series of subsidiary decisions and


the interaction of several

interested parties. The making of critical project


decisions is a fundamental element of

the project sponsor's duties. Gorog [5] describes the


strategic decision points in the

project process which largely determine the degree to which


organisational objectives Client benchmarking of
contractor performance 75

are realised, the selection of supply contractors having a


profound influence upon

project performance and outcomes. The factors which can be


identified which will influence the process of contractor

selection by the project sponsor may be stated as:

• General level of sponsor expertise and experience of the


construction process

• Specific expertise in innovative or unorthodox


procurement methods

• Awareness of supply organisations and their apparent


capabilities

• Access to professional advice either in-house or


externally commissioned
• Statutory controls over contractor qualification notably
as set by European Union codes

• Organisational policy over contractor qualification


particularly in the public sector

• Organisational requirements for project performance


priorities When proposing to sponsor construction
activity the client organisation enters a

process of selectivity to determine the supply


organisation which will be finally

appointed as contractor to the project . This selection


may take one of a number of

forms as determined by the procurement process of the


sponsoring organisation:

• identification of a single contractor organisation with


whom the sponsor intends to enter into a negotiated
contractual relationship

• formation of a restricted panel of selective contractors


required to compete for the project on a number of
criteria, commonly price, but also possibly including
resource capacity, design skills, management expertise, or
funding capability

• facilitation of an open tendering process in which a


large number of responding contractors compete for the
project having normally first satisfied some
prequalification criteria Whichever procurement approach
is adopted there is an overriding requirement for

the project sponsor to be in possession of expert


intelligence as to the characteristics,

merits, drawbacks, and performance record of potential


contractors. An active and

effective process of benchmarking can provide the


mechanism for determining criteria

against which past performance and current capability may


be measured, for

establishing a set of minimum standards as a means of


testing for prequalification, and
for forming the basis for negotiation in respect of risk
allocation, range of services to be

provided, and the terms of the contractual relationship to


be formed.

3 The Benchmarking Process

Benchmarking is commonly applied to key operational


processes within a business to

determine those critical factors which create


organisational success. The majority of

benchmarking activity has been in the form of peer


assessment in which a supply side

organisation measures its capabilities, competencies, and


ultimately its performance

outturns, against relevant and appropriate companies often


from within the same 76 Ba/dry industry. Codling [6] has
identified how three distinct types of benchmarking have
evolved from mutual information sharing relationships: •
Internal intra-company comparisons of practices and
procedures to promote harmonisation of perceived best
practice. • External information exchange for mutual
advantage occurring amongst organisations within the same
industry or on occasions across a range of industries.
This process often utilises the services of a third party
organisation to moderate information and, if required, to
maintain confidentiality of participants. • Best practice
the seeking out of the undisputed leader in a specific
business process which is critical to organisational
success. Competitive forces may mean that this approach
often requires a partnership relationship to be developed
with a leading organisation in an alternative relevant
industry to that occupied by the benchmarking
organisation. It may be recognised from the above that the
intensity of benchmarking activity occurs within
organisations which are part of a product or service
supply chain, being

both providers and procurers of resources and key


components. For an organisation

which is dominantly the end consumer of goods or services,


such as the sponsor of construction project services, the
process requires adjustment and refinement to reflect
the external location of the client organisation, its
limited direct access to market

intelligence, and its often infrequent and occasional


participation in the procurement

process. As has been noted the application of


benchmarking techniques has been widely

adopted in process industries and., in particular, taken


up with enthusiastic vigour by the

rapidly expanding facilities management industry which is


largely building related in its

activities. Some particular difficulties do emerge however


when applying the process to

a project based industry such as construction which do


need to be overcome if optimal

benefits are to be derived. An opposing view to this is


held by Karlof and Ostblom [7]

who propose that the project form of organisational


activity is highly suited to the

application of benchmarking techniques as the formation of


an optimal ad hoc team

with specialised qualifications offers flexibility and the


ability to operate outside regular

channels without being hampered by organisational


formalities. Nevertheless difficulties

do exist which to some degree distinguish construction from


other industries and

include:

• very few projects are alike given the variety of


locations, participants, and product content

• projects are invariably conducted by teams of


participants assembled for the duration of the project
only and which are broken up on completion

• the supply side of the industry is highly fragmented both


in the number and diversity of available organisations

• some project sponsors are regular and frequent


commissioners of construction services whilst others take
part once-in-a-corporate-lifetime Client benchmarking of
contractor performance 77 • the highly competitive and
commercial nature of construction activity does not
encourage either supply or purchasing organisations to be
forthcoming with information • the data generated from
construction activity may be complex and variable and
subject to differing interpretation

• the application of benchmarking in construction has only


minority penetration to date resulting in a lack of
knowledge and enthusiasm for its potential and often being
limited to cost comparisons only If these obstacles to
effective benchmarking are to be overcome a prerequisite is
an

improved industry wide culture of confidence and mutual


trust, a condition which the

industry has largely avoided during its modem history.


Hawke [8] highlights a quotation

from the Editor of Building magazine on the occasion of


that journal's 150th

anniversary: " .... one theme comes twinkling through, the


unchanging nature of human

behaviour. Professional jealousy, competitive friction, and


contractual wrangles

preoccupied the Victorian building industry." Similarly


Powell [9] identified how the

cultural image of the contemporary construction industry


was working against the

formation of values of trustworthiness and integrity. The


development and growth of

benchmarking is dependent on the existence of an atmosphere


of co-operation, which

does not necessarily lead to a diminution in


competitiveness, but may prove to be a

mechanism which is instrumental in assisting the creation


of such a culture.

4 A Benchmarking Process for Construction Clients

Construction clients are commonly obliged to enter into


demanding contractual

relationships with organisations with whom they have had


limited contact and of whom

they have incomplete and inadequate knowledge. Construction


projects contain a high

level of risk for both primary contracting parties, at a


level which in some extreme

circumstances could threaten the survival of the


organisation if a major risk impact was

to occur. Sponsorship of a major construction project


requires the client organisation to

make significant decisions, notable of which is the


selection of the contracting supply

partner (Chicken [4]). For major projects a process of


prequalification is often implemented which is

designed as the first part of a two stage process which


requires putative tenderers to

satisfy some basic criteria to test suitability and


capability to tender and to execute the

contract. Alternatively clients who are regular


participants in the construction

marketplace may retain a continuing "approved" list of


vetted contractors from which

an appropriately sized panel oftenderers may be drawn for a


specific project. This latter

approach is a common occurrence in the public sector as


described by Latham [10] who

particularly notes the CMIS list held by the Department of


Environment to which

private clients may have access to determine whether a


specific contractor is held on

that list. Latham goes on to comment how the preparation


and maintenance of a

multitude of lists represents a wasteful duplication of


effort which significantly adds to

client costs. To mitigate these costs some client


organisations have attempted to levy

charges on contractors for admission to an approved list,


an approach which has raised 78 8a/dry the ire and
contempt of contractors and their trade associations. The
conclusion of Latham is that it would be appropriate for
the DOE to develop the CMIS scheme as a centralised
national resource to assist clients and their advisers to
determine contractor competence against a range of
performance criteria. From a client's perspective this
paper suggests the following essential elements of an
effective scheme for benchmarking contractor capability: •
Comprehensive containing an adequate range of contracting
organisations to meet the clients requirements in terms
of frequency of contracting intentions, geographical
spread, and typical characteristics of contracts •
Interactive capable of presenting the client with choices
and alternatives with which the client may engage to
customise a search process • Regularly updated able to
illustrate the most current and meaningful information of
contractor performance and capability • Targeted capable
of allowing the client to select appropriate specialist
contracting organisations to serve expressed needs and
requirements • Economic demonstrate ease of access and a
reasonable cost profile so as to promote regular and
widespread utilisation

• Reciprocal encourage participative feedback from client


participants on contractor performance and capability in a
form which is defenSlole, appropriately confidential, and
which indemnifies contn"butors against actions in tort The
establishment of a national database of contracting
organisations offers the

possibility for the assembly of factual and measurable


information together with

verifiable value judgements to assist prospective clients


to identifY those companies

which would prequalify for consideration for bid or


negotiation opportunities by

satisfying whichever set of performance criteria the


client wishes to impose, in addition

to those imposed by some other agency such as the European


Union Works and

Services Directives. In this way a client may impose as


it's benchmark standard the

highest degree of satisfaction level which may be achieved


in those success criteria

which are most critical to itself and against which it


would be posSlole to identifY those

companies whose performance record and verified capability


came closest to matching.

The outcome of this approach would be to add an additional


option to the range of

benchmarking approaches, as noted earlier in this paper by


reference to Codling [6],

that of most desirable practice which would be an abstract


achievement which mayor

may not be attained by any participating supply


organisation but which exists as a pure

benchmark of performance. Any database formed would be a


combination of factual and evaluated information

derived from both the participating contracting


organisations themselves and former

clients. Herein lies a particular dilemma as to the degree


of access which should be Client benchmarking of
contractor performance 79 made available to contractors to
verify the factual data on record and update if necessary,
and, if deemed appropriate, to examine the performance
values placed against them by contnbuting clients. It is
proposed that it would be fair and reasonable, and
probably necessary to promote contractor confidence, to
allow contractors full access to the data file held
against them in order to secure feedback on past client
views on their performance, the specific identities of
these clients being necessarily concealed. If such a
benchmarking scheme is to maximise the potential benefits
available the

body charged with the responSIbility for management would


need to display the

following characteristics:

• be independent of contracting and client organisations or


confederations

• be equally accessible to public sector and private sector


client organisations

• be capable of providing a timely and efficient response


to client enquiries

• have sufficient and appropriate marketing and information


dissemination skills as to be able to promote the uptake
and utilisation of the scheme as widely as posSlble
without reliance upon powers of compulsory registration

• have the resources to process, manage, and intexpret data


in a consistent and reliable way to promote meaningful
comparability Latham is of the view that the DOE CMIS
scheme could provide the framework for a

central United Kingdom resource for public sector contracts


based upon an official

registration of contractors. It is suggested in this paper


that such a system would have

limited acceptance into the private sector as the DOE would


be too strongly identified

with the government in its role as a major client of the


industry. Furthermore the

reluctance of government to directly intervene in


commercial relationships in the

construction industry, and the limited capability of the


utilisation of such a scheme

without legislative authority, would effectively hamper its


widespread acceptance and

participation. A preferred solution would be the


formation of a benchmarking service which was
under the management of an organisation which was seen as
neutral by all participants

in the construction process and could be relied upon to be


effective custodians of the

client information service. The Building Research


Establishment and the Construction

Industry Research and Information Association are two


organisations whose function is

the conduct of research into building and associated


matters and yet display the

desirable characteristics noted above, in particular the


absence of any allegiance to any

sector of the construction market, demonstrable expertise


in the gathering and

management of information which would be a perquisite of


the service, and would be

likely to enjoy the support of contracting organisations,


consultancy practices and

professional institutions, and the collective body of


construction sponsors. In addition

the neutrality of such organisations should attract the


support and recognition of a

secondary layer of organisations who have an interest in


the success and efficiency of

the construction process, including material and component


suppliers, insurers, unions,

and consumer associations. 80 Ba/dry The identifiable


success factors of such an arrangement would be the
delivery of a service which came to be relied upon as the
authoritative source of support to the client procurement
decision making process. Watson [11] descnbes how these
critical success factors need to be measured in basic
business terms and become the basic process measures of a
TQM approach. For a sponsor of construction activity the
selection of a supply partner which comes closest to that
sponsor's specific model of supply excellence will enhance
the likelihood of the success of a contractual
relationship. Furthermore the spur of achieving and
maintaining a presence on a widely regarded and valued
database of suppliers of construction services may result
in an elevation of the standards of petformance of
contracting organisations to new levels of excellence and
customer satisfaction. 5 Conclusion Construction clients
are seeking to improve their procurement and supplier
selection

process to reduce project risk and create conditions for a


greater certainty and quality of contractor performance.
This paper has descnbed how the disciplined process of

benchmarking may be adapted from the conventional


inter-company supply side

comparator of process activity into a means for the


reliable and objective assessment of

contractor competence. Notwithstanding the obstacles


presented by the peculiarities of

the construction process, when compared to the


manufacturing or service industries,

and the particular necessity of the development of a


culture of co-operation, it is

proposed that an effective and workable system meeting


certain delivery criteria is

desirable and achievable. The types of organisation which


would be suitable to accept

the responsibility for managing such a service have been


reviewed and appropriate

bodies proposed. The outcome of the establishment and


successful operation of a

contractor petformance benchmarking system is predicted to


be a direct positive aid to

client procurement experiences, and it is also speculated


that improved contractor

performance may result from the competitive forces arising


from participation in a
formalised comparative process.

1. Cousins, R (1995) Guide to Benchmarking in Premises


Management, in Premises and Facilities Management,
February, pp. 45-48.

2. Varcoe, B. (1993) Benchmarking for Competitive


Advantage, in Premises and Facilities Management,
February, pp. 11-12.

3. France, G. (1994) On your Benchmarks, in Building, 2


December, p. 42.

4. Chicken, IC. (1994) Managing Risks and Decisions in


Major Projects, Chapman Hall, UK. Client benchmarking of
contractor performance 81

5. Gorog, M. (1995) Client Orientated Strategic Project


Management, in Proceedings of SOVNET Project Management
Symposium, St. Petersburg, Russia.

6. Codling, S. (1992) Best Practice Benchmarking, Gower


Publishing, UK

7. Karlo£: B. and Ostblom, S. (1993) Benchmarking: a


Signpost to Excellence in Quality and Productivity, John
Wiley, UK

8. Hawke, M. (1994) Mythology and Reality: the perpetuation


of mistrust in the building industry, Construction Papers
No. 41, Chartered Institute of Building, UK.

9. Powell, M. (1994) Building Trust, in Proceedings of


Sixth Annual Conference of ARCOM, UK.

10. Latham, M. (1994) Constructing the Team, Final Report


of the GovemmentlIndustry Review of Procurement and
Contractual Arrangements in the UK Construction Industry,
HMSO, UK.

11. Watson, G. H (1992) The Benchmarking Workbook,


Productivity Press, USA.
2 Productivity estimates

Table 1 14 -Net present value in case monthly inflation is


3% and client effectue this payment on

time and with delays of 1, 2 and 3 months. (monthly real


discount rate: 1 %) NOMINAL NET NET CASH N.P.V. NET
CASH N.P.V. NET CASH N.P.V.

MONTH DISCOUNT RATE CASH N.P.V. FLOW (delay (delay of1


FLOW (delay (delay of2 FLOW (delay (delay of 3 of 1
month, of2 monthsl ot3 month~ %3+%1=%4 FLOW month)
month& months

JANUARY 0.961 -5,000 -4,805 .5,000 -4.805 ·5,000


-4,805 -5,000 -4.805

FEB. 0.924 94,017 86,871 ·280,953 ·259,600 ·280,953


-259,600 -280,953 ·259,600

MARCH 0.888 206.385 183,269 -118,295 .105,045 -493,265


-438,019 -493,265 -438,019

APRIL 0.854 28,717 24,524 280.043 239,156 -44,637


-38,119 -419,607 -358,344

MAY 0.821 29,168 23.946 182,074 149,482 433,400 355.821


108.720 89.259

JUNE 0.790 -3,383 -2,672 51,391 40,598 204,297


161.:394 455,623 359,942

JULY 0.759 -30,909 -23.459 77.656 58,940 132,430 100,514


285,:336 216,570

AUGUST 0.730 -47,965 ~35.014 84,114 61,403 192,679


140,655 247,45:3 180,640

SEPT. 0.702 1:32,079 92,719 240,644 168,932

OCTOBER 0.675 132,079 89.153

TOTAL 262,660 180,129 110,660 43,728

Table 1 15 -Net present value in case monthly inflation is


4% and client effectue this payment on

time an d h ( thl I d' 1 01<) With delays of 1, 2 and 3


mont s. man y rea Iscount rate: ° NOMINAL NET NET CASH
H.P.V. NET CASH H.P.V. NET H.P.V.
MONTH DISCOUNT CASH H.P.V. FLOW (delay (delay of 1 FLOW
(delay (delay of2 CASH (delay of3 RATE FLOW of 1 month)
month) of2 months) months) FLOW months %4+%1=%6 (deiayof
3 month!'t

JANUARY 0.952 -5.000 -4.760 .5.000 -4,760 -5,000 -4.760


·5,000 -4.760

FEB. 0.907 90.498 82.081 -284,720 -258.241 -284.720


-258,241 -284,720 ·258,241

MARCH 0.863 197,032 170,038 -127,671 -110.180 -502,889


-433.993 -502,889 -433.993

APRil 0.822 16,661 13.695 267,974 220,274 -56,729 -46,631


-431.947 .355.060

MAY 0.783 18,970 14.853 171,867 134,571 423,180 331,349


98.477 77.107

JUNE 0.746 -15.160 -11,309 39,606 29,546 192,503 143,607


443.816 331.086

JULY 0.710 -40,331 -28,635 68,229 48,442 122,995 87,326


275.892 195.883

AUGUST 0.676 -51,321 -34.693 81,064 54,799 189,624


128,185 244.390 165.207

SEPT. 0.644 132,385 85,255 240,945 155,168

OCTOBER 0.613 132,385 81.152

TOTAL 201,270 114,461 32.097 46,461

Table 1 16 -Net present value in case monthly inflation is


5% and client effectue this payment on

time an d 'th d I f 1 2 d 3 th ( thl I d' t t 1 o/c) WI


eays 0 an mon s. mon y rea Iscoun ra e: ° NOMINAL NET
NET CASH N.P.V. NET CASH N.P.V. NET CASH N.P.V.

MONTH DISCOUNT RATE CASH N.P.V. FLOW (delay of1


month'(delay of 1 FLOW (delay (delay of2 FLOW (delay
(deiayof3 %6+%1=%6 FLOW month) of2 months months of3
month!!.

JANUARY 0.943 -5,000 -4,715 -5,000 -4,715 -5.000 -4,715


-5.000
FEB. 0.890 88,012 78,330 -287,458 -255,837 -287.458
-255.837 ·287,458

MARCH 0.839 187,588 157,386 -137.137 -115.057 -512,607


-430,077 ·512,607

APRIL 0.792 4,367 3.458 255.667 202,488 -69.058 -54,693


-444,528

MAY 0,747 8,468 6,325 161,355 120.532 412,655 308,253


87,930

JUNE 0.705 -27,408 -19,322 27,351 19,282 180,238 127,067


431,538

JULY 0.665 -50.228 -33,401 58,326 38.786 11:3,085 75,201


265,972

AUGUST 0.627 -54,876 -34,407 77,819 48,792 186,:37:3


116,855 241,132

SEPT. 0.591 132,695 78,422 241,249

OCTOBER 0.558 132.695

TOTAL 163.664 64,271 -39.624

In case both inflation increase and delays in payment by


client occur at the same time that is most

frequently experienced by contracting firms, the


expectation of contracting firm from the mentioned

project maybe determined by probability analyses. In such a


case, contracting firm should determine

all the probabilities concerning occurrence of alternative


situations during the realisation of project.

Considering the total value to be 100, probabilities


concerning the occurrence of all alternatives shall

be calculated. Probability rate for each alternative shall


be determined by taking into consideration

market conditions of the period, competition among firms,


economic conditions of the country,
1 Project planning

Lowe, J G, Moussa, Neveen G, and Lowe H C (1993) "Cash flow


management: An Expert System for the

Construction Clienf', Journal of Applied Expert Systems,


1993, Volume 1(2) pp 134-152

Moussa, Neveen G (1992): "Cash flow forecasting and the


client: an integrated database expert system

model", Unpublished MSc. Dissertation, Heriot-Watt


University, Edinburgh.

Saleh, Sherif Omar (1991): "Developing an expert system


model for cash flow forecasting in the construction

industry", Unpublished MSc. Dissertation, Heriot-Watt


University, Edinburgh.

Shafer, G (1976), "A mathematical theory of evidence",


Princeton University Press, Princeton.

Singh, S (1987) "A computer model for financial resource


planning of high rise building projects" in Lansley,

Peter R & Harlow, Peter A (Eds) "Managing Construction


Worldwide", E & F N Spon, London, 1987, 1,

1 Introduction

Though by introduction of computers the calculation proces


in time planing has been

significantly accelerated,nothing much has been achieved as


regards the accuracy of time

schedules. Superproject, Microsoft Project, Primavera, the


most widely used programmes

cannot guarantee completition dates foreseen in the


schedules. The research done at the

Faculty of Civil Eng. in Osijek *1 suggests that the main


reasone for this unreliability are

similar for all the schedules:inadequately defined duration


of the activities and the neglect

of external factors present in the course of realization of


the project.

The problem of the inadequately defined duration of


activities has been resolved through

the introduction of ''The Theoretical Lenght of duration


of the Activities"*2. The problem of

external factors affecting the duration of a project is


being addressed in this paper. Prior to

analyzing the imapct of external factors on the realization


of project, it would be advisable

to acquint ourselfes briefly with the notion of


theoretical times. This is necesary, for the

terminal time schedule can be done with the standard


(currently used) times Tas, and

theoretical times Tat.

To obtain the most accurate data regarding duration of the


activities an analysis of the

spent times, has been done on all the levels of the


operation complexities. It has been

noticed that on every level (from a single move up to the


project itself) the time can be

divided into a useful and uncontrolled. The term


uncontrolled is deliberately used here, for

up to know there has not been a way to get an idea about


what it is, irrespective of the

fact whether its use in practice is usefull or not.

In terms of organization these problems have been


recognized and entire scientific areas

have been created to deal with them. As regards the times


on the level of moves and

procedures, they are taken care of in 'Work Studies". As


for those on the level of

operations and processes they are accountet for in the


norms. The times on the level
of activities (from simple up to complex processes) have up
to now been defined by way

of deterministic and stohastic calculations, and the


tables used in complex processes

*3.There is an attempt to eliminate uncontrolled time on


the project level usualy trough

"ironong" of labour and equipment histograms.

Looking more closely at the times of activities used up to


the present date (let's call them

standard Tas) we shall see that times in effect indicate


duration of the main proces within

an activity. Such an approach distorts to a large degree


the lenght of the duration of an

activity. IntrodUCing a "tehnical normal" into calculation


enabled us to arrive at a typical

time *4. In Tehnical Normal it is possible to see


(gantogramicaly) what the relation is

among the processes in each of the activities. Normal gives


us an idea about useful times

Tk, reserve (i.e. uncontrolled) Tr times,and obtained times


Td. The obtained time is the

one we extract from the uncontrolled time.When an activity


is composed of a number of

processes then the time running from the beginning of the


first process to the completition

of the last is called Theoretical Length of Duration of an


Activity, Tat. When the same

technologies are concerned this time is stable, therefore


the schedules done with Tat are

more reliable. Neverthless, the schedules based on


theoretical times do not take into

account external conditions present in the course of


duration of the project. Therefore we
say that such a schedule is good as long as optimum
conditions are concerned, similar to

the theoretical capacity of machines, which are likewise


foreseen for optimnm working

conditions. 184 Petrovic Practical time (similar to


practical capacity) is opbteined when local and climatic
conditions are taken into account, of which more will be
said in the continuation. 2 Practical Time Every
project,irrespecctive of whether it uses stndard or
theoretical times of duration of activity, is bound to be
effected by various surrounding conditions in course of its
realization. It is truism that it is different to work in
rainy as opposed dry conditions, in situation when we are
well supplied with the needed materials as opposed to the
shortage of them. The question is now whether these
variable external factors can somehow be icorporatetd in
the process of time scheduling, thus ensuring their
automatic imp-act on the duration of the proceses. Can we
at the same time foresee the intensity of the external
conditions, their selectivness as regards the bearing they
have on individual types of works, which of them are
essential, which dominant. etc.? When the project "New
Methods of Time Scheduling" was initiated the target was a
universal model, which could be extended or reduced at
will, depending on the impact of the surrouding condition.
The problem of cold and rain will not be of much relevance
in Africa countries and will have to be replaced by
factors which will be of lesser importance in some other
countries of world.Cold in Siberia or Alaska will be of
more relevance there than in some other parts of the
world. As far es the Central Europe (and possibly wider)
is concerned the most relevant external factors are:
climate (Kk), logistic (KI), organization (Ko) and safety
(Ks). We departed from the assumption that for a possible
extension of the duration of an activity it is the most
prominent of the external factors that will be of the
highest relevance. The initial investigation has revealed
that as the rule there will be always one among the four
factors mentioned above that will be dominant, ie. all
others are not of sufficient magnitude and are not for the
time being taken into account. Practical time of the
duration of an activity is obtained via the folliwing
formula. Tap = Tat (or Tas) x max (Kk or KI or Ko or Ks)
(1 ) It is evident that the practical time can be derived
from the standard as well as from the theoretical
time.This time is multiplied by the largest coefficient
among the external factors separately for each day. The
formula also shows that the number of external factors can
be changed at will. *5. By selecting four groups of the
most relevant external factors a possibility is opend for
the creation of the entire model. The first step on the
way is to presume the contents of each of the groups of the
aforesaid external factors. A selection of the most
relevant ones is done again and we end up with having the
following sub-factors: Climatic factor Kk embraces the
following sub-factoes Time planning using the Zagreb
method 185

Kk = ( Kk1 ,Kk2,Kk3,Kk4 ) where (2)

Kk1 = impact of rain

Kk2 = impact of cold

Logistic factor Kk3 = impact of heat Kk4 = impact of


wind

KI = (K11 ,KI2,KI3) where (3)

KI1 = impact of the timely supply of materials KI3 = impact


of the avaible labour

KI2 = imapact of the use of plant and equip.

Organization factor

Ko = (K01 ,K02) where (4)

K01 = impact of general organization K02 = impact of the


site organization

The safety factor has for the time being only value

Ks = Ks1 where (5)

Ks1 = the impact of general safety on work efficiency.

The following step is breaking of each of the group factors


into two parts. The first part is

linked to the yearly calendar (termed schedule) with a


common denomination Kv. The

second one measures the sensitivity of each of the


activities to the exsternal condition,

bearing the common denominator Ka. In accordance with the


aforesaid the factors can

be expressed via the following formula

K = Ka x Kv

i.e.

Kk = Kak x Kvk

KI = Kal x Kvl Ko = Kao x Kvo Ks = Kas x Kvs (6)

Each of the four factors (Kk, KI, Ko and Ks) can be now
shown as a combination of

formulas 2, 3, 4 and 5 with formula 6, but bearing on mind


that the ten sub-factors (rein,

heat.... safety) are reflected both within time (terming)


and activity sensitivity. The rule that

the strongest factor is of utmost relevance would apply


here as well. Formula, would

therefore be: 186 Petrovic Kk = max (Kak1 x Kvk1 or Kak2


x Kvk2 or Kak3 x Kvk3 or Kak4 x Kvk4) KI = max (Ka11 x
Kvl1 or Kal2 x Kvl2 or Kal3 x Kv13) Ko = max (Ka01 x Kv01
or Ka02 x Kv02) Ks = Kas1'x Kvs1 (7) In order to be able
to carry out calculation we shall have to give,the
relations shown here their numerical values. Three degrees
of magnitude are foreseen for each sub-group of factors.
It is assumed that the sensitivity of an activity to
external conditions,ie.factor Ka ranges from A = least
sensitivity, B = medium sensitivity C = high sensitivity
On the other hand the intensity of the external influencies
is for the time being expressed through three degrees
relative to factor Kv, ie. a = weak influence b = fair
influence c = strong influence Numerical values for each
of the six said magnitudes will depend on what extension of
an activity we shall decide to take into account, is it an
extension from one day to two, three or four days. Limits
to these should be fixed in advance. There would be no
point, ego to monitor for months an activity suspended on
account of snowy conditions as though it were in progres
while the snowy conditions persist.On the contrary, after a
day or two we shall stop the activity and move the
labourers to another place, or threat them as disengaged
on account of inclement weather conditions. For the cases
of extension lasting 1, 2, 3 days we use the following
values: For an extension from one to two days up to three
days up to four days A=0,75 a=1,33 A = 0,67 a = 1,50 A =
0,50 a = 2,00 B = 0,90 b = 1,66 B = 0,84 b = 2,25 B =
0,75 b = 3,00 C = 1,00 c = 2,00 C=1,00 c=3,00 C = 1,00 c =
4,00 A calculation where we have two rows of ten
coefficients which can turn up in total of 60 numerical
values,performed for each day separately, can be
efficiently done only by a computer. The program which is
being prepared within the project New Mwthods of Tme
Scheduling is conceived in such a way that only the same
coefficients are automaticaly multiplied among themselfs.
Therefore the Kak coefficients will (unless it is zero)
seek only coeff. Kvk, etc. Coeff. linked to term schedule
(a, b, c) can equal zero, which is to say that no
external influence were registered. The result accordingly
will equal zero. Depending on the strength of sensitivity
and external influences we shall have the following values
for one day extension: A x a = 0,75 x 1,33 = 1,00 A x b =
0,75 x 1,66 = 1,25 Axc=0,75x2,00= 1,50 B x a = 1,20 Bxb
= 1,50 B xc = 1,80 C x a = 1,33 Cxb = 1,66 C x c =
2,00 Time planning using the Zagreb method 187

We can likewise calculate the results for extension lasting


two or three days.

The next task of computer program would be to pick from the


maximum of ten possible

results to one of the largest magnitude,which will then be


responsible for the extension in

the duration of an activity. The final time is arrived at


by adding up all daily practical

(altered) times

Tap = Tap daily = 1 (day) x K (8)

The procedure ',s repeated automaticaly for each day of


every activity beginning with the

initial one.

Due to the influence of the surrounding conditions there


will usualy occur an extension in

the duration of an activity, ie. Tap = Tas (or Tat). The


extension thus obtained will also

become subject to the influence of surrounding conditions


and will tend to be extended
further.

Thie Process can be seen in the following diagram I II


Tas ~ Toc 1 ~ , '\ Tap 1 lTac:2 Tap 2 LTc c 3
Tap 3 Fig. 1 Practical times

The calculation is done by adopting the following formulas


(for standard time)

if Tap1 Tas = Tae1 < 0,5 then Tap = Tap1 (9)

if Tap1 Tas = Tae1 > 0,5 (0,5 is the time relating to day
rounding up) 188 Petrovic next we carry out the procedure
mentioned above on time Tae1. The time extended in such a
way is also subject to the influence of external
conditions.Tae1 is, therefore a new, lesser extension
Tae2. Then we pose the same question again: if Tap2 Tap1 =
Tae2 < 0,5 then tap = tap2 if Tap2 Tap1 = Tae2> 0,5 then
time Tae2 is treated in likewise manner to get extension
Tae3 etc. The procedure is repeated until! we reach a
state where the length of the extension is less than 0,5.
This is reached in tree steps at most. Use of Computer
Investigation is under way and a program for the
calculation of practical activity (Tap) has not been
completed as yet. The description that follows is done on
the ssumption that such a program is completed. THE
FIRST STEP is a preparation of termed calendar with
coeff.for the entire company. Several sorts of termed
calendare are constantly updated and extended once they are
fed into a computer in planning department of a company.
These could be calenders with monthly, quarterly or even
longe term weather forecasts with date from multi-annual
calendars, logistic factors related to a state zones, or
areas,details concerning general organization patterns or
organizations on the level of company departmens etc. Term
calenders serve the entire compeny and it is up to the
project manager to choose which of them he is going to
use, ie. monitor. Likewise, we can use a calendar of the
actual external conditions. This one is done
subsequently, ie after the occurrance of the actual
external conditions. It is nesessary for us to be able to
check by a subsequent calculation whether the time on a
site is utilized effectively. A subsequent schedule will
help us to determine through a systematic monitoring which
of the factors are the most prominent and to what degree.
The program is conceivaed in such a way that it is
sufficient to indicate the first and the last day of the
influence factor, whereupon the same value is automaticaly
added to all the days inbetween. SECOND STEP in the
calculation of the practical time is the preparation of the
time schedule (let's take a network for an example) with
initial times (standard or theoretical). The network plan
has an innovation in the node. Now the node has nine
instead of eight pieces of information. A field is added
in the centre of the node in which practical time is
displayed. Time planning using the Zagreb method 189 Es
Tas LS Simb. Tap TF EF FF LF Fig. 3 Network node

If we set out with standard times (which are located in the


middle of the top row) then we

have two possibilities. The first one is the calculation


of the theoretical time. The procedure

is set in motion by activating the field containing


standard time (mouse, cursor). Further

stages are dealt with in the article which studies labour


histograms, and figure (6),

therefore we shall activate the mid (vacant) field,


whereupon a program for calculating

practical time is opend.

Activating the mid field (separately for each activity)


the following table will appear: <5 Kak 1 Kat 2 m Kak
2 Kal 3 :l: iii Kak 3 Koo 1 Kak I. Kao 2 Kat 1 Kas
Fig. 4 Activity sensibility table

Name ie. a symbol, is entered into the table and then in


accordance with the contents of

the process within the activity (predominatly the main one)


we estimate the level of

sensitivity (A, B, C) for the ten of possible external


influences. In case norms are adopted,

these tables can be made beforehand to accompany the norm.


In such event, when norm

activity is called, sensitivity factors are automaticaly


displayed. Evan when ther are no

readu tables an internal data bank will be formed in


course of time. 190 Petrovic THE THIRD STEP consist in
linking the activity data and the coeff.previosly fed into
the term caslendar. Entering the name of the initial
network plan into the term calendar the linking is
achieved. By linking the first activity. ego entering the
initial date by the symbol A, we set the procedure in
motion. In the bottom field of the calendar the first
activity is displayed gantogramically. The command to
begin the calculation of the practical time for each day
separately will instruct the computer to multipay the
complimentary coefficients, selects the highest and
multiplies it by the day. This is repeated until the last
day of the plan fed into the computer is reched.After
adding up 0,5, the practical time will appear on the
screen. In case the practical time is longer than the
initial one, the said procedure will apply to the
difference, ie. extension Tae and the extension prolonged
further. The computer will do likewise with all the
extensions until the value of 0,5 day is reached. After
the first, (now extended activity) the computer will
process the next column of activities, but it should be
noted that all the activities are in the extreme left
position for as yet we cannot tell which of them lie on
the cry tical path into two more positions (mid and right)
to be able to see which practical time is the longest
(being also the most relevant) which is then entered into
the node. The longest time can affect the route of the
criyical path. Doing one column at a time the computer
will come to the last one, thus indicating the terminal
date of a project. THE FOURTH STEP contains a command
instructing us to return to network plan from gantogram,
paying attention to technological links defined by the
initial plan and the practical times of duration of the
activities. The plan can possibly point to a new cry tical
path. This network plan is, of course,valid only for the
time (calendar) for which it is made. If the event the
beginning shifts, or a part of the plan is moved to another
time on account of updating, it is enough to register a
new beginning date and repeat the first four steps
mentioned above. The method of realizing the project and
the time within which it is realized are firmly connected.
A Practical Example The folowing example will illustrate
the procedure adopted in calculation of practical times.
The example will show how the computer behaves in course
of the calcilation. The initial network plan on which
technological links are based looks as follows: OjL L A
0 oj 0 L Time planning using the Zagreb method 191 L /
2 6 10/7 17 r-" B 10 rE 6 ILIL 16 16 I 6 ]3
...... L 16 10 ...... 10 I 3 13 13 /2 15 !:::* c 0
f-F 0 f-G S L 10 10 10 10 13 21( 8 n L I 5 9 13
110 23 L.-o L --0:: H 0 a I L 13 13J 0 23 Fig. 5.
Initial network A (4 days) digging for foundation B (2
days) digging trenches C (6 dayc) concreting foundation
slabs D (7 days) laying services E (5 days) backfilling
F (3 days) building walls and ceilings G (2 days) making
flors H (10 days) errecting roof structure I (7 days)
roofing works LEGENOA: ES Iti EF A/<TlV· iF LSIFF LF
... 2317 Xl r--! I 0 23 I 0 30 f

We can see that the initial plan ends on the 30th day, that
it has 5 columns and cry tical

path A-C-F-H-1. In accordance with Figure 5 a selection of


sensitivity coeff. is for the

acctivities we encounter in the initial plan

c K a k 1 C K a ! 2 C K a k 1 C K a l 2 C K a k 1 B K a ! 2
B ! < o k 1 A K a ! 3 8 K a k 2 A K a ! 3 8 K a k 2 8 K a l
3 B K a k 3 A K a o 1 A K a k 3 A K a o 1 8 K a k ] A K a o
1 A K a k I . A K a o 2 8 K a k l . A K a o 2 A K a k l . A
1 < 0 0 2 A K a l 1 A K a s A K c i 1 A K a s A K a ! 1 C K
a s A ' o E F K a k 1 B K a t 2 B K a k 1 C K a t 2 A K a k
t C K a l ] A K a k 2 A K a t 3 B K a k 2 B K a t 3 B K a k
2 B K a l 3 C K a k 3 A K a o 1 A K a k 3 B K a o 1 A K a k
3 A K a o 1 A ! < o k t . A 1 < 0 0 2 A K a k l . A K a o 2
A K d < l . A K o . o 2 A K a ! 1 A K a s A K a l 1 C K a s
A K a t 1 C K a s B ' ~ G H K a k t A K a t 2 A K a k 1 C K
a t 2 A K a k 1 C K a t 2 A 1 J < a k 2 C K a ( 3 B K c i k
2 B K a t 3 B K a k 1 B K a ( 3 A K a k 3 A K o o 1 B K a k
3 C K a o 1 B K a l e 3 C K o o 1 B K a k l . A K a 0 2 A K
a l e L B K a o 2 A K a k l . C K a o ] A K a f 1 C K a s A
K a ! 1 C K a s B K o . ( 1 C K G l . s C i F i g . 6 A c t
i v i t y s e n s i t i v i t y c o e f f i c i e n t s D /
F S ~ M T W T F S v ; t « T W T F S ~ M T W T F S ~ t « T W
T F S ~ t « T W D / I \ 1 2 X L 5 6 7 8 9 r § 1 1 1 1 1 3 l
L 1 5 1 6 ~ 1 8 1 9 1 0 1 1 1 2 2 3 ' 4 2 5 2 6 2 7 2 8 2 9
3 0 ~ 2 J L " " ~ ~ ~ < 0 ~ ~ ; ; ; [ j . . . . . . . . . I
I ' < D t I D ~ a s ; ; ; c . . . . . . . . . . ' " ' ~ < <
0 0 1 8 r ; D / G r ; : ! z I I ' < D c . r ' " 0 0 < 0 0 0
0 0 < 0 0 0 c . 0 1 0 1 0 1 0 1 0 1 < n 0 1 . . . . . ~ c .
K Y K T b b V a V a b b ' / c b V / / K Y K 2 / . v : V ' /
~ K Y K J V ~ v . ' i V / / K Y K L / / / / / V / V K Y L 1
a a / ' a a a a a a V , a Q a a a a ' i a a a a a a ' / a a
a a a a r / . a a ' a K Y L 2 / / b c b b b b V b b b b b b
/ b b b b b b V / b b K Y L 3 c c : / . c : c : c : b b c V
, , c c / / ' / : ' / K Y O 1 a a ~ a a a a a a V a a a G .
a a V ; a a a a a a / / " 7 K Y O 2 b b V b b V ' / v : t /
K Y S a a V / a a b b b b V b b b b b b v : ' / b b V b b b
~ ! J E ~ ~ ~ ~ 1 I ~ I ~ f ' / ~ B r : ; I / E V I I v : I
I [ 7 I I . . . L V . . . ( A I 0 : , F V I ~ I I ' L I I !
, V I r / I ' I V f . A c ' / . i F 7 ; : : I T 1 ' , / v :
~ / ~ o r ) H i . . . ( ~ ~ , / . ! I ~ t ! i ~ 0 I ( / . ~
T . ~ = r / i F i g , 7 T e r m e d c a l e n d a r 194
Petrovic In this instance we shall go for the the maximum
extension of a day per a day of an activity.Accordingly,
the sensitivity coefficients relating to the activities are
as follows A = 0,80 B = 0,90 C = 1,00 We have
likewise decided that the project will be in progres
during Sept. Oct. 1995 somewhere in central Croatia.
Working hours are 8 hours a day, six days a week. The term
calendar with a gantogram of the initial network plan and
the obtained after the calculation Oh practical times
(double line) would look as Fig. 7 It is evident that due
to the external influeces the completition date has been
siginficantly extended. Seing how the times of individual
activities varies until they settled. Initial Tae1 Tae2
Tae3 Tae4 A 4 6 7 B = 2 3 C = 6 9 11 12 0 5 8
10 E = 7 11 13 14 F = 3 4 5 G 2 3 H 10 17 20 21
22 I 7 10 11 Fig.8 Extension of activities Wi can
conclude that longer activies are more likely to be
extended, thus by the addition of new days being sorted
under new factors, which further extend duration of the
activities. The said days are obtained in the computer by
recurring calculations using the following tables. A part
is shown here only, which will suffice for the procedure to
be comprehended. See Figure 9. C 1 b K k l 1 . 5 K l l
0 K k 2 0 K I 3 B l c 1 . 5 7 5 K k 3 0 K o l A l a 1 . 0 K
k 4 0 1 < 0 2 B i b 1 . 1 2 K l l A l a K s D / a 1 . 0 1 .
0 K k 1 0 K l 2 0 K k 2 0 1 < 1 3 B l c K k 3 0 K o l A l a
K k 4 0 1 < 0 2 0 K l 1 A l a K s B I b C l b K k l K l l 0
K k 2 K k 3 K k L K I I K k l K k 2 K k 3 K k L 1 < 1 1 0 1
< 1 3 B l c 0 K o l A l a 0 K o 2 B i b A l a K s B l a 0 1
< 1 2 0 0 K i l B l c 0 K o l A l a 0 K o 2 0 A l a K s B i
b F i g . 9 F a c t o r m u l t i p l i c a t i o n t a b l
e s C i a K k l K I 1 0 K k l 0 K I 2 0 K k 2 0 K I 3 B l c
K k 2 0 K l l B l c K k 3 0 K o l A l a K k 3 0 K o l A l a
0 K o 2 B i b K k L 1 < 0 2 B i b K k L 0 K I I A l a K s B
l a 1 < 1 1 A l a K s B / a K k l 0 K I 2 0 K k 2 0 K i l B
I b K k 3 0 1 < 0 1 A l a K k L 0 K o 2 0 K l l A l a K s B
I b 196 Petrovic The tables are made for each day and the
highest coefficient is the one by which the day is
multiplied (which is to say that in fact the coff.are added
up). Therefore the first day the hihgest result was KI2
(8 x c = 1,575), the second day K01 (8 x a = 1,12) and the
third (extended) Kk1 (C x b = 1,5). The final network
plan shown in the next diagram suggests that the
completition date is much longer, 55 days (the date with
standard times is 30 days), which seems to indicate that
the external influences should not be ignored. In this
instance the influence of bad logistic and organization
were even stronger than rain which tended to prevail at
the time lEGENOA: 7 2 11 19 7 33 ES ti EF ~ B I.
21 rE 11. 13 AK Tat TF 18 8 32 32 13 1.6 lS FF
LF 0 I. 7 ~ 7 6 19 I19 3 11. 21. 2 17 ~ 1.6 7
57 A 7 0 C 12 0 ~ F 5 0 ~ G 1 19 ----..... I
11 0 0 0 7 7 0 19 19 0 11. 1.3 19 1.6 e.6 u 57
7 5 17 11. C 1.6 ~ 0 I() 7 H 12 01== 1£ I()
11. 11. 0 1.6 Fig. 10 Final network plan Conclusion
When making a conclusion it should be kept on mind that the
study carried out within the project New Methods of
Planing is still in progress. The results reported here
have yet to Time planning using the Zagreb method 197

be confirmed by thoroughly checked numerical values of the


factors (for which a

systematic surwey will have to be carried out in the


field). In addition, a comparison of

calculated and the actual dates of completiton of projects


will have to be made yet

A preparation of a computer program for calculation of


theoretical and practical times is

also foreseen by the project Although it is to be expected


that more knowledge will be

gained in the course of future work on the project, there


are facts thet can already be

applied.

Calculation of theoretical and practical times will become


so simple that it will be in use

with most of present programs concerning time scheduling. A


continual use of this sort of

plans will have for a result a creation of data


bank,adjustment of coefficients to not only

the local conditions bat the conditions prevailing within


one's own company, as well.

Specialists will apper in companies whose job will be to


term plans with coefficients.
Avaibility of more types of plans will enable us to
identify the best months for realization of

a particular project Moreover, it will be possible to do


this automaticaly using a computer

programe. The direct advantage of these will be a more


straightforward policy as

concerns the use of labour and provision of the necessary


materials. Simulation will reveal

up to what degree a bad organization or inadequate safety


can affect the dates of

completition, etc.

It should be noted that the model is devised in such a way


that it will allow new additions

that will surely arise in course of time.

Finaly, it ought to be pointed out that it was only after


practical times had been introduced

that the link between technology, organization and time


become evident What is more,

this link can be assigned a numerical value as well.

1. Petrovic, J., and Vidakovic, D., (1994) The New Method


of Time Scheduling, Civil

Faculty Osijek.

2. Petrovic,J. ,(1995) The Theoretical Lenght of Duration


of the Activities, Gradevinar, Zgb.

3. Nonveiller,S., (1982) Metode mreznog planiranja i


njihova primjena, Zagreb, FGZ,

pp 84.

4. Klepac, J., (1983), Organizacija gradenja, Zagreb, FGZ,


pp.171.

5. Wai-Kin Wa, R., Fuzzy Modus Ponens Deduction Technique


for Construction

Scheduling, Journal of Construction Engng. and Mgmt.,


120,pp 164.

6.Petrovic,J., (1996) Optimalization of Time Plane on


Relation Time-Work Forces, Zgb.

organizing and material interest stimulating methods,


constructions, materials,

workers, mechanisms, etc.) are selected by students basing


oneself on criteria

system reflecting their utility degree. The required


resources must be in maximum

conformity with the requirements of lifetime process of


the building. For this, it is

very important to pick rational suppliers. They must meet


many requirements, for

instance, to be reliable (to observe as accurately as


possible the conditions set in

contract), to be capable to take care that the supplied


resources are competitive, to

be able and could be trusted to make necessary alterations


in supplying process if

such are required by changes in the project. The quality


of used resources and means (equipment, cranes, tools,

constructions, materials, etc.) must meet all presented


requirements. The

efficiency of performed work also very much depends on


quality level, physical

wear-out and obsolescence of used various cranes,


mechanisms and tools. In other

words, the efficiency of construction process closely


depends on other industrial

enterprises connected with construction (extraction and


processing of raw

materials; manufacturing of cranes, mechanisms and tools).


228 Zavadskas and Kaklauskas New requirement') appear when
the construction object is completed and commissioned.
They refer to proper maintenance of the building. The
factors mentioned above are directly connected with project
efficiency increase process. But this is not suffieient
in order to ensure high quality of a building. A lot of
additional factors (economic capabilities, human relations,
passed laws, etc.) must be taken into consideration. The
students can analyse all above mentioned and other factors
by applying the multicriteria decision-making system. 2
The development of knowledge base In order to make a MOM
system to work efficiently, it is necessary to develop as
full as possible knowledge base describing the problems
under investigation. Retrieval of information needed for
the knowledge base, its systematization and coding in
computer language is a complicated, time and effort
consuming process. The knowledge base accumulates various
information enabling the MOM system to efficiently perform
alternative designing and multicriteria analysis of
various projects and their constituent parts. It also
stores various rules, recommendations and formulas by
means of which the knowledge base can be easily updated.
The MOM system is composed of two main parts: knowledge
base and decision-making subsystem' enabling to perform
alternative designing and multicriteria analysis of
projects or their constituent parts. Having at first
analysed various possible structures of knowledge base
and modes of interaction between its separate parts, we
have selected, the most rational one consisting of the
following integrated parts: 1) knowledge sheets for
multicriteria project analysis, i.e. sheets containing
information on systems of criteria describing projects
(their constituent parts) as weB as values and initial
significances of these criteria. 2) knowledge sheets for
alternative designing, i.e. sheets containing information
on possible changing combinations of processes, solutions
and interested parties; 3) knowledge sheets containing
graphical information characterizing the versions (plans,
sections, front views of buildings and so forth); 4)
recommendations on the filling-in of knowledge sheets. In
our opinion, the information of multicriteria analysis and
alternative designing knowledge sheets is best to be
recorded and stored in form of a matrix. In this case, it
can be most easily analysed, and, using a PC, various
mathematical operations can be performed over it. In
order to give more detailed explanation of knowledge
sheets, they will be considered in a context of formation
of knowledge sheets for multicriteria project analysis.
Formation process of multicriteria analysis knowledge
sheets consists of three main stages (determination of
general information on versions being analysed and Using
the multicriteria decision-making system 229 on criteria
describing them; determination of values and initial
significances of criteria; determination of links existing
between the versions being analysed and other projects
(their constituent parts) or processes and solutions
making them up). Formation process of multicriteria
analysis knowledge sheets is started by identitication of
information necessary for multicriteria analysis of
projects. This information is retrieved from the
following sources: various projects, technical
certificates; existing analogues or finished similar work;
experts, with simultaneous application of expert methods;
recommendations, norms, normatives, standards and other
divers literature. At first, general information on
alternatives and on criteria describing them is
established. Basing oneself on various information sources,
proceeds the establishment of alternatives on which the
student had expressed interest, system of criteria
describing the alternatives, types of criteria
(quantitative or qualitative), measuring units and
fluctuation range of values. The wider is the range of
criteria value assessment, the more accurate will be the
analysis of versions. Values of criteria describing the
alternatives are determined on base of projects under
investigation, expert methods, analogues, recommendations,
other documents. It is very important to get exact
knowledge fully reflecting character of the problem
because on this depends the objectivity while selecting the
most efficient version. It can be noted that quantitative
information acquired from compared projects is quite
objective. Each specific project has its specific price,
maintenance costs. The values of qualitative criteria are
rather subjective, but, in case expert methods are applied
for their determination, they markedly become more
objective. The initial signiticances of all criteria are
determined by means of expert methods. Also, using expert
methods, limitations can be set for various criteria
(cost, maintenance expenditures, etc.), and if they are not
complied with, the versions are not considered any more.
Each student has an individual task. Therefore, in each
specific case, the student can alter the number of
alternatives being analysed, the system of criteria
characterizing them, the values and initial significances
of criteria. One student, for instance, regards the
infrastructure advantages of a certain location as more
important than general comfortability of a building. The
other on the contrary. A student, wanting to express this
standpoint in numeric representation, can set different
values of initial signiticances for certain criteria; and
this will influence the assessment of the project on the
whole. Taking a detached view, this may seem as a
"tendentious" choice, a "rule of the thumb" decision.
Although this assessment will be rather subjective, its
outcome most adequatly will correspond to the student's
task, his knowledge and demands. In order to facilitate
amendment and updating of knowledge base, special
recommendations have been prepared. Following the
recommendations, one can easily update or amend criteria
systems, values and initial significances of criteria,
changing combinations of alternative processes and
solutions, graphical views, etc. 230 Zavadskas and
Kaklauskas KNOWLEDGE SHEET FOR MULTICRITERIA ANALYSIS OF
PROJECTS 1.Projectname
________________________________________________ __ 2.
Goals: 1. Determination of alternatives under investigation
and parameters describing them; 2. Determination of links
between the alternatives under investigation and other
projects or their constituent parts 3. Alternatives under
investigation: A(1). A(2) ... A(m) 4. Determination of
links between versions being analysed and other projects
(their constituent parts) or processes and decisions
comprising them, performed in order to find an efficient
life-time process of a building (selection of location,
stages of brief, design, construction and maintenance):
5. Determination of parameters describing the alternatives
Criteria giving exhaustive description Compared of
alternatives under investigation versions x(1 ) x(2) ...
xOl ... x(n) A(1) x(1.1 ) x(1.2) ... x(1 .j) ... x(1.n)
A(2) x(2.1) x(2.2) ... x(2.j) ... x(2.n) A(m) x(m.1)
x(m.2) ... x(m.j) ... x(m.n) Measuring unit M(1)
M(2) ... MOl ... M(n) Initial significance Q(1) Q(2)
... QOl ... Q(n) Limitations A(1) A(2) ... A(j) '"
A(n) Fig. 2.Typical multicriteria project analysis
knowledge sheet Using the multicriteria decision-making
system 231 In order to find a most simple and easy way to
enter the necessary data into knowledge base, to amend
and to update them and then to carry out efficient
calculations over them, there was chose~ a corresponding
standard form for multicriteria analysis knowledge sheets
(Fig.2). In the teaching process the same or similar forms
are used for the recording of necessary information during
the formation of knowledge base. Then this information is
stored in computer memory. In Fig.2, parts related to
multicriteria analysis knowledge sheet's standard form are
highlighted, and the answers to its questions are not. If
a multicriteria analysis knowledge sheet contains no
information on a necessary alternative or criteria
describing it, so it can be easily updated by entering
the missing information. Basing oneself on multicriteria
project analysis knowledge sheets, the initial
decision-making matrix can be worked out. Having this
matrix, one can easily perform alternative multicriteria
assessment and selection of the most efficient versions.
3 Conclusion The multicriteria decision-making system is
used in order to improve students' teaching process. With
the aid of this system (its application facilitates better
mastering of teaching disciplines) a considerable number of
problems can be solved: optimization of goals pursued by
various interested parties; . formation of versions of
projects and their constituent parts; determination of
factors having intluence on the efticiency of project and
its constituent parts and working out of criteria system
describing them; performance of project lifetime process
optimization taking into account economic, maintenance,
aesthetic, comfortability and other factors; determination
of rational interested parties which could increase
lifetime process efficiency of a building; preparation
of recommendations on project development; the students,
when defending their course projects and graduation works,
can compare during discussions the received results with
solutions suggested by lecturers. This enables to check
students' knowledge and their ability to effectively
analyse problems arising in course of work; the students
acquire better understanding of connections existing in
lifetime process of a building between its constituent
parts and making influence on its efticiency; the
students acquire better understanding of mutual
connections between various disciplines; working process
with the multicriteria decision-making system contains game
elements, therefore students can more easily master the
teaching materials. COST GROWTH IN PUBLIC SECTOR
BUILDINGS F.H. Giritli Faculty of Architecture, Istanbul
Technical University, Istanbul, Turkey Abstract
Infonnation on a total of 31 public housing projects has
been collected and this data was analyzed to investigate
the factors which might be responsible for cost overruns in
construction contracts. The analysis confirms that the cost
overrun rate is clearly a function of the percentage
difference between the contract amount and the estimated
tender value. It is expected that the results may be
suitable for developing strategies to reduce cost overrun
rate. Keywords: Public housing projects, cost overrun.
Resume Les infonnations sur tous les projets des maisons
publiques sont reunies et ces donnees sont analysees pour
rechercher les facteurs qui peuvent etre responsables pour
les couts surpasses. Les analyses confrrment que la
vitesse du cout surpasse est c1airement la fonction de la
difference de pourcentage, entre Ie montant envisage et la
valeur estimee de la proposition. On espere que les
resultats soient convenables pour developper les strategies
de diminuer la vitesse des couts surpasses. 1
Introduction The whole of the construction industry very
strongly depends upon the preparation of estimates for a
project that may be perfonned at some stage in the future.
In today's competitive environment, especially cost
estimating is a key factor contributing to the success or
failure of a construction project. In this context, a major
objective of construction economics research is to produce
an accurate cost estimate of a building. However, it is
common in the construction industry for the fmal cost of a
project to differ from its contract sum. Therefore, it is
important for management to identifY ahead of time the
factors that might be responsible for the probable cost
growth. Many options and discussions can be found in
management literature regarding the crucial need for
studies investigating the relationship between the true
cost at the end of a project and the estimated cost at
tender stage. Any client involved with the construction
industry would benefit from knowing potential cost
overruns at an early stage of the project. He would then be
able to adjust the contract sum to arrive at an estimate
for the fmal price. The Organization and Management of
Construction: Shaping theory and practice (Volume Two).
Edited by D.A. Langford and A. Retik. Published in 1996 by
E & FN Spon. ISBN 0419 22240 5. Cost growth in public
sector buildings 233 The objective of this paper is to
examine data on patterns of differences between

contract award and final account. It also attempts to


pinpoint the factors having the

greatest influence on cost overrun rate.

2 Study methodology

This study is based on a set of data extracted from the


final account documents from the

I<:tanbul Public Works. The data base includes a total of


31 housing projects. For each

project in the data base the key items of data are


contract descriptions, overruns,

fluctuations, variations and claims. It is beyond the


scope of this paper to comment fully

on these data. A total of 31 housing projects was analyzed


to investigate the factors which might

influence the cost overrun. Past study on the subject has


shown that a number of factors

have close relations with the cost overrun. In the


literature the following factors have been found to
influence the cost overrun

rate: (1) the size of the project (2) the difference


between the contract award and tender

value (3) the level of competition and (4) the type of


construction. [I] [2] [3] . The dependent variable in this
study is cost overrun rate, which is defined as the

percentage difference in cost, plus or minus, between the


final price and the contract

amount. The independent variables (predicl.Ors) included in


the study are; (1) gross floor

area (2) contract amount (3) contract periods (4) the


percentage ditIerence between the

award amount and the estimated tender value and (5) number
of bidders. Due to inflation, all prices have been
standardized to the same basis. 1995 was chosen

as the referenc.:: year. Since fluctuations are outside


the control of project team and

management and since their forecast is a specialist


economic exerclse, this item was not

analyzed here. For this reason, the value of fluctuations


has not contained in the

standardized final value.

3 Development of the research model

This paper describes a model which has been developed to


enable the public client to

have an idea about the differences between the final price


and the contract amount. It

would then be possible to introduce such a factor


explicitly in to the calculations to cover

the overruns. A linear regression analysis was conducted


to determine if a linear relationship existed
between the dependent variable cost overrun rate and the
influencing variables.

Regression analysis of the data was performed by using the


SPSS sof',ware package. In

developing the regression model, the stepwise procedure was


u~ed to enter the

independent variables into the regression model. From a


few trials the following equation was derived.
2 Construction processplanning

1. Peurifoy, R.L. (1985) Construction planning, equipment


and methods, 4th edition, McGraw-Hill, London.

2. The Chartered Institute of Building. (1991) Planning


and programming in construction: A guide to good practice.

3. Hibberd, P.R. (1986) Variations in construction


contracts, Collins, London.

4. Powell-Smith, V. and Sims, J. (1989) Construction


arbitrations: a practical guide, Legal Studies and
Services.

5. Thomas, R. (1993) Construction contract claims,


Macmillan, London.

6. Pilcher, R. (1992) Principles ojconstruction


management, 3rd edition, McGrawHill, London.

7. Cooke, B. (1992) Contract planning and contractual


procedures, 3rd edition, Macmillan, London.

FINANCIAL AND ORGANIZATIONAL

IMPACTS OF PROJECT MANAGEMENT

Young Hoon Kwak and C. William Ibbs

Department of Civil Engineering, University of California,


Berkeley,

California, uSA

Abstract

Many organizations are projectizing their operations these


days, particularly non

construction enterprises. There is, of course, a range of


levels of Project

Management (PM) sophistication and tools that can be


adapted by such enterprises.

This study, sponsored by the Project Management Institute


(PM I) , examines current

PM levels and practices in various companies and


industries, and proposes a five level

model of PM sophistication. This paper summarizes proposed


PM process maturity

analysis methodology which can be used to evaluate


financial and organizational

impacts of PM to organizations. Also, a benchmarking


system is developed and

presented to quantitatively measure an organization's


level of PM sophistication.

This research is currently in progress. This benchmarking


methodology and the

resulting quantitative data will aid managers in making


wiser PM investment

decisions. Future research will continue to report


quantitative results and findings by

applying this research methodology.

Keywords: Benchmarking, Project Management, Project


Management Body of

Knowledge, Project Life Cycle, Project Management Process


Maturity Model

Resume

Actuellement, de nombreuses organisations planifient leurs


projets, particulierement

les entreprises hors du genie civil. II existe differents


niveaux de sophistication et une

grande gam me d'outils pour la gestion de projets, ceux-ci


peuvent facilement etre

adaptes aces entreprises.

The Organization and Management of Construction: Shaping


theory and practice (Volume Two).

Edited by D.A. Langford and A. Retik. Published in 1996 by


E & FN Span. ISBN 0419222405. Impacts of project
management 253
Cette etude, sponsorisee par Ie "Project Management
Institute (PMI)", examine les

pratiques courantes et les niveaux de raffinement de


differentes compagnies et

industries en matiere de gestion de projets. Elle propose


ensuite un modele a cinq

niveaux pour leur classification, selon leur degre de


sophistication. Dans ce travail,

nous proposons une methode pour analyser Ie degre de


maturite de la gestion de

projets. Elle nous permet de quantifier l'impact financier


et organisationnel de la

gestion de projets sur la compagnie. Un "Benchmarking


System" est developpe et

propose afin de quantitativement mesurer Ie niveau d'une


organisation du point de vue

de sa gestion de projets.

Cette methodologie de "Benchmarking" est actuellement en


cours d'elaboration, elle

permettra avec sec resultats quantitatifs les managers de


mieux determiner les

investissements en matiere de gestion de projets. Nous


poursuivons actuellement nos

recherches afin d'etoffer nos resultats quantitatifs et


decouvrir les parametres affectant

la gestion de projets.

1. Introduction

Corporate organizations are facing enormous competitive


pressures these days. New

markets are hard to penetrate, technology is rapidly


evolving, organizations are

segmented and experts are decentralized. Many companies are


forming strategic

alliances to share their knowledge and resources to produce


and provide high quality

product or services. In today's time-based business


environment, the project-driven

organizational form appears to be attractive.

Project Management (PM) techniques and skills have been


growing and widely being

accepted throughout the industries for the last forty years


[1]. PM is the application

of knowledge, skills, tools, and techniques in order to


meet or exceed stakeholder

requirement from a project [2]. From the construction and


aerospace industries to

software development and pharmaceutical projects, PM has


been adapted to improve

organizational effectiveness. PM techniques allow


organizations to perform work

faster with fewer resources and to effectively implement


any changes during project

life cycle [2].

Each industry and even companies within same industry have


different levels of PM

sophistication. Some of the reasons are: the adaptation


timing of PM, market

situation, and top management's commitment. It is not


clear though "how much" PM

should be injected into a company. However, project


managers agree on the benefits

of applying PM tools and techniques. Some of the benefits


include fulfilling customer

satisfaction, meeting quality standards and improving


organizational effectiveness.
Generally, implementation of PM practices and processes in
organizations is hard to

justify economically. Rationalizing the benefits of PM


processes and the cost of

executing PM is hard to do in precise terms. PM


expenditures in terms of direct cost,

training, and equipment are hard to determine. Previous


research in PM identified

some of the qualitative benefits of PM. However, that


research is very general and

254 Kwak and Ibbs

not helpful to managers trying to answer the hard and


challenging questions that

senior managers raise regarding PM expenditures and


investments.

This paper briefly describes a PM process maturity analysis


methodology that would

be used to determine the financial and organizational


impacts to organizations that

result from the implementation of PM practices, processes


and tools. By determining

quantitative benefits and relationships, this study will


enable managers to promote PM

applications. Also, this study will provide organizations


an opportunity to use PM in

a more cost effective manner.

2. Background "We just need to get the work done. We don't


have time for implementing processes and systems to manage
projects. We have been managing our work successfully for
years. " Anonymous Business Executive

Often times corporate executives request what benefits PM


will provide them. They

demand a better understanding of the relationships between


PM maturity and the value

of the company in the business environment. Managers who


try to promote PM have

to convince executives that implementing PM is a worthwhile


investment. However,

management usually has trouble providing benefits and


paybacks from PM investment

with our current knowledge.

PM practices are unique or nearly unique compare to other


management disciplines.

It provides the tools to plan, control, monitor, track and


manage resources, schedules,

costs, and quality. PM enables project to be on the right


track within limited time

and budget. PM is probably the most suitable management


techniques that integrates

planning and controlling for schedule intensive and


one-of-a kind endeavors. In

today's high-risk, rapidly changing business environment,


effective use of PM

practices is thought to help improve an organization's


competitiveness.

Contemporary strategic planning tools help corporate


organizations to be in a better

position in today's uncertain circumstances. Total Quality


Management (TQM) ,

Business Process Reengineering (BPR) , and Continuous


Process Improvement (CPI)

are some of the few strategic planning applications [3].


PM tools and skills assist the

implementation of these strategic planning tools in


corporate organization.

Eventually, PM will embrace greater acceptance and interest


at the senior

organizational level with corporate awareness and


understanding [4][5]. This will

help PM move from a technical activity to a strategic


management practice. Figure 1

illustrates the relationships of PM with other management


practices. Impacts of project management 255 AU PM
Practices ~~:-,~~ \ Practices ~---Figure 1.
Relationships of PM with Other Management Practices
[Adapted from PMBOK [2]]

The PM process is an integrative series of activities. It


consists of and integrates five

basic management processes within a project life cycle:


initiating, planning,

executing, controlling, and closing [2]. The project life


cycle concept is important

because it underscores the influence that early project


planning has impact on overall

project success. Project success is determined by how well


the project is defined and

planned. In turn the sufficiency and effectiveness of


project planning is strongly

affected by an organization's PM preparedness.

The Software Engineering Institute (SEI) is advocating PM


practices for software

development companies. SEI has developed the Capability


Maturity Model (CMM)

for software development that describes the key elements


of an effective software

process [6]. The CMM can be used for software process


improvement, process

assessments, and software capability evaluations. It is


composed of five maturity

levels [Figure 2]. It is being used to evaluate an


organization's capability to perform

successfully on software engineering contracts.


Disciplined porcess --Standard, consistent process
~--Predictable process ~-Continuously improving process

Figure 2. Five Levels of Software Capability Maturity Model


[Adopted from [6]]

256 Kwak and /bbs

We believe the PM process and the software development


process are closely related.

This study modifies the CMM to systematically evaluate


corporate organization's PM

sophistication.. Our model blends the concept of PM life


cycle and software

development processes as shown in Figure 3. This research


will provide an improved

yardstick for determining and assessing an organization's


current level of PM

processes and systems throughout any project life cycle.


standard Project Tracking Basic Project Planning Ad Hoc
PM Process Advanced Project Planning & Management
Continuous PM Process Improvement Figure 3. Project
Management Process Maturity Model

3. Previous Related Research "Managers in the U.S. smiled


knowingly in the 1950's when Japanese engineers made the
rounds at trade shows, endlessly snapping photos. In the
early 70's, the smile faded as those photos led to
world-class products. Now, the U.S. is embracing an
effective response: Benchmarking. " Business Week, Nov.
30, 1992

3.1 Benchmarking

Benchmarking is a continuing discovery process that opens


the organization to new

and sometimes radical ideas that can playa pivotal role in


improving effectiveness. It

is a method to increase the competitiveness of a firm


through getting information
about the best practices and comparing top performing
companies. It has have been

widely applied to evaluate current practices and


performance of industries such as

construction, manufacturing, automobile, and hi-tech


manufacturing.

MIT's five-year, five-million-dollar study that compared


and analyzed world-class

automobile manufacturers introduced benchmarking to the


public [7]. An on-going

study of the semiconductor industry also uses benchmarking


to find where other

companies are standing and give incentives to companies


who participate [8]. Both

studies tested various performance factors in terms of


regions and companies and

correlate their research by gathering actual project


performance data. Impacts of project management 257

A study of Lotus Notes determined the impact on


organizational productivity and

financial impact of using a category of software called


groupware. Groupware is

designed to enhance productivity by allowing users to share


information, and

customize the view of information to suit individuals


needs. This study calculated and

quantified the return on investment (ROI) that resulted


from implementing groupware

in different organizations [9][ 10].

3.2 Project Management

Previous research on PM benefits and costs is limited to


identifying the "soft"
benefits of applying PM practices and tools. Most studies
were based on surveys of

corporate managers and failed to exploit quantitative


project performance data or a

methodology for developing such data


[11j[12][13JL14J[15][16][17]. Other studies

deal with determining the relationships between


organizational productivity and

organizational structures by comparing functional and


matrix organizational structures

[18][ 19][20J[21 J[22][23].

3.3 Software Development

PM and the software development process share a common


domain. Humphrey [24]

described SEI's capability maturity model and its impact


on Hughes Corporation's

software engineering division. He analyzed actual project


data to show performance

improvement in the division and correlated that with


levels of CMM maturity.

4. Research Methodology

4.1 Literature Review of Related Research

Table 1 compares some of the previous related research and


each study's research

methodology. The purpose of this table is to determine and


choose the research

methodology that is most suitable for our research. It is


also useful for determining

the areas lacking solid understanding.

4.2 Scope of work/Industry

As part of our research we are investigating a number of


companies in various
industries including High-Tech Manufacturing; Information
Movement and

Management; Engineering and Construction; and Utilities. We


are seeking companies

with any level of PM maturity and sophistication.

4.3 Variables

This research intends to identify and benchmark the key


variables needed to

understand where participating companies stand in the use


of PM practices. This will

be accomplished by asking detailed questions that


incorporates PMBOK criteria and

project life cycle phases [Figure 4]. This breakdown


structure will assess an

organization's PM sophistication level in moderate detail.

258 Kwak and /bbs Project Life Cycle I I I 1'1 I I


Figure 4. Blending PMBOK with Project Life Cycle Process

It also examines traditional project performances such as


cost, schedule, quality, and

customer satisfaction. These data are collected from


representative, recently

completed projects. One of the more challenging data that


we would like to collect is

determining annual rate of return on PM investment in the


organizations. This will be

hard to determine precisely, however this research attempts


to estimate these numbers

on an order of magnitude basis.

4.4 Research Steps

This research is a 2-step study.

• Step 1. Evaluating organization's PM maturity using 2


part questionnaire The objective of the 2 part
questionnaire is to effectively collect information about
the organization's current PM maturity level and
statistically correlate it with actual performance data.
This questionnaire is developed and modified to capture
the essence of PM practices in the organization [6][32].
~ Part 1 :Organizational maturity assessment It is used to
precisely evaluate an organization's level of PM
sophistication. PM levels are defined on a 1 to 5 Likert
Scale. 1. Organizational information: Organization's
size, product focus, project management practices return
on investment and quality management. 2. Initiate the
Project: Developing potential project proposal, analyzing
feasibility. Impacts of project management 259 3. Define
and Organize the Project: Defining the project, organizing
project team. 4. Plan the Project: Defining the scope,
establishing schedule, estimating resources and costs, and
risk management. 5. Track and Manage the Project:
Collecting and analyzing status, planning and taking
adaptive actions and reporting status to organization. 6.
Close Out The Project: Effectively brining a project to a
close. 7. Project-driven Organization Environment:
Budgeting for project management and process support,
compensation, and career advancement. =? Part 2:Project
Peiformance Assessment The purpose of part 2 is to collect
actual quantitative project performance information such
as cost, schedule, change, quality, and customer
satisfaction. Data that organization provides for this
research should be chosen from at least one specific,
recently completed project. Also, the chosen project should
represent organization's current PM practices.

This information will be statistically analyzed and


correlated to the responses of the

two part questionnaire. This two part questionnaire has


been pilot tested by

participating organizations and the PM process maturity


analysis methodology is

proven to be working.

• Step 2. In-depth interview with selected organization for


developing mini-case studies We will develop mini-case
studies that contain some particularly unique practices
and business aspects of project management from a
follow-up in-depth interview.

4.5 Research Assumptions


* All of the participating organizations are treated
equally.

* All questions have the same weight for assessing


organizational maturity.

* Quantitative data from at least one specific, recently


completed project represent company's current PM
practices.

I N

S T

Y J a s e l s k i s [ 2 5 ] c o n s t r u c t i o n R u s s
e l l [ 2 6 ] c o n s t r u c t i o n C I I [ 2 7 ] c o n s
t r u c t i o n H e r b s l e b [ 2 8 ] s o f t w a r e P e
a r c e [ 2 9 ] h i t e c h [ 3 0 ] m a n u f a c t u r i n
g I b b s [ 3 1 ] c o n s t r u c t i o n

I A

L E

S /

F A

T O

S p r o j e c t s u c c e s s p r o j e c t s c h e d u l e
p r o j e c t c o s t p r o j e c t i n p u t c h a r a c t
e r i s t i c s p r o j e c t f a i l u r e , n o n f a i l
u r e p r o j e c t c h a r a c t e r i s t i c s t r u s t
i n d i c a t o r c o s t i m p a c t p r o c e s s i m p r
o v e m e n t c o s t p r o d u c t i v i t y d u r a t i o
n q u a l i t y b u s i n e s s v a l u e t i m e c o s t q
u a l i t y p e r c e n t c o m p l e t e c h a n g e c o s
t b u d g e t p r o d u c t i v i t y 8 P M B O K c r i t e
r i a S p t o j e c t l i / e c y c l e p h a s e s s c h e
d u l e , c o s t a n d q u a l i f J ' c u s t o m e r s a
t i s J a c t i i J n c R O H f t . P M . f J r a c t i c e
s

L O

Y q u a n t i t a t i v e m o d e l s t a t i s t i c a l l
y c o r r e l a t e p e r f o r m a n c e a n d p r o j e c
t i n p u t c h a r a c t e r i s t i c s s t a t i s t i c
a l a n a l y s i s : n u m e r i c a l : s t u d e n t t t
e s t q u a l i t a t i v e : c h i s q u a r e t e s t r e
g r e s s i o n a n a l y s i s b e n c h m a r k c o s t i
m p a c t s t a t i s t i c a l a n a l y s i s e m p i r i
c a l m e t h o d s m i n i c a s e s t u d i e s 1 t o 7 L
i k e r t s c a l e c h i s q u a r e t e s t c o r r e l a
t i o n a n a l y s i s l i n e a r r e g r e s s i o n m o
d e l s t u d e n t ' s t t e s t c o r r e l a t i o n a n
a l y s i s r e g r e s s i o n a n a l y s i s " d e v e w
p . q u a t t t i t a t i v e m o d e l 1 t o 5 L i k e r t
s c a l e b e n c h m a r k P M l e v e l

O
N

T R

I B

T I

N p r o j e c t m a n a g e r s c a n p r e d i c t t h e i
r c h a n c e s o f a c h i e v i n g s u c c e s s f u l p
r o j e c t o u t c o m e s b a s e d o n p r e d i c t e d
r e s o u r c e a l l o c a t i o n s t r a t e g i e s c o
n t r a c t a d m i n i s t r a t o r s c a n b e t t e r u
n d e r s t a n d t h e i m p a c t o f c o n t r a c t o r
f a i l u r e s t a t i s t i c a l l y s u p p o r t t h e
n o t i o n t h a t t h e i n c r e a s e d l e v e l o f t
r u s t b e t w e e n p a r t i e s l e a d s t o p r o j e
c t c o s t b e n e f i t s i d e n t i f y s u b s t a n t
i a l g a i n s i n p r o d u c t i v i t y , e a r l y d e
f e c t d e t e c t i o n , t i m e t o m a r k e t a n d q
u a l i t y b y i m p l e m e n t i n g C M M b a s e d s o
f t w a r e p r o c e s s i m p r o v e m e n t d e m o n s
t r a t e t h a t P M p r a c t i c e s p r o v i d e a t l
e a s t o n e w a y o f m a i n t a i n i n g t h e n e c e
s s a r y f o c u s w h i l e b r o a d e n i n g t h e f i
r m ' s b a s i s u n d e r s t a n d h o w c h a n g e o c
c u r s a n d a f f e c t s p r o j e c t h e t f e r u n d
e r s t a n d t h i ! J i n t l f t c U z I a n d o r g a n
i z a t i o n a t b e n e f i t s o f u s i n g P M p r a c
t i c e s i n c o r p o r { J t e o r g a n w t i o n s T a
b l e 1 . C o m p a r i s o n o f R e l a t e d R e s e a r
c h M e t h o d o l o g i e s

S A

P L

S I

Z E 7 5 p r o j e c t s ! 1 0 7 p r o j e c t s 2 6 2 p r o
j e c t s 1 3 o r g a n i z a t i o n s 3 1 7 f i r m s 1 0
4 p r o j e c t s Impacts of project management 261
5. Expected Results/Contributions

5.1 Academic point of view

This research will provide solid, comparative studies on PM


practices among industry

and across industries. Comparing the organizational aspects


of PM practices and

correlating such to the project performance data is a


principal research methodology

and product of this investigation. Statistical analysis


will assure the reliability of the

qualitative and quantitative data analysis.

Benchmarking will provide a framework for identifying


different PM levels by

blending the project life cycle concept and PM body of


knowledge with quantitative

project information. This system can be easily used and


further modified to assess

different aspects of PM practices in more detail.

5.2 Practical point of view

This research will provide an independent reference point


on best PM practices and

skills. The level of PM in the organization and actual


project performance data will

be statistically analyzed to plot possible correlation.


This study may help managers to

better promote PM practices for less PM-sophisticated


industries. Understanding

what level of sophistication is appropriate for a specific


project or environment will

provide greater insight into appropriate levels of PM use.

Executives will even be able to determine the necessary


practices for achieving a fully

project-driven organization [33]. By presenting


relationships between PM practices

and project performance, it may convince top management


that PM is a appropriate

management discipline area in today's time-based,


resource-limited, and highly

competitive environment. The benefits to companies will be


promotion of better

project management practice and a better project management


future.

This study will benefit strategic planning people to plan


and implement PM practices

in the entire organization to achieve and maintain


competitive edge. By comparing

PM practices to similar or different industries, managers


can assess the current PM

level of their own organization and of the competition, and


set more realistic goals for

achieving a more appropriate level of PM sophistication.

An attempt to calculate the PM ROI will assist managers to


determine required future

investments to achieve any specific level of PM maturity.


This will convince top

managers to be aware and invest more on PM practices and


tools.

6. Conclusions

This paper summarizes PM process maturity analysis


methodology that will be used

by the authors to find financial and organizational impacts


of PM to corporate

organizations. A benchmarking system is developed and


presented to quantitatively
measure an organization's level of PM sophistication. It
is expected to have benefits

that such quantitative data and methodology will aid


managers in making better PM

262 Kwak and /bbs

investment decisions. Future research will continue to


report quantitative results and

findings by applying this research methodology.

1. O'Brien, J. (1984) CPM in Construction Management, 3rd


edition, McGraw Hill.

2. The PMI Standards Committee. (1994) A Guide to the


Project Management Body of Knowledge (PMBOK), August, PMI

3. Kwak, Y.H., Clark, A., Grilo, A., Betts, M., and Ibbs,
C.W. (1995) Contemporary Strategic Planning Tools and
Applications for Construction Managers. First
International Conference on Construction Project
Management, Singapore, January, pp. 25-40.

4. Kerzner, H. (1987) In Search of Excellence in Project


Management, Journal of Systems Management, February, pp.
30-39.

5. Cleland, D. (1993) The Future of Project Management, PM


Network, September, pp.6-8.

6. Paulk, M., Weber, C., Garcia S., Chrissis, M, and Bush,


M. (1993) Key Practices of the Capability Maturity Model,
Version 1.1, Software Engineering Institute,
SEI-93-TR-025.

7. Womack, J., Jones, D. and Roos, D. (1991) The Machine


that Changed The World., HarperPerennial.

8. Engineering Systems Research Center (1993) The


Competitive Semiconductor Manufacturing Survey: First
Report on Results of the Main Phase, The Competitive
Semiconductor Program, Report CSM-02, University of
California at Berkeley.

9. Henry, J., Blum, P., and Salloway, E. (1992) The Impact


of Lotus Notes on Organizational Productivity:
Evidencefrom Customers, Final Paper, Telesis.
10. International Data Corporation. (1994) Lotus Notes:
Agent of Change: The Financial Impact of Lotus Notes on
Business, IDC Special Report.

11. Al-Sedairy, S.T. (1994) Project Management Practices in


Public Sector Construction: Saudi Arabia. Project
Management Journal, December, pp. 37-44.

12. Boznak, R.G. (1988) Project ManagementToday's Solution


For Complex Project Engineering. IEEE.

13. Bu-Bushait, K.A. (1989) The Application of Project


Management Techniques To Construction and R&D Projects.
Project Management Journal, June, pp. 17-22.

14. Construction Industry Institute. (1990) Assessment of


Owner Project Management Practices and Performance.
Special ClI Publication.

15. Deutsch, M.S. (1991) An Exploratory Analysis Relating


the Software Project Management Process to Project
Success. IEEE Transactions on Engineering Management, Vol.
38, No.4.

16. Gross, R.L. and Price, D. (1990) Common Project


Management Problems and How They Can be Avoided Through
The Use of Self Managing Teams. 1990 IEEE International
Engineering Management Conference

17. Ziomek, N.L., and Meneghin, G.R. (1984) TrainingA Key


Element In Implementing Project Management. Project
Management Journal, August, pp. 76-83. Impacts of project
management 263

18. Donnelly, R.G. and Kezsbom D.S. (1993) Overcoming the


Responsibility

Authority Gap: An Investigation of Effective Project Team


Leadership for a New

Decade. 1993 AACE Transactions.

19. Gobeli, D.H. and Larson, E.W. (1986) Matrix Management:


More than a Fad.

Engineering Management International, Vol. 4.

20. Larson, E.W. and Gobeli, D.H. (1989) Significance of


Project Management
Structure on Development Success. IEEE Transactions on
Engineering

Management, Vol. 36, No.2.

21. Lundin, R.A., and Soderholm, A. (1994)


Conceptualization and LearningThe

Black Environment of PM. PMI 25th Annual Seminar/Symposium,


Vancouver,

Canada.

22. McCollum, J.K. and Sherman J.D. (1991)The Effects of


Matrix Organization Size

and Number of Project Assignments on Performance. IEEE


Transactions on

Engineering Management, Vol. 38, No.1.

23. Might, R.J. and Fischer, W.A. (1985) The Role of


Structural Factors in

Determining Project Management Success. IEEE Transactions


on Engineering

Management, Vol. EM-32, No.2.

24. Humphrey, W.S., Snyder, T.S., and Willis, R.R. (1991)


Software Process

Improvement at Hughes Aircraft. IEEE Software, July, pp.


11-23.

25. Jaselskis, E.J. and Ashley, D.B. (1991) Optimal


Allocation of Project

Management Resources for Achieving Success. Journal of


Construction

Engineering and Management, Vol. 117., No.2.

26. Russell, J.S. and Jaselskis, E.J. (1992) Quantitative


Study of Contractor

Evaluation Programs and Their Impact. Journal of


Construction Engineering and
Management, Vol. 118., No.3.

27. Construction Industry Institute (1993) Cost Trust


Relationship, publication 24-1.

28. Herbsleb, J., Carleton, A., Rozum J., Siegel, J. and


Zubrow, D. (1994) Benefits

of CMM-Based Software Process Improvement: Initial Results,


Technical Report

SEI-94-TR-13, Software Engineering Institute.

29. Pearce, J.W., Adams, J.R., Mechling, G.W., and Owens,


S.D. (1994)

Operations Focus in High-Tech Firms. Project Management


Institute 25th Annual

Seminar/Symposium, Vancouver, Canada.

30. Pearce, J.W., Adams, J.R., Mechling, G.W., and Owens,


S.D. (1994)

Performance Evaluation and Firm Performance in Project


Management

Organizations. Project Management Institute 25th Annual


Seminar/Symposium,

Vancouver, Canada.

31. Ibbs, C.W., Allen, W.E., and Wang, M. (1995)


Quantitative Impacts of Project

Change, Draft Version, University of California at


Berkeley.

32. Integrated Project Systems (1995) Organizational


Maturity Assessment

Questionnaire.

33. McCauley, M. (1993) Developing a Project-Driven


Organization. PM Network,

September pp. 26-30.

THE APPLICATION OF
CONSTRUCT ABILITY PRINCIPLES IN

THE AUSTRALIAN CONSTRUCTION

INDUSTRY

A.C. Sidwell and V.E. Francis

School of Building and Planning, University of South


Australia,

Adelaide, Australia

Abstract The concept of constructability first emerged in


the United Kingdom and the United

States in the late 1970's, following studies into how cost


efficiencies and quality

improvements could be made in the construction industry.


The lack of integration of

construction knowledge into the design process, encouraged


by traditional procurement

methods hindered the "ability" to construct, and was found


to contribute to projects

exceeding budget and schedule deadlines. The approach to


studies in the UK and the US have differed in many
respects.

Experience in the US, through the work of the Construction


Industry Institute (CII),

based at Austin Texas, has been particularly successful.


There the emphasis has been on

the development of a management system rather than


focussing on techniques and detail

such as site productivity by design rationalisation, as was


done in the UK. The reported

benefits of constructability from the US have indicated


cost benefit ratios as high as 50: 1

and average project savings of 6%. This paper reports the


development of a constructability principles file in
AustraIia
comprising guidelines, general principles and strategies as
well as an expandable data

base compiling constructability examples.

Keywords: Constructability, Australian case studies.

Sommaire

Le concept de constructabilite a apparu au Royaume Uni et


aux Litats-Unis vers la fin

des annees 70, a la suite des recherches faites sur les


cOuts et laqualite; des

ameliorations pouvaient alors etre envisagees dans


l'industrie du batiment. Le manque

d'integration des connaissances dans Ie domaine de la


construction et dans Ie domaine

du dessin des projets, ainsi que les methodes


traditonnelles d'achats des materiaux, ont

entrave la 'capacite' de construire, et ont contribue a la


creation de pro jets qui

depassent les budgets et les dates d'echeance. Les


recherches au Royaume Uni et aux Etats-Unis sont abordees
differemment

It bien des egards. L'exptSrience aux Etats-Unis, par


I'intermediaire du travail du

Construction Industry Institute (CII), base a Austin


Texas, a particulierement bien

reussic. La on a insiste sur Ie developpement d'un systeme


de management plutOt que

sur des techniques et des details tels que la


productivittS du site par la rationalisation du

pro jet, comme au Royaume Uni. Les benefices de la


'constructabilittS' reconnus aux

Etats-Unis montrent un benefices des cOuts de l'ordre de


50: 1 et une moyenne
d'econornic de 6%. Cette communication presente Ie
developpement du dossier sur les principes de

constructabilite en Australie. Ce dossier comprend les


idees directrices,les principes

The Organization and Management of Construction: Shaping


theory and practice (Volume Two).

Edited by D.A. Langford and A. Retik. Published in 1996 by


E & FN Span. ISBN 0 419 22240 5. Application of
constructability principles 265

generaux, les strategics ainsi qu'une banque de donnees des


examples de

constructabilites. Mot-eles: Constructabilite, etudes de


cas en Australie.

1 Introduction

The concept of constructability, or buildability, fIrst


emerged in the US and UK in the

late 1970s. It evolved from studies into how improvements


could be achieved to

increase cost efficiency and quality in the construction


industry. These studies found

that the lack of integration of construction knowledge


into the design process hindered

the "ability" to construct and this was cited as one


reason for projects exceeding budgets

and schedule deadlines. The separation of the design and


construction processes, partly

due to traditional contractual procedures, was seen as a


major factor hindering

constructability.

Constructability has been enthusiastically and widely


adopted in the United States. A

survey by the University of Wisconsin [1] of 62


organisations indicated that 68% had a
formal, or informal, constructability program and
estimated cost savings of

5.7%.Research by the US Construction Industry Institute [2]


indicates cost benefIts as

high as 50: 1, that is the returns in the form of savings


against expenditure on

constructability.

Constructability is an approach which links design and


construction processes which

have traditionally been isolated in the industry. The


increasing complexity of many

projects makes it more and more difficult for designers to


be fully aware of all the

implications of their designs on construction costs.


Making use of construction

knowledge, from the earliest stages of a project where the


ability to influence cost is at

its greatest, makes sense from both practical and fInancial


viewpoints. The well known

cost influence curve, Figure 1, illustrates how the


ability to influence costs is greatest at

the conceptual phase in the project life cycle and reduces


as the design is developed and

firmed up. HIGH

en

o FEASIBILITY

z
w

..J

LL

:::i

iIi

<C

LOW START TIME

Figure 1 Cost Influence Curve [2] POST CONSTRUCTION


COMPLETION ..

266 Sidwell and Francis The CII in the United States is


currently concentrating on education and

implementation of its constructability concepts. In


Australia the emphasis is still on

gaining wide acceptance of the principles and the


development of implementation

strategies.

2 Review of approaches to constructability The most widely


accepted definition's of constructability, or buildability,
are those

developed by the Construction Industry Research and


Information Association (CIRIA)

in 1983 [3], and the US Construction Industry Institute


(CII) in 1987 [4]. Both

definitions emphasise the integration of construction


principles into the design of
buildings. The initial CIRIA report was followed by a
further study by Adams in 1989

[5] in which the original seven categories of buildability


principles were further

developed to present sixteen, more definitive, principles.


This study is most purposeful

since, although it still focuses on design, it does begin


to widen the perspective of

buildability and point the way towards recognising the


complexity of the issues

involved. In 1990 the Royal Australian Institute of


Architects [6] cited factors working

against implementation of buildability as 'the isolation


of designers from the realities of

the construction process ... ', , ... a closeted approach


to practical experiences tends to

keep problems from becoming common knowledge, leading to a


repetition of the same

problem.'

A number of studies in the UK have identified the tendency


for the traditional

procurement approach to militate against the integration


of construction knowledge in the

initial design phases of the project, for example the


Banwell report of 1964 [7], and the

Wood report of 1975 [8]. The difficulties surrounding the


determination of conceptual

boundaries for buildability have been discussed in studies


by Bishop in 1985 [9] and

Griffith in 1985 [10]. It was the narrow focus, together


with the complexities of the

traditional building process, that led to the diminishing


interest in buildability concepts
within the UK construction industry during the late
1980's. The most recent review of

the construction industry by Latham in 1994 [11] reiterates


the difficulties created by the

traditional system in facilitating innovation.

Application of constructability principles in the UK and


US differ in may respects.

Generally, the early work in the UK was narrowly focussed,


highlighting techniques

and details, with an emphasis on productivity by design


rationalism. There was not the

emphasis on management systems and the involvement of


owners and contractors as

was the case in the United States. These factors, together


with the traditional segregated

nature of the building process and a backlash against


building styles developed by

rationalisation, have led to a lack of interest by the


industry in the UK and resulted in

minimal further research. Costs have been reduced


relatively by the use of fast tracking

and management of costs. Where the limits of these methods


have been reached, certain

clients have begun to address constructability.

The US approach, spearheaded by the American CII,


capitalises on a direct link

between owners and contractors. It relies heavily on the


adoption of a management

system rather than detailed check lists, thereby espousing


principles for guiding thought

and creativity. This is in essence the difference between


the approached in the UK and

US and has been used as the basis for the research work by
the Construction Industry

Institute in Australia (CIIA). The approach involves owners


and contractors working

together and concentrates on development of a


constructability management system, ie.

the process not the product.

The American CII developed its Constructability Concepts


File during the late 1980s

and this has spawned a number of other applications by, for


example, the Houston

Business Roundtable, the oil company Chevron, contractors


Kelloggs and Brown Root

Braun. Their success is due to:

• Partnership between owners and contractors driven by the


objective of savings.

• Emphasis on the management system, the development of a


constructability program. Application of constructability
principles 267

• Implementation program stimulated by the CII system.

• Continued momentum stimulated by the CII education


program.

3 Australian research

In 1992 the CIIA identified constructability as an approach


with the potential to bring

significant cost and time savings to the Australian


building industry. At the same time

the use of value engineering was quite widespread but


tended to be applied in a typical

40 hour workshop at a point when design had largely been


developed, thereby missing

out on the maximum savings.

The only research had been by Hon [12] who found some
evidence of application of

constructability and undertook simulated studies and post


facto evaluations. Subsequent

work by Griffith and Sidwell [13] identified examples of


the application of

constructability on a number of Australian projects.

The CIIA established a task force with a carefully balanced


membership of client,

architect, structural engineer, quantity surveyor, project


manager, builder and

researchers. Their objective was to evaluate existing


knowledge and practice and

develop a constructability principles file appropriate to


Australian industry context. If

the US experience could be repeated in Australia, the


adoption of these principles has the

potential to bring improvements in cost efficiency and


quality in the construction

industry.

The Australian researchers visited the United States and


the United Kingdom to

evaluate latest developments and leam from the experiences


of practitioners and

researchers. Companies in the United States were able to


provide hard evidence of

actual savings.

Some of the constructability concepts files developed in


the US for particular

applications are more specific and detailed, however the


system we have developed in

Australia focuses on principles.

The principles developed, which consists of a system for


improving the level of

constructability achieved on a project, is dependent on the


client being committed to its

inclusion in the project procedures from the start. It


involves the whole project team,

from the very beginning of the project, considering the


effects of their actions on the

construction process. Construction personnel, or their


representatives, are encouraged

to be involved; in an ideal situation, the final contractor


should be included in the project

team from the inception stage onwards.

The research team evaluated the overseas concepts against a


series of local case studies

and developed a set of principles tailored to the


Australian industry. These were

evaluated and tested on some twenty examples included in


the database.

The system developed for Australia consists of a best


practice Constructability

Principles File [14] with the following contents:

• Implementation advice on how organisations can establish


a constructability program.

• Flow chart indicating the applicability of the


constructability principles at the various stages of the
project life cycle.

• Executive summaries of the constructability principles.

• Twelve constructability principles.

• Database to record examples of constructability savings.

The implementation section is kept intentionally brief to


account for the individual

cultures of many organisations. Key issues for successful


implementation are covered,

rather than providing specific procedures which may not


suit all organisations and

therefore reduce the likelihood of their continued use.

The flow chart or roadmap is shown in Figure 2 and advises


the user which principles

are most likely to be relevant at particular stages in the


project life cycle.

268 Sidwell and Francis ~A8ILiT_~ FLO-W C-HART--~~--=J


~ASIBILIT.61CONCEPTUAL DESIG~I!TAII:I!D DllSlchNSTRUCTION.1
POST CONSTRUCTION FEASJU ILITY CONCEPTUAL DESIGN DETA
ILED DESIGN CONSTRUCTION POST CONSTRUCTION •
Inlt,rariOll • Inttlrorion 0 InttgrtJlion 0
Inttgrmion 0 Imt'lrtlrion 0 Constl'uction •
ConSlruClion 0 COIISlructiOll 0 Construction 0
Corportltt Know/nlgl KnO'A·/tllgt Kno",I,,~t
Kno'l'l'/,tlgt Objtc';'~$ • Tf'om SkUls • Tf'OmSkills
• TtamSkills • Pro&rmn • F"tlbod • Corpomtt •
Corpora" • A, mi/oblt Rtsourus • Acussibiliry Objf'Cli
l'tS Objter;I'ts • A ''(Ii/obi,. Rnourcrs • Ami/obi,
Rtsourcrs 0 Exumal Facton • COIlJlrucr;on Kno'A'I,dtt
• Exttmal Factors • Exuma/ Factors • Pro8rom 0
Program • Prolmm • Cons /ruction MnlKxlol°IY 0
Construction • Construction • Acctssibility MnhlNlolov
MnhotlololY • Acctssibility • Sptcijicmions Figure 2
Constructability Roadmap [14] The principles file
comprises twelve overriding concepts of constructability.
They

represent current best practise in constructability that


are aimed at encouraging the project

team to apply them, where appropriate, to their projects.


While the team may find some

principles directly applicable to their particular project,


the aim of the file is to stimulate

thought about constructability and how to make it work. The


system avoids a "check

list" approach that stifles creative thought, while


addressing the difficulties associated

with implementation by indicating the relative importance


of each principle at particular

stages of a "typical" project. The twelve principles are


given in Figure 3.

The database contains examples of constructability savings


from some Australian

projects. These are intended as samples only and it is


anticipated that individual

companies will use the database to record their own


experiences. In this way

constructability can be improved in projects in the future


as "lessons learned" can be

recalled and reused where appropriate. The database has


been designed to run on a PC,

stored on the hard disk and updated at the completion of


every project. A pro forma has

been provided so that examples can be recorded as they


arise. This may be during the

project or at the recommended post construction


constructability reviews.

DEFINITION

Constructability is a system for achieving optimum


integration of construction

knowledge in the project delivery process and balancing


the various project and

environmental constraints to achieve maximisation of


project goals and building

performance.

Construction Industry Institute, Australia [15]


Application of constructability principles 269

4 Application of the Principles

The first three principles, Integration, Construction


Knowledge and Team Skills
address the importance of making constructability part of
normal project procedures and

involving the 'right people' from the very beginning of


the project. The next principle,

Corporate Objectives, looks at how constructability can be


enhanced when the project

team understands the corporate, as well as project


objectives. Available Resources and

External Factors address the issue that constructability


will often be affected by factors

over which the project team has little control, but whose
influence can be minimised if

identified early.

The principle entitled Program outlines the importance of


having a realistic,

construction sensitive program which has been developed and


agreed by the whole

project team. Construction Methodology, Accessibility and


Specifications relate to issues

that need to be integrated into the final design and


documentation of the project.

The eleventh principle, Construction Innovation, addresses


the use of construction

knowledge to improve the effectiveness of operations on


site. Where constructability is

correctly integrated into a project, the best solution has


already been identified, evaluated

and documented, with the constructor's assistance, prior to


tender. Therefore, although

the ability to influence cost during construction is less


significant than in the feasibility or

design stages, collectively constructability savings made


during this time can be
substantial.

The final principle, Feedback, relates to the concept of


the life cycle of a project being

a cyclical, cumulative process rather than linear, whereby


information can be used in

similar projects in the future. Two post construction


reviews are recommended. These

are especially concerned with evaluating the effect of


constructability decisions on

construction efficiency and the operational efficiency of


the project.

270 Sidwell and Francis CONSTRUCTABILITY PRINCIPLES

1. INTEGRATION Constructability must be made an integral


part of the project plan.

2. CONSTRUCTION KNOWLEDGE Project planning must actively


involve construction knowledge and experience.

3 . TEAM SKILLS The experience, skills and composition of


the project team must be appropriate for the project.

4 • CORPORATE OBJECTIVES Constructability is enhanced when


the project team gains an understanding of the clients
corporate and project objectives.

5 . AVAILABLE RESOURCES The technology of the design


solution must be matched with the skills and resources
available.

6. EXTERNAL FACTORS External factors can affect the cost


and/or program of the project.

7. PROGRAM The overall program for the project must be


realistic, construction sensitive and have the commitment
of the project team.

S. CONSTRUCTION METHODOLOGY Project design must consider


construction methodology.

9. ACCESSIBILITY Constructability will be enhanced if


construction accessibility is considered in the design and
construction stages of the project.
10. SPECIFICATIONS Project constructability is enhanced
when construction efficiency is considered in
specification development.

11. CONSTRUCTION INNOVATION The use of innovative


techniques during construction will enhance
constructability.

12. FEEDBACK Constructability can be enhanced on similar


future projects if a post construction analysis is
undertaken by the project team.

Figure 3 Twelve Constructability Principles [14]

5 Implementation strategy Following publication of the


constructability principles file the CllA has changed

emphasis to dissemination of the principles and the


development of implementation

strategies to ensure take up by industry. Major funding


for the next stage of this

research was awarded by the Australian Research Council for


a joint project with

Professor D. McGeorge at the University of Newcastle, New


South Wales. Their first

objective has been to conduct a number of case studies of


industry applications of

constructability principles to evaluate optimum research


methodology. The present

study includes:

• Case studies to analyse the application of


constructability principles.

• Industry workshops backed up with questionnaires to


explore the right methodologies for industry.

• In a parallel study McGeorge and his team are analysing a


series of school projects built by the NSW Department of
Public Works. Application of constructability principles
271

• The joint team is exploring decision support systems and


multi-media approaches to the display of
constructability. An indication of the level of savings
achieved is illustrated in three of the case studies

conducted so far, figure 4.

PROJECT Savings achieved by constructability


im31lementation

AUSTRALIS MEDIA CENTRE • Project completion in 9 months


compared to 12-15 months for equivalent project. • A$1.1m
saving on the A$12m project, half

7300 sq m. National Customer Service of which attributed


to constructability.

Centre for Galaxy Media • Enhanced level of fitout.

TOYOTA CAR • Project completion in 107 weeks, 3 weeks

MANUFACTURING FACILITY ahead of schedule. • A$18m savings


on total project cost of A$161m.

120,000 sq m. building area to • Award winning quality


and safety record.

manufacture 100,000 cars per year. • High client


satisfaction.

MELBOURNE MAGISTRATES • Project completion 6 months ahead


of

COURT original 24 month schedule. • Completion within


maximum guaranteed

18,500 sq m. floor area with magistrates price of A$53m


with A$1.1m returned to

courts & chambers, hearing rooms and the client as part of


a 80120 cost sharing

custody centre. agreement. Figure 4 Summary of results


from case studies

6 Conclusion It is our contention that the application of


constructability in the United States has been

more widespread and successful than in the United Kingdom,


and that this would appear

to be due to the different emphasis in the United States


towards treating constructability

as a management system, rather than a design tool. In


particular constructability is used

as the vehicle to bring construction knowledge further


forward in the project delivery

process right up to the initial considerations by the


client. Very often it is client driven

rather than consultant driven. Clearly we must convince


clients of the value of

constructability, as well as consultants in the industry.


In Australia the Cll is pursuing

an implementation strategy that includes a program of


publications, presentations at

conferences and conducting industry workshops to


disseminate the principles. As part

of this process we are collecting data on perceptions of


the barriers to implementation of

constructability. The primary reasons appear to be the


difficulty in including

construction expertise early on in the traditional


procurement process, and the lack of

awareness amongst consultants and owners. This is yet


another example of the

drawbacks in the traditional process and encourages the


search for ways to safeguard the

competitive advantages inherent in the traditional process


and yet overcome the major

disadvantage of the lack of construction knowledge at early


stages. We have not made

much progress since 1964 when Sir Harold Banwell said ' .
.in no other industry is the

responsibility for design so far removed from the


responsibility to construct.'
272 Sidwell and Francis

8 Acknowledgments

The Constructability Implementation Task Force consisted of


a group of industry

members of CIIA and researchers from The University of


South Australia and the

University of Newcastle. The three year project is funded


by CIIA and the Australian

Research Council. The contribution of the task force


members and others providing

case study data is gratefully acknowledged.

1 . University of Wisconsin Madison (1992) Project Level


Model and Approaches to Implement Constructability CII
Source Document 82, the University of Texas at Austin

2. Construction Industry Institute (1986) Constructability


a Primer CII, the University of Texas at Austin, United
States, publication 3-1

3. Construction Industry Research and Information


Association (CIRIA) (1983) Buildability: an Assessment.
CIRIA, London.

4. Construction Industry Institute (1987) Constructability


Concepts File CII, the University of Texas at Austin,
United States.

5. Adams, A (1989) Practical Buildability Construction


Industry Research and Information Association (CIRIA)
Butterworth, London.

6. Royal Australian Institute of Architects (1990)


Buildability: the Effect of Design and Management on
Construction. Practice Division Report, July, RAIA,
Canberra.

7. Banwell, H. (1964) The Placing and Management of


Contracts for Building and Civil Engineering Work. HMSO,
London

8. National Economic Development Office (NEDO) (1975) The


Wood Report: The Public Client and the Construction
Industry. HMSO, London
9. Bishop, D. (1985) Buildability: the Criteria for
Assessment. Chartered Institute of Building (CIOB), Ascot.

10. Griffith, A (1985) Buildability: Time for


Re-assessment. Building Technology and Management, Journal
of the Chartered Institute of Building (CIOB), February,
Ascot.

11. Latham, Sir H. (1994) Constructing the Team HMSO

12. Hon, S.L. (1988) A Study of Buildability within a


Project Management System. M.Bldg. Thesis, University of
Melbourne.

13. Griffith, A and Sidwell, AC. (1995) Constructability in


Building and l!,ngineering Projects. MacMillan,
Basingstoke

14. Construction Industry Institute, Australia, (CIIA),


(1993) Constructability Principles File, CIIA,
University of South Australia, Adelaide.

15 Construction Industry Institute, Australia, (CIIA),


(1995) Constructability Executive Summary, CIIA,
University of South Australia, Adelaide.

OPERATIONAL PROBLEMS FACING A

SAMPLE OF CONSTRUCTION FIRMS IN

TRINIDAD AND TOBAGO

T. Michael Lewis

University of the West Indies, St Augustine, Trinidad and


Tobago

Deogratius D. Mugishagwe

Lee Young & Partners, Port of Spain, Trinidad and Tobago

Abstract

This paper presents the results of a survey of some of the


operational problems facing a

sample of construction firms in Trinidad and Tobago. A


comparison is made with
previous studies of operational problems faced by firms in
the industry within the

Caribbean region.

Sommaire

Ce travail present les resultats d'une recherche sur les


problemes courants qui

affrontent un echantillon des firmes de construction a


Trinite et Tobago. Ce travail

compare les problemes courants dans cet echantillon avec


ceux examines auparvant en

firmes a l'industrie aux antilles.

Keywords: Operational problems, surbvey, construction


industry, Caribbean,

Trinidad & Tobago

1 Introduction

The construction industry has often been identified as


important not only because it

provides the basic infrastructure, shelter and other


facilities necessary for economic and

social development, but also because it plays an important


role in employment

generation and in capital formation. Although it is so


important the industry is also

peculiarly susceptibile to problems that can cause


disruption. Because it tends to be more labour intensive
in structure than most other

industries, the construction industry's role as an


employment generator is considered to

be especially significant in these times of high levels of


unemployment. However, this

characteristic also makes the industry particularly


susceptible to labour related
problems. Similarly, the construction industry tends to
involve large quantities of materials

and the supply and management of this flow of materials


itself creates problems, as

The Organization and Management of Construction: Shaping


theory and practice (Volume Two).

Edited by D.A. Langford and A. Retik. Published in 1996 by


E & FN Spon. ISBN 0 419 22240 5.

274 Lewis and Mugishagwe

well as leaving the industry particularly prone to problems


of supply. The industry is also unusual in that most of
its output is custom built, under

conditions that are unique to the specific project. Because


of this, the construction of

any structure always presents a different set of problems.


Since it is also generally

uneconomic to build construction products in advance of


demand, for stock, the

industry is susceptible to problems of fluctuations in


demand. Within the industry, the constructor's task is to
assemble finance, personnel,

materials and equipment to produce a construction product


within a given time frame

and because this takes place within the dynamics of a


changing economic, social and

technical environment, it is a task that is liable to


suffer from problems. One of the most important agencies
regulating the performance of the industry

in any economy is the government. This is because


governments establish policies

which manage the overall economic activity as well as


establish performance codes

which regulate the technical quality of the products of


the construction industry. Thus
when examining the operational problems of the industry,
the role of the government is

likely to be significant. Developing countries, like the


islands of the Caribbean, also face particular

problems in addition to those troubling the industry


elsewhere. For example, there are

problems related to the shortages of skills, questionable


material quality and shortages,

doubtful plant availability, problems of exchange control


regulations and currency

fluctuations and restrictions, as well as problems related


to environmental conditions. Although it is relatively
easy to anticipate what type of problems may occur, it

is important to know what the industry itself, in practice,


perceives as its major

operational constraints, as this may assist in the


structuring of policy to help reduce or

avoid the problems that are responsible in future.

2 Scope

The survey reported here records the responses of a sample


of contractors about

problems they experience in Trinidad and Tobago. The


problems can be allocated to

two broad categories, firstly there are those which are


within the contractor's

jurisdiction such as the effective management of his


workforce, his site, plant and

materials, and his choice of approach to construction.


Secondly, there are the problems

which are beyond control of the contractor, such as the


availability of work, the

prevailing legal and financial frameworks, the level of


government investment in
construction and the capacity of the local materials
supply industry to meet both the

specifications and the demands of the construction


industry. Although it may be possible to identify and
categorise the problems, it is often

difficult to isolate or generalise their effects. For


example, the recent flotation of the

Trinidad and Tobago dollar was clearly beyond the control


of the industry. The

floatation was effectively a devaluation and it had the


effect of increasing the cost of

importing materials and construction equipment as well as


pushing up the cost of

borrowing funds from financial institutions. Whilst this


made life more difficult for the

contracting side of the industry, the devaluation was a


welcome measure for

consultants and other firms who were exporting labour


skills and exporting materials

and components, because they became cheaper and more


competitive in the

international market. Procedurally, the study was


conducted by questionnaires which were sent to a

random sample of construction firms selected from those


listed in the Telephone

Directory's yellow pages. On a number of occasions this


was followed up by an

interview of the respondents in order to extend and


clarify some of the issues raised in

the questionnaire. Although care was taken over


questionnaire design, there remained

shortcomings in the detail and quantification of the


problems identified. For example it Operational problems
facing construction firms 275
was not possible to determine whether the problems reported
were due more to the

inefficiencies of the firm than to problems with the


environment in which they were

operating. Similarly, the problems identified will have


been conditioned by the status

of the respondent within the firm, and it was not possible


to get a person with a

consistent status to answer the questionnaire, with


respondents varying from the

company owner to a relatively junior technician. In order


to try to ensure a reasonable level of response, the size
of the

questionnaire was necessarily limited, which restricted the


number of questions that

could be asked. A brief trial was made with a longer


questionnaire with more

comprehensive questions, but it was quickly rejected by


respondents who in general

were unwilling to spend more than a few minutes answering


the questionnaire. The starting point for any study must
be the types of operational problem that

have been noted previously in the industry in this part of


the world.

3 Previous Studies in Caribbean Countries

There have not been many published reports of studies


undertaken on operational

problems faced by the construction industry in the


Caribbean. Jenkins [1] looked at the

construction industry in St. Kitts, analysed its problems


and made recommendations on

improvements. He found that the construction sector was


mainly devoted to housing

as is the case in many developing countries although the


construction of tourist

facilities and infrastructure was of growing importance.


It appeared that St. Kitts had an ample supply of tradesmen
and labourers but a

shortage of supervisory, technical and managerial


personnel. There was also a

shortage of appropriate equipment. Salaries and wages were


low and it was felt that

this had contributed to the workforce being poorly


motivated. Overall, not

surprisingly, the levels of productivity in the industry


were very low. As far as materials were concerned, the
industry depended on the majority

being imported. This seemed to result in them being either


very expensive or of very

poor quality. The local materials supply sector was poorly


developed, and no efforts

were being made to develop them for large scale commercial


use. Douce [2] looked at the constraints affecting
construction planning on large

scale state-sector projects in Jamaica. He approached the


subject through an analysis of

the Blue Mountain Water Project. One of Douce's key


findings was the overwhelming

importance of the socio-political environment in state


planning. Political concern over

public opinion often dictated planning strategy, and the


short-term horizon of political

life normally led to longer term planning being neglected.


When this was allied to a

shortage of competent planners and managers in the state


sector, poor results were

inevitable.

4 Trinidad and Tobago


The situation in Trinidad & Tobago has been somewhat
different from that in many of

the other countries of the Caribbean. Trinidad & Tobago has


always had one sector

which has been economically active and attractive. In


recent times it has been the

offshore oil and gas industries. The dramatic fluctuations


in the prices of these

resources have led to similar fluctuations in the economic


fortunes of the twin island

state, and the engineering industry has responded in true


Keynesian fashion to these

booms and busts by exaggerating them. Because it is such a


restricted market, the boom conditions served to undermine

the workings of what should have been a competitive market


in the construction

industry. The boom created a huge surplus of work for the


available contractors, who

were able to push up their profit margins on their bids.


The difficulty of finding

276 Lewis and Mugishagwe

substitute contractors led to clients and consultants being


reluctant to enforce penalty

clauses and other punitive contractual clauses. The


collapse in the price of oil in the early 1980s, together
with the effects of

inflation led to a sudden slump in the fortunes of the


industry and the country.

Construction firms had to compete vigorously for the


limited work available, and to

look very closely at their cost structures. A number of


commentators have written about the effects of this cycle
of
economic boom followed by bust, on the construction
industry in Trinidad & Tobago.

For example, Khan [3] characterised the construction


industry in Trinidad and Tobago

in 1986 as being highly fragmented, with a with a large


number of independent

professionals involved in the design and construction of


projects. This occasionally

caused inconsistency in decision making and delays in


project execution. Khan also cited a number of managerial
shortcomings in the local construction

industry which caused operational problems on site. These


included: (a) a lack of effective co-ordination between
client, consultant and contractor. (b) Improperly planned
safety measures leading to site accidents and labour
dissatisfaction. (c) The lack of effective motivation
mechanisms, so that good performance was rarely rewarded
appropriately. (d) The lack of modem management systems,
capable of taking into account the prevailing local
conditions, for the planning and execution of projects.
Andrews [4] discussed the failure to implement
recommendations put forward

by previous studies, during his Keynote Address to a


Symposium on the Construction

Industry in May 1984. He painted a gloomy picture of the


state of the construction

industry. "The depletion of special funds casts a gloomy


shadow on the state of the

industry today. The general contraction of the economy has


led to the decline of

activities in construction. Capital work appropriations


were restricted principally to the

financing of on-going projects. It is significant to note,


that the number of special

funds for long term projects was reduced from 54 in 1982


to 18 in 1983 and ultimately

to one in 1984 from which $2,341 million was appropriated.


Reduced demand, surplus

of some materials and resources, idle capacity, unemployed


labour, retrenchment and

falling prices are beginning to characterise today's


construction sector" . Andrews noted the positive effects
of this financial squeeze being the lower cost

of labour and materials and of experienced professionals in


the industry. However, for

contractors the situation was made much worse because there


was now more serious

competition for the few available jobs. This competition


also meant lower profit

margins as well as more rigid control from clients and


consultants who were well

aware of the ready availability of alternative contractors


if problems should arise. While Andrews concentrated
detailing the economic problems of the

construction industry, Lewis [5] carried out a much


broader review of the causes of the

problems facing the industry in 1984. The most deep seated


of these problems were

those of the legal and bureaucratic structures, many of


which were inherited from

colonial times and had remained unchanged since. The


situation was exacerbated by

the autocratic approach adopted by the then Prime Minister,


Dr. Eric Williams. Dr. Williams had been in power since
Trinidad & Tobago gained independence

some twenty years previously. With the country's new found


oil wealth, during the

1970's, he had advocated development through major capital


projects setting up

primary processing industries. These projects were largely


implemented by joint
ventures set up through government-to-government
arrangements. It was anticipated

that such arrangements would enable Trinidad and Tobago to


obtain better performance

from firms which were beholden to the governments which


nominated them. This system was instituted to avoid the
cumbersome contract letting procedures

which the government itself had instituted. Not


surprisingly, local firms and Operational problems facing
construction firms 277

professionals objected to the implementation of a system


designed to afford preferential

treatment to foreign firms. The construction industry also


faced significant problems in dealing with the

gross inefficiencies of the public utilities. Electricity


and telephone lines were

overloaded and regularly out of commission. Water and


sewerage lines were

constantly being breached causing interruptions to supply


as well as trenched repair

work in the roads, which caused traffic disruptions on the


already congested roads and

also led to further erosion of the road pavement.


Construction operations were also plagued by low labour
productivity and the

common wisdom was that a poor work ethic was the cause.
This was defined to mean

a lack of a willingness to give a fair day's work for a


fair day's pay. Trades unions

were generally unwilling to discuss productivity


improvements instead relying solely

on confrontation to try to raise wage levels, improve work


conditions and increase job

security. In addition to these labour related problems


there was also a significant lack
of sophistication in the managerial skills employed in the
industry. In 1992, Atherly (6) conducted a detailed
analysis of a number of construction

projects carried out in the previous few years in Trinidad


to determine what problems

had been encountered and what their effects had been. His
interest was mainly in the

causes, cost and responsibility for delays, and he


concluded that: (a) The client was responsible for 55% of
delays by cost, and for 47.4% of the total delay time.
(b) The consultants were responsible for 38% of delays by
cost and for 17.3% of the total delay time. (c) The
contractors were responsible for 6% of the delays by cost,
which involved 31.6% of the total delay time. (d) The
weather was responsible for 0.8% of delays by cost, which
involved 2.7% of the total delay time. (e) The approving
and statutory authorities are responsible for 0.2% of
delays by cost which involved 1 % of the total delay
time. AtherJey's analysis showed that there was no direct
relationship between the

time involved in delays and the cost of the delays, and,


furthermore that the clients and

consultants were responsible for more delays than the


contractors. Thus, the

operational problems tended to result more from the


specification and design of the

projects than from factors under the contractors' control.

5 The Survey

A questionnaire was used to gather responses from


construction firms. Two

questionnaires were mailed to a randomly selected sample of


fifty-five construction

firms whose names appear on the Trinidad and Tobago


Telephone Directory out of one

hundred and eight listed. Some of the mailed


questionnaires did not reach the prospective respondents
either due to the improper address given in the Telephone
Directory's Yellow Pages or

due to mail screening at the respondent's organisations.


Telephone follow-ups and

visits helped to improve the response rate. Out of the


eighty questionnaires mailed to fifty five construction
companies

listed in the yellow pages, only twenty four questionnaires


were returned from 18

construction companies. The response from companies was


32.7% of those firms

which had questionnaires sent to them. The response time


for questionnaires returning varied from one month to four

months with intermediate reminders being sent to some of


the respondents. The 18

firms which responded to the questionnaires represent


sixteen percent of the total

companies listed in the telephone directory's yellow pages.

278 Lewis and Mugishagwe

6 Discussion of Results

In order to get worthwhile results it was important to get


a response from persons in

senior managerial positions as others would not have a


clear overview of the firms'

operations, in this regard it was very satisfying to get


75% of respondents as Managing

Directors or Senior Engineers of their firms. As far as


personnel was concerned, two thirds the firms indicated
that they had

moderate to serious difficulty hiring the professional and


skilled personnel that they

needed. This can have serious consequences, as was seen in


the boom days of the
1970's, when unskilled people were put in positions to do
work for which they had not

been trained. However, it does not appear that this


situation has yet been reached

during this economic upturn, because firms have not yet


started bidding up salaries for

qualified people. If the upturn continues, however, this is


a problem that will become

worse before it gets better, as there have been very few


students from T&T studying

civil engineering over the past five years or so (although


freedom of movement for

qualified persons amongst Caribbean states has been


proposed, it is not yet in

existence). This situation is improving but will take


three years to work through the

system. In general, the respondents were satisfied with


the quality of personnel in the

industry. Three quarters of respondents were satisfied with


the performance of local

tradesmen who seem able to perform to the required


standards. This is probably one of

the spin-off benefits of the boom years when a large number


of trademen acquired and

improved their skills. The comparatively lower level of


work now means that only the

best tradesmen are being hired. Half of the respondents


were unaffected by labour union problems and this is

almost certainly as a result of the extensive use of


subcontractors and of the high level

of unemployment in the country. However, this general


satisfaction with the local

labour force is also reflected in the fact that workers


from T&T are used occasionally
by contractors in over 40% of their overseas projects,
despite the additional problems

that are involved in doing so .. Respondents were less


satisfied with the industry consultants, as only just over

one third of the respondents were happy with their


performance. Although there is a

tradition in T&T of the relationship between contractor


and consultant being

adversarial, the situation seems to be exacerbated by the


style of supervision used by

consultants on site. This level of dissatisfaction by


contractors may also be partly

explained by the large number of problems the contractors


reported associated with

contract documentation. Respondents indicated that there


were few problem in hiring or acquiring

appropriate construction equipment. The only problem seemed


to be with the expense

involved with the high hire rates and the high custom
charges levied on imported

equipment. Some 70% of the respondents reported problems


in obtaining the bulk of

construction materials locally. The problems with local


materials mainly involved their

quality, shortages in supply and unreliability of delivery.


The cost of materials sold

locally was also reported to be high enough often to


justify importing significant

quantities of materials, despite their bulk. Half of the


respondents used an average content of more than twenty
percent of

imported materials in their projects. This is a relatively


high proportion of imports, and
it imposed a number of particular problems. Procurement,
for example, requires sound

planning and good administration to ensure that the


materials are available when needed

but are not delivered so early as to cause storage or cash


flow problems. It is a

problem that is only exacerbated by problems with exchange


rate variations and

currency risk. Over 70% of the respondents borrow from


financial institutions in order to fund

their construction projects. This naturally leaves them


susceptible to changes in interest Operational problems
facing construction firms 279

rates and the availability of funds within the banking


sector. This does not currently

seem to be a problem as the vast majority of the


respondents reported no problem in

acquiring working capital, bonds or credit for their


projects. As a general rule, the contracting firms tended
to make heavy use of smaller

sub-contractors wherever possible. There were a number


resons put forward for this,

mostly involving risk-reduction by the main contractor. It


was noted that sub

contarcting work eased cash flow problems, reduced labour


problems with unions and

passed much of the bidding risk onto the


sub-contractor(s). In a very competitive, high

risk economic environment this is a sound strategy for


firms which can afford risk

aversIOn. Nearly 70% of contracts were let on the basis


of the traditional bills of

quantities and 45% were let as 'fixed price' contracts.


'Cost plus fee' contracts were
used on 26% of the projects and 'design and build'
contracts on 22%. This indicates a

fairly traditional approach to contract procurement, though


there was some anecdotal

evidence that the 'design and build' style of project


letting was on the increase,

especially on larger government contracts. On a related


question, it was discovered that over 80% of the
respondents had

encountered significant problems with contract


documentation such as ambiguous and

inconsistent specifications, poor drawings with inadequate


information or mistakes,

and contradictions with other documents. Whatever the


reason, this almost certainly

contributed to the contractors' lack of satisfaction with


the consultants. Anecdotal

reports suggested that this problem may have been a result


of either the consultants

being pressured to produce these documents within too short


a time period or a lack of

adequately trained personnel. It is also possible that


there is incompatibility between

the products supplied mainly from the U.S.A. and the


consultants' preference for

specifications based on the UK data. The liberal use of


various design codes (British,

American, Canadian) and measurement units, metric and


imperial, however, was not

considered a problem by over 70% of the respondents. This


does seem slightly at odds

with the problems reported above with specifications and


other documentation. Half of the construction firms
responding to the questionnaire undertook
construction activities equally distributed throughout
Trinidad and Tobago. Because of

the recent economic upturn, firms did not have much trouble
finding work, but things

had been much more difficult until just a few years ago.
Recognising that one of the

natural responses to problems finding work in one's own


region or country is to look

outside for work, it was of interest to discover how much


work was being undertaken

by contractors from Trinidad & Tobago in other Caribbean


territories or elsewhere in

the world. The respondents indicated that just under 30%


had work outside T&T,

which is quite a high level of involvement in activity


outside one's own country.

However, one contractor still lamented that preferential


treatment was being accorded to

local contractors in those territories, and this was the


main reason why more Trinidad

and Tobago companies were unable to break into overseas


markets. In dealing with the immediate work environment,
the firms seemed less than

happy. The state of roads and volume of traffic


significantly affected the operations of

over 60% of the respondents. This was mainly a problem with


regard to the delivery

of materials. Furthermore, just over 40% of the


respondents' operations were

significantly affected, and a further 50% silghtly


affected by the unreliability of public

utility services. Power fluctuations and interruptions,


poor telephone communications

and water suply problems were mentioned, however, this does


not seem entirely

consistenet with the fact that very few problems with


communication were reported,

except in remote areas which had no reliable wireless or


telephone communications. Some 75% of the respondents
reported that their operations were affected

significantly by inclement weather. Obviously, this


problem particularly affects

outdoor operations such as foundation excavations,


concreting operations and hot-mix

asphalt paving works, however, the figure is higher than


may have been expected as

contractors are familiar with the climate and should


generally be able to make provision

280 Lewis and Mugishagwe

for it. The respondents were generally satisfied with


clients' honouring of their

contractual obligations. This was perhaps surprising, given


that some three quarters of

the respondent's firms did a significant proportion work


for the government, and

government agencies are not normally considered prompt


payers for services received.

The amount of work being done for government was not


really surprising given that

nearly sixty percent of firms felt that the private sector


demand was low to very low. The reported performance of
government agencies in other regards was also

surprising as delays in approvals from regulatory agencies


did not seem to be a serious

problem except for those firms which involve themselves in


fasttracking, design and

build or undertake special projects with continuous


interaction between design and
construction. In summary, the respondents also indicated
the following as being the other

special problems the construction industry faces in


Trinidad and Tobago; (a) Tender award procedures as well
as prequalification procedures and lack of contractor
classifications. (b) Lack of management and supervisory
skills. (c) Extreme fluctuation in construction demand.
Similarly, the special problems facing Trinidad and Tobago
contractors in other

Caribbean countries were: (a) Logistical problems. (b)


Unnecessary red tape and bureaucracy. (c) Resentment,
uncooperative attitudes of the local work force. (d)
Preferential treatment of indigenous and industrialised
world contractors in contract awards over contractors from
Trinidad and Tobago.

7 Conclusion

Construction firms in Trinidad and Tobago face some of the


problems in their operating

environment which have been classified as 'systemic' in


nature (i.e. stemming from the

adoption of inappropriate systems and procedures Okpala et


al [8]). These problems

include: (a) Poor contract supervision and documentation


by consultants (b) Lack of a classification of
contractors and of uniformity in tender award procedures
and criteria. (c) Low and fluctuating demand for
construction products. There is some scope for reduction
of these problems, and indeed some steps

have already been taken. More information is needed before


any conclusions can be

drawn about the performance of the consultants. A


construction industry institute

could easily take on the task of providing guidelines for


the classification of contractors

and providing a unified basis for tender awards. As far as


demand is concerned, the

government is trying to manipulate demand for construction


by scheduling the

commissioning of new works to try to stabilise the quantum


of demand in dollar terms.

The use of tax and other financial incentives have mainly


been used to encourage

construction work of any description at any time. Other


problems which are classified as 'structural' in nature
(i.e. related to the

nature of the indigenous construction itself Ofori [7])


include the following: (a) The dependence on imported
materials. (b) Auctuations in material prices. (c) Low
worker productivity levels and poor contract management.
(d) Inadequate support infrastructure power, roads and
water supply. (e) The disruptive effects of bad weather
conditions. Operational problems facing construction firms
281 These problems are a little more difficult to deal
with. The use of imported

materials can only be reduced if the contract


specifications change accordingly.

Because of quality problems with locally supplied


materials, reducing imports may

have quality implications for clients. The fluctuations in


the prices of materials could, of course, be reduced
thorugh

government controls. However, the government has taken a


policy decision (at least

partly forced on it by the IMF's 'structural adjustment'


requirements) to reduce

governement subsidies on all goods, and without subsidies,


price controls are difficult

to maintain. Much has been written about 'worker


productivity' over the years, and it

seems clear that more of the blame lies with bad management
than with the bad 'work

ethic' of the workers. The support infrastructure is


improving all the time, and recent moves to de
nationalise the public utilities has gone a long way in
this direction. The water and

sewerage authority has recently become the latest utility


privatised, and it is anticipated

that the new private partner (Severn Trent Water Authority)


will help to continue the

improvement of services. Nothing can realistically be done


about the weather. The violence of tropical

storms is difficult to contend with, although larger


projects can use enclosures

effectively to provide a dry work environment.


Improvements to the national drainage

system could help to avoid the floods which are a regular


feature now, and this would

have immediate benefits it is to be hoped that the


expertise provided by Severn-Trent

will help the local authority in this regard.

2 Douce, Courtney, E.A. (1983) Constraints Affecting


Construction Planning on Large-Scale State Sector
Projects. An Analysis with Particular Reference to the
Experience of the Blue Mountain Project Proposals Jamaica.
M.Sc. Project Report, Programme in Constr. Engineering and
Management, The University of the West Indies, St.
Augustine.

3. Khan, Zaffar. (1986) Management and Cost Effectiveness


in the Construction Industry in Trinidad and Tobago.
M.Sc. Project Report. Programme in Constr. Engineering and
Management, UWI, St. Augustine.

4 Andrews, Richardson. (1984) Keynote Address: Symposium on


the Construction Industry Hosted by Trinidad & Tobago
Management Development Centre in collaboration with The
Association of Professional Engineers of Trinidad and
Tobago, May 15-17, 1984, Trinidad Hilton.

5 Lewis, T.M. (1984) A Review of the Cause of Recent


Problems in the Construction Industry of Trinidad and
Tobago. Journal of Construction Management and Economics,
Vol 2, pp 37-48.
6 Atherley, Beville A. (1992) Analysis of Construction
Delays. M.Sc. Project Report, Programme in Construction
Engineering and Management, The University of the West
Indies, St. Augustine.

7 Ofori, George (1991) Programmes for Improving the


Performance of Contracting Firms in Developing Countries:
A Review of Approaches and

282 Lewis and Mugishagwe Appropriate Options. Journal of


Construction Management and Economics, Vol 9, pp 19-38.

8 Okpala, D.C. and Aniekwu, A.N. (1988) The Effect of


Systemic Factors on Contract Services in Nigeria. Journal
of Construction Management and Economics, Vol 6, pp
171-182. INTEGRATING SITE-RELATED ACTIVITIES INTO THE
PLANNING AND SCHEDULING OF CONSTRUCTION PROJECTS

Abstract: This paper first reviews briefly some of the


common methods used by current building

construction firms in their attempt to integrate


site-related activities into the planning and scheduling

of construction projects. These methods are then analysed


and consequently a computer-based model

which seeks to achieve the needed integration is proposed.


The model at present implemented within

a prototype system demonstrates the potential of


integrated knowledge-based and virtual reality

systems in tackling problems associated with the planning


and scheduling of the entire construction

project in general and site-related tasks in particular.

Sommaire: Cet article commence par revoir brievement


quelques unes des methodes usuelles

employees couramment par les compagnies de construction du


biltiment, dans leurs efforts d'integrer

les travaux de site dans la plannijication et l' emploi du


temps des projects de construction. Ces

methodes sont ensuite analysees, et un modele informatique,


qui cherche a obtenir l'integration
demandee, est propose. Le modele a present implemente a
l'interieur d' un systeme prototype,

demontre Ie potential des systemes bases sur une


connaissance integree et ceux de realite virtuelle, a

resoudre les problemes associes arec la' plannijication et


l' emploi du temps du project entier de

construction en general, et des travaux de site en


particulier.

INTEGRATING SITE-RELATED

ACTIVITIES INTO THE PLANNING AND

SCHEDULING OF CONSTRUCTION

PROJECTS

Theophilus Adjei-Kumi

Department of Civil Engineering, University of Strathclyde,

Glasgow, UK

Arkady Retik

Department of Civil Engineering, University of Strathclyde,

Glasgow, UK

Aviad Shapira

Department of Civil Engineering and National Building


Research

Institute, Technion-Israel Institute of Technology, Haifa,


Israel

INTRODUCTION The integration of site-related activities


into the planning and scheduling of construction projects

has received little attention in practice. In practice many


firms either defer them until the

commencement of construction works or provide for them in


a crude manner. Site-related activities as

mentioned here include items and processes which are both


essential and necessary to assist in the

execution of the permanent works, though at times not


directly. Examples of such activities are

scaffolding and gantries, heavy plants and their


operations, form work etc. which would be classified

in this paper as auxiliary activities, and site


accommodation, temporary services, fencing and access

roads which are also classified hereby as on-site


facilities. The effective planning and scheduling of

site-related activities therefore demands a clear


understanding of how they are generated (Illingworth,

1993). Two industrial sutvey works undertaken separately


by McLellan (1994) and Adjei-Kumi (1994)

form the basis of the analysis of current practices. The


former saw 80 actively practising construction

contractors responding to the administration of a


questionnaire on the use of project management

procedute by construction contractors. A much more specific


survey organised by the latter considered

some aspect of McLellan (1994) (i.e. project planning and


control). This second exercise presents a

survey of the current practice of planning and scheduling


of site-related activities as an integral part of

the construction project. Key questionnaire responses of


the second survey and the work of current

researchers are presented and analysed below.

ANALYSIS OF CURRENT PRACTICES In all, 54 sets of the


questionnaire were sent out to building contractors. Out
of this number 26

responded, giving a response rate of about 50%. 12 out of


the 26 responses were found to be very

informative. The relatively low number of responses was


compensated for by the depth and quality of
respondents' answers. Hence these responses should be
considered as indicative rather than

The Organization and Management of Construction: Shaping


theory and practice (Volume Two).

Edited by D.A. Langford and A. Retik. Published in 1996 by


E & FN Spon. ISBN 0 419 22240 5.

284 Adjei-Kumi, Retik and Shapira

representative of the current practices of building


construction firms. Responding firms comprised 10

building and 2 civil engineering contractors.

Rating System To assist in the quantitative analysis of


the responses, a three-level rating system was introduced

in which the highest level of response carried the maximum


points of 5 with the lowest level

attracting no points. Other responses considered as


Moderate attracted 3 points each. These points

were added up for each enquiry in respect of the twelve


respondents, to give the Aggregated Points for

each response (a maximum of 60 and a minimum of 0). Key


responses to the questionnaire are

discussed under their appropriate headings below:

General Items of Operation in the Firms The contractors


were presented with a list of items and asked to indicate
which of them are

undertaken or used by their outfit. The list of items and


the graphical representation of the responses

are as shown in Fig.I. The responses show that much thought


is given to some of the basic procedure

required for the effective planning and scheduling of


site-related activities. For instance, site layout

drawings which are a major concern in the scheduling of


site-related activities are embraced almost as

much as the usual and more traditional construction


programmes and bar charts. Moreover, site visits

were found to be very much a part of the firms' practices.

Importance and Level of Study of the Project Documents


Here the contractors were asked to indicate what they
consider to be important project documents

for the planning and scheduling of site-related tasks and


the depth to which such documents receive

attention from their outfits. The responses are as in


Fig.2. The nature of the responses suggest that an

appreciably high level of importance is given to some


site-related activities through site plans. Quite

apart from the common practice of taking measurements from


the working drawings and reconciling

the values with those in the BOQ, which could be part of


the reason for the trend established in Fig. 2,

the idea of having to study drawings and site plans in


great detail gives the fIrms much more

opportunity to consider site-related activities.

Company Data Here the respondents were asked to indicate


the level of comprehensiveness and the frequency of

revision of their company's data on resources. The result


of this enquiry is presented in Fig.3. The

responses depict that though the available data in the


firms are adequately revised, the level of

comprehensiveness of some of these data leaves much to be


desired. For example, data on plant

which is one of the very expensive site-related items was


found to be lacking comprehensiveness, a

fact which affects its planning on site.

The Use and Update of Documents Responding firms were


asked to indicate their frequency of use and update of
some relevant

activities and documents. The responses of the fIrms are


shown in FigA. Just a few contractors were

identified as frequent users of site layout drawings. Half


of the respondents fail to update these

drawings to reflect the changing form of the site as


construction work proceeds. To some extent this

attitude of fIrms can be attributed to the lack of


convenient tools. On the contrary, method statements

appear to be very much in use and are frequently Updated.

Timing of Operation Under this section, the respondents


were asked to indicate the timing of some vital operations
in

their fIrms. The response to this enquiry is presented in


Fig. 5. The results indicate some operational

lapses in the fIrms at the pre-tender stage of projects.


It is hardly believable that some firms prepare

method statements only after the contract has been secured,


and construction works are to start. This

practice questions the authenticity of the resulting


estimates and schedules. Moreover, the responses

on site layout drawings show that this exercise is mainly


considered only as a pre-tender activity,

presumably when the set-up of the site is drawn to aid in


the estimation of the preliminaries section of

aBOQ. Integrating site-related activities 285 In summary,


the above analysis presents an indication of the existence
of certain work practices

which does not auger well with the effective planning and
scheduling of the totality of the building

construction process. This brings to light the fact that,


attempts by practising firms to plan, schedule

and control site-related activities have not achieved the


desired results. Efforts to consider some site

related activities (e.g. on-site facilities, scaffolds and


plant) via documents like site layout, fall short of
expectations as these are rarely updated to reflect the
changing form of construction sites. Shapira and

Laufer (1993) reached a similar conclusion based on an


extensive study in the United States. It is worth noting
that updating such documents manually is very tedious and
hence the neglect.

With network-based planning and scheduling tools in full


use by construction firms, it is expected that

though the progress of work would be well monitored in


time, the spatial representation of progress is

not taken care of. Planners are therefore left in a state


of abstract visualisation of the perceived spatial

configuration of the work. This aspect of visualisation of


work even becomes much more complicated

when site-related items like plant which are sometimes


dynamic are considered. It is therefore very difficult to
plan and schedule the entire construction project using
existing

practices. The section following would tend to review some


of the related effort by the research

community to promote the integration of all tasks on the


construction site.

REVIEW OF CURRENT RESEARCH Much research work has recently


been undertaken concerning the modelling of the planning
and

scheduling of the entire construction project. Most models


enjoy the current advancement in computer

graphics (CO) and artificial intelligence (AI) tools.


Depending on the dominant tool on which the

development of a particular system was based, models can


be described as CO-dominated, AI

dominated or integrated systems. In the CO-dominated


approach, not much work has been done in respect of
construction planning

and scheduling. Models, more often than not, come in the


form of computer-aided design (CAD)

systems. An example of this model type is Bechtel's W


ALKTHRU (1991) which uses real-time

animated images and links together three-dimensional(3D)


graphics packages and engineering

databases but can also be modified and used for materials,


temporary facilities and equipment layout

on site. Another example is PROVORIJ (psunder & Nekrep,


1994). Some of the problems identified

with this system type is the full responsibility placed on


planners to generate all the knowledge

required for planning and to re-draw the proposed building


using a CAD system. During operation,

the simulation is effected with respect to the building


product erection without considering the

processes (which are mainly site-related activities) which


assist in the erection. Interaction with the

resultant simulation is also very difficult to achieve


using this system type, a situation which makes it

quite unrealistic working with this model type for site


organisational purposes. ~oing by the AI-dominated
approach, models are developed to implement methods in a
manner

similar to an expert's effort to aid in decision making.


The use of heuristic knowledge in these models

is common place. More often than not and where necessary,


solutions are displayed graphically using

simple graphical representations in the form of barcharts,


lines-of-balance etc. Examples of this

approach can be found in the following: aTOP (Kakhonen,


1993), HISCHED (Warszawski and

Shaked, 1995) and Sirajuddin and Mawdesley (1990). MovePlan


(Tommelein and Zouein, 1993) also

attempts to construct a sequence of layouts to span the


entire duration of a project based on an activity

schedule input via a network-based project management


software without indicating the progress of

work. Hence in using this approach, though the progress of


work could be well monitored in time, the

spatial representation of progress is not taken care of.


Users are therefore left to imagine the spatial

state of work progress. Planning and scheduling of the


entire construction process using this model

type can therefore be very difficult even for experienced


planners. The third research area, integrated systems
approach, which attempts to integrate both the product

(drawings and 3D modelling of a building structure) and


the processes (scheduling, cost forecasts etc.)

of a project (Retik, 1993), bears all the advantages of the


previous models and hence appears the most

prospective. These advantages notwithstanding, most of the


main problems identified with the CO

dominated approach persist in this system. An example of


this approach can be referred to in Morad

and Beliveau(1991). This paper presents an integrated


system called KNOW-PLAN which integrates

AI technology with CAD technology to generate and simulate


construction projects.

286 Adjei-Kumi, Retik and Shapira The field of virtual


reality (VR) which has recently developed out of experience
gained in other

related fields, such as computer graphics and


human-computer integration, is also growing in appeal

to the research community as a very useful tool for future


work. VR is an advanced tool for design,

prototyping and implementation of human-system interfaces,


which is centred on 3D computer

generated and simulated environments. The key elements of


this technology and the environment it

creates are the abilities to navigate in 3D, manipulate


virtual objects and their related data and

interact with the virtual environment. The real


significance of VR lies in the nature and structure of

the data underlying the graphics. This technology is aimed


at visualisation and is seen as an extension

of earlier work on simulation, visualisation and animation


(Hendrickson and Rehak, 1993, Stone,

1993). An application using VR techniques especially for


construction planning and scheduling is yet

to be developed. Such is the nature and direction of


current research which makes bare the fact that though much

has been achieved through the use of computer-based models


in construction planning and

scheduling, the issue of realistic representation of the


entire project picture in a way which assists

planners during planning and monitoring of work progress


is yet to be well addressed. A proposed

approach towards this end is described in the section


following with more emphasis on site-related

activities' integration.

PROPOSED APPROACH This section outlines essential


attributes of a computer-based model still under
development

which seeks to address the problems in existing practices


and models, through the intelligent

simulation and visualisation of the entire construction


project.

General Characteristics of Proposed Computer Implementation


Model The main idea behind this model is to plan and
schedule the entire construction project employing

knowledge-based simulation of the construction progress.


The approach is based on the creation of
real 3D pictures of the project's building structures and
site, and subsequent visual simulation of the

construction process. The main components of this system


are presented in Fig.6. Operations of the

model are: Plan formulation (generation of construction


and site-related activities and their sequence,

schedule generation and resource allocation etc.) via


automated or manual means, automated

(intelligent) and manual (non-intelligent) mapping of


activities and facilities to their appropriate

graphical representations and the projection and simulation


of the progress of work in a virtual

environment on-screen based on the project schedules. In


this approach plans are either generated automatically by
the knowledge-based system after the

user have input certain information defining the project in


question or prepared manually and

supplied to the system via a project network-based


scheduling tool. Automatically generated solutions

can also be relayed to the scheduling tool for schedule


preparation and thus giving planners the

opportunity to make any changes whatsoever to their plans.


With the view of visualising the progress

of work, the system interface provides the linkage between


items in the schedules and a prepared

library of graphical representations of elements on site.


Using the system, this linkage is achievable

manually and antomatically through a non-intelligent


(Visual Basic Interface) and an intelligent

(knowledge-based system) interface respectively. These


mapped items are then projected onto screens

via a visualiser at a pace dictated by the pre-prepared


schedules.
DISCUSSION

Site Organisation The organisation of resources present on


a construction site changes as construction works

proceed according to planned schedules. These schedules


invoke resources onto sites as and when they

are required and take them off after they have served their
purpose. Some of these resources can be

classified as long-term or short-term depending on their


duration on site, dynamic or static, or

activity-independent or dependent. Moreover the path and


location at any particular time in relation to

the associated work, of dynamic resources (for example, a


rail-mounted crane) would have to be well

monitored to offset interference with other plant, laydown


areas etc. Integrating site-related activities 287
Monitoring all the above and many other resources therefore
demands an interface which permits

the visual simulation of the entire construction project


based on the planned schedules and facilitates a

very high level of interaction between the user and the


system. The proposed system demonstrates this

interface and its importance especially in relation to


site organisation.

Facilities and Activities Unlike the planning and


scheduling of construction activities which has received
the attention of

much research work, the planning and scheduling of


site-related activities is yet to be addressed

comprehensively. To integrate these two in a realistic


manner, construction activities should be

considered as the basis for the planning and scheduling of


site-related activities. During this process,

facilities needed to support construction operations must


be identified, their sizes and shapes
determined and their positions within the boundaries of the
site located. Examples of such facilities

are batch plants, warehouses, changing rooms, lay down


areas, fabrication areas etc. Care needs to be

taken in determining their duration on site (Le. some


facilities depend on certain activities or

construction phases, some on the availability of certain


materials, some on the total project work or

the height of operation above the ground). All these must


be taken into account during activity/facility

generation and scheduling. To automate such a system


demands the acquisition of certain

technological and heuristic knowledge which would generate


the list of activities and facilities

required for a particular project and establish their order


and sequence and possibly their duration.

Scheduling Method Like any other professionals, planners


have to select the right tool for the job, a choice which
is

generally dependent on the type of project. Considering the


available scheduling techniques, the

network analysis method has been found to lend itself most


readily to comprehensive scheduling of

the actual and auxiliary activities and on-site facilities.


Quite apart from being appropriate for

resource analysis, networks lend themselves well to


software applications. This system utilises a
network-based construction management software to assist
users to input

their project data manually. With this, firms would still


be reaping from investments made in

network-based systems and planners will still be using some


of the applications they are very much

used to without the need for any special training. With


this choice of scheduling technique, on-site
facilities are included in schedules as hammock activities
and auxiliary activities as normal activities.

These tools are also efficient as far as resource


allocation, levelling and optimisation and the

production of reports are concerned. However during


operation, the system allocates default resource

values (if the user fails to provide them) which form the
basis of activity duration determination.

Controlling and Monitoring Bar charts tend to be an


excellent tool adopted for communicating schedules to
users. On these

charts the actual project status at any control date is


represented alongside the planned status, and

deviations are clearly displayed. The presentation of any


deviations from plans are quite difficult to

understand in a spatial context using bar charts. To


improve on these presentations, the proposed

system uses 3D computer graphics which promotes the viewing


of the project on-screen as it is in

reality. At a user specified date, the actual and expected


status of activities are displayed graphically

using different colours. By this, planners would have the


opportunity to view deviations at their points

of occurrence.

SYSTEM PROTOTYPE The system prototype has being developed


to serve as an environment for the planning of multiple

residential units (low-rise and multi-storey). Emphasis is


placed on realistic graphical presentation

and the development of an interface suitable for


construction industry professionals (see example of

output in Appendix A). A library of the graphic elements to


represent construction activities and plant

has been developed via the use of Superscape's Shape


Editorl. Automatic incorporation of these

lShape Editor is a Superscape VRT 4.0 facility used to


create 3D shapes which can be colow

duplicated and transformed. These shapes are then used to


furnish the Virtual World.

288 Adjei-Kumi, Retik and Shapira

elements into the construction process, assigning


intelligence to the objects, as well as identifying the

appropriate scenario is under development. The prototype


system's interface was made possible

through the use of a non-immersive Desktop VR toolkit,


Superscape VRT 4.0 2 , which provides

dynamic interaction with a virtual project. Appendix A


presents some of the prototype system's outputs. I and II
show the fIfth and seventh

weeks of the erection of a three-storey building using


industrialised construction methods. The

pictures also show some accommodation on site, site fence,


a crane running on rails and the general

system interface. Simulation can be played forward,


backward etc. III is just another view of work

progresses at week seven bringing into picture site access


roads. IV displays some aspects of the

expected state of work on site during the thirty-second


week by highlighting among other things, the

arrival of a truck-mounted concrete mixer. Below is a


brief description of the knowledge-base system in use and
the mode of visualisation of

this prototype system.

Knowledge Base It is worth noting that the main objective


of the proposed system goes beyond just the visual

simulation of the construction process. The additional


objective here is to attach some intelligence to
the whole process. Object-oriented technology appears to
facilitate a near-reality and structured

representation of this knowledge and hence its choice in


the development of the prototype. One of the

most important features of this technique is the coupling


of data and operations. The association of

knowledge to similar objects is simplified by putting these


object in groups. It is also possible to

represent the behaviour of each object using procedures


called 'methods'. This structure therefore suits

the ongoing processes on a typical building site (i.e. a


series of activities working together to change

the form of a building site into the proposed building


facility). Modelling such an environment

therefore demands information about the product (e.g.


building elements, components, facilities) and

about the ~cess (i.e. construction operations). The


knowledge-based system, organised within

Kappa-PC objects is currently under development.

Visualisation Visualisation of the construction progress


can be effected in a virtual environment developed by a

non-immersive or desktop VR system. Such an environment


appears to be ideal for simulating site

operations as it would allow activities and equipment


within the site to be modelled. Using this

system, spatial planning as far as site-related activities


are concerned will be facilitated. Construction

sites can be viewed on plan (as in site layout planning)


and the locations of facilities well determined

via the constant simulation of the work progress.


Interference detection between two or more facilities

would be promoted using this interface and any correction


effected with the least of effort. The use of the dynamic
visual status of all project activities during the entire
construction process

requires the presentation of a comprehensive picture of the


project, including the new construction

(buildings), landscape development and site organisation


with plant and facilities, and their schedule.

CONCLUSION This paper has identified the methods used by


practitioners in planning and scheduling of site

related tasks and outlined a computer-based model which


would achieve the needed integration of the

actual project and the site-related activities. The paper


proposes the use and development of a model

with an added attribute of aiding practitioners to


visualise not only the actual building works, but also

the progress in the site organisation, as well as using a


virtual reality interface. In this respect the

planners do not only observe simulated projects under


differing scenarios but can also interact with a

virtual project by moving equipment, plant and facilities


about to their requirements. 3D dynamic presentation
facilitates the visual validation and simulation of the
project progress

and creates new possibilities for the planning process


which are not available by conventional

methods.

2 Superscape VRT 4.0 is a Virtual Reality Toolkit of


Superscape Ltd.

3 Kappa-PC is an object-oriented applications development


system of IntelliCorp Ltd. Integrating site-related
activities 289

Acknowledgement

The authors wish to express their profound gratitude to all


the construction finns who responded to

the questionnaire and to Douglas Gourlay and Edward Coutts


(both Research Assistants) who helped
Adjei-Kumi, T. The integration of Site-related Activities
into the Planning and Scheduling of

Construction Projects. MSc Thesis, University of


Strathclyde, 1994.

Hendrickson, C. and Rehak, D.R. "The Potential of a


'Virtual' Construction Site for Automation

Planning and Analysis", Proceedings of the 10th ISARC


Conference, Houston, 1993, pp. 511-578.

Illingworth, J. R. Construction: Methods and Planning,


First Edition, E&FN Spon, London, 1993.

Kahkonen, K.E.E. "A Model for Building Construction


Project Scheduling", CIB-65, Trinidad W.I.,

1993, pp. 453-462.

McLellan, R. The Use of Project Management Procedures by


Construction Contractors, PhD Thesis,

University of Strathclyde, Glasgow, 1994.

Morad, A.A. and Beliveau, Y.J. "Knowledge-Based Planning


System", Journal of Construction

Engineering and Management, ASCE, Vol. 117, No.1, March


1991, pp. 1-12.

Psunder, M. and Nekrep, P.M. "Computer Aided Construction


Site-Layout Design", International

Conference on Investment Strategies and Management of


Construction, September 20-24, 1994,

Croatia, pp 375-380.

Retik, A. "Visualisation for Decision Making in


Construction Planning", Visualisation and

Intelligent Design in Engineering and Architecture, 1993,


Computational Mechanics Publications, pp

587-599.

Shapira, A. and Laufer, A. "Evolution of Involvement and


Effort in Construction Planning
Throughout Project Life", International Journal of Project
Management, Vol. 11, No.3, August 1993,

pp.155-164.

Sirajuddin, A. and Mawdesley, J.M. "The Automation of


Project Resource Scheduling Using Site

Layout Mapping", 7th International Symposium on Automation


and Robotics in Construction, Bristol,

June 5-7,1990, pp.535-542.

Stone, RJ. "Virtual Reality in the Services of Transport,


Civil Engineering and Construction", SERC

Conference, September 1993, pp. 327-336.

Tommelein, 1.D. and Zouein, P.P. "Interactive Dynamic


Layout Planning", Journal of Construction

Engineering and Management. ASCE, Vol. 119, No.2, June


1993, pp. 266-287.

W ALKTHRU PC Version 1.0, 3D Simulation, Bechtel's


Software.Inc, User's Manual, 1991.

Warszawski, A. and Shaked, 0. "Knowledge-based System for


Construction Planning of High-rise

Buildings", Journal of Construction Engineering and


Management, ASCE, VoU21, No.2, June,

1995,pp.172-182.

d h

. S

t n

n t

. = : ; N e t w o r k . . . . . , [ C O t l " f ) u t l . :
! r A p p J . o W B ' 0 C o n s . S c h t ! d . e B a r c h
a r t s ~ E S i l l ~ S i t e b l V . F o m l S n e P h o t
o . J S . V i s i t ~ o t o 2 0 3 0 4 0 5 0 6 0 A u r e g a
t e d P o i n t s F i g . 1 G e n e r a l i t e m s o f o p
e r a t i o n i n F i r m s I r v i a h : : r i a l s J ~ L
a b o u r • : " P l n n t I I Q f h c a d s 1 0 I L I I I I
I I 2 0 3 0 A g g r ~ g l l t ~ d P o i n t s ~ 4 0 5 0 o C
o m p r e h e n s i v e n e l l S • F n : q u e n c y F i g
. 3 C o m p a n y D a t a : C o m p r e h e n s i v e n e s
s a n d F r e q u e n c y o f R e v i s i o n B o q : J I .
S p e c s . ~~ D n l l n S S . Q " . 0 ' S . P l a n . t C
. o f I I I I I 1 0 2 0 3 0 4 0 5 0 6 0 A g g r ~ g l l k d
P o i n t s F i g . 2 I m p o r t a n c e a n d L e v e l o
f S t u d y o f P r o j e c t D o c u m e n t s S . V I S f
t S . V I S ' S ( ) I S ~ c e S i l l . ~ 2 P i n g . 0 . "
~ S I . D l 0 M ( . 1 h . M c t . h . S U l l l t S t n l l
l C o n s . S c h e d . o 2 0 4 0 6 0 2 0 4 0 6 0 8 0 1 0 0
A u " ' g a w d P o i n t s P e r c e n t a g r F i g . 4 T
h e U s e a n d U p d a t e o f D o c u m e n t s F i g . 5
T h e T i m i n g o f O p e r a t i o n s N o t e S . V i s
i t = S i t e V i s i t , S L D = S i t e L a y o u t D r a
w i n g s , L O B = L i n e o f B a l a n c e , C o m p u t
e r A p p l . = C o m p u t e r A p p l i c a t i o n s , M
e t h . S t m n ! . = M e t h o d S t a t e m e n t , S i t
e I n v . F o r m = S i t e I n v e s t i g a t i o n F o r
m , O I S P i n g . = O n s i t e P l a n n i n g , O l h e
a d s = O v e r h e a d s , C . o f C . = C o n d i t i o n
s o f C o n t r a c t , S . P l a n = S i t e P l a n , D r
w g s = D r a w i n g s , S p e c s . = S p e c i f i c a t
i o n s , B O Q = B i l l o f Q u a n t i t i e s , C o n s
. S c h e d . = C o n s t r u c t i o n S c h e d u l e C O
N S T R U C T I O N S C H E D U L E C O N S T R U C T I O N
P R O J E C T I N F O R M A T I O N E 1 1 ' C o n s t u c t
i o n s c h e d u l i n g t o o l ( e g . P r i m a v e r a
P r o j e c t P l a n n e r ) I n f o r m a t i o n e n t e
r e d e i t h e r m a n u a l l y ( u s i n g s c h e d u l
i n g t o o l ) o r s u p p l i e d a u t o m a t i c a l l
y t o s c h e d u l i n g t o o l b y k n o w l e d g e b a
s e S Y S T E M I N T E R F A C E I N T E L L I G E N T I N
T E R F A C E O b j e c t O r i e n t e d K n o w l e d g e
B a s e ( U s i n g K a p p a P C d e v e l o p m e n t A p
p l i c a t i o n ) C o n s t r o c t i o n a c t i v i t i
e s ' r e p r e s e n t a t i o n R e p r e s e n t a t i o
n o f c o n s t n l c t i o n m e t h o d s H e u r i s t i
c s B i d i r e c t i o n a l l i n k a g e t o e x t e m a
l a p p l i c a t i o n s A u t o m a t e d a c t i v i t y
g r a p h i c s l i n k a g e N O N I N T E L L I G E N T I
N T E R F A C E V i s u a l B a s i c I n t e r f a c e ( U
s i n g V i s u a l B a s i c T A l 3 . o d e v e l o p m e
n t a p p l i c a t i o n ) M a n u a l l i n k a g e o f a
c t i v i t i e s t o t h e i r g r a p h i c a l r e p r e
s e n t a t i o n s D e v e l o p m e n t o f u s e r s y s
t e m i n t e r f a c e F i g . 6 T h e m a i n c o m p o n
e n t s o f t h e P r o p o s e d S y s t e m G R A P H I C
S S U B S Y S T E M G r a p h i c a l L i b r a r y o f A c
t i v i t i e s ( U s i n g t h e S h a p e E d i t o r o f
S u p e r s c a p e ' s V R T o o l k i t ) P r e p a r e d
l i b r a r y o f g r a p h i c a l r e p r e s e n t a t i
o n o f c o n s t r o c t i o n a c t i v i t i e s O U T P
U T V I S U A L I S E R P r o j e c t i n a v i r t u a l e
n v i r o n m e n t u s i n g S u p e r s c a p e ' s V R T
V i s u a l u s e r

292 Adjei-Kumi, Retik and Shapira APPENDIX A Examples of


project pictures from implemented prototype. (I) (II)
(Ill) (IV)

CASH FLOW TRENDS FOR

INFRASTRUCTURAL WORKS IN

RESIDENTIAL DEVELOPMENTS

S. Singh

National University of Singapore, Singapore

Abstract

This paper discusses the established cash flow trends


(profiles) for major

infrastructural works, based on the most recently completed


projects by Public

Utilities Board, Singapore (electrical cables and


gaslines) and Ministry of

Environment, Singapore (drainage and sewer lines). Based on


the s-curves derived,

cash flow projections for any given contract and market


conditions can be arrived at

for any future projects from the view point of clients,


contractors and developers.

Kevwords: Cash flow, financial planning, building services,


external works,

inf;astructural works. construction.

Sommaire
Le present papier discute les tendances en vigueur des
liquidites pour les

travaux infrastructurels majeurs, sur la base des projets


les plus recents

conduits a terme par Ie Public Utilities Board, Singapour


(cables electriques et

conduites de gaz), et par Ie Ministere de l'environnement,


Singapour

(evacuation des eaux et egouts). Basees sur les derivees de


courbes en S, les

projections de liquidites pour tout contrat et sous toutes


conditions du

marche peuvent etre atteintes pour n'imporle quel projet


futur du point de

vue des clients, des entrepreneurs et des promoteurs.

1 Introduction

Amongst all the construction resources, cash flow


management is most important

since from the contractors' considerations relatively more


construction firms appear

to fail through lack of liquidity than do so by inadequacy


of planning and control of

other resources. Cooke & Jepson [1] and Harris & McCaffer
[2] have discussed the usefulness of

s-curves and Singh & Phua [3] have shown the importance of
establishing s-curves

for different categories of building projects since their


profile varies quite

substantially from one building type to another Cash flow


profiles for infrastructural works in buildings have never
been reported

to have been established, the author therefore made an


attempt to establish the same.
This paper therefore discusses the nature and general
characteristics of

The Organization and Management of Construction: Shaping


theory and practice (Volume Two).

Edited by DA Langford and A. Retik. Published in 1996 by E


& FN Span. ISBN 0 419 22240 5.

294 Singh

infrastructural works, data collected, mathematical models,


cash flow profiles, and

comparison between electrical cables, sewerlines, gaslines


and drainage works. The auth.or was keen to develop
profile for waterlines as well, however, due to

the difficulty of getting access to the past records of


such works, the same could not

be established.

2 Alternative Methods for Cash Flow Projections

Broadly speaking there are two methods for cash flow


projections of constf].lction

projects viz. cash flow based on programme planning


techniques and cash flow

projections based on value-time envelopes or standard


s-curves [1,2,4].

2.1 Cash Flow Projections Based on Programme Planning


Techniques

Normally for all medium and large sized construction


projects, a master-program is

developed for executing the construction project using any


convenient technique such

as bar charts, network based on CPM or PD, line of balance


etc. Based on this

program cash flow projections can be developed by


considering the cost of various
resources needed for different operations and other
information such as contract and

credit conditions of material suppliers, subcontractors


etc. A full explanation of the

calculations based on this approach is exhibited elsewhere


by Singh [4].

2.2 Cash Flow Projections Based on Standard S-curves

Past cost information of completed projects have shown its


immense value in cost

planning during the development of design for approximate


cost estimation,

developing cost plan and for use in bidding after


necessary adjustment etc. Such an

information can also be utilised for establishing the cash


flow trends in different types

of projects and these in turn can be utilised for cash flow


planning of construction

projects from the view point of clients, contractors and


developers. Based on the

trends, standard cumulative percentage of value versus


cumulative percentage of time

curves (s-curves) can be evolved.

3 Nature and General CharacteristiCs ofinfrastructural Works

The construction of infrastructural works like drainage,


sewerlines, gaslines and

electrical cables are external works relating to buildings


which are highly susceptible

to many uncertamtles. For instance, weather conditions,


unforeseeable ground

conditions, terrain and topography of site, and the nature


of works. As the construction of infrastructural works is
completely exposed throughout

the entire project duration, flooding during rainy season


necessitates frequent

pumping of water and unnecessary making good. Likewise,


high water table coupled

with high tide (Singapore environment) can cause flooding


to excavated trenches in

certain areas. Cash flow trends for infrastuctural works


295 The congestion of underground services like electrical
cables, telephone lines, sewerlines, gas and water mains
under roads impose great difficulties especially in
creating space for underground cable installations. In
electrical installations, tunnelling work is required in
order to construct the pipe system to under cross
underground services, drains and culverts. The congestion
of the underground services is aggravated by the
constraints of having to install services at least 2 metres

away from existing trees. This requires services to be


installed close together which

results in overcrowding of the same. Diversion of


sewerlines from their proposed path of works to avoid large
cables

and other obstructions (boulders) is relatively common.


Laying works, especially cables in the city centre must be
carried out at ni'ght to

minimise traffic obstructions and noise pollution. This


requires sectional completion

which impedes the progress of work. Drainage construction,


like large culverts and canals can be an onerous task when

diversion of roads and traffic flow is essential,


especially within a city area. Diversion

of roads and traffic flow further impedes work progress.

4 Data Collection

Table 1 shows the sample size of various types of projects


used in the computation of

s-curves (Figs. 1 to 4). Table I. Sample Size of Completed


Projects Analysed Source Project Type Ministry of
Environment, Singapore Drainage Public Utilities Board,
Singapore
5 Mathematical Equations Sewerlines Electrical cables
Gaslines Sample Size 20 12 16 25

Based on the data collected, the best-fit mathematical


equations were established

between the cumulative percentage of value and cumulative


percentage of time for

various types of works and the same are shown in Table 2.


The general form of the

polynomial established was of the form Y = aX + bX 2 +


cX 3 + -----------+ Z where Y X a b Cumulative
percentage of value Cumulative percentage of time First
degree coefficient Second degree coefficient

296 Singh c = Third degree coefficient, etc z = Constant


The coefficient of correlation varied between 0.7103 to
0.9658 (Table 2) for

various works. Using the mathematical models,


computer-based soft wares can be written and

perfected to develop the cash flow projections as already


shown by Singh [5],

Trimble [6] and Tucker [7 to 9].

Table 2. Best-Fit Polynomials for Infrastmctural Works


Category of Project Electrical Sewer Gas Drainage cables
lines lines

First degree coefficient 0.3083 0.7339 -0.6036 10654

Second degree coefficient 2.4440 0.0123 15.6214 0.3136

Third degree coefficient -1.7774 1.8957 -50.7056 -0.1918

Fourth degree coefficient -1.6270 63.6506 0.0023

Fifth degree coefficient -27.5320 -0.2008

Constant 0.0375 -0.0212 -00017 0.0067

Coefficient of correlation 0.9384 0.9658 0.7103 0.9552

Standard error of estimate 0.3725 0.3598 0.4838 0.3359


Coefficient of detemlination 0.8806 0.9327 0.5055 0.9124

6 Cash Flow Profiles

Cash flow profiles for electrical cables, sewerlines,


gaslines and drainage works were

established for the data collected based on the established


procedures by Singh [4]

and the results are shown in Figs. I to 4 for the above


services. In each case,

statistical mean curve has been shown which in turn can be


used for projection of

cash flow for the respective works based on any given


contract and market

conditions.

6.1 Cash Flow Trends for Electrical Cables

The gradient of the statistical mean curve (Fig. I) shows


relatively constant rate of

progress at the initial about one-third of the project


duration. The rate of progress

increases when cable installation works commence


afterwards. Two projects (shown

dotted) displayed an extremely wide variance band from the


mean curve and the

remaining project curves.

6.2 Cash Flow Trends for Sewerlines

Fig. 2 displays the trends for sewerlines. The mean curve


has the usual

characteristics of an s-curve. Like electrical cables, the


progress rate is relatively

uniform at the beginning of the project, increases as the


project progresses,

presumably due to the installation of sewerpipes, and


consequently tails off nearing to
the completion stage. Cash flow trends for infrastuctural
works 297 In this case, the individual curves which are
identified as exceptional are the two curves below the
mean curve which deviate substantially from the other
project curves. 6.3 Cash Flow Trends for Gaslines

Fig. 3 exhibits a distorted mean s-curve for gaslines. The


double hump s-shape may

be attributed to the return of excess materials by the


contractors during the project

duration. It is the practice of the Ministry of


Environment (Gas Department) to issue

materials at the commencement of the project, so that


excess materials returned can

simply be credited back to the Board's account during the


updating process. This

explains the slow down in the rate of progress at the


35%-60% stage of the ptoject

duration. The sudden escalation of rate of progress during


the 60%-90% stage of

project duration can be attributed to the high value of


cathodic protection for

gaslines. Although cathodic protection is extremely


expensive, it is needed in certain

gasline installation

6.4 Cash Flow Trends for Drainage

Fig. 4 shows the best-fit mean curve for drainage works. It


is almost linear for about

the first half of the project duration. This is in distinct


contrast to mean curves in

other figures.

7 Comparison of Cash Flow Profiles

Fig. 5 shows the cumulative percentage mean value-time


trends for various works. It
can be seen that all works exhibit some consistency in
trends, except gaslines which

demonstrated a distorted s-curve. Initially, due to


mobilisation and arranging construction resources, the
cumulative

percentage of value is low as compared to the corresponding


cumulative percentage

of time, say upto about first quarter of the project


duration. Later, all works, more

or less follow the same trend except gaslines which showed


a distorted s-curve. Further, during about the first half
of the project duration, the rate of work done

for drainage works is greater than electrical cables. This


is due to the high value

work content required in the former for excavation, piling


works, machineries and

dewatering. However, between about 50% to 85% of the


project duration, the rate

of work done for drainage works slowed down, while


electrical cables and sewerlines

picked up at a faster rate. This may be the stage where


electrical cables are delivered

at the site and installed. Prior to completion, all the


three curves tailed off at different

rates, depending on the value of the ancillary works. At


first glance, gaslines deviates substantially from the
other services. The most

appropriate explanation for this is the highly specialised


work involved in installing

gas pipes compared to other types of projects. In addition,


the practice of the

Department in crediting accounts for excess materials


returned is unusual among the

other projects. Consequently a distinct double s-curve is


formed for gaslines.

298 Singh

8 Applications

Based on the mathematical polynomials established or


otherwise by using the

statistical mean curves (Figs 1-4), the cash flow


projections for electrical cables,

sewerlines, gaslines and drainage works can be established


using the contract and

market conditions from the view point of clients,


contractors and developers [I to 4].

9 Concluding Remarks

It is hoped that the established profiles for


infrastructural works in the form of mean

s-curves will be found useful for cash flow projections of


projects related to electrical

cables, gaslines, drainage and sewerlines in residential


developments The established

mathematical equations (Table 2) or mean s-curves (Figs.


1-4) can be used for cash

flow projections from the view point of clients,


contractors and developers

1. Cooke, B. and Jepson, W.B. (1987) Cost and financial


control jar construction firms. The Macmillan Press Ltd.,
London.

2. Harris, F. and McCaffer, R (1986) Modern Construction


Management. The Granada Publishing Ltd, London (UK).

3. Singh, Sand Phua, W.W. (1984) Cash flow trends for high
rise building projects Proceedings oj the 4th
International Symposium on Organisation and Management oj
Construction, Waterloo (Canada), pp. 841-54.

4. Singh, S (1995) Managing cash flow in the construction


industry. Proceedings oj the Inter-Faculty Conjerence on
Effective Management oj Construction Projects, compiled by
School of Building and Estate Management, pp. 1-35.

5. Singh, S. (1995) A computer model for financial resource


planning of high rise building projects. Proceedings oj
the International Cmiference on Managing Construction
Worldwide, London, pp. 337-48.

6. Trimble, E.G. (1982) Microcomputers in construction


management. BlIilding Technology and Management, Vol. 2,
No.4, pp. 11-13.

7 Tucker, S.N. (1984) Building project cash flows and life


cycle costing Proceedings C!f the International Cmiference
on High Rise Construction Techniques and Management jor
the I 990s, Singapore, ClB, National University of
Singapore, etc., pp. 48-61.

8 Tucker, S.N. (1986) Formulating construction cash flow


curves using a reliability theory analogy. Construction
Management and Economics, Vol. 4, No I, pp. 179-188

9. Tucker, S.N and Rahilly, M. (1988) A construction cash


flow model. Australian Institllte oj Building Papers, 3,
pp. 87-99. Cash flow trends for infrastuctural works 299
CULMULATIVE % VALUE 120

300 Singh CUMULATIVE % VALUE

150

100

50 10 20 30 40 50 60 70 80 90 100 CUMULATIVE %
TIME ~ BEST FIT EXCEPTION

Fig. 3. Cash Flow Trend for Gaslines CULMULATIVE % VALUE

120

Fig. 4. Cash Flow Trend for Drainage 120 100 80 60 40


20 CUL\1 ULA TI VE % VALUE ~ /. ~~ ~.~ / ~ ~ 10 20 30
Cash flow trends for infrastuctural works 301 ..~ ~~ 40
50 60 70 / ~ / / 80 90 100 CUL\1ULATIVE % TIME ~
ELECTRICAL CABLES SEWERLINES ~GASLINES -DRAINAGE Fig_ 5 .
Comparison of Cash Flow Profiles
1 Project procurement

1. Dwyer, 1. and Kent, C., (1993) A Re-examination of the


Determinants of Australia's Imports, Reserve Bank of
Australia, Canberra.

2. Runeson, G. and Uher, T., (1995), Aspects of Imports


into the Australian Construction Industry, School of
Building Occasional Papers, UNSW, Sydney.

3. Lindert, P. H., (1991) International Economics, Richard


D. Irwin, Homewood, III.

4. ABS (1994) Australian National Accounts: Input-Output


Tables Commodity Details 1989-90, Commonwealth of
Australia, Canberra.

5. ABS (1994) Australian National Accounts: Input-Output


Tables 1989-90, (Commonwealth of Australia. Canberra.

6. Rawlinson, (1994), Australian Construction Handbook,


Rawlhouse, Sydney.

7. Gray, H. P., (1976), A Generalised Theory of


International Trade, Mcmillan, London.

8. ABS (1993) Foreign Trade Australia: Merchandise Exports


and Imports, Commonwealth of Australia, Canberra.
PROCUREMENT OF A MOTORWAY A CASE STUDY BengtHansson
Department of Construction Management, Lund University,

Lund, Sweden Abstract When procuring a motorway of 18 lan


in length in Sweden afunctional contract was chosen,
(design and construction contract with extended operating
responsibility) i.e. the client procures the construction
of a motorway with associated operation and maintenance
for a seven year period after the project's completion. The
chosen procurement form was judged to be the most
favourable long-term solution for the road authority and
society. The procurement was primarily based on the land
acquisition plan as the only source of information. The
motorway was built between 1992-1994. An evaluation shows
that a functional contract gives the possibility of an
early build-. ing start, short construction time and
production adapted design. Overall production costs with a
traditional construction contract have, in this case,
been judged to be barely 8% higher than with the chosen
functional contract. If traffic benefit is included in
the conclusion due to completion being two years earlier
the cost for the general contract form is over 19 %
higher than the chosen functional contract form. Keywords:
Functional contract, motorway, procurement. Sommaire Des
sommes importantes ont ete investi dans l'aggrandissement
du reseau routier suedois, en vue de favoriser la
productivite du pays. Une autoroute d'environ 18 lans a,
de 1992 a 1994, ete construite pres de Nyk5ping. Lors de la
negociation avec les partenaires a ete choisi un contrat
dit "de fonction" (l'entreprise assurant 1a construction
dans sa totalite ainsi que la maintenance de l'ouvrage) ce
qui veut dire que Ie maitre d'ouvrage a achete une
autoroute faite pour une certaine densite de circulation
et avec cela l'entretien et la maintenance de la
construction pendant 7 ans. La forme du contrat choisi, a
ete considere comme, a long terme, la meilleure solution
pour Ie maitre d'ouvrage ainsi que pour la societe
d'etat. Le contrat a ete signe, en principe uniquement,
sur la base du plan de travaux. Une evaluation du projet a
ete realisee, suivant les techniques, la duree des travaux,
lorganisation et leconomie, pour obtenir une comparaison
avec un contrat de construction traditionel. Cette
evaluation montre que Ie "contrat de fonction" a donne'
les possibilites de demarrer Ie chantier plus vite,
d'ecourter sa duree et d'en planifier mieux la production.
Le cout total de la production avec Ie contrat de fonction
a ete estime a 8% moins cher quavec Ie contrat
traditionel. Si Ie benefice de circulation, 10rsque 1'0n
termine Ie chan tier deux ans plus tOt, etait inclus dans
les calculs de couts, Ie contrat de fonction serait 19,3%
moins cher (46 millions de couronnes suedoises) que Ie
contrat traditionel.

1 Introduction

1.1 Background

With the intention of developing procurement fonus and road


construction tech

niques as well as accelerating the expansion of the road


network, the Swedish Nation

al Road Administration Region Malardalen has negotiated the


realisation of a 18 km

expansion of the E4 to the motorway section comprising the


design and the construc

tion as well as operation and maintenance of the motorway


during a seven year
The Organization and Management of Construction: Shaping
theory and practice (Volume Two).

Edited by D.A. Langford and A. Retik. Published in 1996 by


E & FN Spon. ISBN 0 419 22240 5. Procurement of a motorway
317

period. The contract will be carried out in partnership by


the Swedish National Road

Administration Production East and Skanska Mellansverige AB


(the largest contrac

tor in Sweden). The decision to build a new motorway was


taken by the government

in May 1992 and it was opened for traffic in September 1994.

1.2 Evaluation

Responsible for the evaluation of the construction project


has been Dr. Bengt Hans

son. The evaluation has been carried out focusing on the


technical, time, organisa

tional and economic differences obtained with a comparison


with a traditional pro

curement. The result of the evaluation is presented in


this paper and a more complete

report (1).

1.3 Terms

Some of the terms and keywords used in this paper are


explained below:

• Operation Operation refers to the necessary actions for


a road, bridge or traffic installation to

continuously have the functional characteristics it is


designed for.

• Function Such usability of necessary characteristics for


usability that can usually be estab

lished through measuring, testing or utilisation.


• Functional Contract Contract form in which essential
characteristics of the final product are defined

with (measurable) functional requirements and where


continuous operating responsi

bility is included for a number of years. A contract form


where the contractor has re

sponsibility for design as well as for carrying out the


work.

• Functional requirement Functions specified in measurable


terms.

• General Contract Contract form in which the contractor


normally has responsibility for carrying out

the entire construction contract.

• Design and Construction Contract Contract or


sub-contract where the contractor in relation to the client
is responsible

for the design and construction. Contract form in which a


contractor normally has

responsibility for designing and constructing the entire


construction contract. The

contractor has responsibility that the erected construction


also complies with certain

defined functional requirements. Some design and planning


for the program is done

by the client, but the large part of the detail planning


takes place under the contrac

tor's responsibility .

• Maintenance Maintenance refers to the implementation of


actions the purpose of which is to re

store characteristics of constructions, installations and


devices to the level intended

with the original design or with later improvements.

• Construction Contract Contract or sub-contract where the


client answers for the design of the project and

the contractor for the construction.

2. Functional requirement

2.1 Principles of a functional requirement

The function procurement is seen by many as a new


phenomenon for which there are

no developed routines for how the undertaking should be


formulated, evaluated re

spective how the functional requirement should be


described. It is also seen difficult

to see whether the demanded requirements have been complied


or not. The functional

contract form can however normally be managed based on the


tradition of design and

318 Hansson

construction contracts that exists. Parties with no


experience of design and construc

tion contracts most certainly also experience uncertainty


with functional contracts. The reason why many people see
the function procurement as a new contract form

is the functional requirements demanded with a functional


contract concerning

operations during longer periods and not only the


functional requirements with

commissioning. Generally there is reason to believe that


the client makes functional requirements

formulated as design and construction requirements,


because the operations procure

ment is new and unfamiliar. It is easier to formulate and


measure design and con

struction requirements. In cases where this is done the


scope of the operation
responsibility will decrease for the contractor. The
intention of the client in formulating a functional
requirement instead of a

detail requirement is to allow room for the contractor


carrying out the project to deve

lop his own technical solutions, which meet the demanded


functional requirements to

the lowest overall cost. In those cases the client requires


a certain specific design, for

example, a road surface of asphalt of a very expressed


quality, it is no problem to

formulate specific detail requirements within the framework


of a operations descrip

tion as long as the client is aware that one then takes the
functional requirements

from the contractor for these parts. The removal of


function requirements from cer

tain parts can affect the function of adjoining parts.

2.2 Functional requirement of this motorway project

When procuring this motorway project the client, the


Swedish National Road Admi

nistration Region Miilardalen, prepared a functional


description. In this functional de

scription was several detailed specifications about


designing and constructing the ro

ad. When the client describes in detail the product'S,


road's technical design, the

contractor will fulfil these and not develop better


solutions complying with more

generally formulated functional requirements. The problem


with operations procurement is to specify the requirements
that shall

be complied with during the period the operation is valid


(here the motorway for 7
years) and which requirements are to be demanded of the
road bed that is passed on

to the client (when the road is seven years old). In this


actual operations description

there are no limit values for when the road's operation is


considered to be fulfilled

and how these are to be measured. However, the client ought


to state for how many

vehicles per day the motorway should be constructed for


work. The client must

describe what should happen if the volume is different or


if the conditions change,

e.g. that studded tyres are banned. Under which weather


conditions the motorway

shall remain trafficable? What happens if several extreme


winters occur during the

operations period? Another problem is to produce an


estimatable basis for the functional contract. It is

difficult, for example, for the client to know how


extensive soil explorations that the

client must carry out for the tendering documents. The


results of the soil explorations

must be sufficient for enabling the contractor to dimension


and produce a tender. Yet another problem is the
construction's service life. Wooden piling under a road

and installation can, for example, last 7 years, i.e. the


length of time the contractor

has responsibility for the construction. However, the


client wants, of course, roads

and installations that hold significantly longer. Against


the background of the completed motorway project some
observations can

be made. Conditions in the form of laws and climatological


conditions are not clearly
established. For example, the laws regarding road
construction are not primarily for

mulated as a functional requirement but as design


requirement which leads to condi

tions for function sliding into design requirements for the


contractor. Procurement of a motorway 319 3. Design and
planning In this case a design and construction contract
(functional contract) was chosen. The . difference between
general and design and construction contract is exposed in
Fig 1. The structure plan with general respective design
and construction contract. Note that there is no time
scale in the figureit only illustrates the order and the
structure. Fig 2 shows the time schedule for design and
construction with a design and construction contract for
the studied project called NEWROAD 94, as it was
implemented, alternative general contract. The designers
and planners meant that "the land acquisition plan" must be
more complete and thoroughly worked out to make up a good
tender document for a functional contract than what was
the case here. In addition, it would have been preferable
to produce construction documentation for a part of the
work so that a quick building start was obtained. General
contract Design ~ Procurement Construction
o~----------~~~----------~)9~-------------------~ Design
and construction contract :rocurement~ Design ~ )00....
..... ....... .... , Construction .................. !"o
"'0 Figure 1. The structure plan with general respective
design and construction contracts. 1991 1992 1993 1994

ActIVItIes

Desi2n and construction contract

Actual course

Design

Stage 4.5 10 km

~tage 10 HS km

~tage 1.4 4.5 km

Detailed design stage

Land acqUlsition plan onstructlOn


Procurement l1li

General contract

IAlternatIve course

IDeslgn

Procurement IIIIIIIIIIIII

l onstrucUon

Figure 2. The time schedule for design and construction


with a design and construc

tion contract in the studied project, called NEWROAD 94, as


it was implemented,

alternative general contract.

320 Hansson

The designers' and planners' point of view should be seen


against the background that

the contractor in this project put the planners under


immense pressure with the inten

tion of producing documentation quickly and in a certain


order. Planning and design

was in this case carried out for approx. 1/3 of the road
when work as started. The contractor's point of view
should be set against this, i.e. it is more important

that the tender documents, land acquisition plan with


geotechnical findings make up

computable information, than it being planned. According to


the contractor, the

tender documents do not need to be so thoroughly worked out


as the planners believe,

but at least estimatable. The contract form seems to lead


to large planning and design input during a short

period. The documentation produced is approximately the


same as with a traditional
contract. The planners develop and learn more about
production due to the direct and

continuous co-operation with production. The administration


period will also supply

further knowledge and experience to the planners and


designers. A representative for the client, the Swedish
National Road Administration Region

Miilardalen, expressed the following opinion of the work


carried out in this project,

NEWROAD94:

• This functional contract is not representative for the


contract form's problems and possibilities. This is
because the actors, especially within the Swedish National
Road Administration previously worked in the same
organisation and therefore know each other well. Out of
habit the planners took contact with the client directly .

• In the actual project the designers and planners had won


a "head start" through the planning of the construction
documentation being started before the order of the
contract.

• The requirement of producing related documentation


resulted in the planners not being able to leave
"everything" to the construction site's personnel to solve
and design the documentation must at least be drawn up
afterwards within the framework of the contract, and given
to the client to show how the construction was carried
out. The land acquisition plan gives the conditions for
planning irrespective of the

procurement form. The road zone should probably be extended


to give more freedom

to the contractor and planners when placing the road bed


vertically and laterally. Amongst those issues remaining
are the questions concerning the scope of the

geotechnical information required to provide estimatable


information for tendering. The planning phase's content
and result has changed with a functional contract in

relation to a traditional implementation. The introductory


phase of the planning work
however took place with the Swedish National Road
Administration Region

Miilardalen as the client. The designers and planners have


been interviewed on their experiences. Below is

presented the advantages and disadvantages of the


functional contract (design and

construction contract) formulated by the undersigned and as


approved by the plan

ners:

Advantages

• There is always someone on site with whom one can discuss


the different technical solutions before selecting a
solution.

• The selected solutions due to the co-operation between


those responsible for production are of a better quality
and result in lower overall costs.

• In some cases the production personnel's needs have


increased the planning rate.

• The conditions for exchanging experiences are more


favourable with a design and construction contract form
than with a traditional construction form.

• The possibilities are greater with a design and


construction contract for so-called active design but have
not been utilised in the project.

• The construction phase started one year earlier than what


a traditional general contract would have allowed.
Procurement of a motorway 321

• The intense time schedule also resulted in a need of


documentation for several different parts of the road
route at the same time meaning planners work under pressure
to produce the documentation quickly. This led to lower
planning costs and short design and planning time.

Disadvantages

• Planning has been juggled around to quickly receive


documentation for different sections. Site and project
management have changed the order of included activities
while work was in progress which also resulted in the need
to change the planning order. Planners have had to adapt to
production which initially made scheduling and
implementation of planning difficult.

• Planning order was governed by the order production


required documentation and not in which order had been
most logical to plan.

• The intense time schedule also resulted in a need of


documentation for several different parts of the road route
at the same time meaning planners work under pressure to
produce the documentation quickly. This led to difficulties
for the planners but at the same time helped planners to
develop. The risk of mistakes during the intensive
planning increased.

4. Organisation

The responsibility forms with a traditional general


contract respective with a design

and construction contract are evident from the


organisational chart in Fig. 3. In the

figure companies and organisations have been placed under


the appropriate functions.

The design and construction contract refers to the


responsibility form with the NEW

ROAD 94 project such as it was really carried out and in


the organisational chart for

the general contract the same companies have been entered


for the sake of compari

son. The most important difference between both


responsibility forms is that the cli

ent with a design and construction contract receives one


responsible contractor and

agreement party for the operation and associated stages


such as planning, construc

tion and maintenance. The client sees the following


advantages/disadvantages with the functional contract

(design and construction contract with extended operating


responsibility):

Advantages:

• Early building start can be obtained as work can start as


soon as appropriate parts of the construction
documentation are completed.

• Short construction time as planning and construction can


partly take place in parallel.

• The client only has one agreement with one responsible


company.

• The control requirements can be reduced during


construction if the operation is to be provided over a
number of years.

• Durable technical solutions as the contractor shall


fulfil the operation for a long period.

• The co-operation between planners and contractor should


give lower costs to meet the required operation, better
conditions for production adapted solutions.

• The system for the exchange of knowledge created at the


contractor which improves the conditions to provide
operations at a lower cost.

• Good conditions created for technical development as


planning, contractor and operation are all in the same
organisation.

Disadvantages:

• Functional requirements difficult to formulate.

• The evaluation of the tender can in some cases be


difficult to do as the client shall judge to what degree
the contractor can live up to his undertaking.

• The system for the exchange of knowledge is created at


the contractor and not the

322 Hansson Client (Orderer) The Swedish National Road


Administration Region Malardalen General

contractor

The Swedish Natio


nal Road Adminis

tration

Production East +

Skanska

General

contract Operations The Swedish National Road


Administration Production East Planning The Swedish
National Road Administration Production East Operations
Planning The Swedish The Swedish National Road National
Road Administration Administration Production East
Production East Client The Swedish National Road
Administration Region Malardalen Design and
construction contractor The Swedish National Road
Administration Production East (and Skanska) I I
Construction work The Swedish National Road
Administration Production East Skanska Design and
construction contract

Figure 3. The organisational chart showing the


responsibility forms design and

construction contract for the project and the optional


general contract.

client.

• Reduced number of companies that can submit tenders. The


site management, object manager and deputy object manager
have been inter

viewed regarding their experiences. Below is presented the


advantages and disadvan

tages of the functional contract (design and construction


contract) formulated by the

undersigned based on the experiences of this project and


some interviews and as such

approved by the contractor:

Advantages:

• The number of companies that can submit a tender is


reduced so that the probability of the submitted tender
winning the contract increases .

• Early building start can be obtained as work can start as


soon as appropriate parts of the construction
documentation are completed.

• Short construction time as planning and construction take


place in the same organisation and can thereby be carried
out partly in parallel.

• The contractor has responsibility for the entire project,


that is, planning and conProcurement of a motorway 323
struction.

• The co-operation between the planners and contractor


ought to give lower costs to meet the demanded operation,
better conditions for production adapted solutions.

• The system for the exchange of knowledge created at the


contractor which improves the conditions to provide
operations at a lower cost.

• Good conditions created for technical development as


planning, contractor and operation are all in the same
organisation.

• Work is targeted to achieve a product of the right


quality instead of searching for loop holes in the
contract documentation as is the case in some general
contracts.

Disadvantages:

• Functional requirements up until now have been unclear or


lacking, which has led to the contractor formulating the
wording himself. In turn this results in one choosing
unnecessary costly solutions.

• Evaluation of the tender can in certain cases be


difficult as the client must judge to what extent the
contractor can live up to his undertaking.

5. Construction

The functional contract naturally brings about a greater


tendency for the contractor to

take a responsibility that the operation is fulfilled


directly in connection with the con
struction without further costs for repairs and
maintenance. This has, in this case, re

sulted in a higher quality road bed being chosen (thickness


and choice of ballast in

the surface course). In addition there is a greater


tendency with the chosen contract

form to dig out doubtful material so as not to risk


settlements.

6. Economic consequences

The planning phase has through the design and construction


contract procurement

given a quicker construction start than with the use of a


traditional general contract

procurement. When implementing the project, the client


selected to run it as one large

project instead of dividing it up into a number of smaller


ones. Thereby the produc

tion time was shortened by approximately one year, Fig 4.


The choice of the procurement form and the organisation,
i.e. a functional contract

or a design and construction contract with extended


operating responsibility has giv

en a quicker building start by one year compared to a


traditional general contract and

besides a one year shorter overall construction time.


Below there is a cost compilation, Table 1, for the
project for the procurement

forms, functional contract respective general contract. A


shorter construction time gives in itself a reduction of
the joint cost on the con

struction site that are time dependent by SEK 4 million.


The choice of production

adapted solutions probably lead to a cost saving in the


region of SEK 8-10 million. The capital costs during
planning and construction have been calculated to approxi

mately SEK 38 million with a functional contract respective


SEK 58 million with a

traditional implementation. The overall two year shorter


project time gave capital

costs that were not quite SEK 20 million lower than what a
traditional general con

tract would have given. The benefit of the motorway has


been valued by the Swedish National Road Ad

ministration to approximately SEK 23 million/year or SEK 46


million for two year. In summary a calculation shows that
the order with the selected method of a func

tional contract needs to invest 436 404 = SEK 32 million


less than if a general con

tract had be chosen. The investment is nearly 8 % higher if


a general contract had

been chosen. A traffic benefit is obtained through the two


year shorter project period.

The total effect becomes SEK 78 million (19.3%).To this the


client's lower costs for 324 Hansson Design and
construction contract 400 1 ~ ............ . 20 0 0 +
__ ---=<:f6:="". F· "" .. ",,< ",,< ",,<:a:: ",,: :",,:
:",,: :",,: :",,: :'T: ",,: :c:: ::c:: :c:: :0:: i-_--,
;:::;;:;;;;;;;; I D Constr. costs [ill] Planning costs
General contract '-0 '-0 'f '-0 iJ; tv UJ Vl 6 6 6 6
6 '-0 'P 'P '-0 'P W UJ UJ W UJ 0 0 0 0 0 ID
Constr. costs [JIJ] Planning costs Figure 4. Cost
consumption with a design and construction contract
respective general contract. Table 1. Cost summary

Cost Summary

Project costs excl. runmng and maintenance

Capital costs during planning and construction

Time dependent common costs

Production adaptation actions

Total project cost inc!. capital costs


Traffic benefit with two-year shorter project period

Total Functional General contract contract SEK millIon


SEK millIon 366 366 38 58 4 8 404 436 7,9% 46 404
482 19,3% procurement, management and control with the
selected procurement form should be added.

7. Conclusions and experiences Based only on one practical


case it is relatively limited conclusions and experiences
that can be generalised. Here are a few opinions regarding
generalizability. Procurement of a motorway 325

Knowledge changes

Each new operations procurement that the parties carry out


will give new experienc

es. They give the parties involved a build up of knowledge.


This will be utilised in

the next project irrespective of whether it is procured as


a functional contract or not

The effects of the know ledge development is greater the


more operations are encom

passed by the contract (planning, construction as well as


operations and mainte

nance). The functional and design and construction contract


forms are a more educa

tional organisation that the general contract form. This


experience is generalizable.

Earlier start and short construction period

The design and construction contract and the functional


contract (comprising plan

ning and construction) give the possibility to plan and


construct simultaneously,

which in tum gives the possibility of an earlier building


start. Simultaneous planning

and construction normally give a quicker building start and


a shorter overall project
time than a traditional implemented general contract. This
experience can be general

ized but it should be noted that an early building start


and more or less parallel con

struction can also be carried out with a very divided


contract. However, using the first

solutions produced by the planners, which used crushed


material in the road bed and

surcharge loading with bad ground conditions, it would not


have been technically

possible to construct in such a short time with a general


contract as with a design and

construction contract.

Reduced overall costs

The overall investment cost is reduced if the construction


period is shortened through

capital costs and time dependent joint costs being reduced.


This element is generaliz

able. However the time dependent joint costs rise if the


construction period is short

ened too much. A shorter construction period is achieved in


this case through the

choice of a design and construction contract instead of a


general contract. The possi

bility of further cost reductions increases through


production adapted planning. This

experience is also generalizable.

Functional requirement

A superficial analysis of the functional requirements


included shows the need of ex

tensive development input to produce a system of how


functional requirements
should be formulated for a road and motorway project. This
is a generalizable experi

ence.

Residual value

Processing of the residual value when the contractor hands


over to the client needs to

be studied further.

Administrative experiences

The administration of functional contracts contains a


number of elements that are not

sufficiently clarified to work under other circumstances


than those taking place in this

contract.The system for evaluating tenders regarding


functional contracts should be

developed. In those cases the evaluation is seen as too


subjective by the involved

parties the procurement, seen from a European


point-of-view, can be questioned.

1. Hansson B (1995) A motorway as afunctional contract,


Evaluation of the Gammelsta project, Department of
construction management, Lund University, Lund, Sweden.

FRENCH BUILDING PROCUREMENT

APPROACHES INPUT TO THEORY

AND PRACTICE

G.S. Birrell

Centre for Property Development and Management, University


of

Manchester Institute of Science and Technology,


Manchester, UK

ABSTRACT

After a brief introduction to the building procurement


process, this paper will present three major

approaches to building procurement in France. These are


(a) Equipement/Grand Project, (b)

Complex/Large and (c) Simple/Small. Each serves a


different segment of the building market as (a)

is primarily for large, prestigious government backed


projects, (b) is for complex and large commercial

projects and (c) is for simple, small, projects usually


with local or vernacular constituents. Each

description will be supported by a diagram in which there


will be (i) the set of phases and sub phases

of the approach alongside (ii) the required roles and their


lines of communications. This unique mode

of presentation greatly assists the understanding of each


approach as to its degree of complexity and

how to carry out the work required in each major phase of


the whole procurement process under each

approach. After describing these three French approaches,


the paper will consider their salient features

and then go on to relate them to the major UK and USA


building procurement approaches and discuss

where the latter could benefit from considering inclusion


of some major features from the French

approaches along with required changes to the UK and USA


approaches to enable inclusion of these

French features.

SOMMAIRE

Apres une introduction breve au processus d'obtenir les


projets de construction, ce papier presentera

trois facons principales d'aborder I'obtention des projets


de construction en France. Elles sont (a)

Equipement/Projet Immense (b) Complexe/Grand et (c)


Simple/Petit. Chaque description sera
accompagnee d'un diagramme qui inclura (i) Ie groupe de
phases et sub-phases de la faeon d'aborder

la question et (ii) les roles necessaires et leurs moyens


de communication. Le papier se developpera

en considerant les traits principaux des trois facons


francais d' aborder les projets de construction, et

en les comparant aux methodes britanniques et americaines.


Le papier discutera les moyens duquels

Le Royaume-Uni et l'Amerique pourraient profiter des idees


francaises, et comment ils pourraient

s'adapter pour en incorporer. Le papier est tire des


resultats d'un projet de recherche pour Ie gouvernement
francais (I) dont

I'objet est de demontrer les faeons principales d'obtenir


les projets de construction en France et au

Royaume-Uni. The paper is drawn from the results of a


research project for the French government (I) to map

out the major building procurement approaches in France and


the UK with especial consideration of

the relationships of work and role teams in the Design,


Contracting and Construction phases and

present comparative views on these approaches from


architectural professionals in both France and the

UK.

Keywords: Construction, design, features, French, phases,


procurement, roles, transfer.

The Organization and Management of Construction: Shaping


theory and practice (Volume Two).

Edited by D.A. Langford and A. Retik. Published in 1996 by


E & FN Spon. ISBN 0419 22240 5. Building procurement 327

The Conceptual Building Procurement Process

The simplest presentation of the building procurement


process is the set of required phases in that
process in a realistic, general sequence (2). However, it
should be realised that for some projects

under some circumstances some of these phases may be


carried out in parallel in time or different in

sequence from these presented here. On some projects some


phase or sub phase may be ignored for

an array of reasons from ignorance through to superb


knowledge of building procurement. Generally, more work
and expenditure of time and money is created in later
phases and lack of

quality in the end product by poor work or lack of


definition in earlier phases. Also, the choice of

a procurement approach which is inappropriate for the


project situation can increase cost and duration

of the procurement process and reduce quality of the end


product by putting inhibitions on the

satisfactory use of the completed building over its many


years of subsequent use. IDEA NEED IDENTIFICATION ~
FEASIBILITY STUDY DECISION ~ CHOICE OF PROCUREMENT
APPROACH ~ DESIGN DESIGN '\v CONTRACTING '\v I
CONSTRUCTION DELIVERY ~ I COMMI~G 1 USE

328 Birrell Each of the following set of phases is


described only briefly to introduce the concept of the
building

procurement process within the concept of building


procurement having to deal with decision, design

and delivery (3).

Idea/Need Identification. Defining the need for a future


building and the what, why, where etc

characteristics of the future building in functional,


aesthetic, economic and physical and other desired

features.

Feasibility Study. A study in economic and social terms of


the whole proposed building project so that
it can be evaluated objectively usually as one economic
alternative for the expenditure of capital

investment by the client for the project.

Choice of Procurement Approach. No later than the


completion of the feasibility study a choice

should be made on which alternative approach to building


procurement will be most appropriate for

the procurement of each specific project. The choice


should be made at this time because it has

implications for hiring of agents and communication


patterns among agents throughout the remainder

of the process. All of these can affect the effectiveness


and efficiency of both the building procurement

process and the end product building as a useable asset by


client and users.

Design The phase in which the design of the building to be


built will be crystallised. It will usually

comprise the sub phases of (a) project definition


(brief/program) by the client and advisors, (b)

conceptual design creating the image externally and


internally of the building/end product and (c)

design development which carries the design concept to the


stage of complete drawings and plans from

which the building can be built.

Contracting This phase is in three sub phases parts (a)


creating the contractual documents by the

client and his agents (b) estimating and bidding by


contractors and (c) evaluation of bids and selection

of contractors.

Construction The process and management of the actual


construction work including the flows of all

resources to and on the site under the contractual formats


and the chosen approach to building
procurement.

Commissioning The processes of checking that what has been


built is in good working order for use

of the building and ensuring that all building systems


operate effectively for the user. This may include

the entering of the building by the various users and


their furniture etc as it becomes a useable,

functioning asset for the project client and its occupying


users.

USE The whole raison d'etre of the building is what it is


used for by the various parties involved.

This can span from economic and financial for the client to
functionality and satisfaction of the users

of the building to the aesthetic and social compatibility


or signal to the surrounding neighbourhood and

public at large. Building procurement 329

THE THREE MAJOR FRENCH APPROACHES

Each of these descriptions will comprise an overview and


consideration of the work in each of the

phases of Design, Contracting and Construction as the


phases of which are the focus of building

procurement

French Equipement/Grand Projet Approach (see Appendix 1 for


diagram)

Introductory Overview and Client

This approach is used primarily on major public and


government projects in which government or

national prestige and image considerations are involved or


the building will be a major element of its

urban scenario. This will have effect over a very long


duration of use and usually there will be public
access to such a building and considerable influence from
the building upon the public and its

surrounding location. A major feature is that the


selection of the design concept is by competition among
proposing.

designers. This is usually rather separate from the


subsequent carrying out of the remainder of all

project procurement activities including design


development. This approach gives considerable

consideration and benefit to long term image


appropriateness and aesthetics of the future building and

much less consideration to costs and duration of


procurement and maybe even of functionality of the

bUilding.

Design Phase

At the beginning of the design phase the maitre d'ouvrage


(client) will hire a maitre d'ouvrage delegue

(project manager) who is skilled in handling all


management aspects of the design, contracting and

construction of such prestigious buildings. Selection


criteria will include the past experience, capability

of interaction with government officials at many levels,


handling design competitions, design

development, contracting and construction. The design


phase is in two parts (a) the competition to select the
design and to a lesser extent its

designer and (b) the development of the concept design to


enable contracting to hire the construction

contractors. The design competition sub phase begins with


a considerable amount of work by the project

manager to establish the client's needs, often from many


parts of a large government department and

fairly frequently from many levels of many government


departments plus from outside agencies which
have related interests to the use of the subsequent
building and it's image and use. This work

culminates in the production of a project brief/program to


which the competing designers respond by

providing their conceptual design. Such a brief/program is


often is of a complex and voluminous

nature. Another part of the design competition is (a) the


finding or selection of the competing designers

and (b) the process of selection of the winning


concepteur/maitre d'oeuvre (conceptual designer).

Both of these parts will usually be under the guidance of


the project manager and his organisation will

consult with the client on the format of the competition.


The various designers will each produce a

design in response to the brief/program and each will


primarily and perhaps exclusively be judged by

its external and internal conceptual image with perhaps


some consideration of its functionality. The

selection of the design will usually be by a panel of


experts or interested parties with degrees of

national prestige depending on the level of importance of


the end product building to "La France", and

there will be little consideration of the cost or


constructability of the design. This part of the design

phase ends with the selection of the conceptual designer


by the selection of his design submission.

While the chosen/winning conceptual designer now joins the


project manager on the "project team" it

is reasonably frequent that his work has been mostly


completed by the creation of the design concept

which he submitted in the competition. His position in the


project team on subsequent phases of

procurement may be mostly consultancy to ensure that what


follows as design development,

contracting and construction remains faithful to the


competition winning design concept. The major purpose of
design development sub phase is that a feasible working end
product can

be built. Added to the project team for this is the role


of the bureau d'etudes (design development

agency) along with the array of required specialist


designers in that organisation or as ad hoc specialists

330 Birrell as would be needed for any prestigious, large


and complex building. In this design development work the
design concept will be developed to the design of a full
building. While there may be some

consideration of constructability and construction cost


these will be relatively weak compared to

ensuring that the design concept is faithfully expressed


throughout the developed design. The

conceptual designer will be consulted to ensure the


fundamental compatibility of the design to it's

concept. The design development agency will be appointed


usually as a result of the combined views of the

client and the project manager with some input from the
conceptual designer. The past experiences

of the design development agency, their speciality


expertise for types of buildings and also the

familiarity of and degree to which these various roles


have worked together or is anticipated they will

work together are the major parameters in choosing the


design development agency for a project. It may be that
in design development that a l'enterprise general (general
contractor) will be brought

into the team as a construction advisor on at least an


equal footing with the design specialists

Design/Construction Interface (Contracting/Tendering For


Construction)
Towards the end of the design development there will be an
appraisal of possible general contractors

for the construction work by the whole of the clients team


of agents. Generally selection of the general

contractor will be in the form of a lump sum competitive


bid from a chosen set of general contractors

for that position on the project team. Each bidder will bid
for the construction of the whole building

including the use of their own subsidiary production


propre (trade contractors) and other required sous

traitants (free standing sub contractors) for each required


lot separe (sub trade). While total bid price will be a
consideration in selection, again the delivery capability
and

experience on a project of this type, size and complexity


and previous interactions with the client and

his agents of each building general contractor will be


seriously considered in that selection and may

be the deciding factors.

Construction Phase

The construction work will be carried out by the winning


general contractor and his sub contractors.

However, this construction contractor will be part of the


network of roles which formed the team of

managers and design developers prior to him being


contracted to construct the work. Most likely there

will be considerable amounts of interactions among these


roles as the developed design and its

construction process intertwine with each other. This may


mean a fragmented construction process

with a considerable number of what would be termed


change/variation orders with their price and

duration effects on the final price and completion dates.


However, it seems that these matters are
expected as a normal part of interactions and are settled
out among these roles during construction.

Also, as the client is less concerned about the cost and


completion date of the building than he is

concerned about the quality of image of the end product


throughout its future life in that location or

neighbourhood, there may be some concern about major (but


not minor) cost increases and less concern

for time extensions to completion dates.

French Complex/Large Approach (see Appendix 2 for diagram)

Introductory Overview and Client

This approach is used primarily on large, complex


projects, mainly but not exclusively, for private,

commercial maitre d'ouvrage (clients) or the client may be


a group of private clients or a promoteur

(property developer). The objective is for a balanced


concern between economics, functionality,

procurement duration, and aesthetics. This approach tries


to balance the provision of an attractive eye

catching image for customers and functionality of the


building over its life with concern for capital

costs and duration of procurement to meet a market demand


for its use.

Design Phase

The design work in this phase is usually of a continuous


evolving nature from conceptual design

through to completion of design development with all


appointed roles participating usually under a

"rolling" leadership from within the team of concepteur


(conceptual designer) through to the bureau

d'etudes (design development agency) while the maitre


d'oeuvre (architect) and maitres d'ouvrage Building
procurement 331

delegue (project manager) participate throughout the


process. The promoteur/maitre d'ouvrage

(property developer/client) will also be involved during


the design process and its interactions with the

three major parameters of quality, cost and time. In


addition the client might well have expert

knowledge and as a client of a commercial nature be


vitally interested in balancing aesthetic appeal,

minimising cost and minimising duration of procurement.


There can be variations in the execution of

the design work by selecting professional roles either


simultaneously or in different sequences. This phase
begins with the property developer/client hiring a project
manager who is capable of

balancing out the above objectives and managing all the


required professionals and contractors in the

procurement process. Usually, the brief/program for the


design will be produced by these two parties

and present the specific, complex objectives of this


project for the designers of the building. The

production of the brief/program may be aided by the


architect if he has been hired by that time. The design
process will be usually a continuous flow of conceptual
design and then design

development or one which matches the needs of the


particular project or its clients needs or

circumstances. The many design decisions will be guided by


the client and the project manager seeking

the best balance for the project between the major


objectives of an attractive building, a reasonable

capital and functioning expense and a minimum procurement


duration. There will be careful consideration in hiring
the conceptual designer by either (i) competition or

(ii) by appointment or (iii) as a member of the team of the


architect. The relationship between the

architect and the conceptual designer has to be carefully


set out and managed if both are hired to the

project team as separate roles. Another alternative is


that only one of them is hired and works with

the design development agency to carry out the whole design


process. The work of the conceptual

designer will be primarily dealing with the external


facade of the commercial building with maybe

some considerations of the aesthetics of the internal


areas, especially those to which the public is

exposed. A l'enterprise general (general contractor) may be


brought in as a member of the design

team to assist their work. The capability of each design


role participant to professionally deliver the required
service for that

project to the client along with, and traded off with,


their ability to coordinate with the other role

participants on the team will be major factors in their


selection by the client advised by the project

manager.

Design/Construction Interface (Contracting/Tendering For


Construction)

Towards the end of the design development there will be an


appraisal of possible I' enterprise generals

(general contractors) for the construction work by the


whole of the clients team of agents. Generally

selection of the general contractor will be in the form of


a lump sum competitive bid from a chosen

set of general contractors for that position on the


project team. Each such bidder will bid for the

construction of the whole building including the use of


their own subsidiary production propre (trade
contractors) and other required sous traitants (free
standing sub contractors) for each required lot separe

(sub trade). Alternatively the property developer may


negotiate with one or more general contractors,

especially if an overlap of construction with design is


desired. While total bid price will be a major
consideration in selection, again the delivery capability
and

experience on a project of this type, size and complexity


and previous interactions with the client and

his agents of each general contractor will be seriously


considered in that selection and may be the

deciding factors.

Construction Phase

The construction work will be carried out by the winning


general contractor and his sub contractors.

However, this construction contractor will be part of the


network of roles which formed the team of

managers and design developers prior to him being


contracted to construct the work. While the

commercial client is concerned about the cost and


completion date of the building he is also concerned

about the quality of image of the end product throughout


its future life in that location or

neighbourhood. Thus there is a pressure to minimise change


orders in the construction process which,

in tum, generates pressure to have a complete design and


contract prepared before bidding by the

general contractors. Most likely there will be considerable


amounts of interactions among all project

roles as the developed design and its construction process


intertwine with each other. However, it

seems that these matters are expected as a normal part of


interactions and are settled out among these
332 Birrell roles during construction. French
Simple/Small Approach (see Appendix 3 for diagram)
Introductory Overview and Client This approach is mainly
used on relatively simple or small or local projects where
the client is usually not complex and the construction
resources available and required are local and may be
generalised in skills. Usually, the client for a simple
project may only require or seek the services of one
local, relatively general agent to advise and control the
whole project for him. The client's concern or objectives
may be of domestic scale, maybe with vernacular
compatibility to its surroundings as well

as meeting the available budget of the small client. Such a


client may require considerable advice from

his agent on what he needs as a design and as a project as


well as hiring his ability in management of the phases of
the procurement process

Design Phase

At the beginning of the design phase or before it, the


maitre d'ouvrage (client) will hire by appointment

a local cabinet d'architecture (architect or general


building agent) as his primary advisor and manager

of procurement. Usually the architect will produce a


design brief/program either in writing or verbally with the

client after discussions with the client. The client


probably having little knowledge of building designs

and procurement and may be primarily concerned with not


exceeding his budget and having a design

that is comfortable to his needs and fitting in to the


neighbourhood. The conceptual design will be

produced by the architect, discussed with the client and


adjusted to suit the client's subjective opinions.

Then the architect will develop the design and produce the
documents required for

contracting/tendering for construction. Probably to a large


extent this design will contain features
which are compatible with the local architecture and be of
components available in the local

marketplace. These constituent features of the building


will also be chosen by considering the

capability of local tradesmen to carry out the work. All of


the design will tend to be a trade off

between the needs of the client and the capabilities of the


local construction trade contractors, which

is an ingredient in maintaining of the vernacular of the


neighbourhood and locality.

Design/Construction Interface (Contracting/Tendering for


Construction)

During this phase or towards the end of design (or perhaps


shortly after his own appointment) the

architect will advise the client on the appointment of a


construction pilote (site inspector/manager) who

will supervise the quality and execution of the work as


well as guide and coordinate the work being

carried out on site. The site manager is probably a former


high quality tradesman familiar with all

trades works and who knows and is known by all the local
sub contractors. The architect usually

forms the construction team from the local sous traitants


(sub contractors) for each lot separate (trade)

although the client may have to begin construction work


with only the estimate of cost of some of the

trades which enter the construction process later in that


process. The architect will consider the qualities of the
various sub contractors in each trade required for

the project. He will advise which subcontractors in each


trade should be called on to bid for the work

in each trade given their skills, current work load and his
experience of their performance on past

projects. He will then call for competitive bids from these


sub contractors for each trade either all at

the beginning of the construction process or for each trade


prior to it's work beginning in the

construction process. He may negotiate the contracts for


some specifically required aspects of the work

and may take into consideration work loads of required


local subcontractors in making his decisions.

Construction Phase

The construction work will be carried out by the team of


sub contractors hired and it will be managed

primarily by the site manager with the architect operating


as overall supervisor and linkage to the

client. Usually on a project of this nature the work is


relatively simple and suitable for local skills and

it's design will have been produced with that in mind. It


may contain parts which are of a vernacular Building
procurement 333 nature by a local specialist but that
situation will have been included in the design prior to
contracting

and construction. The construction process for such a


project will usually be on a relatively small site

and thus it may be that construction work is somewhat


sequential as only one or two sub contractors

may have work space on site simultaneously.

Salient Features of Three French Approaches

Equipement/Grand Projet Approach

The salient feature of the Equipement/Grand Project


approach is that a design concept for a building

of national prestige lasting for decades will be put in


place at the end of the procurement process. The

image/concept component of the building during it's


subsequent use is the primary objective of the

client and the procurement team. The cost and duration of


procurement are of considerably less

importance than maintaining the original design


image/concept under this approach. This creates

mainly a procurement management issue in the design


development sub phase which the requires

considerable resistance to simplifying the winning


conceptual design to reduce the cost or the

construction duration or simplify its constructability. The


design developers in France adhere to

developing the winning design concept rather than


simplifying it for ease of procuring the end product. It
is probable that a great part of the complexity of this
approach comes from having to interact

with multiple clients i.e. the government agencies etc.,


as the project client. Their large numbers,

different levels and also inclusion of the opinions of


relative non government agencies in the thinking

of the involved government agencies on the end product and


building procurement can pose

considerable difficulties for the procurement team,


especially in the very early sub phases of creating

the design brief/program and managing the design


competition and ensuring the user needs are satisfied

in the beginning of design development.

Complex/Large Approach

The salient feature of the Complex/Large Approach is the


difficulties in striking a balance between (a)

providing the image/concept desired by the commercial


client for the market place and (b) the cost

minimisation and procurement duration of a purely


commercial project. Thus the scope of the image/concept
aspect is usually only for the external facade of the
building

with perhaps some similar consideration of the internal


public areas. Also, all of this image/concept

work has to be carried out within the strictures and


objectives of a pure commercially driven end

product which has to make a property development profit.


As such it's procurement is probably more

complex to manage and create a design wisely because of


the above difficult interface having to be

satisfied within a desired short time window. However, that


the property developers/commercial client

is relatively closely involved in design and contracting


can provide faster and more explicit decision

making by such a client and the design and contracting


team. Indeed this can induce continuity,

overlapping and combination of design and contracting.


Nonetheless, if such a client is of a multiple

client nature the resolution of such speedy decision


making may benefit from having one prime client

who coordinates the other clients and the procurement


process.

Simple/Small Approach

The salient feature of the Simple/Small Approach is that


the end product is simple and small and is

usually required in a small town or suburban or rural or


semi-rural location. To achieve a balance

between the desires of a client in such a location for


such a building as to it's quality, cost and duration

will primarily require the services of someone who not


only can design the building but also knows

the local market participants among the array of locally


available building trades and sub contractors

including their current and future work loads and


particular work strengths and weaknesses. Such a

role player is a local architectlbuilding manager and


therefore he is the focal role in all phases of the

whole building procurement process.

334 Birrell

Transfer of French Procurement Constituents

To the UK and USA Procurement Approaches

There appears to be three major features of the French


approaches which could benefit the UK and

USA approaches.

Conceptual Design

The major feature in the French approaches which could


benefit UK and USA projects is the

considerable concern for the quality of the conceptual


design and it's effect on the activities

surrounding the building/end product during it's subsequent


use and lifetime. Put simply, that so many

buildings in Paris (and other French cities) have been


procured under this prinCiple may lead to the

French urban scenario of vistas and unique images of


buildings. It can be this concern for conceptual

design in the procurement process which makes visual


excitement and stimulation in French cities and

expectation of what might be round the next street corner


in Paris. When compared to the relatively

prosaic urban scenarios in the UK and USA, stimulates


thoughts and poses the question "how has this

difference come to exist and why do French urban areas


have such architectural excitement which is

considerably less so in UK and USA urban areas?" It is


suggested that the differences between

building procurement in (a) France compared to (b) the UK


and USA enables this visual excitement
of buildings and vistas to be untrarnrnelled by somewhat
prosaic considerations of capital costs and

procurement durations.

Project Management

Another major feature of difference in building


procurement in France from the UK and the USA is

that in France a project manager has been used for decades


whereas in the UK and USA this concept

is recent, perhaps at most, of some two or three decades in


the USA and more recently in the UK.

In the EquipementlGrand Project and the Complex/Large there


is the maitre douvrage delegue and in

the Simple/Small there is the cabinet d'architecture, both


of which are project managers with the

knowledge and expertise appropriate to manage these very


different types of project. Perhaps just as

the project manager becomes a more normal feature of


building procurement in the UK and USA will

enable the other French procurement characteristics of (i)


maintaining the design concept throughout

procurement and (ii) consideration of availability and


skills in the local construction market place as

a creative positive force in the design of buildings to


become more central in building procurement in

the UK and USA as well as providing (iii) linear


coordination during the whole building procurement

process.

Design Competition

The third major feature in the French approaches which


could benefit the UK and USA is the use of

the design competition to select the designer, or more


correctly to select the conceptual design. In the
UK and USA the cornmon approach is to appoint the
architect/designer on the basis of his past record

and experience and then he carries out the design work for
this project which may include writing the

brief/program but certainly producing the conceptual design


as well as design development and may

continue into the creation of the contract documents at


the beginning of the contracting phase. In France the
client and advisors prepare the brief/program and it is
used as the call for conceptual

designs in a competition which can be closed or open. Thus


the competition creates and selects the

conceptual design for the future building/end product and


it's creator is paid the prize and a contract

as a consultant to the design development team. Thus the


conceptual design is selected from an array

of different conceptual designs from different creators and


is known before the design development

agency is appointed. At best in the UK and USA the client


may see two or three alternative

conceptual designs from one source. after his appointment


This crucial point is that the competition

usually selects the design concept and is not just a means


of selecting a designer. The creator of the

winning conceptual design has done most of his work by the


time his conceptual design has been

selected as the winner. The subsequent design development


work is by the design development agency

not by the conceptual designer but the latter is a


consultant on the design team to ensure that design

development remains faithful to the chosen design concept.


To incorporate this approach to the UK and USA situation
would require disturbance to the normal Building
procurement 335

processes because not only would the decision processes and


architect selection process be changed but

there would have to occur the evolution of the equivalent


of the design development agency to carry

out the design development sub process. While large UK and


USA architectural practices are staffed

to do this it would require perhaps the breaking of such


practices into two one part becoming

conceptual designers and the other part becoming design


developers with all the engineering specialists

required in that sub process. However, such an evolution


would not be incompatible to the desires of

most architects (and especially architectural schools) in


both the UK and USA that the architect

provides only the conceptual design.

(1) Birrell, G S. (1994) Array of Building Procurement


Approaches in France and Britain, Centre for Property
Development and Management, UMIST, Manchester/Plan
Construction at Architecture, MInistere De L'Equipement Du
Logement et Des Transports, Paris.

(2) Birrell, G S, (1989) So You Need A New Building? A


Guide to Clients on Procurement Approaches, School of
Building Construction, University of Florida/State of
Florida Building Construction Industry Advisory Committee.

(3) Hastings, R F, (1968) Proposal: A New and


Comprehensive System for Design and Delivery of Buildings,
Architectural Record. r " R . Q U I P I I I I B H T / a l
W l D P R O J I T F L O W O F P H A S . S I P H A S E S I !
d ! . l I ! I ! ! ! I N E E D I D E N T I F I E D C H O I C
E O F A P P R O A C H H I R E M A i T R E D ' O U V A A G E
D E L E G U E P r e s e n t i n g C r e d e n t i a l s N _
F E A S I B I L I T Y S T U D Y B R I E F / P R O G R A M D
E S I G N C O M P E T I T I O N ( T o s e l e c t C o n c e
p l e u r ) A _ " " " " " , , D e w I I o p a n d w d e B r
i e f / P r o g r a r r m e A p p r o v a l b y M a i t r e
O ' O u v r a g e " " " " " , , , , " , O o s i g n U 1 g S
u b m I H i n g C o n c e p t u a l D e s i g n E v a l u a
t J n g D e s i g n s S u b m i l l e d S e I e d 6 n g D e
s i g n C o n c e p t e u r l I R E W I N N I N G C O N C E
P T E U R A S P r e H n l l n g C , . . n t i a l s M A i T
R E D ' O E U V R E N e g o d l l l l n g D E S I G N H I R
I N G B U R E A U D ' E l 1 J O E S D E T A I L D E S I G N
C O N T R A C T I N G F O R C O N S T R U C 1 1 O N H I R I
N G L ' E N T R E P R I S E G E N E R A L A N D C O N T f l
A C T I N G F O R C O N S T R U C T I O N C O N S T R U C T
I O N A w a r d C o n t r a c t R n a l U n g C o n c e p I
u a I D e s i g n R a c e M n g C o n c e p t w d D e s i g
n S U . . . . . . . _ e v . . . . . . . . . P r o p o s a l
s A w a r d C a n t r a d . O o o l g n d _ O b t a I n ~ O
. C o n s t r u l r e W " " " " , , D n I w t n g o C o r b
8 c I D o c u m e n t s P r e a e n l i n g C r e d e n t i
a l s E s l n . l n g S u b r n I t i \ g r e n d a r N e g
o O l a l l n g A w a r d C o n I r a c t P , e _ C a l v e
r y o f R l t S O U r c e s C o o I r o I I n g r < . ' n t
l e f l l r P r ( , p e r t y O e v e I o p m e n t a n d H
a n a g e . e n t U H I S T 1 ' 0 f \ n x B 8 M a n c h e s
t e r 1 1 6 0 1 0 0 . E n g 1 a n d S u b S u t t P b y " h
. , u l ' 1 0 m • B u . . . . u O ' E t u d e s n C o r p s
d ' E l a b I S o u a T r a i l a n t s e s t i m a t i n g
T e n d e r i n g P o s t r e n d e r N e g o U a U o n s A
w a r d C o n t r a c t s I r e l e p h o n e 0 6 1 · 2 0 0
4 2 5 5 I I I I I I ~ a C O N C E P T E U R S ~ I N C O M P
c r m O N / " a P R O D U C T K l N P R O P R E " ' * " a L
' f N T R E J > R J S E O E N E R A L . . l D T S E P A R E
. . . . . . . . . 1 ' ' E A ' 1 I W I T I l n S Q l J S T R
, . \ I T A N T S O N E S O U S 1 R . · \ f ! \ N l > ~ t :
i ~ I F " C o H P L U / L A R O I P L O W O F P H A S . S '
P H A S E S N E E D I D E N T I F I C A T I O N C H O I C E
O F A P P R O A C H . ' i I R I N G M A i T R E D ' O U V R
A G E D E L E G U E F E A S I B I l i T Y S T U D Y H I R I
N G M A i T R E D ' o E U V R E I I ! ! ! . . l b ! I I I P
r e s e n t i n g C r e d e n t i a l s N e g o I l o I I n
g A w O l d " " ' * " " P r e s e n t i n g C r e d e n t i
a l s N o g o I i a U n g _ < d " " " " " " D E S I G N c .
; ; ; ; . . ; ; . u . i i i ; . ; g ; B R I E F / P R O G R
A M H I R I N G B U R E A U D ' E T U D E S D E S I G N F o
n r I n g 8 r t e f l P r o g r a n v n e P r e s e n t i n
g C r e d e n t i a l s N ~ " " ' * " " 8 0 " ' ~ H I r l n
g O n I g n S p _ . . . . O o o i Q n O o v e l o p m o n C
A I O t h e r s y . a . . = , ~ C o n I t r u " . S U b S u
b P h f t t t F . . . . . . C o n c o p I I / I I I / I I I
I I I I I I I I I I C O t f m A C T l N G F O O O O N S n i
i c O O N C c ; , h d ~ . . H I R I N G l ' E N T R E P R I
S E G E N E R A L A N O C O N T R A C T I N G F O R C O N S
m U C T / O N C O N S T R U C T I O N S h o r t U I I I o f
T e n d e r . , . . . P r . . . " " " " B o l d i n g P r n
p o s a l ~ S u b m l t n g T e n d " N e g o I l o I I n g
A . . . . . " " ' * " ' " P r e p a < I n g B u y i n g D e
l v e r y o f R e s o u r c e s C o n t r o l l n g ( . m L
r e t o r P r r ! p C f t y D e v e l o p n e n t a n d H a
n a g e m e n t I 1 l 1 l S f 1 ' 0 R o ~ f : l 8 M a n c h
e s t e r 1 1 6 0 1 0 0 . E n g l a n d n e o r p . d E l a
l a l S o u , T r a l t a r U . E s t t m a t l n g r _ P o
s t r e n d e r N e g o t i a t i o n s A w a r d C o n l r
a d s T e l e p h o n e 0 6 1 2 0 0 4 2 5 5 , I , / L ' E N
T R E P R I S E I f ' / , / / G E N E R A L • P R O D U C I
1 O N P R O P R E J . J M J E P A R E E A C H W r m I I S O
U S T R A n " A N T > " t : I " t : I ~ I : : ) S < N I F R
S I M P L E / S M A L L P L O W o r P H A S i S l P H A S ~
N E E D I D E N T I F I C A T I O N F E A S I B I L I T Y D
E C I S I O N C H O I C E O F A P P R O A C H H I R I N G C
A B I N E T D ' A R C H I T E C T D E S I G N C O N T R A C
T I N G F O J = ! C O N S m U C T I O N H I R I N G n S O U
S T R A I T A N T S ~ 1 J = ! r N G P I L O T E C O N S T R
U C T I O N C r n t r " f o r P r ' l p e r t y D e v e l o
p m e n t a n d H a n a g e l l l e n t l 1 l f ; r r o R n
~ ~ A M ' < 1 n r h p ~ t e r W i I J 1 0 0 E n g l ; m d ~
p P h • • e . B r i e f P r e s e n t i n g C r e d e n t i
a l s N e g o r l a l l n g A w a r d C o n t r ~ c t B a s
i c D e s i g n D e t a i l D e s I g n O b t a i n P e r m
i t O f ! C o n s t r u l r e W o r k i n g D r a w i n g s
C o o t r a d D o c u l T l f l n t a / J 8 8 c h o f n l o
l s S e p a r a l f ! e a c h w i t h n S o u s T l l I l t
a n t , E S I I I M l I n g T M l d e r i n g P o s t T a n
d a r N e g o t I a t i o n s A w a r d C o n l n t c t s P
r e s e n t i n g C r 8 d e n l l a l s N e g o t i a t i n
g A w a r d C o n t r a c t P r e p a r i n g B u y i n g O
f l n v e r y 0 1 ! = I e s o u r c e s C o n t t o A i n g
T e l t ' p h o n t ' 0 6 \ 2 0 0 ~ 2 5 5 / / / C A B I N E
T D ' A R O I I T E C T U R E ( M A I T R . E D ' O E U V R
E ' ) ~ D E S I G N I C O N S T R U C T I O N I N t t R F A
C E D C ! ! ~ ' C A B t N E T D ' A R C H I T E C T U R E (
M A m m D ' O E U V R E ) I I " I n l O T S S F . . P A R E
I I I " I I I E A O f W I T H n S 0 1 1 S T R A I T A N T S
C A B I N E T D ' A R C I I I T r £ T U R E ( M A I T R E D
' O E U V R E ) n I D T S S E P A R E E A C H w r r n O N E
s o n s T R A I T A N T > " C " C t T l Z t : I ~ l > l
INTEGRATING COMPLEXITY I.C. Jennings and R. Kenley
Faculty of Architecture, Building and Planning, University
of Melbourne, Melbourne, Australia Abstract Construction
industries are characterised by the use of an increasing
number of specialist firms for the procurement of
buildings and facilities. This phenomenon is accompanied by
corresponding increases in project complexity and
exacerbated by the temporary nature of project
organisations. To complement such differentiation of firm
scope into more refined specialities, explicit integration
of such firms in the formation and ongoing management of
the project organisation is required to maintained project
performance. Traditionally this function has been provided
by architects and principal contractors however, specialist
managers have begun to emerge from the range of
professional consultants to embrace the complexity of
this integrative role. This paper examines the emergence
of integration specialists within the context of the
construction industry's evolutionary development. In
particular, within the application of the systemic
approach, the role of integration for building project
organisations is discussed with project management as an
example. Keywords: building life span, complexity,
integrative role, project organisations, systemic
thinking, quality culture. Sommaire Les industries de
construction sont caracterises par I'usage qU'elles font
d'un nombre croissant de firmes specialisees dans l'
equippement du biitiment. Ce phenomene est en fonction des
augmentations correspondantes de complexite et de
specialisation des firmes industrielles de pieces
detachees, ceci allant de pair avec la nature temporaire de
I' organisation des projects. Pour complementer une telle
differentiation de I' envergure des firmes il est
necessaire que leur specialisation devienne de plus en plus
ramifee en specialisation; I'integration explicite de ces
firmes it I'interieur de la forrnatin et de la gestion
progressive de l' organisation de projet est essentielle
si les progres des travaux en copurs doirent continuer.
Cette fonction est traditionellement I' apanage des
architects et des principauz entrepreneurs, cependant des
organisateurs specialises commencent it emerger des rangs
des conultants professionei pour embrasser la complexite
du role d'integration necessaire aux projets. Cet expose
examine Ie deveioppement des specialistes d'integration en
tant qu'ecemple du developpement evolutionnaire de
l'industrie du biitiment. En particulier, it travers un
modele systematique, Ie role de l'integration dans I'
organisation des projets de construction sera discutee
avec la gestion des projets comme exemple.

The Organization and Management of Construction: Shaping


theory and practice (Volume Two).

Edited by D.A. Langford and A. Retik. Published in 1996 by


E & FN Spon. ISBN 0419222405.

340 Jennings and Kenley

1. Introduction

The increasing complexity of project organisations


established for building procurement

and use has been accompanied by a complementary increase in


the number and diversity

of industry specialists [1]. This industry characteristic


is a product of a market based

structure and highlights the need for management strategy


to cater for the growing com

plexity of projects and associated project organisations


[2] [3]. Traditionally the role of

managing project organisations has been fulfilled by an


interplay between project archi

tects and principal building contractors [4]. However, this


structure has begun to be

challenged by the emergence of specialist managers


fulfilling the role, for example, proj

ect managers [5]. The temporary associations of firms


which project organisations represent, has di

verted attention from the project organisation to the more


permanent, often more tangi

ble, component firms [6] [7]. These being the professional


practices and contractors

responsible for procurement, and having a relatively


constant structure. They subse

quently attract considerable attention from management as


they are readily studied,

modelled, and provide scope for the development,


implementation, and assessment of

medium and long-term management strategies. This phenomena


is seen in industry

firm-based schemes such as quality assurance, fair


tendering practices, distribution of

contractual risk and responsibility in subcontract


relationships. There is little question

that while focus on the component firms of the industry is


invaluable and can impact
significantly on a project's performance, attention on the
management of the temporary

project organisation is still necessary [8] [9]. The


paper commences with a brief discussion of the impact
which both the indus

try's structure and the complexity of building projects


have on the formation, manage

ment, and divestment of project organisations. This


introduces some of the characteris

tics of the project-based structure of the industry, and


provides the basis for discussing

the relationship between building life span and project


organisation. Within this scope,

the use of a systemic approach is presented. The approach


is subsequently considered

within an industry wide context which establishes the


importance of the role of integra

tion. Given this base, the emergence and role of project


managers as specialist project

integrators is discussed. The paper concludes with a


projection of the future role of

project integration given further increases in project


complexity.

2. Evolution of the construction industry

To study the construction industry and how it has and may


continue to evolve, requires

acknowledgment and appreciation of the cumulative affect


of the interaction between

industry components over time [10] [11]. This largely


takes the form of assessing how

the attributes of components relate, interact, and change


under both static and dynamic

conditions. From this understanding a distinct industry


profile can be created to provide
insight into the industry's organisation for ensuing
building procurement processes, and

how its component firms respond to the environment such as


to develop and maintain a

competitive advantage. It is from an interpretation of


these industry characteristics that

the role of integration in project management is discussed.

2.1 Characteristics of a contemporary construction industry.

The construction 'industry' consists of many markets and


projects rather than being an

industry in an hierarchical sense [12]. Narrowly it may be


perceived as being composed

of the individuals and firms concerned with the assembly


and construction of fixed Integrative role in building
procurement 341 Trading relationships with a market [16]
Example of the use of the project organisation as the
market place Figure 1. Industry market structure. Project
organisations embody a market place for firms to interact
i.e. trade their goods and services.

physical facilities. More widely, it is seen to embrace


suppliers who may have their

primary interests in other fields, and government and


financiers who set and administer

the rules and regulations with which the industry


interacts. Three major dimensions to

the complexity of project organisations can be identified:


firstly construction processes

utilise many specialities; secondly each project occurs at


an open, unique site; and

thirdly, project organisations are temporary. This fluid


structure dispels any notion of

applying purely hierarchical management and organisation to


project organisations but

rather, demands the adoption of a market and hierarchical


approach as exhibited in the

use of sub-contracted and internally supplied production


resources [3] [13] [14]. When

applying a market model, the determinants and processes of


creating and maintaining

relationships between market components (factors of


production) are considered vital.

The participants in procurement processes must similarly


establish relationships with

each other from positions separated by task and profession


boundaries [15]. The

boundaries, representative of competitive and practical


differentiation, must be perme

ated by the formation of relationships in the project


organisation if a useful association is

to occur [9]. This process of relationship creation


illustrates the role of managing re

sources in a market or project based environment. I A


prominent characteristic of the market model, that of the
temporary nature of proj

ect organisations, has become dominant in forming industry


perceptions, particularly for

clients. Clients regularly characterise the construction


industry as being fragmented

based on their relationship with consultants/contractors.


The client originates from a

position similar to that of a consumer and may therefore,


be considered as instigator of

the procurement process. However, few


consultants/contractors have the ability to sat

isfy all client needs without association with others. More


than one practitioner will be

required to provide the necessary project skills. If one


adopts an hierarchical approach,
similar to that of many other industries such as
manufacturing, an initial reaction would

be to expect that given particular client objectives,


processes will be quickly enacted to

fulfil the building or facility's specifications. To solely


adopt this expectation is

incorrect [3]. Using a market approach, project production


capacity is created by

assembling individual consultants and contractors from


independent positions for each

and every project. A new set of consultants/contractors and


relationships are therefore

created for each project, in other words, each project


represents a new market (refer to

Figure 1). This characteristic subsequently presents


clients with a seemingly unassociR.H. Coase in 1937
introduced the theory that alternatives to the market
mechanism for resource allocation exist in advocating
firms are one such alternative [18]. This notion of markets
(e.g. projects) and hierarchies (firms), was taken up by
microeconomics and in particular, transaction cost
economics in seeking to explain the economic affects of
internal and external organisational relationships [13]
[19]. 342 Jennings and Kenley

ated array of consultants and contractors from which a


project OIganisation must be

created. Hence, the fragmented and less orderly industry


characterisation. The action of creating procurement
organisations is complicated by a clients' relative

industry inexperience and lack of expert knowledge,


coupled with the potentially mis

leading expectation that the industry operates


hierarchically i.e. that there is a one-stop

shop selling buildings [7V Therefore, it is not until the


association between practitio

ners is made that a client has an organisation, or process,


that can respond to their

needs. This subsequently fuels perceptions of an already


fragmented industry, leading

to the interpretation of the market based attributes as


problems, rather than inherent char

acteristics of the necessary project structure [17V


Cumulatively, these attributes along

with other aspects such as fixity to site and project


uniqueness, result in project organi

sations being considered as temporary multi-organisations;


an exponent of a project or

market-based industry structure [21] [22]. This notion


plays a leading role in shaping

client perception of the construction industry including


the specific structure and man

agement of project organisations.

2. 2 Industry change-project complexity and specialisation.

Despite the range of possible evolutionary models used to


explain how and why a given

industry or system has evolved, there is little doubt that


the increasing complexity of

projects has and is still continuing to playa significant


role" Complexity as a concept

represents the quality or property of an organisation,


project, or more generally a

system, which is derived from the combined interaction of


the four determinants out

lined in Table 1 [23].

Table 1 Detenninants of system or project organisation


complexity. Generic determinants Project organisation
determinants with examples number of elements comprising
the system number of trades and/or consultants required,
scale of individual finns attributes of specific system
elements different belief structures and social affiliation
e.g. sentient differences between developer and planner
[24] number of interactions among system elements
regularity of group communication and action e.g. client
and site meetings, number of issued directives foreman per
day degree of inherent system organisation familiarity
with traditional versus a custom construction methods e.g.
trade versus activity based organisation This approach is
reminiscent of the traditional method of building
procurement where a client would engage architectural
services to conduct and manage all requirements for
procurement i.e. complete client agency. In other words,
the architect provided the one-stop-shop for
building/facility procurement. Fragmentation is an
attribute of the Australian and U.K. construction
industries that requires definition. It refers to the
relative concentration (%) of work conducted in a
particular industry by a selection of the largest finns.
In Australia the largest twenty finns are used as a scale
with approximately 22% of the work being conducted by
them, where as in mining approx. 68%, and
telecommunications 98% [20]. Various theories of
organizational evolution exist such as organizational
ecology and organisational systematics. The fonner seeking
understanding of dynamic interactions within and among
organizational componentry, the later presents a theory of
organizational differences to explain the processes by
which the practices and structures of organisations air
fonns persist over time [10]. Integrative role in building
procurement 343 Given adaptation of the above criteria to
assessing project organisations, it can be

readily concluded that construction projects are complex


and have manifested dramatic

increases in the diversity and number of specialists used


in project organisations [25]

[26]. Further-more, the potential diversity of such


projects is wide. Project organisa

tion complexity can subsequently be considered as


originating from its component

firms, the relationships between these firms, and/or the


organisations overall structure

and management [1] [27]. However, more generically,


project complexity can be

gauged by the variance and initial division or


differentiation within and between firms

that are destined to form the project organisation.


Various strategies are employed by industry members to
combat project complexity.

Firms, and on a larger scale professions, divide their


tasks into components that enable

specialisation e.g. engineering services may be divided


into mechanical, electrical, and

hydraulic. By reducing complex tasks to more manageable


parameters, work is

arranged in a manner that increases production certainty.


Therefore, by reducing the

number of elements of a system, more effort can be directed


to assessing the attributes

and relationships of the remaining elements [28] [29].


This enables a more complex

project to be tackled efficiently and effectively by


restricting scope of work by individual

producers to manageable limits. The differentiated market


structure of the construction industry implies, without

explicitly identifying, the vital role of integration. As


presented so far, increases in proj

ect complexity have been identified as causing an increase


in number and diversification

of specialist firms. This is accentuated by the competitive


opportunistic construction

environment which catalyses the creation of more distinct


comparative and therefore,

competitive firm boundaries in the form of further


specialisation [30] [31 V

Cumulatively, this has the effect of increasing the number


of relationships to be created

and managed in project organisations. This task of


creating and maintaining relation
ships between firms participating in a project
organisation, may be seen as an

integrative role-relationship management of system


componentry [32]. The importance of the integrative role
matching the complexity of projects has led to

its evolution into a specialist role, especially on more


complex projects. On smaller

projects the role of integration may be implicitly


conducted by task organisations such as

between architect and contractor howevet; on larger


projects specialist project managers

have emerged [4]. Similarly, integration as a task in


itself can be assessed using the

criteria of system complexity presented in Table 1.

3. The role of building procurement systems

The procurement process is undoubtedly the foundation on


which perception of the con

struction industry and therefore, the role of integration


is based. The previous section

presented the industry as an amalgam of specialist firms


that form temporary multi

organisations for individual project procurement. More


specifically, the practice of

managing project organisations is derived from the


individual attributes including objec

tives of specialist firms, project and firm integration


strategies, and the respective

objectives of the client. Therefore, rather than viewing


the construction industry as 'an

industry' with a relatively constant hierarchical


structure, a dynamic market model is

more appropriate. The impact of a market model on the


structure, organisation, and
integration management of project organisations is further
illustrated by examining the

impact of building maturation. The use of a systemic


approach to interpreting project

organisations and their associated integrative role is


presented.

5 Competitive opportunistic environments are a


characteristic of most capitalist based economies. In this
situation a primary motive for firms is the enhancement of
perceived competitive advantage to ensure their survival
and/or increased profitability. 344 Jennings and Kenley

3. 1 The building life span-stimulus for project


organisation evolution

facilities), requires the completion of many activities


that utilise a diverse range of skills

and material resources; all of which must be integrated


and managed by the project

organisation. This is complicated further by the varied


logistical time based relation

ships between associated firms-sequential, reciprocal, and


simultaneous inter-depend

ent relationships [35]. The influence of the time dimension


on firm and relationship

selection is derived from the corresponding completion of


project objectives. In-turn,

these objectives are a function of the buildings


progression through its life span i.e.

building maturation. The building's relative position in


its life span therefore plays a

deciding role in catalysing change in the project


organisation [33] [36]. Assuming the

objectives are relatively identifiable and discrete, the


evolving project, or building

organisation, can be categorised according to the phase of


the building life span it repre

sents. Table 2 outlines five key systems of activity


arising from corresponding building

phases.

Table 2 Building life span phases (derived from [33J and


[34]). conception the system which results in the decision
that the client needs to acquire real property to achieve
its objectives; inception the system of activity which
results in the client deciding upon the form their real
property which is required to achieve client objectives
should take; realisation the system of activity which
encompasses the design and construction of a building;
use the system of activity where the building is managed to
maximise the expectations of owner/occupant objectives i.e.
building considered as a factor of production by the
occupant and/or owner; refurbishment the system of
activity that develops and implements appropriate
refurbishment or divestment strategies to maintain
investment and occupational viability of a building or
alternatively, the system that determines the demolition or
sale of a building or facility i.e. divestment. The
objectives driving the project organisation evolve as the
building progresses

through its life span. Similarly, the project organisation


also evolves by altering the

number, type, and association of component firms to reflect


the changing objectives

(e.g. [37] [38]). This causes the structure of the


organisation and the role of integration

to change. Therefore, both the project organisation and


integrative role are dynamic.

Despite having some elements of the respective systems in


common, such as a developer

and architect through conception, inception and


realisation; or a property consultant and

occupant throughout use and divestment/refurbishment


systems; the required integration

of firms for each project are different. Therefore by


definition, it may be considered that
the evolution of the project or building life span, demands
a corresponding evolution in

the roles of the project organisation. Figure 2 illustrates


the sequential maturation of

project organisations as a function of the building life


span. Common system groupings

of procurement and use are highlighted [34].6 The effect


of the relationship between building life span and project
organisation

integration is well illustrated in the realisation system.


Firms required to commence the

realisation of a building or system are often carried over


from the previous inception

system e.g. architect, quantity surveyor and project


manager from concept design work. Note procurement is
linear where as the building use is cyclical. This model
can also be used to associate other useful characteristics
of the project life span such as the impact of short medium
and long term decisions e.g. life cycle costing and
assessment of long term investment feasibility.
Integrative role in building procurement 345 BUILDING
PROCUREMENT SYSTEMS Figure 2. Project organisation
evolution. BUILDING USE SYSTEMS

Building upon the initial selections, others must be


selected and subsequently integrated

for the project and the organisation to progress. As the


realisation system enters the

construction phase more firms will become associated with


few likely to depart. The

organisation then has a very large number of elements when


construction activity is at its

peak and most trades will be associated with a continued


involvement by professional

consultants remaining for supervision and certification


duties. This period of organisa

tional growth must also be associated with a period of


rapid leaming by the constituent

firms and managers (integrators) to ensure relatively


harmonious operation. This

involves both the firms leaming who and how they need to
work with others, and how

the integration managers may best facilitate these


relationships and disseminate project

objectives. As more of the project is completed natural


attrition of organisation members

occurs with subsequent changes in integration strategies.


The decline of project organi

sation membership will occur until the realisation of the


building has occurred or until

the next phase of the life-span is commenced.

3.2 Systemic modelling

As previously discussed, the increase in complexity of


projects has seen a dramatic

increase in specialisation and number of discrete firms


involved in project organisations.

Similarly, just as there are limits to production scope of


individual firms, there are limits

to the comprehension of the construction industry and its


structure. Our limited or

bounded rationality can be addressed through the use of


metaphors to provide a more

accessible representation of a given case [39] [40].


Different ways of designing, inter

preting and managing organisations can be developed using


ready-made metaphors for

organisation that would have otherwise not been considered.


Further-more, metaphors

relieve managers of the necessity to comprehend and debate


their ontological position
(philosophical theory of knowledge) and methodology, but
rather provide a way of

thinking that can be readily adopted [41]. This paper


proposes the use of a systemic

approach derived from the organismic metaphor for


interpreting project organisations as

part of the integrative role. The consideration of


integration as a function of the complexity of project
organisa

tions (derived from the organisations temporary nature and


building maturation), helps

in identifying the complexity of the role. However, it does


not provide a structure to

interpret such complexity for development of management


strategy. A systemic method

may achieve such clarity. Systemic thinking involves a


means of interpreting a given

phenomena, such as in this case, the integrative role in


project organisations. This is

achieved through the identification and consideration of


all possible significant elements

which contribute to the organisations fulfilment of


objectives and also act as determi

nants of complexity [42]. These elements mayor may not be


explicitly included in the

organisation. A relationship will however, be formed


between them and the project

regardless of their orientation in order to achieve


objectives. The notion of a systemic approach advocates
not only the representation of the proj

ect organisation as a dynamic model, but also the


incorporation of human and cultural 346 Jennings and
Kenley issues often not included in traditional management
strategy. The recognition of nontechnical considerations
highlights the considerably more complex integrative role
through the incorporation of elements such as events,
patterns of behaviour, systems, and mental models [42].
Further-more, given that the integration of firms occurs
via a human interface, recognition of human
considerations is not only logical but vital. The systemic
approach facilitates the integration of technical with
non-technical attributes of an organisation through the
recognition and gradual approximation towards a quality
culture. This culture unites both the reasoning of systems
thinking with the ongoing search for reliable options in
enhancing standards of quality and productivity as
presented in total quality and productivity management
[43]. Table 3 Towards a systemic quality culture (derived
from [43]). Tools Systems thinking Cybernetic
interpretation Synergetic endeavour Concept Outcome the
representation of the phenomena the organisations
responsible for the procure in question as a discrete
unit or and use of a building being considered as sys
system in order for ready understandi.e. the systems and
sub-systems of the bui ing and assessment of its change
in life span ego refer to Table 2 or Figure 2 dynamic
situations acknowledgment of the functional presence of
the intrinsic concept of feedback in human thought and
action devising and determining individual and colle
performance mechanisms to assess the fulfil of objectives
e.g. cash flow monitoring and agement, site meetings the
functional presence of the acknowledgment of the
collectives role and re~ intrinsic concept of ~ sibility
of project organisation member, (cooperation's need) in
the human procuring a building or facility i.e. adequate
mind for making possible individual formance can only be
achieved as a functio survival e.g. reflection of the
whole many elements in harmony rather than in isoJ; being
greater than the sum of the e.g. design team, site
management tearr parts. foreman, leading hands etc.
(Mohsini 1989) More practically, the representation of a
'systemic' quality culture and transposition to an
illustrative model for organisation assessment and design,
is achieved through the utilisation of three intellectual
tools: systems thinking, cybernetic interpretation, and
synergetic endeavour [43]. A description of the concepts
espoused by the theories and their implications for the
project organisation are presented in Table 3.
Systemically interpreting the procurement organisation
involves considering the organisation as a system open to
its environment. Hence the systems approach builds on the
"principle that organisations, like organisms, are open to
the environment and must achieve an appropriate relation
with that environment if they are to survive" [40]. This
metaphoric foundation provides a foundation to launch
investigation and discussion based on the importance of
identifying the relationships between elements, and the
impact of the elements interaction. This can be transposed
to issues such as how the project organisation may evolve
over time; what attributes and strategies of the project
are responsible for particular outcomes; and what role do
the external and internal elements related to the project
organisation play in characterising its performance. A
systemic approach helps to clarify both the static and
dynamic properties of the

construction industry, and how the role of integration may


be implemented in project

organisations. In particulru; through its ability to


clarify and order complexity, application of the systemic
approach is seen as advantageous for integration
management.

Though the range of cases to study are all very rich in


material, the majority of past

organisational analyses focus on the realisation system as


opposed to other forms of the Integrative role in building
procurement 347

project organisation exhibited throughout the building life


span i.e. the design, docu

mentation, and construction of a building or facility. 7

4. Project integrators

The application of a systemic model involves more than


representing an organisation in

terms of interrelated subsystems defined by task, or wholes


within wholes to infer the

interdependence of components within an organisation.


Though this is an important

aspect in representing a phenomena such as a project


organisation systemically, the

complexity of integration will not be accurately


represented without the consideration of

the system's attributes. The development of specialist


integrators such as project man
agers is a direct response to the need for accurate and
strategic management of such

attributes. Following is a brief outline of some of the


salient issues concerning the role

of integration, the application of systemic thinking and


the development of integration

management in the future.

4.1 Project managers: the specialist integrator

In practice the role of integration varies depending on the


complexity of a given project.

It may be an explicit role assigned to a particular


individual or firm that involves coordi

nating relationships between firms (external to the firm),


or it may be part of the role of

members within one firm to assure assimilation of task work


within their firm or work

group [3]. This general example can be readily related to


the construction industry as

illustrated in the following examples of integration:


residential, and large commercial

projects. A large residential project may involve an


architect, client and contractor. As a con

sequence of these three, the client objectives,


architectural design and specification, and

contractors method and means of construction, are all


brought together to form the

project organisation. The role of integration is more


heavily placed on the architect

during the design and documentation of the residence,


where as the contractor plays the

larger role of integration during construction.


Procurement can therefore be considered
as consisting of two relatively distinct systems: design
(managed by architect), and con

struction (managed by contractor). The roles of both


parties involve integration, with

the burden of the role shifting between architect and


contractor to suit the maturation of

the building i.e. match the correct profession to the


required expertise of the building

phase. The roles of ordering tasks, monitoring, and


assigning resources-system,

cybernetic, and synergetic considerations-must therefore be


coordinated between these

two parties. Large more complex projects tend to attract


the use of specialised integrators. In this

case, the responsibility of integration and the management


of client objectives is not un

dertaken by task related consultants such as architects


and quantity surveyors whose role

is limited to the traditional form of their professions.


The reasons for the use of

specialist managers are largely related to project


complexity presented earlier (refer Table

1). A common example necessitating specialist managers is


seen in a complex project

organisation where there are a large number of firms


involved i.e. the mUlti-organisation

nature of project organisations [21]. This will most


likely necessitate numerous

specialist integrators such as a construction manager,


design manager, and an over

seeing project manager along with the traditional


managerial roles conducted in firms

such as foremen for construction, and project architects


for design. The difficulty in in
tegrating highly disparate firms may also necessitate an
integrator to provide The past decade has seen a dramatic
increase in the appreciation of the value of effectively
managing the use phase of a building life span. This has
been illustrated by the rise to prominence of the
facility management profession that specialises in managing
buildings and facilities to ensure effecti ve and
efficient use and investment return.

348 Jennings and Kenley

communication between such firms as acoustics engineer,


information technology

consultant, etc.. However, specialist managers may also be


vital to ensure the correct

representation and achievement of client objectives given


the probable conflict between

individual objectives of the project organisation's


component firms and the client's

objectives [45] [46]. The examples above primarily relate


to the role of integration once a project is run

ning (the dynamic role of integration), however


integration also plays a vital role in the

design and planning of the project organisation [38].


Transaction cost economics is

particularly useful in this case as it provides tools for


assessing the relative benefit or

cost of intemal versus extemal relationships for


production i.e. illustrated by the make

or buy scenario. U sing such a methodology, one may


compare the technical and

economic cost of managing inter-firm relationships either


independently or using another

party as facilitator [9]. Project managers seen as


specialists are used when their benefits

exceed their costs. In other words, through the creation


and/or enhancement of working
environments and operational relationships between firms,
project managers primarily

facilitate others' work rather than conducting 'work'


themselves.

4.2 The future for project integration

Project management has developed along with an increasing


awareness of the key

success factors that clients apply to building projects.


Better coordination of the

disparate component firms was quickly recognised causing


project management to

develop into a central and overall coordinating role as


agent for the client. Methods to

manage time, quality, and cost were soon developed and


adopted as part of the project

management role e.g. scheduling, developing


work-breakdown-structures, cost control,

quality assurance, contract administration etc. [47].


Though many of these activities

reflect the scope presented by the systemic model such as


the cybemetic and systems

considerations, they do little in representing and


applying the synergistic properties of

the project organisation, a property of human endeavour


often left untapped in manage

ment strategy. The concept of synergetic relationships


demonstrates the necessity and value of

managing the relationships between elements in order that


the product, and the added

value from the relationship will occur. However, the


expertise created by specialisation

stimulates the development of sentience by individual


firms to their professions i.e.
affiliation to professional groups and associations [24].
This causes a strengthening in

the differentiation between the firm and the rest of the


environment. Their specialisation

provides the ability for the firm to increase their


effectiveness and efficiency in produc

tion, however their product, be it material or service,


will still have to be integrated with

outputs from other firms. To bring such strongly


differentiated firms together is both

necessary for their products to be used and so as not to


waste the benefit of their spe

cialisation [3] [9]. A role of integration is to ensure


that synergistic potential is not

wasted. However, skills will develop over time for greater


integration of factors that are

important in facilitating synergy despite sentient, social,


psychological, technical, and

organisational differences between component firms. An


additional benefit of adopting a systemic approach that
facilitates system, cyber

netic and synergetic properties of project organisations


in integration strategy, is to

provide a catalyst for organisational learning. A degree of


success can be achieved in

initial planning and design of the procurement


organisation, but the ability to learn and

adapt is vital if a quick response to any disturbance is


to be readily achieved, or to

conceive opportunities for increasing efficiency and


effectiveness [48]. This can be

facilitated by the strategy of assimilating and managing


firms by groups, associated,
directed, and managed by task rather than discipline [49]
[50]. In such cases, objectives

of the project would be suitably rephrased in terms for


multi-disciplinary work teams

based on their relative significance in production. This


exposes the firms to the

synergetic nature of their work and therefore contributes


to instilling a greater sense of

work responsibility. Integrative role in building


procurement 349

5. Conclusion

The proliferation of specialists in the construction


industry, has led to a dramatic

increase in the number of discrete firms involved in


project procurement organisations.

Just as there are limits to the production scope of


individual firms, there are limits to the

comprehension of the construction industry and its


structure. The systemic approach

assists in providing an interpretation of the complex


social and technical interplay

between firms in the industry and within project


organisations by stressing the necessity

for explicit recognition and application of the


integration role. The specification and

subsequent management of integration is derived from a


large variety of factors that

impact significantly on this role and project performance.


Several factors stand out:

location of work at sites, complexity of buildings and


facilities, specialist diversity, the

temporary nature of the project organisation, and the human


interface of firms. The
demand for integration, and the form in which it is
presented (e.g. project managers),

will continue to develop and change to suit the industry.


However, greater reliability of

management performance is assured with increases in


explicit appreciation of the com

plexity of the role through the use of a systemic quality


culture, whether integration is

achieved by a specialist or as part of shared


responsibility between firms.

2. Betts, M. & Ofori, G. (1992) Strategic planning for


competitive advantage in construction. Construction
Management and Economics 10: pp. 511-532.

3. Gunnarson, S. & Levitt, R. E. (1982) Is a building


construction project a hierarchy or a market? Project
Management Tools and Visions, Projektplan, Copenhagen.

4. Ball, M. (1988) Rebuilding construction· economic change


and the British construction industry, London, Routledge.

5. Voropajev, V. & Scheinberg, M. (1992)


Project-management methods and tools for the 21st century:
the SOVIET view. International Journal of Project
Management 10(4): pp. 253-257.

6. Davidson, C.H. & Mohsini, R.A. (1990) Effects of


organizational variables upon taskorganizations'
performance in the building process. Building Economics and
Construction Management, University of Technology Sydney,
Sydney.

7. Mohsini, R. & Davidson, C.H. (1986) Procurement,


Organizational Design and Building Team Performance: a
Study of Inter-Firm Conflict. CIB. 86 Advancing Building
Technology, Washington, D.C.

8. Winch, G. (1987) The construction firm and the


construction process: the allocation of resources to the
construction project. Managing Construction Worldwide, E. &
F. N. Spon, London.

9. Winch, G. (1989) The construction firm and the


construction project: a transaction cost approach.
Construction Management and Economics 7: pp. 331-345.
10. Baum, J. A. C. & Singh, J. V. (1994) Organizational
Hierarchies and Evolutionary Processes: Some reflections
on a theory of organizational evolution. Evolutionary
dynamics of organizations, (eds. J. A. C. Baum and J. V.
Singh), New York, Oxford University Press, pp. 3-20.

II. Jantsch, E. (1975) Design for evolution:


self-organization and planning in the life of human
systems, Braziller, New York.

12. Groak, S. (1992) The idea of buildings thought and


action in the design and production of buildings, E. &
F.N. Spon, London.

13. Williamson, O. E. (1975) Markets and hierarchies,


analysis and antitrust implications: a study in the
economics of internal organization, Free Press, New York.

14. Williamson, O. (1979) Transactions cost economics: The


governance of contractual relations. Journal of Law and
Economics 22: pp. 223-261.

350 Jennings and Kenley 15. Pries, F. & Janszen, F. (1995)


Innovation in the construction industry: the dominant role
of the environment. Construction Management and Economics
13: pp. 43-51.

16. O'Brien, M.J. & AI-Soufi, A. (1993) Electronic date


interchange and the structure of the UK construction
industry. Construction Management and Economics, II, 6,
pp. 443-453.

17. Grmik, S. (1994) Is construction an industry?


Construction Management and Economics 12: 287293.

18. Coase, R.H. (1937) The nature of the firm. Economica


N.S., 4, pp. 386-405.

19. Williamson, O. E. & Winter, S. G., Eds. (1991) The


Nature of the firm: origins, evolution, and development,
Oxford University Press, New York.

20. AB.S. (1994) Year Book Australia 1995, Australian


Bureau of Statistics, Canberra.

21. Cherns, A. B. & Bryant, D. T. (1984) Studying the


client's role in construction management. Construction
Management and Economics 2: pp. 177-184.
22. Hillebrandt, P.M. & Cannon, J. (1990) The modern
construction firm, The Macmillan Press Ltd., London.

23. Schoderbek, P.P., Schoderbek, e.G. & Kefalas, A., G


(1990) Management systems: conceptual considerations, BPI
Irwin, Boston, Ma.

24. Miller, E. J. & Rice, A. K. (1967) Systems of


Organization The control of task and sentient boundaries.
Tavistock Publications Ltd., London.

25. Bennett, J. & Ferry, D. (1990) Specialist contractors:


A review of issues raised by their new role in building.
Construction Management and Economics 8: pp. 259-283.

26. Mohsini, R. A & Davidson, C. H. (1992) Determinants of


performance in the traditional building process.
Construction Management and Economics 10: pp. 343-359.

27. Mintzberg, H. (1979) The structuring of organisations,


Prentice-Hall. Englewood Cliffs, N.J ..

28. Mansfield, R. (1986) Company strategy and


organizational design, Croom Helm, London.

29. Raftery, J. (1994) Risk analysis in project


management. E & F.N. Spon, London.

30. Porter, M. E. (1980) Competitive strategy: techniques


for analyzing industries and competitors, Free Press, New
York.

3 I. Porter, M. E. (1985) Competitive advantage: creating


and sustaining superior performance, Collier Macmillan,
New York.

32. Lawrence, P.R. & Lorsch, J.W. (1986) Organization and


Environment: Managing Differentiation and Integration,
Harvard Business School Press, Boston Mass.

33. Walker, A. & Hughes, W. P. (1986) A


conventionally-managed project: a systems-based case study.
Construction Management and Economics (4): pp. 57-74.

34. Jennings, 1. C. & Kenley, R. (1995) A systemic


interpretation of the building procurement system.
Australian Systems Conference, Perth, Western Australia,
Edith Cowan University.

35. Walker 1989, Project Management in Construction,


Collins, London.

36. Walker, A & Hughes, W. P. (1984) Private industrial


project management: a systems-based case study.
Construction Management and Economics (2): pp. 93-110.

37. Laufer, A., Howell, G. A. & Rosenfeld, Y. (1992) Three


modes of short-term construction planning. Construction
Management and Economics 10: pp. 249-262.

38. Shapira, A. & Laufer, A. (1993) Evolution of


involvement and effort in construction planning throughout
project life. International journal of project management
11(3): pp. 155-164.

39. March, J.G. & Simon, H.A. (1958) Organizations, John


Wiley and Sons, New York.

40. Morgan, G. (1986) Images of organization, pp. 44-45,


Sage, London.

41. Green, S. D. (1992) Sociological paradigms and


building procurement. East meets West Procurement Systems
Symposium, Hong Kong, Department of Surveying, Hong Kong
University.

42. Senge, P.M., Roberts, C., Ross, R.B., Smith, B. &


Kleiner, A. (1994) The fifth discipline fieldbook,
Nicholas Brealey Publishing Ltd, London.

43. Elohim, J. L. (1994) The systemic, cybernetic and


synergetic alternative in quality management. Systems
Research 11(1): pp. 15-45.

44. Mohsini, R. A. (1989) Performance and Building:


Problems of Evaluation. Journal of Performance of
Constructed Facilities 3(4): pp. 235-242.

45. Davidson, C. H. & Mohsini, R. (1987) Building


procurement a strategic organization and management
decision. Managing Construction Worldwide CIB W-65 The
organisation and management of construction 5th
International Symposium, E. & F.N. Spon, London.
Integrative role in building procurement 351

46. Walker, A. & Hughes, W.P. (1987) A project managed by a


multi-disciplinary practice: a systemsbased case study.
Construction Management and Economics, 5, pp. 123-140.

47. Knoepfel, H. (1992) Theory and practice of project


management in construction. International journal
o/project management, 10,4, pp. 243-252.

48. Checkland, P.B. (1980) The systems movement and the


'failure' of management science. General systems, 25, pp.
55-61.

49. Baird, A. (1991) System orientation for the project


team: the key to greater customer satisfaction,
International journal o/project management, 9, 2, pp.
86-89.

50. Lansley, P. R. (1987) Corporate strategy and survival


in the UK construction industry. Construction Management
and Economics 5: pp. 141-155. TOTAL RESOURCE ASSESSMENT
BASED ON EXTENSION OF TRADITIONAL PROCUREMENT SYSTEMS
c. Elliot Department of Building Engineering and
Surveying, Heriot Watt University, Edinburgh, UK Abstract
All buildings are composed of a combination of raw
materials and energy. Present systems evaluate these
resources in terms of cost and measure that cost against
the benefit derived from the building. However increasing
emphasis on environmental issues means that this system
of evaluation is no longer adequate as it makes no true
assessment of the resources used. This paper aims to
provide an alternative system of evaluation that can be
incorporated ink} cxisting procurement systems by extending
the use of the bill of quantities to encompass total
resource assessment Keywords: total resource assessment,
nlW materials, energy, embodied energy, evaluation of
resources, sustainable development, bills of quantities.

Toutes constructions contiennent les materiaux bruts et


I'energie. Miantenant les methodes d'acquisition des
constructions evaluent ces ressources seulement en fonction

du cout fiscal. lis comparent Ie cout fiscal avec I


'avantage de la construction. Cependant

la vie modeme aCL'entue les matieres de I'environnement et


cette methode d'attaque du probleme est insuffisant, parce
que son estimation des ressources utilisees est imparfait.

Cet article presente une technique nouvelle d'evaluer les


ressources qui peut etre

utilisees par les methodes d'acquisition. La technique


etend Ie devis pour comprendre

tous les ressources, fiscal ou non. Introduction


Definition: Total resource assessment is the evaluation of
raw materials, energy, waste

and pollution used or gcncrated by the construction of a


project.

Any building is composed of re.'IOurces taken from the


environment. Under existing

procurcment methods these resources have no real basis of


assessment other than the

cost of the building. Cost however, being a factor of both


market forces and

government control, is an artificial measure against which


to assess resource use, which

has a very large environmental impact. A more realistic


system would be to make an

assessment based on the resources that have actually been


used,

This paper analyses a project by assessing the resources


used in its construction. The

paper further indicates how a rating system can be used to


allocate to buildings an

environmental factor based on resource usage. It is


intended that this total resource

assessment could be used as a standard against which to


compare the environmental

performance of different projects.

2 Resources

Resources come from two sources, raw materials and energy.


The output of using

energy to extrdCt and convert materials into building


products and then buildings is

pollution and waste. In assessing resources we need


therefore to look at these four
basic factors. That is; raw materials, energy, pollution
and waste.

Th~ Organization and Management of Construction: Shaping


theory and practice (Volume Two).

Edited by D.A. Langford and A. Retik. Published in 1996 by


E & FN Spon. ISBN 0 419 22240 5. Total resource assessment
353

2.1 Raw Materials

The current method of examining raw materials is through an


assessment of cost and

quality. Generally, once the level of quality has been


established through either national

standards, client preference or architectural


specification, then the lowest cost is sought.

In terms of total resource assessment this is meaningless


and a truer means of

evaluation would include a measure of sustainability,


length of life and degree of reuse.

None of these three items are difficult to evaluate since


a large body of knowledge

exists for most products used in the construction industry.


It is known that timber taken

from the rain forests is not sustainable and that softwoods


can be replaced at a much

faster rate than hardwoods, and that the average life of


floor coverings is between 10 to

20 years. In addition current research into re-use of


materials highlights that steel can be

effectively recycled but that recycling of plastic is much


more difficult. It is therefore

possible, based on sustainability, length of life and


degree of reuse to rate all the raw

materials used in a construction project. This idea is not


far from the system of green
labelling that is presently corning to the fore. When the
advances that have been made in

food labelling over the last 15 years are considered it


must be recognised that for

manufacturers to state the contents of their products or


to rate them based on a pre

determine scale is by no means a difficult task and one


that could be achieved in a

relati vely short space of time.

2.2 Energy

The diagram below shows the definitions of energy as


commonly used. Energy can be

primary energy as mined, delivered energy which is that


delivered to the consumer, or

embodied energy, which for construction is defined as the


energy consumed in the

production, delivery and fixing of products on the site.


For the purposes of analysing

resources it is necessary to calculate the amount of


embodied energy that goes into the

materials that make up the project. This is shown in the


diagram. CONSTRUCTION PRODUCTS MANUFACTURE CONSTRUCTION
SITES TRANSPORT OF Figure 1 Common definitions of energy

354 Elliot and Palmer

Howard (1991) argued that there is scope for energy


improvement in construction

through the substitution of materials with those of lower


embodied energy. The

building products sector used 11.5 % of total industrial


energy consumption in 1984

and considering that iron and steel were excluded from this
calculation it is probable that
the potential saving achievable is significant. Connaugton
(1987) compared energy

usage in buildings with the saving that could be made by


examining the embodied

energy and argued that the production of materials can


take five times more energy than

is used in running the building for the first year. Brennen


(1995) also concluded that a

typical industrial building consumes more energy in its


construction than through its

entire life. Connaugton suggested estimating the embodied


energy value of a building

over a range of different building types by analysing


bills of quantities and devising

material coefficient per m2 of floor area for each


building type. In effect he recognised

that to calculate the embodied energy value in buildings is


a fairly simple process. It is

made easier by the fact that a small number of building


materials account for a large

proportion of the total embodied energy of a building.


Stein et al (1981) also recognised

this and outlined that only eleven industries contribute


more than 50% of energy

requirements for new construction. Examination of these


products will therefore

encompass a large percentage of the total energy used.


This means that by selecting the

major quantities of material from a bill of quantities it


is possible to calculate a large

proportion of the embodied energy used in the construction


of the building. This

calculation could then be used as a mean of comparing or


rating different alternatives.
For, as Connaughton said," a comparison of the energy
intensity of different building

assemblies ... can provide the basis by which the embodied


energy of construction may

be reduced by material component substitution at the


design stage."

(It should be noted that the figures quoted above do not


relate to the embodied energy

per unit of material but to the overall quantity of the


material, and therefore overall

energy, used in the building.)

2.3 Pollution

One of the major pollution problems caused by the


manufacture of building products is

the emission of C02 and the subsequent environmental damage


this causes. Howard

illustrated that the amount of C02 generated relates to


fuel used in the creation of the

material, and the main scope for reducing this comes from
substituting materials with

lower embodied energy. He also calculated the amount of


carbon dioxide release in the

manufacture of a kilogramme of each major construction


material. As there is a

relationship between the amount of embodied energy and the


amount of C02 emission,

the group of materials responsible for the largest


percentage C02 emission is the same

group that contributes the largest proportion of total


energy used. As such the figures

for C02 emissions when applied to the major quantities of


materials in the BQ will
account for a large percentage of the total C02 emission
caused by the manufacture of

components and construction of the building.

2.4 Waste

The Dutch Building Research Foundation defined building


waste as all materials,

auxiliary materials and packaging supplied in connection


with the realisation of the

building project, which must be removed from the building


site as useless, during or

after the realisation of the project.

Verschuren et al (1987) argued that the first signs of


waste appear on the designers

drawing board and he developed an index that measures waste


by valuing design and

construction aspects of projects. From this he calculated


a waste index which is an

estimate of the waste to be expected on a project. The


waste index is calculated over the

whole building based on a total of 65 factors relating to


design and construction. Total resource assessment 355

Moavenzadeh (1994) outlined that with any waste there is a


hierarchy of preference;

Control it at the source by changing the material or


production technique.

Recycle it.

Treat it.

Dispose of it.

In terms of evaluating a building for the amount of waste


produced,Moavenzadeh's

work is much simpler than the waste index of Verschuren,


as it is possible to rate major
groups of materials depending on whether they can be
recycled or must be disposed of.

However in making such an assessment it is necessary to


include some calculation of

the energy required to recycle the product. As such the


evaluation of waste is probably

the most difficult of all of the four aspects under


examination in this paper, in that it

relates to the design, materials used and the nature of


manufacture. For this reason no

evaluation of waste is included in the total resource


assessment outlined below.

However if total resource assessment is to be fully


developed it is necessary to include

some allowance for waste.

3 Using the BQ as a means of total resource assessment

A bill of quantities for a factory extension was the basis


for the total resource

assessment. The work involved breaking out the existing


surface and constructing a

single storey steel framed building with trussed roof and


external steel profiled cladding

with roof lights. Substructures were mass concrete filled


bases with a reinforced

concrete floor.

As outlined above three items were to be considered in the


total resource assessment;

namely embodied energy, pollution in the form of C02


emissions and finally the raw

materials used. These are examined below.

3.1 Embodied energy and C02 emissions


As outlined above major product groups contribute a large
percentage of total energy

used and these quantities were therefore extracted from the


BQ. [Quantities of material extr~cted f~om the BQ--------1
1_ Hardcore . conc;~;~-t· _m Ste~;u Brick TSOftWOOd r
-~'-'--, I I 1115m3 180lm3 238tn 14m3· 10m3 i 7m3
IQu~;;tities in-;-OOO Kg ____ ~~=___________ --=-1 1784 I
2701.5 J 238 I 31.5 i 6.1 I 14 Table 1 Major materials
extracted from the bills of quantities

Figures of embodied energy values and C02 emissions were


then collated. Embodied energy content Mj/Kg -I I=::~~ore
G~!e r~¥~TS~ft;::Bl~ckl Table 2 Embodied energy values

356 Elliot and Palmer

In order to evaluate the energy content and C02 emissions


of the materials used it is

necessary to have some means of comparison or standard.


However at present no

standard is available so this paper has compared the


project as designed and built with

the same building but substituting the steel frame for a


reinforced concrete frame. The

recalculated quantities are shown in Table 4 below.


Quantities of material with reinforced concrete frame
Hardcore I Concrete I Steel I Brick j Softwood I Block
1115m3 I 2585m3 I 73tn I 14m3 I 10m3 I 7m3
Quantities in '000 Kg I 1784 I 3877.5 I 73 I lliI
6.1 I 14 Table 4 Major quantities using a concrete frame

A comparison of the embodied energy and C02 emissions is


shown in Table 5 and

Figure 2. As Designed and Built (steel) With Concrete


Frame Embodied energJ CO2 emitted Embodied energJ CO2
emitted Material content Mj Kg content Mj Kg Hardcore
1,784,000 178,400 1,784,000 178,400 Concrete 2,701,500
270,150 3,877 ,500 387,750 Steel 11,900,000 1,190,000
3,650,000 365,000 Brick 315,000 3,150 315,000 3,150
Softwood 30,500 1,220 30,500 1,220 Block 28,000 1,400
28,000 1,400 Total 16,759,000 1,644,320 9,685,000 936,920
Table 5 Comparison of steel and concrete frame Embodied
energy; steel and concrete frame
20000000,-------------------------------, 15000000
10000000 D Steel •. Concrete 5000000 o Figure 2
Embodied energy content for steel and concrete frame Total
resource assessment 357 C02 Emissions; steel and concrete
frame 2000000,-------------__________________ ~ 1500000
o Steel 1000000 • Concrete 500000 o Figure 3 C02
Emissions for steel and concrete frame

4. Making a total resource assessment

Having examined the raw material, energy and C02 emISSIOns


a total resource

assessment can be made for the project. As outlined above


the important items with

regard to the raw materials is sustainability, length of


life and re-use. These three items

have been rated on a scale of 1 to 10. A rating of 1 means


poor sustainability and re-use

whereas 10 represents a sustainable source that is


completely recyclable. Sustainability

is based on the sustainability of the source and the


quantity available. In the interests of

simplicity rating of materials has been carried out only on


the major materials. Energy

and pollution are rated on the basis of the percentage


improvement that could be

achieved by an economically viable alternative which in


this case was judged to be a

reinforced concrete frame. (It could be argued that a


timber frame is also a viable

alternative but it was viewed that the fire protection


could not be adequately achieved.) Steel frame Concrete
frame I ~ Materia Quantit Sus'ity Reuse Total Quantit
Sus'ity Reuse i Total

358 Elliot and Palmer

In the example above the average rating per kilogramme of


material used was calculated

along with the quantity of carbon dioxide emissions and


energy used. For the latter two

a figure was derived showing the percentage of the total


energy and C02 emissions that

could be achieved by using a viable alternative design.


That is only 58% of the energy

and 57% of carbon dioxide generated by the steel frame


would be used or generated if

the design was changed to concrete. Although there is


little difference between the two

buildings in terms of financial cost the calculations show


that the steel framed structure

is much more energy intensive, produces more carbon dioxide


and is less sustainable.

If the quantity of materials is viewed in relation to the


amount of energy used and the

degree of pollution produced and these are used as


multiplying factors for the resources

used a steel building has a rating of 12.65 to 4.16 of


concrete. That is, on this scale the

steel frame is a much worse use of resources.

The paper does not suggest that these figures can be taken
as anything other than a

guide to the materials used and an illustration that total


assessment of resources using

the BQ is fairly easily achievable.

5 Conclusion.

Moavenzadeh said that in a market economy those which


produce at the lowest cost

carry the greatest burden and therefore while this system


remains then there is no

incentive for the environmental cost of construction to be


considered. The free market
alone without government intervention does not compel
producers to carry the full

burden of their actions. It is necessary therefore for


systems to be developed that can

assess the total resource assessment of building


construction.

Global environmental awareness and impact measurement is


now becoming a mature

area of research. At present the most useful tools


available are Building Research

Establishments Environmental Assessment Methods (BREEM)


which environmentally

assesses residential and various types of commercial


property. The system is based on

applying a checklist of facilities and standards to


properties. Another method of

assessment is local environmental impacts which are less


easily identifiable and require

considerable qualitative analysis. Both these systems


however although attempting a

more global assessment of construction are still failing


to recognise the resource use,

which is ultimately a global problem.

This paper has attempted to illustrate that by using the BQ


it is fairly simple to make an

assessment of the materials and energy used in a project


along with an estimate of the

carbon dioxide emissions produced. The system as outlined


is fairly crude, largely due

to a lack of available data, however it could be developed


relatively quickly. Naturally it

will only compliment existing methods but as some clients


are already interested in
greener developments or at least in promoting a green image
there is a need for change.

There is no doubt that energy content and environmental


assessment will have to be

considered much more in the future and methods that can


evaluate this need to be

considered now in order to meet this future need.

The system suggested by this paper is in effect a


combination of the macro and micro in

that it examines the building at the micro level but by


making a total resource

assessment assesses the material use at the macro level.


The intention of the paper is to

show that the existing system of procuring construction


work in Britain could very

easily be adapted to make a much broader resource


assessment than it does now.

Ultimately governments may produce a rating within which


construction projects must

comply. By feeding back data taken from the BQ, typical


ratings could be calculated

therefore avoiding abortive design work. Total resource


assessment 359

2 Connaugton IN. The energy cost of construction crn


Fourth International Symposium on Building Economics.
Copenhagen 1987 pp. 171-184

3 Brennan, J. Embodied energy in buildings. Resurgence Nr


169 March/April 1995 PPAO-45

4 Stein, R.G. et al Handbook of energy use for building


construction. US Department of Energy 1981

5 Dutch Building Research Foundation Publication nr 123

6 Verschuren, C. Peter &. Spekkink, D Waste costs in


housing construction projects; methods for calculating the
waste index. crn Fourth International Symposium on
Building Economics. Copenhagen 1987 pp. 80-91

7 Moavenzadeh, F Global Construction and the environment.


Wiley-Interscience 1994 ISBN 0-471-01289-0

8 Building Research Establishment (1993) BREEAMINew


Offices: Version 1193 BRE, Watford

THE RELATIONSHIP BETWEEN

CONSTRUCTION PROCUREMENT

STRATEGIES AND CONSTRUCTION

CONTRACT DISPUTES

J.T. Conlin and D.A. Langford

Department of Civil Engineering, University of Strathclyde,

Glasgow, UK

P.Kennedy

Department of Building and Surveying,

Glasgow Caledonian University, Glasgow, UK

Summary

This paper details and discusses the results of research,


funded by the Engineering and Physical

Sciences Research Council (EPSRC) and jointly run by the


University of Strathciyde and Glasgow

Caledonian University, and which has been set up to examine


the sources, causes and effects of

disputes in the construction industry in the United Kingdom.

It has been found from the results obtained from the


research so far that there is a correlation between

the type of procurement method adopted and the types and


frequencies of disputes occurring.

Twenty-one recently completed projects were analysed


covering five main procurement options
currently in use in the United Kingdom. The sample returned
483 individual dispute events.

In addition to identifying the frequency and type of


dispute found on particular procurement options

the research has also identified which member of the


project team instigated the dispute and what the

main effects of each dispute were on the project.

It is hoped that the results of this research will provide


the industry with a suitable benchmark for

assisting in assessing the risks associated with particular


procurement options as well as creating an

increased awareness, among the project team members, of


likely dispute types and frequencies.

Keywords: Procurement Strategies, Contract Disputes,


Sources of Conflict, Effects of Conflict.

The Organization and Management of Construction: Shaping


theory and practice (Volume Two).

Edited by D.A. Langford and A. Retik. Published in 1996 by


E & FN Spon. ISBN 0 419 22240 5. Procurement strategies
and contract disputes 361

Background

It is widely accepted that the construction industry in the


UK has, in recent years, become highly

adversarial and contentious with many writers and


researchers believing that the presence of conflict

is inherent within the organisational framework of the UK


construction industry (Clegg

1992)(College 1992)(Baden-HeUard 1992)(Langford et a/1992).

The emergence of these conflictual attitudes has resulted


in a dramatic increase in the number of

disputes in which organisations within the industry have


become involved. These disputes manifest

themselves at all levels and can culminate in full blown


litigation, arbitration or, more frequently

nowadays, some form of infonnal dispute resolution.

Many writers and researchers have attempted to identify the


true extent of conflict within the UK

construction industry in a number of ways, although the


vast majority of commentary on the extent of

construction specific conflict has been anecdotal. Fenn and


Gould (1994) suggest that very little

evidence has been produced to support the views that the


construction industry produces more

disputes than any other industry and that most of the


writing has been largely anecdotal.

Fenn (1991) discussing the incidence of disputes in the UK


found that over a period of around twenty

years (to 1986) the number of cases coming before the


courts was stable at around 150 per annum.

This low number is primarily due to the workload of the


courts being at full capacity and therefore

wlable to take on any more cases. To highlight this, Fenn


(1991) also identified that the number of

actual litigation initiations increased dramatically over a


similar period (200 in 1960 to 1150 in

1986).

To reinforce Fenn's findings, figures produced by Newey


(1992) show a 100% increase in litigation in

the period 1973 to 1980 with increases of aroWld 15% per


annwn in the period 1980 to 1989.

Both of these writers have attempted to establish the


magnitude of conflict in the UK construction

industry by examining the extent of litigation proceedings


and litigation initiations in the court

system. This "top down" approach is useful in that it


defmes the situation at one end of the spectrwn
thereby setting parameters for further research.

Other writers and researchers have attempted to examine the


extent of construction conflict on a more

detailed level than that afforded by the "top down"


approach. Heath et al (1994) carried out a survey

of 28 quantity surveyors in industry to try to identify the


incidence and extent of conflict. This

approach attempted to examine the layer of conflict that


cannot be identified by examining litigation

statistics and which, in general, makes up the greater


proportion of construction disputes occurring in

the UK. The results of the research carried out by Heath


et al (1994) appear to be concerued mainly

with disputes which result in fonnal claims submitted by


one party or another with no differentiation

or identification of those conflicts that cause problems


but which never reach formal claim position.

The findings produced by Heath et al (1994) are valuable


in that they provide a further benchmark

and parameter for further research into the nature and


extent of conflict in the UK construction

industry.

Research into the Sources, Causes and Effects of ConOict

The research which has been carried out so far into the
extent of construction conflict has been useful

in that it has provided certain bodies of knowledge for


other researchers to build upon.

The research program has been developed to identify and


quantify the sources, causes and effects of

disputes in the UK construction industry within the


parameters set out in the research methodology.

Objectives
The main objective of the research project was to widen the
understanding of conflict in the UK

construction industry by carrying out research into what


types of disputes occur within the industry, 362 Conlin,
Langford and Kennedy which member of the project team was
the source of the conflict, what was the true cause ofthe
conflict and what the effects of the conflict were.

Sources of Conflict

When carrying out the research the research team abstracted


data from recently completed

construction projects on who was the original source of


conflict. These sources included: clients,

consultants, contractors, subcontractors, suppliers,


financiers and extra contractual third parties.

This information allowed a picture to be built up of who


the conflict iuitiator was.

Causes of Conflict

The cause of conflict was another very important piece of


information that was required when

building up a picture of the type and extent of conflict.


The causes of conflict that were identified

came under a number of headings but included: budgetary


problems, technical problems, commercial

problems and interpersonal differences. Examples of these


causes included: budget overspend due to

variations, spatial co-ordination problems between


suspended ceiling subcontractor and heating and

ventilation subcontractor, subcontractors going into


liquidation and personal differences between key

design team members.

Effects of ConOict

Determining the effects of each conflict event was also


important when collecting data on conflict
events. The range of effects of conflict had to be
documented in order to ascertain how significant the

conflict event was, how avoidable it was and how severe it


was. By carrying out the research in this

manner a sliding scale of conflict significance,


avoidability and severity was built up for each type of

conflict.

In addition to the three broad objectives described above


the research project has also identified,

within the conflict events documented, whether patterns of


conflict emerge as a result of the

following functions: • Procurement type • Project type •


Project value • Client type • Technical complexity •
Form of contract • Geographicallocation

It is anticipated that the data collected from the


research, which includes information on the above

functions, will be sliced in such a manner as to


facilitate the building up of profiles to show how the

above functions affect the type, range, incidence and


frequency of conflict occurring within the UK

construction industry.

Methodology

To obtain an accurate picture of the type, incidence and


frequency of conflict occurring within the

UK construction industry, it was necessary to collect data


on a project by project basis.

The methodology forming the framework of the research is


based around the detailed abstraction of

data from recently completed construction projects. These


projects, chosen at random within project

values of£lm to £IOm are representative of the type of


mainstream work undertaken by the UK
construction industry within the last six years. Overall,
twenty-one projects were examined,

abstracted and documented. These projects covered the range


of procurement methods currently in

use in the UK, the main forms of contract used in the UK, a
range of client types, project values,

geographical locations and technical complexities.


Procurement strategies and contract disputes 363 Once
infonnation was collected on the project itself the
research team then began to read through all the project
documentation to extract any infonnation relating to any
conflict events. By using this method the researchers
were able to build up, not only a picture of the conflicts
arising on that project but also a pathology of how a
conflict progressed through the duration of a project. This
technique

allowed the true source or cause of a conflict to be


identified in relation to what the dispute appeared to be
at that particular point in time. The conflict was then
tracked through the duration of the project

to see how it developed, how it was resolved and what its


consequences were.

After the twenty-one projects had been documented the data


was sorted in a number of ways to

identify how project specific factors affected the type,


incidence, frequency and outcome of conflict.

Dis.putes and Procurement Method

As indicated, the choice and implementation of procurement


methods currently used in the UK

construction industry has been shown to be one of the


causes of conflict identified.

Within the study the procurement methods documented


covered five main options commonly found

in the UK at present. These methods were: traditional


Bill of Quantities (Private Client) traditional Bill of
Quantities (Public Client) traditional Bill of Quantities
(Local Authority Client) design and build (Public Client)
design and build (Private Client)
The conflict events documented in this study were grouped
together under six main headings that

covered the main areas of dispute identified. These main


areas are: Payment and Budget conflicts Perfonnance
conflicts Delay and time conflicts Negligence conflicts
Quality of materials/workmanship/management conflicts
Administration conflicts

Each of the main headings had a number of conflict


classifications contained within them that

allowed an accurate picture of the cause of the conflict


to be built up. The full list of conflict

classifications, along with their respective codes, are


shown in Appendix A.

Pll)'IDent and Budget

The first group of conflicts that were examined were those


which came under the heading of Payment

and Budget problems. Figure I shows the frequency, and


spread, of the conflict events occurring

under this heading and illustrates which procurement


option gave rise to which type of conflict.

It can be seen from figure I that, on the whole, conflicts


occurring within the payment and budget

subgroup had a tendency to occur on the traditionally


procured projects rather than projects procured

under design and build options. Only one conflict event,


namely the non-return of retention money,

was apparent on design and build projects with a private


client (DBPR), where the average number

occurring was 5.50 per project.

The three other variants of traditionally procured


projects returned a spread of conflict events that

were, on the whole, broadly similar. Variation claims by


the contractor, as a cause of conflict,
occurred on traditional private client (TPR) and
traditional local anthority (TLA) projects where they

returned an average number of conflicts per project of


1.17 and 2.67 respectively. Non-payment of

interim payment to contractor and non-payment of interim


payment to subcontractor, as causes of

conflict, returned an average of 0.67 and 2.67 for


traditional public client (TPU), 0.67 for TPR

projects and 1.53 for TLA projects.

364 Conlin, Langford and Kennedy Aver.r.ge number


ofconflcts pM' projllct Figure 1

The only procurement option to return an average number of


conflicts per project for the

non-payment of the balance of the contract sum to a


subcontractor was a TLA project where the

average was 1.33 conflicts per project. The average number


of conflicts per project arising out of

liquidated damages' disputes was 1.33 with all occurring on


TLA projects.

Conflicts arising out of problems with professional fees


occurred only on TPU projects where

additional fees and the basis of the fees accounted for an


average of 0.50 conflicts per project.

Extension of time costs also only occurred on TPU projects


where they accounted for an average

number of conflicts per project of 0.83 .

Conflicts occurring over general budget issues and


additional work occurred only on TLA projects

where they returned an average of 2.67 and 1.33


respectively.

In general , the results obtained from the payment and


budget subgroup show that the types of

conflicts that arise on traditionally procured projects


vary significantly from those obtained on design

and build procured projects. The high average number of


conflicts apparent in DBPR projects, which

are caused by the non-return of retention money, is


significant because it ties in with a high incidence

of conflicts caused by quality issues.

It can be seen then, taking the DBPR project out of the


analysis, that conflicts caused by payment and

budget issues have only occurred on traditionally procured


projects. This can, perhaps, be attributed

to a number of factors, namely: more competition in


bidding for the contract, a higher degree of

incomplete design at tender, more individuals and


organisations involved in traditional procurement

methods, greater degree of client input in traditional


projects and a single point of responsibility

prevalent in design and build projects.

Performance

The second conflict subgroup identified in the study is


Performance. Figure 2 shows the average

number of conflicts per project arising out of performance


issues. Procurement strategies and contract disputes 365

In comparison to the results shown in the previous section


the Performance subgroup is small. There

were no instances of conflicts caused by performance


issues in DBPU, DBPR or TPU projects. In the

case ofTLA projects the study identified that there was an


average of 2.67 conflicts per project

caused by the main contractor failing to proceed in a


competent manner. In comparison TPR projects

returned an average of 1.17 conflicts per project caused


by both the contractor and subcontractor
failing to proceed with the work in a competent manner.

A reason for the lack of conflicts of this nature on design


and build projects may be that the client

finds it difficult to monitor the performance of the


contractor or subcontractor and that the client may

be relying on the contractor for all his technical


information. 2.50 ./ 2.00 3.001 Av ... __ ~r of
conftlcts p« project 1.50

Delay and Time 1.00 0.50 O.OO .---=-.v 0& B Prhele


Client 0& 8 PublIC aienl Figure 2

Conflicts that were caused by delay and time issues


represented a significantly greater proportion of

disputes than those caused by the previous conflict


subgroup. Figure 3 shows the conflict pattern for

the delay and time subgroup.

In general, most of the conflicts caused by delay and time


issues occurred on traditionally procured

projects although there was an average of 3 conflicts per


project on DBPU projects and 0.50 on TPU

projects where the cause identified was the client being


concerned with the progress of the work.

366 Conlin, Langford and Kennedy Figure 3 0& B Prhete


Client 0& B PublIC Client

TIle overall picture of conflict caused by delay and time


issues in the traditionally procured projects

was shown to be biased towards TLA and TPU projects where


the majority of conflicts occurred. TPR

projects only returned an average of 1.17 conflicts per


project where the cause was identified as being

a delay in completion due to the fault of the contractor.

Conflicts caused by extension of time issues were well


represented between TPU and TLA projects.

Extension of time (EoT) conflicts, where the contractor


claimed due to the fault of the client,

occurred on TPU and TLA projects on average 0.50 and 2.67


times per project respectively. EoT

conflicts, due to the contractor claiming because of


matter's outwith the control of the parties

occurred only on TLA projects where the average per project


was 1.33. EoT conflicts caused by the

fault of the design team resulted in an average of 0.83 and


1.33 conflicts per project for TPU and

TLA projects respectively.

The remaining conflict issues that occurred within this


subgroup were those conflicts due to delay on

the part of one of the parties. Delay has been identified


as being different from EoT conflicts because

delay issues represent the actual dispute about the cause


of delay whereas EoT conflicts represent the

dispute about the length of EoT being awarded.

Delay in completion (DiC) was split into four main


categories: fault of contractor; fault of

subcontractor; fault of design team; fault of client. In


the first instance the TPR projects and TPU

projects returned an average of 1.17 and 0.50 conflicts per


project respectively. In the second

instance, where the fault was identified as being the


subcontractors, TPU projects had an average of

0.50 conflicts per project. The remaining causes of


conflict, namely fault of design team and fault of

client, resulted in an average of 1.33 conflicts per


project both on TLA projects. Procurement strategies and
contract disputes 367

The pattern shown in figure 3 is one that shows that delay


and time conflicts tend not to manifest

themselves on design and build procured projects and where


they do occur they tend to be where the

client has been concerned with the progress of work.

In general, the EoT and delay issues tend to occur on


traditionally procured projects.

Negligence

This group contains conflicts that are caused by delictual,


duty of care and negligence issues. 1.40 ¥ 1.20 15. 1
1.00 , 0.80 .. i 0.60 r 0.40 ! 0.20 0.00 ~r--~ __ v
--~ conl:rldor Figure 4 01 B P ...... I. 01 ... 01 IS
Plobtic Cienl

In general, only two main causes of conflict within this


subgroup were identified: negligence of the

architect and negligence of the contractor. The former


cause of conflict occurred on both TPR and

TPU projects where the average number of conflicts per


project was 0.67 and 0.83 respectively.

Negligence of the contractor occurred only on TLA projects


where the average was around 1.33 per

project.

In the quality subgroup, issues such as defective


materials, perceptions of quality and workmanship

problems were identified. Figure 5 shows the pattern of


average conflicts per project for the quality

subgroup.

368 Conlin, Langford and Kennedy 12.00 1 10.00 // 8.00


Average number of 6.00 conflicts per project 4.00 2.00
0.00 Figure 5 o & B Ptiwle Client

It can be seen from figure 5 that, in the quality subgroup,


the causes of conflict occur more often on

the design and build methods than on any of the other


subgroups. For instance, defective materials

and poor construction co-ordination both occur on DBPR


projects with an average number of
conflicts per project of 11.60 respectively. DBPU projects
also returned causes of conflict such as:

clients' perceptions of specialist subcontractor's design


(5.75); non-timeous design infonnation (3);

and poor co-ordination of subcontractors (3 .25).

The traditionally procured projects returned a wider spread


of causes of conflict but at an overall

lower average number per project. TLA projects had a number


of causes covering: defective

materials; clients/design team's perception of quality of


contractor's workmanship; client's perception

of contractors design solution; non-timeous design


infonnation; and poor construction co-ordination.

Each of these causes returned an average number of


conflicts per project of 1.33 respectively.

In the case of TPU projects the spread of conflict covered


issues such as: poor design co-ordination

between consultants (050); poor design co-ordination


between consultants/contractors/subcontractors

(0.83); non-timeous design infonnation(1.33); poor


co-ordination of subcontractors(0.83); poor

construction co-ordination(0.83); differing site


conditions(0.50); restrictions placed on contractors

working methods(0.50).

Projects that were procured tmder the TPR method showed a


much narrower spread than the other

two traditional methods with only three causes of conflict


being identified. Poor design co-ordination

between consultants returned an average of 2.67 conflicts


per projects whereas differing site

conditions and restriction on contractors working methods


both returned 0.60 per project.

The study would appear to indicate that design and build


projects returned a high average number of

conflicts on issues such as defective material, quality of


workmanship and co-ordination of work

because there was a lack of adeqnate supervision on behalf


of the client and the lack of ability on the

clients part to adequately specify and interpret their


requirements. Procurement strategies and contract disputes
369 The spread of causes of conflict relating to
traditionally procured projects, coupled with their
relatively low average nwnber of conflicts per project,
seem to indicate that there may be problems associated
with the interface between members of the design team,
between the design team and the contractor and between the
contractor and subcontractor.

Administration

Within the administration subgroup (Figure 6) the causes


of conflict identified covered issues that

were related to information flow, administrative and


contractual procedures and issue's outwith the

control of the contracting parties.

It can be seen from figure 6 that all the procurement


methods included in the study had causes of

conflict from within this subgroup although design and


build projects returned a much narrower

spread than traditionally procured projects.

Within OBPR projects only one cause of conflict was


identified. Lack of information from design

team/client was responsible for almost 11 .50 conflicts on


average per project within the OBPR group.

In comparison, within the OBPU group, the contractor's


non-adherence to administrative procedures,

poor feedback from the contractor and extra contractual


third party problems all returned an average

of3 .25 conflicts per project respectively.


As was shown in the quality subgroup the traditionally
procured projects had a wider spread of causes

of conflict but returned a lower average nwnber of


conflicts per project than the design and build

methods. 12.00 10.00 8.00 6.00 4.00 2.00 0.00


Figure 6

TLA projects included conflicts caused by: lack of


information from the client; contractor's

non-adherence to administrative procedures; lack of


information from design tearn/c1ient; and

subcontractor's non-adherence to administrative procedures.


Each of these causes returned an average

number of conflicts per project of 1.33. 370 Conlin,


Langford and Kennedy Within the TPU projects the spread of
causes was as wide as that seen in the TLA although the
average number per project was more variable. Within the
TPU projects the main causes were: contractor's
non-adherence to administrative procedure; design team's
non-adherence to administrative procedure; and extra
contractual third party problem. Each of these causes
returned an

average number of conflicts per project of 1.33


respectively. The three others represented included: lack
of information from client; poor feedback from contractor;
and wrong information from design

team. Each of these causes returned an average of 0.50


conflicts per project.

TPR projects returned a narrower spread of conflict causes


within the administration subgroup than

either TLA or TPU projects. Within the TPR projects poor


feedback from the contractor, lack of

information from design team/client and subcontractor's


non-adherence to administrative procedures

all returned an average number of conflicts per project of


1.17 whereas the contractor's non-adherence

to administrative procedures returned an average of 1.83.


It can be seen from figure 6 that, as in the case of the
quality subgroup, design and build projects

return a much narrower spread of causes of conflict but a


higher average number of conflict events

per project than traditionally procured projects. This


could suggest that, due to the greater number of

organisational units involved in a traditionally procured


project, the potential for administrative

conflict is higher than on design and build projects.

Conclusion

This paper has identified that there has been a substantial


gap in the available knowledge of the

sources, causes and effects of conflict in the UK


construction industry.

It has been shown that many writers and researchers have


attempted to ascertain the extent of conflict

in the UK construction industry by examining the problem


from a top down viewpoint. This approach

has been acknowledged as misrepresenting the true picture


of the sources, causes and effects of UK

construction conflict. To overcome these problems the


authors have documented and analysed a

number of recently completed projects to build up an


accurate picture of the true extent and nature of

conflict in the UK construction industry.

One of the main findings of the study was that the


procurement method used, and the type of client

procuring the project, had an effect on the nature,


frequency and spread of conflict occurring on a

project. Six broad groups of conflict causes were


identified, each relating to a specific type of dispute.

These groups covered: payment and budget; performance;


delay and time; negligence; quality;
administration

By using these conflict groups the research team identified


that certain types of conflict occurred on

certain types of procurement method. In the case of payment


and budget issues it was established

that, in the main, it tended to be the traditionally


procured projects that returned disputes that were

caused by payment and budget problems.

The performance group of conflicts highlighted that, for


the most part, it was traditionally procured

projects that were, again, returning disputes. This picture


was broadly the same for conflicts occurring

within the delay and time group. It was shown that, within
the delay and time group and negligence

group, it was mostly traditionally procured projects that


returned disputes.

One conflict group that attracted a high average number of


conflicts per project on design and build

projects was the quality group. Within this group it was


shown that disputes relating to material

quality and quality ofworkroanship were more significant


on design and build projects than on

traditional projects.

The final conflict group, administration, shows that, as


in the case of the quality subgroup, design and

build projects return a much narrower spread of causes of


conflict but a higher average number of

conflict events per project than traditionally procured


projects. Procurement strategies and contract disputes 371

Overall, the study has shown that, in the main, conflicts


relating to administration and quality are

more prevalent on design and build projects than on


traditional projects but conflicts relating to

payments and budgets, delay and time, negligence and


perfonnance are more prevalent on traditional

projects

Baden-Hellard, R (1992) Construction Conflict Management


and Resolution, Construction

Conflict: Management and Resolution, Peter Fenn and Rod


Gameson (Eds), pp 35 46, E & F. N.

Spon, London

Clegg, S. R (1992) Contracts Cause Conflicts, Construction


Conflict: Management and Resolution,

Peter Fenn and Rod Gameson (Eds), pp 128 -144, E & F. N.


Spon, London.

College, B (1992) Construction Contracts: Towards a New


Relationship, Construction Conflict:

Management and Resolution, Peter Fenn and Rod Gameson


(Eds), pp 229 249, E & F. N. Spon,

London.

Fenn, P (1991) Managing Corporate Conflict and Resolving


Disputes on Construction Projects,

ARCOM

Fenn, P and Gould, N (1994) Dispute Resolution in the UK


Construction Industry, Procedings of

First Plenary Meeting ofTG15, Kentucky.

Heath, B. C., Hills, B., & Berry, M (1994) The Origin of


Conflict Within the Construction Process,

Procedings of First Plenary Meeting ofTG15, Kentucky.

Langford, D. A., Kennedy, P. and Sommerville, J (1992)


Contingency Management of Conflict: An

Analysis of Contract Interfaces, Construction Conflict:


Management aud Resolution, Peter Fenn and
Rod Gameson (Eds), pp 64 71. E & F. N. Spon, London.

Newey, J (1992) The Construction Industry, Construction


Conflict: Management and Resolution,

Peter Fenn and Rod Gameson (Eds), pp 21 -24. E & F. N.


Spon, London. THE PROVISION OF INFRASTRUCTURE SERVICES
IN DEVELOPING COUNTRIES W.H.E. Suite Department of Civil
Engineering, University of the West Indies, St Augustine,
Trinidad Abstract Infrastructure development is accepted
as a necessary pre-condition to economic development. So
convinced of this critical factor are the development
economists and planners that they have accorded it a
priority listing on their prescription for the developing
countries since the decade of the 1960s. Three decades
ago, the focus was on the construction of hydroelectric
mega-dams and super-highways. These have given way to
more modest but continued interest, in micro dams and in
road network systems per se, particularly agricultural
access roads and bridges. The new focus has now shifted to
water management, flood control and restoration and
extension of potable water systems with particular
interest in industrial water demand. Against this
background, the central problem facing the planners of the
South is not (only) technical but rather the question of
procuring the necessary funding to carry out these works.
The paper is a case study of the Trinidad and Tobago
situation and a review of the efforts in pursuit of
innovative methods of financing of its infrastructure
needs. The paper discusses the challenges which are being
presented and the problems being encountered in dealing
with all these sectors of infrastructure development.
Keywords: Divestment, infrastructure provision, novel
management approaches, private sector financing,
privatisation, public sector reform, user fees. Sommaire
Le developpement infrastructural est accepte camme une
condition necessaire pour Ie developpement economique.
Les economiste et planeurs du developpement sont assez
convainyu de ces facteurs critiques qu'lls les ont
stipules depuis des 1960 sur les listes prioritoires au
pays du developpement. Avant 30 ans Ie foyer etait la
construction des grands barrages hydroelectriques et des
grand chemins. En ce moment l'accent est sur des petits
barrages et sur les reseau routes et en particulier sur
les routes d'acces et des ponts pour les communautes
agricoles. Cet foyer nouveau est sur l'administration de
reau, la surveillence des deluges, a pourvoir de l'eau
potable et en particuliera pourvoir de l'eau a
l'industrie. Avec cet fond,la probleme primaire rencontn~
par des planeurs au sud est tant technologique q'une
de procurer des fonds necessaires pour faire ces travaux.
Ce travail examine la situation en Trinite et

Tobago et revoit les essais pour obtenir des fonds pour ces
besoins infrastructural. Ce travail discute

les demandes et des problemes reconrrees en tels secteurs


des developpement infrastructural. Mots principaux:
Depouillement, provision infrastructural, approches
nouvelles de l'administration.

finance par Ie secteur prive, privatisation, reform en


secteur public, honoraires payes par l'usager.

The Organization and Management of Construction: Shaping


theory and practice (Volume Two).

Edited by D.A. Langford and A. Retik. Published in 1996 by


E & FN Spon. ISBN 0 419222405. Infrastructure services in
developing countries 373

1 Introduction

Developing countries invest some US$200 billion a year in


new infrastructure which is more or

less 4 percent of their national output and about a fifth


of their total investment (World Bank. 1994).

The terrible backlog of needed infrastructure. a need to


replace losses occasioned by natural .

disasters. population growth. increasing urbanisation and


above all. a drive to fully develop the

economic resources and potential of developing countries.


have signalled increased spending in this

area. Governments of developing countries are now


desperately in search of vast sums to be

invested in infrastructure projects. Of the US$200 billion


annually spent on infrastructure. 90

percent or more of it is generated through government tax


revenues or intermediated by

governments. Almost half of government investment spending


is in this sector. Governments have
sourced funds mainly through foreign financing for
infrastructure. Three streams have been used to

facilitate this investment. publicly guaranteed private


loans. multilateral loans and bilateral loans. A

decade and a half ago (1980). the dominant stream was from
publicly guaranteed private loans (50

percent approximately). with bilateral and multilateral


loans representing approximately equal share

of the remaining 50 percent Governments have found it


increasingly difficult to continue offering

guarantees and consequently. both bilateral and


multilateral streams have increased while guarantee

loans have decreased [World Development Report. 1994].


Today. less than 25 percent (-US$50 b)

are through guarantee. approximately 40 percent.


multilateral ($80.0 b) and 35 percent ($70.0 b)

bilateral loans.

The problem faced by most governments of developing


countries is their inability to continue to

fund even maintenance and replacement of existing


infrastructure systems. after decades of

post-independence neglect and increasing usage. The demands


of increasing urbanisation.

population expansion and new excursions in


industrialisation are not being met and in some cases.

plans for expansion of the sector have been cornmissioned


and completed more than a decade ago.

But above this hum of activity is the increasing criticisms


of the inefficiency. questionable

management. waste and often instances of corruption. They


have all served to intensify the focus on

the state-run infrastructure services. Traditional sources


of funding are no longer willing to provide
unlimited funding and the population is not prepared to
agree to payment of increased rates. New

and innovative mechanisms must now be generated to create


the necessary funding to meet the

increasing demands on the public sector in meeting its


statutory obligations of provision of utilities

and the society's infrastructure systems. The situation


appears so much like the proverbial "chicken

and egg" situation. The existing condition (status) of


utilities and infrastructure requiring repairs.

refurbishment. at times even complete replacement in the


face of almost total collapse. This is

accompanied by plans for expansion or the introduction of


new technologies to meet new industrial

and commercial opportunities and to service a growing


population. The other side of the coin is an

unwillingness of the dissatisfied customers to pay


increased rates or taxes. at least not before the

system is improved. Governments are therefore faced with


the dilemma. on the one hand. a call to

improve the system before increased rates. while on the


other being desperately short of funds. This

situation so often describes the utility or infrastructure


system. overburdened with a backlog of debt

that continues to mount.

It is against this background that the paper attempts to


discuss the Trinidad and Tobago situation.

The study is presented. conscious that the present


predicament in several of the commonwealth

Caribbean islands is almost identical in most of the


utilities and infrastructure systems.

374 Suite 2 Funding of Infrastructure Projects It would


be accurate to say that 100 percent of all infrastructure
and utilities costs, i.e., development

capital expenditure and recurrent costs were for the


account of the central government's coffers, up

to 1990. Annual allocations were made through the national


budget and these represented the

principal financial source since rates collected were


invariably insufficient to meet costs, far less

pay outstanding debts or fund development programmes. The


Public Utilities Commission Act, No.15 of 1966 [Chap.
54:01] was "an Act to permit a Public

Utilities Commission to determine rates for public


utilities and to perform certain other functions

respecting utilities". The initial focus was for rate


setting for telephones, electricity power, Airport

and Port charges, postal charges and water and sewerage


rates. The mechanism which was

employed was that the management would prepare the case in


support of new rates which was

submitted to the Public Utilities Commission (pUC). The


PUC would then publish the intention to

raise rate, inviting the public to peruse and study all the
supporting documentations in their

possession and submit comments or counter arguments. The


PUC would hold public hearings after

which a decision would be taken as to whether the


increased rates would be allowed and if so to

which new rate and for how long. It has generally been felt
that the reason why rates have not been

increased in keeping with increased cost of service is


mainly because of a failure of the management

of the various utilities to present a substantiated case in


support of this. Others have maintained that

it is the government's reluctance to raise rates because it


may consider this issue too politically
sensitive during the years of plenty (1974-83) and moreso
during the lean years from 1983 to the

present. In some cases, rates have not been increased for


Water and Sewerage since 1938. In the

case of telephone and electricity, rates have increased. In


the decade of 1980's, the

telecommunication sector went through a heavy capital


(equipment expansion and modernisation)

upgrading. Soon after, the domestic telephone (TELCO)


company and the international link

(TEXTEL) were merged into a single company (TSTT) and


later privatised. The international

British Cable and Wireless Company now owns majority shares


and the government holds minority

shares. The electrical power generating and distributing


company, T &TEC, has undergone major changes

in the last year (1994). Up until 1983, the debt incurred


by T&TEC was covered by the central

government by way of annual subsidies. These were reduced


in 1983 and by 1988 had stopped

altogether mainly because of the central government's


inability to continue to cover accumulating

debts incurred by the public sector statutory authorities


and companies and not because of any

policy change. The T&TEC had to carry these debts through


borrowing. In 1994, it sought external

funding by entering into a new arrangement with a foreign


partner through a mechanism of

divesting itself of its generating capacity. In this


separate company, PowerGen, T &TEC holds 51

percent shares. PowerGen will now supply T&TEC with


electrical power through a Purchasing

Agreement entered into for the next IS years. All


electrical power-generated must be sold to T &TEC.

It cannot sell directly to a private consumer. The question


of setting new rates for the public

consumer still lies with the PUC and assumes new


proportions. The purchase price by T&TEC

from PowerGen has been set by agreement. In the case of


the Water and Sewerage sector, the Water and Sewerage
Authority (WASA) is

responsible by law, through the Water and Sewerage Act,


Chap. 54:40, earlier Act 16 of 1965, "to

provide for the development and control of water supply and


sewerage facilities in Trinidad and

Tobago and matters of sanitation incidental thereto, the


promotion of the conservation and proper

use of water resources; and for the establishment of an


Authority to administer the several purposes

aforesaid and matters connected therewith". While there is


little debate that rates have not Infrastructure services
in developing countries 375

significantly changed, based on the mechanism employed, the


annual rateable value (ARV) of

property, one is reminded that the WASA Act clearly


identifies under the caption "Financial

Provisions" [26(1) of Chapter 54:40].

"The Authority shall so exercise and perform its functions


as to ensure that its revenues are not

less than sufficient to:

(a) Pay instalments of compensation required by Section 39;

(b) Cover operating expenses, including taxes, if any, and


to provide adequate maintenance and depreciation, and
interest payments on borrowings;

(c) Meet periodic repayments on long-term indebtedness to


the extent that any such repayment exceed the provision
for depreciation;
(d) Create reserves for the purpose of future expansion;
and the sums required for any of the

purposes of the Authority shall be met out of the funds


and resources of the Authority".

It is clear that these provisions in the Act had little


impact on the Board or Management of WAS A,

definitely not the Cabinet nor the PUC.

While the government had raised revenue through the general


taxation of road users, through

licensing of drivers and vehicles, in 1981, the government


established a TT$35 million Road Fund

which was financed from earmark petroleum revenues. The


fund was used to cover overall

maintenance and general development of the road network.


With the downtum in the economy after

1983, the fund was discontinued and the money in the fund
returned to the consolidated fund to deal

with general debts. In 1993, the Government found itself


once more unable to finance the

maintenance of the 9,638 km of the national roads networlc


including 350 bridges and more than

400 landslides, with at least 150 of them in a very serious


condition. A 5 percent fuel tax was

imposed. The revenue generated is to be kept in a dedicated


fund for the exclusive use of road

maintenance and repairs.

Another mechanism employed in respect of generating


revenue for road repairs and expansion is

related to a priority bus route. A priority or dedicated


bus route was built in stages from 1980's to

the early 1990's along an abandoned railway track and


closed to general traffic. The route of
approximately 12 miles in length ran parallel to a major
East-West highway leading east from the

capital city was intended for use by publicly owned buses


but was later opened up to privately

owned minibuses (passenger load of 12, 17, 25). These


minibuses had to pay a special registration

fee to permit use of the route. The route was also opened
to VIPs who had to be granted special

permission for use by the minister responsible for roads


and transport. It has been proposed that this

permission could be extended to a broader class of users


for a fee which could be used as a source of

revenue dedicated to repairs and maintenance of the route.

Since the route was crossed at several points by existing


local roads, this would have prevented the

use of toll gates at the ends. In fact several of the


local roads had to be restricted to generate

sufficient right away on the priority route and to ensure


safety. In fact, the permitted intersections

even today represent the cause of most fatalities and


accidents on the route.

Direct taxation through licensing of vehicles and drivers


and fuel taxes have been the main

approach to raising revenue in small states the use of


toll gate are not very easy to implement

because of the number of small communities existing along


all routes as well as the fact that there

may be alternate and even illegal routes to avoid the toll


gates. Developing countries, particularly

small island states, have therefore been pursuing several


novel approaches for raising financing for

new construction as well as for maintenance and repairs of


existing infrastructure systems, even
though some of the traditional approaches in the developed
countries may not be readily applicable.

376 Suite

3 New Approaches Generally, infrastructure and utilities


are provided and maintained by the public sector or

government in most developing countries. The problem of


sourcing funding for maintenance and

repairs as well as expansion of existing system or the


introduction of new systems continue to be the

problem of the central government. Today, earlier sources


of aid have either disappeared or are

unwilling or unable to meet the growing needs of


developing countries. Multilateral and bilateral

international lending agencies have now raised in unison


the call for privatisation and divestment as

a precondition for any further loans. The infrastructure


system and the utilities have been specially

singled out for early transfer to the private sector. We


are led to believe the partial or complete

divestment would not only relieve the state of the


responsibility and financial burden of locating

funding for maintenance and repairs but for new works. It


is expected to attract more financing

through the new opportunities for local and foreign private


sector investment and loans. To meet the

considerable demands for funding the state has sought joint


venturing consequent upon the fate of

shares or partial divestment. A number of new approaches


are being attempted. In the Airport sector in Trinidad and
Tobago, the car park facilities have been leased out to
another

public sector Company operator who will be responsible for


the upkeep of the car park and its

security. Within the terminal building, private


concessionaires were invited to make prepayment

towards the construction of duty-free shopping booths. The


money realised then financed the

construction. The intention is to expand concessions


within the departure and arrival halls, as well

as the rest of the landslide to accommodate a wide range


of customer facilities. Similar advanced

investment of private sector interests permitted the


Airports Authority to provide facilities for

banking outlets, taxi service and a range of take-away


snacks and gift shops. All these have been

used to raise revenue to carry out the maintenance


programme of the airports. The main thrust in the

direction of funding for a new airport and aviation


industrial/commercial estate has been with the

search for a developer!investor willing to enter into a


Build, Own, Operate and Transfer contract

with the Airports Authority. Such a partner has been


selected after a process of inviting international

proposals. The airport assets are to be vested in a new


company and would then represent the shares

or equity of the Government of Trinidad and Tobago while


the preferred partner is to locate funding

for development of the estate. In this way, the funding


would represent the share of the developer

who would share in In this way, the funding would


represent the share of the developer's equity who

would then share in the ownership and operation of this


facility. After a prior agreed period (17

years), the assets will be sold or transferred back to the


Government of Trinidad and Tobago. This

project has been stale-mated at the stage where the


selected developer has not yet been able to
secure the funding even after two years have passed. The
government seems hopeful that funding

will be located and the project started. In the Sea port


subsector, the public sector ports operated through a
State-owned Port Authority of

Trinidad and Tobago has sought to generate a land


development or land use plan. Through this, it

has identified two separate thrusts to attract financing.


The first is to invite the private sector to enter

into partnership in developing the lands under the


jurisdiction of the port but which is not needed for

actual port operations. This plan has been developed by


independent consultants. Proposals include

hotel facilities, high income executive type apartments, a


convention centre, a cultural centre for the

performing arts. The second thrust stems from the port's


proposal to subdivide its basic functions

into independent financial/corporate entities. The aim is


for the Port Authority to become as far as

is possible, a landlord. Here separate companies, which in


the first instance would be public sector,

will immediately move either to sell shares on the open


market or will seek private sector block Infrastructure
services in developing countries 377

partnership. The leasing out of port lands to private


operators who carry out maintenance and repair

services for pleasure craft at the Chaguaramas Development


Authority, a public sector owned port,

has already commenced.

Joint venturing, sale of shares, leasing and concessioning


are already being explored in both the

air and marine transport sub-sectors. This is together with


contractual arrangements for new works

via the now growing popular, Build, Own, Operator, Transfer


(BOar) system or one of the many

permutations, (BOO and BOT) or variations on the basic


theme.

Within the mandate to provide potable water and sewer


collection and treatment facilities, the

government has again sought to break new ground in the


Caribbean. The Water and Sewerage

Authority (WASA) entered into a management contract with a


UK-based company Severn-Trent!

Wimpey to provide management services to the Water


authority and at the same time to source and

make available a loan to the Authority. This loan is to be


converted into equity into the fully divested

authority at the end of three years. The management


contract has already been entered into and the

contract has recently been initiated.

The basis of these thrusts is two-pronged. The first is to


free the state of the responsibility to raise

the initial quantum of funding by


privatisation/divestment, thus reducing the liability of
the state.

The other thrust is intended to exact from the user, the


cost of maintenance and repairs, as well as

some fraction to be put aside for replacement and


expansion. The second approach has included the

award of maintenance contracts paid for by user fees and


tolls. SOURCE OF FUNDING ~ AID I LOANS i \~ I
Multilateral Bilateral I NEW APPROACHES Pri .. //
vatlsatIon / User Fees Tolls Divestment I Sale of
Shares Joint Venture BOOT Leases Concessions Bonds
Deducted Taxes Maintenance Contracts Advance Payment of
Rates

378 Suite

4 Discussion It must be pointed out that most of the


approaches discussed in this paper have only recent! y been
undertaken in the Trinidad and Tobago situation. Some have
not yet gotten off the ground and

others have not yet run enough of their course to have


presented useful lessons to be learned or help

to anticipate the difficulties which may yet arise. While


some of these have been tried elsewhere,

with varying degrees of success, this is not to say that


they will be applicable in small island states

or all developing countries. The experience here has shown


that it is necessary for the state, contemplating
privatisation, to

undertake a realistic evaluation of all the assets of the


entity to be privatised or divested. This should

include all the non-material assets. The subsequent


management and ownership structure is very

critical. But since this paper is not exclusively intended


to deal with privatisation/divestment, the

only otherissue to be considered is the servicing of that


sector of the market that may not be able to

pay the market price for services. While tolls may be


readily applicable in larger countries, in smaller states,
the small volume of

users or the existence of alternative routes may decrease


the atractiveness of this option. It was pointed out that
the selection of a preferred developer for the airport
project has not yet

borne fruit. The quest for the US$75 million has not been
successful after more than two years since

the contract was signed. The management contract with the


Water and Sewerage Authority has begun to raise several

questions since Severn-Trent has not sought to put in


place support staff with a view to

understudying and strengthening the existing leadership in


implementing the new thrusts. Instead,
they have recommended the replacement of the entire senior
management. This could prove

problematic for the transition to private ownership, if


the intention is to maintain local ownership of

the utility. So far, the leasing and the concessions have


worked very well. The dedicated fuel tax is to be used

by a Privatised Road Authority but even this was initially


to be put in place by 1995 but already

resistance has pushed the schedule for commencement to


1997. Critical to the entire process of seeking private
funding for utilities and infrastructure systems is

the question of surrendering or sharing ownership and


control, but underlying the process is the

reduction of labour force. This represents a major


objection to the issue of privatisation. By way of
caution and concern, we must admit that the government and
management of state

agencies responsible for infrastructure and utilities in


developing countries are in an extremely weak

position. The utilities and infrastructure are in a


terrible condition, and in search of vast sums of

money for rehabilitation or replacement and in some cases,


expansion. They are unable to raise

rates for a number of reasons including the economic state


of many of these countries coupled to the

facts that the public is completely up in arms against


years of poor service but at the same time,

lulled into believing that rates should not be related to


cost of operation. The international lending

agencies are in complete unison that privatisation and


divestment of state agencies in general and

those in the infrastructure and utilities systems in


particular, are necessary preconditions. Third

world academic institutions have joined the call. No one


dares resist the drive to de-state
infrastructure and to privatise. Nevertheless, three issues
must be raised. The new approach to

funding does present certain concerns: (i) There is the


definite fear that only those who can pay the market price
for services will be able to have them. That communities
and individuals on the periphery of the economic process
of wealth generation will be neglected or even denied
access. Infrastructure services in developing countries
379

(ii) Since the driving force for the new philosophy in the
infrastructure/utilities market place must be based on
the ability to pay that priority industrial and commercial
activities, generating foreign exchange say, or involved
in the export thrust or a favoured sector will have
greater access to service before principally
domestic/residential communities. There is the danger
which already has begun to appear that social and
collective needs may not always qualify for priority under
the strict application of market analysis, economic
financial justifiability and return on investment criteria.

(iii) The other areas of concern relates to the resistance


to strengthen environmental and health and safety
regulations and legislation since it is generally perceived
that such a move will be a deterrent to the foreign
investor and intensified industrialisation. Here, it is
often stressed that consistent with the new philosophy,
the state's role is that of facilitator not regulator or
principal actor.

Already those three facts have become serious issues to be


dealt with by those piloting the new

privatisationldivestment thrust and the drive for


innovative private sector financing of infrastructure

works in developing countries.

l. World Development Report. (1994).lnJrastructureJor


Development. Published for the World

Bank, Oxford University Press. 1994.

2. Public Utilities Commission. Act 15 of 1966. Later Chap.


54.0l. Revised Edition of the Laws of

Trinidad and Tobago (1980). ALTERNATIVE DISPUTE RESOLUTION


METHODS IN CONSTRUCTION A TRINIDAD AND TOBAGO CASE W.H.E.
Suite Department of Civil Engineering, University of the
West Indies, St Augustine, Trinidad Abstract During the
period 1974 to 1983, Trinidad and Tobago experienced a
virtual construction boom. It was to generate a dramatic
rise in the incidence of construction disputes some of
which were to end in legal action while others ushered in a
surprising number of arbitration proceedings. Today, 12
years later, some of these disputes have not yet been
finally resolved as they remain trapped in prolonged
arbitrations or appeals in the courts. The construction
process was to yield the first instances of Mareva
injunctions in the local jurisdiction. In these,
sub-contractors and local joint-venture partners sought to
prevent foreign contractors from liquidating their assets
and leaving the jurisdiction while outstanding claims
remained unpaid and disputes unresolved. In this climate,
there were a wide range of disputes which led to claims by
clients, consultants and contractors. Many of these have
not been resolved but have simply been abandoned by the
claimants, either because they were considered to be a lost
cause, in pursuing the proverbial "man of straw" or
because the claimant was no longer financially able to
pursue the claim. The arbitrations have proved more costly
than initially expected and the promise of prompt
resolution has not materialised. The general
disillusionment in the prompt resolution of disputes
through arbitration or litigation has raised serious
questions as to the possible use of other methods of
conflict and dispute resolution. The paper reviews the
experience in Trinidad and Tobago over the period
(1974-1983), the economic boom years and the subsequent
period of economic contraction. It discusses the weakness
in the present system of arbitration and offers a reason
why other methods have not been explored. The paper
concludes with discussion and recommendations for

improving the arbitration process and explores the other


alternative options of dispute

resolution.

The Organization and Management of Construction: Shaping


theory and practice (Volume Two).

Edited by D.A. Langford and A. Retik. Published in 1996 by


E & FN Spon. ISBN 0 419 22240 5. Alternative dispute
resolution methods 381

Sommaire
Pendent des ans 1974 et 1983, Trinite et Tobago eprouve une
grande hausse en construction.

Ceci ont amene aux conflicts de construction. Quelques-uns


d'entre ceux ont fini par des

proces juridiques, l'autres ont amenes It l'arbitrage.


Maintenant, apres 12 ans quelques-uns

d'entre ceux sont encore irresolus parce qu'ils sont


attrapes en tribunaux.

Le procede de construction It amene premierement It un


arret de sursis dans les tribunaux

regionaux. Voila les sous contractants et les associes


regionaux ont prevenu les contractants

etrangers a liquider leurs actifs et a quitter Ie pays


quand les demendes etait non payees et

les conflicts irresolus.

Dans ge situation on avait pleusieurs conflicts qui amene


a demendes par les clients, les

consultants et les contractants. Un plupart de ces


demendes sont abandonnees par les

reclamateurs parceque l'autre part etait ruine ou parceque


les reclamateurs sont failli pour

suivre les demendes. Les arbitrage sont devenu trop cher


et une resolution dans un court

temp n'est pas realisee. Cet desillusionnement general a


amene It une perquisition a l'autre

methodes de resolution des conflicts. Cette etude est sur


les developpement en construction

Ii Trinite et Tobago pendent les annees de grande hausse


(1974 1983) et apres ca pendent

les annees de contraction economique. •

Ce travail discute la debilite de l'arbitrage et offert


raisons pour n'a pas avoir explore
l'autres methodes. Ce travail termine avec discussion et
recommendations pour ameliorer Ie

procede de l'arbitrage et explore autres options de


resolution des conflicts.

382 Suite

1 Introduction

We can begin by saying that the majority of the disputes


which arose within the construction

sector did so because the various actors in the


construction drama had very little prior

knowledge of the mechanics of how disputes arose. Neither


did they give prior thought to

their resolution and as construction activities rapidly


increased, they were simply

overwhelmed. The result was that some of the parties


sought to wish them away in an

authoritariar. manner (consultants) while others simply


thought they would go away in the

increasing frenzy or at the final delivery of the works


(contractors). Yet again others began

to make costly trips to the civil courts which they found


often functioned too slowly and not

necessarily to the satisfaction of the aggrieved party.


The parties had engaged in works, the

contract documents of which included arbitration clauses


but they themselves had little

definite knowledge of the process. When disputes had


arisen in a few instances where

arbitration had been employed, the arbitrators were


lawyers. The professional bodies,

architects, engineers and quantity surveyors generally had


employed the standard form

contracts, e.g., ICE, RIBA, JCT, FIDIC etc., but in some


cases had introduced

modifications in an attempt to indigenise or adapt. These


professionals and by extension,

the professional bodies made provision for or at least


purported to hold themselves out as

being capable of providing arbitration services in the


event of disputes. But, they were

simply not prepared. The architects and the quantity


surveyors may have been better

prepared for arbitration than were the engineers since the


academic programme of training

of engineers contained little or nothing about disputes,


conflict resolution or arbitration. In response to this
growing problem within the construction sector and
involving

engineers in particular, the Association of Professional


Engineers of Trinidad and Tobago

(APETT), in an ad hoc manner, organised one of its


luncheon lectures in 1985 to treat with

the topic of arbitrators. The speaker was an


attorney-at-law, and has since risen to the office

of Chief Justice of Trinidad and Tobago (1995). This


introduction so wet the appetites of the

engineers that a workshop/seminar was organised to follow


(1985). Invited presentations

sought to expose the engineering fraternity to the question


of arbitration in Trinidad and

Tobago from the perspectives of the five related


professions:

1. The Architect

2. The Quantity Surveyor

3. The Engineer (Design)

4. The Lawyer and


5. The Contractor This was the first serious attempt to
deal, in a frontal manner, with this important issue.

The issue was to be treated at two subsequent formal


training sessions by the staff of the

Department of Civil Engineering, Construction Engineering


and Management Programme.

The first was a seminar/workshop entitled, "Contract Law,


Contract Administration and

Contract Practice" organised for the Central Training Unit,


Personnel Department of the

Government of Trinidad and Tobago. This two-week programme


was aimed at construction Alternative dispute resolution
methods 383

staffin the public sector (June 27 July 8,1988). The


specific focus was on arbitration as a

mechanism for conflict resolution in construction reviewing


the Trinidad and Tobago

experience. The other occasion was a one-day


seminar/workshop on the Design and Build

Procurement System organised by the Quantity Surveyor's


Society of Trinidad and Tobago.

The specific focus was "The Factors which tend to frustrate


the Arbitration Process in a

Small Developing Country" (Suite 1990). As the construction


sector heated up with activity

and the disputes began to proliferate, the question of


other dispute resolution methods,

conciliation, mediation and arbitration began to be


introduced as part of the courses

included in the ppstgraduate programme in Construction


Engineering and Management

being offered at the Faculty of Engineering at The


University of the West Indies, St.
Augustine, Trinidad. The latest initiative out of the
Faculty of Engineering were two short

courses entitled, "Contract Management and Contract Law for


the Construction Sector",

and "Preparation for Arbitration in the Construction


Sector". (April, 1995).

While there have been several calls over the last ten years
to APETT to initiate the

formation of an Association of Arbitrators in Trinidad and


Tobago, this has not materialised.

Recently, just such an initiative has been taken by the


Chamber of Commerce, recognising

the need for a body of arbitrators to serve local and


regional business in the resolution of

conflict.

At this juncture, the issue of Alternative Disputes


Resolution (ADR) has found new

resonance in the wider field of business: Construction


disputes are therefore to be seen as

only one area in which disputes resolution techniques may


be required.

In spite of these efforts, one can make several


observations:

1. The general knowledge about arbitration within the


related professions is still very low.

2. The number of persons with direct experience in


conducting an arbitration is relatively small.

3. There is need for some type of training in the conduct


and process of arbitration even if only through a short
course of lectures.

4. There is need for a registrar of persons who could


competently serve as arbitrators, possibly an Association
of Arbitrators.

5. There is a need to engender among the professionals


within the construction sector and contractors as well,
the position that the least costly approach to dispute
resolution is on the site and as soon as they may have
arisen.

6. There is a need for all parties to recognise and embrace


the position that there should be greater recourse to all
the other forms of alternative dispute resolution
strategies before turning to litigation.

A great deal has been written in recommendation of better


contracts and less construction

disputes and conflicts through better specifications and


more specifically better contract

documents (precision, frankness and clarity).

A great deal has been written in respect of better


contracts and less disputes through

greater risk sharing, full declaration and the minimal use,


if any, of exculpatory and

disclaimer clauses. But while these two factors, contract


document and risk-sharing are

384 Suite

necessary conditions to a less dispute-charged contract


climate and to speedier resolution of

conflicts when they do arise, they do not constitute


sufficient conditions to obviate all

conflict. The spirit of give and take, the willingness to


sit and listen and to accept

responsibility for all our actions or inactions, will not


come from a moral revival in

construction. It will come only from a full recognition


that the route of prompt conflict

resolution serves the bottom line and is indeed the least


costly solution. It may be useful to list, even if not
define, the full range of alternative options open to the

participants in the construction sector on the occasion of


conflict and nascent disputes, the
alternative dispute resolution mechanisms, alternatives to
litigation or a trip to the civil

courts.

2 The Alternatives to Litigation

There are several alternatives to litigation, only a few of


which have been employed here is

Trinidad and Tobago.

2.1 Conciliation

Conciliation is an agreement by parties to a dispute to


seek the intervention of a neutral

third party to assist in the resolution of their disputes.


The idea of early resolution of conflict

as offering the least expensive route has still not caught


on. Nevertheless, it is the author's

opinion, based on the general lack of knowledge about


conflict resolutions, that this method

does offer great promise if it is advocated by the


professional bodies involved. The difficulty with the
method, is that with Arbitration, it requires the selection
of a

person knowledgeable in the area central to the dispute,


commanding the respect of both

parties as being independent and clear in his analysis and


thinking. But while the arbitrator

may be selected for nothing more, the conciliator must have


developed skills in reducing

hostility and getting the parties to see the arguments of


the other side. It is important that he

remains impartial. The professional bodies have not really


advanced this option although it

is well-established and has been operating in the area of


industrial or labour disputes by the
labour officers of the Ministry of Labour since 1965.

2.2 Mediation

Mediation is not unlike conciliation, but the inherent


function of the mediator is to evaluate

the merits of the respective cases of the parties. The


exercise may be conducted by separate

discussions or with both parties present. Here, the


mediator must be much more positive in

that options should be formulated and presented to the


disputants by way of resolution. This

method has not been employed in the local construction


sector but may offer advantages.

The mediator would have to command considerable respect of


the disputants based on

knowledge, experience, independence, impartiality and


clarity. Alternative dispute resolution methods 385

2.3 Mini-Trials

This is an "abbreviated trial in which management is


engaged either with or without legal

representation in the settlement process of the dispute as


it allows them to hear and assess

the strengths and weakness of their respective cases"


(Trevor Lee Sc. 1995). A facilitator is

usually utilised to provide the parties with the "best


chances position" should the Mini-Trial

be aborted and the matter has to proceed to litigation or


arbitration. Needless to say, this

avenue is totally unexplored in the local construction


sector.

2.4 Adjudication

We are told that adjudication is a form of arbitration, in


which evidence and written
arguments are submitted by the disputants, together with
all supporting documents, to

permit the adjudicator to arrive at a quick decision.


Usually, the adjudicator is a technical

specialist in the area in question. This option has not


been utilised in Trinidad and Tobago

but should offer speedy and cheap resolution. It offers the


advantage of excluding the direct

adversarial presence of legal representatives allowing the


specialist to quickly and expertly

arrive at a solution.

The parties can enter into agreement to have the findings


binding. As has been said before,

all these methods require a person knowledgeable in the


areas of the disputes and skilled in

getting directly to the centre of the issue at dispute. He


must above all be able to command

respect, while generating confidence in his ability to


remain objective and impartial. Some

methods require him to keep the parties at the table.

The reasons for delay and hence high cost of litigation


have been well documented in

several texts on arbitration and more recently in those on


Alternative Dispute Resolution

mechanisms. The reasons are the same here in Trinidad and


Tobago. The problems which

have frustrated the local attempts at utilising the


Arbitration process in a small developing

country are generally the same problems which have acted to


inhibit the introduction of the

other dispute resolution methods.

3 Arbitration in Trinidad and Tobago


Arbitration is given legal sanction under the Arbitration
Act Chapter 5:01 (Revised Laws of

Trinidad and Tobago, 1980, Ed.), previously, Act 5 of 1939.


All the contract forms

employed in Trinidad and Tobago include arbitration clauses


which make provision for the

aggrieved party to a contract to invoke the arbitration


process in a series of clearly identified

steps once a dispute has arisen. The arbitration process is


designed to avoid the formality

and rigidity of court procedures but with the all pervasive


involvement of attorneys, the

process has grown more and more into one identical to


formal court procedure. The local

practice has drifted more and more into being very similar
in form and operation to the high

courts. This situation has developed partly because the


attorneys would be more

comfortable in their environment but the shift is more so


because of the failure of the

construction professionals to consciously inform themselves


about the mechanics of

arbitration and to demand accountability and prompt service


from their attorneys and the

386 Suite

arbitrator. They have failed to set about training a cadre


of arbitrators. In fact, these

professionals are at sea when faced with the prospect of


litigation or arbitration. The

impending commencement of either of these is sufficiently


daunting and intimidating

prospect to both consulting engineer and contractor.


Neither actually looks forward to them,
even when action has been initiated. The first response
of aggrieved parties is to seek redress by way of the
traditional courts,

even if there is an arbitration clause. This experience


has invariably meant costly legal

actions, long delays and above all, court decisions which


often are not informed by the

soundest technical appreciation of the facts, or of the


unique environment of construction

processes. Increasingly, arbitration has become the


inevitable recourse. Nevertheless,

developing countries have found a plethora of obstacles


strewn in the path of what initially

was conceived of as being the more appropriate conflict


resolution mechanism. The main

obstacles to Arbitration will be presented hereafter as


well as the reasons for the more

recent quest for even more efficient and effective


alternative dispute resolution mechanisms. Small island
states attempting to have recourse to arbitration are faced
with several

problems. A few of the more critical are presented here:

1. Too small a pool of personnel from which to select the


arbitrator(s).

2. Potential arbitrators have too little experience and no


formal training and may actually be ill-suited and as a
result, the unfortunate selection may do the process more
harm than good.

3. No Arbitrators' Association or Institute is in existence


and therefore no collegiality has been able to develop
among arbitrators.

4. Frequently, the arbitrators have had and may in the


future have business relations with one of the parties or
may even be related by way of family or old school or club
connections.

5. There is no roster or register of potential arbitrators


to provide quick information on available resources. All
these problems apply to the other conflict resolution
avenues. In fact, the lesser

known approaches may present even more problems. Within the


Caribbean region where

populations may be as low as 10,000, the problems of


arbitration would be several fold.

Arbitrators would therefore have to come from the other


territories with a stronger, more

numerous and experienced body of construction


professionals. While this would increase

the element of independence, it will increase costs since


the arbitrator may have to be brought

in from the United States or the United Kingdom as has


been the case. One of the critical issues faced by
conducting the arbitration process stems from the

inexperience and hence lack of confidence within the


construction sector for the arbitration

process. Frequently, one disputant procures a team of


attorneys, including Senior Council

(SC) (equivalent to the British QC) and junior and


instructing attorney (previously the

solicitor). The immediate response is for the contending


side to procure an equally powerful

team. The effect of this is to drive the costs up but


above all to present a nightmare of Alternative dispute
resolution methods 387

scheduling dates on which the senior legal persons can


attend. This is particularly a problem

since the arbitrator has no back up staff and lacks the


confidence and machinery to compel

the attendance of parties and witnesses. The entire


process is based on consensus and the

arbitrator has to be constantly concerned that the


process, once started, is not aborted. There
is always the risk of long drawn out schedules biasing
this consensus. There is always the

risk of abortion as the lawyers constantly seek to


transform what should be an informal

climate into a formal court setting and as they seek to


exclude some submission or to

introduce what they maintain is a point oflaw. They


frequently calion the arbitrator to give

rulings on different points. These could later be the


basis of appeals. The question of a convenient place
(room) with support facilities to hold the arbitration

hearings does present considerable problems which may not


exist in developed countries.

Frequently, arbitrations are held in hotels or in the


conference rooms of the lawyers involved.

Several of the alternative disputes resolution mechanisms


require space that would permit

staging of hearings and the problem will apply to


conciliations, mediations and mini trials

as well. Another problem that may appear as a huge


obstacle to arbitration is the question of

taping of evidence and or the use of palantypists to record


verbatim all that transpires. It is

not likely that the arbitration will be able to procure the


services of a palantypist and if

evidence is recorded manually, then it must be transcribed


at the end of each day. These

difficulties could loom large in a small developing country.

The fact that the Arbitrator has no coercive machinery such


as is available to the judges

of the high court nor the capacity to exercise sanction to


an offending party, means that his

modus must be based always on consultation and consent.


This introduces an element of

caution and hence the question of delay is always an issue.

It is clear that there has been very little experience in


the several alternative dispute

resolution methods in the construction sector here in


Trinidad and Tobago and for that matter

in the rest of the Commonwealth Caribbean states. What


experience there has been is in

arbitrations and as we have seen, even this practice


leaves much to be desired. One may ask

"Why entertain the other dispute resolution methods?"

To answer the question, we must understand how disputes


arise in general and in the

construction sector in particular. We must understand why


they fester and what causes them

to explode. Are conflicts inherent in the construction


process? Can they be averted or reduced?

It is obvious that some of the characteristics of the


construction sector favour the occurrence

and development of conflicts e.g.:

1. Ease of entry of new form.

2. Low level of skill experience and knowledge of many of


the new entrants.

3. High rate of failure and bankruptcy.

4. All pervasive adversarial relationships.

5. Expectation of high return on investment.

6. Little self-policing and monitoring with the sector of


quality of goods and or services

exchanged.

P
r e

s e

n t

o u

t e

p l

o y

e d r E N D ~ E N D \ I ; t ~ I C o n c i l i a t i o n l ~
I T I M i n i T r i a l ~ R r b i t r a t i o n I ~ E N D D
i s p u t e \ l I E N D ( C o n s u l t a n t C o C o n t r
a c t o r R e s o l u t i o n ) ~ ~ 1 > 1 M e d i a t i o n
I + " ' f ~ \ I I 4 E N D , ~ , . . F i g . 1 . A l t e r n
a t i v e D i s p u t e R e s o l u t i o n F l o w R d j u
d i c a t i o n 1 t \ 4 ' 1 1 1 1 1 1 1 1 1 1 1 1 I > E N D
1 1 1 1 1 11 1 \ V l i t i g a t i o n I ~ E N D
Alternative dispute resolution methods 389

7. Low level of training for and within the sector in


general but in dispute resolution in particular. It is
clear that the local experience in the use of the
arbitration process has produced

frustrations attendant upon the inordinate delays and the


high costs. The local experience is

that arbitration involves on as average at least five


years and in some cases as much as ten

years to produce a resolution. But it yet appears a better


route than the courts. This would

suggest that the sector must undertake both a serious


re-evaluation of the local practice to

find ways to make the process more effective by reducing


the period between the initiation
of arbitration and the final resolution. The next thing
would be for the participants within

the sector to explore the use of alternative dispute


resolution methods, particularly those

that have been successfully employed in other areas of


business activity e.g., industrial

disputes.

4 Discussion The objectives of the construction sector in


respect of appropriate methods of dispute

resolution can be set out as follows:

1. To avoid conflicts and disputes and to solve them


immediately when they do occur. This can bedone by better
specifications, replacing the adversarial relationship
between consultant and contractor with one of dialogue,
partnership and risk-sharing.

2. Should the dispute develop, all attempts should be made


to deal with it as swiftly as possible, while seeking to
minimise the impact by containment and employing one of
the alternative dispute resolution methods.

3. Parties to building contracts must become better aware


of the spectrum of resolution methods available and how to
prepare to employ them.

It is clear that the present approach has been to have


recourse to arbitration, based on the

inclusion of an arbitration clause in the contract


document. However, arbitration should

definitely not be the first course of action. One or other


of the Alternative Disputes

Resolution methods, such as conciliation, mediation, mini


trials and adjudication could, to

better effect be tried even prior to resort to Arbitration.

1. Trevor Lee. Sc. "Arbitration, Conciliation, Mediation


and Other Methods of Alternative Disputes Resolution".
Presented at a Short Course on Contract Management and
Contract Law for the Construction Sector by the Continuing
Engineering Education Centre, UWI, St. Augustine. April
1995.

390 Suite

2. Suite, Winston H.E. "The Factors which tend to Frustrate


the Arbitration Process in Small Developing Countries".
Workshop organised by the Quantity Surveyors Society of
Trinidadand Tobago and the Faculty of Engineering, UWI.
1990. CAPITAL WORKS PROCUREMENT:

OWNER'S OBLIGATIONS UNDER THE 'TENDERING CONTRACT'

R.W. Craig

Department of Civil and Building Engineering, Loughborough

University, UK

P. Davenport

Faculty of the Built Environment, University of New South


Wales,

Sydney, Australia

Abstract

This paper examines the New Zealand case of Pratt


Contractors in which the court held

that a 'tendering contract' had been created between


plaintiff tenderer and local

authority, that the contract was broken when the authority


accepted a non-conforming

alternative tender, and that the plaintiff was entitled to


damages. The basis for

establishing the quantum of such damages is argued. The


paper concludes with advice

to building owners with regard to the 'tendering contract'.

Keywords: Australian law, Competition, Construction


procurement, Engineering,

procurement, English law, New Zealand law, Tenders.

Sommaire
Ce papier approfondit la cause de la maison Pratt
Contractors en Nouvelle-Zelande

dans laquelle Ie tribunal a tenu qu'un contrat de


soumission (,tendering contract') fut

cree entre I' offreur plaignant et Ie defendeur, que Ie


contrat fut viole au point ou

I'autorite a agree une contre-soumission non-conforme, et


que Ie demandeur a ete

habilite a des dommages-interets. Pour conclure, Ie papier


renseigne des proprietaires

au sujet du contrat de soumission (,tendering contract').

1 Introduction

For many years an invitation to tender was considered to be


no more than an invitation

to treat, creating no obligations for either party until


the essential elements of a binding

contract were present. The inviter appeared to be free of


any obligation and could reject

any or all offers. There was in fact one restriction placed


on the inviter: there must be

the intention to award a contract, otherwise the invitation


is a fraud giving an invitee a

cause of action in the tort of deceit. The costs of


tendering are normally borne by the

The Organization and Management of Construction: Shaping


theory and practice (Volume Two).

Edited by D.A. Langford and A. Retik. Published in 1996 by


E & FN Span. ISBN 0 419 22240 5. 392 Craig and Davenport
tender, with expectation of recovery of those costs only
through successful tenders which result in the award of
contracts. But when the inviter indicated to the lowest
tenderer that a contract award was likely, asked for more
information beyond the scope usually necessary for the
consideration of tenders, then abandoned the project, the
court held that the lowest tenderer was entitled to
restitutionary recompense on the basis of a quantum
meruit. J Recently, the court established the tenderer's
right in contract to have his tender, submitted in
accordance with detailed procedures prescribed by the
inviter, duly

considered if other tenders are considered. Here the


inviter's contractual obligation to

consider all conforming tenders arose, not out of an


express term of the invitation, but

by implication in the circumstances. 2 The inviter was


obliged to pay damages for the

breach of contract. Similar cases exist in other


jurisdictions, 3 and from these cases we

can observe the recent emergence of the 'tendering


contract' where the inviter becomes

contractually obliged to give consideration to all tenders


which are submitted in

accordance with the inviter's stipulations.

2 The Pratt Contractors case

The New Zealand case of Pratt Contractors Ltd v.


Palmerston North City Council,4

highlights the problems for all building owners associated


with 'alternative tenders' and

the 'tendering contract'. The plaintiff contractor sued the


local Council for damages

because it did not obtain the contract. The Council


required tenders for the construction of a flyover
interchange.

Interested parties were required to submit a non-refundable


deposit of $100 at pre

registration stage. The tender documentation was detailed


and included provisions for

the evaluation of tenders received. There were two tender


evaluation methods open to
the Council: in this case the process to be adopted was
described as "lowest price

conforming tender method". This process involved each


tenderer submitting

information against six non-price attributes. The Council


was then required to assess

each tenderer's responses against each of these attributes


on a pass-fail basis. A fail on

any of the attributes meant that the relevant tender was


not a conforming tender and

would not therefore be considered. Only a pass on each


attribute permits a tender to be

considered on price alone the lowest tender is the


successful tender. Four conforming tenders were received.
Pratt Contractors submitted the lowest

conforming tender and on that basis expected to be awarded


the contract. But one

tenderer submitted an alternative tender in addition to


its conforming tender. Tendering

procedures had contemplated alternative tenders, which


might be permitted as a means

of encouraging or permitting innovation. Proposals for


alternative construction methods

or choice of materials are considered but such proposals


must not alter the scope of the

final product. The alternative tender outlined a different


design solution which would

achieve the same product: "the saving in the construction


costs would be in the order of

$250,000.,,5 Certain other claims were made for the


alternative scheme and it

concluded: "We would be happy to meet and discuss this


proposal or forward any

further information you may require ,,6 The saving offered


by the alternative tender was attractive to the Council.
After

some negotiation over the exact status of the alternative


tender, the Council accepted The tendering contract 393
same and advised the other tenderers of the contract award
decision. When matters were fully resolved a formal
contract was executed between the Council and the
submitter of the alternative tender. Pratt Contractors had
submitted their tender, not only in expectation of making
a

profit from the completed contract, but also as a means of


establishing for itself a track

record in this type of work. Aware that their tender was


lower than the successful

tenderer, and in the full knowledge that they had passed


the attributes test, Pratt was

aggrieved with the Council's decision and commenced


proceedings for damages. They

contended, inter alia, that by submitting their tender a


contrace was created between

themselves and the Council, whereby the Council became


obliged to consider only

tenders which complied with the tender stipulations. They


further argued that this

contract had an implied term obliging the Council to treat


Pratt fairly and equally with

other tenderers, and that should another design option be


put forward by the Council,

Pratt would be given the opportunity of pricing that


option, and that there would be no

negotiation with another tenderer. Pratt alleged that


implied and express terms of the

contract documents had not been complied with, and as a


result they had lost (i) the

cost of preparing the tender; and (ii) the profit on the


contract which should have been
awarded to Pratt; and (iii) the opportunity to gain
qualification for other substantial

construction projects, and consequently further lost


profits. In defence, the Council argued that their request
for tenders was no more than an

invitation to treat, and that therefore no contractual


obligations arose. The Council

denied the alleged failures catalogued by Pratt, and argued


that, even if this was not

correct, Pratt had no basis for recovery. They contended


that the contract had been

properly awarded on the basis of the alternative tender,


properly submitted In

accordance with the tender documents, and that Pratt had no


right to damages.

3 The issues considered in detail

3.1 Do the Council and Pratt have a contractual


relationship?

The first issue is whether the submission of the tender by


Pratt creates a contractual

relationship. Having considered several authorities, Gallen


J said: "Authority makes it clear that the starting point
is that a simple uncomplicated request for bids will
generally be no more than an invitation to treat, not
giving rise to contractual obligations, although it may
give rise to obligations to act fairly. On the other hand,
it is obviously open to persons to enter into a
preliminary contract with the expectation that it will lead
in defined circumstances to a second or principal
contract, along the lines of the analysis in the Canadian
cases. Whether or not the particular case falls into one
category or the other will depend upon a consideration of
the circumstances and the obligations expressly or
implicitly accepted.,,8

Did the parties intend to create a contractual relationship


with respect to the submission

of the tender? Gallen J thought that there were several


factors pointing to the answer

yes. "First, this was not a situation where there was a


mere calling for tenders and nothing more. The first
advertisement requested contractors to register their
interest for the construction of the project. In order to
tender at all, interested contractors had to register their
interest and pay a $100 non

394 Craig and Davenport refundable deposit before they


received the tender documents for consideration. The actual
submission of a tender was therefore contemplated as a
second step and moreover, one which followed upon a
declaration of interest backed by a non-refundable
deposit. This is I think a significant point. Its is at
least as strong and in fact in my view rather stronger,
than the suggestion in the Blackpool case that the
selection oftenderers was a significant factor. Secondly,
the tender documents were extensive, detailed and
substantial. They set out not only the nature of the
project contemplated, supported by detailed specifications
and drawings, but also set out the conditions of contract
which would apply if a construction contract were entered
into. Most significantly they included an addendum to the
conditions of tendering which contained the following
clause: l.(b) Tenders will be evaluated by the Lowest
Price Conforming Tender Method, as prescribed in the
Transit New Zealand Manual of Competitive Pricing
Procedures, Volume 1: Physical Works and Professional
Services (CPP Manual). Attributes shall comprise the
following: • Relative Experience • Track Record •
Technical Skills (personnel) • Resources (plant,
equipment, material) • Management skills • Methodology •
Price This tender evaluation process shall be conducted in
two stages: (i) The first stage shall consist of
determination of tender acceptability when assessed against
each of the six non-price attributes and no others. Each
attribute shall be scored on a pass! fail basis. Any
attribute which scores a fail will exclude that tender from
further consideration. Any tender which alters the scope
of the end result shall be excluded from further
consideration. (ii) The second stage shall consist of
determining which of the remaining (non-excluded) tenders
has the lowest price. The Principal shall only enter into
a contract for the non-excluded tender with the lowest
price.,,9

Gallen J said: "That indicates in detail the precise way


in which the Council will evaluate tenders and indicates in
mandatory terms, the basis on which a contract will be
entered into. If that is to impose obligations upon the
Council so that it is required to act in accordance with
its indicated intention, then of course it may become
binding in a number of ways. That is evidence by the number
of causes of action pleaded in this case, but in a
commercial setting of the nature of the tendering process,
by far the most convenient framework within which
obligations may be said to arise and within which they can
be considered, is a contractual one ...... . The Council
has here sought interested tenderers who were required to
express their interest in obtaining the tender documents,
by the paying ofa non-refundable deposit [NZ$100]. The
basis upon which tenders were sought is detailed and
complete and is in itself required to be accompanied by a
substantial deposit of $10,000. Under those circumstances,
ifthe Council were to attempt to deal with the tenders on
any basis other than that contained in the tender
documents, at least the elements for an estoppel argument
would be present but I think it is far preferable to deal
with the matter in terms of contract." I 0 The tendering
contract 395 It was true that there were distinguishable
facts in the previous tender cases, but the one thing they
all had in common was that in order to give effect to the
various stipulations contained within the tender documents
it was necessary to recognise a contractual relationship.
The court was satisfied that a contract was created by the
act of submitting

a tender in accordance with the Council's requirements.

3.2 Is the Council in breach by failing to award the


contract to Pratt?

Having established that a contract has been created, the


second issue is whether the

Council are in breach of that contract. What are the terms


of that contract? They are to

be found within the policy and specifications upon which


the tender was submitted. And

that includes the promise to evaluate tenders in


accordance with the tender conditions.

But is it a term of that contract that the Council is


obliged to award the contract to the

lowest conforming tenderer? The tender conditions state


that: "The principal shall only
enter into contract for the non-excluded tender with the
lowest price." A Canadian court held that a provision
that "no tenders need necessarily be

accepted" did not cancel an award provision which stated


that the award "will be made

on the basis of the highest offer made by that tenderer ..


,,11 But here the Council

argued that where an invitation to tender is no more than


an invitation to treat, it is

unnecessary for a building owner or employer to state that


there is no obligation to

accept the lowest tender. But is this the position when


there is a contractual relationship

rather than a mere invitation to treat? Seeking to avoid


any obligation, the Council

relied on words which footed the tender form: "We


understand that the Principal is not

bound to accept the lowest or any tender he may receive".


They argued that it was of

no consequence that Pratt Contractors won the competition;


they were not obliged to

accept Pratt's tender. But the court did not find any
conflict in the several provisions within the tender

documents. The Council's general powers of rejection are


not compromised by the

other provisions. The Canadian court's words had to be put


into context. Gallen J said: .. that a Council could not
be permitted to use the general power to reject tenders to
make an arbitrary choice. In selecting a particular
tender, the Council is in my view bound by the terms it
has itself imposed. as well as the requirements of
fairness and equity which may well have an application.
To hold however that a Council retains a power to reject
all tenders. is not the same as allowing it to use such
power to select tenders.,,12

The court therefore rejected Pratt's claim that they were


entitled to the contract award

since they had submitted the lowest price conforming


tender. The Council is not in

breach for failing to award the contract to Pratt.

3.3 Is the alternative tender a conforming tender capable


of acceptance within

the Council's tender conditions, or is the Council in


breach for accepting same?

Pratt argued that the alternative tender was not a tender


at all because it lacked

certainty of price, and that it did not meet the specific


requirements laid down in the

tender conditions. The language used in the alternative


tender was too vague on which

to found a contract. 13 Gallen J agreed and said: 396


Craig and Davenport I do not see how that could possibly
be regarded as having the certainty to found a contract,
nor did the Council so see it. (The) Council's advisers
sought additional information and also carried out there
own cost assessment. 14 If the conforming tender had been
couched in such vague terms as the alternative

tender, it would not have been considered to be


conforming: "in any event (the

alternative tender letter) refers to a saving in


construction costs and not to a price at

all." 15 The alternative tender is therefore not a


conforming tender. It is insufficiently

precise to be capable of acceptance within the Council's


tender conditions. The Council

themselves realised that the alternative tender could not


be accepted in the form

submitted, and sought clarification. The alternative tender


did not therefore comply

with the Council's tendering stipulations. In purporting to


accept the alternative tender
the Council is in breach of the 'tendering contract'.

3.4 Does the law impose a duty of fairness on the Council


when dealing with

tenders, and, if so, was that duty broken?

Gallen J said: "There is also an aspect of fairness. It


was conceded by ... (the Council), that the Council was
obliged to proceed in a manner which met the general
requirements of that indefinable term 'fairness'. To
accept as an alternative tender and thus deprive the lowest
conforming tenderer of such opportunity as that
qualification gave it, a document which is indefinite in
terms of price, which required elucidation and
confirmation, was I think unfair. That comes close to
negotiating with one of the tenderers within the tender
process, but not on terms which apply to other tenderers.
,,16

It appeared from the evidence that the cost savings offered


by the alternative tender

were not wholly due to more efficient design, but instead


due to the omission of items

which would be required an any event. Gallen J sensed not


only unfairness, but danger.

He said: "Effectively therefore, (the alternative


tenderer) was indicating that it would be prepared to
reduce its tendered amount by a substantial sum, which
did not result from the proposed change. That could give
rise to very real dangers in the contracting process and
could easily enough be manipulated to ensure that an
unsuccessful tenderer could reduce his or her tender, by a
sum sufficient to secure the contract by a means which
was disguised by reference to some form of alternative
construction .... ... an unscrupulous tenderer, could not
only achieve success over other tenderers in the way
already described, but if that tenderer was in fact the
lowest tenderer, could avoid being held to the alternative
if the proposal was insufficiently precise to give rise to
contractual obligations. 17

It is dangerous to consider alternative tenders without


sufficient definition of the term.

An adequate basis of assessment is needed for sound


management and to avoid

unfairness to tenderers. Here there is a breach of the


Council's duty to treat all

tenderers fairly. The tendering contract 397

4 Quantum of damages

The court had thus found for the plaintiff tenderer against
the Council. It remained only

to fix the quantum of damages. The general principle should


be consistent in all breach

of contract cases. The successful plaintiff is to be put,


"so far as money can do it ... in

the same situation ... as if the contract had been


performed.,,18 In fact what Gallen J

said is that "the plaintiff is entitled to be restored to


the position it would have been in

had the Council complied with the obligations imposed upon


it."19 The significance of

this restatement is argued below. Pratt sought damages


under three heads: the wasted expenditure in preparation of

their tender, the loss of profit which would have been


earned had they been awarded

this contract, and loss of future profits which they would


have earned from future

contracts, but for the loss off attributes caused by the


failure to win this prestige

contract.

4.1 Wasted expenditure

Pratt tendered on the basis that tender costs would not be


directly recoverable. But

since the Council was in breach of the tender conditions,


Pratt was entitled to recover

its wasted costs of tendering. Pratt recovered $17,822


under this head of claim.

4.2 Loss of profit due to the failure to secure this


contract

Pratt argued that it would have been awarded the contract


had the alternative tender not

been accepted, and that it would have made a profit in the


amount claimed, based on a

percentage of their tender submitted. The Council argued


that, had it not been for the

alternative tender, no contract would have been awarded due


to the excess of tendered

price over budget. They also contended that had Pratt been
awarded the contract they

would have sustained loss rather than profit. The judge


did not accept that the project

would not have proceeded without the acceptance of the


alternative tender. It

represented a saving of only 6.7% on a budget of $3m. On


the evidence, the judge

concluded that had it not been for the alternative tender,


Pratt would have been

awarded the contract. But what profit would have been


earned by Pratt if it had been awarded this

contract? The Council produced evidence to demonstrate the


lack of profitability in the

contract. The judge accepted that this had proved a more


difficult contract to perform

than had been anticipated, but he was not prepared to


accept that Pratt would

necessarily have earned no profit. Gallen J made his


"overall assessment in the round",

and awarded $200,000 to Pratt. This was the amount by which


the successful tenderer
had reduced the price to secure the contract. Gallen J
said: The $200,000 is not disproportionate to the savings
that the Council made by adopting a practice which I do
not consider was open to it. It bears some relationship to
the sums which the successful contractor effectively wrote
off its non-conforming tender and it is comparable to the
savings which were identified by the Council's advisers.
2o 398 Craig and Davenport 4.3 Loss of future profits due
to the loss of attributes caused by the failure to

secure this contract

In Pratt's most speculative claim, they argued that the


current system of tendering

placed great emphasis on the pass/ fail test applied to


the attributes of each tenderer.

Winning this prestige project would have enhanced Pratt's


attributes when under

consideration on other projects. Evidence was adduced which


demonstrated Pratt's lack

of success in being considered for other work. This lack of


success, it was argued, was

due to the lack of attributes which would have been earned


had they been awarded this

contract. But the Council was able to demonstrate that


even if Pratt had been awarded

this project, and successfully completed it, there would


have been little impact on its

ability to secure these other projects. But the court held


that this claim was too

speculative and remote. Pratt therefore succeeded on the


first two heads of claim, but

not on the third. They recovered $217,822 against the


Council and were entitled to

costs.

5 Davenport's criticism of the decision by Gallen J21

Gallen J is criticised for awarding Pratt Contractors


reliance loss and expectation loss at

the same time. Gallen J awarded Pratt Contractors their


wasted tendering costs when

the Council, in breach of the 'tendering contract',


awarded the contract to other than

the lowest tenderer. Pratt incurred that tendering cost


before the Council breached the

contract. The cost was therefore not caused by the breach.


Pratt would have incurred

these costs even if they had been awarded the contract in


question. The wasted

tendering costs could only have been recovered as reliance


loss, whereas Pratt's claim

was, in truth, for expectation loss, that is the loss of


profit which would have been

earned but for the Council's breach. The award of


$200,000 to Pratt for loss of profit, was, with respect,
not based on a

logical method of assessing damages. An Australian court,


faced with the same claim

and without proof that Pratt would have made a profit if


awarded the contract, would,

it is submitted, follow Amann Aviation 22 and award only


reliance loss, which here is the

cost of tendering. On the other hand, given proof of loss


of profit, the court would

award that loss of profit, but not in addition to the cost


of tendering. In no

circumstances should Pratt be able to recover both cost of


tendering and loss of profit.

6 Craig's defence and support of the decision by Gallen J

In cases of breach of contract the classical analysis23


produces three situations in
awarding contract damages: (1) where the injured party in
reliance on the other, has

conferred some benefit to the other who has failed to


perform; the policy here is to

prevent unjust enrichment and may be termed the


restitution interest; and (2) where the

injured party has relied on the other and changed his


position to his detriment and may

be termed the reliance interest; and (3) ignoring


enrichment and reliance, a policy which

seeks to give the value of the expectation created by the


contract which may be termed

the loss of bargain or expectation interest. Admittedly,


the English court has only

recently taken on board this sort of analysis, and maybe a


less than wholesale adoption.

The restitution measure is not normally used in England in


breach of contract claims: an The tendering contract 399

examination of what the injured party has lost is more


likely than an assessment of what

the other has gained, but frequently the expenditure will


more or less be about equal to

the gain.

6.1 The recovery of wasted costs as reliance loss

In the case of Anglia Television v. Ree(P a leading actor


repudiated his contract after

the plaintiff TV company had committed expenditure on other


actors etc. Note that not

only was this wasted cost expended before the breach but
some part was expended

before the contract with Reed was made. Lord Denning MR


said that in such a case a

plaintiff was not limited to claiming expenditure after


the contract was made:

expenditure could be claimed which arose before the


contract was made "provided that

it was such as would reasonably be in the contemplation of


the parties as likely to be

wasted if the contract was broken. ,,25 Recovery of the


pre-contract expense is justified

because that loss cannot be avoided after the breach 26 To


paraphrase Lord Denning

again: when Palmerston North City Council broke its


'tendering contract' it must have

known perfectly well that much expenditure had already been


incurred on the costs of

preparing the tender. They must have contemplated, or at


any rate it is reasonably to be

imputed to them, that if the contract was broken, all that


expenditure would be wasted,

whether it was incurred before or after the contract (or


its breach). They must pay

damages for all the expenditure so wasted and thrown away.

6.2 Recovery of lost profit as expectation loss

Davenport criticises the New Zealand court for awarding


both the wasted cost of

tendering and the loss of profit caused by the City


Council's failure to award the

contract to the plaintiff. At first glance this objection


receives support from Lord

Denning in the Anglia Television case: " ... a plaintiff


in such a case as this has an

election: he can either claim for his loss of profits; or


for his wasted expenditure. But he

must elect between them. He cannot claim both." Lord


Denning cited Cullinane v.
British 'Rema' Manufacturing Co Ltef? as authority for this
statement of law. But the

question must be asked: what is meant by the term


'profit'? Is it gross profit or net

profit? If the former, then clearly the statement is


correct, otherwise double recovery of

wasted expenditure would occur. That is gross profit would


include the expenditure

necessary to secure the contract, namely the costs of


tendering. But if the term refers to

net profit, then surely there is no objection in principle


to recovery of both the wasted

expenditure to secure the contract and the profit net of


all costs necessary to perform

the contract. In Hydraulic Engineering Co Ltd v. McHaffie,


Goslett & C0 28 the

plaintiffs recovered wasted expenditure and the net profit


which would have been

earned had the contract been performed without breach. In


Miller's case 29 the plaintiff

recovered the price paid for defective machinery


(restitution), installation costs

(reliance loss) and net loss of profits resulting from the


breach (loss of bargain!

expectation loss). It seems clear from the judgment of


Gallen J that net profit was

awarded here, and awarded quite properly, to the plaintiff.

6.3 Recovery of both wasted costs and lost profit as


restitutio nary compensation?

To hark back to Fuller and Perdue's analysis: on what basis


should the breach of I

contract damages in this case be classified? Is it


restitution interest, reliance interest or
expectation interest that is being protected and
compensated? Davenport suggests the

400 Craig and Davenport

wasted tendering costs are a reliance loss and the loss of


profits are an expectation

loss, and that on well-founded principle both types of


damages cannot be recovered.

That is the conventional position. At first glance Gallen


J does not appear to help us on

this point. But the clue is in the statement: "The


plaintiff is entitled to be restored to the

position it would have been in had the Council complied


with the obligations imposed

on it.,,30 Gallen J sees this award as restitutionary


compensation. This type of damage

is appropriate when there is a total failure of


consideration, as there is in this case. Pratt

relied on the Council under the terms of the 'tendering


contract' and conferred a benefit

on them. The Council failed to discharge their obligations


and should be forced to

disgorge the value received from Pratt, who therefore


recovers his expenditure on

tendering, plus the amount by which the Council has


benefited. The policy is to prevent

unjust enrichment. The restitution interest comprises the


two elements of reliance and

resultant gain.

6.4 Conclusion on quantum of damages

The traditional view held in England and Australia is not


to use a restitution measure to

assess damages for breach of contract. For example in Tito


v. Waddell (No2) Megarry

V-C said ··First. it is fundamental to all questions of


damages that they are to compensate the plaintiff for his
loss or injury by putting him as nearly as possible in the
same position as he would have been in had he not suffered
the wrong. The question is not one of making the defendant
disgorge what he has saved by committing the wrong. but
one of compensating the plaintiff ... 31

Clearly the New Zealand court takes a different approach.


In England there are

exceptions which do allow the recovery in restitution of


the profit made by a contract

breaker. 32 It has been argued that this remedy should be


more widely available. 33 The

English contributor submits that breach of the tendering


contract is a worthy exception

where recovery of the restitution interest should be


available. The Australian

contributor disagrees.

7 Conclusion

7.1 Owners should be mindful of the 'tendering contract'


which places obligations on

the owner: mainly to treat all tenderers fairly and to


consider all conforming tenders.

7.2 Owners could seek to avoid the obligations of the


'tendering contract' by reducing

all tendering conditions to the very minimum (consistent


with other obligations), on the

basis that it is the requirement for compliance with


demanding tender regulation which

creates the 'tendering contract'. This advice is


inconsistent with advice given below,

particularly in the matter of alternative tenders.

7.3 Owners could place an exclusion clause in every tender


notice and invitation to

tender. An example would be: This invitation to tender is


not an offer capable of acceptance. This invitation to
tender is an invitation to treat. The submission of a
tender does not create any contract between the tenderer
and the owner. The owner does not warrant compliance with
the conditions of tender or with any tender codes or
regulations. The tendering contract 401

7.4 Owners should not ask for cash or deposits from


tenderers. Such payments could

be construed as an element in the formation of the


'tendering contract'.

7.5 If the tender conditions incorporate other documents


(or parts of documents) by

reference, this must be clearly drafted to avoid ambiguity.


Any confusion in the drafting

will be construed against the owner. If the owner is


obtaining funds from a funder who

requires compliance with specific provisions as to


tendering, these provisions must be

included within the owner's conditions of tendering.


Failure to do so effectively could

breach the funding agreement.

7.6 There are good public policy reasons for considering


alternative tenders.

Alternative tenders "are an important means of ensuring


that innovative approaches as

to contracts are available to tendering authorities ...


the public may very well benefit to

a considerable degree from the encouragement of such


innovation and the availability of

cheaper methods of construction than have been contemplated


by the tendering

authority or their advisers. ,,34


7.7 The taking of and consideration of 'alternative
tenders' presents pitfalls to the

unwary. If alternative tenders will not be considered in


any circumstances, this should

be clearly stated in the invitation and the tender


conditions. If alternative tenders will be

considered, the invitation and conditions must make clear


exactly what 'alternatives'

will be considered and the means of their evaluation.


Thought must be given as to

whether an alternative tender merely adjusts a previous


tender, or stands as an

independent offer capable of acceptance without reference


to the previous tender. Does

the consideration of the alternative tender mean that


reassessment of the tenderer's

attributes must be made?

7.8 Provisions for the consideration of alternative


tenders must be made with a clear

policy on the degree of departure from the original scheme


which is permitted. The

New Zealand conditions stated that any proposal must be


"within the scope of' the

request for tenders. But what does "within the scope of'
mean? Subsequently a

definition of the word scope was provided: "Scope is the


project's principal purpose(s)

and service( s) to users as specified in ... ". It was


suggested in evidence that this a

practical definition that would suit the contracting world.


35 Other evidence suggested

that scope should "be considered in relation to the nature


of the project, as distinct from
its purposes and in that case, its conformity became a
matter of degree." Other

suggestions would limit the definition of scope, such as a


provision proposing that

"alternative methods or materials which may alter the


quality or durability but not the

scope of the end result". 36

7.9 The concept of a conforming alternative tenders must


not be defined to tightly so

as to restrict innovation, but must be not so broad as to


permit a different design

proposal, which would be unfair to tenderers who submit


conforming tenders.

7.10 Any departure from the conditions of tender risks


unfairness to the tenderer(s).

The owner's obligation to be fair to all tenderers should


not be compromised by bad

management.

402 Craig and Davenport

I See the authors' paper Capital Works Procurement: A


Comparative Analysis of

Procurement in England and in New South Wales, Australia


presented to the CIB W92

Procurement Systems Symposium, Durban, South Mrica, January


1996 at page 97.

2 Blackpool & Fylde Aero Club v. Blackpool Bor. Council


[1990] 1 WLR 1195 (CA).

3 See CIB W92 (Durban) Proceedings, supra, for a list of


the relevant cases.

4 [1995] 1 NZLR 469, in the New Zealand High Court,


Palmerston North.

5 Reference to the alternative tender letter, reproduced


ibid. at 473115-38.
6 Ibid. at 473/37-38.

7 That is the 'tendering contract', not to be confused with


the building contract.

8 [1995] 1 NZLR469, at 478/51-479/5.

9 Ibid. at 479/48 480115.

10 Ibid. at 480116.

II Canamerican Auto Lease & Rental Ltdv. Canada (M ofT)


198777 NR 141 (Can.)

12 [1995] 1 NZLR 469 at 481152-482/1.

13 A saving of $250,000 was mentioned, but not as a price,


merely as a 'saving in

construction cost'. The figure was not given definitively,


but put 'in the order of.

14 [1995] 1 NZLR 469 at 482/33-35.

15 Ibid. at 483/4.

16 Ibid. at 483/34-41.

17 Ibid. at 483/47-53 and 484110-13.

18 Robinson v. Harman (1848) 1 Ex 850,855.

19 [1995] 1 NZLR 469 at 487112-13.

20 Ibid. at 489122-26.

21 See Davenport's article in (1995) Australian


Construction Law Newsletter (ACLN).

22 C'wealth of Aust. v. Amann Aviation Pty (1991) 104 ALR


1; (1992) 23 ACLN 35

23 Fuller and Perdue (1936) 46 Yale LJ 52,52-56 The


reliance interest in contract

damage; see Beale, Bishop & Furmston (BBF)(1990) Contract


Cases and Materials

(2nd ed.) Butterworths, London, at pp. 466-467 and 562.


24 [1971] 3 All ER 690 (CA).

25 Ibid. at 692c.

26 CCC (London) Films Ltd v. Imperial Quadrant Films [1985]


QB 16.

27 [1954] 1 QB 292; [1953 2 All ER 1257 (CA).

28 (1878) 4 QBD 670.

29 Miller's Machinery Co Ltd v. David Way & Son (1935) 40


Com Cas 204.

According to Treitel (1987) The Law of Contract (7th ed) at


p.726, there is no logical

objection to combining these types of claims, so long as


the plaintiff does not recover

the same loss twice.

30 [1995] 1 NZLR 469 at 487112-13.

31 [1977] Ch 106, 332.

32 See (BBF) (1990) Contract Cases and Materials at p.553.


The example is that ofa

party in breach who owes a fiduciary duty to the injured


party.

33 Refer to Jones (1983) 99 LQR 443 and Birks [1987] LMCLQ


421, cited by BBF.

34 [1995] 1 NZLR 469 per Gallen J at 485122-26.

35 Ibid at 486/7.

36 Ibid. at 486/8-18, ref TNZManual of Competitive Pricing


Procedures (CPP)
2 Partnering

4. Lehtinen, U. (1991). Alihankintajarjestelma


1990-luvulla. (Supplier system in the 1990 's.) Sitra no
114. Helsinki. (in Finnish)

5. Schonberger, R. J. (1986). WCM World Class


Manufacturing. The Free Press. New York.

6. Kano, N. (1986). Laatu turvaa tuloksen -TQC, yrityksen


uusi toimintatapa. (Results with Quality -TQC, the new
way). Suomen laatuyhdistys ry. (in Finnish)

7. Tanskanen, K. (1987). Osahankintayhteistyo


yritysesimerkkeja (Customer-supplier Co-operation Case
Examples). MET 3/87. Helsinki. (in Finnish)

Mots-cles: l'arbitrage; Ie "dessin-construire"; Resolution


des con flits; Latham; Les

The Organization and Management of Construction: Shaping


theory and practice (Volume Two).

Edited by D.A. Langford and A. Retik. Published in 1996 by


E & FN Spon. ISBN 0 419 22240 5. A US review of the Latham
Report 415 Etats-Unis, des differences de la part de
Royaume-Uni. 1 Introduction and Background The early
1990s were a terrible time for the construction industries
in the United States and the United Kingdom. Overbuilt
markets, overheated economies, overextended developers
and, indeed, simple greed and mismanagement, led to a
significant decline in construction volume. The effect on
each country's economy -construction accounts for 8% of
GDP in the UK [1] and 4. 4% of GDP in the US [2] -cannot
be understated. However, it can be argued that the
industry's litigiousness as much as anything else played a
major role in its difficulties. In the UK, disputes
surrounding major projects such as Canary Wharf and the
Channel Tunnel came to exemplify what many saw as the
decline of a once-magnificent industry which had built an
Empire. In the US, where the absolute number of claims
peaked in 1989 [3], somewhat earlier than reported in the
UK, the cost per claim for design professionals insured by
one professional indemnity carrier climbed steadily from
$179,000 in 1985 to $268,000 in 1993 [4]; and similar
results were reported for the aggregate amount of damages
claimed in construction arbitration cases in general [5].
Whether the claims explosion of the '80s and early '90s
was a cause, symptom, or effect of the construction
industry's other difficulties may be left to others to sort
out. What is certain is that -on both sides of the
Atlantic -the industry's factiousness cannot have helped
to ameliorate an already desperate situation. In sorting
through the debris, one might examine a number of possible
explanations for this phenomenon. Undoubtedly, there are
many opinions: high· interest rates, inflation, feverish
competition for fewer projects, and speculative frenzy can
all take their place in the line of suspects. Certainly,
however, poor project organisation -a lack of attention
to the details relating to project structure,
communication, and execution -can be singled out
anecdotally as a key factor in many claim-ridden projects.
In response to this perception, Sir Michael Latham, a
former Conservative MP and ex-director of the UK
Housebuilders Federation, was commissioned by HM
Government to lead a year-long, £250,000 enquiry with the
purpose of ending "the culture of conflict and
inefficiency that dogs Britain's biggest industry" [6].
The report, entitled Constructing The Team, Final Report
of the Government / Industry Review of Procurement and
Contractual Arrangements In The UK Construction Industry
[HMSO, London, 1994 (hereinafter "the Report")], was
initially greeted with "almost universal praise" [7]. In
addition to reviewing the state of the UK construction
industry, Sir Michael makes 30 recommendations for
improving the industry. Among the recommendations were:
creation of a standard form of contract based upon the
New Engineering Contract; establishment of a building
clients' lobbying organisation (called 'NewCo' by Sir
Michael [8]); clarification of building liability
responsibilities; implementation of lO-year building
defects insurance similar to the insurance utilised in many
parts of Europe; implementation of productivity
improvements leading to a 30 per cent reduction in 416
King real construction costs (Sir Michael points out that
construction costs about 30 per cent more in the UK than
in the US [9]); requirement of trust funds to ensure
companies get paid; broader utilisation of so-called
"alternative dispute resolution methods"; and more
extensive use of contracting strategies such as design and
build. This paper focusses on the final two
recommendations in the foregoing list. These
recommendations are discussed in chapters 9 and 3,
respectively, of the Report. Chapter 9 of the Report is
entitled "Dispute Resolution", and Chapter 3 is entitled
"Project and Contract Strategies and Briefing". After
summarising each chapter, the paper will describe how the
issues raised and recommendations made by Sir Michael
have been dealt with in the US; attempt to explain the
differences; discuss the similarities; and suggest how the
US experience might be of use in developing a further
understanding of Sir Michael's recommendations. 2
Discussion 2.1 Summary In Chapter 9 of the Report, Sir
Michael expresses dissatisfaction with the current methods
available for resolving disputes in the UK construction
industry. He recommends development of a project
adjudication process which would permit speedy resolution
of disputes essentially as soon as they arise. As
recommended in the Report, the US construction industry
has also moved to establish dispute resolution methods
other than arbitration, and seems to have travelled
farther down this road than the UK industry. In Chapter
3, Sir Michael emphasizes the importance of developing
appropriate project and contract strategies so as to
establish proper allocations of risk, divisions of
authority, and lines of communication. In the US, employers
have been utilising design and build on private projects
for many years, with considerable success in avoiding
claims. 2.2 Chapter 9: Dispute Resolution Dissatisfaction
not only with the frequency of construction disputes but
with the manner of resolving them seems strong in both
the US and in the UK. Arbitration, which until recently
has been a favoured method of resolving such disputes, is
under attack in the UK because of its "perceived
complexity, slowness, and expense" [10]. Similar
criticisms [11] have been levelled in the US, where
arbitration for many years has been well entrenched as the
preferred method of private construction dispute
resolution [12]. Interestingly, however, despite the
superficial similarities of the criticisms levelled
against arbitration in the US and the UK, Sir Michael
summarises a basis for dissatisfaction with arbitration in
the UK which is the exact opposite of the main cause for
criticising arbitration in the US. In the UK, it is the
"constant spectre of appeal" to the High Court from an
arbitrator's decision "which has emasculated the whole
{arbitration} process" [13]. In contrast, in the US it is
precisely the lack of ability to appeal from an
arbitrator's decision in most cases, except for the most A
US review of the Latham Report 417 egregious circumstances
such as demonstrated fraud or bias [14], combined with the
lack of a requirement for the arbitrator to offer any
reasons whatsoever for his or her decision, which has
resulted in the most withering attacks upon US-style
arbitration [15]. In the US, according to one study, "a
significant number of arbitrators" admit to not following
either the law or the parties' contract in rendering their
awards [16]. Although an arbitration award can be set
aside because the arbitrators exceeded their authority
(which presumably includes the duty to apply the parties'
contract including its governing law provisions) [17], in
practise since the arbitrators need not explain their
decision it is very difficult to establish this ground as
a basis for vacating the award. This attitude appears to
enjoy considerable support in the courts. In one case
[18], a dispute developed between the employer on a town
home development and the design-build contractor who had
constructed the project. Approximately $250,000 worth of
repairs were needed. Instead of awarding the employer
damages for the cost of repairs, the arbitrators ordered
the contractor to purchase the entire development from the
employer at a cost of several million dollars -an
equitable form of relief which not only far exceeded the
scope of the arbitrators' authority, but also ran afoul
of the Statute of Frauds. Notwithstanding, the Minnesota
Supreme Court refused to vacate the award "merely because
the court may believe the arbitrators have erred." [19]
Cases such as this one have led many in the US
construction industry to reevaluate arbitration as a
dispute resolution mechanism. In the author's own
situation, even though he is a member of the American
Arbitration Association's (AAA) panel of construction
arbitrators, and although there is some suggestion in .
the research that design professionals tend to fare
reasonably well in arbitration [20], the risk of an
illegal or extra-contractual decision is viewed as being so
great that he has written arbitration altogether out of
the contracts utilised by his firm. Even the AAA's general
counsel now seems to view arbitration mostly "as a useful
backstop when attempts at nonbinding processes fail." [21]
What is taking arbitration's place? In the US over the
last several years, a potpourri of "alternative dispute
resolution" or "ADR" options have developed, including:
"partnering", a sort of bonding process whereby the
project participants meet periodically throughout the
project -usually facilitated by an outside consultant -to
discuss common goals and difficulties and to attempt to
resolve disputes at the lowest possible level [22];
"mediation", a non-binding but structured settlement
discussion through which a third-party neutral endeavours
to guide, cajole, and sometimes browbeat the disputatants
to a mutually-acceptable settlement [23]; and "dispute
resolution boards", consisting of pre-selected industry
experts called in as needed during the project to settle
disputes concerning variations and the like as soon as
they arise [24]. This is an "innovation" which in some
respects recalls the grand assizes established by Henry II
in 418 King the Twelfth Century [25]. Another option is
the "mini-trial", whereby an abridged version of the
parties' case is presented to a neutral evaluator.
Sometimes, ADR options are mixed and matched in a manner
limited only by the diabolical creativity of the lawyers.
For example, on one major stadium project in the US, the
contract provides for "first effort" and "second effort"
negotiations at the project manager and CEO levels,
respectively; then, if no agreement is reached, a "Neutral
Evaluation Process" by a preselected expert neutral; then
binding arbitration by arbitrators taken from a
preselected pool, with a written decision required in any
matter exceeding $200,000; and finally, appeal to the
local courts if the award is in excess of $200,000 [26].
In the Report, Sir Michael has recommended an adjudication
process in which an adjudicator / expert is selected in
advance, and disputes arising during the project are
referred to him or her for more or less immediate decision
and implementation, with appeals to court or arbitration
taking place only after practical completion [27]. In his
view, the critical issue is keeping the cash flowing during
the Project. He states that this view represents the
"wishes of the industry" [28], although one wonders if
this statement is somewhat naive. Nonetheless, Sir
Michael's recommendation for adjudication seems fairly
close to the practise of utilising dispute resolution
boards in the US, although in contrast to what seems to be
happening in the US, Sir Michael seems to entertain a
continued role in some form for the design professional as
an impartial, first-line adjudicator. In the US, although
under the standard contracts the design professional is
nominally given this role [29], in the author's experience
this clause is either written out of the contract (often
to the relief of the design professional, who rarely gets
paid for performing this noble service!); or, if it stays
in, is essentially ignored by the employer and contractor.
Although the author has never had the privilege of being
involved in a dispute involving any of his company's
projects in the UK, his own experience combined with the
overall thrust of the Report suggests that the US
construction industry may be a few years ahead of the UK
in seeking out and implementing ADR mechanisms. For
example, in negotiating the contract for a major project in
Dublin last year, when the author suggested
contractually-required mediation to his

counterpart, an experienced English solicitor, the


solicitor averred that he had

never heard of mediation. Such a response in the US, where


we are weekly

bombarded with the brochures of new mediation firms having


sprung up and retired

judges are finding new life as mediators at several


thousand dollars a day, would

today be unthinkable. If indeed the US construction


industry is slightly ahead of the UK in developing "new
and improved" dispute resolution mechanisms, then perhaps a
few

suggestions, based upon admittedly personal experience in


the US, are in order as

the UK industry seeks to implement Sir Michael's


recommendations. First, despite

all the new "partnering" methods available, behaviour has


really not changed that

much. As Sir Michael points out, "it is not easy to create


teamwork in construction A US review of the Latham Report
419 when everyone is struggling to avoid losses"[30]. Sir
Michael also mentions that a real problem with his
recommended adjudication process is the possibility that a
party will refuse to abide by the result [31]. Even worse,
in the US, the author has seen projects where one of the
parties simply refuses to participate in
contractuallymandated ADR, or grudgingly goes through the
motions. Second, both based upon the statistics mentioned
at the beginning of this paper [supra, notes 3-5] and
based upon the author's own personal experience, there has
in the US been a perceptible decline in the absolute
number of construction lawsuits and arbitration claims. In
the author's opinion, a substantial contributing factor to
this decline, as well as to the current interest in ADR, is
the increasingly ruinous cost of prosecuting or defending
a .construction case, regardless of the outcome. In the
US, of course, each side bears its own attorneys' and
experts' fees, win or lose. In implementing ADR reforms,
this significant difference from the UK's "loser pays"
system should be evaluated before importing any features
from US-style ADR methods. Indeed, one of the most
distressing pieces of news to cross the Atlantic in recent
months has to be the new legislation allowing contingent
lawyers' fees in certain cases [32]. Finally, in
comparing approaches to dispute resolution in the US with
the UK, and considering whether to transplant US-style
ADR concepts, one must not forget the inherent
litigiousness of American society. As de Tocqueville
noted, "{a}n American does not know how to converse, but
he argues; he does not talk, but expatiates" [33].
Although the British are not necessarily less argumentative
than the Americans, perhaps a greater social consensus
which favours resolution over conflict will lead to better
success for certain US-style ADR approaches, such as
partnering, which have not fared especially well here. 2.3
Chapter 3: Project Organisation and Strategies Chapter 3
of the Report, "Project Organisation and Strategies",
attempts to review the common factors involved in the
early planning stages of a construction project in an
effort to determine the key elements needed to properly
structure a project for success. Ultimately, it can be
argued that a proper approach to project organisation
will minimise disputes. In his introduction to the Report,
Sir Michael pointed out that "Clients are at the core of
the process" in construction, but their "interests are
dispersed and vary greatly" [34]. In Chapter 3, after
discussing some of the problems with so-called
"traditional" construction, Sir Michael focusses upon the
allocation of risk as the key to determining what type of
project organisation might work best for various types of
employers. For example, if a particular employer is most
concerned about early completion, single-source
responsibility, and avoiding risk to itself, Sir Michael
suggests that it might want to consider the use of design
and build construction. Conversely, if the employer's
main concerns are price certainty, minimising variations,
and quality, he suggests the use of so-called
"traditional" construction as reflect in the JCT 80 form
[35]. Interestingly, as is the case with arbitration, the
situation in the US seems to be a mirror-image of that
in the UK. Whereas in the UK "traditional" construction
420 King usually means line-item tenders based upon a bill
of quantities, in the US the "traditional" method usually
involves a lump-sum, fixed price bid for the entire job
(although line item bids are relatively common on civil
works) with the contractor performing his own quantity
takeoff in preparation for bidding. Although on the
surface the contractor seems to accept more risk in a
US-style lump sum contract, in fact disputes frequently
arise concerning the scope of the works, and change
orders and delays often result [36]. In the US, the risk
analysis has been employed in a fashion similar to the
analysis in Sir Michael's Report, but the conclusion which
seems to be building in the US is in favour of
"guaranteed maximum price" (GMP) contracts utilising the
design and build method of construction. On a GMP project,
the contractor bases its bid on partially-complete
documents and, extrapolating from them, warrants to the
Owner that the price will not exceed a certain sum. The
work is then paid for at the contractor's actual cost plus
a fee, until the GMP is reached. After that, the
contractor "eats" the overage. If the actual cost of the
work is less than the GMP, the owner keeps the savings (or
sometimes agrees to share a portion of them with the
contractor as an incentive). As one commentator has noted,
in a GMP project the employer (owner) gets the best of
all worlds: "Basically, with a lump-sum, the contractor
gets all the savings and takes all the risk. With time
and materials, the owner gets the savings and takes the
risk. And with guaranteed-maximum-price, the owner gets
all the savings, the builder takes the risk" [37]. On a
design and build project, as its name suggests, a single
entity controls both the design and construction services,
and accepts the financial risks associated with the works
by utilising a GMP contract approach. In the US, the data
are beginning to suggest that a design-build GMP
arrangement may meet not only the employer's cost
concerns, but his programme and quality worries as well.
For example, a 1990 study by the Hennepin County,
Minnesota Regional Railroad Authority studied three
turnkey design-build projects with respect to programme
(schedule), cost control, and qUality. The study "found
that the turnkey projects were completed more quickly than
traditional projects -40 to 43 months versus 67 to 73
months after completion of preliminary engineering." [38]
Similarly, another study has suggested that when public
agencies in the US have utilised design-build, "projects

have come in 15 to 20 percent below the engineers'


estimate" [39]. Finally,

although statistics are hard to come by, anecdotal


evidence and the author's own

experience strongly suggest that the quality of


design-build projects, if properly

structured, is at least equal to "traditional" projects and


-judging by the

demonstrably lower rate of claims -perhaps better.


Ultimately, on both sides of the Atlantic there is
agreement that employers need

to spend more time briefing the project and thinking about


organisational issues

earlier rather than later. As Sir Michael points out,


"adequate time must be
allowed" for these tasks, and if the brief is inadequate
due to lack of time, "the

27. Latham, supra, note 1, p.9l.

28. Id.

29. See, e.g., AlA Document A201, supra, note 12, " 4.2,
4.3.

30. Latham, supra, note 1, p. 9

31. Id., at p. 91.

32. Goddard, S. (1995) "U.K. Law on Legal Fees Will Spur


Injury Suits", Business Insurance, 14 August 1995, p.35.

33. de Tocqueville, A. (1848) Democracy In America (l2th


ed.), Lawrence, G., trans!., New York, Anchor Books, 1969,
p.243.

34. Latham, supra., note 1, p. 3.

35. Id., at pp. 16-17.

36. Macomber, J. (1989) "You Can Manage Construction Risk",


Harvard Business Review, March-April 1989, pp. 155, 161.

37. Id., at p. 164. Emphasis in original.

38. See, Capital Alternatives, et al (1990) LR&T


Implementation Alternatives Study and Case Studies,
Minneapolis, November 1990; quoted language is from
Hoffman, "Turnkey Procurement -Back To The Future In Mass
A US review of the Latham Report 423 Transit", Contract
Management, April, 1993, pp. 24-26. 39. Myers, et aI.
(1995) "Report on Design-Build As An Alternative
Construction Delivery Method for Public Owners",
Georgetown, MD, Building Futures Council, 1995, p. 4.
40. Latham, supra note 1, p. 19 THE PRICING OF CONTRACT
PRELIMINARIES: QUANTITY SURVEYORS AND CONTRACTORS
COMPARED P.A. Bowen Department of Building and Surveying,
Glasgow Caledonian University, Glasgow, UK K.A. Hall
Department of Construction Economics and Management,
University of Cape Town, Cape Town, South Africa P.J.
Edwards Department of Building and Construction Economics,
Royal Melbourne Institute of Technology, Melbourne,
Australia Abstract This paper documents the results of
an empirical study into the methods adopted by quantity
surveyors and contractors for estimating the preliminaries
component of project tenders. The pricing procedures of
twenty-seven quantity surveying firms and twenty-five
contracting organisations were studied through an opinion
survey, using a structured questionnaire supplemented by
formal interviews. Differences found between the two groups
are discussed. Keywords: Contractors, preliminaries,
pricing, quantity surveyors. Sommaire Ce document d6crit
les r6sultats d'une 6tude empirique des m6thods adopt6es
par les m6treurs et les entrepreneurs pour estimer les
616ments preliminaires des 6tats de quantit6. Les m6thodes
d'estimation de 27 entreprises de m6trage et de 25
entreprises de construction ont 6t6 analys6es 11 I'aide
d'un sondage, par I'utilisation d'un questionnaire et par
des entretiens formels. Des diff6rences d'6valuation des
coats ont 6t6 identifi6s entre les 2 groupes observ6s. 1
Introduction The preliminaries costs of construction
projects can be defined as those items that are not
directly related to the individual items of measured work.
Where tender bills of quantities 'Professor Paul Bowen is
currently on sabbatical leave from the Department of
Construction Economics and Management, University of Cape
Town, and is Visiting Professor to the Department of
Building and Surveying, Glasgow Caledonian University,
Glasgow, Scotland.

The Organization and Management of Construction: Shaping


theory and practice (Volume Two).

Edited by DA Langford and A. Retik. Published in 1996 by E


& FN Spon. ISBN 0 419 22240 5. The pricing of
preliminaries 425 are prepared, these items are usually
grouped together in a 'preliminaries' section. Examples
of preliminaries costs include plant, accommodation,
temporary services, scaffolding, and insurances. The
preliminaries can be grouped into items that relate to the
contractor's general overheads, and items relating to the
client's requirements. Examples of the latter include
insurances, penalties for non-completion and general site
restrictions. The preliminaries items can be seen as
falling into two categories, namely, time-related costs
and fixed costs. Fixed costs can be further divided into
costs that are value-related (e.g., insurances),
method-related (e.g., temporary works and plant), and
quantity-related (e.g., hoardings and scaffolding).
Time-related costs relate to those items of the
preliminaries directly affected by the time they are
required on site e.g., the cost of supervision and site
accommodation. Most preliminaries items possess both a
fixedand a time-related component in their overall cost
build-up. This can be illustrated if one considers the
cost components of an equipment item, such as a tower
crane. The tower crane has fixed costs for the
transportation of the crane to and from the site and for
the erection and dismantling of the

crane. In addition, time-related costs apply to the


duration for which the crane is present on site either in
the form of hire charges or in the form of opportunity and
depreciation

costs if the crane is owned by the contracting


organisation. Moreover, the method of

construction and the quantity and type of materials to be


placed per week may impact on

the positioning of the crane and the number of cranes


required. Studies conducted by Gray [1] [2] on the
pricing of preliminaries by contractors

concluded that 90% of the value of the preliminaries can


be found in only six items, namely,

the costs of site staff, plant, scaffolding, site


accommodation, electricity and cleaning. He

also found that contractors generally only price sixteen


items in the preliminaries section of

a tender bills of quantities. Bennett et al. [3] reached


similar conclusions. The 'Preliminaries' document
published by the A.S.A.Q.S. [4] for use with the Joint

Building Contracts Committee (J.B.C.C.) 'Principal


Building Agreement' [5] makes

provision for items contained in the preliminaries section


to be priced by the contractor as

either 'fixed', 'variable with value' or 'variable with


time', or a combination of these. This

breakdown is then used as the basis for the payment and


any subsequent adjustment of the

preliminaries. The purpose of this paper, then, is to


document the results of an empirical study into the

methods adopted by quantity surveyors and contractors in


estimating and pricing the

preliminaries component of project tenders.

2 Theoretical discussion of the pricing function

The functional separation of design and construction has


been reflected in the development

of price forecasting/cost estimating techniques. For


quantity surveyors, the object is to

inform clients and architects about the price implications


of design decisions. For

contractors, the need is to be informed of the anticipated


cash flow implications should the

contract be acquired. Although the nature of the


competitive tendering process is such that

quantity surveyors and contractors are essentially


concerned with the same function

(forecasting the market price of the project), the


potential for contractors to access

production cost information is a determining factor in the


type of technique used [6]. The 426 Bowen, Hall and
Edwards generic form of quantity surveyors' traditional
price models are given below. These equations were
developed by Bowen [7] from the work of Skitmore and
Patchell [6]. P = [(PI + P2 + ... + Pn) + G].I n = [ ~
(ql) + G ].I j (i = 1, ... , n) i=l n k = [ ~ (qjrJI j
+ ~ (qlj).I j ] j=l j=l (i = 1, ... , n; j = 1, ... , k)
where: P = total price of the work p = the individual
product price of each item or work package qj = measure
(quantity) associated with the i th item or work package
rj = price per unit measure of the i th item or work
package qj = the measure associated with the jth
preliminaries item or work package rj = price per unit
measure of the jth preliminaries item or work package n =
the number of items or work packages k = the number of
preliminaries items or work packages G = the price of the
preliminaries I = a general price index for time
adjustment Ij = a price index for the time adjustment of
the i th item or work package (1) (2) (3) I j = a
price index for the time adjustment of the jth
preliminaries item or work package Consider the method
adopted by most quantity surveyors in the pricing of
preliminaries.

The basic form in which preliminaries items are represented


in bills of quantities is that of '~(ql/ (Eq. 3).
Throughout the early design stages when approximate price
forecasting

techniques are used, and often when pricing bills of


quantities as the final pre-tender price

forecast, quantity surveyors adopt the procedure of adding


on a percentage allowance to the

priced builders' work. This percentage allowance is usually


obtained from an analysis of

priced bills of quantities of a 'similar' nature, with an


intuitive adjustment allowing for the

differences between projects. This presupposes that there


is knowledge of the composition

of the preliminaries and the relevant items which should be


adjusted because of the varying

circumstances of the project. The pricing of the


preliminaries must be seen as a potential

source of considerable forecasting error given that this


section can account for some 15-20%

of the tender value [1] [2]. Contractors recognise the


dangers inherent in this approach,

preferring to adopt an individual assessment of each


project to calculate the work content

and cost of each preliminaries item '~(qll (Eq. 6 below)


[3] [8]. Research in the United Kingdom [9] [1] showed
that preliminaries costs, when expressed

as a percentage of contract value, display wide


variability. This variability is not

signiticantly affected by the size of the project, its


type of construction or complexity.

There is also no significant correlation between the


preliminaries percentage and the value
of the project. The relationship between the preliminaries
and the overall duration of the

project reflects a higher correlation, which improves


further in projects of a more complex

nature. However, the standard data sources and methods of


price forecasting used by The pricing of preliminaries 427

quantity surveyors do not consider this relationship at


all. The percentage addition approach,

determined in relation to the value of the project, is


highly subjective and unrelated to the

process of construction. Little published data exist in


South Africa regarding the percentage

contribution made by preliminaries to tender price for


various types of projects. The pricing function employed
by contractors in tender bidding may be represented by:
B=Cm = [( c 1 + c 2 + ... + Cn) + G'].m n k = [ L
(ql') + L (qlj)].m ;=1 j=l (i = 1, ... , n; j = 1, ... ,
k)

where:

B = the value of the market price bid made by the contractor

C = the estimated costs of production

m = a 'mark-up' value to be determined by the bidder

c = the product cost of each item or work package

G' = the cost of the preliminaries

q; = measure (quantity) associated with the i th item or


work package

r;' = cost per unit measure of the i th item or work


package

qj = the measure associated with the jth preliminaries item


or work package

r j ' = cost per unit measure of the jth preliminaries item


or work package

n = the number of items or work packages


k = the number of preliminaries items or work packages (4)
(5) (6) The emphasis in tender bidding is the
determination of a suitable value for 'm' which

will provide the best trade off between the probability of


winning the contract and the

anticipated profit should the bid be successful. Component


'C' of the model is essentially

similar to the basic price forecast model for 'P' (Eq. 2).
Costs are usually current with little

use being made of price indices. If the same items are


used (a basic assumption inherent

in Eq. 6) in providing both design and construction price


forecasts (e.g., pricing the bills of

quantities as the basis for the bid), Eq. 6 may be


simplified to n n B = L (q;r'J,m = L (q;r) = P (i = 1,
... , n) (7) i=l i=l

as 'B' and 'P' are essentially forecasts of the same value,


namely, the market price of the

contract [6]. Given this underlying theoretical framework


to the pricing of the preliminaries component

of project tenders, how do quantity surveyors and


contractors differ in their practical

approaches to this task? 428 Bowen, Hall and Edwards 3


Opinion survey 3.1 Survey design and administration An
opinion survey, using interviews and incorporating a
structured questionnaire, was conducted in the Western
Cape region of South Africa, to establish the methods used
by quantity surveyors and contractors for the pricing of
preliminaries items. Telephone contact was made with
twenty-seven quantity surveying practices and twenty-five
contracting organisations and their participation sought.
The quantity surveyors were selected using the directory
of registered (regional) practices of the Association of
South African Quantity Surveyors. Contracting
organisations were drawn from the membership directory of
the local Master Builders' Association. In ail instances
interviews were arranged with a quantity surveying partner
or chief estimator/contracts manager. The survey
interviews addressed a number of issues relating to
quantity surveying and construction management processes.
The questionnaire for quantity surveyors amounted to
fifteen A4 pages; while that for contractors contained
forty-seven pages. The interviews were thus quite lengthy.
However, participants were sent a copy of the relevant
questionnaire beforehand, thus enabling them to offer more
informed and more considered opinions. The interviewer
does not think: that any of the question responses was
affected by survey fatigue. The section of the
questionnaire dealing with the pricing of contract
preliminaries was similar in content and format for both
sets of participants. After a number of questions
relating to company demographics and workload statistics,
the questionnaires dealt specifically with the relative
proportion of various preliminaries cost items to the
total preliminaries value; participants' methods of
calculating the cost of the preliminaries; the use of
standard formats and checklists; detailed pricing of
preliminaries items; factors influencing the cost of
preliminaries items; and factors influencing the accuracy
of preliminaries estimates. 3.2 Survey results The survey
results are discussed question by question and compare the
participating quantity surveyors' and contractors'
opinions about each issue. Question J: On average, what
proportion of the total contract value does the
preliminaries

section represent?

Various authors have pointed to the cost significance of


the contract preliminaries expressed

as a percentage of total contract value [9] [l] [10]. None


have compared the assessments

of quantity surveyors and contractors, and the question


sought to explore this gap. Table 1

summarises the opinions of the survey participants about


this question. Most respondents believe that contract
preliminaries, expressed as a proportion of total

contract value, lie in the range 4% 10%. Some contractors;


however, believe that

preliminaries may, on average, amount to more than 20% of


contract value; suggesting that,

in some instances at least, the proportion may be much


greater than 20%. While quantity surveyors and contractors
participating in the survey hold broadly similar

opinions about this question, there is an underlying


difference between them. So, although

the modal response in each case was that preliminaries


account for 7% 8% of total contract

value, most quantity surveyor respondents believed that


preliminaries account for between The pricing of
preliminaries 429

7% and 10% of contract value; whereas the large majority of


contractors opted for a wider

range: 4% 10%. Clearly contractors expect a greater


variability in preliminaries costs.

Table 1 Contribution of the preliminaries to total contract


value Percentage contribution 0-1% 2-3% 4 6% 7 8% 9
-10% 11 -12% 13 -15% 15 20%

Exceeding 20% Assessment of quantity surveyors and


contractors Quantity surveyors Contractors [n = 27] [n =
25] % % 0 0 0 0 9 33 48 38 39 19 4 5 0 0 0 0
0 5

Question 2 (to quantity surveyors): 2(a) In undertaking


(the preparation of) an approximate

cost estimate. which of the following methods do you use


to determine the (total) value of

the preliminaries? And 2(b): In pricing bills of


quantities. which of the following methods

do you use to determine the (total) value of preliminaries?

Question 3 (to contractors): Please indicate which of the


following methods you use to

determine the (total) value of the preliminaries for tender


purposes.

These questions were intended to explore how quantity


surveyors and contractors might

differ in their overall approach to determining the total


value of the contract preliminaries
for a project. Participants were given a choice of three
alternative methods, plus 'other'; and a choice

of five frequencies ranging from 'always' to 'never'.


Quantity surveyors were asked two

questions to reflect situations where more project


information is available to them when

producing a final estimate by pricing the tender bills of


quantities. By far the most common method chosen by
quantity surveyors, when preparing

approximate cost estimates, was that of making a


percentage addition to the estimated net

project cost (96% of respondents reckoned that they


'always' or 'frequently' use this

method; with a third of these indicating that they 'always'


use it). Making a lump sum

addition to the net estimated cost was a less popular


method. Only a quarter of the quantity

surveyors 'frequently' use this approach; while


three-quarters use it 'occasionally', 'seldom'

or 'never'. Less than ten per-cent of quantity surveyors


'frequently' calculate the cost of

each preliminaries item when preparing approximate cost


estimates. 430 Bowen, Hall and Edwards Similarly, 93% of
quantity surveyors 'always' or 'frequently' use the
percentage addition method to value preliminaries when
pricing bills of quantities. Even with the greater level
of infonnation now available, more than 80% of quantity
surveyors only 'occasionally', 'seldom' or 'never' price
each individual bill item of preliminaries. Indeed, a
somewhat surprising 40% of them 'frequently' or
'occasionally' resort to making a lump sum addition for
preliminaries when pricing the bills of quantities.
Clearly, the percentage addition method is the approach
most favoured by quantity surveyors at any stage in the
estimating process, notwithstanding the proven lack of
significant correlation between preliminaries percentage
and project price [9] [1] [10]. The adoption of this
technique also ignores the influence of project duration on
preliminaries costs [7]. In contrast to the quantity
surveyors, most of the contractors interviewed do not
favour making tender allowances for the cost of the
preliminaries by applying a percentage addition based on
the net contract value. Three-quarters of them 'seldom' or
'never' use this method. A similar number do not favour a
lump sum addition approach to pricing preliminaries. More
than half of the contractors interviewed 'always' calculate
the cost of each individual preliminaries item. Question
4: Where the cost of each preliminaries item is calculated,
is a standard format (i.e., method of calculation) used?
Fewer than fifteen per-cent of quantity surveyors answered
'yes' to this question. Where standard fonnats are used,
they may incorporate assessments relating to the fixed
cost, time, or value-related components of preliminaries
items. Just over half of the contractors interviewed do
use standard fonnats for assessing the cost of
preliminaries items. They also include fixed cost, timeand
value-related methods of assessment. Question 5: Is a
formal checklist used to minimise errors/omissions in the
pricing of preliminaries?

Just over a third of the quantity surveyors reckoned to use


a standard checklist of items when pricing preliminaries,
compared with two-thirds of the contractors. At the
bill-pricing stage, of course, the preliminaries bill
itself fonns the checklist for

quantity surveyors. Some contractors still use their own


standard checklist at this point to

ensure that sufficient detail has been incorporated in the


preliminaries section of the tender

bills of quantities.

Question 6: Please indicate the extent to which each of


the fol/owing factors influences the

total value of the preliminaries.

The purpose of this question was to see to what extent


quantity surveyors and contractors

were in agreement about causal influences on preliminaries


costs. Survey participants were offered a list of eleven
different factors, plus 'other'. Against

each factor, five possible response choices ranged from 'no


influence' to 'strong influence'.

The survey results are shown in Table 2. No additional


factors were specified by either

group of respondents. The pricing of preliminaries 431

Table 2 Influence of project factors on pricing of


preliminaries Degree of influence of factors None Little
Moderate Significant Strong Factor Q.S. Cont. Q.S. Cont.
Q.S. Cont. Q.S. Cont. Q.S. Cont. (%) (%) (%) (%) (%)
(%) (%) (%) (%) (%) Project type 0 0 11 17 11 8 37 46
41 29

Project value 0 8 0 29 33 29 48 21 19 13

Project size 0 4 0 21 11 17 63 42 26 17

Contract duration 0 4 0 0 11 17 37 29 52 50

Location 0 4 12 4 35 38 35 38 19 17

Expected number 15 33 35 21 39 25 8 17 4 4

of bidders

State of market 0 17 23 25 15 33 27 17 35 8

Quality of tender 0 13 23 33 46 21 31 17 0 17

information

Project timing 0 9 19 9 31 44 31 26 15 13

Project complexity 0 0 4 13 27 21 46 54 23 13

Client organisation 8 8 39 33 54 17 0 29 0 13

Project type was considered to be a 'significant' to


'strong' influencing factor on the total

value of preliminaries by most quantity surveyors (78%)


and most contractors (75%). Project value attracted less
support, particularly among the contractors. Over half of

them (58%) thought that project value had 'little' to


'moderate' influence on preliminaries

costs, and nearly ten per-cent thought it had 'no'


influence. No quantity surveyors thought

that project value had 'little' or 'no' influence, but one


third thought it had only 'moderate'
influence. Two thirds of the quantity surveyors; however,
still thought of project value as

having a 'significant' to 'strong' influence on


preliminaries costs (compared with only 44%

of contractors). Opinions on the influence of project size


varied more sharply. Nearly ninety per-cent of

the quantity surveyors thought it had a 'significant' to


'strong' influence on preliminaries

costs, compared with less than 60% of contractors. No


quantity surveyors thought that

project size exerted anything less than a 'moderate'


influence; whereas nearly 25% of the

contractors thought the influence of project size would be


'little' or even non-existent. Contract duration was
considered to be a 'significant' to 'strong' influence on

preliminaries costs by both quantity surveyors (89%) and


contractors (79%). Project location was seen as less
influential, with just over half of quantity surveyors, and

half of the contractors, believing it to be a


'significant' to 'strong' influence. Competitiveness (the
expected number of bidders) seems to be even less
influential. Half

of the quantity surveyors, and a little over half of the


contractors, thought this factor had

'little' or 'no' influence on preliminaries costs. There


was some intra-group disagreement; 432 Bowen, Hall and
Edwards however, as over ten per-cent of quantity
surveyors thought it might be a 'significant' to 'strong'
factor; as did 21 % of contractors. The state of the
market was less favoured by contractors than by quantity
surveyors. Three-quarters of the contractors considered
it to have 'moderate', 'little' or 'no' influence on the
total cost of preliminaries; compared with 38% of quantity
surveyors who thought its influence was 'moderate' or
'little'. Less than a quarter of the contractors suggested
that its influence was 'significant' or 'strong'; while
just over half the quantity surveyors believed this was
the case. Rather surprisingly, the quality of tender
information did not rate highly with either group as an
influential factor in the total cost of preliminaries. Only
about a third of each group considered it to be a
'significant' to 'strong' influence. Project timing
attracted a little more favour. Nearly half of the quantity
surveyors, and almost 40% of the contractors, thought
this was a 'significant' to 'strong' influence on the
total cost of preliminaries. Project complexity was
generally thought to exert a 'significant' to 'strong'
influence on the total cost of preliminaries; with 69% of
quantity surveyors and 67% of contractors opting for this
view. No quantity surveyors rated the client organisation
above a 'moderate' influence on the total cost of
preliminaries. However, more than 40% of the contractors
thought it would have a 'significant' to 'strong'
influence. Question 7: Please indicate the extent to which
the following cost centres contribute to the total cost
of the preliminaries of an "average" project undertaken
over the past three years

(express cost centre value as a percentage of total


preliminaries value).

This question was intended to find out to what extent


quantity surveyors and contractors

were in agreement about the cost significance of


individual preliminaries items. Interestingly, many of
the quantity surveyor respondent group (44%) declined to
answer

this question, claiming that they 'did not know'. The


results are shown in Table 3 with

those for quantity surveyors reflecting the views of the


reduced group size. The displayed

statistics represent the means of the values expressed by


participants. It might be argued

that the modal values would be a better indicator of group


opinions in this instance, and

future extended analysis will explore this. Compared with


the contractors, the quantity surveyors appear to
over-value the costs of

site personnel and providing temporary site accommodation,


mechanical plant, and site

security. On the other hand quantity surveyors may tend to


under-value preliminaries costs

for scaffolding, hoardings and name boards, and site


transport, when compared to contractor

assessments of these items. The pricing of preliminaries


433

Table 3 Contractors' and quantity surveyors' opinions


regarding the significance of individual

preliminaries cost centres Mean group values for


percentage contribution of preliminaries cost centres
Preliminaries cost centres Contractors Quantity surveyors
[n = 15] [n = 25] (mean response values %) (mean response
values %)

Head office personnel 10-15 10-15

Site personnel 30 35-40

Temporary 0-5 5-10

accommodation

Telephones 0-5 0-5

Temporary power and 0-5 0-5

lighting

Plant (mechanical) 5-10 15-20

Plant (non-mechanical) 0-5 0-5

Protective clothing 0-5 0-5

Setting out 0-5 0-5

Scaffolding 5-10 5

Water supply 0-5 0-5

Hoardings and name 5-10 0-5

boards

Security 0-5 5-10

Temporary roads 0-5 0-5


Temporary works (e.g., 0-5 0-5

storage facilities)

Drying out 0-5 0-5

Rates. notices and fees 0-5 0-5

Insurances 5-10 5-10

Contract conditions 0-5 0-5

Cleaning 5 0-5

Transport 10-15 0-5

Abnormal overtime 0-5 0-5

Attendance on nominated 0-5 0-5

sub-contractors 434 Bowen, Hall and Edwards Question 8:


How important do you consider the following factors to be
in the calculation of an "accurate" preliminaries value
for a project? Quantity surveyors and contractors need to
have confidence in the accuracy of their pricing, but this
can be affected by a number of factors. For example, the
heavy reliance by quantity surveyors on the percentage
addition technique (as a means of determining a total
preliminaries value) implies that the forecaster's
judgement, project details and feedback from previous
projects are all important in the selection of an
appropriate percentage. The question sought to ascertain
how participants viewed the importance of such factors.
Survey participants were offered a choice of seven factors,
> with three levels of importance for each. The results
are shown in Table 4. Table 4 Quantity surveyors' and
contractors' opinions regarding the importance of factors
influencing the accuracy of the preliminaries estimate
Importance attached to factor Unimportant Important Very
important Factor Quantity Contractors Quantity
Contractors Quantity Contractors Surveyors Surveyors
Surveyors (%) (%) (%) (%) (%) (%) Detailed knowledge of
4 0 50 35 46 65 project Experience in estimating 4 0 60
46 36 54 Extensive knowledge of 11 0 58 54 31 46
construction techniques Feedback from previous 8 8 60 71
32 21 projects Extensive data base 25 35 50 52 25 13
Time spent in estimating 42 44 54 39 4 17 Quality of
tender 8 4 64 58 28 38 information Detailed knowledge of
the project is considered to be an 'important' or 'very
important' factor by virtually all respondents, with
contractors tending to ascribe slightly more importance to
this than quantity surveyors. However, it was not clear
from the survey whether the type of detailed knowledge so
highly valued by contractors is different to that

enjoyed by quantity surveyors. Respondents were almost


unanimously agreed that estimating experience is
'important' to 'very important' for accurate pricing of
preliminaries. Contractors tended to rate the importance
of extensive knowledge of construction

techniques more highly for the accurate pricing of


preliminaries than did quantity surveyors.

This suggests that contractors may have a better


understanding than quantity surveyors of

the resource implications of these technologies. The


pricing of preliminaries 435 It might have been
anticipated that both groups would overwhelmingly have
rated factors

such as feedback from previous projects, the availability


of an extensive database, the time

spent in estimating, and the quality of tender


information, as 'very important' in influencing

the accuracy of preliminaries pricing. In fact, these were


generally regarded more as

'important' rather than 'very important'. The availability


of an extensive database was

actually thought to be an unimportant influence on the


accuracy of preliminaries pricing by

a quarter of the quantity surveyors and by over one third


of the contractors; which suggests

that they thought such a resource to be an unnecessary


luxury. More surprisingly, over two

fifths of each group believed that spending more time in


estimating would not be an

important factor in influencing the accuracy of


preliminaries pricing.
Question 9: As a standard procedure, do you use feedback
from previous projects to check

on the accuracy of your preliminaries pricing?

More than 80% of quantity surveyors confirmed that they do


use historical feedback as a

standard procedure for checking the accuracy of their


preliminaries pricing. Only 60% of

contractors reckoned to do this, however. This suggests


that contractors may be more

prepared to take a 'fresh' view of each new project.

Conclusions

Several important findings arise from the survey. Firstly,


quantity surveyors may take an

overly narrow view of the proportional contribution of


preliminaries costs to total project

tender value. Secondly, despite its recognised


shortcomings, quantity surveyors rely strongly

on the percentage addition method of calculating an


overall value for contract preliminaries.

Thirdly, quantity surveyors may over-rate the influence of


project value and project size on

preliminaries costs. Fourthly, quantity surveyors may


under-rate the influence that the nature

of the client organisation exerts on the minds of tendering


contractors. Fifthly, when

estimating, quantity surveyors may under-rate the impact


of scaffolding, site hoardings and

site inspection items on preliminaries costs. In


conclusion, it is evident that quantity surveyors are
unlikely to improve their methods

of pricing preliminaries without becoming more involved in,


and aware of, the implications

of the construction programme and its relationship with


building design.

1. Gray, C. (1981) Analysis of the Preliminary Element of


Building Production Costs. Unpublished M.Phil.
Dissertation, Department of Construction Management,
University of Reading, Reading.

2. Gray, C. (1983) Estimating preliminaries. Building


Technology and Management, Parts 1-7, Chartered Institute
of Building, Englemere, Ascot.

3. Bennett, 1., Morrison, N.A.D. and Stevens, S.D. (1980)


Construction Cost Data Bases. Second Annual Report
prepared by the Department of Construction Management,
University of Reading, for the Property Services Agency,
Department of the Environment.

436 Bowen, Hall and Edwards 4. Association of South


African Quantity Surveyors (A.S.A.Q.S.) (1991)
Preliminaries. June 1991 Edition, A.S.A.Q.S. 5. Joint
Building Contracts Committee (J.B.c.c.) (1991) Principal
Building Agreement. 1991 Edition, J.B.c.c. 6. Skitmore,
R.M. and Patchell, B. (1990) Developments in contract price
forecasting and bidding techniques, in Quantity Surveying
Techniques: New Directions (Ed. P.S. Brandon), Blackwell
Scientific Publications, Oxford, pp.75-120. 7. Bowen, P.A.
(1993) A Communication-based Examination of Price Modelling
and Price Forecasting in the Design Phase of the
Traditional Building Procurement Process in South Africa.
Unpublished Ph.D. Thesis, University of Port Elizabeth. 8.
Chartered Institute of Building (C.LO.B.) (1983) Code of
Estimating Practice. Fifth Edition, C.I.O.B, October. 9.
Flanagan, R. (1980) Tender Price and Time Prediction for
Construction Work. Unpublished Ph.D. Thesis, University of
Aston in Birmingham, Birmingham.

10. Pearl, R.G. (1992) Factors Affecting the Accuracy of


Quantity Surveyors' Pre-Tender Price Forecasts in South
Africa. Unpublished M.Sc. Dissertation, University of Cape
Town. CLIENT-PROFESSIONAL COMMUNICATION DURING THE EARLY
STAGES OF PROJECT DEVELOPMENT R.N. Gameson Department of
Building Engineering, University of Manchester Institute
of Science and Technology, Manchester, UK Abstract There
are now a proliferation of alternative methods by which
clients may procure their buildings. The move to the use
of different procurement systems has been, to a great
extent, client driven where large business organisations
and their representatives have introduced their own
systems of procuring property. The construction industry
has responded to the demands of its clients by extending
the services which it has historically offered. This has
led to construction professionals from a number of
disciplines such as: architecture, quantity surveying,
consulting engineering and contracting offering their
services, in an overall advisor / management capacity,
directly to clients. The inception stage where clients
communicate their perceived requirements to construction
professionals, and receive analysis and advice in return,
is arguably one of the most critical stages in any
project's life cycle. This paper will investigate the
services offered by professionals, from the four
disciplines outlined above, to clients during the
inception stage of a project's development. It will
examine the interaction process between clients, of
varying levels of construction experience, and construction
professionals from the four disciplines. The analysis will
focus on the first meeting between clients and potential
professional advisers to discuss a possible building
requirement. Results will be presented from the analysis
of a series of meetings between clients and construction
professionals held to discuss clients' perceived building
requirements. Keywords: Clients, construction
professionals, interaction, project inception. Sommaire
11 Y a aujourd'hui une proliferation de methodes
alternatives selon lesquelles les clients peuvent se
procurer des batiments. Le changement vers l'utilisation de
The Organization and Management of Construction: Shaping
theory and practice (Volume Two).

Edited by DA Langford and A. Retik. Published in 1996 by E


& FN Spon. ISBN 0419222405. 438 Gameson differents
systemes d'obtention a ete, dans une large me sure ,
commande par les clients dans la me sure ou d'importantes
entreprises et leurs representants ont introduit leurs
propres systemes d'accession a la propriete. L'industrie
de la construction a reagi a la demande de ses clients en
elargissant la gamme de services qu'elle avait offerts par
Ie passe. Cela a conduit les professionnels de la
construction d'un certain nombre de disciplines tels que:
les architectes, les metreurs, les ingenieurs conseil et
les entrepreneurs a offrir leurs services, generalement a
titre de conseiller / gestionnaire, directement a la
clientele. L'etape de mise en route ou les clients
communiquent leurs exigences precom;ues aux professionnels
de la construction et, en retour, re<;:oivent des analyses
et des conseils, est certainement une des etapes les plus
critiques du cycle de vie de n'importe quel projet. Cet
expose s'attachera a examiner les services offerts par les
professionnels des quatre disciplines mentionnees
ci-dessus, aux clients lors de l'etape de mise en route du
developpement d'un projet. Nous examinerons egalement Ie
processus d' interaction entre les clients dont les niveaux
d' experience en matiere de construction sont varies, et
les professionnels de la construction des quatre
disciplines. L'analyse se concentrera sur la premiere
rencontre entre les clients et les conseillers
professionnels potentiels discutant de possibles exigences
de construction. Les resultats seront presentes a partir
de l'analyse d'une serie de rencontres entre clients et
professionnels de la construction tenues afin de discuter
des exigences de construction precon<;:ues par les
clients. Mots cles : Clients, professionnels de la
construction, interaction, mise en route de projet. 1
Introduction The construction industry is a service
industry offering its services to customers for an
appropriate remuneration. One party who is involved in
every construction project is some form of client.
Historically the architect has been the first point of
contact for clients considering building. However, today
professionals from wide range of construction disciplines
are offering their services directly to clients in a
principal adviser capacity [1], including project managers
who are increasingly being used by clients [2]. The aim
of this paper is to investigate the interaction between
clients, considering building new premises, and
construction professionals, offering advice to such
clients, at the project inception stage. The discussion is
based upon the premise that previous client experience of
construction is a key variable at this stage. 2
Construction clients

A client is an essential ingredient to any construction


project; they are the project initiators, and without them
there would be no projects. However, the role which

such clients play in their projects, and the relationships


which they develop with

external consultants, can vary considerably. Bresnen and


Haslam [3] suggest that the

choice of a management organisation for a project is


heavily influenced by client

attributes rather than by project variables. Therefore,


irrespective of whatever precise Client-professional
communication 439 organisational structures are
established, clients become part of their own construction
projects' organisation, defined by Cherns and Bryant [4]
as a "Temporary MultiOrganisation (TMO) " . Once the
client has reached a decision that a building will satisfy
their future needs they then need to seek advice and/or
procure the services of external organisations to assist
them in the development of their projects. The key
variable regarding clients, and the relationship which they
establish with the construction industry, is their
previous experience of involvement in construction
projects [5]. Abbott [6] defines this situation as
"differentiation" stating that differences in clients
themselves affects their relationships with professional
advisors. Because construction industry clients are so
diverse it is very difficult to produce an all
encompassing definition which describes them. Blackmore
[7] has possibly got closest to such a definition when
quoting John Brandenburger, of Ove Arup and Partners, "
... clients are simply an assorted collection of men and
women seeking advice from a member of one or more of the
professions. II In the United Kingdom construction
industry the client sector has undoubtedly been changing
in recent years. Green [8] suggests that the 1990's has
seen a change in the demand/supply equation placing
clients in the ascendancy. In both the private and public
sectors out-sourcing of professional skills has grown
dramatically, in some cases as a result of a deliberate
strategy, in others it has been driven by circumstance
[9]. Examples of this can be seen following the
privatisation of large, previously publicly owned, utility
companies (eg. water, gas and electricity). Therefore many
client organisations, who previously dealt with many of
the facets of their construction projects in-house are now
seeking greater assistance from external organisations.
This mirrors the principles of "markets and hierarchies"
as defined by Williamson [10]; rather than conducting
transactions within their own organisational

hierarchy such clients are increasingly approaching the


construction marketplace to

procure professional services.

2.1 Client types

A number of authors have suggested systems which can be


utilised to distinguish

particular types of client. For example, Newman et al [11]


proposed a four type

system: once in a lifetime / inexperienced, regular /


repeat, expert and special. Other
authors suggest two factor systems: sophisticated and naive
[12] and primary and

secondary [13]. Having analysed established


classifications of client types Gameson [5] has defined

a system for classifying clients based upon the following


two characteristics, firstly,

whether they are primary or secondary constructors and,


secondly, their level of

construction experience. Definitions of constructors are:


1. Secondary: "Clients for whom expenditure on constructing
buildings is a small percentage of their total turnover,
and for whom buildings are necessary in order to undertake
a specific business activity, such as manufacturing."

2. Primary: "Clients, such as property developers, whose


main business and primary income derive from constructing
buildings."

Levels of construction experience are defined as: 440


Gameson 1. Inexperienced: "No recent and relevant
experience of constructing buildings, with no established
access to construction expertise." 2. Experienced: "Recent
and relevant experience of constructing certain types of
buildings, with established access to construction
expertise either in-house or externally. " Considering
these two characteristics together four alternative client
types are produced: Secondary Inexperienced, Secondary
Experienced, Primary Inexperienced and Primary
Experienced. For the purposes of this research one of the
alternative client types shown above, primary
inexperienced, has been excluded from further discussion.
When considering the definitions stated, for primary and
inexperienced, it is clear that it would be most unlikely
to find a client organisation which exhibits such
characteristics. 2.1.1 Secondary inexperienced clients A
number of authors have highlighted the difficulties
encountered by inexperienced clients when approaching the
construction industry for advice [11] [14]. Having
observed the interactions between inexperienced clients and
construction experts Glaser [15] suggests that lay clients
will follow the advice of such experts giving them power
over their working relationship. Because such clients
possess limited or no construction expertise within their
own organisations they have no alternative but to approach
the construction market to obtain the services of
construction professionals [10] . 2.1.2 Secondary
experienced clients Most business organisations require
some form of premises within which they perform their
business function. Therefore their prime business function
is not solely related to constructing buildings. It is in
this category of clients where perhaps the greatest
client diversity lies. Such clients build up an in-house
expertise which is likely to be related to the
construction of a particular type of building. They may
also engage external professionals on a long-term basis to
work on projects with

them, in addition to having in-house construction experts


[16]. Therefore much of

the development of their projects, particularly in the


early stages, is conducted within

their own organisations. Because of their previous


experience they are not as

dependent on the construction market as inexperienced


clients [10]. Such clients are

able to "preprofessionalize" their own problems before


approaching external

professionals [6]. However, secondary experienced clients


need to understand the limitations of their

own construction expertise. When faced with building a type


of building outside of

their previous experience they may need to consider


employing different professionals

and using different procedures. Bresnen and Haslam [3]


suggest that such clients may

adopt a process which they describe as "habituation",


where they use historically

developed systems in preference to the uncertainty and


disturbance likely to be caused

by changing their normal practices.

2.1.3 Primary experienced clients

Growth in institutional investment in property has led to


large organisations, such as Client-professional
communication 441 pension funds and insurance companies,
investing large capital sums in property. This situation
perhaps reached its zenith in the 1980's when, as Green
[8] states, successful developers possessed a very clear
understanding of what they required in terms of their
buildings, and were able to provide detailed specifications
to their construction professionals. Such clients will
also employ construction professionals to represent them,
looking after their interests in a project [17]. Therefore
this type of client, having access to construction
expertise and previous construction experience, is in a
strong position to clearly communicate their requirements
to construction professionals. 3 Construction
professionals There are now a proliferation of alternative
methods by which construction industry clients may procure
their buildings [1]. This is exemplified by the various
"procurement systems" now being offered by construction
professionals from varying disciplines. The main
difference in the procurement systems used relates to the
organisational and contractual relationships between the
parties involved. However, whatever procurement system is
adopted the same professional skills will be required,
primarily: a designer (architect), a financial manager
(quantity surveyor), a structural advisor (consulting
engineer) and a building constructor (construction
manager). It is important to acknowledge at this point
that other professionals may be involved, for example:
building services engineers, building surveyors and, most
recently, project managers [2]. However, the research
described in this paper concentrates on the four primary
disciplines: architecture, quantity surveying, consulting
engineering and contracting. Support for this contention
is given by the R.I.B.A. "Plan of Work" [18], which
defines the functions and responsibilities of these four
disciplines thus confirming the prominence of their role
in a construction project. In any interaction process with
their clients, professionals will adopt a procedure which
begins with diagnosis and ends with treatment [6]. During
this process a factor suggested by Glaser [15], which
contributes to the client-professional relationship, is
"power symmetry". This relates to the distribution of power
between client and

professional in their working relationship, which Glaser


suggests usually favours the

professional.

4 Research methodology
Having looked the characteristics of both clients and
construction professionals the

next stage of the research was to investigate the nature


of the interaction process

which takes place between these parties when discussing a


potential construction

project. The literature review suggested that the


interaction process would be affected

by a number of factors. The results presented in this


paper concentrate on one of the

factors, namely level of previous client experience.


Therefore the following sections

outline the research approach employed. 442 Gameson 4.1


Research method The research method adopted involved the
collection of data from a series of interviews between
clients, with different levels of construction experience
who perceived a need for a new building, and construction
professional from four disciplines. From this 11 detailed
client case studies were produced. 4.2 Research
participants Client organisations taking part in the
research interviews can be classified into two of the
client types previously identified: secondary inexperienced
(5 No.) and secondary experienced (6 No.). The types of
client organisations ranged from a small one-man business
to a multi-national computer company. The professionals
taking part came from the four primary disciplines
identified previously: architects (3 No.), quantity
surveyors (3 No.), consulting engineers (3 No.) and
construction managers (3 No.). 4.3 Data collection The
primary source of data was the recording of interviews
between the clients and the professionals. Each client was
interviewed, individually, by a representative from each
of the four professional disciplines. The order in which
the professionals interviewed clients was varied, using a
latin squares method [19], to reduce the element of bias
towards a particular profession. Interviews were conducted
in a "laboratory" setting in an attempt to impose certain
constraints upon the situation and to enable valid
comparisons to be made between both individual interviews
and different clients. However, although the setting may
be considered to be un-natural a crucial part of the
interviews was that the nature of the discussion should
remain as open and natural as possible [20]. Secondary
data was collected in the form of post-interview
questionnaires and the completion by each participant of
a brief written personality test. 4.4 Data analysis The
research interviews produced primary data in the form of 33
hours of audio recordings of 44 interviews between the
various clients and professionals. The next critical stage
was to process the collected data to provide measures
relating to the interaction between the parties involved.
Krippendorff [21] estimates that the analysis of such
unstructured data may take between 10 and 100 times the
time covered by the tapes. Therefore implications of
timescale and resources available to conduct this process
need to be considered. Taking this point into
consideration, the techniques adopted combined processing
of data with the early stages of the analysis, namely the

coding procedure, using a "Content Analysis" approach [22].


The key to the success of any analysis of human
interaction is the categorisation or

coding of data; any content analysis is only as good as


its coding system [21]. A number of alternative coding
systems were investigated, and a system called "Bales'

Interaction Process Analysis (IPA)" [23] was selected to


be used. Bales' system

consists of the 12 categories, into which face-to-face


interactions can be assigned, as

shown in Table 1. Client-professional communication 443


Table 1. Bales' interaction process analysis (IPA)
categories Category 1 2 3 4 5 6 7 8 9 10 11 12
Description SHOWS SOLIDARITY raises others status, gives
help, reward. SHOWS TENSION RELEASE jokes, laughs, shows
satisfaction. AGREES shows passive acceptance,
understands, concurs. GIVES SUGGESTIONS direction,
implying, autonomy for others. GIVES OPINION evaluation,
analysis, express feeling, wish. GIVES ORIENTATION
information, repeats, clarifies, confirms. ASKS FOR
ORIENTATION information, repetition, confirmation. ASKS
FOR OPINION evaluation, analysis, expression of feeling.
ASKS FOR SUGGESTION direction, possible ways of action.
DISAGREES shows passive rejection, formality, withholds
help. SHOWS TENSION asks for help, withdraws out of field.
SHOWS ANTAGONISM deflates others status, defends self.
Recordings of interviews were transcribed and coded with
each sentence being assigned to a Bales category. These
coded files were then entered into a computer software
package called the "Oxford Concordance Program (OCP)"
which produces output of frequencies of occurrence of
words and user specified codes [24]. The database of
interview transcripts consists of approximately 215,000
words with 14,000 IPA codes assigned to sentences. For
each interview a profile showing the

percentage of each IP A category, in terms of the whole


interview, for each interview

participant (client and professional) was produced. In


addition a profile for each

client case study, averaging the IPA scores per category


for a set of 4 interviews was also produced.

4.5 Results

To illustrate the results obtained from the data analysis


average interaction profiles

for two typical client case studies will now be presented.


In the first case study the

client is an auto centre supply company providing services


such as new tyres and

exhausts. It had existing premises in numerous locations


throughout the UK and was

involved in an expansion programme. Therefore this client


was classified as "secondary experienced". The client
representative interviewed was the company's

regional property manager with 1 0 years experience of


working in the construction

industry. The second case study's client is a small


company manufacturing analytical

equipment for the chemical industry. The company's existing


premises were too

small, and therefore they were looking to move into larger


premises. This client had

no previous experience of building, and was therefore


classified as a "secondary

inexperienced". The company's owner, who knew nothing about


construction, took
part in the interviews. Average interaction profiles for a
set of four interviews between the client's

representative and four construction professionals, one


from each discipline, are used

to illustrate the interaction process for each case study


in Figs. 1 and 2. The vertical 444 Gameson scale of these
twinned bar charts shows the 12 Bales' IPA categories, BALl
to BALl2, with the final bar, labelled SUM, giving a total
percentage for all of the bars shown above. Horizontal
bars to the left and right of zero show the average client
and professionals contributions respectively. BAL1 BAL2
.Client _ Professionals 8AL3 15 0.3 BAL4 0.8 BAL5
23.4 18.9 BAL6 375 6.4 BAL7 13 89 BAL8 02 0.8 BAL9
BAL10 BAL11 BAL 12 SUM 63.9 36.1 100 80 60 40 20 o 20
40 60 80 100 Overall Percentage Scores Fig. 1. Auto
centre supply company, average IPA interview profile 4.5.1
Auto centre supply company The average interaction
profile, shown in Fig. 1, demonstrates that this client
takes the lead in the interviews, primarily as
information provider and analyser. The

professionals' role is that of analysers, questioners and


information providers. In this case an experienced client
representative with specific building requirements, and

established building procurement procedures, leads the


interviews. The professionals,

acknowledging the client's experience take on the role of


opinion providers. This is

supported by the following comment made by one of the


professionals in his post

interview questionnaire, "We learn from them and not vice


versa".

4.5.2 Small manufacturing company

Fig. 2 shows the average interaction profile for this


client. The profiles show that

the professionals take the lead in the interviews


concentrating primarily on analysis

and information provision. The client responds to the


professionals taking the role
of information provider and analyser. In the post-interview
questionnaire one of the

professionals made the following comment about the client,


" ... no experience of

dealing with people in the building industry ... needs


guidance through the various

processes ... " . This case illustrates a client, with


no experience of construction, putting forward

his outline ideas to the professionals, seeking


clarification and advice in return. Client-professional
communication 445 BAL1 BAL2 BAL3 BAL4 BAL5 BAL6 BAL7
BALS BAL9 BAL10 BAL11 BAL 12 SUM _ Client _
Professionals 2 21 2.7 6.S 36.3 9.5 31 4.7 3.1 09 07
0.2 24.1 100 SO 60 40 20 o 20 40 60 Overall
Percentage Scores Fig. 2. Small manufacturing company,
average IPA interview profile 5 Conclusions 759 SO 100
The two case studies presented in this paper show
significant disparities in the interaction process between
the different client types and construction professionals.
Statistical t-tests conducted on the data from all 11 case
studies supports this

contention, showing results at the 1 % level of


significance. The results of the

research show that the interaction process between clients


and construction

professionals is heavily influenced by the clients'


previous construction experience. Secondary experienced
clients have the benefit of in-house construction experts
and

established methods and procedures to procure their


buildings. Such clients "preprofessionalize" their own
problems and are therefore in a position to clearly

communicate their requirements to external professionals


based upon their previous

experience of constructing buildings. Glaser [15] suggests


that this type of client

adopts the role of "knowledgeable layman". Conversely


secondary inexperienced clients, with no in-house
construction expertise

and no established procedures, are not in a position to


clearly communicate their

requirements. Such clients adopt what Glaser [15]


describes as the "traditional" role

in the client-professional relationship. The entire


construction process, from inception to completion,
involves significant

interaction between the parties involved. At the inception


stage dialogue commences

between the parties and patterns of communication are


established. Therefore it is

crucial that the parties involved understand their roles in


it. The ultimate aim must

be for the professionals to provide a service which


satisfies their clients. However,

as has been demonstrated in this paper, clients are


different and, therefore,

construction professionals must be able to respond to


their characteristics and needs

21. Krippendorff,K. (1980) Content Analysis: An


Introduction To Its Methodology, Sage Publications.

22. Berelson,B. (1971) Content Analysis. Hafner.

23. Bales,R.F. (1951) Interaction Process Analysis.


Addison-Wesley.

24. Hockey,S. (1988) Micro OCP User Manual. Oxford


University Press. CONSTRUCTION DISPUTE MINIMISATION M.M.
Kumaraswamy Department of Civil and Structural
Engineering, University of Hong Kong, Hong Kong Summary

Disagreements can develop into debilitating disputes that


lead to 'lose-lose' scenarios on

construction projects. This paper focuses on disputes


arising from disagreements on construction

claims. Recent trends towards 'partnerlng', 'dispute


review boards' and 'dispute resolution

advisers' demonstrate the industry recognition of the


superiority of 'dispute avoidance' and

'dispute minimisation', over 'dispute resolution'. It is


thus deemed useful to avoid or minimise

avoidable disputes; and also to minimise the frequency and


impact of unavoidable disputes. In

order to achieve this, it appears necessary to identify the


common causes of construction claims

and consequential disputes so as to control their root


sources. This paper presents the interim

results of research in Hong Kong into such common causes


of construction claims and disputes;

and the perceived effectiveness of different dispute


minimisation strategies. Certain categories

and causes of claims and disputes therefrom, are seen to


be more significant in frequency and

magnitude and therefore merit more attention in dispute


minimisation strategies. While dispute

resolution through litigation and even arbitration are


generally seen as onerous, it appears that

even the widely available alternative strategies such as


mediation and adjudication are considered

less effective than direct negotiation.

Sommaire Certains desaccords dans des projets de


construction peuvent se

transformer en disputes debiles qui menent it des scenarios


de type "~ro

partout". Le present papier se penche plus precisement sur


les disputes nees

de desaccords concernant des reclamations. La tendance


recente vers Ie

partenariat, les conseils de revision de disputes et


autres conseillers en

resolution de disputes est la preuve que l'industrie


reconnait la superiorite de

I'evitement des disputes, voire leur minimalisation, sur la


resolution des

disputes. n semble ainsi utile d'eviter ou de minimaliser


les disputes que l'on

peut eviter, tout comme il semble bon de minimaliser Ia


frequence et I'impact

des disputes inevitables. Dans ce but, il apparait


necessaire d'identifier Ies

causes recurrentes des reclamations dans Ie secteur du


b4timent et Ies

disputes subsequentes, afin de pouvoir en contrOler Ia


source. Le present

papier rend compte tout d'abord des resultats


intermediaires de recherches

menees it Hong-Kong sur les causes les plus frequentes des


reclamations et

sur les disputes qui en resultent, sur l'efficacite,


ensuite, des differentes

strategies de minimalisation des disputes. Certaines


categories et causes de

reclamations et de disputes semblent E!tre plus frequentes,


d'une part, d'autre

part prendre des proportions demesurees; elles meritent en


consequence

qu'on leur accorde une attention toute particuliere en


termes de strategies de

minimalisation. Alors que la resolution des disputes par


litige ou arbitrage

est en general onereuse, i1 n'en reste pas moins que les


strategies alternatives,
largement accessibles, telles la mediation et
I'adjudication, sont considerees

comme etant moins efficaces que la negotiation directe.

The Organization and Management of Construction: Shaping


theory and practice (Volume Two).

Edited by D.A. Langford and A. Retik. Published in 1996 by


E & FN Spon. ISBN 0 419 22240 5. 448 Kumaraswamy 1
Construction conflict, claims and disputes Conflicts on
construction projects can lead to claims for extra money
and! or time; and unresolved claims result in disputes.
However, all conflicts do not lead to claims; and all
claims do not result in disputes. Conflict has been said
to be 'inevitable in human relationships' [1] and its
positive and constructive components can be beneficially
harnessed [2]. To accomplish such synergy, it is useful
to isolate the root causes of conflicts [3]. Conflicts can
arise both within and between the multiple project
participants on construction projects; for example within
Joint Ventures or at contractor I sub-contractor
interfaces. Unhealthy or unmanaged conflict can lead to
debilitating disputes in general and even to unreasonable
claims for extra money and lor time. Reasonable claims may
also arise on the other hand, for example when extra work
is instructed. Such a claim is an 'assertion of a right to
money, property or a remedy' and can be made either under
the contract conditions themselves for breach of
contract; for breach of a duty in common law; or on a
quasi~contractual basis [4]. Some legitimate claims may be
accepted by the 'Engineer' or 'Architect' representing the
client in a construction contract, while others may be
disputed, along with any unreasonable claims. The reasons
for disputing even some legitimate claims, may be traced to
either unhealthy conflict or other disputes; or may also
arise from differences in perception of the legitimacy or
quantum of the claim. For example, the 'Engineer' may not
readily endorse claims for delays caused by incomplete or
delayed design information if (s)he is of the opinion that
the information at hand was adequate for the job to
proceed smoothly at that stage; or indeed if s(he) is
apprehensive of being blamed for any such lapse. Disputes
have been defined differently in the context of
construction. For example: according to

Clause 66(2) of the Sixth Edition of the Institution of


Civil Engineers (ICE) Conditions of

Contract: 'a dispute shall be deemed to arise when one


party serves on the engineer a notice in

writing stating the nature of the dispute'; whereas


according to Rule 1 of the ICE Arbitration

Procedure of 1983 'a dispute or difference shall be deemed


to arise when a claim or assertion

made by one party is rejected by the other party and that


rejection is not accepted'. The latter

broader perspective is preferred for the purposes of this


paper; which in fact also extends this

further to incorporate general disputes not arising from


claims. A similar approach is adopted in

Clause 86 of the General Conditions of Contract for Civil


Engineering Works in Hong Kong [6]. Construction dispute
minimisation 449

2 The need for dispute minimisation

Protracted disputes detract from the performance of all


participants involved, leading to 'lose

lose' scenarios whilst also generating ill will that


triggers destructive disputes in most future

interactions. The costs oflitigation and even arbitration


can be substantial in relation to the value

of the item(s) in dispute, and in comparison with even the


value of the project itself [7, 8]. The

1994 Latham Report looked at the growing popularity of


Alternative Dispute Resolution (ADR)

approaches but concluded that 'the best solution is to


avoid disputes' [9].

Latham also 'highlighted the need for a reversal of the


adversarial relationships and practices

that dominated the industry [10], leading to calls for


'teamworking', 'collaborative working' and

'partnership' between the multiple participants on a


construction project.
:3 Methodologies of dispute minimisation

'Partnering' strategies between project participants were


originally structured in the U.S. Army

Corps of Engineers from the 1980's, as a co-operative


approach to contract management and

problem solving; and have led to savings in project time


and cost [10]. Principles and good

practice in 'partnering' have been documented as a


'concept for success' by the Associated

General Contractors of America [11]; and have also been


used and advocated in Europe and

Australia [12, 13].

Dispute Review Boards which also originated in U.S.A.,


particularly in sub-surface works,

have also been successful in avoiding disputes, or in their


quick resolution [14]; and their very

presence on a job has been said to have resulted in lower


bids from some contractors who have

recognised such strengths. While Dispute Review Boards can


be set up at the start of a contract

with one or three members, they need to be customised for


each job. They may tend to ftmction as

job-site level dispute resolution panels at the worst; but


introduce elements of dispute avoidance

in the best examples.

This principle has been extended in establishing a high


powered Dispute Review Panel by the

Provisional Airport Authority in Hong Kong to deal with


disputes on the new Airport works. The

related Airport Core Programme (ACP) infrastructure


mega-projects have an elaborate dispute

resolution procedure, which incorporates 'mediation' and


'adjudication' stages before reference
needs to be made to arbitration. However there has been
some criticism of the virtual

encouragement to label any potential dispute as a 'dispute'


as soon as possible, so that it is

incorporated into the dispute resolution system. The


special requirements of cost and time

certainty on these critical mega-projects, perhaps dictated


this philosophy and the related

procedures. A relatively large number of claims are thus


being generated on the ACP projects,

but this was not unexpected because of the stringent time


bars that can disqualify late claims. 450 Kumaraswamy
Hong Kong has a mediation provision incorporated in the
standard civil engineering contract form [6] and a well
developed set of Mediation Rules which is expected to be
soon up-graded further on the strength of recent
experiences in mediation. However, anecdotal evidence
collected during the recent investigation together with
responses to questionnaires, indicate some misgivings as
to letting disputes proceed even to the extent of
mediation. One complaint was that mediators often tend to
actively encourage compromise settlements even where one
party is clearly 'in the right'; so that a party who is
convinced of his 'case' may be tempted to proceed direct
to arbitration on litigation to extract his full 'dues'.
Another common complaint is the reluctance of government
officers to agree to any compromise and their consequential
preference for a 'judgmental' settlement. Perhaps such
misgivings have encouraged the emergence of the 'Dispute
Resolution Adviser (DRA) system that has been used to
anticipate and minimise disputes at site level in some
recent government hospital and other building projects in
Hong Kong [15]. Thus the DRA system Dispute Review Boards,
and 'partnering' are all methodologies that can help
achieve the objective of minimising avoidable construction
disputes. They can also help settle some of the unavoidable
disputes before they crystallise to proportions that may
require sophisticated and costly dispute resolution
machinery to be mobilised. However, designing alternative
methodologies to deal with potential or developing disputes
is still equivalent to treating the 'symptoms'. Disputes
could be better minimised if the 'causes' were identified
and 'attacked' at their roots. 4. Common causes of
construction disputes 4.1 Common sources of claims and
disputes As discussed at the outset all construction
claims are not disputed; nor do all disputes lead to
claims. However, since most disputes arise from claims for
extra time or payments, this subsection will look at
common sources of both claims and disputes simultaneously,
in an attempt to identify some root-causes. Some previous
investigations that sought the sources of construction
claims and disputes have contributed the following
observations: Hewitt [16] identified predominant types of
claims as caused by: changes of scope; changed

conditions; delays; disruptions; acceleration; and


termination. Semple et al identified common

categories of claims, along with the corresponding common


contract clauses, based on a survey

in Western Canada [17]. They then narrowed down the common


causes to the following in

ascending order of frequency: acceleration; restricted


access; weather; increase in scope.

Heath et al classified and compared the main sources of


claims as: extension of time; variation in

quantities; variation in specifications; and drawing


changes; based on a survey of quantity

surveyors in the UK [18]. They also categorised and


compared the main sources of disputes as:

contract terms; payments; variations; time extensions;


nomination; re-nomination; and

availability of information. The 'knock on' effect of


competitive tendering has also been identified as a major
factor causing

disputes [19]. Anecdotal evidence of 'claims conscious' or


even 'greedy' contractors has also

been encountered, which of course evokes reminders about


'tight-fisted' clients and! or 'over

protective' consultants. Rhys Jones identified [1] the


following factors contributing to the

development of construction disputes; and also


interestingly differentiated the perceptions of
construction lawyers from others in the industry as to the
relative importance of their own

contribution: poor management; adversarial culture; poor


communication; inadequate design;

adverse economic environment; unrealistic tendering;


influence of lawyers; unrealistic client

expectations; inadequate contract drafting; and poor


workmanship. Construction dispute minimisation 451

4.2 The Hong Kong scenario

Being a favourite focus of international construction


organisation, the causes of claims and

disputes are not very different in Hong Kong. For example,


Lamont listed the common sources of

cost claims [20] as variations; the valuation of the


variations; and claims for loss and expenses.

However, Yogeswaran et al identified particular types of


disputes arising from ground conditions

risks in Hong Kong, consequent to the use of conditions of


contract that attempt to exclude

claims for unforeseen ground conditions [21). Such an


inability to claim directly for unforeseen

ground conditions, may for example lead to disputes as to


whether the bore-hole information

supplied by the employer was a 'misrepresentation'.

4.3 Hong Kong surveys: on the common categories of


construction claims

An ongoing investigation into the root causes of claims in


Hong Kong, commenced with the

collection of data on recently completed construction


projects, as to the frequency and magnitude

of claims. The latter were compared as a percentage of


original contract value in the case of cost
claims, or as a percentage of original contract period for
time claims. Figure I illustrates such relative magnitudes
of the average cost claims in the common

categories of claims encountered over the first 61


projects analysed. The standard deviations

therein indicate the degree of variability in the claims


in such categories. However, it must be

noted that since all projects did not necessarily have


claims in any given category, the averages

taken for each category, were based only on those projects


which actually had such claims. Table

I is therefore an useful supplement to compare the


relative frequencies of claims in any given

category. Furthermore, Table I also lists the 'success'


rate of the claims in terms of average paid!

claimed. This reflects the relative settlements of the


claims, or conversely of the residual

(unsettled) disputes therefrom. It may be noted that most


claims under the predominant claims

category of 'Engineer's instruction to change', were


eventually classified as variations, if granted.

The parallel and similar analysis of the time claims is


not presented herein due to lack of space.

The 61 projects analysed so far included building and


various type of civil engineering projects.

Similar data from another 32 projects has been collected.


The envisaged consolidation and re

analysis of the data will include a classification into


different types of projects, so as to identify

claims categories that are more typical of certain types


of works such as roadworks.

4.4 Questionnaire survey: on causes of construction claims;


and dispute resolution

A recent questionnaire issued to a group of civil engineers


in Hong Kong, elicited the perceptions

of 46 respondents, as to the main categories of claims as


in Table 2(a); the main causes of such

claims as in Table 2(b); and the relative effectiveness of


different approaches to dispute

resolution as in Table 2(c). Respondents rated the


significance of each factor litem on a scale

from I to 5; after which the combined (group or overall)


ratings were transformed to indices with

a range from I to 100. These were then ranked for ease of


comparison. The tables also highlight

the differences in perception between contractors, clients


and consultants.

Many possible factors were suggested in the questions


relating to both Tables 2 (a) and 2 (b);

and only the top ten were selected according to the


overall ranking. The overall indices have been

weighted to correct for the different numbers of


respondent from contractors (8), clients (21) and

consultants (17). While the results in Table 2 are based on


the subjective responses of the

respondents, it may be considered to be an useful


reflection of their experience on a series of

projects, unlike the previously reported ongoing surveys


which quantified data from specific

projects. A fair degree of consistency is noted between


the group perceptions [in Table 2 (a); and

also in Table 2 (c»). It must be noted that the perceived


'causes' and 'root causes' were listed

together in the question relating to Table 2 (b), which


may have contributed to some

inconsistencies in the significance assigned to each


factor therein. S T A N D A R D D E V I A T I O N 4 ( ) 2
0 0 1 . 6 2 C C I 0 . 5 1 C C 2 0 . 1 ) C C . 1 . 6 0 C C ,
C C B U 7 C C . 1 . 1 O C C I O c e l l c e l 2 1 . " 1 c c
" 0 . 0 5 C C W C C I 6 e e l 1 . 6 0 9 c m 3 3 . 6 0 L . .
' _ _ _ _ _ c e i S A . . . . C C I S B C C I 8 B + c e l s
e • . . , . d c c " A m b i g u i t y i n d o c u m e n t S
" I • • • C o n s t r u c t i o n m e t h o d C h a n g ~ d
u e 1 0 , . E n g i n e e r ' s c o m m e n t s , U n c o v
e r i n g o f w o r k s f o r e x a m / n a t t o n . . . .
. . . . . . D e l a y e d J s s e s s i o n o f s i l t ~ A
c c e l e r a t i o n o ( w o r k s . . . . . . . S u s p e
n s i o n o f w o r k s 1 0 . . . . . . . . . . . . . . . A
d d i l i o n a l w o r k s d u e 1 0 r e p a i r s I d d e
t : u I n l e m l o n c l a i m s d u c 1 0 l a i C t l U l
l t o n " 1 • • • • • • • • • • 0 ' r u p t i o n o f p r o
g r e s s b y E m p l o y e r o r , . E n g i n e e c r ~ E
m p l o y e r ' s b r e a c h o f c o n t r a c t ~ . . . .
. . . . . . . . . . O t h c r r e a s o n s A d d i t i o n
a l B u i l d i n g O r d i p r o c e d u r e s o r l a I C
c o n t D e l a y f r o m o b s t r u c t i o n 1 0 r o o a
l i o n s . . . . . . . . . . . . . . . . . . O c l a y d u
c t o v a r i a t i o n A V E R A G E ( % ) 1 5 O b l i g a
t i o n ( 0 o b t a i n m a r i n e l i c e n c e F i g . !
. A v e r a g e s a n d s t a n d a r d d e v i a t i o n s
o f c l a i m e d / o r i g i n a l c o n t r a c t v a l u
e s i n c o m m o n c o s t c l a i m c a t e g o r i e s 2
0 2 5 n g i n e t r ' s i n s l r u c l i o n 1 0 c h a n g
e Construction dispute minimisation 453 Table 1. Selected
'indicators' of cost claims and payments III common cost
claim categories No. of projects No. of projects Average
claimed Average paid Average

Cost Claim [ Claimed ITotal No of [ Paid/OCV ITotal No


of (Paid Category IOCV (%)] projects (%)] projects
IClaimcd) CCI 1.79 0.13 0.36 0.08 0.31 CC2 1.68 0.07
2.01 0.02 1.00 CC6 0.18 0.02 0.14 0.02 0.88 CC7 1.11
0.05 I.lI 0.05 1.00 CC8 1.39 0.02 0.49 0.02 0.35 CC9
3.68 0.18 1.28 0.15 0.34 CCIO 1.60 0.03 2.28 0.02 0.86
CCII 2.35 0.02 0.00 0.00 0.00 CCI2 5.58 0.02 3.72
0.02 0.67 CCI4 1.44 0.03 9.41 0.03 1.00 CCI5" 4.56
0.18 3.12 0.15 0.48 CCI6 1.30 0.02 1.20 0.02 0.93 CCI7
19.79 0.08 20.96 0.11 1.32 CCI8 5.80 0.13 3.54 0.10
0.53

CCI8A++ 1.86 0.02 0.74 0.02 0.40 CCI8B 4.65 0.02 0.00
0.00 0.00 CCI8B+ 1.49 0.02 1.12 0.02 0.75 CCI8C+ 6.98
0.02 0.00 0.00 0.00 CCI9 10.53 0.62 17.67 0.59 0.83 OCV
Original Contract Value 454 Kumaraswamy Table 2(a).
Perceived significance of common categories of construction
claims (as perceived by contractors, clients and
consultants; and listed in descending order of overall
perceived significance) Overall Contractors Clients
Consultants Rank Index Rank Index Rank Index Rank
Index Variations due to site conditions 58.2 1 67.5 2
48.6 4 58.6 Variations due to client changes 2 55.6 2
60.0 4 46.7 1 60.0 Variations due to design errors 3 54.4
3 47.5 1 57.1 3 58.6 Unforeseen ground conditions 4 49.0
4 42.0 5 45.0 2 41.9 Ambiguities in contract documents 5
43.0 6 30.0 3 47.6 9 51.4 Variations due to external
events 6 40.6 5 37.5 7 40.0 10 44.3 Interference with
utility lines 7 40.5 7e 30.0 6 40.0 8 51.4
Exceptional inclement weather 8 40.2 9 30.0 9 36.2 5
54.3 Delayed site possession 9 39.4 7e 30.0 10 35.2 6
52.9 Delayed design information 10 34.5 12 12.5 8 38.1 7
52.9 Table 2(b). Perceived significance of common causes
of claims (as perceived by contractors, clients and
consultants; and listed in descending order of overall
perceived significance) Cause Overall Contractors Clients
Consultants Rank Index Rank Index Rank Index Rank
Index Inaccurate design information 1 57.3 1 62.5 4 45.3
1 64.3 Inadequate design information 2 50.6 4 50.0 2
54.3 5 54.3 Inadequate site investigations 3 49.3 5
50.0 5 42.1 4 55.7 Slow client response (decisions) 4 46.9
3 50.0 11 37.9 6 52.9 Poor communications 5 45.7 10 40.0
12 35.8 2 61.4 Unrealistic time targets 6 45.0 2 52.5
7 41.1 12 41.4 Inadequate contract administration 7 44.6
15 30.0 3 45.3 3 58.6 Uncontrollable external events 8
44.1 12 35.0 1 51.6 10 45.7 Incomplete tender
information 9 41.9 6 42.5 13 34.7 8 48.6 Unclear risk
allocation 10 41.3 7e 40.0 6 41.1 11 42.9 Table 2(c).
Perceived effectiveness of dispute resolution methods (as
perceived by contractors,

clients and consultants; and listed in descending order of


overall perceived effectiveness) Category Overall
Contractors Clients Consultants Rank Index Rank Index
Rank Index Rank Index

Direct negotiation 1 80.1 1 76.7 1 86.2 1 77.5

Mediation! Conciliation 2 44.8 4 46.7 2 58.5 2 29.4

Arbitration 3 38.6 5 40.0 3 47.7 3 28.2

Adjudication 4 35.8 2e 50.0 4 33.8 4 23.5

Litigation 5 34.8 2e 50.0 5 30.8 5 23.5

Notes: (1) the 'Overall' indices are weighted to account


for different numbers in the three groups;

(2) 'e' signifies equal rank with another; in which case


the next rank is bypassed; (3) maximum

index value = 100 Construction dispute minimisation 455


5 Interim Conclusions Both the foregoing questionnaire
survey results and anecdotal evidence in the ongoing Hong
Kong survey indicate the perceived superiority of
negotiations as an effective method of resolving
construction disputes. While the most appropriate
resolution method may be chosen, depending on the project,
the participants and the nature of the dispute; such a need
should ideally only arise in the case of unavoidable
disputes. Avoidable disputes should on the other hand,
ideally be avoided by identifying and controlling the
potential root causes of claims and disputes. Figure 2
indicates the different hierarchical levels of potential
root (indirect) causes, direct causes and categories of
claims. Figure 2 gives examples of common causes of
claims whereas Figure I indicates examples of common
categories of claims in Hong Kong. Future analysis may
attempt to relate sets of root causes to causes and
categories, when more information is obtained from the
ongoing investigation, so that some form of hierarchy may
emerge. Two ongoing case-studies would help in this regard.
Current perceptions indicate however, that claims may arise
in each category from different direct causes and varying
root causes, although these may perhaps be grouped into
connected sets and sub-sets, after further study. Current
indications from the predominant cost claim categories in
Figure 1 (and Table 1) are

that variations and their consequences are a major source


of cost claims; whereas their principal

causes need to be investigated; as to for example, whether


a large proportion originate from

client-related, or consultant-related causes as in Figure


2. In the absence of ideal conditions even all avoidable
disputes will not be avoided, but their

incidence can still be minimised. The interim results of


the ongoing investigation as to the relative

magnitude of claims in different categories will guide


managers and those entrusted with dispute

avoidance, to focus their particular attention on the


potential high impact claim areas whether in

terms of cost and! or time impact so that the common


critical claims and consequential disputes

are pre-empted or at least minimised . Meanwhile, the


alternative dispute resolution strategies being developed,
as in Hong Kong, can

play an useful role in minimising the prolongation and


impact of unavoided and/or unavoidable

claims and disputes arising therefrom.

456 Kumaraswamy Unfair risk allocation Unclear risk


allocation Unrealistic time / cost / quality targets
Uncontollable external events Adverserial (industry)
culture Unrealistic tender pricing Inappropriate contract
type Lack of competence of project participants Lack of
professionalism of project participants Clients lack of
information or decisiveness ~ ROOT (INDIRECT) CAUSES I •
.. Inadequate brie Poor communications , Personality
clashes , Vested interests Changes by client Slow client
response Exaggerated claims , Estimating errors Other
(eg. work) errors Internal disputes (eg: in JVs)
Inadequate contract administration Inaccurate design
information r Incomplete tender information r Inadequate
design documentation Inappropriate contractor selection
Inappropriate payment modalities Inappropriate contract
form DIRECT CAUSES according to contractual requirements)
& DISPUTES FIG. 2. Common causes of construction claims
and disputes Construction dispute minimisation 457 6.
Government of Hong Kong (1993) General Conditions of
Contract for Civil Engineering Works, Government of Hong
Kong. 7. Hartman, F.J., (1995) Re-engineering, the
construction contract, First International Conference on
Project Management, January 1995, Singapore, pp. 47 57.
8. Bristow, DJ. and Vasilpoulos, R. (1995) The new CCDC 2:
Facilitating Dispute Resolution of Construction Projects,
Construction Law Journal, Vol. 11, No.2, pp. 95 117. 9.
Latham, M. (1994) Constructing the Team, HMSO, u.K. 10.
Pokora, 1. and Hastings, C. (1995) Building Partnerships,
Construction Papers, No. 54, Chartered Institute of
Building, Ascot, u.K. 11. The Associated General
Contractors (AGe) of America (1991) Partnering A conceptfor
success, Sep. 1991, AGe, USA 12. European Construction
Institute (ECI) (1992) Partnering, Publication EV411, ECI,
Loughborough, UK. 13. Quick, R.W. (1994) Partnering: The
Australian experience, Construction Conflict: Management
and Resolution, (ed. P. Fenn), Proceedings of the CIB TG 15
Conference at Kentucky, USA, Oct. 1994, CIB Publication
171, pp. 279 308. 14. Denning, 1., (1993) More than an
underground success, Civil Engineering, Dec. 1993, ASCE,
pp. 42 45. 15. Wall, C.J., (1994) The Dispute Resolution
Adviser system in practice, Construction Conflict:
Management and Resolution, (ed P. Fenn), Proceedings of
the CIB TG 15 Conference at Kentucky, USA, Oct. 1994, CIB
Publication 171, pp. 154 167 16. Hewitt, R. (1991)
Winning construction disputes strategic planningfor major
litigation, Ernst & Young. 17. Semple, C., Hartman, F.T
and Jergeas G. (1994) Construction claims and disputes:
causes and cost/time overruns, Journal of Construction
Engineering and Management, ASCE, Vol. 120, No.4, pp. 785
795. 18. Heath, B. C., Hills, B. and Berry, M., (1994) The
nature and origin of conflict within the construction
process, Construction Conflict: Management and Resolution,
(ed. P. Fenn), Proceedings of the CIB TG 15 Conference at
Kentucky, USA, Oct. 1994, CIB Publication 17l, pp. 35 48.
19. Brooker, P and Lavers, P. (1994) Perceptions of the
role of Alternative Dispute Resolution in the settlement
of construction disputes: lessons for the UK from the US
experience, Construction Conflict: Management and
Resolution, (ed. P. Fenn), Proceedings of the CIB TG 15
Conference at Kentucky, USA, Oct. 1994, CIB Publication
17l, pp. 49 69.

20. Lamont, AH. (1991) Heads of claim and use offormulae,


Seminar on Contractual aspects of Construction Works in
Hong Kong, Seminar F4, 19, Nov. 1991, Hong Kong
Institution of Engineers.

21. Yogeswaran, K., Miller, DRA and Kumaraswamy, M.M.


(1994) Allocation of risk in respect of ground conditions
in Hong Kong, Construction Conflict: Management and
Resolution, (ed P. Fenn), Proceedings of the CIB TG 15
Conference at Kentucky, USA, Oct. 1994, CIB Publication
171, pp. 141 153. THE CASE FOR THE INTEGRATION OF THE
PROJECT PARTICIPANTS' ACTIVITIES WITHIN A CONSTRUCTION
PROJECT ENVIRONMENT R.A.C. Luck and R. Newcombe
Department of Construction Management and Engineering,
Reading University, Reading, UK Abstract This paper
reviews the theoretical background which underpins the
Engineering and Physical Science Research Council (EPSRC)
funded research project, "The design of rapid team
integrating strdtegies for multi-organisation teams at
various project stages" currently being conducted at the
University of Reading. The research is founded on the
premise that the formation of a project team will have a
beneficial effect upon the performance of that team and
ultimately the success of the project. The research of
Cherus and Bryant (1984) underpins this study and suggests
that the endemic characteristics of construction projects
make the formation of a project team difficult.
Teambuilding is considered to be an ideal; the integration
of the project organisation is a more realistic aim. The
study investigates a subject which traverses many
disciplines and draws upon existing knowledge found in
disparate research areas and fields. A key section of the
paper is the review of relevant literature and its
application in a construction context, to present the case
that greater integration will enhance projcct performance.
Keywords: construction, eo-ordination, integration, project
organisation, teambuilding. ResumecS Ce dossier analyse
les fonde thcSriques qui cStayent Ie projet de recherches
fonde par I'EPSRC, lila conception de Strategies rapide
d'integration d'equipcs pour les cSquipes d'organisation
mUltiple a plusieurs stages du projet", couramment menepar
l'UniversitcS De Reading. La recherche est basee sur
l'id6e que la formation d'une equipe de projets aura un
effet avantageux sur la performance de cette equipe et, en
fin de compte, Ie succe du projet. Les recherches de
Cherus et Bryant, (1984) soutiennent cette etude et
suggerent que les carateristiques endemiques des projets
de construction rendent la formation d'une equipe de
projet difficile. La fomation d'equipe est considere com
me Ull ideal; I'integration de I'organisation du projet
et un dessein bien plus realiste. L'etude examine un sujct
qui traverse de Ilombreuses disciplines et entraine des
connaissancces existantes que I'on trouve dans des
superficies de recherches dispartes. Un des plus
importants secteurs de cette etude est la revue de
literature relatif, et son application dans un contexte
de construction, pour prcSsenter la condition qu'une
integration superieurc ren<:hCrira la perfomance du
projet. 1 Introduction

This paper substantiates the need for the integration of


people within a construction project through a review of
existing literature. The concept of teams and teambuilding

The Organization and Management of Construction: Shaping


theory and practice (Volume Two).

Edited by D.A. Langford and A. Retik. Published in 1996 by


E & FN Spon. ISBN 0419222405. Integration of partcipants'
activities 459 is introduced discussing the performance
benefits to be gained through forming a team. Certain
characteristics of the construction industry which make
team building difficult are identified. The concept of
integration is introduced which also has a benefical
effect upon organisational performance. Integration is
offered as an attainable objective within a construction
project organisation. The mechanisms used to integrate and
coordinate the inputs of individuals and firms within a
project are discussed and placed in a theoretical
framework. 2 Groups and teams Social scientists have
devised research tools and terms which have allowed them to
develop frameworks for understanding the behaviour of
people in organisations. Schein (1980) is one such
psychologist who identified different types of group;
formal and informal are two major types. Formal groups are
specifically created to perform organisational tasks, work
groups (Kelly and Male, 1993) which can be either
permanent or temporary. The individual membership of a
formal permanent group may change but the group continues
to exist and is unlikely to be disbanded. In contrast the
members of temporary formal groups are conscious that some
time in the future the group will cease to exist. A
project team is an example of a temporary formal group. A
group is less formal than a team. It is dependent upon a
collection of people who interact perceiving themselves
to be a unit (Hunt, 1981). Handy (1976) also observed
that an individuals' perception of membership was
important but he identified other characteristics of
groups which are equally relevant; the group has common
objective/s, predetermined hierachies and defined
membership criteria. These characteristics are upheld
within formal groups, teams. A teambuilding body of
knowledge has become established which uses various
parameters to investigate the influences upon team
behaviour and effectiveness. Belbin (1981) identified eight
roles of team members, plant, shaper etc. which need to be
present within a fully effective team. Mayo observed that
informal inter-group relations influence group norms and
the performance expectations of a team. The task conducted
by the team will influence the type of team to be formed.
It was observed that a team passes through distinct phases;
forming, storming, norming, performing before it works at
its most effective. It is acknowledged that this process
takes time and that the increased effectiveness gained
through forming a team must be balanced against other
priorities. When all members of

the team have the same objective/s, super-ordinate goals,


the team will tend to be more

effective. The Ashridge team-working approach (Hastings et


aI., 1989) involved the

establishment of eight stages or concepts through which to


develop a team towards the

superteam vision. These studies of team building have


acknowledged some of the 460 Luck and Newcombe variables
which influence team performance. 2. 1 The benefits of
forming a team The benefits attributed to working within
successful teams include increased productivity,
efficiency and also the increased motivation of the
members of a team (Adair, 1986). The advantage of
integrating teams within a construction project is that
information can be processed and tasks can be completed
more efficiently. During the 1960's the successful
establishment of teams at the top (within organisations)
lead to the teambuilding from the top to the bottom,
vertical integration within an organisation. This was
considered highly beneficial for increasing goal attainment
and motivating individuals to utilise their energy in a
concerted direction (Likert, 1961). Group dynamics have
been shown to have a significant impact on construction
performance (Pantaleo and Rwelamila. 1994). More
specifically construction productivity has been shown to
improve along a learning curve, the second distinct phase
of which is the routine acquiring phase (United Nations,
1965). Improvements during this stage are

attributed to growing familiarity with the work and


refinements of the work method and

organisation. These observations acknowledge the importance


and benefits obtained

when individuals, or groups within a project are familiar


with those working around

them.

Measures have been used to grade performance in human and


commercial terms. The

human performance terms include; satisfaction, information


processing and perceptions

of the firm's effectiveness with which they manage change.


In commercial terms the

measures have included profitability, return on capital


employed and profit, turnover

ratios and the growth in sales turnover (Lansley, 1974).


This research project

considers team building to be desirable in both human and


financial terms. Having
described the benefits of forming a team the factors which
influence the formation of a

construction project team are discussed.

3 Barriers and constraints to team formation

There are many charactenstics of the construction industry


which make the formation of

teams difficult; two are described here. The first is the


project-based social construct

within which construction projects are procured. The second


is the role ambiguity

(Handy, 1976) experienced by members of a project


organisation.

3. 1 Project organisation

A project based organisation is one formed to perform a


specific task and is disbanded

upon completion of that task. This may be referred to as


temporary organisation.

Cherns and Bryant (1984) used the term temporary


multi-organisation (TMO) Integration of partcipants'
activities 461 specifically to describe the
socio-technical system of a construction project
organisation. This term uses the legal definition of an
organisation's boundary and acknowledges that a
construction project is composed of a multitude of
organisations. The structure of the construction project
organisation is considered to be complex. There are many
characteristics of construction projects which make them
complex. Bennett (1991) considered that the number of
different activities needed to complete a task determines
its complexity. Construction projects are realised through
the completion of many tasks during the pre-construction
and site assembly stages by numerous firms. Many firms are
needed because of the differentiation of tasks within a
project and the specialised skills and expertise within
each firm. The parameters of technology, territory and
time influence the separation of tasks amongst the firms
and the complexity of a project organisation. The
structure and composition of the project organisation
changes during the life span of the project in response to
the tasks to be completed. Firms are appointed to complete
specific tasks which do not last for the full duration of
the project. Previous studies of the Broadgate project
have shown the change in numbers and composition of the
project organisation during the construction phase of the
project; illustrating the complexity of construction
project organisations. 3. 1. 1 Deficiencies caused by the
temporary nature of projects Katz (1982) investigated the
effects of group longevity on project communication and
performance in R&D project groups. It was found that the
short term tenured appointment of project personnel had
an adverse affect upon project performance. The temporary
nature of R&D project groups is a characteristic in common
with

construction project organisations. Cherns and Bryant


(1984) observed that within

construction projects individuals or groups from several


"parent" organisations, each

with its own goals and values, were all drawn together in
the achievement of a task.

Once completed the organisation was disbanded and the


individuals or groups separated

to go their own way. The similar temporary nature of the


two types of project

organisation permits the transfer of the findings from one


industry to another. The

assumption is therefore made that the performance of


construction project organisations

could be improved if the temporary nature of construction


project organisations could

be changed.

The total break up of a project organisation can be


reduced when firms have long-term

relationships. This may involve entering partnering


arrangements. Partnering is an

American concept which has been applied and shown to have


2-10% cost benefits
when applied to a project and cost savings of up to 30%
when strategic partnering 462 Luck and Newcombe
arrangements are used (Bennett and Jayes, 1995). This
rationale has underpinned the recent trend for firms to
partner and to encourage repeat working amongst firms
within the construction industry. This is one method used
to overcome the impermanence of the construction project
organisation which has performance benefits but does not
result in the formation of a team, according to the
previous definitions. Because of the difficulty in forming
a team within the construction industry the research
project being conducted at the University of Reading is
currently investigating methods to rapidly integrate the
inputs of project participants. 3.2 Role ambiguity The
second characteristic of the industry which inhibits the
formation of teams is the absence of prescriptive roles
for members of the project organisation. This causes role
ambiguity and necessitates adjustment and the alignment of
roles within a project (Maier, Read & Hoover, 1959). This
is a consequence of the historic structure of the
construction industry which is composed of professionals,
trades and craftsmen. Roles attributable to particular
project participants emerged which have changed throughout
history. For example the Architect's Appointment Document
(1982) describes a presumptive role which rarely reflects
the architect's role today. The rate of change of these
roles has increased. Historically the title of a
participant within a construction project would describe
their role, which could be interpreted in terms of
services which that individual would supply. This is no
longer the case. Within construction projects it is
possible for a service to be provided by more than one
individual (Luck, 1993) therefore there is an opportunity,
within a free market situation, for the substitution of
an individual to supply a service. Because the role titles
do not describe the service to be provided there is
increasing dependence upon the appointment documentation
to specify which services will be provided and by whom.

The implication of this for the project team is that no


members of the team can approach

a new project with any certainty of their role or the


services they will supply. It has become necessary for
members of the team to adjust to their roles to suit the
rest of the

team. This adjustment and alignment takes time and reduces


the efficiency of the team
whilst this process is on going.

More recent management methods of procurement and


documents explaining the

philosophy behind these approaches (CSSC, 1991) have used


generic titles, e.g.

"designers", to describe the range of services which an


individual may provide on a

construction project. This approach acknowledges the


reality of working practices

within the industry. This creates an opportunity at the


project outset to design the

organisation most suited to complete the building. The


organisation structures are Integration of partcipants'
activities 463 tailored for a particular project and is a
factor which inhibits the formation of teams. This is
because there is an adaptation period during which
individuals and firms become acquainted with their
contribution to the project and their relationship to other
members of the project organisation. The objective of the
research project is to develop integration strategies to
speed-up this process. This is possible using the
theoretical concepts of integration and co-ordination. 4
Integration and Co-ordination Lawrence and Lorsch (1967)
established a correlation between integration and
performance. Good performance was found to lie in the
achievement of an adequate level of integration. Because
both teambuilding activities and integration have a
positive effect on organisational performance the concept
of integration is used to replace teambuilding within
construction project organisations. Child (1984) concludes
that effective integration can contribute substantially to
high organisational performance. There is an
inter-relationship between integration and co-ordination.
Integration and co-ordination are different entities which
apply in the same dimension. They differ in that
integration is of a higher order of magnitude than
co-ordination. Co-ordination is concerned with the inputs
of tasks and individuals meanwhile integration is concerned
with establishing common objectives for the organisation as
a whole. Integration applies at a strategic level whilst
co-ordination is concerned with the task. Both integration
and co-ordination are relevant to construction project
organisations. Co-ordination is pertinent at the task
level as the inputs of the individuals should be directed
towards achieving a common objective, the completion of the
project. Rwelamila (1994) considers that the over-all
effectiveness of a construction project depends on the
co-ordinated efforts of individuals working in groups.
Integration is necessary within the construction industry
because of the differentiated specialists involved in the
construction process (Winch, 1984), increasing
technological specialisation (Morris, 1973) and sentience
(Miller and Rice, 1967) to employers and professions
rather than the project organisation. It is important to
establish integration throughout the project, to create a
sense of project identity and culture.

4" 1 Defining Integr"ation Integration was defined by


Lansley (1974) as, "the extent to which the activities of

members of a management system are closely co-ordinated in


relation to overall

objectives". That study refined Bums and Stalker's (1961)


model of an organisation's

structure and its effect upon performance to include the


variables of control, integration 464 Luck and Newcombe
and environment. Integration is considered to be part of an
organisation's structural dimension. Other definitions of
integration include Lawrence and Lorsch's (1967)
description of integration as "the process of achieving
unity of effort among the various sub-systems in the
accomplishment of the organisation's task". Mouzellis
(1967) addresses the problem of integration in
organisation structures referring to it as the process
which ensures "an adequate level of solidarity and
cohesion between subsystems". Each of these definitions is
concerned with the integration of sub-systems within an
organisation, intra-organisational integration. This
research project is primarily concerned with inter-firm
integration (between organisations) as well a~ that
within a firm. The application of findings from previous
studies to this work is dependant upon the assumption that
observations of integration within organisations
(intra-organisation integration) can be applied to
integration between organisations (inter-organisational
integration). This is an issue associated with the unit
of analysis being investigated. 4.2 Defining the
organisation system: the unit of analysis. Lawrence and
Lorsch (1967) when investigating differentiation and
integration took a systems theory approach, the primary
unit of analysis being the organisational system. The
organisation is defined as a system of interrelated
behaviours of people who are performing a task that has
been differentiated into several distinct subsystems. The
task of the organisational system is a complete
input-transformationoutput cycle involving the design,
production and distribution of some goods and services.
Using these definitions the boundaries of organisations
will not always coincide with the legal boundaries of a
firm and may sometimes encompass a number of organisations.
The flexibility of a systems approach is useful when
applied in a construction context. It becomes possible to
consider the project to be an organisational system and to
look at the project organisation as the unit of analysis.
Taking this approach the project system crosses the legal
boundaries of firms, as individuals, rather than complete
firms are drawn together to form the project organisation
with the common objective of completing the project. The
project organisation exists for the duration of the project
and passes through distinct phases. A building's
procurement process passes from inception through to
completion before the cycle is complete. When the project
is considered to be the unit of analysis its boundaries
define the organisation system and the separate firms which
meet to form a temporary coalition can be considered to be
the sub-systems units to be

integrated within the whole. Winch (1989) considers that


integration in the

construction project is between firms not within them.


Integration of partcipants' activities 465 4.3 The
integration of tasks and the integration of people. The
concept of integration applies to both tasks and people
(Walker, 1984). It has been the intention of this study
to focus on the task orientation aspects of integration
rather than the human aspects. The research project is
concerned with the rapid formation of efficient groups and
acknowledges the imperfect conditions of a construction
environment in which time, amongst other constraints,
inhibit complete integration. It is considered that
emphasis on the integration of tasks will have pronounced
benefits in performance terms. Handy (1976) observes that
although satisfaction does not necessarily lead to
productivity, productivity can often lead to satisfaction.
The integration of tasks can only occur when the
individuals conducting the tasks understand the boundaries
of their tasks and the interfaces with other tasks. Because
tasks are conducted by individuals the integration of task
and people cannot be completely dissociated. The
integration of people is a welcome consequence of the
integration of tasks. Many organisational theorists have
observed that integration occurs within organisations and
have classified the mechanisms used to integrate the
inputs. The next section is a chronological review of some
of the most important theories of integration and
co-ordination. 4.4 Integration mechanisms. I t has been
suggested that the achievement of integration is the task
of top management (Rice, 1958). Other theorists have
observed that additional integration and coordination
devices complement conventional hierarchy. Litterer (1965)
suggested that there are three main ways of achieving
integration within organisations; hierarchy, through
administrative or control systems and through voluntary
activities. These were collectively called the integration
mechanisms. Lawrence and Lorsch (1967) in their study of
the comparative performance of organisations observed that
the integration devices as identified by Litterer (1965)
were in use. These were; hierarchies, administrative
control systems and voluntary activities. They augmented
these devices with two others. The members of an
integrative sub-system have the specific function of
integrating different sub-systems within an organisation.
Integration teams differ because they are composed of
representatives from each of the basic sub-systems and
integrative sub-systems. Integration within an
organisation was achieved using a combination of these
mechanisms.

Thompson (1967) observed that the field of organisational


theory was beginning to mature as it is possible to
compare and contrast different theorists' findings to
reinforce 466 Luck and Newcombe assumptions. He uses
March and Simon's model (1958) when describing coordiantion
within an organisation. Co-ordination within an
organisation was considered to occur using the following
three co-ordination methods; standardisation,
co-ordination by plan and mutual adjustment. He made no
comment on the effect which the organisation's structure
or hierarchy had upon the co-ordination of activities
within the organisation. Galbraith (1973) considered
organisations to be information-processing networks and
identified the following co-ordination devices within
organisations; rules, programmes and procedures was the
first device, hierarchy the second, targeting or goal
setting the third. He observed that the organisation's
design strategy could also affect its information
processing ability. The use of slack resource or the
creation of subprojects reduced the need for information
processing. Vertical information systems and the creation
of lateral relations increased an organisation's capacity
to process information. Mintzberg (1983) considered there
to be five co-ordination mechanisms. The mechanisms were,
direct supervision, when one person take responsibility for
the work of others, issuing instructions to them and
monitoring their actions. Mutual adjustment achieved the
co-ordination of work by the simple process of informal
co-ordination. Standardisation was sub-divided into three
categories; standardised work processes, used when the
contents of the work are specified or programmed,
standardised outputs act as a co-ordination mechanism when
the results of the work are specified, standardisation of
skills (and knowledge) occurred when the training required
to do the work is specified. Bennett (1991) re-visited
Galbraith's co-ordiantion devices and applied them in a
construction context. The basic set of co-ordiantion
devices were procedures,

management hierarchy, professionalisation and targets. In


common with Galbraith

Bennett observed that information systems and lateral


relations increased an

organisation's information processing capacity and that


self-contained sub-projects and

slack resource reduced the need for co-ordination. The


major difference between their

work is that Bennett introduced professionalisation as a


co-ordiantion device. This

device acknowledges that professionals have skills which


allow them to approach a

unique problem and apply general principles to resolve the


problem.

Morris (1973) and Walker (1984) both consider that project


management techniques

can provide the required linkage mechanisms to achieve


integration. Morris (1983)

considered that the matrix organisation structure is an


integrative mechanism. Integration of partcipants'
activities 467 The integration and co-ordination
mechanisms observed by the organisational theorists have
been summarised and are presented in Table 1.
Organisation structure formal mechanisms informal
mechanisms Litterer (1965) hierarchies control systems
VOIWltary acti vities Integration mechanislllS Lawrence
& hierarchies admin. control systems vohilltaryactivities
Lorsch integrative sub(1967) systems Integration devices
integrating teams Thompson (1967) standardisation mutual
adjustment Co-ordination methods co-ordiantion by plan
Galbraith (1973) hierarchies rules and programmes goal
setting lateral relations vertical info. systems self
-contained tasks slack resource Mintzberg (1983) direct
supervision standardisationmutual adjustment Co-ordination
of output mechanislllS processes (procedures) skill &
knowledge Bennett (1991) management hierarchy project
processes Co-ordination devices lateral relations targets
self-contained task infonnation systems slack resource
professionaiisation

Morris (1984) matrix structure

simplified hierarchy fonnal procedures infonnal adjustment

mechanisms

Table 1. Integration and Co-ordination mechanisms

It can be seen from Table 1 that there are similarities


between the co-ordination and

integration mechanisms identified by the various


organisational theorists. I t has been

possible to classify the mechanisms into three categories;


the organisation's structure, a

formal mechanism or an informal mechanism. Using this


structure the mechanisms can

be grouped and tenned; hierarchy, formal procedures and


informal adjustment. These

terms can be applied to describe the used mechanisms in a


simplified model of a

construction project.

The hierarchy and the structure of the project organisation


is established at the

appointment stage within the appointment documentation.


These documents will define 468 Luck and Newcombe the
responsibilities of each person or sub-organisation within
the project organisation. Although professionals may be
appointed with skills which are transferable between
projects the services required will be unique for each
project. The administration and control systems used are
the formal procedures which are established to co-ordinate
the inputs of the project participants. These will be
established at the project outset and will be influenced
by the project manager's preferred style of management and
any "best practice" procedures which that firm applies
when managing any project. These will also include any
procedures which are introduced to suit the characteristics
of a particular project. The informal adjustment
activities are those which are noncontractual or defined by
procedures which assist the integration of inputs within a
project. Individuals often mutual adjustment to suit their
preferred ways of working. The research being conducted
at the University of Reading collects information from
projects conducted using a construction management (eM)
procurement route. One advantage of this method is its
flexibility, which readily allows new procedures to be
introduced and used when managing a construction project. A
characteristic of the eM philosophy is that the
specialist and trade contractor contracts are held directly
with the client. This reduces the levels of contractual
hierarchy within the organisation and results in a flatter
structure than other forms of procurement. A consequence of
this may be that the integration strategies will place
increased emphasis upon the formal and informal mechanisms
rather than hierachical mechanisms, as the opportunity to
use this variable has been reduced. 5 Conclusions

This paper has discussed the reasons why the formation of


teams is impaired by

characteristics of the construction industry and introduced


integration as a plausible

alternative. It has summarised the inter-relationships


between the concepts of co

ordination mechanisms, devices and integration. These


mechanisms will be used to

develop integration strategies for construction project


organisations. The anticipated

benefits for the construction industry industry will be


increased productivity; as

learning curve effects will be reduced and the completion


of projects in a more efficient
manner. These characteristics will complement the
philosophy of the eM procurement

470 Luck and Newcombe Mouzelis, M. (1967)


OrgallisatiollandBureaucracy: An analysis of modern
theories. Routledge and Kegan: London. Pantaleo, W. D and
Rwelamila (1994) "Group dynamics and the construction
project manager"

Construction Mallagement and Economics,

RIBA (1982)Architect's Appointment. RIBA London.

Rwelamila, P. D. (1994) Group dynamics and cOIIStruction


project manager: Journal of Construction

Engineering and Management Vo1.l20, I, 3-10.

Rice, A. (1958) Productivity and social organisation.


Tavistock London.

Schein, E. H. (1980) Organisational psychology. Prentice


Hall London.

Thompson, J. D. (1967) Organisations in action. Mc


Graw-Hill. London:.

United Nations Committee on Housing (1965) Building and


Planning: effect of repetition on building

operatiollS and processes on site. United NationsNew York.

Walker, A. (1984) Project management in cOIIStrruction:


Collins London.

Winch, G. (1989) The cOIIStructiolljirm and the


cOIIStruction project: a trallSaction cost approach:

Construction Management and Economics, 7, 331-345.


SUBCONTRACTING THE SUBCONTRACTOR'S VIEW J.D. Matthews, A.
Tyler and T. Thorpe Civil and Building Engineering
Department, Loughborough University of Technology,
Loughborough, UK Summary In the modern construction
process an increasingly major role is played by
subcontractors. Despite the importance of subcontracting
very little has been written on the performance of main
contractors viewed by subcontractors, and how their
dealings with subcontractors can be improved. This paper
presents a survey which focused on these subjects with
particular emphasis on payment issues, communications,
feedback, selection, tendering, contracts management and
contract administration. The paper provides information on
how a particular UK building company's performance
compares to that of other main contractors. Earlier
involvement of subcontractors in the building process was
seen to cultivate mutual understanding and develop trust.
Main contractors feedback was seen as being only adequate,
whilst it was felt that tender feedback would help
subcontractors become more competitive. Inviting
subcontractors to tender was seen as an infrequent method
of obtaining subcontractor tenders. Keywords: Building
Sub-Contractor, Main Contractor, Performance, Relationships
Abbreviations used: (SC) = Subcontractor(s), (MC) = Main
Contractor, (PWP) = Pay when Paid, (PDM) = Project Design
Managers. Sommaire Le role des entreprises de sous
traitance dans Ie processus de construction moderne prend
de plus en plus d'importance. Malgre I'importance de la
sous traitance, il y'a tres peu d'information concernant
la performance des entreprises principales vues par les
entreprise de sous traitance. Cet article presente une
etude qui a ete focalisee dans ce domaine concentrant sur
les payements, communications, feed-back, selections,
soumissions, gestion des contrats et administration des
contrats. L'article demontre comment la performance d'une
societe de construction au Royaume Uni se compare aux
autres entreprises principales. Une participation plus
avancee des entreprises de sous traitance dans Ie
processus de construction peux ameliorer la comprehension
et creer une atr.losphere de confiance. Le feed-back des
entreprises principales est juste acceptable, alors qu'il
a ete demontre que Ie feed-back de la sou mission aide les
entreprises de sous traitance a etre 'plus competitifs.
Inviter les entreprises de sous traitance a soumissionner
a ete considere comme methode peu frequente pour obtenir
des sou missions de ses

entreprises.

The Organization and Management of Construction: Shaping


theory and practice (Volume Two).

Edited by D.A. Langford and A. Retik. Published in 1996 by


E & FN Span. ISBN 0419222405. 472 Matthews, Tyler and
Thorpe 1 Introduction The efficient use of resources,
from tender through to construction and beyond, has become
an even more important issue to the construction industry
since the publication of Sir Michael Latham's review of
the construction industry, 'Constructing the Team'. Latham
puts forward 30 proposals with the aim of, "making
recommendations to Government, the construction industry
and its clients regarding reform to reduce conflict and
litigation and encourage the industry's productivity and
competitiveness[ 1]". It is recognised by both
practitioners and academics that as much as 90%[2] of a
main contractors turnover can be attributed to
subcontractors. It seems logical therefore that if main
contractors are to improve their performance and
productivity they should concentrate their efforts where
the majority of the work takes place, i.e. subcontracting.
This paper discusses some of the findings from research
undertaken by a top 30 (in terms of construction turnover)
UK main contractor referred to as BC. All the areas
discussed within this paper had been identified through
internal research as areas which have the greatest impact
on main contractor and subcontractor performance. It is
hoped that these areas will improve main contractor sub
contractor relationships. 2 Research methodology The aim
of the study was to identify how BC's performance compared
to other main

contractors with regard to SC relationships. This survey


was undertaken after previous studies were completed to
identify, "What a Main Contractors staff want from
subcontractors", and "What subcontractors want from main
contractors". The overall

objective of these studies was to identify ways to improve


the relationship between a

main contractor and its subcontractors.

2.1 Questionnaire

Data relating to the areas found to be important by the


previous studies was collected

from subcontractors by interview based on structured


questionnaires. The areas were:

• payment issues: timing, pay when paid clauses.

• communication: understanding, earlier involvement of SC's.

• feedback: amount, pre-contract, performance.

• selection issues: number of subcontractors, notification


of enquiry, preferential treatment.

• tendering: detrimental effects on.


• contracts management: performance of contract staff.

• contract administration.

Each subject area contained a series of open, closed and


tick box questions. During the development of the
questionnaire it was decided to underline keywords in

similar questions so that the questions were not confused


and that differences between

questions could be easily identified by the interviewee.


For ease of understanding these

words have been underlined within this paper.

2.2 Building subcontractors interviewed

17 interviews covering 13 specialities, based throughout


the UK, took place over a 4

week period. The types of subcontractor trades identified


for inclusion in this study

were: Suspended Ceiling (1), Steel Frame (2), Concrete


Frame (1), Cladding (2), Piling

(1), Ground Works (2), Landscaping (1), Scaffolding (1),


PlasterworklDry lining (1),

BrickIBlock (1), Roofing (2), Tiler (1), Partitioner (1).


Turnovers of these companies

ranged from £500k to £60m. 59% (10/17) of those


subcontractors interviewed offered

a design, manufacture, supply and fix service.


Subcontracting the subcontractor's view 473 These
subcontractors were chosen because many of them had been
previously interviewed; they were all seen by BC as
critical building subcontractors for the successful
execution of a project; they had differing needs in the
co-ordination of a project. 2.3 Method of analysis A
basic method of statistical analysis was used to analyse
ali the data obtained from closed and tick the box
questions. This provided an overall ;;.\erage which was
then correlated to a set list of ranks. Open-ended
questions were analysed by identifying the Gl0St prevalent
answers. Percentages (%) were given to show the
percentage of occurrence. 3. Results 3.1 Payment issues
Question 1, "From your dealings with BC, do you believe
that they are timely payers". 76% (13/17) stated that BC
were timely payers. The remaining -+ (24%) subcontractors
stated that they could not comment as it was greatly
dependent on the project, client and the form of
procurement in question. The following question asked,
"Are 'Pay when Paid' procecures more prevalent in

BC or in other main contractors?" Zero respondents stated


that PWP procedures were

more common in BC, whilst 14 (82%) thought they were more


common in "others" and

3 (18%) believed they were the same as each other. Many


subcontractors further stated that Pay when Paid clauses
were a fact of life in

construction and as long as the overall client was


reputable and "blue chip" they (SC)

did not have a problem with them. The final question of


the payment section, No.ll, was included to get an overall

perspective on whether BC or other main contractors paid


quicker. 41 % (7117) believed

that BC paid quicker whilst 47% (8117) believed that the


quickness of BC's and others

payment was the same.

3.2 Communication

Previous research within BC had identified that a


significant majority of subcontractors

believed that they should be involved earlier within the


building process than they are at

present. The main aims of this being to help develop


mutual understanding of the

project and to utilise the SC's expertise to every ones


benefit. Question 1 of the communication section
synthesised all these findings into a single

question to identify if this conclusion was correct and


could be used in Be. The
question asked, "Do you believe that BC subcontractors
should be involved earlier in the

building process to develop mutual understanding of the


project and to utilise your (SC)

experience". All 17 (100%) interviewees believed that SC


should be involved earlier. Question 2 asked "at what
time do you feel this earlier involvement should take
place?"

15 (88%) of the respondents believed it should be at "Pre


contract estimating". Other

results include, "Once contract has been won by BC" 2 (12%)


responses (12%), "Just

before subcontract works are to commence", "Once


construction has started" and

"other" did not receive any responses. The responses show


that pre contract estimating

was the highest. This was further expanded on by the


subcontractors stating that SC

involvement is more advantageous the earlier it happens.


474 Matthews, Tyler and Thorpe To set the preceding
question into perspective within the context of BC specific
performance, question 3 asked the subcontractors if they
are invited to become more involved in the project earlier
with other main contractors. 9 (53%) stated they were
involved earlier. This involvement was achieved by: • "MC
phoning us (SC) earlier to identify a desire or ability to
tender". • "Earlier use of our (SC) knowledge in design
details and specifications". • "Assist MC in identifying
alternative specifications. (Primarily on Design and
Construct projects)". The same 9 SC's were then asked what
advantages they saw in doing this. The most prevalent
answers were found to be: "Improves knowledge and
understanding (SC & MC) of the project which is of benefit
to all involved" and "We can share each others specialist
knowledge". These findings support those results from
question 1 of the communication section. The next issue
to be dealt with was that of improving communication
between SC and BC to improve relationships. Question 6
asked, "Do you believe that by improving

communication, BC could improve their relationships with


subcontractors?" The

interviewees were almost unanimous with 94% (17/18)


believing that relationships

could be improved this way.

3.3 Feedback

Within this section the subcontractor were firstly asked


if they thought that they got

adequate feedback from Be. 35% (6/17) of the


subcontractors believed that they were

getting adequate feedback. The remaining 11 (65%) were


then asked: (a) "What type of

feedback do you require?" (b) "When do you require it?" and


(c) "How often would you

want it?" The following are the most prevalent points


made:

a) Post contract feedback was required the most with a 45%


(5/11) prevalence.

b) Tender feedback helps the SC know where they stand and


enables them, in certain instances, to be more competitive
on future tenders. 55% (6/11) prevalence.

The next question asked the SC's to rate the feedback that
they received on their tenders,

both for BC and other Me. Responses were as follows: No.


of Responses

Score Rank BC Others

(1) Excellent [0] = 0 [0] = 0

(2) Good [7] = 14 [3] = 6

(3) Adequate [4] = 12 [11] = 33

(4) Poor [3] = 12 [2] = 8

(5) Very Poor [2] = 10 [1] = 5 16/48 17/52

Overall Score/Rank 3.00 = Adequate 3.27 = Adequate


By employing the method of analysis outlined in the
methodology it was concluded the

BC's tender feedback was 'Adequate', whilst other MC's was


just below 'Adequate'. Continuing with the feedback
subject, interviewees were asked if they believed they

got more feedback at precontract stage. 29% (5/17) stated


that they did, whilst the

remaining 12 (71 %) said they did not. Subcontractors were


subsequently asked, "If BC

were to give you more feedback at precontract stage, how


would this affect; tender

price, accuracy of estimate and overall performance. 38%


of the respondents said that Subcontracting the
subcontractor's view 475 feedback would make their tender
price more accurate, whilst 46% said accuracy would
improve with increased feedback. Overall performance would
not be improved. The ensuing question was asked, "How do
you rate the performance feedback you get from Be and
from other MC's". No. of Responses Score Rank Be
Others (1) Excellent [0] = 0 [0] = 0 (2) Good [8] = 16
[4] = 8 (3) Adequate [4] = 12 [9] = 27 (4) Poor [3] = 12
[4] = 16 (5) Very Poor [0] = 0 [0] = 0 15/40 17/51
Overall ScorelRank 2.66 = Adequate 3.00 = Adequate The
aim of this question was to establish if BC's performance
feedback was better or worse than their competitors.
Previous study's had shown that BC's performance feedback
was perceived as, "very minimal in terms of amount and
substance". Be scored 2.66 which amounts to between an
'adequate' and 'good' rank. Whilst other main contractors
feedback scored 3.00 which this also equates to an
'adequate' rank but with a difference of 0.34 between
scores. To conclude the feedback section of questions and
to sum-up holistically how Be compares to other MC's the
subcontractors were asked to rate 'overall' feedback. No.
of Responses Score Rank Be Other (1) Excellent [0] = 0
[0] = 0 (2) Good [4] = 8 [1] = 2 (3) Adequate [8] =
24 [11] = 33 (4) Not adequate! [3] = 12 [2] = 8
Acceptable (5) Very poor [1] = 5 [3] = 15 16/49 17/58
Overall ScoreIRank 3.06 = Adequate 3.41 = Adequate Be
scored 3.06 whilst others scored 3.41. Although both scores
equate to an 'adequate and acceptable' rank, Be did score
lower making them slightly better than the others. 3.4
Selection During previous studies it was noted that
preferential treatment from subcontractors would take the
form of returning main contractors tenders priced. Also,
many SC's stated that because of main contractors
requesting tenders which they would not use, SC's would
not quote until a Me had been awarded a contract. The
first question within the selection section asked, "Do you
frequently get enquiries

from MC's who you do not wish to work for?" 76% (13117) of
the respondents stated that they did get enquiries from
MC's who they did not want to work for. Question 2 asked
the interviewees whether they were invited to tender for
Be or did the enquiry simply arrive unannounced. 53% (9)
of the respondents believed that

enquiries did arrive unannounced whilst 1 (6%) respondent


said they were invited. 53%

(9117) of the SC's believed that other main contractors


sent enquiries unannounced

whilst 41 % (7117) believed that enquiries were both


announced and unannounced. 476 Matthews, Tyler and Thorpe
Previous studies had also shown that there was a genuine
belief by subcontractors that benefits would be obtained
by MC consulting SC before enquiries were sent out. 76%
(13/17) of the subcontractors interviewed within this study
believed that benefits could be gained from this which
would confirm the previous findings. Such benefits were
seen to be: • "Suitability of project to that work
normally undertaken by the us (SC)". • "Ability to do the
job. (Make resources available that would be otherwise tied
up)". • "Assist in defining specifications and design
details". Leading on from this question the next asked if
a bid would be more competitive if only 1 subcontractor
was used in tendering. 71 % believed that their bid would
be more competitive. However, 2 respondents did state that
their price would be higher. 29% stated that they always
gave the market rate anyway. Previous research had shown
that SC's became very irritated when they were

tendering against companies who were not offering a


comparable service. "Do you find that you (SC) are being
asked to tender on BC projects against non

comparable companies", was asked to identify how prevalent


non-comparable tendering

was in Be. 70% (12117) stated that they were asked to


tender against non comparable
companies either "always" or "sometimes". Only 2 (18%) of
the SC's interviewed said

that this "never" happens. However, when asked if this was


more prevalent with other

MC's 47% (8117) said it was, whilst 41 % (7/17) said BC and


other MC's were the

same.

Tendering

The first two questions of the tendering section were set


to identify if BC received any

preferential treatment from SC's at the tendering stage.


Of those 10 SC's who stated that they gave preferential
treatment, all 10 said BC

benefited in this way. Previous research had identified


certain issues which were

frequently mentioned as having a detrimental effect on a SC


tendering/estimating

service. These issues were: (a) Slow payment by MC on


previous contracts, (b) Unfair

contracts, Cc) Pay when paid clauses and Cd) MC


re-tendering once contract had been

won. In this survey the subcontractors were asked to rank


the previously mentioned issues

from 1 being most frequent to 4 being least frequent.


Subcontracting the subcontractor's view 477 Table 6,
Question 3. Section: Tendering. "The following
characteristics of a main contractor have been identified
as having a detrimental effects on (SC) tendering and
estimating service. Which if any occur most freuently?"
4 .---------------------------------------------~ 3.5 3
2.5 2 1.5 0.5 3.46 3. 15 1.85 lOBe IillOthersl Most
frequent = (I). Least Frequent = (5)S 2.92 2.28 2.21
From the above it can be seen that 'MC re-tendering once
contract has been won' was

most frequent in BC than in other MC's. Least frequent


effect for BC was 'slow
payment' and for others 'PWP clauses' . Most frequent for
others was 'unfair

contracts' .

3.5 Contracts management

It had been concluded from previous in-house BC research


that there was a perception

by SC's that whilst MC's were good at managing their own


direct labour, they are not

so adept at managing SC's. When asked to comment on the


above statement all bar 3

respondents thought that it was true. However, 38% (6/16)


believed that BC were

better than most and (7/16) thought BC were about the same
as the rest. None of the

SC's thought BC were worse. The next question was used


with the aim being to identify the perceived performance

of contract stage disciplines both within BC and other MC's.

Discipline BC Position Others Position Diff

Site Managers [2.13] 3rd= [3 .20] 5th 1.07

Contracts Managers [2.13] 3rd= [2.93] 4th 0.80

Projects Managers [1. 93] 1 st [2.46] 1st 0.53

Project QS [2.33] 5th [2.80] 3rd 0.47

Site Engineer [2.12] 2nd [2.57] 2nd 0.45

Average 2.12 (Good) 2.79 (Adequate) 478 Matthews, Tyler


and Thorpe Highest rank obtained by BC was for 'Project
Managers' with a 'Good' rank. This was followed by 'Site
Engineers' with a score of 1.12 (Good). Highest score for
others MC's was also for 'Project Managers' with a score
of 2.46. Site managers received the lowest score of 3. IO
(Adequate). BC staff consistently scored higher than the
other MC's with an overall average of2.12 (Good) compared
to 2.79 (Adequate). 3.6 Contract administration Previous
studies had shown that attitude, fairness of payment, trust
and fair dealing were the most important characteristics
to have when dealing with MC's and SC's. Question I, Table
8, Section: Contract Administration. "How would you rate
the following in the context ofBC and the industry norm?"
4 3.5 3.23 3 2.5 2 1.5 0.5 3.05 I DBC ~Others I
ExceUent = (I), Good = (2), Adequate = (3), Poor = (4),
Very Poor = (5).

The first question within this section asked the SC's to


rank from 1 (Excellent) to 5

(Very Poor) these characteristics in terms of BC and the


industry norm. BC scored a

rank of 'good' for all the characteristics with 'trust'


having the highest individual score

and fairness of payment having the lowest score of 2.29.


BC's scores more comparable

in value, with only 0.24 separating the highest from the


lowest values. This would lead

the researcher to conclude that BS have a balanced approach


when dealing with SC's.

By contracts, the industry norm consistently scored higher


than BC with 'fair dealing'

having the highest individual score of 3.23.


Subcontracting the subcontractor's view 479 SC's were
asked to rate the performance of pre-contract based staff.
Again SC's had to score each discipline, for both BC and
other MC's, from 1 (Excellent) to 5 (Very Poor).
Discipline BC Position Others Position Diff Estimators
[2.33] 2nd [2.76] 1st 0.43 Buyers [2.25] 1st [3.08]
2nd 0.83 PDM's [2.80] 3rd [3.20] 3rd 0.40 Average
2.46 (Good) 3.01 (Adequate) BC scored consistently higher
than 'others' with Buyers obtaining the highest score of
2.25 (Good). Estimators also obtained a 'good' grade but
with a score of 2.33. PDM's obtained the lowest grade
(adequate) but this may not be a correct representation due
to the fact that only 5 responses were obtained who knew
what a PDM was. Architects and Design Engineers did not
receive any results as SC's did not have any dealings with
them. Other MC's received all adequate grades with PDM's
receiving the lowest score. The final question in the
Contract administration section asked, "Do you believe
there would be any benefit in BC developing a non
contractual agreement which would promote fairness and
ruse between BC and its SC's". 71 % (12117) believed that
there would be a benefit in BC developing a non
contractual agreement. This was substantiated by the SC's
by saying that it would "promote trust" in order to
"reduce adversarial relationships" and it would be
construed as a "positive step in the right

direction". However, 5 SC's (29%) believed that there would


be no benefit in

developing an agreement as all it would be is 'lip service'.

4.0 Conclusions

It was apparent from this study that there are many areas
in which BC and main

contractors in general could improve their performance and


in turn improve their

relationship. It can be concluded that by involving


subcontractors earlier in the building process,

understanding of the project can be increased helping the


overall relationship. It should

also help to promote trust and team working between the


parties. Both BC and other main contractors tender
feedback was seen as 'adequate'. The

subcontractors stated that they would like more tender


feedback which would in turn

help them become more competitive. By adopting this


approach, BC and other main

contracting organisations will become more competitive


within the market place. It was identified that the
majority of subcontractors were not 'invited' to tender,

tenders simply arrived unannounced. This increases the


probability of confusion and

mis-understanding which inevitably leads towards conflict.


It was evident from this study that subcontractors do give
preferential treatment to

main contractors when tendering. In order to receive this


preference main contractors

should only be seen to use subcontractors who are of


similar size and who can offer a

comparable service. Slow payment was not seen to be a


problem in BC as it was within other main

contractors. This prompt payment helps BC obtain a high


score/grade for trust. Trust between BC and subcontractors
was seen to be 'good' but for other main

contractors this was seen to be 'adequate'. BC's lowest


score/grade was for 'fairness of

payment', however this still received a 'good' grade. Other


main contractors highest

score/grade was for 'fairness of payment' but this only


received an 'adequate' grade. Previous in-house BC
research had shown that SC's gave preferential treatment

during tender stage to MC's. SC's stated that slow payment,


unfair contracts, pay when

paid clauses and MC retendering once contract had been won


would all detrimentally

effect the service a SC gave during tendering/estimating.

480 Matthews, Tyler and Thorpe Benefit was seen in having


non-contractual agreements between BC and SC's. The

main benefits were identified as; promoting trust; a


positive step in the right direction;

help to reduce adversarial relationships. However, some


SC's were not in favour of a

non contractual agreement as all it would mean is that MC


would be paying 'lip service'

to better relationships.

2 Ndekugri, I.E. (1988), Sub-contractor control, the key to


successful construction. CIOB Technical Information
Service. THE WORLD ACCORDING TO SUBCONTRACTORS z. Sazen
and M.A. Kuguk Faculty of Architecture, Istanbul Technical
University, Istanbul, Turkey Abstract The present paper
attempts to look at problems of continuity and uncertainty
from a subcontractor's perspective. Evidence for the usage
of coping mechanisms was found in a sample of 33 Turkish
subcontractors. The [mdings of the study reveal that
subcontractors establish long term commitments with main
contractors and sublet work to secondary subcontractors
under pressure. Keywords: Subcontracting, boundaries,
construction firms, uncertainty. Sommaire La presente
communication traite Ie probleme de continuite et
l'incertitude pour soustraitants. Dne etude a ete
entreprise pour examiner les habitudes de sous-traitants
turcs. La conclusion la plus important est que les
sous-traitants etaslissent relations de longue duree avec
les entrepreneurs de constructions et employent
sous-traitants secondaires sous l'urgence des affaires. 1
Introduction Problems of continuity, uncertainty and
unclear boundaries seem to be beyond the scope of a single
organization to solve. Such problems require the pooling of
resources and expertise among stakeholders with different
goals, values and unequal power. Subcontractors operating
in the construction sector, just like main contractors, are
faced with uncertainty in securing contracts. It is
reasonable to argue that they should resort to
collaborative mechanisms to cope with this problem. While
presenting a simple picture of collaboration seems to be a
valid aim, collaboration alternatives are highly complex.
Complexity is due to power differences and also to the
existence of embryonic forms of organization in the
construction sector, namely sub-subcontractors. Thus while
there are collaborative relations between main and
subcontractors, there are also collaborative relations
between sub and sub-subcontractors. Consequently,
collaboration, from the subcontractors' perspective, has a
double profile: collaborations on the two levels are not
identical. As mentioned above, the factors contributing to
the differences are precisely the levels at which the
collaborative actions take place, multiple goals, power
differences. and differing organizational cultures.

The Organization and Management of Construction: Shaping


theory and practice (Volume Two).

Edited by D.A. Langford and A. Retik. Published in 1996 by


E & FN Spon. ISBN 0419222405. 482 80zen and Kuyuk 2
Subcontractors' responses to uncertainty Subcontractors in
the construction industry operate within a highly
unpredictable and competitive environment. The
unpredictability results mainly from two factors: a)
securing contracts on a long term basis b) changing
technology. For these organizations continuity of
professional life depends on the performance shown in
securing contracts and successful completion of the task.
Variations in performance in securing contracts leads to
fluctuations in business volume and problems of
personnel/machinery/equipment planning. On the other hand,
technological complexity of building subsystems (e.g. floor
heating, heating, insulation, security, mechanical systems,
etc.) has increased beyond the capacity of anyone firm or
organization to easily maintain control over the
design/manufacture/construction of a subsystem. The
present paper will argue that subcontractors attempt to
combat ambiguity by means of two mechanisms: (1)
Establishing stable relations with main contractors (2)
Subcontracting work sublet to them by main contractors.
Due to environmental uncertainty, subcontractors are forced
to establish long-term relationships with general
contractors. The relative length of the main
contractofsubcontractor relationship relieves some of the
burdens associated with the securing of contracts. Yet
under time and economic pressures, subcontractors tend to
bid for more work than their capacity and specialization
would allow. If they are successful in securing work,
they may sublet parts of the project to secondary
subcontractors. This practice allows them to • handle an
overload of work • transfer manpower and equipment
planning problems to secondary subcontract • minimize
manpower and equipment costs • handle a job beyond their
technological expertise and capacity (especially when the
specialized assets are critical) • earn a commission
without doing the job themselves (by bargaining with the
secondary subcontractors) Embryonic organizations like the
secondary subcontractors are likely to offer very

low prices in exchange for an opportunity to work and to


establish a relationship.

3 Method

3.1 The unit of analysis

The subcontractor organization is the unit of analysis in


this research, as an intermediate

level between the secondary-subcontractor and the main


contractor. World according to subcontractors 483

3.2 Data collection and analysis

The research was undertaken between February 1993 and


August 1994 in Istanbul,

Turkey (1)(2). The data is based on a questionnaire


directed to 33 subcontractors operating in
Istanbul. Due to difficulties in fmding a file of
sub-contractors, we worked with a

convenience sample. The questionnaire was made up of 2


sets of questions: the first set pertaining to

subcontractor-main contractor relationships and the second


set to subcontractor-secondary

subcontractor relationships. Descriptive statistics and


correlation analyses were used in the interpretation of

data collected. Due to space restrictions, only descriptive


statistics will be reported within

the scope of this paper.

4 Results

4.1 Variations by trade

Subcontractors making up the sample were found to engage in


the following activities: • Design • Earth moving work •
Formwork • Steel structures • Concrete work • Masonry
• Roofmg and related work • Plastering and stucco •
Window and door framing • Painting and fmishes • Glass
• Interior decoration • Building chemistry •
Mechanical installations • Electrical installations •
General contracting 484 50zen and K{j~{jk Activity focus
range is significant. The distribution of firms undertaking
one or more of these activities is as follows. Table 1.
Distribution of activities Number of activities 4.2 Size
1-3 4-6 7-10 11-17 Table 2 presents the distribution
of personnel size. Table 2. Size Number of workers
employed 4.3 Age ::;10 11-25 >25 Number of firms 12
11 4 6 Total: 33 Number of firms 13 10 10 Total: 33
The subcontractor organizations showed the following age
distribution. Table 3. Age Age (yrs) ::;10 11-20 >20
Number of firms 16 12 5 Total: 33 It is interesting to
note that the majority of subcontractors have been at most
10 years in business. There ore only 5 subcontractors
older than 20 years, which shows that the subcontractors
in the sample are rather young. World according to
subcontractors 485

4.4 Subcontractor-main contractor relationships

The group of questions belonging to this category


demonstrate the existence of stable
relationships between subcontractors and main contractors.
As expected, all of the subcontractors in the sample had at
least worked on 5

projects with a main contractor. The distribution of


responses for the maximum number

of jobs completed for a main contractor is summarized by


Table 4. (2 subcontractors did

not reply, reducing the number of valid observations to 31)

Table 4. Maximum number of jobs with a main contractor


Number of jobs I 5 10 20 On a continuous basis
Number of subcontractors (f) o II 8 5 7 Total: 31
Subcontractors were further asked to indicate the extent to
which they would

provide support for their main contractors in case the main


contractor had a conflict with

the client. As shown in Table 5, the cumulative percent for


"Always, generally,

sometimes" responses is 97.

Table 5. Support provided for main contractors Response


category Always Generally Sometimes Rarely Never
Number of subcontractors (f) 8 12 12 o Total: 33 It
may be reasonable to argue that solidarity in
subcontractor-main contractor

relations is an important factor in maintaining an enduring


collaboration. One other

prerequisite of maintaining a stable relationship is


providing free consultancy services to

the main contractor at some stage of the job. Most of the


subcontractors have replied that

they "always" provide free consultancy services to the


main contractor when asked to do

so (Table 6). 486 S6zen and Kil9ilk Table 6. Free


consultancy services provided for main contractors
Response category Always Generally Sometimes Rarely
Never Number of subcontractors (f) 13 7 11 Total: 33
The distribution of responses to this category shows that
subcontractors do not regard time spent for consultancy
services as a cost, but rather as an investment for
settling established relationships. A further advantage
might be access to information on technical and
administrative details, as well as costs and conditions of
the job undertaken. 4.5 Subcontractor-secondary
subcontractor relationships The second group of questions
aimed to collect data on further subcontracting practices
of subcontractors. Subcontractors were asked to indicate
the frequency of subletting work to secondary
subcontractors. Table 7 shows the distribution of
responses to this question, which was formulated as
follows: "Would you sublet work to secondary
subcontractors in case you are overloaded with work or are
under time pressure?" Table 7. Work sublet to secondary
subcontractors Response category Always Generally
Sometimes Rarely Never Number of subcontractors (f) 9
7 7 8 2 Total: 33 It is interesting to note that only
2 of the subcontractors replied that they would not sublet
work under any circumstances. The remaining 31 are willing
to subcontract work under pressure. Another question
designed to provide evidence for the existence of this
practice was as follows: "Would you sublet work to a
secondary subcontractor offering a price lower than the
price you offered to the main contractor for commercial
purposes?" (Table 8). The number of subcontractors who
replied "never" was 7, showing that the remaining 26 might
think of subletting with commercial considerations. World
according to subcontractors 487

Table 8. Commercial considerations in subletting work


Response category Always Generally Sometimes Rarely
Never Number of subcontractors (f) 3 7 8 8 7 Total:
33 Further evidence or the existence of the practice was
provided by asking

subcontractors to indicate the extent of difficulties


encountered in controlling quality,

duration and cost of work performed by a secondary


subcontractor. The findings showed

that all respondents did sublet work in contradiction with


the findings reported by Table

7. (2 of the subcontractors had replied that they never


sublet work further down)

Table 9. Difficulties encountered in the control of


secondary subcontractors Response category
5 Conclusions Always Generally Sometimes Rarely Never
Number of subcontractors (f) 6 7 14 3 3. Total: 33

The research provides evidence that subcontractors lay


emphasis on the maintenance of

enduring relationships with main contractors and they do


sublet work under pressure. Subcontractors value
solidarity as a means of sustaining relationships with the

main contractor and consequently, provide some free


services in return for the continuity

of the relationship. On the other hand, pressures (time,


overload and commercial considerations) play

an important role in the further subcontracting of work.


Subcontractors' preference is that

main contractors do not learn about the practice. One of


the reasons for this is the

commercial side of further subletting. Another might be


the risk of losing future jobs to

secondary subcontractors because of their very competitive


prices. And finally, subcontractors do seem to accept the
fact that there are problems of

control with work subcontracted.

488 S6zen and Kuyuk The fmdings of the research provide


evidence for the existence of an additional

ring in the production chain. This additional ring might be


causing mainly two types of

problems: • extra costs incurred by the main contractor •


organizational and managerial problems caused by a group of
workers not directly supervised by the main contractor's
control team. The study calls for new avenues of
additional research. To begin with, a

complementary study on a larger sample of subcontractors


would add a supplementary

perspective. Furthermore, a differential analysis of


trades would be beneficial to see

whether these practices are adopted by all trades. Another


suggested research direction

refers to the quantification of the extra cost brought by


the practice of subletting work to

secondary subcontractors. Further research in different


countries, would be able to

illustrate whether the pattern is universal and if it is,


which variables contribute to it.

1. Kiiyiik, M.A. (1995), j~aat Sektoriinde Alt Yiiklenici


Davram#arz, unpublished M.Arch dissertation, Faculty of
Architecture, Istanbul Technical University.

2. Sozen, Z., and M.A. Kiiyiik (1995), Siireklilik ve


Baglmlzhk, jn!jaat Sektoriinde Alt Yiiklenici Davram#arz,
5th National Management Congress, Istanbul.
Value management

1. Gray, C., Hughes, W. and Bennett, J. (1994) The


successful management of design. University of Reading,
UK.

2. Gray, C. and Flanagan, R. (1989) The changing role of


specialist and trade contractors. Chartered Institute of
Building, Ascot, UK.

3. Gibb, A.G.F. and Brand, P.R. (1996) Vintners Place:


Procurement, design development and construction of a
complex building facade with a traditional architectural
appearance. Proceedings of the Institution of Civil
Engineers (Structures and Buildings), London, UK.
(Awaiting publication)

4. Gibb, A.G.F. (1994) Prefabricated modules in


construction contrasting approaches

to prefabrication. Chartered Institute of Building, Ascot,


UK, Construction Paper No.

38, pp. 1-8.

DESIGN QUALITY CONCEPT TO

IMPROVE BUILDING QUALITY

S.B. Melhado and V. Agopyan

Civil Construction Engineering Department,

University of Sao Paulo, Sao Paulo, Brazil

Abstract

Despite the fact that there is a common sense in several


published research about the

importance of the design's contribution to quality


improvement, the design concept itself

has not been properly analyzed by many authors. Almost all


these works present many

factors related only to the building characteristics as a


product, not as a complex process. This work discusses
the potential contribution of design to quality and how it
could be
more effective, or rather how building design procedure
must be organized and considered

as a part of the project plan to achieve the best quality


results. For this purpose, a case

study is presented as a referential portrait. The clients


satisfaction factors, involving mainly the needs of
customers, construction

companies and investors, are analyzed under a contemporary


and systematic point of view.

On the basis of this analysis, a proposal of guidelines


will be briefly described in order to

approximate the production and the design objectives, which


will consequently change the

design team arrangement and the design co-ordination and


control methods.

Keywords: Building design, building technology, building


quality, quality management.

Resume

Malgre Ie reconnaissance pour la majorite des recherches


pub lies sur Ie sujet de

l'importance de la contribution de la conception du projet


pour l'amelioration de la

qualite, Ie concept il n'a pas ete analise par beaucoup de


ces travaux. Ce travail discute la contribution potentiel
pour la qualite et comment il pourrait etre

plus efficient, c'est a dire, comment Ie processus du


projet doit etre organise comme partie

de l' entreprise pour atteindre les meilleurs resultats.


Dans ce concept, un etude de cas sera

presente comme un cadre de renseignements. Les facteurs de


contentement des clients du projet, enveloppant les
necessites des

usagers, des entreprises de construction et des


entreprenants sont analises de fa90n
sistematique de la contemporaineite. Base dans cet analise,
ce sont propose des lignes

directrices pour rapprocher les objectives du projet et de


la production, en consequant

alternant la composition de l' equipe des projetistes, da


coordination et les methodes de

controle.

The Organization and Management of Construction: Shaping


theory and practice (Volume Two).

Edited by D.A. Langford and A. Retik. Published in 1996 by


E & FN Spon. ISBN 0419222405. Designing for building
quality 503

1 Design quality

According to Giuffre [1], there is a conceptual distance


between "qualitative architecture"

and "quality of architecture". The first is concerned about


the result in the use of a

product, while the second one is essentially related to


the process elements that generates

that product.

This paper deals with the second definition above


mentioned, which emphasizes the

industrial character of design, as part of a production


cycle.

A research about materials wasted in the construction


industry reach a conclusion that

design parts integration and its buildabilities are


significant factors of this wasting process

[2]. Otherwise, it is possible to say that, under


appropriate conditions, design quality will

be just a result of the companies' quality systems, or


rather a result of the projects' quality
plan. If there are non-solved quality problems, design
will show them.

Although building costs are very difficult to be estimated


without design detailing, the

main question is to reduce them through a rationalization


analysis, which is possible to be

made even in the very early stages. Marketing strategies,


in general, need a very fast

response from the architect, concerning the preliminary


design solutions. The accuracy of

these solutions is not satisfactory in many cases, being of


paramount importance to create

a new integrated design methodology to change this


situation. For the same reason,

technological innovation requires a new design methodology


to be successfully

implemented.

If building quality is an objective, the main


characteristics of design must include the

following [3]:

• Design is a part of the comprehensive production cycle:


it cannot be understood as

a process itself, since designers take part in the whole


project process, as do suppliers,

builders, sub-contractors, quality supervisors, etc.;

• Design is a preview of building: it needs to contain


information about technological

specifications, constructive methods, production


organisation and quality control, in

order to solve the main questions of on-site building


activities, and to conciliate

product (the building) and production (to build) needs;


• Design is more than a drawing and describing process: it
is an important activity

that improves the building process quality and generates


more than drawings and

documents; it is also a service which must last until site


work ends and client accepts

the building;

• Design is not only an architectural or engineering


problem, but a multidisciplinary

work, which involves marketing analysis, cost analysis,


technological choices,

production process study, etc.;

• Design should work as a mean of communication of


technological innovation; the

necessary changes to improve competitiveness are much more


effective when they can

be implemented during design development and not after it


has been completed.

To many people, the main emphasis seemed to be on how to


control design documents

and quantify a numerical index that should express the


quality of resultant solutions.

However, the critical point seems to be how to avoid


typical problems that can affect

design quality.

504 Melhado and Agopyan According to other author [4],


design quality can be defined as a combination of "design

solution quality" (the product concept quality), "product


description" and "design process

quality". However, the last component will always be the


one that generates the others. Another important factor
involves the design detailing and how much it aims at

production activities. The traditional role of Architects


in detailing the design is changing

[5], so that other design specialists are also performing


it (e.g. masonry detailing). The importance of those
ideas explained above will be clearer as more expectation
about

evolutional changes is considered. Thus, when a company is


trying to manage its quality

problems through a technological improvement, design needs


to be focused as described.

This last affirmation can be demonstrated by a case-study


analysis, which is following

presented.

2 A case-study describing design practices inside a company

This case study refers to a work involving a Brazilian


private building company, which is

carrying out during a 12-month cooperative research program


among University of Sao

Paulo and this company. The conclusions described here are


a partial result of this

program. It is a company that executes externally


contracted building works or its own projects.

As it expresses an expectation on a well oriented income


growth, specially based on the

second mentioned group of projects, the company carried


out an extensive quality

program. The main objective related to design quality


subject was to develop a

methodology in order to establish an integrated performing


of design and production

processes. The first activity of the research program


consisted of a diagnosis focusing the company

internal relations and the performance of its main


departments, concerning their influence
over design quality. It was essential to provide basic
comprehension about: ordinary

procedures; responsibilities division; non-satisfied


expectations; and other related features. The diagnosis
permitted the identification of several factors that were
affecting design

quality and aimed at the proposal of methodological


changes in the usual procedures.

These factors are explained below:

• As different performing areas, real estate developing and


building were separated but undefined and incoherent
activities, without a common acting philosophy; this
separation among fundamental activities did not aim to
implement essential procedure changes;

• Reflecting the quality problem, there were non-specified


subjects in the designers contracts; they were only
informally oriented by very busy co-ordinators;

• The real estate developer "culture" included


low-expensive design; associated to this minimum expense,
there was a practice of minimizing the design solutions
detailing, reducing its accuracy and utility, specially
in terms of build ability;

• The emphasis on the product itself, like an exclusively


marketing problem, was very predominant during the first
stage of the project; as a result, almost all
technological questions were not discussed, so they could
not influence the designed characteristics;

• The design co-ordination process was too informal that it


generated a nondocumented and poor integration of design
parts; as a result, design documents were full of wrong
or missing information and they had a poor reputation among
site personnel; Designing for building quality 505

• There were no systematic criteria for decision making to


orient design work,

concerning buildability needs; during the design detailing


stage, site operations

efficiency was not properly considered;

• The analysis of design quality was not possible, since


detailed information was

available only at the end of design process;

• The practice of maintaining some finishing material


specifications undefined, until

someone asks for them, was a important quality improvement


barrier; this situation

remained until suppliers or site personnel needed the


specification to buy the materials

or contract the services;

• Most of the constructive details were not useful, since


they were presented to

describe only the product final appearance or specific


characteristics, but the details did

not show how the product had to be built; and,


furthermore, presented incoherent

dimensional data and missing information.

During this research program about design quality problems


in that private building

company, involving the production of buildings, it was


possible to develop a group of

guidelines to a new design methodology, considering the


special needs of this kind of

design.

3 Proposed design methodology

Searching for a new methodology that would consider the


difficulties above mentioned

and would include the necessary changes to achieve quality


improvement objectives, some

guidelines will be proposed to design co-ordination


process. Those methodological

guidelines, that will involve either internal or external


relationship, since both of them
influence design quality, are described below:

• Product and production process must be equally


considered, since the very early

beginning of design process -it means a significant


buildability improvement;

• The post-occupancy systematic evaluation must be


implemented as a part of a feedback

information system that aims at designers and prevent some


possible repetition of

technological errors;

• Building design, as a multidisciplinary activity, needs a


multidisciplinary team of several

specialized designers and consultants working together


since the very early stage of

design process;

• Design co-ordination needs pre-established parameters and


criteria in order to orient,

analyze and criticize design solutions properly;

• Design quality involves not only design review


procedures, which are related to the real

estate developing and the construction companies, but also


a well supervised quality

control procedure inside the contracted design firm;

• Supply, work training, technological development, design


and production processes

must be oriented by the same statements of a quality


program that a company is

implementing.

As many problems were spotted when analysing the above


mentioned company, we

proposed the described guidelines in order to feel how they


would work. The

implementation of the new design methodology is now in the


process of conduction

through an experimental way, adopting a project to a


preliminary introduction of the new

506 Melhado and Agopyan

procedure. Although people involved were convinced that the


adoption of this proposed

methodology would enable the company to get best quality


results, there are some

potential difficulties. The first difficulty of a series


appeared in the early beginning, when it was necessary to

create the multidisciplinary team and choose its


co-ordinator. The discussion about rights

and responsibilities division, as a whole, became


non-consensual. The real estate

developing company wanted to get all things under control


till the legal presentation has

been done. On the other hand, the construction company


could not agree with it, since on

that way it will not be possible to use both buildability


and marketing principles, side by

side, influencing design solutions. At the end, the


directors of the holding company, which comprisses the
building and the

real estate developing companies, forced all the


executives to a compulsory change of

their positions and the design team had to be co-ordinated


by the real estate develop

company or the construction company leaders, depending on


the specificity of each

subject, what were previously defined. Another difficulty


that created a significant barrier involved the designers'
contracts,
which were postponed until the limit, trying to save some
money in the first stage of this

project. The new metr..odology anticipates the usual


payments to designers and creates

also new ones, what seems to the real estate developer a


not so useful thing, considering

just only his own objectives; to improve design quality,


design stages have to incorporate

all specialists sooner. See figures I and 2 to make it


clearer. When the design process started, some designers
reacted friendly to those new demands,

while others did not understand the asking of different


information and presentation of it

to their design parts. It was demonstrated, again, how


motivation is an essential part of

any quality improvement program. After this "stormy"


phase, this design process has been more accepted and the
project

activities are now expected to continue in a more


appropriate rhythm.

4 Conclusion

The results of the design procedure conceptual changes are


undoubtedly significant to

improve production efficiency, in terms of build ability


and production costs control, which

are essentially concerned about competitiveness of the


project. A product like a two-bedroom flat to be sold by
around US 55,000, that is very often

determined by marketing studies, cannot be competitive if


there is not a quality effort

involved, because of waste of materials, manpower,


re-building and other similar

components. Technological innovation and its design


integration are naturally associated
with quality implementation. The practice seems to show
that there is not any profit barrier; on the contrary,
there is a

great potentiality of associating cost saving to quality


improvement. For instance, floor

levering had a cost reduction of about 75%.

I. Giuffre, R. (1994) A quality of architecture, or a


qualitative architecture? in Eureka Conference: Quality
Management in Building and Construction, (ed. O.Sj0holt),
Norwegian Building Research Institute, Lilleharnmer, June
1994. pp. 163-7. Designing for building quality 507

2. Franchi, C.C., Soibelman, L. and Formoso, c.T. (1993) As


perdas de materiais na industria da constru~ao civil, in
Proceedings of the 2nd Seminario Qualidade na Construfiio
Civil, NORIE-UFGRS, Porto Alegre, June 1993. pp. 133-98.

3. Melhado, S.B. and Agopyan, V. (1995) 0 Conceito de


Projeto na Constru~ao de Edificios: Diretrizes para sua
Elabora~ao e Controle. Boletim Tecnico. EPUSP, Sao Paulo.
(BTIPCC No. 139)

4. CTE-Centro de Tecnologia de Edifica~oes. (1994) Sistema


de gestiio da qualidade para empresas construtoras,
SindusCon-SP, Sao Paulo.

5. Hughes, T.B. and Williams, T. (1994) Quality problems


with Quality Systems arising from the motivation of
organisations and their methods of implementation, in
Eureka Conference: Quality Management in Building and
Construction, (ed. O.Sj0holt), Norwegian Building Research
Institute, Lillehammer, June 1994. pp. 254-9. I I
L:'i':G_I I ARCHIT,.ECTURAl I I ~RELIMINARV LPESIGN
--r= ENGINEERING I ~-m -CONSULTANTS [ SCHEME [
(INFORMAL) DESIGN LEGAL :~~~g!'0F mm---'-m------l '
STRUCTURAL ARCHITECTURAL HI BUILDING SERVICES I[ DEFIN/T,E
DEFINrrE DEFINITE DESIGN DESIGN DESIGN I I I I I I
PRODUCTION ,II ~(ONSITE) ~ Fig. 1. The usual design
procedure.

508 Melhado and Agopyan BRIEFING ARCHITECTURAL ~ i


PRELIMINARY I i DESIGN J ENGINEERING AND TECHNOLOGICAL
CONSULTANTS (FORMAL) IAJ ,MULnDfflC~LINARr-____ ~ I
SCHEME DESIGN -~I I I I I I I , .. I BUILDING
SERVICES DESIGN ARCHITECTURAL DESIGN STRUCTURAL DESIGN
PRODUCTION PROCESS DESIGN I ~ I I ! SUPPLIERS
QUALITY SUPERVISORS A~$~~AL -----.-.------i DEFINITE
DE;;;;;-Ii II 1 II PRODUCT II PRODUCTION I I II
(Bui/ding) II PROCESS I i ~-:----~:J~-==~ '---.~
---------1 I PRODUCTION I FEEDBACK I (ON SITE) I I~
_____ ------: Fig. 2_ The proposed design procedure
considering the guidelines for quality improvement

A DESIGN TOOL FOR INCORPORATING

CONSTRUCTION KNOWLEDGE DURING

DESIGN

Bob G. McCuliouch

School of Civil Engineering, Purdue University, West


Lafayette,

Indiana, USA

ABSTRACT

The United States has traditionally used the DesignLow


Bid-Construct process.

This arrangement consists of a separate Designer and


Constructclr on a project.

The designer is chosen and employed by the owner of the


desired facility. The

contractor selection is based on low bid. This scenario is


well knclwn and

understood. One of the major inherent deficiencies with


this systE!m is the lack

of construction knowledge incorporated into the design


document:;. This is

commonly called "constructability." Because each


responsibility is separated

this integration is hard to achieve.

Constructability has been defined as the integration of


construction knowledge

and experience during all phases of the facility


development procl!ss. The
primary objectives of constructability are to improve
construction, as well as the

overall performance of the facility. The input of


construction knowledge during

the design phase is especially important to achieve these


goals. To accomplish

this, the design team requires either direct field


experience, or at least

immediate access to experts in construction issues.


Unfortunately, most

designers do not possess sufficient construction


experience. Furthermore, there

are few construction professionals who have sufficient


design expertise to

function effectively as constructability experts for the


design team This creates

a serious obstacle to achieving constructability in a


project.

Th,is paper describes how this obstacle can be overcome


with a cI)mputerized

constructability support system. The system organizes and


presents

construction knowledge as both concepts and lessons


learned. Specifically, the

paper describes a computer tool that captures, records, and


stores

constructability concepts and lessons learned, while


providing deHign

profeSSionals with easy access and graphical retrieval of


concepts and lessons

to deepen their understanding of constructability issues.


The syst.!m uses a

"windows" environment, an open navigation architecture for


the user, and full

The Organization and Management of Construction: Shaping


theory and practice (Volume Two).

Edited by D.A. Langford and A. Retik. Published in 1996 by


E & FN Spon. ISBN 0419 22240 5.

510 McCullouch

range of multimedia displays to represent constructability


knowleclge.

The multimedia feature significantly improves user


comprehension. Text,

graphics, images, video and sound are used to represent


constru(;tion

knowledge more completely. The richness of graphic


retrieval ancl multimedia

representation combine to enable a designer to more


effectively assimilate

constructability knowledge into his or her own existing


knowledge of design.

The approach used in this system provides many advantages


over existing

systems. Not only can the integration of construction


knowledge and

experience at the earliest stages of project planning now


be possible, but also,

constructability knowledge base now can be rendered


economical:ly feasible to

create, update and use.

Sommaire

Dans ce memoire il est decrit un outil a ordinateur


multimedia pour I'aptitude de

construction. L' aptitude de construction est


I/integration de la science
de construction et de I'experience dans la conception afin
d'ameliorer la

methode de construction et la performance de


I~nfrastructure UnEl fois complete.

La multimedia nous donne une sarie de d1information


complete, qui permet de

capter cette connaissance. A travers des outils imperatifs


, on arrive a une

application robuste qui est facile a I'usage et qui est


tres representative de cette

domaine d'information. Les organisations de construction et


du dessain,

peuvent utiliser cet outil pour creer leurs propres


"lessons appris" afin de capter

liexperience et de la mettre disponible pour utilisation


prochaine. L' outil se

presente en CD-ROM et fonctionne dans un milieu Windows


sur ordinateur

individuel.

Introduction

A primary factor, contributing to lack of productivity


gains in the U. S. construction

industry is the failure on the part of design and


construction teamn to effectively

record, for future use, so called,


'constructability-Iessons-Iearned.' This is not a

new problem. For many years experienced construction


personnEll have

provided input into construction projects in order to


enhance constructability and

consequently improve a contractor's performance. Zyhaljo


[1] advised that

structural engineers are still not usually trained or


educated in construction

methods and are therefore unaware of the impact of


construction ,:;onstraints on

design. Fisher [2] claimed that due to the fragmentation


in the construction

industry, structural engineers rarely use explicit


constructability knowledge when Design tool for
incorporating construction knowledge 511

making decisions about the layout and dimensioning of


structural elements.

Construction systems tend to be islands of automation in


speciali2:ed firms.

Integration of design and construction is still at the


level of face-to-face review

meetings and post construction design reviews ([3],[4]).

Constructability has been defined as the integration of


construction knowledge

and experience during program development, conceptual


plannin!~, engineering

design, and construction operations; to achieve project


efficiency. Since

developing a clear understanding of a project's objectives


and priorities is the

first responsibility of the owner's team, it necessarily


includes construction cost,

and its related schedules, quality and safety


considerations. Projl!ct value

engineering analysis can and should include additional


consideration for

aesthetics, reliability, leasability, public image,


operability and maintainability,

etc. [5]

Construction experience is knowledge based on methods to


perform

construction field operations, gathered primarily from the


results of prior projects.

This knowledge provides technical, operational,


contractual, or administrative

guidance for subsequent projects. [6] The primary objective


of constructability is

the enhancement of project performance. This may be


accomplisl1ed by using

construction knowledge or lessons learned especially


during the planning,

conceptual and schematic design phases. Doing this at the


early stages will

Significantly reduce construction labor and equipment cost,


decrease the amount

of change orders, help prevent cost overruns, lessen scope


growth, and most

likely minimize claims, time extensions, and litigation.

The advantages of constructability programs are well


documented. In the mid

1970's Proctor and Gamble developed a manual on


constructability, based on

13 in-house case studies documenting the benefits of a


concertecl effort [7].

Ardery [8] found they will payoff 10-20 times the cost of
the progr.am. The

Construction Industry Institute (CII) reported that


specific projects have realized

a 6-23% savings and project schedule savings of up to


fourteen months, by the

addition of a constructability program [9]. Fisher [2]


determined that through

such programs engineers can be trained more quickly, and


better decision

support data and knowledge will be available. According to


Jaselskis [10], the

probability of successful project schedule performance


increases ·From 2% to

33% with a constructability program. Indeed,


implementation of a

constructability program seems to have a significant impact


on achieving overall

project success as well as better schedule performance


especially on

fixed-price contracts ([11], [8]).

512 McCullouch

Computer Tool Development

Bringing construction knowledge into the design environment


can significantly

impact project performance as described in the previous


section. With current

computer technologies tools can be developed that allow


the capturing of

construction experience or "lessons learned" and store


this information in a

format that can be retrieved into the design. Construction


knowle,dge is not

easily represented and explained by traditional computer


alphanumeric

characters. Other media forms such as pictures, details,


drawings, sounds, and

video can represent a much broader field of construction


knowledge. These

media forms are commonly called "multimedia." Since


multimedia is able to
represent and explain these "lessons" more effectively, a
constru(:tability tool

that utilizes multimedia was developed. The next section


describes this tool.

Tool Description

Early in development objectives were established and


followed in creating the

tool. One it had to be easy for the user to navigate and


find an individual lesson.

Secondly, it had to have maintenance features for updating


the information

base(which contains the lessons) and adding, deleting, and


channing individual

icons representing lessons. Thirdly, the information base


where the lessons are

grouped and described had to have hyperlinking capability


to a full range of

multimedia files as well as query capabilities.

To achieve these objectives a careful evaluation of


software options was

performed. For the navigation interface, it was decided to


use icons for

representing constructability categories, groupings, and


individuc:11 lessons.

Also the navigation process can be performed on one screen


so tile user can

see the path while the other possibilities are still


present. Another important

feature is all actions are initiated by the user with the


clicking of a mouse. NO

commands are required so the user does not have to interact


with the keyboard.

To accomplish this Microsoft Visual Basic was chosen. The


below two figures

show a sample screen where the user has navigated to a


particular lesson and

how the navigation process works. Design tool for


incorporating construction knowledge 513 Figure 1 User
Navigation Screen O.~iled. Litvel ···· Di~p!ay . Figure
2Navigation Process Lesson Learned Background Display

514 McCullouch

The above two figures illustrate the navigation process and


the graphical

environment. The user navigates with the mouse by choosing


and clicking

icons. The complete search process is described on one


screen. This facilitates

a better understanding of where particular lessons are


located and how the

lessons are categorized.

The fourth window contains a picture or figure


representation of the lesson.

Double clicking anywhere inside this fourth window


initiates a search for the

lesson that is retrieved and displayed on the screen.


Figure 3 is an example of

a lesson that is displayed to the screen.

Each lesson is described with the follOwing format:


guideline, qualifiers and

exceptions, benefits, reasons, examples with graphics or


other supporting media

data. The guideline is a concise description of the


constructability example. It

is usually stated in one sentence. Qualifiers are those


conditions where a

lesson applies and exceptions where a lesson doesn't.


Benefits quantifies the

savings that could be generated by applying the


constructability principle.

Reasons describe why this lesson should be applied.


Examples are specific

lesson cases that have occurred on a project and the


originator of the lesson.

Graphics are media examples(picture, fiQure, video, etc.)


of the lesson. :: . Guideline: If extending an existing
bridge, the designer should check existing bridge foundat
ions to determine if seals were used. If seals were used,
then they should be specified again. Qualifiers : I .
Check soils report information and recommendations.
B.""llts: This is a safety issue at the job site. Reasons:
The use of a concreto seal at the bottom of a coffer
dam.avoids boUom blowoul The workman's lives can be tost
if this rather sudden quick. condition occurs when they are
in the hole. It is caused by a combination ofhigh
hydraulic head and susceptible .oils. A .ealis cosUy, and
the engineer should consult old field records to see if the
existing bridge foundations required them during
construction. SolU'Ce: Weddlo Bros. Construction
Proceduns for bostallby: a seal I . Remove tho soil inside
tho cofferdam (through clamming or some other technique) to
the olevation of tho .eal bottom. (Cofferdam is not
dewaterod) 2. Install the foundation piles to desired tip
elevations or bearing capacities . 3. Place seal concrete
usir!8 the tremie method. (See DetailofTreWlie _tltMl For
the concrete pump option, the dis charge hose is submerged
in the water as far as possible but does not come in
contact with the bottom. This procedure help" eliminate
any separation of the mix. (SeerPifUrtl 4. A vibrator is
used fre limit the amount of voids

Figure 3 Lesson Learned Design tool for incorporating


construction knowledge 515

One very important development objective was to use a full


range of media

forms to help explain and enhance the textual description.


The software chosen

with this capability was Folio Views. Folio Views is an


electronic information
manager that has the capability to embed graphics inside
the text or hyperlink to

other media files that can be displayed or played on the


screen. Figure 4 shows

a lesson learned with a hyperlinked media file displayed


on top of the lesson.

These media files can be pictures, figures, sound clips,


and media clips. : , :.,: ".:.: : The worl<man'.live.
can be lost ifthi. rather sudden quick.conclition OCcut.
when they are in the hole. It is c.used by. combin.tion of
high hydraulic he.d and susceptible soils. A • • oJ i.
cosUy, and the engineer should consult old field records to
see if the existing bridge . . 6. Random mea.urement
ofth. seoJ . Ievation during tho pour is .ccomplished by
submerging. me.suring tape in the water until it rest on
the top of the poured concrete and m ••• ur. to the top
of a coff.rdam fram •. (See !!lCM~ 7. Once the seoJ has
been J' ... . ~,! .. d and cured, dew.urthe cofferdam and
cut the pipe pil •• off at grade . (See~

Figure 4 Byperlinked Media Files .: :

When the user completes the review of a lesson then to


return to the user

interface screen a click on the minimize button located in


the upper right part of

the screen is required. From this screen the user can


search for additional

lessons or exit the application.

This tool can also provide other types of information to


the designer besides

construction knowledge or experiences. Hyperlinks to


design manuals,

standards, or details can provide this type of information


electronically and

516 McCullouch

quickly. Also specifications, design tables for structural


members or system
components, design memorandums can all be accessed through
this tool. A

comprehensive designer performance support tool can be


developed and

provided that can significantly enhance the performance of


an ennineer.

Tool Distribution

The tool will come in two versions. One is a user version


that will be distributed

on a CD-ROM disk. Currently the application is


approximately 510

MB(megabites) in size which can fit on a CD. The reason for


the large size is

that the 19 video files on the CD require approximately


450MB of storage. The

CD version is now ready and available for distribution. It


was developed for

Windows 3.x but it also runs under Windows 95. It has been
tested on a 486

33 Mhz with 4MB of RAM up to a Pentium running at 100 Mhz


with 16 MB of

RAM. The PC needs a sound card and speakers for hearing


the Bound files and

movie audio clips. The application requires 1.5 MB of hard


disk storage space

for creating a directory to copy some application run


files into. At the conference

a complete demonstration can be performed from the CD-ROM.

The second version is for a developer to modify and update


the information base

with. Screens with forms for this type of application


maintenance were

developed. Because of space limitations these screens can


not be displayed

and explained within this paper.

Final Summary

What has been briefly explained in this paper is a


constructability tool for

transportation organizations and design consultants. It


helps to bridge the

information gap between the design environment and the


construction jobsite.

Multimedia can be used to capture and represent a broader


field of construction

knowledge which can be recorded in electronic form and


brought into the

designer environment.

This type of technology application can also be used by


civil engineering

organizations to record and store their own "lessons


learned." Historical

examples can be saved, experience knowledge can be recorded


and not lost

through retirement or leaving for other employment. So this


type of "experience

knowledge" can be accessed and passed on to younger and


less experienced

employees. And in the times of corporate downsizing and


lean staffs this type of

information is crucial for the success of any


organization. A company that can

effectively use this type of technology in managing


information will have

competitive advantages through providing their employees


with information to
improve their job performance. Design tool for
incorporating construction knowledge 517

1. Zyhaljo, E.; "Construction, Design and Feasibility of


High Rise Buildings," ProceedingsFirst National Structural
Engineering Conference, Melbourne, August 26-27, 1987.

2. Fisher, Martin; "Design Construction Integration Through


Constructibility Design Rules for the Preliminary Design
of Reinforced Concrete Structures," Ph. D Thesis, Stanford
University, 1991.

3. O'Connor, James T., Rusch, Stephen E., and Schulz,


Martin J.; "Constructibility Concepts for Engineering and
Procurement," Journal of Construction Engineering and
Management, ASCE, Vol 113, No.2, June 1987, pp 235-248.

4. Tatum, C. B.; "The Project Manager's Role in Integrating


Design and Construction," Project Management Journal,
Volume XVIII, No. 2. June, 1987a, 96-107.

5. Tatum, C. B., Vanegas, J. A., and Williams, J. M.;


"Constructibility Improvement During Conceptual Planning,"
Technical Report No. 290, Department of Civil Engineering,
Stanford University, November, 1985.

6. Reuss, Mark C., and Tatum, C.B.; "Requirements and Tools


for Transferring Construction Experience Between
Projects," Technical Report of the Center for Integrated
Facility Engineering, Stanford University, Jan. 1993.

7. "Constructability-It Works," Procter & Gamble, Inc.,


Cincinnati, Ohio, 1977, unpublished.

8. Ardery, Edward R., Editor & Committee on Construction


Mcmagement, ASCE; "Constructability and constructability
programs," White paper, Journal of Construction
Engineering and Management, v 1 '17, 1 Mar 1991, pp 67-89.

9. "Constructability, A Primer," Publication 3-3,


Construction Industry Institute, University of Texas at
Austin, Austin, TX. 1987.

10. Jaselskis, Edward J.; "Achieving construction project


success through predictive discrete choice models," Ph.D
Dissertation, University of Texas

518 McCullouch at Austin, 1988.

11. Jaselskis, Edward J., Ashley, David B.; "Optimal


allocation of project management resources for achieving
success," Journal of Construction Engineering and
Management, v117, 2 Jun 1991, pp 321-340.

THE COST OF DEFECTS IN

CONSTRUCTION

P-E. Josephson and Y. Hammarlund

Department of Building Economics and Construction

Management, Chalmers University of Technology, Gothenburg,

Sweden

Abstract

To perform rational defect prevention, it is necessary to


have knowledge about defects,

their causes and associated costs. The purpose of the


study presented here is to

stimulate improvements by indicating where preventive


measures are most effective,

and by indicating how to perform these measures. A study


of defects in construction was performed 1986-90. A new and
deeper study

is now being performed by the same research group. Seven


building projects are being

monitored during a 6 month-period each. Observers spend 8


hours a day at the site

analysing and describing defects occurring. A total of


approximately 3000 defects will

be collected and fully described, including their root


causes. Formal interviews with

approximately 100 key actors are being made. The


data-collection is still ongoing, and

thus the results presented here are preliminary.

Keywords: Building project, causes of defects,


consequences of defects, defect, defect
costs, origin of defects, quality.

Sommaire

Pour effectuer une prevention appropriee des defauts de


construction, il est necessaire

d'en avoir la connaissance ainsi que la connaissance de


leurs causes et des frais

provoques par ces defauts. Le but de l'etude ci-presentee,


c'est de stimuler les

ameliorations en indiquant les mesures de preventions les


plus efficaces et d'indiquer

comment prendre les mesures preventives. Une etude des


defauts de construction a ete realisee en 1986-90. Une
nouvelle

etude plus profonde est en trliine d'etre realisee par Ie


meme groupe de recherche.

Chaqu'un des sept projets de construction est surveille par


des moniteurs pendant une

periode de six mois. Les observateurs passent 8 heures par


jour sur place en anlysant

et en faisant une description des defauts qui se


produisent. Un total d'environ 3000

defauts sera collectionne et completement decrit aussi


bien que les circonstances qui

provoquent ces defauts. Des interviews minutieux avec 100


personnes, qui a ce sujet

sont tres importantes, sont en train d'etre realises.

Mots cles: projet de construction, cause des defauts, les


consequences des defauts,

defauts, frais de defaut, l'origine des defauts, qualite

The Organization and Management of Construction: Shaping


theory and practice (Volume Two).

Edited by D.A. Langford and A. Retik. Published in 1996 by


E & FN Spon. ISBN 0 419 22240 5.

520 Josephson and Hammarlund

1 Introduction

The conditions for construction are always changing. To


succeed, companies must

develop and improve continuously. Changes must be based on


knowledge of both the

environment and one's own work. In this situation knowledge


of the nature of defects

that have occurred is important. With such knowledge,


effective actions can be taken

to improve the process. In this paper, a study made in


seven construction companies is presented. The

nature of defects detected during production is discussed.


The study is performed in co-operation between the
Department of Building

Economics and Construction Management at Chalmers


University of Technology and

"R&D-West"; a group of construction companies in Sweden.


The study is a

continuation and deepening of a study carried out in


1986-90 by the same R&D-group.

1.1 Defect studies

There are a large number of studies of defect costs


occurring in the production and

maintenance phases. There are only a limited number of


studies about the briefing and

design phases. The cost of defects occurring during


production is stated to be 2-6% of the cost of

production [1] [2] [3] [4]. In our first study, the defect
cost in one building project was

approximately 6% of the production cost. The cost of


defects occurring during the
maintenance phase is stated to be 3-5% of the production
cost [5] [6] [7] [8]. The origin of defects occurring
during production is principally in production, but

also in design [4] [9] [10] [11] [12]. In our first study,
54% of the defect cost could be

ascribed to production; 34% to site management and 20% to


workmanship [4]. The

origin of defects occurring during maintenance is


principally in design, but also in

production [5] [6] [8] [13] [14]. A summary of a number of


defect studies is presented

in table 1. Organisations consist of individuals who


co-operate with a specific aim. Therefore,

it is natural for the defects to be ascribed to individuals


[4] [15] [16] [17]. It is

generally believed that defects are caused by lack of


knowledge, lack of information or

lack of motivation. Carelessness is stated to be the most


common cause [4] [11] [15]

[18]. Lack of knowledge is often mentioned as the second


most common cause of

defects, but information is also often mentioned. Although


defects are ascribed to

individuals, the basic cause can be found in organisational


phenomena.

2 Frame of reference

2.1 The roles

Building project organisations are temporary. When the


project is completed, the

organisation breaks up. Most actors only take part for a


limited time. Therefore, the

organisation is continuously changing during the process.


This study was performed to
find potentials for improvements in these organisations.
Some of the most important roles in a building project
organisation are played by

the client, designer, contractor, sub-contractor, material


supplier, machine supplier, and Cost of defects in
construction 521

Table 1. The origin of defects in a number of studies (% of


total defect cost)

Client

Design

Production

Material

Maintenance

Other During production During maintenance "R&D-West"


Summary of Summary of 1986-90 [4] several studies several
studies 3 5-15 0 20 15-30 40-55 54 35-55 20-45 20
5-20 5-15 o 0 5-10 3 0-15 0-10

the user. It is through the co-ordinated actions of these


actors that the building is

actually built. In similar ways, defects in the product or


in the process can be ascribed

either to the actors or to the co-ordination amongst them.

2.2 Defect a chain of events

All defects can be considered as a chain of events


including cause, erroneous action,

manifest defect, consequence and corrective measure, Fig. 1


[19]. This model of a

defect constitutes the basis for our study.

2.2.1 Cause

We define cause, in accordance with [20], as a proven


reason for the existence of a
defect. Often there are several causes of the same
erroneous action. There may be

either combined causes, or a chain of causes. For that


reason, the term "root cause" is

sometimes used to describe the most basic reason for an


undesirable condition. If the

root cause is eliminated or corrected, this will prevent


the reoccurrence of the defect

[21] [22]. The direct causes of defects can primarily be


attributed to individuals. However,

every action by an individual is influenced by conditions.


If individuals are to find it

worthwhile to act at all, motivation, expectations and


commitment are necessary [23].

Motivation is people's desire to contribute, through their


own actions, to the resultant

organisational action. Expectations imply that individuals


believe that their actions

will result in an organisational action. Commitment means


that in order to achieve

something together, people must have some "control" over


one another, i.e. they must

be able to rely on certain types of behaviour and certain


attitudes in the rest of the

team. This control is secured by the creation of mutual


commitment. Henceforth, we

use "motivation" to describe the sum of these three


conditions. Motivation alone is not enough. If an
individual is to act correctly, on the basis of

his/her own prerequisites, from their quality, the


individual must also have the

necessary knowledge and the necessary information for the


specific task. Knowledge

is information and understanding about a subject which a


person has in his or her mind

or which is shared by all human beings [24]. Knowledge


includes skill and experience.

Skill is the knowledge and ability that enables you to do


something such as ajob,

game, or sport very well [24]. Experience is knowledge or


skill of a particular job that

you have gained because you have worked at the job for a
long time [24]. Information

522 Josephson and Hammarlund Fig. 1. Principal model of a


defect

about the operation is received in communication between


individuals or between

organisations. Motivation, knowledge and information are


mutually dependent [19]. For instance,

insufficient information involves lower motivation. The


concepts of risk and stress are also used in the analysis
of causes. Calculated

risk is part of all actions, and thus it is difficult to


entirely avoid defects. The term

"risk" implies that there is a probability of a defect.


"Calculated risk" means a

conscious probability of defects. Higher calculated risk


means that a higher

probability of defects is accepted. Stress seems


characteristic for temporary organisations. Stress is the
general

reaction of an organism, which moves in to function when


the individual is threatened

[25].

2.2.2 Erroneous action and manifest defect

We distinguish between erroneous action and manifest


defect, i.e. the result of an
erroneous action. The manifest defect is a non-desired
condition in the product or

process. We start from [26], which defines defect as 'the


non-fulfilment of intended

usage requirements'. Some requirements are given by law


and in regulations, building standards, etc.,

and in contract documents, site meeting records and other


project documentation. But

all requirements cannot be specified. Every individual also


has non-expressed basic

needs. There are also many details which are difficult to


specify. These demands are

referred to as "usage" requirements. Sometimes the


specified requirements are wrong.

In such cases we rely on opinions from the actual


organisation. Non-fulfilment of

these opinions gives rise to defects. The changes which


are made because of new or changed needs during production
or

use phase are not seen as defects.

2.2.3 Consequences and corrective measures

By "consequence", we mean all consequences of a manifest


defect, including

consequences for both the product and the process. By


"corrective measure", we mean

all actions performed with a view to completely or partly


remedying manifest defects,

and their consequences. The extent of consequences and


corrective measures taken

constitutes the defect cost.

3 The method

The method used is based on our study performed in


1986-1990 [4]. The method has
been modified to a minor extent. The organisation of the
study, i.e. the group of

companies and the research group, are the same as in the


first study. Cost of defects in construction 523

3.1 The building projects

In this study, six projects are being followed up during a


six-month period each, one

project is followed up for four months. The seven projects


are being performed by

different companies. The projects has been chosen with the


intention of acquiring

knowledge about different types of projects. Some


characteristics are presented in

table 2.

• Project A is a conversion of an older museum, and a


technically complicated new construction of an entrance.
It has a complicated client organisation, including
several authorities to consult, severe saving demands,
small spaces. For reasons of financing, the time of
production was cut down from 17 to 12 months.

• Project B mainly concerns a new construction of an upper


secondary school. For part of the building, the framework
of an old fire station is used. The school personnel was
not employed when the construction work started. There was
specific demands for an allergy-free school. This is a
complex building because of the many different methods
and materials used.

• Project C is a new construction of university building.


The building is of high technical standard, especially the
ventilation. The time of production was shortened from
20 to 16 months at a very late stage. The project
organisation consists of companies and individuals who
have worked together before.

• Project D concerns a new construction of two similar


multi-dwelling blocks, which are similar to two 5-year old
blocks in the same area. The total price has been forced
down because the contract is part of a larger contract.
The production work is strongly influenced by a large
development program in the company. The site is exposed to
hard winds.

• Project E is conversion of an industry, with a very short


production time. A lot of work activities are ongoing at
the same time. Periodically, there are lot of workers in
small spaces. The building includes a lot of
installations. Except for these characteristics, it is
quite a simple construction.

• Project F concerns a new construction of a fire station.


Part of the building includes a lot of installations. For
this, the authorities have high security requirements.
Major user influence during production.

• Project G is a conversion of several shops in a large


shopping center. Quite a divided site with a lot to be
taken into consideration because the shops are open during
production.

Table 2. The building projects

Project Type New constr. Type of Production cost Time


or conversion contract (SEKM) (months)

A Museum New/Conv. General c. 30 12

B School New General c. 130 l3

C University New Turnkey c. 100 16

D Housing New Turnkey c. 21 14

E Industry Conversion General c. 15 4

F Fire station New Turnkey c. 55 15

G Shopping centre Conversion General c. 30 l3

524 Josephson and Hammarlund

3.2 Data collection

One starting-point is to register and analyse all defects


occurring in the building

projects during a six-month period. One observer is placed


at each site. The observer

has no other task than to register, follow-up and describe


defects occurring. By making rounds on site, the observer
has daily contact with all the personnel,

both the building contractor's personnel as well as the


sub-contractor's. When

necessary, the observer contacts the client, designers,


material manufacturers, etc. He

takes part in meetings and reads all documentation. Each


observer has been educated in the method and introduced at
the site. During

the study the observer and the researchers have continuous


contact. At special

meetings, the observers compare notes. The observers are


engineers or civil engineers. They have between 0 and 30
years

of experience from construction. Our first study showed


that young people with only a

little experience of construction are the most successful


in the data collection. People

with more experience tend to perceive some situations as


normal and for that reason

fail to describe them as defects. The data collection


consists of three main parts:

• Defect descriptions. Each defect is described on a


special form. Approximately 20 questions are coded. They
are supplemented with detailed descriptions of causes,
erroneous action, manifest defect, consequences and
corrective measures. The defect cost is estimated.
Sketches, drawings and photographs are appended. A total
of approximately 3000 defects are registered. Some of them
consists of several similar defects.

• Project description. To enable analyse, each building


project is fully described. Among other things, the
project organisation and the site organisation changes
during the process, systems for leading, planning methods,
policies regarding choice of sub-contractors, etc.,
activities included and their dependence, are described.
Schedules, drawings, site meeting records and diary are
appended. Costs and times for the whole project and for
separate physical elements, activities and materials are
stated.

• Interviews. In each project, the research group


interviews 10-15 key actors. Each interview is
approximately 1 hour. The interviews are tape-recorded and
transcribed in full afterwards. During the interviews,
mainly the characteristics of the building project are
discussed.

4 Results

The study will be completed in June 1996. The data


collection is still ongoing, why

the following results are preliminary.

4.1 Number of defects and defect cost

The number of defect descriptions varies between 283 and


450 per project. Some

descriptions contains several similar defects, so that the


real number of defects is

higher. The defect costs varies between 2.2 and 9.0 % of


the production cost, arising

during the time of the study, see table 3. Cost of


defects in construction 525

Table 3. Number of defects and defect cost (as of August


1995)

Project Number of defects Defect cost (number) (SEK) (%


of prod. cost) A 450 750000 4.6 B 422 980000 3.1 C 360
560 000 2.2 D 300 1 800000 9.0 E 283 820 000 5.9 F 373
470000 G 475 710000

Among noteworthy conditions, the following can be mentioned:

• In project A, the time for a complex blasting was gravely


underestimated, so the whole project was delayed. Severe
savings demands involved several changes in the production
method. The complicated organisation involved a lot of
last-minute instructions from the client.

• In project B, the contractor received extra orders for


SEK 4 M. One reason was that no school personnel was
employed when the production started. Only a few of these
extra orders have been registered as defects.
• Project C was successful according to several actors. The
largest defect was a part of the ventilation pipes, which
fell down.

• In project D, the total price was overdrawn. Many extra


tasks were imposed on both the site managers and the
worker, and the situation was stressful. The project was
exposed to a lot of disturbances because of the weather,
however these have not been registered as defects. There
were also problems with deliveries of prefabricated
concrete elements.

• In project E, a lot of problems arose because the project


was an intensive one, with a lot of workers in small
spaces. Several workers described the project as 'messy'.
The main defect was a delayed elevator contract.

• In project F, there have been some late changes because


of the user's influence during production. The design
process was described as faulty. The inexperienced
manager of the design process felt that he should have
directed the process more firmly.

• Project G was described as 'messy' because of the


fragmented site and the adaptations of the production
work to the opened shops. A lot of customers to the shops
had to cross the site. The contractor received a lot of
extra orders from the shops, which involved delays in the
contract.

4.2 The origin of defects

The preliminary analysis indicates that on the average 32%


of the defect costs

originated in the early phases, i.e. in relation to the


client and the design.

Approximately 50% of the defect cost originated on the


site, i.e. in relation to the site

management, the workers and the sub-contractors.


Approximately 15% of the defect

cost originated in materials or machines, see table 4. In


four projects, defects attributed to sub-contractors were
largest. Design defects

dominate in two projects. In project D, material defects


are the main defects. In this

526 Josephson and Hammarlund

Table 4. The origin of defects (% of defect cost, as of


August 1995)

Project Client Design Site maWorkSub-conMateMachiOther


nagem. manship tractors rials nes A 10 14 23 7 32 9 5
1 B 5 49 6 11 14 14 1 0 C 10 32 5 6 38 9 0 D 4
18 24 18 7 25 2 1 E 8 11 2 2 66 4 6 F 1 48 12 15
6 4 10 5 G 4 12 14 6 36 6 5 16

Average 6 26 12 9 28 10 4 4

project there are large problems with prefabricated


concrete elements. Project E is

dominated by the delayed elevator contract.

4.3 The causes of defects

The causes were often difficult to identify, which means


that our results should be

extrapolated from with caution. In most situations, we


found that the individual who

gave rise to a defect had the necessary knowledge and right


information for the specific

task, but that the cause was lack of motivation. An


average of 40% of the defect cost

could be ascribed to this category, see table 5. A deeper


analysis indicates that most

'motivation defects' are forgetfulness or carelessness.


Only a few of the 'motivation

defects' were intentional. 32% of the defect cost was


caused by lack of knowledge,

while a small part was ascribed to lack of communication,


stress and risk.

4.4 Causes per actor

An analysis of causes for each actor has been made. Table 6


presents the average for
projects A-E. For design defects, 30-35% Qf the defect
cost was found to be caused

by lack of knowledge, information and motivation,


respectively. For defects in site

management, the picture is more fragmented. Stress and risk


have also been identified

as causes. For defects in workmanship motivation dominated,


but risk is also

identified as a cause. For the sub-contractors, 40% of the


defect cost was found to be

caused by knowledge and motivation, respectively.

Table 5. The causes of defects (% of the defect cost, as


of August 1995)

Project KnowInformaMotivaStress Risk ledge tion tion A


47 11 32 0 9 B 5 25 44 7 19 C 40 26 31 0 3 D 50 5
39 3 3 E 20 29 33 14 4 F 43 6 44 5 G 17 10 66 1 6

Average 32 16 41 4 7 Cost of defects in construction 527

Table 6. Causes of defects for each category of actors, %


of defect cost per actor

respectively (as of August 1995)

Actor Know

Design

Site management

Workmanship

Subcontractors

5 Conclusions ledge 37 27 5 38 Information 27 23 4


13 Motivation 32 31 59 36 Stress 3 10 5 1 Risk
1 9 27 13

The aim of the study is, through increasing the knowledge


of defect causes, to find

motivation for improvement of the building process. We


have only pointed out some

objective results in this paper. However, in the full


study, we intend to obtain a deeper

understanding by making comparisons with our first study,


and by analysing the

defects. The method for the study has been chosen with the
intention of collecting a variety

of information about defects occurring, with a view to


producing improvements. Such

improvements can be made using one of three strategies: (1)


elimination of defect

causes by preventive actions, (2) confining defect


consequences by early detection

through inspection, and (3) avoidance of repetition of the


defects by learning from

defects that have already occurred [19]. These strategies


must be borne in mind in

further analyses.

7. STATT, Rationellt byggande metoder, hjiilpmedel och


maskiner, "Utlandsrapport" from the Swedish Attache of
Technology, STATT 8906,1989.

8. Pinter, J., Quality and regulation by the analysis of


building failures and it's costs, Working paper W86/5/9
of crn W86, Oct. 1989.

528 Josephson and Hammarlund 9. Herbert, A, Martvall, K.,


and Wirdenius, H., Byggarbetsledning och
produktionsstiirningar, The Swedish Council for Building
Research, Report 36: 1969, Stockholm, 1969.

10. Kullstedt, M., and Wirdenius, H., Arbetsledning pl1


bygget 341 platschefers mOte med storningar i
produktionen, Report R2: 1976, The Swedish Council for
Building Research, Stockholm, 1976.

11. Bonshor, RB., and Harrison, H.W., Quality in


traditional housing, Vol 1 : an Investigation into faults
and their avoidance, Department of the Environment,
Building Research Establishment, London, 1982.
12. ByggnadsinspektOrerna, Sunda hus och kommunal tillsyn,
Sammanstallning av enkatsvar fdm ca 100
byggnadsinspektOrer, Internal survey, 1990.

13. CSTC (Reygaerts, J., Gasper, M., and Dufordoir, C.),


1200 problemes, CSTC Revue nr 3, 1976.

14. Matousek, M., Outcomings of a Survey on 800


Construction Failures, IABSE Colloquium on Inspection and
Quality Control, Cambridge, England, July 1977.

15. Matousek, M., A System for a Detailed Analysis of


Structural Failures, in Yao, J.T.P., Corotis, R, Brown,
C.B. and Moses, P. (ed.), Structural Safety Studies,
Proceedings, 3rd International Conference on Structural
Safety and Reliability, American Society of Civil
Engineers, Denver, Colorado, 1985.

16. Nowak, AS., Human Errors in Structures, Offshore


Mechanics and Arctic Engineer, 11th international
conference, Vol. II, s 335-341, Calgary, Canada, June
1992.

17. CIB, Building Pathology A State-of-the-Art Report, CIB


Report, Publication 155,1993.

18. NEDO (National Economic Development Office), Achieving


Quality on Building Sites, Building Economic Development
Committee, London, 1987.

19. Josephson, P.-E., Orsaker tillfel i byggandet en studie


omfelorsaker, felkonsekvenser, samt hinder for inliirning i
byggprojekt, Dissertation, Report 40, Department of
Building Economics and Construction Management, Chalmers
University of Technology, Gothenburg, 1994.

20. Gryna, P.M., Quality Improvement, in Juran, J.M., and


Gryna, P.M., luran's Quality Control Handbook, 4th
edition, McGraw-Hill, 1988.

21. Dew, J.R, In Search of the Root Cause, Quality


Progress, March 1991.

22. Wilson, P.F., Dell, L.D., and Anderson, G.P., Root


Cause Analysis: A Toolfor Total Quality Management, ASQC
Quality Press, ASQC, Milwaukee, Wisconsin, USA, 1993.

23. Brunsson, N., The Irrational Organisation, John Wiley


& Sons, Chichester, 1985.
24. Collins Cobuild English Language Dictionary,
HarperCollins Publishers, London, 1987.

25. SOderberg, S., Psykologi och arbetsorganisation,


LiberLaromedel, Malmo, 1979.

26. SS-ISO Svensk Standard, SS 020104, Kvalitet


Terrninologi, SIS Standardiseringskommissionen i Sverige,
1987.

GROUP DECISION SUPPORT FOR

VALUE MANAGEMENT

S.D. Green and S.J. Simister

Department of Construction Management and Engineering,

University of Reading, Reading, UK

Abstract

This paper outlines a revised theoretical framework for


value management based on

the principles of group decision support (GDS). In contrast


to the currently dominant

paradigm of value management, the concept of GDS is based


on an underlying

ontological position of social constructivism. It is


contended that the existing

positivist paradigm is only applicable to well-defined


technical problems which can

be specified in advance. GDS differs in that it recognises


that the problems which

characterise the early stages of building design often


defy any attempt at pre

definition. The articulation of the GDS paradigm is seen


to have important

implications for the discipline of building economics. It


is asserted that building
economists have traditionally failed to provide clients
with effective group decision

support as a result of their reluctance to leave the


sanctuary of the rational high

ground. The paper identifies three GDS methodologies which


are currently untested

for the purposes of value management within the context of


building design. An

ongoing research project is described which seeks to


propagate the use of GDS

methodologies in practice. The research is not concerned


with revealing 'objective

truths', but with establishing the GDS paradigm by means


of a dialectic debate with

practitioners. The validity of the adopted methodology must


therefore be judged in

accordance with the principles of naturalistic inquiry.


Preliminary results are

encouraging in that the research has already achieved


changes in the way that value

management is implemented in the UK construction industry.

Keywords: Group decision support, value management,


briefing, building economics,

methodology.

The Organization and Management of Construction: Shaping


theory and practice (Volume Two).

Edited by D.A. Langford and A. Retik. Published in 1996 by


E & FN Spon. ISBN 0 419 22240 5.

530 Green and Simister

Sommaire

Cet article expose brievement une structure theorique


revisee pour Ie management de
la valeur, basee sur les principes du soutien d'un groupe
de decision (ODS).

Contrastant avec Ie paradigme dominent actuellement du


mangement de la valeur, Ie

concept du ODS est base sur une position ontologique


sous-jacente de constructivisme

social. II est clair que Ie paradigme positiviste existant


est seulement applicable a des

problemes techniques bien definis, qui puissant etre


prealablement specifies. ODS

difrere en ce qu'il reconnait que les problemes qui


caracterisent les premiers stades

de la construction defient sou vent toute tentative de


pre-definition. L'articulation du

paradigme ODS est consideree pour avoir d'importantes


implications dans la discipline

des aspects economiques du b1l.timent il est certain que


les economistes du b1l.timent

ont traditionnellment echoue a fournir aux clients Ie


soutien d'un groupe de decision

efficace, en consequence de leur reticence a quitter Ie


refuge de la position surelevee

rationnelle. L'article identifie tres methodologies ODS,


qui sont actuellement non

verifiees dans l' optique du management de la valeur, dans


Ie contexte de la conception

du b1l.timent. Un project continuel de recherche est decrit


qui vise a propager l'usage

des methodologies ODS dans la practique. La recherche ne


vise pas a reveler des

"verites objectives" mais a etablir Ie paradigme ODs au


moyen d'un debat dialectique

avec les praticiens. La validite de la methodologie adoptee


doit, par consequent, etre
jugee selon les principes de la "naturalistic inquiry". Les
resultats preliminaires sont

encouageants en ce que la recherche a deja produit des


changements dans la maniere

dont Ie management de la valeur est applique dans


l'industrie de la construction.

1 Introduction

The concept of value management is attracting an increasing


amount of interest from

construction clients. The sustained level of demand for


value management suggests

that it does indeed constitute a service which is distinct


from the more traditional

approaches to achieving value-for-money. Despite this wide


extent of interest, the

underlying theory of value management remains strangely


underdeveloped. Many

academics continue to perceive value management to be


something of a 'black art'.

The paper draws from an ongoing research project which


seeks to develop a valid

theoretical framework for value management. The research


differs from previous

work in the field of value management in that the guiding


theory is derived from the

concept of group decision support (ODS), as recently


developed within the emerging

paradigm of soft operational research. The theoretical


justification for ODS is initially

established and contrasted with the assumptions which


underpin the dominant

paradigm of building economics. The adopted research


methodology is then described
for establishing the alternative ODS paradigm within value
management practice.

Finally, a summary overview of the research results to


date is presented.

2 Group decision support

Whilst many definitions of ODS have been offered, the


following is the most pertinent

for the purposes of this paper: Group decision support for


value management 531 , .... any designed process that
supports a group of people seeking individually to make
sense of, and collectively act in a situation in which
they have power' [1]. The key element of the above
definition is the explicit recognition that individuals
will make sense of situations in different ways, and yet
invariably need to act in a collective manner. The
tendency of individuals to interpret problems in different
ways is central to Rittel and Webber's [2]
long-established concept of 'wicked' problems. By
definition, a wicked problem is multi-perspective in nature
and defies any attempt at pre-definition. In contrast,
previous approaches to value management [3]-[6] accord

with the unitary paradigm of hard operational research.


These approaches invariably

assume that problems are 'tame' in that they can be


specified in advance of any

analysis and that they then remain unchanged throughout the


analysis. The same

assumptions also underlie the techniques of building


economics [7]. It is taken for

granted that the decision-maker's objectives can be


pre-determined and effective

decision support can be provided by the single-criterion


decision models of investment

appraisal. Where multiple objectives are recognised, it is


assumed that they can be

collapsed into a single 'utility' rating. The ontological


position which lies behind such
approaches is one of naive positivism. It is presumed that
the best answer exists 'out

there' and is waiting to be identified. Whilst the


impossibility of identifying , optimal

solutions' is generally recognised within the building


economics community, the

alternative concept of bounded rationality [8] is still


reflective of an underlying

POSItIvIsm. To recognise that rational humans must act in


accordance with the

limitations of their processing capacity does not in


itself deny the theoretical existence

of an optimal solution. The concept of GDS, as developed


within the pluralistic paradigm of soft

operational research, reflects an underlying ontological


position of social

constructivism. In contrast to the paradigm of hard


operational research it is no longer

assumed that problems can be modelled in isolation from the


problem owners [9].

'Reality' is now seen to be a social construct which is


continually renegotiated, rather

than an underlying truth which exists 'out there'. GDS


therefore makes no pretence

at revealing an underlying 'right' answer, the emphasis


lies in building a shared

understanding and common commitment amongst the


problem-owners. The

interpretation of value management as a designed process


for achieving GDS also

requires a reinterpretation of 'value-for-money'. Within


the guiding paradigm of

GDS, value-for-money is no longer seen to lie in the


content of the decision, but in

the means by which the decision is reached. In comparison


to the unitary paradigm

of decision-support, GDS therefore places less emphasis on


substantive data and more

emphasis on consensus building and the decision-making


process. The constructivist

equivalent to 'objectivity' is inter-subjective agreement


[10, 11]. As a caveat to the preceding argument it is
necessary to emphasise that the

ontological position of social constructivism does not


deny the existence of' objective'

data, it merely differentiates between data and the


meanings which different

individuals ascribe to that data. There is therefore an


important difference between

inter-subjective agreement on the basis of carefully


collected data, and inter-subjective

agreement on the basis of supposition. The acceptance of


an ontological position of

social constructivism does not therefore rule out the use


of positivist research methods

532 Green and Simister

where deemed appropriate. However, GDS also recognises that


problems can rarely

be represented in terms of facts and logic alone. Of equal


importance will be the

myths and meanings by means a/which human beings make sense


a/their world [12].

Further justification for the adopted theoretical position,


together with a more extended

critique of established approaches to value management,


can be found in Green [13]
[15] and Green and Simister [16].

3 Decision-making groups

GDS methodologies are ideally suited for situations where


groups of individuals make

decisions. The notion of a decision-making group implies


that the individuals within

the group have a considerable degree of autonomy in their


own actions. If a group is

characterised by subordinate-superordinate relationships


then it would not qualify as

a decision-making group. Decisions made by an individual


in consultation with others

does not constitute group decision making. Genuine


decision-making groups comprise

individuals who have their own interests and perspectives,


which lead them to pursue

different objectives and to identify different factors as


relevant. Such groups possess

a high potential for conflict and also face high levels of


uncertainty. In these

conditions, problems which can be pre-defined and which


remain static over time will

be few and far between. There is therefore a confusion


between cause and effect

when considering decision-making groups and wicked


problems. Many 'wicked'

problems become relatively tame when perceived by a single


executive decision

maker. The extent to which problems can be perceived to be


wicked or tame

therefore depends, at least in part, on the distribution


of power amongst the

stakeholders. The nature of the relationships amongst a


group of decision-makers has

important implications for the appropriateness of different


decision-support paradigms.

The following characterisations, derived from Flood and


Jackson [17], are useful in

developing the argument:

• Unitary: stakeholders share common interests and


objectives.

• Pluralistic: stakeholders possess different


interpretations of the problem and in consequence,
different objectives. Nevertheless they are prepared to
come to an accommodation due to a basic compatibility of
interest.

• Coercive: stakeholders do not agree upon objectives and


genuine compromise is not possible. Influence is brought
to bear by the more powerful in order to coerce others to
accept decisions.

The traditional paradigm of hard operational research


assumes that all problem

situations are unitary. In contrast, the soft methodologies


of GDS assume a pluralistic

context together with an underlying willingness to come to


an accommodation. The

absence of any such underlying willingness constitutes a


coercive context, thereby

rendering many ODS methodologies inappropriate. When faced


with coercive

contexts any methodology for decision support will


inevitably be manipulated in

support of the dominant power group. It is therefore


apparent that the applicability

of GDS methodologies is dependent upon the extent to which


the decision context is

pluralistic. Group decision support for value management


533
4 Relevance of group decision support to client briefing

The tendency of many building clients to be pluralistic is


well recognised in the

briefing literature. Cherns and Bryant [18] contend that


clients are often multi-faceted

in nature, comprising several different interest groups


whose objectives differ, and

may well be in conflict. Becker [19], Goodacre et al [20]


and Murray et al [21] have

all questioned the assumption that a client's objectives


can be pre-determined. The

processes of briefing and designing are seen to be


iterative and interdependent,

whereby an understanding of the client's requirements


emerges as a result of a

dialectic debate which takes place over a period of time.


The process is one by which

a group of, often disparate, individuals come together to


formulate a single, coherent

statement of requirements. Within the context of the


preceding discussion of GDS the

following quote is especially illuminating: '{bJuilding


design is a problem solving process which cannot always be
stated comprehensively at the outset because of the many
different interests which have to be satisfied. In many
cases each problem is 'owned' by a group of people, each
with varying requirements and ambitions for its solution'
[22].

Further evidence that the early stages of building design


are characterised by 'wicked'

problems is provided by Powell [23], Lawson [24] and Rowe


[25]. There is therefore

a considerable body of opinion which suggests that the


problem context which occurs
during the briefing stage is often pluralistic. In these
situations the 'hard' paradigm

of traditional value engineering, as underpinned by an


ontological position of

positivism, is clearly invalid. Any attempt to model the


'real problem' in isolation of

the interpretations of the project stakeholders would be


doomed to failure. Of course,

the early stages of building projects are not always


pluralistic. In those situations

where the client acts as a single decision-maker and the


objectives can be pre

determined, the unitary paradigm of decision-support is


directly relevant. This is well

evidenced by the successful application of value


engineering by the speculative

developer clients of the 1980s [26]. Within this context


alternative design solutions

could be generated and appraised in accordance with their


impact on (i) construction

cost, (ii) construction time, (iii) investment value. In


the final analysis all of these

could be accounted for in financial terms. The 'alternative


designs solutions' often

comprised the use of innovative technology which reduced


the cost of construction.

The underlying ontological position of positivism was


justified in that the alternative

technical solutions did indeed exist' out there', but had


not been previously identified.

Nevertheless, unitary contexts of this nature are the


exception rather than the general

rule. This is especially the case in the 1990s when


building clients tend to be owner
occupiers rather than speculative developers. Buildings are
therefore increasingly

designed to cater for the needs of bespoke multi-faceted


clients, rather than for

standardised institutional requirements. Within this


context, it would be meaningless

to suppose that value-for-money could be modelled in


isolation from the differing

aspirations of the client's key stakeholders. 534 Green


and Simister 5 Group decision support in the 'swamp' In
the light of the preceding discussion it is enlightening to
consider the extent to which building economics has
offered effective decision-support to pluralistic clients.
It is initially worthwhile building on the previously
described distinction between problem types by quoting
SchOn [27], who has graphically contrasted the 'rational
high ground' with the 'swamp': '{i]n the swampy lowland,
messy, confusing problems defy technical solution. The
irony of this situation is that the problems of the high
ground tend to be relatively unimportant to individuals or
society at large, however great their technical interest
may be, while in the swamp lie the problems of greatest
human concern. The practitioner must choose. Shall he
remain on the high ground where he can solve relatively
unimportant problems according to prevailing standards of
rigor, or shall he descend to the swamp of important
problems and non-rigorous inquiry?'.

Whilst the authors would take issue with the 'non-rigorous


inquiry', the above

quotation depicts the dilemma for those who wish to


provide building clients with

decision support. The tendency of building economists to


keep out of the swamp is

well illustrated by Ruegg and Marshall [7]:


'{oJptimisation is sometimes used to describe the process
of determining the most desired choice where noneconomic
and sometimes nonquantifiable benefits and costs are
included in the objective function ...... We focus in this
book on the more narrow definition of the term, and all
our examples involve benefits and costs that are
measurable in monetary terms'.
There would therefore appear to be little danger of Ruegg
and Marshall descending

from their rational high ground to help clients with the


messy problems of the swamp.

Their refusal to consider 'nonquantifiable benefits' could


hardly be more stark. A

similar position is also adopted by Ferry and Brandon [28]:


'[iJt is not usually the economist's responsibility to
actually provide "value" as this must be the province of
the team as a whole, of which, however, he should be a
contributing member'.

Whilst Ferry and Brandon clearly recognise that the


building economist cannot provide

'value' by working alone on the rational high ground, they


fail to offer clients any real

guidance, other than the comment that: '{ijn theory, the


team will pool their combined knowledge for the benefit of
the client, whose representative should wherever possible
be a member of the team and play his own part in the
corporate decision-making process.'

The reference to the client's 'representative' in the


singular is in itself indicative of

a naive understanding of building clients. It is further


notable that those economists Group decision support for
value management 535 [29]-[32] who have attempted to
address the issue of value in its wider sense have done so
from within the paradigm of hard operational research.
Needless to say, they have never really progressed beyond
Simon's [8] position of satisficing. It should also be
recognised that there have been a few dissenting voices
from within the building economics community. Specific
examples include Canak et al [33], Eastman and Penz [34],
Tucker [35] and more recently, Gray and Tippett [36].
Nevertheless, as notable as these dissenting contributions
are, they have not as yet constituted a serious challenge
to the still dominant paradigm of rational-positivism.

6 Potentially suitable GDS methodologies

An extensive review of the existing literature on GDS has


identified several
methodologies as being potentially useful for the purposes
of value management. The

following three have been singled out for particular


consideration:

• Soft Systems Methodology [37]

• Strategic Choice [38]

• Strategic Options Development and Analysis [39]

The above approaches have all been developed within the


paradigm of soft operational

research and are considered to be particularly suitable for


the purposes of structuring

problem situations which are distinguished by complexity,


uncertainty and conflict [9].

They would therefore appear to be directly applicable to


the early stages of building

design. For comparison purposes, the decision conferencing


strategy of SMART value

management will also be considered [13]. Within the


constraints of this paper, it is

not feasible to describe the identified methodologies in


any detail. A full appreciation

of their richness can only be achieved by reference to the


source literature.

Nevertheless, it is worthwhile offering a brief comment on


the intellectual origins of

these approaches. Soft systems methodology (SSM) has


evolved from 'hard' systems

engineering as a result of a 20-year programme of action


research at Lancaster

University [40]. Strategic choice is rooted in the


socio-technical approach pioneered

by the Tavistock Institute in the 1970s [41]. Given the


dominance of the rational

positivist paradigm within building economics, it is


interesting to note that some of

this early work was directed towards improving


communication in the building

industry [42]. The origins of strategic options


development and analysis (SODA) lie

within cognitive psychology and the early political models


of organisations [39].

Despite their disparate origins, all three methodologies


share an explicit epistemology

of social constructivism, thereby accepting the


multi-perspective nature of reality.

They also all recognise the importance of a skilled


facilitator and the interdependence

between decision content and decision process. In contrast


to hard operational

research, the various models upon which the methodologies


are based are seen to be

facilitative devices rather than representations of


'reality'. 536 Green and Simister 7 Research methodology
In the light of the researchers' previous success in the
development and application of SMART value management [13,
43] through action research, it was decided to adopt a
similar approach for the current research project. However,
past experience has demonstrated that there are a number
of practical and methodological problems with an action
research approach which relies solely on exploratory case
studies in real situations. One of the major difficulties
lies in securing consultancy commissions which correspond
to the timescale of the research project. Even if such
commissions

are forthcoming, there can be no guarantee that the


situations presented would be

suitable for the above methodologies. A further limitation


relates to the extent to

which the results achieved by the research team could be


replicated by other

practitioners. It was therefore decided to adopt a


methodology based upon exploratory

case studies carried out in a 'laboratory setting'. This


has been achieved by inviting

a range of experienced clients and value management


practitioners to participate in a

series of six simulated exercises using data based on past


construction projects. It is,

of course, impossible to simulate the richness of a real


project in a laboratory setting.

However, this does allow for a greater emphasis to be


given to the methodologies

themselves, rather than being distracted by issues of


content. Given the objective to

improve the practice of value management, it is also


arguably more valuable to

ascertain the credibility of the methodologies to a


selected group of influential

practitioners, in the hope that they would go on to apply


them in real situations. The

collection of long-term feedback from the participants


therefore constitutes an

important part of the research [44]. Given the purpose of


ascertaining whether or not GDS methodologies are

considered to be credible and usable by practitioners,


together with the

epistemological basis of GDS, it would clearly have been


inconsistent to have adopted

a positivist research methodology. The validity of the


adopted methodology, and of

the results obtained to date, must therefore be judged in


accordance with the principles
of naturalistic inquiry [10, 11, 45]. In addition to
ascertaining the extent to which the three GDS
methodologies are

seen to be credible and usable, it has also been necessary


to expose the research

participants to the underlying theory. In particular,


feedback was invited on the

critique of the established approach to value management


and the contention that its

success is dependent upon the problem context being


unitary. Participants were also

asked to comment on how useful they considered it to be to


distinguish between

unitary, pluralistic and coercive situations. Further


qualitative data was realised by

asking them to discuss six case study scenarios with


reference to the three identified

decision contexts.

8 Research results

At the time of writing three one-day expert seminars have


been conducted to ascertain

the credibility and perceived usefulness of the proposed


methodologies. Two of the

seminars involved twenty-two value management practItIOners


and client

representatives, and the other involved ten. The first


seminar focused on the extent Group decision support for
value management 537 to which the principles of ODS are
appropriate to value management studies. The second and
third seminars emphasised the potential use of Checkland's
soft systems methodology (SSM). Further seminars
addressing the remaining ODS methodologies are planned
to take place during 1996. The research has also included
an ongoing dialogue with the practitioners in between the
seminars. A full exposition of the qualitative results
obtained to date would require detailed descriptions of
the simulated case studies together with an analysis of the
observed process issues. It is also considered
inappropriate to present quantitative results in

isolation from the context from which they were derived. A


grounded description of

the results obtained to date must therefore be left for a


future publication.

Nevertheless, it is reasonable to present some summary


observations relating to issues

which have become apparent. It has become clear that there


is some recognition within the value management

community of the need for new ideas together with more


theoretically coherent

methodologies. This is evidenced by their willingness to


participate in the research

seminars. It is also notable that the proposal to match


different methodologies to

different problem situations finds an intuitive acceptance


amongst practitioners.

However, they display a stubborn resistance to the notion


that 'problem situations' can

ever be classified in any prescriptive way, thus


reinforcing the theoretical argument

that any such attempt would be epistemologically


inconsistent. The expected

resistance to the terminology of SSM has been confirmed,


as has the tendency of

practitioners to collect different 'techniques' rather than


to 'buy in' at the methodology

level. Nevertheless, their initial exposure to SSM has


stimulated a demand for further

training, thereby demonstrating that the methodology is


indeed seen to be a potentially

useful aid to client briefing. The one technique of SSM


which has gained a ready
acceptance is that of drawing 'rich pictures' in order to
make sense of complex

problem situations. Indeed, three of the participating


practitioners have already used

the rich picture approach in real situations on the basis


of their participation in the

first seminar. The acceptance of this technique is


underpinned by a recognition of the

limitations of existing value management techniques for


the purposes of 'sense

making'. Whilst the above discussion of the research


results has by necessity been somewhat

superficial, there is one observation which positivist


critics cannot dismiss lightly: the

research project has already had a direct impact on the


practice of value

management. Several influential practitioners now perceive


value management in a

different way than they did previously. The process of


debate between the researchers

and selected practitioners has also established the


credibility of ODS as a guiding

framework for the continued development of value


management. Future research will

monitor the extent to which these selected practitioners


will act as agents of change

in propagating further the guiding principles of the ODS


paradigm.

9 Conclusion

This paper has developed a theoretical framework for value


management based on the

concept of group decision support (ODS). ODS differs from


the existing theoretical
basis of value management in that it is grounded on an
ontological position of social

538 Green and Simister

constructivism. The nature of decision-making groups has


been considered and a

distinction has been made between unitary, pluralistic and


coercive situations. The

concept of GDS has been seen to be especially appropriate


for the pluralistic decision

contexts which often dominate during the early stages of


design. It has been further argued that the concept of GDS
enables value management to

leave the 'rational high ground' in order to provide


decision support in the 'swamp'.

It has been the continued reluctance of building economists


to deal with the intangible

aspects of value which has caused the increasingly large


demand for value

management. A range of GDS methodologies has been


identified which enables value

management practitioners to match different approaches to


different situations. Whilst the research described in
this paper is by no means complete, it has already

had an impact on the practice of value management in the


UK construction industry.

The research is also much more ambitious than the majority


of positivist approaches

in that it seeks to change the dominant paradigm of value


management practice. It

is contended that the continued propagation of the GDS


paradigm will have a

significant effect on the future development of value


management and the way in
which the industry perceives value-for-money.

10 Acknowledgement

This paper is derived from an ongoing research project


entitled 'Group Decision

Support for Value Management'. The project is funded by the


UK Engineering and

Physical Sciences Research Council (EPSRC) whose support


is gratefully

acknowledged.

1. Bryant, J. (1993) Supporting management teams. OR


Insight, Vol. 6, No.3, pp. 19-27.

2. Rittel, H. W. J. and Webber, M. M. (1972) Dilemmas in a


General Theory of Planning, Working Paper No. 194,
Institute of Urban and Regional Development, University
of California, Berkeley.

3. Miles, L. D. (1972) Techniques of Value Analysis and


Engineering, 2nd edn., McGraw-Hill, New York.

4. Dell'Isola, A. J. (1982) Value Engineering in the


Construction Industry, 3rd edn. Van Nostrand Reinhold, New
York.

5. Kelly, J. and Male, S. (1993) Value Management in


Design and Construction, E & FN Spon, London.

6. Norton, B. R. and McElligott, W. C. (1995) Value


Management in Construction: a Practical Guide, MacMillan,
Basingstoke.

7. Ruegg, R. T. and Marshall, H. E. (1990) Building


Economics: Theory and Practice, Van Nostrand Reinhold,
New York.

8. Simon H. A. (1957) Administrative Behaviour, 2nd edn.,


MacMillan, New York. Group decision support for value
management 539 9. Rosenhead, J. (1989) Introduction: old
and new paradigms of analysis, in Rational Analysis for a
Problematic World (ed. J. Rosenhead), John Wiley,
Chichester, pp. 1-20.

10. Lincoln, Y. S. and Guba, E. G. (1985) Naturalistic


Inquiry, Sage, Newbury Park, London.
11. Rowen, P. and Reason, J. (eds.) (1981) Human Inquiry:
a Sourcebook of New Paradigm Research, John Wiley,
Chichester.

12. Checkland, P. (1989) Soft systems methodology, in


Rational Analysis for a Problematic World, (ed. J
Rosenhead), John Wiley, Chichester.

13. Green, S. D. (1994) Beyond value engineering: SMART


value management for building projects. International
Journal of Project Management, Vol. 12, No.1, pp. 49-56.

14. Green, S. D. (1994) A paradigm crisis in value


management?, in Proc. 10th ARCOM Conference, Loughborough
University of Technology pp. 410-421.

15. Green, S. D. (1994) Sociological paradigms and building


procurement, in Proc. CIB W-92 Symposium, Procurement
Systems: East meets West, (ed. S. Rowlinson), Hong Kong,
pp. 89-97.

16. Green, S. D. and Simister, S. J. (1996) Theoretical


perspectives on the development of a meta-methodology for
value management, in Proc. CIB W-92 Symposium, Procurement
Systems: North meets South, (ed. R. G. Taylor), Durban,
pp. 168-179.

17. Flood, R. L. and Jackson, M. C. (1991) Creative Problem


Solving: Total Systems Intervention, John Wiley,
Chichester.

18. Cherns, A. B. and Bryant, D. T. (1984) Studying the


client's role in construction. Construction Management
and Economics, Vol. 2, No.2. pp. 177-184.

19. Becker, F. (1990) The Total Workplace: Facilities


Management and the Elastic Organisation, Van Nostrand
Reinhold, New York.

20. Goodacre, P., Pain, J., Murray, J. and Noble, M. (1982)


Research in Building Design, Occasional Paper No.7,
Department of Construction Management. University of
Reading.

21. Murray, J. P., Gameson, R. and Hudson, J. (1993)


Creating decision support systems, in Professional
Practice in Facility Programming, (ed. W. F. E. Preiser),
Van Nostrand Reinhold, New York, pp. 427-441.
22. Gray, C., Hughes, W. and Bennett, J. (1994) The
Successful Management of Design, Centre for Strategic
Studies in Construction, University of Reading.

23. Powell, 1. A. (1987) Is architectural design a trivial


pursuit? Design Studies, Vol. 8, No.4, pp. 187-206.

24. Lawson, B. (1990) How Designers Think, 2nd edn.,


Butterworth Architecture, London.

25. Rowe, P. G. (1987) Design Thinking, MIT Press,


Cambridge, Massachusetts.

26. Green, S. D. and Popper, P. A. (1990) Value


Engineering: the Search for Unnecessary Cost, Occasional
Paper No. 39, Chartered Institute of Building, Ascot.

27. SchOn, D. A. (1987) Educating the Reflective


Practitioner: Towards a New Design for Teaching and
Learning in the Professions, Jossey-Bass, San Francisco.
540 Green and Simister 28. Ferry, D. 1. and Brandon, P. S.
(1991) Cost Planning of Buildings, 6th edn., Granada,
London. 29. Kelly, 1. (1990) Building design
optimisation, in Proc. CIB 90 Building Economics and
Construction Management, Vol. 2, pp. 1-l3. 30. Newton, S.
(1990) Formal optimization and informal design, in Proc.
CIB 90 Building Economics and Construction Management,
Vol. 2, pp. 182-193.

31. Warszaski, A. (1980) Evaluation of multiobjective


ventures, in Proc. CIB W-55 Methods for Comparing and
Evaluating Alternative Products and Designs, Vol. IV, pp.
159-165.

32. Wilson, A. (1987) Building design optimisation, in


Proc. CIB W-55 4th International Symposium on Building
Economics, Keynotes, pp. 58-71.

33. Canak, M., Gavrilovic, B., Jankovic, I. and Petovar,


K. (1980) Methodological problems in evaluating the
quality of urban dwellings, in Proc. CIB W-55 Methods for
Comparing and Evaluating Alternative Products and Designs,
Vol. IV, pp. 49-68.

34. Eastman, C. and Penz, A. (1974) Market information in


building, in Proc. CIB W-55 1st International Symposium on
Building Economics, Assessing the Economics of Building,
Vol. 2, pp. 7/1-7/8.

35. Tucker, S. N. (1980) Economic decision making in the


building development process, in Proc. CIB W-55
Investment Appraisals and Use Costs, the Life-Cycle
Concept for Buildings, Vol. I, pp. 93-105.

36. Gray, 1. and Tippett, H. (1993) Building quality


assessment: a prerequisite to economic analysis, in Proc.
CIB W-55 International Symposium on Economic Evaluation
and the Built Environment, Vol. 4, Lisbon, pp. 79-89

37. Checkland, P. B. and Scholes, 1. (1990) Soft Systems


Methodology in Action, John Wiley, Chichester.

38. Friend, 1. K. and Hickling, A. (1987) Planning under


Pressure: the Strategic Choice Approach, Pergamon,
Oxford.

39. Eden, C. (1989) Using cognitive mapping for strategic


options development and analysis (SODA), in Rational
Analysis for a Problematic World, (ed, 1. Rosenhead), John
Wiley, Chichester.

40. Checkland, P. (1995) Soft systems methodology, in


Rational Analysis Revisited, (ed. A. Reinhold),
Operational Research Society, Birmingham, pp. 12-22.

41. Hickling, A. (1995) Strategic Choice the


Socio-Political Dimension, in Rational Analysis Revisited,
(ed. A. Reinhold), Operational Research Society,
Birmingham, pp. 31-45.

42. Crichton, C. (ed.) (1966) Interdependence and


Uncertainty: a Study of the Building Industry, Tavistock,
London.

43. Green, S. D. (1992) A SMART Methodology for Value


Management, Occasional Paper No. 53, Chartered Institute
of Building, Ascot.

44. Robinson, V. (1993) Problem Based Methodology:


Research for the Improvement of Practice, Pergamon,
Oxford.

45. Robson, C. (1993) Real World Research: a Resource for


Social Scientists and Practitioner-Researchers, Blackwell,
Oxford.

INTERNATIONAL COMPARISON OF

VALUE MANAGEMENT PRACTICE


Albert P.C. Chan and Betty P.V. Ho

School of Building and Planning, University of South


Australia,

Adelaide, Australia

C.M. Tam

Department of Building and Construction,

City University of Hong Kong, Hong Kong

Abstract

Value management is defined by the Society of American


Value Engineers (SAVE) as

the systematic application of recognised techniques which


identifY the function of a

product or service, establish a monetary value for that


function, and provide the

necessary function reliability at the lowest overall cost.


The philosophy of value

management is based on the premise that a certain amount


of unnecessary cost is

inevitable in building design due to the inherent


complexity of the process and that

significant cost savings can therefore be achieved by the


identification and subsequent

elimination of this unnecessary cost. Value management has


worked successfully in

the US under the name of value engineering or value


analysis. However it is still a

relatively new cost engineering concept in Australia. The


main theme of this paper is

to examine the application of value management in the


Australian construction

industry. The Australian practice was then compared


critically with the established
practice in the US. Two cases of value management
application on Australian

construction projects were studied. The information was


collected from the

questionnaire surveys on the participants and structured


interview with the pertinent

project managers. The results of the case studies showed


that the Australian practice

deviated markedly from the US practice. Very limited


application of the techniques

advocated in the US were practised in Australia.

Keywords: Value management, Australian practice, US


practice.

Sommaire

La gestion de la Valeur Appliquee est definie par la


Society of American Value

Engineers (SAVE) comme l'application systematique de


techniques reconnues qui

identifient la fonction d'un produit ou d'un service,


etablissent une valeur monetaire a

chaque fonction, el permettent d'etablir, avec fiabilite,


chaque fonction pour Ie colit Ie

plus bas possible. La philosophie est fondee sur Ie


principe que dans un projet de

The Organization and Management of Construction: Shaping


theory and practice (Volume Two).

Edited by DA Langford and A. Retik. Published in 1996 by E


& FN Spon. ISBN 0 419 22240 5.

542 Chan, Ho and Tam construction une partie des couts


n'est pas necessaire, mais est inevitable au depart, car
Ie processus est d'une complexite inherente. Des economies
peuvent alors etre

faites en identifiant, puis en eliminant ces couts


inutiles. La gestion de la Valeur

Appliquee a connu du succes aux Etats-Unis sous les termes


d'ingenierie de la Valeur appliquee ou Analyse de la
Valeur. Cependant, ce concept d'ingenierie des couts est

encore nouveau en Australie. Le theme principal de cette


communication est I'examen

de I'application de la gestion de la Valceur Appliquee


dans I'industrie du batiment en

Australie. La pratique australienne est alors comparee it


la pratique americaine.

L'application de la gestion de la Valeur Appliquee est


etudiee dans deux projets de

construction en Australie. L'information a ete recueillie


par questionnaires pour les

participants et par des entrevues structurees avec les


responsables de projets. Les

resultats de ces etudes de cas montrent que la pratique


australienne est visiblement

differente de la pratique aux Etats-Unis. Seule une tres


petite proportion des

techniques pronees aux Etats-Unis est appliquee en


Australie.

Mots-c1es: Valeur Appliquee, Pratique australienne,


Pratique americaine.

1 Introduction

Construction industry is important to the Australian


economy. Its output amounts to 6

to 7% of the GDP in the past few years [1], its input


represents 60% of all new

investments [2], and its product is the input capital to


all other economic activity.

Efficiency of the construction industry is crucial to the


success of investment in new
resource and manufacturing projects. However, as identified
in the proceedings of the

Launch of the National Construction Industry Reform


Strategy in late 1991, the

industry is suffering from an average cost disadvantage of


up to 20% higher than it

needs to be. This extra 20% contributes neither to quality


nor to extra performance of

the end product. The low value of construction money


degrades the international competitiveness

of the industry, discourages the level of investment in


construction and presents an

additional cost to projects which must be born by all


Australians; either as consumers

or tax payers. In the current economic climate, it is


imperative to identify initiatives

that will eliminate the extra cost of construction for the


future viability of the industry

itself and of the overall economy. Adams [3] asserts that


all engineers and architects experience mental roadblocks

of single solution fixation whilst undertaking design


activities. The shortcomings of

individual decision making are magnified by the


characteristics of the construction

industry: multiple dimensions in technologies and


knowledge required, ,sensitivity to

environmental changes, and the diversity of the parties


involved. To eliminate the extra cost elements caused by
this aspect of inefficiency, a cost

reduction system must target improving the quality of the


decisions made throughout

the life cycle of construction projects. One such cost


reduction system with the

principle of rationalising decisions made at various


levels is "Value Management" or

"Value Engineering" as termed in the US where it originated


[4]. The main theme of this paper is to examine the
application of value management in

the Australian construction industry. The Australian


practice was then compared

critically with the established practice in the US. Two


cases of value management

application on Australian construction projects were


studied. The information was International comparison of
value management 543

collected from the questionnaire surveys on the


participants and structured interview

with the pertinent project managers.

2 Concepts of Value Management

Several authors have described "Value


EngineeringlManagement" in different ways.

From the very definition given by Miles [5], "created for


one specific purpose

identification of unnecessary costs through a common sense


approach, ... born largely

through the rearrangement of known concepts, plus the


addition of a few new ones",

to Dell' Isola's definition: "A creative, organised


approach whose objective is to

optimise cost and or performance ofa facility or system"


[6]. The official definition of Value Engineering offered
by the SAVE is: "The

systematic application of recognised techniques which


identify the function of a

product or service, establish a monetary value for that


function, and provide the

necessary function reliability at the lowest overall cost"


[7]. In Australia, Barton [8] defined Value Management as
"An analytical process

which aims to maximise value within a system. The objective


is to ensure that cost and

worth correspond".

3 Previous Research in the Australian Construction Industry

A number of studies have been carried out in the context of


Australian construction

industry regarding this discipline: value engineering or


value management as used in

the Australian context. The focal points of discussion on


value management have been

its principles and its relationship with quantity


surveying. There are also limited

reviews on personal experience with value management in


the Australian construction

industry. Shaw and Chan [9] conclude that:

1. Value management will improve the competitiveness of the


construction industry.

2. The Australian public sector is introducing value


management into their area of expertise. Due to
accelerating construction cost, value management will be
required by large leading institutions.

3. Large corporations or public bodies will impose a value


management exercIse upon their subsidiaries as a formal
project control review procedures. Value management has
been undertaken by Barton [8] for a wide range of

Australian projects. From his experience, a glimpse on


Australian practices can be

obtained:

1. The range of projects undertaken included commercial


office buildings, hospitals, prisons, shopping malls,
international hotels, convention centre, railway systems
and waste water treatment plants. Most of them had major
cost savings.
2. The team approach was used and all disciplines involved
with the project concerned might participate, including
the client and building users.

3. Value management studies are an ideal forum for the


project participants to meet which is not available
otherwise.

544 Chan, Ho and Tam

4. The use of function analysis formed the foundation for


the whole process which was phased into several basic
steps: collection of information, analysis of the
functions, generation of alternatives, evaluation of
alternatives, and development of selected alternatives.

5. In most projects, at least two hundred ideas were


generated.

6. Most of the studies undertaken lasted for three to four


days.

7. The objectives of the studies included cost reduction,


validation of current design proposals, resolution of
other project problems such as time constraint and
communication, and establishment, clarification and
prioritising project objectives.

8. The most effective approach seemed to be the short


preliminary study at early project development followed
by a major study at final sketch plan stage.

4 Research Methodology of the Study

This study can be broadly divided into three parts:

1 . Review of literature.

2. Pilot study of the local practices.

3. In depth case studies of selected Value Management


Workshops.

4.1 Literature Review

An extensive literature review was conducted in the early


stage of the research so as to

form a knowledge base for further research. This included


computer searches of
library materials plus information obtained from
professional journals, published

proceedings and text books. Most of the literature reviewed


related to value

engineering being practised in the us. However, only


limited publications on this

topic were released from the Australian context and were


reviewed in this study.

4.2 Pilot Study

With the small amount ofiiterature regarding the local


practices on value management,

a pilot study was undertaken. The purpose of the pilot


study was two fold. Firstly, it

was used to identifY further sources of information and to


get a feel of the local scene.

Secondly, it served as a source of information to fulfil


the objectives stated, i.e.

develop a general picture to answer the questions of "why",


"when", "for what

purpose" and "for whom" value management has been carried


out in Australia.

4.3 Case Studies

The main focus of the case studies is to explore the


methodology currently adopted in

value management studies in the Australian construction


industry. Being an

exploratory study, the target was to collect a set of the


critical features of conducting

value management workshops. Two cases in Adelaide were


chosen for in-depth

examination. The sources of information for the cases were


identified during the first
phase of the pilot study. International comparison of
value management 545 5 Results of the Case Studies Two
cases namely, Salisbury Campus of Elizabeth ofTAFE, and
Waite Campus of the University of Adelaide, were studied.
Table 1 summarises the details of the two cases studied.
T bl 1 S a e f h C Stud' ummaryo t e ase les

I······ .................... ••••••••••••••••••••••••• ••


CaseN('j:l . ................................ CaseNo.2 ..
.... Project Salisbury Campus of Elizabeth Waite Campus
of the College of T AFE University of Adelaide Client
DETAFEofSA University of Adelaide, CSIRO Dept of
Agrionture of SA Allocated Construction Cost $9.4M $70M
(the portion studied worth $50M~ Procurement Method
Traditional lump sum contract Traditionallum~ sum contract
Purposes of the Study As a trial to testifY the As an
independent review of efficiency & effectiveness of the
requirements of the project VM and as a trial to VM

Project Stage of Applying VM Early design development


Design 100% completed and documentation 30% completed

Duration I full day, 2 half days 4 full days

(Lay Daysl) (3 days) (l day)

Facilitator Internal staff External VM consultant The


study of these cases was to facilitate the following: 1.
Find out the nature of the projects to which value
management studies had been applied.

2. Identity the purposes of applying value management.

3. Review current value management methodologies adopted


III the Australian construction context in the aspects
of: • the make up of a value team • the services offered
by a value management facilitator • the duration, the
process, the ways of conducting and the techniques applied
in a value management study

5.1 Case No.1: Salisbury Campus ofDETAFE

The project involved the redevelopment of the Salisbury


Campus of the Elizabeth

College of T AFE. The site was located in the centre of


the Salisbury business and

commercial district. The objectives of the project were to:


1. provide a multi-purpose workshop for technical and other
studies,

2. provide better and more functional accommodation for


existing courses as well as new programs, and

3. enhance the education and training services in the


Salisbury area.

I Lay days are the free days allowed between the workshop
meetings for in-depth investigation and refinement of
ideas generated or discussed during the workshops.

546 Chan, Ho and Tam The proposal of the project was


initiated in late 1987 and the feasibility study was

completed in April 1991. In total the gross floor area to


be constructed was roughly

13,500m 2 , and 355 car parks. The project was totally


funded by the Commonwealth

through specific purpose grants. The recurrent costs for


operation and maintenance

would be met by State budget. The estimated budget was


$9,425,000 (at October

1993 cost level). The client was the Development of


Employment and Technical and

Further Education of South Australia (DET AFE). The


end-users were those who

were disadvantaged by location, social and economic


background or ethnicity; mainly

the residents in northern Adelaide. The project manager


was the South Australia

Department of Housing and Construction (SACON), on behalf


of the DET AFE. The value study was undertaken at the
early stage of the design development and

documentation phase of the project; upon completion of the


sketch design in mid

December 1991. The study lasted for one full day and two
half days with two lay days
in between. It was the client's initiative to have a value
management study for this

project. According to the project manager, the client had


shown great interest in value

management, by that time, as a new tool in cost


management. This study was one of

the first trials by the client to test its efficiency in


cost saving. The study had three

major purposes:

1. to identifY the factors that forced the cost upward,

2. to clarifY the project's functional objectives, and

3. to identifY the areas of risk and uncertainty. The


study team was composed of one value facilitator and
thirteen team members.

The value facilitator was appointed internally the program


manager of SACON. He

was an architect by profession and had attended two short


courses in value

management. This was the first study he had facilitated. He


was not a member of the

project team. There were 52 ideas generated in the first


day. Brainstorming was the major

technique used in generating ideas. Out of the 52 ideas,


26 of them, which were

ranked "excellent" or "very good", were refined. Not all


of these ideas were

successfully developed into proposals. As explained by the


project manager, this was

due to the lack of time, and the relatively low savings


potential perceived. In the final

report, thirteen proposals were made. Eight of them were


developed from the

"excellent" ideas and five from "very good" ideas. Out of


these proposals eleven were

implemented.

5.2 Case No.2: Waite Campus of the University of Adelaide

The Waite Campus is one of the four campuses of the


University of Adelaide located

15 minutes drive from the North Terrace. The current value


was $100 million (1990

cost level), with some additional buildings utilised by


Commonwealth Scientific and

Industrial Research Organisation (CSIRO), and the State


Department of Agriculture.

The redevelopment of the campus was managed through a joint


venture comprising of

these three users. In 1989, these three agencies were


planning the restructuring of their

organisations. Their main focus was the rationalisation of


their assets with Strategic

Assets Planning. According to the original brief, the whole


project included the

development of eight main building blocks and refurbishment


of one old building. The

total gross floor area was approximately 30,000m 2


comprising 30 discrete subInternational comparison of value
management 547

projects. The allocated budget for the project was


approximately $70 million at 1991

cost level; roughly $2,500/m 2 . The fund for the project


was shared among the three

. agencies: $8M by the University, $5M by CSIRO and the


balance by the Department

of Agriculture with the public funds controlled by the


Treasury. The University of Adelaide was responsible for
the overall site coordination as it
owned the property for the development. The other partners
would be lessees of the

campus property. Due to the multi-client situation, the


management of the project was

quite disparate with separate project managers and


consultants for individual portions.

Most of the contracts were awarded as traditional


contracts. Being publicly funded, the projects needed to
be reviewed regularly and at certain

stages of development. Value management had been initiated


as part of the review

process at early design stage. However the study was not


carried out until the

completion of the design when the Treasury insisted on


having a value management

study. The reasons for introducing the study were two


fold. Firstly, the client wished

to justify the concept, brief, design and cost of the


project. Secondly, the client used it

as a trial to review the process and efficiency of value


management and thus to

evaluate its application as a routine project review


process for government projects.

The latter reason for applying value management concepts


reinforces the findings of

Shaw and Chan [9]. The study was undertaken when the
design was 100% completed and

documentation 30% completed. It was organised by the


construction planning

consultant as part of the planning review process on the


whole project. Since the

Treasury was interested in reviewing the sub-projects


funded by the public money, the

study concentrated on the Department's sub-projects which


in fact encompassed the

greatest portion of the whole project; around $50M worth of


the construction cost. The facilitator in this case was
an external consultant. The facilitator's pre-study

work included involvement in the preparation of the


agenda, and limited advice on

selection of the participants. During the study, the


facilitator led and chaired the

workshop by:

1. organising the participants,

2. maintaining the climate of the study and executing the


rules to allow open forum discussion, stimulating the
participants' lateral thinking by questioning, challenging
and giving relevant examples,

3. giving guidelines in evaluations and assessments of


various ideas,

4. facilitating communication and decision making among the


parties,

5. resolving conflicts raised,

6. consolidating and recording all the outcomes of the


group's discussion,

7. keeping an overview on the whole process to ensure that


the main themes were followed and the critical issues were
addressed, and,

8. monitoring the progress of the discussion. The team was


selected by the Department, the Treasury and the organiser
the

construction planning consultant. The workshop lasted for


four days with one lay day

in between. The first two days of study were devoted to


corporate issues and the team

was made up of mainly the senior management of the


agencies. The design consultants

were included in the last two days of the workshop for


technical input. The value team

included the project teams of the three partner agencies.


No sophisticated value

management techniques such as FAST diagram, cost/energy


model, or graphical 548 Chan, Ho and Tam functional
analysis were applied in this workshop. Instead of
concentrating on how to organise the problems with charts
and graphs, more effort had been paid to organising the
group to make evaluations, assessments and final
decisions. In total there were 50 ideas generated for
improving the project. Eight of them were discarded,
thirty six were examined further, and six of them were put
to action plan. Of the 36 ideas classified as "examine
further", twenty of them were further developed into
action plan, making the total of twenty six proposals
which proposed the actions and possible savings for each
building and site infrastructure. However, only eight
proposals were implemented. 6 Comparing the Value
Management Practice Based on the information obtained from
the two case studies of value management workshops in
Australia, an attempt was made to compare the Australian
practice with American practice. The comparison is
highlighted in Table 2. The characteristics and features
of the US practice are derived from the previous research
works by Palmer [10], Dell' Isola [6] and Norton [11].
From Table 2, it can be observed that the methodologies
adopted in the cases examined have little similarity to
the US practice in terms of duration and the nature of
the value team. On the other hand, the form of value
management consultancy offered in Australia can both be an
integrated part of other consultancy or an one-off.
Although FAST is advocated as the most popular US
technique for value management, it was not applied in all
two cases under scrutiny. The job plans adopted in the case
studies are less rigid and the techniques are more on
managing the human side of the exercise. Table 2
Characteristics of the US, UK Value Management Workshops
and the 2 Workshou Studied . Feafures ••••••••••• ••••
US ..•. ••• ••••••• ••••• ••• Casel •. • ••• ease 2
Duration Standard 40 hrs 5 days 1 full day, 2 half days 4
full days with 1 lay workshop. Completed with 2 lay days
in day in between. in 1 wk w/o lay days. between. Nature
of the team A qualified value All members of project
Project team plus engineer leading a 2nd team including
the external agencies led design team of relevant
client led by a staff of by an external professionals.
the project mgt. facilitator. agency. Site for workshop
Neutral site. Client's conference Organiser's conference
room. room. Form of VM One-off services Integrated
services of One-Off services consultancy offered at 35%
sketch PM. offered by value design by value specialist.
specialist. Major Techniques used Brainstorming, FAST
Brainstorming. Brainstorming Size of Team 6-8 13 8 (day
1 & 2) 11 (day 3 &4) The duration of the workshops are
shorter than the five day workshops advocated in the US.
One of the workshops studied lasted for four days and one
lasted for two days only. The range of workshop duration
in the two cases are in line with the work International
comparison of value management 549 of the Australian
practitioners [8], [12]. Contrasting the project sizes in
terms of construction cost with the duration of the
studies (Table 1), no meaningful relationship can be
observed from them. Thus, it may be fair to suggest that
the duration of the workshop is determined more by the
availability of resources than by the scope of work to be
studied. Lay days, however, were allowed between the
workshop meetings for in-depth investigation and
refinement of ideas generated or discussed during the
workshops This can be beneficial in the sense that the
consultants' investigations are better supported with
information and expertise in their own offices. Table 3
indicates that there are more feasible proposals made in
Case 1 which allowed more lay days between the workshop
meetings. T bl 3 RIo h O b a e e atIOns Ip b fl d d
etween num er 0 ay ays an proposa s t d genera e -CasH
Case 2 Lay Days 2 1 Proposals: Ideas generated 13:52
(13o/~ 2650 (52%) Implementation: Proposals 11:13
(84.6%) 826 (30.8%) There is also a reverse relationship
observable between the number of lay days allowed and the
percentage of proposals made to the ideas generated. This
can be

explained by, perhaps the fact that the ideas generated


have undergone more severe

investigation during the lay days and consequently, less


feasible ideas are discarded

before the proposal phase. The feasibility of each


proposals is thus enhanced and the

percentage of proposals being implemented is increased. In


the two cases, no FAST, cost/energy models, or
one-verb-one-noun approach

were used. The techniques used were more to do with


managing the human side: how
to process group discussion, how to stimulate creativity
and how to make group

decisions in various situations. There was very limited


consideration on life cycle cost

and the workshop was concerned mainly with operation and


maintenance: costs of the

building system and using current cost levels. There was no


discussion of other

categories of life cycle costs: costs of ownership, cost


impact to end-users, etc. as

advocated by Dell' Isola [6].

7 Conclusion

Value management is a structured, systematic, flexible,


team oriented approach for

assessing the relationship between function, cost and


worth. The philosophy of value

management is based on the premise that a certain amount of


unnecessary cost is

inevitable in building design due to the inherent


complexity of the process and that

significant cost savings can therefore be achieved by the


identification and subsequent

elimination of this unnecessary cost. Value management has


worked successfully in

the United States and Europe under the name of value


engineering or value analysis

However it is still a relatively new cost engineering


concept in Australia. The main

theme of this paper is to examine the application of value


management in the

Australian construction industry. Two cases of value


management application on

construction projects were studied. The information was


collected from the

questionnaire surveys on the participants and structured


interviews with the pertinent

project managers. The results of the case studies showed


that the Australian practices

550 Chan, Ho and Tam

have little commonality with the US practices in terms of


duration, nature of value

team and the flexibility of the job plan. Very limited


application of the techniques

advocated in the US were found in the case studies. On the


other hand, the emphasis

was on how to evaluate the subjects of workshop discussion


and how to reach

agreement in the group. Nonetheless, brainstorming was


still the major tool used.

1. Ireland V (1986) An investigation of us building


performance, Sydney, NSW Institute of Technology.

2. Construction Industry Development Agency (1992)


Construction Industry Reform Strategy, Australia.

3. Adams JL (1980) Conceptual blockbusting: a guide to


better ideas, 2nd Edition, Norton, New York.

4. Chan A (1993) Value management and its application in


the construction industry, CIB W-55, W-95 Symposium 1993,
Lisbon, September, 11-20.

5. Miles LD (1961) Techniques of value analysis and


engineering, New York, McGraw Hill.

6. Dell' Isola AJ (1982) Value engineering in the


construction industry, Third Edition, New York, Van
Nostrand Reinhold.

7. Green SD and Popper PA (1990) Value engineering: the


search for unnecessary cost, Occasional Paper No. 39, The
Chartered Institute of Building.

8. Barton R (1989) Value management, The Building


Economist, September, 8-10.

9. Shaw M and Chan A (1992) Value management: a gateway to


a more competitive construction industry, The Building
Economist, Vo1.31, No.1, June, 7-11.

10. Palmer A (1990) A critique of value management, The


Chartered Institute of Building, Technical Information
Service, No.124.

11. Norton B (1992) Value engineering: a value engineering


case study, Chartered Surveyor, September.

12. Dawson B (1988) An outline of value management in the


construction industry, Project Managers Forum Seminar,
Canberra, April.

PROFESSIONAL INTEGRATION IN THE

BUILDING DESIGN TEAM

A. Whyte and H.M. Edge

School of Surveying, Robert Gordon University, Aberdeen, UK

Abstract Whilst the designer is charged with the initial


creative art of invention, it is the design

team which should, theoretically, be responsible for an


innovative design. Design team

members interact; their relationships with one another


figure greatly in the process and

production of specific briefs. Organisational and group


participation, in the fulfilment of a

specific brief by the individuals who make-up the design


team, can affect performance, the

innovative process, and the efficiency of a specific


product. In a more universal sense,

participation levels in the achievement of a common


objective in a technologically complex

process can determine, to a large extent, the efficiency


of industry. If affective participation is sought to
improve efficiency levels in the organisation,
motivational mechanisms (such as ego involvement;
increased identification with colleagues

and the organisation; trust and overarching goal


acceptance) which are inseparable from

group mentality, require to be addressed. Specialist


building knowledge must compliment

recognition that fulfilment of professional potential is to


be found in combining particular

skills in a participative design team. This paper presents


findings from a recent attitude scale

of the construction professions and seeks to assess the


process of organisational participation

in the construction design team, through an appraisal of


the values, expectations and attitudes

of organisational members.

Keywords: Attitude scale, design team, integration.

Sommaire On confie au dessinateur Ie premier acte createur


mais c'est Ie role de l'equipe de

recherche d'assumer la responsabilite du projet de


conception. L'echange d'idees entre les

membres de l'equipe et les rapports entre eux contribuent


en grande mesure au processus et a

la production asssocies a un projet de recherche. Le


travail en groupe et la facon dont cette

participation s'organise pour mener a bien un projet,


peuvent influencer Ie bon

fonctionnement, Ie processus innovateur et l'efficacite du


produit. Quand il s'agit d'un

processus technologique complexe, Ie niveau de


participation dans fa realisation d'un objectif

commun peut en grande mesure decider de l'efficacite de


l'industrie. Si on vise une participation active pour
ameliorer la performance, if faut mettre en
place des mechanismes de motivation etroitement lies a la
mentalite du groupe. On peut

realiser Ie potentiel professionnel des membres de


l'equipe en faisant appef a leurs

competences diverses. eet article presente les resultats


d'un sondage mesurant les attitudes

dans Ie secteur de construction et cherche a evaluer Ie


processus de participation au niveau

The Organization and Management of Construction: Shaping


theory and practice (Volume Two).

Edited by D.A. Langford and A. Retik. Published in 1996 by


E & FN Spon. ISBN 0 419 22240 5.

552 Whyte and Edge 1 Introducing the links between


participation, innovation, attitude and education

The following discussion explores factors which influence


partIcIpation within an

organisation. Participation is presented as a way by which


knowledgeable individuals

contribute to a decision, address conflicting points of


view, or gain new sources of

expertise and experience. Discussion then explores how to


understand better the

processes of participation of the construction design


team, in terms of an assessment of

psychological, organisational, and environmental


contingencies. The potential for

improvements in the participative process is discussed in


terms of an ability to enhance

interpersonal specialist contact, the performance of the


participants, and consequently

improve output.

Contextual, structural and individual variables of the


innovative process are highlighted,
and discussion explores arguments l that organisation
member attitudes playa critical

role in predicting innovation. Important links, between


attitude and behaviour, and a

related significant relationship between education and


attitude, are introduced at this

stage. Research findings are presented which argue that


adherence to traditional

vocational courses influence attitudes held towards


professional peers.

2 Organisational participation and the processes of


innovation in the building industry

The disposition of the building design team may vary but it


is basically a grouping of

individuals, each with a different skill, who combine to


create and maintain the built

environment. Design team members interact; their


relationships with one another figure

greatly in the process and production of specific briefs.


Participation, in the fulfilment of

a specific brief by the individuals who make-up the design


team, can affect performance,

the innovative process, and the efficiency of a specific


product. In a more universal

sense, participation levels, in the achievement of a


common objective in a

technologically complex process, can determine, to a large


extent, the efficiency of

industry. Indeed many researchers suggest that the


individual specialist interaction

occurring in the team can be said to represent industry in


microcosm. Bion 2 argued that

'the development of individuals, through group endeavour,


to achieve smooth co
operative activity' can be used to examine the workings and
efficiency of any complex

organisation. Landsley and Riddick 3 also argue that


observation of small group

interaction is a means of understanding issues in the


wider, more complex organisational

environment. They further argue that interpersonal


relationships occur as a result of the

enactment of activities and that an assessment of group


mentality can be used as a gauge

for the wider efficiency levels of organisational


communication.

The link between group mentality and participation is


discussed further by Locke,

Schweiger & Lathan 4 • They suggest that if effective


participation is sought to improve

efficiency levels of organisational communication, the


'motivational' and 'cognitive'

mechanisms, which are inseparable from group mentality,


require assessment. The

motivation mechanism includes factors such as trust, ego


involvement, increased

identification with the organisation, increased overall


goal acceptance, and greater Professional integration in
the design team 553

control of working tasks. Whilst cognitive mechanisms


include: a better understanding

of the overall rationale underlying the decision making


process, and the better utilisation

of all available information. Lathans 5 research


concentrates on cognitive mechanisms as

a basis for improving the participative process. He found


that individuals instilled with
an ability to marry their own objectives to the rationale
underlying the decision making

process of the group, lead to improvements in the


utilisation of skill and knowledge of

the collective members. He stresses that such improvements


in the utilisation of skill and

knowledge will only occur as long as participants have


sufficient task knowledge to

make a useful contribution. Kanter 6 also argues that


participation should be used to

allow knowledgeable individuals to contribute to a


decision, to address conflicting

approaches of view, or to gain new sources of expertise


and experience.

Specialist knowledge must be held, if participation between


individuals is to prove

effective. Once confidence in a specialist area is


attained, individuals must then seek to

combine these skills in the participative team.


Motivational mechanisms, such as trust

and ego involvement, in conjunction with cognitive


mechanisms, to allow individuals

better to understand the overarching rationale of the


decision making process, require

to be addressed, if an improvement in the efficiency level


of organisational

communication is sought.

Shaskin7 argues that participation properly implemented by


those involved, is effective in

improving performance, productivity and employee


satisfaction. He suggests that in

any valid method for analysing the effects of participation


(and participative
management), three types of contingencies must be
examined: psychological,

organisational, and environmental. Applicability of these


contingencies extends towards

most complex organisations. To allow a greater


understanding of the process of

participation of the construction design team, assessment


must seek to acknowledge: the

values, expectations and attitudes of organisation members


(categorised as

psychological contingencies); the degree to which members


are interdependent at

different stages of the project (organisational


contingencies); and, the changes in

technology, contractual procedure and competition of the


industry (environmental

contingencies).

A participative (psychological) contingencl, is emphasised


by the existance of

perceived hierarchical structures which exist within an


organisational climate. If one

member of the design team is seen as autocratic (possibly


the traditional leader) then it

is unlikely that participative efforts will succeed 9 •


Lickert suggests that by 'slowly but

meaningfully changing the individuals expectations, the


organisational climate will also

change and become more suited to a group participation


method'. In the relatively

constant environment provided by the majority of


industrial and business organisations,

such an initiative might easily be acted upon 'in-house'.


However in a constantly
changing design team, fed by somewhat reactionary
professional consultancies, a

process which requires a slow but meaningful change in


individual expectations is

difficult to achieve. This suggests a need to address the


formative period of a building

professionals development

554 Whyte and Edge

Notwithstanding the importance of improvements to the


perfonnance and the

productivity of integrating professionals by an increased


awareness of participation,

studies by Katz & Kahn 10 also suggest that interpersonal


contact in the context of work

activities is a basic human work need. Indeed Shashkin"


cites various works which

argue that interpersonal contact and participation in the


working environment is a

fundamental human necessity. Freud is cited as suggesting


that interpersonal contact is

extremely significant in working environments, since it is


'through work that one makes

basic contact with the physical and social world around


us'. Shashkin continues by

suggesting that the interpersonal need for social contact


in the workplace can be traced

back to the work of Karl Marx on 'Autonomy and Control' and


Elton Mayo on 'Social

Isolation and Meaninglessness'.

The link between participation; interpersonal contact as a


basic human need; and the

perfonnance of the participants, is highlighted by French &


Caplan '2 • Their study of
NASA engineers and managers revealed that those who had
increased opportunity to

participate in the overall decision making process were


found to have: low psychological

strain; a higher use of skills; increased feelings of


responsibility; better work

relations; more positive attitudes toward work; and higher


output, than those employees

not afforded the choice of participation. Low levels of


participation found in other

technologically complex design industries, might also be


expected to exhibit the

obstacles to process and product described among NASA


engineers. Indeed Cook '3

suggests that a cultural development of traditionally


procured building design team

relationships affords little opportunity for


multidisciplinary participation. The traditional

UK building design team is more of a hierarchical


infonnation transfer system which

exhibits relatively little prospect for participation in


the overall rationale underlying the

decision making process.

Becker '4 differentiates between on the one hand, a 'relay


race' model of communication

in the design process, in which infonnation generated by


one group or discipline is

handed off to another group in a sequential process and a


'rugby' model of the product

development process on the other. In his rugby model,


different disciplines interact in a

dynamic constantly fluctuating fashion. Leadership shifts


as the nature of the project
evolves. The hallmark is that all 'players' are involved
from the beginning. Traditional

project procurement lS and working practice is very much a


'relay race' of infonnation

transfer. Whilst no legislative restrictions exist which


limit participation to this lineal

infonnation transfer, the development of relationships


between the professions are

largely confined by tradition, making this restrictive,


'cultural container' of social

interaction difficult to avoid '6 • This traditional system


is used in the vast majority of UK

projects l7 , and by implication, the low levels of


participation result in (what French and

Caplan have found to be) an undesirable and detrimental


affect on the efficiency of the

process and the effectiveness of the output of industry.

The argument for a participative process to exist within


the organisation, centres on the

premise that interpersonal specialist contact enhances the


perfonnance of the

participants and consequently improves the output. However


many designers adhere to

an alternative assumption 18: that a design, if it is to be


innovative, results from a single

minded, egotistic belief in what constitutes an aesthetic


and functionally successful Professional integration in
the design team 555

proposal 19. Discussion of participation then, must address


innovation: both in the

organisation and in building design.

3 Innovation in the organisation and in building design


If a design is to be called innovative, it must go beyond
inception and the creative art of

invention. A building which is aesthetically and


functionally successful extends the

creative art of invention. It is only the first or early


employment of an idea which allows

invention to become an innovative design. Whilst the


designer is charged with the initial

creative art of invention, it is the design team which


should, theoretically, be responsible

for an innovative design. Indeed Carro1l 20 sees


innovation as a 'social process of

organisational adoption in contrast to independent


discovery'. Pierce & Delb ecq 21 argue

that innovation is 'the initiation, adoption and


implementation of new ideas or activities

within an organisational setting' and they argue that the


process of innovation depends

little on the individual, rather it is argued to be


dependant upon the communication

processes of the organisation. Becker & Whisle?2 also


focus on innovation as an

organisational or social process. To them innovation is a


process that follows

'invention'. Kante?3 summarised the process of innovation


as: idea generation, coalition

building, idea realisation, and idea transfer. This


corresponds with Thompsons 24 earlier

work which classifies the process as: initiation (an idea


or proposal which when adopted

will lead to enactment within the organisation); adoption


(where organisational decision

makers provide a mandate and resources for progress); and


implementation.
Bastien & Hostaler 25 suggest that innovation within an
organisational environment

may be regarded as an influencing factor in the overall


communication process. They

state that the implementation, of the social task of


innovation, is critically reliant on an

overall collective knowledge of cultural background,


dictating the individuals place

within an organisational. Innovation they suggest, is


dominated by informal codes and as

such a cultural background, which in tum directly affects


interpersonal communication.

This parallels, to a large extent, dissatisfaction with the


communicative processes in the

building industry26. The evolution of formal and informal


hierarchies in construction

have frustrated the idea of the design team as an


innovative entity, so much so that

contemporary communication between design team members can


be said to reflect

simply an unsatisfactory lineal pecking order of


contribution to the initial brief.

4 Three variables which influence innovation

If the design team is to attain its theoretical status as


organisational innovator 27 , the

innovation process must be addressed, by breaking it down


into its constituent parts.

Kante?8 reviews several studies which suggest that the


variables which have greatest

influence over the innovation process of an organisation


are: (i)contextual variables (ii)

structural variables and (iii) individual member variables.


Kanter argues that the
factors which make up the contextual issues influencing
innovation in the organisation,

are associated with: business environment,


inter-organisational interdependency,

economic climate, Governmental policy, and the formation


and termination of the

innovative team by organisational senior managment. However


whilst change in anyone

of these Contextual variables may be enough to hinder the


innovative processes within

556 Whyte and Edge

the organisation in general, the building design team is


perhaps less susceptible to

contextual issues; since in the construction industry


contextual variables (which include:

environmental uncertainty; design team project duration;


and inter-organisational

interdependencies) are continually in a state of flux. The


construction industry is forever

peaking and troughing in economic terms. Government policy


and markets at home and

abroad are never certain. The formation and termination of


disparate traditional design

team organisations are a constant feature, and the


professional consultancies which fed

these design teams invariably compete for larger slices of


the market. The construction

industry can be said to differ from more theoretical


innovatory processes in that, it

continually endures these contextual changes. Whilst an


ability to perform in the light of

constant contextual fluctuation does not necessarily show


that the industry has suitably
addressed the contextual challenges to the innovationary
process, it does imply that they

hold little surprise for the building design team, and as a


result influence little, design

innovation.

The second variable of the innovative process, the


Structural variable is argued by

Kanter to include: differentiation, participation,


formalisation, and stratification.

Kanter argues that an absence of a single professional


ideology (Differentiation of

occupational types) will promote a cross-fertilisation of


ideas. She then suggests that

during the participation stage a greater number of sources


of information and a freer

information flow in the decentralised network will generate


a 'greater ego-involvement

and commitment to facilitate the implementation stage of


innovation,29. However in the

multi-disciplinary design team, an evolutionary process of


lineal information transfer and

professional relationships might be argued to restrict


professionals from realising the

theoretical variables of differentiation and


participation. Indeed the formalisation of the

building design team can be said to restrict co-operative


participation. This is worthy of

note since Pierce and Dellbeq argue that 'predetermined


modes of behaviour which have

become rigidified cause a restrictive culture within a


grouping which is detrimental to

relaxed information exchanges'.


The Structural variable of the process of innovation is
also argued above to include

stratification (status mobility). Thompson 30 citing


Maslows work on 'motivation &

personality' and Mayos work on 'the meaning of anxiety'


states that 'stratification leads

to personal insecurity' and that 'status striving behaviour


is incompatible with creative

thinking.' Henderson 31 echoes the concern over perceived


hierarchies and has shown that

similar formal or informal aspects of control,


significantly influence the extent to which

people clearly perceive, and enact their roles in a


communicative relationship. Mongue,

Edwards & Kirste 32 found that organisational equals,


either perceived by the individual

or represented in the structural hierarchy of the group,


are more likely to discuss

problems or proposed changes to improve output, than are


individuals who see

themselves as differing in status. This variable once more


links innovation with aspects

of design team participation discussed in previous


sections; chiefly without professional

equity, participative efforts and innovative design can be


expected to occur only in an

indeterminate fashion.

The third variable of the innovative process, the


Individual variable is argued by Kanter

to include: the attitudes which organisation members hold.


Pierce and Delbeq33 argue Professional integration in the
design team 557

that attitudes playa critical role in predicting


innovation. Cyert & March 34 concur and
state that 'innovative behaviour differs, depending on
whether or not the members of the

organisation perceive (themselves and their colleagues in)


the organisation to be

successful or unsuccessful'. Rage and Aitken 35 also found


attitudes relating to self and

peers to be important in the innovative process of an


organisation. They found that

professionals of (a perceived) equal stratification, who


were satisfied with their

relationships with others, were more likely to search for


ways to improve interaction,

output and product. Pierce and Delbeq cite research by:


Trumbo; Kirton & Mulligan;

and Kaplan 36 when they argue that there is a positive


relationship between education,

and attitude toward change and innovation; where


facilitating an acknowledgement of

the possible potential of change, precedes the wish for an


organisation or team to seek

innovative solutions. Pierce and Delbeq further suggest


that values held by

organisational decision makers, favourable to an


appreciation of the requirement for

change and evolution of (member relationships within) the


organisation, will be

positively related to innovation.

Clearly then, links can be said to exist between attitude


and behaviour (which seeks

innovative and participative solutions). Apparent also, is


a significant relationship

between education and attitude. Discussion of these


important relationships, in terms of
thesis methodology, are developed in subsequent sections.

5 The link between problems in communication and


professional disparity

There appears to be a growing international trend to


fractionalise professional input. As

a result, uncertainty has arisen on how best to prepare


future design team specialists to

succeed in changing legislative and economic environments


3 ? Government and industry

are currently appealing for an improvement in communication


across disparate

professional interfaces, as the way towards a more


efficient and effective construction

industry. These appeals represent an impressive body of


opinion, which believes that the

construction process in the UK has yet to achieve an


optimum level ofproduction 38 •

One of the strongest reported barriers to project team


performance is professional

power struggles and inter-professional conflice 9 • The


need to address the perceptions

and cognitions of each participating specialist towards


their peers, to reduce conflict in

the multi-disciplinary design process, is clear 40 • It is


more the building professions and

their disparate value systems, and less an adherence to


organisational procedure, which

influences the occurrence of conflictual exchange in the


building design team 41 •

The findings which follow represent part of an on-going


research project by the School

of Surveying, Robert Gordon University, Aberdeen. The


results presented find that
attitudes held towards professional peers, potentially
detrimental to the communication

process of the building design team, are a function of


differences between disciplines.

The findings show that pursuing a particular specialist


course of study during the

vocational educational process influences significantly


attitude towards design team

colleagues.

558 Whyte and Edge

6 Disparate professional disciplines: the major influence


in the contribution to group differences in attitude scale
scoring

To assess the extent to which adherence to a specialist


discipline is able to predict

attitude, a discriminant function analysis was carried out


on a data set of 534 attitude

scale questionnaire responses. Discriminant analysis of the


scores obtained from

application of the attitude scale questionnaire was


carried out, by examining the

independent characteristics of the students who took part


in the study. This allowed an

analysis of whether it was possible to isolate groups (of


students from different courses)

on the basis of available independent variables.

The goal of discriminant analysis is to classify cases


into one of several mutually

exclusive groups, on the basis of an observed set of


characteristics. This allows

educators to adapt integrative techniques to best suit an


identifiable group.
The attitude scale questionnaire required each student to
provide additional independent

variables. These independent variables were coded and input


into the data set. The

following independent variables were examined as potential


predictors of attitude scale

scoring: age; construction industry experience; course


undertaken; curriculum

structure; domicile; parent/guardian occupation; sex;


university attended; stage of

study; and subject of questionnaire submitted.

The number of functions used in the discriminant analysis


represented the eleven

independent variables identified above. Variables were


ordered by size of correlation

within the function. The variables of: course of study and


university attended were

found to have the largest absolute correlation with the


first and second discriminant

function stages. In other words course and university are


identified as contributing

substantially to differences in group scores. Although


group membership (in terms of

one variable) was not predicted, the results indicate that


the variables of course and to a

lesser extent university are important in predicting the


attitude scale scoring of the

sample.

The two variables of course and university identified by


discriminate analysis as key

contributors to attitude scale scoring, were further


investigated. Conventional Mann

Whitney and Kruscal-Wallis tests were used to determine


significant differences in the

mean scores between the subgroups of course, and then


independently of university.

Further analysis of university, found this independent


variable to be of no significance in

attitude scale scoring. No significant differences were


recorded for the non-paramentric

Kruscal Wallis I-Way Anova test concerning overall attitude


scale scoring by university

at the three Universities used in the sample (Robert


Gordon, Aberdeen; Strathclyde,

Glasgow; and, UCE, Birmingham). Similarly, no significant


differences were recorded

for the non-parametric Mann Whitney U Wilcoxon Rank Sum W


test concerning

overall attitude scale scoring by university, in an


analysis of the two Universities which

made up the majority of the sample (Robert Gordon,


Aberdeen, and UCE, Birmingham).

Based on these tests the variable of university is not seen


to be a significant indicator of

attitude score. Professional integration in the design


team 559

Examination of the variable of course on the other hand,


produced results indicating that

this independent variable was indeed responsible for


significant differences in attitude

scale scoring. A non-paramentric Kruscal Wallis I-Way Anova


test of mean rank

student attitude scale scores for the eight disciplines of


Architecture, Quantity

Surveying, Building Surveying, Landscape Architecture,


Estate Management,
Environmental Planning, Interior Design and Building Design
Engineering, records a

highly significant difference between the eight different


disciplines. Further examination

of this test allows inference that the mean ranks displayed


by the disciplines of

Architecture, Building Surveying and Quantity Surveying are


considerably lower than

the other five disciplines used in the study. In other


words Architecture, Building

Surveying and Quantity Surveying students have less


favourable attitudes towards

colleagues than the other five disciplines.

Mann Whitney U Wilcoxon Rank Sum W tests further explored


this grouping of the

disciplines of Architecture, Building Surveying, and


Quantity Surveying. Significant

differences were found to exist in the scores of


respective pairings of these three

courses. Notably however no significant difference was


found between the attitude

scores of respondents from Architecture and Quantity


Surveying. The results show close

similarities in attitude score towards colleagues


discplayed by these two disciplines.

Interestingly this similarity is based on a shared


unfavourable attitude, displayed by both

Architecture and Quantity Surveying, towards their


professional peers.

7 Summary

In summary then, the results above highlight the variable


course as influential in the

contribution to group differences in attitude scale


scoring. Findings also reflect the need

to address, in education, the traditionally accepted


truism of suspicion that exists

between the design element, and the building management


element of the traditional

UK building design team. Adherence to traditional


vocational courses influence attitudes

held towards professional peers; these in tum can be said


to influence the potentially

detrimental communication processes of the building design


team.

IPierce, J. & Delbecq, A. (1977) 'Organization structure,


individual attitudes and innovation' Academy

of management review, vol 2, p.27

2Bion, W. (1970) 'Experoeneces in groups', London,


Tavistock.

3Lansley, P. & Riddick, J. (1991) 'The implications of


small group interactions for understanding

aspects of organizational culture', Construction Management


and Economics. vol 9 no 3 p.219-229

"Locke, E., Schweiger, D. & Lathan, G. (1986)


'Participation in Decision making: When should it be

used?', Orgainizational Dynamics, vol 11, p.65 -79.

5Latham, G. (1984) 'Goal setting:A motivational technique


that works' Prentice Hall.

~anter, R. (1982) 'Dilemmas of managing participation'


Organisational Dynamics, Summer 1982.

7Sashkin, M. (1984) 'Participation management is an ethical


imperative' Organisational Dynamics vol

9 p.56-67

8Likert, R. (1967) 'The human organisation' McGraw-Hili.

9Research by Tavistock in the mid 60's and Faulkner & Day


in the mid 80's indicate a relationship

between performance of the construction design team, and


perceived hierarchal orientation of the

design team.

560 Whyte and Edge

l<Xatz, D. & Kahn, R. (1978) 'The social psychological of


organisations' Wiley

llSashkin, M. (1984) 'Participation management is an


ethical imperative', Organisational Dynamics,

vol 9, p.56-67.

12French, J. & Caplan, R, (1972) 'Organisational stress


and individual strain' in Marrow (Ed) (1972)

'The failure of success' AMACOM.

13Cook "Construcion tendering :theory and practice"


BatsfordiCIOB 1991. p.22-SS.

14Becker, J (1991) 'Workplace planning, design and


Management' in Zube & Moore(Eds) 'Advances

in environment, behaviour and design' Plenum

15Chartered Institute of Building (1982) 'Project


Managment in building' CIOB/Ascot.

I~ansley & Riddick (1991) 'The implications of small group


interactions for understanding aspects of

organizational culture', Construction Management and


Economics. vol 9 no 3 p.219-229.

17The Chartered surveyors geographical directory 1993 lists


31384 single disciplined, private practice

RICS members. The 1993 RIBA directory of architectural


practices lists a similarly large number of

single disciplined organisations. Engineering professional


bodies also describe thousands of UK single

disciplinary specialist consultant practices


18 Hutchison, M., the Royal Institution of British
Architects president elect (1989) & Professor L.

Hudson at Building Industry Council: Heads of courses


meeting, May 1989, also Brawne, M. (1989)

speaking on behalf of the Standing Conference of Heads of


Schools of Architecture: AI 31.0S.89

19MacKinnon, D. (1963) 'The personality correlates of


creativity: a study of American architects'. In

Proceedings of the fourteenth congress on applied


psychology. Copenhagen, Denmark :Munksgaard

p.1l-39, vol 2.

2°Carroll, J. (1967) 'A note on departmental autonomy and


innovation in medical schools', The journal

of business, vol 40, pS31-S34.

2lPierce, J. & Delbecq, A. (1977) 'Organization structure,


individual attitudes and innovation'

Academy of management review, vol 2, p.27

22Becker, S. & Whistler, T. (1967) 'The innovative


organisation: a selective view of current theory and

research', The journal of business, vol 40, p.462-469.

23Kanter, E. (1988) 'When a thousand flowers bloom:


structural, collective, and social conditions for

innovation in organisation', Research in organizational


behaviour, vol 19, p.169-211.

2~ompson, V. (1969) 'The innovative organisation' in


'Increasing the innovative capacity of

organisations, University of Illinois, Monograph.

25Bastien & Hostager (1988) 'Jazz as a process of


organizational innovation' Communication research,

vol IS, no S, p.S82-602.

26 most recently ... Latham, M. (1994) 'Constructing the


team: Joint report of the Government / Industry
review of procurement and contractual arrangements in the
UK construction Industry" London,

HMSO.

27Kanter, E. (1988) 'When a thousand flowers bloom:


structural, collective, and social conditions for

innovation in organisation', Research in organizational


behaviour, vol 19, p.169-211.;

28Kanter, E. (1988) 'When a thousand flowers bloom:


structural, collective, and social conditions for

innovation in organisation', Research in organizational


behaviour, vol 19, p.169-211.;

Pierce, J. & Delbecq, A. (1977) 'Organization structure,


individual attitudes and innovation' Academy

of management review, vol 2, p.27.;

Thompson, V. (1969) 'The innovative organisation' in


'Increasing the innovative capacity of

organisations, University of Illinois, Monograph.

29 P ierce, J. & Delbecq, A. (1977) 'Organization


structure, individual attitudes and innovation'

Academy of management review, vol 2, p.27

3~ompson, V. (1969) 'The innovative organisation' in


'Increasing the innovative capacity of

organisations, University of Illinois, Monograph.

3lHenderson, (1987) 'The contextual nature of


interpersonal communication in management theory and

research', Manangement communication quarterly, vol 1., no


1, p.7-31 Aug

32Mongue, Edwards & Kiste (1978) 'The determinants of


commmunication and communication

structure in large organisations: a review of research'


Communication Yearbook 2, vol 2.
33Pierce, J. & Delbecq, A. (1977) 'Organization structure,
individual attitudes and innovation'

Academy of management review, vol 2, p.27Professional


integration in the design team 561

34Cyert, R & March, J. (1963) 'A behavioral theory of the


finn' Prentice-Hall

3SHage, J. & Aitken, M. (1970) 'Socail change in complex


organisations' Random House

36oy-rumbo, D. (1961) 'Individual and group correlates of


attitudes to work related change' Journal of

applied psychology, vo145, p.338.

Kirton, M. & Mulligan, G. (1973) 'Correlates of managers


attitudes towards change' Journal of applied

psychology, vol 58, p.lOI-107.

Kaplan, H. (1967) 'Implementation of program change in


community agencies' Milbank memorial

fund quarterly, vol 45, p.321.

37Burnham "Specialised knowledge and the discipline of


architecture" p.53Journal of architectural

education vol. 141 no 21988; ...

38 Andrews, J. & Derbyshire, A. (1992) 'Crossing


boundaries: a report on the state of commonality in

education and training for the construction industry',


paragraphs 1.2-1.5, London, CIC;

39 Thamhain, H. & Wilemon, D. (1987) 'Building high


perfonnance engineering project teams'

IEEE Transactions on Engineering Management vol. EM34 no 3


p 130-; ...

40 Pondy, L. (1967) 'Organisational conflict: concepts and


models' Administrative science quarterly

vol. 12 p.296-320; ...

41 Ruscio, P. (1985) 'Specialisation in academic


Disciplines: Spokes on a wheel' Annual conference of

the association for the study of higher education, March


1517, Palmer House, Chicago;

CLIENT MANAGEMENT OF THE DESIGN

PROCESS FOR BUILDINGS

Graham Miller

School of Construction and Building Sciences,

University of Western Sydney (Hawkesbury), Australia

Abstract

This paper presents the findings from a research project,


which examined current

practice in the area of client management of the design


process for some recent award

winning and/or architecturally significant buildings in the


Perth region of Western

Australia.

Keywords: client management of design process; design


briefing; managing building

design.

Sommaire

Le present papier rend compte des resultats d'un projet de


recherche qui se

proposait d'examiner les pratiques actuelles dans Ie


domaine de la gestion

client en phase conception pour des edifices de la region


de Perth, dans

l'ouest australien, qui ont recemment ete primes etj ou


possedent un interet

architectural certain.

1 Introduction
Client management of the design process can take many
forms, from total

involvement including physically constructing the building


and designing

simultaneously. to minimal involvement allowing the


architect total control of the

outcome of the final product, even to the extent of site


selection and purchasing

negotiations. The course of arriving at a design solution


and then a completed building that

satisfies the client's requirements is often fraught with


difficulties. Achieving a result

that is also good architecture must to many clients and


architects alike seem almost

impossible when they first start out on the journey of


analysis and synthesis. This paper presents findings from
a research project carried out by the author in

connection with a thesis for a MSc degree through


Loughborough University of

Technology, Department of Civil Engineering, England,


which examined current

practice in the area of client management of the design


process for some recent award

winning and/or architecturally significant buildings in


the Perth region of Western

Australia.

The Organization and Management of Construction: Shaping


theory and practice (Volume Two).

Edited by D.A. Langford and A. Retik. Published in 1996 by


E & FN Spon. ISBN 0 419 22240 5. Client management of the
design process 563 1.1 Types of clients and buildings

The following types of clients and buildings were studied:

Specialist corporate client hospital


Expert corporate client speculative office building

Novice corporate client crematorium and chapels

Expert individual client residence

Novice individual client large extension to residence

Community client aquaticlleisure centre

Community housing client community housing.

Five of the projects studied have won recognition by way of


awards for the quality of

their design from the architectural profession, the


construction industry or civic

bodies. Two of the projects (the Community projects) have


been included because of

their relatively unusual design process stage. It is


accepted that the awards gained

may not necessarily reflect client or user satisfaction


with the buildings, however

results of studies show that in all cases the clients have


expressed a high level of

satisfaction with the general design of their buildings. No


attempt was made to

measure user satisfaction.

2 Summary of Findings

Client management of the design process is influenced by a


number of factors namely;

• the type of client e.g. corporate, individual, community


etc

• the level of knowledge, expertise and confidence of the


client with regard to design

• the natural management style of the client

• the expertise of the various consultants, in particular


the architect

• the type of project e.g. speculative office building in


central business district or an extension of a residence.

However despite the numerous and sometimes disparate


factors and the complex nature

of the design process, the research carried out for this


study indicates that the clients

choice of management strategy, or approach, can be


classified as follows:

a) Hand over control to a consultant (normally an


architect).

b) Maintain overall cohtrol with regard to major design


decisions, e.g. relationship of

rooms, and major cost expenditure, with appointed


consultant controlling the design

process generally.

c) Maintain overall control with regard to major design


decision e.g. relationship of

rooms and major cost expenditure, with separate specialist


consultants 1) An architect/consultant for the feasibility
study and detailed analysis of clients requirements, and
compilation of the brief. 2) A different
architect/consultant to prepare detailed designs (from
brief developed by 1st consultant) through to completion
of the building

564 Miller 2a)A variation of this approach is when a third


architect/consultant is employed to carry out production
information requirements to job completion. It is normal
for this third consultant to work in association with the
briefing and design stage consultants.

d) Client manages all stages of the design process. This


is common with large

construction companies for example, where they have


architects etc. employed within

the company. The company may employ 'outside' consultants


for specific stages,
commonly a particular architect for sketch designs.

e) Client manages feasibility to outline proposal or scheme


design stage, using 'in

house' architects/consultants and then employs outside


architects/consultants for

remainder of the work, but using in-house consultants as


supervisors/liaison.

f) Client may manage all stages of the design process using


'in-house' expertise, and

employ outside consultants for specific tasks, e.g.


interior design. This approach is

common among Local Authorities that have no architect or


building management or

similar departments.

Techniques of 'Information Analysis' and 'Design Process


Management', and/or any of

the methods listed below (Techniques for client managing of


the design process) may of

course be used for client management of the design process.


Findings from the study of

current practice in the Perth region of W.A. however,


indicate that certain techniques

or methods of approach may be more appropriate in certain


circumstances. The limited study of current practice
reveals certain commonality of approach of

client management for small, less complicated projects. But


for large complex projects,

techniques used at certain stages of the design process


vary greatly. It is likely that the areas of commonality
approach, that of round the table discussion

between client and architect, with a reliance on sketches


for illustrating, planning etc.

for small, less complicated projects is a result of


tradition, 'the normal way of running a

project', which is traditionally taught to undergraduate


architects and which most

clients seem to understand. This is not say that this is


the best approach for small

projects, but the fact that the projects studied are


considered worthy of awards and that

the clients have unanimously recorded their general


satisfaction with the process,

suggests that it at least works. Further research is


necessary to ascertain the extent of

use of this approach and if alternative approaches are used


which yield as good, or

better results. With large projects of a complex nature,


techniques used vary considerably. This

may be attributed to a number of things, including type of


client (expert, novice etc);

the architects expertise and experience; the nature of the


problem etc. Again further

research is necessary to ascertain the different techniques


used over a range of

successful projects as well as research into the


suitability of, as yet, untried techniques. Findings from
this study indicate that certain techniques coupled with
suitable client

management techniques may be more appropriate under certain


circumstances and/or at

certain stages of the design process. Client management


of the design process 565 Although Gamble[ I] points out
that "It is important to recognise that all attitudes

and consequently decisions are subjective ... this area of


client designer decision making

which relies for its success on the experience of the


people involved may be amenable
to the application of computers". Computer based 'Expert
Systems' in the area of

client briefing and management of the design process are


still in their relatively early

stages of development, and are not yet viable alternative


to specialist advice from

appropriate consultants. However, research work throughout


the world is beginning to

show the potential of computers as a powerful tool in this


area.

2.1 Techniques for client management of the design process

The following is a selection of some of the techniques


available to clients and their

architects for analysing design requirements [2]:

Collective decision methods which include: Brainstorming


Buzz sessions Group discussions Role play Synectics

Comparison methods which include: Paired comparisons


Ranking and weighting Preference matrix Evaluation matrix
Trade-off games

Rating methods which include: Rating scale Guttman scale


User rating scale Building performance test Spatial
performance test

Visual preference methods which include: Visual preference


Spatial preference Attribute

Check lists which include: Code and zoning check list


Activities check list

Descriptive and Evaluation methods which include:


Behavioural mapping Social mapping (sociogram) Activity
Log

566 Miller Design method which include: Activity analysis


Pattern language Performance method Morphological method
Systems method.

2.2 Techniques Used in W.A.

The study has revealed, as was expected, that the


techniques used for managing the

design process varies depending on:

a) type and expertise of client

b) the architect

c) nature of the project.

2.2.1 Inception stage

In a few of the stages of the design process, which could


be considered as

fundamental, the techniques used were identical or very


similar. Perhaps the most

crucial of these stages is at inception where all of the


clients except the community

clients made the decision that it was necessary to build


rather than, for example,

modify the existing facilities, relocate to another


building or invest elsewhere, without

seeking advice from an architect or other consultant. This


is surprising when one

considers that this is the stage when a single decision


establishes perhaps the entire

budget for the project. Whereas further along in the


decision process, many hours

may be spent by both client and consultants on decisions


affecting only a small

percentage of the contract.

2.2.2 Selecting an architect

All of the clients selected their architect either because


they had previously worked

with them (and liked them) or because of the architects'


reputation. Only one of the

clients appointed their architect at the Feasibility


Stage. Some clients left the

appointment of the design architects until after Outline


Proposal Stage.

2.2.3 The brief

Only one client (Specialist Corporate) employed the


services of a specialist consultant,

an architect, to assist specifically with the preparation


of the brief. Detail design,

documentation and contract supervision being handled by


another architect. The other

clients used their architect to develop the brief and also


design the building. With all but one client, certain
aspects of the brief were changed or the brief

amended up to and in some cases beyond the Production


Drawing stage. Only the

'Expert Individual' client confirmed that the brief was not


changed after the 'Outline

Proposal' stage. The fluidity of the brief suggest that


briefing is part and parcel of the

design process requiring constant re-evaluation and


re-appraisal.

2.2.4 Drawings and models

The other key area of commonality was the method used by


architects to convey

design ideas to their clients. The principal and normally


sole technique used by nearly

all of the architects was two and three dimensional


drawings. Only one used mockClient management of the design
process 567

ups (for the 'Specialist Corporate client'). Techniques


such as photomontage,

computer simulations, or even models were not used by the


groups studied. This is
not to say however that these and other techniques are not
used by these architects on

other projects or by other architects in W A. Perhaps it


was because of the paucity of

techniques used by the architects, that nearly all of the


'clients' found it necessary to

visit similar buildings and/or use photographs of existing


buildings to gain an

understanding of how 'their' building might look. This was


particularly the case for

interior spaces and colour and texture of materials.

2.2.5 Basic building requirements

Only two of the clients (,Expert Corporate Individuals',


and 'Novice Individual')

chose to consult an architect regarding the basic


requirements for their building i.e.

number and type of rooms. However all of the clients used a


consultant (architect or

engineer) to help them appraise the suitability of their


site.

2.2.6 Tender action/procurement

All but one of the clients (the 'Expert Corporate') acted


upon their architect's advice

regarding tender action/procurement methods. The smaller


contracts were 'fixed fee +

costs' without bills of quantities. The larger contracts


were 'fluctuating price' with

approx. bills of quantities and re-measured. The clients


with a government involvement (Specialist Corporate and
Community)

advertised for an expression of interest from potential


tenderers and then drew up a

short list based on advice from their architects. The other


clients relied upon their

architect to advise them of suitable tenderers. Usually 3


or 4 contractors were asked

to tender.

2.2.7 Construction planning and site operations

Two of the clients 'Expert Corporate' and 'Community


Housing', had considerable

involvement at this stage, approving construction


techniques, phasing, location of

contractors' storage areas. All clients were interested in


the quality control of their

projects. The clients with government involvement and the


'Expert Corporate' client

(a contracting company) used in-house operations managers


to inspect/supervise the

works with their architect merely inspecting the works. The


other clients relied on

their architect to supervise and inspect the construction


and report regularly. Despite employing an architect,
some clients-'Specialist Corporate', 'Expert

,Corporate', 'Novice Individual', took it upon themselves


to instruct contractors

directly. This caused some problems ego contractors'


claims for extension of time,

and extra costs.

2.2.8 Costs

Once an overall budget for the project had been established


only one of the clients

(Expert Corporate) required constant (weekly) monitoring of


costs. The other clients

relied on the architect to advise them of major


variations. Even during the design
stage these clients relied on the architect to be prudent
in the choice of materials etc.

so as to ensure the cost of the final design would not


exceed the clients budgets. It 568 Miller seems that an
unstated understanding develops between client and
architect regarding aspects of cost as well as style,
image etc. In all cases payment of the contractor was by
the client, upon certification by the architect. 2.2.9
Completion stage All clients or their representatives were
present when the architect carried out the 'final
inspection' of the building, before and after the issue of
the certificate of practical completion. 2.2.10 Feedback
All clients received as-built record drawings. Two
clients'Specialist Corporate' and 'Novice Corporate'
carried out a formal Post Occupancy Evaluation of their
building. The 'Expert Corporate' client prepared an in
depth report/appraisal for in-house use on the project
overall, including design and method of procurement,
construction, structure, services and performance of
consultants and contractors. The other clients provided
feedback informally to the architect on the overall
performance of their buildings and the construction, ie.
when something went wrong, or at dinner parties

etc.

2.3 Time

The amount of time spent by clients on the various stages


varied depending on the

complexity of the project and the clients desire to be


involved. Figures 1 and 2,

illustrate the percentage of time spent by clients.

Inception(28.7%)

Feasibility(13.5%) Outline(7.6%)

Scheme Oes(7.7%) Detail Oes(8%} Prod Info{3.8%)


80IQ(0.4%)

Tender Acfn(2.1 %)

Proj Plan'g(1.3%) SiteOps(12.1%) 005 + , + , I ,


, t i I

CompleUon(4.6%) =Feedback(2.9%) AVERAGE % TIME SPENT ON


EACH STAGE 0.1 0.15 0.2 , I

Fig. 1 Average time spent by clients on each stage (all


clients). 0.25 0.3 Client management of the design
process NOVlCE INONIOlW.:.". TIME SPENT 00 EACH STAGE
0.00% 5.00% 10.00% 15.00% 20.00% 25.00"(" 30.00%
InelpliOn(27 .• %) -==::;==:;==;==;:===:-l
FUSltldily(27.... ~ Ol,lllinl(O,$%' ) Scheme 01 •.
(2..)"4) .~~.D~~~(.:~:~: ~. _____ ~_ 9.of 0.(0,.., I
Tlnde, Aern(O.I%) Proj. Pan'Q.(O.SY.) I c~:p~~:·~~~";~:
~~--i'--~--~--i--";Fledba.ck(o.""f.) )
NOVICECQnPO'V'oTE:'V. TIME SPCNT 00 EACH STi\GE 0.00%
10.00% 20.00"4 30.00"4 '0.00"1. 50.00% 60.00~.
~:::~li~I::~~:;~: : .•-----~-~--~--~ OulliOo(12.7.,...)
___ Schome 00.(6.3%):j Dotall 00'16.3"4) _ Prod Inlo(2.1
%oj i' I 801 a (0"4) Tende, "'c(n('.2%) _ , Proi
Plan'OlZ.! %) :I Sil. Ops(O%) j Com"~lion(O.l%J
F"db.ack(2.1%) ,. 0.00% 5.00% 10.00.... 15.00% 20.00%
25.00% Ine.,lIion(14.8-to) FUliOil i ly(7.'%) CUllin_,
11.1 '%oj Sd\emIOas(II.I"f.) 5 ~1-r--ella,1 Oes(l.1"4) __
Prod Inlo(O"f.) f 9010(0%) Tendlr Acfn(l.i'%) _ Pfoj
Plan·Q(l.7%) :_ Si'l Ops(22.2"Y.) :::::~:r::t--i-Com pi,
loon! 14.1"'4 F .. ~.cll!7.4"'.) 10.00 15.00 20.00 25.00
lO.OO l5.00 40.00 0.00% 5.00% % % % % % % %
Inclption{lS.5"!.} -::::;::;::-r-t-t-;--l
Fliisibilily(17.8%} :QuUin.,1.9%} :--..SeIl,me Ols.(·Ui"!.)
_ OltadOes.( •. S%} ,... Prod. In1o.{'.5%) _ B.ol
0.(2.2%) .. T,ndl' Acrn(2.2To.} )III Pfoi· Pbn·g(O.I"'4)
I SitIOps.(1.9"1.1 ___ Complllion(6.7"1.) ~
FlldbKk(7.4%) EXPERT 1N0M0\.JAl.: % TIME SPENT ON EIoCH
srAGE 10.00 12.00 1".00 16.00 0.00% 2.00"1. 4.00% 6.00%
'.00"1. % % Inclplion(14.9%1 :.' ...
--!'--'I'--i--i--i--:FIiIs>bilty(2.4%) ._ Oullinl{ •• 7%)
~~~§~~~=~=~=~-i Wlme OIS.(I •. 2%) . Ollall OIS.( 11.8"'4
, Plod. Inlo.(11.8%) B.ol O.{O%) I I I I I I Tender
Acfn(O.l"!.} .P,.j. P, .. · .. O." .. , .. Sill Op5.(2.1%)
.Compllllon(0.7%) r I F .. db~{O~'.J

Fig. 2 Bar charts showing the percentage time spent by


clients on each stage of the

project (expressed as a percentage of total time spent by


the client on the stages). 569

570 Miller

3 Conclusion

The study has shown that the fundamental decision, that of


deciding to build is often
made by the client without consulting an architect. Even
decisions about the basic

accommodation required in the new building is often made


without the architect's

help. Once these decisions are made by the client it seems


that their architects are

reluctant to question them or if they do have little


impact. Once the architect is

appointed however, with one exception, clients appear to be


prepared to leave the

management of the design process to their architect. The


one exception was the

'Expert Corporate' client, who presumably because of the


speculative nature of their

building project, involving many millions of dollars and


their high level of expertise,

preferred to have greater control and influence on the


management. Survey results show a high level of client
satisfaction with the stages of the design

process when their architect was involved but a


significantly lower level of

satisfaction with those stages where the architect wasn't


directly involved. (Fig 3).

Scheme 00.(92.9%)

Ootail Des(92.9%) Prod Inlo(92.9%) 6 of 0(100%)

Tender Ac1n(92.9%)

PIOj Plan'g(92.9%) Sile Ops(85.7%)

Complotion(65.7%)

Feodback(67.9%) 0.1 0.2 AVERAGE % SATISFACTION -All


CLIENTS 0.3 0.4 0.5 0.6 0.7 0.8 0.9

Fig. 3 Average level of satisfaction (all clients) with the


various stages of the design
process Client management of the design process 571

Apart from the 'Community Housing' client the techniques


used by the architects to

formulate a brief, develop designs and inform their clients


could be termed

'traditional' ie. round table discussions using 2D and 3D


sketches. The architect for

the Community Housing project, found it necessary to use


more novel techniques such

as group participatory games aimed at allowing the client


body 'to get in touch with

their emotions'; visual imagery to stimulate design


awareness; democratic means of

arriving at decisions etc. The nature of this particular


type of client; which included

the members of the different households, precluded the


'traditional approach'. The number of projects studied
(seven) was relatively small, the findings therefore

cannot be considered conclusive, and are merely an


indication of how the clients for

these particular schemes managed the process of design. The


results do suggest

however that clients are prepared to trust their


architect's judgement and management

of the design process generally.

3.1 Future Research

This study has shown that there are a number of aspects of


client management of the

design process which require further investigation with the


aim of improving the

process and ultimately the end result the buildings. The


main areas identified can be
categorised as follows:

Communication between client and designers particularly in


the area of design ideas at

the early stages of the process.

Selection and appointment techniques for the client in


connection with the design team.

Investment-feasibility decisions made at the beginning of


a project relating to whether

to build as well as where and what to build.

Building procurement methods, i.e. what kind of design,


tendering, management and

construction strategy should be adopted.

The decision making process generally.

1. Gamble, 1.(1986) Briefing Methods a review of current


research (Report No.

. 1.86), Building Research Centre, School of Building, The


University of New South Wales, p 5.

2. A detailed description of these techniques can be found


in Sanoff, H.(1977) 'Methods of Architectural
Programming', Bowden, Hutchinson-Ross Inc.

THE CONSTRUCTION PROJECT AS A

PROCESS OF INNOVATION

M.F. Dulaimi and A.T. Baxendale

Faculty of the Built Environment, University of the West of

England, Bristol, UK

D.A. Langford

Department of Civil Engineering, Strathclyde University,

Glasgow, UK

Abstract
Innovation is the new buzzword in the construction
industry. The importance of

innovation is unquestionable. There are calls for the


industry to be more

innovative by adopting models, technologies and


philosophies used by other

sectors. . This paper will argue that current trends and


future developments of

organisations and current management concepts used to


explain organisational

behaviour are similar to accepted models of the


construction project. Therefore,

perceived disadvantages of the construction project's set


up maybe seen as key

ingredients to a more innovative industry. The paper will


compare modem theories and concepts of management to those

of construction to examine the hypothesis that the


construction process is a process

of innovation. The main advantage will be the exploitation


of the potentials in the

multi-system organisation of the construction project to


create an environment

conducive to innovation and creativity.

Keywords: Innovation, Creativity, Construction


l\Ifanagement, Organisational

Behaviour.

Sommaire

Innovation est Ie nouveau mot de passe dans l'industrie du


bitiment et des

travaux publics. Son importance est indlmiable. Le secteur


est appele de

toutes parts a etre plus innovant en adoptant des modeles,


des technologies et
des politiques appliquees dans d'autres secteurs. Le
present papier soutient que les tendances actuelles, les
futurs

developpements des organisations et les concepts de


gestion utilises pour

expliquer les comportements organisationnels sont


similaires aux schemas

acceptes dans les travaux de construction. C'est pourquoi


il est possible de

voir dans les faiblesses de l'organisation des projets du


bitiment les

ingredients des vers une industrie plus innovante. n


compare ensuite les theories et concepts de gestion modemes
it ceux

en vigueur dans Ie bitiment afin d'examiner l'hypothese


selon laquelle Ie

processus de construction est un processus innovant


L'avantage majeur est

l'exploitation des potentiels de l'organisation


multi-systeme des projets de

construction pour creer un environnement propice it


l'innovation et la

creativite.

The Organization and Management of Construction: Shaping


theory and practice (Volume Two).

Edited by D.A. Langford and A. Retik. Published in 1996 by


E & FN Spon. ISBN 0419222405. Construction innovation 573

1 Introduction

An increase in attention to innovation and R&D is evident


in all sectors of British

industry. The United Kingdom has registered an annual


growth in R&D spending

of 2.5 per cent, $21.6 billion in 1993, while the rest of


its industrial partners

registered a decline [1]. A strong and effective R&D base


is essential for a

successful innovation. The question for any organisation


striving to increase its

ability to innovate is how to create the environment and


establish the processes by

which new ideas are encouraged and flourish. It is argued


that new ideas are

being created daily in organisations. Whether those ideas


are turned into a

successful innovation i.e product, process or new technique


is another issue. This

issue requires to be addressed, as it is suggested that in


the UK between 65% and

80% of all new products introduced fail [2]. It is reasoned


that the decline in

British industry's ability to innovate does not stem from


any lack of performance in

the advanced areas of academic or fundamental research. It


is in the determined

and innovative application of science and technology that


British industry is

lagging today [3]. In many industries the development of


new higher quality products and services

has become vital to companies survival in today's market


environment. Market

pressures have turned companies attention also to not only


reducing the cost of

existing inadequate processes but also developing new


processes [4]. This has lead

then to the rethinking of the organisational set up


essential to increase innovation. The study will present
an analysis of the organisational set up in construction
and compare that with the current thinking and developments
in the understanding

of the necessary ingredients and contributors to the


establishment of a creative and

innovative organisation and culture.

2 1lte Comtmction set-up

The construction industry is one of the largest industries


in this country in terms of

the number of people it employs and its contribution to the


growth and

development of the whole economy. The nature of


construction work has been

described by Bresnen et al [5] "the product is immobile


and produced at the point

of consumption; work is prone to seasonal fluctuations;


demand can be em:dic; and

the production process continues to rely heavily upon the


use of traditional skills

.and crqfts'~ The construction project can be viewed as a


temporary system, set up. for a

specific purpose, with well-defmed tasks and time scale.


This definition points to

the main difference between construction organisations and


other settings where

there is a constant steady long term organisation. Those


organisations will then

develop an environment which can foster consistent patterns


of relationships within

the group. This is seen to provide other industries with an


advantage as they will

be dealing with organisations where groups have the time to


set-up and develop
standard norms and united interests and goals which the
management will regularly

and progressively bring together with the firms interest.


On the other hand the

construction project consists of different groups which


possess different goals

574 Dulaimi, Baxendale and Langford

which could be achieved by completing the project on time


at the right Cost and

quality [6]. The construction team, which includes


architects, engineers, tradesmen,

subcontractors, material and component suppliers, changes


from one job to

another. Every project then is seen to be unique and no


jobs are ever quite alike. The use of subcontractors by
contracting finns, faced with the fluctuating

environment of the construction industry and the high cost


of direct recruitment,

has added another variable to a more complex organisation.


The challenge to

management is to negotiate, compromise and accommodate the


different people

with different individual needs and style, possessing


different identities belonging

to different groups with different aims and objectives.


Management should aim to

achieve and build an alliance to meet the main objective


(the project).

3 The future shape of organisatiom

New challenges and opportunities are being created by new


developing .

technologies, globalization of markets, increase in


competition, emergence of new
markets and competitors. The emergence of a new breed of
customer which is

more sophisticated and informed has increased demand on


industries to deliver

better value, higher quality and innovative products and


services. Existing models

and concepts of management and organisations are not


capable of responding to

these challenges and opportunities. The new paradigm has


shifted to a new era where responding effectively to the

market and new demands are no longer enough to put the


organisation in a position

where it can lead and/or compete. "The old paradigm rules


of competition that

dictated success are being replaced by new rules that have


moved from total

quality, to learning to stay ahead of change, to


world-class continuous improvement

and innovation" [7]. Interestingly, one important


characteristic of the world class

organisation is that the customer is seen to be central to


its strategy and activities

where customer needs and expectations will be met or


exceeded.

3.1 The virtual organisation

The organisational set up essential to provide the


flexibility and the ability to

innovate and develop new ideas does not relate to the old
model of organisations.

The old model of organisation which is based on


hierarchical and departmental

integrated structure is giving way to the "virtual


organisation". The virtual
organisation, a term borrowed from computer programming,
is an alliance of

organisations comitig together and pooling skills,


expertise and knowledge to

respond to specific demand, opportunity, innovation or


challenge. "Virtual

companies can harness the power of market forces to


develop, manufacture,

market, distribute, and support their offerings in ways


that fully integrated

companies cannot duplicate" [8]. This is a mirror of the


organisational set-up

found in the procurement of construction projects. In


their analysis Chesbrough and Teece [8] have identified
several problems and

benefits of the virtual organisation which are comparable


to that experienced in

construction projects. The benefits of taping into the


resources, intellects, skills

and knowledge of outside parties, referred to as


outsourcing, are counterbalanced Construction innovation
575

with the need to maintain adequate coordination and


organisation between the

different tasks of the project. They also found the need


to maintain good and

friendly relationships between the different parties is


sometimes problematic.

3.2 The role of individuals

There is a new view of careers which is characterised with


inter-firm mobility

referred to as the boundaryless career. DefIllippi &


Arthur [9] argue that career

paths may involve sequences of job opporttmities that go


beyond the boundaries of

single employment setting. Professional careers are seen as


a platform for new

learning, and "in turn for continuing boundaryless career


activities. The

construction industry is a good example where such


opporttmities exist. Further

evidence is emerging in construction of the erosion of


professional barriers where

for example quantity surveyors are adapting to the new


trend toward project

management and management consultancies. Therefore, the


construction team model seems to be replicated by other
sectors

of the economy, where employees are fmding that they need


to adapt a new

approach to employment which is increasingly dominated by


short term contracts.

The disadvantage of lack of common objective, identity or


shared vision is being

replaced by the ability of employees to achieve


"psychological success". Mirvis

and Hall [10] equate psychological success with people's


abilities to make sense of

their constantly changing work agenda and to integrate


their work experiences into

a coherent self-picture. "This loosening of employees


identification is associated

with the emergence of organisational contexts, such as the


starburst and outsource

forms, which expect significant portions of their workforce


to embrace more

entrepreneurial and/or occupational values and work


identities" [9].
3.3 The role of management

The role of management in this new organisational set up is


becoming ever more

important in two respects. First, in this virtual


organisation strong leadership is

essential to provide the axis, direction and focus to the


innovation process.

Second, management needs to fulfIl its coordination role to


achieve a closely nit

alliance of the different parties to achieve the


objective. The advantage of the

virtual organisation is in achieving objectives beyond the


abilities of the individual

parties. However, it is also a disadvantage in losing the


control an integrated

organisation may enjoy. "As incentives become greater and


risk taking increases,

coordination among parties through the marketplace becomes


more and more

difficult, precisely because so much personal reward is at


stake" [8]. This is the

same problem from which the construction industry has


suffered. The unforseen

risks or problems that might face any of the parties to the


construction process

will create challenges and opporttmities that may work as


an advantage to some,

but it may well be a disadvantage to others. One way or the


other the alliance

may turn to be an unfriendly one and therefore the


alignment or coordination will

be lost. This leads to dispute and inevitably to the


stalling of the cooperation and
development process. It is essential for management in
construction to recognise the innovative nature

of the procurement process and the potentials of the


organisational set up in

providing the environment conducive for developing more


creative and innovative

576 Dulaimi, Baxendale and Langford

solutions. The adoption of management techniques and


approaches as well as the

establishment of R&D base is required for the innovative


solution to be

appreciated. This will also ensure these new ideas are


turned into successful

processes, designs and products. An attempt by management


to reduce

uncertainties and risks by adopting "standard" solutions


to maximise production

and individual work output will only stifle innovations. It


would also discount the

possibility of developing new methods and products that


may reduce the cost of

production as well as provide higher quality products and


services. The standard

approach relies heavily on experience to create an


inefficient solution for similar

problems rather than identical problems.

Instead we need to reconstruct our experience to create a


new solution to a new

problem. Therefore, its the use of standard elements, after


modification or

adaptation of parameters or applications, that creates


innovative products and
services to satisfY the needs and expectations of the
market in providing improved

value and quality.

4 Discussion

The evidence suggests that the construction industry is at


an advantage. This

advantage stems from the construction project's inherited


organisational set up.

Together with the professional roles developed around this


set-up seems to reflect

the needs and characteristics of the future leading


organisations. World class

organisations are seen to be the ones that lead by


creating change by innovation

and development that will create new markets and customers.


The main

disadvantage for construction may well be that the


multi-system organisation has

evolved in a completely different environment, socially and


economically. This

system which has been also developed over the last 30 years
for completely

different reasons, has lead to the development of a very


strong culture. This

adversarial and non-cooperative culture is encouraged by


the professions and will

require a new approach and attitude by management. In


order for the advantages

to be reinforced and disadvantages to be minimised within


the context of the new

evolving management thinking change will be required.

1. Target, S. (1995) UK research spending lags but still


bucks the trend, The Times Higher Education supplement,
11th of August, page 3.

2. Touche Ross (1992) Readers Swvey: Innovation, Insight,


London.

3. Rooke, D. (1991) Industrys R&D record criticised,


Financial Times, 27th of August, page 6, London.

4. Lorenz, C. (1995) Process matters, Financial Times, 13th


of October, page 14, London.

5. Bresnen, M. J., Bryman, A, Beardsworth, A, Ford, J.R and


Keil, E.J. (1985) The flexibility of recmitment in the
constmction industry: Fonnalisation or Re-Camalisation?,
Sociology, Vo1.19, No.1, pp. 108-124. Construction
innovation 577 6. Dulaimi, M F. (1991) Job Behaviour of
site managers: Its detenninants and lEsessment, PhD
thesis, University of Bath, UK. 7. Hodgetts, R M, Luthans,
F. and Lee, S. M, (1994)New paraligm organisations: From
Total Quality to Learning to World-CllEs, Organisational
Dynamics, Winter, Vol 2213, pp. 5-20, US. 8. Chesbrough,
HW. and Teece, D.J., (1996) When is virlual virtuous.?
Organising for innovation, Harvard Business Review,
January-February, pp. 65-73. 9. Defilippi, RJ. and
Arthur, MB., (1994) The boundaryless career: a
competency-blEed perspective, Journal of Organisational
Behaviour, Vol. 15, pp. 307-324. 10. Mirvis, P.H and
Hall, D.T. (1994)Psyclwlogical success and the boundaryless
career, Journal of Organisational Behaviour, Vol 15, pp.
365-380.
THE USE AND ABUSE OF HUMOUR IN
CONSTRUCTION MANAGEMENT

1. Townsend, R. (1970) Up the Organisation, Michael Joseph


Ltd. London.

2. Bergson, H.L. (1900) Laughter An Essay on the Meaning of


the Comic, (translated 1911 by Brereton & Rothwell)
Macmillan, London.

3. Sully, J. (1902) An Essay on Laughter: its forms, its


causes, its development and its value, Longmans, Green &
Co., London.

4. Beerbohm, M. (1909) Yet Again, The Bodley Head, London.

5. Disher, M.W. (1925) Clowns and Pantomimes, Constable,


London.

6. Eastman, M. (1937) Enjoyment of Laughter, Hamish


Hamilton, London.

7. Nicholson, H. (1956) The English Sense of Humour,


Constable, London.

8. Freud, S. (1905) Jokes, and their Relation to the


Unconscious, (translated 1960 by James Strachey) Routledge
& Kegan Paul, London.

9. Feibleman (1938) In Praise of Comedy A Study in its


Theory and Practice, Russell & Russell, New York.

10. Hobbes, T. (1651) On Human Nature in the Works of


Thomas Hobbes, Vol. IV (1839), John Bohn, London.

11. Kant, I. (1790) Critique of Practical Reason,


(translated 1878 by T .K. Abbott) Longman, Green, London.

12. Schopenhauer, A. (1819) The World as Will and Ideas,


(translated 1911 by Kemp and Haldane) Kegan Paul, London.

13. Lorentz, K. (1963) On Aggression, Methuen, London.

14. Zillman, D. (1983) Disparagement Humour; in McGhee,


P.E. & Goldstein, J.H.(Eds), Handbook of Humour Research,
Simon & Schuster, New York.

15. McGhee, P.E. (1979) Humour; Its Origin and Development,


Freeman & Company, San Francisco.
16. Kushner, G. (1990) The Light Touch; How to Use
Humourfor Business Success, Simon & Schuster, New York.

17. Gregory, R.L. ed (1987) The Oxford Companion to the


Mind, OUP, Oxford.

18. Kim, S.H. (1987) Essence of Creativity: OUP, Oxford.

19. Gunning, J.G. (1994) Creativity in Construction


Management Research, 10th Annual Conference of Association
of Researchers in Construction Management, pp. 41-53,
University of Loughborough.

20. Koestler, A. (1949) Insight and Outlook, Picador,


London.

21. Short (1970) Humour, Darton, Longman& Todd, London.

22. Peters, T. (1994) The Pursuit of WOW!, Macmillan, London

23. Wilde, O. (1894) A Woman of No Importance, John Lane,


London.

24. Sypher, W. (1956) Comedy, Doubleday, Anchor, USA.


ASPIRATIONS, COMMITMENT AND CAREERS IN
CONSTRUCTION MANAGEMENT

1. Sadler P, Webb T, Lansley P (1974) Management Style and


Organisation Structure in the Smaller Enterprise,
Ashridge Management Research Unit; Berkhamsted.

2. Lansley P, Quince T, Lea F (1979) Flexibility and


Efficiency in Construction Management, Ashridge
Management Research Unit; Berkhamsted.

3. Lans1ey P (1987) Corporate Strategy and Survival in the


UK Construction Industry, Construction Management and
Economics, Vol 5 No 2.

4. Lansley P, Quince T (1981) Organisational Responses to a


Major Recession, Construction Papers, Vol 1, No 2.

5. Lansley P (1994) Analysing Construction Organisations,


Construction Management and Economics, Vol 12 No 4.

6. Ball M (1988) Rebuilding Construction, Routledge; London.

7. Hillebrandt P, Cannon J, Lansley P (1995) The


Construction Company In and Out of the Recession,
Macmillan; Basingstoke.
INTRINSIC JOB SATISFACTION IN CONSTRUCTION

I. Staw, B.M. (1986) Organisational psychology and the


pursuit of the happy/ productive worker. California
Management Review, 28(4), 40-53.

2. Locke, E.A (1976) The nature and causes of job


satisfaction. In The Handbook of Industrial and
Organisational Psychology, (ed. M.Dunnette). Chicago:Rand
McNally.

3. Hackman, J.R. & Lawler, E.E. (1971) Employee reactions


to job characteristics. (Monograph). Journal of Applied
Psychology, 55, 259-286.

4. Walker, C.R. & Guest, RH. (1952) Man on the Assembly


Line. Harvard University Press: Cambridge, Mass.

5. Kornhauser, A (1965) Mental Health of the Industrial


Worker. Wiley: New York.

6. Hackman, J.R & Oldham, G.R (1975) Development of the job


diagnostic survey. Journal of Applied Psychology, 60,
159-170.

7. Hackman, J.R & Oldham, G.R (1976) Motivation through the


design of work: Test ofa theory. Organisational Behaviour
and Human Performance, 16,250279.

8. Loher, B.T., Noe, RA, Moeller, N.L. & Fitzgerald, M.P.


(1985) A metaanalysis of the relation of job
characteristics to job satisfaction. Journal of Applied
Psychology, 70, 2, 280-289.

9. Dunham, RB. (1976) The measurement and dimensionality of


job characteristics. Journal of Applied Psychology, 61, 4,
404-409.

10. Harvey, RJ., Billings, RS. & Nilan, K.J. (1985)


Confirmatory factor analysis of the Job Diagnostic Survey:
Good news and bad news. Journal of Applied Psychology,
70,13, 461-468.

II. Idaszak, J.R & Drasgow, F. (1987) A revision of the Job


Diagnostic Survey: Elimination of a measurement artifact.
Journal of Applied Psychology, 72, 1, 69-74.

12. Fried, Y. & Ferris, G.R (1986) The dimensionality of


job characteristics: Some neglected issues. Journal of
Applied Psychology, 71, 3, 419-426.
13. Turner, AN. & Lawrence, P.R. (1965) Industrialjobs and
the worker. Harvard University Graduate School of Business
Administration: Boston.

14. Borcherding, J.D. & Oglesby, C.H. (1974) Construction


Productivity and Job Satisfaction. Journal of the
Construction Division ASCE, vlOO, C03, 413-431.

628 Davies and Duff

15. Borcherding, A.M. & Oglesby, C.H. (1975) Job


Dissatisfactions in Construction Work. Journal of the
Construction Division ASCE, vIOl, C02, 415-434.

16. Maloney, W.F. & McFillen, 1M. (1985) Valence of and


Satisfaction with Job Outcomes. Journal of Construction
Engineering and Management ASCE, vIII, 1,53-73.

17. Maloney, W.F. & McFillen, 1M. (1986) Motivational


Implications of Construction Work. Journal of Construction
Engineering and Management ASCE, v112, 1, 137-151.

18. Latham, M. (1994) Constructing the Team. HMSO: London.

19. Kelly, G.A. (1955). The psychology of personal


constructs. Norton: New York.
RAPID TEAM INTEGRATION TO OVERCOME THE
CONSTRUCTION INDUSTRY'S FRAGMENTATION

1. Drucker P.P. (1974) Managing For Results, Heinemann

2. Latham M. (1994) Constructing the Team -Final Report,


Joint Review of Procurement and Contractual Arrangements
in the United Kingdom Construction Industry, HMSO London

3. Mintzberg H. (1973) The Nature of Management Risk,


Harper and Row

4. Sayles L.R. (1979) Leadership What Effective Managers


Really Do, and How They Do It, McGraw-Hill

5. Kahn R.L. et al (1964) Organisational Stress: Studies in


Role Conflict and Ambiguity, Wiley

6. Handy c.B. (1976) Understanding Organisations, Penguin

7. Bresnen M.J. (1992) Research Methods on Construction


Visits. In Research Methods and Organisational Studies,
Contemporary Social Research: 20, (ed Bryman A.),
Routledge, 2nd Ed.

8. Zander, A. (1982) Making Groups Effective, Jassey-Bass

9. Adair J. (1986) Effective Teambuilding, Pan

10. Belbin R.M. (1981) Management Teams Why They Succeed


or Fail, Heinemann, London

II. Deming W.E. (1992) Out of the Crisis, Cambridge


University Press, 18th Ed.
PERCEIVED RELATIVE IMPORTANCE OF TRAINING
IN CONTRACTOR DEVELOPMENT IN NIGERIA

1. Intermediate Technology. (1970) Nigerian building


contractors: Practices, problems and needs, Intermediate
Technology, London.

2. Wahab, K.A. (1977, May) Improving efficiency in the


building sector. West African Technical Review, pp.
81-9.

3. Aniekwu, A.N. and Okpala, D.C. (1987) Contractual


arrangements and the performance of the Nigerian
construction industry (the structural component).
Construction Management and Economics, Vol. 5, No.1. pp.
3-11.

4. Aniekwu, A.N and Okpala, D.C. (1988) The effect of


systemic factors on contract services in Nigeria.
Construction Management and Economics, VoL 6, No.2, pp.
171-182.

5. Olugbekan, 0.0. (1991, November) The construction


industry and the Nigerian engineer. Paper presented for
the Tenth October lecture, Nigerian Society of Engineers,
Lagos.

6. Adams, O.A. (1993) Management Training Needs of Nigerian


Indigenous Contractors and their Preferred Delivery
Systems. PhD Thesis submitted to the University of
London.

7. Aniekwu, A.N. (1995) The business environment of the


construction industry in Nigeria. Construction Management
and Economics, Vol. 13, No.5, pp. 445455.

8. Edmonds, G.A. and Miles, D.W. (1984) Foundationsfor


change, aspects of the construction industry in developing
countries, Intermediate Technology, London.

9. World Bank. (1984) The Construction Industry Issues and


strategies in developing countries, World Bank
Publications, New York.

10. ILO (1987) Guidelines for the Development of


Small-scale Construction Enterprises.,ILO, Geneva.

11. Kirmani, S.S. (1988) The construction industry in


development issues and options. (Report INU 10), World
Bank, Washington.
12. Ofori, G. (1991) Programmes for improving the
performance of contracting firms in developing countries:
A review of approaches and appropriate options.
Construction Management and Economics, Vol. 9, No.1, pp. 19
-38.

13. Schatz, S.P. (1977) Nigerian capitalism. Berkeley,


University of California Press, California.

14. Ibid.

15. Federal Republic of Nigeria (FRN) (1980) Fourth


national development plan 1981-85, Federal Ministry of
National Planning, Lagos.

16. FRN (1981) Report of the ministerial committee on the


causes of the excessively high cost of government
contracts in Nigeria. Lagos: Federal Government Press.

17. FRN (1991) National Construction Policy, Federal


Government Press, Lagos.

18. World Bank. (1984). Importance of contractor training


in Nigeria 649

19. ILO (1987).

20. Hemes, T. (1988) Training Contractors for Results A


Guide for Trainers and Training Managers, ILO, Geneva

21. Anekwe, C.M. (1987) Contract award Nigerian experience.


Journal of Professional Issues in Engineering, Vol. 113,
No.3, pp. 229-235.

22. Hemes, T. (1988).

23. ILO (1987).

24. Aniekwu, A.N. and Okpala, D.C. (1987).

25. Aniekwu, A.N and Okpala, D.C. (1988).

26. Aniekwu, A.N. (1995).

27. Adams, O.A. (1995) Indigenous contractors' perceptions


of the constraints on contractors' performance and
development programmes required in Nigeria. Habitat
International, Vol. 19, No.4, pp. 599-613.
28. Aniekwu, A.N. and Okpala, D.C. (1987).

29. Aniekwu, A.N and Okpala, D.C. (1988).

30. Edmonds, G.A. and Miles, D.W. (1984).

31. Olugbekan,o. 0. (1991).

32. Aniekwu, A.N. (1995).

33. Tait, E. (1990) Owner-managers' perceived management


education needs: An integrative framework. International
Small Business Journal, Vol. 8, No.4, pp. 33-48.

34. Mahmood, A (1992) Educational interests and needs of


owner-managers of small building firms. Unpublished Ph.D.
Heriot-Watt University, Edinburgh.

34. Schatz, S.P. (1977).

36. Adams, O.A. (1993).

37. FRN (1980).


THE POTENTIAL FOR EMPLOYEE INVOLVEMENT IN
CONSTRUCTION

10. Brannen, P., (1983); Authority and Participation in


Industry; Batsford, London
TASKS PERFORMED BY THE SITE MANAGER - A
REVIEW OF THE LITERATURE

23. Peters, T. (1987) Thriving on Chaos. Harper and Row.


New York.

24. Crosby, P. (1984) Quality without Tears. McGraw Hill.


London.

25. Langford, V. (1988) Stress Satisfaction and Managers


in the Construction Industry. Occupational Psychologist.

26. Sutherland, V. and Davidson, M.J. (1993). Using a


stress audit: The construction site manager experience in
the UK. Work and Stress, Vol. 3, Nr. 3. pp. 273-286.
PEOPLE AND PROJECTS - BUILDING SUCCESSFUL
COMBINATIONS

1. Porter, Elias H. (1976) "On the Development of


Relationship Awareness Theory: A Personal Note," Group
and Organization Studies, September, VI, N3, pp. 302-309.

2. Tolman, E.C. (1967) Purposive Behavior in Animals and


Men, (New York: Irvington Books).

3. FrolllIll, E. (1947) Manfor Himself, (New York: Holt,


Rinehart, and Winston).

4. Phillips, Steven R. (1994) Creating Effective


Relationships: A Basic Guide to Relationship Awareness
Theory, Pacific Palisades, CA: Personal Strengths
Publishing.
THE INFLUENCE OF PROJECT SIZE ON SITE
MANAGERS' EFFECTIVENESS

comparison of multiple models. Academic Press, San Diego.


19. Bass, B.M. (1990) Bass & Stogdill handbook of
leadership: Theory, research, and

managerial applications. Free Press, New York.

20. Badin, I.J. (1974) Some moderator influences on


relationships between consideration, initiation of
structure, and organisational criteria. Journal of Applied

Psychology, Vol 59, pp. 380-82. 692 Djebarni 21. Farris,


G.F. & Butterfield, DA (1972) Control theory in Brazilian
organisations. Administrative Science Quarterly. Vol 17,
pp. 574-85. 22. Sinha, lB.P. (1990) A model of effective
leadership styles in India. In Management in developing
countries. (Eds A.M. Jaeger & RN. Kanungo), pp. 252-263,
Routledge, London. 23. Maeda, RD. (1967) An Experimental
study ofleadership in India. Journal of Social

Psychology, Vol 72, pp. 35-43. 24. Clegg, S. & Dunkerley,


D. (1980) Organisation, class and control Routledege &

Kegan, London.

25. Sutermeister, RA. (1976) People and productivity. Mc


Graw Hill, New York. 26. Pugh, D.S. & Hickson, D.l (1976)
Organisational structure in its context: The

Aston programme I. Saxon House, London.

27. Vroom, V.H & Mann, F.C. (1960) Leader authoritarianism


and employees

attitudes. Personnel Psychology, Vol 13, pp. 125-40.

28. Ford, RM. (1975) Departmental context and formal


structure as constraints on

leader behaviour. Academy of management journal, Vol 24,


pp. 274-88.
International projects

1. Dieter Ackernecht and Hugh But'gess, ProFessional


Education For Environmental Designers In Saudi arabia, CED
REVI EW, 1986.

2. Adel Shaheen A ldosary, Towards The Reduction Of


Foreign Workers In Saudi Arabia, U.M.I Inc., Ann Arbor,
1991.

3. Ministry of Planning, Kingdom of Saudi Arabia,Fifth


Development Plan, 1990.

4. Ministry of Finance and National Economy, Kingdom of


Saudi Arabia, Statistical Indicator, 1994.

to bring the work back on a schedule. These actions


constitute the monitor and

rescheduling phases of the job management system.

FeatUl'es of Time Control:

The main objective of project time control is to keep the


work activities on schedule,

and this can be accomplished by the following actions:

aReport and record job progress.

bCompare work actually accomplished with that planned.

cTake appropriate action to correct schedule slippage.

d. Update schedule of work yet to be done.

In order to maintain a job schedule, it must be possible to


detect quickly any

divergence through some system of feedback from the


project. The first step of time

control that of monitoring, requires that a system of


progress reporting be established

that makes prompt identification possible of schedule


deviations. This requires that

actual progress to compared with that planned. Project


monitoring, therefore,
involves progress reporting from the job and recording this
infOlmation in a fOlmat

convenient to its comparison with the progress planned.


Critical path method ( CPM)

activities constitute a good basis for progress reporting


and recording (6).

Criteria For Goo(IProject Control:

An effective control system, in addition to celtain general


characteristic, should

provide a means of accomplishing celtain objectives for


both work force and

management. The general characteristic of an effective


control system are flexibility,

coordination and difficulty of prediction ( 7).

The first and probably most impOltant characteristic of a


good control system is

flexibility. Flexibility is required by the very nature of


technical functions. It is also

required because the normal state of affairs in technical


organization is one of

change. In fact, it is a rare construction project that is


carried out from beginning to

end exactly as originally conceived and planned. Therefore,


the project manager

should recognize this constancy of change and provide the


necessary flexibility in the

control system to accommodate it.

A second general characteristic of a good control system is


that it should provide the

information and mechanism for the coordination of effort


within the organization.

Most engineering projects require support that crosses


organizational lines. In order

for all the organizational elements to plan for and


provide this support adequately,

they must be kept aware of what support is required, the


approximate magnitude of

this support, and when it will be required. 726 Enshassi


A third general characteristic that the control system
should recognize is the difficulty of predicting results
and the effort required for a project. In a wellmanaged
production operation of any type, an order for a certain
quantity, quality, and type of product can be placed and
the delivery time and cost can be accmately predicted,
plus or minus a few percent. This is, however, not the case
in construction projects. A realistic planing should be
thoroughly conducted, but the project manager must
recognize the limitations and probability of its accmacy
in the design of a control system. Construction Project
Monitoring and Progress Reporting: The project should be
monitored by resomces ( labor, material, equipment)
schedule and budgeting plans, and progress reports. The
level of monitoring, the information in, and the interval
between progress reports will be determined by the
contractual requirements and by the engineer's management
requirement (8). Good judgment would indicate that every
project should be monitored at a minimum on a general task
or area basis, with progress measmed by comparing actual
progress against planned progress. Total expenditmes
should also be tr·acked. The frequency of progress reports
will probably be established by the contract but should
usually be at least monthly. Depending upon contractual
requirements or special management requests and the degree
of computer usage available, this basic system can be
expanded to track progress of specific items, individual
drawings, monitor specific expenditmes such as manpower by
pay grade or employee name, or sort information to produce
reports in two or more accounting system. In addition the
system could make forecasts based on historic performance
to predict futme manpower requirements and expenditmes and
could identify potential bottlenecks and futme problem
areas. The progress reports may also contain narrative
descriptions of work progress, including discussions of
problems encountered or anticipated and measmes being taken
(9). The monitoring procedmes for conceptual and
preliminary engineering projects should be designed to
provide project control information at frequent intervals
and to control projects with small numbers of tasks in the
most cost-efficient manner possible. The project schedule
will usually be a bar -chart task schedule. Critical path
method ( in network analysis) may be established if
required by the client or the project manager or if the
project work contains critical task interrelationships. A
project monitor report showing progress and status should
be prepared. This report will contain the status of each
task including its estimated percentage of completion,
amount of budget used, scheduled percent complete, and
original budget. The information should be summarized in
appropriate groupings, and an overall project summary
should be prepared showing any variance from the original
project plan and Project control in Gaza Strip 727

budget. The cunent schedule will be included as required,


with a shOli nanative

concerning critical items. The project monitor report will


be reviewed and approved

by the project manager prior to submittal to the client


(10).

The purpose of planning, scheduling, and monitoring


procedure is to provide the

client, the engineers management, and the project manager


with an evaluation of the

cunent and projected status of the total engineering


effOli. This is accomplished

through the development of an engineering work plan and


schedule, and by the

maintenance of this schedule with cunent progress and cost


information which

provides the statistical data necessary for project control.

The planning engineers, using the information contained in


drawing and

specifications, and in consultation with the project


manager, may prepare a

computerized critical path method network for the


engineering effort. This schedule

will include all project milestone, associated studies,


drawing and specification
activities, procurement and construction schedule
interfaces, and all interdisciplinary

constraints between activities. Each activity in the


schedule should be identified with

the responsible engineering discipline and may contain the


associated manpower and

budget information. This schedule will then be reviewed and


approved by the project

manager and will serve as the basis for project monitoring.

An engineering progress chart based on the schedule and


budget should be prepared

for the project. This progress chaIi could be organized by


engineering discipline

within work areas and could reflect actual percentage of


completion, scheduled

percentage of completion and scheduled and actual manpower


for each reporting

area, discipline, and the total project could be included.

At the end of each monitoring period, the planning engineer


should collect all cost,

labor, and progress information for the project. Estimated


percentages of completion

for the preparation of each activity will be used to


update the engineering progress

chaIi. This information, together with the remaining cost


and progress data, will

provide the basis for updating critical path method


network. The progress monitor

report should be reviewed for completeness and accuracy.

During the initial portion of the final engineering design


stage, the equipment and

materials lists should be developed. The material engineer


should coordinate the

preparation of these lists and would assign the equipment


and material numbers. The

finalized list should then be submitted to the planning


engineer for the development

of the schedule.

Utilizing the equipment and material lists, the planning


engineers, purchasing agent,

expediter, and the project manager should determine the


procurement events and

assist in preparing the schedule. Critical items


identified as requiring long lead time,

as being necessary for critical construction stages will be


shown. After these critical

procurement cycle activities can then determined. These


activities will serve as the

basis for the complete procurement schedule (11). 728


Enshassi Designing an Effective Monitoring System: It is
general know that the first step in setting up any
monitoring system is to identify the key factors to
controlled. The project manager wants to monitor, cost, and
time, but he has to define precisely which specific
characteristics of performance, cost, and time should be
controlled and then establish exact boundaries within which
control should be maintained. There may also be other
factors of importance worth noting, at least at milestone
or review points in the life of the project, e.g. the
number of labor hours used and the number of extent of
engineering changes (I 2). The best source of items to be
monitored is the set of actions plans of a construction
project which describe what is being done, when, and the
planned level of resource usage for each task, work
package, and work unit in the project. The monitoring
system is a direct connection between planning and control.
If it does not collect and report information on some
significant element of the plan, control can be faulty or
missing. The action plan furnishes the key items that must
be measured and reported to the control system, but it is
not sufficient. For example, the project manager might
want to know about changes in the clients attitudes toward
the project. Information on the morale of project team
might be useful in preparing for organizational or
personnel changes on the project. These two items may be
quite important, but are not reflected in the project's
action plans (13). Unfortunately, it is common to focus
monitoring activities on data that are easily gathered,
rather than important, or to concentrate on objective
measures that are easily defended at the expense of
softer, more subjective data that may be more valuable for
control. Monitoring should also concentrate on measuring
various facets of output rather than intensity of
activity. It is crucial to remember that effective project
managers are not primarily interested in how hard their
project teams work, they are interested in achieving
results. Performance criteria, standards, and data
collection procedures must be established for each of the
factors to be measured. The criteria and data collection
procedures are usually set up for the life of the
project. However, the standards themselves may not be
constant over the projects life. they may changed as a
result of altered capabilities within the organization or
a technological breakthrough made by the project team. In
some cases, standards and the criteria change because of
factors that are not under the control of project
manager. The monitoring process is based on the criteria
and standards because they constrain the set of relevant
measures (14). The information to be collected must be
identified. This may consist of accounting data, operating
data, engineering test data, specification changes, and the
like. The fundamental problem is to determine precisely
which of all the available data should be collected. The
typical determinant for collecting data too oftens seems to
be simply the ease with which they can be gathered. Of
course the nature of the required data is dictated by the
project plan, the goals of the organization, the needs of
the Project control in Gaza Strip 729

client, and by the fact that it is desirable to improve the


process of managing projects

(15).

After the data collection has been completed, reports on


project progress should be

generated. These include project status reports, time /cost


repOlts, variance reports,

and others. Causes and effects should be identified and


trends noted. Plans, charts,
and tables should be updated on a timely basis. In creating
the monitoring system,

some care should be devoted to the issues of honesty and


bias. The former is dealt

with by setting in place an internal audit. The audit


serves the purpose of ensuring

that the information gathered is honest. No audit, however


can prevent bias (16).

The nature of the monitoring reports should be consistent


with the logic of the

planning, and scheduling systems. The primalY purpose is,


of course, to ensure

achievement of the project plan through contl·ol. There


are many benefits of detailed

reports delivered to the proper people on a timely basis,


aInong them are (17) :

Mutual understanding of the goals of the project.

AWal'eness of projects progress and of problems associated


with coordination

among a activities.

Eal'ly warning signals of potential problems and delays in


the project.

Faster management action in response to unacceptable or


inappropriate work.

Higher visibility to top management.

Keeping the client and donors up to date on project status.

Methodology:

The saInple consisted of 35 construction companies that are


implementing

infrastlucture projects in two main sectors, water and


sewerage, and Roads in the

Gaza Strip. The author has visited the projects and


obtained the information from

35 general managers of the construction firms and 70


project managers of all

sites. Table 1 illustrates the type and locations of


project. The estimated cost for

water and sewerage sector is US $27 Million and for road


sector is 33 US $ Million

(Table 2).

The infrastructure projects al'e funded by the world Bank


and co-financers and they

are managed by the Palestinian Economic Council for


Development and

Reconstructi on

( PECDAR) in coordination with municipalities and local


Village councils in the

Gaza Strip. The relationship between all paIties involved


in the infrastructure

projects are described in organizational chart I and 2.


730 Enshassi Table 1 : Locations Types of Projects.
Geographical Sector Number in the Percentage of Location
sample the sample Water & Sewerage 8 12 North Area
Roads 11 16 Water & Sewerage 10 14 Gaza City 1 Roads
9 27 Water & S. 4 5 Middle Area Roads 3 4 Water &
Sewerage 7 10 South Area Roads 8 12 Total 70 % 100
Table 2 : Estimated Cost ($M) For Each Projects Sector.
Sector Estimated Client Donors Implementing Cost ($M) A2
enc y PECDAR -IDA Municipalities Water & Sewage 27 SF
33 PECDAR -IDA Municipalities Roads SF

(Source: World Bank 1994) Project control in Gaza Strip


731 Occupied Territories Emergency Assistance Program &
Emergency Rehabilitation Project Organization Chart I
Overall Program Organization r--4------...... PECDAR
Gtoop 732 Enshassi

( Sou~ce: World Bank 1994 ) Occupied Territories


Emergency Assistance Program & Emergency Rehabilitation
Project Organization Chart II PEC;:DAR: General
Organization Project control in Gaza Strip 733
Results:

In Gaza Strip, there are a number of problems conceming the


implementation of

infrastructure projects. The problems are perceived through


inappropriate capital

projects which have been carried out and through slow


constmction and increased

costs. More efficient and rapid construction is only


possible if it is performed in an

organized way with full coordination and effective


communication of all parties

involved in the process of preparation, construction,


financing and delivery to users.

This study shows that the report system for top management
about construction

progress and costs are week and need to be improved.

It has been found that the majority of infrastructure


projects contractors in Gaza Strip

have no effective monitoring repOlts that should be


obtained by the regular monthly

updating of designers plans. All contractors ( 100 % of


observed firms) prepare

daily and weekly reports as required by the client.


However, they are not analyzing

the collected information and using it to improve the


construction process and take

the proper action if there is any deviation in certain


tasks. This is because of the lack

of experience and constructive training in controlling and


monitoring projects. In

addition, the unstable political environment in Gaza Strip


poses extra problems to the

contractors as they could not import building materials


easily from abroad.

This study shows that a large numbers of infrastmcture


projects ( 92% of the

sample) were found behind the schedule. The main reason


was, the lack of

controlling and monitoring the projects, other reasons were


found to be :

inappropriate planning, extreme difficulties in obtaining


construction materials, lack

of skilled professional engineers in project management and


disputes with the client.

Monitoring and controlling of projects is an essential


part of project management that

is, unfortunately, the least considered in observed


infrastmcture projects in Gaza

Strip. Special problem in these phase is concemed with


collecting of the information

on the construction site and its transfer to computer where


time and cost plans are

derived. Most companies do not have an appropriate,


permanent system for

collecting infOlmation and it is transfer to computer.


Such films still don't wish to

engage a specialized local consultant office to perform the


project management

completely, and keep them informed about the progress of


the projects in respect to

performance, time and costs. This might be traced to the


nature and culture of

general mangers, who are normally the owner of the firms,


in Gaza Strip as they feel

that they can practice the overall management themselves.

The study indicates that the client of all infrastructure


projects ( PECDAR) in Gaza

strip in cooperation with intemational donor ( The W orId


Bank) have engaged an

intemational management consulting firm to monitor and


control the projects

completely, and to keep both PECDAR and the World Bank


informed permanently

about the progress of the works in respect to the time and


costs. This intemational

consulting finn should also transfer the know-how to the


PECDAR Palestinian

engineers who supervise the infrastructure projects jointly


with Gaza Strip 734 Enshassi municipalities engineers
who belongs to the local govemment authority. It has been
observed that the intemational consulting firm does not
transfer the know-how to Palestinian engineers. This will
not enable them to cany out a modem an effective
monitoring and controlling system in the future. Therefore,
it is strongly recommended that an immediate action
should be taken to overcome this problem. It has been
found also that there is a weak communication channels and
coordination system between all patties involved in the
project. Future studies in this issue is recommended.
Conclusion and Recommendations: Project management
technique is a versatile tool for planning, monitoring, and
CO!1trolling projects which are complex in nature and
involve large number of activities. These activities are
to be integrated for the achievement of the final goal of
project. These are often requiring more time to complete
with more investment of money. The planning ( budgeting
and scheduling) methods require a significantly greater
investment of time and energy early in the life of the
project, but they significantly reduce the extent and cost
of poor performance and time /cost overruns. Note that
this is no guarantee of a trouble -free project, merely an
improvement in the risk of failure. The purpose of the
monitoring system is to gather and report data. The purpose
of the control system is to act on the data. Monitoring
can serve to maintain high moral on the project team as
well as to alert team members to problems that will have
to be solved. The key issue is to create an information
system that gives project managers the information they
need to make informed, timely decisions that will keep
project performance as close as possible to the project
plan. The project manager has to have a smoothly operating
monitoring /control system to manage the project
effectively. In project control, managers should
concentrate on the achievement on the distributed
objectives by balancing time, resources and costs. Tools
of the project control are planning, monitoring and
information system. There is an urgent need for an
effective controVmonitor system to be used in construction
and rehabilitation projects in Gaza Strip. This system
should accomplish the objectives of organizational
management and the intemational donors. Among the benefits
of an effective control/monitor system are: The
control/monitor system should assure management that a
project is as well planned in advance as possible. This
will eliminate as much wasted effort and as many false
statts as possible. The control/monitor system should help
management to determine whether personnel of the
organization are working on projects that are within the
interests and mission of organization. Project control
in Gaza Strip 735 The control Imonitor system should
provide the information to allow management to detelmine
that the costs of a project are kept reasonable in light of
the importance of the project, and progress being made.
The control system should provide the infOlmation that will
allow the project manager to determine the current and
committed work load of organization, this information
will allow the determination of when new projects can be
undertaken.

The designed control monitor system for the management of


construction projects in

Gaza sbip must somehow provide for project initiation,


selection, evaluation

determination of resources allocation, and periodic


review. If the system is effective,

it should result in a smooth flow of well-chosen projects


whose status are updated

and reviewed periodically. The system should help to insure


that projects that

promise the best expected payoff to the construction


organization are identified and

selected for support.

It is recommended that data on the actual progress of


construction projects should be

regularly collected and analyzed to verify whether the


effort is progressing in

conformance with plans. With that data, the project manager


will attempt to detect

any deviations or variance that occur and develop a way to


compensate for or correct

such activity so as to meet the project completion date.


The project manager should

develop procedures for coordination and integrating the


activities of the project

participants, and he should establish effective


communication channels.

The major problem facing project management in Gaza Sbip


is that of obtaining and

retaining an organizations most critical source, that is


skilled and creative personnel.

The determination of technical program, organizational


structure, and procurement of

financial support and facilities are all meaningless if


there is no skilled and motivated

engineers. Only people can produce innovative results. If


the project manager have

good staff in the right jobs and they are properly


motivated, the construction

activities will take care of itself with just a little


guidance. If construction

organizations in Gaza strip are to be continuing success,


they must have well design

and well conducted oriented training courses in specific


fields, e.g. planning,

monitoring, and controlling. This is extremely important,


because an inadequate
qualified engineer will adversely impact an organizations
chance for success. It is

highly recommended that international management consulting


firms should transfer

the know -how to the Palestinian engineers in order to an


conduct effective valuable

1.0 Introduction

Massive changes are taking place in the Chinese


construction industry. The old system of state

control over prices for materials and finished construction


work is now beginning to be replaced

by a move toward competitive tendering, and the indications


are that this trend is likely to

continue as the Chinese economy continues to expand. China,


however, will continue to offer a

construction environment like none other in the world, in


that although some degree of market

forces are being allowed to operate, the industry as a


whole must still operate within the

constraints of a centrally planned economy. This will in


turn mean that Chinese construction

companies and their clients will need to become much more


interested in contractual issues,

competitive tendering strategies, profit and cost control.


Aside from journal articles covering

specific areas of China (e.g. Shanghai), comprehensive


published reviews of the Chinese

construction industry are few. Walker and Flanagan (1987)


examine the industry from the

perspective of construction joint ventures, and this is


complemented by Wilkins (1994). Walker

(1991) describes the organization of the Chinese


construction industry. However, the changes
which are presently taking place mean that whilst these
previous studies still have much to offer

from the point of view of background information, they are


now somewhat outdated in detail.

It is also known that Chinese construction companies are


seeking to expand their activities

internationally. At present, this is mainly done through


state controlled enterprises such as the

China State Construction Engineering Corporation, but as


the industry expands and firms

become more used to working in a competitive environment,


it is likely that more Chinese

organizations may begin to look to compete for work outside


China. Low wage costs within

China could seem to imply that the volume of work


undertaken outside China may mushroom in

the medium term.

All of these factors are presently giving rise to an


increase in demand, within the local Chinese

construction industry, for professionals skilled in the


provision of fmancial advice, procurement

advice, measurement and valuation of construction work,


construction tendering and bidding,

and construction contract law and administration. These


roles are those which, in other parts of

the world, have conventionally been taken by the


professional quantity surveyor. Whilst

quantity surveying is not well known in China by that name,


a number of quantity surveying

functions are regularly carried out within the domestic


Chinese construction industry, including

the measurement and estimating of construction work. The


unique structure of the Chinese
industry, however, means that these functions are rather
different from those practiced elsewhere.

The development of quantity surveying / cost engineering


disciplines which are specifically

tailored to the unique Chinese environment is essential to


the industry's successful development. 760 Ng Wing Fai
There seems to be considerable interest in the development
of the quantity surveying profession within China with a
view to producing graduates who will be recognized and
accepted for membership by the Surveying Institutions in
the rest of the world. There are, however, significant
problems to be overcome. The Chinese economy will still
continue to be centrally planned and the Chinese legal
system is unlike that established either in the western
world or in Hong Kong. In addition, the Chinese
educational system is different to that in the West, and
linguistic and cultural differences mean that the
translation of Western concepts and ideas may be
imprecise and improperly understood. It is also likely that
the Chinese construction environment will continue to be
very different from that pertaining in the West, perhaps
even unique, and Hong Kong quantity surveyor wishing to
practice there have already found that they need to change
their methods and ideas to cope with the local situation.
Quantity Surveyoring courses designed to produce
professionals aiming to operate in this market will need to
pay special regard to the problems of providing a
"professional" standard of education within this very
different srJcial and cultural context, and it is for this
reason that it is believed that traditional "western"
style courses, even those developed in Hong Kong, may not
easily be transported directly to the Chinese situation.
The special nature of the Chinese environment means that
special courses are required. Quantity Surveying as a
profession has been established in Hong Kong for many
years. Institutionally, Hong Kong has its own branch of
the Royal Institution of Chartered Surveyors. Hong Kong
Institute of Surveyors is rapidly growing in prominence
and authority. Quantity Surveying education is also well
represented and including the Hong Kong University, City
University of Hong Kong and Polytechnic University of Hong
Kong which are well to develop courses specifically for
the Chinese construction industry. Smith (1993,1994) has
shown that a small number of Chinese tertiary education
institutions are recognized as specialists in high-level
construction education. Those so far identified are Tongji
University in Shanghai, Qinghua University in Beijing,
Tianjin University, Harbin Architecture and Civil
Engineering Institute, Shanghai Institute of Urban
Construction and Xian University of Architectural and
Technology. Some of these institutions (e.g. Tongji
University and Tianjin University) do have "quantity
surveying type" courses, although they are generally called
by some other name. None of these courses are presently
accredited by any of the professional bodies. The only
professionally recognized course is the u.K. College of
Estate Management Diploma offered under franchise by the
Shanghai Institute of Urban Construction. Quantity
surveying in China 761

2.0 Curriculum

The curriculum for an in-service quantity surveying


training program in the Department of

International Construction Management at the SlUC is as


follows: YEAR: ONE Semester A Semester B Marxist Theroy
English for Building English for Building Contemporary
Chinese History Building Law Mathematics for Building
Mathematics for Building Site Surveying Construction
Management I Technical Communication II Computer
Application Construction Technology I YEAR: TWO Semester
A Semester B Works of Deng Xiao Ping Building Structure
English for Building Operational Research Mathematics for
Management English for Building Mechanics Urban Land
Economics Economics Construction Technology ill
Construction Technology II Measurement & Valuation I
Building Design 762 Ng Wing Fai YEAR: THREE Semester A
Semester B Oral English Oral English Construction
Economics II Development Apprasial Accounting
Construction Technology ill Civil Engineering Project
Programming Building Regulations Measurement & Valuation
ill Measurement & Valuation II Building Law Building Law
Building Economics Town Planning YEAR:FOUR Semester A
Semester B Oral English Dissertation Development &
Finance Project Management Project Cost Control
Measurement & Valuation IV Contract Administration
Quantity surveying in China 763

3.0 Attitudes of employers against in-service training

An attitude test, by questionnaires and follow-up telephone


calls, was conducted by the author in

1994. This survey intended to study the attitudes of


employers about allowing their employees

participating in the in-service programs, and it aimed to


collect information such that in future

the in-service training programs could be more reasonably


arranged and more efficient handling

ing problems. A total of 220 questionnaires were delivered


to the employers of the students

who enrolled in the International Construction Management


program in the SlUC. The return

rate of the questionnaires was 41.36% (91 in total


number). Generally, most of the employers

(or direct supervisors of the students) were not


enthusiastic about returning the questionnaire

except for those who had received a follow-up telephone


call from the author.

TABLE 1

Distribution of the surveyed samples (classified according


to the students' full-time employment)

Classification of Career No. of Questionnaires Returned


Percentage of Total

Education 33 36.26

Government Departments and 12 13.21

Public Sectors

Industries 18 19.77

Commerce 17 18.68

Consultants 4 4.39

Others 7 7.69

Total 91 100

As shown in Table 1, most of the surveyed employers (or


direct supervisors) were from

educational sectors (36.26%). For this population of


surveyed samples, 81.8% were aware of
and had provided encouragement for employees for
participating in the training programs.

They generally feel that open and continuous mode of


education extended the scope of

knowledge to their employees and the cost management


experiences were useful. Nevertheless,

those employers expressed a general worry in that their


employees might spend too much time in

committing to these programs. Most of them (>80%) had


assigned duties on cost management

to those who had studied the in-service program. 764 Ng


Wing Fai About l3% of the students were from government
departments and public sectors. They had day-time jobs in
the Electrical and Mechanical Services Bureau,
Environmental Protection Bureau, Bank of China, New Area
Management Authority. This population of students received
moderate (41.7%) recognition and encouragement from their
direct supervisors. Most of them were however
self-financed in pursuing the degree program and no
time-off was awarded for their study hours. Among this
group of student, 72% of their direct supervisors found
the students increased in cost awareness after attending
the courses and 33.3% of them were assigned special
duties in cost management due to their knowledge obtained
from the courses. As revealed by follow-up telephone
calls, all the supervisors are satisfied with the
students' performance in cost related task. The special
tasks that the supervisors assigned to students included:
cost planning, loan monitoring, procurement, etc. Most
disappointment was from the industrial and commercial
sectors. Only 5.71 % were aware of and had showed
encouragement to their employees' in-service training in
cost management. Most of the employers in the industrial
and commercial sectors showed very negative attitudes
toward in-service program. None of them agreeed in-service
program would be profitable. Nevertheless, the population
showed very positive attitudes toward their employees'
training programs, all of them agree the programs were
relevant to the business of their companies and 66.67% of
them had cost management duties to those employees who were
studying the inservice programs. All satisfied with the
students' performance in cost management and they found
the program could save time and cost in training
specialists. Most encouraging comments were received from
the private consultants. 75% of them favoured the
in-service and distance learning mode of studies. They
found this mode could save time and cost in training
professionals. Because of the non working hours in
consulting firms, all of them agreed that the distance
learning mode offered more flexibilities for students to
study in their own pace and own arrangement. 75% of the
employers found the program in the SIUC being useful in
correlating real cost problems with what students learn in
the teaching materials. All of them found their employer
being more efficient in taking cost management problems
after attending the training courses. Quantity surveying
in China 765

4.0 Students' Responses to the In-service Training Program

This survey is on the basis of a Course Evaluation Report


compiled by SIUC. Questionnaires

were sent to students, tutors and the course coordinator


of the International Construction

Management Program and the course scores of student were


assessed in respect of

students' attitudes in questionnaires. Opinions were


gathered on a Likert Scale with various

pedetermim!d aspects of the course being tested and


evaluated. The overall response rates were

49% and 100% for students and tutors respectively.

Results revealed that over 86% of students satisfied with


the course materials and most of them

found the materials from the SIUC relevant to and useful


for solving cost management problems.

Nevertheless, more than 88% of the students expressed


their interests for more local example,

more information on government policies. They also found


the field surveys and individual

projects very practical, mainly because of the local


relevance of these contents. While only

26% of the students got a "pass" or above in their overall


scores, more than 88% of them
intended to complete the program within 5 years by
part-time.

Negative feedbacks from students included: feeling isolated


in their self-Ieaming processes

(66.67%), lack of motivation or incentives from employers


(33.3%), requirement of a high level

of literacy (88%) for the self-Ieaming materials, and not


sufficient tuition support for the

individual projects (66.67%). These problematic areas in


the International Construction

Management program, however, are common to those studying


in an open and self-Ieaming

mode of continuous education.

5.0 Discussion

The present paper reviews the demands on professional and


technical trainings in the SIUC

program. It also evaluates the effectiveness and


insufficiencies of surveying education by a

continuous, self-Ieaming mode of study. In consideration


that Shanghai is a metropolis in

which quantity surveying is at its beginning, the


in-service training program might inject fresh

human resource in tackling the development problems arisen


by fast economic growth. Besides,

the experiences can be shared by other countries in the


rest of China where have a similar
HOW DO GOVERNMENT REGULATIONS IMPACT
RESIDENTIAL CONSTRUCTION ACTIVITY?

Research Center Dr. Joseph Bordogna; Dr. Ivan KingNational


Science Foundation Engineering
RISK MANAGEMENT: MAINTAINING PROGRAMMED
CONSTRUCTION TIME IN ECONOMIES IN
TRANSITION

1. Raftery, J.,(1994) Risk Analysis in Project Management,


E& FN Spoon, London

2. Thompson, P.A., Perry J.G. (1992) Engineerig


Construction Risks, Thomas Telford, London

3. World Bank (1990) Annual Review of Project Perfonnance


Results, Operations Evaluation Department, World Ban

4. Radujkovic M., (1993) Analysis of Factors that Affect


Construction Time Period,University of Zagreb,
Unpublished PhD, Zagreb, Croatia

5. Flanagan R., Nonnan G., (1993) Risk Management and


Construction, Blackwell Scientific Publications, Oxford

6. Barnes M., We arne S. (1993) The future for Major


Project Management, International Journal of Project
Management, vol. 11, No 3, pp 135-142
BUILDING CONTRACTORS' RISK MANAGEMENT OF
SUBCONTRACTORS IN REFURBISHMENT PROJECTS

Torrance, V.B., Okoroh, M.I., Quah, L.K. & Teo, H.P. (1991)
An Expert System for Tendering and Bidding in
Reforbishment Contracts, Proc. European Symposium on

Construction Management, Quality and Economics, Lisbon


30th Sept 4th Oct.

Okoroh, M.l., Quah, L.K. Torrance, V.B., and Teo, H.P.


(1992) Cognitive Processes

in Risk Evaluation for Decision Making when Applied to


Knowledge Based Expert

Systems, Proc. CIB/W70, International Symposium, Rotterdam,


28-30 Oct.
DESIGN MANAGEMENT THROUGH QUALITY
EVALUATION

study oj IOOOOjailure reports). Annales de L'Institut


Technique du Bil.timent et des Travaux

Publics, n0378, Paris, France, 1979. [2] CNUDDE, M., Lack


of quality in construction economic losses. Paper to the

European Symposium on Management, Quality and Economics in


Housing. Quality and

Economics in Housing, pgs. 508-515 (Ed. A. Bezelga e P.


Brandon). E&FN Spon, London,

UK, 1991. 842 Moriera da Costa and Abrantes (3)


HAMMARLUND, Y. and P.-E. JOSEPHSON, Sources of quality
failures in building. Paper to the European Symposium on
Management, Quality and Economics in Housing. Quality and
Economics in Housing, pgs. 671-680 (Ed. A. Bezelga e P.
Brandon). E&FN Spon, London, UK, 1991. [4] MOREIRA DA
COST A, Jorge, Metodos de avalia.;ao da qualidade de
projectos Caracteristicas, desenvolvimento e
implementa.;ao (Design quality evaluation methods
Characteristics, development and use). Seccao de
Construcoes Civis, Faculdade de Engenharia da Universidade
do Porto, Porto, Portugal, 1986. [5) MOREIRA DA COSTA,
Jorge, Cost structures and quality control. Paper to the
Architectural Management International Symposium.
Architectural and Project Management (Ed. M.
P.Nicholson), pgs. 228-233. School of Architecture,
University of Nottingham, Nottingham, UK, 1992. [6)
MOREIRA DA COSTA, Jorge, Coordena.;ao de projecto e
controle da qualidade (Design coordination and quality
control). Paper to the Las Jornadas de Construcoes Civis.
Ed. Seccao de Construcoes Civis, Faculdade de Engenharia
da Universidade do Porto, Porto, Portugal, 1992. [7)
ABRANTES, Vftor, Qualidade na constru.;ao (Quality in
building construction). Published by Seccao de
Construcoes Civis, Faculdade de Engenharia da Universidade
do Porto, Porto, Portugal, 1994. [8) ASSOCIATION
QUALITEL, Guide Qualitel. Association Qualitel, Paris,
France, 1993. [9] WIEGAND, J., K. AELLEN e T. KELLER,
Evaluation de logements Systeme d'evaluation de logements
(SEL) Edition 1986 (Dwelling evaluation SEL Method 1986
version). Bulletin du logement, volume 35. Office Federal
du Logement, Berne, Suisse, 1992. [10) MOREIRA DA COSTA,
Jorge, Metodos de avalia.;ao da qualidade de projectos de
edificios de habita.;ao (Design quality evaluation methods
for housing buildings). Faculdade de Engenharia da
Universidade do Porto, Porto, Portugal, 1995.
TOTAL QUALITY MANAGEMENT OF CONSTRUCTION
WORK: FROM SAFETY EXCLUSION TO A
COMPREHENSIVE MANAGEMENT STRATEGY

1. SMALLWOOD, JJ. 1995. Total Quality Management: Its Role


in Occupational Health, Hygiene and Safety Improvement.
Occupational Hygiene Certificate Course, University of
Port Elizabeth. 34p.

2. LEVITT, RE & SAMELSON, NM. Construction Safety


Management. 2nd Edition. New York: John Wiley & Sons Inc.
273p.

3. JEFFREY, J & DOUGLAS, I. 1994. Safety Peiformance of


the UK Construction Industry. 5th Annual Rinker
International Conference focusing on Construction Safety
and Loss Control. University of Florida, Gainesville. pp.
233-253.

870 Smallwood and Rwelamila

4. TYLER, WW. March 1992. Total Involvement Safety.


Professional Safety pp.26-29.

5. SMALLWOOD, JJ. 1995. The Influence of Management on the


Occurrence of Loss Causative incidents in the South
African Construction Industry. MSc Dissertation,
University of Port Elizabeth. 305p.

6. SMALLWOOD, JJ. 1995. Report on the 2nd. National


Conference on Ergonomics, Safety and Health in
Construction, Washington, DC.

7. CROSBY, PB. 1984. Quality Without Tears The Art of


Hassle Free Management. New York: McGraw-Hill Book
Company. 205p.

8. THE BUSINESS ROUNDTABLE. 1991. The Workers' Compensation


crisis ... Safety excellence will make a difference. New
York: The Business Roundtable. 21 p.

9. HOOD, S. May/June 1994. Developing Operating Procedures:


9 Steps to Success. Accident Prevention. pp. 18-21.

10. TENAH, KA. 1994. Incorporating Safety Mechanisms into


Engineering Design. 5th Annual Rinker International
Conference focusing on Construction Safety and Loss
Control. University of Florida, Gainesville. pp. 211-221.
ADDRESSING CONSTRUCTION WORKER SAFETY IN
THE DESIGN PHASE

1. The Construction (Design & Management) Regulations


(1994) SI 1994/3140 HMSO.

2. Raggs, R.E. and Cunningham, J. (1988) Safety and


Efficiency in Steel Construction The Broadgate
Experience. Civil Engineering (London), May. pg. 35.

3. Morpurgo, S. (1992) Accident Prevention at Dam


Construction Sites. International Water Power and Dam
Cons/mc/ion, Vol. 44, No.8. pg. 13.

4. Hinze, J. and Wiegand, F. (1992) Role of Designers in


Construction Worker Safety. Journal of Constl'llc/ion
Engineering and Mgn1l1t., Vol. 118, No.4. pp. 677-84.

5. U.S. Department of Labor, Occupational Safety and Health


Administration (1990), Analysis (?fConstl'llction
Fatalities Ihe OSHA Data Base 1985 -1989.

6. Joyce, R. (1995) The Constrlfction (Design and


Management) Regulations Explained, Thomas Telford
Publications, London.

7. Jeffrey, J. and Douglas, I. (1994) Safety Performance of


the UK Construction Industry. Proceedings l?f the F?fth
Annual Rinker International COl!ferellCe Foclising on
COllstructioll Safety and Loss Control, Univ. of Florida.
pp. 233-53.
BEYOND ADR - DISPUTE REDUCTION IN THE
CONSTRUCTION INDUSTRY THROUGH REALISTIC
CONTRACT RISK ALLOCATION

1. Preventing and Resolving Construction Disputes, Center


for Public Resources, 1991.

2. Vorster, M.C., Dispute Prevention and Resolution,


Virginia Polytechnic Institute & State University,
Blacksburg, Virginia, October 1993.

3. Construction Industry Attitudes on Disputes and


Prevention/Resolution Techniques, James E. Diekmann and
Matthew J. Girard (unpublished manuscript produced by the
Construction Industry Institute's Dispute Prevention and
Resolution Research Team, 1993).

4. Disputes Potential Index, The Construction Industry


Institute Disputes Prevention and Resolution Research
Team, September 1994.

5. Diekmann, James E. and Matthew J. Girard, DPI Disputes


Potential Index: A Study Into the Predictability of
Contract Disputes, University of Boulder Department of
Civil, Environmental, and Architectural Engineering,
Boulder, Colorado, January 1994.
RISK MANAGEMENT AND MAJOR CONSTRUCTION
PROJECTS

Riggs, James L & West, Thomas M (1986) "Engineering


Economics", Third Edition, McGraw-Hili, New

York.

Walker, A, (1984) "Project organisation", Chartered


Quantity Surveyor, February.

Вам также может понравиться